Effective Verification and Validation Testing. Steve Holt Boeing Commercial Airplanes August 2013. Effective Verification & Validation Testing Summary - Commercial Airplane Product Development. Initiatives Were Put In Place to Address: Incomplete or unnecessary test requirements - PowerPoint PPT Presentation
Citation preview
Copyright © 2012 Boeing. All rights reserved.
Effective Verification and Validation Testing
Steve HoltBoeing Commercial AirplanesAugust 2013
Copyright © 2012 Boeing. All rights reserved.
Initiatives Were Put In Place to Address: Incomplete or unnecessary test requirements Immature test capability Inefficient test conduct
Success found in: Application of systems engineering tools and methods Teaming across design and test functions early in the design cycle Test engineering participation in requirements and V&V development
Questioning why past requirements are needed Questioning current methods of verification
Focusing on problematic design features and complex integration areas Optimizing affordability to include risk mitigation (cost avoidance) as well as
cost reduction
Effective Verification & Validation TestingSummary - Commercial Airplane Product Development
Copyright © 2012 Boeing. All rights reserved.
Navigate:
Requirements
DesignersLab Test Value
Stream
Flight Test Value StreamStart
validating the design
here!
• Inspection• Analyses• Modeling
• Modeling• Simulation• Hardware Bench
Testing• Integrated System
Testing
Full ScaleIntegrated Testing
Verification Planning
Verification & Validation CycleCommercial Airplane Product Development
Copyright © 2012 Boeing. All rights reserved.
Verification & Validation TargetEarly Verification and Risk Retirement
Typical Plan
Target
AnalysesInternalBenchTesting
SupplierBenchTesting
IntegratedSystems
Laboratory
AirplaneFlightTest
Modeling&
Simulation
Req
uire
men
t Ve
rific
atio
n
Copyright © 2012 Boeing. All rights reserved.
Verification ToolsEducating Design Engineering on Capability
Wind Tunnel
Bench Tests
Full Scale Test Articles
Integrated System Testing
Modeling & Simulation
Culture Shift
Copyright © 2012 Boeing. All rights reserved.
Requirement
Verification Plan
Facility Needs
SatisfyingData
Test Statement of Work
Test System Readiness Triggers
Integrated Test Plan
Data Source Determination
Test Optimization
Verification & Validation
Governance
• Verification Approach• Verification Culture• Verification Capture
Interactive Development Among Design and Test Engineers
Test article readiness ensures early risk
mitigation
Part of test efficiency initiatives
Verification & Validation DevelopmentCross-Functional Verification, Test, and Means of Compliance
Copyright © 2012 Boeing. All rights reserved.
Requirement Area
Analyses Modeling & Simulation
Laboratory Testing
Integrated System Tests
Flight Article
Flight Loads Concurrent
High Speed Mach Buffet
Multiple Failure Assessment
Safety of Flight
System Functionality
Crew Workload Determination
Pilot & Airport Operations
Concurrent
Spatial Integration
Structural & Actuation Loads
Structural Interfaces
Systems Interfaces
Verification Exercise – Folding Wing TipExample of Earlier Verification and Risk Retirement
Copyright © 2012 Boeing. All rights reserved.
• A culture change is often necessary to qualify “Affordability” as cost optimization, to include investment in early verification and risk mitigation
• Using test experts to scrutinize design requirements and means of verification leads to a more robust and mature product
• Shifting verification “to the left” as much as practical helps ensure a mature and cost-optimized product
• Focusing on test readiness and efficiency throughout the development life cycle helps ensure verification success
• Complex systems yield emergent effects. Some of them increase risks, some of them increase opportunities.
Effective Verification & Validation TestingConclusions