Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
EAST LEAKE QUARRY – REMPSTONE SAND AND
GRAVEL EXTENSION – PLANNING STATEMENT
2014
1
CEMEX UK MATERIALS LTD
APPLICATION TO CONSOLIDATE PREVIOUS PLANNING PERMIS SIONS AND EXTENSION OF
EXISTING QUARRY INVOLVING THE EXTRACTION OF SAND AN D GRAVEL WITH RESTORATION
TO AGRICULTURE AND CONSERVATION WETLAND, RETENTION OF EXISTING AGGREGATE
PROCESSING PLANT, SILT LAGOON AND ACCESS / HAUL ROA D
REMPSTONE, EAST LEAKE QUARRY
August 2014
VOLUME 1 – PLANNING STATEMENT
Submitted to : Nottinghamshire County Council
Trent Bridge House
Fox Road
West Bridgford
Nottingham
NG2 6BJ
Prepared by: CEMEX UK Operations Ltd
CEMEX House
Evreux Way
Rugby
CV21 2DT
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
2
Report Prepared by National Reserves Department Cemex House Evreux Way Rugby CV21 2DT Report Reference: 00_12_ELE_699_PS_KHH_250214_rempstone Report Status; Final Approval SIGNATURE DATE
QUARRY MANAGER
REGIONAL OPEPERATIONS MANAGER
ESTATES MANAGER
PLANNER
Revisions Record: Issue Report
status Comments Author Approved Date
2 Draft Amended MOW
Format History Policy Production rate
KHH 29/4/2015
3 Final Draft Amend ROW Amend Restoration – permissive path Amend – MOW permissive ROW routes Dust
KHH 23/5/2014
4 Final Draft Amend MOW KHH 16/06/2014 5 Final Draft Description KHH 23/06/2014 6 Final Draft Page 3 – updated page numbers, contents
/ appendix subdivided topographical plans and added Extraction Area plan Page 7 – Amended plan numbers (13_C007_ELEK/P5/689/8A & P2/968/9/6a) and added plan ref; P4/689/4C and Quarry Survey Amended Plan ref on application form Amended Appendix ref on pages; Page 14 (1.5.7), Page 15 (1.6.5), Page 19 (1.6.17), Page 26 (1.7.17 & 1.7.18), Page 28 (1.8.0), Page 35 (1.9.1) Page 37 (1.10.6)
KHH 2/7/2014
7 Final Draft Application date, Soil Handling Strategy New plan P5/689/12 (APPENDIX 25)
KHH 21/08/2014
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
3
The following plans have been UPDATED; P5/689/10 replaced by P5/689/10A, 13_C007_ELEK_007, 13_C007_ELEK_001, 13_C007_ELEK_004, 13_C007_ELEK_006_A, 13_C007_ELEK_012, 13_C007_ELEK_005_B, P5/689/8A, P5/689/9, Number of pages / Contents Landscape, restoration and aftercare (Appendix 16)
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
4
PLANNING STATEMENT – CONTENTS
PAGE
PART ONE (A) – DETAILS OF THE APPLICATION
1.1.0 INTRODUCTION 6
1.2.0 SUBMITTED DOCUMENTS / APPLICATION SUMMARY 8
1.3.0 ENVIRONMENTAL ASSESSMENT PROCESS 10
1.4.0 SITE LOCATION AND DESCRIPTION 11
1.5.0 PLANNING HISTORY 14
1.6.0 THE PROPOSED DEVELOPMENT 16
1.7.0 METHOD OF WORKING 24
1.8.0 RESTORATION 29
1.9.0 AFTERCARE 36
1.10.0 SUMMARY OF MAIN ENVIRONMENTAL & SOCIAL EFFECTS 37
PART TWO (B) – PLANNING POLICY CONSIDERATIONS
2.1.0 INTRODUCTION 41
2.2.0 THE NEED FOR THE DEVELOPMENT 41
2.3.0 NATIONAL POLICY 45
2.4.0 LOCAL POLICY 53
PART THREE (C) – SUMMARY
3.1.0 BENEFITS OF THE DEVELOPMENT 73
3.2.0 STATEMENT OF COMMUNITY INVOLVEMENT 73
3.3.0 CONCLUSION 74
APPENDICES
1 APPLICATION FORMS, LANDOWNER AND AGRICULTURAL HOLDINGS
CERTIFICATES
2 LOCATION PLAN (13_C007_ELEK_007)
3 SITE PLAN (13_C007_ELEK_001)
4 EXTENSION AREA (13_C007_ELEK_012)
5 METHOD OF WORKING (13_C007_ELEK/P5/689/8A)
6 RESTORATION PLAN – REMPSTONE (13_C007_ELEK/P5/689/9)
7 COMPOSITION RESTORATION OF WHOLE SITE (P5/689/10A)
8 LINGS FARM AND JENKS RESTORATION (P2/689/9/6A)
9 BURTONS RESTORATION (P4/689/4C)
10 ORIGINAL INTERMIN RESTORATION PLAN – EAST LEAKE QUARRY
(P2/689/13B)
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
5
11 TOPOGRAPHICAL SURVEY (OCT 2007) (REM_SUR_PW_1007.PDF)
12 QUARRY SURVEY (DEC 13) (EAL_MOD_PW_1213)
13 AREAS OF RESTORATION, BUNDING, SOIL STRIPPING
(EAL_BAP_PW_1213)
14 WATER LAGOON SYSTEM (ELEK_PLA_689_CAW_261112)
15 RIGHT OF WAY DIVERSION (13_C007_ELEK_005B)
16 LANDSCAPE, RESTORATION AND AFTERCARE SCHEME
17 GEOLOGY REPORT AND PLANS
18 SOIL HANDLING, MACHINERY AND PROCEDURES
19 EAST LEAKE PLANNING HISTORY (13_C007_ELEK_004)
20 LAND IN AFTERCARE – (13_C007_ELEK_003)
21 ANCILLARY OPERATIONS
22 BURTON METHOD OF WORKING P4/689/3E
23 106 HEADS OF TERMS
24 SURFACE WATER SCHEME
25 LANDSCAPING TO ALL SAINTS CHURCH – P5/689/12
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
6
1.0 PART ONE (A) – PLANNING STATEMENT
DETAILS OF THE APPLICATION
1.1 INTRODUCTION
1.1.2 The following planning statement has been prepared by CEMEX UK Operations Ltd (Cemex shall
be hereafter referred to as the ‘Applicant’) in support of this planning application for proposed
sand and gravel extraction on land known as Rempstone which shall form part of East Leake
Quarry as an extension to the existing quarry on adjacent land, with restoration to agriculture,
water features and woodland conservation.
1.1.3 The Applicant, is a leading global producer of cement, concrete and other building materials and
operates a number of quarries in the East Midlands and East Anglia Region. These operations
are focused on the extraction of sand and gravel reserves for the production of concrete and
mortar to local markets. The Applicant’s existing quarry at East Leake is a key strategic site
ideally situated to serve the south Nottinghamshire and north Leicestershire markets with
aggregates.
1.1.4 The proposed development is to form an extension to the applicant’s existing operations at East
Leake Quarry and consists of the extraction of approximately 1.78million tonnes of sand and
gravel over a period of approximately 10-12years from an area of agricultural land covering
approximately 27.5 hectares. The land would be restored to agriculture and water feature and
woodland conservation. This application would consolidate existing permission at East Leake
Quarry providing a single permission for the entire site.
1.1.5 The restoration concept for the site has been carefully designed to ensure that the final landform
compliments the existing restoration scheme for East Leake Quarry and takes into consideration
potential for bird strike and ecological enhancement. Cemex has developed experience over
many years in the restoration and management of land for a range of after-uses such as nature
conservation, recreation and woodland management. Notable examples of Cemex restoration
include Lackford Lakes in the County of Suffolk and Attenborough Nature Reserve in
Nottinghamshire. Restoration of these sites to a series of lakes have led to the creation of
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
7
regionally and nationally important nature reserves, now managed by Suffolk Wildlife Trust and
Nottinghamshire Wildlife Trust respectively.
1.1.6 The Company commissioned this application in 2012 taking into consideration baseline
information and operations at this time. Through the production of this application the Company
has amended the scheme taking into consideration operation, recent planning permissions,
technical data and consultee comments. The final scheme as presented within this application
provides a balance of operational efficiency and environmental and social protection and where
possible enhancement.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
8
1.2 SUBMITTED DOCUMENTS
1.2.1. The following documents comprising the planning application have been submitted to
Nottinghamshire County Council, the determining planning authority:
• Planning Statement (Parts 1, 2 and 3)
• Application forms and landowner and agricultural certificates (Appendix 1)
• Plans, correspondence and supporting technical information (Appendix 2-24)
1.2.2 The application plans consist of the following:
• LOCATION PLAN - - 13_C007_ELEK_007
• SITE PLAN - 13_C007_ELEK_001
• EXTRACTION AREA -13_C007_ELEK_012
• METHOD OF WORKING - 13_C007_ELEK/P5/689/8A
• REMPSTONE RESTORATION PLAN - 13_C007_ELEK/P5/689/9
• OVERALL COMPLEX RESTORATION - P5/689/10A
• LINGS RESTORATION - P2/689/9/6A
• BURTONS RESTORATION PLAN - P4/689/4C
• LINGS INTERIM RESTORATON - P2/689/13B
• TOPOGRAPHICAL PLAN - REM_SUR_PW_1007.PDF
• QUARRY SURVEY PLAN - EAL_MOD_PW_1213
• AREAS OF RESTORATION, BUNDING, SOIL STRIPPING – EAL_BAP_PW_1213
• ANCILLARY OPERATIONS - 13_C007_ELEK_006_A
• WATER LAGOON SYSTEM - ELEK_PLA_689_CAW_261112
• RIGHT OF WAY DIVERSION - 13_C007_ELEK_005B
• PLANNING APPLICATION HISTORY - 13_C007_ELEK_004
• AFTERCARE PLAN - 13_C007_ELEK_003
• BURTONS METHOD OF WORKING - P4/689/3E
• LANDSCAPING TO ALL SAINTS CHURCH - P5/689/12
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
9
APPLICATION SUMMARY
1.2.3 Extraction area = 27.5ha
Sand and gravel extraction = 1.78million tonnes
Life of the site = 10-12 years
Production rate = 150,000- 180,000 tpa
Vehicle movements = 100 movements per day (50in/ 50out)
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
10
1.3 THE ENVIRONMENTAL ASSESSMENT PROCESS
1.3.1 Environmental Impact Assessment (EIA) is an important statutory procedure for ensuring that the
likely effects of a proposed development on the environment are fully understood and are taken
into account before the development is allowed to go ahead. The EIA process is designed to
identify any potential adverse environmental impacts and if appropriate, recommend the use of
mitigating measures or monitoring programmes that can be incorporated into the design of the
proposal to achieve an environmentally acceptable development. The EIA process enables the
Local Planning Authority, consultees and the general public to reach an informed opinion as to
the environmental consequences of the proposal. The findings of the EIA, together with any
mitigation measures, are a material consideration in determining whether or not planning
permission should be granted for the development.
1.3.2. The application site itself has been assessed internally to determine if an environmental
assessment is required. The proposed development is Scheduled 1 development under the
Town and Country Planning (Environmental Impact Assessment) (England and Wales)
Regulations 2011. The development is Schedule 1 as the proposed extraction area shall exceed
25hectares and shall be additional to the existing East Leake Quarry. It is therefore concluded
that an environmental statement is required under the Town and County Planning (Environmental
Impact Assessment) (England and Wales) Regulations 2011 and an Environmental Statement
has therefore been submitted with the planning application.
1.3.3 An Environmental Statement has been produced to accompany this planning application and can
be found in Volume 2 and Non Technical Summary within Volume 3.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
11
1.4 SITE LOCATION AND DESCRIPTION
1.4.1 Cemex UK Materials Ltd operates the existing mineral extraction and processing plant at East
Leake Quarry. The quarry (including proposed extension) is located approximately 1km south
east of East Leake Village and 300m west of Rempstone Village. Nottingham City is located
approximately 15km to the north, Derby City is located 17km to the north west and Loughborough
Town 4km and Leicester City 14km to the south (see Appendix 2 – location plan reference
number 13_C007_ELEK_007). The Ordnance survey national grid reference is SK 564 247. The
site is located within the County of Nottinghamshire and District of Rushcliffe. The site is located
in close proximity to the M1, M42, A46 and A6 all leading off the A6006.
