DUNE Project Status Jolie Macier DUNE PMG Meeting December 20, 2016

DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

  • Upload
    others

  • View
    11

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

DUNE Project StatusJolie MacierDUNE PMG MeetingDecember 20, 2016

Page 2: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

Outline

• ES&H Update• QA Update• Schedule & Budget Status• PM Update• Far Detector Report• SPPD Report

• Design & Construction – reports by subsystem• Onsite  ‐ installation & instrumentation

• DPPD Report• Upcoming Events

2 20-DEC-2016 Jolie Macier | DUNE PMG

Page 3: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

ES&H

• Completed a site visit to the University of Wisconsin Physical Sciences Lab with Kevin Fahey• Observed the dye penetrant welding testing on the first APA frame completed 

by TEAM• Discussions relating to compliance with AWS & CERN welding requirements• Completed a shop tour including the APA winding area

• Working with Terri Shaw, Jim Priest & Olga Beltramello (CERN) to develop a DUNE Engineering Note to define criteria for ProtoDUNE-SP cables installed at the CERN EHN1 Facility • Guidance includes smoke & fire ratings for cables including the use of 

halogenated vs. non‐halogenated cables inside and outside of the detector

3 20-DEC-2016 Jolie Macier | DUNE PMG

Page 4: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

Quality Assurance

• PSL APA • Witnessed the NDE (Visual and PT) of the welds on APA 1 at PSL. The results 

were satisfactory. Reports are being corrected to reflect traceability back to APA 1.

• Provided further information on AWS D1.6 and pre‐qualified Weld Procedure Specifications. 

• Discussed welding plans for the future APAs to ensure compliance with AWS D1.6.

• Continuing development of the template for the QC Plan• Following up on the requirements for the Production

Readiness Reviews

4 20-DEC-2016 Jolie Macier | DUNE PMG

Page 5: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

DUNE Stop Light Report – November 2016

20-DEC-2016 Jolie Macier | DUNE PMG5

• Cost variances on APA, CPA persist due to accruals

Far DetectorNovember 30, 2016Currency in: $K

WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%)131.02 DUNE 1,130 814 1,826 (316) ‐28% (1,011) ‐124%   131.02.02 Far Detector 1,130 814 1,826 (316) ‐28% (1,011) ‐124%      131.02.02.20 Far Detector 167 91 169 (76) ‐46% (79) ‐87%         131.02.02.20.01 Far Detector Management 44 44 26 0 0% 19 42%         131.02.02.20.02 APAs 0 0 0 0 0% 0 0%         131.02.02.20.03 CPA/FC/HV 0 0 0 0 0% 0 0%         131.02.02.20.04 Cold Electronics 106 34 105 (72) ‐68% (71) ‐209%         131.02.02.20.05 Photon Detector 0 0 0 0 0% 0 0%         131.02.02.20.06 DAQ 0 0 0 0 0% 0 0%         131.02.02.20.07 Installation 0 0 0 0 0% 0 0%         131.02.02.20.08 Integration 16 12 38 (4) ‐25% (26) ‐214%         131.02.02.20.09 Simulation and Modeling 0 0 0 0 0% 0 0%      131.02.02.30 ProtoDUNE Design and Construction 850 637 1,498 (213) ‐25% (861) ‐135%         131.02.02.30.02 ProtoDUNE APAs 208 201 530 (7) ‐3% (329) ‐164%         131.02.02.30.03 ProtoDUNE CPA/FC/HV 210 107 720 (104) ‐49% (613) ‐576%         131.02.02.30.04 ProtoDUNE Cold Electronics 278 164 176 (114) ‐41% (12) ‐7%         131.02.02.30.05 ProtoDUNE Photon Detector 45 33 38 (12) ‐27% (4) ‐13%         131.02.02.30.08 ProtoDUNE Integration 108 132 34 24 22% 98 74%      131.02.02.40 ProtoDUNE Onsite 114 87 158 (26) ‐23% (71) ‐82%         131.02.02.40.01 ProtoDUNE Installation Management 21 17 11 (4) ‐18% 7 39%         131.02.02.40.06 ProtoDUNE DAQ 60 28 140 (33) ‐54% (112) ‐404%         131.02.02.40.07 ProtoDUNE Installation 32 42 7 10 33% 35 84%         131.02.02.40.10 ProtoDUNE Instrumentation 0 0 1 0 0% (1) ‐Total 1,130 814 1,826 (316) ‐28% (1,011) ‐124%

