Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
E2868
V1
Environmental Impact Assessment Report
for Xiangyang Urban Transportation
Project with World Bank Loan
(FINAL VERSION TO WORLD BANK)
Construction unit: Xiangyang Construction Investment & Operation Co.,
Ltd.
Assessment unit: China Railway Siyuan Survey and Design Group Co., Ltd.
Class A: G.H.P.Z.J.Zi No.2605
September 2011
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
1.0 General description
1.1 General situation of the project
1.1.1 Name of the project
Xiangyang Urban Transportation Project with Loan of World Bank
1.1.2 Composition of the project
Xiangyang Urban Transportation Project with Loan of World Bank, according to the
different administration and implementation organizations, is divided into 4 sub-
projects of public traffic preferential corridor improvement, traffic safety and control,
road perfection as well as the organization development & capacity construction.
1.1.3 Location of the project
All contents of the project are distributed within the scope of Xiangyang urban area,
the newly built roads of the road perfection sub-project in civil works are located at
Pangdong new zone of Xiangcheng District of Xiangyang; The sub-project of public
traffic preferential corridor improvement-the dedicated public traffic road and railway
public traffic hub reconstruction works of Changhong Road section is located within
Fancheng district, newly built Xianshan parking and service yard is located within
Panggong new zone of Xiangcheng district, newly built Xiangyang Economic
Development Zone parking and service yard is inside Shenzhen Industrial Park of
Xiangzhou district. Details refer to the diagram of its geographic location.
1.1.4 Construction unit
Xiangyang Urban Investment & Operation Co., Ltd.
1.1.5 Background of the project
Along with the drawing up of the national strategy of “the growing up of Central
China”, Xiangyang as a sub-central city in Hubei, the most important metropolis in
northwest of Hubei has met with unprecedented development opportunities. Resort to
its unique geographical location and convenient traffic conditions, Xiangyang shall
enjoy with the stronger external radiation and industrial cohesion. At present, the
traffic construction of Xiangyang is faced with austere challenges, the location
advantage shall be changed into the economic advantage only by taking the traffic or
communication as a bridge, and embodying the urban fascination and enhancing the
urban comprehensive competitive power needs to construct a modernized urban
traffic system. In order to improve the urban traffic and urban functions, boost the
construction of the experiment zone reform test of state level of Xiangyang urban
circle, at the same time, it’s necessary to further increase the force or the traffic
construction and meet the traffic demand of continuous development.
In July 2009, at the loan project meeting jointly held by National Development and
Reform Commission and Ministry of Finance, World Bank agreed to the draft
resolution of USD 100,000,000 loan to Xiangfan urban traffic project. At the meeting,
each party planned to submit the project to be built to the board of director of World
Bank for approval, in order to be included into World Bank 2012 financial loan
program.
From Nov. 5~6, 2009, World Bank dispatched the first delegation to Xiangfan for
conducting the preliminary communication for this project.
In May 2010, the Proposal for Utilizing World Bank Loan by Xiangfan Urban Project
Construction by Xiangfan city, Hubei Province was completed.
In Dec. 2010, World Bank further promoted conducting the feasibility study on
Xiangyang Urban Transportation Project with loan of World Bank by Xiangyang,
perfecting the road network system of Panggong area, boosting the construction on
the parking lots and public traffic stations. Greatly implement the strategy of “public
traffic preference”, enhance the public traffic service level. Strengthen the traffic
control and get done with the traffic jam removal and smooth traffic protection work.
1.2 Objective of environmental impact assessment
The construction and operation of the project shall have certain impact on the
environment of the area for building the project, on basis of investigation on the
current situation of the project area, through analysis on its pollution, the assessment
intends to predict the impact of the project construction on the environment, put
forward the feasible measures for controlling the pollution and alleviating the impact,
in order to provide reference to the decision making for the project, guide the design
for its environment protection and the environment management for its construction
period and operation period, enable the construction of the project to reach the
unification of economic benefit, social benefit and environment benefit.
1.3 Guiding ideology
The guiding ideology of the assessment is based on the detailed project analysis, in
accordance with the requirement of Technical Guidance Rules for Environmental
Impact Assessment (HJ/T2.1-93, HJ/T2.3-93, HJ/T2.2-2008, HJ/T2.4-1995, HJ19-
2011) and Environmental Impact Assessment Codes for Highway Construction
Works(trial) (JTJ 005-96), fully utilized the current basic information and use for
reference the related highway construction works assessment results, reasonably
determined the assessment scope, monitoring items. And according to the
characteristics of the project, selected the most representative monitoring locations,
monitoring factors and predictive models. The conclusion would be maximally
scientific, objective, just, clear and reliable.
1.4 Assessment basis
1.4.1 Laws, rules and regulations and policies of the country
(1) Environmental Protection Law of the People’s Republic of China, implemented on
Dev. 26, 1989;
(2) Law of the People’s Republic of China on Environmental Impact Assessment,
implemented on Sept 1, 2003;
(3) Law of the People's Republic of China on the Prevention and Control of
Atmospheric Pollution, implemented on Sept 1, 2000;
(4) Law of the People's Republic of China on Prevention and Control of Pollution
from Environmental Noise, implemented on March 1, 1997;
(5) Law of the People's Republic of China on Prevention and Control of Water
Pollution, revised on Feb. 28, 2008;
(6) Law of the People’s Republic of China on the Prevention and Control of
Environmental Pollution, implemented on April 1, 2005;
(7) Urban and Rural Planning Law of the People’s Republic of China, implemented
on Jan. 1, 2008;
(8) Law of the People's Republic of China on Land Management, implemented on
August 28, 2004;
(9) Law of the People's Republic of China on Water and Soil Conservation,
implemented on June 29, 1991;
(10) The People's Republic of China- State Council (1998) No. 253 order for
Regulations for Environmental Protection Management for the Construction Works,
implemented on Dec. 12, 1998;
(11) Document of State Environmental Protection Administrative Bureau H.F.[2003]
No.94: Notification Relating to Environmental Noise in the Environmental Impact
Assessment for highway, railway (include light railway) and other construction
works;
(12) State Environmental Protection Administrative Bureau H.F. 2006[No. 28]
Tentative Procedure for the Public Participating the Environmental Impact
Assessment; implemented on March 18, 2006.
1.4.2 Local rules, policies and documents
(1) Environmental Protection Regulations of Hubei revised), Hubei Provincial
People’s Standing Commission, implemented on Jan.1, 1998;
(2) Regulations for Atmosphere Pollution Control in Hubei, Hubei Provincial
People’s Congress Standing Commission, implemented on Dec. 3, 1997;
(3) Regulations for Hubei Urban Environmental Noise Control, Hubei Provincial
People’s Congress Standing Commission, implemented on April 1, 1987;
(4) Procedure for Hubei to Implement the People’s Republic of China Water
Pollution Control Law, implemented on Jan. 1, 2001;
(5) Implementation Procedures for Xiangfan Urban Construction Wastes Control,
X.F.Z.F[2005] No.36;
(6) Procedure for Controlling Xiangyang Urban Hightime Construction, Xiangyang
People’s Government ordinance No. 16.
1.4.3 Relevant documents of World Bank
(1) World Bank OP/BP4.01 and appendixes (environmental assessment), Jan. 1999;
(2) World Bank OP/ (environmental assessment), Jan. 1999;
(3) Documents assembly of World Bank environmental impact assessment.
1.4.4 Documents related to the planning and environmental function division
(1) Xiangfan Urban Master Plan (2008—2020);
(2) Xiangfan Overall Planning of Land Uses (1997—2010);
(3) Xiangfan Comprehensive Urban Traffic Planning (2007);
(4) Xiangfan Urban Public Traffic Planning(2007�2020);
(5) Xiangcheng district Planning for Ancient City Protection (2007);
(6) Panggong New Zone Planning (2010);
(7) Xiangfan environmental function division;
(8) Xiangfan statistical yearbook and related statistics bulletin in past years.
1.4.5 The project design information
(1) The Feasibility Study Report on Xiangyang Urban Transportation Project with
World Bank Loan (general report) 2011.8;
(2) The Feasibility Study Report on Xiangyang Urban Transportation Project with
World Bank Loan (sub-project of the road perfection) 2011.8;
(3) The Feasibility Study Report on Xiangyang Urban Transportation Project with
World Bank Loan (sub-project of the urban public traffic) 2011.8;
(4) The Feasibility Study Report on Xiangyang Urban Transportation Project with
World Bank Loan (sub-project of the traffic safety and control) 2011.8.
1.4.6 Technical codes for environmental impact assessment
(1) The People’s Republic of China environmental protection industry standard
HJ/T2.1-93 Environmental Impact Assessment Technical Guide Rules-General
Principles;
(2) The People’s Republic of China environmental protection industry standard
HJ2.2-2008 Environmental Impact Assessment Technical Guide Rules-Atmosphere
environment;
(3) The People’s Republic of China environmental protection industry standard
HJ/T2.3-93 Environmental Impact Assessment Technical Guide Rules-surface water
environment;
(4) The People’s Republic of China environmental protection industry standard
HJ/T2.4-2009 Environmental Impact Assessment Technical Guide Rules·-acoustic
environment;
(5) The People's Republic of China environmental protection industry standard HJ19-
2011 Environmental Impact Assessment Technical Guide Rules-ecological impact;
(6) The People’s Republic of China industrial standard-code for Highway
Construction Environment Impact Assessment (JTG B03-2006).
1.4.7 Standard letters of affirmation
Letters of Xiangyang Environmental Protection Bureau Relating to Environmental
Impact Assessment Implementation Standard for Xiangyang Urban Transportation
Project with World Bank Loan (X.H.P[2011]No.25).
1.5 Assessment rating and scope
1.5.1 The division method stipulated by World Bank OP4.01
According to the division method stipulated by World Bank business handbook—
Environmental Impact Assessment (OP4.01), the assessment type is divided as type
B.
1.5.2 Work class of domestic environmental impact assessment
Work class of domestic environmental impact assessment is different to that of World
Bank, according to technical guide rules of environmental impact assessment of
China, the assessment work classes are divided into 3 classes. According to the
characteristics and the local environmental characteristics of the sub-project to be
constructed, in accordance to the technical guide rules of environmental impact
assessment and code for highway environmental impact assessment on the topic of
each sub-project assessment and the assessment work class, the determined results
refer to table 1-1.
Table 1-1 Assessment topic and assessment work class division
Name of sub-
project
Assessment
topic Rating Rating determination basis
Ecology Class 1
Impact scope<20km2, generated biomass reduced
to<50%, species diversity reduced <50%, no
ecological sensitive area within the project scope.
Noise Class 1
Recent traffic volume in operation is over 10,000
vehicles/day (standard mini-passenger car), within
60m to the road central line with more than 50
households, school and other sensitive object.
Sub-project of
road
perfection
Air Class 1
Recent traffic volume in operation is over 50,000
vehicles/day (standard mini-passenger car), and
within assessment scope with more than 50
households, school and other sensitive object..
Ecology Class 1
Impact scope<20km2, generated biomass reduced
to<50%, species diversity reduced <50%, no
ecological sensitive area within the project scope.
Noise Class 3
Recent traffic volume in operation for each public
traffic station is less than 5,000 vehicles/ day
(standard mini-passenger car).
Air Class 3
Recent traffic volume in operation for each public
traffic station is less than 20,000 vehicles/day
(standard mini-passenger car). Sub-project of
public traffic
Water
environment Class 3
Sewage discharge of each public traffic station
is�200 m3/d, discharged water pollutants are
mainly non-permanent pollutants, water quality
parameters number needs to predict the
concentration is �7, complex degree of sewage
quality is simple, it shall be drained into the
municipal sewage network after the treatment, and
final entered into urban sewage treatment plant.
1.5.3 Assessment scope
According to the provisions of the technical guide rules of environmental impact
assessment, the code to highway construction environmental impact assessment, the
assessment scope determined for assessment this time refers to table 1-2.
Table 1-2 Assessment topic and assessment scope
Name of sub-project Assessment
factors Assessment scope
Ecology Respectively 100m scope at two sides of newly built road central
line and possible area involved by the project construction.
Noise Respectively 200m scope at two side of newly built road central
line.
Vibration Respectively 60m scope at two side of newly built road central line.
Sub-project of road
network perfection
Air Respectively 200m scope at two side of newly built road central
line.
Ecology Public traffic station project scope and its construction possible
involved area.
Noise 60m outside the Public traffic station boundary line
Vibration 60m outside the Public traffic station boundary line
Air Public traffic station project scope and its construction possible
involved area.
Sub-project of public
traffic preferential
corridor
improvement
Water
environment
Not divide the assessment scope, only conduct the discharge
standard qualification analysis.
1.6 Assessment factors
According to the pollution characteristics of the project, through selection and
identification, environmental impact assessment factors of each assessment topic refer
to Table 1-3.
Table 1-3 Summary table for main factors of environmental impact assessment
Assess main factors Assessment
elements Construction period Operation period
Acoustic
environment
Equivalent continuous acoustic
level A Equivalent continuous acoustic level A
Vibration
environment VLzmax VLz10
Water
environment SS, COD, oil, etc.
PH,BOD5,COD, animal and vegetable oil, oil type,
ammonia nitrogen
Environment
air TSP NOX(NO2),CO
Solid wastes Construction waste, domestic
waste
Domestic waste of the public traffic station staff and
passenger carried waste.
Ecological
environment
Water and soil loss, urban
greening Landscape, vegetation recovery.
1.7 Assessment standard
1.7.1 Acoustic environment
According to letters of standard affirmation, assessment adopted acoustic
environmental noise refers to Table 1-4.
Table 1-4 Implemented standards for acoustic environment assessment
Standard No. Standard
name
Standard value and
class
(Type)
Scope of application Remarks
GB3096-2008
Acoustic
environment
quality
standard
Class 4a area:
Daytime 70dB(A)
Night time
55dB(A)
Southeast section of inner ring road, Xingguang
Avenue, Jianghua Road, Xiangyang Road,Zhakou
Road,Panggong Road, planned No.13 road, area of
the building facing to one side of the road.
Next to the
road is 3f or
over building
The adjacent is type 2,3 standard applicable area,
respectively area within 35,25m to the road
boundary line
Next to the
road is 3f or
less building
Class 3 area:
Day time 65dB(A)
Night time
55dB(A)
Scope of industrial area
Class 2 area:
Day time 60dB(A)
Night time
50dB(A)
Other areas and other sensitive points of project
scope
Include
school class
rooms and
hospital
within class 4
area
GB12348-2008
Environment
noise
discharge
standard for
industrial
enterprise
boundary
for industrial
enterprise
boundary
Class 2 area:
Day time 60dB(A)
Night time
50dB(A)
Public traffic station(Xianshan parking and service
yard, Xiangzhou district-Shenzhen Industrial Park
Parking and Service Yard, railway public traffic
hub)1m outside the boundary
GB12523-90
Noise Limits
for
Construction
Site
Earthwork period:
Day time75dB,
Night time 55d B;
Piling period: Day
time 85dB, Night
time no
construction;
Structural period:
Day time
70dB,Night time
55d B;
Decoration period:
Day time 65dB,
Night time 55d B.
With the boundary line of relevant construction site
of sensitive areas
1.7.2 Vibration environment
According to letters of standard affirmation, vibration environment standards refer to
Table 1-5.
Table 1-5 Implemented standards for vibration environment assessment
Standard
No.
Standard
name
Standard value
and class Scope of application
Standard
Selection
basis
Mixed area
standard: Day
time 75dB,
Night time
72dB
Sensitive points located within
noise function division type “2”
area
GB10070-
88
Environment
vibration
standard for
urban area
Industrial area
standard: Day
time75dB, Night
time 72dB
Sensitive points located within
noise function division type “3”
area
Determination
for the
standard class
refers to noise
function area
type
Standard value
for two sides of
primary traffic
road network:
Day time75dB,
Night time
72dB
Sensitive points located within
noise function division type “4a”
area
1.7.3 Water environment
The project is mainly urban road, sewage during construction period and operation
period is sewage pipe network of urban drained sewage, finally entering urban sewage
treatment plant, according to the letter of standard affirmation, sewage discharge
standard is implementing class 3 Standard of sewage comprehensive discharge
standard (GB8978-1996), details refer to Table 1-6.
Table 1-6 Implemented standard for water environment assessment
Standard No. Standard name Standard value
and class Pollutants Standard value(mg/L)
pH 6 9
SS 400
BOD5 300
COD 500
Oil type 20
Animal and
vegetation oil
v���
100
Ammonia nitrogen
/
GB8978-1996
Comprehensive
sewage discharge
standard
Class 3
LAS 20
This project is close to Han River, according to the function division for Xiangyang
earth’s surface water environment, Hanjiang section where the project is located is
type � water body, and the water quality standard refers to Table 1-7.
Table 1-7 Han River water environment quality standard for the project area
Standard No. Standard name
Standard
value and
class
Pollutants Standard value(mg/L)
pH 6~9
SS 0.2
BOD5 4
COD 20
Oil type 0.05
GB3838-2002 Earth’s surface
water
environment
quality standard
Type �
Ammonia nitrogen
1.0
LAS 0.2
1.7.4 Atmosphere environment
According to letters of standard affirmation, atmosphere environment quality standard
for the area along the project shall implement class 2 standard of Ambient Air Quality
Standard (GB3095-1996), details refer to Table 1-8.
Table 1-8 Implemented standard for atmosphere environment assessment
Standard No. Standard name
Standard value and class
Pollutants Standard value(mg/cubic
meter)
Annual mean 0.2 TSP
Daily mean 0.3
Annual mean 0.05
Daily mean 0.10 NOX
1h mean 0.15
Annual mean 0.04
Daily mean 0.08 NO2
1h mean 0.12
Daily mean 4.0
GB3095-1996
Embient air quality standard
Class 2
CO
1h mean 10.0
1.8 Assessment prediction time interval
This assessment time intervals are construction period and operation period.
Construction is same to the project construction period; Operation period is consistent
to vehicle flow prediction year. Namely:
Construction period: 2011y~2015y.
Operation period: 2015y~2020y.
1.9 Emphases of the assessment
According to major potential environment impact of the project and the regional
environment sensitive degree, this assessment takes the topic of the following
environmental impact assessment as emphases of the assessment:
(1)Topic on acoustic environmental impact assessment: Stress on assessing the impact
of the project operation on schools, hospitals and concentrated residents quarters at
two sides of the road.
(2)Topic on urban ecological environmental impact assessment: Mainly analyze the
harmony of the road landscape and the surrounding environment.
(3)Topic on environment air impact assessment: Stress on assessing the impact of
vehicle tail gas on schools, hospitals and concentrated residents quarters at two sides
of the road.
(4)Public participation: Stress on investigation for units, schools, hospitals and
concentrated residents quarters at two sides of the road.
1.10 Assessment technical method
According to the principle of “based on the point, combining point with the line and
feedback of whole line, it’s adopted mode calculation, analog method and
investigation and research method for conducting assessment.
Ecological environment is adopted the method of data collection and diagnosis; water
environment assessment is adopted analog method; Acoustic and atmosphere
environment assessments are adopted mode calculation method; Social environment is
adopted diagnosis method; Risk analysis is adopted the method of probability analysis
combining with mode prediction.
1.11 Identification of the construction project impact elements
According to the construction project nature and the improvement of the traffic
environment and discharge characteristics of pollutants and others, environment
impact elements identification table for the project impact environment is adopted
for identifying the degree and nature of the project impact element on the
environment, identification results refer to Table 1-9, Table 1-10.
Table 1-9 Identification of environment impact element degree of the project
Natural environment Ecological resources Social environment Living quality
Environment
resources Under-
round
hydrolog
y
Undergroun
d
water quality
Surface
hydrology
Surface
Water
quality
Atmospher
e
quality
Noise
environment
Urban
ecology
Fore
st
veg
etat
ion
Wil
d a
nim
al
Aquat
ics
anim
al
Endanger
ed
anim
al
Fis
hin
g
bre
edin
g
Lan
d u
se
Indust
rial
dev
elopm
en
t Agri
cult
ura
l dev
elo
pm
ent
Wat
er
supply
Tra
ffic
Fu
el
stru
cture
Save
ener
gy
Est
het
ics
tour
Hea
lth
safe
ty
So
cial
ec
onom
y
Rec
reat
ion
Cult
ura
l an
tiquit
y
Liv
ing
stan
dar
d
Site clear / / / -1 -1 -1 -1 / / / / / / / / / -1 / / -1 / / / / /
Ground
exc. / / / -1 -2 -2 -1 / / / / / / / / / -1 / / -1 / / / / /
Transp. / / / -1 -1 -1 / / / / / / / / / / -1 / / -1 / / / / /
Install
constr. / / / / / -1 / / / / / / / / / / -1 / / -1 / / / / /
Const
ruct
ion p
erio
d
Material
store / / / -1 -1 / / / / / / / / / / / / / / -1 / / / / /
Sub-total / / / -4 -5 -5 -2 / / / / / / / / / -4 / / -4 / / / / /
Sewage
discharge / / / / / / / / / / / / / / / / / / / / +1 / / / /
Waste
gas
dis-
charge
/ / / / -1 / / / / / / / / / / / / / / / -1 / / / /
Noise / / / / / -1 / / / / / / / / / / / / / / -1 / / / /
Solid dis-
charge / / / / / / / / / / / / / / / / / / / / / / / / /
Product / / / / / / / / / / / / / / / / / / / / / / / / /
Employ-
ment / / / / / / / / / / / / / / / / / / / / / +1 / / +1
House / / / / / / / / / / / / / / / / / / / / / +1 / / +1
Sub-total / / / / -1 -1 / / / / / / / / / / / / / / -1 +2 / / +2
Notes: � 3�Major impact;2�medium impact;1�light impact; “�” indicates favorable impact; “�” indicated unfavorable impact. � Degree of environment impact element by the project operation period includes positive and negative respects, whereas the benefit is bigger than the harm, the
listed in the table are major impacts.
Table 1-10 Analysis on the nature of the project impact on the environment
Unfavorable impacts Favorable impacts
Construction period Operation period Construction period Operation period Impact nature
Environment resource Short term
Long term
Reversible Irreversible Local Wide Short term
Long term
Reversible Reversible Local Wide Short term
Long term
Local Wide Short term
Long term
Local Wide
Underground hydrology
Underground water quality Earth’s surface hydrology Earth’s surface water quality √ √ √
Atmosphere quality √ √ √ √ √ √
Natural
resources
Noise environment √ √ √ √ √ √
Urban ecological √ √ √ √ √
Forest animals
Wild animals
Aquatic animals�
Endangered animals
Living
resources
Fishing breeding
Land use √ √ √ √ √
Industrial development √ √
Agricultural development √ √ √
Water supply √ √ √ √ √
Traffic √ √ √ √ √
Social
environment
Fuel structure
Save energy source
Esthetics tour √ √ √ √ √
Health safety
Social economy √ √ √ √ √
Recreation
Cultural antiquity
Living
quality
Living level √ √ √ √ √
It’s clear from Table 1-9 and Table 1-10, unfavorable impacts of the project on the
environment are mainly in construction period, mainly manifest in the impact on the
land occupation of the construction section, traffic, social economy, acoustic
environment, environment air and ecological environment, the nature is local, in short
term, but can be reversible; Main unfavorable impact during operation period,
environment elements of the impact include urban ecological, industrial development,
traffic and transport, social economy and living standard along the line, the nature is
wide and long term.
1.12 Environment protection targets
1.12.1 Ecological sensitive targets
Through investigation, the assessment scope of the project has not involved natural
reserves, scenic spots, forest parks, historical and cultural sites under government
protection, basic farmland protection area and other ecological sensitive objects.
1.12.2 Water environment protection targets
Due to Panggong area where the main civil works located having no river water
system at present, at the same time, the project has not involved the scope inside Han
River levee, so the project has not involved water source protection area. But, due to
partial road section of the project road works being close to Han River, in
consideration of the water drainage in construction period and environmental accident
risk in operation period, which may possibly cause impact on Han River, therefore,
Han River is taken as the water environment protection object by this assessment. Han
River water environment function surrounding the project is classified as class III
water quality.
1.12.3 Noise, atmosphere environment protection targets
According to the determined assessment scope, its noise and atmosphere environment
protection targets refer to Table 1-11.
Table 1-10 Noise and atmosphere environment protection object within the assessment scope
Minimum distance(m) Distance to related roads(m)
Road
name No.
Sensitive
point name Mileage Distance
to road
central
line
Distance
to road
red line
Height
difference
Locatio
n
relation
to road
Related
road
name
Distance
to road
central
line
Distance
to road
red line
Height
differenc
e
Relation
related to
road
location
Overview of sensitive
points
Environmen
t impact
Panggong
Road 1 Yiheyuan K0+000 45.3 19.6 0 End
Existing
Zhakou
Road
25.8 12.3 0 Left
side
Under construction, 10
floors, 6 buildings, in frame
structure, total 240
households
Road traffic
noise, social
life noise.
Panggong
Road 2
Xiangyang
National
Taxation Bureau
yard
K0+010�K0+070
24.5 4.5 0 Left side
Existing
Zhakou
Road
31 17.5 0 Right
side
1990s to now, 2fl.office
building, 1 building, 3fl
office building, 1 building,
7fl resident building, 1
building with 42
households, brick and
concrete structure.
Road traffic
noise, social
life noise.
Panggong
Road 3
Youzhi Corp/
Family yard,
Panggong
Jiayuan, Taixin
Garden
K0+070�K0+200
28.5 8.5 0 Left side
2000, 7-8fl resident
building, 15 buildings with
630 households, brick and
concrete structure.
Road traffic
noise, social
life noise.
Panggong
Road 4
Panggong
Garden
K0+010�K0+110
20 0 0 Right
side
Zhakou
Road 85 65 0
Right
side
2006, 7fl, 5 buildings, total
176 households.
Road traffic
noise, social
life noise.
Panggong
Road 5
Xiangyang No.
23 High School
K0+250�K0+350
53 33 0 Right
side
1700 teachers and students,
3fl teaching building, 1
building, 6fl building, 2
buildings.
Road traffic
noise, social
life noise.
Panggong
Road 6
Hongwei
Chemical Factor
family yard
K0+200�K0+280
22.2 2.2 0 Left side
1990s, 5fl. 2 buildings,
brick and concrete
structure., total 80
households
Road traffic
noise, social
life noise.
Panggong
Road 7
Tihua Textile
Factory family
yard
K0+340�K0+500
41.7 21.7 0 Right
side
1980s, 5fl, 5 buildings,
brick and concrete
structure., total 180
Road traffic
noise, social
life noise.
households.
Panggong
Road 8
Hongqi Living
quarter
K0+500�K0+560
51 31 0 Right
side
Xingguang
Avenue 76 36 0
Right
side
1990s, 8fl, 3 buildings,
brick and concrete
structure, total 192
households
Road traffic
noise, social
life noise.
Panggong
Road 9
Meihua
Corp.family
yard
K0+480�K0+570
53 33 0 Left side
2000, 6fl residential
building, 3 buildings, with
132 households, brick and
concrete structure.
Road traffic
noise, social
life noise.
Panggong
Road 10
Wangjiawa
group 7
K0+320�K0+600
24.1 4.1 0 Left side
1990s to now, 2-3 fl, brick
and concrete structure, total
33 households
Road traffic
noise, social
life noise.
Panggong
Road 11
Weather Bureau
family yard
K0+730�K0+800
22.1 2.1 0 Right
side
1980s to now, 4fl
residential building, 1
building, 5fl, 3 buildings,
total 122 households, brick
and concrete structure.
Road traffic
noise, social
life noise.
Panggong
Road 12
Xiangyang
Degong Hospital
K0+710�K0+800
26 6 0 Left side 2fl, 1 building, 30 beds.
Road traffic
noise, social
life noise.
Panggong
Road 13
Xinghuo
Bearing Factory
employees
dormitory
K0+850�K1+000
24 4 0 Right
side
1980s, 7fl residential
building, 2 buildings, 56
households, brick and
concrete structure.
Road traffic
noise, social
life noise.
Panggong
Road 14
Zhongfang
Dingshengyuan
K1+000�K1+270
35 15 0 Right
side
Under construction, brick
and concrete structure.,
frame structure, 6fl, 2
buildings, 14fl, 1 building,
total 120 households
Road traffic
noise, social
life noise.
