Click here to load reader
Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
DUSN Prototype Initial Field Tests
Garry Heard DRDC – Atlantic Research Centre
Defence Research and Development Canada
Reference Document
DRDC-RDDC-2017-D034 May 2017
Template in use: (2010) SR Advanced Template_EN (051115).dotm
© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017
© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale,
2017
DRDC-RDDC-2017-D034 i
Abstract
The Distributed Undersea Sensor Network (DUSN) is a component of the Force ASW project.
DUSN consists of research directed toward the implementation of autonomous UW networked
ASW sensors. Included in the project is an international agreement with Norway and Sweden,
which is also called DUSN.
The DUSN project is attempting to create useful sized networks of ASW sensors and therefore
DRDC is building a dozen DUSN nodes. These nodes, when combined with nodes from the other
countries, will form a network that is just large enough to begin to demonstrate network issues;
both positive and negative influences on performance. These nodes have UW acoustic
communications, on-board detection and processing, and will allow for the development of UW
network protocols and signal processing algorithms.
The first Canadian prototype DUSN node is nearing completion and must under-go a series of
engineering tests before full investment in the remaining eleven units is undertaken. This Bedford
Basin Barge Trial is intended as the first engineering trial for the prototype sensor node.
ii DRDC-RDDC-2017-D034
Résumé
Le réseau de distribution de capteurs sous-marins (RDCS) est un élément du projet de guerre
anti-sous-marine (GASM) de la force. Le RDCS comprend la recherche orientée vers la mise en
œuvre de capteurs de GASM autonomes sous-marins en réseau. Le projet comprend également
une entente internationale avec la Norvège et la Suède, également appelée RDCS.
Dans le cadre du projet RDCS, on cherche à créer des réseaux de capteurs de GASM de taille
utile. C’est pourquoi RDDC est en train de construire une dizaine de nœuds de RDCS. Lorsqu’ils
seront conjugués à ceux d’autres pays, ces nœuds constitueront un réseau juste assez grand pour
pouvoir démontrer les problèmes qu’il peut occasionner, leur influence positive et négative sur le
rendement. Ces nœuds permettront d’établir des communications acoustiques sous-marines, et de
procéder à la détection et au traitement embarqués. Ils permettront également d’élaborer de
nouveaux protocoles de réseaux sous-marins et de nouveaux algorithmes de traitement du signal.
Le premier prototype canadien de nœud de RDCS est presque achevé et doit faire l’objet d’une
série d’essais techniques avant que la totalité des fonds soit consacrée aux onze nœuds restants.
L’essai sur la barge dans le bassin de Bedford devrait être le premier essai technique du prototype
de nœud de capteurs.
Project FASW 01CA03
DUSN Prototype Initial Field Tests
Aug 2016
DRDC Atlantic File: 4118-02
OPI: Heard, Garry
Underwater Sensing Section
DRDC Atlantic Research Centre
902-426-3100 x310
PM: Adrian Hewitt
V2016.08.18
DUSN Prototype Initial Field Tests
Chief Scientist: Dr. Garry J. Heard [email protected]
Project Manager: Adrian Hewitt [email protected]
Overview The Distributed Undersea Sensor Network (DUSN) is a component of the Force ASW project. DUSN
consists of research directed toward the implementation of autonomous UW networked ASW sensors.
Included in the project is an international agreement with Norway and Sweden, which is also, called
DUSN.
The DUSN project is attempting to create useful sized networks of ASW sensors and therefore DRDC is
building a dozen-DUSN nodes. These nodes when combined with nodes from the other countries will
form a network that is just large enough to begin to demonstrate network issues; both positive and
negative influences on performance. These nodes have UW acoustic communications, on-board
detection and processing, and will allow for the development of UW network protocols and signal
processing algorithms.
The first Canadian prototype DUSN node is nearing completion and must under-go a series of
engineering tests before full investment in the remaining eleven units is undertaken. This Bedford Basin
Barge Trial is intended as the first engineering trial for the prototype sensor node.
Participation DRDC Atlantic:
Trial Chief Scientist: Dr. Garry J. Heard
Eight DRDC personnel will be needed for the testing and analysis of the data.