1.4.2 The application site, outlined in red, covers a total of approximately 93ha although the proposed
extraction area would cover approximately 27.5ha. The proposed extraction area consists of one
relatively flat, rectangle shaped agricultural parcel separated from the existing site by a mature
hedgerow which runs north to south.
1.4.3 The field is bound to the south by the A6006 (Melton/ Ashby Road), to the west by Jenks sand
and gravel extraction (8/12/01488/CMA). Rempstone Church, Clifton Lodge, Beech Tree Lodge
and Loughborough Road bound the site to the east. Sheepwash Brook bounds the site to the
north in addition to pockets of woodland planting. The southern bound includes mature hedgerow
and trees. There are two existing agricultural accesses to the south on to the A6006.
1.4.4 The proposed extraction area is located 200m to the north of Lings Farm and 150m from
Rempstone Hall (both separated by the A6006). Rempstone Church and Clifton Lodge bound the
site to the south east. Beech Tree Lodge bounds the site to east. There are various properties
located to the south on the opposite side of the A6006 including Farm Cottage, Rempstone Hall
Farm and East Lodge. Oaklands Farm and 4 Loughborough Road look down upon the site from
the top of the wolds approximately 130m to the north of the extraction area.
1.4.5 As stated above the application site is currently in agricultural arable use. The extraction areas
agricultural land classification can generally be classified as Grade 2-3b agricultural land with the
majority of the site subgrade 2 and 3a and with small patches of subgrade 3b which complements
the surrounding agricultural classification.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
12
1.4.6 The topography of the application area and surrounding landscape is generally flat with a small
undulation to the north east typical of the Leicestershire and Nottinghamshire Wolds. Due to the
topography and existing hedgerow screening along the A6006 reduces views into the proposed
extension area although Oaklands Farm, The Oaklands and Beech Tree Farm have more
prominent views into the site. The main vantage point is the Public right of way which runs
across the site, Oaklands Farm and The Oaklands due to the topography and also Beech Tree
Lodge to the east.
1.4.7 There is one right of way crossing the proposed extraction area which runs north west to south
east existing near Rempstone Church on the A6006. There is a bridleway crossing the previous
extraction area known as Jenks.
1.4.8 The main East Leake Quarry aggregate processing plant, reception offices, silt lagoons and
stocking area lies towards the northern boundary within the centre of the application boundary.
The internal access road between the extraction area and plant site shall run through previous
extraction area known as Jenk’s. A small gap would be made in the mature hedgerow into
Rempstone (and shall be gated) providing access from the existing plant site through into the
proposed extraction area.
1.4.9 Access to East Leake Quarry from the public highway is via an existing haul road leading onto
Rempstone Road. The site has a designated traffic route along the Rempstone Road leading
onto the A6006. All traffic is strictly controlled and restricted to this route in order to avoid passing
through the village of East Leake.
1.4.10 The quarry is well placed to serve local building suppliers and concrete plants in Nottinghamshire,
Leicestershire and East Midlands.
1.4.11 The site is located within East Midlands Aerodrome consultation area (arrival path and holding
area). The site is not located within a National Park or Area of Outstanding Natural Beauty. The
site is not located within 2km of a Special Area of Protection, Site of Special Scientific Interest,
Ramsar or Ancient Scheduled Monument. The site is located within 1km of a registered national
Park and Gardens – Stanford Hall. Stanford Hall is a grade II listed building and set within 113ha
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
13
of registered park and gardens. The landscape park dates back to the 18 Centuries with
additional features added in the 19 and 20 Centuries.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
14
1.5 PLANNING HISTORY
1.5.1 Mineral extraction has been sought in the East Leake area since the mid eighties with the Local
Minerals Planning Authority refusing two applications mainly due to the lack of need and being
contrary to planning policy. Planning permission was first granted in 1991 after the company
appealed the last planning refusal (application reference number 8/J1/85/1141/P). The planning
approval was subject to 37 planning condition and low level restoration to agriculture and a lake.
The original planning permission included the construction of the existing aggregate processing
plant. This permission area is known as Lings.
1.5.2 In 2009 planning permission was issued (reference 8/07/02187/CMA) for an additional three
phased extension to the east of the main quarry. The 2009 planning permission was granted
contrary to being an un-allocated site due to its small scale, duration and location to the local
markets. Planning permission 8/07/02187/CMA has been amend to extend the period of
extraction for a further 12months to accommodate increased reserves and slight economic down
turn (8/12/01488/CMA). This permission area is known as Jenks
1.5.3 In 2013 planning permission was issued (reference 8/11/00157/CMA) for an additional 4 phased
extension to the south west of the existing plant site. Extraction commenced September 2013
and shall be completed within 3 years (September 2016). This permission is known as Burtons
1.5.4 The existing processing plant, silt lagoons and haul road has the benefit of planning permission
until 30 September 2017 (PP8/14/00341.CMA) (Lings).
1.5.5 This planning application to extract material from land known as Rempstone shall seek to
continue to utilise the existing plant site and proposes to retain the void within Jenks as a means
of silt disposal. The use of the existing plant is considered the most sustainable and
environmentally acceptable option as the plant is established and screened. It is proposed that
Rempstone would commence during final phase of Burton’s permission to ensure there is a
continuation of mineral extraction at East Leake Quarry.
1.5.6 The proposed extension area is not allocated within the Nottinghamshire Minerals Local Plan as a
future mineral site. The proposed extension area has been put forward as part of the emerging
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
15
Local Development Framework. No formal conclusion has been undertaken determining if the
proposed extension area is a suitable allocated site for future mineral working. It is considered
that the proposed extension provides a strategic release of sand and gravel to the south of the
County and provides opportunity of conservation restoration. The Rempstone extraction area is
considered a logical progression of mineral working within the East Leake area ensuring the
release of quality reserves prior to quarrying operations ceasing in this area.
1.5.7 The Company, in seeking to continue extraction of sand and gravel and utilise existing
infrastructure on site. Plan ref:13_C007_ELEK_004 with the proposed extraction area illustrated
on plan 13_C007_ELEK_012 Appendix to this application illustrates the permission boundaries
related to East Leake Quarry.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
16
1.6 THE PROPOSED DEVELOPMENT
1.6.1 This proposal is for the extraction of approximately 1.78 million tonnes of sand and gravel from an
area of approximately 27.5 hectares split into 6 phases. Following extraction the site will be
restored at a lower level incorporating agriculture, lakes and woodland conservation which shall
integrate and complement permitted restoration schemes at East Leake Quarry and established
wildlife habitats.
1.6.2 The proposal involves the continued use of the existing access to the public highway onto
Rempstone Road, reception facilities, aggregate processing plant, and the silt and freshwater
lagoons.
Geology
1.6.3 Geological investigations have indicated that the proposed extraction area contains
approximately 1.78 million tonnes of sand and gravel at an average thickness of 4.96 metres
although maximum depth could be over 9m. The Geological Report is located in Appendix 17
within the Planning Statement.
1.6.4 The original geological investigation looked at the whole agricultural field and estimated 2.20
million tonnes over an area of approximately 30ha. The Company has used this geological data
as the foundations and starting point of this application. The extraction area has been influenced
by the geological data, high clay spots and possible interburden layers, hydrology, noise, dust
and ecological data. The final extraction boundary takes into consideration necessary standoff,
for example highways 30m from the A6006, electricity line, Sheepwash brook (15m), Planting
(root protection areas of 3-10m). The final extraction boundary for Rempstone is identified within
the Method of working plan (13_C007_ELEK/P5/689/8A).
1.6.5 The final extraction boundary and reserve of 1.78mt would enable extraction to continue at the
quarry for an additional 10-12 years. The proposal would be worked in 6 principle phases, as an
extension of the existing quarry, at a rate of approximately 150,000 to180,000 tonnes per annum:
ultimately the extraction rate would depend on the strength of the demand from the local market.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
17
1.6.6 East Leake sand and gravel reserve is of a glacial origin and has bedrock of mercia mudstone
group of Triassic age which consists of predominantly of mudstone with siltstones and thin
limestones. The Geological report summaries two investigations in 1992 and 2007 and takes into
consideration workings undertaken on site and it is concluded that the reserve will continue to
have a high level of fines of 20% although this could drop to 7% or increase to 30% this is due to
a high level of clay and silt within the deposit. The anticipated soil and overburden levels vary
over the geological search area from 0.2m to 13m with an average of 3.07m providing an overall
figure of approximately 1mt to be removed and used as restoration material. The geological
report identified a significantly deep overburden section along the northern boundary towards
Sheepwash Brook which also holds high level of silty fines. It has been concluded that the
northern area and south east corner be excluded as they are economically unviable to work due
to high levels of overburden/ clay and silty fines. The overall mineral thickness ranges from 0-
9.95m with an average of 4.96m, although reserves in Jenks adjacent did appear to reach nearly
12m in depth. The mineral quality should produce an average of 37.8% gravel, 49.1% sand and
13.1% fines. The deposit has varied in quality which has led to the larger phases that can be
worked in two benches. Due to the varied quality the Company proposed to commence extraction
in Rempstone whilst completing the final phase of Burton’s.
Sequence of extraction
1.6.7 The proposed extension would commence during the final phase of extraction within the
permitted area known as ‘Burtons Land’. Access to the proposed extension area would be
gained by the internal haul road through a small section of hedgerow along the western boundary
with Jenks Land. Internal traffic signs and routing would be introduced ensuring right of way to
external HGV vehicle movements and rights of way users. The proposed extension would not
increase annual output from the site only increase the duration of mineral extraction at the site by
a maximum of 12 years.
Method of Extraction
1.6.8 It is proposed for the site to be dewater via a pump, then excavate the mineral using a 360
degree hydraulic excavator and transporting the mineral to the existing processing plant at the
quarry via dumper truck. It is proposed that mineral extraction would be worked in regular
campaigns throughout the year to meet demand. Raw material would be stockpiled within the
existing plant site stocking area, for processing and sale. The pump for dewatering will be
located along the western boundary and kept to the north were possible to reduce noise impact to
sensitive receptors located on A6006 and A60, the pipe would travel through the internal access
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
18
point and buried under the bridleway linking into the existing surface water management system
of Jenks and Lings which would be utilised and retained for the life of the processing plant as
shown on plan ELEK_PLA_689_CAW_261112.
1.6.9 The general approach to the extraction of sand and gravel within Rempstone would be to peg out
the extraction area, fence any hedgerow and Rights of Way as necessary. Clear any vegetation,
strip soils and overburden which would be principally stored in bunds along the southern and
eastern boundary or direct placement to assist restoration. The mounds would provide acoustic
and visual screening. Archaeological investigation would be implemented in accordance with an
approved WSI during soil stripping. It is proposed each face will be worked to an angle of 1 in 2.
A surface water trench shall be created along the southern boundary as necessary to catch water
from the soil bunds to prevent water travelling on the A6006.
1.6.10 Overall approximately 1mt of overburden / clay including topsoil’s would be removed as part of the
extraction process which would be used as part of the sites reclamation.
Production Rate
1.6.11 Extraction and processing is dictated by market demand and taking into consideration the last 5
years sales the Company anticipate a production rate of between 150,000 – 180,000tpa.
Equipment Required
Processing Plant
1.6.12 The static aggregate processing plant would be retained within the existing quarry plant site
complex for the crushing, washing and grading of the excavated sand and gravel.
1.6.13 The existing fresh and small silt water lagoons would similarly be retained in order to allow for
settlement of the silt fraction washed from the sand and gravel, and also to supply fresh re-
circulated water to the plant.
1.6.14 The existing finished product stockpile area would also be retained, as will the workshop building,
weighbridge, site office/messroom and car park area.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
19
Mobile Plant
1.6.15 A number of elements of mobile plant are required, namely:
i) Soil Stripping and Handling – soil and overburden would be removed using a hydraulic
excavator with dump trucks being used to take the material to either create a temporary
storage/screen bund to place the soil directly on to a previously worked area for final
restoration.
ii) Mineral Extraction / Restoration – this would entail the use of a 360o excavator and
wheeled loading shovel working on benches set below ground level. The shovel would
also be used to load the dumper. A dozer and shovel will place restoration material to
achieve permitted contours.
iii)Lorry Loading – a second wheeled shovel would be employed within the plant area to feed the
plant with raw material for processing, load lorries with the finished products and general
stockpile handling.
All of this plant currently operates in this manner within the existing extraction area.
