ECG ENGINEERING, P.C. Inspection Report #3 ECG 2685 Wappingers Central School District Energy Performance Contract Inspection Dates: 01/25/2013 10:30am 1:00pm 01/29/2013 7:00am 9:00am Inspector: Harold R. Friedman Met with Craig Rebecca of Ameresco at the Facilties & Operations Office located on the Roy C. Ketcham Senior High School Campus, and proceeded to review work performed on various energy conservation measures within the following buildings. This inspection occurred after our scheduled project meeting with Ron Broas, Director of Facilities & Operations of the Wappingers Central School District in which we discussed current status of project and any outstanding issues: Fishkill Elementary School ECM-4 Integrated and New Energy Management System During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed in progress. All work within project design specifications. Reference pictures as appropriate. ECM-7 Infiltration Reductions Work was reportedly 50% complete. Work was inspected and verified. It was observed due to each existing door structure conditions multiple weather stripping materials were installed. Reference pictures as appropriate. All work within project design specifications. ECM 14 Boiler Replacements At the time of this inspection it was observed that two (2) field erected Smith 28HE Series High Efficiency Steam Boilers were installed and set in place on new reinforced concrete housekeeping pads with a Power Flame dual fuel burner, Model C2-GO-20B with remote fuel oil pump connected to each boiler respectively. Integral to the steam system providing heat to the building is the installation of boiler feed tank with three (3) ½ HP centrifugal pumps, and condensate tank with two (2) ½ HP condensate pumps including all appurtenances. Boiler venting was reconnected to existing at points indicated as per the SED approved design (Refer to photos). The insulation of the piping system was currently in progress. During this inspection the steam boilers were operational, but currently not controlled through the building management system. The contractor also provided a separate electrical panel dedicated to all boiler related equipment (burners, remote fuel oil pump, existing duplex fuel oil pump, boiler feed, vacuum, and condensate pumps). The contractor also provided labeling of all electrical conduit runs from the boiler burners back to the dedicated electrical panel to assist in future service as necessary. Proper hangers and supports were installed, and the contractor stated that upon completion of all boiler work all ceiling penetrations where pipe hanger rods were mounted, the ceiling shall be repaired. The steam boilers have been commissioned with training remaining to be administered to the appropriate District’s personnel.

ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

ECG ENGINEERING, P.C. Inspection Report #3

ECG 2685 Wappingers Central School District Energy Performance Contract

Inspection Dates: 01/25/2013 10:30am – 1:00pm

01/29/2013 7:00am – 9:00am

Inspector: Harold R. Friedman

Met with Craig Rebecca of Ameresco at the Facilties & Operations Office located on the Roy C.

Ketcham Senior High School Campus, and proceeded to review work performed on various energy

conservation measures within the following buildings. This inspection occurred after our scheduled

project meeting with Ron Broas, Director of Facilities & Operations of the Wappingers Central

School District in which we discussed current status of project and any outstanding issues:

Fishkill Elementary School

ECM-4 Integrated and New Energy Management System

During this inspection, work was estimated to be 50% complete within building. Installation of

necessary wiring, conduit, raceways and relays were observed in progress. All work within project

design specifications. Reference pictures as appropriate.

ECM-7 Infiltration Reductions

Work was reportedly 50% complete. Work was inspected and verified. It was observed due to each

existing door structure conditions multiple weather stripping materials were installed. Reference

pictures as appropriate. All work within project design specifications.

ECM 14 Boiler Replacements

At the time of this inspection it was observed that two (2) field erected Smith 28HE Series High

Efficiency Steam Boilers were installed and set in place on new reinforced concrete housekeeping

pads with a Power Flame dual fuel burner, Model C2-GO-20B with remote fuel oil pump connected

to each boiler respectively. Integral to the steam system providing heat to the building is the

installation of boiler feed tank with three (3) ½ HP centrifugal pumps, and condensate tank with two