Panggong
Road 15
Xuemei Corp.
family yard
K1+020�K1+080
27.7 7.7 0 Left side
1990s to now, 6-8fl, brick
and concrete structure., 6fl,
1 building, 8f, l3 buildings,
total 224 households
Road traffic
noise, social
life noise.
Panggong
Road 16
Panggongci
Village group 1
K1+230�K1+360
34.9 14.9 0 Left side
1990s to now, 2-3fl, brick
and concrete structure., 52
households
Road traffic
noise, social
life noise.
Panggong
Road 17
Panggongci
Village group 5
K1+650�K1+840
20.6 0.6 0 2 sides No. 13
road 20.6 0.6 0 End
1990s to now, 2-3fl, brick
and concrete structure., 25
households
Road traffic
noise, social
life noise.
households life noise.
Zhakou
Road 18
Sujiayuan
Comunity
K0+010�K0+280
37 17 0 Right
side
1990s to now, 2-3fl, brick
and concrete structure., 100
households
Social life
noise
Zhakou
Road 19
Jinyu Corp. Siji
apartment
K0+020�K0+070
20.4 0.4 0 Right
side
Existing
Panggong
Road,
existing
Zhakou
Road
70 50 0 Right
side
2000, 7fl, 1 building, brick
and concrete structure., 70
households
Road traffic
noise, social
life noise.
Zhakou
Road 20
Cement works
family yard
K0+120�K0+220
21.3 1.3 0 Left side
1980s to now, 5-8fl, 5
buildings, brick and
concrete structure.,230
households
Social life
noise
Zhakou
Road 21
Jiancai
Xiangyang
residential
quarter
K0+180�K0+230
30.5 10.5 0 Right
side
1990s, 7-8fl, 2 buildings,
brick and concrete
structure.,92 households
Social life
noise
Zhakou
Road 22
Hepanlinyu,
Hexie residential
quarter
K0+270�K0+510
26.9 6.9 0 Right
side
2000, 6-7fl, 13 buildings,
brick and concrete
structure, 720 households
Social life
noise
Zhakou
Road 23
No.1 Light
Industry Corp.
family yard
K0+300�K0+450
68 48 0 Left side
1990s, 5-7fl, 4 buildings,
brick and concrete
structure, 98 households
Social life
noise
Zhakou
Road 24
Agricultural
Research
Institute family
yard
K0+370�K0+450
22.5 2.5 0 Left side
1990s, 3-5fl, 3 buildings,
brick and concrete
structure, 32 households
Social life
noise
Zhakou
Road 25
Farm Machinery
Corp.family yard
K0+450�K0+550
89.5 69.5 0 Left side
2011, 17fl, 1 building,
frame structure; 3-5fl,
2buildings, brick and
concrete structure,136
households
Social life
noise
Zhakou
Road 26
Sanjiayuan
group 3
K0+470�K0+660
20.5 0.5 0 Right
side
1990s to now,2-3fl, brick
and concrete structure, 67
households
Social life
noise
Zhakou
Road 27
Sanjiayuan
group 4
K0+870�K0+920
72 52 0 Right
side
1990s to now, 2-3fl, brick
and concrete structure, 9
households
Social life
noise
households
Zhakou
Road 28
Hongmiao
Village group 4
K1+450�K1+600
38.8 18.8 0 Left side Jianghua
Road 86 66 0
Left
side
1990s to now, 2-3fl, brick
and concrete structure, 39
households
Social life
noise
Zhakou
Road 29
Hexin Village
group 7
K1+770�K1+900
44.1 24.1 0 Left side Jianghua
Road 77 57 0
Right
side
1990s to now, 2-3fl, brick
and concrete structure, 25
households
Social life
noise
Zhakou
Road 30
Hexin Village
group 5
K2+170�K2+360
23.9 3.9 0 2 sides Inner ring
road 31 1 0
Left
side
1990s to now,2-3fl, brick
and concrete structure,40
households
Social life
noise
Zhakou
Road 31
Roulianchang
family yard
K2+750�K2+800
23.5 3.5 0 Right
side
1990s, 5fl, 2 buildings,
brick and concrete
structure, 80 households
Social life
noise
Zhakou
Road 32
Zhijiamiao
group 5
K2+850�K3+060
29.7 9.7 0 Left side Xiangyang
Road 25 5 0
Left
side
1990s to now, 2-3fl, brick
and concrete structure, 120
households
Social life
noise
Xingguang
Avenue 33
Wangjiawa
residnetial
quarter
K0+950�K1+000
45 20 0 Right
side
2005, 8fl, 2 buildings, brick
and concrete structure, total
160 households
Social life
noise
Xingguang
Avenue 34
Dongcheng
Yijing pahse 1
K1+000�K1+150
33.5 8.5 0 Right
side
2010, 8fl, 7 buildings, brick
and concrete structure,196
households
Social life
noise
Xingguang
Avenue 35
Dongcheng
Yijing phase 2
K0+900�K1+070
35 10 0 Left side
2010, 7fl, 5 buildings, brick
and concrete structure, 140
households
Social life
noise
Xingguang
Avenue 36
Wangjiawa
Primary School
teachers
dormitory
K1+160�K1+200
25 0 0 Left side
2000, 5fl, 1 building, brick
and concrete structure, 20
households
Social life
noise
Xingguang
Avenue 37
Wangjiawa
group 7
K1+150�K1+500
26.5 1.5 0 Right
side
1990s to now, 2-3fl, brick
and concrete structure, 70
households
Social life
noise
Xingguang
Avenue 38
Wangjiawa
group 5
K1+540�K1+700
31.7 6.7 0 Left side
1990s to now, 2-3fl, brick
and concrete structure, 44
households
Social life
noise
Xingguang
Avenue 39
Hongmiao
Village group 5
K1+810�K1+940
135 110 0 Right
side
1990s to now, 2-3fl, brick
and concrete structure, 31
households
Social life
noise
Xingguang
Avenue 40
Hongmiao
Village group 2
K2+250�K2+350
27.2 2.2 0 Left side
1990s to now, 2-3fl , brick
and concrete structure, 30
households
Social life
noise
Xingguang
Avenue 41
Hongmiao
Village group 3
K2+300�K2+470
56 31 0 Right
side
Jianghua
Road 60 40 0
Left
side
1990s to now, 2-3fl, brick
and concrete structure, 61
households
Social life
noise
Xingguang
Avenue 42
Hexin Village
group 4
K2+700�K2+950
28.8 3.8 0 Right
side
1990s to now, 2-3fl, brick
and concrete structure, 51
households
Social life
noise
Xingguang
Avenue 43
Hexin Village
group 3
K2+750�K3+050
31.6 6.6 0 Left side
1990s to now, 2-3fl, brick
and concrete structure, 72
households
Social life
noise
Xiangyang
Road 44
Zhijiaiao groups
2,3
K1+150�K1+450
21.3 1.3 0 Right
side
1990s to now,2-3fl, brick
and concrete structure,140
households
Social life
noise
Xiangyang
Road 45
Zhijiamiao
Primary School
K1+250�K1+300
84 64 0 Right
side
208 teachers and students,
2fl teaching building, 1
building
Social life
noise
Xiangyang
Road 46
Zhijiamiao
group 1
K1+450�K1+750
20.3 0.3 0 Right
side
1990s to now,2-3fl, brick
and concrete structure, 63
households
Social life
noise
Xiangyang
Road 47
Yangjiahe
Village groups
6,7,8
K1+950�K2+450
36.1 16.1 0 Right
side
1990s to now,2-3fl, brick
and concrete structure, 257
households
Social life
noise
Xiangyang
Road 48
Yangjiahe
Village1, groups
3,4
K2+450�K2+900
25.1 5.1 0 Left side
1990s to now, 2-3fl, brick
and concrete structure, 82
households
Social life
noise
Inner ring
road
southeast
section
49 Hexin Village
group 6
K2+300�K2+450
49 19 0 Right
side
1990s to now, 2-3fl, brick
and concrete structure, 32
households
Social life
noise
Inner ring
road
southeast
section
50 Sunjiagang
group 7
K0+950�K1+100
56 26 0 Right
side
No.13
road 21.2 1.2 0
Right
side
1990s to now, 2-3fl, brick
and concrete structure, 35
households
Social life
noise
Jianghua
Road 51
Hongmiao
Village group 1
K1+850�K2+250
29.4 9.4 0 2 sides
1990s to now, 2-3fl, brick
and concrete structure,102
households
Social life
noise
No.13
road 52
Panggongci
Village group 6
K0+000�K0+050
31.5 11.5 0 Left side
1990s to now, 2-3fl, brick
and concrete structure, 15
households
Social life
noise
No.13
road 53 Yaojiawan
K0+100�K0+500
22.4 2.4 0 2 sides
1990s to now, 2-3fl, brick
and concrete structure, 138
households
Social life
noise
No.13
road 54 Yangjiaci
K0+700�K0+900
20.8 0.8 0 Left side
1990s to now, 2-3fl, brick
and concrete structure, 36
households
Social life
noise
No.13
road 55
Tuxiang Village
groups 2,3
K1+200�K1+300
21.3 1.3 0 Left side
1990s to now, 2-3fl, brick
and concrete structure,50
households
Social life
noise
No.13
road 56
Sunjiagang
groups 1,3
K1+870�K2+200
20.2 0.2 0 2 sides
1990s to now, 2-3fl, brick
and concrete structure, 140
households
Social life
noise
No.13
road 57
Sunjiagang
group 6
K2+580�K2+950
21.7 1.7 0 Left side Inner ring
road 121 91 0
Left
side
1990s to now, 2-3fl, brick
and concrete structure, 45
households
Social life
noise
22
2.0 Overview of the project
Xiangyang Urban Transportation Project with World Bank loan this time is a
systematic engineering composed of a number of traffic sub-projects, which includes
hardware construction, but also covers improvement and perfection of related
softwares. It may be classified according to nature of each sub-project, which may be
generalized as 4 major sub-systems, respectively: sub-project of road perfection, sub-
project of public traffic preferential corridor improvement, sub-project of traffic
safety and control as well as sub-project of organization development and capacity
construction. Summary of the contents for Xiangyang Urban Transportation Project
construction refers to table 2-1.
Table 2-1 Summary of the contents for Xiangyang Urban Transportation Project
Construction
Sub-project
name Construction contents
Project
nature
Static
investment(100
million yuan)
Sub-project
of road
perfection,
Construction for
Panggong new
zone backbone
road network
Southeast section of newly built
inner ring road, Xingguang
Avenue, Panggong Road, Jianghua
Road, Xiangyang Road, Zhakou
Road, planned No.13 road, total
length is 17.182km
Hardware
construction 4.42
Construction for
No. 13
dedicated public
traffic road
Changhong road, Chunyuan road~
Daqing west road section, total
length is about 2.5km
Hardware
construction
Newly built
Xianshan
parking and
service yard
Yard total area is 5000m2
Hardware
construction
Newly built
Xiangyang
Economic
Development
Zone parking
and service yard
Yard total area is 18000m2
Hardware
construction
Reconstruction
for Xiangyang
Railway Station
public traffic
hub
Construct sun-shade, slow speed
passage, reconstruct existing
platform.
Hardware
construction
Traffic works facility for No. 13 public traffic
preferential corridor, reconstruct harbor type bus stop
and purchase high performance vehicles.
Software
improvement
and
perfection
GPS dispatch service system
Software
improvement
and
perfection
Sub-project
of public
traffic
preferential
corridor
improvement
Construct No. 13 public traffic harbor platfrom,
Panggong area circular public traffic preferential
corridor-waiting booth.
Hardware
construction
1.21
23
Traffic organization and improvement
Software
improvement
and
perfection
Public traffic preference
Software
improvement
and
perfection
Road channeling design
Software
improvement
and
perfection
ATC system design
Software
improvement
and
perfection
Sub-project
of traffic
safety and
control
Road user propaganda and education
Software
improvement
and
perfection
0.81
Sub-project
of
organization
development
and capacity
construction
Include its smooth implementation and normal
operation management later on, sustainable
development of urban traffic construction, provide the
topic study, training and investigation, consultation
services, urban traffic strategy planning matching and
construction for the organization capacity, etc.
Software
improvement
and
perfection
0.13
2.1 Sub-project of road perfection
Sub-project of road perfection mainly aims at relieving the traffic jam of central urban
area, reducing river cross traffic pressure, strengthening the traffic contact between
central urban area with the surrounding clusters or groups, at the same time, in
cooperation with Han River No. 5 Bridge being constructed recently, main study area
of this sub-project is the road network planning for Xiangcheng district Panggong
new zone in Xiangyang while covering the new construction for the backbone
road(southeast section of inner ring road, Xingguang Avenue, Panggong Road,
Jianghua Road, Xiangyang Road, Zhakou Road, planned No.13 road), total length is
17.182km, construction and installation costs reach 442 million yuan. The design of
this period has included the investment for the internal road network of Panggong
area into general investment of this project, excluding the backbone road, but, no
concrete design has been done at this period, general investment for internal road
network is about 500.53 million yuan.
Recommended scheme for road network of Panggong area this time refers to Table 2-
2, Fig. 2-1.
Table 2-2 Recommendation for designing the construction of road network of
Panggong area
24
Road No. Name of recently
constructed roads
Road
nature
Red line
width(m)
�Green line
width(m)
Road length
(m)
1 Southeast section of
inner ring road
Primary
road 60 / 2046.8
2 Xingguang Avenue Primary
road 50 80 3187
Jianghua Road(east of
Zhakou Road)
Primary
road 40 50 1694
3 Jianghua Road(west of
Zhakou Road)
Primary
road 30 / 259
Panggong Road(east of
Zhakou Road)
Primary
road 40 50 1820
4 Panggong Road(west of
Zhakou Road)
Primary
road 30 / 215
5 Xiangyang Road Primary
road 40 / 1798
6 Zhakou Road Primary
road 40 / 3081
7 Planned No. 13 road Primary
road 40 / 3081
Total 17181.8
Notes:�Green line width means the control line of green land at 2 sides of the road, it’s road red line plus the
width of green land of 2 sides.
25
Fig. 2-1 Recommended scheme for Panggong area road construction
2.2 Sub-project of public traffic preferential corridor improvement
Sub-project of public traffic preferential corridor improvement mainly includes dedicated 2.5km
long or so public traffic road for Changhong road section, design scope: From Chunyuan Road at
the north to Daqing West Road at the west; traffic work facilities for No. 13 Road public traffic
preferential corridor, reconstruction of harbor type bus stop and purchase of high-performance
vehicles; Construction for No. 13 Road public traffic harbor station, public traffic waiting booth
26
for circular public traffic preferential corridor of Panggong area; Construct Xianshan parking and
service yard, Xiangyang Economic Development Zone parking and service yard and
reconstruction works for railway public traffic hub; GPS dispatching service system.
2.2.1 Design scheme for dedicated public traffic road
Total length of the newly built No. 13 dedicated public traffic road by the project is
about 2.5km, design scope: From Chunyuan Road at the north to Daqing West Road
at the west. Changhong Bridge is the most important passage for connecting
Xiangcheng and Fancheng districts, Changhong Road is directly connected with
Changhong Bridge, therefore, it’s selected as the most important road section for
improvement, and used as dedicated public traffic road, details refer to Table 2-3, Fig.
2-2.
Table 2-3 Construction works for dedicated public traffic road
Dedicated public traffic road Length(m) Remark
Chunyuan Road ~Jianhua Road 400
Jianhua Road ~Liye Road 300
Liye Road ~Renmin Road 770
Renmin Road~Jianshe Road 630
Changhong Road
(2.5km)
Jianshe Road~Daqing West Road 400
27
Fig.2-2 The starting and terminating points for No. 13 Road dedicated public traffic road
2.2.2 Design scheme for the public traffic terminal yard
The construction for the public traffic terminal yard of the project mainly covering: newly built
Xianshan parking and service yard and Xiangyang Economic Development Zone parking and
service yard, reconstructing the exiting railway station public traffic hub. Details for the
construction of public traffic terminal station refer to Table 2-4.
Table 2-4 Schedule and composition of newly built public traffic terminals
Terminal yard name Works contents Works quantity
28
Plane layout
The parking lot occupies 21,305 m2, with 250 parking spaces; with
one entrance and one exit, exit is at the planned branch road, entrance
is at Sijiqing Road; with 5 vehicle maintenance pits, the space before
the maintenance house is also with function of vehicle washing, in
which, building area is 407m2; Vehicle parking is adopted vertical
type, vehicle space is 13.0×3.5m(including road, consider back of the
parking space has greening zone with enough width, public traffic
vehicle rear end may enter into the greening zone, so the length of the
parking space is duely adjusted); Build one 3fl type comprehensive
public traffic building and 2fl staff rest rooms, with building area of
1,127m2, building area of the staff dormitory is 629m2; With one
money receiving room, there is a money receiving passage before the
money receiving room, of which, building area is 25m2. Details refer
to Fig.2-3.
Subgrade
pavement
Parking lot is adopted 20cm C30 cement concrete pavement and
30cm thick cement stabilized crushed stone base.
Site vertical and
drainage
The site vertical of the service yard shall be controlled according to
the longitudinal grade vertical to passage direction not over 3%, the
longitudinal grade parallel to the passage direction not over 1%; Rail
water, sewage, water supply pipelines and the support facilities shall
be unified designed according to the situation of site surrounding
road network drainage facilities, details refer to the table of works
quantity.
Xianshan parking
and service yard
Greening works
Greening area is about 6,340m2, greening rate is 21.2%, 4.5m high
panicled goldrain trees planted at 5m interval to the surrounding
greening zone are used as protective network for the site surrounding
areas, the middle has been planted some 4.5m high camphor trees for
beautifying in order to form the shade tree inside the site, which not
only increases the greening area, but also plays a role of summer
shade. The road turning areas inside the site are mainly laid bushes,
for forming penetration type design, reducing the interference to the
sight line of the driver to the minimal extent, in consideration of the
length of the parking space, greening scope of 2m to the parking
space may only plant vegetation.
Plane layout
Parking and service yard is at south of Hubei Shenzhen Industrial
Park, parking lot occupies about 18,000 m2, with 150 parking spaces;
With one entrance and one exit, exit is at Nanwei Sixth Road,
entrance is at Nanjing Third Road; The vehicle parking is parked in
vertical, parking space is 13x3.5m(including road, consider back of
the parking space has greening zone with enough width, public traffic
vehicle rear end may enter into the greening zone, partial parking
space occupies the greening zone); Greening land under high voltage
line is included into general area; Built one 2fl comprehensive public
traffic building and staff rest rooms, building area is 2,527m2; Newly
built one gas station, with 4 gas filling parking spaces, building area
is 1800m2; Build one money receiving room, set up two vertically
parallel money receiving vehicle passages, of which, building area is
60m2; Build one maintenance room, with 10 maintenance pits, the
space before the maintenance room has also the function for washing
vehicles, building area is 900m2. Details refer to Fig.2-4.
Subgrade
pavement
Parking lot is adopted 20cm C30 cement concrete pavement and
30cm thick cement stabilized crushed stone base.
Xiangyang
Economic
Development Zone
parking and service
yard
Site vertical and
drainage
The site vertical of the service yard shall be controlled according to
the longitudinal grade vertical to passage direction not over 3%, the
longitudinal grade parallel to the passage direction not over 1%; Rail
water, sewage, water supply pipelines and the support facilities shall
be unified designed according to the situation of site surrounding
road network drainage facilities
29
Greening works
Greening area is 7136m2(including greening land under high voltage
line), greening rate is 23.2%. 4.5m high panicled goldrain trees
planted at 5m interval to the surrounding greening zone are used as
protective network for the site surrounding areas, the middle has been
planted some 4.5m high camphor trees for beautifying in order to
form the shade tree inside the site, which not only increases the
greening area, but also plays a role of summer shade. The road
turning areas inside the site are mainly laid bushes, for forming
penetration type design, reducing the interference to the sight line of
the driver to the minimal extent, in consideration of the length of the
parking space, greening scope of 2m to the parking space may only
plant vegetation.
Newly increased
sun-shade
Considering the distance from the existing public traffic getting-on
passenger door front side to the back site of getting-off passenger
door is about 6m, propose the sun-shade to set up the top ceiling of
108m long and 7m wide, lateral interval of vertical column is 6m,
longitudinal interval shall be adjusted taking the bearing capacity as
criterion, set up at the platform in order not to block the public traffic
vehicle driving, at the same time, set up sun-shade top ceiling at the
entrance and exit of underground passage at one side of public traffic
hub to the public traffic platform section, in order to provide a
conformable environment to passengers entering or leaving the hub.
Propose to adopt green light penetrating plastic top ceiling, set up arc
round top for the benefit of drainage, fully using natural light. Details
refer to Fig.2-5.
Newly increased
slow speed lane
According to the proportion of length and width of the public traffic
hub, vertically set up 1 crosswalk, transversely set up 3 crosswalks,
for the convenience of passengers to take the vehicle in different
places, as well as the public traffic passengers to rapidly and safely
leave public traffic hub.
Construction works
for railway public
traffic hub
Platform
reconstruction
The current platform is ruined, due to limit by the turning angle when
the vehicle entering the platform, public traffic vehicles are often
driven to the platform, which shall wear and damage the platform
tile.
Propose to newly place cement concrete at two ends of the platform,
and make it into arch slope, for providing convenience to the
handicapped, while preventing the platform from being damaged
again by the public traffic vehicles.
30
Fig.2-3 Schematic diagram for the layout of Xianshan parking and service yard
31
Fig.2-4 Schematic diagram for the layout of Xiangyang Economic Development Zone
public traffic parking and service yard
32
Fig.2-5 Scheme for improving railway station public traffic hub
2.3 Sub-project of traffic safety and control
Sub-project of traffic safety and control mainly, according to the requirements for the traffic
control and safety put forward in the urban master planning, took“ the corridor” as the object, and
solved main conflicts, starting from the traffic safety improvement“3E” (Engineering-
Engineering, safety education-Education, law enforcement-Enforcement), enhanced the safety of
urban road traffic, maximally improved residents trip environment, thus reducing the impact of the
traffic growth on the living environment. The construction of the project including: Traffic
organization and improvement, public traffic preference, road channelizing design, ATC system
design and road user propaganda and education, etc. Its investment is 81 million yuan.
2.4 Sub-project of organization development and capacity building
Sub-project of organization development and capacity construction includes the
smooth implementation and normal operation management later on for the project,
sustainable development of urban traffic construction, providing the topic study,
training and investigation, consultation service, construction for internal preparation
33
of urban traffic strategy planning and organization capacity. Its investment is 13
million yuan.
2.5 Investment estimation and financing
General static investment of the project is 1.343 billion yuan, of which, the project
construction cost is 0.901 billion yuan, resettlement cost of affected residents is 13
million yuan, technical assistance cost is 30.6 million yuan, other costs are 4.7323
million yuan, contingency fund is 103 million yuan.
Composition of the project fund resources: World Bank loan totaling USD 0.1 billion
(converted to RMB 0.6824 billion yuan, exchange rate is 1:6.8242), internal fund is
0.62 billion yuan.
Internal fund resources: The project capital: 0.335 billion yuan, all resources are from
the special fund for Xiangyang urban construction and development; Domestic bank
loan is 0.285 billion yuan, from the loan of Hubei Branch of China Development
Bank.
The loan of World Bank and the domestic bank shall be repaid within 15y after the
completion of the project, namely from 2015y-2029y, repayment per year is in equal
amount, and interest shall also be paid.
The loan compensation resource is from the special fund for Xiangyang urban
construction and development.
2.6 General implementation progress for the project
Details for general implementation progress for the project refer to Table 2-5.
34
Table 2-5 Table for general implementation progress for the project
2010 2011 2012 2013 2014 2015 2016
3 6 9 12 3 6 9 12 3 6 9 12 3 6 9 12 3 6 9 12 3 6 9 12 3 6 9 12
Pro
ject
pre
par
atio
n
Pro
ject
asse
ssm
ent
Pro
ject
neg
oti
atio
n
Pro
ject
des
ign
Bid
ing
pu
rch
ase
Pro
ject
co
nst
ruct
ion
Pro
ject
accep
tan
ce
Han
do
ver
fo
r u
se
35
2.7 Overview of the project land occupation
The land occupation types of the project along the line mainly include: arable
land(paddy field, dry land), woodland(forest land, bush land), housing estate, grass
land, etc, totaling 88.19hm2, of which, permanent land occupation is 80.59hm
2,
interim land occupation is 7.60hm2. Statistics table for land occupation refers to 2-6.
Table 2-6 Summary table for the project land occupation
Unit: hm2
Type of land occupation
Arable land Forest Housing
estate
Land
occupation
by traffic
transport
Grass
land Project sub-area
Irrigable
land Dry land
Forest
land
Bush
land Commercial Highway
Other
grass
lands
Total
Permanent land occupation 26.59 24.73 / / 9.03 20.24 / 80.59
Sub-total 26.59 24.73 / / 9.03 20.24 / 80.59
Excavation waste
dump / / / 0.27 / / 0.75 1.02
Earth material yard / / / / / / 0.28 0.28
Interim earth yard / 2.88 / / / / / 2.88
Interim construction
road area / 0.60 0.41 / / / 1.56 2.57
Interim
land
occupation
Construction
production and
living area
/ 0.45 / / / / 0.4 0.85
Sub-total / 3.93 0.41 0.27 0 0 2.99 7.6
Total 26.59 28.66 0.41 0.27 9.03 20.24 2.99 88.19
2.8 The earth work
According to design data and calculations, the excavation earth work is 387,900m3,
earth filling work is 344,100m3, the earth utilization is 336,900m
3, the borrow earth is
7,200m3, the abandoned earth is 51,000m
3(of which, 35,800
3 shall be sent to
Huanglongguan waste yard, 15,200m3
construction waste shall be sent to the urban
refuse site), interim earth is 101,600m3. The balance table for the earthwork refers to
Table 2-7. The flow direction of the earthwork of the project area refers to Fig.2-6.
Table 2-7 The balance table for the earthwork Unit: 10,000m3
36
Project sub-
area Location
Exc./
removal Backfill Use Borrow
Interim
earth Abandoned Disposal of abandoned earth
Removal of
surface
building
1.37
1.16
1.16
0.21 Urban refuse site
Subgrade 2.28 2.17 2.17 0 0.11 Huanglongguan excavation
waste dump
East
section of
south
inner ring
road Surface soil 1.48 1.48
Interim earth site, it shall be
used as soil for greening
later on.
Removal of
surface
building
5.00
4.25
4.25
0.75 Urban refuse site
Subgrade 8.34 5.86 5.86 0 2.48 Huanglongguan excavation
waste dump
Xingguang
Road Surface soil 2.54 0 2.54
Interim earth site, it shall be
used as soil for greening
later on.
Removal of
surface
building
0.61
0.52
0.52
0.09 Urban refuse site
Subgrade 1.02 1.49 1.02 0.47 0 Huanglongguan excavation
waste dump
Jianghua
Road Surface soil 0.78 0 0.78
Interim earth site, it shall be
used as soil for greening
later on.
Removal of
surface
building
0.52
0.44
0.44
0.08 Urban refuse site
Subgrade 0.87 0.76 0.76 0 0.11 Huanglongguan excavation
waste dump
Panggong
Road Surface soil 0.45 0 0.45
Interim earth site, it shall be
used as soil for greening
later on.
Zhakou
Road
Removal of
surface
building
1.00
0.85
0.85
0.15 Urban refuse site
Subgrade 1.67 1.92 1.67 0.25 0 Huanglongguan excavation
waste dump
Surface soil 1.25 0 1.25 Interim earth site, it shall be
used as soil for greening
later on.
Xiangyang
Road
Removal of
surface
building
0.67
0.57
0.57
0.10 Urban refuse site
Subgrade 1.12 0.93 0.93 0 0.19 Huanglongguan excavation
waste dump
Surface soil 0.84 0 0.84
Interim earth site, it shall be
used as soil for greening
later on.
Planned
road
Removal of
surface
building
0.94
0.80
0.80
0.14
Subgrade 1.56 1.38 1.38 0 0.18 Huanglongguan excavation
waste dump
Surface soil 1.31 0 1.31
Interim earth site, it shall be
used as soil for greening
later on.
Sub-total Removal of
surface
building
10.12
8.60
8.60
1.52 Urban refuse site
Subgrade 16.86 14.51 13.79 0.72 3.07 Huanglongguan excavation
waste dump
Surface soil 8.65 8.65 8.65 0 8.65
Interim earth site, it shall be
used as soil for greening
later on.