Current Period

Page 6: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

DUNE Stop Light Report – Cumulative (November 2016)

20-DEC-2016 Jolie Macier | DUNE PMG6

Far DetectorNovember 30, 2016Currency in: $K

WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI131.02 DUNE 11,654 11,064 10,991 (589) ‐5% 74 1% 0.95 1.01   131.02.02 Far Detector 11,654 11,064 10,991 (589) ‐5% 74 1% 0.95 1.01      131.02.02.20 Far Detector 2,282 2,043 2,044 (239) ‐10% (1) 0% 0.90 1.00         131.02.02.20.01 Far Detector Management 397 397 400 0 0% (3) ‐1% 1.00 0.99         131.02.02.20.02 APAs 37 37 0 0 0% 37 100% 1.00 ‐         131.02.02.20.03 CPA/FC/HV 0 0 0 0 0% 0 0% ‐ ‐         131.02.02.20.04 Cold Electronics 1,407 1,163 648 (245) ‐17% 515 44% 0.83 1.79         131.02.02.20.05 Photon Detector 6 6 0 0 0% 6 100% 1.00 ‐         131.02.02.20.06 DAQ 65 65 0 0 0% 65 100% 1.00 ‐         131.02.02.20.07 Installation 26 26 34 0 0% (7) ‐27% 1.00 0.78         131.02.02.20.08 Integration 342 348 962 6 2% (614) ‐176% 1.02 0.36         131.02.02.20.09 Simulation and Modeling 0 0 0 0 0% 0 0% ‐ ‐      131.02.02.30 ProtoDUNE Design and Construction 8,608 8,379 8,145 (229) ‐3% 234 3% 0.97 1.03         131.02.02.30.02 ProtoDUNE APAs 2,925 2,798 2,861 (127) ‐4% (63) ‐2% 0.96 0.98         131.02.02.30.03 ProtoDUNE CPA/FC/HV 1,108 1,115 1,963 7 1% (848) ‐76% 1.01 0.57         131.02.02.30.04 ProtoDUNE Cold Electronics 3,014 3,017 1,982 3 0% 1,035 34% 1.00 1.52         131.02.02.30.05 ProtoDUNE Photon Detector 953 884 1,046 (69) ‐7% (161) ‐18% 0.93 0.85         131.02.02.30.08 ProtoDUNE Integration 608 564 294 (44) ‐7% 271 48% 0.93 1.92      131.02.02.40 ProtoDUNE Onsite 764 643 802 (121) ‐16% (159) ‐25% 0.84 0.80         131.02.02.40.01 ProtoDUNE Installation Management 21 39 21 18 84% 18 47% 1.84 1.88         131.02.02.40.06 ProtoDUNE DAQ 307 329 578 22 7% (249) ‐76% 1.07 0.57         131.02.02.40.07 ProtoDUNE Installation 435 275 201 (161) ‐37% 73 27% 0.63 1.37         131.02.02.40.10 ProtoDUNE Instrumentation 0 0 2 0 0% (2) ‐ ‐ 0.00Total 11,654 11,064 10,991 (589) ‐5% 74 1% 0.95 1.01

Cumulative to Date

Page 7: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

Project Management Highlights

• Planning for upcoming IPR• Received charge from OPA/HEP• Planning agenda with LBNF:

• Two DUNE plenary talks• Two DUNE breakouts: ProtoDUNE & Cost, Schedule,

Management• Plan for year-long continuing resolution impacts DUNE ~$1m (Q3)• Coordination with CERN HSE (safety) for installed ProtoDUNE

components will require significant effort• Working with DUNE Collaboration on logistics for CERN

assignments / relocations / operations fund; Mark Thomson, Eric James & Ami Dave to HEP in January

• Developed watch list for key protoDUNE-SP delivery activities; DUNE Executive Committee also monitoring

7 20-DEC-2016 Jolie Macier | DUNE PMG

Page 8: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

Alignment – CR103

• As part of CR0090, LBNF removed detector related alignment activities from the beamline subproject with the expectation that DUNE review its alignment requirements and revise its plan accordingly.

8 20-DEC-2016 Jolie Macier | DUNE PMG

FY22 FY23 FY24 FY25 FY26 Total

Far Detector $ (53,195) $178,209  $                 ‐ $130,666  $              ‐ $255,680 Near Detector $217,487  $49,740  $                 ‐ $ ‐ $              ‐ $267,227 Total $164,292  $227,949  $                 ‐ $130,666  $              ‐ $522,907 

Page 9: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

T2 Milestones Changes – CR140

9 20-DEC-2016 Jolie Macier | DUNE PMG

Activity Name (*)Finish Revise / Add:T2 MS ‐ ProtoDUNE SP PD Technology selection 15‐Mar‐17T2 MS ‐ ProtoDUNE Design reviews completed 21‐Jun‐17T2 MS ‐ Full Scale Prototype APA complete 25‐Oct‐17 T2 MS ‐ ProtoDUNE SP Detector Production complete

T2 MS ‐ ProtoDUNE SP Detector Installation completeT2 MS ‐ ProtoDUNE SP Detector ready for operations 17‐Jan‐19T2 MS ‐ Interface Agreement with all Detector Subgroups Complete 21‐Feb‐19T2 MS ‐ Far Detector Design Completed and Ready for Baseline 13‐Aug‐19T2 MS ‐ Collaboration decision on the Detector #2 Technology 10‐Jan‐21T2 MS ‐ Detector #1 Commissioning Complete 31‐Jul‐25T2 MS ‐ Detector #2 Commissioning Complete 18‐Dec‐26

Page 10: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

T3 Milestone Changes – CR140

10 20-DEC-2016 Jolie Macier | DUNE PMG

Milestone Description Start Finish Revise / Add T3 Milestones

T3 MS - Photon Det Technology selection 15-Dec-16* T3 MS - ProtoDUNE SP PD Technology selection

T3 MS - ProtoDUNE Design reviews completed 23-Mar-17* T3 MS - ProtoDUNE SP Design Reviews Complete

T3 MS - ProtoDUNE SP Cryostat Installation Complete

T3 MS - ProtoDUNE SP APA #1 Arrives @ CERN

T3 MS - ProtoDUNE SP First APA Production Electronics @ CERN

T3 MS - ProtoDUNE SP First APA Installed in Cryostat

T3 MS -Full Scale Prototype APA complete 27-Jul-17* T3 MS - ProtoDUNE SP Detector Production Complete

T3 MS - ProtoDUNE SP First Row of APAs Ins talled in Cryostat

T3 MS - ProtoDUNE SP Fourth APA Installed in Cryostat

T3 MS - ProtoDUNE SP Ready to Close TCO

T3 MS - ProtoDUNE SP External Cryogenics Ready

T3 MS - ProtoDUNE SP Detector Installation Complete

T3 MS - ProtoDUNE SP Detector ready for operations 19-Oct-18* T3 MS - ProtoDUNE SP Detector ready for operations 17-Jul-18*

T3 MS - Interface Agreement with all Detector Subgroups Complete 23-Nov-18* T3 MS - Interface Agreement with all Detector Subgroups Complete 23-Nov-18*

T3 MS - Far Detector Design Completed and Ready for Baseline 15-May-19* T3 MS - Far Detector Design Completed and Ready for Baseline 26-Jun-19*