Soil Handling
1.6.16 A 360 degree back actor excavator and a dumper truck will be used in the soil stripping
operations. The storage bund will be formed by the loose placement of stripped soils by the
dumper and shaped using a bulldozer with low pressure tracks. Topsoil /overburden/ clay will be
stored separately with the bunds being a maximum of 3 and 5m high and seeded and maintained
until replacement.
1.6.17 All personnel involved with the soil stripping and restoration of the extraction area will be given
specific instructions from the Quarry Manager with regard to the importance of conserving the soil
resource and not causing inadvertent loss or damage. No soils will be moved in wet weather or
when ground conditions are not suitable. Details of soil handling, machinery and procedures is
set out in Appendix 18.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
20
Hours of Operations
1.6.18 It is proposed to continue to operate the quarry on the same hours and days as currently
permitted which are:
07.00 – 19.00 Monday to Friday
07.00 – 13.00 Saturdays
And no such operations shall be carried out on Sundays or Public (bank) Holidays.
Access / Vehicle Movements
1.6.19 As stated above the proposal will continue to use the main site access onto Rempstone Road /
A6006. The traffic movements associated with the proposal would continue at approximately 72
movements per day with a maximum of a 100 vehicle movements as previously conditioned. The
proposed extension will only result in the continuation of historic production levels. As a result
traffic movements associated with these operations will remain the same as currently experienced
at the permitted quarry site. The access route to the quarry was designed with this level of traffic
in mind and the Company strictly adheres to the designated access route and agreed practices.
The type of vehicles which enters the site varies greatly depending on the requirement of each
customer. Typically the average vehicle is a two tonne truck with the largest vehicles to visit the
site having a twenty tonne capacity. Additional vehicles will be small private vehicles of quarry
and company staff.
1.6.20 Existing signs at the quarry entrance instructs all HGV drivers to turn left only out of the site this
shall be maintained throughout the life of the development and all drivers of HGVs shall exit the
site turning left only. The existing wheelwash facility would be utilised as and when necessary to
ensure no mud debris is deposited on the public highway. The wheelwash shall be maintained at
all times.
Rights of Way
1.6.21 The proposed development shall affect one right of way and one bridleway. Bridleway
Rempstone BW11 and Right of Way Rempstone FP1 which leads into East Leake FP1 to the
north.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
21
1.6.22 Bridleway Rempstone BW11 has been temporarily diverted round the perimeter of Jenks
permission area to enable mineral extraction to be undertaken in this area and shall be restored
along the definitive route once restoration has been completed.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
22
1.6.23 The diversion order of Rempstone BW11 was issued on the 18th March 2011 and is in place until
completion of development and restoration of the site. The use of Jenks field for silt disposal
related to mineral extraction on adjacent land shall delay reinstatement of the bridleway but shall
also ensure the definitive route is reinstated to a suitable condition for its lawful use as a public
bridleway. Until this time it is proposed that the Bridleway diversion route continue until
restoration works have been completed.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
23
1.6.24 To assist mineral extraction within the proposed extension the Company seek to temporarily
divert Rempstone FP1 to follow a southerly then westerly route following the internal field
boundary as illustrated on plan ref: 13_COO7_ELEK_005B. The Company seek to link the
existing bridleway diversion with the proposed Rempstone FP1 diversion with a small gate
created within the hedgerow between Jenks and Rempstone extraction area, this gate would be
removed once restoration has been completed and replanted with species rich hedgerow. The
proposed diversion shall be a grassed surface covering a width of 2m and shall be in place until
final restoration at which point the original definitive route shall be reinstated.
1.6.25 The Company is committed to maintain the current definitive rights of way Rempstone FP1 as
long as possible. In addition to the formal diversion route the Company also propose to provide a
route following the eastern and northern permission boundary which is considered to be more
interested. During phase 1 and 2 a small diversion would be identified around the proposed
extraction area as shown illustrated on plan 13_COO7_ELEK_005B this route would be fenced to
protect public users.
1.6.26 The proposed routes should provide continued access of Rempstone FP1 during extraction and
once restoration has been completed the original definitive route shall be reinstated. As the land
is privately owned and shall be restored and handed back to the landowner as agriculture and
conservation it is not possible to introduce additional access routes.
1.6.27 The Company shall continue to provide a new link from bridleway to the Rempstone FP1 as
approved through previous planning permissions.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
24
1.7 METHOD OF WORKING
(Details of the method of working can be seen on plan 13_C007_ELEK/P5/689/8A)
1.7.1 Prior to the commencement of development the following works shall be undertaken within the
initial phase
• Vegetation clearance
• Archaeological investigation
• Fencing of any root protection area
• Creation of initial soil bunds
• Creation of internal haul road
• Laying any water / silt pipe work
1.7.2 It is proposed for works to commence within Rempstone during the final phase of Burton’s. This
approach has been identified due to the geological variation within the deposit at East Leake
Quarry. The Company seeks to maintain a full product range which may require blending of the
upper deposit of Rempstone and lower deposit of Burton’s phase 4 (Plan ref; P4/689/3e).
Burton’s operation is undertaken on a campaign basis and this approach would be continued for
the initial working of phase 1 within Rempstone. The Company does not propose to extract
mineral simultaneously from the Burton’s phase 4 and Rempstone phase 1 so as to reduce any
environmental effects of extraction upon local residents.
1.7.3 Works shall commence in the south west corner of Rempstone in phase 1, extraction would then
progress in a general anticlockwise direction back to the plant site. The Company seek to extract
phase 1 as silt lagoon to ensure sufficient capacity is provided and water recharge can be
achieved. The internal haul road shall be located along the northern extraction boundary
spearing south into the individual phases as and when necessary. All haul roads created on site
shall ensure that one way systems are introduced to prevent the need for vehicles to reverse
reducing noise impact upon surrounding residents. Stand offs include 3m from existing
hedgerow, minimum of 35m from the A6006 (which shall include soil bunds, surface water trench
if necessary and ROW diversion), 100 metres from Beech Tree Lodge and 15m from Sheepwash
Brook.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
25
1.7.4 Phase 1 covers an area of approximately 4.93ha and shall extract approximately 298,000 tonnes
split between several campaigns over a period of up to 1.6-1.9years. Soils would be stripped
starting from the south western corner of the extension area moving in a northerly direction.
Topsoil stripped would be deposited in storage mounds along the southern boundary of the
A6006 providing additional screening to properties along Ashby Road (Melton Road). Clay
removed shall be located in a bund to the north, east and south east which shall be a height of
4m.
1.7.5 The soil mound along the A6006 shall be to a maximum height of 3 metres and seeded and
maintained for the duration of extraction. The remaining soils and overburden shall be stored
along the northern and eastern boundary for the duration of the operations creating the acoustic
mound surrounding Beech Tree Lodge. All soils shall remain on site and used in the restoration.
Phase 1 would be used to create two silt lagoons to assist the processing of the material and
recycling of water on site.
1.7.6 Phase 2 has been split into 3 areas to assist progressive extraction, restoration and silt disposal.
Phase 2a covers an area of 2.31ha, phase 2b covers 1.54ha and phase 2c covers 2.19 ha and in
total shall release 306,000t of sand and gravel. Working within all areas of phase 2 should take
approximately 1.7-2.04 years.
1.7.7 Phase 2a topsoil is placed within phase1 to assist the silt lagoon bank profiling. Interburden and
clay shall be used to assist the formation of phase 1 silt lagoons and final restoration contours
within phase 2a. Remaining clays shall be stored to the east ready for final placement.
1.7.8 Phase 2b topsoil shall be placed along the southern boundary of the A6006. Interburden
released shall be used within phase 2b remaining interburden and clay shall be placed within
phase 2a.
1.7.9 Phase 2c topsoil and interburden shall be directly placed into phases 2b and 2c. Working within
phase 2c shall be in a northerly direction
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
26
1.7.10 The third phase covers an area of approximately 4.08 ha split into two equal areas removing a
total of approximately 272,000 tonnes of sand and gravel over a period 1.5 – 1.8y. Phase 3a,
topsoil and interburden would be stripped with topsoil being placed within phase 2b and 2c,
interburden shall be placed within phase 3a and clay would be placed within phase 2c and
northern storage bund. Phase 3b would continue to be worked in an easterly to northerly
direction, interburden would be directly placed within phase 3a and 3b, topsoil would be placed to
the east and stored ready for restoration and clay material would be placed within phase 3a.
1.7.11 The fourth phase covers an area of 2.87ha removing approximately 210,000tonnes of sand and
gravel over 1.1 -1.4years. Phase 4, topsoil would be stripped shall be directly placed within
phase 3a to assist restoration. Clay shall be placed within phase 3b with interburden placed
within phase 3b and 4 ready for topsoil. Clays stored in the northern bund shall be moved and
placed within phase 3b.
1.7.12 The fifth phase covers an area of 5.1ha removing 397,000tonnes of sand and gravel over 2-2.6
years. Topsoil would be directly placed into phase 3b to assist restoration and stored to the east.
Clay and interburden shall be placed within phase 4 with a significant proportion placed within
phases 4 and 5.
1.7.13 The sixth phase covers an area of 4.62ha removing 298,000tonnes of sand and gravel over 1.6-
1.9years. Topsoil would be and directly placed into phase 5 to assist restoration. Clay from
phase 6 shall be placed within phase 5 in addition to the clay bunds to the east and north. As
phase 6 is worked soil shall be taken from the eastern bunds and used to restore phase 5.
1.7.14 Topsoil from the southern boundary shall be used to restore the remainder of phase 5 and phase
6. Virgin material between phase 1 and 2 shall be cut and used to re-profile the silt lagoons in
phase1. On site clay, silt, interburden and topsoil shall be used to achieve the restoration
contours. Material is progressively used to restore phase 1 and 6 in accordance with restoration
plan ref P5/689/9. It is anticipated that the restoration of the site would be completed within 24
months from the cessation of mineral extraction.
1.7.15 The silt produced from the proposed extraction and processing of phase 1- 3 would be placed
into silt lagoons within Jenks. The remaining silt created from the processing of phases 3-6 shall
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
27
be disposed within the newly created silt lagoons created within Rempstone phase 1. The newly
created silt lagoons shall be linked to the existing fresh water lagoon and existing processing
plant as shown on plan ELEK_PLA_689_CAW_261112.
1.7.16 The extraction area shall be linked to the existing processing plant via an internal haul road for
quarry vehicles and plant through a gap to be created through the existing hedgerow between 1c
Jenks and Phase 1 Rempstone. The haul road shall continue through Jenks into the existing
processing plant.
1.7.17 Soils would continue to be handled in accordance with DEFRA (MAFF’s) good practice guide for
soil handling as demonstrated in Appendix 18. Soils would be stripped and stored for restoration
within the proposed extension area.
1.7.18 Restoration should be completed within two years of cessation of mineral extraction. Once the
restoration profile contours have been achieved soils shall be placed in anticipation of planting in
accordance with Appendix 16. Planting shall be undertaken within the first available planting
season.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
28
1.8 RESTORATION
(Plans of the restoration scheme are contained in Appendix 6, within Plan No P5/689/9.)
Rempstone
1.8.1 The proposed restoration seeks to complement adjacent restoration details and provide a
balance of agriculture and conservation helping to assist the Counties bio-diversity targets.
Approved restoration schemes at East Leake Quarry consist of low level agriculture, silt lagoons
naturally regeneration to conservation, wetland and landscaped planting. The proposed
restoration scheme for Rempstone has been designed to complement the restoration schemes
already approved, taking into consideration geological constraints, maintaining the landscape
character of the Nottinghamshire Wolds whilst protecting best and most versatile agricultural land
and further enhancing conservation and biodiversity. The proposal offers a mix of woodland,
agriculture and water conservation.
1.8.2 The current landform at Rempstone is an undulating arable field with no internal drainage ditches,
hedgerow or mature trees. The site is bound by mature hedgerow and planting which shall be
retained as part of the proposed sand and gravel operation.
1.8.3 The restoration scheme for Rempstone scheme involves the creation of 7 lakes along the
northern extraction boundary with the remaining land being restored to similar grade agricultural
land and woodland. The lakes will be created from the silt lagoons and extraction void and shall
be restored in a manner as to protect aerodrome safety whilst promoting bio-diversity.