Maj
or
pro
ject
are
a
Total 35.62 31.75 31.03 0.72 8.65 4.59
37
Excavation
waste dump Surface soil 0.31 0.31 0.31 0.31
Stack inside the waste yard,
it shall be returned after end
of the completion.
Borrow pit Surface soil 0.08 0.08 0.08 0.08
Stack in the borrow pit, it
shall be returned after end of
the completion.
Interim
construction
road area
Subgrade 1.15 1.15 1.15
Interim earth
area Surface soil 0.86 0.86 0.86 0.86
Just for interim stacking, it
shall be returned after end of
the completion.
Surface soil 0.26 0.26 0.26 0.26
Just for interim stacking, it
shall be returned after end of
the completion.
Construction
Production
and living
area Hardening
layer 0.51 0.51
Huanglongguan excavation
waste dump
Total 38.79 34.41 33.69 0.72 10.16 5.10
38
/
1. 37
12. 0= 35. =0 24. 2= 0. 72
1. 80 m31. 37 m30. 88 m3
3. 33 m3
5. 005. 77 m38. 34 m31. 54 m3
10. 11 m3
0. =10. 87 m31. 02 m30. =8 m3
1. 54 m3
0. 520. =4 m30. 87 m30. 25 m3
1. 20 m3
1. 001. 20 m37 m3
0. 75 m3
2. 42 m3
0. =71. 13 m31. 12 m30. 54 m3
1. 50 m3
0. 941. =3 m31. 5= m30. 81 m3
2. 18 m3
0. 47 m3
0. 25 m3
0. 72
1. =3 m3 0. 31 m3
1. =3 m3 0. 08 m3
1. =3 m3 0. 8= m3
1. =3 m3 0. 2= m30. 51 m3
Fig.2-6 The earthwork flow chart for the project
Abandoned earth Exc./removal Backfill Borrow
39
2.9 Overview of the temperary land occupation
2.9.1 Excavation waste dump
According to the need of the project, set up 1 excavation waste dump, the excavation
waste dump is located at Huanglongguan ravine zone of 8km to the southwest of the
project area, the dump is now the bush land, with small rain water confluence, and the
scouring is not obvious, it’s favorable for placing the waste interception measures.
Through site investigation, the possible area to be used by this bottom land is
1.53hm2, the waste stacking elevation may be stacked from 112.00m~125.00m, the
slope of the waste stacking face is even, 15° in average.
2.9.2 Borrow pit
This project needs total borrow earth for 7,200m3, according to geological
investigation, the borrow pit is located between the army oil depot ~cement factory at
west of Qianying Village Jiaoliu railway to the southwest of the project, it’s borrowed
from the hill, designed average excavation depth is 2~3m, no impact shall be met
from underground water at the designed borrow depth. Through investigation, the
selected borrow pit of the project has not passed the land consolidation area as
stipulated by the state, earth material nature is clay, it conforms to the earth use
requirement for the project. This pit is 70m long, 40m wide, with an area of 0.28hm2,
the type of land occupation is barren grass land, water confluence area is 1.42hm2.
This borrow scheme is adopted two-level borrow mode from the top to bottom, in the
borrow process, first remove surface soil, the surface soil is placed within the
expropriated land, no repeated expropriation shall occur, after the end of the borrow,
it shall be returned to forest land according to local land use policy.
2.9.3 Interim stack site
Partial road sections of the project penetrate through arable land, it needs to remove the
surface cultivated soil and soil with plant roots. The removed surface soil shall be used as
interim abandoned soil, it shall be concentrated stacked at the interim stack site set up at
the subgrade side according to the line topographical sections, interim stack site is mainly
selected the bottomland area at the road side outside the subgrade, for the benefit of use
for road greening, one interim stack site is set up at each road section of the project,
totaling 7 places. Through estimation, total newly increased interim land occupation is
about 2.88hm2. Schedule of interim stack site refers to Table 2-8.
40
Table 2-8 Schedule of interim stack site
Interim stack
site No.
Waste road
section
Interim stack
site stake No.
Surface soil
stack
quantity(10,0
00
Haul
distance(m)
Land
occupation
area (hm2)
Type of land
occupation
Average stack
height (m)
1#
East section of
inner loop south
road
NH1+000 1.48 1000 0.49 Arable land 3
2# Xingguang Road XG1+500 2.54 1500 0.85 Arable land 3
3# Jianghua Road JH1+000 0.78 1000 0.26 Arable land 3
4# Panggong Road PG0+800 0.45 800 0.15 Arable land 3
5# Zhakou Road ZK1+500 1.25 1500 0.42 Arable land 3
6# Xiangyang Road XY1+000 0.84 1000 0.28 Arable land 3
73 Planned No. 13
Road GH1+500 1.31 1500 0.44 Arable land 3
Total 8.65 2.88
2.9.4 Construction production and living area
Though the project being severely affected by local work point topographical
conditions, the layout for construction production and living area is quite difficult,
yet, most of construction prefab yard, pavement base, asphalt concreting mixing plant
and others, may be placed by selecting the construction site with better conditions,
But, interim land occupation shall try to occupy the minimal arable land, pay attention
to environment protection and exiting the site for the farm. Total 7 construction
production and living areas, details for construction production and living area refer to
Table 2-9.
Table 2-9 Schedules for construction production and living quarter
No. Road section Center stake No. Size Floor space (hm2)
Type of land
occupation
1
East section of
inner loop south
road
NH2+000 50*20m 0.10 Barren
bottomland
2 Xingguang Road XG1+080 50*30m 0.15 Arable land
3 Jianghua Road JH1+900 50*20m 0.10 Barren
bottomland
4 Panggong Road PG1+800 50*20m 0.10 Barren
bottomland
5 Zhakou Road ZK1+800 50*30m 0.15 Arable land
6 Xiangyang Road XY2+000 50*20m 0.10 Barren
bottomland
7 Planned No. 13
Road GH1+300 50*30m 0.15 Arable land
Total 0.85
41
2.9.5 Interim construction road
The project is constructed in urban area, the existing Xingguang Road, Panggong
Road, Jianghua Road and others are crisscross, they may be used as construction
roads. The newly increased construction roads of the project are mainly leading to
excavation waste dump, borrow pit and road of construction sites. According to
preliminary estimation in this period, the general length of the interim construction
road needs to be kept, lay interim construction road areas along the relevant road
sections of the line, the project needs totally constructing interim road areas reaching
3.67km, of which, 1.75km road is leading to waste yard, 1.07km road is leading to
stock yard, 0.85km road is leading to construction site. Expropriation width is 7m,
pavement width is 3-3.5m, adopting cement consolidated pavement, interim land
occupation is 2.57hm2, and type of land occupation is arable land and grass land.
3.0 Overview of natural environment and social environment
3.1 Natural environment overview
3.1.1 Climate
Xiangyang is located in north subtropical monsoon climatic region. It is cold in winter and hot in
summer. Rain and heat are over the same period. Four seasons are distinct. The average
temperature of the whole city except high mountains is 15~16�. Frost-free period is 228~249
days long. The annual precipitation of the whole city is 820~1,100mm. Precipitation in summer is
400~450mm. The number of rainy days are 107~135 days. Sunshine duration is long. Total annual
average sunshine duration is 1,800~2,100 hours. The rainy season in Xiangyang region is mainly
in June and July.
3.1.2 Topography and landform
Xiangyang, of diverse landform, lies in the transitional zone from the second step to the third step
of topography. The terrain becomes lower and lower from the periphery to center, forming an
irregular basin where Han River passageway opens to Yicheng. The northern part of Xiangyang is
between Wudang Mountain and Tongbai Mountain. It is an undulating earth hummock called
“Hillock in north of Hubei”. In the west is a mountainous area where Jingshan Mountain range
links to the residual part of Wudang Mountain range. In the south is a low mountainous area. At
the heart of Xiangyang is an open plain as a result of alluviation of the Han River, Tanghe River,
Baihe River, Gunhe River and Qinghe River. In the east is a low mountainous area between the
Dahong Mountain and Tongbai Mountain. Hillock accounts for 65.8% of total area. Low
mountainous area accounts for 13%. The alluvial plain along rivers accounts for 21.2%.
42
The Panggong area where the project is located is at the first step of Han River, 3.5km long at the
most from east to west, 5.5km long at the most from south to north. The terrain at the project
location is high in the west and north, lower in the east and south. The existing terrain elevation is
at 63~68m, averaged at 64~67m. Terrain is flat. The middle and eastern parts of the area are
mainly farmland and vegetable plots. There are a lot of irrigation canals. In the southern low-lying
parts of the area are several fishponds. There is a flood protection embankment of the river in this
area. Generally, the geological conditions of this area are favorable, free of geological hazard,
suitable for construction.
3.1.3 Rivers, hydrology and water resource
There are 817 well-known rivers in Xiangyang, the majority of which are mountain streams,
including 13 rivers occupying a basin area of above 1,000km2, 73 rivers occupying a basin area of
above 100km2 but below 1,000km2. These rivers belong to either Changjiang River water system
or Huai River water system. Major natural rivers in the project area are the Han River, Tangbai
River and Nanqu Canal.
(1) Han River
The Han River is one of the largest tributaries at the middle reaches of the Changjiang River,
rising in Ningqiang County in the south of Qinling Mountains. The tributary flows through
Hanzhong, Ankang (in Shaanxi Province), Shiyan, Xiangyang, Jingmen, Tianmen, Qianjiang,
Xiantao, Xiaogan etc. (in Hubei Province) to the Changjiang River in Wuhan. The overall length
of the Han River is 1,567Km. The total basin area of the Han River is 15.9×104Km2, accounting
for 8.8% of total basin area of the Changjiang River. The geographic position of the basin is
106°12′~114°14′E and 30°08′~34°1l′N. Northern boundary is the Qinling Mountains,
Waifangshan Mountain, Funiushan Mountain and Yellow River basin. Northeast boundary is the
Funiushan Mountain, Tongbaishan Mountain and Huai River basin. Southwest boundary is the
Dabashan Mountain, Jingshan Mountain, Jianglingjiang River and Juzhangjiang River. There is no
distinct natural water divide. The Han River links to Dongjinhe River on the right and is adjacent
to Fuhe River water system on the left. The water system of the whole basin is in a veined
distribution.
The portion of the Han River in Xiangyang is 216km long, with a basin area of 17,313.1km2.
According to the records kept at Xiangyang hydrologic station, the maximum flood in the history
appeared on Jul. 7, 1935, with peak discharge of 52,400m3/s and water level of 71.11m; the lowest
water level appeared on Jul. 6, 1941 at 60.61m/s; the dryest discharge appeared in 1958, at
145m3/s; Average annual discharge is 1,710 m
3/s; the maximum annual runoff is 65.1 billion m
3/s;
the minimum runoff is 26.1 billion m3/s. Average annual runoff is 43.5 billion m
3/s. Nanqu Canal,
Tangbai River and Manhe River are the largest tributaries of the Han River.
43
(2) Tangbai River
The source of Tangbai River is two rivers, both of which rise in the south of the Funiushan
Mountain in Henan Province. One is Baihe River. It flows eastward through Nanzhao, Nanyang,
Xinye etc. to Xiangyang at Quwan and reaches Lianghekou at Shuanggou Town. The river is
264km long, with basin area of 192km2. The other river is Tanghe River. It flows through
Fangcheng, Tangxian County and Shitaisi to Xiangyang. It reaches Lianghekou from the west of
Shuanggou Town. The river is 230km long, with basin area of 8,685km2. The portion of the river
in the Xiangyang is 46.8km long, with basin area of 1,192km2. Two rivers converge at
Lianghekou and combine into a river named Tangbai River. The Tangbai River flows southward
and reaches the Han River at Zhangjiawan. The Tangbai River is 22.6km long. The total area of
Tangbai River basin is 24,134km2. According to observation at Dongpo Hydrological Station, the
maximum discharge is 11,778m3/s (on Aug. 8, 1978); the minimum discharge is 3.1m3/s; average
annual discharge is 197m3/s; average annual runoff is 271.96mm deep. Average annual runoff is
6.234 billion m3. The maximum runoff is 8.278 billion m3. The minimum runoff is 3.248 billion
m3. The river is 700~1,000m wide, with sandy riverbed. The water level of the river is 2~3m in
dry season. The safe flood carrying capacity of the rivercourse is 6,000m3/s.
(3) Nanqu Canal
Nanqu Canal is also called Xiangqu and Xiangshui in ancient times. It is a flood discharge canal in
the west of the Bianshan Mountain located in the north of Xiangyang. It rises in Taishanmiao, Yiji
Village, Xiangcheng District. It flows through Qilindian Village and Yingpan Village and then it
flows eastward to Shengli Street corner. At Shengli Street corner, it twists southward and reaches
the Han River at Guanyingge at Xianshou Mountain. Nanqu Canal is 14km long with a basin area
of 29.34km2. Average river slope is 1/1500. At present, it is used not only for discharging flood
but also for draining rainwater and sewage and beautifying the image of the city.
Xiangyang is rich in water resource. The total average annual water resource of the whole city is
49.015 billion m3, among which foreign (pass-by) water resource is 42.929 billion m
3 and local
water resource is 6.086 billion m3. There are 683 rivers in Xiangyang, including 66 rivers
occupying a basin area of above 100km2, belonging to the Changjiang River water system. There
are 845 reservoirs (including 9 large-scale, 57 medium-sized) in the whole city. Total reservoir
storage capacity of 3.778 billion m3. Normal storage capacity is 2.368 billion m
3. Effective
irrigation area is 263,000 hectares. The quality of underground water is good. Total underground
water resource is 19 billion m3.
3.1.4 Geology
3.1.4.1 Geological structure
44
In terms of Geological structure, the project area is located on the boundary of two primary
tectonic units, bounded by Qingfeng, Xiangfan—Guangji fracture. In the north is the secondary
tectonic unit of Qinling, Tongbai and Dabie nappe belt (Qinling fold system)—Lushan—Queshan
uplift-depression belt, east Qinling orogenic belt, graben basin in the south of Xiangyang and
Suizhou—Yingshan nappe belt. In the south is the secondary tectonic unit of Yangtze deformation
belt (Yangtze paraplatform) —Exi Yangtze deformation belt (in the west of Hubei), Ezhong basin-
range deformation belt (at the center of Hubei) and Dongting graben basin of the Han River. The
near field region of the project (within a radius of 30km from the center of project site) is in the
south of Nanxiang graben basin (in the south of Xiangyang), in the north of Ezhong basin-range
deformation belt, in the west of Suizhou-Yingshan nappe belt.
3.1.4.2 Unfavorable geological condition
The project is located on the first terrace of the Han River. Overall geological condition is good.
The alluvial first terrace of the Han River is composed of clay and gravel, with good stability.
3.1.4.3 Earthquake
According to the Seismic Ground Motion Parameter Zonation Map (GB18306-2001) in 2002, the
seismic peak ground acceleration in the project area is 0.05g; the characteristic period of ground
motion is 0.35s; basic seismic intensity of the project area is equal to VI grade. It is recommended
that general structures be protected at the level of VI grade and important control structure be
protected at the level of VII grade.
3.1.4.4 Hydrogeology
The project is located in north subtropical monsoon climatic region, with humid
climate, adequate rainfall, developed surface runoff and abundant surface and
underground water. Underground water is composed of pore water, pore fissure water
and fissure karst water.
The pore water aquifer of Quaternary system are mainly distributed in the alluvial sandy loam,
fine-medium sand, sand gravel layers of riverbed, floodplain and I terrace and underground sand
gravel layer of II terrace. Pore water is recharged mainly by atmospheric precipitation and drained
to the Han River. Ground water quantity is medium to abundant. Generally, the depth of ground
water on I terrace is 5~6m. Water level is at El.56.8~58m; the depth of ground water on II terrace
is 2~15m. Water level is at El.57~70m. The level and amplitude of ground water in the sand bank
and the zones approaching the river are almost the same as river water. The dynamic changes in
the water level of the sand bank and these zones slightly lag behind rive stage fluctuation. The
ground water on the sand bank generally flows to the downstream of the Han River from the
upstream. For terrace, water level amplitude is generally less than 0.5m. The dynamic changes in
45
the water level of terrace slightly lag behind rive stage fluctuation. Flow direction is nearly
perpendicular to bank slope.
The pore fissure water in the clastic rock of the Neogene system within the upper Cretaceous
system is mainly distributed in Xiangcheng, covering structural basin and its edge. The terrain is
mainly low mountains and hillock. Aquifers are mainly of the Tertiary system within the upper
Cretaceous system. Ground water resource is insufficient. The ground water is mainly recharged
by atmospheric precipitation. It runs off and drains through fissure from high land to lowland. It is
mainly heavy calcium carbonate water and heavy calcium magnesium carbonate. Salinity is below
1g/l. Hardness of water is generally 16~25 German degrees.
Fissure karst water mainly containing carbonatite of Sinian system, Cambrian system
and lower Triassic system is mainly distributed in Xiangcheng. Aquifers are exposed
off and on. Exposed area is small. Aquifers are mainly in Sinian strata, Paleozoic
strata and Triassic strata. Aqueously lithology is mainly dolomite, dolomitic
limestone, siliceous dolomite, limestone and argillaceous dolomite. However, karst is
slightly developed. The majority of ground water runs off and drains through fissure.
Ground water is subject to the impact of atmospheric precipitation.
3.2 Social environment overview
3.2.1 Geographic position
Xiangyang is at the heart of central region of China, with particularly favorable
natural conditions. It has an obvious geographic advantage. To the east of Xiangyang
are Jiangsu and Zhejiang provinces. Xiangyang is in the west of Hubei province and
Hunan province. To the west of Xiangyang is the territory of Qin and Shu in history.
Xiangyang links to Nanyang and Luoyang in the north. It is less than 1,000km from
Xiangyang to Wuhan, Zhengzhou, Xi’an, Chongqing and Chengdu. It is at the center
of Y-shape transportation network across central China region, northwest region and
southwest region. It is an important transport hub connecting the east, west, south and
north.
46
Figure 3-1 Geographical location map of Xiangyang
3.2.2 Social and economic development
Xiangyang is divided into Xiangcheng District, Fancheng District, Xiangzhou
District, with an area of 19,700km2 and a population of 5,888,800. The built urban
area is 116km2, with a population of 1,203,000. The economy of urban area is always
ranked second in Hubei. The economy of the whole city is ranked third in Hubei.
In 2010, Xiangyang’s GDP reached RMB153.83 billion, increased by 16.2%; gross
industrial output of enterprises above designated size reached RMB230 billion,
increased by more than 54%; local financial revenue reached RMB14.1 billion,
increased by 48.8%; local general budget revenue reached RMB5.1 billion, increased
by 37.8%; gross industrial output, financial revenue, gross agricultural output, total
retail sales of consumer goods and other indicators are ranked second in Hubei
province. See Table 3-1 for the change in the main national economic indicators of
Xiangyang.
47
Table 3-1 Statistical table of main national economic indicators of Xiangyang
Year GDP
(RMB100 million)
Primary industry
(RMB100
million)
Secondary
industry
(RMB100
million)
Tertiary industry
(RMB100 million)
2000 415.29 97.19 197.04 121.06
2001 450 102 216 132
2002 456.62 103.5 207.9 145.2
2003 503.31 106.89 234.08 162.34
2004 557.88 117.2 259 181.67
2005 601.54 121.91 261.12 218.51
2006 675.18 126.43 290.73 258.02
2007 785.45 140.03 342.43 302.99
2008 1002.46 175.6 450.92 375.94
2009 1201.01 200.21 575.32 425.48
2010 1538.3 234.7 798.2 505.4
Figure 3-2 Economic growth of three industries in Xiangyang
3.2.3 Industrial structure and distribution
Xiangyang is one of traditional industrial bases in Hubei Province, where industrial
system based on automobile, textile and power is formed. It is also a big agricultural
city in history. It is one of the largest ten summer grain crops production areas
throughout the country and the second largest production bases of grain, cotton and
oil. Xiangyang is one of 36 distinguished industrial cities nationwide, where national
and provincial-level “three-line” military industrial enterprises and institutions are
located. Gross industrial output value is second only to Wuhan in Hubei Province. In
terms of textile industry, it is listed among the 39 key cities throughout the country.
Industrial system is developed in this city, wherein light industry, textile, machinery,
48
automobile manufacturing, electronics, medicines, building materials, chemistry and
food are major pillar industries.
In 2010, GDP per capita is 25,638 yuan based on the permanent resident population in
Xiangyang. The proportions of three industries changed to 15.3:51.9:32.8 in 2010
from 23.4:47.4:29.2 in 2000.
Table 3-2 Change in proportions of three industries in Xiangyang (%)
Primary industry Secondary industry Tertiary industry Total
2000 23.4 47.4 29.2 100
2001 22.7 48 29.3 100
2002 22.7 45.5 31.8 100
2003 21 46.4 32.6 100
2004 21.2 46.5 32.3 100
2005 20.3 43.4 36.3 100
2006 18.7 43.1 38.2 100
2007 17.8 43.6 38.6 100
2008 17.5 45 37.5 100
2009 16.7 47.9 35.4 100
2010 15.3 51.9 32.8 100
Figure 3-3 Proportion diagram of three-industry structure of Xiangyang
3.2.4 Overview of project area
The project is mainly located in the Panggong area. The Panggong area is in the east
of Xiangcheng, adjacent to the ancient Xiangyang City in the west, opposite to the
northern Old City in Fancheng across the river, coordinating with the “green heart”
Yuliangzhou and Dongjin cluster in the east. The project is at the point of
interesection of major development lines in the city. It is an important area to
implement urban spatial development strategy.
49
At present, the Panggong area is under the jurisdiction of the Panggong Office,
composed of 9 villages (Panggongci, Wangjiawa, Xujiaxiang, Tujiaxiang, Hongmiao,
Hexin, Sunjiaxiang, Yangjiahe, Shijiamiao and Guanyinge), 62 villager groups and
4,702 households, with population of 14,469 and total area of land for construction up
to 1.70km2. In the west and north of the area, the outskirt of ancient Xiangyang City is
under urbanization. Organizations of administration, education, industry and storage
are scattered. There are over 20 industrial enterprises, belonging to category II
industry and category III industry. Most of enterprises are under poor operating
conditions. Some are closed down or bankrupt.
The Panggong area is gradually formed in the process of long-term development and
evolution of the city. This area reflects the image of the city at different stages:
historic sites, industrial enterprises started in 1970s and 1980s, modern commercial
residential quarter, office building and family-member communities of various
organizations, “villages inside the city”, “villages at the border of the city”, plenty of
farmland and water body. The existing land in this area is mainly used for residence,
industrial warehouses and agricultural production.
3.3 Overview of infrastructure development in project area
3.3.1 Overview of transport development
3.3.1.1 Existing urban roads
The existing road network in Xiangyang is made up of skeleton road networks in
Xiangcheng District, Fancheng District and Xiangzhou and the access roads
connecting these areas. Because of different geographic conditions, the road network
patterns of these three areas are differentiated from each other. In Xiangcheng
District, due to the limit of the Han River and southern mountains, urban land is a
long, narrow area from east to west. The structure of road network is like a strip.
Skeleton roads are Tanxi Road and Huanshan Road along the Han River from east to
west. Primary roads perpendicular to the Han River are East Huancheng Road, Nanjie
Street, South Changhong Road. In Fancheng District where terrain is open and wide,
the structure of road network is like a cheskerboard. The skeleton road network of this
area includes five horizontal lines and five vertical lines. They are Dengcheng
Avenue, Changhong Road, Chunyuan Road, Zhongyuan Road, Songhe Road, Renmin
Road, Daqing Road, Changzheng Road and Qianjin Road. Xiangzhou District is made
up of Xiangzhou District and Automobile Industrial Development Zone. Major roads
include Hangkong Road, Zuanshi Avenue, Dongfengqiche Avenue and Fukang
Avenue. This area is under mixed development.
50
Access roads connecting these areas are mainly Changhong Avenue, Hangkong Road,
Chunyuan North Road, Han River Bridge and Secondary Han River Bridge. Han
River Bridge and Secondary Han River Bridge link Xiangcheng District and
Fancheng District. Hangkong Road and Chunyuan North Road links Fancheng
District are and Xiangzhou District.
Road intersections in central area are grade crossing. There are many T-intersections
and staggered intersections. There are 7 bridges across the river, 2 over the Han River,
4 over the Qinghe River and 1 approaching to Yuliangzhou. Existing primary roads
and railways are in grade separation. In Fancheng District, only a few access roads
across railways. They are Sanyuan Road, Danjiang Road, Tai’an Road, and Daqing
Road. Tai’an Road is only for pedestrian (motor vehicles are not allowed). The roads
across railways are subject to heavy traffic load, becoming traffic bottleneck. In recent
years, the road construction in Xiangyang has undergone stable development. A lot of
primary roads and secondary roads are newly built or reconstructed. Road conditions
are improved. Road network pattern has become more reasonable. Primary roads and
secondary roads adopt three-board cross-section. Motor vehicle lanes and non-motor
vehicle lanes are separated by greenbelts. Motor vehicle lanes are wide. The
environment of non-motor vehicle lanes is good. Most primary roads and secondary
roads have a bituminous pavement. Some have cement pavement. In the recent years,
the municipal government has applied bitumen to cement pavement and transformed
street ancillary facilities like road signs, pavement marking, street lamps, greenbelts,
guardrails and signal lamps. With these efforts, driving comfort and safety are
improved.
3.3.1.2 Integrated urban transport planning
Objective of urban transportation development: building a high-standard, modern
integrated transportation system oriented to public transport and in harmony with the
social and economic development of Xiangyang to provide safe, efficient,
environment-friendly service and to enable the harmonious development of human
and nature and city and nature in the development direction of being efficient
convenient, fair, orderly, safe, comfortable, energy-saving and environment-friendly.
Development strategy: further consolidating the status of Xiangyang as a central city
and continuously carrying forward the planning and construction of intercity transport
like railways and highways to realize the effective connection of internal
transportation system and intercity transport system; building urban transport
corridors to surmount the rivers and railways that separate intercity transport and
supporting and guiding the spatial development strategy of “multiple clusters” in
51
central area to leave sufficient room for the long-term development of the city;
vigorously developing public transport and giving priority to public transport to
promote land development and utilization along the line under the influence of high-
capacity, quick, convenient public transport; strengthening transportation
management, improving the operating efficiency of road network and ensure the
safety of transportation.
Road transport planning: the structure of primary road network for central area is “one
ring road, four horizontal lines, five vertical lines and eight radiating lines” as
follows:
Figure 3-4 Structural Map of urban planning road system
One ring road: the long-term spatial development mode of Xiangyang is “five towns
around a river”. The scales of Xiangcheng, Fancheng, Xiangzhou, Dongjin clusters
are large. An inner ring road can connect these areas (clusters). Inner ring express way
can quickly evacuate intercity transportation and diverge through transportation on the
national highways and provincial highways.
Four horizontal lines: one horizontal line is an express way formed by Yiwu Avenue
and Dengcheng Avenue. Other three horizontal lines are primary roads, namely
Xiwang Road--Fan 10th
Road Corridor, Fan 1st Road--Fukang Avenue Corridor,
Renmin Road--Daqing Road--Hangkong Road Corridor.
Five vertical lines: West Qilihe Road-Xinhua Road--Tai’an Road--Dongfeng Road--
Fourth Han River Bridge--Xiang 1st Road Corridor, Qiaoying Road--Third Han River
52
Bridge--Qilin Avenue Corridor, Changhong Road--Secondary Han River Bridge--
South Changhong Road Corridor, You 4th
Road--East 4th
Road Corridor, East Inner
Ring Road Corridor.
Eight radiating lines: to quickly evacuate intercity transport and improve the
accessibility of the city, the entry sections of national highways and provincial
highways namely G316 (E.), G316(W), G207(N), G207(S), S217, S218, S303 and
S305 should be built to be first-class highway.
Intercity transport planning: four highways (namely Xiangfan-Jingzhou, Xiangfan-
Shiyan, Xiaogan-Xiangfan, Weijiaji-Xiangfan) and national highways (namely 316
and 207) are used as skeleton to upgrade the provincial highways and county-level
highways for horizontal and vertical connection and form a road network together
with skeleton roads. In this way, high-level road network can cover the whole city,
moving forward road transport from axial development to high-level network
development and consolidating the hub position of urban road transport at a higher
level.
