Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
DYNAMIC PILE TESTING REPORT
Queens Lake Pedestrian and Pipe Bridge York County, Virginia Schnabel Reference # 16C33018 October 27, 2016 Prepared For:
T/ 757-947-1220 F/ 757-947-122511836 Canon Blvd, Suite 400 / Newport News,VA / 23606
schnabel-eng.com
October 27, 2016 Mr. Kevin C. Campbell Engineer I Department of Environmental & Development Services York County 105 Service Drive Yorktown, VA 23690 Subject: Project 16C33018, Dynamic Pile Testing and Test Pile Observation Report –
Queens Lake Sanitary Sewer Project - Pedestrian & Pipe Bridge, Queens Lake, York County, Virginia
Dear Mr. Campbell: SCHNABEL ENGINEERING, LLC (Schnabel) is pleased to submit our report for the dynamic pile testing performed for the above project. These services were provided in accordance with our proposal dated February 22, 2016 and PO 27775. PROJECT DESCRIPTION The project consist of a pile supported pedestrian and pipe bridge across Queens Lake approximately 80 ft upstream of the existing dam. The proposed bridge will be supported on timber piles with 8 inch diameter tips. The piles have a design capacity of 12 tons, except for Sta 18+88 to 19+44 that have design capacity of 20 tons (Test Pile 6). Considering the design factor of safety of 2, the required ultimate capacities are 24 tons (48 kips) and 40 tons (80 kips), respectively for pedestrian and pipe bridge. The test pile program for this project includes driving and dynamically testing the restrike of seven test piles. We understand the allowable compression and tension driving stresses for timber piles is three time the allowable working stress. The allowable working stress is 1,200 psi. Therefore, the allowable driving stresses are 3,600 psi. PILE HAMMER The hammer for this project is an ICE I-8v2 single acting diesel impact hammer with a manufacturer’s maximum rated energy of 21,120ft-lbs.
York County Queens Lake Pedestrian and Pipe Bridge
October 27, 2016 Page 2 Schnabel Engineering, LLC Project 16C33018 @2016 All Rights Reserved
DYNAMIC TESTING On October 24, 2016 we observed the restriking of all seven test piles. The restrike of the test piles were dynamically tested with a PAK Model Pile Driving Analyzer (PDA) manufactured by Pile Dynamics, Incorporated. The results of these analyses are summarized in Table 1.
Table 1 – Dynamic Pile Test Results, Restrike
Test Pile
Tip Grade at Time of
Restrike (ft)
Restrike Blowcount
(bpi)
CASE Method Capacity (kips)
(BOR) Test Pile No.
1 -15 2 42
Test Pile No.
2 -36 2 52
Test Pile No. 3
-46 2 58
Test Pile No. 3A
-34 2 39
Test Pile No. 4
-41 3 87
Test Pile No. 5
-29 5 128
Test Pile No. 6
-30 5 136
*BOR- beginning of restrike CASE Method results are dependent on an assumed damping factor. Based on local experience and the soil conditions on site, we considered a CASE damping factor of 0.5 when establishing CASE Method capacities reported in Table 1. It should be noted that CASE method results assume uniform pile section. Since the cross section of the piles varies along their length, CASE Method capacities are not representative of actual pile capacity. We conducted CAPWAP analyses on selected hammer blows near the beginning of the restrike. The results of these analyses are included as Appendix A and are summarized in Table 2. As driven and restrike test pile logs are included in Appendix B.
York County Queens Lake Pedestrian and Pipe Bridge
October 27, 2016 Page 3 Schnabel Engineering, LLC Project 16C33018 @2016 All Rights Reserved
Table 2 – Summary of CAPWAP Results, Restrikes
Test Pile Tip Grade at
Time of Restrike (ft)
CAPWAP Capacities (kips)
Total Shaft Friction End-Bearing
Test Pile No. 1
-15 56 28 28
Test Pile No. 2
-36 60 53 7
Test Pile No. 3
-46 82 15 67
Test Pile No. 3A
-34 39 25 14
Test Pile No. 4
-41 95 81 14
Test Pile No. 5
-29 76 30 46
Test Pile No. 6
-30 76 31 45
CONCLUSIONS Based on the results of the dynamic testing performed on the above piles, we believe the piles develop ultimate capacities in excess of the required ultimate compressive capacity (24 kips and 40 kips) and will provide a factor of safety of at least 2.0 in compression when driven to the design minimum tip grades specified Addendum No. 2 IFB No. 1980 prepared by York County dated February 11, 2016. We have endeavored to prepare this report in accordance with generally accepted geotechnical engineering practice and make no warranties, either express or implied, as to the professional advice provided under the terms of our agreement and included in this report.
York County Queens Lake Pedestrian and Pipe Bridge
October 27, 2016 Page 4 Schnabel Engineering, LLC Project 16C33018 @2016 All Rights Reserved
We appreciate the opportunity to be of service for this project. Please contact either of the undersigned if clarification is needed for any aspect of this report. Sincerely, SCHNABEL ENGINEERING, LLC Donald J. Smith, PE Senior Engineer Gilbert T. Seese, PE Principal DJS:GTS:dah Appendices:
A) CAPWAP Results, Restrike B) Test Pile Logs
October 27, 2016 Schnabel Engineering, LLC Project 16C33018 @2016 All Rights Reserved
APPENDIX A
CAPWAP ANALYSIS, RESTRIKES
5 195
-80
0
80
160
ms
kips
66 L/c
Force MsdForce Cpt
5 195
-80
0
80
160
ms
kips
66 L/c
Force MsdVelocity Msd
Pile
0
1
2
3
4
kips
/ft
0
15
30
45
60
kips
Shaft ResistanceDistribution
Pile Forceat Ru
0 15 30 45 600.000
0.500
1.000
1.500
2.000
Load (kips)
Dis
plac
emen
t (in
)
Pile TopBottom
Ru = 56.5 kipsRs = 27.6 kipsRb = 28.9 kipsDy = 1.37 inDx = 1.87 in
queens lake dam sanitary projec; Pile: Test Pile 1 Restrike; 14" timber; Blow: 2 (Test: 01-Jan-2001 00:13:) 26-Oct-2016Schnabel Engineering CAPWAP(R) 2006-3
CAPWAP(R) 2006-3 Licensed to Schnabel Engineering
queens lake dam sanitary projec; Pile: Test Pile 1 Restrike Test: 01-Jan-2001 00:13:14" timber; Blow: 2 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 1 Analysis: 26-Oct-2016
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 56.5; along Shaft 27.6; at Toe 28.9 kips
Soil Dist. Depth Ru Force Sum Unit Unit SmithSgmnt Below Below in Pile of Resist. Resist. DampingNo. Gages Grade Ru (Depth) (Area) Factor
ft ft kips kips kips kips/ft ksf s/ft
56.51 6.7 1.7 3.8 52.7 3.8 2.28 1.09 0.0502 10.0 5.0 2.3 50.4 6.1 0.69 0.33 0.0503 13.3 8.3 0.6 49.8 6.7 0.18 0.09 0.0504 16.7 11.7 0.0 49.8 6.7 0.00 0.00 0.0005 20.0 15.0 0.0 49.8 6.7 0.00 0.00 0.0006 23.3 18.3 2.3 47.5 9.0 0.69 0.33 0.0507 26.7 21.7 8.9 38.6 17.9 2.67 1.28 0.0508 30.0 25.0 9.7 28.9 27.6 2.91 1.39 0.050
Avg. Shaft 3.4 1.10 0.53 0.050
Toe 28.9 82.78 0.000
Soil Model Parameters/Extensions Shaft Toe
Quake (in) 0.064 0.953Case Damping Factor 0.072 0.000Damping Type SmithUnloading Quake (% of loading quake) 100 75Reloading Level (% of Ru) 100 100Unloading Level (% of Ru) 43Soil Plug Weight (kips) 0.04
CAPWAP match quality = 4.14 (Wave Up Match) ; RSA = 0Observed: final set = 0.500 in; blow count = 24 b/ftComputed: final set = 0.802 in; blow count = 15 b/ftReplay Factor: F3:1.000; V3:1.000; V4:1.000;
max. Top Comp. Stress = 0.8 ksi (T= 29.2 ms, max= 1.410 x Top)max. Comp. Stress = 1.1 ksi (Z= 23.3 ft, T= 30.6 ms)max. Tens. Stress = -0.17 ksi (Z= 26.7 ft, T= 139.7 ms)max. Energy (EMX) = 5.9 kip-ft; max. Measured Top Displ. (DMX)= 1.40 in
queens lake dam sanitary projec; Pile: Test Pile 1 Restrike Test: 01-Jan-2001 00:13:14" timber; Blow: 2 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 2 Analysis: 26-Oct-2016
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.No. Gages Stress Stress Energy
ft kips kips ksi ksi kip-ft ft/s in
1 3.3 89.5 -14.0 0.8 -0.12 5.89 6.7 1.4242 6.7 87.3 -13.8 0.9 -0.14 5.88 7.5 1.4153 10.0 80.8 -11.6 1.0 -0.14 5.33 7.8 1.4054 13.3 75.7 -10.4 1.0 -0.14 4.99 8.0 1.3945 16.7 72.3 -10.0 1.0 -0.14 4.88 8.0 1.3826 20.0 70.4 -9.8 1.1 -0.15 4.86 7.7 1.3697 23.3 66.0 -9.7 1.1 -0.16 4.83 8.9 1.3538 26.7 53.6 -8.7 1.0 -0.17 4.49 9.6 1.3369 30.0 40.2 -4.6 0.8 -0.09 2.03 10.0 1.321
Absolute 23.3 1.1 (T = 30.6 ms) 26.7 -0.17 (T = 139.7 ms)
CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9RP 71.1 58.4 45.7 33.0 20.3 7.6 0.0 0.0 0.0 0.0RX 71.1 68.3 66.0 64.0 62.6 62.2 62.1 62.0 61.9 61.9RU 71.1 58.4 45.7 33.0 20.3 7.6 0.0 0.0 0.0 0.0
RAU = 61.2 (kips); RA2 = 69.8 (kips)
Current CAPWAP Ru = 56.5 (kips); Corresponding J(RP)= 0.12;
RMX requires higher damping; see PDA-W
VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUSft/s ms kips kips kips in in in kip-ft kips
6.63 28.89 121.8 76.2 111.0 1.397 0.500 0.500 5.9 74.5
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
0.00 113.10 2019.7 65.000 2.094 5.00 95.03 2019.7 65.000 2.094 10.00 78.54 2019.7 65.000 2.094 15.00 70.88 2019.7 65.000 2.094 20.00 63.62 2019.7 65.000 2.094 25.00 50.27 2019.7 65.000 2.094 30.00 50.27 2019.7 65.000 2.094
Toe Area 0.349 ft2
queens lake dam sanitary projec; Pile: Test Pile 1 Restrike Test: 01-Jan-2001 00:13:14" timber; Blow: 2 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 3 Analysis: 26-Oct-2016
Segmnt Dist. Impedance Imped. Tension Compression Perim.Number B.G. Change Slack Eff. Slack Eff.