(2) ½ HP condensate pumps including all appurtenances. Boiler venting was reconnected to existing

at points indicated as per the SED approved design (Refer to photos). The insulation of the piping

system was currently in progress. During this inspection the steam boilers were operational, but

currently not controlled through the building management system. The contractor also provided a

separate electrical panel dedicated to all boiler related equipment (burners, remote fuel oil pump,

existing duplex fuel oil pump, boiler feed, vacuum, and condensate pumps). The contractor also

provided labeling of all electrical conduit runs from the boiler burners back to the dedicated

electrical panel to assist in future service as necessary. Proper hangers and supports were installed,

and the contractor stated that upon completion of all boiler work all ceiling penetrations where pipe

hanger rods were mounted, the ceiling shall be repaired. The steam boilers have been

commissioned with training remaining to be administered to the appropriate District’s personnel.

Page 2: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Field erected Smith 28HE Series High Efficiency Boilers

Power Flame dual fuel burner, Model C2-GO-20B with remote fuel oil pump

Page 3: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Emergency boiler water feeder and low water cut-off to

blow down funnel and piped to the nearest floor drain.

Installation of Siemen’s Ventless Gas Train ready to be connected to burner.

Page 4: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Stainless steel boiler flue vent piping for each boiler with

insulation of all steam piping currently in progress

Stainless steel boiler flue vent piping reconnected to existing

stainless steel chimney flue up through ceiling of boiler room.

Page 5: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Stainless steel flue vent piping from Boiler B-1

reconnect to existing brick chimney inside boiler room.

Single pipe roll with threaded steel hanger rods mounted to the ceiling of the

boiler room to support the steam pipe header above new boilers

Page 6: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

New Shipco Boiler Feed Tank with three (3) ½ HP centrifugal pumps.

New Shipco Condensate Tank with two (2) ½ HP centrifugal pumps located in boiler pit.

Page 7: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Existing duplex fuel oil pumps with electrical connection to new dedicated electrical panel.

New dedicated Boiler Sub-Panel which currently provides power for Boiler No. 1 & No. 2, Oil Feed

Control Panel, Water Feed Control Panel, and the Condensate Pumps

Page 8: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Re-piping of the existing domestic hot water heater Culligan Pre-Treatment system.

Combustion air dampers manually opened during operation of

Boilers. Electronic Actuation of combustion air dampers remains to be installed.

Page 9: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Exterior Combustion Air Louvers with manually opened dampers and

sheet metal blank off of bottom half of louvers during boiler operations.

Existing combustion air louver blanked off with sheet metal and placed

by the contractor as inactive in lieu of the new combustion air louver/ dampers.

Page 10: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Existing combustion air louver blanked off with sheet metal and placed

by the contractor as inactive in lieu of the new combustion air louver/ dampers.

Installation of new RPZ valve with air gap temporarily piped with PVC piping to outside of

building with hard piping of drain to remain to be completed.

Page 11: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of new mushroom type emergency boiler shut down break

glass station on inside wall of Boiler Room at the exterior means of egress.

John Jay High School

ECM 14 Boiler Replacements

At the time of this inspection it was observed that two (2) Unilux Bent Water Tube Boilers, Model

No. ZF 1200LS-FE3 was installed and set in place on new reinforced concrete housekeeping pads

with a Power Flame C-Max dual fuel burner, Model CMR9A-GO-30 with remote air compressor

with pulsation chamber and remote fuel oil pump connected to each boiler respectively. Integral to

the steam system providing heat to the building is the installation of 500 gallon boiler feed tank with

three (3) 1½ HP centrifugal pumps & two (2) 5 HP vacuum producer pumps, and a 65 gallon

condensate tank with two (2) ¾ HP condensate pumps including all appurtenances. Boiler venting

was reconnected to existing at points indicated as per the SED approved design (Refer to photos).

The insulation of the piping system was currently in progress. During this inspection the steam

boilers were operational, but currently not controlled through the building management system.