1.8.4 The existing hedgerow has small gaps which would be planted to improve screening within the
first available planting season. The hedgerow would be maintained along the site and allowed to
grow up to improve screening throughout the duration of the operations. Additional trees shall be
planted within the hedgerow to improve the ecological value of the hedgerow and landscape
character. New hedgerow is proposed within the agricultural fields providing additional
biodiversity, these hedgerows shall also benefit from field ditches that will flow into the water
features.
1.8.5 Around the lake margins natural regeneration and planting of reedbed would be promoted and
conservation grassland which would be managed at a height of 200mm. Planting would
predominantly consisting of tree species such as Field Maple, Alder, Wild Cherry, Oak and Crack
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
29
Willow with additional shrub planting of Dogwood, Hazel, Hawthorn, Holly, Blackthorn, Goat
Willow, Grey Willow, Wych Elm and Osier.
1.8.6 To create this restored landform clay, interburden and soils would be stored or directly placed.
Interburden soils would be laid at a depth of approximately 20cm. Top soil will be progressively
spread out from storage mounds to a depth of 40cm.
1.8.7 It is considered that this area of the restoration should have a soil equivalent to the existing grade
2-3b classification. Upon restoration this area will provide a valuable agricultural resource for the
farmer restoring traditional farming activities to continue alongside water nature conservation.
Lings (Plan Ref:P2/689/9/6A)
1.8.8 The permitted restoration of Lings Farm shall be amended as part of this application to take into
consideration the current situation. One constraint of the site is that it has evolved through the
placement of silt material therefore It has become necessary to revise the permitted restoration
scheme.
1.8.9 The principle reasons for the proposed amendments have arisen due to additional silt being
disposed within the Lings water management system. As part of the 2007 planning permission to
extract sand and gravel from land known as Jenks it was intended that silt created through the
processing of material extracted from Jenks be placed within the void at Jenks through a series of
silt lagoons. The increased depth of the working within Jenks and time necessary to create a
sealed silt lagoon rendered the void unsuitable for silt disposal within the given time frame.
Therefore it was necessary to continue to use the existing silt lagoons system within Lings
permission area for the processing of material extracted from Jenks altering the final water levels
and lake formations. The additional silt has amended the final landform.
1.8.10 Since the restoration plan for Lings Farm was approved 22/2/1991 amendments to the site
contours and developing habitats has led to this revised restoration scheme. None of the
variations are adverse or contrary to the ethos of the restoration to wetland, conservation and
agriculture previously approved. The variations proposed reflect the current situation
experienced on site and the constraints these impose on the final land form.
1.8.11 In summary the revised Lings restoration scheme illustrates the provision for a mixed use
restoration scheme which would incorporate the following proposed landscape elements:
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
30
• Agricultural land
• Lake
• Seasonal wetland
• Conservation grassland
• Sand face
• Hedgerows
Lings Current Position
1.8.12 Over a third of the site has been restored through the process of silt disposal and replacement of
soils in accordance with the approved restoration scheme P2/689/9/6A. The agricultural field
along the southern boundary have been restored and H8, H7, H6 and P1hedgerows and
woodland were planted in 2011/ 12. The rough grassland to the north west has been created and
northern lake formed which has seen the establishment of wetland margins and aquatic habitat.
The wet grassland over silt disposal adjacent to P1 planting and H4 has naturally regenerated
with reeds and willow developing. A soil mound located around Home Farm Cottage remains and
has been historically planted. It is not proposed for this mound to be removed until final
restoration.
1.8.13 The larger open water features to the south of The Lings Farm properties has been extracted and
the final contours have been created through silt disposal. The silt lagoon barriers between the
water features have been located in a more easterly position as necessary to assist deposition of
silt particles and to ensure water quality remains clear within the large open water feature to the
east of The Lings Farm. Final bank profiles are yet to be completed around the lake perimeter.
The temporary soil mound around The Lings Farm still remains and H9 hedgerow is still to be
completed. The original silt pipe work is still located along the southern lake margin separating
the water features and wet grassland which shall be removed in 2014 allowing restoration of this
area. The water feature to the north of The Lings Farm has been created but the three small
ponds along the northern boundary have not been established, they have been replaced by the
final lake bank profile. The historic silt lagoons which run along site Sheepwash Brook have
naturally regenerated into wet woodland of willow.
1.8.14 The water feature located under the plant site has not been created due to ongoing use of
existing infrastructure. The approved interim restoration scheme has been implemented whilst
existing infrastructure remains on site illustrated on plan ref:P2/689/13b. Soil mounds are located
along the internal haul road and to the east of the site to assist final restoration.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
31
Lings Proposed Landform
1.8.15 A review of the site survey and existing landform when compared to the permitted restoration
scheme identified a need to update the approved contours as part of the overall restoration plan
for East Leake Quarry.
1.8.16 Alterations of the landform have become necessary to take account of the differing on site levels,
increased silt deposit and lake levels, amendment to the large lake profile and location of
hedgerows. As such the variations represent minor alterations to the approved plan recognising
that there are always minor variations that need to be accounted for when restoring a sand and
gravel quarry.
Lings Proposed Amendments
1.8.17 It is propose that the hedgerows H8, H6 and H4 follow the final contours around the wet
grassland instead of straight lines providing a more natural line with the land. It is proposed for H2
to be removed due the retention of the soil bund around Home Farm Cottage and future use as
an agricultural field. H8 hedgerow has been extended in a more northerly direction to replicate an
historic hedgerow line. The agreed hedgerow mix shall remain as approved and implemented
accordingly.
1.8.18 The middle lake depth has been reduced to less that 0.5m and shall develop into a seasonal
wetland / silt conservation area instead of being open water. The sand martin face shall be
retained. The northern and western wetland margins shall be re-profiled with soils currently stored
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
32
in temporary bunds along the boundary with The Lings Farm. Once the silt pipe has been
removed 2014 the southern lake margins shall be graded providing a gentle slope (excluding
sand face) between the established wet grassland and the new seasonal wetland. Once the soil
bund along The Lings Farm has been removed once mineral extraction has ceased hedgerow H9
shall be planted within the next available planting season.
1.8.19 The small water feature to the north of The Lings Farm shall be retained in its current form and
part of hedgerow H9 shall be planted 2014/15. The small water feature shall be maintained as
temporary light grazing until mineral extraction ceases and final restoration is completed through
the removal of the soil mounds, the land shall then be reseeded as conservation grassland. The
northern lake formation shall alter from the previously approved plan taking into consideration silt
disposal and final extraction face. The three ponds proposed to the north of along site
Sheepwash Brook shall now be incorporated into the lake although it is proposed for the margins
to be stepped to provide seasonal variation linking to the small pond to the north of The Lings
Farm. To compensate the loss of the three small water features it is proposed to retain the water
feature to the east near the offices and provide a link to the main lake feature through the existing
stocking area. The final water levels shall also reduce due to silt disposal providing a more
diverse wetland feature. The Company do not proposed to extract sand and gravel from beneath
the plant site and therefore the dog leg part of the lake shall not be created. It is proposed for this
area to be reinstated to a conservation grassland area with pockets of bare sand floor and
various small scrapes being created to enhance the biodiversity of the area. The historic silt
lagoons located to the north of the site following Sheepwash Brook shall be retained with
additional woodland / shrub planting being created enhancing the existing hedgerow around the
silt lagoons linking the different landforms and contours. The soil bund along Sheepwash Brook
shall be maintained until mineral extraction has ceased at which point it shall be partially removed
reducing the height by a 1m or remain in situ as to necessary to retain surrounding habitats
naturally regenerating, the Company seek to monitor the evolving landscape and seek
confirmation from the County Ecologist and Landscape officer prior to final restoration of this
area, any soils removed would assist final restoration of Lings Farm permission area.
1.8.20 It is considered that the proposed amendments shall not negatively impact the overall aims of the
original restoration scheme. The proposed landform provides a rich seasonal wetland habitat
with reduced large water features which will benefit bird strike management on site.
1.8.21 Jenks and Burton Restoration
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
33
1.8.22 Jenks and Burtons permitted restoration scheme shall remain as permitted and have been
transposed upon the overall restoration plan to show full context of the final restoration of East
Leake Quarry. The proposed extraction at Rempstone should not delay restoration of Burton’s
and shall ensure Jenks restoration can be implemented in accordance with approved details.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
34
1.9 AFTERCARE
1.9.1. The Applicant recognises it’s social, legal and environmental responsibility in ensuring successful
integration of the restored landform into its surroundings. This will only be achieved by the
implementation of an aftercare programme. A restoration and aftercare assessment and
management have been included as part of this planning application, please see Appendix 16. It
is proposed that should planning permission be granted the aftercare scheme would be
implemented progressively on completion of restoration. Essentially the scheme covers the
management of the woodland, grassland and reinstated agricultural areas and the new habitats
created in accordance with good practice.
1.9.2 The main objective of aftercare is to restore land covered by the proposed development to a
condition similar to that of undisturbed land and to enhance and develop the biodiversity and
nature conservation.
1.9.3 Detail of the proposed aftercare management is detailed in Appendix 16 of the Planning
Statement.
1.9.4 Agricultural aftercare shall be undertaken for a period of 5y and woodland and conservation areas
shall be managed for an aftercare period of 10y.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
35
1.10 SUMMARY OF MAIN ENVIRONMENTAL EFFECTS
1.10.1 It has been concluded that the development is EIA development and therefore requires an
Environmental Statement. This section provides a brief overview of the possible environmental
effects assessed in the Environmental Statement attached to this planning application.
1.10.2 LANDSCAPE AND VISUAL AMENITY: The proposed development is not likely to lead to any
adverse landscape, significant magnitude of change or long term visual impacts. The proposed
development shall have a moderate impact during the operation period but this should be limited
upon ROW users and sensitive receptors and mitigated by careful placement of screening bunds
and progressive restoration. The proposed development is not within a designated landscape
area and the proposed restoration will not appear out of keeping with the surrounding landscape.
It is recognised that the proposed extraction is encroaching Rempstone Village and properties
along the A6006, it is considered with proposed screening mounds along the southern and
eastern boundary that views into the site shall be reduced to limited first floor views.
1.10.3 RESTORATION AND AGRICULTURE: Following the careful stripping, storage and replacement
of soils it will be possible to reinstate part of the land for agricultural use which can then be
returned to the Landowner for farming. The remaining land would be used to create a
conservation feature including planting. A benefit of restoring part of the site to nature
conservation is assisting bio-diversity targets through the creation of broadleaved woodland, field
margins, conservation grassland and water margins.
1.10.4 ECOLOGY: In respect of ecology, the site is of low ecological value and therefore no adverse
impact has been identified. The conservation habitat being offered as part of the proposed
restoration will enhance local biodiversity and will contribute towards the targets of the
‘Nottingham Biodiversity Action Plan’. The principle biodiversity action plan targets include;
Arable field margins, reedbeds, hedgerows, oak- birch woodland and unimproved neutral
grassland.
1.10.5 ARCHAEOLOGY: This site was subject to an archaeological survey as part of the planning
application for the current extraction site. The proposed extraction area has potential for anglo
saxon remains related to St Peter’s Church and Rempstone Estate, but no national significant
remains have been discovered to date that has required preservation in situ. Therefore it is
unlikely that adverse impacts will arise from the proposed development and in fact the proposals
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
36
will contribute towards the knowledge and understanding of local archaeology and its wider
setting. It is proposed that the existing archaeological scheme be developed to include the
proposed extension area, this could be controlled by a planning condition.
1.10.6 HYDRO-GEOLOGY: Groundwater levels would be reduced for the duration of the development. It
is not envisaged that this will have a significant effect on nearby properties or agricultural land.
As part of assessing the material considerations and impacts of the proposed extension a Flood
Risk Assessment has been undertaken. It is concluded there should be no adverse impact on
flooding within the area, mitigation measures are recommended with regard to surface water
collection in a trench from soil mounds as necessary (scheme attached in Appendix 24 provides
details of trench as necessary) and seasonal wetland around the restored lake margins to
accommodate any significant flood flows.
1.10.7 TRAFFIC: The proposal represents a continuation of existing activities with no increase in vehicle
movements. So as not to compromise the use, safety or amenity of other road users the site
already possesses the entire necessary site access arrangements and infrastructure. East Leake
Village would continue to be protected from HGV site traffic which enters or leaves the site.
1.10.8 NUISANCE: It is not envisaged that dust or noise would be a problem during the development.
The following dust suppression methods would continue to be implemented for the duration of
operations.
