Upload
yinka-eduok
View
219
Download
0
Embed Size (px)
Citation preview
7/29/2019 Electric power distribution Feeder
1/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 1 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
LIST OF CONTENTS
1. PLANT DETAILS
2. TESTING OBJECTIVES
3. TESTING PROPOSALS
4. SERVICES REQUIRED
5. SAFETY PRECAUTIONS
6. EMERGENCY PROCEDURES
7. STATE OF THE PLANT
8. COMMISSIONING PROCEDURE
9. COMPLETION CRITERIA
10.APPENDICES
7/29/2019 Electric power distribution Feeder
2/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 2 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
1. PLANT DETAILS:
The system consists of
i. SF6 Circuit breaker
ii. Isolators
iii. Earth switches
iv. Current transformer
v. Capacitor voltage transformer
vi. Lightning arrestor
NAME PLATE DETAILS:
1. SF6 CIRCUIT BREAKER
MAKE : BHEL HYDERABAD TYPE : 3AT2
LOCATION : 400 KV SWITCHYARD
RATED VOLTAGE : 420 KV RATED CURRENT : 3150 AMPS
CONTROL VOLTAGE : 220V DC
2. ISOLATORS (MAKE : S &S SWITCHGEAR, CHENNAI )
TYPE : HORIZONTAL CENTRE BREAK
RATED VOLTAGE : 400 KV RATED CURRENT : 2000 A
AUX. SUPPLY : 220 V DC CONTROL
415 V AC MOTOR3. EARTH SWITCHES
MAKE : S & S SWITCHGEAR TYPE : V L E
7/29/2019 Electric power distribution Feeder
3/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 3 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
4. CURRENT TRANSFORMER:
MAKE : BHEL BHOPAL TYPE : OUTDOOR
SYSTEM VOLTAGE : 400 KV RATIO : 500-1000-2000/1 A
SHORT TIME THERMAL RATING : 40 KA/ 1 SEC. NO. OF CORES: 5
CLASS : PS (4 CORES) & 0.2 ( 1 CORE) MET CT BURDEN: 40 VA
KNEE POINT VOLTAGE : 2000 volts EXCITATION CURRENT : 30 mA (s1-s3)
60 mA(s1-s2)
5. CAPACITOR VOLTAGE TRANSFORMER:
MAKE : BHEL BHOPAL TYPE : OUTDOOR
RATED VOLTAGE (PH N) : 400 KV/3 / 110 V/3
VOLTAGE FACTOR : 1.5/3 SEC TOTAL CAPACITANCE : 4400 pf
NOMINAL INTERMEDIATE VOLTAGE : 22 KV/3
6. LIGHTNING ARRESTORS:
MAKE : WS INDUSTRIES(INDIA) LTD,BANGALORE
TYPE : METAL OXIDE , GAPLESS
RATED VOLTAGE : 390 KV (rms) RATED CURRENT : 10 KA
MAXIMUM DISCHARGE CAPABILITY: 8KJ/KV
MAXIMUM FRONT OF WARE SPARK OVER VOLTAGE : 1050 KVP
7/29/2019 Electric power distribution Feeder
4/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 4 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
2. TESTING OBJECTIVE:
TO TEST THE 400 KV SWITCHYARD FEEDER /LINE AND MAKE
IT READY FOR COMMISSIONING.
7/29/2019 Electric power distribution Feeder
5/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 5 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
3. TESTING PROPOSAL:
The 400 KV Switchyard feeder will be checked and tested as per the standard
checklist and field test reports of its under mentioned equipments.
i. SF6 Circuit breaker
ii. Isolators
iii. Earth switches
iv. Current transformer
v. Capacitor voltage transformer
vi. Lightning arrestor
vii. Control & Relay panel
7/29/2019 Electric power distribution Feeder
6/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 6 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
4. SERVICES REQUIRED:
4.1 Calibrated Test Kit
a. 5 KV Hand/Motorised Megger
b. 500 V Megger
c. Earth Megger
d. Pressure and Temperature gauges
e. Milli second timer
f. Digital Multimeter
g. Micro Ohm meter / Kelvins Double bridge
h. Clamp-on meter for current measurement
i. Operational analyzer(Optional)
j. Motwane analogue multimeter
k. Tan delta equipment
4.2 Current Injection Kit
4.3 3 Phase 415 V AC 50 Hz Supply
4.4 1 Phase 230 V AC 50 Hz Supply
4.5 1.5 V Battery cell for checking the polarity of CTs
7/29/2019 Electric power distribution Feeder
7/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 7 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
5. SAFETY PRECAUTIONS:
5.1 The engineer-in-charge of the testing team will inform each member of
the test as to exact nature and extent of his contribution and
responsibilities towards tests carried out.