The contractor also provided a separate electrical panel dedicated to all boiler related equipment

(burners, remote fuel oil pump, existing duplex fuel oil pump, boiler feed, vacuum, and condensate

pumps. The contractor also provided labeling of all electrical conduit runs from the boiler burners

back to the dedicated electrical panel to assist in future service as necessary. Proper hangers and

supports were installed, and the contractor stated that upon completion of all boiler work all ceiling

penetrations where pipe hanger rods were mounted, the ceiling shall be repaired.

Page 12: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

New dedicated Boiler Sub-Panel which currently provides power for Boiler No. 1 & No. 2, Oil Feed

Control Panel, Water Feed Control Panel, and the Condensate Pumps

Installation of new mushroom type emergency boiler shut down break

glass station on inside wall of Boiler Room at the exterior means of egress.

Page 13: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of new Unilux Boilers located in the basement Boiler Room

Installation of new PowerFlame C-Max Dual Fuel Burner located

in the basement Boiler Room

Page 14: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of Siemen’s Ventless Gas Train located in the basement Boiler Room

Installation of new PowerFlame C-Max Dual Fuel Burner Control Panel

floor mounted in basement Boiler Room

Page 15: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Piping work at the rear of Boiler No. 1

Installation of Skidmore, Model JVBF-42-500-402 Triplex Vacuum/ Boiler Feed Pump System

with 500 gallon steel receiver tank.

Page 16: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Front elevation of Skidmore, Model JVBF-42-500-402 Triplex Vacuum/ Boiler Feed Pump System

with 500 gallon steel receiver tank, and the two (2) 5 HP vacuum producer pumps mounted with

vacuum tank on top of steel receiver tank.

Side elevation of Skidmore, Model JVBF-42-500-402 Triplex Vacuum/ Boiler Feed Pump System

with 500 gallon steel receiver tank, and the three (3) 1½ HP condensate pumps mounted alongside

the steel receiver tank.

Page 17: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Front elevation of the Skidmore, Model VJS-202-65 Duplex Condensate Pump System which

includes the 65 gallon steel receiver set on existing concrete housekeeping pad, two (2) ¾ HP

condensate pumps, and a duplex motor control panel.

New gas piping connected to existing gas valve for connection to new boilers.

Page 18: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of boiler breeching with boiler flue connector observed

connected to breeching located in the basement Boiler Room

Combustion air dampers open as follows: Top half of dampers open during operation of Boiler No.

1, and bottom half of dampers open during operation of Boiler No. 2. Electronic actuation is

installed with tie-in to EMS remaining.

Page 19: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of new emergency eye wash manufactured by Encon Safety Products.

Installation of new mushroom type emergency boiler shut down break

glass station on inside wall of Boiler Room at the exterior means of egress.

Page 20: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Van Wyck Junior High School

ECM-5 Steam Trap Replacement

At the time of this inspection it was observed this work to be 95% complete. Work was inspected

and verified within the boiler room and at various locations throughout the school building where

accessible. Reference pictures as appropriate. All work within project design specifications.

Ameresco to provide an As Built of replaced/retrofitted steam traps.

Ret

Retrofit of F & T steam traps on the condensate side of steam boiler (Typical)

ECM-7 Infiltration Reductions

Work was reportedly 100% complete. Work was inspected and verified. It was observed due to each

existing door structure conditions multiple weather stripping materials were installed. Reference

pictures as appropriate. All work within project design specifications.

Weatherization of exterior door (second means of egress) existing Boiler Room.

Page 21: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Weatherization of exterior doors at Front Entrance of school building.

ECM 14 Boiler Replacements

At the time of this inspection it was observed that two (2) Unilux Bent Water Tube Boilers, Model

No. ZF 1200LS-FE3 were installed and set in place on new reinforced concrete housekeeping pads

with a Power Flame C-Max dual fuel burner, Model CMR9A-GO-30 with remote air compressor

with pulsation chamber and remote fuel oil pump connected to each boiler respectively. Integral to

the steam system providing heat to the building is the installation of 500 gallon boiler feed tank with

three (3) 1½ HP centrifugal pumps, and 110 gallon condensate tank with two (2) 2 HP condensate

pumps & two (2) 5 HP vacuum producer pumps including all appurtenances. Boiler venting was

reconnected to existing at points indicated as per the SED approved design (Refer to photos). The

insulation of the piping system was currently in progress. During this inspection the steam boilers

were operational, but currently not controlled through the building management system. The

contractor also provided a separate electrical panel dedicated to all boiler related equipment