Leased Vessel:
Testing will be conducted on and around the vicinity of the DRDC Atlantic Calibration Barge. The
Connor’s Diving boat used for personnel and equipment transportation will be employed as the tow/dip
vessel for a hand-held (BATS) acoustic source. No additional funding is required for the use of this boat.
Objectives The objectives with respect to the testing of the Innovation are:
Testing the rapid deployment of the packaged array system
Testing of the underwater modem networking
Testing of the basic DUSN node sensor operations
Collection of test data sets
Recovery mode testing
Area Clearances An area clearance consisting of a large region in Bedford Basin has been requested. See the included
memorandum in Annex B.
Network Accreditation and Certification Not applicable.
Experiments The experiments are intended to produce the data to verify component and system operations, rapid
deployment, and the collection of test data sets.
Testing Rapid Deployment The DUSN sensors are packaged much like a sonobuoy. The package is held together with locking pins,
which are removed prior to deployment. Once the pins are removed, the DUSN body falls through the
water column. The bottom separates and forms the anchor system, while the top also separates and
floats upward pulling the Vertical Line Array (VLA) and Cross-Dipole Array (CDA) out of the package.
Despite the relatively large size of the DUSN, all the components are a tight fit inside. The purpose of
this effort is to ensure that the arrays and anchor deploy properly.
In order to do this part of the experiment a number of underwater cameras and lights have been
obtained. The prototype DUSN node will be repeatedly deployed, recovered, and re-packed at the
Bedford Basin Acoustic Calibration Barge (ACB) to facilitate filming of all aspects of the deployment. The
intention is to also ensure that deployment is reliable and to identify issues before we build another
eleven DUSN nodes.
Testing of the Underwater Networking Once the deployment tests have been completed, the DUSN node will be left in a deployed condition.
An Ethernet data cable will be attached to the node to facilitate communications and alterations to the
internal processor.
A Benthos Modem Seaweb gateway node will be deployed about 100-m from the ACB and tests will be
conducted to ensure that the acoustic networking is functioning properly and that no difficulties are
produced by the node’s physical arrangement.
Testing of the DUSN Node Operations This part of the effort is an engineering test to insure that data are collected and stored within the DUSN
node memory, that the internal signal detection, beamforming, and message generation algorithms are
all functional and producing the proper results. In addition, the tests will ensure that the secondary
sensors (orientation, temperature, etc.) are all functional.
System operation will be checked end-to-end including autonomous detection, target tracking, and
message generation and communications. The Connor’s boat will be used as a cooperative target and as
a tow boat for an acoustic projector during these tests.
Collection of Test Data Sets The Connor’s boat will be used to conduct a series of transits past the prototype sensor in order to
collect a number of controlled boat transits for future algorithm development.
Recovery Mode Testing Each DUSN node has a pair of acoustic releases embedded within the plastic body. As a final test, we will
attempt to operate the acoustic releases and drop the anchor section of the body. The DUSN will then
rise to the surface under the influence of the VLA float.
Primarily this test is concerned with ensuring that the body of the DUSN does not obscure the acoustic
release receivers from the release signal.
Schedule The schedule for the array field tests is uncertain at present due to delays in the manufacturing of the
system. A relative schedule is presented below.
Week prior COMEX DUSN prototype, tools, and other supplies transported to ACB.
Saturday/Sunday Lab closed
COMEX Begin deployment testing
COMEX + 3 Deployment tests complete, modem gateway deployed, acoustic comms tests.
COMEX + 4 Begin testing node operations
Weekend Lab closed
COMEX + 7 continue node operation tests.
COMEX + 8 Collection of test data sets
COMEX + 10 Recovery testing
COMEX + 11 Barge Testing Ends
Equipment Larger items for the testing are identified in the table below.
Barge Boat Miscellaneous
- Walky-talky - Acoustic source(s) for 20-11000 Hz - DUSN prototype - Benthos seaweb modems - Subsea sonics release controller and
transducer - Small ROV to assist in filming and
recovery of bottom anchor
- Recording GPS - Walkie-Talkie - DACS?? - BATS source
- Tools - Super-88 Vinyl Tape - Tie Wraps assorted - Marine Band
Walkie-Talkies - Scope - DMM
Records A trial log book will be maintained in electronic form.
