Click here to load reader

DUSN Prototype Initial Field Testsonnor’s Diving boat used for personnel and equipment transportation will be employed as the tow/dip vessel for a hand-held (BATS) acoustic source

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • DUSN Prototype Initial Field Tests

    Garry Heard DRDC – Atlantic Research Centre

    Defence Research and Development Canada

    Reference Document

    DRDC-RDDC-2017-D034 May 2017

  • Template in use: (2010) SR Advanced Template_EN (051115).dotm

    © Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

    © Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale,

    2017

  • DRDC-RDDC-2017-D034 i

    Abstract

    The Distributed Undersea Sensor Network (DUSN) is a component of the Force ASW project.

    DUSN consists of research directed toward the implementation of autonomous UW networked

    ASW sensors. Included in the project is an international agreement with Norway and Sweden,

    which is also called DUSN.

    The DUSN project is attempting to create useful sized networks of ASW sensors and therefore

    DRDC is building a dozen DUSN nodes. These nodes, when combined with nodes from the other

    countries, will form a network that is just large enough to begin to demonstrate network issues;

    both positive and negative influences on performance. These nodes have UW acoustic

    communications, on-board detection and processing, and will allow for the development of UW

    network protocols and signal processing algorithms.

    The first Canadian prototype DUSN node is nearing completion and must under-go a series of

    engineering tests before full investment in the remaining eleven units is undertaken. This Bedford

    Basin Barge Trial is intended as the first engineering trial for the prototype sensor node.

  • ii DRDC-RDDC-2017-D034

    Résumé

    Le réseau de distribution de capteurs sous-marins (RDCS) est un élément du projet de guerre

    anti-sous-marine (GASM) de la force. Le RDCS comprend la recherche orientée vers la mise en

    œuvre de capteurs de GASM autonomes sous-marins en réseau. Le projet comprend également

    une entente internationale avec la Norvège et la Suède, également appelée RDCS.

    Dans le cadre du projet RDCS, on cherche à créer des réseaux de capteurs de GASM de taille

    utile. C’est pourquoi RDDC est en train de construire une dizaine de nœuds de RDCS. Lorsqu’ils

    seront conjugués à ceux d’autres pays, ces nœuds constitueront un réseau juste assez grand pour

    pouvoir démontrer les problèmes qu’il peut occasionner, leur influence positive et négative sur le

    rendement. Ces nœuds permettront d’établir des communications acoustiques sous-marines, et de

    procéder à la détection et au traitement embarqués. Ils permettront également d’élaborer de

    nouveaux protocoles de réseaux sous-marins et de nouveaux algorithmes de traitement du signal.

    Le premier prototype canadien de nœud de RDCS est presque achevé et doit faire l’objet d’une

    série d’essais techniques avant que la totalité des fonds soit consacrée aux onze nœuds restants.

    L’essai sur la barge dans le bassin de Bedford devrait être le premier essai technique du prototype

    de nœud de capteurs.

  • Project FASW 01CA03

    DUSN Prototype Initial Field Tests

    Aug 2016

    DRDC Atlantic File: 4118-02

    OPI: Heard, Garry

    Underwater Sensing Section

    DRDC Atlantic Research Centre

    902-426-3100 x310

    [email protected]

    PM: Adrian Hewitt

    V2016.08.18

  • DUSN Prototype Initial Field Tests

    Chief Scientist: Dr. Garry J. Heard [email protected]

    Project Manager: Adrian Hewitt [email protected]

    Overview The Distributed Undersea Sensor Network (DUSN) is a component of the Force ASW project. DUSN

    consists of research directed toward the implementation of autonomous UW networked ASW sensors.

    Included in the project is an international agreement with Norway and Sweden, which is also, called

    DUSN.

    The DUSN project is attempting to create useful sized networks of ASW sensors and therefore DRDC is

    building a dozen-DUSN nodes. These nodes when combined with nodes from the other countries will

    form a network that is just large enough to begin to demonstrate network issues; both positive and

    negative influences on performance. These nodes have UW acoustic communications, on-board

    detection and processing, and will allow for the development of UW network protocols and signal

    processing algorithms.

    The first Canadian prototype DUSN node is nearing completion and must under-go a series of

    engineering tests before full investment in the remaining eleven units is undertaken. This Bedford Basin

    Barge Trial is intended as the first engineering trial for the prototype sensor node.

    Participation DRDC Atlantic:

    Trial Chief Scientist: Dr. Garry J. Heard

    Eight DRDC personnel will be needed for the testing and analysis of the data.