T3 MS - Collaboration decision on the Detector #2 Technology 12-Oct-20*

T3 MS - Detector #1 Commissioning Complete 02-May-25* T3 MS - Detector #1 Commissioning Complete 02-May-25*

T3 MS - Detector #2 Commissioning Complete 19-Sep-26* T3 MS - Detector #2 Commissioning Complete 19-Sep-26*

T3 MS - Detector #3 Commissioning Complete 12-Nov-27* T3 MS - Detector #3 Commissioning Complete 12-Nov-27*

T3 MS - Detector #4 Commissioning Complete 26-May-29* T3 MS - Detector #4 Commissioning Complete 26-May-29*

Added production & installation milestones

Page 11: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

T4 Milestone Changes – CR140

11 20-DEC-2016 Jolie Macier | DUNE PMG

Current Scheduled Milestone New MilestonesT4 MS - FY16 Funds Available T4 MS - FY16 Funds AvailableT4 MS - TPC/Cryostat Interface Defined T4 MS - TPC/Cryostat Interface DefinedT4 MS - Stakeholders Submit Requirements & Interfaces for FSCF T4 MS - Stakeholders Submit Requirements & Interfaces for FSCFT4 MS - UK Funding available (if not rebuild the schedule for APA 4) T4 MS - UK Funding available (if not rebuild the schedule for APA 4)T4 MS - Stakeholders Submit Updated Requirements & Interfaces for FSCF Design Commencement

T4 MS - Stakeholders Submit Updated Requirements & Interfaces for FSCF Design Commencement

T4 MS - Photon Det Technology selection T4 MS - Photon Det Technology selectionT4 MS - FY17 Funds Available T4 MS - FY17 Funds Available

T4 MS - ProtoDUNE Design reviews completed

T4 MS - FY17 Funds Available for 2nd allocation T4 MS - FY17 Funds Available for 2nd allocationT4 MS - ProtoDUNE SP ASIC Production readiness reviewT4 MS - ProtoDUNE SP Submission of Production ASIC FabricationT4 MS - ProtoDUNE SP Feedthrough Production readiness reviewT4 MS - ProtoDUNE SP PD Production Readiness ReviewT4 MS - ProtoDUNE SP FNAL Cold Electronics Integration Test-stand Operational

T4 MS - Stakeholders Written Approval of 30% FSCF Final Design Documents T4 MS - Stakeholders Written Approval of 30% FSCF Final Design DocumentsT4 MS - Stakeholders Submit FINAL Requirements & Interfaces for FSC F T4 MS - Stakeholders Submit FINAL Requirements & Interfaces for FSC F

T4 MS - ProtoDUNE SP BNL Cold Electronics Integration Test-stand OperationalT4 MS - ProtoDUNE SP FEMB Production readiness review

T4 MS - ProtoDUNE SP Submission of Production FEMB FabricationT4 MS - ProtoDUNE SP CPA Production r eadines s rev iew c ompleteT4 MS - ProtoDUNE SP FC Top/Bottom pr oduction readiness review completeT4 MS - ProtoDUNE SP FC Endwall production readiness review completeT4 MS - ProtoDUNE SP Ash River Trial Assembly Complete

T5 MS - ProtoDUNE SP Start InstallationT4 MS - FY17 Funds Available for 3rd allocation T4 MS - FY17 Funds Available for 3rd allocation

T4 MS - ProtoDUNE SP 35ton HV Tes t ( Phas e 1) CompleteT4 MS - ProtoDUNE SP PD First 10 modules ready to ship to CERN

T4 MS - ProtoDUNE APAs Production Readiness Review T4 MS - ProtoDUNE SP APA Production Readiness Review

