Electric power distribution Feeder

Embed Size (px)

Citation preview

  • 7/29/2019 Electric power distribution Feeder

    1/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 1 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    LIST OF CONTENTS

    1. PLANT DETAILS

    2. TESTING OBJECTIVES

    3. TESTING PROPOSALS

    4. SERVICES REQUIRED

    5. SAFETY PRECAUTIONS

    6. EMERGENCY PROCEDURES

    7. STATE OF THE PLANT

    8. COMMISSIONING PROCEDURE

    9. COMPLETION CRITERIA

    10.APPENDICES

  • 7/29/2019 Electric power distribution Feeder

    2/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 2 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    1. PLANT DETAILS:

    The system consists of

    i. SF6 Circuit breaker

    ii. Isolators

    iii. Earth switches

    iv. Current transformer

    v. Capacitor voltage transformer

    vi. Lightning arrestor

    NAME PLATE DETAILS:

    1. SF6 CIRCUIT BREAKER

    MAKE : BHEL HYDERABAD TYPE : 3AT2

    LOCATION : 400 KV SWITCHYARD

    RATED VOLTAGE : 420 KV RATED CURRENT : 3150 AMPS

    CONTROL VOLTAGE : 220V DC

    2. ISOLATORS (MAKE : S &S SWITCHGEAR, CHENNAI )

    TYPE : HORIZONTAL CENTRE BREAK

    RATED VOLTAGE : 400 KV RATED CURRENT : 2000 A

    AUX. SUPPLY : 220 V DC CONTROL

    415 V AC MOTOR3. EARTH SWITCHES

    MAKE : S & S SWITCHGEAR TYPE : V L E

  • 7/29/2019 Electric power distribution Feeder

    3/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 3 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    4. CURRENT TRANSFORMER:

    MAKE : BHEL BHOPAL TYPE : OUTDOOR

    SYSTEM VOLTAGE : 400 KV RATIO : 500-1000-2000/1 A

    SHORT TIME THERMAL RATING : 40 KA/ 1 SEC. NO. OF CORES: 5

    CLASS : PS (4 CORES) & 0.2 ( 1 CORE) MET CT BURDEN: 40 VA

    KNEE POINT VOLTAGE : 2000 volts EXCITATION CURRENT : 30 mA (s1-s3)

    60 mA(s1-s2)

    5. CAPACITOR VOLTAGE TRANSFORMER:

    MAKE : BHEL BHOPAL TYPE : OUTDOOR

    RATED VOLTAGE (PH N) : 400 KV/3 / 110 V/3

    VOLTAGE FACTOR : 1.5/3 SEC TOTAL CAPACITANCE : 4400 pf

    NOMINAL INTERMEDIATE VOLTAGE : 22 KV/3

    6. LIGHTNING ARRESTORS:

    MAKE : WS INDUSTRIES(INDIA) LTD,BANGALORE

    TYPE : METAL OXIDE , GAPLESS

    RATED VOLTAGE : 390 KV (rms) RATED CURRENT : 10 KA

    MAXIMUM DISCHARGE CAPABILITY: 8KJ/KV

    MAXIMUM FRONT OF WARE SPARK OVER VOLTAGE : 1050 KVP

  • 7/29/2019 Electric power distribution Feeder

    4/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 4 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    2. TESTING OBJECTIVE:

    TO TEST THE 400 KV SWITCHYARD FEEDER /LINE AND MAKE

    IT READY FOR COMMISSIONING.

  • 7/29/2019 Electric power distribution Feeder

    5/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 5 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    3. TESTING PROPOSAL:

    The 400 KV Switchyard feeder will be checked and tested as per the standard

    checklist and field test reports of its under mentioned equipments.

    i. SF6 Circuit breaker

    ii. Isolators

    iii. Earth switches

    iv. Current transformer

    v. Capacitor voltage transformer

    vi. Lightning arrestor

    vii. Control & Relay panel

  • 7/29/2019 Electric power distribution Feeder

    6/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 6 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    4. SERVICES REQUIRED:

    4.1 Calibrated Test Kit

    a. 5 KV Hand/Motorised Megger

    b. 500 V Megger

    c. Earth Megger

    d. Pressure and Temperature gauges

    e. Milli second timer

    f. Digital Multimeter

    g. Micro Ohm meter / Kelvins Double bridge

    h. Clamp-on meter for current measurement

    i. Operational analyzer(Optional)

    j. Motwane analogue multimeter

    k. Tan delta equipment

    4.2 Current Injection Kit

    4.3 3 Phase 415 V AC 50 Hz Supply

    4.4 1 Phase 230 V AC 50 Hz Supply

    4.5 1.5 V Battery cell for checking the polarity of CTs

  • 7/29/2019 Electric power distribution Feeder

    7/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 7 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    5. SAFETY PRECAUTIONS:

    5.1 The engineer-in-charge of the testing team will inform each member of

    the test as to exact nature and extent of his contribution and

    responsibilities towards tests carried out.