5.2 Only nominated persons will take part in the tests. All others will remain
clear of the area.
5.3 All persons must acquaint themselves with use and location of fire
extinguishers and First-Aid Box.
5.4 Each test will be carried out under the control of test team leader
5.5 A strict and safe method of applying test leads shall be practiced. Bare
wires should not be used in stead proper lugs must be used. All test
connections shall be tightened and rechecked.
5.6 A record of any alterations made during the tests such as shorts or
disconnections shall be made and annexed to the relevant test
procedures.
5.7 Each test will be carefully planned so that there is no mechanical or
electrical damage to the equipment under test.
5.8 Test area will be kept clean ,clearly defined and cardoned off.
5.9 When high voltage test are being made Danger/Warning notices shallbe fixed at relevant points to ensure safety and a sanction for test taken.
All isolating points to be manned.
7/29/2019 Electric power distribution Feeder
8/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 8 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
6. EMERGENCY PROCEDURE:
6.1 Shock treatment chart and first-aid box will be made available.
6.2 Emergency telephone numbers for hospital and fire services shall be
prominently displayed.
6.3 A telephone will be available nearby
7/29/2019 Electric power distribution Feeder
9/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 9 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
7. STATE OF THE PLANT:
7.1 Erection of 400 KV Bus and its associated equipments completed.
7.2 Earthing of the equipments completed
7.3 Oil level in CT,CVT & Circuit Breaker is OK.
7.4 400 KV Bus Bar is dead
7.5 Clearance from erection department for carrying out various tests obtained.
7.6 Area of test is completely isolated from illegal entry of trespassers
7/29/2019 Electric power distribution Feeder
10/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 10 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
8. COMMISSIONING PROCEDURE:
8.1.0 CURRENT TRANSFORMER
An outdoor CT is of a single-phase design. It is used in a switchyard for
metering as well as protection purposes.
CT TESTS
8.1.1 Insulation Resistance test
Insulation resistance test has to be carried out for checking the
healthiness of the Insulation. A 5 / 2.5 kV Megger is used for testing the
insulation between Primary terminal and earth. Same test is repeated
between primary and secondary windings.
However, a 500 V Megger is used for testing Insulation between secondary
and earth. If CT has more than one secondary windings, then insulation is
measured between secondary windings also.
8.1.2 Polarity Test
Each current transformer must be subjected to polarity test to prove that
the primary (P1 and P2) and secondary (S1 and S2) terminals are correctly
identified. For this test a moving-coil analogue multimeter is connected
across the secondary winding, with the meter positive terminal coupled to
S1. A low voltage battery, with series-connected switch, is then connected to
the primary terminals, such that the battery positive terminal is coupled to
P1. When the battery is switched on, the meter should flick in the positive
direction .The meter will flick negatively when the switch is opened.
7/29/2019 Electric power distribution Feeder
11/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 11 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
8.1.3 Magnetizing curve
Energizing the secondary winding from a variable voltage AC mains source,whilst the primary remains open-circuited checks the magnetizing curve of
each CT. It is customary to measure the applied voltage and the
magnetizing current at five points in increasing steps. The test results, when
plotted, resemble a B-H curve, but represent the properties of the CT as
whole rather than just the properties of the core material. The CT is said to
be approaching the knee or saturation point when a 10% increase of
applied voltage results in a 50% increase in magnetizing current. For a
protection class CT, the knee point may not occur until approximately 10
times rated secondary current is attained. In order to obtain the voltage
required to carry out a magnetizing test for a 1A secondary CT, a stepup
transformer has to be used.
8.1.4 Current - Ratio
Finally a ratio check has to be carried out. It is customary to conduct this in
conjunction with the primary injection tests mentioned later. Current is
passed through the primary circuit with the help of a primary injection kit. A
suitable ammeter is connected to the secondary circuit, which is connected
to its normal circuit load. The ratio of the primary to the secondary currents
should approximate closely to that stamped on the CT identification plate.
For ratio check primary current injected shall be approx. 50% of the rated
current.
8.1.5 Secondary Winding Resistance should be taken with a Digital
multimeter.
