    S.No. Descrip t ion Quan ti ty Rate Un it Amount Rs

    Civil Works

    1 Foundation trenches up to 3'-6" 7500 2.50 Cft 18,750.00

    2 For Basement up to 5'-6" depth. 13000 4.50 Cft 58,500.00

    3 Termite proofing. 6000 4.50 sft. 27,000.00

    4 P.C.C 1:4:8 in foundation. 1800 45.00 Cft 81,000.00

    5 Brick work in foundation (1:6) 2650 50.00 Cft 132,500.00

    6 Brick work in Super Structure 9"thick(1:5) 9000 53.00 Cft 477,000.00

    7 Brick work 4-1/2" in Super Structure (1:4) 900 30.00 Sft 27,000.00

    8 D.P.C. 1-1/2" to 2" thick (1:2:4) Horizontal 1050 28.00 Sft 29,400.00

    9 D.P.C. 3/4' thick (1:4) Vertical 250 18.00 Sft 4,500.00

    10 RCC WORKS

    a Rcc footing. 650 90.00 Cft 58,500.00

    b Rcc slab on grade. 250 90.00 Cft 22,500.00

    c RCC Slab 1:2:4 2800 100.00 Cft 280,000.00

    d RCC Beams and lintels 1:2:4 350 110.00 Cft 38,500.00

    e RCC Retaining Wall 1:1.5:3 1200 120.00 Cft 144,000.00

    f RCC columns 1:1.5:3 80 120.00 Cft 9,600.00

    g Stair wast slab and steps. 150 100.00 Cft 15,000.00

    h Rcc ramp slab. 200 110.00 Cft 22,000.00

    I Parapet wall. 275 110.00 Cft 30,250.00

    11 Steel reinforcement. 18000 28.00 Kg. 504,000.00

    12 Plaster to ceiling and soffits 1/2"(1:3) 7140 12.00 Sft 85,680.00

    13 Plaster internal walls 1/2" to 3/4" (1:4) 20500 12.00 Sft 246,000.00

    14 Plaster External walls 1/2" to 3/4" (1:4) 6500 13.00 Sft 84,500.00

    15 Dry brick ballast under floor 3" thick 7140 15.00 Sft. 107,100.00

    16 PCC 1:2:4 -2" thick under floor 2250 20.00 Sft. 45,000.00

    17 Terrazzo flooring with CS. (1:3) gray 4900 42.00 Sft 205,800.0018 Terrazzo skirting. 750 20.00 Rft 15,000.00

    2,769,080.00

    Bil l of quanti t ies

    Construct ion of

  • 8/10/2019 Dr Tahir

    2/4

    374.20

  • 8/10/2019 Dr Tahir

    3/4

    S.No. Descrip t ion Quan ti ty Rate Un it Amount Rs

    Civil Works

    1 Foundation trenches up to 3'-6" 7500 2.50 Cft 18,750.00

    2 For Basement up to 5'-6" depth. 13000 4.50 Cft 58,500.00

    3 Termite proofing. 6000 4.50 sft. 27,000.00

    4 P.C.C 1:4:8 in foundation. 1800 45.00 Cft 81,000.00

    5 Brick work in foundation (1:6) 2650 50.00 Cft 132,500.00

    6 Brick work in Super Structure 9"thick(1:5) 9000 53.00 Cft 477,000.00

    7 Brick work 4-1/2" in Super Structure (1:4) 900 30.00 Sft 27,000.00

    8 Plaster to ceiling and soffits 1/2"(1:3) 7140 12.00 Sft 85,680.00

    9 Plaster internal walls 1/2" to 3/4" (1:4) 20500 12.00 Sft 246,000.00

    10 Plaster External walls 1/2" to 3/4" (1:4) 6500 13.00 Sft 84,500.00

    11 D.P.C. 1-1/2" to 2" thick (1:2:4) Horizontal 1050 28.00 Sft 29,400.00

    12 D.P.C. 3/4' thick (1:4) Vertical 250 18.00 Sft 4,500.00

    13 RCC WORKS

    a Rcc footing. 650 90.00 Cft 58,500.00

    b Rcc slab on grade. 250 90.00 Cft 22,500.00

    c RCC Slab 1:2:4 2800 100.00 Cft 280,000.00

    d RCC Beams and lintels 1:2:4 350 110.00 Cft 38,500.00

    e RCC Retaining Wall 1:1.5:3 1200 120.00 Cft 144,000.00

    f RCC columns 1:1.5:3 80 120.00 Cft 9,600.00

    g Stair wast slab and steps. 150 100.00 Cft 15,000.00

    h Rcc ramp slab. 200 110.00 Cft 22,000.00

