Easterly Tunnel Dewatering Pump Station June 19, 2012 Presented by: Michael Ritossa, MWH Anna Santino, MWH

Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

  • Upload
    phamthu

  • View
    217

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Easterly Tunnel Dewatering Pump Station June 19, 2012

Presented by: Michael Ritossa, MWH Anna Santino, MWH

Page 2: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

OUTLINE

• Project Technical Overview

• Pump Design and Operation

• Architectural and Pump Station Support Facilities

• Below Grade Facilities

• Geotechnical

2

Page 3: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Project Technical Overview

3

Page 4: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Combined Sewer Area

4

Consent Decree Requires 98% Capture of CSO Volume by 2036

Page 5: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

126 CSO Locations Throughout the Combined Sewer Area are Driving a Systematic Approach to Mitigate Overflows

5

Page 6: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Tunnel

Dewatering

Pump Station

Project Clean Lake – Easterly Service Area

6

Easterly Service

Area Includes:

• Five Tunnels

• Dewatering

Pump Station

• Ancillary

Consolidation

Sewers

• Regulator

Improvements

Page 7: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

DWIRS $64M ECT $200M DST $150M ETDPS $70M E. 140th $41M Substation $5M Euclid Creek PS $11M $541M

7

Village of

Bratenahl

City of

Cleveland

ETDPS

Easterly WWTP

ECT

The Nine Mile Site Will Be the Nexus of Seven Projects:

Page 8: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Nine Mile Project Site is Accessed from East 140th Street

8

E. 1

40

th S

tre

et

ETDPS

STAGING

AREA

ETDPS

PROJECT

SITE

Page 9: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

3D Rendering From Above

9

ECT Shaft 1

Electrical Substation

Page 10: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Northeast Corner

10

Page 11: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

ETDPS Project Technical Overview

1. Cavern Style Pump Station

• 160 MGD Firm Capacity

• 230 +/- Feet Deep

2. Receives Flows from 3 Storage Tunnels:

• Euclid Creek 61MG

• Dugway 51MG

• Shoreline 48 MG

3. Delivers Flows to Easterly Interceptor

• Gravity Delivery to Easterly WWTP

• Easterly Flow Management Important

11

Page 12: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Below-Ground Facilities

12

Page 13: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

ETDPS Programmed to be Complete Shortly After ECT is Activated and Ready to Accept Flows.

ETDPS must coordinate w/ ECT for final connections:

• Install Roller Gate

• Final Adit Connection

• Pump Testing and Commissioning 13

Project

2011 2012 2013 2014 2015 2016 2017

Euclid Creek Storage Tunnel

Tunnel Dewatering Pump Station

Dugway Storage Tunnel

Jan 2012 3 years 6 months duration Jun 2015

Apr 2011 4 years duration Apr 2015

Sep 2015 4 years duration

SHORT PERIOD TO FINALIZE WORK

Page 14: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Pump System: Pumped Flow & Hydraulic Design

14

Page 15: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Pump Design and Operation - Objectives

1. Meet Requirements of Consent Decree

2. Cost-Effective, Reliable System

3. Operability/Maintainability Considerations

• Collection/Tunnel System

• Pump Station

• Easterly

15

Page 16: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Pump Design and Operation - Components

16

1. Main Dewatering Pumps • 4 @ 40 MGD • 1 @ 20 MGD

2. Final Dewatering Pumps • 2 @ 10 MGD

3. Valves • Suction (Isolation)

A. Knife Gate Valves (5 Main Dewatering Pumps) B. Plug Valves (2 Final Dewatering Pumps)

• Discharge (Isolation/Flow Control) A. Hydraulically Operated Cone Valves

4. Emergency Sump Pumps

• 2 @ 1 MGD

Page 17: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

17

Key Hydraulic Elevations – Tunnel and Pump Station

System

Con

e V

alv

e -

Th

rott

ling

Top of Header Normally

Submerged at End of

Pumping Cycle

17

EL 412 (7.8 MG)

SHUT OFF

20/40 MGD

ECT/DST

STORAGE (MG)

INV EL 402.75

Throttled Operation

30 hours/yr @ 160 mgd

[0.2 BG volume]

10% of operating volume

Un-throttled Operation

303 hours/yr @ 160 mgd

[2 BG volume]

90% of operating volume

Tunnels will fill to HWL

EL. 575 about 3 times

in an average year

Page 18: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

18

Suction

Header

Final Dewatering Pumps

Main Dewatering Pump Suction Lines Emerg.