Raiways: it is planned to consolidate the railway hub from function, level of facilities,
scientific management and service and to enhance the transport capacity of trunk
railway in Xiangyang. It is also planned to build Xiangyang-Chongqing and Wuhan-
Danjiangkou high-speed railways. Zaoyang, Yicheng and Gucheng railway stations
and yards in Xiangyang should be planned at level 2 and built at level 3. Xiaowan
Station is upgraded to be auxiliary station of Xiangyang passenger station. A land for
the development of Xiangyang marshalling station should be reserved. The transfer
efficiency between railway stations and yards and other means of transportation
should be strengthened to form the overall ganged linkage of railways, to consolidate
its position as railway hub and to improve competitiveness. The railway connection to
other central cities outside Xiangyang should be enhanced. In the long run, inter-city
trains will be run throughout Wuhan, Yichang, Jingzhou, Nanyang, Zhengzhou and
other cities.
Cross-river tunnel planning: overall cross-river tunnel planning is designed to realize
a fast, direct access through cross-river tunnels. It is planned to build four bridges,
respectively at the upstream of Laohekou, between Xiangcheng and Fancheng,
Xiangcheng and Dongjin and at the upstream of Yicheng. A bridge over the Han
River between Xiangcheng and Fancheng (namely the Third Han River Bridge) will
be built in due time.
Public transport planning: it is designed to improve public transport policies and
regulations, to define the priority of public transport, to properly arrange public
53
transport yards and stations and to establish an urban public transport network based
on public transport and supplemented by taxis. It is planned to build a convenient,
efficient, safe, comfortable public transport system characterized by advanced
facilities, good management and coordinated urban-rural public transport
development.
3.3.1.3 Road network planning for the Panggong area
Planned road network of the Panggong area basically adopts grid pattern. Planned
roads can be divided into city express ways, primary roads, secondary roads, branch
roads and riverside landscape roads. The red line of city express ways is 60m wide.
These ways should be controlled according to 120m wide. The red lines of riverside
roads are 12m, 25m and 30m wide. Other roads except city express ways and
riverside roads should be classified into primary roads, secondary roads or branch
roads.
Primary roads: it can be summarized as “six horizontal lines and six vertical lines”.
“Six horizontal lines” refer to 6 east-west roads, namely Jianjin Road, Panggong
Road, Planned 5th
Road, Jianghua Road, Xiangyang Road, Planned 7th
Road. “Six
vertical lines” refers to 6 south-north roads, namely Huancheng East Road-
Huancheng South Road-Shengli Street-Xianshan Road, Sijiqing Road, Zhakou 2nd
Road, Xingguang Avenue, Shengfeng Road and Planned 13th
Road. Primary roads are
main roads serving the transport link of motor vehicles. Primary roads mainly serve
public transport and supports living needs. The red line of primary roads is 24.5-50m
wide. Primary roads mainly adopt three-board cross-section. Some primary roads
adopt single-board or two-board cross-section.
Sub-primary roads: it can be summarized as “five horizontal lines and three vertical
lines”, mainly designed for the transport link of functional clusters in various areas.
Their red lines are 25-30m wide. All of them adopt single-board cross-section.
Branch roads: referring to minor roads for various functional clusters in the area. It is
emphatically planned to improve the density of branch road network, reconstruct the
T-intersection and staggered intersection, unblock cul-de-sacs and dead end
highways, enhance the degree of connectivity and accessibility of roads. The red line
of branch roads is 12-20m wide. All of them adopt single-board cross-section.~~
3.3.2 Urban Drainage Project Overview
3.3.2.1 District Drainage Status
The existing urban areas of Xiangyang city are divided into three major drainage
areas which are named Xiangcheng, Fancheng and Xiangyang by Han River,
54
Xiaoqing River and Tangbai River. The terrain is high in north-south, low in the
middle, hilly in south, loess and down land in north and terrace punched by Han River
in the middle. At present, the total length of existing urban drainage pipe is of
213.65km; the per capita sewer length is 0.2m; the sewer coverage is 81.47%. The
status built-up area has formed 28 drainage districts, 9 in Fancheng, 6 in Xiangcheng
and 12 in Xiangzhou District. The area, north to Qilihe, east to Xiaoqing River and
north to Dengcheng Avenue are rain automatic drainage area. For the other area,
forcing emission is carried out only in flood season. Rain and sewage drainage
pumping stations in the existing city were 27, while service area is 5941ha and the
total pumping capacity is 110.45m3 / s. Refer to figure 3-5 for Xiangyang City
Drainage Division.
55
Figure 3-5 Xiangyang City Drainage Division Status
The terrain of Xiangcheng District is high in south and low in north, high in west and
low in east. In addition, part of the place is low-lying. The status drainage system in
Xiangcheng District is intercepted combined system. The rainwater is drained into the
nearest water. The sewage system is connected to the east of Xiangcheng. Two
intercepted sewage main pipe in the south is delivered to Guanyinge sewage treatment
plant for treatment. Xiangcheng has six drainage areas Xiangyanggucheng, Tanxi,
56
Lingyun Road, 102, Yanshan and Zhakou which has already formed 6 drainage
systems. Currently, it has 10 drainage pump station with drainage capacity of
31.52m3/ s.
The existing drainage system for the improvement project of the project road in
Panggong district is Yanshan drainage system (P3) and Zhakou drainage system (P1).
Yanshan drainage system is mainly for the urban drainage of Yanshan District with its
entrance in front of TV factory and catchment area of 2.12km2. The existing drainage
system is rain water and sewage intercepted system. The main drainage pipes within
the region were not built. Only Yanshan Road has D800-D1000 intercepted trunk
which is eventually flowing into Yanshan pumping station. The rain water is drained
into South channel and sewage enters into Xiangcheng south sewage intercepted main
pipes. Currently, the terrain of Nanqiangxiang and surrounding Jianghua community
for the district is low-lying. The interior pipe network construction of each unit and
community is seriously lagged. The Nanqiangxiang area drains rain sewage through
Nanqianxiang pumping station. Jianghua Community drains rain sewage mainly
through self-built small scaled drainage pumping station by jianghua Mechanical
Factory. The drainage capacity of this pumping station is limited. When heavy rain is
coming, pond shall be formed seriously. According to the calculation, the total flow
amount in Yanshan district is 6.54m3/s during return period within 1 year. In this
connection, the drainage capacity (4.1m3 / s) of Yanshan pumping station can not
meet the drainage requirement of total rain flow within 1 year return period. The
water logging in Shengli Street is mainly caused by storm in short period, flash floods
rushing, poor drainage of south channel and low pumping capacity of pumping
station. The Zhaikou drainage services cover East Huancheng Road, Zhakou Road,
Panggong Road, Jianjin Road Street and North Jinzhou Section, Binjiang Road East
Section, Xinchengwan Street and Xiangyang Park, with catchments area of 3.4km2.
The existing drainage system of Zhakou is rain water and sewage intercepted system.
The existing pipe network and pumping station is formed in 0.5 year storm return
period. The pumping capacity of Zhakou pumping station is 6.64m3/s. The sewage
enters into Zhakou pumping station and drained into Xiangcheng intercepted drainage
pipe. The rain is enhanced into Han River. The catchments area is mainly in
Xiangyang Park and the Yiqiao Road railway culvert. The reason is that the partial
section of flood discharge channel from Hucheng River to Han River is blocked.
3.3.2.1 Regional Drainage Planning
According to the drainage district planning, Xiangcheng drainage district is increased
from 6 to 10. Four drainage areas are increased which are Tanxi T2, T3 drainage area,
57
Panggong P2, P5 drainage area. After the plan implementation, the drainage area will
cover the entire Panggong drainage area. Refer to table 3-3, figure 3-6 for details.
Division No. Catchment Area(ha) The Water for Drainage Remarks
P1 250 Han River Status Division
P2 270 Han River Planning Division
P3 212 South Channel Planning Division
P4 51 South Channel Planning Division
P5 556 Han River Planning Division
Figure 3-6 Xiangyang District Drainage Planning
58
After the implementation of the drainage district planning, Xiangcheng shall increase
four pumping stations. While pumping capacity shall be increased from 31.52m3 / s
to 31.52m3 / s.
3.3.3 Overview of Wastewater Project
(1)Overview of the project area sewage treatment plant
Road improvement sub-project and newly built Yanshan car park maintenance plot in
Panggong District is within the connection scope of Guanyinge sewage treatment. The
phase 1 of Guanyinge sewage treatment plant has already been finished with the
designed sewage treatment capacity of 100,000 t/d. currently the actual sewage
treatment capacity is 60,000 t/d. The sewage, after being treated by A2/O treatment
technique, with ending water reaching Grade 1 Standard B of Municipal Wastewater
Treatment Plant Emission Standards (GB18918-2002), shall be discharged into south
channel finally. The sludge, after being concentrated and digested, shall be delivered
to Yuliangzhou sewage treatment plant. The treated sludge shall be used by Xiangfan
Municipal Agricultural Commission as fertilizer comprehensively. The long-term
sewage treatment capacity of Guanyinge sewage treatment is 200,000 t / d.
The newly built Xiangzhou District Shenzhen industrial car park maintenance sites
are located within the sewage collecting scope of Dongjin sewage treatment plant.
Because Dongjin sewage treatment plant has not yet been built, the sewage of this
area is mainly discharged into Yuliangzhou sewage treatment plant currently. The
current sewage treatment capacity of Yuliangzhou sewage treatment plant, after being
expanded, reaches 300,000 t / d. The sewage, after being treated by A2/O treatment
technique, with ending water reaching Grade 1 Standard B of Municipal Wastewater
Treatment Plant Emission Standards (GB18918-2002), shall be discharged into Han
River finally. The treated sludge, after being concentrated and digested, shall be used
by Xiangfan Municipal Agricultural Commission as fertilizer comprehensively. The
long-term sewage treatment capacity of Yuliangzhou sewage treatment is 485,000t/d.
(2)The overview of sewage pipe network construction within project area
Xiangcheng District status drainage system is intercepted combined system. The
sewage, after being connected to the east of Xiangcheng and south two intercepted
main pipes, shall be delivered to Guanyinge sewage treatment plant for treatment. It
plans to add Yujiahu sewage main pipe with the total length of 7826m. Sewage pipes
D700 shall be paved along 305 provincial road so as to receive the sewage produced
by the east of Xiangcheng which includes Sifu Industrial Park and Xiangnan prison.
59
Sewage pipes D800-D1000 shall be paved along the south of Xianglong Road so as to
receive the sewage produced by Longzhong and surrounding areas. The project
involves Panggong District. Currently Panggong Road has been paved with sewage
treatment pipe network. The Xiangyang Road, north to newly built Yanshan car park
maintenance site has been paved with sewage treatment pipe network. Shengli Street,
north to the site has also been paved with sewage treatment pipe network. At the same
time, Xiangyang Road of the project shall be also been paved with sewage treatment
pipe network (Zhakouerlu East Section). Refer to figure3-7 for the involved Panggong
District sewage treatment pipe distribution status.
60
Figure 3-7 Xiangcheng Drainage Status
Xiangyang Economic Development Zone car parking and maintenance site in Hubei
Shenzhen Industrial Park has made a detail plan for the land uses and road network
layout. Currently the built road network in industrial park has been equipped with
sewage pipe network. Xiangyang Economic Development Zone parking and
maintenance has built south latitude 6°sewage pipe network. The sewage within
Industrial Park, after being collected into Liyuan Channel through pipe network, shall
be finally discharged into Tangbai River. Currently, Xiangyang Sewage Company is
building two Zhangwan intercepted sewage main pipe along Hangkong Road, East
Dengcheng Road and Chunyuan Road. After the establishment of two Zhangwan
intercepted sewage pipe, it can receive the sewage from the east of Qinghe, west of
East Inner Ring Road, south of Fukang Avenue, north of Tangbai River and Hubei
Shenzhen industrial park phase1 sewage. The sewage, after passing through
intercepted sewage pipes, shall be collected in Yuliangzhou sewage treatment plant.
According to the progress, Zhangwan interception trunk can be completed at the end
of 2011, when the Hubei Shenzhen Industrial Park sewage will be collected into
Zhangwan interception trunk rather than directly into Tangbai River. Refer to Figure
3-8 for the sewage pipe network distribution status involved in Hubei Shenzhen
Industrial Park.
61
Figure 3-8 Shenzhen Industrial Park. Drainage Status
3.4 Project area where various types of protected areas and protection of historical and
cultural overview
Xiangyang currently has two provincial urban conservation areas which are Xianshan
Conservation Area and Lumen Temple Conservation Area. The above mentioned two
conservation areas are also national forest parks. In the urban area, there are
Longzhong scenic spots, Lianshan Conservation Area and Putuoyan Scenic spots at
present. Currently, there is one Wetland Park in total which is also Xiangyang
Cuijiaying provincial Wetland Park. Refer to Figure 3-9 for details. None of the above
mentioned protection area is involved in the sub-projects of the project.
62
Xiangyang currently has 59 relics’ protection units at all levels as shown in Figure 3-
10. None of the relics’ protection unit is within the scope of the sub-projects of the
project.
According to Xiangfan Historical and Cultural City Protection Plan, Xiangyang
currently decided two streets Fancheng Laochengxiang and Dongjin Crossed Street as
historical cultural street and 7 historical cultural districts such as Zhongshan Qianhou
District, Dingzhong Street to Jiaotongxiang, Ciqi Street, Youyi Street, Xiangyang
North Street, Jinzhou North Street and Lvyingbixiang. Refer to Figure 3-11 for
details. None of the decided historical cultural street or historical cultural district is
within the sub-projects of the project.
63
Figure 3-9 The Distribution of Natural Reserves, Forest Park and Scenic Spot around the Project
64
Figure 3-10 Distribution of Cultural relics around the Project
65
Figure 3-11 Historic and Cultural Street Distribution around the Project
66
4.0 Survey and assessment of existing environment
4.1 Survey and assessment of existing ecological environment
The project is mainly located in the Panggong area of Xiangyang. The project location
is typically agroecological system. The ecological system in the scope of the
assessment is relatively stable and functionally integral. With effective manual
management and energy supply, the system can be stably sustained and developed,
with certain resistance to jamming.
4.1.1 Existing land usage in project area
The land in the Panggong area is mainly used for agricultural production, industrial
warehouse and residence. Plough accounts for 61.03% of total area while residential
land accounts for 21.49%. See Table 5-1.
Table 5-1 Existing land usage in the Panggong area
No. Land usage Area (ha) Proportion (%)
1 Residential land 329.55 21.49
2 Land for public service facilities 24.60 1.60
3 Industrial land 80.90 5.28
4 Warehouse land 18.72 1.22
5 Intercity transport land 20.39 1.33
6 Land for roads and squares 40.54 2.64
7 Land for municipal utilities 24.84 1.62
8 Green land 12.85 0.84
9 Specially-designated land 5.13 0.33
Waters and miscellaneous 976.25 63.66
Waters 5.74 0.37
Plough 935.89 61.03
Forestry 1.13 0.07
Open space 18.52 1.21
10 Including
Dikes 14.97 0.98
11 Total planning land 1533.42 100.00
4.1.2 Plant resources
Agricultural vegetation predominates in the Panggong area, mainly including food
plants (wheat, broad beans, rice, corn, soybeans, potatoes etc.), oil plants (rape,
sesame, peanuts), melon and fruit (cucumbers, wax gourd, pumpkin), vegetables
(turnip, Chinese cabbage, Caitai, savoy cabbage, spinach etc.) and cotton and hemp
(cotton and ramie). In the Panggong area, street trees and agricultural afforestation are
main trees, including sycamore, privet, metasequoia, populus etc.
67
According to field survey and referring to pertient materials, rare and endangered plants, ancients
and rare trees are not found in the project area.
4.1.3 Animal resources
As human activities have long influenced the Panggong area, terrestrial animals can
be found in this area are mainly domestic livestock and some small wild animals.
Domestic animals mainly include cattles, pigs, sheep, rabbits, dogs, cats, chicken,
ducks and geese etc.
Amphilians mainly include Bufo gargarizans, Rana plancyi, Rnigromaculata etc., the
majority of which is Bufo gargarizans.
Reptiles mainly include Chinemys reevesii, Trionyx sinensis, Eumeces chinensis,
Zaocys dhumnades, Elaphe mandarina etc., the majority of which are Eumeces
chinensis, and Zaocys dhumnades.
Birds mainly include Egretta garzetta, Bubulcus ibis, Larus ridibundus, Anas.
Platyrhynchos, Alcedinidae, Alcedo atthis, Hirundinidae, Hirundo rustica, Lanius
schach, Dicrurus macrocercus, Acridotheres cristatellus, Cyanopica cyana, Pica
pica, Passer montanus, Streptopelia orientalis, the majority of which is Hirundo
rustica.
Beasts mainly include Erinaceus europaeus, Pipistrellus abramus, Lepus sinensis,
R..novegicus, Cricetulus barabensis, Callosciurus ergthraeus, Mustela sibirica etc.,
the majority of which are Lepus sinensis and R..novegicus.
No national or provincial-level key protected wild terrestrial animal is found in the
project area under assessment.
4.1.4 Existing water loss and soil erosion
According to the Announcement of the Provincial People’s Government on Key
Prevention and Control Zones of Water Loss and Soil Erosion promulgated by Hubei
Provincial People’s Government, the project is in a key prevention and control zone
of water loss and soil erosion because a shallow-hill area near the Jianghan Plain in
68
Hubei Province is along the line of the project. The allowable value of water loss and
soil erosion is 500t/km²•a in the project area. The type of water loss and soil erosion is
slight in the project area. Local section is subject to water loss and soil erosion due to
road excavation in municipal construction.
4.2 Survey and assessment of existing acoustic environment
4.2.1 Regional ambient noise and traffic road noise
According to the Bulletin of Environment of Xiangyang in 2010, the annual value of
regional ambient noise and the annual value of traffic road noise are 55.5dB(A) and
67.9dB(A) respectively in 2010. See Table 4-2 for monitored values.
Table 4-2 Noise monitoring result in 2010
Noise level dB(A)
Monitoring item
Monitored values in 2010 Monitored values in 2009
Annual value of regional ambient noise 55.5 55.3
Annual value of traffic road noise 67.9 67.8
Urban road network hasn’t been formed in the Panggong area. At present, the quality
of regional acoustic environmental is good.
4.2.2 Existing acoustic environment at sensitive points
An ambient noise monitoring plan is set out for the environmental impact assessment.
China Railway Siyuan Survey And Design Group Co., Ltd. is responsible for
fulfilling the plan.
(1) Executive standard and specification applied in the measurement
The Environmental Quality Standard for Noise (GB3096-2008) should be applied.
(2) Measurement plan
� Measuring instrument
The ambient noise monitoring adopts RION NL-31 precision sound level meters. The
performance of all the measuring instruments should meet t he requirements of
monitoring standard.
69
� Measurement time and method
Ambient noise monitoring should be performed in the daytime and at night.
Equivalent continuous sound level should be measured for 20 min when flow is not
below average. It should represent the level of existing acoustic environment. For the
regions subject to the impact of road traffic, measured statistic (L90) should be used
as background level. For the regions mainly subject to the impact of living noise, the
measured values of existing acoustic environment should be used as background
level.
� Measurement and assessment value
The Measurement and assessment value is equivalent continuous noise level A.
(3) Principle of measuring point distribution
The project is partially located in the built-up area of the City. The impact of road
traffic noise is great along the line. All the noise sensitive points are covered in the
ambient noise monitoring. Noise monitoring points are set at different floors for high-
rise buildings. In this way, measured values can not only reflect the existing
environment of the area under assessment but also be used as reliable data for noise
forecast.
(4) Monitoring result
� Overview of noise source
In the road network improvement project, Panggong road section is mainly subject to
the impact of existing traffic noise. The majority of vehicles are heavy duty truck,
agricultural vehicles and motorcycles whose horn blows frequently. Social activities
such as farm product trade are frequent. Great noise is in this section. The quality of
acoustic environment is poor. For other planned road sections, the quality of the
quality of acoustic environment is good because these sections are mainly subject to
the impact of noise from social life
� Analysis on monitoring result of existing ambient noise
57 sensitive points for different kinds of environment are set along the project, 2
points at schools, 1 point at hospital and the rest 54 points at residential building.
The ambient noise at sensitive points along the Panggong road section is 52.1~63.4dB
in the daytime and 46.1~52.8dB at night. The noise at Yiheyuan is out of limit by
1.4~1.9dB in the daytime. The noise at Yiheyuan and Xiangyang Degong Hospital are
70
out of limit by 0.5~1.3dB at night. This is because the majority of vehicles are heavy
duty truck, agricultural vehicles and motorcycles whose horn blows frequently and
loudly. There is a farm product market at the intersection of Panggong Road and
Zhakou 2nd
Road. The noise from commercial complex and social life is great. The
ambient noise at the other sensitive points can meet corresponding environmental
standards both in the daytime and at night.
The noise at the sensitive points along other planned lines is 48.2~59.1dB in the
daytime and 41.9~47.7dB at night, meeting the limits of “60dB in the daytime, 50 dB
at night” in class II area. The noise is mainly from several country roads in the
planned project area. Sensitive points are set in the suburbs, far from urban area.
Sensitive buildings are mainly subject to the impact of social life. The quality of
acoustic environment is good.
4.3 Survey and assessment of existing water environment
The project doesn’t involve the main water systems of Xiangyang. No river system is
in the Panggong area. In this assessment, the existing water environment of the water
systems near the project is surveyed.
In 2010, six monitoring sections are set along the main stream of the Han River:
Fujiazhai section and Xianrendu section in Laohekou City, Baijiawan, Qianying
section, Yujiahu section in Xiangyang, Guo’an section in Yicheng (among which
Fujiazhai section flows into Xiangyang and Guo’an section outflow from Xiangyang).
According to monitoring result, the water quality of the main stream of the Han River
is very good. Compared with the previous year, there is no significant change in the
overall water quality. The 6 monitoring sections meet class-2 water quality, at the
same level as the previous year. See Table 4-3.
Table 4-3 Assessment of classification of water quality of the main stream of the
Han River in 2010
River section
monitored
Name of
section
Required
class
Class
this year
Class
last year
Name of
items and the
time
exceeding
standard
Fujiazhai � � � ~
Laohekou
Xianrendu � � � ~
Xiangyang Baijiawan � � � ~
71
Qianying � � � ~
Yujiahu � � � ~
Yicheng Guo’an � � � ~
The moat of Xiangyang belongs to a lake inside the city. Nanqu Canal is a canal to
hold pollutant and sewage in the city. According to monitoring result, Nanqu Canal is
suffered from serious pollution. The quality of water is the same as the class inferior
V last year. The water quality of the moat is slightly polluted, down to class IV from
class III.
See Figure 4-1 for the distribution of surrounding water system.
72
Figure 4-1 Distribution map of surrounding water system
4.4 Survey and analysis of existing ambient air
4.4.1 Urban ambient air
According the Bulletin of Environment of Xiangyang in 2010, the annual value of SO2 is
0.029mg/m3; the annual value of NO2 is 0.028mg/m3; the annual value of inhalable particles is
73
0.089mg/m3. In 2010, the number of effective monitoring days in urban area is 365days. The
quality of air is excellent in 316 days, accounting for 86.6% of the effective monitoring days. In
2010, the critical pollutant is inhalable particles. See Table 4-4 for monitoring result.
Table 4-4 Statistical result of atmosphere in Xiangyang in 2010
~ 2010monitored values 2009monitored values Remarks
Annual concentration of
SO2 0.029 mg/m
3 0.028mg/m
3
Annual concentration of
NO2 0.028mg/m
3 0.024mg/m
3
Annual concentration of
inhalable particles 0.089 mg/m
3 0.096mg/m
3
API<=50 days 67 28
50 days<API<100 days 249 286
100 days<API<150 days 47 51
API>150 days 2 0
In 2009,
effective
monitoring
days are
365days. In
2010, effective
monitoring
days are 365.
4.4.2 Existing ambient air in the project area
The project financed by the loans from the World Bank is mainly located in the
Panggong area. Assessment unit has authorized the Xiangyang Environment
Monitoring Station to monitor the quality of ambient air.
(1) Monitoring factors
Referring to the Highway Construction Environment Impact Assessment (JTG B03-2006) and the
Ambient Air Quality Standard (GB3095-1996) (revision on Jan. 6, 2000) and combining the
features of the project and the monitoring capacity of Xiangyang Environment Monitoring Station,
NO2 and PM10 are determined as the monitoring factors of existing ambient air monitoring.
(2) Monitoring analytical method
See Table 4-5 for monitoring analytical method.
Table 4-5 Analytical method for ambient air samples
Monitoring item NO2 PM10
74
analytical method Griess saltzman method Gravimetric method
Source of method GB/T15436-95 GB/T15262-95
(3) Monitoring time and frequency
Monitoring period is from August 9~August 16, 2011 (continuous monitoring). Four time a day
(Beijing time 8:00-9:00, 14:00-15:00, 20:00-21:00 and 02:00-03:00). Meteorological
oberservation should be conducted synchronously.
(4) Distribution of monitoring points
Location of monitoring points:
� Zhakou 2nd
Road: Hongmiao Village Group 4;
� Panggong Road: Panggong Garden;
� Southeast section of Inner Ring Road: Sunjiaxiang Village Group 7.
(5) Monitoring result
� Primary NO2 concentration at various monitoring points in the monitoring period is
0.010~0.075mg/m3, meeting the second level criterion (0.24mg/m
3) of the Ambient Air Quality
Standard GB3095-1996.
� Daily PM10 concentration at various monitoring points in the monitoring period is
0.1574~0.4854mg/m3, exceedinging the second level criterion (0.15mg/m
3) of the Ambient Air
Quality Standard GB3095-1996.
In conclusion, the primary NO2 concentration at various monitoring points in the
monitoring period meets the second level criterion of the Ambient Air Quality
Standard GB3095-1996. However, the daily PM10 concentration at various monitoring
points in the monitoring period exceeds the second level criterion (0.15mg/m3) of the
Ambient Air Quality Standard GB3095-1996. It can be seen that the pollution caused
by motor vehicle exhaust is not very serious. The cause of serious PM10 pollution is
the construction of the Fifth Jianghan Bridge. Because of the construction, there are
many construction vehicles in the project area. During transportation and travelling,
vehicles raise a lot of dust.
4.4.3 Existing management of urban atmosphere
At present, Xiangyang municipal people’s government has implemented some
prevention and control measures for atmospheric pollution as follows:
75
(1) Xiangyang municipal people’s government has completed the 12th
Five-year
Planning for Total Emission Control of Major Pollutants in Xiangyang. The planning
emphasizes structural emission reduction and strengthens engineering emission
reduction to constantly carry forward pollutant emission reduction through strict
management.
(2) Strict implementation of emission standard for newly licensed vehicles
The promulgation of the Limits and Measurement Methods for Emissions from Light-
duty Vehicles GB18352.3-2005 (III, IV), the Limits and Measurement Methods for
Exhaust Pollutants from Compression Ignition and Gas Fuelled Positive Ignition
Engines of Vehicles GB17691-2005 (III, IV, V) and the Limits and Measurement
Method for Exhaust Pollutants from Gasoline Engines of Heavy-duty Vehicles (III,
IV) one after another reflects that China has attached more and more importance to
the environmental problems caused by the exhaust pollutants from motor vehicles.
The emission standards for new vehicles become stricter and stricter. At present, the
above standards have been implemented in Xiangyang as of the date of
implementation, strengthening the control over emissions from vehicles
(3) Improvement on quality of fuels and application of alternative fuels
At present, fuel oils for vehicles on the market in Xiangyang are mainly light diesel
oil, vehicle-use unleaded gasoline, vehicle-use ethanol gasoline. The quality of fuel
products are improved greatly. Vehicle fuel available on the market in Xiangyang
meets relevant national standards. Moreover, some buses and taxies have undergone
oil-to-gas transformation. These vehicles consume cleaner energy to further mitigate
pollution caused by emissions from vehicles. The replacement of alternative fuels is
under way.