• Water bowser
• Dampening of haul roads
• Spraying of stockpiles
• Seeding of soil mounds
• Wheelwash
Even though the site will be dewatered the mineral would still be moist when excavated.
1.10.9 Construction noise levels are of a short duration while the operational noise levels would remain
within acknowledged levels as indicated in a revised noise report commissioned as part of this
proposal (see Environmental Statement Volume 2 - Noise). It is not proposed that noise levels
shall increase through the proposed extension. The Company proposes to operate in
accordance with the following noise limits
Noise Limits
Location Site Noise Limit dB LAeq, 1h (freefield)
Lings Farmhouse 55
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
37
Home Farm Cottage 53 Rempstone Church 55
4 Loughborough Road 53 Beech Tree Lodge 54 Holy Cross Cottage 55
Rempstone Hall 55 Home Farm 50
The Lings Farm 50
Temporary operations would continue to operate at a level of 70 dB LAeq, 1 hour (free field).
1.10.10 Comments were raised through the public exhibition regarding reversing alarms from vehicles on
site. To mitigate potential reversing alarms the Company shall ensure all vehicles have white
noise alarms, introduce one way haul routes and where possible remove reversing alarms and
use alternative reserving safety measures. The Company recognises that as extraction moves in
an easterly direction it will become closer to the Parish Church and the site are happy to
accommodate when necessary sensitive working during certain Church services to maintain the
tranquil setting.
1.10.11 The proposed extension does not include the erection of any lighting. Should any lighting be
required further approval would be sought from the Mineral Planning Authority.
1.10.12 The proposed scheme has been assessed against bird strike potential from operations and
restoration, the following mitigations are proposed to reduce any significant impact;
• Planting at 4m centres
• Reedbed planting on lake margins
• Maintenance of grass at 200mm height
• Limited berry-bearing species
1.10.13 The following permission implements the following stand offs
A6006 – 35M (includes electricity line stand off)
Hedgerows – 3m
Sheepwash Brook – 15m
Beech Tree Lodge – 100m
Ash Tree – 13m
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
39
2.0 PART TWO (B) – PLANNING POLICY CONSIDERATIONS
2.1 INTRODUCTION
2.1.1 When determining planning applications the approved Development Plan policies are a material
consideration and planning authorities must have regard to these, and the extent to which the
proposal complies with them, when making its decision on whether or not to grant planning
permission.
2.1.2 An assessment of a proposal against the relevant planning policies allows the principle of the
development and its details to be properly assessed against planning policy objectives and
requirements. This in turn assists in balancing the impacts associated with a particular
development against the need for the proposal and its overall merits and benefits.
2.2 NEED FOR THE DEVELOPMENT
2.2.1 Nottinghamshire County Council falls within the East Midlands region. Nottinghamshire Annual
Monitoring Report identifies a land won sand and gravel apportionment figure of 2.65 million
tonnes per annum for the County (as stated in the Minerals Local Plan).
2.2.2 Nottinghamshire Minerals Local plan has 23 million tonnes allocated at 7 sites which were
expected to sustain a minimum 7 year landbank until 2015 based on sales continuing at
forecasted levels. The seven sites include Gunthorpe, Bleasby, Rampton, Sturton le Steeple,
Lound East, Mission – Finningley and Newington South. Of these allocated sites 5 have been
granted planning permission equating to approximately 13.95 million tonnes.
2.2.3 Nottinghamshire Local Aggregate Assessment 2013 provides an overview of the Counties
permitted reserves, production and landbank. Sand and gravel production between 2001 and
2011 has been varied and impacted by the economic climate. Production saw a high in 2004 with
3.37 million tonnes and a low of 1.27 million tonnes in 2009. Production has steadily risen since
2009 up to 1.71 million tonnes in 2011 which is still below the County apportionment of 2.65
million tonnes per annum.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
40
2.2.4 There are currently 12 permitted sand and gravel sites in the county although only 9 are currently
active. The County landbank stood at 7.3y December 2011 which equates to 19.3million tonnes.
Utilising average sales between 2001 and 2011 the apportionment figure should be 2.58 million
tonnes which is slightly less than previous apportionment figures but above current production.
Sales over the last 3 years have been an average low of 1.51 million tonnes.
2.2.5 The proposed extension is not allocated and is therefore a departure from the existing Minerals
Local Plan. The current Minerals Local Plan provided allocated sites until the end of the plan
period 2015. The Company have put forward Rempstone extension area to be considered as
part of the emerging Local Development Framework but has not been formally approved as a
preferred site although it forms part of the recent consultation document. It is considered that
delay in the review of the Minerals Local Plan due to the changes in National legislation and new
Planning Policy Framework has prevented full consideration of Rempstone as an allocated site
leading to this departure. Although the proposed extraction area is a significant departure from
the existing local plan it meets the principles of sustainable development and National Planning
Policy Framework as an extension to an existing site.
2.2.6 It is proposed for Rempstone to come online in 2016 during the final stages of the permitted
extraction in Burton’s. The site would release 1.78 million tonnes over a period of 10-12y. The
commencement of Rempstone would be in the final years of the permitted landbank should
production levels rise to an apportionment figure of 2.58mtpa which would assist the Counties
supply of sand and gravel between 2016 and 2028 depending on market demand. Should
production remain below at the current average of 1.51 million tonnes per annum then
Rempstone could be seen as slightly premature as current permitted reserves would not be
below 7 years until 2018. National Planning Policy Framework states there should be a minimum
of 7y landbank it does not state a maximum it also states;
Longer landbanks may be appropriate to take account of the need to supply a range of types of
aggregates, locations of permitted reserves relative to markets, and productive capacity of
permitted sites.
2.2.7 Although reserves have been permitted at East Leake on, land known as Burtons, these reserves
would be depleted within 3 years. East Leake is the only sand and gravel quarry within
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
41
Nottinghamshire to serve the southern markets of Nottinghamshire and northern markets of
Leicestershire. With the closure of Holme Pierrepoint and Hoveringham quarries in 2004 and
2007 and the failure for Gunthorpe Quarry coming online there is only East Leake serving this
market. It is proposed that this extension would enable East Leake to continue operating and
supplying local markets.
2.2.8 Without the reserve contained within the application site existing operations will cease at the
quarry and the processing plant will be removed. In effect, the reserve will be sterilised from
being a high grade product. At any future point in time it could be excavated and sold
unprocessed ‘As Raised’ material for low grade specification uses such as bulk fill.
2.2.9 It is appreciated that the current landbank is currently over the required 7 years but it is
considered an increase to this figure to ensure the continuation of East Leake Quarry and the
effective use of the mineral reserve, be appropriate in the long term.
2.2.10 It is considered appropriate to bring this extension at East Leake Quarry now as it will continue to
supply an essential product to the southern markets of Nottinghamshire and northern market of
Leicestershire, utilise existing infrastructure and provide restoration benefits.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
42
2.3 NATIONAL POLICY
2.3.1 The new National Planning Policy Framework (NPPF) was published on the 27th March 2012 and
is the principle policy document which sets out the overarching planning policy that shall be
implemented through the development plan and determination process. NPPF identifies a
presumption in favour of sustainable development. There are three dimensions to sustainable
development, economic, social and environmental, the planning system as a function should
perform a number of roles;
‘An economic role – contributing to building a strong, responsive and competitive economy, by
ensuring that sufficient land of the right type is available in the right places at the right time...’
‘A social role – supporting strong, vibrant and healthy communities by providing the supply of
housing required...’
‘An environmental role – contribution to protecting and enhancing our natural, built and historic
environment; and as part of this helping to improve biodiversity, use natural resources prudently,
minimise waste and pollution and mitigate and adapt to climate change including moving to a low
carbon economy.’
2.3.2 Sections 18 to 219 taken as a whole contribute to the definition of sustainable development which
includes the implications upon mineral extraction and reclamation.
2.3.3 The new planning policy framework does not move away from being a plan led system and that
the development plan should be the starting point of any decision making process and the NPPF
is a material consideration in determining any application.
2.3.4 The presumption in favour of sustainable development means; approving development proposals
that accord with the development plan without delay, and where the development plan is absent,
silent or relevant policies are out of date, granting planning permission unless – any adverse
impacts of doing so would significantly and demonstrably outweigh the benefits. The benefits
should be assessed against the policies in this framework taken as a whole; or as specific
policies in this Framework indicate development should be restricted.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
43
2.3.5 There are 12 Core Planning Principles that underpin the decision making process which are
summarised below;
1) Plan-led
2) Be creative, enhance and improve the places people live
3) Proactively drive and support sustainable economic development and respond positively to
wider opportunities for growth, set out clear strategies for allocating sufficient land which is
suitable for development in their areas.
4) High quality design and good standard of amenity.
5) Take into account the different roles and character of different areas recognising the intrinsic
character and beauty of the countryside and supporting thriving rural communities.
6) Support the transition to a low carbon future in a changing climate. Taking full account of flood
risk and coastal change and encourage reuse of existing resource.
7) Contribute to conserving and enhancing the natural environment and reducing pollution.
8) Encourage the effective use of land.
9) Promote mixed use development and encourage multiple benefits from the use of land in
urban and rural areas, recognise that some open land can perform many functions (such as for
wildlife, recreation, flood risk, mitigation, carbon storage or food production)
10) Conserve heritage assets in a manner appropriate to their significance, so that they can be
enjoyed for their contribution to the quality of life of this and future generations.
11) Actively manage patterns of growth ...and focus significant development in locations which
are or can be made sustainable; and
12) Take account of and support local strategies to improve health, social and cultural wellbeing
for all, and deliver sufficient community and cultural facilities and services to meet local needs.
NPPF includes various sub headings which contribute to the definition of sustainable
development those of relevance to this development are summarised below;
2.3.6 Supporting a prosperous rural economy- Policies should support economic growth in rural
areas in order to create jobs and prosperity by taking a positive approach to sustainable
development, support the sustainable growth and expansion of all types of business and
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
44
enterprise in rural areas and promote the development and diversification of land-based rural
businesses.
2.3.7 Promoting sustainable transport – Transport policies have an important role to play in
facilitating sustainable development but also in contributing to wider sustainability and heath
objectives. All development that generates significant amounts of movements should be
supported by a Transport Statement or Transport Assessment. Plans and decisions should take
account of whether opportunities for sustainable transport modes have been assessed and if
improvements can be undertaken within the transport network that cost effectively limit the
significant impacts of development. Development should only be prevented or refused on
transport grounds where the residual cumulative impacts of development are severe.
Development should be located to efficiently deliver goods and supplies.
2.3.8 Requiring good design – Great importance is placed on the design of the built environment.
Good design is a key aspect of sustainable development and should contribute positively to
making places better for people.
2.3.9 Promoting healthy communities – As part of facilitating social interaction and creating healthy,
inclusive communities we should aim to deliver social, recreational and cultural facilities and
services the community needs. Access to high quality open spaces and opportunities for sport
and recreation can make an important contribution to health and well being of communities.
Polices should protect and enhance public rights of way and access.
2.3.10 Meeting the challenge of climate change, flooding and costal change – Proactive strategies
to mitigate climate change taking full account of flood risk coastal change, water supply and
demand considerations. Developments should be located in a manner which reduce greenhouse
gas emissions and actively support energy efficiency, landform, layout, orientation, massing and
landscaping. New development shall be planned to avoid increased vulnerability to the range of
impacts arising from climate change. Development should take account of the impacts of climate
change by; applying the sequential test, if necessary exceptions test, safeguard land from
development that is required for current and future flood management and use opportunities
offered by new development to reduce the causes and impacts of flooding. Development should
not cause flood risk elsewhere.
2.3.11 Conserving and enhancing the natural environment – The planning authority should
contribute to and enhance the natural and local environment by; protecting and enhancing valued
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
45
landscapes, geological conservation interests and soils; recognising the wider benefits of
ecosystems services; minimizing impact on biodiversity and providing net gains in biodiversity
where possible reducing the decline in biodiversity; preventing new and existing development
from contributing to or being put at unacceptable risk or being adversely affected by unacceptable
levels of soil, air, water or noise pollution or land instability. Proposals should propose remediate
and mitigate despoiled, degraded, derelict, contaminated and unstable land where appropriate.