    Leased Vessel:

    Testing will be conducted on and around the vicinity of the DRDC Atlantic Calibration Barge. The

    Connor’s Diving boat used for personnel and equipment transportation will be employed as the tow/dip

    vessel for a hand-held (BATS) acoustic source. No additional funding is required for the use of this boat.

    Objectives The objectives with respect to the testing of the Innovation are:

    Testing the rapid deployment of the packaged array system

    Testing of the underwater modem networking

    Testing of the basic DUSN node sensor operations

    Collection of test data sets

    Recovery mode testing

    mailto:[email protected]:[email protected]

  • Area Clearances An area clearance consisting of a large region in Bedford Basin has been requested. See the included

    memorandum in Annex B.

    Network Accreditation and Certification Not applicable.

    Experiments The experiments are intended to produce the data to verify component and system operations, rapid

    deployment, and the collection of test data sets.

    Testing Rapid Deployment The DUSN sensors are packaged much like a sonobuoy. The package is held together with locking pins,

    which are removed prior to deployment. Once the pins are removed, the DUSN body falls through the

    water column. The bottom separates and forms the anchor system, while the top also separates and

    floats upward pulling the Vertical Line Array (VLA) and Cross-Dipole Array (CDA) out of the package.

    Despite the relatively large size of the DUSN, all the components are a tight fit inside. The purpose of

    this effort is to ensure that the arrays and anchor deploy properly.

    In order to do this part of the experiment a number of underwater cameras and lights have been

    obtained. The prototype DUSN node will be repeatedly deployed, recovered, and re-packed at the

    Bedford Basin Acoustic Calibration Barge (ACB) to facilitate filming of all aspects of the deployment. The

    intention is to also ensure that deployment is reliable and to identify issues before we build another

    eleven DUSN nodes.

    Testing of the Underwater Networking Once the deployment tests have been completed, the DUSN node will be left in a deployed condition.

    An Ethernet data cable will be attached to the node to facilitate communications and alterations to the

    internal processor.

    A Benthos Modem Seaweb gateway node will be deployed about 100-m from the ACB and tests will be

    conducted to ensure that the acoustic networking is functioning properly and that no difficulties are

    produced by the node’s physical arrangement.

    Testing of the DUSN Node Operations This part of the effort is an engineering test to insure that data are collected and stored within the DUSN

    node memory, that the internal signal detection, beamforming, and message generation algorithms are

    all functional and producing the proper results. In addition, the tests will ensure that the secondary

    sensors (orientation, temperature, etc.) are all functional.

    System operation will be checked end-to-end including autonomous detection, target tracking, and

    message generation and communications. The Connor’s boat will be used as a cooperative target and as

    a tow boat for an acoustic projector during these tests.

  • Collection of Test Data Sets The Connor’s boat will be used to conduct a series of transits past the prototype sensor in order to

    collect a number of controlled boat transits for future algorithm development.

    Recovery Mode Testing Each DUSN node has a pair of acoustic releases embedded within the plastic body. As a final test, we will

    attempt to operate the acoustic releases and drop the anchor section of the body. The DUSN will then

    rise to the surface under the influence of the VLA float.

    Primarily this test is concerned with ensuring that the body of the DUSN does not obscure the acoustic

    release receivers from the release signal.

    Schedule The schedule for the array field tests is uncertain at present due to delays in the manufacturing of the

    system. A relative schedule is presented below.

    Week prior COMEX DUSN prototype, tools, and other supplies transported to ACB.

    Saturday/Sunday Lab closed

    COMEX Begin deployment testing

    COMEX + 3 Deployment tests complete, modem gateway deployed, acoustic comms tests.

    COMEX + 4 Begin testing node operations

    Weekend Lab closed

    COMEX + 7 continue node operation tests.

    COMEX + 8 Collection of test data sets

    COMEX + 10 Recovery testing

    COMEX + 11 Barge Testing Ends

    Equipment Larger items for the testing are identified in the table below.

    Barge Boat Miscellaneous

    - Walky-talky - Acoustic source(s) for 20-11000 Hz - DUSN prototype - Benthos seaweb modems - Subsea sonics release controller and

    transducer - Small ROV to assist in filming and

    recovery of bottom anchor

    - Recording GPS - Walkie-Talkie - DACS?? - BATS source

    - Tools - Super-88 Vinyl Tape - Tie Wraps assorted - Marine Band

    Walkie-Talkies - Scope - DMM

  • Records A trial log book will be maintained in electronic form.