5.0 Scheme comparison and selection
In the project design, there are no Comparison schemes for road strike and station
yard site selection. The Comparison schemes in current design mainly involve with
comparison for road cross section. In this assessment, different Comparison schemes
for road cross section were compared and analyzed. In addition, scheme comparison
for road strike was given from the environmental impact perspective in order to
determine the construction scheme with minimum negative environmental impact
through comparing different schemes and provide reference for optimized decision-
making by the project construction decision-making authority.
76
5.1 Road cross section comparison and selection
5.1.1 Comparison schemes for cross section of the southeast section of the inner ring road
For scheme comparison for cross section of the southeast section of the inner ring road, refer to
Table 5-1. With environment comparison and selection, the recommended scheme in the
assessment conforms to the recommended design scheme, namely the scheme A.
Table 5-1 Scheme comparison for cross section of the southeast section of the inner
ring road
Existing
conditions Scheme A Scheme B
60m=3.5m sideway+3.5m non-
motorized vehicle way +7.25m
green belt+11.75m drive way+8m
median separator+11.75m drive
way+7.25m green belt +3.5m
non-motorized vehicle way+3.5m
sideway
60m=4.75m non-motorized vehicle
way +7.0m auxiliary road+6.5m
green belt+23.5m drive way+6.5m
green belt +7.50m auxiliary road
+4.75m pedestrian and non-
motorized vehicle way
Scheme
Comparison
No road
Environmental
impact during
construction
period
Scheme A and B have the same Environmental impact during construction period.
Environmental
impact on
ecology and
landscape
Scheme A and B have the same road red line, and occupy the same land. From the
ecological environmental impact, scheme A and B are same; from the environmental
impact on landscape, greening rate of scheme A is higher than that of scheme B and
road landscape design is beautiful.
Acoustic
environment
impact during
operation
period
Greening rate of scheme A is higher than that of scheme B. In addition, it will plant
several rows of arbor at both sides of the road, which is good for reducing impact of
road noise on sensitive spots at both sides of the road during the operation period.
Ambient air
impact during
operation
period
Greening rate of scheme A is higher than that of scheme B. In addition, it will plant
several rows of arbor at both sides of the road, which is good for reducing impact of
automobile exhaust gas on sensitive spots at both sides during the operation period.
Conclusion It is necessary to construct the southeast section of the inner ring road. For such
aspects as environmental impact on landscape, impact on acoustic environment and
ambient air during operation of scheme A is better than those of scheme B.
Recommendati
on
Scheme A is recommended based in this assessment, it is same to the recommended
scheme in design.
5.1.2 Comparison schemes for cross section of the Xingguang Avenue
For scheme comparison for cross section of the Xingguang Avenue, refer to Table 5-
2. With environment comparison, the assessment holds that landscape in scheme B is
better than that of recommended design scheme (Scheme A). In addition, effects of
preventing and control impact of noise and automobile exhaust gas are of scheme B
77
better than scheme A. Thus, the assessment recommends for scheme B for road cross
section of Xingguang Avenue.
Table 5-2 Scheme comparison for cross section of the Xingguang Avenue
Existing
conditions Scheme A Scheme B
80m=15m green line +6.75m
pedestrian and non-motorized
vehicle way +5m green belt
+11.75m drive way (0.5m marginal
strip included) +3m median
separator +11.75m drive way (0.5m
marginal strip included)+5m green
belt+6.75m pedestrian and non-
motorized vehicle way+15m green
line. Greening rate is 26%. Type of
cross section: two-plate type
80m=15m green line+4.75m sideway
(1.5m tree pool included)+3.5m non-
motorized vehicle way+3.5m green
belt +11.75m drive way (0.5m
marginal strip included)+3m median
separator+11.75m drive way (0.5m
marginal strip included)+3.5m green
belt+3.5m non-motorized vehicle
way+4.75m sideway (1.5m tree pool
included) +15m green line. Greening
rate is 26%. Type of cross section:
four-plate type
Scheme
Comparison
No road
Environmental
impact during
construction
period
Cross section of scheme A is two-plate type, namely the bi-direction motor vehicle are
mutually separated by the median separator. Cross section of scheme B is the four-plate
type, namely the motor vehicle, non-motorized vehicle and land along the street are
mutually separated by the median separators. Two-plate type is convenient than four-plate
type in construction, the earthwork volume is smaller. From the environmental impact
during the construction period, scheme A is better than scheme B.
Environmental
impact on
ecology and
landscape
Scheme A and B have the same road red line, and occupy the same land. From the
ecological environmental impact, scheme A and B are same; from the environmental impact
on landscape, road landscape design of scheme B is more beautiful than that of scheme A.
Acoustic
environment
impact during
operation period
Under the same greening rate, compared with scheme A, scheme B will plant several rows
of arbor at both sides of the road, which is good for reducing impact of noise on sensitive
spots at both sides during the operation period.
Ambient air
impact during
operation period
Under the same greening rate, compared with scheme A, scheme B will plant several rows
of arbor at both sides of the road, which is good for reducing impact of automobile exhaust
gas on sensitive spots at both sides during the operation period.
Conclusion
Although environmental impact of scheme A during the construction period is smaller than
that of scheme B, after construction is completed, construction impact will be eliminated
also. Relative to the construction period, during the operation period, landscape
beautification, noise and atmosphere protection effect of scheme B is better than those of
scheme A.
Recommendation In the assessment, scheme B is recommended, which is different to the recommended
design scheme.
5.1.3 Comparison schemes for cross section of the Jianghua Road
For scheme comparison for cross section of the 30m-redline section of Jianghua
Road; refer to Table 5-3. With environment comparison and selection, the
recommended scheme in the assessment is same to the recommended design scheme,
is the scheme A. For scheme comparison for 40m-redline and 50m-greenline of the
78
section of Jianghua Road, refer to Table 5-4. With environment comparison and
selection, the recommended scheme in the assessment is same to the recommended
design scheme, is the scheme A.
Table 5-3 Scheme comparison for cross section of the 30m-redline section of
Jianghua Road
Existing
conditions Scheme A Scheme B
30m=5m pedestrian and non-
motorized vehicle way+2m green
belt+16m drive way+2m green
belt+5m pedestrian and non-
motorized vehicle way. Greening
rate is 13.3%. Type of cross
section: three-plate type
30m=2m sideway +3.5m non-
motorized vehicle way+1.5m
greening belt+16m drive
way+1.5m greening belt +3.5m
non-motorized vehicle way+2m
sideway. Type of cross section:
one-plate type
Scheme
Comparison
No road
Environmental
impact during
construction
period
Cross section of scheme A is three-plate type, namely the motor vehicle, non-
motorized vehicle and land along the street are mutually separated. Cross section
of scheme B is the one-plate type, namely the motor vehicle and non-motorized
vehicle are not mutually separated. Compared with the three-plate type, one-plate
is more convenient for construction, the earthwork volume is smaller. From the
environmental impact during the construction period, scheme B is better than
scheme A.
Environmental
impact on
ecology and
landscape
Scheme A and B have the same road red line, and occupy the same land. From the
ecological environmental impact, scheme A and B are same. However, greening
rate of scheme A is higher that that of scheme B, and the long-term ecologic
benefit of scheme A is better than that of scheme B in operation period.
From the environmental impact on landscape, scheme A and scheme B about the
same.
Acoustic
environment
impact during
operation period
Scheme A and scheme B are about the same.
Ambient air
impact during
operation period Scheme A and scheme B are about the same.
Conclusion
Although environmental impact of scheme A during the construction period is
smaller than that of scheme B, after construction is completed, construction impact
will be eliminated also. Under the similar landscape beautification, noise during
operation period, atmosphere protection effect, greening rate of scheme A is higher
that that of Scheme B, and the long-term ecologic benefit of scheme A is better
than that of Scheme B in operation period.
Recommendation In the assessment, scheme A is recommended, which is same to the recommended
design scheme.
Table 5-4 Scheme comparison for cross section of the 40m-redline section of
Jianghua Road
Scheme
Existing
conditions Scheme A Scheme B
79
50m=5m for width of green
line+4.5m sideway (1.5m tree pool
included)+4.5m non-motorized
vehicle way+3m green belt+16m
drive way+3m green belt+4.5m non-
motorized vehicle way+4.5m
sideway+5m for width of green line.
Greening rate is 27.5%. Type of
cross section: three-plate type
50m=5m for width of green line+6.5m
pedestrian and non-motorized vehicle
way+5.5m green belt+16m drive
way+5.5mm green belt+6.5m
sideway+5m for width of green line.
Greening rate is 22.5%. Type of cross
section: one-plate type
Comparison
No road
Environmental
impact during
construction
period
Cross section of scheme A is three-plate type, namely the motor vehicle, non-motorized
vehicle and land along the street are mutually separated. Cross section of scheme B is the
one-plate type, namely the motor vehicle and non-motorized vehicle are not mutually
separated. Compared with the three-plate type, one-plate is more convenient for
construction, the earthwork volume is smaller. From the environmental impact during the
construction period, scheme B is better than scheme A.
Environmental
impact on
ecology and
landscape
Scheme A and B have the same road red line, and occupy the same land. From the ecological
environmental impact, scheme A and B are same. However, greening rate of scheme A is
higher that that of scheme B, and the long-term ecologic benefit of scheme A is better than
that of Scheme B in operation period.
From the environmental impact on landscape, road landscape design of scheme A is more
beautiful than that of scheme B.
Acoustic
environment
impact during
operation period
Compared with scheme B, scheme A will plant several rows of arbor at both sides of the
road, which is good for reducing impact of noise on sensitive spots at both sides during the
operation period.
Ambient air
impact during
operation period
Compared with scheme B, scheme A will plant several rows of arbor at both sides of the
road, which is good for reducing impact of automobile exhaust gas on sensitive spots at both
sides during the operation period.
Conclusion
Although environmental impact of scheme A during the construction period is smaller than
that of scheme B, after construction is completed, construction impact will be eliminated
also. Relative to the construction period, during the operation period, landscape
beautification, noise and atmosphere protection effect of scheme A is better than those of
scheme B.
Recommendation In the assessment, scheme A is recommended, which is same to the recommended design
scheme.
5.1.4 Comparison schemes for cross section of the Zhakou 2nd
Road
For scheme comparison for cross section of Zhakou 2nd
Road; refer to Table 5-5. With
environment comparison and selection, the recommended scheme in the assessment is
same to the recommended design scheme, is the scheme A.
Table 5-5 Scheme comparison for cross section of Zhakou 2nd
Road
Scheme
Existing
conditions Scheme A Scheme B
80
40m=4.75m sideway (1.5m tree pool
included)+ 4m non-motorized
vehicle way+2m motor vehicle and
non-motorized vehicle
separator+7.75m drive way (0.5
marginal strip included)+3m median
separator+7.75 drive way (0.5
marginal strip included)+ 2m motor
vehicle and non-motorized vehicle
separator+4m non-motorized vehicle
way+4.75m sideway (1.5m tree pool
included)
Greening rate is 27.5%. Type of
cross section: three-plate type
40m=5m sideway (1.5m tree pool
included)+ 5.5m auxiliary road+2m
motor vehicle and non-motorized
vehicle separator+15m drive way+2m
motor vehicle and non-motorized
vehicle separator+ +5.5m auxiliary
road+ 5m sideway (1.5m tree pool
included)
Greening rate is 22.5%. Type of cross
section: one-plate type
Comparison
No road
Environmental
impact during
construction
period
Cross section of scheme A is three-plate type, namely the motor vehicle, non-motorized
vehicle and land along the street are mutually separated. Cross section of scheme B is the
one-plate type, namely the motor vehicle and non-motorized vehicle are not mutually
separated. Compared with the three-plate type, one-plate is more convenient for
construction, the earthwork volume is smaller. From the environmental impact during the
construction period, scheme B is better than scheme A.
Environmental
impact on
ecology and
landscape
Scheme A and B have the same road red line, and occupy the same land. From the
ecological environmental impact, scheme A and B are same. However, greening rate of
scheme A is higher that that of scheme B, and the long-term ecologic benefit of scheme A is
better than that of Scheme B in operation period.
From the environmental impact on landscape, road landscape design of scheme A is more
beautiful than that of scheme B.
Acoustic
environment
impact during
operation period
Compared with scheme B, scheme A will plant several rows of arbor at both sides of the
road, which is good for reducing impact of noise on sensitive spots at both sides during the
operation period.
Ambient air
impact during
operation period
Compared with scheme B, scheme A will plant several rows of arbor at both sides of the
road, which is good for reducing impact of automobile exhaust gas on sensitive spots at both
sides during the operation period.
Conclusion
Although environmental impact of scheme A during the construction period is smaller than
that of scheme B, after construction is completed, construction impact will be eliminated
also. Relative to the construction period, during the operation period, landscape
beautification, noise and atmosphere protection effect of scheme A is better than those of
scheme B.
Recommendation In the assessment, scheme A is recommended, which is same to the recommended design
scheme.
5.1.5 Comparison schemes for cross section of the Xiangyang Road
For scheme comparison for cross section of Xiangyang Road; refer to Table 5-6. The
section mainly discusses advantages and disadvantages of the Comparison schemes
for cross section in design without altering road strike. For details on comparison for
Xiangyang Road strike, refer to 5.2.
Table 5-6 Scheme comparison for cross section of Xiangyang Road
81
Existing conditions Scheme A Scheme B
The existing road is
cement road wide in
3m, there are street
trees (Chinese
redwood) at both
sides.
40m=4.75m sideway (1.5m
tree pool included)+ 4m non-
motorized vehicle way+2m
motor vehicle and non-
motorized vehicle
separator+7.75m drive way
(0.5 marginal strip included)
+3m median separator+7.75m
drive way (0.5 marginal strip
included) +2m motor vehicle
and non-motorized vehicle
separator+4m non-motorized
vehicle way4.75m sideway
(1.5m tree pool included)
Greening rate is 27.5%. Type
of cross section: three-plate
type
40m=5m sideway (1.5m tree
pool included)+ 5.5m
auxiliary road+2m motor
vehicle and non-motorized
vehicle separator+15m drive
way+2m motor vehicle and
non-motorized vehicle
separator+ +5.5m auxiliary
road+ 5msideway (1.5m tree
pool included)
Greening rate is 22.5%.
Type of cross section: one-
plate type
Scheme
Comparison
Environment
al impact
during
construction
period
Cross section of scheme A is three-plate type, namely the motor vehicle, non-motorized
vehicle and land along the street are mutually separated. Cross section of scheme B is
the one-plate type, namely the motor vehicle and non-motorized vehicle are not
mutually separated. Compared with the three-plate type, one-plate is more convenient
for construction, the earthwork volume is smaller. From the environmental impact
during the construction period, scheme B is better than scheme A.
Environment
al impact on
ecology and
landscape
Scheme A and B have the same road red line, and occupy the same land. From the
ecological environmental impact, scheme A and B are same. However, greening rate of
scheme A is higher that that of scheme B, and the long-term ecologic benefit of scheme
A is better than that of Scheme B in operation period.
From the environmental impact on landscape, road landscape design of scheme A is
more beautiful than that of scheme B.
Acoustic
environment
impact
during
operation
period
Compared with scheme B, scheme A will plant several rows of arbor at both sides of
the road, which is good for reducing impact of noise on sensitive spots at both sides
during the operation period.
Ambient air
impact
during
operation
period
Compared with scheme B, scheme A will plant several rows of arbor at both sides of
the road, which is good for reducing impact of automobile exhaust gas on sensitive
spots at both sides during the operation period.
Conclusion
Although environmental impact of scheme A during the construction period is smaller
than that of scheme B, after construction is completed, construction impact will be
eliminated also. Relative to the construction period, during the operation period,
landscape beautification, noise and atmosphere protection effect of scheme A is better
than those of scheme B.
Recommend
ation
In the assessment, scheme A is recommended, which is same to the recommended
design scheme.
82
5.1.6 Comparison schemes for cross section of the Panggong Road
For scheme comparison for 40m-redline and 50m-greenline of the section of
Panggong Road, refer to Table 5-7. With environment comparison and selection, in
the assessment, it is believed that section from K0+215 to K1+365 shall maintain the
existing cross section, it only requires broadening the road and provide additional
non-motorized vehicle way to meet the requirement of 40m-redline of the road. In
addition, it shall upgrade the existing pavement; for the section from K1+365 to the
end point, it agrees with the recommended scheme in design, namely scheme A.
Table 5-7 Scheme comparison for cross section of Panggong Road
Existing conditions Scheme A Scheme B
For section from
K0+215 to K1+365,
the existing road is
the one-plate road
whose redline is 30m.
30m=8m green
belt+14 drive
way+8m green belt.
Greening at both
sides of the road is
fairly good; for the
section from K1+200
to the end point, it is
the cement road wide
in 6m, and there are
not street trees at both
sides.
50m=5m for width of green
line+4.5m sideway (1.5m tree
pool included)+4.5m non-
motorized vehicle way+3m
green belt+16m drive way+3m
green belt+4.5m non-
motorized vehicle way+4.5m
sideway+5m for width of
green line.
Greening rate is 27.5%. Type
of cross section: three-plate
type
50m=5m for width of green
line+6.5m pedestrian and
non-motorized vehicle
way+5.5m green belt+16m
drive way+5.5mm green
belt+6.5m sideway+5m for
width of green line.
Greening rate is 22.5%.
Type of cross section: one-
plate type
Scheme
Comparison
Environment
al impact
during
construction
period
It will reserve the section from K0+215 to K1+365. With the existing road cross
section, it will only upgrade the road section. The environmental impact during the
construction period is greatly smaller than those of scheme A and B.
Environment
al impact on
ecology and
landscape
If Panggong Road is built with scheme A and B, it will damage greening at both sides
of existing road and affect the ecology and landscape. While if the existing road cross
section is maintained, project construction will have much less impact on ecology and
landscape.
Acoustic
environment
impact
during
operation
If Panggong Road is built with scheme A and B, it will damage greening at both sides
of existing road. After greening at both sides will be restored after construction is
completed, but the newly grown trees or the transplanted original trees are not very
luxuriant, its noise prevention effect is greatly inferior to that of the original luxuriant
83
operation
period
trees. Thus, maintaining the existing road cross section has better noise prevention
effect than those of scheme A and B.
Ambient air
impact
during
operation
period
Ditto
Conclusion
If the existing road cross section is maintained, environmental impact, impact on
ecology and landscape during the construction period are smaller than those of scheme
A and B; in addition, the noise and atmosphere protection effect are also better than
those of scheme A and B.
Recommend
ation
It will not take up scheme A and B. According to assessment, for section
from K0+215 to K1+365, it will maintain the existing cross section, it
only requires broadening the road and provide additional non-motorized
vehicle way to meet the requirement of 40m-redline of the road. In
addition, it shall upgrade the existing pavement; for the section from
K1+365 to the end point, it agrees with the recommended scheme in
design, namely scheme A.
5.1.7 Comparison schemes for cross section of the Planned 13th Road
For scheme comparison for cross section of Planned 13th Road; refer to Table 5-8.
With environment comparison and selection, the recommended scheme in the
assessment is same to the recommended design scheme, is the scheme A.
Table 5-8 Scheme comparison for cross section of Planned 13th Road
Existing
conditions Scheme A Scheme B
40m=4.75m sideway (1.5m tree pool
included)+ 4m non-motorized
vehicle way+2m motor vehicle and
non-motorized vehicle
separator+7.75m drive way (0.5
marginal strip included)+3m median
separator+7.75 drive way (0.5
marginal strip included)+ 2m motor
vehicle and non-motorized vehicle
separator+4m non-motorized vehicle
way+4.75m sideway (1.5m tree pool
included)
Greening rate is 27.5%. Type of
cross section: three-plate type
40m=5m sideway (1.5m tree pool
included)+ 5.5m auxiliary road+2m
motor vehicle and non-motorized
vehicle separator+15m drive way+2m
motor vehicle and non-motorized
vehicle separator+ +5.5m auxiliary
road+ 5m sideway (1.5m tree pool
included)
Greening rate is 22.5%. Type of cross
section: one-plate type
Scheme
Comparison
No road
Environmental
impact during
construction
period
Cross section of scheme A is three-plate type, namely the motor vehicle, non-motorized
vehicle and land along the street are mutually separated. Cross section of scheme B is the
one-plate type, namely the motor vehicle and non-motorized vehicle are not mutually
separated. Compared with the three-plate type, one-plate is more convenient for
construction, the earthwork volume is smaller. From the environmental impact during the
construction period, scheme B is better than scheme A.
Environmental
impact on
ecology and
Scheme A and B have the same road red line, and occupy the same land. From the ecological
environmental impact, scheme A and B are same. However, greening rate of scheme A is
84
ecology and
landscape
higher that that of scheme B, and the long-term ecologic benefit of scheme A is better than
that of Scheme B in operation period.
From the environmental impact on landscape, road landscape design of scheme A is more
beautiful than that of scheme B.
Acoustic
environment
impact during
operation period
Compared with scheme B, scheme A will plant several rows of arbor at both sides of the
road, which is good for reducing impact of noise on sensitive spots at both sides during the
operation period.
Ambient air
impact during
operation period
Compared with scheme B, scheme A will plant several rows of arbor at both sides of the
road, which is good for reducing impact of automobile exhaust gas on sensitive spots at both
sides during the operation period.
Conclusion
Although environmental impact of scheme A during the construction period is smaller than
that of scheme B, after construction is completed, construction impact will be eliminated
also. Relative to the construction period, during the operation period, landscape
beautification, noise and atmosphere protection effect of scheme A is better than those of
scheme B.
Recommendation In the assessment, scheme A is recommended, which is same to the recommended design
scheme.
5.2 Comparison and selection for road strike
Presently, street trees at both sides of Xiangyang Road grow well and are plenty, it
must damage these trees if the road is built along the existing road. In consideration of
the reducing the relocation work volume of the project, in the assessment, it is
suggested that the design scheme for Xiangyang Road will be entirely translated for
3~5m toward the north side and will not occupy the road and the street trees at both
sides. In this way, it cannot only eliminate damage of the project against the existing
trees, reduce relocation work volume, the existing road can be used as construction
detour and reduce environmental impact on of the temporary works. Although
Xiangyang Road is entirely translated toward the north side, the road strike keep same
to the strike of Xiangyang Road in the road network planning of Panggong area.
6.0 Environmental Impact Assessment
6.1 Environmental impact analysis during construction period
6.1.1 Ambient air quality impact analysis during the construction period
During construction of the project, the main sources causing atmospheric pollution
include dust emission caused by construction excavation and transport vehicle, dust
emission and falling during handling, transport and stacking of construction building
materials (cement, lime, sandstone material) and during excavation and stacking and
transport of excavation spoil, exhaust gas from different construction machinery and
transport vehicle.
85
During the construction period, dust emission has the greatest impact on ambient air.
From dust emission from excavation and bore drilling of the dry ground surface, some
of such dust emission will suspended in air, and other will flutter to the ground and
building surface nearby with wind; during stacking of the excavation soil, the dust
will fly if the wind force is greater; during handling and transport, it will cause some
of dust emission to fly and fall; the soil carried by rain washing will spread on the
road surface, after being dried, dust emission will be caused again by vehicle
movement or wind; during backfilling for excavation, it will also cause a great deal of
dust emission; during handling, transport and stacking of building materials, it will
also cause dust falling and flying.
Hazardness of dust emission pollution during construction shall not be neglected. If
the dust emission suspending in air is breathed in by the construction personnel and
the residents around, it will not only cause different respiratory diseases, the dust
emission can also carry a great deal of pathologenic bacteria, infect various diseases
and serious harm health of the construction personnel and residents around. In
addition, excessive dust emission can reduce the visibility and lead to traffic accident.
If the dust emission falls on buildings and trees, landscape will be affected. Therefore,
the Constructor shall strengthen management; take up proper measures and strictly
control dust emission caused during the construction period.
For the exhaust gas produced during construction machinery and heavy-duty vehicle
running, the key pollutants is carbon monoxide (CO), nitric oxide (NOX) and
hydrocarbon (HC).
For the road engineering of the project, all of roads take up bituminous concrete
pavement structure. During implementing works, it will set up bitumen mixing plant
and cement and concrete mixing plant, which will mainly produce the pollutants of
bitumen fume and TSP. Bitumen fume, is produced during decocting and mixing
produce of the bitumen. According to the bitumen fume pollution monitoring result
along the bitumen fume mixing plant at southern section of Beijing-Zhuhai express
highway, the source Intensity of mixing plants of different types is given in Table 6-1.
Table 6-1 Bitumen fume pollution monitoring result of bitumen mixing plant
No. Equipment model
Range of effluent
concentration of
bitumen fume
(mg/m3)
Mean value of
effluent
concentration of
bitumen fume
(mg/m3)
1 M3000 (Xi’an Road
Construction Machinery Plant) 12.5~15.5 15.2
86
2
VILLEROY&BOCH
(Germany) WKC100
12.0~16.8 13.9
3 M356, Parker Corporation
(UK) 13.4~17.0 14.2
Exhaust gas from the construction machinery and transport vehicle driven by fuel will
lead to increase of gross volume of the air pollutants in regional ambient air. During
the construction period, other vehicles will not be allowed to travel or it will reduce
the traffic of other vehicles in the existing road section, automobile exhaust gas
discharge amount during the construction period will be reduced compared with that
in current time and environmental impact of automobile exhaust gas on ambient air
during the construction period will be reduced compared with that in current time.
According to data analog, during pavement work, at about 60m under the wind,
dissipated phenol in hot bitumen material is ≤0.01mg/m3 (standard value (former
USSR) was 0.01mg/m3) and THC≤0.16mg/m
3 (standard value (former USSR) was
0.16mg/m3). That is to say, the affecting range of bitumen fume during paving
bitumen in pavement can reach 60m. Therefore, during bitumen paving work of the
project, the bitumen fume will have certain impact on residents and organizations at
one side of the surrounding roads. However, paving process is short-time and one-
disposable work and hot bitumen concrete temperature falls fast, thus impact is
temporary. When construction activities are over, fume emission will be also basically
stop.
6.1.2 Noise impact analysis during the construction period
(1) Noise source during the construction period
During construction period of the project, noise will mainly come from construction
machinery, such as road roller, loader, excavator, blender and so on; the noise also
include noise from construction and transport vehicle, building demolition and
crushing of the existing road and so on. When the machinery operate, the noise can
reach 90~112dB (A) at the place 5m away from the noise source. This emergency and
unstable noise will have adverse impact on the construction personnel and
surrounding residents. According to analog investigation and field data of ordinary
machinery, noise source intensity of different construction machinery and vehicles
during the construction period is given in Table 6-2 and 6-3.
Table 6-2 Noise source intensity of road construction machinery and vehicle
Construction
stage No.
Construction
equipment
Distance from the measuring
point to the construction
equipment (m)
Lmax (dB (A))
87
1 Hydraulic wheel
excavator 5 84
2 Bulldozer 5 84
3 Wheel loader 5 90
4 Different drilling
machines 5 87
5 Truck 5 94
Earthwork state
6 Pneumatic hammer 5 98
7 Different pile drivers 10 93~112
8 Grader 5 90 Piling stage
9 Air compressor 5 92
10 Vibrator 5 84
11 Concrete pump 5 85
12 Pneumatic wrench 5 95
13 Different road rollers 5 76~86
Structure stage
14 Spreading machine 5 87
15 Movable crane 5 96 Finishing stage
16 Elevator 72 15
Table 6-3 Tested value of concrete mixer
No Mixer model
Distance from the
measuring point to the
construction place
(m)
Maximum sound
level
Lmax[dB(A)]
1 parker LB1000(UK) 2 88
2 LB30 (Xi’an Road Construction
Machinery Plant) 2 90
3 LB2.5 (Xi’an Road Construction
Machinery Plant) 2 84
4 MARINI (Italia) 2 90
(2) Environmental impact analysis of construction noise
� If single set of construction machinery is utilized, it can reach the standard limit
value stipulated in the Noise Limits for Construction Site (GB12523-90) at 35m away
from the construction site in daytime and reach the standard limit value at 218m away
from the construction site at night. However, in actual construction process, many
types of machinery are utilized together; the range affected by noise will be larger.
� In the range where the project noise sensitive points have a mean distance about 5-
30m away from the construction site boundaries, the construction noise will have
fairly great impact on the surrounding acoustic environment. The acoustic
environment protection goal along the project mainly are within the range 30m away
from the redline, and thus the first row of residential building, school and hospital at
88
both sides of the road will be affected in daytime; at night, it will have especially
obvious impact on rest of the residents, thus it shall take up strict measures to reduce
impact of the construction noise on the environmental protection goals in maximum
degree.