    5.2 Only nominated persons will take part in the tests. All others will remain

    clear of the area.

    5.3 All persons must acquaint themselves with use and location of fire

    extinguishers and First-Aid Box.

    5.4 Each test will be carried out under the control of test team leader

    5.5 A strict and safe method of applying test leads shall be practiced. Bare

    wires should not be used in stead proper lugs must be used. All test

    connections shall be tightened and rechecked.

    5.6 A record of any alterations made during the tests such as shorts or

    disconnections shall be made and annexed to the relevant test

    procedures.

    5.7 Each test will be carefully planned so that there is no mechanical or

    electrical damage to the equipment under test.

    5.8 Test area will be kept clean ,clearly defined and cardoned off.

    5.9 When high voltage test are being made Danger/Warning notices shallbe fixed at relevant points to ensure safety and a sanction for test taken.

    All isolating points to be manned.

  • 7/29/2019 Electric power distribution Feeder

    8/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 8 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    6. EMERGENCY PROCEDURE:

    6.1 Shock treatment chart and first-aid box will be made available.

    6.2 Emergency telephone numbers for hospital and fire services shall be

    prominently displayed.

    6.3 A telephone will be available nearby

  • 7/29/2019 Electric power distribution Feeder

    9/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 9 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    7. STATE OF THE PLANT:

    7.1 Erection of 400 KV Bus and its associated equipments completed.

    7.2 Earthing of the equipments completed

    7.3 Oil level in CT,CVT & Circuit Breaker is OK.

    7.4 400 KV Bus Bar is dead

    7.5 Clearance from erection department for carrying out various tests obtained.

    7.6 Area of test is completely isolated from illegal entry of trespassers

  • 7/29/2019 Electric power distribution Feeder

    10/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 10 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    8. COMMISSIONING PROCEDURE:

    8.1.0 CURRENT TRANSFORMER

    An outdoor CT is of a single-phase design. It is used in a switchyard for

    metering as well as protection purposes.

    CT TESTS

    8.1.1 Insulation Resistance test

    Insulation resistance test has to be carried out for checking the

    healthiness of the Insulation. A 5 / 2.5 kV Megger is used for testing the

    insulation between Primary terminal and earth. Same test is repeated

    between primary and secondary windings.

    However, a 500 V Megger is used for testing Insulation between secondary

    and earth. If CT has more than one secondary windings, then insulation is

    measured between secondary windings also.

    8.1.2 Polarity Test

    Each current transformer must be subjected to polarity test to prove that

    the primary (P1 and P2) and secondary (S1 and S2) terminals are correctly

    identified. For this test a moving-coil analogue multimeter is connected

    across the secondary winding, with the meter positive terminal coupled to

    S1. A low voltage battery, with series-connected switch, is then connected to

    the primary terminals, such that the battery positive terminal is coupled to

    P1. When the battery is switched on, the meter should flick in the positive

    direction .The meter will flick negatively when the switch is opened.

  • 7/29/2019 Electric power distribution Feeder

    11/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 11 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    8.1.3 Magnetizing curve

    Energizing the secondary winding from a variable voltage AC mains source,whilst the primary remains open-circuited checks the magnetizing curve of

    each CT. It is customary to measure the applied voltage and the

    magnetizing current at five points in increasing steps. The test results, when

    plotted, resemble a B-H curve, but represent the properties of the CT as

    whole rather than just the properties of the core material. The CT is said to

    be approaching the knee or saturation point when a 10% increase of

    applied voltage results in a 50% increase in magnetizing current. For a

    protection class CT, the knee point may not occur until approximately 10

    times rated secondary current is attained. In order to obtain the voltage

    required to carry out a magnetizing test for a 1A secondary CT, a stepup

    transformer has to be used.

    8.1.4 Current - Ratio

    Finally a ratio check has to be carried out. It is customary to conduct this in

    conjunction with the primary injection tests mentioned later. Current is

    passed through the primary circuit with the help of a primary injection kit. A

    suitable ammeter is connected to the secondary circuit, which is connected

    to its normal circuit load. The ratio of the primary to the secondary currents

    should approximate closely to that stamped on the CT identification plate.

    For ratio check primary current injected shall be approx. 50% of the rated

    current.

    8.1.5 Secondary Winding Resistance should be taken with a Digital

    multimeter.