ft kips/ft/s % in in ft
1 3.33 19.04 0.00 0.000 0.000 -0.000 0.000 2.0942 6.67 16.02 0.00 0.000 0.000 -0.000 0.000 2.0943 10.00 14.15 0.00 0.000 0.000 -0.000 0.000 2.0944 13.33 12.79 0.00 0.000 0.000 -0.000 0.000 2.0945 16.67 11.94 0.00 0.000 0.000 -0.000 0.000 2.0946 20.00 11.12 0.00 0.000 0.000 -0.000 0.000 2.0947 23.33 9.96 0.00 0.000 0.000 -0.000 0.000 2.0948 26.67 8.65 0.00 0.000 0.000 -0.000 0.000 2.0949 30.00 8.46 0.00 0.000 0.000 -0.000 0.000 2.094
Pile Damping 2.0 %, Time Incr 0.278 ms, Wave Speed 12000.0 ft/s, 2L/c 5.0 ms
5 205
-100
0
100
200
ms
kips
40 L/c
Force MsdForce Cpt
5 205
-100
0
100
200
ms
kips
40 L/c
Force MsdVelocity Msd
Pile
0
1
2
3
4
kips
/ft
0
20
40
60
80
kips
Shaft ResistanceDistribution
Pile Forceat Ru
0 20 40 60 800.000
0.400
0.800
1.200
1.600
Load (kips)
Dis
plac
emen
t (in
)
Pile TopBottom
Ru = 60.8 kipsRs = 53.1 kipsRb = 7.7 kipsDy = 0.59 inDx = 1.09 in
queens lake dam sanitary projec; Pile: Test Pile 2 restrike; 12" timber; Blow: 3 (Test: 01-Jan-2001 00:39:) 26-Oct-2016Schnabel Engineering CAPWAP(R) 2006-3
CAPWAP(R) 2006-3 Licensed to Schnabel Engineering
queens lake dam sanitary projec; Pile: Test Pile 2 restrike Test: 01-Jan-2001 00:39:12" timber; Blow: 3 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 1 Analysis: 26-Oct-2016
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 60.8; along Shaft 53.1; at Toe 7.7 kips
Soil Dist. Depth Ru Force Sum Unit Unit Smith QuakeSgmnt Below Below in Pile of Resist. Resist. DampingNo. Gages Grade Ru (Depth) (Area) Factor
ft ft kips kips kips kips/ft ksf s/ft in
60.81 13.8 5.8 0.0 60.8 0.0 0.00 0.00 0.000 0.2882 20.6 12.6 0.0 60.8 0.0 0.00 0.00 0.000 0.2883 27.5 19.5 0.0 60.8 0.0 0.00 0.00 0.000 0.2884 34.4 26.4 1.3 59.5 1.3 0.19 0.01 0.119 0.2885 41.3 33.3 9.0 50.5 10.3 1.31 0.05 0.119 0.2886 48.1 40.1 18.6 31.9 28.9 2.71 0.11 0.119 0.2887 55.0 47.0 24.2 7.7 53.1 3.52 0.14 0.119 0.280
Avg. Shaft 7.6 1.13 0.04 0.119 0.285
Toe 7.7 22.06 0.049 0.272
Soil Model Parameters/Extensions Shaft Toe
Case Damping Factor 0.333 0.020Damping Type SmithUnloading Quake (% of loading quake) 29 29Reloading Level (% of Ru) 100 100Unloading Level (% of Ru) 43Soil Plug Weight (kips) 0.09
CAPWAP match quality = 4.68 (Wave Up Match) ; RSA = 0Observed: final set = 0.500 in; blow count = 24 b/ftComputed: final set = 0.309 in; blow count = 39 b/ft
max. Top Comp. Stress = 1.0 ksi (T= 21.5 ms, max= 1.526 x Top)max. Comp. Stress = 1.6 ksi (Z= 48.1 ft, T= 25.5 ms)max. Tens. Stress = -0.66 ksi (Z= 41.3 ft, T= 49.6 ms)max. Energy (EMX) = 5.7 kip-ft; max. Measured Top Displ. (DMX)= 0.89 in
queens lake dam sanitary projec; Pile: Test Pile 2 restrike Test: 01-Jan-2001 00:39:12" timber; Blow: 3 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 2 Analysis: 26-Oct-2016
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.No. Gages Stress Stress Energy
ft kips kips ksi ksi kip-ft ft/s in
1 3.4 118.6 -37.3 1.0 -0.33 5.66 6.7 0.7572 6.9 117.2 -39.1 1.1 -0.35 5.65 6.8 0.7503 10.3 115.4 -40.7 1.1 -0.38 5.65 7.0 0.7434 13.8 112.8 -42.1 1.1 -0.40 5.65 7.1 0.7365 17.2 109.4 -43.5 1.1 -0.42 5.64 7.2 0.7276 20.6 106.1 -44.4 1.1 -0.46 5.64 7.3 0.7187 24.1 102.9 -45.1 1.1 -0.49 5.63 7.4 0.7088 27.5 99.7 -45.2 1.2 -0.53 5.62 7.6 0.6989 30.9 99.3 -45.4 1.2 -0.57 5.62 7.8 0.68610 34.4 100.3 -45.0 1.3 -0.60 5.61 7.9 0.67311 37.8 93.4 -43.3 1.3 -0.63 5.45 7.9 0.65812 41.3 94.7 -42.5 1.5 -0.66 5.45 8.1 0.64213 44.7 85.7 -35.4 1.4 -0.59 4.49 7.6 0.62814 48.1 89.4 -34.7 1.6 -0.62 4.49 7.9 0.61315 51.6 67.1 -20.9 1.3 -0.39 2.74 8.8 0.60316 55.0 55.9 -20.4 1.1 -0.40 0.37 9.3 0.592
Absolute 48.1 1.6 (T = 25.5 ms) 41.3 -0.66 (T = 49.6 ms)
CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9RP 100.0 86.3 72.7 59.1 45.5 31.8 18.2 4.6 0.0 0.0RX 125.9 115.8 106.2 96.5 86.9 78.0 72.0 66.3 63.6 62.3RU 100.0 86.3 72.7 59.1 45.5 31.8 18.2 4.6 0.0 0.0
RAU = 59.3 (kips); RA2 = 58.8 (kips)
Current CAPWAP Ru = 60.8 (kips); Corresponding J(RP)= 0.29; matches RX9 within 5%
VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUSft/s ms kips kips kips in in in kip-ft kips
10.78 21.77 205.3 30.9 138.9 0.895 0.501 0.500 4.7 80.3
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
0.00 113.10 2019.7 65.000 25.130 10.00 107.51 2019.7 65.000 25.130 15.00 103.87 2019.7 65.000 25.130 20.00 95.03 2019.7 65.000 25.130
queens lake dam sanitary projec; Pile: Test Pile 2 restrike Test: 01-Jan-2001 00:39:12" timber; Blow: 3 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 3 Analysis: 26-Oct-2016
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
25.00 86.59 2019.7 65.000 25.130 30.00 78.54 2019.7 65.000 25.130 35.00 70.88 2019.7 65.000 25.130 40.00 63.62 2019.7 65.000 25.130 45.00 56.75 2019.7 65.000 25.130 55.00 50.27 2019.7 65.000 25.130
Toe Area 0.349 ft2
Segmnt Dist. Impedance Imped. Tension Compression Perim.Number B.G. Change Slack Eff. Slack Eff.