� When the project is completed, impact of the construction noise will not exist.
Adverse impact of construction noise on environment is temporary and in short term.
6.1.3 Vibration impact analysis during the construction period
(1) Vibration source during construction period
During construction period of the project, vibration sources mainly include vibration
caused by power-type construction machinery. For vibration intensity of different
construction machinery, refer to Table 6-4.
Table 6-4 Vibration source intensity reference vibration level of construction
machinery
Distance from the measuring point to the construction equipment (m) Construction
equipment 5 10 20 30 40
Excavator 82~84 78~80 74~76 69~71 67~69
Bulldozer 83 79 74 69 67
Road roller 86 82 77 71 69
Truck 80~82 74~76 69~71 64~66 62~64
Air compressor 84~85 81 74~78 70~76 68~74
Drilling machine 63
(2) Environmental impact analysis of construction vibration
The construction machinery for the project are mainly utilized for vibration work,
including vibration caused by excavation and other work and vibration caused during
transport and handling by the transport vehicle. Thus, it will bring about impact on
traffic, building and people’s living along the road during the construction work.
The vibration level of ordinary construction and equipment can reach 63-85dB at the
place 10m away from the vibration source, and the vibration level can be less than or
close to 71dB at the place 30m away from the vibration source, and it can meet the
standard value at night at both sides of the main traffic artery stipulated in the
Standard on Vibration in Urban Area Environment (GB10070-88). It is predicted that
89
construction vibration will have impact on sensitive points within the range of 10-20m
around the work area.
According to the road construction characteristics, it will usually conduct road
maintenance and pavement work at night, the source intensity of vibration includes
spreading machine, vibrating spear, transport machinery and so on, and it will have
vibration impact on sensitive buildings within the range of 10-20m away from the
vibration source.
6.1.4 Water environmental impact analysis during the construction period
(1) Production waste water
Production waste water mainly includes sand and stone material washing waste water,
concrete mixing waste water and mechanical equipment washing waste water. The
sand and stone material washing waste water and mechanical equipment washing
waste water contain sediment, COD and a little of petroleum. After such treatment as
deposition, oil removal and so on, they can be recycled for use. A little of waste water
will be discharged into the municipal pipe network after passing the sedimentation
tank and will not have impact on the water environment basically.
(2) Surface runoff
During road construction, subgrade excavation, building demolition and so on will
bring about a great deal of sediment and dust emission. For construction in rainy
season, the sediment and dust will come to the nearby receiving water body together
with rain water and affect the water quality. The rain water will scour the construction
site and pollute the surrounding water body. Especially, construction in urban area
may block the urban drainage pipe network system and cause increase of suspended
matter concentration of the rain water drainage system.
(3) Domestic sewage of the construction personnel
During road construction, the living quarter the construction personnel are dispersed,
domestic sewage is little. In addition, the project area is basically the farmland. The
domestic sewage will be discharged after treatment in septic tank, and will have small
impact on environment.
According to investigation on construction waste water of municipal transport project,
discharge of construction waste water is given in Table 6-5.
Table 6-5 Analog and investigation result of construction waste water of municipal
transport project
90
Waste water Discharge amount Item COD Petroleum
matter SS
Domestic sewage 0.1-0.3(m3/d./person)
Pollutant concentration
(mg/L) 200~300 <5.0 80~120
Washing water discharge
from construction site 10(m3/d)
Pollutant concentration
(mg/L) 50~80 1.0~2.0 150~200
Equipment cooling water
discharge 4(m3/d)
Pollutant concentration
(mg/L) 10~20 0.5~1.0 10~15
6.1.5 Environmental impact analysis for solid waste during the construction period
During the construction period, there will be a great deal of residual mud, residual soil
(including residual soil from demolition of existing buildings), residual mud from
surface excavation, residual waste material in construction and so on. If these solid
wastes from buildings are not treated properly, it may impeded traffic and pollute
environment. During transport, if it does not focus on clean transport by the vehicle, it
may spread and fall soil along the road, pollute the street and road and affect urban
landscape and traffic.
For details of earthwork balancing, borrow pit and spoil ground of the project, refer to
section 2.5 and 2.6.
During stacking and transport of spoil soil, if treatment is not properly, it may impede
traffic and pollute environment. If the transport vehicles for excavation spoil oil travel
on the urban roads, it will not only increase the vehicle flow in the area along the road
and cause traffic jam, falling and leakage of soil can also bring about hazard against
urban sanitation. If the excavation spoil soil is stacked and dump without regulation,
water and soil loss will be caused with rainstorm scouring. On the construction site in
urban area, the rainwater runoff usually enters the municipal gullies in the form of
“yellow muddy water” and will block the gullies after deposition. In addition, muddy
water will also carry cement, oil stain and other pollutants from the construction site
into the water body and cause water body pollution.
In the project, it will reallocate house of 64064m2. according to the analog
investigation of relocation works in similar urban areas, after recovering most of
useful building materials (such as brick, reinforcement, timber and so on), the
91
building rubbish for each square meter of reallocation area will be about 0.1m3, and
thus the building rubbing from house reallocation will be 6406.4m3.
6.1.6 Ecologic environmental impact analysis during the construction period
(1) Impact on agricultural ecology and vegetation
The project area in Panggong District is basically farmland. Permanent land for the
project will damage some of farmland and vegetation, and the occupied land will lose
agricultural production function permanently and cause certain biomass loss. This
impact is not reversible, and will bring about certain adverse effect on agricultural
production in this area.
Temporary land occupation by some of temporary works and construction detour will
also lead to damage against of agricultural ecology and vegetation. However, it can be
recovered after the construction is completed and will have little impact on vegetation
and agricultural ecology in this area.
There are many street trees along the existing Panggong Road and Jianghua Road,
land expropriation will damage these trees and cause loss of urban greening area.
(2) Impact on animal
During the construction period, damage against ground surface vegetation, land
occupation and activities of construction personnel will have certain adverse impact
on animals within certain range, and such impact will basically disappear when the
construction is completed.
(3) The principal works of the project is within the urban area, topography is even,
there are less high-filling works and deep excavation, there will not be water and soil
loss basically. However, during construction, it will bring about certain impact on
urban ecology during temporary storage of earthwork, rockwork, sand and stone
materials, cement, clay and other building materials, spoil and waste materials.
Especially, if the spoil soil is not under proper stacking and protection and is scoured
92
by rainwater, it is easy to block the road drainage pipe and affect traffic and urban
landscape. It shall conduct timely ecological recovery after the borrow pit and spoil
ground are filled and leveled up, such as planting trees and grass. After conducting
timely ecological recovery, soil borrow and spoil of the project will have small impact
on ecological environment.
(4) During the construction period, when earthwork, rockwork, sand and stone
materials, cement and other building materials are transported by vehicle and the
protection measures are not proper, it will bring about a great deal of dust emission,
and it will have impact of dust emission on road surface, greening belt and residents at
the both sides of the road where the vehicle travel, and it will also bring about certain
impact on urban sanitation environment.
6.1.7 Social environmental impact during the construction period
6.1.7.1 Analysis of impact on urban traffic
(1) Road construction will disturb the existing traffic. During project construction, it
shall make construction while not interrupt the existing traffic and transport in order
to complete road network construction and planning smoothly. However, during the
construction period, there will be traffic congestion and jam during peak hours in
some road sections. The traffic control department shall make management for these
conditions, organize traffic with adjacent road network and shunt traffic load and
guarantee not to disturb normal living of the residents.
(2) During project construction period, it will utilize a great deal of construction
machinery and transport vehicle, which will increase the traffic flow in the area along
the road and have certain disturbance against the urban traffic.
6.1.7.2 Analysis of impact on urban resident living
(1) According to analysis of impact of the project on urban traffic, it shows that it
may disturb the urban traffic during project construction period, cause traffic jam and
congestion of urban road, it shall take up such temporary measures as shunting and
93
going-around and so on. The bus route shall be arranged again. All of these will bring
about impact and inconvenience against travel, work and living of urban residents.
(2) During project construction period, noise from the construction machinery and
dust emission from the transport vehicle will have certain impact on normal living of
the residents at the sensitive points near the road. If the engineering technology
requires night work, it will have impact on rest of the residents.
6.1.7.3 Impact on infrastructure
During project construction, it will affect different ground and underground pipeline
and pipes of municipal works, such as water supply pipe, fuel gas pipe, heat supply
pipe, communication and power pipeline and so on, it will bring about certain impact
and inconvenience against normal living of the residents. The project is mainly within
the city suburb area, it will be slightly affected by demolition of electric power,
communication, pipe and so on. The ordinary infrastructure along the road is
agricultural irrigation trench. Project construction will interrupt some trench and
disturb the agricultural irrigation and drainage system. However, impact is temporary.
With building up of the road, drainage system and irrigation trenches at both sides
will be interlinked; it can effectively improve the drainage and agricultural irrigation
system and make better use of them.
6.2 Analysis of environmental impact during operation period
6.2.1 Analysis of impact on ambient air quality during the operation period
6.2.1.1 Pollution source for atmospheric environment during the operation period
After the project is built up, there is no spray painting work in the bus maintenance
yard, and thus automobile exhaust gas will be the main source for ambient air
pollutant. The discharge amount of the pollutants is proportional to the traffic volume,
and is related to the vehicle type and automobile operating conditions. Automobile
exhaust gas pollutants mainly are caused by exhaust of air leakage of crankcase,
volatization of fuel system and exhaust pipe, the pollutants mainly include carbon
94
monoxide, nitrogen oxide and non-methane total hydrocarbon. Daily average
discharge amount of each pollutant can be calculated based on the following formula:
Where,
QJ-- J pollutant source intensity discharged by the running automobile at
certain speed, mg/(m·s);
Ai-- hourly traffic volume of vehicle type i, vehicle/h;
B - Correction factor for converting NOX discharge amount into c NO2
discharge amount;
Eij- discharge factor of single vehicle, namely, J pollutant amount discharged
by vehicle type I at certain speed, mg/vehicle·m, (refer to Table 6-6).
Table 6-6 Suggested value for discharge factor for single vehicle Unit:
mg/(vehicle·m)
Mean vehicle speed 50.00 60.00 70.00 80.00 90.00 100.00
CO 31.34 23.66 17.90 14.76 10.24 7.72
THC 8.14 6.70 6.06 5.30 4.66 4.02 Small
vehicle
NOx 1.77 2.37 2.96 3.71 3.85 3.99
CO 30.18 26.19 24.76 25.47 28.55 34.78
THC 15.21 12.42 11.02 10.10 9.42 9.10 Medium
vehicle
NOx 5.40 6.30 7.20 8.30 8.80 9.30
CO 5.52 4.48 4.10 4.01 4.23 4.77
THC 2.08 1.79 1.58 1.45 1.38 1.35 Large
vehicle
NOx 10.44 10.48 11.10 14.71 15.64 18.38
6.2.1.2 Prediction assessment content
ADMS mode recommended in the Guidelines for Environmental Impact Assessment-
atmosphere environment (HT2.2-2008) was used for predicting impact of automobile
exhaust gas on ambient air during the project operation period. The maintenance work
of newly built bus yard in this project will not include spray painting work.
(1) Prediction content
∑=
−=3
1
13600i
ijiJ EBAQ
95
According to the project pollutant characteristics and requirement of the atmosphere
guidelines and in consideration of the pollution climatic feature of this area, it
conducted prediction of atmosphere environmental impact by the day by day and hour
and hour way. The prediction and analysis and assessment content are given as
follows:
� Under typical hourly climatic conditions of the area, it analyzed impact of the
project on the regional environment, analyzed whether it exceeds the limit value or
not, the limit-exceeding degree and maximum limit-exceeding position; analyzed
whether the sensitive point exceeds the limit or not and the limit-exceeding degree,
analyzed the hour concentration limit-exceeding probability and maximum duration.
� Under typical daily climatic conditions of the area, it analyzed impact of the project
on the regional environment, analyzed whether it exceeds the limit value or not, the
limit-exceeding degree and maximum limit-exceeding position; analyzed whether the
sensitive point exceeds the limit or not and the limit-exceeding degree, analyzed the
hour concentration limit-exceeding probability and maximum duration.
� Under long-term climatic conditions of the area, it analyzed impact of the project
on the regional environment, analyzed whether it exceeds the limit value or not, the
limit-exceeding degree and maximum limit-exceeding position; analyzed whether the
sensitive point exceeds the limit or not and the limit-exceeding degree.
(2) Prediction factor
The factors for motor vehicle exhaust main pollutant discharge factors were CO and
NO2.
(3) Prediction time of period
Prediction time of period is the year of 2015.
6.2.1.3 Prediction result
(1) Under typical hourly climatic conditions, impact of pollutants on the area and
environment goal
●Maximum hourly concentration of NO2 at each of sensitive goal
According to prediction, NO2 hourly concentration over-limit rates at the sensitive
points at Panggong Park, Panggongci Village Group 5, Siji dormitory of Jinyu
Company, Sanjiayuan Group 3, teacher dormitory of Wangjiawa primary school,
96
Shijiamiao Village Group 1, Sunjiaxiang Village Group 1 and 3 were 0.21%, 0.05%,
0.03%, 0.05%, 0.15%, 0.06% and 0.04% respectively; the maximum hourly
concentration at other 55 sensitive points could meet the class II standard limit value
in the Ambient Air Quality Standard (GB3095-1996).
●Maximum hourly concentration of CO at each sensitive goal
According to prediction, the maximum hourly concentration of CO at each sensitive
point can meet class II standard limit value in the Ambient Air Quality Standard
(GB3095-1996).
(2) Under typical daily climatic conditions, impact of pollutants on the area and
environment goal
●Maximum average daily concentration of NO2 at each of sensitive goal
According to prediction, average daily values at such seven sensitive points as
Panggong Park, Panggongci Village Group 5, Siji dormitory of Jinyu Company,
Sanjiayuan Village Group 3, teacher dormitory of Wangjiawa primary school,
Shijiamiao Village Group 1, Sunjiaxiang Village Group 1 and 3 exceeded the limit
value in different degrees; the maximum average daily concentration at other 55
sensitive points could meet the class II standard limit value in the Ambient Air
Quality Standard (GB3095-1996).
●Maximum hourly concentration of CO at each sensitive goal
According to prediction, the maximum hourly concentration of CO at each sensitive
point can meet class II standard limit value in the Ambient Air Quality Standard
(GB3095-1996)
(3) Under long term climatic conditions, impact of pollutants on the area and
environment goal
According to prediction, average daily values at such four sensitive points as
Sanjiayuan Village Group 3, teacher dormitory of Wangjiawa primary school,
Shijiamiao Village Group 1, Sunjiaxiang Village Group 1 and 3 exceeded the limit
value in different degrees; the maximum average daily concentration at other 58
sensitive points could meet the class II standard limit value in the Ambient Air
Quality Standard (GB3095-1996).
According to the results for predicting impact of road pollutants on the area and
sensitive goals under typical hourly, typical daily and average annual climatic
conditions, the pollutants mainly concentrate within the road red line range. There are
97
seven sensitive points close to the road, such as Panggong Park, Panggongci Village
Group 5, Siji dormitory of Jinyu Company, Sanjiayuan Village Group 3, teacher
dormitory of Wangjiawa primary school, No.1 team of Shijiamiao Village,
Sunjiaxiang Village Group 1 and 3 and so on.
With automobile industry development, discharge amount of automobile exhaust gas
pollutant will be reduced continuously (for example, Euro III standard or stricter
standard will be executed). It is predicted that the actual concentration value of each
sensitive point in 2020 will be lower than the prediction value in this assessment.
6.2.2 Analysis of noise impact during the operation period
6.2.2.1 Prediction method
For the environmental impact assessment, it took up the acoustic environment noise
prediction mode in the Environmental Impact Assessment-acoustic environment
(HT2.4-2009) for calculating the road traffic noise.
6.2.2.2 Prediction mode
(1) Calculation mode for acoustic noise level
+= backgroundtraffic AeqAeq
Aeq
LLL
1.01.0
tenvironmen1010lg10
Where, Leq environment─environmental noise value at the prediction point, dB (A);
Leq traffic─road traffic noise value at the prediction point, dB (A);
Leq background─background noise value at the prediction point dB (A);
(2) Calculation mode for road traffic noise level
16)/)lg((10)/5.7lg(10lg10 21 −∆+Ψ+Ψ+++= LrTV
NLiL
i
ioiAeq π
[ ]SL AeqAeqMAeqAeqtraffic
LLLL
1.01.01.0101010lg10 ++=
Where, iLAeq — i-vehicle type, generally for S, M and L, hourly
equivalent sound level of the vehicle, dB;
AeqtrafficL —Equivalent sound level of road traffic noise, dB;
oiL —Average radiated noise level of the vehicle at the reference point
(7.5m away from the vehicle), dB;
iN —hourly flow rate of such vehicle type, vehicle/hr;
T —Time for calculating the equivalent sound level, T=1h;
98
iV —Average running speed of vehicle of such type, km/h;
r—Distance from the lane center line to the prediction point, m;
1Ψ , 2Ψ —Field angle and radian from the prediction point to the both
ends of the road section;
L∆ ─Correction caused by other factors (dB (A)) can be calculated
based on the following formula:
321 LLLL ∆+∆−∆=∆
pavementgradient LLL ∆+∆=∆ 1
miscbargratm2 AAAAL +++=∆
1L∆ —Correction caused by road factor, dB (A);
gradientL∆ —Correction caused by longitudinal gradient dB (A);
pavementL∆ —Correction caused by road pavement material, dB (A);
2L∆ —Attenuation value caused by sound wave diffusion, dB (A);
3L∆ —Correction caused by emission and so on, dB (A);
atmA —Correction caused by atmospheric absorption, dB (A);
grA —Correction caused by ground effect, dB (A);
barA —Attenuation caused by barrier, dB (A);
miscA —Correction caused by other effects, dB (A).
6.2.2.3 Method for determining the parameters in the road traffic noise prediction
mode
(1) Vehicle type classification
The vehicle types include small, medium and large. For classification criteria, refer to
Table 6-7. The vehicle type can be determined based on the traffic volume
investigation results provided in the feasibility study report.
99
Table 6-7 Criteria for vehicle classification
Vehicle type Gross mass of vehicle
Small vehicle (s) Below 3.5t
Medium vehicle (M) Above3.5t~12t
Large vehicle (L) Above 12t
Note: Small vehicles generally include buggy, sedan, touring car (below 7 seats (included) ) and so on;
Large vehicles generally include container vehicle, towed vehicle, engineering vehicle, coach (above
40 seats), and large cargo truck and so on;
Medium vehicles generally include medium truck, medium coach (7-40 seats), agricultural three-wheel
vehicle, four-wheel vehicle and so on.
(2) radiated noise level of single vehicle-Loi
� The average radiated noise level of type I vehicle at the reference point (7.5m)-Loi
S type vehicle Los =12.6+34.73lgVS+�Lroad
M type vehicle LoM =8.8+40.48lgVM+�Llongitudinal gradient
L type vehicle LoL =22.0+36.32lgVL+�Llongitudinal gradient
Where, S, M and L represent small, medium and large types vehicle;
Vi-- average running speed of vehicle of such type, km/h.
� Correction of source intensity
Correction of traffic noise source intensity ( gradientL∆ ) caused by road longitudinal
gradient can take the values given in Table 6-8.
Table 6-8 Correction value of road longitudinal gradient noise level
Longitudinal gradient (%) Correction value of noise level (dB(A))
Small vehicle gradientL∆ =50*β
Medium vehicle gradientL∆ =73*β
Large vehicle gradientL∆ =98*β
β Road longitudinal gradient, %
Correction of traffic noise source intensity (�L) caused by road pavement can take
the values given in Table 6-9.
Table 6-9 Correction value for ordinary pavement Unit: dB (A)
Correction for different travelling speeds
km/h Pavement type
30 40 >=50
100
Bituminous concrete pavement 0 0 0
Cement concrete pavement 1.0 1.5 2.0
(3) Ground calculation for ground absorption sound attenuation-�L
3.1)
1005.8(
8.4
+−
×−∆ rr
h
pavement
m
eL
Where, hm represents sound source, average height from the tie-line of receiving
(prediction) points to the ground, m;
r represents the distance from the equivalent lane center lie to the
receiving point, m.
(4) Calculation for the correction caused by traffic noise (�L1) in road bends section
or section of limited-length:
∆ o180
lg101 θL
Where, θ─included angle from the prediction point to the visual line of ends of
the road (º).
(5) Calculation for the sound attenuation caused by barrier
�LBarrier =�Lhouse+�LSound shadow zone
�Lhouse represents the barrier attenuation of the building. If the buildings are dispersed, their estimated noise additional attenuation value can take values given in Table 6-10.
Table 6-10 Estimate value for building noise attenuation
Building condition
S/S0 Attenuation ∆L
Floor area of the first row of house occupy :
40~60% -3 dB (A)
Floor area of the first row of house occupy :
70~90% -5 dB (A)
Increase by one row of house -1.5 dB (A)
Maximum absolute attenuation ≤10dB (A)
Note: It is only applicable to buildings at road side of flat embankment.
�LSound shadow zone represents attenuation of diffracted noise caused within sound
shadow zone at both sides of embankment (bridge) or cutting.
When the prediction is located at the noise shining area, �Lsound shadow zone=0
When the prediction point is at sound shadow zone, �Lsound shadow zone will mainly be
determined by the acoustic path difference (δ)
101
For calculating the attenuation of diffracted sound, it took up the Fresnel number Nmx
, which is defined as follows:
λδ2
max =N
Where, Nmx―――Fresnel number;
λ---Wave length of sound, m;
δ---Acoustic path difference, m;
The calculation mode for line source diffracted sound attenuation is given as
follows:
>−+×
−×××−
≤
+−
×
−×××−
=∆−
)1()))1(ln(2
)1(3lg(10
)1()
)1(
)1(tan4
)1(3lg(10
L
2
2
1
2
zone shadow sound
giventtt
t
givent
t
t
t
π
π
Where, t=20×Nmx/3
6.2.2.4 Prediction technical conditions
(1) Prediction period
According to the feasibility study report of the project and relevant vehicle flow rate
prediction, the prediction period for the traffic of the project is 2015 in near term and
2020 in long term. Thus, the noise prediction time in this environmental impact
assessment is 2015 in near term and 2020 in long term.
(2) Designed running speed and maximum longitudinal gradient
According to the feasibility study report of the project, the designed running speed
and maximum longitudinal gradient are given in Table 6-11.
Table 6-11 Designed travel speed and maximum longitudinal gradient
Road name
Southeast section of
the Inner Ring
Road
Xingguang
Avenue
Panggong Road, Jianghua
Road, Xiangyang Road,
Zhakou 2nd
Road, 13 # Road under
planning
Designed speed (km/h) 60 50 40
Designed maximum
longitudinal gradient
(%)
5 6 6
102
(3) Pavement and station yard subgrade engineering
The road pavement to be built is modified bituminous concrete pavement, and the
station yard subgrade pavement is the cement concrete pavement.
6.2.2.5 Environmental noise prediction result and assessment
(1) Environmental noise prediction result at sensitive point
�After the project is put into operation, in near term (2015), the environmental noise
along the road will be 49.6-65.8dB in day time and will be 43.6-59.8dB at night.
There are 15 sensitive points that can meet the standard value, such as No.23 middle
school of Xiangyang, living quarter of Meihua Company, Shijiamiao primary school,
Panggongci Village Group 1 and so on, and they accounted for 26.3% of the sensitive
points. The other 42 sensitive points exceeded the limit, and they exceeded the limit
by 0.4-1.1dB at daytime and night.
In long term (2020), the environmental noise along the road will be 51.0-67.2 dB in
day time and will be 45.0-61.2dB dB at night. There are 11 sensitive points that can
meet the standard value, such as living quarter of Meihua Company, Sujiayuan
community, Shijiamiao primary school, Hongmiao Village Group 5 and so on, and
they accounted for 19.3% of the sensitive points. The other 46 sensitive points
exceeded the limit, and they exceeded the limit by 0.3-4.5dB and 0.1-8.7dB
respectively at daytime and night.
� Increase of noise prediction value of each road section compared with existing
conditions
Compared with the existing conditions, the near-term noise prediction noise values
increased by 0.2-15.2dB and 0.1-15.3dB at daytime and night respectively; Compared
with the existing conditions, the long-term noise prediction noise values increased by
0.2-14.8dB and 0.1-15.6dB at daytime and night respectively; Out of them, the
existing Panggong Road is the traffic main artery of Xiangyang, the existing noise is
fairly greater that is mainly caused by main vehicles (medium transport vehicle, farm
truck and motorcycle and so on) frequently whistle, thus the noise environment
quality is not very good; compared with the existing conditions, the predicted value of
noise the Panggong Road will have a smaller increase. Out of them, noise of sensitive
points at ends of the Panggong Road (such as Yiheyuan residence, the yard of
Xiangyang Municipal State Tax Bureau, living quarter of Oil Grease Company,
Panggong Home Residence, Taixin Garden Residence and so on) at day time will
become smaller, which is mainly caused by that the running vehicle structure and
ration change (small vehicles increase) after the project is built up. In addition, the
103
farm product market at the crossing of Panggong Road and Zhakou 2nd
Road will be
removed, and the prediction value is better than that in current time; for other road
sections, the acoustic environment quality is fairly good before project construction,
noise value will increase in a great degree after the project. The traffic noise of the
project is mainly contribution factor.
(2) Noise prediction and analysis for the bus lane
The project will provide bus lane in the Changhong Road. The designed full length is
about 2.5km. The design scope starts from Chunyuan Road in north, passes Jianhua
Road, Liye Road, Renmin Road and Jianshe Road, reaches West Daqing Road in
south. The full line is in double line and 2 lanes. After the project is executed, the road
red line width will not change, vehicle flow rate will not change significantly
compared with existing conditions, and speed of bus will be improved greatly.
However, with the smooth road, traffic noise will be reduced compared with the under
the idle speed travel. In addition, with continuous improvement of bus service, it will
attract more and more citizens to select taking bus for travel, thus it reduces the traffic
volume of private cars and taxi and reduces the quantity of pollution source. In
summary, environmental noise at both sides of the road will maintain the existing
conditions basically.
(3) Noise prediction and analysis for the bus yard
The project will build the new Xianshan parking and maintenance yard and parking
and maintenance yard in Shenzhen industrial park in Xiangzhou District, alter the bus
terminal station in railway station. According to investigation of existing conditions,
there are no acoustic environment sensitive points within the range of 60m away from
the bus terminal station in railway station, Xianshan parking and maintenance yard
and parking and maintenance yard in Shenzhen industrial park in Xiangzhou District.
For the existing monitored values of Xianshan parking and maintenance yard to be
built, the noise value at day time is 53.0dB and 46.8dB at night. According to analog
monitoring for the existing conditions of Xianshan parking and maintenance yard, it
shows that the noise when the vehicle is under idle speed travelling state is 75-78dB;
for peak hour, one bus will be dispatched every 2-3min, and average is 3-4min/bus.
After sound insulation and distance geometrical attenuation, the existing value at the
place 1m away from the southern boundary is 56.4dB at day time and 49.7dB at night.
Compared with class II standard requirements in the Emission Standard for Industrial
Enterprises Noise at Boundary, the environment noise at day time and night at
boundary can reach the standard value.
104
For the existing monitored values of maintenance yard in Shenzhen industrial park in
Xiangzhou District to be built, the noise value at day time is 51.5dB and 44.6dB at
night. For peak hour, one bus will be dispatched every 2-3min, and average is 3-
4min/bus. After sound insulation and distance geometrical attenuation, the existing
value at the place 1m away from the southern boundary is 56.6dB at day time and
49.7dB at night. Compared with class II standard requirements in the Emission
Standard for Industrial Enterprises Noise at Boundary, the environment noise at day
time and night at boundary can reach the standard value.
Bus terminal station in railway station is opposite to the Xiangyang railway station,
and it is one open-type bus terminal station. Affected by noise of the project itself,
traffic noise from Zhongyuan Road and Qianjin Road and social living noise, the
existing monitored noise value is 65.5dB at day time and 55.3dB at night. The day
time noise can meet the class IV standard requirement of the Noise Emission Standard
for Acoustic Environment and the noise value at night exceeds by 0.3dB. The reason
for limit exceeding at night is mainly caused by traffic noise from Zhongyuan Road
and Qianjin Road. It will upgrade the bus terminal station in the project, after the bus
terminal station is built up, the noise will maintain the existing conditions basically.
