Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
ELABORATION OF TECHNICAL PROJECT CONCEPT OF THE
FUEL SWITCH TO BIOMASS IN PROKUPLJE
INCLUDING ECONOMICAL EVALUATION AND
RECOMMENDATIONS FOR IMPLEMENTATION STRUCTURE OF
DISTRICT HEATING GRID
Prepared for:
Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
Dag Hammarskjöld Weg 1-5
Postfach/ P.O.Box 5180
65760 Eschborn
Prepared by:
K.R.B. Consulting & agency
Starovlaška 89
32250 Ivanjica
September 2017
2
Table of Contents
1. EXECUTIVE SUMMARY ........................................................................................................... 8
2. INTRODUCTION .................................................................................................................... 11
3. PROJECT LOCATION ............................................................................................................ 13
4. EXISTING HEATING SYSTEMS............................................................................................. 16
5. BIOMASS MARKET ANALYSIS.............................................................................................. 35
6. TECHNICAL DESIGN CONCEPT ............................................................................................ 39
6.1 TECHNICAL SOLUTIONS AND SIZING THE BOILER ........................................................... 39
6.2 HEATING PLANT, LOCATION AND FACILITIES ................................................................... 44
6.2.1 HEATING PLANT ‘А’ ............................................................................................................ 44
6.2.2 HEATING PLANT ‘B’ ............................................................................................................ 46
6.3 CONCEPT OF DISTRICT HEATING NETWORK.................................................................... 48
6.3.1 CONCEPT OF DISTRICT HEATING NETWORK................................................................. 48
6.3.2 SCHEME OF DISTRICT HEATING NETWORK ................................................................... 49
6.3.3 CONCEPT OF HEATING SUBSTATIONS ........................................................................... 60
7. PRELIMINARY COST ESTIMATES ........................................................................................ 62
8. PRELIMINARY FINANCIAL ANALYSIS .................................................................................. 65
9. PROJECT EVALUATION ........................................................................................................ 67
10. LEGAL FRAMEWORK ........................................................................................................... 68
11. ENVIRONMENTAL IMPACT .................................................................................................. 69
12. ENERGY EFFICIENCY MEASURES AND CONCLUSION .................................................... 72
13. ANNEX .................................................................................................................................. 73
3
List of tables Table 1- Public buildings in Prokuplje ............................................................................................. 8
Table 2 - The structure of Prokuplje land ..................................................................................... 14
Table 3 - Data on population of Prokuplje from 1961 to 2011 ....................................................... 15
Table 4 - Data on population of the town of Prokuplje from 1961 to 2011 .................................... 15
Table 5 - Microclimate data for the City of Prokuplje .................................................................... 16
Table 6 - Data on buildings connected to the boiler room of Gymnasium ..................................... 17
Table 7 - Data on the building of primary school ‘Ratko Pavlović Ćićko’ ...................................... 20
Table 8 - Data on the buildings of Kindergartens ‘Biseri’ and ‘Bambi’ ........................................... 21
Table 9 - Data on buildings of the Municipality and Police station ................................................ 23
Table 10 - Data on the buildings connected to the boiler room in Technical school ...................... 24
Table 11 - Data on the building of primary school ‘9. Oktobar’ ..................................................... 26
Table 12 - Data on the Sports hall ................................................................................................ 27
Table 13 - Calculated capacity of future heating plants ................................................................ 28
Table 14 - Current situation, energy and fuel consumption, price, CO2 emission ......................... 31
Table 15 - Requirements for wood chips according to SRPS EN ISO 17225-4:2015 ................... 35
Table 16 - Classification of wood chips based on the moisture content according to
SRPS EN ISO 17225-4 ................................................................................................................ 35
Table 17 - Classification of bulk density of wood chips according to SRPS EN ISO 17225-4:2015
.................................................................................................................................................... 35
Table 18 - Requirements for wood chips according to SRPS EN ISO 17225-4:2015 ................... 36
Table 19 - Data on forests provided by SE ‘Srbijašume’, FE ‘Kuršumlija’ ..................................... 36
Table 20 - The energy potential of green chips from forestry, with wood waste from sawmill
industry, in the municipalities of Nova Varos, Priboj and Prijepolje ............................................... 38
Table 21 - The energy potential of biomass from FE ‘Kuršumlija’ ................................................. 38
Table 22 - Characteristics of wood chips depending on the percentage of moisture .................... 38
Table 23 - Unit price of wood chips depending on the percentage of moisture ............................. 39
Table 24 - Comparative analysis of the costs of currently used fuels in Prokuplje and costs of
biomass ....................................................................................................................................... 39
Table 25 - Overview of the areas and capacity of central biomass heating systems ‘A’ and ‘B’ .... 41
Table 26 - Calculated capacity of future heating plant .................................................................. 42
Table 27 - Sizing the pipe network by routes ................................................................................ 58
Table 28 - Calculation of operation point of network pump, heating plant ‘A’ ................................ 59
Table 29 - Calculation of operation point of network pump, heating plant ‘B’ ................................ 59
Table 30 - Working points of circulation pumps for heating plant ‘A’ and ‘B’ ................................. 59
Table 31 - Selection of substations in the facilities ....................................................................... 61
Table 32 - Investment costs ......................................................................................................... 62
Table 33 - Operational costs ........................................................................................................ 64
Table 34 - Costs of energy production ......................................................................................... 65
Table 35 - Unit costs of heating energy ........................................................................................ 67
4
List of figures Figure 1 - Location of the Toplica District ..................................................................................... 13
Figure 2 - Municipalities of the Toplica District ............................................................................. 13
Figure 3 - Energy consumption per fuel types - current situation .................................................. 31
Figure 4 - CO2 emission per fuel types, current situation .............................................................. 32
Figure 5 - Annual energy costs per fuel types, current situation ................................................... 32
Figure 6 - Unit price of energy per fuel type, current situation ...................................................... 33
Figure 7 - State and private forestsper Municipalities and Districts .............................................. 37
Figure 8 - Share of forest’s area in the total area of the Serbian municipalities ............................ 37
Figure 9 - Annual energy costs per fuel types - comparison with biomass ................................... 40
Figure 10 - Unit price of energy per fuel type - comparison with biomass ..................................... 40
Figure 11 - Diagram of the annual distribution of the heat capacity of the heating plants ............. 42
Figure 12 - Situation plan of heating plant ‘A’ ............................................................................... 44
Figure 13 - Situation plan of heating plant ‘B’ ............................................................................... 46
Figure 14 - Disposition of drawings of the heating network per numbers ...................................... 49
Figure 15 - Drawing No 1 of the heating network ......................................................................... 50
Figure 16 - Drawing No 2 of the heating network ......................................................................... 51
Figure 17 - Drawing No 3 of the heating network ......................................................................... 52
Figure 18 - Drawing No 4 of the heating network ......................................................................... 53
Figure 19 - Drawing No 5 of the heating network ......................................................................... 54
Figure 20 - Drawing No 6 of the heating network ......................................................................... 55
Figure 21 - Drawing No 7 of the heating network ......................................................................... 56
Figure 22 - Drawing No 8 of the heating network ......................................................................... 57
Figure 23 - Scheme of compact substation DSA 1 Mini Danfoss .................................................. 60
Figure 24 - Substation DSA - Mini Danfoss .................................................................................. 61
Figure 25 - Substation DSP – MAXI Danfoss ............................................................................... 61
Figure 26 - Emission of CO2 per a fuel type ................................................................................. 71
Figure 27 - Comparative analysis of costs of heating energy and savings ................................... 74
Figure 28 - Savings from fuel switch ............................................................................................ 75
Figure 29 - Operational costs and depreciation ............................................................................ 76
Figure 30 - Comparison of total costs of the existing system, new heating system and new system
supported by KfW Credit .............................................................................................................. 77
Figure 31 - Cash flow balance...................................................................................................... 78
5
List of photos Photo 1 - Building of Gymnasium ................................................................................................. 17
Photo 2 - Light fuel oil boilers, 3x550kW ...................................................................................... 17
Photo 3 - Insulated hot water collector ......................................................................................... 17
Photo 4 - Gymnasium .................................................................................................................. 17
Photo 5 - Gym hall ‘Sokolski dom’ ................................................................................................ 18
Photo 6 - Building of ‘Sokolski dom’ ............................................................................................. 18
Photo 7 - Building of National Museum Toplice ............................................................................ 18
Photo 8 - Panel radiator in the Museum ....................................................................................... 18
Photo 9 - Primary school ‘Nikodije Stojanović Tatko’ .................................................................... 19
Photo 10 - Movie Theatre, street view .......................................................................................... 19
Photo 11 - Movie Theater and Gymnasium schoolyard view ........................................................ 19
Photo 12 - Primary school ‘Ratko Pavlović Ćićko’ ........................................................................ 20
Photo 13 - Wood pellet boilers, 2x250kW .................................................................................... 20
Photo 14 - Insulated hot water collector ....................................................................................... 21
Photo 15 - Radiator without thermostatic valve ............................................................................ 21
Photo 16 - Kindergarten ‘Biseri’ .................................................................................................... 22
Photo 17 - Kindergarten ‘Bambi’ .................................................................................................. 22
Photo 18 - Boiler in Kindergarten ‘Biseri’ ...................................................................................... 22
Photo 19 - Underground fuel oil tank in the yard of Kindergarten ................................................ 22
Photo 20 - Damaged insulation of hot water collector .................................................................. 22
Photo 21 - Building of the Municipality ......................................................................................... 23
Photo 22 - Police station .............................................................................................................. 23
Photo 23 - Fuel oil boilers in municipal boiler room ...................................................................... 23
Photo 24 - Uninsulated hot water collectors in municipal boiler room ........................................... 24
Photo 25 - Underground oil tank in the yard of the Police station ................................................. 24
Photo 26 - Technical school ’15. maj’ and School gym ................................................................ 25
Photo 27 - Primary school ‘Milić Rakić Mirko’ ............................................................................... 25
Photo 28 - Fuel oil boilers in Technical school ............................................................................. 25
Photo 29 - Uninsulated hot water collectors ................................................................................. 25
Photo 30 - Underground fuel ........................................................................................................ 25
Photo 31 - Primary school ‘9. Oktobar’, main building .................................................................. 26
Photo 32 – Secondary building of the School ............................................................................... 26
Photo 33 - Fuel oil boilers in primary school ‘9. oktobar’............................................................... 26
Photo 34 - Hot water collectors in the School ‘9. Oktobar’ ............................................................ 27
Photo 35 - Underground fuel oil tank in the Schoolyard................................................................ 27
Photo 36 - Sports hall ‘Dr. Zoran Đinđić’ ...................................................................................... 27
Photo 37 - Sport court inside the Sports hall ................................................................................ 27
Photo 38 - LPG boiler .................................................................................................................. 28
Photo 39 - Circulation pumps ....................................................................................................... 28
Photo 40 - Locked LPG switch ..................................................................................................... 28
Photo 41 - LPG infrared heater .................................................................................................... 28
Photo 42 - Fenced underground LPG tank ................................................................................... 28
Photo 43 - Auxiliary facility of planned boiler room ....................................................................... 29
Photo 44 - Insulated connection ................................................................................................... 29
6
Photo 45 - Location of the heating plant ‘A’ .................................................................................. 44
Photo 46 - Pre-insulated pipes for the district heating network ..................................................... 48
7
List of abbreviations CAPEX - Capital Expenditure
CO2 - Carbon Dioxide
€ - Euro (currency)
(E) IRR - (Economy) Internal Rate of Return
(E) NV - (Economy) Net Present Value
FE - Forest enterprise
(F) IRR - (Financial) Internal Rate of Return
(F) NPV - (Financial) Net Present Value
LUC - Levelled Unit Costs
OPEX - Operating Expenditure
PVC - Polyvinyl chloride
RS - Republic of Serbia
SE - State enterprise
8
1. EXECUTIVE SUMMARY
This study elaborates technical concept of a fuel switch in public buildings in Prokuplje municipality
and introduction of biomass as a fuel, as well as the installation of a biomass boiler and construction
of district heating network.
