Earthing Desing v42-255

Embed Size (px)

Citation preview

  • 7/28/2019 Earthing Desing v42-255

    1/5

    AbstractElectrical railway system relies on the tractionsubstation to enhance its voltage operation. Performing High Voltage

    (HV) maintenance with a multicraft work force creates a special set

    of safety Challenges. The safety aspect will be discussed in this paper

    from an earthing point of view. An effective approach to design the

    earthing system of the traction substation will be proposed and

    explained. Finally, this paper provides an analytical example to the

    proposed method.

    KeywordsSoil Resistivity, Earthing Design, OHEW.

    I. INTRODUCTIONLECTRICAL Railway employ traction substations to

    advance the operational voltage of their trains, the traction

    substation play an imperative role in ornamental the power

    capability of the catenary line. Many of those traction

    substations are located in the vicinity of resident, some are

    few meters away. The safety of the people as well as the

    workers must be carefully addressed to guarantee the safe

    operation of those traction substations. Earthing design is one

    of the main areas of concerns when it comes to the control andthe safety of the traction substation. Earthing system provides

    a safe working environment for workers and people passing

    by during a fault or malfunction of the power system.

    Some of these traction substations are fed through a feeder

    without the existing of the over head earth wire (OHEW),

    meaning that the entire fault current will reach the earth grid

    and create a danger earth potential rise (EPR). Some utility

    design and install a continuous OHEW between the traction

    substation and the supplier, others choose to install OHEW for

    few hundred meters on both side of the traction substation to

    expand the substation grid. These OHEW with its associated

    electrode assist the substation earth grid in the debauchery of

    the fault current and enhance the touch, step and EPR voltage.

    This paper will converse the case where the substation is be

    fed by a feeder without the OHEW, the study will include the

    OHEW for few hundred meters both side of the substation.

    Also this paper shows significant between different

    approaches when it comes to simulation the earth grid.

    M. Nassereddine, Research student at the University of Western Sydney,

    Australia (e-mail: [email protected])

    A. Hellany, Senior lecture at the University of Western Sydney, Australia

    (e-mail: [email protected])

    II. SOIL RESISTIVITYBefore departing into the detail design of the earth grid, it is

    imperative to study the ground around the site. Soil resistivity

    plays a fundamental part in determining the earthing grid

    details, soil resistivity can be carried out using different

    method, it is essential for an efficient earthing design to have

    more than a test carried out onsite, it is suggested to carry at

    least two tests if possible as shown in figure 1, also it is to thebenefit of the design if a longer test can be carried out, test

    around 100 meters if possible to give more accurate reading

    for the bottom layer.

    Fig. 1 Soil Resistivity test layout for a proposed site

    Below is the most three popular methods to perform soil

    resistivity test:

    Wenner method

    Wenner method consists of four electrodes; two are for

    current injection and two for potential measurement [1], as

    shown in figure 2.

    Fig. 2 Wenner four probe arrangement

    The soil resistivity formula related to Wenner method is

    shown in equation 1.

    aR 2= (1)

    OHEW Earthing Design Methodology of

    Traction SubstationA. Hellany M., Nassereddine

    E

    World Academy of Science, Engineering and Technology 42 2010

    1630

  • 7/28/2019 Earthing Desing v42-255

    2/5

    Where

    R is the resistance measured by the machine,

    a is the spacing of the probe

    Wenner array is considered to be the least efficient from

    labour perspective as it requires four people to perform the

    task in a short time. On the other hand it is considered to bethe most competent method when it comes to ration of

    received voltage per unit of transmitted current. [2]

    Schlumberger Array

    This method is more economical when it comes to the man

    power when compared to Wenner method. The outer electrode

    can be moved four or five times for each move of the inner

    electrode [2]. As shown in figure 3 Schlumberger method can

    be performed. This method can incur an error is the top layer

    is of high resistivity. Every machine has maximum loop

    impedance, in some cases where the soil resistivity of the top

    layer is very high, that will lead to loop impedance higher that

    the maximum loop impedance of the machine. In this case

    the reciprocity theorem can be applied to the Schlumbergerarray, this method is known as the Inverse Schlumberger

    Array (ISA), this method provides a safer working

    environment for the tester under high current supply also

    reduce the heavier cable may be needed during the test. The

    soil resistivity can be calculated using equation 2: [2-4]

    l

    RL

    2

    2

    = (2)

    Where:

    L is the distance the centre from the outer probe

    l distance to the centre from the inner probe

    Fig. 3 Schlumberger Array layout

    Driven Rod Method

    This method is also known as the three probe method or

    three pin method [5]. This method is mainly suitable for an

    area where the physical layout makes the usage of the Wenner

    and Schlumberger methods are difficult; equation 3 can be

    used to compute the soil resistivity under this method:

    =

    d

    l

    lR

    8ln

    2 (3)

    Where:

    l is the length of driven rod in contact with earthd driven rod diameter

    Fig. 4 Driven Rod test layout

    After completion the soil Resistivity test, using software to

    determine the soil structure or can be done using handcalculation relaying on IEEE standards. After the agreement

    on the soil structure it is possible to compute the grid

    resistance or the electrode resistance using one the following

    formulas.

    Equation 4 can be used to compute the earth grid of a mesh

    that buried at a depth of 0.5 meter:

    = 1

    )(

    4ln

    5.0dh

    L

    LR

    (4)

    Where

    h is the buried depthL length of the electrode

    d diameter of the electrode

    Equation 5 can be used to compute the resistance of a grid

    consisted of multiple electrode in parallel.

    = 1

    2ln

    b

    L

    LR

    (5)

    Where

    L is the buried length of the electrode

    b equivalent radius off the electrode at the surface

    ( )5.02

    2

    25.0

    )4( shS

    dhsSb

    +=

    =(6)

    Where:

    d is the diameter of the electrode

    h buried depth

    s distance between 2 parallel electrode

    S distance from one electrode to the image of the other in

    meters

    Equation 7 can be used to calculate the resistance of the

    electrode at each pole of the OHEW:

    World Academy of Science, Engineering and Technology 42 2010

    1631

  • 7/28/2019 Earthing Desing v42-255

    3/5

    = 1

    8ln

    2 d

    L

    LRg

    (7)

    Where

    L is the buried length of the electrode in meters

    D the diameter of the electrode in meters

    III. SOIL RESISTIVITY TEST VERIFICATIONIt is recommended by IEEE and Australian standards, to

    bear a method to verify the soil Resistivity test results; one of

    these methods could be the fall of potential. For this method to

    convene its purpose it is vital to swipe for the area metal

    detector to ensure that there is no intrusion from any metal

    objects in the area. It is recommended to drive an electrode or

    cupper stick to a depth of more than 0.5 meters in the ground,

    the deeper the electrode the more accurate are the results.

    This method can be carried out using the same machine for

    the soil Resistivity test such as SYSCAL, figure 5 shows the

    layout of the fall of potential test. Figure 6 shows the layout ofthe result of the test:

    Fig. 5 fall of potential test.

    Fig. 6 Result of the fall of potential test.

    A similar electrode characteristic will be used in a

    simulation process to determine the best soil structure for the

    site. This can be done by matching the fall of potential test

    with the simulated one. This method will assist in

    determining the most accurate soil profile for the designed

    substation.

    IV. SAFETY IN EARTHINGThe main reason behind the design of an earth grid is to

    achieve a safe working and living environment. According to

    many standards, such as IEEE and Australian standards, the

    hazard can jeopardise two categories of people:

    The public that can be affected by the step and touchvoltage. (50kg person)

    Workers who can be affected by the step and touchvoltage as well as the earth potential rise (EPR) zone.

    (70kg person)

    It is a common practice, as per IEEE and AustralianStandard, to compute the step and touch voltages using the

    following equations.

    t

    CV sstouchkg

    174.011650

    += (8)

    t

    CV ssstepkg

    696.011650

    += (9)

    t

    CV sstouchkg

    236.015770

    += (10)

    t

    CV ssstepkg

    942.015770

    += (11)

    09.02

    109.0

    1+

    =s

    s

    sh

    C

    (12)

    Where

    Cs is the de-rating factor relating to surface layer thickness

    and resistivity

    s is the top surface layer

    t is the primary clearance time

    V. EARTHING DESIGNAs mentioned before, this paper will discuss the earthing

    study of a traction substation fed by a 33kV line and its

    associated feeder with few hundred meters of OHEW at both

    side of the substation. Figure 7 shows the proposed layout of

    the design; it shows the substation grid, the feeder and the

    OHEW with its associated electrode. The OHEW is extended

    for a length of 1000 meters at each end of the site with a 100

    meters separation between poles.