(4) Protection distance analysis
With calculation, protection distance for each road was obtained and given in Table 6-
12.
Table 6-12 Protection distance for each road
Standard limit distance (distance away from the road red line/m)
Road name Day time (70dB) Nighttime (55dB) Day time (60dB)
Nighttime
(50dB)
Panggong Road / 10 16 24
Jianghua Road / 7 10 30
Inner Ring Road / 27 33 80
Xiangyang Road / 7 6 24
Zhakou 2nd
Road / 12 14 40
Xingguang Avenue / 18 36 69
13 # Road / 5 / 15
Note: The result is obtained based on recent data.
6.2.3 Analysis of vibration impact during the operation period
6.2.3.1 Prediction method
105
The vibration during the operation period of the project is mainly caused by road
vibration during vehicle travelling. Its impact is long term. To assess its
environmental impact, this prediction and assessment referred to the mature
experiences of such environmental impact assessment projects as the Urban Traffic
Construction Project in Shijiazhuang with Loan from the World Bank, Environmental
Impact Assessment for Shanghai Yangpu Bridge and so on that have passed review by
the World Bank and domestic environmental impact review, selected prediction mode
of Japanese Construction Ministry for calculation. With analog investigation and
monitoring, the rules for vibration source and attenuation were obtained to determine
the relevant parameters for prediction and verify the prediction result.
� Prediction mode for traffic vibration
Where,
VLz10 traffic——Accumulated 10% Z vibration grade of traffic vibration,
dB;
Alg (lgQ*) +b+20——Predicted basic value, dB;
Q*——Equivalent traffic volume (vehicle/500s/lane);
αz——Corrected value of pavement evenness dB;
αf——Corrected value of pavement dominant frequency, dB;
αl——Corrected value of range attenuation, dB.
� Prediction mode for environment vibration
Where,
VLZ10 total——Environment vibration value at the prediction point, dB;
VLZ10 background——the background vibration value without traffic
vibration of the project at the prediction point, dB.
� Prediction parameter
1) Equivalent traffic volume
Equivalent traffic volume Q* refers to flow rate of each lane every 500s, and can be
calculated based on the formula
Where, Q1——Small vehicle flow rate (vehicle/hour; )
lfztrafficz bQaVL ααα +++++= 20)lg(lg *
10Formula (8-1)
( )21
* 21
3600
500QQ
MQ +×=
Formula (8-3)
Formula (8-2) [ ]backgroundZtrafficZ VLVL
totalZVL 1010 1.01.0
10 1010lg10 +=
106
Q2——Large vehicle flow rate (vehicle/hour; )
M——Total lane number in up and down travel
2) Determination of coefficients a and b
With reference to relevant data at home and abroad and engineering design data, the
coefficients are selected as follows:
a=58.3, b=29.7
3) Correction of pavement evenness
Corrected value of pavement αz can be calculated based on the following formula:
Where, z——Pavement evenness, z=4mm
4) Corrected value of pavement vibration dominant frequency
Corrected value of pavement vibration dominant frequency αf can be calculated
based on the following formula:
Where, f——Pavement dominant frequency when large vehicle passes, f=15Hz.
5) Corrected value of range attenuation
Corrected value of range attenuation αl can be calculated based on the following
formula:
Where, l——Distance from the prediction point to effective vibration source,
m
β——Multiple range attenuation value, β=4dB
( )2.24 −×= zzα Formula (8-4)
( ) 5.58/lg20 +−= ffαFormula (8-5)
�8<f<90�
( )βα 8.1lg3.3 +−= ll Formula (8-6)
107
6.2.3.2 Assessment for vibration environment prediction
With the above prediction method, the traffic vibration at the red line of the road
VLz10 is 62.2-70.9dB at day time and 61.6-67.8dB at night. Thus, it reckons that the
traffic vibration will be less than 71dB in assessed areas at both sides of the road after
the project is put into operation, it can meet the standard requirements at both sides of
traffic artery stipulated in GB10070-88. after the project is built, road traffic vibration
will not have obvious impact on surrounding environment.
6.2.4 Analysis for water environmental impact during the operation period
The waste water produced during the operation period of the project mainly includes
domestic sewage of the workers in the newly built bus maintenance yard, vehicle
washing and overhaul waste water. In addition, road rainwater will also produce some
amount of waste water.
6.2.3.1 Analysis for water environmental impact in the bus maintenance yard
(1) Waste water source
The waste water during the operation period of the bus maintenance yard mainly
consists of two sources: the first is oily waste water for vehicle overhaul and vehicle
washing waste water; the second is office and domestic sewage of the workers, such
as bathroom bathing water, wash water from canteen, drainage for keeping sanitation
and toilet flushing water.
(2) Waste water quality and discharge amount
The oily waste water from vehicle overhaul mainly contain such pollutants as COD,
BOD5, petroleum and so on; waste water from vehicle washing mainly contains such
pollutants as COD, BOD5, petroleum, LAS and so on; domestic sewage mainly
contains such pollutants as COD, BOD5, animal and vegetable oil, ammonia nitrogen
and so on. According analog with similar projects, the prediction of discharged
sewage quality is given in Table 6-13.
Table 6-13 Prediction of sewage quality discharged in operation period
Sewage source Prediction of sewage quality
pH COD(mg/L) BOD5(mg/L) Petroleum
(mg/L) Oily sewage from
vehicle overhaul
7.8 425 127 40
pH COD(mg/L) BOD5(mg/L) Petroleum
(mg/L) LAS(mg/L) Waste water from
vehicle washing
8.1 300 30 23.1 16.8
pH COD(mg/L) BOD5(mg/L)
Animal and
vegetable oil
(mg/L)
Ammonia
nitrogen
(mg/L) Domestic sewage
7.5~8.0 150~200 50~90 5~10 23
108
According to the design document, the discharge amount of waste water from the bus
maintenance yard and parking lot is given in Table 6-14.
Table 6-14 Discharge sewage amount in operation period
Oily sewage from
vehicle overhaul
(m3/d)
Waste water from
vehicle washing
(m3/d)
Domestic
sewage
(m3/d)
Total
(m3/d)
Xiangzhou
maintenance yard 12 58.5 3 73.5
Xianshan
maintenance yard 13 65.5 3 81.5
Total 25 124 6 155
(3) Waste water discharge destination and discharge standard
According to field investigation and urban sewage treatment plant planning in
Xiangyang City, the surrounding positions of the newly built maintenance yard have
connect to the urban sewage pipe network. The sewage produced in the operation
period can enter the urban sewage treatment plant via the sewage pipe network. The
sewage from the Xianshan maintenance yard will finally enter the Guanyinge sewage
treatment plant, and the sewage from the Xiangzhou maintenance yard will enter the
Yuliangzhou sewage treatment plant. The sewage discharge during the operation
period shall comply with the class III standard stipulated in the Sewage
Comprehensive Discharge Standard (GB8978-1996).
(4) Waste water treatment process and expected result
For oily waste water from vehicle overhaul and waste water from vehicle washing, it
will make treatment with oil separation tank; for domestic sewage, it will make
treatment with septic tank. For sewage quality after treatment, refer to Table 6-15.
Table 6-15 Water quality of the waste water after treatment
Water quality of the waste water after treatment (mg/L)
Treatment
technique pH
value BOD5 COD SS Petroleum
Animal
and
vegetable
oil
LAS Ammonia
nitrogen
Oily sewage from
vehicle overhaul
Oil separation
tank
Waste water from
vehicle washing
Oil separation
tank
7.67 / 50 / 10 / 0.5 /
Domestic sewage Septic tank 7.5~8.0 70 180 80 / 8 / 17.5
109
According to Table 6-15, it shows that sewage quality after treatment can meet class
III standard stipulated in the Sewage Comprehensive Discharge Standard (GB8978-
1996). In project design, it has made treatment for domestic sewage with septic tank
and has made treatment with oil separation tank for oily waste water from vehicle
overhaul and waste water from vehicle washing.
(5) Statistics of water pollutant discharge quantity
For water pollutant discharge quantity after the project is put into operation, refer to
Table 6-16.
Table 6-16 Statistic table of water pollutant discharge amount during the operation
period
Blowdown
unit Item
Sewage
amount
(m3/a)
BOD5
(t/a)
CODcr
(t/a)
SS
(t/a)
Petroleum
(t/a)
Animal
and
vegetable
oil
(t/a)
LAS
(t/a)
Ammonia
nitrogen
(t/a)
Production
sewage 25732.5 0 1.287 0 0.257 0 0.013 0 Xiangzhou
maintenance
yard Domestic
sewage 1095 0.077 0.197 0.088 0 0.009 0 0.019
Production
sewage 28652.5 0 1.433 0 0.287 0 0.014 0 Xianshan
maintenance
yard Domestic
sewage 1095 0.077 0.197 0.088 0 0.009 0 0.019
Total
Sewage
discharge
amount 56575 0.154 3.114 0.176 0.544 0.018 0.027 0.038
(6) Analysis for water environmental impact during the operation period
During the project operation period, the gross discharge amount of sewage from the
newly built bus maintenance yard will be 155m3/d. The discharged sewage mainly
includes oily waste water from vehicle overhaul and waste water from vehicle
washing, domestic sewage of the workers. Quality is simple. After being treated, the
sewage will finally enter the urban sewage treatment via the urban sewage pipe
network and will not have impact on the surrounding surface water.
6.2.3.2 Analysis for water environmental impact during the operation period of the
road
After the road work of the project is built up, the waste water during the operation
period is mainly rain water. The main pollution factors of rain water are SS and COD.
The pollutant concentration of the road surface rainwater will undergo the process
from large to small. The pollutant concentration will reach the peak during 0-15 min.
110
After that time, the concentration will reduce and become stable after raining for one
hour.
Pollutant concentration in rain water is fairly lower, it only has impact during raining
period and the urban drainage system along the roads in the project will also be
improved with the project construction, and thus road rain water will not have obvious
impact on the water environment along the roads after the project is built up.
6.2.3.3 Investment estimate for sewage treatment measure
In project design, it has provided drainage design for the newly built maintenance
yard, made treatment for the domestic sewage with the septic tank and made treatment
for the oily waste water from vehicle overhaul and waste water from vehicle washing
with oil separation tank. For the quantity of main facilities and investment, refer to
Table 6-17.
Table 6-17 Quantity table for the project sewage treatment design
Project name Quantity (set) Investment
(RMB10000)
Septic tank 4 0.6 Xianshan
maintenance yard Oil separation tank 4 8
Septic tank 3 0.45 Xiangzhou
maintenance yard Oil separation tank 3 6
Total 14 15.05
6.2.5 Analysis of solid waste impact during the operation period
The solid wastes produced in the project mainly include domestic garbage, sludge
from sewage treatment, oil sludge and replaced parts from vehicle repair. The vehicle
repair wastes included dismounted aged machine parts and so on, which will be
collectively collected and recovered periodically; the waste engine oil, battery
electrolyte, accumulator, produced in repair, sludge produced from waste water
cycling system equipment and waste gloves produced in vehicle repair are hazardous
solid wastes, which shall be collectively sent to the hazardous waste disposal center
who has qualification for disposal.
During the operation period of the project, the garbage quantity produced in daily life
of the workers of the newly built maintenance yard can be calculated based on the
newly increased worker quantity. It can be calculated based on 0.5kg of domestic
garbage discharged by each person every day. The newly built maintenance yard will
newly increase 60 workers. This, it is predicted that the discharge quantity of
111
domestic garbage of the newly built maintenance yard will be 11t/a. During the
operation period, besides the domestic garbage produced by the workers, the
passengers in the bus yard will also carry some quantity of garbage. After the project
is put into operation, only if it can set up garbage stacking point within the newly
maintenance yard, and contact the sanitation department in the project area to
transport the garbage periodically and send the garbage to the appointed place for
disposal, and the domestic garbage produced during the project operation period will
not have impact on the environment.
6.2.6 Analysis for impact on ecology and landscape during the operation period
6.2.6.1 Impact on greening during the operation period
After the roads are built up, greening along the roads will compensate some of
biomass loss. The roads of the project will not be enclosed, and thus the biological
system along the roads will maintain the original state basically. It will plant trees and
grass manually at both sides of the roads. These newly plant trees and grass will co-
inhibit and co-grow with the local dominant trees and grass, and will also become the
place for small and micro animals and birds to inhabit, multiply and overwinter. Road
greening work will not increase landscape and beautify the environment, but also can
protect the agricultural ecology environment and compensate the vegetation loss
caused by the project land occupation in some degree, and also can increase the
diversity of the plant in the area.
However, if it plants special and foreign species in road greening, these species can
adapt to and disturb the local environment, may lead to reduction of species growing
in local place and gradual degradation of trees. It may form the invasion access of
foreign species in the bare area along the roads, and gradually become the dominant
cluster in some place, exclude the local and native vegetation. Thus, the tree species
for greening shall be the ordinary trees in local place.
6.2.6.2 Impact of automobile exhaust gas emission on agricultural crop growth during the
operation period
In the assessed area, there is much farmland. After the roads are built up, the vehicle quantity
passing the road will increase significantly, and the emission quantity of exhaust gas will increase
greatly. According to relevant data, the effluent from the vehicle is the main source for small
particles. For different gases and solid pollutants in air, gas will mainly have relationship with
agricultural crops. Gas and pollutant substance whose diameter is generally less than 1Lm will be
absorbed by the air pore in the agricultural crops leave surface and reach the vessel via the
intercellular space, and then be transferred to other parts. Thus, vehicle exhaust gas during the
112
operation period of the road will have some impact on the agricultural crops along the roads.
However, there are greening belts at the both sides of the roads, the green belts can effectively
absorb automobile exhaust gas, reduce impact of automobile exhaust gas on the agricultural crops
and can purify the air.
6.2.6.3 Impact on urban landscape during the operation period
After the project is built up, it will improve greening ratio and make reasonable configuration for
the newly built roads, it can achieve such comprehensive environment benefits as protecting
pavement, reducing water and soil loss, reducing traffic dust and traffic noise, regulating and
improving road micro-climate and so on, further improve the landscape environment along the
roads and beautify the road landscape. In summary, it will have positive benefit for the urban
ecological landscape after the project is built up, and it will make people to feel happy. To be
specific, it is represented in the following aspects:
(1) The urban landscape comes from the people’s feeling toward activities along the roads. The
project mainly includes urban trunk roads. Quality of road greening has very great impact on
urban landscape and urban appearance. In addition, most of new building and alteration works of
the roads will be made in the built-up urban area, there are many buildings at both sides of the
roads, and the streets appear to be very narrow. With barrier effect of greening, it can reduce
depression of buildings against the people. From the color perspective, blue sky and green tree are
under calm colors and can make people to feel calm.
(2) Plant is one of factors for creating beautiful urban space. With specific lines, form colors and
seasonal change of plants and other aesthetic factors and with different tree species, appreciation
periods and configuration mode and decorated with street lamp, flower red, garbage bin and so on,
it can form rich and colorful street landscape. In addition, it can meet the demand of greening
space from the residents in high-rise residence.
6.3 Analysis of impact on water and soil erosion
The project has completed its water and soil conservation scheme report, and the
assessment will mainly refer to the main conclusions in the water and soil
conservation scheme.
6.3.1 Responsibility scope and prevention area for water and soil loss
(1) Responsibility scope for water and soil loss
Responsibility scope for water and soil loss of the project covers 97.81hm2, area of
construction area covers 88.19 hm2; area under direct impact covers 9.63 hm
2. Out of
them, the construction area for principal works covers 80.59 hm2, area under direct
113
impact covers 7.26hm2; excavation waste dump area covers 1.29 hm
2, area under
direct impact covers 0.27 hm2; borrow pit area covers 0.39hm
2, area under direct
impact covers 0.11 hm2; area for construction temporary road covers 4.04 hm
2, area
under direct impact covers 1.47 hm2; construction production and living area covers
1.02 hm2, area under direct impact covers 0.17 hm
2.
(2) Prevention area for water and soil loss
In consideration of the water and soil loss caused by the original topography and
layout of the principal works, it divides the prevention areas for water and soil loss as
follows: 1. principal work area, 2. excavation waste dump area, 3. borrow pit area, 4.
temporary soil stacking yard area, 5. construction temporary road area and 6.
Construction production and living area.
6.3.2 Prediction for water and soil loss
(1) Prediction scope
The prediction scope of the project refers to the ground surface scope disturbed by the
project, includes principal work area, excavation waste dump area, borrow pit area,
temporary soil stacking yard area, construction temporary road area and 6construction
production and living area and the prediction area covers 88.19hm2.
(2) Prediction period
The prediction period for water and soil loss of the project consists of three periods,
namely construction preparation period, construction period and natural restoration
period.
(3) Prediction method
Based on characteristics of water and soil loss and waste soil and residue produced in
different construction units and different construction techniques, for prediction of
potential water and soil loss quantity, according to different water and soil loss area
and based on investigation and analysis of analogy projects, prediction was conducted
with the analogy method.
The water and soil loss quantity caused by disturbance against the ground surface can
be calculated as follows:
∑∑==
××=3
11
)(k
ikikik
n
i
TMFW
Quantity of newly increased water and soil loss:
114
∑∑==
××=∆3
11
)(k
ikikik
n
i
TMFW
Where, W—water and soil loss quantity caused by disturbance against the
ground surface (t);
i—Prediction unit (1, 2, 3, ……n);
k—Prediction time (1, 2, 3, construction preparation period, construction
period and natural restoration period);
Fik—the original ground surface area disturbed and damaged of the ith
prediction unit in different construction periods (km2);
Mik—average soil erosion modulus of the ith prediction unit in different
construction periods (t/km2•a);
Tik—Prediction period of the ith prediction unit in different construction
periods (a);
(4) Prediction result
With prediction, the gross water and soil loss quantity of the project during
construction period is 5154t. Compared with the original topography, it increases
water and soil loss quantity of 4439t. In project area, there is much water and soil
loss in waste dump area, temporary soil stacking yard, borrow pit and so on, and
these areas are the key prevention areas for water and soil loss. Construction period
is the key period for water and soil loss.
6.3.3 General arrangement and system for water and soil loss prevention measures
According to the prediction result of water and soil loss and prevention responsibility
scope and in consideration of water and soil loss prevention areas and analysis of
works who have owned water and loss conservation functions in the principal works,
it determines that different prevention areas will take up different prevention
measures and layout for forming the water and soil loss prevention measure system
and general arrangement of the project. For different types of prevention measure
arrangement, it shall take the existing water and soil conservation measures into
account, and combine the temporary prevention measures with engineering measures
and plant measures. Piloted by the temporary prevention measures, it shall assure
that water and soil loss can be effectively control during construction. In addition, it
shall focus on protection for surface layer farming soil in each prevention area for
vegetation restoration or rehabilitation in later stage; focusing on the engineering
measures, it shall make use of its fast effect an guarantee effect; aided by plant
measures, it shall achieve long term and stable water and soil conservation effect,
115
and can also achieve greening and beautify the surrounding environment of the
project area.
For water and soil conservation and prevention measure system of the project, refer to
Table 6-18.
Table 6-18 Water and soil conservation and prevention measure system
Project sub-area Type of measure Prevention measure
Engineering
measure
Pipe culvert for rain-sewage diversion
at both sides of subgrade
Plant measure Road landscape greening
Urban road prevention
area
Temporary measure Temporary blocking at the filled
subgrade side Engineering
measure Land reallocation
Plant measure Spread green manure and grass seed Temporary stack yard
Temporary measure
Blocking with bagged soil, covered
with geotechnical fabric, soil drainage
trench
Engineering
measure
Spoil blocking wall, surface soil
stripping and return
Plant measure Italian poplar +Chinese red
pine/lilyturf root+Bermuda grass Spoil yard
Temporary measure Blocking with bagged soil, covered
with geotechnical fabric
Engineering
measure Surface soil stripping and return
Plant measure Italian poplar + amorpha/trifolium
repens+Bermuda grass Borrow pit
Temporary measure Blocking with bagged soil, covered
with geotechnical fabric
Engineering
measure
Drainage trench at excavation side
and blocking at excavation side Construction
temporary road
Plant measure Lilyturf root +trifolium repens
116
Engineering
measure
Surface soil stripping and return, soil
drainage trench and grit chamber Construction
production and living
quarter
Plant measure Lilyturf root +trifolium repens
6.3.4 Work volume for water and soil conservation
The work volume of each area is separately listed according to its water and soil
conservation measures. For detailed work volume, refer to Table 6-19.
Table 6-19 Work volume summary schedules for water and soil conservation measures
Quantity Volume of works Prevention
area Water and soil conservation measure
Unit Qty Work Unit Qty
D1080 concrete
pipe m
18154.1
4 Rain drainage system km 18.15
Gutter inlet and
reinforcement Set 857
D720 concrete
pipe m
18154.1
4
Sewage drainage system km 18.15 D1000 inspection
well
reinforcement
Set 484
Engineerin
g measure
(drainage
work)
Surface soil stripping and
transfer
100
00
m3
8.65
Street tree km 15.78 Plant tree at road
sides
Indi
vidu
al
plan
t
4551 Plant
measure
Greening km 15.78 Road landscape
greening hm2 19.07
Urban road
prevention
area
Temporary
measure Blocking at road sides km 4.28
Bagged soil
blocking and
removal
m3 2140
Foundation
excavation m
3 248.18
Earthwork
backfilling m3 63.82
Cement laid stone
masonry m
3 364.8
Cement laid stone masonry
spoil retain wall m 120
PVC drainage
pipe (Φ10mm) m2 1517.04
Canal groove
excavation m3 441.6
Earthwork
backfilling m
3 165.61
Lined with
cement laid stone
masonry
m3 79.4
Drainage ditch m 460
Plastered with
M10 mortar m2 846.4
Spoil yard
prevention
area
Engineerin
g measure
Sedimentation tank set 2 Earthwork
excavation m
3 32.7
117
Earthwork
backfilling m3 16.4
Lined with
cement laid stone
masonry
m3 8.48
Plastered with
M10 mortar m
2 20.32
Plant locust hm2 0.98
Good seedling
aged in 2 years
Indi
vidu
al
plan
t
2455
Plant amorpha hm2 0.027
4
Good seedling
aged in 2 years
Indi
vidu
al
plan
t
122
Plant
measure
Spread trifolium repens
grass seed hm2 0.99
Trifolium repens
grass seed kg 45.9
Surface soil stripping hm2 1.02 Earthwork
volume m3 3060
Surface soil return hm2 0.99
Earthwork
volume m
3 3060
Reclamation with
bagged soil m3 48
Bagged soil blocking and
removal m 96
Removal of
bagged soil m
3 48
Covered with geotechnical
fabric m2 280
Geotechnical
fabric m2 280
Temporary
measure
Spread trifolium repens
grass seed hm2 0.23
Trifolium repens
grass seed kg 11.5
Reclamation with
bagged soil m3 910 Bagged soil blocking and
removal m 1820
Removal m3 910
Temporary side trench m 2240 Earthwork
volume m3 470.4
Temporary sedimentation
tank Set 2
Earthwork
volume m3 3
Temporary
measure
Covered with geotechnical
fabric m
2 6705
Geotechnical
fabric m2 6705
Plant
measure Spread alfalfa hm2 2.63
Trifolium repens
grass seed kg 157.8
Temporary
stack yard
prevention
area
Engineerin
g measure Land rectification hm
2 2.88
Surface soil
stripping and
return
m3 8600
Canal groove
excavation m
3 266.8
Earthwork
backfilling m3 90.2
Lined with
cement laid stone
masonry
m3 132.3
Interception and drainage
ditch m 245
Plastered with
M10 mortar m2 450.8
Earthwork
excavation m
3 32.7
Earthwork
backfilling m3 16.4
Lined with
cement laid stone
masonry
m3 8.48
Borrow pit
prevention
area
Engineerin
g measure
Sedimentation tank set 2
Plastered with
M10 mortar m
2 20.32
118
Plant Chinese red pipe hm2 0.28 Good seedling
aged in 2 years
Indi
vidu
al
plan
t
350
Plant Italian poplar hm2 0.28 Good seedling
aged in 2 years
Indi
vidu
al
plan
t
350
Plant
measure
Spread Bermuda grass +
trifolium repens seed hm2 0.28
Bermuda grass +
trifolium repens
seed
kg 16.8
Surface soil stripping hm2 0.28 Earthwork
volume m3 828
Surface soil return hm2 0.26
Earthwork
volume m
3 828
Reclamation with
bagged soil m3 20
Bagged soil blocking and
removal m 40
Removal of
bagged soil m3 20
Covered with geotechnical
fabric m
2 90
Geotechnical
fabric m
2 90
Temporary
measure
Spread trifolium repens
grass seed hm2 0.04
Trifolium repens
grass seed kg 2
Bagged soil retain wall m 1800 Reclamation with
bagged soil m
3 900
Drainage ditch m 1800 Earthwork
volume m3 386
Engineerin
g measure
Sedimentation tank Pcs 1 Earthwork
volume m3 2
Plant amorpha hm2 0.38 Good seedling
aged in 2 years
Indi
vidu
al
plan
t
1707
Constructio
n temporary
road
prevention
area Plant
measure
Spread trifolium repens
grass seed hm
2 0.38
Trifolium repens
grass seed kg 19
Drainage ditch m 1120 Earthwork
volume m3 235
Sedimentation tank Pcs 7 Earthwork
volume m3 21 Engineerin
g measure
Removal of hardened layer hm2 0.85 Removal of
hardened layer m3 2550
Surface soil protection hm2 0.85
Surface soil
stripping and
return
m3 2250
Temporary blocking m 220
Reclamation with
bagged soil and
removal
m3 110
Temporary cover m2 460 Geotechnical
fabric m2 460
Constructio
n production
and living
quarter
prevention
area Temporary
measure
Temporary grass planting hm2 0.13
Trifolium repens
grass seed kg 6.5
6.3.4 Investment estimate for water and soil conservation
The gross investment for water and soil conservation of the project is
RMB80367300 yuan, and the newly increased water and soil conservation
investment is RMB6012800 yuan. Out of it, the newly increased investment for
119
engineering measure is RMB1685600 yuan, the newly increased investment for
plant measure is RMB118300 yuan and the newly increased investment for
temporary work measure is RMB511200 yuan, the newly increased investment for
independent fee is RMB2523600 yuan. Water and soil conservation facility
compensation fee is RMB883800 yuan.
6.4 Impact on travel and living quality of the residents along the road
The project provides sideway, pedestrian overpass and other facilities. For sideway,
road crossing, pedestrian overpass, bridge, bus stop and so on, it provides barrier-free
design to meet the demands that the disabled, people with disabled limb, weak aged
people and children can travel with the road traffic facilities. Therefore, it will provide
significant convenience for normal travel of residents at both sides of the road,
production and transport after the project is built up.
The project will newly build drainage pipe network to achieve diversion of rain water
and sewage, it can improve the living environment of the residents along the roads
and improve their living quality.
After the roads are built up and put into operation, it will greatly improve the traffic
conditions, living environment and urban landscape along the roads. In addition, with
improvement of traffic conditions, it will also promote emergency of the tertiary
industry and development and utilization of the resources along the roads,
continuously improve the economic benefit of the enterprises, economy in the area
will achieve great development. Meanwhile, it also can provide a great deal of
employment opportunities and improve the income of the people along the roads.
With improvement of material living standard of the people, their demands for such
spiritual life as sanitation, education, communication, culture, entertainment and so on
will also become more greater, and it will better promote development of society,
medical treatment, sanitation, culture, education and so on along the roads.
6.5 Analysis of demolition and resettlement impacts of the project
6.5.1 Analysis of impact of the enterprise to be reallocated
According to migration and resettlement investigation data statistics, it will reallocate
9 enterprises in total for the urban traffic project in Xiangyang City. For the
conditions of the affected enterprises, resettlement measures and environmental
impact, refer to Table 6-20.
Table 6-20 Conditions of the affected enterprises, resettlement measure and
environmental impact
120
No
.
Enterpris
e name
Relocat
ion area
(m2)
Description of affected
conditions
Resettlement and
restoration measure Environmental impact
1
Wangjiawa
neibourhood
committee
825.9
Total in two parts: the
first is the fencing wall
of the soy sauce bottle
factory of Group 8 of
Wangjiawa village; the
second is the one waste
warehouse of Group 5
of Wangjiawa Village.
