24
BIMT/4 Meeting Report DRAFT REPORT THE 4 TH BANGLADESH INDIA MYANMAR THAILAND ATM COORDINATION GROUP MEETING (BIMT/4) 17-19 August 2016, Thailand ------------------------------------------------- Introduction 1 The Fourth Bangladesh India Myanmar Thailand ATM Coordination Group Meeting (BIMT/4) was held on 17 19 August 2016 at the Aetas Lumpini Hotel, Bangkok, Thailand. The meeting was attended by 41 participants from ANSPs, regulators, airspace users, as well as IATA and ICAO. The participant list along with their organizations can be found in Attachment 1. 2 Mrs. Sirikes Niemloy, Vice President Air Traffic Management, Aeronautical Radio of Thailand, Ltd (AEROTHAI) presided as the chairperson for the meeting. She was assisted by Mr. Suvichan Sthitgitpichead, Director of Network Operations ATM Centre, AEROTHAI as moderator and acting chairperson when needed. In the opening speech, Mrs. Sirikes welcomed all delegates to Bangkok and remarked that this multi-state coordination is a key platform to discuss various pressing air traffic management issues in the sub-region and is an important contribution toward the seamless and harmonized Asia-Pacific sky as envisioned in the APAC Seamless ATM Plan. The topics to be discussed, ranging from route structure design to ATM enhancement initiatives, are beneficial to the improvement of ATM operations among the States present. Mrs. Sirikes thus wished the meeting to be a fruitful one and hoped that this level of coordination between States will be continued for the years to come. 3 This Meeting Report summarizes key points agreed at the meeting and forms the basis for further coordination to move forward with the implementation effort. Relevant documents referred are attached to this report. Other related documents and presentations can be downloaded at http://tinyurl.com/bimt-4-thailand.

DRAFT REPORT - aaians.org to A03... · DRAFT REPORT THE 4TH BANGLADESH ... are beneficial to the improvement of ATM operations among ... Conclusion BIMT/4-3 – BOBCAT Terminology

  • Upload
    lamphuc

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

BIMT/4

Meeting Report

DRAFT REPORT

THE 4TH BANGLADESH – INDIA – MYANMAR – THAILAND

ATM COORDINATION GROUP MEETING (BIMT/4)

17-19 August 2016, Thailand -------------------------------------------------

Introduction

1 The Fourth Bangladesh – India – Myanmar – Thailand ATM Coordination Group

Meeting (BIMT/4) was held on 17 – 19 August 2016 at the Aetas Lumpini Hotel, Bangkok,

Thailand. The meeting was attended by 41 participants from ANSPs, regulators, airspace users,

as well as IATA and ICAO. The participant list along with their organizations can be found in

Attachment 1.

2 Mrs. Sirikes Niemloy, Vice President – Air Traffic Management, Aeronautical Radio

of Thailand, Ltd (AEROTHAI) presided as the chairperson for the meeting. She was assisted

by Mr. Suvichan Sthitgitpichead, Director of Network Operations ATM Centre, AEROTHAI

as moderator and acting chairperson when needed. In the opening speech, Mrs. Sirikes

welcomed all delegates to Bangkok and remarked that this multi-state coordination is a key

platform to discuss various pressing air traffic management issues in the sub-region and is an

important contribution toward the seamless and harmonized Asia-Pacific sky as envisioned in

the APAC Seamless ATM Plan. The topics to be discussed, ranging from route structure design

to ATM enhancement initiatives, are beneficial to the improvement of ATM operations among

the States present. Mrs. Sirikes thus wished the meeting to be a fruitful one and hoped that this

level of coordination between States will be continued for the years to come.

3 This Meeting Report summarizes key points agreed at the meeting and forms the basis

for further coordination to move forward with the implementation effort. Relevant documents

referred are attached to this report. Other related documents and presentations can be

downloaded at http://tinyurl.com/bimt-4-thailand.

2

BIMT/4

Meeting Report

Table of Contents

Introduction ............................................................................................................................................ 1

List of Attachments ................................................................................................................................. 2

List of Conclusions ................................................................................................................................... 3

List of Action Items ................................................................................................................................. 4

Agenda Item 1: Adoption of Agenda ...................................................................................................... 5

Agenda Item 2: Review of BIMT/3 Action Items ..................................................................................... 5

Agenda Item 3: Air Traffic Situation Update ........................................................................................... 5

Agenda Item 4: BIMT Collaborative Route Design .................................................................................. 7

Agenda Item 5: ATM Matters ............................................................................................................... 10

Agenda Item 6: Bi-Lateral Meetings ..................................................................................................... 19

Agenda Item 7: Future Direction .......................................................................................................... 23

Agenda Item 8: Any Other Business...................................................................................................... 23

Closing of the Meeting .......................................................................................................................... 24

List of Attachments

Attachment Number Detail

Attachment 1 List of Participants

Attachment 2 Table of Action Items

Attachment 3 Revised BOBCAT AIP/AIP Supplement Template

Attachment 4 Outcome of Multi-Lateral Meeting between MAAR, Bangladesh,

India, Myanmar, IATA and ICAO,

Attachment 5 Outcomes of Bi-Lateral Meeting between Bangladesh – India, and

Tri-Lateral Meeting between Bangladesh – India - Myanmar

Attachment 6 Outcome of Bi-Lateral Meeting between India – Myanmar

Attachment 7 Draft AIP Supplement on Operating Procedures for RNP10

Operations on ATS Routes L507, P646, N895, L524 and L301

Attachment 8 Rocket Launch Coordination Points of Contact

3

BIMT/4

Meeting Report

List of Conclusions

Conclusion BIMT/4-1 – Air Traffic Situation Update for BIMT Meeting

The BIMT/4 meeting agreed that air traffic situation updates shall be added to the list of

Agenda Items to be discussed at all subsequent BIMT meetings. This will ensure that Member

States are kept aware of the air traffic demand situation in the sub-region and can

collaboratively discuss initiatives to handle the growing air traffic demand appropriately.

Conclusion BIMT/4-2 – Standard Operating Procedure for Diversion Management

The BIMT/4 meeting agreed to jointly develop Standard Operating Procedure (SOP) on cross-

border Diversion Management to ensure safe and effective handling of aircraft diversions,

particularly those that transcends across FIR borders. This will be added to the list of Agenda

Items to be discussed at BIMT/5.

Conclusion BIMT/4-3 – BOBCAT Terminology Standardization

The BIMT/4 meeting agreed on the proposed change of BOBCAT terminologies to match

those of global ATFM standards, particularly introducing the use of Calculated Take-Off

Time (CTOT) in place of the existing Allocated Wheels-Up Time (AWUT) along with other

related terminologies. The meeting agreed to use either December 2016 or January 2017

AIRAC cycle as an effective date for the change.