Added PRR, production, test stand and shipping milestones

Page 12: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

T4 Milestone Changes – CR140

12 20-DEC-2016 Jolie Macier | DUNE PMG

Current Scheduled Milestone New MilestonesT4 MS - ProtoDUNE SP Installation reviewT4 MS - ProtoDUNE SP Design Reviews CompleteT4 MS - ProtoDUNE SP Cryostat Installation CompleteT4 MS - ProtoDUNE SP APA #1 Arrives @ CERN

T4 MS - Decision to fabricate APA #7 T4 MS - ProtoDUNE SP Decision to fabricate APA #7T4 MS -Full Scale Prototype APA completeT4 MS - Stakeholders Written Approval of 60% FSCF Final Design Documents T4 MS - Stakeholders Written Approval of 60% FSCF Final Design DocumentsT4 MS - FY17 Funds Available for 4th allocation T4 MS - FY17 Funds Available for 4th allocation

T4 MS - ProtoDUNE SP First APA Production Electronics @ CERNT4 MS - ProtoDUNE SP 35ton HV Tes t ( Phas e 2) Complete

T4 MS - ProtoDUNE SP APA #2 Arrives @ CERNT4 MS - ProtoDUNE SP Cold Integration Testing of APA#1 CompleteT4 MS - ProtoDUNE SP APA #3 Arrives @ CERNT4 MS - ProtoDUNE SP First APA Installed in Cryostat

T4 MS - ProtoDUNE Installation completedT4 MS - ProtoDUNE SP Detector Production Complete

T4 MS - FY18 Funds Available T4 MS - FY18 Funds Available

T4 MS - ProtoDUNE SP Decision on APA ConfigurationT4 MS - ProtoDUNE SP APA #4 Arrives @ CERNT4 MS - ProtoDUNE SP First Row of APAs Ins talled in Cryostat

T4 MS - Stakeholders Written Approval of 100% FSCF Final Design Documents T4 MS - Stakeholders Written Approval of 100% FSCF Final Design DocumentsT4 MS - ProtoDUNE SP APA #5 Arrives @ CERNT4 MS - ProtoDUNE SP APA #6 Arrives @ CERNT4 MS - ProtoDUNE SP Fourth APA Installed in CryostatT4 MS - ProtoDUNE DP Installation completed

T4 MS - ProtoDUNE TPC Construction Complete

T4 MS - ProtoDUNE SP External Cryogenics ReadyT4 MS - ProtoDUNE SP Ready to Close TCOT4 MS - ProtoDUNE SP Detector Installation Complete

T4 MS - ProtoDUNE SP Detector ready for operations T4 MS - ProtoDUNE SP Detector ready for operationsT4 MS - ProtoDUNE SP Detector Start of Commissioning T4 MS - ProtoDUNE DP Detector Start of CommissioningT4 MS - Interface Agreement with all Detector Subgroups Complete T4 MS - Interface Agreement with all Detector Subgroups CompleteT4 MS - FY19 Funds Available T4 MS - FY19 Funds Available

T4 MS - Far Detector Design Completed and Ready for Baseline T4 MS - Far Detector Design Completed and Ready for Baseline

Added installation milestones

Page 13: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

ProtoDUNE-SP Tracking Milestones

13 20-DEC-2016 Jolie Macier | DUNE PMG

LEGEND:  Completed milestones = green * delayed, unaccomplished milestones = red (only in future) * on‐time projected milestones = black

June

July

August

Septem

ber

Octob

erNovem

ber

Decembe

rJanu

ary

Februa

r y

Task Responsible

Original Deadline

Projected Completion

Actual Completion Comments Nov2016 (12/8) status Activity

EHN1 MilestonesBeneficial Occupancy of EHN1 Fowler Aug‐16 Sep‐16 Complete cryostat exoskeleton SP Fowler Nov‐16 Dec‐16 will be completed in DecemberClean Room Installation Complete Fowler Jan‐17 DAQ ProtoDUNE‐SP DAQ milestones revised, December 2016DAQ proposal (core elements)  approved TB Barr May‐16 Jul‐16 DAQ define specifications of new RTM and firmware Graham Aug‐16 Aug‐16 13122.03.01.07.215

