Dyckman Avenueover Black River:A Movable Bridge
RehabilitationSouth Haven, Michigan
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 1
• Project Location
• History
• Condition Assessment
• Funding
• Design
• Construction
• Acknowledgements
• Questions
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 2
Summary of Presentation
Location of South Haven, Michigan
Project Location
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 3
Location of Dyckman Ave Bridge
Project Location
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 4
• Four Movable Bridges at Dyckman Avenue
crossing of the Black River
• First Bridge constructed in 1856
• Construction cost was $1,120
• Timber drawbridge
• Second Bridge constructed in 1877
• Timber drawbridge
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 5
History
• Third Bridge constructed in 1890
• Steel through Truss Swing Bridge
• In service for 78 years
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 6
History
• Current Bridge constructed in 1967-68
• Designed by State Highway Department
• Cost of Construction was $782,157
• Double Bascule Span
• Hydraulic Cylinders as Prime Mover
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 7
History
General Plan of Structure
History
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 8
Approach Span Construction
History
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 9
Bascule Span Installation
History
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 10
• Identify Scope of Rehabilitation Needs
• Review 1993 Repairs
• Work Started in 2007
• Efforts Continued through 2010
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 11
Condition Assessment
Concrete Deck
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 12
Traffic Gate Operator
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 13
Bascule Span Sidewalk
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 14
Bascule Span Deck Grating
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 15
Floor Beams
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 16
Main Cylinder
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 17
Brake Cylinder
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 18
Position Sensor
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 19
Tail Bearing
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 20
Hydraulic Power Unit
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 21
Hydraulic Controls
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 22
Hydraulic Control Tubing
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 23
Submarine Cables
Condition Assessment
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 24
• Concrete Deck Overlay
• Riveted Steel Grid Deck and Floor Beams
• Non-skid Steel Plate Sidewalks
• Submarine Cables
• Hydraulic Cylinders, Power Units, and Controls
• Scour Countermeasures
• Shimming and Balancing
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 25
Condition Assessment
• Local Bridge Program Application Submitted in 2009, 2010, and 2011
• Regional Bridge Council Commitment
• Movable Bridges considered Major Structures
• Selected for Funding in 2014 FY
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 26
Funding
• Total Construction Cost - $2,498,500
• Local Bridge Program - $1,573,200
• Small Urban Program - $375,000
• Local Funding - $550,300
• Engineering Fees - $607,500
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 27
Funding
• Great Lakes Engineering Group, LLC – Underwater Inspection/Scour Mitigation
• Hardesty & Hanover – Structural, Mechanical & Electrical Engineering
• City Staff – Traffic Control Plan
• Spicer Group – Construction Observation & Administration
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 28
Design Phase
Open Steel Grid Decking
Design Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 29
Non-skid Steel Plate Sidewalks
Design Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 30
Hydraulic Schematic
Design Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 31
Electric Schematic
Design Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 32
• 2014-15 Winter Construction
• Construction started October 13, 2014
• Completion date of April 30, 2015
• Long Lead Time Items: Hydraulic Cylinders and Open Steel Grid Decking
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 33
Construction Phase
Deck Removals
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 34
New Floor Beams
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 35
Steel Curb Beam
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 36
Open Steel Deck Grid
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 37
Open Steel Grid Deck
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 38
Non-skid Steel Plate Sidewalks
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 39
Submarine Cable
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 40
Submarine Cable
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 41
Hydraulic Power Unit
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 42
Hydraulic Control Valves
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 43
Programmable Logic Controller
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 44
Main Hydraulic Cylinder
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 45
Tail Lock Cylinder
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 46
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 47
Video of Opening
Construction Phase
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 48
• MDOT Staff
• RBC and LBAB Volunteers
• Consultants
• Contractor (Anlaan Corporation)
• Citizens of South Haven
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 49
Acknowledgements
March 23, 2016Dyckman Avenue Bascule Bridge Rehabilitation 2014-15 50
Questions