  • 7/29/2019 Electric power distribution Feeder

    12/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 12 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    8.1.6 Spark gap setting

    Check spark gap setting on p1 terminal by placing a 6 mm thick packerinside the gap, adjust the cam and tightened its screw (applicable for CTs of

    220 kV class and above).

    Lastly, it must be ensured that the power factor testing terminal earthing link

    is in its proper position and CT must be energized only if earthing link is

    firmly connected.

    8.2.0 CAPACITOR VOLTAGE TRANSFORMER

    An outdoor CVT is of a single-phase design. It is used in a switchyard for

    Metering as well as protection purposes.

    CVT TESTS

    Insulation Resistance test

    Insulation resistance test has to be carried out for checking the

    healthiness of the Insulation. A 5 kV / 2.5kV Megger is used for testing the

    insulation between Primary terminal and earth. Same Test is repeated

    between primary and secondary windings.

    However a 500 V Megger is used for testing Insulation between secondary

    and earth. If VT/ CVT has more than one secondary windings then insulation

    is measured between secondary windings also.

  • 7/29/2019 Electric power distribution Feeder

    13/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 13 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    8.2.2 Polarity test

    Voltage transformer polarity is checked in the same manner as for a CT,taking care to ensure that the battery is connected to the primary winding.

    8.2.3 Voltage Ratio test

    Ratio test is conducted using a low voltage, i.e. mains source. A single-

    phase 230V supply is applied to the primary winding with the secondary

    winding open-circuited, then a high impedance voltmeter is used to measure

    the secondary voltage to determine the voltage ratio.

    8.2.4 Secondary Winding Resistance should be taken with Digital multimeter.

    8.3.0 LIGHTNING ARRESTOR:

    A station lightning arrestor is of single-phase design, suitable for outdoor

    service. It is designed to limit surge voltages to a safe value by

    discharging the surge current to ground.

    LIGHTNING ARRESTOR TESTS:

    8.3.1 Insulation Resistance Test

    Insulation resistance test has to be carried out for checking the

    healthiness of the Insulation. A 5 kV Megger is used for testing theinsulation between each stack and earth.

  • 7/29/2019 Electric power distribution Feeder

    14/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 14 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    8.3.2 Test for healthiness of milliammeter

    Continuity of ammeter can be checked by giving a single-phase voltage, insteps of 5 volts, starting from 5 volts. The ammeter will show deflection

    corresponding

    to the voltage applied. For each step of increase in voltage, the

    corresponding deflection will be more.

    8.3.3 Test for healthiness of surge counter

    Applying a single-phase ac source can check operation of counter. A 220

    volts pulse is given to the two ends of counter momentarily, with the help

    of a 1-phase variac and then disconnected. The value of counter will

    change, which indicates the healthiness of counter.

    8.4 CIRCUIT BREAKER :

    8.4.1 INSULATION RESISTANCE MEASUREMENT:

    Insulation Resistance is measured using a 5 KV Motorised Megger for

    checking the healthiness of insulators. It is measured across poles when CB is

    open and between each pole and earth when CB is closed.

    A 500 V Megger is used to check the insulation level of control wiring and

    incoming 3 phase AC supply cable

    8.4.2 MEASUREMENT OF COIL RESISTANCE TRIP & CLOSING:These are measured with the help of a digital multimeter for site record.

    8.4.3 CONTACT RESISTANCE MEASUREMENT:

    Contact resistance can be measured by passing 100A DC current through

    the contacts and measuring millivolt drop across the contacts using thin

  • 7/29/2019 Electric power distribution Feeder

    15/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 15 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    leads having negligible voltage drop. Then contact resistance is calculated

    as a ratio of measured millivolt to the applied current. These values are

    compared with factory tests and should match with them.

    8.4.4 C & TAN DELTA VALUE MEASUREMENT OF GRADING CAPACITORS:

    Using a Semi-automatic/automatic 10 KV test kit consisting of a schering

    bridge ,this measurement is carried out at site. The values are directly

    recorded from the test kit in UST mode when the bridge is balanced.

    8.4.5 CONTACTS CLOSING AND OPENING TIME MEASUREMENT:

    It is measured with the help of time interval meter/breaker operational

    analyzer. The readings are directly recorded from the test kit. These

    values should match with the factory test results and should be within

    acceptance limit.

    8.5 ISOLATORS:

    8.5.1. INSULATION RESISTANCE MEASURMENT:

    Insulation Resistance is measured using a 5 KV Motorised Megger for

    checking the healthiness of insulators.

    Healthiness of insulation of control wiring and motor circuit is checked with

    the help of a 500 v Megger.

    8.5.2 HEALTHINESS OF AUXILIARY CONTACTS:

    It can be checked with the help of a continuity tester. All the NO and NC

    contacts are checked in both the positions of isolators i,e open and close.