(burners, remote fuel oil pump, existing duplex fuel oil pump, boiler feed, vacuum, and condensate

pumps). The contractor also provided labeling of all electrical conduit runs from the boiler burners

back to the dedicated electrical panel to assist in future service as necessary. Proper hangers and

supports were installed, and the contractor stated that upon completion of all boiler work all ceiling

penetrations where pipe hanger rods were mounted, the ceiling shall be repaired. . The steam

boilers have been commissioned with training remaining to be administered to the appropriate

District’s personnel.

Page 22: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

New gas meter rig with concrete bollards and fenced enclosure with main gas piping routed to the

boiler room horizontally on the roof above the kitchen cafeteria.

Routing of new gas piping from above the roof down and penetrated into boiler room.

Page 23: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Side elevation of Siemen’s Ventless Gas Train with gas piping connected on Boiler No. 2

Side elevation of Siemen’s Ventless Gas Train with gas piping connected on Boiler No. 1

Page 24: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of Siemen’s Ventless Gas Train located in the basement Boiler Room

Installation of new PowerFlame C-Max Dual Fuel Burner located

in the Boiler Room

Page 25: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of new PowerFlame C-Max Dual Fuel Burner Control Panel

floor mounted in Boiler Room

Rear elevation of Boiler No. 1 with pipe insulation installed to date.

Page 26: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

New dedicated Boiler Sub-Panel which currently provides power for Boiler No. 1 & No. 2, Oil Feed

Control Panel, Water Feed Control Panel, and the Condensate Pumps

Front elevation of the Skidmore, Model JVC-42-110-502 Duplex Vacuum/ Condensate Pump

System which includes the 110 gallon steel receiver set in existing pit with two (2) 2 HP condensate

pumps, two (2) 5 HP vacuum producer pumps and a duplex motor control panel.

Page 27: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Side elevation of the Skidmore, Model JVC-42-110-502 Duplex Vacuum/ Condensate Pump

System

Installation of new domestic hot water heater and heat exchanger with all piping insulated to date.

Page 28: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of Skidmore, Model VJSSM-402-500 Triplex Boiler Feed Pump System with all

components insulated to date.

Routing of the PVC vent piping for the Elite Direct Vent Hot Water Boiler

Page 29: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Termination of the PVC vent piping for the Elite Direct Vent Hot Water Boiler

Note: PVC termination at top of building elevation is venting out of flue gases, and PVC

termination below with T-fitting is for combustion air intake.

Installation of Elite Direct Vent Hot Water Boiler

Page 30: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of new Taco heat exchanger with insulation completed to date.

Installation of new emergency eyewash as manufactured by Encon Safety Products.

Page 31: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Exterior elevation of new combustion air louvers with dampers which currently open through

electronic actuation during boiler operations.

Combustion air dampers open as follows: In left hand photo, the far left damper opens and the top

half of center dampers open during operation of Boiler No. 1, and in right hand photo, the far right

damper opens and the bottom half of center dampers open during operation of Boiler No. 2.

Electronic actuation of combustion air dampers are currently interlocked with boilers respectively.

Page 32: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Brickerhoff Elementary School

ECM-7 Infiltration Reductions

Work was reportedly 50% complete. Work was inspected and verified. It was observed due to each

existing door structure conditions multiple weather stripping materials were installed. Reference

pictures as appropriate. All work within project design specifications.

James S. Evans Elementary School

ECM-4 Integrated and New Energy Management System

During this inspection, work was estimated to be 60% complete within building. Installation of

necessary wiring, conduit, raceways and relays were observed in progress. All work within project

design specifications. Reference pictures as appropriate.

Installation of new JACE located in Storage/Copy Room adjacent to main lobby of school.

