ECW542 Sewage Treatment Lecturer: DA/RH At the end of Week 5 students should be able to - describe preliminary treatment - apply knowledge related to preliminary treatment Learning Outcome Screening, Pumping Station, Grit and Grease Removal PRELIMINARY TREATMENT  Smaller sized openings generate more  Remove larger particles, which can  Screening devices can be broadly classified SCREENING as coarse or fine.  Need to work at low and high flows. SCREENING openings.

Citation preview

Page 1: ECW542-wk05-L13

Lecturer:

Sewage Treatment

Wastewater Engineering

ECW542

DA/RH

Tower 1/ Aras , Room

Ext.

Page 2: ECW542-wk05-L13

Learning Outcome

At the end of Week 5 students should be able to

- describe preliminary treatment

- apply knowledge related to preliminarytreatment

Page 3: ECW542-wk05-L13

PRELIMINARY TREATMENT

Screening, PumpingStation, Grit

and Grease Removal

Page 4: ECW542-wk05-L13
Page 5: ECW542-wk05-L13
Page 6: ECW542-wk05-L13

SCREENING

Remove larger particles, which caninterfere with subsequent equipment orprocesses.

Screening devices can be broadly classifiedas coarse or fine.

Smaller sized openings generate morescreenings and more contaminants onscreenings.

Page 7: ECW542-wk05-L13

SCREENING

Need to handle, store, dispose of screenings.

Often have screenings of decreasingopenings.

Need to work at low and high flows.

Page 8: ECW542-wk05-L13

SCREENING DESIGN

Bar spacing, materials of construction anddimensions.

Channel depth, width and approach velocity.

Headloss through the screens (hL = 1(V2-v2/2g)C

Discharge height to accommodate screeningsconveying equipment.

Page 9: ECW542-wk05-L13

SCREENING DESIGN

Angle of screen.

Materials of construction and coatings foroverall unit.

Screen cover to block wind and improveaesthetics and reduce odor.

Drive unit service factor.

Page 10: ECW542-wk05-L13

Drive motor size and enclosure (forexample;

totally enclose fan cooled)

Spare parts.

Provision of redundant screen or bypassscreen.

SCREENING DESIGN

Page 11: ECW542-wk05-L13

THANK YOU