Upload
emi-whitley
View
46
Download
2
Embed Size (px)
DESCRIPTION
Efficient installation of offshore wind farms…also in the future. Case study: Burbo Banks Offshore Wind Farm. Rasmus Lund, Siemens Wind Power A/S. Agenda. Siemens’ offshore track record Siemens’ offshore wind turbines Efficient installation of offshore wind farms - PowerPoint PPT Presentation
Citation preview
© Siemens Wind Power A/S. All rights reserved
Efficient installation of offshore wind farms…also in the futureCase study: Burbo Banks Offshore Wind Farm.Rasmus Lund, Siemens Wind Power A/S
© Siemens Wind Power A/S. All rights reserved
Siemens’ offshore track record
Siemens’ offshore wind turbines
Efficient installation of offshore wind farms
Case study: Burbo Banks Offshore Wind Farm
Agenda
© Siemens Wind Power A/S. All rights reserved
Worldwide market leader in offshore projects
1) In progress
Lynn / Inner Dowsing, UK
54 turbines (2008)
Rhyl Flats, UK 25 turbines1)
London Array, UK 175 turbines1)
Sheringham Shoal, UK 88 turbines1)
Walney, UK 102 turbines1)
Burbo Banks, UK 25 turbines (2007)
Frederikshavn, DK 1 turbine (2003)
Baltic I, DE 21 turbines1)
Rødsand/Nysted, DK 72 turbines (2003)
Vindeby, DK 11 turbines (1991)
Middelgrunden, DK 20 turbines (2000)
Samsø, DK 10 turbines (2002)
Rønland, DK 4 turbines (2002)
Horns Rev II, DK 91 turbines1)
Gunfleet Sands, UK 48 turbines1)
Greater Gabbard, UK 140 turbines1)
Rødsand II, DK 90 turbines 1)
Hywind, NO 1 turbine (2009)
Lillgrund, SE 48 turbines (2007)
© Siemens Wind Power A/S. All rights reserved
2.3 MW - 82 m rotor introduced
2002, certified for IEC IA
2.3 MW - 93 m rotor introduced 2005, certified for IEC IIA
2.3 MW - 101 m rotor introduced 2009, certified for IEC IIB
3.6 MW - 107 m rotor introduced
2004, certified for IEC IA
3.6 MW - 120 m rotor planned for installation late 2009, to be certified for IEC IA/B
Two new family members for Siemens offshore
Siemens’ offshore line-up
© Siemens Wind Power A/S. All rights reserved
Larger projects
Projects located further offshore
Year-round installation
Trends
Efficient installation is becoming more critical
Increased focus on efficient installation of offshore wind farms
© Siemens Wind Power A/S. All rights reserved
Improved wind turbine design for easy interface and safe installation
Well planned onshore pre-assembly and tests at base harbor
Efficient wind turbine component arrangement and planning of installation vessels
Ensuring co-operation with owner and all suppliers in design, planning and execution
Focus on efficient quality control at base harbor
Choice of an efficient buffer system at base harbor
Key elements of efficient installation
There are many pieces to the puzzle when it comes to efficient installation
© Siemens Wind Power A/S. All rights reserved
An example: Burbo Banks
© Siemens Wind Power A/S. All rights reserved
25 x 3,6 MW
Round 1 UK project: 90 MW output
Tip height 137m above mean sea-level.
Water depth: 7-12 m
Tide: +/- 5m
Distance to shore: 7-12 km
Mean wind speed: 9 m/s
The wind farm is generating enough electricity to power the equivalent of over 80,000 homes
Key project facts
107 m
83,5 m
137 m
© Siemens Wind Power A/S. All rights reserved
25 pcs SWT-3.6-107 offshore wind turbines
Transportation, installation, commissioning and tests
34kV switchgear
SCADA system
5 years service and maintenance
Scope of work
© Siemens Wind Power A/S. All rights reserved
UK
BladesTowers
NacellesHubsPower units
Logistics
© Siemens Wind Power A/S. All rights reserved
One vessel for 6.25 turbines
© Siemens Wind Power A/S. All rights reserved
Location
© Siemens Wind Power A/S. All rights reserved
Port layout
Port of Mostyn, UK
Purpose- Logistics centre- Buffer
Arrangement - 45,000 m²
Main tasks at harbor- Pre-assembly- Test- Quality control- Vessel loading
© Siemens Wind Power A/S. All rights reserved
Port layout
Port of Mostyn, UK
Purpose- Logistics centre- Buffer
Arrangement - 45,000 m²
Main tasks at harbor- Pre-assembly- Test- Quality control- Vessel loading
© Siemens Wind Power A/S. All rights reserved
Nacelle loading
© Siemens Wind Power A/S. All rights reserved
Blade loading
© Siemens Wind Power A/S. All rights reserved
Installation jack-up
© Siemens Wind Power A/S. All rights reserved
Tower installation
© Siemens Wind Power A/S. All rights reserved
Nacelle installation
© Siemens Wind Power A/S. All rights reserved
Blade installation
© Siemens Wind Power A/S. All rights reserved
End result
All 25 SWT-3.6-107 wind turbines were successfully installed in 43.5 days, well ahead of schedule
© Siemens Wind Power A/S. All rights reserved
Another example: Lillgrund110 MW – 48 x SWT-2.3-93
© Siemens Wind Power A/S. All rights reserved
Example 3: Lynn & Inner Dowsing194 MW – 54 x SWT-3.6-107
© Siemens Wind Power A/S. All rights reserved
Example 4: HywindThe world’s first floating WTG – 2.3 MW – 1 x SWT-2.3-82
© Siemens Wind Power A/S. All rights reserved
Pre-assembly and tests at base harbor
Arrangement of installation vessels
Installation within time schedule
Very good co-operation with clients and subcontractors
Detailed planning of all phases early in the project
Importance of pre-assembly setup and efficient quality control at base harbor
Importance of an efficient buffer system
Sufficient time lag between difference project phases
Lessons learned
Successes and lessons learned
Successes