Account should be taken of the economic and other benefits of best and most versatile
agricultural land. Great weight should be given to conserving landscape and scenic beauty in
National Parks, the Broads and Areas of Outstanding Natural Beauty which have the highest
status of protection, taking into consideration wildlife and cultural heritage conservation. Planning
permission should be refused for major development in these designations except in exceptional
circumstances and where it can be demonstrated they are in the public interest and have assess
the need (including National considerations) impact upon local economy, cost and scope of
developing elsewhere or meeting the need in another way. Proposals should assess any
detrimental effect on the environment, landscape and recreational opportunities.
2.3.12 When determining planning applications the development should aim to conserve and enhance
biodiversity this may be undertaken through the implementation of adequate mitigation measures,
compensation. Proposed development on land within or outside of a Site of Special Scientific
Interest that has an adverse impact shall only be permitted where the benefits clearly outweigh
both the impact and the features which constitute the SSSI. Development proposals where the
primary objective is to conserve or enhance biodiversity should be permitted; opportunities to
incorporate biodiversity in and around development should be encouraged. Planning permission
should be refused for development resulting in the loss or deterioration of irreplaceable habitats,
including ancient woodland, loss of aged or veteran trees unless the need or benefit of the
development clearly outweighs the loss. Presumption in favour of sustainable development does
not apply where development requiring appropriate assessment is necessary.
2.3.13 Planning polices and decisions should aim to; avoid adverse impact by means of noise; mitigate
and reduce noise impacts. Take into account the presence of Air Quality Management Areas and
the cumulative impacts on air quality from any new development and individual sites in a local
area. Encourage good design to limit light pollution upon local amenity and nature conservation.
2.3.14 Conserving and enhancing the historic environment – A planning application should describe
the significance of any heritage assets affected including any contribution made by their setting;
the level of detail shall be proportionate to the assets importance and no more than is sufficient to
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
46
understand the potential impact of the proposal on their significance. Where a site on which
development is proposed includes or has the potential to include heritage assets with
archaeology interest local planning authorities should required developers to submitted an
appropriate desk-based assessment and, where necessary, a field evaluation.
2.3.15 When consideration is given to the impact of a heritage asset great weight will be given to
conservation, the more important the asset the greater weight should be given, significance can
be harm or lose through alteration, destruction of the heritage asset or development within its
setting. Substantial harm to a grade II listed building, park or garden should be exceptional.
Where a proposed development will lead to substantial harm to or total loss of significance of a
designated heritage asset it should only be permitted if the public benefits outweigh that harm or
loss.
2.3.16 Non designated archaeological assets of interest that are demonstrably of equivalent significance
to schedule monuments, should be considered subject to the policy for designated heritage
assets which include;
• The nature of the heritage asset prevents all reasonable uses of the site; and
• No viable use of the heritage asset itself can be found in the medium term through
appropriate marketing that will enable its conservation; and
• Conservation by grant-funding or some form of charitable or public ownership is
demonstrably not possible; and
• The harm or loss is outweighed by the benefit of bringing the site back into use.
Where a development proposal will lead to less than substantial harm to the significance of a
designated heritage asset, this harm should be weighed against the public benefits of the
proposal, including securing its optimum viable use.
2.3.17 Developers should record any heritage assets to be lost (wholly or in part) in a manner
proportionate to their importance and the impact, and to make this evidence (and any archive
generated) publicly accessible. However, the ability to record evidence of our past should not be
a factor in deciding whether such loss should be permitted
2.3.18 Facilitating the sustainable use of minerals – “Minerals are essential to support
sustainable economic growth and our quality of life ” . NPPF recognises the importance of
sufficient supply of material to provide the infrastructure, buildings, energy and goods that the
country needs and that minerals can only be worked where they are found. When proposals are
determined the following points shall be considered;
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
47
• Great weight shall be given to the benefits of mineral extraction to the economy
• Where practical provide for the maintenance of landbanks of non energy minerals from
outside National Parks, the Broads, Areas of Outstanding Beauty and World Heritage
Sites, Scheduled Monuments and Conservation Areas.
• No unacceptable adverse impacts on the natural and historic environment, human health
and aviation safety and take into account the cumulative effect
• Avoid noise, dust and particle emissions are any blasting vibrations through mitigation
and removal of sources and appropriate control levels.
• No peat extraction
• Provide for restoration and aftercare at the earliest opportunity to be carried out to high
environmental standards through planning conditions (bonds and financial agreements
shall only be sought in exceptional circumstances)
• Conserve mineral resources within safeguarding zones where possible so not to
constrain potential future use.
2.3.19 The local plan should provide for a steady and adequate supply of aggregate by preparing an
annual local aggregate assessment based upon a rolling average of 10y sales data and other
relevant data and all supply options (recycled sources). Landbanks should be a minimum of
7years within the local plan for sand and gravel and 10y for silica sand, crushed rock and 15y for
chalk and limestone and 25y for clay. Landbanks should provide a stock of permitted reserves to
support the level of actual and proposed investment required for a new or existing plant and the
maintenance and improvements needed.
2.3.20 Longer landbanks may be appropriate to take account of the need to supply a range of types of
aggregates, locations of permitted reserves relative to markets, and productive capacity of
permitted sites.
2.3.21 Planning Practice Guidance
The guidance document provides additional information on various planning and environmental
topics. Those considered pertinent to this proposal including environmental impact assessment,
minerals, flood risk, air quality, and noise to name a few all of which reaffirms detail as set out in
the National Planning Policy Framework.
2.3.22 As set out in the National Planning Policy Framework, minerals planning authorities are expected
to ensure that plan proposals do not have an unacceptable adverse effect on the natural or
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
48
historic environment or human health. Residents living close to mineral workings may be exposed
to a number of environmental effects and particular care should be taken in respect of any
conditions they attach to a grant of permission for working in proximity to communities.
Dust
2.3.23 The scope of a dust assessment study should be agreed with the minerals planning authority and
local planning authority. Such studies should be used to:
• establish baseline conditions of the existing dust climate around the site of the proposed
operations;
• identify site activities that could lead to dust emission without mitigation;
• identify site parameters which may increase potential impacts from dust;
• recommend mitigation measures, including modification of site design; and
• make proposals to monitor and report dust emissions to ensure compliance with appropriate
environmental standards and to enable an effective response to complaints.
Noise
2.3.24 Those making development proposals should carry out a noise emissions assessment, which
should identify all sources of noise and, for each source, consider the proposed operating
locations, procedures, schedules and duration of work for the life of the operation. Proposals for
the control or mitigation of noise emissions should consider:
• the main characteristics of the production process and its environs, including the location of
noise-sensitive properties;
• proposals to minimise, mitigate or remove noise emissions at source;
• assessing the existing noise climate around the site of the proposed operations, including
background noise levels at nearby noise-sensitive properties;
• estimating the likely future noise from the development and its impact on the neighbourhood of
the proposed operations;
• monitoring noise emissions to ensure compliance with appropriate environmental standards.
Noise standards
2.3.25 Noise levels shall be subject to a maximum of 55dB(A)LAeq, 1h (free field), and ensure levels do
not exceed the background level by more than 10dB(A). Normal working hours have been
identified as (0700-1900) and evening as (1900-2200) limits should not exceed background level
by more than 10dB(A) and night-time limits should not exceed 42dB(A) LAeq,1h (free field) at
noise-sensitive dwellings.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
49
2.3.26 All mineral operations will have some particularly noisy short-term activities that cannot meet the
limits set for normal operations. However, these activities can bring longer-term environmental
benefits. Increased temporary daytime noise limits of up to 70dB(A) LAeq 1h (free field) for
periods of up to 8 weeks in a year at specified noise-sensitive properties should be considered to
facilitate essential site preparation and restoration work and construction of baffle mounds where
it is clear that this will bring longer-term environmental benefits to the site or its environs.
Stability in surface mine workings and tips
2.3.27 Appraisal of slope stability issues for new workings should be based on existing information,
which aims to:
• identify any potential hazard to people and property and assess its significance;
establish the basis for reserve calculation;
• identify any features which could adversely affect the stability of the working to enable basic
• Quarry design to be undertaken
Restoration and aftercare of mineral sites
2.3.28 Restoration and aftercare should be undertaken at the earliest opportunity to be carried out to
high environmental standards. This should include through provision of a landscape strategy,
restoration conditions and aftercare schemes as appropriate
Landscape strategy
2.3.29 A site-specific landscape strategy to accompany applications for either a new site or any
significant extension to an existing working site should include:
• defining the key landscape opportunities and constraints;
• considering potential directions of working, significant waste material locations, degrees of visual
exposure etc;
• identifying the need for additional screening during operations;
• identifying proposed after-uses and preferred character for the restored landscape.
2.3.30 Planning conditions for reclamation should be specific to the proposed site and should normally
be framed with the intended after-use in mind. They will vary according to the characteristics of
the individual site; the intended after-use; the type of mineral to be worked; the method of
working; the timescale of the working; the general character of, and planning policies for the area.
Aftercare schemes
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
50
2.3.31 The preparation of a successful aftercare scheme requires two levels of information from the
mineral operator:
• an outline strategy of commitments for the five year aftercare period; and
• a detailed programme for the forthcoming year.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
51
2.4 LOCAL POLICY
Nottinghamshire Minerals Local Plan
2.4.1 Nottingham Minerals Local Plan was adopted 5 December 2005, GOEM have saved a number of
policies under the 2004 Planning and Compulsory Purchase Act which this development needs to
be considered in the context of.
2.4.2 M2.1 – Sustainable Development
Planning permission for mineral development will only be granted where it has been
demonstrated that the plan’s sustainable development objectives have, where appropriate, been
fully addressed.
2.4.3 M3.1 – Information in Support of Planning Applications
Planning permission for minerals development will not be granted unless sufficient information is
provided to enable a balanced assessment of all relevant factors. Such information should
include as appropriate details of, geology, design, routing etc as much information regarding the
proposed development should be included within the planning application.
2.4.4 M3.3 – Visual Intrusion
Planning permission for mineral development will only be granted where any adverse visual
impact can be kept to an acceptable level. Where appropriate, conditions will be imposed to
ensure that plant, structure, buildings and storage areas are:
a) located in such a position as to minimize impact on adjacent land;
b) kept as low as practicable to minimize visual intrusion;
c) of appropriate colour, cladding or suitable treated to reduce their visual impact;
d) satisfactorily maintained to preserve their external appearance;
e) removed upon cessation of extraction and the site restored to an acceptable level,
In addition, measures should be taken by sympathetic design and / or screening to void
unacceptable light intrusion caused by extraneous light from the development.
2.4.5 M3.4 – Screening
Where planning permission for mineral development is granted condition will be imposed to
ensure that screening and landscape proposal reduce visual impact. Such conditions should
where appropriate include:
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
52
a) measures to retain, enhance, protect and manage existing features of interest and value for
screening and their contribution to the reclamation of the site;
b) measures to screen the site by the use of walls, fencing, earth mounding and or tree and
shrub planting
c) details of the method of working and phasing to cause least visual intrusion;
d) details of the location form, number, species size, method of planting, site preparation and
any necessary measures for replacing plant material which fails following initial planting.
Where appropriate, screening proposals should maximise the potential to enhance the landscape
and wildlife potential through appropriate planting.
2.4.6 M3.5- Noise
Planning permission for minerals development will only be granted where noise emissions
outside the boundary of the mineral workings do not exceed acceptable levels. Where
appropriate conditions will be imposed to;
a) restricted hours of operations;
b) require the use of conveyors instead of dumper trucks;
c) sound – proof fixed and mobile plant
d) set maximum noise labels at sensitive locations
e) impose standoff distances between operations and noise sensitive locations
f) require the use of acoustic screening such as baffle mounds or fencing.
2.4.7 M3.7 – Dust
Planning permission for minerals development will only be granted where dust generation will not
lead to an unacceptable impact. Where appropriate conditions will be imposed to suppress dust
generation such conditions may relate to the;
a) layout of the site, design or stockpiles;
b) containment of conveyors and processing plant and dust collection equipment;
c) use of bowsers, sprays and vapour masts on haul roads stockpiles, transfer points
d) design of material – handling systems, drop heights, wind guards, loading points
e) use of binders on haul roads and stockpiles;
f) limiting on site vehicle speed
g) soil handling strategies
h) limiting levels of dust measures in a specific way; provision of monitoring facilities
The quarry undertakes dust suppression at present and would continue whilst the quarry is
operational.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
53
2.4.8 M3.8 – Water Environment
Planning permission for minerals development will only be granted where;
a) surface water flows are not detrimentally altered
b) groundwater levels, where critical are not affected
c) there are no risks of polluting ground or surface waters
Unless engineering measures and / or operational management systems can adequately mitigate
such risks.