Conclusion BIMT/4-4 – BIMT Surveillance Data Sharing

The BIMT/4 meeting agreed to focus more efforts on improving surveillance coverage in the

North Bay of Bengal through surveillance data sharing. As the first steps to that, the following

has been agreed:

India and Myanmar shall expedite their process of ADS-B data sharing; and

Bangladesh, India, Myanmar would consider surveillance data sharing between them

Conclusion BIMT/4-5 – Large Height Deviation (LHD) Online Reporting

The BIMT/4 meeting agreed with MAAR’s proposed online LHD reporting system, which will

also ensure LHD reports are automatically sent, at the time of submission, to all relevant ATS

units as well as MAAR and BOBASMA. The online reporting system is in the testing and fine-

tuning phase and should be ready by October 2016.

*Note: Bangkok ACC has a separate reporting coordination with MAAR, though the reports

will still be entered into the system

Conclusion BIMT/4-6 – Large Height Deviation (LHD) Coordination

Bangladesh, India, Myanmar agreed on an immediate coordination between the point of

contact and/or the watch supervisor on-duty, which shall be within 3 days from the date of

occurrence. Upon initial contact by the unit where the LHD occurred, the contacted unit shall

respond within 7 days to discuss the matter. Once an agreement is reached among the relevant

units, a formal LHD report will be submitted.

Conclusion BIMT/4-7 – Periodic Teleconferences on Resolving LHDs and Other ATS

Issues

Bangladesh, India, Myanmar agreed to hold periodic bi or tri-lateral teleconferences between

ATS authorities to discuss LHD occurrences and mitigation measures along with other ATS

issues.

4

BIMT/4

Meeting Report

Conclusion BIMT/4-8 – BIMT Route Structure Development, Phase 1

The BIMT/4 meeting agreed on the implementation new RNAV ATS routes L524, M506 and

L877 route structures as shown in Figure 4 and Table 4 during Phase 1 of BIMT Route

Structure Development initiative. The target implementation date of these routes is 8

December 2016. Associated work plan (Table 5) for this implementation has been discussed

and will be followed accordingly.

Conclusion BIMT/4-9 – BIMT Route Structure Development, Phase 2

The BIMT/4 meeting agreed on the implementation of routes structures as shown in Figure 5

during Phase 2 of BIMT Route Structure Development initiative. Detail regarding these routes

and work plan will be discussed at the next BIMT meeting (BIMT/5).

List of Action Items

Action Item BIMT/4-1 – Air Traffic Situation Update

BIMT Member States will take the task of evaluating air traffic demand situation within their

respective FIRs and prepare the information to be presented at BIMT/5 meeting.

Action Item BIMT/4-2 – Development of Standard Operating Procedure for Diversion

Management

BIMT Member States and IATA will take the task of further assessing the occurrences of cross-

border diversions and prepare input to the discussion on this Agenda Item during BIMT/5

meeting.

Action Item BIMT/4-3 – BOBCAT Terminology Standardization

Thailand will take the task of coordinating with other States in the region involved with

BOBCAT ATFM operations to explore agreement to the terminology standardization and the

timeframe of December 2016 or January 2017 AIRAC cycle for such changes.

Action Item BIMT/4-4 – Bangladesh, India, Myanmar Surveillance Data Sharing Process

Bangladesh, India, Myanmar will initiate the process of surveillance data sharing and update

the status at BIMT/5 meeting.

Action Item BIMT/4-5 – LHD Online Reporting Instructional Package MAAR, upon completion of system tuning and testing, will send Member States an

instructional package on the new LHD Online Reporting System to help States familiarize

themselves with the platform, including a link to access the system for States to try out the

system.

Action Item BIMT/4-6 – LHD Coordination E-Mail Template India will provide a reporting template for the initial e-mail exchange between ATS units

regarding LHD occurrences.

5

BIMT/4

Meeting Report

Agenda Item 1: Adoption of Agenda

1.1 The meeting reviewed and adopted the provisional agenda prepared by

AEROTHAI. Key discussions include air traffic situation update, collaborative route design,

ATM system implementation, ATS coordination, air traffic flow management (ATFM), AIDC,

surveillance data sharing, and safety reporting. There were also bi-lateral meetings organized

between State-pairs to discuss in-depth bi-lateral issues; outcomes from these side meetings

are also included in this report.

Agenda Item 2: Review of BIMT/3 Action Items

2.1 The meeting reviewed the 4 conclusions from the previous meeting (BIMT/3).

These conclusions are captured in BIMT/3 meeting report and also shown in this BIMT/4

meeting’s main presentation; both documents are downloadable from the link shown in the

Introduction above. The conclusions include matters related to PBN route structure design,

longitudinal separation at transfer of control points, airspace closure notification, and Large

Height Deviations (LHD) reporting. The meeting had no further feedback on conclusions

captured.

2.2 The meeting also reviewed the 6 action items from the previous meeting

(BIMT/3). These action items, along with additional ones generated from this meeting, are

captured in the Table of Action Items attached to this report (Attachment 2). As the 6 BIMT/3

action items are related to the various Agenda Items discussed at this meeting, they were

deliberated and concluded during their relevant discussions. The attached Table of Action

Items presents latest status of all Action Items following this BIMT/4 meeting.

Agenda Item 3: Air Traffic Situation Update

Thailand Air Traffic Situation Update

3.1 Thailand presented an update on air traffic demand within Bangkok FIR, which

has been seeing a steady growth over the years and a forecasted 7% average annual growth rate

for the next decade (FY 2016 – 2026). Majority of the growth is from a surge of traffic between

destinations in Thailand and China; however, traffic in other directions has also been rising

consistently. Of concern to the BIMT group is the western traffic which saw a 6% international

traffic growth over the past year.

3.2 With the steadily-rising air traffic demand, airspace sectors in Bangkok FIR are

beginning to face serious demand-capacity imbalance challenges. Similarly, major airports

such as VTBS, VTBD, VTCC, and VTSP are also seeing the same trend with ATS units at

those airports operating at or near maximum capacity during peak hours of the days. This

prompts AEROTHAI to initiate and engage in various capacity enhancement and traffic

demand management efforts including ATM system modernization and cross-border air traffic

flow management (ATFM) project.

3.3 Details of the traffic situation in Bangkok FIR can be found in the presentation

downloadable from the web link mentioned above.

6

BIMT/4

Meeting Report

Myanmar Air Traffic Situation Update

3.4 Myanmar informed the meeting of the consistent growth in air traffic demand

no different from that seen by other Member States in the Asia-Pacific region. Within Yangon

FIR, military operations continue to present challenges to enhancing airspace capacity and the

Myanmar government is in the process of alleviating this problem.

3.5 Myanmar also informed the meeting of the plan to establish a new Yangon

International Airport (?) located approximately 60 kilometers north of the existing one. The

construction of this new airport is planned to commence by the end of 2016 and is planned to

be in operations by 2022, barring any unforeseen delays due to safety assessment process. It is

envisioned that the new airport will be used primarily for international traffic, while the

domestic traffic will continue to use the existing one.