7/29/2019 Electric power distribution Feeder
12/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 12 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
8.1.6 Spark gap setting
Check spark gap setting on p1 terminal by placing a 6 mm thick packerinside the gap, adjust the cam and tightened its screw (applicable for CTs of
220 kV class and above).
Lastly, it must be ensured that the power factor testing terminal earthing link
is in its proper position and CT must be energized only if earthing link is
firmly connected.
8.2.0 CAPACITOR VOLTAGE TRANSFORMER
An outdoor CVT is of a single-phase design. It is used in a switchyard for
Metering as well as protection purposes.
CVT TESTS
Insulation Resistance test
Insulation resistance test has to be carried out for checking the
healthiness of the Insulation. A 5 kV / 2.5kV Megger is used for testing the
insulation between Primary terminal and earth. Same Test is repeated
between primary and secondary windings.
However a 500 V Megger is used for testing Insulation between secondary
and earth. If VT/ CVT has more than one secondary windings then insulation
is measured between secondary windings also.
7/29/2019 Electric power distribution Feeder
13/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 13 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
8.2.2 Polarity test
Voltage transformer polarity is checked in the same manner as for a CT,taking care to ensure that the battery is connected to the primary winding.
8.2.3 Voltage Ratio test
Ratio test is conducted using a low voltage, i.e. mains source. A single-
phase 230V supply is applied to the primary winding with the secondary
winding open-circuited, then a high impedance voltmeter is used to measure
the secondary voltage to determine the voltage ratio.
8.2.4 Secondary Winding Resistance should be taken with Digital multimeter.
8.3.0 LIGHTNING ARRESTOR:
A station lightning arrestor is of single-phase design, suitable for outdoor
service. It is designed to limit surge voltages to a safe value by
discharging the surge current to ground.
LIGHTNING ARRESTOR TESTS:
8.3.1 Insulation Resistance Test
Insulation resistance test has to be carried out for checking the
healthiness of the Insulation. A 5 kV Megger is used for testing theinsulation between each stack and earth.
7/29/2019 Electric power distribution Feeder
14/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 14 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
8.3.2 Test for healthiness of milliammeter
Continuity of ammeter can be checked by giving a single-phase voltage, insteps of 5 volts, starting from 5 volts. The ammeter will show deflection
corresponding
to the voltage applied. For each step of increase in voltage, the
corresponding deflection will be more.
8.3.3 Test for healthiness of surge counter
Applying a single-phase ac source can check operation of counter. A 220
volts pulse is given to the two ends of counter momentarily, with the help
of a 1-phase variac and then disconnected. The value of counter will
change, which indicates the healthiness of counter.
8.4 CIRCUIT BREAKER :
8.4.1 INSULATION RESISTANCE MEASUREMENT:
Insulation Resistance is measured using a 5 KV Motorised Megger for
checking the healthiness of insulators. It is measured across poles when CB is
open and between each pole and earth when CB is closed.
A 500 V Megger is used to check the insulation level of control wiring and
incoming 3 phase AC supply cable
8.4.2 MEASUREMENT OF COIL RESISTANCE TRIP & CLOSING:These are measured with the help of a digital multimeter for site record.
8.4.3 CONTACT RESISTANCE MEASUREMENT:
Contact resistance can be measured by passing 100A DC current through
the contacts and measuring millivolt drop across the contacts using thin
7/29/2019 Electric power distribution Feeder
15/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 15 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
leads having negligible voltage drop. Then contact resistance is calculated
as a ratio of measured millivolt to the applied current. These values are
compared with factory tests and should match with them.
8.4.4 C & TAN DELTA VALUE MEASUREMENT OF GRADING CAPACITORS:
Using a Semi-automatic/automatic 10 KV test kit consisting of a schering
bridge ,this measurement is carried out at site. The values are directly
recorded from the test kit in UST mode when the bridge is balanced.
8.4.5 CONTACTS CLOSING AND OPENING TIME MEASUREMENT:
It is measured with the help of time interval meter/breaker operational
analyzer. The readings are directly recorded from the test kit. These
values should match with the factory test results and should be within
acceptance limit.
8.5 ISOLATORS:
8.5.1. INSULATION RESISTANCE MEASURMENT:
Insulation Resistance is measured using a 5 KV Motorised Megger for
checking the healthiness of insulators.
Healthiness of insulation of control wiring and motor circuit is checked with
the help of a 500 v Megger.
8.5.2 HEALTHINESS OF AUXILIARY CONTACTS:
It can be checked with the help of a continuity tester. All the NO and NC
contacts are checked in both the positions of isolators i,e open and close.