2.4.9 M3.12- Highway Safety and Protection
Planning permission for minerals development will only be granted where measures are in place
to the County Council’s Satisfaction that prevents damage to the highway and also prevents mud
and other debris material contaminating public highways. Such measures may include;
a) wheel cleaning facilities;
b) sheeting of lorries
c) metalling haul roads near their point of access to the public highway
2.4.10 M3.13 – Vehicular Movements
Planning permission for minerals development will only be granted where the highway network
can satisfactorily accommodate the vehicle movements likely to be generated and would not
cause unacceptable impact upon the environment and disturbance to local amenity.
2.4.11 M3.14- Vehicular Routing
In granting planning permission for minerals development the County Council will as appropriate;
a) impose conditions requiring the posting of site notices and / or the issuing or instructions to
lorry drivers detailing any routes to be avoided;
b) seek to negotiate planning obligations in order to secure highway improvements;
c) seek to negotiate agreements under section 111 of the Local Government (Miscellaneous
Provisions) Act 1972 in order to specify agreed vehicular routes
2.4.12 M3.17- Biodiversity
Planning permission will not be granted for minerals development which will adversely affect the
integrity of continuity or habitats or features identified as priorities in the UK and/ or Nottingham
Local Biodiversity Action Plan, unless an overriding need for development is demonstrated which
outweighs the nature conservation importance of the feature. If the loss of the habitat or feature
cannot be avoided, provision will be made, where practicable for the creation of an equivalent
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
54
habitat or feature, either on the development site or under the terms of a voluntary agreement on
a suitable alternative location within the County.
2.4.13 M3.19 – Sites of special scientific interest
Planning permission will not be granted for minerals development which would have an adverse
effect, directly or indirectly on the special interest of an SSSI or a candidate SSSI unless the
reason for the development outweighs the nature conservation considerations. The assessment
of any adverse impact will take account of the scope for mitigation and/ or compensatory
measures to replace the loss.
2.4.14 M3.20 – Regional and Local Designated Sites
Planning permission for minerals development in areas which are regional or local designated
sites will only be granted where it can be demonstrated that the importance of the development
outweighs the regional or local value of the site, taking into account measures to mitigate/
compensate against any adverse impact.
2.4.15 M3.21 – Protected Species
Planning permission for minerals development likely to cause harm to protected species or their
habitats will only be permitted of the protection and conservation of species can be secured by
condition or planning obligations or if there is an overriding need for the development. Planning
permission for mineral development will not be granted until a full survey of the affected species
has been carried out.
2.4.16 M3.22 – Landscape Character
Operators must demonstrate that landscape character and local distinctiveness are fully taken
into consideration within development proposals. Planning permission will not be granted for
minerals development which is likely to adversely impact upon the character and distinctiveness
of the landscape unless there are reasons of overriding public interest or where ameliorative
measures can reduce the impact to an acceptable level.
2.4.17 M3.24 – Archaeology
Planning permission will not be granted for minerals development which would destroy nationally
important archaeological remains and their settings, where scheduled or not. Planning
permission will only be granted for development which would affect archaeological remains of
less that national importance where it can be demonstrated that the importance of the
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
55
development outweighs the regional or local significance of the remains and where appropriate
provision is made for the excavation and recording of the remains.
2.4.18 M3.25 – Listed buildings, conservation areas, historic battlefields and historic parks and
gardens
Planning permission will not be granted for minerals development which would cause an
unacceptable level of harm to the character, appearance, condition or setting of conservation
areas, listed buildings, historic battlefields and historic parks and gardens.
2.4.19 M4.3 - Soil conservation and use of soil making materials
Where planning permission involves the reclamation of mineral workings, schemes should
include measures to ensure the proper identification of all soil resources and their characteristics,
together with other potential horizons within the mineral deposit that may be suitable for creating
a soil profile, in addition to stripping, storage and placement methods which ensure that the soils
are safeguarded for their intended afteruse. Where soils are absent or deficient, schemes should
be include measures to ensure that available vegetation cover can be established to achieve the
required after i.e. Such measures may include;
a) concentrating soils within area where they will provide most benefit;
b) utilising on-site, or imported soil making materials which with suitable treatment are capable
of supporting plant growth.
c) Volumetric estimates of the soil profile showing the amounts of topsoils, subsoils and
overburden stripped, stored and re-spread in conjunction with the proposed extraction and
restoration plan.
2.4.20 M4.4 Landscape Treatment
Where planning permission involves the reclamation of mineral workings landscaping proposals
will be required that include;
a) an overall landscape concept or brief;
b) details of the final landform which should harmonise with the existing landscape character
and aim to promote strategic landscape features;
c) the location, form, numbers, species, size and method of planting
d) details of establishment, maintenance and longer term management proposals, including
measures for replacing failed planting.
2.4.21 M4.9 – Aftercare
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
56
The County Council will attach aftercare conditions to all mineral planning permissions where
reclamation is to agriculture, forestry or amenity.
2.4.22 M4.10 After-use – details required and objectives
Where planning permission involves the reclamation of mineral workings, schemes should
include full details of the proposed after-use and be designed to maximize opportunity to enhance
the environment, biodiversity and amenity of the local community
2.4.23 M4.11 After-use – management and other agreements
The Company is committed to long term management through aftercare / management schemes.
2.4.24 M4.12 Agricultural After-use
Where planning permission involves the reclamation of mineral working to agriculture the County
Council will encourage such proposals to take full account of the Countryside Appraisal and Local
Biodiversity Action plan.
2.4.25 POLICY M6.2 Sand and Gravel Landbank
The County Council will endeavour to maintain a landbank of permitted reserves of sand and
gravel sufficient for at least 7 years extraction and also an adequate production capacity in order
that Nottinghamshire will meet its reasonable share of regional provision of aggregates
throughout the plan period.
2.4.26 POLICY M6.3 Sand and Gravel Extraction In Unallocated Land
Proposals for sand and gravel extraction falling outside allocated areas will not be permitted
unless it is evident that existing permitted reserves and the remaining allocations cannot sustain
an adequate landbank and processing capacity as provided for in Policy M6.2.
Nottinghamshire Emerging Core Strategy
2.4.27 Policy SP1 – Sustainable Development
1. When considering development proposals the Council will take a positive approach that
reflects the presumption in favour of sustainable development contained in the National Planning
Policy Framework. The Council will work proactively with applicants jointly to find solutions which
mean that proposals can be approved wherever possible, and to secure development that
improves the economic, social and environmental conditions in the area.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
57
2. Planning applications that accord with the policies in this Local Plan (and, where relevant, with
policies in other plans which form part of the development plan) will be approved unless material
considerations indicate otherwise.
2.4.28 Policy SP2 – Biodiversity-Led Restoration
1. Restoration schemes contributing to the delivery of habitat creation targets within the
Nottinghamshire Local Biodiversity Action Plan and contribute to the delivery of the Trent Valley
Biodiversity Opportunity Mapping Project shall be supported where appropriate, unless the need
for non-biodiversity restoration can be clearly demonstrated.
2. Where appropriate, schemes will be expected to demonstrate how restoration will contribute to
the delivery of the Water Framework Directive targets.
3. Restoration schemes for allocated sites should be in line with the relevant Site Restoration
Brief.
2.4.29 Policy Sp3 – Climate Change
1. All minerals development, including site preparation, operational practices and restoration
proposals should minimise their impact on the causes of climate change for the lifetime of the
development. Where applicable development should assist in the reduction of vulnerability and
provide resilience to the impacts of climate change by:
a) Being located, designed and operated to help reduce greenhouse gas emissions and move
towards a low-carbon economy;
b) Avoiding areas of vulnerability to climate change and flood risk. Where avoidance is not
possible, impacts should be fully mitigated;
c) Developing restoration schemes which will contribute to addressing future climate change
adaptation.
2.4.30 Policy SP4 – Minerals Provision
1. The strategy for the supply of minerals in Nottinghamshire is as follows:
a) Identify suitable land for mineral extraction to maintain an adequate and steady supply of
minerals during the plan period;
b) Give priority to the extension of existing sites, where economically, socially and
environmentally acceptable;
c) Allow for development on non-allocated sites where a need can be demonstrated; and
d) Ensure the provision of minerals in the plan remains in-line with wider economic trends through
regular monitoring.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
58
2. All proposals for mineral development must demonstrate that they have prioritized the
avoidance of adverse social, economic and environmental impacts of the proposed development,
or make use of appropriate mitigation measures
2.4.31 Policy MP1; Aggregate Provision
To meet identified levels of demand for aggregate mineral over the plan period (2012-2030) the
following provision will be made;
49.02 million tonnes of sand and gravel
8.74 Million tonnes of Sherwood Sandstone
1.52 Million tonnes of Limestone
The County Council will make provision for the maintenance of landbanks of at least 7 years for
sand and gravel and Sherwood Sandstone and at Least 10years for Limestone, whilst
endeavouring to maintain a steady and adequate supply over the plan period.
Proposals for aggregate extraction outside those areas identified in policies MP2, MP3 and MP4
will be supported where it can be demonstrated there is an identified shortfall in the landbank.
2.4.32 Policy MP2; Sand and Gravel provision
An adequate supply of sand and gravel will be identified to meet expected demand over the plan
period from;
The extraction of remaining reserves at the following permitted sites;
SGk East Leake
The following extensions to existing sites and new Greenfield sites
MP2K East Leake East…
2.4.33 Policy DM1; Protecting Local Amenity
Proposals for minerals development will be supported where it can be demonstrated that any
potential adverse impacts on amenity associated with the following considerations are avoided
and or adequately mitigated to an acceptable level;
Visual Intrusion
Noise
Blast vibration
Dust
Air emissions
Lighting
Transport
Proximity to properties
Stability of the land at and around the site both above and below ground level
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
59
2.4.34 Policy DM2; Water resources and flood risk
Water resources
1 Proposals for minerals development will be supported where it can be demonstrated that;
Surface water flows at or in the vicinity of the site are not detrimentally altered;
Groundwater quality and levels where critical and are not altered;
There are no risks to polluting ground or surface waters;
Water resources, where required should be used as efficiently as possible
Flooding
Proposals for mineral development will be supported where it can be demonstrated there will be
no unacceptable impact on;
Flood flows and storage capacity
The integrity of function of flood defence or structures acting as flood defence
Local land drainage systems
Local communities
Where the opportunity exists restoration proposals should seek to incorporate flood risk reduction
measures e.g. flood plain storage, flood defence structures, land management land practices etc.
to benefit local communities
Proposals for mineral extraction that increase flood risk to local communities must be fully
mitigated
Proposals for minerals development should consider the potential for flood storage schemes to
be incorporated into restoration proposals to reduce future flooding issues.
Minerals development should include sustainable drainage systems (SuDS) to manage surface
water drainage.
2.4.35 Policy DM3: Agricultural Land and Soil Quality
Agricultural land
1. Proposals for minerals development located in the best and most versatile agricultural land
(grades 1, 2 and 3a) will only be supported where it can be demonstrated that:
a. There is no available alternative and the need for development outweighs the adverse impact
upon agricultural land quality; or
b. Proposals will not affect the long term agricultural potential of the land; or
c. Alternative land of lower agricultural value has considerations which outweigh the adverse
impact upon agricultural land quality.
2. Where alternative options are limited to varying grades of best and most versatile land, the
development should be located within the lowest grade.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
60
Soil quality
3. Measures will be taken to ensure that soil quality will be adequately protected and maintained
throughout the life of the development and, in particular, during stripping, storage, management
and final placement of soils, subsoils and overburden arising as a result of site operations;
2.4.36 Policy DM4: Protection and Enhancement of Biodiversity and Geodiversity
1. Proposals for minerals development will be supported where it can be demonstrated that:
a) There will be no significant adverse impacts on habitats or species or, where impacts cannot
be avoided, adequate mitigation and/or compensation relative to the importance of the resource
can be put in place; and
b) They will not give rise to any significant effects on the integrity of a European site, either alone
or in combination with other plans or projects, as a result of changes to air or water quality,
hydrology, noise, light and dust and that any impacts identified can be mitigated.