ft kips/ft/s % in in ft
1 3.44 19.04 0.00 0.000 0.000 -0.000 0.000 25.1302 6.88 18.56 0.00 0.000 0.000 -0.000 0.000 25.1303 10.31 18.23 0.00 0.000 0.000 -0.000 0.000 25.1304 13.75 17.85 0.00 0.000 0.000 -0.000 0.000 25.1305 17.19 17.31 0.00 0.000 0.000 -0.000 0.000 25.1306 20.63 16.32 0.00 0.000 0.000 -0.000 0.000 25.1307 24.06 15.33 0.00 0.000 0.000 -0.000 0.000 25.1308 27.50 14.37 0.00 0.000 0.000 -0.000 0.000 25.1309 30.94 13.44 0.00 0.000 0.000 -0.000 0.000 25.13010 34.38 12.54 0.00 0.000 0.000 -0.000 0.000 25.13011 37.81 11.67 0.00 0.000 0.000 -0.000 0.000 25.13012 41.25 10.83 0.00 0.000 0.000 -0.000 0.000 25.13013 44.69 10.02 0.00 0.000 0.000 -0.000 0.000 25.13014 48.13 9.40 0.00 0.000 0.000 -0.000 0.000 25.13015 51.56 9.03 0.00 0.000 0.000 -0.000 0.000 25.13016 55.00 8.65 0.00 0.000 0.000 -0.000 0.000 25.130
Pile Damping 2.0 %, Time Incr 0.286 ms, Wave Speed 12000.0 ft/s, 2L/c 9.2 ms
5 105
-150
0
150
300
ms
kips
16 L/c
Force MsdForce Cpt
5 105
-150
0
150
300
ms
kips
16 L/c
Force MsdVelocity Msd
Pile
0
1
2
3
4
kips
/ft
0
30
60
90
120
kips
Shaft ResistanceDistribution
Pile Forceat Ru
0 30 60 90 1200.000
0.300
0.600
0.900
1.200
Load (kips)
Dis
plac
emen
t (in
)
Pile TopBottom
Ru = 82.5 kipsRs = 15.8 kipsRb = 66.7 kipsDy = 0.65 inDx = 0.85 in
queens lake dam sanitary projec; Pile: Test Pile 3; 12" timber; Blow: 3 (Test: 01-Jan-2001 01:23:) 26-Oct-2016Schnabel Engineering CAPWAP(R) 2006-3
CAPWAP(R) 2006-3 Licensed to Schnabel Engineering
queens lake dam sanitary projec; Pile: Test Pile 3 Test: 01-Jan-2001 01:23:12" timber; Blow: 3 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 1 Analysis: 26-Oct-2016
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 82.5; along Shaft 15.8; at Toe 66.7 kips
Soil Dist. Depth Ru Force Sum Unit Unit SmithSgmnt Below Below in Pile of Resist. Resist. DampingNo. Gages Grade Ru (Depth) (Area) Factor
ft ft kips kips kips kips/ft ksf s/ft
82.51 20.5 5.0 0.0 82.5 0.0 0.00 0.00 0.0002 27.3 11.8 0.0 82.5 0.0 0.00 0.00 0.0003 34.2 18.7 0.4 82.1 0.4 0.06 0.03 0.0494 41.0 25.5 0.5 81.6 0.9 0.07 0.03 0.0495 47.8 32.3 0.5 81.1 1.4 0.07 0.03 0.0496 54.7 39.2 4.2 76.9 5.6 0.61 0.29 0.0497 61.5 46.0 10.2 66.7 15.8 1.49 0.71 0.049
Avg. Shaft 2.3 0.34 0.16 0.049
Toe 66.7 191.08 0.063
Soil Model Parameters/Extensions Shaft Toe
Quake (in) 0.049 0.200Case Damping Factor 0.041 0.221Unloading Quake (% of loading quake) 30 74Reloading Level (% of Ru) 100 100Unloading Level (% of Ru) 0Soil Plug Weight (kips) 0.07
CAPWAP match quality = 5.52 (Wave Up Match) ; RSA = 0Observed: final set = 0.200 in; blow count = 60 b/ftComputed: final set = 0.156 in; blow count = 77 b/ftReplay Factor: F3:1.000; V3:1.000; V4:1.000;
max. Top Comp. Stress = 1.6 ksi (T= 21.1 ms, max= 1.483 x Top)max. Comp. Stress = 2.4 ksi (Z= 58.1 ft, T= 25.6 ms)max. Tens. Stress = -0.37 ksi (Z= 61.5 ft, T= 44.7 ms)max. Energy (EMX) = 4.1 kip-ft; max. Measured Top Displ. (DMX)= 0.80 in
queens lake dam sanitary projec; Pile: Test Pile 3 Test: 01-Jan-2001 01:23:12" timber; Blow: 3 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 2 Analysis: 26-Oct-2016
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.No. Gages Stress Stress Energy
ft kips kips ksi ksi kip-ft ft/s in
1 3.4 180.1 -28.6 1.6 -0.25 4.05 10.8 0.6142 6.8 175.9 -4.0 1.7 -0.04 4.02 11.0 0.6153 10.3 172.9 -5.1 1.8 -0.05 3.99 11.2 0.6094 13.7 170.3 -8.5 1.8 -0.09 3.95 11.3 0.5975 17.1 167.7 -11.7 1.9 -0.13 3.91 11.5 0.5806 20.5 165.1 -16.5 1.9 -0.19 3.88 11.6 0.5607 23.9 162.5 -19.1 1.9 -0.23 3.84 11.8 0.5488 27.3 160.0 -19.4 1.9 -0.24 3.80 11.9 0.5359 30.8 157.6 -22.0 2.0 -0.28 3.75 12.1 0.51810 34.2 155.2 -21.2 2.0 -0.28 3.70 12.2 0.49711 37.6 152.3 -25.6 2.1 -0.35 3.62 12.4 0.47512 41.0 149.9 -24.9 2.1 -0.35 3.57 12.5 0.46113 44.4 146.8 -25.1 2.1 -0.36 3.47 12.7 0.44514 47.8 144.2 -23.4 2.2 -0.35 3.41 12.9 0.42315 51.3 140.8 -21.8 2.2 -0.34 3.31 13.1 0.39616 54.7 141.7 -21.4 2.4 -0.36 3.24 12.9 0.37117 58.1 132.8 -20.4 2.4 -0.36 2.93 13.1 0.35118 61.5 122.0 -19.4 2.3 -0.37 2.50 14.2 0.327
Absolute 58.1 2.4 (T = 25.6 ms) 61.5 -0.37 (T = 44.7 ms)
CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9RP 84.2 72.1 60.1 48.0 35.9 23.8 11.7 0.0 0.0 0.0RX 163.0 154.5 146.0 137.5 129.0 120.5 111.9 106.3 106.0 105.7RU 84.2 72.1 60.1 48.0 35.9 23.8 11.7 0.0 0.0 0.0
RAU = 77.4 (kips); RA2 = 108.4 (kips)
Current CAPWAP Ru = 82.5 (kips); Corresponding J(RP)= 0.01;
RMX requires higher damping; see PDA-W
VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUSft/s ms kips kips kips in in in kip-ft kips
11.29 21.07 215.0 -10.0 257.4 0.800 0.200 0.200 1.7 42.0
queens lake dam sanitary projec; Pile: Test Pile 3 Test: 01-Jan-2001 01:23:12" timber; Blow: 3 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 3 Analysis: 26-Oct-2016
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
0.00 113.10 2019.7 65.000 2.094 10.00 95.03 2019.7 65.000 2.094 20.00 86.59 2019.7 65.000 2.094 30.00 78.54 2019.7 65.000 2.094 40.00 70.88 2019.7 65.000 2.094 50.00 63.62 2019.7 65.000 2.094 61.50 50.27 2019.7 65.000 2.094
Toe Area 0.349 ft2
Segmnt Dist. Impedance Imped. Tension Compression Perim.Number B.G. Change Slack Eff. Slack Eff.