India Air Traffic Situation Update

3.6 India presented an update on the PBN route structures in India, which currently

sees 43 international RNP10 routes along with a number of domestic PBN routes with

specifications ranging from RNP10 to RNAV5 as well as RNP2. Additionally, India also

informed the meeting of the newly finalized National Civil Aviation Policy 2016 (NCAP

2016) which aims to establish an integrated aviation eco-system leading to significant civil

aviation growth that can contribute to economic prosperity. The different focus areas in the

NCAP 2016 are detailed in the associated presentation.

3.7 Additionally, India has also been upgrading airspace around airports with hourly

traffic of 20 aircrafts or more to be Class C Airspace equipped with both primary and secondary

surveillance radar. Trial operation for this has been ongoing since 15 August 2016 at Chennai,

Hyderabad and Cochin TMAs.

3.8 India also informed the meeting of an agreement with Bangladesh to establish

5 new ATS routes between Kolkata and Dhaka FIRs. This is elaborated in detail in the Agenda

Item 4.

3.9 Details of the update provided can be found in the presentation downloadable

from the web link mentioned above.

Traffic Situation Update for Future Meetings

3.10 To enhance situational awareness on traffic demand within the sub-region, the

meeting moderator requested that air traffic demand situation update be given by each Member

State in the future BIMT meetings. The request was accepted by the meeting and is captured

here as Conclusion BIMT/4-1 and Action Item BIMT/4-1

Conclusion BIMT/4-1 – Air Traffic Situation Update for BIMT Meeting

The BIMT/4 meeting agreed that air traffic situation updates shall be added

to the list of Agenda Items to be discussed at all subsequent BIMT meetings.

This will ensure that Member States are kept aware of the air traffic demand

situation in the sub-region and can collaboratively discuss initiatives to

handle the growing air traffic demand appropriately.

7

BIMT/4

Meeting Report

Action Item BIMT/4-1 – Air Traffic Situation Update

BIMT Member States will take the task of evaluating air traffic demand

situation within their respective FIRs and prepare the information to be

presented at BIMT/5 meeting.

Agenda Item 4: BIMT Collaborative Route Design

Bangladesh – Discussion Paper on Collaborative Route Design

4.1 Bangladesh presented a discussion paper on collaborative route design between

Bangladesh and India as a follow up on Action Item BIMT/3-1. Through bi-lateral

coordination, 5 new route structures over Dhaka FIR have been agreed and shown as follows:

Figure 1 - Route Structures Agreed by Bangladesh and India

4.2 Details of these routes will be discussed in the bi-lateral meeting between

Bangladesh and India during their bi-lateral meeting. .

4.3 Bangladesh also informed the meeting that, to support the collaborative

establishment of North Bay of Bengal ATS routes L507N (L507), L507S (M509), and P646,

CAA Bangladesh has coordinated with the military authority to realign the danger areas VGD-

31, VGD-32, VGD-33, VGD-34, and VGD-35 to ensure proper spacing between the areas and

ATS routes. The proposed areas and route structures are shown below:

Figure 2 - Proposed Realigned Danger Areas Bangladesh

8

BIMT/4

Meeting Report

4.4 Due to the realignment of these danger areas, Bangladesh requested the meeting

to consider shifting a segment of the planned L507S (M509) and P646 to the south to ensure

separation from AREA-3, AREA-4, AREA-5 and AREA-6 shown in the figure. This would be

discussed further in their bi-lateral meeting.

4.5 The discussion paper with more information can be downloaded from the web

link mentioned above.

India – Information on Bangladesh Danger Area Activities in Kolkata FIR

4.6 India presented information from NOTAM A0173/16 issued by Bangladesh

regarding the Bangladesh Navy’s firing activities within the areas VGD-31, 32, 34 between

0000 – 1700 and 2200 – 2359 UTC in August 2016. The activities could present safety risk to

aircraft operating on ATS routes near those areas, as shown in the figure below:

Figure 3 - Danger Areas affected by Bangladesh Navy Activities

4.7 In light of these activities, India noted the importance of appropriate

coordination procedure with respect to activation, deactivation, and suspension of the activities

and the danger areas between relevant authorities, e.g. in the case of Bangladesh Navy the

coordination procedure between Bangladesh Navy and Kolkata ACC should be in place. In

addition, proper vertical segregation of the danger areas should also be provided in lieu of

blanket airspace closures.

4.8 India also proposed for the establishment of L507N (L507), L507S (M509), and

P646 to remain pending subjecting to proper development of danger area coordination

procedures aforementioned.

Myanmar – Route Structure in the North Bay of Bengal: BIMT Route Structure

4.9 Myanmar presented information on the historical progress for implementation

of new BIMT route structures spanning Bangkok, Yangon, Kolkata, and Dhaka FIRs including

establishment of new RNAV ATS routes L524 and M509. M509 was pending after safety

assessment while L524 was agreed to be implemented. PfA to BANP of L524 was sent to

ICAO APAC by AAI. (to be elaborated by Thailand in subsequent section).

9

BIMT/4

Meeting Report

4.10 Myanmar informed that, due to the recent transition from 2-sector to 4-sector

operations in May 2016 (to be discussed during Agenda Item 5.1), Myanmar is facing

challenges in changing route structures and will thus need to adopt phased approach to route

structure implementation. The proposal called for implementation of L524, M506, and L877

first before implementing other routes such as L507S (M509) subsequently. For the first phase

of implementation, Myanmar proposed AIRAC cycle of 8 December 2016 as effective date.

4.11 Detailed information provided by Myanmar can be found in the presentation

downloadable from the web link mentioned above. Additionally, Myanmar would conduct bi-

lateral meeting with Thailand to discuss other issues pertaining to route development and

operating procedures.

Thailand – Route Structure in the North Bay of Bengal: BIMT Route Structure

4.12 Following the discussion and agreement in BIMT/3 and taking into account

readiness of Member States; Thailand proposed a phased implementation for the different route

structures, with a focus on L524, M506, and L877 in the first phase as shown below:

Figure 4 - L524, M506, L877 Routes

4.13 For these flights, the proposed directions are as follows:

Routes Waypoints Conditions

10

BIMT/4

Meeting Report

L524 NAGPUR –

KAMKO – BKK

- Eastbound traffic (east of KAMKO)

- Bi-directional (west of KAMKO)

M506 DWI – KAMKO Westbound traffic to join L524 after KAMKO

L877 DWI – MIGAR Eastbound traffic on L301, P762, M502 with

VTBD, VTBS as destination Table 1 - Thailand's Proposal for Route Structure

4.14 In agreement to Myanmar’s proposal of 8 December 2016 as effective date for

the first phase of implementation, Thailand also proposed a revised work plan as detailed in

the presentation.

4.15 Following the implementation of L524, M506, L877 in the first phase, the

second phase of BIMT route structure development can focus on realignment L507, P646 and

N895 and implementation of M509 appropriately.