Sump

Pumps

Knife Gate

Valve

Plug Valve

Main Dewatering Pumps & Motors

ELEV. 369

ELEV. 389

Page 19: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

19

Separate Discharge Headers Were Provided to Maintain Minimum Velocities and Minimize Solids Accumulation

Page 20: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

20

Pump Room - Floors Added

Mezzanine

Upper Level

Lower Level

Page 21: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

21

Ventilation Designed to Avoid Hazardous Classification (i.e. Explosion Proof Devices)

• Occupied: 6 Air Changes

• Unoccupied: 6 Air Changes with 75% Recirculation

Page 22: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

22

Pump Room - Entire Structure Added

• Cast-in-Place Concrete for Shafts

• Shotcrete in Pump Room Walls and Roof

Page 23: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

23

Consideration was Given to Ensure Adequate Space for Maintenance and Repair

Pump Room Looking East – Elev. 369

Page 24: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

24

Pump Room Looking East - Elevs. 389 & 400

Page 25: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

25

Pump Room Looking West - Elevs. 389 & 400

Page 26: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

26

West End of Pump Room - Elevs. 389 & 400

Page 27: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Pump Design and Operation – CFD Model

27

Phase 1

The Original Model showed two of four pumps could experience adverse flow conditions of pre-swirl and axial velocity deviation.

Phase 2

The model was revised by adding straightening vanes and adding reducing type bends.

Page 28: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

28

CFD Modeling Confirmed Need For Flow Straightening Vanes

Flo

w D

irection

Vanes are Shaped to be “Self-cleaning”

Page 29: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Main Dewatering Pump Supports

29

Finite Element Analysis of Pump Supports were used for Vibration Analysis

Page 30: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Architectural and Pump Station Support Facilities

30

Page 31: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Architectural and Pump Station Support Facilities

Superstructure Contains: • Materials Handling Features • Electrical, Communications

and Control Rooms • Hydraulic Room • Maintenance-Related

Rooms • Rest Rooms

31

Page 32: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Pump Building Plan - Architectural

32

Page 33: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

33

Pump Building at Grade - Roof Removed

Page 34: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

34

Material Handling

5 Ton Jib Crane designed to lift mid sized items to at-grade floor level 609.0

12’x12’ roof hatch provides access for wheel or track mounted crane to move large equipment to and from cavern.

Page 35: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Below Grade Facilities

35

Page 36: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Below-Ground Facilities

36

Page 37: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

37

Access Shafts - Looking North

Page 38: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Below-Ground Facilities

38

Page 39: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Cavern and Access Shaft Dimensions

Cavern

Height

68 Ft

39

Primary Shaft Support in Overburden

Steel Liner Plate and Steel Ribs on 4” COC

Spacing.

Primary Shaft Support in Rock

Rock Dowels in 6’ x 6’ Pattern with 2” Thick Layer of

Shotcrete (WWM or Fiber-Reinforced) . 4” Thick

Shotcrete for 20’ Zone above Cavern Roof.

Page 40: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Geotechnical

40

Page 41: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

41

Access Shafts - Looking North

Soil

95 Ft

Rock

130 Ft

Page 42: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Current Principal Topics of Geotechnical Evaluation

• Permanent structural support

– Rock bolt lengths, diameter, spacing

– Shotcrete thickness, strength, reinforcing

• Long term stability of shale

– Slaking

• Long term durability of permanent support

– Corrosion of steel

– Deterioration of shotcrete

• Permanent drain system

– Drain spacing

– Encrustation prevention

42

Page 43: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

43

Rock Bolt/Dowel Pattern – Cavern Roof and Walls

5’ x 5’ Dowel

Pattern on

Walls

5’ x 4’ Bolt

Pattern on

Roof and

Haunches w/

Add’l Bolts @

Shafts

297 Dowels 487 Bolts 306 Dowels

Two 2” Thick Layers of Reinforced Shotcrete on

Walls with a Layer of Non-Reinforced

Smoothing Shotcrete on Lowest 10’

Two 3” Thick Layers of

Reinforced Shotcrete on

Roof and Haunches

Page 44: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

44

Rock Dowel Pattern – Cavern Floor

270 Dowels

5’ x 5’ Dowel

Pattern on

Floor

Page 45: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

45

Raw Water Tunnel

Page 46: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

46

Page 47: Easterly Tunnel Dewatering Pump Station Tunnel Dewatering Pump Station June 19, ... • Permanent structural support –Rock bolt lengths, diameter, ... Two 2” Thick Layers of Reinforced

Questions?

49