Page 33: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

ECM-7 Infiltration Reductions

Work was reportedly 50% complete. Work was inspected and verified. It was observed due to each

existing door structure conditions multiple weather stripping materials were installed. Reference

pictures as appropriate. All work within project design specifications.

Weatherization of exterior doors (second means of egress) exiting Boiler Room.

Weatherization of side entrance doors.

Page 34: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Gayhead Elementary School

ECM-7 Infiltration Reductions

Work was reportedly 50% complete. Work was inspected and verified. It was observed due to each

existing door structure conditions multiple weather stripping materials were installed. Reference

pictures as appropriate. All work within project design specifications.

Sprayed seal method of roof/ wall joint (typical)

Myers Corners Elementary School

ECM-7 Infiltration Reductions

Work was reportedly 50% complete. Work was inspected and verified. It was observed due to each

existing door structure conditions multiple weather stripping materials were installed. Reference

pictures as appropriate. All work within project design specifications.

Weatherization of exterior doors at front entrance of school building.

Page 35: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Oak Grove Elementary School

ECM-1 Lighting System Improvements

Work was reportedly complete. Work was inspected and verified at multiple locations within the

school. Reference pictures as appropriate. All work within project design specifications.

Installation of new 6-lamp, 4-foot long, T8, 28W hi bay fixtures with integral occupancy sensor

located above school cafetorium.

Installation of new 6-lamp, and 3-lamp, 4-foot long, T8, 28W hi bay fixtures with integral

occupancy sensor located above school cafetorium.

Page 36: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of ceiling mounted exterior LED lighting fixtures located at loading dock/receiving area

of school building.

Installation of new 8’ long standard wrap fixture, 2 lamp normal power instant start electronic

ballast, white reflector, and (2) 4’ long 28 watt T8 lamps surface mounted at ceiling. (Typical for

majority of classrooms.)

Page 37: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Sheafe Road Elementary School

ECM-7 Infiltration Reductions

Work was reportedly 50% complete. Work was inspected and verified. It was observed due to each

existing door structure conditions multiple weather stripping materials were installed. Reference

pictures as appropriate. All work within project design specifications.

Weatherization of exterior doors at front entrance of school building.

Wappingers Junior High School

ECM-5 Steam Trap Replacement

At the time of this inspection it was observed this work to be 80% complete. Work was inspected

and verified within the boiler room and at various locations throughout the school building where

accessible. Reference pictures as appropriate. All work within project design specifications.

Ameresco to provide an As Built of replaced/retrofitted steam traps.

Page 38: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Roy C. Ketcham High School

ECM-1 Lighting System Improvements & ECM-2 Lighting Controls

Work was reportedly complete. Work was inspected and verified at multiple locations within the

school. Reference pictures as appropriate. All work within project design specifications.

Installation of combination exit sign/emergency lighting with (2) 5-watt MR16 lamps. (Typical exit

sign setup throughout school building).

Installation of new 8’ long standard wrap fixture, 2 lamp normal power instant start electronic

ballast, white reflector, and (2) 4’ long 28 watt T8 lamps surface mounted at ceiling. (Typical for

majority of classrooms.

Page 39: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

Installation of new 6-lamp, 4-foot long, T8, 28 watt hi bay fixtures with integral occupancy sensor

located above Gymnasium.

Installation of new 8’ long standard wrap fixture, 2 lamp normal power instant start electronic

ballast, white reflector, and (2) 4’ long 28 watt T8 lamps surface mounted at ceiling. (Typical for

majority of classrooms.

Page 40: ECG ENGINEERING, LLC · During this inspection, work was estimated to be 50% complete within building. Installation of necessary wiring, conduit, raceways and relays were observed

New LED lamps installed in existing fixtures above Auditorium main seating area.

ECM-7 Infiltration Reductions

Work was reportedly 100% complete. Work was inspected and verified. It was observed due to each

existing door structure conditions multiple weather stripping materials were installed. Reference

pictures as appropriate. All work within project design specifications.

Weatherization of exterior doors at front entrance of school building.

END OF INSPECTION REPORT