    Some designers break the system into two sections, theOHEW of the feeder and the substation earth grid, this could

    lead to an over engineered design or to unsafe environment

    They use the split study to determine the current into the grid,

    and then using this split current to compute the EPR in the

    substation using the stand alone earth grid resistance

    They consider this EPR to be the maximum EPR for the

    system which lead to the assumption that is the maximum

    EPR that can be transferred to each electrode at each pole of

    the feeder. The design will be safe but way over engineered as

    will be shown further in the study. The substation grid and the

    OHEW on both sides must be part of the simulation design at

    all time, including the substation grid with the OHEW. During

    the simulation of the fault this will give more accurate reading

    World Academy of Science, Engineering and Technology 42 2010

    1632

  • 7/28/2019 Earthing Desing v42-255

    4/5

    for the touch voltage, step voltage and EPR in and around the

    nominated site.

    Fig. 7 the proposed layout for the traction substation

    When the traction substation is being fed from one side, the

    split current will determine the return in the OHEW of the

    feeding side. The mutual impedance between the faulted line

    and the OHEW of the feeding side will have an influence on

    the return current. Also the split study will not determine theground current into the substation earth grid.

    For example if 40% of the current return in the OHEW, that

    doesnt mean that 60% goes into the substation earth grid as

    some will be dissipated in the OHEW on the other side of the

    substation. This side does not have any mutual impedance

    from the fault current as there is no parallel section between

    this side and the faulted line. The OHEW in the opposite side

    of the fault will act as an extended grid to the substation. This

    shows that a one simulation that tables the entire system

    (substation grid and OHEW) will have a more efficient

    earthing study.

    Figure 8 shows the electrical circuit of the designed system.

    It does not show the electrode for the poles, but shows thefaulted line impedance, the substation earth grid and the

    OHEW impedance at both end of the substation. The mutual

    impedance exist between the Z-OHEW and Z-Transmission-

    line and can be determined using equation 13, the split current

    can be found using equation 15

    Fig. 8 The single line diagram of the OHEW and earth grid

    ++=

    GM

    e

    gwgw

    R

    Dfj

    fRZ

    10

    7

    7

    log10938.28

    1088.9

    (13)

    fDe

    4.658= (14)

    gwZ self impedance of the OHEW in Ohms/m

    GMR is the geometric mean radius of the OHEW in m

    f is the frequency

    efg III = (15)

    Where;

    gI Is the ground current

    eI Is the current that return in the OHEW

    eI is the current that return in the OHEW Figure 5 shows

    Ie and Ig can be determined using the following

    equation:

    f

    gw

    gm

    ge

    gm

    fe IZ

    Z

    RZ

    RZII

    = (16)

    Where

    mZ mutual impedance between phase conductors and

    OHEW in Ohms

    eZ input impedance of the OHEW in Ohms

    gR resistance of the earth grid in Ohms

    gmZ mutual impedance per meter between OHEW and

    phase conductors in Ohms/m

    The two facts below can lead to an EPR at the last electrode

    of the 1000 meters of OHEW much higher than the one at the

    substation:

    The electrode resistance of the poles will be muchhigher than the substation earth resistance.

    The OHEW is not continuous to the supplier. OHEW current will dissipate in the last electrode.The case study will discuss two different scenarios and

    explain how that impacts the substation.

    VI. CASE STUDYThe case study will be conducted under the following terms:

    Stand alone substation earth grid is 0.5 OhmPole electrode resistance of 10 OhmsBee OHEW AAC 7/4.9Pole separation of 100 metersSL-Ground fault current of 2000ASplit factor of 0.4The Bee OHEW has a resistance of 0.268 Ohms/km. The

    maximum EPR at the substation can be computed to be 400V.

    Figure 9 shows the studied circuit for one side of the

    substation. Using circuit analysis considering that Ie is 1000A,

    the 200A assumed to be utilised by the OHEW on the other

    side.