Overtime Working day lengths are limited by the transportation vessel contract. Extensive over-time is not
anticipated to be required; however, transportation of gear to and from the dock may extend the
normal working day. Additional effort may also be required from time-to-time in order ensure a
successful trial outcome in a timely fashion. Personnel will be paid for hours worked and a log of over-
time will be kept by the Chief Scientist.
No work on weekends is currently anticipated.
A blanket over-time request will be created and forwarded to H/US for advance approval in case extra
working time is needed. The OT, if any, will be minimal and is to be covered by the centre. This OT
authorization will request a maximum of 12 hours for each of the eight personnel.
Security Operations will be conducted in an unclassified manner. System operation will be shut-down as
necessary to ensure that classified data is not collected
Physical security for the equipment is limited. There is no overnight commissionaire on the barge. The
barge is alarmed.
Safety In general, during boat operations safety will be the responsibility of the masters of the individual
vessels. Activities on the barge will be monitored by Rick Vienneau, who is the appointed Safety Officer
(FSO) for this field trial. A floater jacket or other certified personal floatation device (PFD) is required for
use on boats and around the moon pool or the barge. All personnel will bring a helmet, PFD, and hard-
toed shoes. Work gloves as required should also be obtained from Stores.
Safety briefings will be held by the Chief Scientist prior to personnel joining the transport vessel to the
barge for the first time. The safety briefing will be given to all participants. The FSO will brief on Barge
Safety to all personnel. All procedures mandated are to be followed. All participants will be responsible
to remain vigilant to safety concerns in the trial conduct.
Sunscreen and a hat are strongly recommended as well as personal supplies of drinking fluids.
Annex A contains a hazard risk assessment for this trial based on `Occupational Health and Safety
Hazard and Risk Assessment—MARLANT Defence Research and Development Canada’, Final Report,
DND Contract HX 099015—Call Up 4. REA Project No. 14111.4, June 4, 2010.
Contact Numbers:
Barge 902-426-5946
DRDC—Atlantic Research Centre 902-426-3100
Dial 6 for a name directory Commissionaire x120
Calvin Hyatt (CD) x114 CDR Craig Bradley x159
Queen’s Harbour Master 902-427-0550 x6001
Environmental All work will be conducted near the Bedford Basin with the Acoustic Calibration Barge as the focus of the
activities. This work is covered under the new Stantec Report, “Updated Environmental Baseline Study
of the DRDC Acoustic Calibration Barge.”
Communications Hand portable radios will be used between the vessel, barge, and shore.
Personnel This field activity will involve a total of eight personnel. The participants are listed below.
Since this trial is being held within 2 hours of medical treatment, in accordance with DRDC SOP, medicals
are NOT required for the personnel.
Field Team
1. Garry J. Heard Chief Scientist
2. Derek Clark Computer Specialist
3. Stephane Blouin Defence Scientist
4. Sean Pecknold Defence Scientist
5. Val Shepeta Electronics Technologist
6. Mark Fotheringham Electronics Technologist
7. Ricky Vienneau Mechanical Technologist
8. Tracey Robertson Photographer
Signatures
Distribution - Dan Hutt H/US
- LCdr Mark Titus
- R. (Lex) Stuart
- Adrian Hewitt
- Sean O’Grady
- Stephane Blouin
- Sean Pecknold
- David Hazen CD
- CR
- Garry Heard
- Derek Clark
- Val Shepeta
- Dan Graham
- Ricky Vienneau
- Tracey Robertson
ANNEX A
Hazard Risk Assessment for the 2016 DUSN Prototype Initial Field Tests
A hazard identification and risk assessment was conducted for this trial based on the report, `Occupational
Health and Safety Hazard and Risk Assessment—MARLANT Defence Research and Development
Canada’, Final Report, DND Contract HX 099015—Call Up 4. REA Project No. 14111.4, June 4, 2010.
Risks and hazards likely to be encountered during the trial were extracted from the listing in the REA
report regardless of the Work Location (column 1). The point scores for consequence were adjusted for
the conditions of the DUSN trial in accordance with the DRDC Atlantic SEMS Manual. A colour coded
scale indicates the severity of the risk. The point scale in the column labelled ‘LxSum(C)’ also indicates
the severity of the hazard.
Twenty-five risks were identified in total that might be encountered in some form during the trial. Three
of these risks were above the acceptable level and specific mitigation, notice, and attention is to be
applied. All of the risks are listed in Annex 3A of the DRDC – Atlantic SEMS Manual, which has been
printed and used for the risk identification.