Conclusion on BIMT Route Structure Development

4.16 Due to the various issues surrounding route structure development, the

discussions were taken forward to be conducted between various Member States during

Agenda Item 6 – Bi-Lateral Meetings. The conclusions on BIMT Route Structure Development

are recorded under that Agenda Item.

Agenda Item 5: ATM Matters

Agenda Item 5.1 – ATM System Implementation

VHF and Surveillance Redundancy in Kolkata FIR

5.1 India presented information on the surveillance coverage within Kolkata FIR

provided by 9 RADAR and 8 ADS-B stations. The system comes with 3 redundant layers as

described in the given presentation to ensure coverage for 7 ACC sectors and part of 1 Oceanic

sector.

5.2 India also presented information on the VHF communication coverage and

redundancy systems within Kolkata FIR, with 23 frequencies in service. Technical description

of the system in included in the given presentation.

5.3 Details of the information can be found in the presentation downloadable from

the web link mentioned above.

Re-Sectorization of Yangon FIR

5.4 Myanmar presented information on Yangon ACC re-sectorization to handle

increasing traffic demand and heavy ATC workload especially during peak hours. Prior to May

2016, Yangon ACC had been operating in a 2-sector configuration which proved inadequate

for the traffic demand. Thus Myanmar embarked on a project to introduce 4-sector operation

along with the ATM system upgrade, with the help from ICAO Asia-Pacific Regional Sub-

Office (ICAO RSO).

11

BIMT/4

Meeting Report

5.5 Since 26 May 2016, Yangon ACC transitioned to the 4-sector operation with

the upgraded TopSky ATM System as the backbone. The transition helped ease ATC’s

workload significantly which in turn aid in the reduction of Large Height Deviations (LHDs)

due to coordination errors.

5.6 The remaining issue, however, is the needs for more ATCs to staff the new

positions. Myanmar is in the process of recruiting and training new ATCs, while transferring

some ATCs from domestic towers to ACC sectors. The training of new ATCs has been done

in-house using a simulator to ensure ATCs are familiar with the new sector configurations.

5.7 Details of the new sector information can be found in the presentation

downloadable from the web link mentioned above.

Thailand Modernization CNS/ATM System (TMCS) Project

5.8 Thailand presented progress update from the Thailand Modernization

CNS/ATM System (TMCS) project, a project to transition the ATM system country-wide to

the upgraded TopSky ATM System in order to improve the quality of service and ensure

capability to handle the ever-increasing air traffic demand. The new ATM system will

introduce several new features and operational concept to Thailand’s air traffic service

provision. These new features include, inter alia:

Integration with air traffic flow management provision;

Stripless operations in the ACCs and electronic strip operations in the

TWRs;

AIDC;

Enhanced safety net and improved conflict detection and alert

Electronic pre-departure clearance (PDC) delivery; and

Multi-Surveillance Sensor Processing capability

5.9 The transition process is planned for 2017 – 2018 timeframe and is divided into

3 phases – Shadowing, Ghosting, and Monitoring – with detail as follows:

Transition Phase Description Planned Timeframe

Shadowing

New system is used in the background

while current system is used in traffic

service provision

Beginning April 2017

Ghosting

New system is used in traffic service

provision while current system remains

on standby and ready for operations if

needed

October 2017 – August 2018

Monitoring

New system is fully used in traffic

service provision nationwide while

being monitored to ensure smooth

operations

Mid-2018 onward

Table 2 - Thailand TMCS Transition Phases

5.10 Details of this transition plan can be found in the presentation downloadable

from the web link mentioned above.

12

BIMT/4

Meeting Report

Agenda Item 5.2 – ATS Coordination

Ground – Ground Communication Difficulty

5.11 Thailand informed the meeting of ATS coordination challenge faced during the

early days of Myanmar’s transition to 4-sector operations in Yangon FIR. Specifically,

Bangkok ACC had difficulty establishing ground-ground voice connection with the new

Yangon Sector 3 at the transfer of control point BETNO, resulting in coordination workload

and delay. The issue has since been resolved through coordination between Thailand and

Myanmar accordingly.

Diversion Management

5.12 Another issue faced recently was that of aircraft diversion, whereby; on 7

August 2016, 1 of 2 flights destined for VYYY had diverted to VTCC due to adverse weather

without prior coordination between Yangon ACC and Bangkok ACC. This resulted in ATC

confusion and needs to handle unplanned traffic. On this matter, Myanmar informed that 7

August 2016 saw a large thunderstorm cell over Yangon FIR resulting in several airport

closures and heavy ATC workload that could lead to a lapse in proper ATC-ATC coordination.

In any case, Myanmar agreed to investigate the case further and to put in place proper

mitigation measure.

5.13 On a similar note, Bangladesh also informed the meeting of an occurrence

where 6 aircrafts had diverted from Kolkata FIR into Dhaka FIR to avoid adverse weather

without prior coordination between the ACCs.

5.14 The meeting moderator also cautioned the meeting to note that a lapse in proper

coordination such as the cases discussed could result in air defense response and an unfortunate

case such as that faced by Malaysia Airlines MH17. It is therefore of utmost importance that a

proper coordination procedure be put in place to prevent such incidents.

5.15 To mitigate such occurrences, IATA requested that BIMT takes on the task of

developing joint Standard Operating Procedure (SOP) regarding Diversion Management. The

meeting agreed to the request and planned to discuss in-depth as another Agenda Item at the

next BIMT meeting. In the meantime, Member States would assess the cases discussed further

and prepared information or proposal to discuss at the next meeting appropriately. This has

been captured as Conclusion BIMT/4-4 and associated Action Item BIMT/4-2.

Conclusion BIMT/4-2 – Standard Operating Procedure for Diversion

Management

The BIMT/4 meeting agreed to jointly develop Standard Operating Procedure

(SOP) on cross-border Diversion Management to ensure safe and effective

handling of aircraft diversions, particularly those that transcends across FIR

borders. This will be added to the list of Agenda Items to be discussed at

BIMT/5.

Action Item BIMT/4-2 – Development of Standard Operating Procedure for

Diversion Management

13

BIMT/4

Meeting Report

BIMT Member States and IATA will take the task of further assessing the

occurrences of cross-border diversions and prepare input to the discussion

on this Agenda Item during BIMT/5 meeting.

Agenda Item 5.3 – Air Traffic Flow Management (ATFM)

BOBCAT Terminology Standardization and Operational Revision

5.16 Thailand presented a proposal to standardize ATFM terminologies used for

BOBCAT ATFM operations so as to ensure alignment with global ATFM standards. The issue

was initially raised during the 6th ICAO ATFM Steering Group Meeting (ATFM/SG/6),

whereby the meeting agreed that terminologies used in ATFM operations and initiatives within

Asia-Pacific should follow those defined in the Asia-Pacific Regional Framework for

Collaborative ATFM and ICAO Manual on Collaborative ATFM (Doc 9971). This will ensure

that all relevant personnel have the same understanding of terminologies regardless of the

origin of ATFM programs.

