View
215
Download
0
Tags:
Embed Size (px)
Citation preview
Earned Value Managementmade Simple
Keith Lee, SAP Systems Integration AmericaJay Wilson, SAP Labs
Session 3802Monday May 19, 200311:20 AM to 12:50 PM
Content Area: Project Systems
Objectives
Understand Basics of Earned Value Management Systems (EVMS)
Understand SAP/R3 approach to EVMS
Learn Simple steps to configure EVMS in SAP/R3
Become Aware of Options to approaching EVMS in SAP/R3
Earned Value Management is the analysis of work completed compared compared to the amount of work planned and the cost of the work.
Simple example: The task is creating a 10 foot Wall and takes $1000 (material and labor)
1. Prepare Ground – 10%2. Pour Concrete Base – 20%3. Every foot of wall – 7%
In this example, when completed with the first 2 steps and 3 feet of wall the amount of work complete is 30% + 21% = $510.
What is Earned Value?
What is Earned Value?
• There are lots of ways to measure Earned Value.
• The wall example uses a combination of milestones (first 2 steps) and counts (feet of wall)
• The simplest approach is to use “estimate”. I am 70% complete because I say so.
Why use EVMS?
• Given: – total budget of $1000– 5 months effort– produce 10’ brick wall
• Status:– spent to date: $700– time elapsed: 4 months– Wall in process
• How are you doing, and how do you know how you are doing?
• How far along are you? (75%, 50%, >40%)
Life without EVMS
Why use EVMS?
• Early and accurate identification of trends and problems
• Accurate picture of contract status– cost, schedule, and technical
• Basis for course correction• Supports mutual goals of contractor and
customer– bring project in on schedule and cost
Five Basic Elements
BCWS Budgeted Cost of Work Scheduled
BCWP Budgeted Cost of Work Performed
ACWP Actual Cost of Work Performed
BAC Budget at Completion
EAC Estimate at Completion
A Spectrum of Implementation
Where
When
Core EV PrinciplesANSI/EIA-748-1998
(32 criteria)Tailored Applications
Small Companies Larger Companies
Major Defense
Contractors
as desired
Government Organic
Reports
Foreign Countries
streamlined, no paper?
corporate policy,
“enterprise wide”
DoD Non-Major Contracts
(>12 months)
<$6M* >$6M
DoD Major Contracts
>$70M RDT&E
>$300M Prod
tailored to needs C/SSR CPR
FFP contracts?
Commercial or Defense
SAP Approach to EVMS
• Integrated with all financials and schedule.
SAP Approach to EVMS
• Calculate both BCWS and BCWP based on a “Baseline” cost Plan using an Earned Value Method.
Period Plan $ BCWS % BCWP % BCWS $ BCWP $1 300$ 30% 10% 300$ 100$ 2 150$ 15% 20% 150$ 200$ 3 200$ 20% 14% 200$ 140$ 4 200$ 20% 7% 200$ 70$ 5 150$ 15% 150$
SAP Approach to EVMS
• Calculate ALL elements of cost for an object using the same percentage
Period Plan Mat $ Plan Lab $ BCWP % BCWP Mat $ BCWP Lab $1 200$ 100$ 10% 35$ 65$ 2 50$ 100$ 20% 70$ 130$ 3 50$ 150$ 14% 49$ 91$ 4 50$ 150$ 7% 25$ 46$ 5 -$ 150$
CONFIGURATION
• Statistical Key Figures (SKF’s)– Use SKF’s to store the planned and actual percent
complete• Versions – Baseline, Progress, EAC, …• EV Methods
– Methods can be tailored and named to suite the client• EV Cost Elements
– Create cost elements that summarize the planned cost elements into groups (ex: Engineering labor, Manufacturing Labor, Materials, G&A, …)
• Value Categories– Make Value categories consistent with the EV cost
elements for ease of reporting
3 different SKF’s are required
Aggrigated – Summary of all percents up the structure based on weighting
Non-Aggrigated – the individual object’s percent complete
Results Analysis – Percent complete used in results analysis (revenue recognition based on EV)
SKF Configuration
Version Configuration
Version Configuration
EV Methods Configuration
EV Cost Elements
EV Cost Elements
Value Categories
Cost Element group should containAll normal cost elementsANDThe earned value cost element
This is the same cost element group as associated with the EV cost element
A Simple Example
• With these few basic configuration settings it is now possible to do Earned Value.
• Now let’s see a simple example– A project with 1 network activity that is 40%
complete– Run EV using CNE1 (Calculate Progress)– See the results
Project Example
Calculate Earned Value
Report
40% of BCWS
Report
What is the good news?What is the bad news?
Questions
Thank you for attending!
Please remember to complete and return your evaluation form following this session.
Session Code: 3802Keith Lee – [email protected] Wilson – [email protected]