21
DOVER AREA SCHOOL DISTRICT Capital Project Update Community Night August 16, 2017

DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

DOVER AREA SCHOOL DISTRICT

Capital Project Update

Community Night

August 16, 2017

Page 2: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Looking Back• 2016

• Discussions and Presentations were held by the Board of Directors surrounding future capital project needs based on Educational Programming and current building deficiencies

• Feasibility study was completed and approved prior to the Planconmoratorium in May of 2016

• Architectural Firm search began

• March 2017 – Board of Directors appointed Crabtree Rohrbaugh and Associates as the Architect of Record for a potential project

Page 3: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Looking Back

• April 2017 – Three planning committees were formulated:1. Educational Programming Committee – assists in the planning and design of a

21st century learning environment

2. Core Planning Committee – directing the planning, implementation, and administrative needs of the project

3. Steering Committee – comprised of stakeholders including staff, administration, community members, parents, and students. This committee makes recommendations to the Board in regards to planning, design, and implementation of the project

Page 4: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Educational ProgrammingPlanning Group

Tracy Krum Assistant SuperintendentJennifer Benko Business ManagerBradPerkins CommunicationsDaveNelson Facilities/SafetyJaredWastler HSPrincipalChuck Benton DirectorofCTEVictoriaGross ISPrincipalDrewBecker Teacher– History

LaurenCraig Teacher– Gym/Health

SamanthaPatton LibraryMediaSpecialistBarbLomenzo Teacher- EnglishAmandaOswalt Teacher- LifeSkillsSamRoberts Teacher- Choral/MusicTaraFocht GuidanceMattSpahr Teacher- ChemistryNolanSmith Teacher- WoodShop/Engineering

Page 5: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Core Administrative Planning Group

Tracy Krum Assistant Superintendent

Jennifer Benko Business Manager

Brad Perkins Communications

Dave Nelson Facilities/Safety

Jared Wastler HS Principal

Page 6: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Steering Committee to the Board

Nathan Eifert Board Member, PresidentDennis Dacheux Board MemberTracy Krum Assistant Superintendent

Jennifer Benko Business Manager

Brad Perkins Communications

Dave Nelson Facilities/Safety

Deb Curry Cafeteria

Jared Wastler HS Principal

Chuck Benton Director of CTE

Cliff Harris Parent

Greg Eckard Parent

Tara Focht Guidance

Matt Spahr Chemistry

Silas Barnes Student

Brianna Carter Student

Shyanne Fleming Student

Amy Goebeler Parent

Amanda Renfrew Parent

Page 7: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Looking Back

• May/June 2017

• Committees reviewed various options in regards to new construction and renovation projects and relayed information to the Board of Directors

• July 2017

• Board of Directors voted to transition to the design phase of constructing a new High School at the Intermediate Site which includes renovating the current High School to ultimately move the current Intermediate School students to the renovated building

Page 8: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Going Forward – Projected Timeline• August - September 2017: Architect works with committees to define educational specification

proposals

• August – September 2017: Schematic design formulation by committees and architects

• October – December 2017: Design development by architect based on schematic formulation

• December 2017 – April 2018: Preparation of construction documents including obtaining necessary approvals from PDE, Municipalities, and PennDOT

• April – June 2018: Project goes out to bid

• July 2018: Construction begins

Note: This an estimated timeline which is subject to change based on Board approval of all phases and other contributing factors.

Page 9: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Crabtree, Rohrbaugh & Associates

SCHOOL DISTRICTN EW DOVER AREA

HIG H SCHO O L

Crabtree, Rohrbaugh & Associates

Page 10: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

4 O P T I O N S E VA L U AT E D

1 2

3 4

• NEW HS ON HS SITE• RENOVATIONS & ADDITIONS TO EXISTING IS

• NEW HS ON IS SITE• CONVERT HS TO IS

• RENOVATIONS & ADDITIONS TO EXISTING HS• RENOVATIONS & ADDITIONS TO EXISTING IS

• CONVERT IS TO HS• CONVERT HS TO IS

Total Cost: $94, 600,000 Total Cost: $69,800,000

Total Cost: $82,900,000 Total Cost: $65,800,000

Page 11: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

OPTION

H S

I S

2

• BOARD APPROVED OPTION• CONSTRUCT NEW HS ON I.S. SITE • DEMOLISH EXISTING I.S.• CONVERT H.S. TO I.S. (MINOR ADDITIONS & RENOVATIONS)• EXISTING H.S. CAN ACCOMMODATE 6TH GRADE WITHOUT

ADDITIONS

Page 12: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

CONCEPTUAL SITE PLAN

PHASING• CONSTRUCTION

NEW HS• UPON

SUBSTANTIAL COMPLETION, DEMOLISH EXISTING IS SCHOOL

• COMPLETE SITE WORK

Page 13: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

PROJECT DESIGN SCHEDULE

Option AnalysisProgrammingSchematic DesignDesign DevelopmentConstruction DocumentsBiddingConstruction Start

OCT NOV DEC JAN FEB MAR

2017 2018MAY JUN AUG SEPJUL APRIL MAY JUN JUL

Page 14: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

TENTATIVE CONSTRUCTION SCHEDULE

HS ConstructionIS DemolitionConvert HS to IS

DECJUN JUL AUG SEP OCT NOVSEP OCT NOV DEC

2020JAN FEB MAR APR MAYJAN FEB MAR

2018 2019APR MAY JUN JUL AUGNOV DECJUN JULY AUG SEP OCT

Page 15: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Fund Balance and Tax History/Impact

• Dover has a stable fund balance in both of the General Fund and Capital Project Fund, which can and will most likely be utilized to minimize future tax increases

• In 2016-2017, Per Capita Tax was eliminated, in effect, decreasing taxes

• The District has not increased taxes for the 3 fiscal years. We are one of only three Districts in York County to have a consecutive three year tax freeze or decrease.

Page 16: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Fund Balance

0

5

10

15

20

25

2011 2012 2013 2014 2015 2016 2017

General Fund Fund Balance (in $millions)

General Fund Fund Balance (in $millions)

Page 17: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Fund Balance

0

5

10

15

20

25

2011 2012 2013 2014 2015 2016 2017

Capital Project Fund Balance (in $millions)

Capital Project Fund Balance (in $millions)

Page 18: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

York County Property Tax Millage RatesFour-Year Look Back

Page 19: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

Potential Effect on Average Tax Bill• Assumed:• $70M project providing an allocation for both a new high school at the

Intermediate School site and renovations to the existing high school.

• 6% reimbursement

• Current rates (60 year lows) + 60 and 75 bps

• Utilizing $8M in district reserved funds (as long as district receives Planconfunds due from previous projects)

• The average tax bill could increase approximately $24 per year for a period of 10 years for approx. a total of $235; or mills would need re-allocated in the current budget to debt service; or a combination of both.

Page 20: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

For Further Information:

Please visit http://www.doversd.org/building-project/ for further transparent information on this project.

Page 21: DOVER AREA SCHOOL DISTRICT Capital Project Update · 8/16/2017  · Chuck Benton Director of CTE ... Tara Focht Guidance Matt Spahr Chemistry Silas Barnes Student Brianna Carter Student

THANK YOU!!!!