5.17 In this regard, Thailand had taken on a task to standardize terminologies used

for BOBCAT ATFM operations, specifically the introduction the following:

New Terminology Old Terminology Definition

CTOT AWUT Calculated Take-Off Time

CTO ETO Calculated Time-Over

(Waypoint)

Kabul FIR Slot Allocation

Allocated slot parameters

including:

- CTOT

- CTO at Kabul FIR

entry waypoint

- Allocated FL

- Allocated ATS route Table 3 - New BOBCAT Terminologies

5.18 To affect the change accordingly, Thailand proposed the joint revision of AIP

or AIP Supplement relevant to BOBCAT operations. The proposed revised template is attached

to this meeting report as Attachment 3. Accordingly, Thailand requested the meeting to

consider appropriate AIRAC cycle for which the revised AIP / AIP Supplement shall be made

effective and operations with revised terminologies commenced. The meeting agreed on using

either the December 2016 (8 December 2016) or January 2017 (5 January 2017) AIRAC cycle

to allow time for all relevant States to process their AIP revisions accordingly. Thailand agreed

to take the decision of the meeting and coordinate further with other States involved to ensure

the timing is acceptable. This is captured in Conclusion BIMT/4-5 and associated Action Item

BIMT/4-3

Conclusion BIMT/4-3 – BOBCAT Terminology Standardization

The BIMT/4 meeting agreed on the proposed change of BOBCAT

terminologies to match those of global ATFM standards, particularly

introducing the use of Calculated Take-Off Time (CTOT) in place of the

existing Allocated Wheels-Up Time (AWUT) along with other related

14

BIMT/4

Meeting Report

terminologies. The meeting agreed to use either December 2016 or January

2017 AIRAC cycle as an effective date for the change.

Action Item BIMT/4-3 – BOBCAT Terminology Standardization

Thailand will take the task of coordinating with other States in the region

involved with BOBCAT ATFM operations to explore agreement to the

terminology standardization and the timeframe of December 2016 or January

2017 AIRAC cycle for such changes.

5.19 In addition to standardization of terminologies, Thailand also proposed the

meeting to consider adjusting CTOT compliance window to allow for greater flexibility on the

part of departure ATS units and airspace users, taking into account aircraft’s ability to adjust

speed and time while enroute to ensure compliance with CTO at Kabul FIR entry waypoint.

The meeting was in agreement with the concept and Thailand would take the discussion further

with other relevant States in the region to explore this change.

5.20 Details of Thailand’s proposal, including proposed table of variable CTOT

compliance window, can be found in the presentation downloadable from the web link

mentioned above.

Collaborative Air Traffic Flow Management Over SAMAR (CATOS)

5.21 India presented information on the newly developed Collaborative ATFM Over

SAMAR (CATOS), an ATFM system to regulate westbound flights overflying SAMAR

waypoint at the Delhi – Lahore FIR boundary between 0700 – 1100 UTC. SAMAR waypoint

is a point of congestion for India because of (1) transfer flight level restriction with Pakistan

(FL300 or above) for flights on N644, (2) converging traffic on A466 and M890, and (3)

aircraft’s climb performance particular those departing from Delhi Airport (VIDP). This

congestion occurs mostly between 0700 – 1100 UTC of each day, outside of BOBCAT ATFM

operations window, and prompted India to begin the development of CATOS.

5.22 CATOS works similarly to BOBCAT by assigning SAMAR slots – Calculated

Time Over SAMAR (CTO SAMAR) and assigned FL – to flights intending to overfly the

waypoint during the affected period. These slots will be assigned on a first-come, first-served

basis and airspace users have the ability to request to reserve preferred slots up to 4 hours prior

to their Estimated Time Over SAMAR.

5.23 Details of CATOS, including its features and sample screenshots, can be found

in the presentation downloadable from the web link mentioned above.

5.24 IATA remarked that any ATFM initiatives to be introduced in the region should

incorporate airspace users and relevant ANSPs’ input and feedback. Additionally, all initiatives

should be aligned with the regional direction of cross-border ATFM and proper discussions

between stakeholders should be ensured at appropriate meetings.

Distributed Multi-Nodal ATFM Operational Trial Project Progress

5.25 Thailand, as a core project member in the initiative, presented updates from the

Distributed Multi-Nodal ATFM Operational Trial project; a collaborative project among

15

BIMT/4

Meeting Report

several States / Administrations in Asia-Pacific to trial and implement a new concept of cross-

border ATFM in the region. The project stemmed from the needs to handle fast-growing

demand of air traffic within Asia-Pacific and the geopolitical landscape that requires the region

to implement cross-border ATFM in the absence of a central ATFM authority. The concept

explored and subsequently endorsed was that of a Distributed Multi-Nodal ATFM Network,

which accords flexibility and freedom to States in managing their own demand-capacity

balance while ensuring that they are guided by the same ATFM principles and operational

procedures, supported by region-wide interconnected network of information-sharing

protocols. This concept has since been endorsed as a viable solution for cross-border ATFM in

Asia-Pacific and included in the Asia-Pacific Regional Framework for Collaborative ATFM

by APANPIRG.

5.26 The Operational Trial project to develop and validate the operational procedure

for the concept has been ongoing since June 2015, with the first phase focusing on addressing

demand-capacity balancing at constrained arrival airports through departure Ground Delay

Program (GDP) with provision of CTOT. Details of the work in this phase were provided to

the meeting in the given presentation.

5.27 The project is now at the last stage in the first phase (Stage 3 – Limited-Scope

Operational Service) with a focus on methodically introducing the procedures in operational

environment with capacity-limiting situations, beginning with planned events such as special

airspace closure and planned subsequent expansion to include unplanned events. The first of

such events was the Singapore National Day Parade 2016 (NDP16) where CTOTs were issued

to international flights to regulate traffic flow into WSSS while the airport and airspace closure

was in effect due to aerial activities for the occasion.

5.28 The activities during Singapore NDP16 went smoothly, and post-operations

analysis will be conducted among core project members in the upcoming meeting late August

2016. Lessons learned will be used in the continuation of the project and will be updated to

States / Administrations in the region periodically at various occasions including BIMT

meetings.

5.29 Details of the project concept and progress can be found in the presentation

downloadable from the web link mentioned above.

5.30 IATA remarked again that ATFM initiatives in the region should ensure

involvement of stakeholders including airspace users and should also be aligned and

harmonized throughout the region. IATA also suggested that BIMT States explore viability of

embarking on cross-border ATFM similar to that of the Distributed Multi-Nodal ATFM

Operational Trial. To this point, Thailand remarked that the Multi-Nodal ATFM Network

concept is scalable and the project has plan to widen the scope to include other States in Asia-

Pacific progressively, and in-depth discussion in ATFM should be taken up at appropriate

meetings such as the ICAO ATFM/SG.