Table 1 shows public buildings in Prokuplje and heating related data:
Institution Location of
existing boiler room
Type of fuel
Heating
area estimated capacity
m2 kW
1 Gymnasium
Gymnasium building
Light fuel oil
3,710 779
2 Gym hall ‘Sokolski Dom’ 574 145
3 National Museum Toplice 513 115
4 Movie Theatre 423 148
5 Primary school ‘Nikodije Stojanović Tatko’
1,360 272
6 Primary school ‘Ratko Pavlović Ćićko’ Own boiler
room Pellet 2,839 497
7 Kindergarten ‘Biseri’ Kindergarten ‘Biseri’
Light fuel oil
458 59
8 Kindergarten ‘Bambi’ 529 79
9 Building of the Municipality Building of the Municipality
Light fuel oil
2,518 466
10 Police station 954 143
11 Secondary Technical School ’15. maj’ Technical
school Light fuel
oil
2,790 446
12 School gym 780 196
13 Primary school ‘Milić Rakić Mirko’ 1,524 244
Heating plant "A" cadastral plot
2308/1 18,972 3,589
14 Primary school ‘9. oktobar’ Primary school Light fuel
oil 2,080 364
15 Sports hall ‘Dr. Zoran Đinđić’ Sports hall Electricity 2,070 767
Heating plant "B" cadastral plot
1704/1 4,150 1,131
TOTAL BIOMASS HEATING PLANTS 23,122 4,720
Table 1- Public buildings in Prokuplje
As shown in Table 1, public buildings currently have various heating systems and use different types
of fuel to obtain thermal energy. Almost all of these heating systems and boilers are functional, but
in a poor condition. These systems are economically and energy inefficient, expensive to
maintaining and servicing. Furthermore, they are big pollutants.
Offered technical solution envisages construction of following:
- Two Central boiler rooms with biomass (wood chips) heated boilers
- Two District heating network
9
- Heating substations, where delivered heating energy would be measured, and which would
serve to managing consumption of heating energy in particular buildings.
Considering that public buildings in Prokuplje are spread all over the town, it is necessary
construction of two biomass-heating plants.
Heating plant ‘A’ is envisaged in the city zone, on cadastral plot 2308/1, that is location of former
landfill on left riverbank of the Toplica River. Pipeline is planned from the plant ‘A’ to central city
boiler rooms located in the buildings of Gymnasium, primary school ‘Ratko Pavlović Tatko’,
kindergarten ‘Biseri’, Municipality, and Technical school ’15. maj’. Capacity of the boilers in the plant
‘A’ is 2,000+2,500 kW. Facility with area of 680 m² is planned for boilers, equipment, and for storage
of wood chips sufficient for four days of operations. It is also planned central storage for wood chips
with area of 2,640 m² and with capacity of 5,270 m³, i.e. 1,580 t. Envisaged central storage of wood
chips has adequate capacity for annual supply of all of public buildings analysed in this study.
Heating plant ‘B’ is envisaged on cadastral plot 1704/1, in immediate vicinity of primary school
‘9 Oktobar’. There will be installed one boiler with capacity of 1,500 kW. Pipeline is planned from
the plant ‘B’ to the boiler rooms of primary school ‘9. oktobar”, and the Sports hall ‘Dr. Zoran Djindjić’.
In the building of Sports hall ‘Dr. Zoran Djindjić’, offices are heated by electricity, while the gym is
not heated, due to which fact its functioning and maintenance are jeopardized. Facility with area of
305 m² is planned for boilers, equipment, and for storage of wood chips sufficient for four days of
operations. For boiler operations during four coldest consecutive weeks in a year, it is necessary
wood chips storage with area of 100 m² and with capacity of 190 m³, i.e. 55 t.
Considering workforce requirements, it is planned engagement of two highly technically educated
employees and one manager in each plant. Workers with lower qualifications would be replaced
from existing assignments in the facilities that will be included in a fuel switch project.
Planned capacity of the district heating network is sufficient for the public buildings, as well as for
potential connection to additional, smaller consumers.
Full load hours in public buildings in Prokuplje is low (808 kWh/kW) due to the heating during working
hours only. The fuel switch project would enable better utilization of the facilities of the Sports hall
in terms of providing commercial services, such as renting, thus generating additional income.
There are forests at territory of the Municipality of Prokuplje and the Toplica District sufficient to
provide biomass for district heating plant. In addition, biomass can be purchased as residues from
orchards and private forests. In such way, local community could close the circle of production and
consumption of heating energy.
Estimated investment value for implementation of this project is 2,151,200 €. Expected period of
return of investment is 9 years from the start of operations.
If the investment was financed from KfW Bank's program, with grant of 20%, grace period of 5 years
and a repayment period of 10 years, the positive business results would be achieved after 7 years
from the start of operations.
The investment could be reduced by 70,000 € in case of construction of the storage of wood chips
10
with area of 1,200 m2 instead of the planned 2,640 m2. However, the storage of 1,200 m2 would
have a capacity sufficient for 50% of annual consumption only.
Prerequisites for successful operations of the plant are following:
‒ Selection of an appropriate financing model (from own funds, credit line or public-private
partnership)
‒ Entering into long-term contracts for the supply of the biomass
‒ Ensuring sufficient fuel storage supply covering consumption in the coldest month of the
year
‒ During the construction phase, train personnel who would take over management and
maintenance of the boiler plant
‒ Ensure high quality maintenance of the specific equipment in cooperation with the supplier
of the equipment.
This investment will achieve the following benefits:
‒ Lower costs of heating energy
‒ Low emission of harmful substances in the exhaust gases
‒ Reduction of CO2 emissions – combustion of wood biomass releases CO2 ‘neutral’
‒ Raising the comfort of all future consumers of the Prokuplje district heating
Techno-economic indicators of the future energy system with wood chips are as follows:
Heat capacity of boilers Woodchips boiler 1,500 + 2,000 + 2,500 kW
Fuel
Woodchips
M30 according to
SRPS EN ISO 17225-1:2015, and
SRPS EN ISO 17225-4:2015
Annual production of thermal energy 3,815 MWhth /a
Annual fuel consumption Woodchips 1,578 t/a
Efficiency on the threshold of the heat plant 0.90 x 0.92
Annual reduction in CO2 emission 689 t/a
CAPEX 2,151,200 €
OPEX (the amortization period) 3,840,636 €
LUC 79.30 EUR/MWh
11
2. INTRODUCTION
The program ‘Development of a Sustainable Bioenergy Market in Serbia’ (GIZ DKTI) is implemented
jointly by the KfW (financing component) and GIZ (technical assistance component). It is funded by
the German Federal Ministry for Economic Cooperation and Development (BMZ) under the German
Climate Technology Initiative (DKTI). The main implementing partner and beneficiary of the
technical assistance (TA) component is the Serbian Ministry of Agriculture, Forestry and Water
Management (MAFWM). The general objective of the project is to strengthen capacities and create
an enabling environment for the sustainable use of bioenergy in Serbia. The TA component includes
the following five activity areas:
1) Policy advice: Assessment of bioenergy potentials and regulatory framework for creating and
enabling environment for private sector investment in bioenergy projects etc.
2) Biomass supply: Accompany investments in biomass-fired district heating plants in up to
three pilot regions with TA to secure a reliable and cost-effective supply of biomass in a
sustainable manner.
3) Efficient firewood utilization at household level: Increase the efficiency of firewood
consumption for heating at household level through the promotion of firewood drying and
efficient stoves/ovens.
4) Project development: Support in cooperation with the national and international private sector
the development and the implementation of feasible bioenergy projects – from biogas or straw
combustion plants in the industry sector to wood based heating boilers in private and public
buildings.
5) EU-Project BioRES – Regional Supply Chains for Woody Bioenergy: BioRES aims at
introducing the innovative concept of Biomass Logistic and Trade Centres (BLTCs) in Serbia,
Croatia, and Bulgaria based on cooperation with technology leaders from Austria, Slovenia,
Germany, and Finland. The BLTCs as regional hubs will help increasing local supply and
demand for wood bioenergy products in these countries.
The development of a biomass supply is required only if there are liable regional consumers of
biomass. As a supporting institution, GIZ DKTI has received a Letter of Expression of Interest signed
by the mayor of Serbian municipality Prokuplje to declare their demand for guidance, legal and
technical assistance in the process of the development of a fuel switch of public buildings in
Prokuplje to biomass. Heating grid will have to be planned.
This fuel switch from existing fuels (electricity, wood, light fuel oil, heavy fuel oil) to biomass should
provide savings in the budget of the municipality by strengthening local incomes with local produced
wood fuel and should reduce emissions of the renewed heating system.
The aim of this study is to establish technical concept for switching to biomass heating, the
installation of a wood chip heating plant including storage recipient and design of the distribution
system including grid and substations.
In addition, it is necessary to estimate the investment costs of the plant, distribution system, perform
financial evaluation of savings from woodchip heating system (compared to current situation)
regarding fuel costs, efficiency, investment and operation costs, cash-flow analysis through savings
12
and sensitivity analysis regarding fuel prices, investment cost and boiler efficiency.
The study includes the following:
- Assessment of the current energy situation in public buildings in Prokuplje regarding
heated area, boiler capacity and current performance, energy consumption and cost
efficiency, condition of distribution system and connections.
- Techno-economic analysis of the proposed system for the production of thermal energy
by burning biomass (wood chips), and distribution system with heating grid and
substations which should include:
Proposal of a technical concept for central woodchip heating system including
boiler, feeding system, storage unit and grid installation taking into consideration
future efficiency measures in the buildings.
Financial evaluation of savings from woodchip heating system (compared to
current situation) regarding fuel costs, efficiency, investment and operation
costs, cash-flow analysis through savings and sensitivity analysis regarding fuel
prices, investment cost and boiler efficiency.
An assessment of CO2 emissions reduction.
The recommendation concerning the quality and availability of wood chips to
supply the plant in the future, taking into account the prices and local suppliers
of wood chips.
Technical concept and preliminary design for heating grid in Prokuplje,
substations and further necessary equipment, including losses, connected to
planned biomass plant.
Estimation of overall investment costs for the heating grid, substations and
further necessary equipment.
Financial evaluation of heat prices compared to current situation taking into
account fuel costs, efficiency, investment and operation costs
13
3. PROJECT LOCATION
The Toplica District is situated in southern part of the Republic of Serbia, covering geographic and
historic area known as Toplica, located in the basins of rivers Toplica and Kosanica. Area of the
District is 2,231 km², and according to Census 2011, number of inhabitants is 91,754 with population
density of 41people/ km². Western border of the District is mountain massif of Kopaonik, and
northern border are mountains of Veliki and Mali Jastrebac. In the east of this District there is the
basin of Južna Morava River towards Niš, and its southern borders are mountains of Vidojevica and
Pasjača. Whole area, as well as the river flowing through this area, are named after numerous hot
water sources (Serbian: toplica, or banja) and spas that are known since the Roman era (such as:
Prolom, Lukovska, Kuršumlijska). The Toplica District consists of:
1. City of Prokuplje 2. Municipality of Blace 3. Municipality of Kuršumlija 4. Municipality of Žitorađa
1 2
City of Prokuplje with area of 759 km2 covers 34% of territory of the Toplica District and
encompasses 1 city and 106 settlements. Urban area is inhabited by 27,333 people, and 17,086
people inhabit the settlements. Main industry is food processing. Confectionery Company ‘Hissar’
is operating successfully after the privatization, while alcoholic beverage production company
‘Prokupac’ broke. It is also significant ‘Leoni’ Company, producing wires, optical cables and fibres;
as well as the Company ‘Nikodije Stojanović Tatko’, producing felt.
1 https://sr.wikipedia.org/sr/Топлички_управни_округ 2 Ibid
Figure 1 - Location of the Toplica District Figure 2 - Municipalities of the Toplica District
14
There is developed road traffic, and railway traffic to some extent. One of important routes in the
area is main road M- 25 between Niš and Priština. This main road connects Prokuplje to highway
E-75 Belgrade- Skopje. Local roads are not in a good condition.
Agriculture is important industry in Prokuplje. Most represented are growing crops, fruit (plums,
apples, cherries, grapes). The land is also suitable for the development of cattle breeding, due to
large area of meadows and pastures.
Surface area of fertile land ha 44,599
Arable land ha 30,567
Orchard land ha 5,954
Forest land ha 29,529
Meadow and pasture land ha 8,078
Table 2 - The structure of Prokuplje land3
Climate is moderate continental with cold winters. Basic meteorological data (average annual
values) of the Toplica District are following:
- Insolation: 145.5 hours/month, i.e. 1,746 hours/year
- The amount of rainfall: 590 mm/year
- Air temperature: 17.3°C, Relative humidity: 70.7 %
- Daily solar radiation on a horizontal surface: 3.62 kWh/m² day
- Atmospheric pressure: 95.2 kPa
- Wind speed: 2.0 m/s (measured at 10 m from the ground)
- Ground temperature: 11.1°C
- Degree day heating: 2,613
- Heating days: 179
- Average temperature during heating days: 5.4°C
Toplica River flows through Prokuplje. On the right bank of the River, there are industrial zone,
sports complex ‘Toplica’, hospital complex, and railway station. On the left riverbank, there is the
city core, which is not homogenous, but concentrated along main road M-25 Niš-Priština. In the
strict city core there are municipal and other public institutions, while schools’ buildings are spread
in the direction of main road. Except for the main City street and main directions to neighbouring
places, the streets in Prokuplje are narrow, not intended for frequent traffic. The relief is such that
the city extends from the slopes on the left riverbank of Toplica towards surrounding slopes of the
mountain Jastrebac. Except for several residential buildings, people live in family houses.