2. Nottinghamshire’s biodiversity and geological resources will be enhanced by ensuring that
minerals development:
a) Retains, protects, restores and enhances features of biodiversity or geological interest, and
provides for appropriate management of these features, and in doing so contributes to targets
within the Nottinghamshire Local Biodiversity Action Plan; or
b) Appropriately mitigates for unavoidable adverse impacts on biodiversity and geology, with
compensatory measures used only as a last resort;
2.4.37 Policy DM5: Landscape Character
1. Proposals for minerals development will be supported where it can be demonstrated that it will
not adversely impact on the character and distinctiveness of the landscape unless there is no
available alternative and the need for development outweighs the landscape interest and the
harmful impacts can be adequately mitigated;
2. Restoration proposals should take account of the relevant landscape character policy area as
set out in the Landscape Character Assessments covering Nottinghamshire and, where
appropriate, the Areas of Multiple Environmental Sensitivity Study.
2.4.38 Policy DM6: Historic Environment
1. Proposals for minerals development will be supported where it can be demonstrated that:
a) The development would protect and where appropriate enhance nationally important historical
assets and their settings;
b) The importance of the development outweighs the significance of any regionally or locally
important designated or non-designated heritage assets that would be directly or indirectly
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
61
affected by the development and where appropriate provision is made for the excavation and
recording of any affected archaeological remains;
2. No development shall take place within the archaeological resource area at South
Muskham.
2.4.39 Policy DM7: Public Access
1. Proposals for minerals development will be supported where it can be demonstrated this will
not have an unacceptable impact, including that upon the enjoyment of use, on the existing public
rights of way network whilst the minerals development is being undertaken.
2. Where this is not practicable, satisfactory proposals for temporary or permanent diversions,
which are of at least an equivalent interest or quality, must be agreed in advance of the
commencement of the proposal.
3. Improvements and enhancements to the rights of way network will be sought and where
possible public access to restored minerals workings will be increased.
2.4.40 Policy DM9: Highways Safety and Vehicle Movements/ Routeing
1. Proposals for minerals development will be supported where it can be demonstrated that:
a) The highway network can satisfactorily and safely accommodate the vehicle movements,
including peaks in vehicle movements, likely to be generated;
b) The transportation of minerals would not cause unacceptable impact on the environment and
disturbance to local amenity;
c) Where appropriate, adequate vehicle routeing schemes have been put in place to minimise the
impact of traffic on local communities;
d) Measures have been put in place to prevent material such as mud contaminating public
highways.
2.4.41 Policy DM10: Planning Obligations
1. The County Council will seek to negotiate planning obligations as measures for controlling
mineral operations and to secure sustainable development objectives which cannot be achieved
by the use of planning conditions.
2.4.42 Policy DM11: Restoration, After-Use and After-Care
1. Proposals for minerals development will be supported where it can be demonstrated that the
scheme includes details to allow an appropriate phased sequence of extraction, restoration, after-
use and after-care which will enable long-term maintenance and enhancement of the
environment.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
62
Restoration
2. Where it is impracticable to submit full restoration details at the planning stage proposals
should include:
a) An overall concept plan with sufficient detail to demonstrate that the scheme is feasible in both
technical and economic terms; and
b) Illustrative details of contouring, landscaping and any other relevant information as appropriate.
3. Mineral extraction proposals which rely on the importation of waste for restoration must:
a) Include satisfactory evidence that the waste will be available over an appropriate timescale in
the types and quantities assumed;
b) Provide the optimum reclamation solution; and
c) Provide evidence that it is not practical to re-use or recycle the waste.
After-use
4. Where proposals for the after use includes habitat creation, applicants will be required to
demonstrate how they contribute to the delivery of the Nottinghamshire
Local Biodiversity Action Plan and have regard to the biodiversity led restoration strategy.
5. Where proposals for the after use is agricultural, applicants will be required to make provision
for the retention or replacement of soils and any necessary drainage, access, hedges and fences.
6. The after-use will be required to have regard to the wider context of the site, in terms of the
character of the surrounding landscape and historic environment and existing land uses in the
area.
7. Where opportunities arise, after-use proposals should provide benefits to the local and wider
community which may include enhancement and creation of biodiversity and geodiversity
interests, linking of site restoration to other green infrastructure initiatives, enhanced landscape
character, improved public access, employment, tourism or provision of climate change mitigation
measures.
Aftercare
8. Restoration proposals will be subject to a minimum five year period of aftercare.
Where proposals or elements of proposals, such as features of biodiversity interest, require a
longer period of management the proposal will only be permitted if it includes details the period of
extended aftercare and how this will be achieved.
2.4.43 Policy DM12: Airfield Safeguarding (Bird Strike)
1. Proposals for minerals development within the following Airfield Safeguarding
Areas will be supported where the applicant can demonstrate that the proposed extraction,
restoration and after use will not constitute a hazard to air traffic:
a) East Midlands Airport;
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
63
b) Gamston (Retford) Airport;
c) Hucknall Aerodrome;
d) Netherthorpe Airfield;
e) Nottingham City Airport;
f) Robin Hood Airport Doncaster Sheffield;
g) RAF Scampton MoD Aerodrome;
h) RAF Syerston MoD Aerodrome;
i) RAF Waddington MoD Aerodrome.
Any new safeguarding area notified to the Council during the Plan period will also be
safeguarded.
2. All proposals within the safeguarding zones will be required to consult the relevant airfields.
Rushcliffe Replacement Local Plan
2.4.44 Under the Planning and Compulsory Purchase Act 2004, which brought in the system of Local
Development Frameworks (LDF), the policies in the adopted Rushcliffe Replacement Local Plan
(1996) would expire on the 27 September 2007 unless they have been formally saved.
2.4.45 The Secretary of State’s assessment of whether saved policies should be extended is based
upon the criteria set out in Planning Policy Statement 12 and the Department for Communities
and Local Government Protocol on saving policies. The Policies of the Rushcliffe Replacement
Local Plan (1996) which the Secretary of State proposes to save are as follows;
• ENV15 GREEN BELT.
• H1 HOUSING ALLOCATIONS.
• E1 EMPLOYMENT LAND PROVISION.
• E4 TOLLERTON AIRFIELD.
• E7 REDEVELOPMENT OF EMPLOYMENT SITES.
• E8 LANGAR AIRFIELD.
2.4.46 None of the saved polices have any direct relevance to the proposed extension to East Leake
Quarry.
2.4.47 Rushcliffe Borough Council Emerging Core Strategy includes polices enhancing biodiversity
(Policy 16) and Landscape (Policy 15). The Strategy also considers transport infrastructure /
travel demands, design and enhancing local identity and the spatial vision for Rushcliffe.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
64
Policy Summary
2.4.48 Although the proposed application is a departure to the adopted Minerals Local Plan, the land is
being promoted in the forth coming Local Development Plan (Local Plan). The extension to sand
and gravel is considered a sustainable option to meeting the apportionment figures of the
County’s sand and gravel targets for the forthcoming plan period. The site would be an extension
to the existing quarry utilising existing infrastructure and mitigation measures already in place.
2.4.49 This application is to extend sand and gravel on land to the east of the existing plant covering an
area of 27.5h for additional period of 10-12y utilising existing infrastructure. To sterilize the
remaining reserve is not considered sustainable, existing infrastructure, services and local market
enable the continuation of extraction until all permitted reserves be exhausted as the most
appropriate course of action and sustainable development. The existing operations are
undertaken to a high environmental standard protecting, minimising and mitigating any adverse
impacts on the local environment and sensitive receptors. Restoration provides the opportunity to
develop water conservation whilst restoring part of the land to agriculture complementing the
existing landscape character.
2.4.50 The proposed scheme seeks to increase screening to that already permitted and to maintain
existing hedgerow and mature trees. No additional plant, buildings or structures would be erected
as part of the proposed development. The existing plant which is well screened would continue to
be used for the processing of material extracted.
2.4.51 The proposed extension to mineral workings should not cause a noise nuisance at sensitive
receptors. The site can demonstrated that current mineral operations do not cause any exceeded
noise levels and operations shall continue in a similar manner. The main noise source is the
A6006 which is representative in the noise report.
2.4.52 All surface water shall be collected on site and filter through the void and pumped to the existing
water management system. There are no chemicals to be stored on site that could pollute ground
or surface waters. All fuels are placed in concrete bases and bunded in line with Environment
Agency standards.
2.4.53 The proposed application would not increase impact upon traffic movements or vehicular access.
The site would continue to use the existing access, wheel wash and routing agreement. There
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
65
would be no increase in HGV movements to and from the site. It is considered that the existing
access is suitable to continue HGV movements subject to approved routing agreements.
2.4.54 The proposed development shall have a short to medium impact upon the local landscape and
cause some visual intrusion to upper view points along the A60 and A6006. It is considered the
long term landscape impact would be minimal through the reintroduction of agricultural land,
woodland and hedgerow. The site is not located on a SSSI or local Designated Area. The site is
of limited ecological value and any mitigation measures would be implemented to ensure no
protected species are affected. The final restoration has been designed taking into consideration
bird strike potential whilst also trying to achieve local bio-diversity action plan targets e.g.
woodland, hedgerow, field margins and reedbeds.
2.4.55 The extraction area is location within 1km of Stanford Hall and 200m of St Peter’s Church. The
site shall be subject to a watching brief approved by the Mineral Planning Authority and any
development shall be undertaken in accordance with that plan.
2.4.56 The proposed development shall take full regard to the correct measures of reclaiming the land
through DEFRA’s good practice guide to soil replacements. It is proposed that the site be
restored to agriculture and nature conservation. Once restoration has been completed the site
shall be managed for successful after-use.
2.4.57 The Company has taken into consideration mineral safeguarding of the surrounding British
Gypsum which is a finite resource of regional and national importance. The proposed sand and
gravel extraction and restoration shall not impede permitted British Gypsum reserves at East
Leake as the operation shall maintain the necessary standoff of 30-35m. The Company has
sought comments from British Gypsum and no objections have been raised and it is considered
both operations can operate with impacting the safety of the mine.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
66
3.0 PART THREE (C) – SUMMARY
3.1 BENEFITS OF THE DEVELOPMENT
3.3.1 Quarrying is a traditional rural activity. The existing quarry directly employs a maximum of 6 full
time staff. The Quarry’s employees live within a close proximity of the quarry.
3.3.2 The application proposals are an extension of operations at the East Leake Quarry and would
enable retention of existing jobs for a further period of around 10-12years. The quarry would also
allow the continued supply of construction materials to the established local markets and thus
continue contributing to the local economy by way of providing the means for development to be
undertaken, the use of local services, payment of business rates and use of local contractors.
3.2 STATEMENT OF COMMUNITY INVOLVEMENT
3.2.1 As part of producing the application to extend mineral extraction at East Leake Quarry the
company presented the proposed scheme at a public exhibition at Rempstone Village Hall.
Neighbour notification letters were distributed to surrounding properties around the existing
quarry and proposed extension, and properties near the cross roads within Rempstone. Notices
of the exhibition were also displayed on public notice boards at East Leake Parish Council,
Rempstone Village Hall and the White Horse Public House Rempstone. Email notification was
also undertaken to local Councillor’s, Parish Councils and Nottinghamshire Parish Council.
3.2.2 The public exhibition was undertaken at Rempstone Village Hall on 20 May 2014 between 2-8pm.
Exhibition boards were displayed (as shown in App 12 ???of Volume 2 ES) and leaflets which
were also left for the following coffee morning. Approximately 25 people attended and the general
comments received included continued assess of Rempstone Right of Way FP1, reduction of
reserving vehicle alarms, continuation of plant within the current location and retention of soil
bund along Sheepwash Brook. No negative comments were received regarding current
operations, noise, dust or vehicle movements.
EAST LEAKE QUARRY – REMPSTONE SAND AND GRAVEL
EXTENSION – PLANNING STATEMENT 2014
67
3.3 CONCLUSION
3.3.1 It is clear that this development offers consideration benefits. Extending the life of the existing
mineral extraction operations at the site ensures continued employment for quarry staff. It also
offers the best opportunity in terms of sustainable development as an extension takes advantage
of existing quarry infrastructure and proximity to the local markets of Nottinghamshire and
Leicestershire. Furthermore restoration of the site will significantly enhance the habitat quality of
the site increasing local biodiversity. It will also establish more diverse and consequently,
sustainable farming opportunities on site.
3.3.2 The proposed extension takes into consideration all material considerations and environmental
impacts and it is therefore considered that with suitable mitigation measures and best practice
there shall be no significant impact in accordance with planning policy.
3.3.3 Therefore the proposed development offers opportunity with many environmental and social
advantages that meet the key principles of Government aims for sustainable development.