Revised RCE firmware ready for VST Graham Sep‐16 Nov‐16 complete; confirmed with M. Graham 11/15 13122.03.01.07.215

ProtoDUNE prototype RTM x3  fabricated Graham Oct‐16 Aug‐16 ProtoDUNE RCE+WIB Timing system interface defined Barr Jun‐16 Jun‐16 ProtoDUNE Timing system design complete Barr Aug‐16 Sep‐16 13122.03.01.07.255

DAQ proposal online software suite approved TB Barr Jul‐16 Oct‐16

Slow control preliminary design complete Barr Sep‐16 RCE Ready for APA testing essy, Lehmann M Mar‐17artDAQ ready for APA testing essy, Lehmann M Feb‐17 Timing system ready for APA testing essy, Lehmann M Feb‐17 Photon Detector SPDecision on SiPM ganging Blucher Jun‐16 Aug‐16 13122.05.01.05.250

Specification for SSP modifications available Djurcic Jul‐16 Dec‐16 complete; presentation 12/6 @ FNALDip Coated Bar Acrylic fabrication complete Toups Jul‐16 Sep‐16 13122.05.01.05.695PD design Review Mualam Aug‐16 Aug‐16 Dip Coated Bar Prototype production started Toups Dec‐16 Dec‐16 complete, December 2016 13122.05.01.05.725Procure WLS plate blanks Mufson Jan‐17 Dip Coated Bar Prototype production complete Toups Feb‐17 13122.05.01.05.725

2016 ###

milestone

Few November milestones; November status includes comment on December progress

Page 14: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

ProtoDUNE-SP Tracking Milestones

14 20-DEC-2016 Jolie Macier | DUNE PMG

Cold Electronics SPFEMB prototype V1 production complete HC/JF Aug‐16 Sep‐16 13122.06.01.01.120FEMB prototype V1 testing complete HC/JF Oct‐16 Dec‐16 13122.06.01.01.125FEMB prototype V2 production complete HC/JF Feb‐17 13122.06.01.01.130FE ASIC prototype P1 fabrication complete HC Jun‐16 Jul‐16 13122.06.01.04.110FE ASIC prototype P2 submitted for production HC Oct‐16 FE ASIC prototype P2 production complete HC Jan‐17 Nov‐16 complete, delivered in NovemberADC ASIC prototype P1 submitted for production HC Feb‐16 Jul‐16 ADC ASIC prototype P1 production complete HC Oct‐16 Nov‐16 completeFeedthru mechanical design finished RH Jul‐16 Jul‐16 Cables ordered HC/LB Oct‐16 Jan‐17 Cables tested and delivered to CERN

Power supplies ordered  LB/TS Oct‐16 Dec‐16 Power supplies tested and delivered to CERNPrototype feedthrus available for noise testing HC Nov‐16 Dec‐16 WIB prototype P1 available for testing HC/JF Aug‐16 Aug‐16 WIB prototype P2 available for testing HC/JF Jan‐17 APAFinalize APA design Paulos Mar‐16 Jul‐16 Winding machine mech. Construction complete Paulos Apr‐16 Jun‐16 13122.02.07.01.110Design review APA Paulos Jul‐16 Jul‐16 UK funding available for APA construction May‐16 Jun‐16 13122.02.07.01.185MSIntegrated US‐UK APA plan available Aug‐16 Sep‐16 ProtoDUNE Build/assemble APA process prototype compl Paulos Aug‐16 Oct‐16 13122.02.07.01.170

APA frame #1 with mesh complete Paulos Sep‐16 Dec‐16

complete in November, but disassembled for inspection; will be complete in December 13122.02.07.01.225