Public buildings are mostly heated by light oil fuel. Solid fuels or electricity are used to a lesser
extent. In particular buildings, there is ongoing modernization of heating systems and fuel switch to
wood pellets.
3 http://www.prokuplje.org.rs/images/content/file/profil%20zajednice.pdf
15
Population of the administrative municipality Prokuplje
Number Census year
of 1961 1971 1981 1991 2002 2011
Inhabitants: 60,075 57,315 56,256 52,969 48,501 44,419
Households: 13,639 15,543 16,806 16,641 16,204 15,119
Table 3 - Data on population of Prokuplje from 1961 to 20114
Population of urban zone of Prokuplje
Number Census year
of 1961 1971 1981 1991 2002 2011
Inhabitants: 13,679 20,104 25,602 28,303 27,673 27,333
Table 4 - Data on population of the town of Prokuplje from 1961 to 20115
The most significant energy potential, which would ensure sustainable development, is the use of
biomass as a fuel. Wood potential of forests and orchards, as well as developed agriculture;
represent a good basis for collecting biomass with the purpose of solving the energy needs of public
and residential buildings in the city. Solution for energy requirements of the buildings is based on
the development of district heating network and installation of biomass boiler.
Positive planning documents, i.e. Detailed regulation plan of the city heating plant from 2011,
consider the central heating source only, and omit the heating network. Therefore, the first step in
establishment of the heating system and a fuel switch to biomass would be to revise the planning
documents, to create a development strategy, and General regulation plan of Prokuplje.
4 The Census of Population, Households and Dwellings in the Republic of Serbia, 2011 http://popis2011.stat.rs/?page_id=2134 5 Ibid
16
4. EXISTING HEATING SYSTEMS
Public institutions in Prokuplje are located in separate buildings with individual radiator systems and
individual boilers using light fuel oil and coil. Qualified personnel manage the boiler rooms. In several
buildings, electric heaters are used.
Particular problem is the use of the fuel oil, which combustion produces negative environmental
effects. Under certain microclimate conditions, the allowed emission limits are exceeded, which
could lead to a closure of the heat source.
In all of the buildings, radiator-heating systems are designed for temperature regime of 80/60°C and
the outdoor design temperature for the region of Prokuplje is -14.5°C.
Microclimate data
Air temperature
Relative humidity
Daily insolation
Atmospheric pressure
Wind speed
Soil temperature
(°C) (%) (kWh/m2) (kPa) (m/s) (°C)
January 0.3 80.5 1.59 95.5 1.9 -1.6
February 2.0 74.2 2.42 95.3 2.0 0.1
March 6.6 66.0 3.41 95.2 2.5 5.3
April 11.8 64.4 4.13 94.9 2.2 10.8
May 16.9 66.0 5.08 95 2.0 16.7
June 19.9 66.9 5.75 95.1 1.8 20.6
July 22.2 63.1 6.00 95.1 1.9 23.2
August 22.1 62.1 5.42 95.1 1.8 23.3
September 17.5 68.7 3.95 95.3 1.7 18.2
October 12.4 73.3 2.67 95.5 1.8 12.0
November 6.1 78.2 1.62 95.4 1.9 4.8
December 1.7 81.4 1.28 95.5 2.0 -0.5
Year 11.7 70.4 3.62 95.2 2.0 11.1
Table 5 - Microclimate data for the City of Prokuplje6
6 RET Screen International & NASA Software, updated 2014
17
Analysis of heating systems connected to the boiler room in the building of Gymnasium
Several buildings are connected to distributive system of the boiler room located in the building of
Gymnasium. There are three light oil fuel boilers of 3x550kW.
No Institution Heated
area Heating capacity
Calculated consumption
(m2) (kW) (kWh/a)
1 Gymnasium 3,710 779 756,172
2 The gym ‘Sokolski Dom’ 574 145 66,531
3 National Museum Toplice 513 115 92,739
4 Movie Theatre 423 148 44,204
5 Primary school ‘Nikodije Stojanović Tatko’ 1,360 272 264,029
Total 6,580 1,459 1,223,675
Table 6 - Data on buildings connected to the boiler room of Gymnasium
Operations of the boilers are controlled by flow temperature
thermostats installed on the boilers. There are closed
expansion tank with compressor, water circulation pumps,
and collector for distribution of heating energy. Equipment
in the boiler room is outdated, but well preserved and
functional. There is two-pipe radiator heating system with
no thermostatic valves on radiators.
Photo 1 - Building of Gymnasium
Photo 2 - Light fuel oil boilers, 3x550kW Photo 3 - Insulated hot water collector
Photo 4 - Gymnasium underground fuel tank
18
Underground pipeline connects the boiler room in the building of Gymnasium to several other
buildings. First building on the route of underground pipeline is Gym hall ‘Sokolski dom’. It is used
for activities of Gymnasium and sports clubs. There is two-pipe radiator heating system without
thermostatic valves and ventilation system with air heated from the boiler room in the building of
Gymnasium. Ventilation system is used occasionally.
After the building of ‘Sokolski dom’, National Museum Toplice is connected to the pipeline. There
is two-pipe radiator heating system with panel radiators without thermostatic valves on radiators in
the Museum.
Photo 5 - Gym hall ‘Sokolski dom’ Photo 6 - Building of ‘Sokolski dom’
Photo 7 - Building of National Museum Toplice Photo 8 - Panel radiator in the Museum
19
Building of primary school ‘Nikodije Stojanović Tatko’,
also connected to the boiler room in Gymnasium, has
two-pipe radiator heating system without thermostatic
valves. Schoolwork is conducted in two shifts. School
building is modernized by reparation of the facade and
installation of PVC windows, which increased energy
efficiency of the building.
Photo 9 – Primary school ‘Nikodije Stojanović Tatko’
Movie Theatre is located in the building of Gymnasium. There is two-pipe radiator heating system
without thermostatic valves in Movie Theatre.
Photo 11 – Movie Theater and Gymnasium schoolyard view
Photo 10 - Movie Theatre, street view
20
Analysis of heating system in the primary school ‘Ratko Pavlović Ćićko’
Primary school ‘Ratko Pavlović Ćićko’ is heated from the boiler room located within the school
building. There are two wood pellet heated new boilers with power of 2x250kW, produced by
‘Šukom’, Knjaževac.
No Institution Heated
area Heating capacity
Calculated consumption
(m2) (kW) (kWh/a)
1 Primary school ‘Ratko Pavlović Ćićko’ 2,870 502 487,289
Total 2,870 502 487,289
Table 7 - Data on the building of primary school ‘Ratko Pavlović Ćićko’
Until the end of heating season 2016-17, the School was heated by solid fuel. In summer of 2017,
the heating system was modernized. Former boilers were dismantled, and there were installed two
modern biomass (wood pellets) boilers, produced by ‘Šukom’, model Šukoplam PR 250. These
boilers have additional ventilator for airflow through the boiler. There is ongoing installation of rail
transporters for delivery of wood pellets to the boilers. There are also installed new circulation pumps
and new hot water distributors.
Photo 13 – Wood pellet boilers, 2x250kW
Photo 12 - Primary school ‘Ratko Pavlović Ćićko’
21
There is two-pipe radiator heating system without thermostatic valves in the School building.
Schoolwork will continue in two shifts. Operations of the boilers, ventilator, and rail transporter are
automatized in accordance with output water temperature from the boilers.
Analysis of heating systems connected to the boiler room in Kindergarten ‘Biseri’
Kindergartens ‘Biseri’ and ‘Bambi’ are both heated from the boiler room located in the Kindergarten
‘Biseri’. Underground pipeline connects Kindergarten ‘Bambi’ to the boiler room. ,
No Institution Heated
area Heating capacity
Calculated consumption
(m2) (kW) (kWh/a)
1 Kindergarten ‘Biseri’ 458 59 48,460
2 Kindergarten ‘Bambi’ 529 79 64,887
Total 987 138 113,347
Table 8 - Data on the buildings of Kindergartens ‘Biseri’ and ‘Bambi’
There is two-pipe heating system without thermostatic valves in both kindergartens. Recently, there was
implemented energy rehabilitation of Kindergarten ‘Biseri’ by installation of thermal insulation and PVC
windows.
Photo 15 – Radiator without thermostatic valve
Photo 14 - Insulated hot water collector
22
Photo 16 – Kindergarten ‘Biseri’
Light oil fuel heated boiler is produced by ‘Sime’, model 2R 10, with
capacity of 200kW. There are circulation pumps and hot water
collector with damaged insulation. Equipment in the boiler room is
outdated and in a poor condition. There is underground fuel tank in
the yard of Kindergarten ‘Biseri’.
Photo 18 – Boiler in Kindergarten ‘Biseri’
Photo 20 – Damaged insulation of hot water collector
Photo 17 - Kindergarten ‘Bambi’
Photo 19 – Underground fuel oil
tank in the yard of Kindergarten
23
Analysis of heating systems connected to the boiler room in the building of Municipality
Building of the Municipality and Police station are heated from the boiler room located in the building
of the Municipality. Underground pipeline connects the Police station to the boiler room.
No Institution Heated
area Heating capacity
Calculated consumption
(m2) (kW) (kWh/a)
1 Building of the Municipality 2,518 466 313,161
2 Police station 954 143 244,646
Total 3,471 609 557,808
Table 9 - Data on buildings of the Municipality and Police station
There is two-pipe radiator heating system without thermostatic valves on radiators in these two
buildings.
Photo 21- Building of the Municipality
There are two light oil fuel boilers produced by ‘Toplota’, Zagreb, with capacity of 2x290kW. There are circulation pumps and hot water collector without insulation. Equipment in the boiler room is outdated and in a poor condition. There is underground fuel tank in the yard of the Police station. Photo 23 – Fuel oil boilers in municipal boiler room
Photo 22 - Police station
24
Analysis of heating systems connected to the boiler room of Technical school ’15. Maj’
Building of Technical school ’15. Maj’, the School gym, and primary school ‘Milić Rakić Mirko’ are
heated from the boiler room located in the building of the Technical school ’15. Maj’. Underground
pipeline connects these buildings to the boiler room.
No Institution Heated
area Heating capacity
Calculated consumption
(m2) (kW) (kWh/a)
1 Technical school ’15. Maj’ 2,790 446 432,930
2 School gym 780 196 89,932
3 Primary school ‘Milić Rakić Mirko’ 1,524 244 236,850
Total 5,094 886 759,711
Table 10 - Data on the buildings connected to the boiler room in Technical school
In all of above listed buildings, there are two-pipe radiator heating systems. In the School gym and
in primary school ‘Milić Rakić Mirko’, there are no thermostatic valves on radiators, while in Technical
school, thermostatic valves are installed. The building of Technical school was reconstructed and
energy rehabilitated by installation of thermal insulation and PVC windows. Schoolwork in both
schools is conducted in two shifts.
Photo 25 - Underground oil tank
in the yard of the Police station
Photo 24 - Uninsulated hot water collectors in municipal boiler room
25
There are two light oil fuel boilers with capacity of 2x750kW in the boiler room. There are circulation pumps and hot water collector without insulation. There is expansion tank with compressor. Installations in the boiler room are new, dated on recent reconstruction of the School building. Level of automatization of the boilers’ operations is low. Functioning of the boilers is regulated in accordance with temperature of water in the boiler. Underground fuel tank is located in the schoolyard.
Photo 30 - Underground fuel
oil tank in the Schoolyard
Photo 27 - Primary school
‘Milić Rakić Mirko’
Photo 26 - Technical school
’15. maj’ and School gym
Photo 29 - Uninsulated hot water collectors Photo 28 - Fuel oil boilers in Technical school
26
Analysis of heating system in the primary school ‘9. Oktobar’
Primary school ‘9. oktobar’ is heated from the boiler room located within the school building. There
are two oil fuel heated boilers with power of 2x400kW, produced by ‘Kran Inženjering’, Knjaževac.
No Institution Heated
area Heating capacity
Calculated consumption
(m2) (kW) (kWh/a)
1 Primary school ‘9. oktobar’ 2,080 364 353,333
Total 2,080 364 353,333
Table 11 - Data on the building of primary school ‘9. Oktobar’
Premises of primary school ‘9. oktobar’ are located in two buildings. Boiler room is located in main
building, and secondary building is connected to the boiler room by underground pipeline. In both
buildings, there is two-pipe radiator heating system without thermostatic valves on radiators.