7/29/2019 Electric power distribution Feeder
16/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 16 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
8.5.3 OPERATING CURRENT OF THREE PHASE AC MOTOR:
It is measured with the help of a clamp-on meter. The current in all threephases should be balanced.
8.5.4 OPERATION OF OVERLOAD RELAY:
This relay is checked using the phenomenon of single phasing. For
this,the output is connected to motor and set the overload relay for a
particular value. Then current is applied by means of a secondary
injection kit through any two phases at the input of the relay;leaving the
third phase open. Check the relay is operated around set value of
bimetallic relay.
8.5.5 CONTACT RESISTANCE MEASURMENT:
Contact resistance can be measured by passing 100A DC current through
the contacts and measuring millivolt drop across the contacts using thin
leads having negligible voltage drop. Then contact resistance is calculated
as a ratio of measured millivolt to the applied current. These values are
compared with factory tests and should match with them.
8.5.6 LOCAL & REMOTE OPERATION (ELECTRICAL):
For the local operation of isolator, its earthswitch and associated circuit
breaker should be open and all other interlocks with the bus earth switch
are satisfied. The castle key is inserted and DC&AC supplies are switchedON. Now the local command is given through a rotary switch mounted on
the MOM Box in the field.
For the remote operation,the local./remote switch is put in remote mode
and the command is given from the control panel in the control room
through a rotary switch.
7/29/2019 Electric power distribution Feeder
17/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 17 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
8.6 EARTHSWITCHES:
8.6.1 INSULATION RESISTANCE MEASURMENT:
8.6.2 HEALTHINESS OF AUXILIARY CONTACTS:
8.6.3 OPERATING CURRENT OF THREE PHASE AC MOTOR:
8.6.4 OPERATION OF OVERLOAD RELAY:
The above tests are carried out as same as that of isolators as mentioned
above.
8.6.5 CHECKING OF CONTINUITY OF EARTH BLADE WITH EARTHING
SYSTEM :
It is checked with the help of a 500 V Insulation Tester and the value
should be zero which confirms the continuity of the earth blade with the
earthing system.
8.6.6 LOCAL OPERATION (ELECTRICAL & MECHANICAL):
For the local electrical operation of Earthswitch, its isolator should be open.
The castle key is inserted and DC&AC supplies are switched ON. Now the
local command is given through a rotary switch mounted on the MOM Box
in the field.
For the local mechanical operation, Castle key is taken out from the frontdoor and put into the side door fitting of MOM Box. Now the earthswitch is
free to be operated manually with the help of the lever.
7/29/2019 Electric power distribution Feeder
18/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 18 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
9. COMPLETION CRITERIA:
ALL MEASUREMENTS TAKEN DURING TESTS HAVE BEEN
RECORDED AND FOUND IN ACCEPTANCE LIMITS. FEEDER IS
READY FOR SYSTEM COMMISSIONING.
7/29/2019 Electric power distribution Feeder
19/19
STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/
Page 19 of 19
PLANT AREA : 400 KV SWITCHYARD
TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER
10. APPENDICES:
DRAWINGS :
1. SINGLE LINE DIAGRAM OF 400 KV SWITCHYARD (No: TB DG 186
510 0101 ,REV 02)
2. OGA DRAWINGS OF CT,CVT & LIGHTNING ARRESTORS (No: TB
DG 186 316 0241/01,251/01 & 351/01)
3. OGA DRAWINGS OF CB, BPI (No: TB DG 186 316 0201/00,301/00)
4. WIRING DRAWINGS OF CT,CVT & SF6 CIRCUIT BREAKERS (No:
TB DG 186 316 0242/01,252/01 & 205/00)
5. SCHEMATIC DRAWINGS FOR ISOLATORS AND EARTHSWITCHES.
(No: 3 562 510 0277)
6. GENERAL ARRANGEMENT DRAWINGS FOR ISOLATORS AND
EARTH SWITCHES. (No: 3 562 316 0271,272, 274)
7. SCHEMATIC DRAWING OF 400 KV FEEDER(No: 3 562 316
0296/R03)
8. SCHEMATIC, WIRING & GA DRAWINGS FOR CIRCUIT BREAKER
(No: 3 562 316 0204/01,205/00 & 201/00)
9. O&M MANUAL OF CT, CVT, ISO, LA (No: TB OM 186 316 0250, 260,
297, 362)