ft kips/ft/s % in in ft
1 3.42 19.04 0.00 0.000 0.000 -0.000 0.000 2.0942 6.83 17.48 0.00 0.000 0.000 -0.000 0.000 2.0943 10.25 16.44 0.00 0.000 0.000 -0.000 0.000 2.0944 13.67 15.72 0.00 0.000 0.000 -0.000 0.000 2.0945 17.08 15.23 0.00 0.000 0.000 -0.000 0.000 2.0946 20.50 14.75 0.00 0.000 0.000 -0.000 0.000 2.0947 23.92 14.28 0.00 0.000 0.000 -0.000 0.000 2.0948 27.33 13.82 0.00 0.000 0.000 -0.000 0.000 2.0949 30.75 13.35 0.00 0.000 0.000 -0.000 0.000 2.09410 34.17 12.91 0.00 0.000 0.000 -0.000 0.000 2.09411 37.58 12.46 0.00 0.000 0.000 -0.000 0.000 2.09412 41.00 12.03 0.00 0.000 0.000 -0.000 0.000 2.09413 44.42 11.60 0.00 0.000 0.000 -0.000 0.000 2.09414 47.83 11.18 0.00 0.000 0.000 -0.000 0.000 2.09415 51.25 10.75 0.00 0.000 0.000 -0.000 0.000 2.09416 54.67 10.13 0.00 0.000 0.000 -0.000 0.000 2.09417 58.08 9.46 0.00 0.000 0.000 -0.000 0.000 2.09418 61.50 8.80 0.00 0.000 0.000 -0.000 0.000 2.094
Pile Damping 2.0 %, Time Incr 0.285 ms, Wave Speed 12000.0 ft/s, 2L/c 10.3 ms
10 60
-100
0
100
200
ms
kips
9 L/c
Force MsdForce Cpt
10 60
-100
0
100
200
ms
kips
9 L/c
Force MsdVelocity Msd
Pile
0
1
2
3
4
kips
/ft
0
20
40
60
80
kips
Shaft ResistanceDistribution
Pile Forceat Ru
0 20 40 60 800.000
0.300
0.600
0.900
1.200
Load (kips)
Dis
plac
emen
t (in
)
Pile TopBottom
Ru = 39.5 kipsRs = 25.4 kipsRb = 14.1 kipsDy = 0.35 inDx = 0.85 in
queens lake dam sanitary projec; Pile: Test Pile 3A; 12" timber; Blow: 8 (Test: 01-Jan-2001 01:08:) 26-Oct-2016Schnabel Engineering CAPWAP(R) 2006-3
CAPWAP(R) 2006-3 Licensed to Schnabel Engineering
queens lake dam sanitary projec; Pile: Test Pile 3A Test: 01-Jan-2001 01:08:12" timber; Blow: 8 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 1 Analysis: 26-Oct-2016
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 39.5; along Shaft 25.4; at Toe 14.1 kips
Soil Dist. Depth Ru Force Sum Unit Unit SmithSgmnt Below Below in Pile of Resist. Resist. DampingNo. Gages Grade Ru (Depth) (Area) Factor
ft ft kips kips kips kips/ft ksf s/ft
45.51 14.0 5.0 0.0 45.5 0.0 0.00 0.00 0.0002 21.0 12.0 0.0 45.5 0.0 0.00 0.00 0.0003 28.0 19.0 0.0 45.5 0.0 0.00 0.00 0.0004 35.0 26.0 0.9 44.6 0.9 0.13 0.06 0.0245 42.0 33.0 7.7 36.9 8.6 1.10 0.53 0.0246 49.0 40.0 15.8 21.1 24.4 2.26 1.08 0.024
Avg. Shaft 4.1 0.61 0.29 0.024
Toe 21.1 60.44 0.001
Soil Model Parameters/Extensions Shaft Toe
Quake (in) 0.148 0.148Case Damping Factor 0.031 0.001Unloading Quake (% of loading quake) 79 30Reloading Level (% of Ru) 100 100Unloading Level (% of Ru) 0Soil Plug Weight (kips) 0.32
CAPWAP match quality = 4.52 (Wave Up Match) ; RSA = 0Observed: final set = 0.500 in; blow count = 24 b/ftComputed: final set = 0.513 in; blow count = 23 b/ft
max. Top Comp. Stress = 1.0 ksi (T= 20.7 ms, max= 1.687 x Top)max. Comp. Stress = 1.7 ksi (Z= 49.0 ft, T= 24.5 ms)max. Tens. Stress = -0.05 ksi (Z= 28.0 ft, T= 35.0 ms)max. Energy (EMX) = 2.6 kip-ft; max. Measured Top Displ. (DMX)= 0.99 in
queens lake dam sanitary projec; Pile: Test Pile 3A Test: 01-Jan-2001 01:08:12" timber; Blow: 8 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 2 Analysis: 26-Oct-2016
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.No. Gages Stress Stress Energy
ft kips kips ksi ksi kip-ft ft/s in
1 3.5 110.8 -2.9 1.0 -0.03 2.57 6.3 0.7462 7.0 109.1 -2.5 1.0 -0.02 2.56 6.9 0.7413 10.5 107.4 -2.3 1.0 -0.02 2.55 7.0 0.7364 14.0 105.4 -5.0 1.0 -0.05 2.54 6.7 0.7315 17.5 103.2 -2.0 1.0 -0.02 2.53 6.6 0.7266 21.0 100.2 -1.9 1.0 -0.02 2.51 6.8 0.7217 24.5 97.0 -2.8 1.1 -0.03 2.49 6.9 0.7158 28.0 94.0 -4.5 1.1 -0.05 2.48 7.1 0.7079 31.5 91.1 -1.6 1.2 -0.02 2.46 7.3 0.69910 35.0 88.3 -1.3 1.2 -0.02 2.45 7.5 0.69111 38.5 85.1 -1.1 1.2 -0.02 2.39 7.7 0.68312 42.0 84.7 -1.3 1.3 -0.02 2.38 7.7 0.67513 45.5 91.2 -0.9 1.6 -0.01 1.96 7.8 0.66914 49.0 87.4 -1.2 1.7 -0.02 1.04 8.4 0.661
Absolute 49.0 1.7 (T = 24.5 ms) 28.0 -0.05 (T = 35.0 ms)
CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9RP 36.5 21.3 6.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0RX 82.4 78.5 74.7 70.8 67.0 63.2 59.3 55.5 51.6 47.8RU 36.5 21.3 6.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0
RAU = 5.2 (kips); RA2 = 1.1 (kips)
Current CAPWAP Ru = 45.5 (kips); Corresponding J(RP)= 0.00; matches RX9 within 5%
VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUSft/s ms kips kips kips in in in kip-ft kips
10.41 21.00 198.2 -10.2 128.1 0.988 0.499 0.500 1.3 20.3
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
0.00 113.10 2019.7 65.000 2.095 10.00 103.87 2019.7 65.000 2.095 20.00 95.03 2019.7 65.000 2.095 30.00 78.54 2019.7 65.000 2.095 40.00 63.62 2019.7 65.000 2.095 49.00 50.27 2019.7 65.000 2.095
queens lake dam sanitary projec; Pile: Test Pile 3A Test: 01-Jan-2001 01:08:12" timber; Blow: 8 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 3 Analysis: 26-Oct-2016
Toe Area 0.349 ft2
Segmnt Dist. Impedance Imped. Tension Compression Perim.Number B.G. Change Slack Eff. Slack Eff.