Removal of fencing
wall will not affect
production, the
warehouse is in idle
state, and there will be
no any actual effect.
1. The fencing wall of the
soy sauce bottle factory
will be reconstructed
behind the original place,
production and operation
will not be affected;
2. It will directly provide
monetary compensation for
removal of the warehouse.
Fencing wall and idle
warehouse will be under
demolition, there will be
no remaining pollutant
and waste.
2
Xiangfan
Synthetic
Fiber
Factory
534.03
The gatehouse and
bicycle parking shed in
the dormitory area of
Xiangfan Synthetic
Fiber Factory will be
under demolition.
It will provide monetary
compensation, and it will
reconstruct the fencing
wall and gatehouse after
removal.
The gatehouse and bicycle
parking shed will be under
demolition, there will be
no remaining pollutant
and waste.
3
Longzhon
g
Pharmace
utical
Factory
790.72
The fencing wall of
Longzhong
Pharmaceutical Factory
will be under
demolition, it will not
affect production and
operation.
It will be reconstructed
behind the original place.
The fencing wall will be
under demolition, there
will be no remaining
pollutant and waste.
4
Lifang
Electroni
c Co.,
Ltd.
887.62
The gatehouse and
bicycle parking shed in
the dormitory area of
Lifang Electronic Co.,
Ltd. will be under
demolition.
It will provide monetary
compensation, and it will
reconstruct the fencing
wall and gatehouse after
removal.
The gatehouse and bicycle
parking shed will be under
demolition, there will be
no remaining pollutant
and waste.
5
Wangjia
wa
vegetable
wholesale
market
1998.82
It is one vegetable
wholesale market
owned by the
Wangjiawa
neibourhood
committee, and the
entire market will be
under demolition.
It has arranged one place
that is 300m away from the
existing market for
reconstruction. The size
and grade are higher than
those of the existing
market. All of operation
shops can be reallocated to
the new market.
The vegetable wholesale
market is not one
production enterprise, and
there will be no remaining
pollutant and waste after
completing demolition.
6
Xiangfan
warehous
e directly
under
China
Grain
Reserves
Corporati
on
(Sinograi
n)
568.7
Fencing wall and
gatehouse of the grain
warehouse will be
under demolition, it
will affect the principal
buildings.
It will provide monetary
compensation, and it will
reconstruct the fencing
wall and gatehouse behind
the original place after
removal.
The gatehouse, bicycle
parking shed and fencing
wall will be under
demolition, there will be
no remaining pollutant
and waste.
7
Sijiqing
Dadongm
en market
5691 The entire market will
be under demolition.
All of shops and operators
will transfer to the newly
built wholesale market.
The market is not one
production enterprise, and
there will be no remaining
pollutant and waste after
completing demolition.
121
8
Property
managem
ent
company
of
Sujiayuan
communit
y
844 All of buildings will be
under demolition.
The Company will transfer
to the new market for
continuous operation.
The company under
demolition is not one
production enterprise, and
there will be no remaining
pollutant and waste after
completing demolition.
9
Railway
maintena
nce
station
1437
Some of buildings will
be under demolition; it
will not affect normal
operation.
It will provide monetary
compensation, and it will
make reconstruction
behind the original place.
The buildings under
demolition are not one
production buildings, and
there will be no remaining
pollutant and waste after
completing demolition.
6.5.2 Analysis of impact on new resettlement area
According to investigation data statistics, it will reallocate the private-owned houses
covering a total area of 88554.36 m2 for the urban traffic project in Xiangyang City. It
will involve with 272 households and 1498 persons. For the households under
demolition for each project and resettlement conditions, refer to Table 6-21.
Table 6-21 Type and area of reallocated private house
Sub-project Household Population Area Resettlement
mode Impact of resettlement
Xingguang Road 65 334 22133.57
Jianghua Road 56 361 13876.35
Xiangyang Road 74 366 25075.29
Zhakou 2nd Road 77 437 27364.63
Monetary
resettlement,
resettlement with
affordable house,
resettlement
through building
the resettlement
area
For the community and
resettlement area where take up
resettlement with affordable
house, resettlement through
building the resettlement area,
the sewage will connect to the
urban sewage pipe network,
domestic garbage will be
collectively gathered and sent to
the urban refuse treatment plant
via the refuse transfer station.
Total 272 1498 88554.36
Xiangyang Construction Investment and Operation Co., Ltd. Plans to build three
resettlement areas for resettling the families to be reallocated in the project.
1# resettlement area is located at the Guanyinge Village; the construction size is
72540m2. It can resettle more than 700 households, and is expected to be completed in
September, 2012. It can resettle the households from Hexing Village and Shijiamiao
Village affected by demolition in Jianghua Road and Zhakou 2nd
Road in the project.
2# resettlement area is located at the Wangjiawa Village; the construction size is
46667m2. It can resettle more than 450 households, and is expected to be completed in
July, 2014. It can resettle the households from Wangjiawa Village, Hongmiao
Village, Hexing Village and Shijiamiao Village affected by demolition in Xingguan
Avenue and Zhakou 2nd
Road in the project.
122
3# resettlement area is located at the Yingpan Village; the construction size is
61627m2. It can resettle more than 4630 households, and is expected to be completed
in October, 2011. It can resettle the villagers from Yangjiahe Village, Hongmiao
Village, Hexing Village and Shijiamiao Village affected by demolition in Xingguan
Avenue, Zhakou 2nd
Road and Xiangyang Road in the project.
6.6 Environmental risk analysis
According to the stage of risk produced in the project, the project risk consists of
construction risk and operation risk. In the design, there is detailed risk control and
prevention contingency plan for project risk. In consideration of project risk analysis,
the potential environmental risk of the project mainly includes environmental impact
and control caused by accident risk. For nature of the project, it mainly includes
accident risk of road dangerous goods transport against surrounding water body and
accident risk of gas filling station of the bus yard.
6.6.1 Analysis of road dangerous goods transport accident
(1) Definition of dangerous goods
For goods transport, any goods that have combustion, explosion, corrosion, poison,
and radioactivity and so on, may cause personnel death/injury and property loss
during transport, handling and storage and require special protection are defined as
dangerous goods. The definition above includes three specific requirements:
� The dangerous goods have certain dangerous nature, such as combustion,
explosion, corrosion, poison, radioactivity and so on, namely have internal and
potential factor that may bring about hazard.
� Dangerous goods can bring about hazard, it may lead to hazard effect under certain
conditions, cause goods loss and hazard the environment.
� It requires special protection during transport, handling and storage, such as special
package requirement, ambient temperature control, addition of inhibitor, radiation
shield, assembly requirement and so on.
(2) Classification of hazard
The dangerous goods will be classified based on hazard, generally there are three
hazards-fire and explosion hazard, human health hazard and reaction hazard.
(3) Risk characteristic of road transport mode
123
Dangerous goods have potential hazard itself. However, its risk against environment
is caused by external inducing factor. Physical explosion is caused by substance
sudden physical change of state or pressure; chemical explosion is caused by
substance that obtains the explosion energy and is fast decomposed and gives out a
great deal of gas and heat; fire hazard is substance combustion, which shall have three
conditions: fuel, combustion improver (oxygen) and heat (fire source)-namely the fire
triangle.
These so many external factors are inducing conditions causing risk during transport.
For risk characteristics of transport mode, refer to Table 6-22.
Table 6-22 Risk characteristics of transport mode
Transport
mode Risk type Hazard Cause brief analysis
Leakage
Pollute land area
Pollute surface water
Fire hazard and explosion
Cracking and vehicle upturn
Failure of handling equipment
Maloperation Road
transport Fire hazard
and explosion
Property loss
Personnel death/injury
Pollute environment
Fuel leakage
Mechanical, temperature, electric power,
chemical, fire source
(4) Environmental risk impact of dangerous goods transport
After the construction project is put into operation, risks mainly come from dangerous
transport vehicle. There may be leakage, fire hazard and explosion accident risk for
the vehicles that load different kinds of inflammable, explosive, toxic, corrosive and
radioactive dangerous goods. The storage and transport system, including transport of
raw material, intermediate and product and their sump and tank have potential hazard.
For example, it requires special protection (including special packaging requirement,
ambient temperature control, addition of inhibitor, radiation shielding, assembly
requirements and so on) during transport, handling and storage of chlorine fluid, nitric
acid, sulfuric acid, toluene, gasoline, ammonia and so on.
Once there is any accident, it may cause leakage, fire hazard and explosion, it will
bring about serious pollution against the ambient air, surface water and soil ecology
within the area. Once the dangerous good leak and infiltrate the soil, different
organisms and plants in soil will die, it will take very long time to thoroughly purify
the polluted soil, and it may take more than one decade (even longer time) to restore
its original functions.
6.6.2 Risk analysis for bus yard
(1) Hazard identification of major materials
124
In the project, it will newly build one gas filling station in the parking and
maintenance yard in Xiangyang Economic Development Zone. During operation of
the bus yard, it may involve with natural gas that is toxic, inflammable and explosive.
Natural gas is one kind of inflammable and explosive material and may have
explosion, leakage, fire hazard and other environmental risks.
Major constituent of natural gas is methane, natural gas also contains a little of ethane,
butane, nitrogen gas and carbon dioxide. It is difficultly to dissolve in water, can
dissolve in alcohol and ether. Its flash point is 188�, fusion point is -182.5� and
boiling point is -161.5�. According to classification of inflammable materials
stipulated in the Fire Prevention Code of the Petro-chemical Enterprise Design
(GB50160-92), fire hazard grade of natural gas is A of class I.
(2) Identification of significant hazard source
According to Identification of Significant Hazard Source (GB18218-2000) and
Appendix A of the Technical Guidelines for Environmental Risk Assessment on
Projects (HJ/T169-2004), natural gas used in the bus yard is dangerous material that
is combustible and inflammable. In Table 6-23, it indicates that critical quantity of
dangerous matter can be used as the basis for determining significant hazard source.
Table 6-23 Critical quantity of hazardous substance
Critical quantity (t) No. Substance
Production site Storage area
1 Gasoline 2 20
2 Natural gas 1 10
The maximum storage volume of the natural gas storage tank in the bus yard of the
project is less than critical quantity. Thus, according to classification principles of risk
assessment rate stipulated in the Technical Guidelines for Environmental Risk
Assessment on Projects (HJ/T169-2004), the natural gas storage tank in the bus yard
will not be significant hazard source. Therefore, environmental risk assessment rate of
the bus yard is class II. Thus, with reference to the standard, the assessment conducted
risk identification, conducted brief analysis of accident risk, conducted analysis of
range and degree affected by accident.
(3) Environmental impact of accident
Environmental risk accident mainly refers to emergency disaster accident that has
great hazard and extensive affected range. The potential risk accidents of the proposed
project include leakage and intoxication accident and combustion and explosion
125
accident. According to analysis of causes of chemical product and dangerous waste
environment accident in the similar type of enterprise, it shows that the causes mainly
include leakage, fire source, violating operating instructions, external factors and so
on.
The storage volume of the natural gas storage tank in the project is less than critical
quantity of dangerous matter. Thus, it only conducted qualitative analysis for the
potential risk. Once there is leakage or fire hazard accident against the natural gas
storage tank, there may be such environmental impacts as given in Table 6-24.
Table 6-24 Environmental impact of risk accident
Risk type Cause overview Hazard
Leakage (pop-up,
surge, leakage)
Tank and cylinder and pump under pressure,
pipe breakage and damage; corrosion against the
embedded part of tank and cylinder and pipe;
liquid and gas flooding of tank and cylinder,
bumping of oil tank; insufficient capacity of fire
dike; leakage of tank and cylinder; maloperaton
Cause fire hazard and
explosion
Fire hazard and
explosion
Leakage of stored matter Mechanical, temperature, electric power, chemical,
fire source
Property loss
Personnel death/injury
Pollute environment
7.0 Public Consultations and Information Publicity
7.1 Purpose and Significance
Because the highway construction deals with land occupation, housing demolition and
other major issues relating to the vital interests of the peasants, the public
participation, as an important component of environmental impact report, is crucially
important for improving decision-making, it can directly reflect the public opinions on
project construction, make the decision-making section timely discover the existing
problems, timely modify and improve the design proposal and solve the problems
raised by the public; furthermore, it can make the construction scheme of the project
become perfect and reasonable, and make the economic benefits, environmental
benefits and social benefits be closely coordinated with each other. Moreover, letting
the public learn about the construction project and express their ideas and opinions
can not only gain understanding and support of the construction project from the
public, but also make the public improve their environmental consciousness in the
activities they participate in, supervise the environmental protection work and protect
126
the ecological environment to ensure the implementation of sustainable development
strategy.
7.2 Survey Scope and Modes
7.2.1 Survey Scope
According to the requirements of national laws and regulations on environmental
protection, as per the principle of conducting the survey fairly, openly, truly and
objectively, a comprehensive public opinion survey has been conducted on the
important sensitive points, enterprises and public institutions, merchants, schools,
hospitals and residential areas on both sides of the project construction road and the
surrounding areas of the stations.
7.2.2 Modes of Survey
The modes of public participation survey of the project mainly are newspaper
publicity, website publicity, posting notices and issuing questionnaires, combined
with individual counseling.
On June 23 and June 28, 2011, the environmental impact assessment on the project
was publicized for the first time on the websites of Hubei Environmental Protection
Portal and Xiangyang Environmental Protection Agency, and the pages for public
notices are shown as in figure 7-1 and figure 7-2.
On August 4, 2011, the environmental impact assessment on the project was
publicized for the second time on the websites of Hubei Environmental Protection
Portal and Xiangyang Environmental Protection Agency, and the abridged edition of
the report was linked to the websites; the pages for public notices are shown as in
figure 7-3 and figure 7-4.
From August 7 to August 11, 2011, the assessment units conducted on-site
questionnaire survey and posted notices on the notice boards of all residents’
committees and village committees in the areas involved in the project, which is
shown in figure 7-1.
When the environmental impact report and environmental management plan of the
project were completed initially, as per the requirements of the World Bank, on
August 23, 2011, the environmental impact assessment of the project was made public
on Xiangyang Daily (newspaper and website) (see figures 7-5 & 7-6), meanwhile, the
full texts of the environmental impact report and environmental management plan
were made public on the website www.crfsdi.com (see figure 7-7) for convenient
reference for the residents.
127
The assessment units conducted on-site questionnaire survey for the second time from
September 13 to September 15.
Figure 7-1 Situation of On-Site Questionnaire Survey and Posting Notice
Public Notice in Sujiayuan Community Public Notice in Hongmiao Village
Public Notice in Sunjiaxiang Village Public Notice in Tujiaxiang Village
Public Notice in Yangjiahe Village Public Notice in Shijiamiao Community
Public Notice in Guanyinge Community Public Notice in Wangjiawa Community
128
Public Participation on Site of Residential Area Public Participation on Site of Residents’ Committee
Figure 7-1 The Public Notice of the first Environmental Impact Assessment on
Website of Hubei Environmental Protection Portal
129
Figure 7-2 The Public Notice of the first Environmental Impact Assessment on
Website of Xiangyang Environmental Protection Agency
130
Figure 7-3 The Public Notice of the second Environmental Impact Assessment on
Website of Hubei Environmental Protection Portal
131
Figure 7-4 The Public Notice of the second Environmental Impact Assessment on
Website of Xiangyang Environmental Protection Agency
132
Figure 7-5 Public Notice on Newspaper of Xiangyang Daily
133
Figure 7-6 Public Notice on Website of Xiangyang Daily (http://xfrb.hj.cn)
Figure 7-7 Public Notice of Environmental Impact Report and Environmental
Management Plan on Website of www.crfsdi.com
134
7.3 Survey Results
7.3.1 Personal Survey Results
From August 7 to August 11, 100 questionnaires were issued for the first on-site
questionnaire survey, 80 pieces were recovered, and the recovery ratio was 80%.
Details of the respondents of public opinions are shown in table 7-2.
Table 7-2 Details of Respondents of Public Opinions
Total Number of
Respondents Number of Males/Ratio Number of Females/Ratio
80 57 71.3% 23 28.7%
Under 18
Number/Ratio
18-40
Number/Ratio
41-60
Number/Ratio
Above 61
Number/Ratio Age Ratio (%)
13 16.3% 25 31.3% 31 38.8% 11 13.8%
Illiteracy
Number/Ratio
Primary School
Number/Ratio
Middle School
Number/Ratio
Above College
Degree
Number/Ratio Education Degree
Ratio (%)
10 12.5% 17 21.3% 30 37.5% 23 28.8%
Cadre
Number/Ratio
Teacher, Student
Number/Ratio
Peasant
Number/Ratio
Others
Number/Ratio Occupation Ratio
(%) 7 8.8% 3 3.8% 37 46.3% 33 41.3%
See table 7-3 for basic information of questionnaire survey for main public
opinions
Table 7-3 Basic Information of Questionnaire Survey for Public Opinions
S/N Survey Contents Response
Broadcast Newspaper TV program Others
1
What makes you learn
that Xiangyang Urban
Traffic Project
Engineering by World
Bank Loan is to be
constructed
0 22% 0 78%
Satisfied Relatively satisfied Dissatisfied Indifferent
2
Are you satisfied with
the environmental
conditions of your
present residence place
or work place
62% 25% 13% f0
Serious General Not serious 3
Effect of existing road
vehicle exhaust on you 8% 40% 52%
Serious General Not serious 4
Effect of existing road
noise on you 17% 42% 41%
5 The project
construction may cause Noise Vibration Dust
Sewage and
mud Traffic jam Others
135
environmental pollution
or disturbance to your
life, what do you think
will be the main effect
30% 11% 55% 48% 60% 0
Noise Vehicle exhaust Others
6
The project operation
may cause
environmental pollution
or disturbance to your
life, what do you think
will be the main effect
51% 42% 10%
Regional environment The whole dwelling
environment Bedrooms
7
What do you think is
the place where
environmental quality
must be ensured 10% 65% 50%
Low-noise
pavement
Ventilating
and
soundproof
window
Relocation Greening Planning
control Others
8
What do you think is
the environmental
protection measure to
be taken in operation
period 38% 22% 9% 40% 10% 0
Economic
compensation
Require treatment
to meet the
specified standard
Relocation Indifferent
9
If the project
construction may
influence your dwelling
environment, in what
way do you hope to
solve the problem 35% 55% 6% 4%
Understanding Understanding, but require
mitigation measures Complaining
10
What’s your attitude
towards the temporary
influence caused in
construction period 13% 87% 0
Complain to the
environmental protection
department
Solve the problem through
legal procedures
Stop the construction and
operation of the project 11
What way do you think
is effective for solving
the problem of
environmental pollution
resulting from the
project
56% 44% 0
Willing Unwilling
Willing
under
certain
condition
Helpful
effect
Adverse
effect Little effect
12
What’s the effect of
relocation on your
production and life
20% 15% 65% 17% 15% 68%
Support Conditional support Nonsupport Undecided
13
What’s your attitude
towards the project
construction 73% 17% 0 10%
From September 13 to September 15, 50 questionnaires were issued for the
second on-site questionnaire survey, 40 pieces were recovered, and the recovery ratio
was 80%. Details of the respondents of public opinions are shown in table 7-4.
Table 7-4 Details of Respondents of Public Opinions
Total Number of
Respondents Number of Males/Ratio Number of Females/Ratio
40 35 87.5% 5 12.5%
Under 18
Number/Ratio
18-40
Number/Ratio
41-60
Number/Ratio
Above 61
Number/Ratio Age Ratio (%)
0 0% 25 62.5% 15 37.5% 0 0%
136
Illiteracy
Number/Ratio
Primary School
Number/Ratio
Middle School
Number/Ratio
Above College
Degree
Number/Ratio Education Degree
Ratio (%)
8 20% 0 0% 12 30% 20 50%
Cadre
Number/Ratio
Teacher, Student
Number/Ratio
Peasant
Number/Ratio
Others
Number/Ratio Occupation Ratio
(%) 0 0% 0 0% 8 20% 32 80%
See table 7-5 for basic information of questionnaire survey for main public
opinions
Table 7-5 Basic Information of Questionnaire Survey for Public Opinions
S/N Survey Contents Response
Broadcast Newspaper TV program Others
1
What makes you learn
that Xiangyang Urban
Traffic Project
Engineering by World
Bank Loan is to be
constructed
0 52% 13% 35%
Satisfied Relatively satisfied Dissatisfied Indifferent
2
Are you satisfied with
the environmental
conditions of your
present residence place
or work place
65% 35% 0 0
Serious General Not serious 3
Effect of existing road
vehicle exhaust on you 20% 40% 40%
Serious General Not serious 4
Effect of existing road
noise on you 25% 50% 25%
Noise Vibration Dust Sewage and
mud Traffic jam Others
5
The project
construction may cause
environmental pollution
or disturbance to your
life, what do you think
will be the main effect
30% 8% 62% 45% 50% 0
Noise Vehicle exhaust Others
6
The project operation
may cause
environmental pollution
or disturbance to your
life, what do you think
will be the main effect
50% 45% 12%
Regional environment The whole dwelling
environment Bedrooms
7
What do you think is
the place where
environmental quality
must be ensured 15% 40% 45%
Low-noise
pavement
Ventilating
and
soundproof
window
Relocation Greening Planning
control Others
8
What do you think is
the environmental
protection measure to
be taken in operation
period 30% 35% 10% 42% 18% 0
9 If the project
construction may
influence your dwelling
Economic
compensation
Require treatment
to meet the
specified standard
Relocation Indifferent
137
environment, in what
way do you hope to
solve the problem
20% 65% 10% 5%
Understanding Understanding, but require
mitigation measures Complaining
10
What’s your attitude
towards the temporary
influence caused in
construction period 35% 65% 0
Complain to the
environmental protection
department
Solve the problem through
legal procedures
Stop the construction and
operation of the project 11
What way do you think
is effective for solving
the problem of
environmental pollution
resulting from the
project 30% 70% 0
Willing Unwilling
Willing
under
certain
condition
Helpful
effect
Adverse
effect Little effect
12
What’s the effect of
relocation on your
production and life
18% 10% 55% 12% 10% 55%
Support Conditional support Nonsupport Undecided
13
What’s your attitude
towards the project
construction 80% 20% 0 0
Statistical analysis of results: both of the recovery ratios of the public opinions
questionnaires of the two times reach up to 80%, which shows that the public is very
concerned about the construction of the project; most people want to express their
opinions by this opportunity, they hope to reflect their opinions and ideas through
normal channels, and they have placed high expectations on it.
The results of the two on-site questionnaire surveys indicates that 91.7% of the
respondents support or conditionally support the construction of the project, 8.3% of
them haven’t make their attitude clear, and no one opposes the construction of the
project; the main reasons of the supporters are as follows:
� At present, the traffic situation in Panggong area is poor, and the road facilities
can’t meet the traffic demands, while the construction of the project can improve
the present traffic situation and bring convenience to people.
� The project implementation can improve the dwelling environment of the
residents along the line, and improve their quality of life as well.
The conditional supporters mainly care about the pollution control and relocation
measures during construction period and operation period.
7.3.2 Results of Unit Survey
For the public participation this time, questionnaire surveys were conducted among 12
units such as the residents’ committee, village committee and hospitals within the
scope the project area, and all units recovered the questionnaires (with official seals of
the sectors). The units’ questionnaires and related survey results are shown in tables
7-6 and 7-7.
138
Table 7-6 Statistical Table of Attitude and Opinions of Units along the Line to Project
Construction
S/N Name Attitude towards the
Project Construction Main Opinions They Presented
1 Sujiayuan Community
Committee
Give active support,
speed up the
construction
The newly built roads shall have separate sidewalk and
traffic lane
2 Zhakou Community
Committee
Give active support,
speed up the
construction
/
3
Wangjiawa
Community
Committee
Give active support,
speed up the
construction
/
4
Panggongci
Community
Committee
Give active support,
speed up the
construction
/
5 Hongmiao Village
Committee Support /
6 Hexin Village
Committee
Give active support,
speed up the
construction
/
7 Sunjiaxiang Village
Committee
Give active support,
speed up the
construction
/
8 Tuxiang Village
Committee
Give active support,
speed up the
construction
/
9 Yangjiahe Village
Committee
Give active support,
speed up the
construction
/
10
Shijiamiao
Community
Committee
Give active support,
speed up the
construction
/
11
Guanyinge
Community
Committee
Give active support,
speed up the
construction
The construction time and construction period shall
comply with relevant regulations, and reduce the impact
on the masses in surrounding areas
12 Panggong Hospital
Give active support,
speed up the
construction
/
Table 7-7 Statistical Table of Results of Questionnaire Survey among Units along the
Line
S/N Item Contents Sector
(Nos.)
Percentage
(%)
Broadcast, newspaper, TV program,
etc 2 16.7%
The questionnaire 10 83.3% 1 In what way to learn about the
construction of the project
Others 0 0
Satisfied 4 33.3%
Relatively satisfied 3 25.0%
Dissatisfied 5 41.7% 2
Whether feel satisfied with the
environment of the existing
residence or work place
Indifferent 0 0
Dust 7 58.3%
Noise 6 50.0%
Vibration 4 33.3%
Sewage and mud 6 50.0%
Traffic disturbance 5 41.7%
3 Understanding of
environmental impact during
construction period
Land requisition and demolition 3 25.0%
139
Others 0 0
Understanding 5 41.7%
Understanding, but require mitigation
measures 7 58.3% 4
Attitude towards
environmental impact during
construction period Undecided 0 0
Noise 6 50.0%
Vehicle exhaust 8 66.7%
Landscape 4 33.3% 5
Understanding of
environmental impact during
operation period
Others 0 0
Economic compensation 4 33.3%
Require treatment to meet the specified
standard 8 66.7%
Relocation 1 8.3% 6
If the project construction’s
environmental impact on work
environment of the unit
exceeds the requirement of
environmental standard, the
measures and compensation
modes hope to be adopted Indifferent 0 0
Give active support, speed up the
construction 11 91.7%
Support 1 8.3% 7 Attitude towards the
construction of the project
Nonsupport 0 0
Note: part of the respondents selected two items or more, some items have not been filled in.
Statistical analysis of results: for the environmental impact assessment this time, the
recovery ratio of the units’ questionnaires reaches up to 100%, which shows that most
of the units want to express their opinions by this opportunity, they hope to reflect
their opinions and ideas through normal channels, and they have placed high
expectations on it. 91.7% of the surveyed units actively support the construction of
the project, and they hope to speed up the construction; 8.3% of the surveyed units
support the construction of the project; none of the surveyed units opposes the
construction.
7.3.3 Feedback of other Public Opinions
In the public participation this time, except issuing questionnaires on the site, no other
opinion feedbacks by phone and Email have been received from the public at present,
which indicates that the public has a higher degree of recognition to the project.
8.0 Environmental Management Plan
See separate editions of environmental management plan of the project for details.
9.0 Overall Conclusions
The urban traffic project by World Bank Loan mainly covers the road network
engineering in the southern section of inner loop and in Panggong area, and it is an
important component of the most central skeleton road system. After completion of
the project, it will play an important role and have a profound influence on such
140
aspects as separating urban through traffic, easing the traffic pressure in Xiangyang
City Center, especially Xiangyang Ancient City, shortening the travel time of
residents, improving the system capacity of corridors crossing river and urban roads,
supporting urban land expansion and guiding urban development, and enhancing city
quality and grade.
The construction of the project conforms to the integrated traffic development planning of
Xiangyang City, and also conforms to relevant overall urban planning. The impact of the project
on the environment is mainly reflected in the construction period, so the construction units shall
strengthen the environmental management during construction period, strengthen environmental
protection education to the construction teams, and try to be strict in management and be civilized
in the construction. The construction contract signed by the engineering contractor shall have
specific terms, in which, the contractor shall promise to take pollution control measures, and
formulate strict procedures of punishment for breach of contract.
By comprehensive analysis, it is concluded that the engineering design has considered
the requirements of environmental protection, the established environmental
engineering design proposal is technically and economically feasible, and it has strong
operability. After implementation of the environmental protection program proposed
by engineering design and the environmental protection countermeasures raised by
the report and environmental management plan, the adverse impact of engineering
construction on the environment can be well controlled.
To sum up, it is feasible to assess the project from the perspective of environmental
protection.
141