Schoolwork is conducted in two shifts.
There are water circulation pumps and thermally insulated hot water collectors. Equipment is outdated, but functional. Underground fuel tank is located in the Schoolyard.
Photo 32 – Secondary building of the School
Photo 33 - Fuel oil boilers in primary school
‘9. oktobar’
Photo 31 - Primary school ‘9. Oktobar’, main building
27
Photo 34 - Hot water collectors in the School ‘9. Oktobar’
Analysis of heating system in Sports hall ‘Dr. Zoran Đinđić’
Sports hall ‘Dr. Zoran Đinđić’ has no heating system. In the building consisting of the sports hall,
utility rooms, and offices, there is two-pipe panel radiator heating system, and heating system of the
sports hall by air conditioning chamber.
No Institution Heated
area Heating capacity
Calculated consumption
(m2) (kW) (kWh/a)
1 Sports hall 2,070 767 325,180
Total 2,070 767 325,180
Table 12 - Data on the Sports hall
Photo 35 - Underground fuel oil tank in the Schoolyard
Photo 37 - Sport court inside the Sports hall
Photo 36 - Sports hall ‘Dr. Zoran Đinđić’
28
Electric boilers are heating 230 m² of business premises in the building, while the sports hall is not
heated. Annual consumption of electricity for heating business premises is 200 kWh/m2, i.e. 46,000
kWh. As temporary solution, there are three LPG (liquefied petroleum gas) boilers with capacity of
2x48kW and 1x36kW, and the system of pipeline, circulation pumps, and collectors. As part of this
temporary solution, there are infrared heaters installed in the Sports hall immediately by the roof
structure. There is underground tank of LPG at fenced location behind the Sports hall.
LPG switch between the tank and equipment in the hall (boilers and infrared heaters) is installed on
the facade of the building. Bulkhead valve of the LPG switch is locked and secured by the Fire
department. This temporary LPG heating system is not operational due to failure in meeting
requirements of fire protection.
Planned solution for the heating of the Sports hall was construction of the boiler room that would be
connected to the Sports hall by underground pipeline. Behind the Sports hall, auxiliary facility of the
boiler room was constructed, but the boiler room has never been constructed.
Photo 38 - LPG boiler Photo 39 - Circulation pumps Photo 40 - Locked LPG switch
Photo 41 - LPG infrared heater Photo 42 - Fenced underground LPG tank
Table 13 - Calculated capacity of future
heating plants
29
Photo 43 – Auxiliary facility of planned boiler room
Overall analysis
Based on the displayed, heating systems differ by fuel type and by the type and number of users.
Heating systems with electric heaters in buildings are not connected to a separate line of electricity.
Due to the complex heating system, it is not possible to collect data of energy consumption;
therefore, energy consumption is calculated according to the following:
yeHDDtt
QH
epi
C
24
H - Estimated consumption (kWh)
QC - Capacity of heating installation (kW)
ti - internal temperature (20°C)
tep - external project temperature (-14.5°C) HDD - Degree days of heating (2,613)
e - correction for the effect of wind and heating switch
y - correction for the effect of daily consumption profile
Photo 44 – Insulated connection
30
Based on these equations, calculated values are shown in the following table:
No Institution
Operation Calculated consumption
Type of time days A Q q
by by
energy from to Institution heat source
h h m2 kW W/m2 kWh/a kWh/a
1 Gymnasium
Light fuel oil
7 20 125 3,710 779 210 756,172
1,223,675
2 Gym hall ‘Sokolski Dom’
12 20 125 574 145 253 66,531
3 National Museum Toplice
10 20 135 513 115 224 92,739
4 Movie Theatre 18 22 125 423 148 350 44,204
5 Primary school ‘Nikodije Stojanović Tatko’
7 20 125 1,360 272 200 264,029
6 Primary school ‘Ratko Pavlović Ćićko’
Pellet 7 20 125 2,839 497 175 482,436 482,436
7 Kindergarten ‘Biseri’ Light fuel
oil
6 17 125 458 59 129 48,460
113,347
8 Kindergarten ‘Bambi’
6 17 125 529 79 149 64,887
9 Building of Municipality Light fuel
oil
7 16 125 2,518 466 185 313,161 557,808
10 Police station 6 22 179 954 143 150 244,646
11 Technical School ’15. maj’
Light fuel oil
7 20 125 2,790 446 160 432,930
759,711 12 School gym 12 20 125 780 196 251 89,932
13 Primary school ‘Milić Rakić Mirko’
7 20 125 1,524 244 160 236,850
13 Primary school ‘9.oktobar’
Light fuel oil
7 20 125 2,080 364 175 353,333 353,333
14 Sports hall Electricity
for offices
14 20 154 2,070 767 371 325,180 325,180
23,122 4,720 204 3,815,490 3,815,490
Table 13 - Overview of data on the analysed facilities and consumption
Facilities of public institutions are very energy-inefficient. This is presented by power density, which
is 204 W/m2. Reasons to that are building structure and purpose of the facilities. Facilities with higher
floor-to-floor heights, such as the Sports hall, Gymnasium and Museum, bear bigger thermal load
(over 210 W/m2). Compact buildings with smaller heights, with glass surfaces, smaller surface of
the façade and good thermal insulation, such as the kindergarten ‘Biseri’ and ‘Bambi’, bear thermal
load of 130 W/m2.
31
Energy costs per a type of fuel are shown in Table 14. Considering that only offices are heated in
the building of Sports hall, this analysis considers their consumption only. It is not considered
presumed consumption in case of heating whole space of the Sports hall.
Current situation Unit Type of fuel
Total Light Fuel oil Pellet Electricity
Energy consumption
Annual (kWh) 3,007,874 482,436 46,000 3,536,310
Unit (kWh/m2) 165 170 200 166
Emission of CO2 (kg) 842,205 0 15,180 857,385
Efficiency of system (%) 90% 90% 99%
Consumption of fuel (t, m3) 291 108
Heated area (m2) 18,213 2,839 230 21,282
Unit fuel price (€/t, €/kWh, €/m3) 1,020 180 0.09
Annual energy cost (€) 296,428 19,492 4,140 320,060
Unit price of energy (€/m2) 16.28 6.87 18.00 15.04
(€/MWh) 98.55 40.40 90.00 90.51
Table 14 - Current situation, energy and fuel consumption, price, CO2 emission
Figure 3 - Energy consumption per fuel types - current situation
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,000
4,000,000
Light Fuel oil Pellet Electricity Total
3,007,874
482,436
46,000
3,536,310
Consumption of energy (kWh)
32
Figure 4 - CO2 emission per fuel types, current situation
Figure 5 - Annual energy costs per fuel types, current situation
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
900,000
Light Fuel oil Pellet Electricity Total
842,205
0 15,180
857,385
Emmision of CO2 (kg)
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
Light Fuel oil Pellet Electricity Total
296,428
19,4924,140
320,060
Annual energy costs (€)
33
Demand for heating energy in any facility is determined by working hours of the tenant of the facility.
Due to the heating during working hours only, the full load hours of 808 kWh/kW is low. If the facilities
would be used longer than during working hours, full load hours would be over 1,618 kWh/kW, which
is extremely high value. Installation of thermal insulation in the buildings would increase energy
efficiency and enable more comfort with same amount of energy consumed.
Figure 6 - Unit price of energy per fuel type, current situation
According to energy efficiency indicators, local heating systems in Prokuplje are very inefficient.
Energy efficiency of local heating systems depends on efficiency of following systems:
- System for production of heating energy- heating energy source
- Pipe systems for distribution of hot water
- Heating systems in the buildings
- Energy efficiency of the buildings
Systems for production of heating energy with boilers that use light fuel oil, or electricity as a fuel,
are energy efficient, but economically unsustainable systems. Almost all of the buildings in
Prokuplje, except for kindergarten ‘Biseri’ and technical school ‘15 Maj’, are not thermally insulated;
there is neither the control of the heating system, nor the control of the air temperature, which makes
all of these buildings and their heating systems inefficient. It is recommended the implementation of
energy efficiency measures aimed to reconstructing thermal insulation of the buildings, which would
certainly result in reduced consumption of heating energy.
Boilers using light fuel oil, are inacceptable in central city area due to environmental pollution and
high CO2 emissions.
Increase of energy, economic, and environmental efficiencies of heating systems in public buildings
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Light Fuel oil Pellet Electricity Averge
16.28
6.87
18.00 15.04
98.55
40.4
90 90.51
Unit price of energy (€/m2), (€/MWh)
(€/m2) (€/MWh)
34
in Prokuplje could be achieved through following activities:
- Installation of central boiler for the city, which will use cheaper fuel with low CO2 emissions
- Establishment of remote district heating system for all city zones
- Connection of larger number of buildings to the remote district heating system aimed to
better utilizing remote heating system used longer.
Using biomass as a fuel instead of fuel oil, coal, gas and electricity, will result in higher economic
efficiency of the system, as well as in decrease of environmental pollution.
35
5. BIOMASS MARKET ANALYSIS
Biomass represents a renewable energy source, which is defined as the organic matter of vegetable
or animal origin (wood, straw, vegetable residues from agricultural production, manure, organic
fraction of communal solid waste). Biomass is used in combustion process and converted in power
plants into the heat, electricity, or both- heat and electricity. Biomass is used for the production of
liquid and gas fuels. Only the biomass of wood origin in the form of wood chips will be considered
as a part of this study.
Biomass is one of the renewable sources of energy and as such is considered as CO2 neutral. Since
biomass combustion emits exact amount of carbon dioxide as the plant binds during the process of
photosynthesis during growth, in that sense coefficient of carbon dioxide emissions of biomass
equals zero. However, this information is valid only when exploitation of biomass is accompanied
by a forestation, otherwise CO2 emissions should be taken into account.
Wood chips are intended as the biomass for combustion in heating plants. The quality of wood chips
is defined by the standard for solid fuel SRPS EN ISO 17225-1:2015, and SRPS EN ISO 17225-
4:2015 determines the fuel quality classes and specifications of graded wood chips. The following
table shows the requirements defined by the standards in Serbia:
Table 15 - Requirements for wood chips according to SRPS EN ISO 17225-4:2015
M10 M15 W20 W25 W30 W35 W40
Moisture content %
M<10 10<M≤15 15<M≤20 20<M≤25 25<M≤30 30<M≤35 35<M≤40
Table 16 - Classification of wood chips based on the moisture content according to SRPS EN ISO 17225-4
Moisture (%)
8 < % < 18 18 < % < 25 25 < % < 35 35 < % < 45
Bulk density (bulk-kg/m3)
225< BD200 <250 250< BD250 <280 280< BD250 <320 320< BD300 <380
Table 17 - Classification of bulk density of wood chips according to SRPS EN ISO 17225-4:2015
Wood chips
Standard SRPS EN ISO 17225-1:2015
SRPS EN ISO 17225-4:2015
Particles size
Amax = 6 cm2
L = 10 cm (max 10% - 35cm)
Moisture content W10 – W60
suitable: 40% max
Bulk density < 350 kg/m3
Calorific value 2.80-3.40 kWh/kg
36
Dimensions (mm)
The fracture >60% by weight
Fine fracture Rough fracture Maximum particle length
P16 3.15 ≤ P ≤ 16 mm < 3.15 mm, < 15% <6%, > 31.5 mm < 45 mm
P31 3.15 ≤ P ≤ 31.5 mm < 3.15 mm, < 10% <6%, > 45 mm < 150mm
P45 3.15 ≤ P ≤ 45 mm < 3.15 mm, < 10% <10%, > 63 mm < 200mm
Moisture (%)
M10 ≤ 10%
Dried M15 ≤ 15% M20 ≤ 20% M25 ≤ 25%
Suitable for storage M30 ≤ 30%
M35 ≤ 35% Limited for storage
M40 ≤ 40%
M50 ≤ 50% Unsuitable for storage M55 ≤ 55%
M60 ≤ 60% Wet
Ash content (%)
A 0.5 ≤ 0.5%
A 0.7 ≤ 0.7%
A 1.0 ≤ 1.0%
A 1.5 ≤ 1.5%
A 2.0 ≤ 2.0%
A 3.0 ≤ 3.0%
Table 18 - Requirements for wood chips according to SRPS EN ISO 17225-4:2015
Total forest area in the municipality of Prokuplje is about 29,529 ha. The forest area covers 39% of
the territory of the city; the degree of utilization of resources is around the national average. State
owned forests represent 62%, and privately owned forests are 38% of total forest area of Prokuplje.