ft kips/ft/s % in in ft
1 3.50 19.04 0.00 0.000 0.000 -0.000 0.000 2.0952 7.00 18.23 0.00 0.000 0.000 -0.000 0.000 2.0953 10.50 17.68 0.00 0.000 0.000 -0.000 0.000 2.0954 14.00 17.15 0.00 0.000 0.000 -0.000 0.000 2.0955 17.50 16.63 0.00 0.000 0.000 -0.000 0.000 2.0956 21.00 16.09 0.00 0.000 0.000 -0.000 0.000 2.0957 24.50 15.24 0.00 0.000 0.000 -0.000 0.000 2.0958 28.00 14.26 0.00 0.000 0.000 -0.000 0.000 2.0959 31.50 13.30 0.00 0.000 0.000 -0.000 0.000 2.09510 35.00 12.41 0.00 0.000 0.000 -0.000 0.000 2.09511 38.50 11.53 0.00 0.000 0.000 -0.000 0.000 2.09512 42.00 10.65 0.00 0.000 0.000 -0.000 0.000 2.09513 45.50 9.77 0.00 0.000 0.000 -0.000 0.000 2.09514 49.00 8.90 0.00 0.000 0.000 -0.000 0.000 2.095
Pile Damping 2.0 %, Time Incr 0.292 ms, Wave Speed 12000.0 ft/s, 2L/c 8.2 ms
5 105
-100
0
100
200
ms
kips
16 L/c
Force MsdForce Cpt
5 105
-100
0
100
200
ms
kips
16 L/c
Force MsdVelocity Msd
Pile
0
1
2
3
4
kips
/ft
0
25
50
75
100
kips
Shaft ResistanceDistribution
Pile Forceat Ru
0 25 50 75 1000.000
0.250
0.500
0.750
1.000
Load (kips)
Dis
plac
emen
t (in
)
Pile TopBottom
Ru = 95.3 kipsRs = 81.3 kipsRb = 14.0 kipsDy = 0.71 inDx = 0.96 in
queens lake dam sanitary projec; Pile: Test Pile 4; 12" timber; Blow: 2 (Test: 01-Jan-2001 01:45:) 26-Oct-2016Schnabel Engineering CAPWAP(R) 2006-3
CAPWAP(R) 2006-3 Licensed to Schnabel Engineering
queens lake dam sanitary projec; Pile: Test Pile 4 Test: 01-Jan-2001 01:45:12" timber; Blow: 2 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 1 Analysis: 26-Oct-2016
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 95.3; along Shaft 81.3; at Toe 14.0 kips
Soil Dist. Depth Ru Force Sum Unit Unit Smith QuakeSgmnt Below Below in Pile of Resist. Resist. DampingNo. Gages Grade Ru (Depth) (Area) Factor
ft ft kips kips kips kips/ft ksf s/ft in
95.31 27.3 6.8 2.4 92.9 2.4 0.35 0.17 0.047 0.2792 34.2 13.7 6.1 86.8 8.5 0.89 0.43 0.047 0.2783 41.0 20.5 10.7 76.1 19.2 1.57 0.75 0.047 0.2784 47.8 27.3 21.2 54.9 40.4 3.10 1.48 0.047 0.2785 54.7 34.2 19.4 35.5 59.8 2.84 1.36 0.047 0.2686 61.5 41.0 21.5 14.0 81.3 3.15 1.50 0.047 0.241
Avg. Shaft 13.6 1.98 0.95 0.047 0.266
Toe 14.0 40.10 0.272 0.053
Soil Model Parameters/Extensions Shaft Toe
Case Damping Factor 0.202 0.200Damping Type SmithUnloading Quake (% of loading quake) 100 120Reloading Level (% of Ru) 100 100Unloading Level (% of Ru) 0Resistance Gap (included in Toe Quake) (in) 0.014Soil Plug Weight (kips) 0.04
CAPWAP match quality = 4.68 (Wave Up Match) ; RSA = 0Observed: final set = 0.250 in; blow count = 48 b/ftComputed: final set = 0.020 in; blow count = 605 b/ft
max. Top Comp. Stress = 1.6 ksi (T= 20.8 ms, max= 1.397 x Top)max. Comp. Stress = 2.2 ksi (Z= 47.8 ft, T= 24.5 ms)max. Tens. Stress = -0.03 ksi (Z= 61.5 ft, T= 50.7 ms)max. Energy (EMX) = 3.8 kip-ft; max. Measured Top Displ. (DMX)= 0.72 in
queens lake dam sanitary projec; Pile: Test Pile 4 Test: 01-Jan-2001 01:45:12" timber; Blow: 2 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 2 Analysis: 26-Oct-2016
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.No. Gages Stress Stress Energy
ft kips kips ksi ksi kip-ft ft/s in
1 3.4 175.7 0.0 1.6 0.00 3.77 10.5 0.6122 6.8 169.9 0.0 1.6 0.00 3.72 10.8 0.5983 10.3 164.4 0.0 1.7 0.00 3.67 11.0 0.5824 13.7 158.9 0.0 1.7 0.00 3.59 11.3 0.5625 17.1 154.3 0.0 1.8 0.00 3.49 11.6 0.5396 20.5 151.0 0.0 1.9 0.00 3.41 11.8 0.5177 23.9 148.5 0.0 1.9 0.00 3.33 11.9 0.4958 27.3 146.3 0.0 2.0 0.00 3.23 12.0 0.4709 30.8 142.4 0.0 2.0 0.00 3.04 12.1 0.44410 34.2 141.1 0.0 2.0 0.00 2.93 12.1 0.41611 37.6 134.8 0.0 2.0 0.00 2.66 12.1 0.39212 41.0 134.6 0.0 2.1 0.00 2.58 12.1 0.36713 44.4 126.4 0.0 2.0 0.00 2.22 11.9 0.34314 47.8 128.9 0.0 2.2 0.00 2.14 11.6 0.31715 51.3 112.9 0.0 2.0 0.00 1.65 11.4 0.29716 54.7 114.5 0.0 2.1 0.00 1.61 11.2 0.27917 58.1 90.3 -0.9 1.7 -0.02 1.31 12.1 0.26718 61.5 86.4 -1.6 1.7 -0.03 1.04 12.5 0.255
Absolute 47.8 2.2 (T = 24.5 ms) 61.5 -0.03 (T = 50.7 ms)
CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9RP 171.0 154.5 138.0 121.5 104.9 88.4 71.9 55.4 38.8 22.3RX 171.0 154.5 139.9 138.7 137.5 136.3 135.4 135.4 135.4 135.4RU 171.0 154.5 138.0 121.5 104.9 88.4 71.9 55.4 38.8 22.3
RAU = 91.3 (kips); RA2 = 100.6 (kips)
Current CAPWAP Ru = 95.3 (kips); Corresponding J(RP)= 0.46;
RMX requires higher damping; see PDA-W
VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUSft/s ms kips kips kips in in in kip-ft kips
10.41 20.78 198.3 138.0 201.0 0.719 0.250 0.250 3.2 79.5
queens lake dam sanitary projec; Pile: Test Pile 4 Test: 01-Jan-2001 01:45:12" timber; Blow: 2 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 3 Analysis: 26-Oct-2016
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
0.00 113.10 2019.7 65.000 2.095 10.00 95.03 2019.7 65.000 2.095 20.00 78.54 2019.7 65.000 2.095 30.00 70.88 2019.7 65.000 2.095 40.00 63.62 2019.7 65.000 2.095 50.00 56.75 2019.7 65.000 2.095 61.50 50.27 2019.7 65.000 2.095
Toe Area 0.349 ft2
Segmnt Dist. Impedance Imped. Tension Compression Perim.Number B.G. Change Slack Eff. Slack Eff.