    Overtime Working day lengths are limited by the transportation vessel contract. Extensive over-time is not

    anticipated to be required; however, transportation of gear to and from the dock may extend the

    normal working day. Additional effort may also be required from time-to-time in order ensure a

    successful trial outcome in a timely fashion. Personnel will be paid for hours worked and a log of over-

    time will be kept by the Chief Scientist.

    No work on weekends is currently anticipated.

    A blanket over-time request will be created and forwarded to H/US for advance approval in case extra

    working time is needed. The OT, if any, will be minimal and is to be covered by the centre. This OT

    authorization will request a maximum of 12 hours for each of the eight personnel.

    Security Operations will be conducted in an unclassified manner. System operation will be shut-down as

    necessary to ensure that classified data is not collected

    Physical security for the equipment is limited. There is no overnight commissionaire on the barge. The

    barge is alarmed.

    Safety In general, during boat operations safety will be the responsibility of the masters of the individual

    vessels. Activities on the barge will be monitored by Rick Vienneau, who is the appointed Safety Officer

    (FSO) for this field trial. A floater jacket or other certified personal floatation device (PFD) is required for

    use on boats and around the moon pool or the barge. All personnel will bring a helmet, PFD, and hard-

    toed shoes. Work gloves as required should also be obtained from Stores.

    Safety briefings will be held by the Chief Scientist prior to personnel joining the transport vessel to the

    barge for the first time. The safety briefing will be given to all participants. The FSO will brief on Barge

    Safety to all personnel. All procedures mandated are to be followed. All participants will be responsible

    to remain vigilant to safety concerns in the trial conduct.

    Sunscreen and a hat are strongly recommended as well as personal supplies of drinking fluids.

    Annex A contains a hazard risk assessment for this trial based on `Occupational Health and Safety

    Hazard and Risk Assessment—MARLANT Defence Research and Development Canada’, Final Report,

    DND Contract HX 099015—Call Up 4. REA Project No. 14111.4, June 4, 2010.

  • Contact Numbers:

    Barge 902-426-5946

    DRDC—Atlantic Research Centre 902-426-3100

    Dial 6 for a name directory Commissionaire x120

    Calvin Hyatt (CD) x114 CDR Craig Bradley x159

    Queen’s Harbour Master 902-427-0550 x6001

    Environmental All work will be conducted near the Bedford Basin with the Acoustic Calibration Barge as the focus of the

    activities. This work is covered under the new Stantec Report, “Updated Environmental Baseline Study

    of the DRDC Acoustic Calibration Barge.”

    Communications Hand portable radios will be used between the vessel, barge, and shore.

    Personnel This field activity will involve a total of eight personnel. The participants are listed below.

    Since this trial is being held within 2 hours of medical treatment, in accordance with DRDC SOP, medicals

    are NOT required for the personnel.

    Field Team

    1. Garry J. Heard Chief Scientist

    2. Derek Clark Computer Specialist

    3. Stephane Blouin Defence Scientist

    4. Sean Pecknold Defence Scientist

    5. Val Shepeta Electronics Technologist

    6. Mark Fotheringham Electronics Technologist

    7. Ricky Vienneau Mechanical Technologist

    8. Tracey Robertson Photographer

  • Signatures

    Distribution - Dan Hutt H/US

    - LCdr Mark Titus

    - R. (Lex) Stuart

    - Adrian Hewitt

    - Sean O’Grady

    - Stephane Blouin

    - Sean Pecknold

    - David Hazen CD

    - CR

    - Garry Heard

    - Derek Clark

    - Val Shepeta

    - Dan Graham

    - Ricky Vienneau

    - Tracey Robertson

  • ANNEX A

    Hazard Risk Assessment for the 2016 DUSN Prototype Initial Field Tests

    A hazard identification and risk assessment was conducted for this trial based on the report, `Occupational

    Health and Safety Hazard and Risk Assessment—MARLANT Defence Research and Development

    Canada’, Final Report, DND Contract HX 099015—Call Up 4. REA Project No. 14111.4, June 4, 2010.

    Risks and hazards likely to be encountered during the trial were extracted from the listing in the REA

    report regardless of the Work Location (column 1). The point scores for consequence were adjusted for

    the conditions of the DUSN trial in accordance with the DRDC Atlantic SEMS Manual. A colour coded

    scale indicates the severity of the risk. The point scale in the column labelled ‘LxSum(C)’ also indicates

    the severity of the hazard.