  • 7/29/2019 Electric power distribution Feeder

    16/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 16 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    8.5.3 OPERATING CURRENT OF THREE PHASE AC MOTOR:

    It is measured with the help of a clamp-on meter. The current in all threephases should be balanced.

    8.5.4 OPERATION OF OVERLOAD RELAY:

    This relay is checked using the phenomenon of single phasing. For

    this,the output is connected to motor and set the overload relay for a

    particular value. Then current is applied by means of a secondary

    injection kit through any two phases at the input of the relay;leaving the

    third phase open. Check the relay is operated around set value of

    bimetallic relay.

    8.5.5 CONTACT RESISTANCE MEASURMENT:

    Contact resistance can be measured by passing 100A DC current through

    the contacts and measuring millivolt drop across the contacts using thin

    leads having negligible voltage drop. Then contact resistance is calculated

    as a ratio of measured millivolt to the applied current. These values are

    compared with factory tests and should match with them.

    8.5.6 LOCAL & REMOTE OPERATION (ELECTRICAL):

    For the local operation of isolator, its earthswitch and associated circuit

    breaker should be open and all other interlocks with the bus earth switch

    are satisfied. The castle key is inserted and DC&AC supplies are switchedON. Now the local command is given through a rotary switch mounted on

    the MOM Box in the field.

    For the remote operation,the local./remote switch is put in remote mode

    and the command is given from the control panel in the control room

    through a rotary switch.

  • 7/29/2019 Electric power distribution Feeder

    17/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 17 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    8.6 EARTHSWITCHES:

    8.6.1 INSULATION RESISTANCE MEASURMENT:

    8.6.2 HEALTHINESS OF AUXILIARY CONTACTS:

    8.6.3 OPERATING CURRENT OF THREE PHASE AC MOTOR:

    8.6.4 OPERATION OF OVERLOAD RELAY:

    The above tests are carried out as same as that of isolators as mentioned

    above.

    8.6.5 CHECKING OF CONTINUITY OF EARTH BLADE WITH EARTHING

    SYSTEM :

    It is checked with the help of a 500 V Insulation Tester and the value

    should be zero which confirms the continuity of the earth blade with the

    earthing system.

    8.6.6 LOCAL OPERATION (ELECTRICAL & MECHANICAL):

    For the local electrical operation of Earthswitch, its isolator should be open.

    The castle key is inserted and DC&AC supplies are switched ON. Now the

    local command is given through a rotary switch mounted on the MOM Box

    in the field.

    For the local mechanical operation, Castle key is taken out from the frontdoor and put into the side door fitting of MOM Box. Now the earthswitch is

    free to be operated manually with the help of the lever.

  • 7/29/2019 Electric power distribution Feeder

    18/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 18 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    9. COMPLETION CRITERIA:

    ALL MEASUREMENTS TAKEN DURING TESTS HAVE BEEN

    RECORDED AND FOUND IN ACCEPTANCE LIMITS. FEEDER IS

    READY FOR SYSTEM COMMISSIONING.

  • 7/29/2019 Electric power distribution Feeder

    19/19

    STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-NTPC REF NO : SIM/1/TS/1/

    Page 19 of 19

    PLANT AREA : 400 KV SWITCHYARD

    TESTING SCHEDULE : 400 KV SWITCHYARD FEEDER

    10. APPENDICES:

    DRAWINGS :

    1. SINGLE LINE DIAGRAM OF 400 KV SWITCHYARD (No: TB DG 186

    510 0101 ,REV 02)

    2. OGA DRAWINGS OF CT,CVT & LIGHTNING ARRESTORS (No: TB

    DG 186 316 0241/01,251/01 & 351/01)

    3. OGA DRAWINGS OF CB, BPI (No: TB DG 186 316 0201/00,301/00)

    4. WIRING DRAWINGS OF CT,CVT & SF6 CIRCUIT BREAKERS (No:

    TB DG 186 316 0242/01,252/01 & 205/00)

    5. SCHEMATIC DRAWINGS FOR ISOLATORS AND EARTHSWITCHES.

    (No: 3 562 510 0277)

    6. GENERAL ARRANGEMENT DRAWINGS FOR ISOLATORS AND

    EARTH SWITCHES. (No: 3 562 316 0271,272, 274)

    7. SCHEMATIC DRAWING OF 400 KV FEEDER(No: 3 562 316

    0296/R03)

    8. SCHEMATIC, WIRING & GA DRAWINGS FOR CIRCUIT BREAKER

    (No: 3 562 316 0204/01,205/00 & 201/00)

    9. O&M MANUAL OF CT, CVT, ISO, LA (No: TB OM 186 316 0250, 260,

    297, 362)