Forest enterprise ‘Kuršumlija’, Kuršumlija, manages following forest administration offices:
Kuršumlija, Prokuplje, Blace, with total forest area of 62,189 ha.
Forest enterprise Forest area
Total wood volume
Annual growth
Annual return
Kuršumlija ha m3 m3/ha m3
Kuršumlija 33,795 6,202,228 4.8 90,130
Prokuplje 20,409 3,811,438 5.7 49,402
Blace 7,985 1,888,400 6.4 29,317
Total 62,189 11,902,066 16.9 168,849
Table 19 - Data on forests provided by SE ‘Srbijašume’, FE ‘Kuršumlija’7
7 http://www.srbijasume.rs/kursumlija.html
37
8 9
Calculation of the potential of forest waste in the municipality of Prokuplje is based on the study
‘Potentials and Possibilities of Commercial Use of Wood Biomass for Energy Production and
Economic Development of the Municipalities Nova Varoš, Priboj and Prijepolje’. This Study was
carried out as the analysis of the availability of wood waste from the sawmill industry and forestry in
the municipalities of Nova Varoš, Priboj and Prijepolje. The results showed that following amounts
are available to meet energy needs:
8 ‘Potentials and Possibilities of Commercial Use of Wood Biomass for Energy Production and Economic Development of the Municipalities Nova Varoš, Priboj and Prijepolje’, 2009, author: Branko Glavonjić, PhD 9 ibid
Figure 8 - Share of forest’s area in the total area of the Serbian municipalities
Figure 7 – State and private forestsper Municipalities and Districts
38
Nova Varoš Priboj Prijepolje Total
Forest (ha) 22,400 30,400 44,000 96,800
Wood waste volume (m3)
Chips from forestry 3,100 4,300 5,400 12,800
Wood industry 9,364 1,194 11,739 22,297
Total 12,464 5,494 17,139 35,097
Wood waste mass (t)
Chips from forestry 1,813.5 2,515.5 3,159.0 7,488
Wood industry 5,477.9 1,137.2 6,867.3 13,482
Total 7,291 3,653 10,026 20,970
Annually available energy value (MWh/a)
Chips from forestry 4,003.2 5,532.2 6,950.0 16,485
Wood industry 15,901.6 3,308.2 19,932.6 39,142
Total 19,905 8,840 26,883 55,628
Table 20 - The energy potential of green chips from forestry, with wood waste from sawmill industry, in the municipalities of Nova Varos, Priboj and Prijepolje10
Calculated energy value of forest waste, without the waste of the sawmill industry of SE ‘Srbijašume'
and FE ‘Kuršumlija’ is shown in the table below:
Territory
Forest area
Volume of wood waste
Mass of wood waste
Annually available energy
ha m3 t MWh/a
Prijepolje, Priboj, Nova Varoš 96,800 35,097 20,970 55,628
Forest farm ‘Kuršumlija’ 62,189 22,548 13,472 35,738
Table 21 - The energy potential of biomass from FE ‘Kuršumlija’11
Biomass of wood origin in the form of pellets available on the market is not suitable for analysis due
to the high purchase price. Some of the benefits of wood chips compared to wood pellets are lower
prices and lower level of wood processing. Domestic market transactions are performed on a small
scale between manufacturers and wholesalers, where price reaches 180 €/t of wood pellets.
Depending on the time of purchase, end customers pay between 200 and 220 €/t. The advantage
of pellets is higher bulk density, which means lower transportation costs and smaller storage for the
same amount of fuel in terms of energy produced. Due to lower processing level, wood chips has
lower price, but higher moisture content, which affects its energy value, bulk density, and price.
Wood chips Moisture Energy value Bulk density Cost
(%) (kWh/m3) (bulk-kg/m3) (€/t)
30-40 940-1,200 300-350 45-60
Table 22 - Characteristics of wood chips depending on the percentage of moisture
10 ‘Potentials and Possibilities of Commercial Use of Wood Biomass for Energy Production and Economic Development of the Municipalities Nova Varoš, Priboj and Prijepolje’, 2009, author: Branko Glavonjić, PhD 11 Own calculation
39
6. TECHNICAL DESIGN CONCEPT
6.1 TECHNICAL SOLUTIONS AND SIZING THE BOILER
Aimed to decreasing fuel costs for heating public buildings in the Prokuplje municipality, it is
designed the concept of the construction of central boiler room with biomass- wood chips heated
boiler, remote district heating pipe system, and substations. Comparative analysis of annual fuel
costs in existing systems, and in case of using wood chips is shown in Table 24. The analysis does
not consider area of sports hall within the building of Sports hall ‘Dr. Zoran Đinđić’. In calculations
of total heating energy produced by future biomass heating system, the heating of this whole
building is included, which provides actual parameters of comparative analysis. Following Table
shows variation of energy value and unit price of energy, depending on percentage of moisture. Due
to large contact surface, wood chips easily exchanges moisture with environment, which affects its
energy value and unit price of energy.
Moisture
Caloric value
Unit price
(%) (kWh/t) (€/t) (€/kWh)
Biomass, wood chips
30 3,400 53
0.016
40 2,800 0.019
Table 23 - Unit price of wood chips depending on the percentage of moisture
Unit Fuel type
Biomass Light fuel oil Pellet Electricity Total
Energy consumption (kWh) 3,007,874 482,436 46,000 3,536,310 3,815,490
Emission of CO2 (kg) 842,205 0 15,180 857,385 0
Efficiency of system (%) 90% 90% 99% 0 83%
Increase for heating up the system
(%) 0% 0% 0% 5%
Consumption of fuel (t), (m3) 291 108 0 1,578
Heated area (m2) 18,213 2,839 230 21,282 21,282
Unit fuel price (€/t), (€/kWh),
(€/m3) 1,020 180 0.09 53
Annual energy cost (€) 296,428 19,492 4,140 320,060 83,631
Unit price of energy (€/m2) 16.28 6.87 18.00 15.04 3.93
Unit price of energy (€/MWh) 98.55 40.40 90.00 90.51 21.92
Table 24 - Comparative analysis of the costs of currently used fuels in Prokuplje and costs of biomass
Based on collected data, calculated annual fuel costs in buildings used by public institutions in
Prokuplje are estimated to be around 320,000 €. If the analysed facilities used biomass-wood chips
for heating, annual fuel costs would come to amount of approximate 85,000 €. The use of biomass
for the heating of analysed facilities can reduce annual fuel costs by the amount of 220,000-
250,000 €.
40
Figure 9 - Annual energy costs per fuel types - comparison with biomass
Figure 10 - Unit price of energy per fuel type - comparison with biomass
The program of switching existing fuels with biomass in buildings used by public institutions of
Prokuplje requires a complex analysis in order to select the best technical and economic solutions.
Facilities of public institutions are dispersed all around the town, so replacement of individual boilers
requires the construction of two new central biomass boiler rooms with pipe system for district
heating.
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
Light Fuel oil Pellet Electricity Total
296,428
19,4924,140
320,060
65,933
10,575 1,008
83,636
Annual energy cost (€)
Existing fuel (€) Biomass, ships (€)
0.00
20.00
40.00
60.00
80.00
100.00
Light Fuel oil Pellet Electricity Biomass
16.286.87
18.00
3.93
98.55
40.4
90.00
21.92
Unit price of energy (€/m2), (€/MWh)
(€/m2) (€/MWh)
41
Heating plant marked ‘A’ would be connected to public buildings in immediate city core. Heating
plant marked ‘B’ would be connected to the buildings of primary school ‘9. oktobar’, and Sports hall
‘Dr. Zoran Đinđić’, which are distant from the future heating plant ‘A’ app. 1 km. If these building
would be connected to the heating plant ‘A’, route of the pipeline would run through hardly
approachable streets on very unevened terrain. Furthermore, there are no other public buildings-
bigger consumers of heat energy on that route. In respect to these facts, connection of primary
school ‘9. oktobar’ and Sports hall ‘Dr. Zoran Đinđić’ to the heating plant ‘A’ would result in delay of
delivery of heating energy compared to consumers in the city centre, and in lower quality of the
system. Considering aforementioned, there will be constructed heating plant ‘B’ to satisfy
consumption of primary school ‘9. oktobar’ and Sports hall ‘Dr. Zoran Đinđić’.
Local boiler rooms Heating
area capacity
m2 kW
BOILER ROOM – HETAING PLANT - SYSTEM ‘A’
Gymnasium 6,580 1,459
Primary school ‘Ratko Pavlović Ćićko’ 2,839 497
Kindergarten ‘Biseri’ 987 138
Building of the Municipality 3,471 609
Technical School ’15. maj’ 5,094 886
TOTAL ‘A’ 18,972 3,589
BOILER ROOM – HETAING PLANT - SYSTEM ‘B’
Primary school ‘9. oktobar’ 2,080 364
Sports hall 2,070 767
TOTAL ‘B’ 4,150 1,131
Table 25 - Overview of the areas and capacity of central biomass heating systems ‘A’ and ‘B’
For each system (‘A’ and ‘B’) will be Construction district heating network which should enable the
connection of the considered public facilities, with the possibility of connecting others buildings in
the future. This district heating system represents an investment in infrastructure.
The required installed capacity of the boiler and level of efficiency of the heating system is calculated
using the formula:
C
B
QB (kW) Installed boiler capacity
QC (kW) Net consume (capacity)
η System efficiency
η = ηB · ηC
ηB Boiler efficiency
ηC Efficiency of district heating system
τ Simultaneity factor
42
The calculated heat demand would be covered by installing heating plant of nominal heat output
presented in the next table:
Table 26 - Calculated capacity of future heating plant
Figure 11 - Diagram of the annual distribution of the heat capacity of the heating plants
The number of hours of boiler operations can be determined using Sochinsky formula:
max
1
0
0
0
11 QQ
m
b
max
min0
Q
Q
maxQ
Qmm
Q - heating capacity at the time,
- time,
minQ - minimum heating capacity of boiler
maxQ - maximum heating capacity of boiler
mQ - required capacity
0
1000
2000
3000
4000
5000
0 500 1000 1500 2000 2500 3000 3500
kW
Working hours
Heating Capacity (kW) - Heat Load Curve
System "A" System "B"
System Capacity
Qc ηB ηC Τ
Calculate QB
Sizing of the boiler
(kW) (kW) (kW)
‘A’ 3,589 0.9 0.92 0.9 3,901 4,500
‘B’ 1,131 0.9 0.92 0.9 1,229 1,500
43
During winter, every heating system is a subject to great fluctuations that depend on the weather
and user’s habits. The maximum output power is utilized very shortly during periods of very cold
weather. Regularly, the boiler is operating for long intervals of time at low load. Therefore, it is
important for the boiler to be operated efficiently during off-peak periods. This can be achieved in
one of the following ways:
1. The biomass boiler can provide the maximum capacity, while a buffer (a hot water tank) covers
short-term load fluctuations and ensures that the boiler can be operated efficiently during off-peak
periods.
2. Combination of more biomass boilers. More boilers increase the reliability of supply and ensure
that the heating operates efficiently, even in off-peak periods.
Optimal model for biomass plant ‘A’ would be the solution with two wood chips heated boilers,
2,500kW + 2,000kW, and hot water tanks with 45m3 volume . One boiler would be used at higher
outside temperatures. In this way, the system would be efficient even in lower operating modes. For
biomass plant ‘B’, optimal model would be the solution with one wood chip heated boiler, 1500kW
and hot water tank with 15m3 volume. Existing boilers in aforementioned facilities would serve as a
backup solution.
Comparison of biomass and existing fuels is based on the full load hours of 808 kWh/kW. This
consumption value implies that the heating systems are in a maintenance mode after working hours
and in schools during winter holidays. According to this data, it is necessary to produce yearly
consumption of 3,815 MWh. The unit production cost of the heating energy, according to the solution
with wood chips as a fuel, is about 21.92 €/MWh. Current unit cost for buildings described in this
study, with existing heating systems, is up to 90.51 €/MWh.
44
6.2 HEATING PLANT, LOCATION AND FACILITIES
6.2.1 HEATING PLANT ‘А’
The plot intended for the construction of a new power plant is located on a part of cadastral plot
2308/1 CM Prokuplje with surface of 4,200m2. This location is on the site of the former landfill, on
the left bank of the Toplica River.
Figure 12 - Situation plan of heating plant ‘A’
Photo 45 - Location of the heating plant ‘A’
45
The heat source consists of two boilers capacity 2,000kW and 2,500kW, for combustion of biomass
with total nominal thermal capacity of 4,000 kW. In the plant with two boilers, stable operations are
ensured with low outdoor temperatures, as well as with higher outdoor temperatures. In cases of
higher outdoor temperatures, one boiler can provide sufficient heating, without the risk of cooling
entire system. The regime of the boiler temperature is 100/70°C. Maximum operating pressure is
6 bars. The minimum temperature return to boiler is 60°C. It is planned to install a buffer tank with
volume of 45 m3 in order to optimize the operation of the heat source. Circulator pumps are located
between the boiler and buffer tank, as well as three-way mixing valve in order to provide protection
for the cold parts of boilers.
