Efficiency, Integration and Collaboration
- Delivering SNS Decommissioning
Richard Tocher
Decommissioning Manager1
2
SNS Infrastructure
Fast Facts
• 38 platforms
• 9 subsea installations
• 140,000 tonnes
• 145 wells
• 1,650 km of pipelines
• Onshore terminal
• 3rd party infrastructure
• Multiple joint ventures
Cessation of Production
• Viking – January 2016
• LOGGS – August 2018
• CMS – August 2018
Decommissioning commenced June 2014
3
Campaign Strategy: Minimise Risk and Cost
ACCOM. WORK VESSEL (AWV)
1. Final clean2. Stabilisation3. Pre-rig abandonment
1: FINAL CLEAN
• Topside purging• Flowline destruct• Pipeline cleaning
2: STABILISATION
• Dropped object protection• Asset integrity repairs• Handrail/grating repairs
2: REMOVAL PREPARATION
• Installation of lifting aids• Reinstating access
3: PRE-RIG ABANDONMENT
• Detailed survey• Clear access paths• P&A pre-works
1: P&A
• Set barriers• Pull conductors
3: FINAL DISCONNECT
• Commission solar powered AtoN
• Transition to cold stack
SIMOPS SIMOPS
RIG (ENSCO 92)
1. Well P&A2. Removal preparation3. Final disconnect (topside)
HEAVY LIFT VESSEL (HLV)
1. Platform removal2. Transportation to shore
4
Progress to Date
*68% of wells (145), 68% of platforms (38)
3rd Party Operated
Chrysaor Operated
Ready for removal (platform)Flushed & cleaned (pipeline)
99 wells P&A’d*
LOGGSViking Bravo
Murdoch
All pipelines flushed and cleaned
7 platforms removed,
19 ready for removal*
Viking Bravo & LOGGS de-manned
TGT ready for demolition
Rigorous safety case management
20% reduction in campaign cost
28% reduction in well P&A cost
Careful environmental execution
5
Well P&A: Downward Cost Trend Continues
✓ Reduced rig rate
✓ Crew learning curve
✓ Well suspension from AWV
✓ Bunter formation flow testing
✓ Through-tubing abandonments
• Reduced need for logging
• Reduced completion pulling
• Fewer BOP runs
✓ Sabre conductor cut & recovery
✓ Offline work-scopes
✓ Rig modifications
Ensco 92
• CMS Area campaign in Q2 2019
• 4 operators, several joint ventures
• Integrated AWV & DSV campaign
• Flushing into Murdoch disposal well
• Commercial framework established
• Significant cost savings realised 6
Collaboration to Reduce Cost
Pipeline Cleaning Shared Subsea Campaigns Joint P&A Campaign
• Several operators involved
• Pipeline disconnects
• Conductor removals
• Surveys
• Debris clearance
• Shared mob/demob/weather risk
• Multi-well campaign by Spirit Energy
• Chrysaor KX well
• Cost savings from batch operations
and vessel sharing
7
2019 Boskalis-Scaldis Removal Campaign
Campaign ongoing for 9 platform removals and 1 subsea template
• OSV Da Vinci – rigging, preparation and supporting scopes across 7 platforms
• Bokalift 1 – 11 of 14 major lifts completed
• Gulliver – all 4 major lifts completed
KD LD GD DD CD HD ED UR JD
Topside Jacket Topside Jacket Jacket Jacket JacketSide
towersJacket Topside Jacket Topside Jacket Helideck Topside Jacket
Subsea
Template
Gulliver H1 H3 H2 H4
Bokalift 1 H6 H8 H6 H4+5 H1 D1 H D1 H D7 D5 H9 D
November 26, 2019
Great Yarmouth Disposal Facility
Bokalift 1OSV - Da Vinci Gulliver
VIKING ED TOPSIDE LIFT(21 AUGUST)
GULLIVER WITH VIKING LD TOPSIDE IN TRANSIT
(23 AUGUST)
VIKING CD JACKET
LIFT(8 OCT)
Looking Ahead
Ensco 92 P&A
Programme
Platform
Removals
Subsea
Campaigns
Oct Nov AugJulJunMayAprMarFebJanDec Sep
VM
Oct Nov FebJanDec AugJulJunMayAprMar Sep
November 26, 2019
TMTM
Murdoch
TD
CMS
2019
TGT
2020
RD – 12 wells
VM
CMS
Phase I: Cold Suspension
& De-manningPhase II: Site Demolition & Disposal
To
2025
2021
Murdoch ready for removal
Phase III: Land Remediation &
Restoration
To
2024
To
2024
To Q1
2022