    Twenty-five risks were identified in total that might be encountered in some form during the trial. Three

    of these risks were above the acceptable level and specific mitigation, notice, and attention is to be

    applied. All of the risks are listed in Annex 3A of the DRDC – Atlantic SEMS Manual, which has been

    printed and used for the risk identification.

    This trial consists mostly of work on a moored barge in Bedford Basin. Bedford Basin is an inland

    waterway and is somewhat sheltered. The work is being done in late August to early September, with

    the result that pleasant weather conditions can be expected. The work will require transportation by a

    contracted vessel to and from the Barge. The contracted vessel will also be used to carry out some

    limited work with a sound source near the barge.

    One of the most hazardous events in the work is simply getting on and off the vessel. The weather

    conditions are expected to be benign at the time and the area is sheltered by the land on all sides. We

    can therefore expect that rain and wind will be the most detrimental conditions that could occur and

    these will not increase the hazard substantially except for possibly increasing the likelihood of slipping.

    At the dock, the height differential between the boat and dock is dependent on the tides. The probable

    transfer location is equipped with a ramp to mitigate issues and avoid climbing a ladder. At the Barge

    the docking area and the Contractor vessel are of similar height. These conditions should facilitate safe

    embarkation and disembarkation. At both locations, personnel must wait for others to be ready to assist

    before attempting to transfer. When appropriate gang planks and similar transfer equipment will be used.

    The other two significant risks are related to the electrical risk in connecting the large power amplifier to

    acoustic sources and the manual handling of equipment. All personnel are trained in the laboratory

    requirements which include the hook-up of electrical equipment. Personnel must ensure that power is

    removed from transducers and cables before attempting to connect/disconnect these devices.

    All personnel should pay particular attention to the lifting of heavy loads—particularly on and off the

    boat! Extreme care must be used in deployment and recovery of equipment. PFD’s and other

  • appropriate safety equipment must be worn. No unnecessary personnel will be in the immediate area,

    but should be ready to assist in the event of an emergency.

    Two or more of the trials personnel are trained and current in First-Aid (Derek Clark, Sean Pecknold), while

    most of the other personnel have been First Aid trained on multiple occasions, but may not be current.

  • ANNEX B

    Area Clearances

    The area outline below was requested 2016.08.08 by liaison officer LCdr D. Brennan.

    1. The op area requested is outlined below.

    WP Lat (N deg) Lon (E deg)

    1 44.680 63.649

    2 44.683 63.656

    3 44.688 63.657

    4 44.702 63.657

    5 44.703 63.631

    6 44.675 63.631

    7 44.675 63.6411

    ACB 44.684 63.6521

    The attached figure illustrates the region in Bedford Basin that is requested.

    2. As of today, the activity is booked for 29 Aug – 2 Sept, 2016 inclusive.

    3. Adrian Hewitt is the PM for this effort under the FASW project.

  • Figure B1. Map showing the waypoint locations and the requested operational area for the trial.

  • DOCUMENT CONTROL DATA (Security markings for the title, abstract and indexing annotation must be entered when the document is Classified or Designated)

    1. ORIGINATOR (The name and address of the organization preparing the document.Organizations for whom the document was prepared, e.g., Centre sponsoring a

    contractor's report, or tasking agency, are entered in Section 8.)

    DRDC – Atlantic Research CentreDefence Research and Development Canada9 Grove StreetP.O. Box 1012Dartmouth, Nova Scotia B2Y 3Z7Canada

    2a. SECURITY MARKING (Overall security marking of the document including

    special supplemental markings if applicable.)

    UNCLASSIFIED

    2b. CONTROLLED GOODS

    (NON-CONTROLLED GOODS) DMC A

    3. TITLE (The complete document title as indicated on the title page. Its classification should be indicated by the appropriate abbreviation (S, C or U) in parentheses after the title.)

    DUSN Prototype Initial Field Tests

    4. AUTHORS (last name, followed by initials – ranks, titles, etc., not to be used)

    Heard, G.

    5. DATE OF PUBLICATION (Month and year of publication of document.)

    May 2017

    6a. NO. OF PAGES (Total containing information,

    including Annexes, Appendices,

    etc.)

    18

    6b. NO. OF REFS (Total cited in document.)

    0

    7. DESCRIPTIVE NOTES (The category of the document, e.g., technical report, technical note or memorandum. If appropriate, enter the type of report,e.g., interim, progress, summary, annual or final. Give the inclusive dates when a specific reporting period is covered.)

    Reference Document

    8. SPONSORING ACTIVITY (The name of the department project office or laboratory sponsoring the research and development – include address.)