For the purposes of technical calculation, the documentation was used made by ‘Topling-heating
Beograd’, including additional mechanisms for feeding fuel, extracting exhaust gases and ash. For
the purposes of circulation in the distribution system, circulation pump with inconstant flow and
pressure sensors are planned.
Construction of following facilities is envisaged at the site of future heating plant ‘A’:
Building A:
- Space to install biomass boilers with area of 250 m2 is needed for installation of following
boilers:
a) one boiler with capacity of 2,000 kW. Space necessary for operations of such boiler has
following dimensions: width x length x height = 6.8 x 9.2 x 5.8m
b) one boiler with capacity of 2,500kW. Space necessary for operations of such boiler has
following dimensions: width x length x height = 8.0 x 10.2 x 6.3m
The rest of a space is manipulative space for access to maintaining and safe passage.
- Space to install daily tank of woodchips with surface of 250 m2 and capacity of 100 m3,
i.e. 30 t, and space for daily fuel storage sufficient for 4 days of operations.
- The area of processing equipment (buffers, pumps, collectors) of 130 m2
- Office space of 50 m²
Building B:
- Wood chips storage for whole heating season and for both heating plants (‘A’+’B’), with
area of 2,640 m2 and minimum useful height of 7 m. Capacity of this storage is 5,270 m3 or
1,580 t of wood chips, which is sufficient for the needs of both heating plants to provide
energy for the heating of all public buildings.
Total area of buildings of the heating plant ‘A’ is 3,320 m2 (250+250+130+50+2,640 m2) and the
degree of availability of cadastral parcel is 80%.
46
6.2.2 HEATING PLANT ‘B’
The plot intended for the construction of a new power plant ‘B’ is located on a part of cadastral plot
1704/1 CM Prokuplje with surface of 1,500m2. The location is behind primary school ‘9. oktobar’ and
Sports hall ‘Dr. Zoran Đinđić’.
Figure 13 - Situation plan of heating plant ‘B’
The heat source consists of one boiler capacity 1,500kW, for combustion of biomass, and hot water
buffer tank with volume of 15 m3 in order to optimize the operation of the heat source. In the plant
with boiler and hot water buffer tank, stable operations are ensured with low outdoor temperatures,
as well as with higher outdoor temperatures. In cases of higher outdoor temperatures, one boiler
can provide sufficient heating, without the risk of cooling entire system. The regime of the boiler
temperature is 100/70°C. Maximum operating pressure is 6 bars. The minimum temperature return
to boiler is 60°C. Circulator pumps are located between the boiler and buffer tank, as well as three-
way mixing valve in order to provide protection for the cold parts of boilers.
For the purposes of technical calculation, the documentation was used made by ‘Topling-heating
Beograd’, including additional mechanisms for feeding fuel, extracting exhaust gases and ash. For
the purposes of circulation in the distribution system, circulation pump with inconstant flow and
pressure sensors is planned.
Construction of following facilities is envisaged at the site of future heating plant ‘B’:
47
Building A:
- Space to install biomass boilers with area of 150 m2 is needed for installation of a boiler
with capacity of 1,500 kW. Space necessary for operations of such boiler has following
dimensions: width x length x height = 6.8 x 9.2 x 5.8m
The rest of a space is manipulative space for access to maintaining and safe passage.
- Space to install daily tank of wood chips with area of 55 m2 and capacity of 22 m3 or 6.5 t
that is sufficient for 4 days of operations
- The area of processing equipment (buffers, pumps, collectors) with area of 50 m2
- Office space of 50 m²
Building B:
- Wood chips storage with area of 100 m2 and minimum useful height of 7 m. Capacity of
this storage is 190 m3 or 55 t of wood chips, which is average 4 weeks consumption in the
coldest period of a year. This storage would be supplied by wood chips from central storage
located in the complex of heating plant ‘A’
Total area of buildings of heating plant ‘B’ is 405 m2 (150+55+50+50+100 m2) and the degree of
availability of cadastral parcel is 27%.
48
6.3 CONCEPT OF DISTRICT HEATING NETWORK
6.3.1 CONCEPT OF DISTRICT HEATING NETWORK
Heating network is designed to connect aforementioned public buildings. The pipe network consists
of pre-insulated steel pipes that are installed directly in the prepared soil. Distribution network will
contain chambers with bulkhead valves.
Photo 46 - Pre-insulated pipes for the district heating network12
The quality of the pipes corresponds to 1.0254 i.e. P235
TR1 according to EN10217 T1 (or St.37.0 of the technical
requirements and delivery conditions according to
DIN1626). The operating temperatures at the threshold of
the heat source are:
- The flow temperature is 100℃,
- The return temperature is 70℃
The difference in altitude between the highest point of the
town (on the outskirts) and the lowest point is less than
30 m, so the lowest required operating pressure in the
pipeline is 6 bar.
Route of the pipeline runs through main streets, or through land plots owned by the City or by other
state body/ company. An example is cadastral plot No 5686, owned by Public Water Management
Company ‘Srbijavode’, necessary for connection of Technical school ’15. maj’ to the heating
network.
Before designing the heating network, it is necessary preparation of a document at the municipal
level, which will define the Prokuplje construction strategy and direction of the future development
of the city centre.
Concept plan of the heating network is preliminary, and designed for the planning of the budget
expenditures.
12 Source: Website of the company Konvar d.o.o., Belgrade
49
6.3.2 SCHEME OF DISTRICT HEATING NETWORK
Based on the position of public institution buildings, as well as on the position of the main town
streets, residential buildings and individual houses, heating network plan would be as follows:
Figure 14 - Disposition of drawings of the heating network per numbers
50
Figure 15 - Drawing No 1 of the heating network
51
Figure 16 - Drawing No 2 of the heating network
52
Figure 17 - Drawing No 3 of the heating network
53
Figure 18 - Drawing No 4 of the heating network
54
Figure 19 - Drawing No 5 of the heating network
55
Figure 20 - Drawing No 6 of the heating network
56
Figure 21 - Drawing No 7 of the heating network
57
Figure 22 - Drawing No 8 of the heating network
58
Dimensions of heating pipes for the network calculated with the planned reserve for future additions to the network:
Within the analysis, heating network is divided by the routes and transparent points, as shown on the drawings:
Type Route Distance Capacity of Unit price of network
of from to heat substations Dimension Total
route (m) (kW)
main A B 90 2200 DN150 310 27,900
main B C 95 2700 DN200 465 44,175
main C D 285 2900 DN200 465 132,525
main E E1 350 900 DN100 220 77,000
main F F1 100 500 DN80 175 17,500
main G G1 100 1000 DN125 265 26,500
connection A1 100 700 DN100 220 22,000
connection A2 160 1500 DN125 265 42,400
connection B1 110 500 DN80 175 19,250
connection C1 60 200 DN50 130 7,800
connection E1 10 900 DN100 220 2,200
connection F1 10 500 DN80 175 1,750
connection G1 10 1000 DN125 265 2,650
TOTAL 1,480 423,650
Table 27 - Sizing the pipe network by routes
According to the prices of units needed to construct a network of pre-insulated pipes, the costs of
the construction of heating network are estimated to 424,000 €. The additional costs of the
construction of the chamber with necessary fittings and installation of the fittings increase estimation
for 10%, leading to total costs of the heating network of 470,000 €.
Q - The amount of heat transported by the pipeline
w - Velocity of flow of the working fluid
ρ - Density of the working fluid
cp - Specific heat capacity
Δθ - Temperature difference
p
incw
QD
4
59
Calculation of operating point of the network pump is shown in the following Tables:
Table 28 - Calculation of operation point of network pump, heating plant ‘A’
Table 29 - Calculation of operation point of network pump, heating plant ‘B’
The operating point of the network pump (or a pair of network pumps, depending on the solution
adopted in the preliminary design) is as follows:
Heating plant ‘A’ Heating plant ‘B’
Flow l/h 95,000 50,000
Pressure drop kPa 87 55
Table 30 - Working points of circulation pumps for heating plant ‘A’ and ‘B’
The operating point is selected on a basis of the pressure drop in the hydraulically least favorable
heating substation.
Aimed to saving electricity for pumping the working fluid, it is necessary to incorporate the engine
frequency controls in order to optimize the operation of network pumps and synchronize it with the
actual required thermal energy to be delivered to the consumer.
Flow Lenght Speed
from to diemeter wall unit total friction local TOTAL
kW l/h m mm mm m/s Pa/m kPa kPa kPa
D C 2.900 85.508 90 219,1 5,9 0,704 22,08 1,987 3,603 5,590
C B 2.700 79.611 120 219,1 5,9 0,656 19,20 2,3 1,5 3,761
B A 2.380 70.175 150 168,3 4,5 0,979 58,36 8,8 3,2 12,001
A A2 1.500 44.228 190 139,7 4,0 0,902 63,05 12,0 2,8 14,741
MAX: 85.508 SUM: 36,1
10% 8.551 Security increase: 25% 9,0
Total for calculate: 94.059 heat excanger: 30
Adopted va lue: 95.000 (l/h) reserve: 10
Total for calculate: 85,1
Adopted for ca lc. (kPa): 87
Route Dimension of pipe Pressure dropCapacity
60
6.3.3 CONCEPT OF HEATING SUBSTATIONS District heating transfer stations provide the link between district heating suppliers and the customers’ systems. They incorporate the necessary equipment to tailor the supplied heat to the needs of the user. Indirect connections (in which district heating and in-house systems are hydraulically isolated) incorporate components to separate the systems (heat exchanger), to limit the flow volume, regulate the secondary supply temperature and measure the energy consumption. Substations are designed for installation in already existing boiler rooms. The existing boilers will be reviewed in terms of functionality. Those that do not meet the minimum requirements for safe operations will be removed from the substations (i.e. from the existing boiler rooms). Those that meet the minimum technical requirements will remain as a backup heat source in case when, for any reason, the heating system goes into breakdown of operational mode; or to serve as back up heating source if there is an increase of heat consumption that cannot be foreseen at this moment. The operating pressure in the primary part of the substation will be up to 6 bars max., and will correspond to the parameters of the heating network, while the temperature range will be 100/70℃ in the primary part and 80/60℃ in the secondary part. The further development of the heating system, with a focus on the connection of residential buildings, would involve the installation of heating substations of the packet type in each building, with identical operating parameters as for heating substations in public institutions or business facilities.
1- External sensor 2- Thermometer 3- Manometer 4- Sensor 5- Air vent 6- Drainage 7- Prim. Connection DHW 8- Safety thermostat 9- Connection to expansion 10- Controller 11- Strainer 12- Heat meter 13- Ball valve 14- Safety valve 15- Heat exchanger
Figure 23 - Scheme of compact substation DSA 1 Mini Danfoss13
13 www.danfoss.com
61
14 15
Substations models DSP-MAXI are designed for power stronger than 100 kW. Substations DSA1-Mini are designed to power up to 100 kW and can be mounted on the wall. Heat substation should be dimensioned according to the size of the heat loss of the building. The reconstruction of the existing boiler rooms should be executed in a way that does not change the working fluid distribution system and the heating substation is connected to the existing supply and return collectors. The existing circulation pumps should be replaced by more energy-efficient units with motors of variable frequency, in order to achieve savings in power consumption and reduce heat dissipation in the buildings.
No Institution Position on the
drawing
Type of No of subst. Power Price
substation
(kW) (€)
1 Gymnasium A-2 DSP-MAXI-32 3 500 18,000
2 Primary school ‘Ratko Pavlović Ćićko’
B-1 DSP-MAXI-22 2 250 11,000
3 Kindergarten ‘Biseri’ C-1 DSP-MAXI-22 1 200 5,400
4 Building of the Municipality A-1 DSP-MAXI-31 2 350 11,800
5 Technical School ’15. maj’ E-1 DSP-MAXI-32 2 450 12,000
6 Primary school ‘9. oktobar’ P-1 DSP-MAXI-32 1 500 6,000
7 Sports hall ‘Dr. Zoran Đinđić’ R-1 DSP-MAXI-32 2 500 12,000
TOTAL: 76,200
Table 31 - Selection of substations in the facilities
14 www.danfoss.com 15 Ibid
Figure 25 - Substation DSP – MAXI Danfoss Figure 24 - Substation DSA - Mini Danfoss
62
7. PRELIMINARY COST ESTIMATES
The task of this study has a number of levels:
‒ Fuel switch to biomass of existing heating systems in public buildings in Prokuplje, by
construction of the central biomass heating plant
‒ Construction of district heating distribution system to connect the public buildings
Fuel switch to biomass of heating systems in public buildings in Prokuplje should provide lower costs
of heating energy, reduce CO2 emissions, contribute to environmental protection, and enhance local
economic development in terms of growing and processing biomass. Implementation of the project
should provide savings in the Prokuplje municipal budget, and thus a quick return of the investment.
