p o r t me t r o v a n c o u v e r.c o m June 19, 2014 EAST VANCOUVER PORT LANDS COMMITTEE

EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

June 19, 2014

EAST VANCOUVER PORT

LANDS COMMITTEE

Page 2: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Agenda

• South Shore Corridor Project

• Traffic Control - Commissioner Street Staging Area

• Centerm Expansion Project

• Columbia Containers Updates:

• Replacement Transloading Facility & Storage

• Sheet Pile Retaining Wall Realignment

• Installation of Modular Office

• New Main Office Installation

• Saltworks Technologies – Temporary Storage Location

• Port Metro Vancouver Foreshore Stabilization Work at Columbia Containers

2

Page 3: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

2901 Commissioner Street Staging Area –Traffic Control Options

• Safety issues with flaggers necessitates utilizing either dynamic message signs (DMS) or traffic control lights

• To control vehicles entering Staging Area, a single two text row DMS facing east will be installed

• Two options to control vehicles leaving the 15-Lane Staging Area

• Recommend the traffic control lights, as they will have less visual impacts

• DMS and traffic control lights not lit when not in use

• Port construction permit required to undertake this work; have not yet applied

3

Page 4: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

2901 Commissioner Street Staging Area – Option 1 Traffic Control

4

Page 5: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

2901 Commissioner Street Staging Area – Option 2 Traffic Control

5

Page 6: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Centerm Expansion Project

6

Page 7: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Centerm Expansion Project

7

Page 8: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Centerm Expansion Project

• Container traffic will more than double over next 15 years

• Centerm, operated by DP World, handles 1/5 of Port's annual container cargo

• Decision to close Ballantyne Cruise Terminal and consolidate cruise operations at Canada Place provides opportunity to expand Centerm to meet demand

8

Page 9: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Centerm Expansion Project

• Expand from current 900,000 TEU capacity to a possible 1.8 million TEUs

• Over the next year, Project Team will develop Preliminary Design Options

9

Page 10: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Centerm Expansion Project

10

1. Expansion of Centerm Terminal

2. Waterfront Access

3. Stewart Street Overpass

Page 11: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Centerm Expansion Project

• The Preliminary Design Phase will continue until mid 2015

• We are committed to fulsome consultative process with the community and other stakeholders prior to finalizing the design

• Construction could commence in late 2016

11

Page 12: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Project Details:

• One year temporary lease;

• Storage of four empty containers (not stacked, containers next to each other).

Saltworks Technologies

12

Page 13: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Port Metro Vancouver Foreshore Stabilization Works at Columbia Containers

Port Metro Vancouver currently reviewing an application from PMV

Engineering for a Project Permit.

Project Details:

• Port Engineering-led initiative (works are planned to facilitate Columbia Containers’ office relocation);

• Approximately 110m section of shoreline to be repaired (adjacent to the former Ocean Fisheries site);

• Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2;

• Vegetation and existing material along the shoreline impeding rock placement to be removed.

Project timelines:

• Pending approvals, anticipated start date – August 18, 2014 and completion - August 29, 2014.

13

Page 14: EAST VANCOUVER PORT LANDS COMMITTEE · • Approximately 1,000m3 rock to be transported to the site and spread over a footprint of 950m2; • Vegetation and existing material along

p o r t m e t r o v a n c o u v e r.c o m

Port Metro Vancouver Foreshore Stabilization Works at Columbia Containers

14