5.31 India also informed the meeting of the C-ATFM project which is an initiative

to introduce centralized ATFM operations in Indian airspace. The project is progressing in a

similar manner to that of the Multi-Nodal and has plans to ensure alignment and harmonization

in the future.

16

BIMT/4

Meeting Report

Agenda Item 5.4 – AIDC Operationalization

Thailand AIDC Implementation Update

5.32 Thailand presented updates from the ATS Inter-Facility Data Communication

(AIDC) Implementation initiative. The initiative arose from the needs to handle ever-increasing

traffic demand in and out of Bangkok FIR through reduction of longitudinal separation between

consecutive aircrafts at the transfer of control points with neighboring FIRs. This requires

efficient, preferably automated, flight information coordination with adjacent ACCs. In this

regard, Thailand has initiated a plan to implement AIDC message exchange with all 4

neighboring ACCs (Vientiane, Yangon, Phnom Penh, and Kuala Lumpur) with target

completion timeframe of 2018, prior to country-wide transition to the new ATM system.

5.33 Currently, Thailand is in the first phase of the implementation plan – the

connection test with adjacent units. Of concern to BIMT is the planned connection test between

Bangkok ACC and Yangon ACC (Thailand and Myanmar) due to start in September 2016.

Following successful completion of the connection test, interoperability test which includes

defining and testing different message sets will be commenced. This step has been ongoing

between Thailand – Cambodia and Thailand – Lao PDR.

5.34 Subsequent to the first 2 phases, pre-operation testing and operational trial will

be conducted throughout 2017 with target completion and LOA review planned for the first

quarter of 2017.

5.35 Details of Thailand AIDC Implementation Plan along with the timeline can be

found in the presentation downloadable from the web link mentioned above.

5.36 India cautioned that attention should be paid to potential problems arising from

route truncation by the flight plan processor, which may be difficult to detect during the

interoperability test as India also faced the same problem. Additionally, India also requested

that Thailand provide detailed analysis of the interoperability test cases at the next opportunity.

Thailand noted the request and informed that the interoperability test is still ongoing with more

data to be gathered in the upcoming months.

Agenda Item 5.5 – ADS-B Data Sharing

Myanmar ADS-B Implementation Status

5.37 Myanmar presented the progress of ADS-B implementation within Yangon

FIR. The project has been ongoing since 2013 with 5 ADS-B ground stations installed in

Sittwe, Co Co Island, Yangon, Mandalay, and Myeik. Data from these stations, except that

from Co Co Island, have been integrated into the Controller Working Positions with the

upgraded TopSky ATM System since April 2016. Integration with data from Co Co Island

station is still in progress due to unreliability of electrical power on the island which renders

the data unstable.

5.38 ADS-B data sharing agreement between Myanmar and India has also been

signed in May 2015 and can proceed, subjecting to availability of infrastructure.

17

BIMT/4

Meeting Report

5.39 Details of Myanmar ADS-B implementation status can be found in the

presentation downloadable from the web link mentioned above.

Bangladesh ADS-B Implementation Status

5.40 Bangladesh informed the meeting that there are still issues relating to CNS

systems in the country and thus delaying the process of ADS-B implementation. However, the

installation is planned to begin in 3 – 4 months, with a period of 18 – 24 months required for

completion.

5.41 India suggested that ADS-B data sharing agreement process between India and

Bangladesh should be initiated now to ensure that when ADS-B stations are fully installed in

Bangladesh, the data sharing can proceed immediately. Bangladesh noted the suggestion and

agreed to discuss during the bi-lateral side meeting.

Surveillance Data Sharing among BIMT States

5.42 Following the updates of ADS-B implementation from different States, India

proposed that the meeting adopt a conclusion and an action item to ensure that Member States

focus more efforts on improving surveillance coverage in the North Bay of Bengal region

through data sharing. The meeting was in agreement and this was captured as Conclusion

BIMT/4-6 and Action Item BIMT/4-4.

Conclusion BIMT/4-4 – BIMT Surveillance Data Sharing

The BIMT/4 meeting agreed to focus more efforts on improving surveillance

coverage in the North Bay of Bengal through surveillance data sharing. As

the first steps to that, the following has been agreed:

India and Myanmar shall expedite their process of ADS-B data

sharing; and

Bangladesh, India, Myanmar would consider surveillance data

sharing between them

Action Item BIMT/4-4 – Bangladesh, India, Myanmar Surveillance Data

Sharing Process

Bangladesh, India, Myanmar will initiate the process of surveillance data

sharing and update the status at BIMT/5 meeting.

Agenda Item 5.6 – Large Height Deviations (LHD) Hotspots, Action Plan and Reporting

MAAR Report on LHDs

5.43 Monitoring Agency for Asia Region (MAAR) reported to the meeting on

situations of Large Height Deviations (LHDs), defined as a vertical deviation of 90 meters /

300 feet or more from the assigned flight level, near the interface between Kolkata, Yangon,

and Dhaka FIRs. LHDs are used by Regional Monitoring Agencies (RMAs) to estimate

airspace risk for reporting to RASMAG and APANPIRG.

5.44 The area along Dhaka – Kolkata – Yangon FIR borders is currently a hot spot

in the Asia Pacific region, having the highest number of LHD occurrences; most of which were

18

BIMT/4

Meeting Report

Category E – Coordination Error in the ATC-to-ATC transfer of control responsibility as a

result of human factor issues. To ensure that there is coordination between the two involving

ATS units to uncover the cause and prevent future occurrences, the Cross-Boundary LHD

Coordination Procedure was recommended for every LHD occurrence that involved another

ATS unit; the procedure was agreed and adopted in BIMT/3. Such recommended practice can

be found in the presentation given.

5.45 MAAR also presented the Action Plan, which was a compilation of completed

and planned activities, by related States and Agencies, addressing LHD Hotspots near western

and eastern boundaries of Indian FIRs. States/ANSPs were invited to review and provide

updates to MAAR at any time for reporting to RASMAG and APANPIRG.

5.46 In order to facilitate LHD reporting from States to the Monitoring Agency for

Asia Region (MAAR), a prototype of online LHD reporting system was proposed during the

meeting for comments and feedback. The online reporting system would automatically, at the

time of submission, send the report to all relevant ATS units as well as MAAR and

BOBASMA. Upon completion of system tuning and testing, ANSPs may partially or fully

participate by submitting an LHD report either through the existing channel or the new online

system while all relevant units would receive notification/information through the new system.

More information on the system could be found in the given presentation.

5.47 India requested a sharing of experience on low LHD occurrences along

Bangkok – Yangon FIR border. Myanmar clarified that the area along that border was under

full surveillance coverage and Bangkok ACC also normally send inbound estimates 1 – 2 hours

prior to aircrafts reaching the transfer of control points. This was in contrast with Kolkata –

Yangon FIR border, where the inbound estimates were sent only 30 minutes in advance as per

the existing Letter of Agreement. India agreed to discuss this issue further with Myanmar

during the bi-lateral side meeting.

