This is a slideshow presentation shown to the Bellevue City Council on Sept. 22, 2014, detailing Sound Transit's tentative traffic maintenance plan when East Link light rail construction begins in the city.
Citation preview
East Link Monthly Project Update
Bellevue City Council
September 22, 2014
1
Tonights Agenda
Estimated Project Schedule
Project Permitting
Maintenance of Traffic During Construction
Operation and Maintenance Satellite Facility (OMSF) Update
2
East Link Estimated Schedule
3
Early Nov 2014 South Bellevue Final Design Open House
Dec 2014 East Link Baseline Milestone
Q2 2015 Downtown Final Design Open House
Q4 2015 Overlake-Redmond Final Design Open House
2015 Estimated Construction Early Work - Utility Relocation 136th Pl NE (OPL) - Utility Relocation 112th Ave NE (City)
Early Q3 2015
Late Q1 2016
Estimated Construction - Tunnel (E330)
Q4 2015 Q4 2016 - South Bellevue (E320)
Q1 2016 Q1 2017 - Bel Red (E340)
Q1 2016 Q2 2016 - Redmond-Overlake (E360 Design-Build)
Q2 2017 - Downtown (E335 GC/CM)
Light Rail Permitting
Submitted Permits
Shoreline Substantial Development
Shoreline Variance
Bel-Red Design and Mitigation
South Bellevue Design and Mitigation
4
Light Rail Permitting Citizen Advisory Committee (CAC)
Bi-monthly meetings
Pre-development review advisory documents All segments
Final advisory document pending for Bel-Red
Currently reviewing South Bellevue
Final advisory document for South Bellevue end of 2014, early 2015
Downtown/East Main and 120th Station permits submitted later this year
5
Maintenance of Traffic
Begun meeting with interested community groups and organizations
Engaging in high level discussion of current construction traffic management concepts
Understand additional community concerns
6
DRAFT 09/19/2014 7
SR 520
I-90
14
8th
Ave
NE
112th Ave SE (SE 15th to SE 8th)
Bellevue Way
112th Ave SE (SE 8th to Main St)
I-405
110th Ave NE
NE 8th St & 116th Ave NE
Bel-Red Overlake/Redmond
NE 8th St
16
4th
Ave
NE
Maintenance of Traffic
Bellevue Way E320
Goal: Maintain 2 lanes of traffic in peak direction
Park & Ride closed during construction (approximately 48 to 60 Months)
1 Lane each direction with a reversible lane (approximately 36 to 48 Months)
12 to 15 weekend full closures
I-90 westbound night closures
8
I-90
DRAFT 09/19/2014
Maintenance of Traffic
112th Ave SE (SE 15th to Se 8th) E320
Goal: Minimize traffic diversion to 108th Ave SE and Bellevue Way
Maintain 1 lane each direction during construction
Temporary road 1 Lane each direction (18 months)
112th Ave SE (SE 8th to Main St) E320
Goal: Minimize construction truck traffic
Off-peak lane closures
9
11
2th
Ave
SE
Main St.
Be
llevu
e W
ay
DRAFT 09/19/2014
Maintenance of Traffic
110 Ave NE E 330/E335 Goal: Minimize impact to business access Two 1-month full closure of 110th Ave NE
south of the intersection Two 3-month lane closures (NE 4th to NE
6th (considering total closure between City Center 2 and NE 6th)
SB lanes from NE 2nd to NE 3rd closed for duration of construction
NE 2nd Pl closed for duration of construction
I-405 E335 Overnight HOV ramp closures Overnight lane closures NE 8th St & 116th Ave NE E335 Goal: Minimize impact to business access Overnight street closures Off-peak lane closures
10
I-4
05
Main St
NE 8th St
11
6th
Ave
NE
DRAFT 09/19/2014
Maintenance of Traffic
Goal: Minimize impact to businesses Lane closures on NE 20th, 130th, 132nd, 136th, and NE 16th (Spring Blvd.) Intersection closure @ NE 20th/136th PL NE, NE 16th St (Spring Blvd.)/132nd Ave. NE
and NE 16th St (Spring Blvd.)/136th PL NE Overnight closures at various locations along NE 16th St (Spring Blvd.) Full closure on NE 16th St (Spring Blvd.) from 132nd to 136th PL NE (6 to 9 Months) Full closure on 136th Pl NE from NE 16th St (Spring Blvd.) to NE 20th St (One Month)
Advanced Utility Relocation (4 to 6 weeks) 11
NE 20th St
13
0th
Ave
NE
13
2n
d A
ve N
E
NE Spring Blvd
Bel-Red E340
DRAFT 09/19/2014
Maintenance of Traffic
12
Overlake/Redmond E360
Overnight Street/Lane Closures
NE 24th St
14
8th
Ave
NE
14
0th
Ave
NE
NE 20th St
DRAFT 09/19/2014
Maintenance of Traffic
OMSF Update
Sound Transit Board action July 24, 2014
BNSF site identified as preferred
Direction to Sound Transit staff
Design charrette September 5, 2014
1st Stakeholder workshop September 18, 2014
2nd Stakeholder workshop October 9, 2014
13
Questions
14