The preliminary cost estimates includes annual investment and operating costs. Investment would
include the purchase of equipment and boilers, necessary construction works, mechanical works,
and electrical works on the construction and installation of a new boiler, the heating network, heating
substations; and connecting the buildings to the new distribution system.
Position Investment costs – Description (€)
1. Access road and landscaping plots for the new building and for the route of new pipeline.
60,000
2. Construction of the heating plants (‘A’+’B’) buildings with boiler room, equipment space and office, the total area 985m2
250,000
3. Construction of the fuel storage facility area 100+2640m2 55,000
4. Energy plant, mechanical and electrical equipment works (except boilers) 140,000
5. Biomass boilers and associated equipment 1500+2000+2500 kW 750,000
6. Chimneys 180,000
7. Construction of heating grid - distribution network 470,000
8. Heating substations for public administration buildings 76,200
9. Adaptation of spaces for heating substations in public buildings 35,000
10. Drum wood chipper 15,000
11. Documentation, construction management, commissioning of the plant and heating grid
80,000
12. Unforeseen costs 40,000
CAPEX (Capital Expenditure) 2,151,200
Table 32 - Investment costs16
The composition of operational costs (OPEX) is diverse and affected by many factors. In order to
calculate operational costs, there will be reviewed analysis of all annual expenses.
After reconstruction, energy rehabilitation and modernization of the buildings, it is expected
reduction of annual energy consumption for 0.1%.
16 Own calculations
63
Based on the forecast of the World Bank17, expected variations of fuel prices in a period of 10 years
are following:
- Liquid fuels: 57% - Wood chips 23%
Description Unit 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Heat energy consumption
(MWh/a) 3,815 3,812 3,808 3,804 3,800 3,796 3,793 3,789 3,785 3,781
Wood chips consumption
(t) 1,578 1,576 1,575 1,573 1,572 1,570 1,569 1,567 1,565 1.564
Price of wood chips (€/t) 53 54 55 57 58 59 61 62 63 65
Unit price of energy from wood chips
(€/MWh) 21.92 22.41 22.92 23.44 23.97 24.51 25.06 25.63 26.21 26.80
Light fuel oil price (€/t) 1,020 1,078 1,140 1,205 1,273 1,346 1,422 1,504 1,589 1,680
Pellet (€/t) 180 184 188 192 197 201 206 210 215 220
Electricity price (€/MWh) 0.09 0.09 0.09 0.10 0.10 0.10 0.10 0.11 0.11 0.11
Unit price of energy from existing fuels
(€/MWh) 90.51 95.44 100.65 106.14 111.95 118.08 124.56 131.40 138.62 146.25
Maintenance of equipment and installation
% CAPEX / a 0.50 0.50 0.50 0.50 0.50 1.00 1.00 1.00 1.00 1.00
Cost (€/a) 7,181 7,181 7,181 7,181 7,181 14,362 14,362 14,362 14,362 14,362
Insurance % CAPEX / a 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
Cost (€/a) 9,841 9,608 9,381 9,162 8,948 8,742 8,542 8,349 8,163 7,984
Electricity - costs of the plant
kWhel / MWhth
2 2 2 2 2 2 2 2 2 2
Cost (€/a) 687 703 720 737 755 773 792 811 830 850
Labour costs (€/a) 20,000 20,300 20,605 20,914 21,227 21,546 21,869 22,197 22,530 22,868
Removal and disposal of ash
(t/a) 31.6 31.5 31.5 31.5 31.4 31.4 31.4 31.3 31.3 31.3
Cost of removal and disposal of ash
(€/a) 947 960 973 987 1,001 1,015 1,029 1,043 1,058 1,073
Chemical treatment of circulating water
Volume (m3) 180 180 180 180 180 180 180 180 180 180
Losses (m3 / a) 5 5 5 5 10 10 10 10 10 15
Unit price (€/m3) 3.00 3.03 3.06 3.09 3.12 3.15 3.18 3.22 3.25 3.28
Cost (€/a) 27 27 28 28 56 57 57 58 58 89
Depreciation of equipment and installations
% / a 3 3 3 3 3 3 3 3 3 3
Cost (€/a) 43,086 41,793 40,501 39,208 37,916 36,623 35,331 34,038 32,745 31,453
Depreciation of buildings
% / a 1 1 1 1 1 1 1 1 1 1
Cost (€/a) 4,900 4,851 4,802 4,753 4,704 4,655 4,606 4,557 4,508 4,459
17 World Bank Commodity Forecast Price Data, July 2015
64
Description Unit 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
Heat energy consumption
(MWh/a) 3,778 3,774 3,770 3,766 3,762 3,759 3,755 3,751 3,747 3,744
Wood chips consumption
(t) 1,562 1,561 1,559 1,558 1,556 1,554 1,553 1,551 1,550 1,548
Price of wood chips (€/t) 65 66 67 67 68 69 69 70 71 72
Unit price of energy from wood chips
(€/MWh) 27.07 27.34 27.61 27.89 28.17 28.45 28.74 29.02 29.31 29.61
Light fuel oil price (€/t) 1,697 1,714 1,731 1,748 1,766 1,783 1,801 1,819 1,837 1,856
Pellet (€/t) 222 225 227 229 231 234 236 238 241 243
Electricity price (€/MWh) 0.12 0.12 0.12 0.12 0.13 0.13 0.13 0.14 0.14 0.14
Unit price of energy from existing fuels
(€/MWh) 147.74 149.24 150.75 152.28 153.83 155.39 156.97 158.57 160.18 161.81
Maintenance of equipment and installation
% CAPEX / a 1.50 1.50 1.50 1.50 1.50 2.00 2.00 2.00 2.00 2.00
Cost (€/a) 21,543 21,543 21,543 21,543 21,543 28,724 28,724 28,724 28,724 28,724
Insurance % CAPEX / a 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
Cost (€/a) 7,811 7,645 7,485 7,332 7,186 7,047 6,914 6,789 6,669 6,557
Electricity - costs of the plant
kWhel / MWhth
2 2 2 2 2 2 2 2 2 2
Cost (€/a) 870 891 913 935 957 980 1,003 1,027 1,052 1,077
Labor costs (€/a) 23,211 23,559 23,912 24,271 24,635 25,005 25,380 25,760 26,147 26,539
Removal and disposal of ash
(t/a) 31.2 31.2 31.2 31.2 31.1 31.1 31.1 31.0 31.0 31.0
Cost of removal and disposal of ash
(€/a) 1,088 1,103 1,118 1,134 1,150 1,166 1,182 1,199 1,216 1,233
Chemical treatment of circulating water
Volume (m3) 180 180 180 180 180 180 180 180 180 180
Losses (m3 / a) 15 15 15 15 20 20 20 20 20 20
Unit price (€/m3) 3.31 3.35 3.38 3.41 3.45 3.48 3.52 3.55 3.59 3.62
Cost (€/a) 89 90 91 92 124 125 127 128 129 130
Depreciation of equipment and installations
% / a 3 3 3 3 3 3 3 3 3 3
Cost (€/a) 30,160 28,868 27,575 26,282 24,990 23,697 22,405 21,112 19,820 18,527
Depreciation of buildings
% / a 1 1 1 1 1 1 1 1 1 1
Cost (€/a) 4,410 4,361 4,312 4,263 4,214 4,165 4,116 4,067 4,018 3,969
Table 33 - Operational costs18
Estimation of operational costs (OPEX) predicts that after first 10 years, prices will stabilize and achieve small growth of 1% annually. In following 10 years, it is expected wood chips price increase up to 65€/t, and pellet price increase up to 220€/t. After this period, the price would continue growing per 1% annually. For the price of electricity, it is foreseen annual growth at a rate of 2.5%. Insurance costs are estimated for all of facilities, equipment, and installations built by the investment. Considering workforce, it is planned engagement of two highly technically educated employees and
one manager. Workers with lower qualifications would be replaced from existing assignments in the
facilities that are the subject of this study. Salaries costs would increase per annual rate of 1.5%.
Costs of cleaning exhaust systems and ash disposal are proportional to quantity of ash (2%) in
burned wood chips. Unit price of these costs would increase per annual rate of 1.5%.
18 Own calculations
65
8. PRELIMINARY FINANCIAL ANALYSIS
Sustainability of the plant will be analysed for a period of 20 years. Variations of operational costs
according to the structure for a period of 20 years are shown in tabular form. Analysis of operational
costs considers forecasts of price variations for each item.
Preliminary financial analysis consists of the table of costs of energy production, and following
figures, (enclosed in the Annex): comparative analysis of costs of heating energy and savings;
savings resulted by a fuel switch; operational costs and depreciation; comparison of total costs of
the existing and a new heating system; and cash flow.
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Biomass - wood chips 83,631 85,436 87,280 89,163 91,087 93,052 95,060 97,111 99,206 101,347
Ash 947 960 973 987 1,001 1,015 1,029 1,043 1,058 1,073
Electricity 687 703 720 737 755 773 792 811 830 850
Water 27 27 28 28 56 57 57 58 58 89
Summary 85,292 87,127 89,001 90,915 92,899 94,897 96,938 99,023 101,153 103,359 Employee – Labor costs 20,000 20,300 20,605 20,914 21,227 21,546 21,869 22,197 22,530 22,868
Maintenance 9,906 9,906 9,906 9,906 9,906 18,177 18,177 18,177 18,177 18,177
Insurance costs 9,841 9,608 9,381 9,162 8,948 8,742 8,542 8,349 8,163 7,984
Summary 39,747 39,814 39,892 39,981 40,082 48,465 48,588 48,723 48,870 49,028
Depreciation 47,986 46,644 45,303 43,961 42,620 41,278 39,937 38,595 37,253 35,912
Total costs 173,025 173,585 174,195 174,857 175,600 184,640 185,463 186,341 187,276 188,299
2028 2029 2030 2031 2032 2033 2034 2035 2036 2037
Biomass - wood chips 102,258 103,178 104,105 105,041 105,985 106,938 107,899 108,870 109,848 110,836
Ash 1,088 1,103 1,118 1,134 1,150 1,166 1,182 1,199 1,216 1,233
Electricity 870 891 913 935 957 980 1,003 1,027 1,052 1,077
Water 89 90 91 92 124 125 127 128 129 130
Summary 104,306 105,262 106,227 107,202 108,216 109,209 110,212 111,224 112,245 113,276 Employee – Labor costs 23,211 23,559 23,912 24,271 24,635 25,005 25,380 25,760 26,147 26,539
Maintenance 26,993 26,993 26,993 26,993 26,993 36,899 36,899 36,899 36,899 36,899
Insurance costs 7,811 7,645 7,485 7,332 7,186 7,047 6,914 6,789 6,669 6,557
Summary 58,015 58,197 58,390 58,596 58,814 68,951 69,193 69,448 69,715 69,995
Depreciation 34,570 33,229 31,887 30,545 29,204 27,862 26,521 25,179 23,838 22,496
Total costs 196,891 196,687 196,505 196,344 196,235 206,022 205,926 205,851 205,798 205,767
Table 34 - Costs of energy production19
Financial analysis shows that future plant can generate positive cash flow after the period of 9 years
from the start of operations. Such long period needed to achieving the sustainability of the project
is caused by high initial investment costs and by low full load hours (808 kWh/kW) in public buildings.
19 Own calculations
66
Low biomass price, compared to currently used fuels, would enable better utilization of public
buildings - the Sports hall ‘Dr. Zoran Djindjić’ and Movie Theatre, to the general benefit of local
community.
Offered technical solution provides to the municipality the establishment of a sustainable heating
system, which would increase the quality of life, and create a positive impact to the environment.
If the investment was financed from KfW Bank's program, with grant of 20%, grace period of 5 years
and a repayment period of 10 years, the positive business results would be achieved after 7 years
from the start of operations.
67
9. PROJECT EVALUATION
Evaluation of the project is based on the collected and calculated data; costs of the construction of
the biomass plant with two wood chips heated boilers and district heating system; and operational
costs (OPEX). Analysis included variations of fuel prices and operational costs throughout whole
period of analysis.
