e-Learning: Fight Against Oil SpillsKick off meetingBrussels 22 january 2014Call for proposals for prevention and preparedness projects
Partners
Coordinator:
TRAGSA
Beneficiaries:
Dirección General de Protección Civil y Emergencias - Ministerio del Interior (España)
Direction Générale de la Sécurité et de la Gestion des Crises – Ministére de L´Ìnterieur (France)
e-Learning: Fight Against Oil Spills
• Total eligible costs: 236.063,43€
• EC contribution (75%): 177.038,43€
• Duration: 10 months
Tragsa
The project e-Learning: Fight Against Oil Spills
Form, Train and prepare volunteers focused on health risk
Professionals training specialized in managing volunteers
The Strengh of the tool it is to train thousands of people at the same time in case of need
Regulate the number of volunteers who can intervene in terms of the need demanded during the emergency and the existing logistic capabilities
04
Tragsa
Background information
Main objective it is to improve the response system
In previous cases manager can´t controll flow of volunteers to the emergency area
Public opinionPublic healthProffessionals usually aren´t adequately
prepared to manage volunteers
05
Tragsa
Results
06
Two on line courses:-volunteers-professionals
One platform to control how many people attend each course-per number of students-per time open to attend it
The access is free for volunteers3 different languages to attend the course
-spanish-french-english
Tragsa
Deliverables and deadlines
07
Task Deliverables
Task A: reporting to the
Commission
22 January 2014 Kick-off meeting report
April 2014 Progress report n°1
Before 31 September 2014
Final report
Task B: Task search, analysis and selection of
feasible solutions and alternatives
31 january 2014 Website
31 january 2014Selection of e-learning platform
Task C: Task material
identification28 february 2014 Collecting specific manuals
Tragsa
Deliverables and deadlines
08
Task Deliverables
Task D: Search for interested
profiles28 february 2014 Profiles selection
Task E: Material development
31 may 2014 Technical documentation
30 june 2014 Evaluation tests
Task F: Evaluation and project control
30 july 2014 Prototype
Tragsa
Deliverables and deadlines
09
Task Deliverables
Task G: Monitoring of the
prototype
31 august 2014 Feed back about prototype
15 september 2014
Improvements of the prototype
Before 31 September 2014
Final report
Task H: Publicity
31 january 2014 Website
Follow Up
Tragsa
Follow up
Main objective it is monitoring the evolution project via website
Ensure the operation of the wbsite through continuous testing for faults
Literature review that makes available the most current training materials
Revision and updating of technical documentation by consulting experts
010
Tragsa 011
Thank you for your atention
E-FAOS Project