IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 2/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
EFDA GOAL ORIENTED TRAINING PROGRAMME
TASK AGREEMENT WP08-GOT-ITER_PPE
“Network Report for year 2009”
1. GENERAL PROGRESS OF THE PROJECT
a) The Project is running as originally planned
b) Some minor modifications are needed
c) Major modifications are needed
�
❏
❏
The thematic of the ITER Goal Oriented Training Programme on Port Plug Engineering (PPE) is in the field of Engineering Design and Construction, this training program is associated to the procurement of the ITER Port Plug including: design, structural analysis, neutronics, material requirement, nuclear requirement, safety, manufacturing aspect, assembly aspect, maintainability. Six work packages of three years duration are identified: 2 CEA, 1 FZJ, 2 KIT, and 1 HAS. The official starting date of the ITER GOT PPE is 1st september 2008 established for 4 years, the first year being devoted to the recruitment of the trainees. All Contracts have already started and all the trainees have been recruited during the first year, the ITER GOT PPE training program will run from the 01 September of 2008 to the 07 July of 2012. This programme is now running effectively and in good accordance with the spirit of the Task Agreement WP08-GOT-ITER_PPE signed with EFDA. The first deliverable ‘’Personal Career Development Plan’’ has been delivered in due time for each Work Package. Progress reports for the first year have been produced in the beginning of 2010 (see annexe 1 to 6). A kick off meeting in November 2008 and a review meeting in December 2009 have been organised and the minutes produced. During those meeting courses and events, sharing between associations and sharing with industry to be organised in 2010 and 2011 have been defined. Concerning financial matters, there is no deviation of the budget devoted to the expenditures under additional support (around 30 % has been used). Nevertheless, the mobility costs represent only ~8% of the total amount; this is because we are at the beginning of the program so all the work has been done inside the host associations. In 2010 this situation will evolve with training periods shared in partner associations. 2. IDENTIFICATION OF PROBLEMS ENCOUNTERED AND CORRECTIVE ACTION (S) TAKEN ; ACTIVITIES ON
CRITICAL PATH
If you answered b) or c) under 1.), please include a detailed description of the research problems encountered, deviations and/or modifications to the project during the reporting period.
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 3/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
3. ADMINISTRATIVE MATTERS OR ANY OTHER POINTS OF RELEVANCE
E.g., changes in TA positions (coordinator, scientist-in-charge) should be reported.
Changing in TA positions:
Coordinator:
L.Doceul replaces L.Meunier since September 2008.
Scientist in charge:
WP1: S.Salasca replaces L.Meunier since September 2008.
WP2: D.Keller replaces JP.Martins since January 2010.
WP3: T.Scherer replaces D.Strauss since December 2008.
WP5: G.Grunda replaces O.Bede since July 2009.
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 5/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
5. TIME AND DURATION OF EACH INDIVIDUAL CONTRACT Network Partner Name of the trainee Start of training /
employment contract Duration of contract (months)
CEA DAPENA FEBRER Miguel 05/01/2009 36 CEA WAGREZ Julien 03/06/2009 36 FZK AIELLO Gaëtano 01/09/2008 36 FZK ZEILE Christian 05/06/2009 36 HAS NEMETH József 06/07/2009 36 FZJ VOINCHET Romaric 05/01/2009 36 6. IMPLEMENTATION STATUS Rate of recruitment for each participant (trainee) and for the TA as a whole (ratio person-months filled/offered) A B C C/B Network Partner Man-months
training contractually foreseen at the end of the reporting period (cumul)
Man-months training performed at the end of reporting period (cumul)
Percentage of compliance
CEA (WP1) 12 12 100 CEA (WP2) 7 7 100 KIT (WP3) 16 16 100 KIT (WP4) 7 7 100 HAS (WP5) 6 6 100 FZJ (WP6) 12 12 100
Nature and justification for adjustments, if any, to the original overall number of person-months per trainee 7. ORGANISATION OF THE NETWORK MEETINGS (CAN BE REMOTE )
Place of TA meeting Date and duration of TA meeting Cadarache-IRFM 19/11/2008
Culham-JET 08-12/06/2009 Cadarache-IRFM 07-11/12/2009
8. PRESENTATIONS BY THE TRAINEES TO PEER GROUPS Name of trainee Title of presentation Date Place
Equatorial Port Plug Safety Approach. First ideas and impressions
March 2009 Cadarache-IRFM
Overview of the Work Performed in WP1 April 2009 Cadarache-IRFM S1 – Fundamental safety principles December 2009 Cadarache-IRFM S2 – Radiation and dosimetry December 2009 Cadarache-IRFM
DAPENA FEBRER Miguel
Presentation of WP1 status at second review meeting
07-11/12/2009 Cadarache-IRFM
Overview of the Work Performed in WP2 08-12/06/2009 Culham-JET WAGREZ Julien Presentation of WP2 status at second review
meeting 07-11/12/2009 Cadarache-IRFM
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 6/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
Overview of the Work Performed in WP3 08-12/06/2009 Culham-JET AIELLO Gaëtano Presentation of WP3 status at second review
meeting 07-11/12/2009 Cadarache-IRFM
ZEILE Christian Presentation of WP4 status at second review meeting
07-11/12/2009 Cadarache-IRFM
NEMETH József Presentation of WP5 status at second review meeting
07-11/12/2009 Cadarache-IRFM
Overview of the Work Performed in WP6 08-12/06/2009 Culham-JET Presentation of the first estimations of the mirror deformation analysis
October 2009 Eindhoven VOINCHET Romaric
Presentation of WP6 status at second review meeting
07-11/12/2009 Cadarache-IRFM
Cumulative overview from the respective start of the training:
Name of trainee Total No. of presentations to peer groups so far
No. of presentations to peer groups expected by the end
of the training DAPENA FEBRER
Miguel 5 6
WAGREZ Julien 2 6 AIELLO Gaetano 2 6 ZEILE Christian 1 6 NEMETH József 1 6
VOINCHET Romaric 3 6 9. PAPERS SUBMITTED BY THE TRAINEES FOR PUBLICATION OR PRESENTED AT CONFERENCES
Name of trainee
Title of paper Lead Author
Y/N
Authors Name of the Journal
Name, date and place of conference
M.Dapena Febrer
Aina safety code, a review of loss of plasma control transients in ITER: Sudden increase in fuelling rate, sudden increase of auxiliary heating.