    OHEWea ZIEPRV = (17)

    OHEWa

    eab ZRt

    VIVV

    = (18)

    gwOHEW ZZ = (19)

    World Academy of Science, Engineering and Technology 42 2010

    1633

  • 7/28/2019 Earthing Desing v42-255

    5/5

    gwR is the self resistance of the OHEW in Ohms/m. Similar

    analysis will be carried out on the circuit in figure 9 using the

    400 EPR at the substation as the voltage source:

    VVa 322=

    VVb 261=

    VVc 86

    AIFinal 759

    The voltage at point c

    VRtIV Finalc 759010759

    This proves that the maximum EPR under the single line to

    ground fault is 7590 V and not the 400 volts drop at the

    substation. Under the condition where eI is forced to the

    OHEW, equation 20 will determine the number of poles

    needed to have electrode and OHEW,

    OHEW

    i

    k

    k

    eii ZRt

    V

    IVV

    =

    =

    1

    11 (20)

    RtIV ii = (21)

    Rt

    V

    II

    i

    k

    k

    eFinal

    ==

    1

    1 (22)

    ==n

    k

    keFinal VRtIV1

    (23)

    i : represent the pole numbers

    iI : represent the current in i the electrode

    FinalI : represent the current in the last electrode

    The voltage drop at the substation must be bigger than the

    drop voltage at the electrode as shown in equation 24

    =

    >>1

    1

    i

    k

    ke VRtIEPR (24)

    This condition can occur under the following conditions

    (otherwise the maximum EPR will occur on the electrode and

    not the substation): Existing of a large number or electrode Small return current Small electrode resistance

    Under the assumption that the voltage drop across the

    electrode is almost the same for the ten electrodes, the number

    of electrode is ten, figure 10 shows the relation between the

    OHEW current and the number of electrode needed to

    dissipate the current. This figure is under the assumption

    where the voltage drop across the electrodes is of the EPR

    at the substation on average

    n number or electrode

    0

    50

    100

    150

    200

    250

    300

    350

    400

    0 500 1000 1500 2000 2500 3000

    OHEW current (A)

    NumberofElect

    rode

    Fig. 10 the number of electrode against the OHEW current

    VII. CONCLUSIONIn conclusion this paper shows that the design, of an earthing

    system for a traction substation with few hundred meters of

    OHEW at each end, needs to be assessed as part of the grid tooptimize the design and to eliminate any dangerous situations.

    In Addition, this paper shoes that the attempt to compute the

    EPR in the substation using the stand alone earth grid

    resistance will lead to an over engineered design or to unsafe

    environment and create a false assumption that the maximum

    EPR that can be transferred to each electrode at each pole of

    the feeder.

    REFERENCES

    [1].IEEE guide to safety in AC substation grounding, 2000 (IEEE, NewYork, 2000)

    [2].AS/NZS 4853:2000 electrical hazards on metallic pipelines.[3].M. Nassereddine, A. Hellany, How to design an effective earthingsystem to ensure the safety of the people ACTEA conference, conference

    proceedings pp. 112-116, July 2009.

    [4].M. Nassereddine, A. Hellany, AC interference study on pipeline: theimpact of the OHEW under full load and fault current computer andelectrical engineering, 2009. ICCEE, Vol 1, 28-30 Dec. 2009 Pages:497-501

    [5].M. Nassereddine, A. Hellany, Designing a lightning protection systemusing the rolling sphere method computer and electrical engineering,2009. ICCEE, Vol 1, 28-30 Dec. 2009 Pages:502-506

    [6].R. Hans, A practical approach for computation of grid current, IEEEtransactions on power delivery, Vol. 14, No. 3, July 1999.

    [7].C.N. Chang, computation of current-division factors and assessment ofearth-grid safety at 161/69kV indoor-type and outdoor-type substations

    IEE proc.-Gener. Transm. Distrib., Vol. 152, No. 6, November 2005.

    [8].A. Campoccia, A method to evaluate voltages to earth during an earthfault in an HV network in a system of interconnected earth electrodes of

    MV/LV substations IEEE transactions on power delivery, Vol. 23, No. 4,

    Oct 2008.

    [9].S. Mangione, A simple method for evaluation ground fault currenttransfer at the transition station of a combined overhead-cable line, IEEE

    transaction on power delivery, Vol. 23, No, 3, July 2008.

    [10]. E. Viel, Fault current distribution in HV cable systems IEE proc-Gener. Transmission distribution, Vol. 147, No. 4, July 2000.

    [11]. L. D. Grcev, Transient electromagnetic fields near large earthingsystems IEEE transactions on magnetic, VOL. 32 No. 3, May 1996.

    [12]. F. Dawalibi, Measurements and computations of fault currentdistribution on overhead transmission lines IEEE on transactions on

    power apparatus and systems, Vol. PAS-103, No. 3, March 1984.

    World Academy of Science, Engineering and Technology 42 2010

    1634