APA #1 Start winding Paulos Oct‐16 Dec‐16 13122.02.07.01.250APA #1 Winding and tension testing complete Paulos Feb‐17 13122.02.07.01.345APA Production Readiness Review Paulos Feb‐17 Mar‐17 13122.02.07.01.230APA #1 testing at PSL complete and delivered to CERN Paulos May‐17 13122.02.07.01.380APA frame #2 complete with mesh Paulos Jan‐17 13122.02.07.01.382Start UK winding machine production Paulos Oct‐16 Oct‐16 13122.02.07.01.240CPA/FC/HV SP

LEGEND:  Completed milestones = green * delayed, unaccomplished milestones = red (only in future) * on‐time projected milestones = black

June

July

August

Septem

ber

Octob

erNovem

ber

Decembe

rJanu

ary

Februa

r y

Task Responsible

Original Deadline

Projected Completion

Actual Completion Comments Nov2016 (12/8) status Activity

2016 ###

milestone

Page 15: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

ProtoDUNE-SP Tracking Milestones

15 20-DEC-2016 Jolie Macier | DUNE PMG

LEGEND:  Completed milestones = green * delayed, unaccomplished milestones = red (only in future) * on‐time projected milestones = black

June

July

August

Septem

ber

Octob

erNovem

ber

Decembe

rJanu

ary

Februa

r y

Task Responsible

Original Deadline

Projected Completion

Actual Completion Comments Nov2016 (12/8) status Activity

2016 ###

milestone

g pCPA/FC/HV SPCPA build and test prototype Guarino Jun‐16 Aug‐16 Design FNAL HV test detector finished Guarino Jul‐16 Jul‐16 CPA/FC/HV design documents available  Guarino Aug‐16 Sep‐16 CPA Design/Build mockup for Ash River Guarino Sep‐16 Sep‐16 13122.02.07.02.170CPA/FC/HV Design review  Guarino Oct‐16 Nov‐16 complete

Test assembly of FNAL HV test  complete Guarino Oct‐16 Feb‐17 shift to February (phase 1)CPA construction facility at ANL available  Guarino Oct‐16 Aug‐16 CPA Assembly/Test facility at CERN available  Jan‐17 Decide FC profile material Guarino Jun‐16 Dec‐16 FC top/bottom mockup complete Guarino Sep‐16 Aug‐16 13122.02.07.03.200FC top/bottom full scale prototype done  Guarino Sep‐16 Sep‐16 FC top/bottom production facility  ready Guarino Oct‐16 Jan‐17 FC ground plane procurement done Guarino Nov‐16 Jan‐17 FC Top/Bottom ready to start production Guarino Jan‐17 Feb‐17 Build End wall mockup  Guarino Oct‐16 Aug‐16 13122.02.07.03.190FC Build Endwall prototype complete Guarino Oct‐16 Nov‐16 complete 13122.02.07.03.350End wall fabrication facility ready Guarino Oct‐16 Jan‐17 13122.02.07.03.550Start EndWall FC production  Guarino Oct‐16 Feb‐17 13122.02.07.03.610FC Build First set of Endwall modules Guarino Dec‐16 Feb‐17 13122.02.07.03.610FC top/bottom fabrication complete Guarino Apr‐17 Jun‐17 13122.02.07.03.620CPA/FC/HV Production Readiness Review Guarino Feb‐17

Installation SP

Trial assembly facility ready for installation tests Miller Nov‐16 Oct‐16 13122.04.06.125All Parts delivered to Ash River for trial assembly  Miller Nov‐16 Nov‐16 complete 13122.04.06.125Complete design of integrated cold test facility (ICTF) Zani Nov‐16 Dec‐16 will be complete in December 13122.07.02.100

Page 16: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

Far Detector Activities

• Refining plan toward CD 2/3 in 2019• FY18 schedule review (upcoming change request)• FY19 schedule review (upcoming change request)

• Integration activities with FSCF team• Cryostat top plate optimization – EFIG, 6 December