    I Parapet wall. 275 110.00 Cft 30,250.00

    14 Steel reinforcement. 18000 28.00 Kg. 504,000.00

    15 Dry brick ballast under floor 3" thick 7140 15.00 Sft. 107,100.00

    16 PCC 1:2:4 -2" thick under floor 2250 20.00 Sft. 45,000.00

    17 Terrazzo flooring with CS. (1:3) gray 4900 42.00 Sft 205,800.0018 Terrazzo skirting. 750 20.00 Rft 15,000.00

    27 Roof water proofing. 3570 60.00 Sft 214,200.00

    Total for civil work 2,983,280.00

    Civil Work 7400 403.00 2,982,200.00

    Plumbing Work 7400 25.00 185,000.00

    Electrical work 7400 35.00 259,000.00

    463.00 3,426,200.00

    Bil l of quanti t ies

    Construct ion of

  • 8/10/2019 Dr Tahir

    4/4

    S.No. Descrip t ion Quan ti ty Rate Un it Amount Rs

    Civil Works

    1 Foundation trenches up to 3'-6" 7500 2.50 Cft 18,750.002 For Basement up to 5'-6" depth. 13000 4.50 Cft 58,500.00

    3 P.C.C 1:4:8 in foundation. 1800 45.00 Cft 81,000.00

    4 Brick work in foundation (1:6) 2650 50.00 Cft 132,500.00

    5 Brick work in Super Structure 9"thick(1:5) 9000 53.00 Cft 477,000.00

    6 Brick work 4-1/2" in Super Structure (1:4) 900 30.00 Sft 27,000.00

    7 Plaster to ceiling and soffits 1/2"(1:3) 7140 12.00 Sft 85,680.00

    8 Plaster internal walls 1/2" to 3/4" (1:4) 20500 12.00 Sft 246,000.00

    9 Plaster External walls 1/2" to 3/4" (1:4) 6500 13.00 Sft 84,500.00

    10 D.P.C. 1-1/2" to 2" thick (1:2:4) Horizontal 1050 28.00 Sft 29,400.00

    11 D.P.C. 3/4' thick (1:4) Vertical 250 18.00 Sft 4,500.00

    13 RCC WORKS

    a Rcc footing. 650 90.00 Cft 58,500.00

    b Rcc slab on grade. 250 90.00 Cft 22,500.00

    c RCC Slab 1:2:4 2800 100.00 Cft 280,000.00

    d RCC Beams and lintels 1:2:4 350 110.00 Cft 38,500.00

    e RCC Retaining Wall 1:1.5:3 1200 120.00 Cft 144,000.00

    f RCC columns 1:1.5:3 80 120.00 Cft 9,600.00

    g Stair wast slab and steps. 150 100.00 Cft 15,000.00

    h Rcc ramp slab. 200 110.00 Cft 22,000.00

    I Parapet wall. 275 110.00 Cft 30,250.00

    14 Steel reinforcement. 18000 28.00 Kg. 504,000.00

    15 Dry brick ballast under floor 3" thick 7140 15.00 Sft. 107,100.00

    16 PCC 1:2:4 -2" thick under floor 2250 20.00 Sft. 45,000.00

    17 Terrazzo flooring with CS. (1:3) gray 4900 42.00 Sft 205,800.00

    18 Terrazzo skirting. 750 20.00 Rft 15,000.0019 Ceramic tile flooring with CS. (1:3) 500 80.00 Sft 40,000.00

    20 Ceramic tile walls with CS. (1:3) 600 85.00 Sft 51,000.00

    21 Marble flooring 12"x12"x1/2" with CS. 1:3 1750 75.00 Sft 131,250.00

    22 Marble skirting. 180 30.00 Rft 5,400.00

    23 Stair and ramp railing MS pipe. 250 450.00 Rft. 112,500.00

    24 Aluminum glazed windos 550 215.00 Sft 118,250.00

    25 Aluminum glazed doors. 150 300.00 Sft 45,000.00

    26 Flush doors. 950 275.00 Sft 261,250.00

    27 Roof water proofing. 3570 50.00 Sft 178,500.00

    28 Vinyle emulsion paint for ceiling. 6000 9.00 Sft 54,000.00

    29 Plastic emulsion paint for walls. 11500 9.00 Sft 103,500.00

    3,842,730.00

    Civil Work 7400 519.29 3,842,730.00

    Plumbing Work 7400 25.00 185,000.00

    Electrical work 7400 35.00 259,000.00

    579.29 4,286,730.00

    Bill of quantities