This trial consists mostly of work on a moored barge in Bedford Basin. Bedford Basin is an inland
waterway and is somewhat sheltered. The work is being done in late August to early September, with
the result that pleasant weather conditions can be expected. The work will require transportation by a
contracted vessel to and from the Barge. The contracted vessel will also be used to carry out some
limited work with a sound source near the barge.
One of the most hazardous events in the work is simply getting on and off the vessel. The weather
conditions are expected to be benign at the time and the area is sheltered by the land on all sides. We
can therefore expect that rain and wind will be the most detrimental conditions that could occur and
these will not increase the hazard substantially except for possibly increasing the likelihood of slipping.
At the dock, the height differential between the boat and dock is dependent on the tides. The probable
transfer location is equipped with a ramp to mitigate issues and avoid climbing a ladder. At the Barge
the docking area and the Contractor vessel are of similar height. These conditions should facilitate safe
embarkation and disembarkation. At both locations, personnel must wait for others to be ready to assist
before attempting to transfer. When appropriate gang planks and similar transfer equipment will be used.
The other two significant risks are related to the electrical risk in connecting the large power amplifier to
acoustic sources and the manual handling of equipment. All personnel are trained in the laboratory
requirements which include the hook-up of electrical equipment. Personnel must ensure that power is
removed from transducers and cables before attempting to connect/disconnect these devices.
All personnel should pay particular attention to the lifting of heavy loads—particularly on and off the
boat! Extreme care must be used in deployment and recovery of equipment. PFD’s and other
appropriate safety equipment must be worn. No unnecessary personnel will be in the immediate area,
but should be ready to assist in the event of an emergency.
Two or more of the trials personnel are trained and current in First-Aid (Derek Clark, Sean Pecknold), while
most of the other personnel have been First Aid trained on multiple occasions, but may not be current.
ANNEX B
Area Clearances
The area outline below was requested 2016.08.08 by liaison officer LCdr D. Brennan.
1. The op area requested is outlined below.
WP Lat (N deg) Lon (E deg)
1 44.680 63.649
2 44.683 63.656
3 44.688 63.657
4 44.702 63.657
5 44.703 63.631
6 44.675 63.631
7 44.675 63.6411
ACB 44.684 63.6521
The attached figure illustrates the region in Bedford Basin that is requested.
2. As of today, the activity is booked for 29 Aug – 2 Sept, 2016 inclusive.
3. Adrian Hewitt is the PM for this effort under the FASW project.
Figure B1. Map showing the waypoint locations and the requested operational area for the trial.
DOCUMENT CONTROL DATA (Security markings for the title, abstract and indexing annotation must be entered when the document is Classified or Designated)
1. ORIGINATOR (The name and address of the organization preparing the document.Organizations for whom the document was prepared, e.g., Centre sponsoring a
contractor's report, or tasking agency, are entered in Section 8.)
DRDC – Atlantic Research CentreDefence Research and Development Canada9 Grove StreetP.O. Box 1012Dartmouth, Nova Scotia B2Y 3Z7Canada
2a. SECURITY MARKING (Overall security marking of the document including
special supplemental markings if applicable.)
UNCLASSIFIED
2b. CONTROLLED GOODS
(NON-CONTROLLED GOODS) DMC A
3. TITLE (The complete document title as indicated on the title page. Its classification should be indicated by the appropriate abbreviation (S, C or U) in parentheses after the title.)
DUSN Prototype Initial Field Tests
4. AUTHORS (last name, followed by initials – ranks, titles, etc., not to be used)
Heard, G.
5. DATE OF PUBLICATION (Month and year of publication of document.)
May 2017
6a. NO. OF PAGES (Total containing information,
including Annexes, Appendices,
etc.)
18
6b. NO. OF REFS (Total cited in document.)
0
7. DESCRIPTIVE NOTES (The category of the document, e.g., technical report, technical note or memorandum. If appropriate, enter the type of report,e.g., interim, progress, summary, annual or final. Give the inclusive dates when a specific reporting period is covered.)
Reference Document
8. SPONSORING ACTIVITY (The name of the department project office or laboratory sponsoring the research and development – include address.)