5.48 Myanmar remarked that, while reporting was important, mitigation procedure

should also be discussed. One way to reduce such LHD occurrences would be immediate

coordination between relevant ATS units; a practice that had been put in place between Kolkata

and Yangon ACCs using e-mails.

5.49 IATA also remarked on the importance of LHD reporting and the risk posed by

such occurrences especially in the northern Bay of Bengal region frequently plagued by

inclement weather. To improve coordination and reduce the airspace risk in this area, IATA

proposed a more frequent LHD discussion – e.g. monthly – to ensure enough data could be

gathered for discussion, analysis and identification of ways to reduce the occurrences.

5.50 Bangladesh noted the importance of LHD reporting and the high occurrences

along Dhaka – Kolkata FIR border highlighted by India, and requested further discussion with

MAAR on reporting procedure and system during the bi-lateral side meeting.

BOBASMA Report on LHDs

5.51 Bay of Bengal Arabian Sea Indian Ocean Safety Monitoring Agency

(BOBASMA) presented an analysis of Category E LHD reports filed by Chennai, Kolkata, and

Yangon ACCs over the 6-month period from January to June 2016. It was found that

19

BIMT/4

Meeting Report

coordination error due to incorrect passing of assigned flight level information accounted for

the majority of occurrences. BOBASMA also remarked that the number of occurrences during

the 6-month period in 2016 (92) was higher than the number of occurrences recorded during

the 10-month period in 2015 (73), despite a new LHD handling procedure being put in place

since January 2016.

5.52 In light of the trend, BOBASMA urged States to put greater emphasis on

avoiding coordination errors and adhering to LHD reporting procedure, in addition to the

implementations of support systems such as AIDC and ADS-B data sharing. BOBASMA also

requested that they be copied in the coordination between relevant ATS units on LHD

occurrences to ensure that they would be kept up to date.

5.53 Details on the report by BOBASMA could be found in the given Working Paper

downloadable from the web link mentioned above.

Agenda Item 6: Bi-Lateral Meetings

Multi-Lateral Meeting

Outcome of Meeting between MAAR, IATA, ICAO, and Bangladesh, India, Myanmar

6.1 MAAR conducted multi-lateral meeting with IATA, ICAO, Bangladesh, India,

and Myanmar to further discuss the Large Height Deviation (LHD) reporting and the online

LHD reporting system proposed during Agenda Item 5.6.

6.2 MAAR demonstrated the actual system to the participants to show the user

interface of the new online form in more details. The meeting agreed with the concept of the

proposed system and MAAR informed that they would provide an instructional package to help

States familiarize with platform. Since this concerned all BIMT Member States, the conclusion

and action item had been captured as the meeting’s Conclusion BIMT/4-5 and Action Item

BIMT/4-5.

Conclusion BIMT/4-5 – Large Height Deviation (LHD) Online Reporting

The BIMT/4 meeting agreed with MAAR’s proposed online LHD reporting

system, which will also ensure LHD reports are automatically sent, at the time

of submission, to all relevant ATS units as well as MAAR and BOBASMA. The

online reporting system is in the testing and fine-tuning phase and should be

ready by October 2016.

*Note: Bangkok ACC has a separate reporting coordination with MAAR,

though the reports will still be entered into the system

Action Item BIMT/4-5 – LHD Online Reporting Instructional Package

MAAR, upon completion of system tuning and testing, will send Member

States an instructional package on the new LHD Online Reporting System to

help States familiarize themselves with the platform, including a link to access

the system for States to try out the system.

20

BIMT/4

Meeting Report

6.3 In order to improve safety and reduce LHD occurrences, Bangladesh, India, and

Myanmar also agreed on a more stringent coordination timeframe between the point of contact

and/or watch supervisors on-duty. In reference to the Cross-Boundary LHD Coordination

Procedure, ACC A shall contact ACC B within 3 days from the date of occurrence, whereby

ACC B shall respond within 7 days from the date of notification. After agreeing on the facts of

the occurrence, ACC A will submit the LHD report to MAAR using the online system, which

will automatically notify all relevant parties. This had been captured as the meeting’s

Conclusion BIMT/4-6 as well due to its multi-state nature. To facilitate the coordination, India

also agreed to provide a reporting template for the initial e-mail exchange between ATS units

concerned regarding LHD occurrences, captured as Action Item BIMT/4-6.

Conclusion BIMT/4-6 – Large Height Deviation (LHD) Coordination

Bangladesh, India, Myanmar agreed on an immediate coordination between

the point of contact and/or the watch supervisor on-duty, which shall be within

3 days from the date of occurrence. Upon initial contact by the unit where the

LHD occurred, the contacted unit shall respond within 7 days to discuss the

matter. Once an agreement is reached among relevant units, a formal LHD

report will be submitted.

Action Item BIMT/4-6 – LHD Coordination E-Mail Template India will provide a reporting template for the initial e-mail exchange between

ATS units regarding LHD occurrences.

6.4 Additionally, the topic of periodic LHD review teleconferences was also

discussed again per IATA suggestion. States agreed with the concept and informed the meeting

that bi-lateral phone conversations had been already taking place to discuss ATS issues. The

meeting agreed to include conversations regarding LHDs and their mitigating measures into

these discussions. This had been captured as the meeting’s Conclusion BIMT/4-7.

Conclusion BIMT/4-7 – Periodic Teleconferences on Resolving LHDs and

Other ATS Issues

Bangladesh, India, Myanmar agreed to hold periodic bi or tri-lateral

teleconferences between ATS authorities to discuss LHD occurrences and

mitigation measures along with other ATS issues.

6.5 More information from the multi-lateral meeting between MAAR, IATA,

ICAO, Bangladesh, India, and Myanmar could be found in Attachment 4.

Bi-Lateral and Tri-Lateral Meetings

Outcome of Meeting between Bangladesh – India

6.6 Bangladesh and India conducted bi-lateral meeting during the allocated time

and discussed issues pertaining to route structure development, flight level allocation, and

naming of waypoints. Outcome of the discussion is attached to this report as Attachment 5.

6.7 One key issue discussed during this bi-lateral meeting was the realignment of

Bangladesh danger areas (VGD-31, 32, 33, 34, 35) and the shifting of a segment of the planned

L507S (M509). Since the shifting of L507S (M509) segment may render the spacing between

the route and the planned P646 to be insufficient for RNP10 route specifications, further

21

BIMT/4

Meeting Report

discussion on this route structure is needed following relevant States’ surveys of CNS

infrastructure in the area and revision of route specifications. Accordingly, the realignment of

danger areas will be pending until the decision regarding L507N (L507), L507S (M509), P646

is reached.