16 20-DEC-2016 Jolie Macier | DUNE PMG

Page 17: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

Far Detector Activities

• Cryostat top plate optimization – EFIG, 6 December

17 20-DEC-2016 Jolie Macier | DUNE PMG

Page 18: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

SPPD Design & Construction – Subsystem Reports

APA• Process prototype winding complete; using for soldering training• APA#1 frame reassembled & survey complete• UK team visit @ PSL, 30 Nov – 2 December• Internal production readiness review week of 5 December

Photon Detector• Testing dip-coated bars in Tallbo after warm testing at MIT• Radiator bars (40; Eljen) received• 1000 SiPMs received; still need to be tested

18 20-DEC-2016 Jolie Macier | DUNE PMG

Page 19: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

SPPD Design & Construction – Subsystem Reports

Cold Electronics• Testing P2 FE ASICs continues• Working to setup the WIB teststand• Flange testing ongoing• Electronics teststand at DAB set-up continues

CPA/FC/HV• PC4 HV test

• LAPD full• Field cage shipping from William & Mary on 20 Dec• Have received the HV power supply, feedthrough, cables, filters from UCLA• KSU will test and ship the resistor network• Cameras arrived from CERN

• Installation planning for CPA/FC designs, movement into and within cryostat

19 20-DEC-2016 Jolie Macier | DUNE PMG

Page 20: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

SPPD Design & Construction – Subsystem Reports

Installation / Integration• Intend to deliver DSS documentation to CERN in January• Installation Review planned for April 2017 • Clean room layout design underway with CERN; analyzing

height requirement between monorail & DSS bridge beams• Engineering meeting @ Ash River Trial Assembly, 14-16

December• Execute lifting movements for APA, FC, CPA• Review of CPA and FC drawings/analysis/assembly/installation and 

documentation• Review interface between FC and APA, use prototype latches, hoist on Beam B 

to lower and raise FC 

20 20-DEC-2016 Jolie Macier | DUNE PMG

Page 21: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

21 20-DEC-2016

Jolie Macier | DUNE PMG

Page 22: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

22 20-DEC-2016 Jolie Macier | DUNE PMG

Page 23: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

23 20-DEC-2016

Jolie Macier | DUNE PMG

Page 24: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

SPPD On-Site

• Installation• New Integration, Testing & Installation meeting initiated in December• Monitoring cryostat installation progress• Visit to Ash River, 12/13‐12/16• Visit to BNL, this week 

• DAQ & Instrumentation• Revised milestones• Cryogenic instrumentation definition underway • Planning for external cosmic ray tagging system

24 20-DEC-2016 Jolie Macier | DUNE PMG

Page 25: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

SPPD On-Site – material for cold structure, 12/09/16

25 20-DEC-2016 Jolie Macier | DUNE PMG

Page 26: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

SPPD On-Site – roof shimming, bolting, 12/09/2016

26 20-DEC-2016 Jolie Macier | DUNE PMG

Page 27: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

Dual-Phase - Technical Progress

• 1x1x3 – filling delayed until January due to multiple factors; anticipate operation to begin ~25 January

• Piping purge scheduled to be complete by 5 December

• During CERN winter shutdown, system will remain with gas purge in closed loop purification

• Cool down and filling to occur in January after CERN reopens

• ProtoDUNE-DP final design to be complete by end of November

• Anticipating design review in March 2017

• Milestones incorporated into DUNE international schedule

27 20-DEC-2016 Jolie Macier | DUNE PMG

Page 28: DUNE Project Status - INDICO-FNAL (Indico) · WBS (2), Work Package.WBS (3), Work Package.WBS (4), Work PBudget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 11,654

Upcoming Events

• DUNE Collaboration Meeting, January 23-26 at CERN• DOE IPR Progress Review, week of February 27 at FNAL• CAD integration meeting, March 2-3 at FNAL• Installation Review, April 2017 at CERN• Production Readiness Reviews, TBD at production sites• Instrumentation Review, TBD • ProtoDUNE-DP Design Review, March 2017 at CERN• LBNC Review, March 23-25, 2017 at FNAL

28 20-DEC-2016 Jolie Macier | DUNE PMG