ft kips/ft/s % in in ft
1 3.42 19.04 0.00 0.000 0.000 -0.000 0.000 2.0952 6.83 17.48 0.00 0.000 0.000 -0.000 0.000 2.0953 10.25 16.44 0.00 0.000 0.000 -0.000 0.000 2.0954 13.67 15.45 0.00 0.000 0.000 -0.000 0.000 2.0955 17.08 14.51 0.00 0.000 0.000 -0.000 0.000 2.0956 20.50 13.56 0.00 0.000 0.000 -0.000 0.000 2.0957 23.92 12.94 0.00 0.000 0.000 -0.000 0.000 2.0958 27.33 12.50 0.00 0.000 0.000 -0.000 0.000 2.0959 30.75 12.06 0.00 0.000 0.000 -0.000 0.000 2.09510 34.17 11.63 0.00 0.000 0.000 -0.000 0.000 2.09511 37.58 11.21 0.00 0.000 0.000 -0.000 0.000 2.09512 41.00 10.80 0.00 0.000 0.000 -0.000 0.000 2.09513 44.42 10.40 0.00 0.000 0.000 -0.000 0.000 2.09514 47.83 10.00 0.00 0.000 0.000 -0.000 0.000 2.09515 51.25 9.61 0.00 0.000 0.000 -0.000 0.000 2.09516 54.67 9.27 0.00 0.000 0.000 -0.000 0.000 2.09517 58.08 8.95 0.00 0.000 0.000 -0.000 0.000 2.09518 61.50 8.63 0.00 0.000 0.000 -0.000 0.000 2.095
Pile Damping 2.0 %, Time Incr 0.285 ms, Wave Speed 12000.0 ft/s, 2L/c 10.3 ms
5 185
-60
0
60
120
ms
kips
42 L/c
Force MsdForce Cpt
5 185
-60
0
60
120
ms
kips
42 L/c
Force MsdVelocity Msd
Pile
0
1
2
3
4
kips
/ft
0
20
40
60
80
kips
Shaft ResistanceDistribution
Pile Forceat Ru
0 20 40 60 800.000
0.400
0.800
1.200
1.600
Load (kips)
Dis
plac
emen
t (in
)
Pile TopBottom
Ru = 76.3 kipsRs = 29.8 kipsRb = 46.5 kipsDy = 0.98 inDx = 1.17 in
queens lake dam sanitary projec; Pile: Test Pile 5; 12" timber; Blow: 1 (Test: 01-Jan-2001 02:05:) 26-Oct-2016Schnabel Engineering CAPWAP(R) 2006-3
CAPWAP(R) 2006-3 Licensed to Schnabel Engineering
queens lake dam sanitary projec; Pile: Test Pile 5 Test: 01-Jan-2001 02:05:12" timber; Blow: 1 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 1 Analysis: 26-Oct-2016
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 76.3; along Shaft 29.8; at Toe 46.5 kips
Soil Dist. Depth Ru Force Sum Unit Unit Smith QuakeSgmnt Below Below in Pile of Resist. Resist. DampingNo. Gages Grade Ru (Depth) (Area) Factor
ft ft kips kips kips kips/ft ksf s/ft in
76.31 17.3 2.3 0.0 76.3 0.0 0.00 0.00 0.000 0.1102 24.2 9.2 0.7 75.6 0.7 0.10 0.05 0.160 0.1103 31.2 16.2 4.8 70.8 5.5 0.69 0.33 0.160 0.1104 38.1 23.1 10.2 60.6 15.7 1.47 0.70 0.160 0.1105 45.0 30.0 14.1 46.5 29.8 2.04 0.97 0.160 0.102
Avg. Shaft 6.0 0.99 0.47 0.160 0.106
Toe 46.5 133.20 0.047 0.547
Soil Model Parameters/Extensions Shaft Toe
Case Damping Factor 0.250 0.114Damping Type SmithUnloading Quake (% of loading quake) 30 100Reloading Level (% of Ru) 100 100Resistance Gap (included in Toe Quake) (in) 0.000Soil Plug Weight (kips) 0.06
CAPWAP match quality = 3.70 (Wave Up Match) ; RSA = 0Observed: final set = 0.200 in; blow count = 60 b/ftComputed: final set = 0.178 in; blow count = 67 b/ftReplay Factor: F3:1.000; V3:1.000; V4:1.000;
max. Top Comp. Stress = 0.7 ksi (T= 28.0 ms, max= 1.780 x Top)max. Comp. Stress = 1.3 ksi (Z= 38.1 ft, T= 38.4 ms)max. Tens. Stress = -0.37 ksi (Z= 31.2 ft, T= 122.0 ms)max. Energy (EMX) = 3.9 kip-ft; max. Measured Top Displ. (DMX)= 0.80 in
queens lake dam sanitary projec; Pile: Test Pile 5 Test: 01-Jan-2001 02:05:12" timber; Blow: 1 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 2 Analysis: 26-Oct-2016
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.No. Gages Stress Stress Energy
ft kips kips ksi ksi kip-ft ft/s in
1 3.5 84.5 -23.5 0.7 -0.21 3.90 5.4 0.7912 6.9 82.8 -23.6 0.8 -0.23 3.87 5.4 0.7783 10.4 81.2 -23.6 0.8 -0.24 3.83 5.3 0.7644 13.8 82.2 -23.6 0.9 -0.26 3.78 5.3 0.7485 17.3 83.1 -23.7 1.0 -0.28 3.74 5.2 0.7326 20.8 80.3 -23.9 1.0 -0.30 3.68 5.5 0.7137 24.2 76.9 -24.1 1.0 -0.32 3.65 5.8 0.6938 27.7 78.1 -23.5 1.1 -0.34 3.54 6.0 0.6729 31.2 80.1 -23.6 1.2 -0.37 3.54 5.8 0.64710 34.6 75.2 -19.0 1.2 -0.31 2.98 5.4 0.62411 38.1 77.1 -19.0 1.3 -0.33 2.91 5.3 0.59912 41.5 64.3 -9.4 1.2 -0.17 2.17 5.6 0.57713 45.0 63.7 -9.5 1.2 -0.18 1.23 6.0 0.553
Absolute 38.1 1.3 (T = 38.4 ms) 31.2 -0.37 (T = 122.0 ms)
CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9RP 76.0 66.1 56.2 46.4 36.5 26.6 16.8 6.9 0.0 0.0RX 100.1 95.8 92.1 88.5 86.9 86.9 86.9 86.9 86.9 86.9RU 76.0 66.1 56.2 46.4 36.5 26.6 16.8 6.9 0.0 0.0
RAU = 78.5 (kips); RA2 = 86.0 (kips)
Current CAPWAP Ru = 76.3 (kips); Corresponding J(RP)= 0.00;
RMX requires higher damping; see PDA-W
VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUSft/s ms kips kips kips in in in kip-ft kips
5.66 27.69 107.8 66.9 82.0 0.803 0.200 0.200 3.9 93.4
Possible Pile Damage at 0.16 L Below Gages?
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
0.00 113.07 2019.7 65.000 2.095 10.00 95.03 2019.7 65.000 2.095 20.00 78.54 2019.7 65.000 2.095 30.00 63.62 2019.7 65.000 2.095
queens lake dam sanitary projec; Pile: Test Pile 5 Test: 01-Jan-2001 02:05:12" timber; Blow: 1 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 3 Analysis: 26-Oct-2016
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
45.00 50.27 2019.7 65.000 2.095
Toe Area 0.349 ft2
Segmnt Dist. Impedance Imped. Tension Compression Perim.Number B.G. Change Slack Eff. Slack Eff.