J.Dies J. Dies, M. Dapena, M. Ramon, R. López, J. García, J.C. Rivas, A. Calvo, S. Reyes
Fusion Science and Technology
July 2009
J.Wagrez Support for a mechatronics finite element analysis of the ITER equatorial cask & plug remote handling system
J-P.Martins J-P.Martins, J.Wagrez
October 2009
G.Aiello Prototyping and testing of ITER ECH upper launcher components
G.Aiello
G.Aiello, T.A .Scherer, D. Strauss, S. Schreck, P .Späh, A. Meier, A. Vaccaro
21st Joint Russian-german Workshop on ECRH and gyrotrons, Greiswald, 11-16 May 2009
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 7/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
Cumulative overview from the respective start of the training:
Name of trainee Total No. of publications submitted so far
No. of publications expected by the end of the
training DAPENA FEBRER
Miguel 1 2
WAGREZ Julien 1 2 AIELLO Gaetano 1 2 ZEILE Christian 0 2 NEMETH József 0 2
VOINCHET Romaric 0 2 - More Categories like above, e.g., patents, can be included if considered useful in the particular context – 10. COURSE WORK COMPARED WITH THE TARGET AGREED Indicate the overall target of course days.
Name of trainee
Course title Date Place Duration (days)
Master Fusion INSTN February 2009
Cadarache 10
TRIPOLI-4 training course May 2009 Cadarache 2 FZK Summer school September
2009 Karlsruhe 10
DAPENA FEBRER Miguel
Specificities INB ITER December 2009
Cadarache 4
Training session about vacuum in fusion environment, tritium and remote handling, project management, optical diagnostics
June 2009 Culham 5
Summer school on Fusion Technology in Karlsruhe
September 2009
KIT 10 WAGREZ
Julien
Specificities INB ITER December 2009
Cadarache 4
2ND Summer school on fusion technologies
September 2008
KIT 10
Catia and Smarteam courses December 2008
KIT 5
Training session about vacuum in fusion environment, tritium and remote handling, project management, optical diagnostics
June 2009 Culham 5 AIELLO Gaetano
Training session on nuclear engineering December 2009
Cadarache 4
Training session at JET June 2009 Culham 5 Summer school on Fusion Technology in Karlsruhe
September 2009
KIT 10 ZEILE
Christian ITER GOT PPE training session December
2009 Cadarache 4
NEMETH József
Nuclear safety ITER GOT PPE training session
December 2009
Cadarache 4
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 8/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
Training session at JET June 2009 Culham 5 Summer school on Fusion Technology in Karlsruhe
September 2009
KIT 10
Seminar on vacuum techniques November 2009
Cologne 3 VOINCHET
Romaric
ITER GOT PPE training session December 2009
Cadarache 4
Cumulative overview from the respective start of the training, including previous reporting:
Name of trainee Total No. of course days attended so far
No. of course days to be attended by the end of the
training:
DAPENA FEBRER Miguel 26 50 WAGREZ Julien 19 50 AIELLO Gaetano 24 50 ZEILE Christian 19 50 NEMETH József 4 50
VOINCHET Romaric 22 50 11. REPORT ON TRAINING ACTIONS BY THE TRAINEES AND THE SCIENTISTS IN CHARGE For each trainee, a Trainee Report for the reporting period produced by the trainee and confirmed by the supervisor for quality and progress against the planned work must be annexed to this Periodic Activity Report:
Trainee report of Annex number DAPENA FEBRER
Miguel 1
WAGREZ Julien 2 AIELLO Gaetano 3 ZEILE Christian 4 NEMETH József 5
VOINCHET Romaric 6
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 9/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
ANNEX 1:
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 10/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 11/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
ANNEX 2:
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 12/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 13/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
ANNEX 3:
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 14/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 15/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
ANNEX 4:
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 16/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 17/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
ANNEX 5:
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 18/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 19/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
ANNEX 6:
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 20/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page
IRFM IRFM/SIPP/GIPM L. Doceul PEFC/NTT-2010.014 #00 05/03/10 21/21
Structure Service/Groupe Premier auteur Référence Indice Date mise à jour page