    DRDC – Atlantic Research CentreDefence Research and Development Canada9 Grove StreetP.O. Box 1012Dartmouth, Nova Scotia B2Y 3Z7Canada

    9a. PROJECT OR GRANT NO. (If appropriate, the applicable research and development project or grant number under which the document

    was written. Please specify whether project or grant.)

    9b. CONTRACT NO. (If appropriate, the applicable number under which the document was written.)

    10a. ORIGINATOR’S DOCUMENT NUMBER (The official document number by which the document is identified by the originating

    activity. This number must be unique to this document.)

    DRDC-RDDC-2017-D034

    10b. OTHER DOCUMENT NO(s). (Any other numbers which may be assigned this document either by the originator or by the sponsor.)

    11. DOCUMENT AVAILABILITY (Any limitations on further dissemination of the document, other than those imposed by security classification.)

    Unlimited

    12. DOCUMENT ANNOUNCEMENT (Any limitation to the bibliographic announcement of this document. This will normally correspond to theDocument Availability (11). However, where further distribution (beyond the audience specified in (11) is possible, a wider announcement

    audience may be selected.))

    Unlimited

  • 13. ABSTRACT (A brief and factual summary of the document. It may also appear elsewhere in the body of the document itself. It is highly desirable that the abstract of classified documents be unclassified. Each paragraph of the abstract shall begin with an indication of the security classification of the

    information in the paragraph (unless the document itself is unclassified) represented as (S), (C), (R), or (U). It is not necessary to include here abstracts in

    both official languages unless the text is bilingual.)

    The Distributed Undersea Sensor Network (DUSN) is a component of the Force ASW project.

    DUSN consists of research directed toward the implementation of autonomous UW networked

    ASW sensors. Included in the project is an international agreement with Norway and Sweden,

    which is also called DUSN.

    The DUSN project is attempting to create useful sized networks of ASW sensors and therefore

    DRDC is building a dozen DUSN nodes. These nodes, when combined with nodes from the

    other countries, will form a network that is just large enough to begin to demonstrate network

    issues; both positive and negative influences on performance. These nodes have UW acoustic

    communications, on-board detection and processing, and will allow for the development of UW

    network protocols and signal processing algorithms.

    The first Canadian prototype DUSN node is nearing completion and must under-go a series of

    engineering tests before full investment in the remaining eleven units is undertaken. This

    Bedford Basin Barge Trial is intended as the first engineering trial for the prototype sensor node.

    -------------------------------------------------------------------------------------------------------------------

    Le réseau de distribution de capteurs sous-marins (RDCS) est un élément du projet de guerre

    anti-sous-marine (GASM) de la force. Le RDCS comprend la recherche orientée vers la mise en

    œuvre de capteurs de GASM autonomes sous-marins en réseau. Le projet comprend également

    une entente internationale avec la Norvège et la Suède, également appelée RDCS.

    Dans le cadre du projet RDCS, on cherche à créer des réseaux de capteurs de GASM de taille

    utile. C’est pourquoi RDDC est en train de construire une dizaine de nœuds de RDCS.

    Lorsqu’ils seront conjugués à ceux d’autres pays, ces nœuds constitueront un réseau juste assez

    grand pour pouvoir démontrer les problèmes qu’il peut occasionner, leur influence positive et

    négative sur le rendement. Ces nœuds permettront d’établir des communications acoustiques

    sous-marines, et de procéder à la détection et au traitement embarqués. Ils permettront

    également d’élaborer de nouveaux protocoles de réseaux sous-marins et de nouveaux

    algorithmes de traitement du signal.

    Le premier prototype canadien de nœud de RDCS est presque achevé et doit faire l’objet d’une

    série d’essais techniques avant que la totalité des fonds soit consacrée aux onze nœuds restants.

    L’essai sur la barge dans le bassin de Bedford devrait être le premier essai technique du

    prototype de nœud de capteurs.

    14. KEYWORDS, DESCRIPTORS or IDENTIFIERS (Technically meaningful terms or short phrases that characterize a document and could be helpful in cataloguing the document. They should be selected so that no security classification is required. Identifiers, such as equipment model designation,

    trade name, military project code name, geographic location may also be included. If possible keywords should be selected from a published thesaurus,

    e.g., Thesaurus of Engineering and Scientific Terms (TEST) and that thesaurus identified. If it is not possible to select indexing terms which are

    Unclassified, the classification of each should be indicated as with the title.)

    acoustics; underwater; towed array

    AbstractRésuméTable of contents11.1