Based on investment costs (Table 32) and operating costs for the period of 20 years (Table 33)
economic indicators are given in the Table 35 above. Economic indicators necessary for the
investment plan are following:
‒ (F) IRR - (Financial) Internal Rate of Return ‒ (E) IRR - (Economy) Internal Rate of Return ‒ (F) NPV - (Financial) Net Present Value ‒ (E) NPV - (Economy) Net Present Value ‒ DR - Discount Rate
Unit cost heat energy Unit Value
The investment value – Capex € 2,151,200
Annual production of heat energy (first year of operation) MWh / a 3,815
Total heat production (20 years) MWh 75,859
The operation value (20 years) – Opex € 3,840,636
LUC - Levelized Unit Costs € / MWh 79.3
NPV € 1,755.475
DR % 1
IRR % 6.470
Sensitivity to changes in the price of fuel (biomass) IRR%
Price biomass is less 5% 6.606%
Price biomass increased 5% 6.258%
Price biomass increased 10% 6.052%
Price biomass increased 15% 5.845%
Table 35 - Unit costs of heating energy20
Based on the results of the analysis of techno-economic indicators, it is concluded that the
investment in the construction of a new biomass plant with district heating system for public buildings
in Prokuplje is acceptable.
IRR = 6.470% > DR = 1 %
Financial indicators of sustainability are stable related to change of the price of biomass. Increase
of the price of biomass even up to 15% would not affect sustainability of the project, and such
increase would not significant prolong a period of the return of the investment. High increase of the
prices, than anticipated, of fossil fuels and of electricity would affect shortening a period of the return
of the investment to less than 9 years.
20 Own calculations
68
10. LEGAL FRAMEWORK
EU Directive 2009/28/EC promotes the use of energy from renewable energy sources. It sets
binding national goals for the overall share of energy from renewable sources in final energy
consumption (less than 20%), as well as the share of RES in transport (10% of energy from
renewable sources in transport by 2020).
In order to support investments in renewable energy sources, the Republic of Serbia adopted a
number of laws and bylaws related to the use of biomass and other renewable energy sources.
These are the following acts:
- Energy Law (Official Gazette of the Republic of Serbia 145/2014)
- Energy Sector Development Strategy of the Republic of Serbia for the period by 2025 with
projections by 2030 (Official Gazette of the Republic of Serbia 101/2015)
- Solid biofuels – Fuel specifications and classes SRPS EN ISO 17225-1,4:2015
- Law on Planning and Construction (Official Gazette of the Republic of Serbia 72/2009,
81/2009-corr, 64/2010 – Decision of the Constitutional Court, 24/2011, 121/2012, 42/2013 –
Decision of the Constitutional Court, 50/2013 – Decision of the Constitutional Court, 98/2013
– Decision of the Constitutional Court)
- Law of efficient energy consumption (Official Gazette of the Republic of Serbia 25/2013)
- Law on Environmental Protection (Official Gazette of the Republic of Serbia 135/2004,
36/2009, 36/2009 and other law, 72/2009 and other law, 43/2011 – Decision of the
Constitutional Court, and 14/2016)
- Law on The Strategic Assessment of Environmental Impact (Official Gazette of the Republic
of Serbia 135/2004 and 88/2010)
- Law on Integrated Prevention and Control of Environmental Pollution (Official Gazette of the
Republic of Serbia 135/2004, 25/2015)
- Law on Waste Management (Official Gazette of the Republic of Serbia 36/2009, 88/2010,
14/2016)
- Law on Air Protection (Official Gazette of the Republic of Serbia 36/2009, 10/2013)
- Law on the Ratification of the Kyoto Protocol to the UN Framework Convention on Climate
Change (Official Gazette of the Republic of Serbia – International Contracts, 88/2007 and
38/2009- other law)
‒ National Renewable Action Plan of the Republic of Serbia (Official Gazette of the Republic of Serbia 53/2013).
69
11. ENVIRONMENTAL IMPACT
Implementation of the project affects the area where the biomass is collected, prepared for
transportation, and transported at territory of Prokuplje and at territory of the immediate
surroundings. The environmental impact may be registered as noise, vibration, emissions of
particulate matter from the exhaust gases, etc.
During the construction of the plant, adverse impacts on local environment may occur due to
construction and installation works. Particularly negative impact would produce preparation works
for the construction of the boiler room and storage of wood chips where it would be necessary to
clear and level the ground. Construction works will cause noise and vibration generated by using
construction machinery, as well as increased dust emissions due to the works on the excavation of
foundations, leveling the ground, and the construction of access roads. All of the effects listed above
are of low intensity, and relatively short in duration. The construction site will be surrounded by the
fence, so adverse environmental impacts outside of the fence will be negligible.
Prior to the beginning of works, the Investor is required to prepare a study on the organization of the
site which will display the work areas, corridors for internal transport, temporary storage of
equipment and materials, temporary site landfill, manner and place of storage of flammable and
hazardous materials. The study will show the connection to the outside infrastructure and
installations, usage of protective agents, the method of disposal of solid and liquid waste and other
specific measures, which will be implemented to reduce risks to health and safety of the personnel
engaged; as well as environment protection actions.
During the operations of the energy block, the harmful substances contained in the exhaust gases
will exert the highest impact on the environment. In addition to dust from the fuel, the exhaust gas
also contains solid particles. Adding a cyclone device as a part of a boiler for combustion of biomass
would have effects on the following:
- Nitrogen oxides (NOx) in the case of combusting low moisture biomass: the temperature of
combustion is high in this case, and NOx content is significantly higher than in case of
combusting biomass with high percentage of moisture
- Sulfur oxides (SOx) are low because of the low sulfur content in the biomass
- Carbon dioxide (CO2) is considered neutral because the biomass is a renewable energy
source, so that the entire amount of the carbon emitted in the exhaust gas has been previously
taken from the environment in which the tree grew
- Carbon monoxide (CO) in practice does not occur due to the structure of the boilers and
constant monitoring of the combustion process.
In any case, the planned biomass plant should replace the existing local boilers which use fuel oil,
wood and electricity, and which are extremely unfavorable for the environment.
The heating plant itself does not require a significant amount of water. While in operation, the heating
plant does not have losses and uncontrolled water runoff except in the cases of emergencies
(failures). Such situations are extremely rare with this type of plants, so it is safe to say that there
70
is no risk of environmental pollution, as well as of pollution of surface and/ or groundwater.
The existing sewerage system is able to accept the wastewater that may be of atmospheric origin;
from washing facilities and equipment with a negligible content of oils and grease; waste and
sanitary sewage. In the cases of discharging the installations, a coolant tank is used with a grease
separator, and after the deposition, water is discharged into the sewer system.
The exhaust gases contain solid particles of ash, which are retained in the cyclone device prior to
entering the chimney and discharged into the atmosphere. A metal cartridge is placed into the
cyclone where the separated ash is deposited. In addition, the boiler unit has a cartridge for the
disposal of ash that occurs as a solid residue of the combustion process. The total amount of ash
deposited is 31 t/a, i.e. between 150 and 200 kg per day during the heating season. The ash will be
disposed in a safe place and once a week transported to the landfill under a contract with the local
utility company. The amount of ash is relatively small and does not represent a risk to the
environment.
The operations of the boilers and electric motor drives in the boiler room represent a source of
constant noise and vibration. All equipment that emits noise and vibration is located within the area
of the boiler room so that the sound is quite absorbed by the walls of the building. After
commissioning the boiler room, the measures will be implemented to eliminate or reduce the noise
to the acceptable level according to the Law on the protection of environmental noise21. According
to this Law, the maximum allowable noise level is 35 dB (A) during the day and 30 dB (A) during
night.
The user of this space will implement specific measures to minimize the negative impact on the
environment. These measures will be applied to the control of air emissions, as well as to the
management of wastewater, solid waste and noise.
Thermal energy for public institutions in the municipality of Prokuplje is obtained from different
types of fuel, so the production of CO2 is different for each heat source. Existing heating systems
in public buildings in Prokuplje produce up to 850 t of CO2 annually.
21 Official Gazette of the Republic of Serbia No 36/2009 and 88/2010
71
Figure 26 - Emission of CO2 per a fuel type
If the biomass for combustion were obtained by deforestation and without reforestation, an emission
of CO2 by biomass combustion would be 6 times less than from the combustion of existing fuels. If
the biomass for combustion were provided from wood waste or from forestation, then reduction of
CO2 emissions would be lower for 650 t per year.
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
900,000
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
31
20
32
20
33
20
34
20
35
20
36
20
37
20
38
Ave
rage
Emission CO2 (kg), Comparasion to fuel
Emision CO2 (kg) - Existing fuel Emision CO2 (kg) - Biomass
72
12. ENERGY EFFICIENCY MEASURES AND CONCLUSION
Public buildings in the Prokuplje municipality are heated by electric heaters-boilers, biomass pellet
and light fuel oil, in individual boiler rooms located in the buildings. These heating systems require
high fuel expenses and a lot of engagement on purchase and storing the fuel; as well as on regular
maintenance and servicing.
Heating system that use pellet as a fuel (Primary school ‘Ratko Pavlović - Ćićko’) is a good example
of using biomass as a fuel. The pellet boiler system in the Primary school ‘Ratko Pavlović - Ćićko’
is new and was built during the year 2017. These boilers have a good automatic boiler control
system. Despite the automatic management of such systems it is necessary to regularly clean and
maintain, which is their fault if there are more such systems in a small area.
Heating systems that use light fuel oil have high level of automation in terms of maintaining water
temperature. In spite of high efficiency, they are big pollutants, and the fuel expenses are high for
such systems.
Facilities heated by electricity are energy very inefficient, even though the heating is easily
managed, and desired air temperatures are easily reached.
In respect to the above, the existing heating systems in public buildings in Prokuplje are energy
inefficient, and they require high expenses related to the following: the purchase of the fuel;
maintenance; servicing. Furthermore, these systems are big environmental pollutants.
Construction of two central boiler rooms, with biomass heated boilers of 6 MW and of heating
network will enable sustainable, cheaper, more reliable, manageable, and ecologically acceptable
heating system to public buildings in Prokuplje. Heating systems in the buildings would be connected
to the district heating network in the heating substations, which would enable measuring of delivered
heating energy and management of consumption in accordance with the requirements of specific
facility.
Construction of biomass heating plant and of district heating network will enable following:
‒ lower costs of the heating,
‒ reduction of fuel consumption,
‒ reduction of CO2 emission,
‒ reduction of environmental pollution,
‒ increased comfort, and increased quality of services,
‒ decrease of a fuel expense and of maintenance costs.
There are forests at territory of the Municipality of Prokuplje and the Toplica District sufficient to
provide biomass for district heating plant. In addition, biomass can be purchased as residues from
orchards and private forests. In such way, local community could close the circle of production and
consumption of heating energy.
73
13. ANNEX
74
Figure 27 - Comparative analysis of costs of heating energy and savings
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
Existing fuels x 103 345,3 363,7 383,2 403,7 425,4 448,3 472,4 497,8 524,7 553,0 558,0 563,1 568,3 573,5 578,7 584,0 589,4 594,8 600,2 605,7
Wood chips x 103 83,63 85,43 87,28 89,16 91,08 93,05 95,06 97,11 99,20 101,3 102,2 103,1 104,1 105,0 105,9 106,9 107,8 108,8 109,8 110,8
Saving x 103 261,6 278,3 295,9 314,6 334,3 355,2 377,3 400,7 425,4 451,6 455,8 460,0 464,2 468,4 472,7 477,1 481,5 485,9 490,4 494,9
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
Comparative analysis of cost heat energy and saving - (€)
75
Figure 28 - Savings from fuel switch
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
450,000
500,000
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
Saving x 103 261, 278, 295, 314, 334, 355, 377, 400, 425, 451, 455, 460, 464, 468, 472, 477, 481, 485, 490, 494,
Saving from fuel switch - (€)
76
Figure 29 - Operational costs and depreciation
0
50,000
100,000
150,000
200,000
250,000
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
Operational costs and Depreciation - (€)
Biomass - wood chips Extra energy Employee – Labor costs Maintenance & Insurance costs Depreciation
77
Figure 30 - Comparison of total costs of the existing system, new heating system and new system supported by KfW Credit
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
Total costs of Existing sistems - CAPEX+OPEX - KfW Credit (€)
Existing heating sistems CAPEX+OPEX KfW Credit
78
Figure 31 - Cash flow balance
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
TotalCashFlow x103 -2,19 -1,99 -1,77 -1,53 -1,27 -994, -692, -365, -13,0 366,7 747,7 1,133 1,525 1,922 2,324 2,727 3,136 3,550 3,969 4,394
-3,000,000
-2,000,000
-1,000,000
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
Cash flow balance - (€)