Outcome of Tri-Lateral Meeting between Bangladesh – India – Myanmar

6.8 Bangladesh, India, and Myanmar conducted tri-lateral meeting during the

allocated time and discussed issues pertaining to Large Height Deviation (LHD) occurrences

brought up by MAAR and BOBASMA. Of particular concern are flights overflying CHILA

via A599 and APAGO via B465 as these are waypoints located where Dhaka, Kolkata, and

Yangon FIRs intersect and create an LHD hotspot. The coordination procedure between Dhaka,

Kolkata, and Yangon ACCs has been discussed and recorded as outcome from the tri-lateral

meeting. The record can also be found in Attachment 5.

Outcome of Bi-Lateral Meeting between India – Myanmar

6.9 India and Myanmar conducted bi-lateral meeting during the allocated time and

discussed issues pertaining to (1) AIDC implementation between Kolkata and Yangon ACCs,

(2) LHD mitigation measures, and (3) 50NM longitudinal separation at transfer of control

points. The summary of outcomes can be found in Attachment 6.

Outcome of Bi-Lateral Meeting between Myanmar – Thailand

6.10 Myanmar and Thailand conducted bi-lateral meeting to discuss the revision of

Letter of Agreement (LOA). The draft LOA has been agreed with a tentative signing planned

for early October 2016.

6.11 Additionally, the bi-lateral meeting also discussed draft AIP Supplement on

Operating Procedures for RNP10 Operations on ATS Routes L507, P646, N895, L524 and

L301. This draft AIP Supplement can be found in Attachment 7 for review and comment.

Conclusion on BIMT Collaborative Route Development

6.12 Following various side meetings, the meeting agreed to conclude the discussion

on BIMT collaborative route structure development with a phased approach to the

implementation. This will allow Member States to prepare the process and discuss any

remaining issues accordingly.

6.13 The first phase (Phase 1) of the implementation focuses on agreed routes L524,

M506, and L877 (shown in Figure 4 above) with summary as follows:

Routes Waypoints Conditions States

L524 NAGPUR–

KAMKO - BKK

- Eastbound traffic (east of KAMKO)

- Bi-directional (west of KAMKO)

India, Myanmar,

Thailand

M506 DWI – KAMKO Transition route for westbound traffic

on L301 to join L524 after KAMKO

Myanmar,

Thailand

22

BIMT/4

Meeting Report

L877 DWI – MIGAR

Transition route for eastbound traffic

on L301, P762, M502 with VTBD,

VTBS as destination

Myanmar,

Thailand

Table 4 - Phase 1 Route Implementation

The target implementation date for these routes will be 8 December 2016.

6.14 With the new implementation plan for Phase 1, a revised work plan was

discussed and agreed; shown here as follows:

Tasks By Completion Target Remark

1 Approval of route design BIMT/3 17 Dec 2015

2 Approval of work plan 17 Dec 2015

3 Safety assessment BIMT Jan 2016

4 Waypoint and route

designator Jan 2016

New route designator

L524 and M509

received

5 AIP drafting Feb 2016 BIMT States submit

to AAI

6 Submit BANP Mar 2016

7 Review work plan BIMT 17 Aug 2016

8 PfA to BANP Approval ICAO 2 Sep 2016 Error correction by

BIMT States

9 LOA Addendum BIMT Nov 2016 BIMT States

10 ATC Training BIMT Nov 2016 BIMT States

11 AIP Publication (Phase 1) BIMT Sep-Oct 2016 BIMT States

12 Effective Date (Phase 1 8 Dec 2016

13 Post-operations review BIMT TBD Table 5 - Revised Phase 1 Route Implementation Work Plan

6.15 The second phase (Phase 2) of the implementation will focus on longer routes

L507N (L507), L507S (M509), P646 and others shown below. Further details of these routes

will be discussed at BIMT/5 meeting, following Member States’ internal analysis and safety

assessment as well as CNS infrastructure surveys.

Figure 5 - Phase 2 Routes

23

BIMT/4

Meeting Report

6.16 Decisions regarding route implementation above have been captured as the

meeting’s Conclusion BIMT/4-8 and Conclusion BIMT/4-9.

Conclusion BIMT/4-8 – BIMT Route Structure Development, Phase 1

The BIMT/4 meeting agreed on the implementation of route structures as

shown in Figure 4 and Table 4 during Phase 1 of BIMT Route Structure

Development initiative. The target implementation date of these routes is 8

December 2016. Associated work plan (Table 5) for this implementation has

been discussed and will be followed accordingly.

Conclusion BIMT/4-9 – BIMT Route Structure Development, Phase 2

The BIMT/4 meeting agreed on the implementation of routes structures as

shown in Figure 5 during Phase 2 of BIMT Route Structure Development

initiative. Detail regarding these routes and work plan will be discussed at

the next BIMT meeting (BIMT/5).

Agenda Item 7: Future Direction

7.1 The meeting discussed arrangements for future annual BIMT meetings. For the

upcoming BIMT/5, Bangladesh informed the meeting that they are not yet able to host a

meeting and will be able to do so beginning in 2019. Myanmar informed that they will also not

be able to host due to the hosting of Mekong ATM Coordination Group Meeting. India thus

tentatively agreed to host the meeting in June 2017, subjecting to internal coordination within

AAI and will revert with information to Member States when able. Accordingly, the meeting

agreed on the following tentative plan for future BIMT meetings:

Meeting Timeframe Host / Venue

BIMT/5 Tentative: June 2017 India

BIMT/6 2018 Myanmar

BIMT/7 2019 Bangladesh

BIMT/8 2020 Thailand Table 6 - BIMT Meeting Plan

Agenda Item 8: Any Other Business

China Involvement in BIMT Meetings

8.1 Mr. Suvichan, the acting chairperson, informed the meeting that China has been

requesting to attend BIMT meetings to discuss issues relating to route structure development

between China and this sub-region. The meeting discussed the role of China in BIMT and

concluded that it would be more appropriate for China to raise any ATS issues through other

regional-level channels such as the ICAO meetings (APANPIRG, ATM/SG) as BIMT deals

primarily with matters within the Northern Bay of Bengal sub-region.

24

BIMT/4

Meeting Report

8.2 The meeting agreed, however, for China to send delegates as observers to future

BIMT meetings if desired. Myanmar volunteered to liaise with delegates from China on this

topic further as they plan to visit Myanmar’s facilities in the upcoming month.

Revision of Rocket Launch Coordination Points of Contact

8.3 Following up on the action item from BIMT/3 meeting (Action Item BIMT/3-

4), India brought up the topic of coordination points of contact for rocket launch activities. The

contact details sent to India thus far has been compiled and is attached to this report as

Attachment 7. India reminded the meeting to update the points of contact and associated detail

accordingly.

Closing of the Meeting

In closing, Mr. Suvichan thanked all delegates for attending the meeting and for

the fruitful discussion that led to many key conclusions and action items to ensure progress of

the various joint initiatives. Head of Delegates from each Member States as well as ICAO and

IATA also had opportunity to express appreciation to all delegates and offered closing remarks

to the meeting.

----- o -----