DRDC – Atlantic Research CentreDefence Research and Development Canada9 Grove StreetP.O. Box 1012Dartmouth, Nova Scotia B2Y 3Z7Canada
9a. PROJECT OR GRANT NO. (If appropriate, the applicable research and development project or grant number under which the document
was written. Please specify whether project or grant.)
9b. CONTRACT NO. (If appropriate, the applicable number under which the document was written.)
10a. ORIGINATOR’S DOCUMENT NUMBER (The official document number by which the document is identified by the originating
activity. This number must be unique to this document.)
DRDC-RDDC-2017-D034
10b. OTHER DOCUMENT NO(s). (Any other numbers which may be assigned this document either by the originator or by the sponsor.)
11. DOCUMENT AVAILABILITY (Any limitations on further dissemination of the document, other than those imposed by security classification.)
Unlimited
12. DOCUMENT ANNOUNCEMENT (Any limitation to the bibliographic announcement of this document. This will normally correspond to theDocument Availability (11). However, where further distribution (beyond the audience specified in (11) is possible, a wider announcement
audience may be selected.))
Unlimited
13. ABSTRACT (A brief and factual summary of the document. It may also appear elsewhere in the body of the document itself. It is highly desirable that the abstract of classified documents be unclassified. Each paragraph of the abstract shall begin with an indication of the security classification of the
information in the paragraph (unless the document itself is unclassified) represented as (S), (C), (R), or (U). It is not necessary to include here abstracts in
both official languages unless the text is bilingual.)
The Distributed Undersea Sensor Network (DUSN) is a component of the Force ASW project.
DUSN consists of research directed toward the implementation of autonomous UW networked
ASW sensors. Included in the project is an international agreement with Norway and Sweden,
which is also called DUSN.
The DUSN project is attempting to create useful sized networks of ASW sensors and therefore
DRDC is building a dozen DUSN nodes. These nodes, when combined with nodes from the
other countries, will form a network that is just large enough to begin to demonstrate network
issues; both positive and negative influences on performance. These nodes have UW acoustic
communications, on-board detection and processing, and will allow for the development of UW
network protocols and signal processing algorithms.
The first Canadian prototype DUSN node is nearing completion and must under-go a series of
engineering tests before full investment in the remaining eleven units is undertaken. This
Bedford Basin Barge Trial is intended as the first engineering trial for the prototype sensor node.
-------------------------------------------------------------------------------------------------------------------
Le réseau de distribution de capteurs sous-marins (RDCS) est un élément du projet de guerre
anti-sous-marine (GASM) de la force. Le RDCS comprend la recherche orientée vers la mise en
œuvre de capteurs de GASM autonomes sous-marins en réseau. Le projet comprend également
une entente internationale avec la Norvège et la Suède, également appelée RDCS.
Dans le cadre du projet RDCS, on cherche à créer des réseaux de capteurs de GASM de taille
utile. C’est pourquoi RDDC est en train de construire une dizaine de nœuds de RDCS.
Lorsqu’ils seront conjugués à ceux d’autres pays, ces nœuds constitueront un réseau juste assez
grand pour pouvoir démontrer les problèmes qu’il peut occasionner, leur influence positive et
négative sur le rendement. Ces nœuds permettront d’établir des communications acoustiques
sous-marines, et de procéder à la détection et au traitement embarqués. Ils permettront
également d’élaborer de nouveaux protocoles de réseaux sous-marins et de nouveaux
algorithmes de traitement du signal.
Le premier prototype canadien de nœud de RDCS est presque achevé et doit faire l’objet d’une
série d’essais techniques avant que la totalité des fonds soit consacrée aux onze nœuds restants.
L’essai sur la barge dans le bassin de Bedford devrait être le premier essai technique du
prototype de nœud de capteurs.
14. KEYWORDS, DESCRIPTORS or IDENTIFIERS (Technically meaningful terms or short phrases that characterize a document and could be helpful in cataloguing the document. They should be selected so that no security classification is required. Identifiers, such as equipment model designation,
trade name, military project code name, geographic location may also be included. If possible keywords should be selected from a published thesaurus,
e.g., Thesaurus of Engineering and Scientific Terms (TEST) and that thesaurus identified. If it is not possible to select indexing terms which are
Unclassified, the classification of each should be indicated as with the title.)
acoustics; underwater; towed array
AbstractRésuméTable of contents11.1