ft kips/ft/s % in in ft
1 3.46 19.04 0.00 0.000 0.000 -0.000 0.000 2.0952 6.92 17.46 0.00 0.000 0.000 -0.000 0.000 2.0953 10.38 16.41 0.00 0.000 0.000 -0.000 0.000 2.0954 13.85 15.41 0.00 0.000 0.000 -0.000 0.000 2.0955 17.31 14.45 0.00 0.000 0.000 -0.000 0.000 2.0956 20.77 13.49 0.00 0.000 0.000 -0.000 0.000 2.0957 24.23 12.59 0.00 0.000 0.000 -0.000 0.000 2.0958 27.69 11.73 0.00 0.000 0.000 -0.000 0.000 2.0959 31.15 10.88 0.00 0.000 0.000 -0.000 0.000 2.09510 34.62 10.28 0.00 0.000 0.000 -0.000 0.000 2.09511 38.08 9.76 0.00 0.000 0.000 -0.000 0.000 2.09512 41.54 9.24 0.00 0.000 0.000 -0.000 0.000 2.09513 45.00 8.72 0.00 0.000 0.000 -0.000 0.000 2.095
Pile Damping 1.0 %, Time Incr 0.288 ms, Wave Speed 12000.0 ft/s, 2L/c 7.5 ms
5 185
-60
0
60
120
ms
kips
42 L/c
Force MsdForce Cpt
5 185
-60
0
60
120
ms
kips
42 L/c
Force MsdVelocity Msd
Pile
0
1
2
3
4
kips
/ft
0
20
40
60
80
kips
Shaft ResistanceDistribution
Pile Forceat Ru
0 20 40 60 800.000
0.400
0.800
1.200
1.600
Load (kips)
Dis
plac
emen
t (in
)
Pile TopBottom
Ru = 76.7 kipsRs = 31.8 kipsRb = 44.9 kipsDy = 1.01 inDx = 1.21 in
queens lake dam sanitary projec; Pile: Test Pile 6; 12" timber; Blow: 1 (Test: 01-Jan-2001 02:05:) 26-Oct-2016Schnabel Engineering CAPWAP(R) 2006-3
CAPWAP(R) 2006-3 Licensed to Schnabel Engineering
queens lake dam sanitary projec; Pile: Test Pile 6 Test: 01-Jan-2001 02:05:12" timber; Blow: 1 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 1 Analysis: 26-Oct-2016
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 76.7; along Shaft 31.8; at Toe 44.9 kips
Soil Dist. Depth Ru Force Sum Unit Unit Smith QuakeSgmnt Below Below in Pile of Resist. Resist. DampingNo. Gages Grade Ru (Depth) (Area) Factor
ft ft kips kips kips kips/ft ksf s/ft in
76.71 17.3 2.3 0.8 75.9 0.8 0.35 0.17 0.139 0.2122 24.2 9.2 1.4 74.5 2.2 0.20 0.10 0.139 0.2123 31.2 16.2 4.0 70.5 6.2 0.58 0.28 0.139 0.2124 38.1 23.1 9.8 60.7 16.0 1.42 0.68 0.139 0.2125 45.0 30.0 15.8 44.9 31.8 2.28 1.09 0.139 0.197
Avg. Shaft 6.4 1.06 0.51 0.139 0.204
Toe 44.9 128.62 0.035 0.572
Soil Model Parameters/Extensions Shaft Toe
Case Damping Factor 0.232 0.083Damping Type SmithUnloading Quake (% of loading quake) 40 100Reloading Level (% of Ru) 100 100Unloading Level (% of Ru) 87Soil Plug Weight (kips) 0.24
CAPWAP match quality = 4.07 (Wave Up Match) ; RSA = 0Observed: final set = 0.200 in; blow count = 60 b/ftComputed: final set = 0.162 in; blow count = 74 b/ftReplay Factor: F3:1.000; V3:1.000; V4:1.000;
max. Top Comp. Stress = 0.7 ksi (T= 28.0 ms, max= 1.786 x Top)max. Comp. Stress = 1.3 ksi (Z= 38.1 ft, T= 38.4 ms)max. Tens. Stress = -0.34 ksi (Z= 31.2 ft, T= 122.3 ms)max. Energy (EMX) = 3.9 kip-ft; max. Measured Top Displ. (DMX)= 0.80 in
queens lake dam sanitary projec; Pile: Test Pile 6 Test: 01-Jan-2001 02:05:12" timber; Blow: 1 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 2 Analysis: 26-Oct-2016
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.No. Gages Stress Stress Energy
ft kips kips ksi ksi kip-ft ft/s in
1 3.5 82.6 -23.3 0.7 -0.21 3.92 5.5 0.8172 6.9 80.8 -23.4 0.8 -0.23 3.88 5.5 0.8043 10.4 79.1 -23.5 0.8 -0.24 3.84 5.5 0.7904 13.8 79.3 -23.5 0.9 -0.26 3.80 5.4 0.7745 17.3 84.2 -23.5 1.0 -0.27 3.75 5.3 0.7586 20.8 84.7 -22.8 1.1 -0.28 3.64 5.4 0.7407 24.2 82.6 -22.9 1.1 -0.31 3.58 5.5 0.7218 27.7 75.8 -21.7 1.1 -0.31 3.41 5.9 0.7009 31.2 75.7 -21.9 1.2 -0.34 3.34 6.2 0.67710 34.6 73.7 -18.6 1.2 -0.30 2.98 6.1 0.65311 38.1 75.7 -18.7 1.3 -0.32 2.90 5.5 0.62812 41.5 63.9 -10.5 1.2 -0.19 2.22 5.5 0.60513 45.0 65.3 -10.6 1.3 -0.20 1.22 6.0 0.582
Absolute 38.1 1.3 (T = 38.4 ms) 31.2 -0.34 (T = 122.3 ms)
CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9RP 76.0 66.1 56.2 46.4 36.5 26.6 16.8 6.9 0.0 0.0RX 100.1 95.8 92.1 88.5 86.9 86.9 86.9 86.9 86.9 86.9RU 76.0 66.1 56.2 46.4 36.5 26.6 16.8 6.9 0.0 0.0
RAU = 78.5 (kips); RA2 = 86.0 (kips)
Current CAPWAP Ru = 76.7 (kips); Corresponding J(RP)= 0.00;
RMX requires higher damping; see PDA-W
VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUSft/s ms kips kips kips in in in kip-ft kips
5.66 27.69 107.8 66.9 82.0 0.803 0.200 0.200 3.9 93.4
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.ft in2 ksi lb/ft3 ft
0.00 113.07 2019.7 65.000 2.095 10.00 95.03 2019.7 65.000 2.095 20.00 78.54 2019.7 65.000 2.095 30.00 63.62 2019.7 65.000 2.095 45.00 50.27 2019.7 65.000 2.095
Toe Area 0.349 ft2
queens lake dam sanitary projec; Pile: Test Pile 6 Test: 01-Jan-2001 02:05:12" timber; Blow: 1 CAPWAP(R) 2006-3Schnabel Engineering OP: D. Smith,PE
Page 3 Analysis: 26-Oct-2016
Segmnt Dist. Impedance Imped. Tension Compression Perim.Number B.G. Change Slack Eff. Slack Eff.
ft kips/ft/s % in in ft
1 3.46 19.04 0.00 0.000 0.000 -0.000 0.000 2.0952 6.92 17.46 0.00 0.000 0.000 -0.000 0.000 2.0953 10.38 16.41 0.00 0.000 0.000 -0.000 0.000 2.0954 13.85 15.41 0.00 0.000 0.000 -0.000 0.000 2.0955 17.31 14.45 0.00 0.000 0.000 -0.000 0.000 2.0956 20.77 13.49 0.00 0.000 0.000 -0.000 0.000 2.0957 24.23 12.59 0.00 0.000 0.000 -0.000 0.000 2.0958 27.69 11.73 0.00 0.000 0.000 -0.000 0.000 2.0959 31.15 10.88 0.00 0.000 0.000 -0.000 0.000 2.09510 34.62 10.28 0.00 0.000 0.000 -0.000 0.000 2.09511 38.08 9.76 0.00 0.000 0.000 -0.000 0.000 2.09512 41.54 9.24 0.00 0.000 0.000 -0.000 0.000 2.09513 45.00 8.72 0.00 0.000 0.000 -0.000 0.000 2.095
Pile Damping 1.0 %, Time Incr 0.288 ms, Wave Speed 12000.0 ft/s, 2L/c 7.5 ms
October 27, 2016 Schnabel Engineering, LLC Project 16C33018 @2016 All Rights Reserved
APPENDIX B
TEST PILE LOGS
Job No.Project Name:Contractor:Inspector:
Hammer Type: Pile Location: 7Hammer Energy: Date Driven: 4:07 P Stop: 4:13 PM
Pile Type & Size:Design Capacity: (tons)Pile Length: (ft)Pile Batter:
Plumbness: (%)(%)
Date: 10/24Inch Blows
1 32 23 14 1567891011121314151617181920212223
Pile Driving Log
Sequence:Start:
Depth Blows Depth Blows Depth Blows
Ice 8v2- Single Action
1Depth Blows
26 51Depth Blows
76 1012 27 52 77 1023 28 53 78 1034 W.O.H. 29 54 79 1045 30 55 80 1056 31 56 81 1067 32 57 82 1078 33 58 83 1089 34 59 84 10910 35 60 85 11011 36 61 86 11112 37 62 87 11213 38 63 88 11314 39 64 89 11415 40 65 90 11516 41 66 91 11617 42 67 92 11718 43 68 93 11819 44 69 94 11920 45 70 95 12021 2 46 71 96 12122 5 47 72 97 12223 5 48 73 98 12324 5 49 74 99 12425 5 50 75 100
Remarks:
Restrike Data
125
10/20/16(ft-lbs)17,600TP-1
16C33018.00Queens Lake Sanitary Sewer ProjectWaterfront Design & Construction/ J. Sanders Constru D. Smith, PE
N/S Ground Surface EL: 4
8" tip timber1250
Design12.75-34 -34
End of Initial Final
E/W Blowcount Reference EL: 9
Top of PileTip Grade
24
Job No.Project Name:Contractor:Inspector:
Hammer Type: Pile Location: 6Hammer Energy: Date Driven: 4:07 P Stop: 4:13 PM
Pile Type & Size:Design Capacity: (tons)Pile Length: (ft)Pile Batter:
Plumbness: (%)(%)
Date: 10/24Inch Blows
1 22 23 14567891011121314151617181920212223
E/W Blowcount Reference EL: 9
Top of PileTip Grade
2712.75-38
End of Initial Final
-38
N/S Ground Surface EL:
8" tip timber1265
Design
16C33018.00Queens Lake Sanitary Sewer ProjectWaterfront Design & Construction/ J. Sanders Constru D. Smith, PE
10/20/16(ft-lbs)17,600TP-2
Restrike Data
125
Remarks:
12425 2 50 75 100
12324 49 74 99
12223 48 73 98
12122 47 15 72 97
12021 46 15 71 96
11920 45 15 70 95
11819 44 15 69 94
11718 43 14 68 93
11617 42 11 67 92
11516 41 11 66 91
11415 40 10 65 90
11314 39 12 64 89
11213 38 8 63 88
11112 37 8 62 87
11011 36 7 61 86
10910 35 5 60 85
1089 34 5 59 84
1078 33 4 58 83
1067 32 2 57 82
1056 31 1 56 81
1045 30 1 55 80
1034 W.O.H. 29 5 54 79
1023 28 5 53 78
1012 27 5 52 77
51Depth Blows
761Depth Blows
26 1
Pile Driving Log
Sequence:Start:
Depth Blows Depth Blows Depth Blows
Ice 8v2- Single Action
Job No.Project Name:Contractor:Inspector:
Hammer Type: Pile Location: 4Hammer Energy: Date Driven: 11:56 AStop: 12:06
Pile Type & Size:Design Capacity: (tons)Pile Length: (ft)Pile Batter:
Plumbness: (%)(%)
Date: 10/24/16Inch Blows
1 42 33 24567891011121314151617181920212223
E/W Blowcount Reference EL: 9
Top of PileTip Grade
1912.75-46
End of Initial Final
-46
N/S Ground Surface EL: 4
8" tip timber1265
Design
16C33018.00Queens Lake Sanitary Sewer ProjectWaterfront Design & Construction/ J. Sanders Constru R. Rountree
10/19/16(ft-lbs)17,600TP-3
Restrike Data
125
Remarks:
12425 50 6 75 100
12324 49 5 74 99
12223 48 8 73 98
12122 47 9 72 97
12021 46 9 71 96
11920 45 6 70 95
11819 44 4 69 94
11718 43 4 68 93
11617 42 4 67 92
11516 41 5 66 91
11415 40 4 65 90
11314 39 2 64 89
11213 38 2 63 88
11112 37 2 62 87
11011 36 4 61 86
10910 35 4 60 85
1089 34 59 84
1078 33 58 83
1067 32 57 82
1056 31 56 81
1045 30 55 7 80
1034 29 54 7 79
1023 28 53 6 78
1012 27 52 7 77
51 6Depth Blows
761Depth Blows
26
Pile Driving Log
Sequence:Start:
Depth Blows Depth Blows Depth Blows
Ice 8v2- Single Action
Job No.Project Name:Contractor:Inspector:
Hammer Type: Pile Location: 5Hammer Energy: Date Driven: 4:07 P Stop: 4:14 PM
Pile Type & Size:Design Capacity: (tons)Pile Length: (ft)Pile Batter:
Plumbness: (%)(%)
Date: 10/24Inch Blows
1 22 13 14 1567891011121314151617181920212223
Pile Driving Log
Sequence:Start:
Depth Blows Depth Blows Depth Blows
Ice 8v2- Single Action
1Depth Blows
26 51Depth Blows
76 1012 27 52 77 1023 28 53 78 1034 29 54 79 1045 30 55 80 1056 31 56 81 1067 32 57 82 1078 33 58 83 1089 34 59 84 10910 35 60 85 11011 36 61 86 11112 37 62 87 11213 38 63 88 11314 39 64 89 11415 40 65 90 11516 41 2 66 91 11617 42 2 67 92 11718 43 2 68 93 11819 44 69 94 11920 45 70 95 12021 46 71 96 12122 47 72 97 12223 48 73 98 12324 49 74 99 12425 50 75 100
Remarks:
Restrike Data
125
10/19/16(ft-lbs)17,600TP-3A
16C33018.00Queens Lake Sanitary Sewer ProjectWaterfront Design & Construction/ J. Sanders Constru R. Rountree
N/S Ground Surface EL: 4
8" tip timber1250
Design12.75-34 -34
End of Initial Final
E/W Blowcount Reference EL: 9
Top of PileTip Grade
16
Job No.Project Name:Contractor:Inspector:
Hammer Type: Pile Location: 3Hammer Energy: Date Driven: 9:46 A Stop: 9:58 AM
Pile Type & Size:Design Capacity: (tons)Pile Length: (ft)Pile Batter:
Plumbness: (%)(%)
Date: 10/24Inch Blows
1 42 23 14 1567891011121314151617181920212223
Pile Driving Log
Sequence:Start:
Depth Blows Depth Blows Depth Blows
Ice 8v2- Single Action
1Depth Blows
26 51Depth Blows
76 1012 27 1 52 77 1023 28 1 53 78 1034 29 3 54 79 1045 30 6 55 80 1056 31 4 56 81 1067 32 5 57 82 1078 33 4 58 83 1089 34 4 59 84 10910 35 6 60 85 11011 36 6 61 86 11112 37 7 62 87 11213 38 10 63 88 11314 39 10 64 89 11415 40 12 65 90 11516 41 12 66 91 11617 42 11 67 92 11718 43 11 68 93 11819 44 11 69 94 11920 45 12 70 95 12021 46 13 71 96 12122 47 13 72 97 12223 48 13 73 98 12324 49 11 74 99 12425 50 11 75 100
Remarks:
Restrike Data
125
10/19/16(ft-lbs)17,600TP-4
16C33018.00Queens Lake Sanitary Sewer ProjectWaterfront Design & Construction/ J. Sanders Constru R. Rountree
N/S Ground Surface EL: 4
8" tip timber1260
Design12.75-41 -41
End of Initial Final
E/W Blowcount Reference EL: 9
Top of PileTip Grade
19
Job No.Project Name:Contractor:Inspector:
Hammer Type: Pile Location: 2Hammer Energy: Date Driven: 11:59 AStop: 12:06 PM
Pile Type & Size:Design Capacity: (tons)Pile Length: (ft)Pile Batter:
Plumbness: (%)(%)
Date: 10/24Inch Blows
1 32 23 24 1567891011121314151617181920212223
E/W Blowcount Reference EL: 9
Top of PileTip Grade
2012.75-30
End of Initial Final
-30
N/S Ground Surface EL: 4
8" tip timber1250
Design
16C33018.00Queens Lake Sanitary Sewer ProjectWaterfront Design & Construction/ J. Sanders Constru R. Rountree
10/18/16(ft-lbs)17,600TP-5
Restrike Data
125
Remarks:
12425 3 50 75 100
12324 1 49 74 99
12223 2 48 73 98
12122 1 47 72 97
12021 1 46 71 96
11920 45 70 95
11819 44 69 94
11718 43 68 93
11617 42 67 92
11516 41 66 91
11415 40 65 90
11314 39 64 89
11213 38 16 63 88
11112 37 15 62 87
11011 36 14 61 86
10910 35 9 60 85
1089 34 11 59 84
1078 33 10 58 83
1067 32 5 57 82
1056 31 4 56 81
1045 30 4 55 80
1034 W.O.H. 29 5 54 79
1023 28 7 53 78
1012 27 7 52 77
51Depth Blows
761Depth Blows
26 7
Pile Driving Log
Sequence:Start:
Depth Blows Depth Blows Depth Blows
Ice 8v2- Single Action
Job No.Project Name:Contractor:Inspector:
Hammer Type: Pile Location: 1Hammer Energy: Date Driven: 11:59 AStop: 12:06 PM
Pile Type & Size:Design Capacity: (tons)Pile Length: (ft)Pile Batter:
Plumbness: (%)(%)
Date: 10/24Inch Blows
1 42 33 24567891011121314151617181920212223
Pile Driving Log
Sequence:Start:
Depth Blows Depth Blows Depth Blows
Ice 8v2- Single Action
1Depth Blows
26 12 51Depth Blows
76 1012 27 12 52 77 1023 28 13 53 78 1034 W.O.H. 29 14 54 79 1045 30 18 55 80 1056 31 18 56 81 1067 32 15 57 82 1078 33 16 58 83 1089 34 13 59 84 10910 35 14 60 85 11011 36 16 61 86 11112 37 25 62 87 11213 38 31 63 88 11314 39 36 64 89 11415 40 28 65 90 11516 41 32 66 91 11617 42 35 67 92 11718 43 68 93 11819 44 69 94 11920 1 45 70 95 12021 1 46 71 96 12122 1 47 72 97 12223 2 48 73 98 12324 4 49 74 99 12425 11 50 75 100
Remarks:
Restrike Data
125
10/18/16(ft-lbs)17,600TP-5
16C33018.00Queens Lake Sanitary Sewer ProjectWaterfront Design & Construction/ J. Sanders Constru R. Rountree
N/S Ground Surface EL: 4
8" tip timber2050
Design12.75-30 -30
End of Initial Final
E/W Blowcount Reference EL: 9
Top of PileTip Grade
20