Upload
dophuc
View
229
Download
0
Embed Size (px)
Citation preview
DOCUMENT RELEASE AND CHANGE FORM Prepared For the U.S. Department of Energy, Assistant Secretary for Environmental Management By Washington River Protection Solutions, LLC., PO Box 850, Richland, WA 99352 Contractor For U.S. Department of Energy, Office of River Protection, under Contract DE-AC27-08RV14800
1a. Doc No: RPP-PLAN-57352 Rev. 01
1b. Project Number: ☒ N/A
1 SPF-001 (Rev.0)
TRADEMARK DISCLAIMER: Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof or its contractors or subcontractors. Printed in the United States of America.
Release Stamp
2. Document Title
Double-Shell Tank Integrity Improvement Plan
3. Design Verification Required
☐ Yes ☐ No
4. USQ Number ☒ N/A 5. PrHA Number ☒ N/A
Rev.
6. USQ Screening:
a. Does the change introduce any new failure modes to the equipment? ☐ Yes ☒ No
Basis is required for Yes:
b. Does the change increase the probability of existing failure modes? ☐ Yes ☒ No
Basis is required for Yes:
c. For Safety Significant equipment, does the change require a modification to Chapter 4 of the DSA and/or FRED? ☐ Yes ☐ No ☒ N/A
Basis is required for Yes:
7. Description of Change and Justification (Use Continuation pages as needed)
New Document
8. Approvals
Title Name Signature Date
Clearance Review RAYMER, JULIA R RAYMER, JULIA R 07/20/2015
Document Control Approval RAYMER, JULIA R RAYMER, JULIA R 07/20/2015
Originator GARFIELD, JOHN GARFIELD, JOHN 05/26/2015
Other Approver BOOMER, KAYLE D BOOMER, KAYLE D 06/25/2015
Responsible Manager BAIDE, DAN BAIDE, DAN 06/25/2015
9. Clearance Review:
Restriction Type:
☒ Public
☐ Undefined
☐ Unclassified Controlled Nuclear Information (UCNI)
☐ Export Control Information (ECI)
☐ Official Use Only Exemption 2-Circumvention of Statute (OUO-2)
☐ Official Use Only Exemption 3-Statutory Exemption (OUO-3)
☐ Official Use Only Exemption 4-Commercial/Proprietary (OUO-4)
☐ Official Use Only Exemption 5-Privileged Information (OUO-5)
☐ Official Use Only Exemption 6-Personal Privacy (OUO-6)
☐ Official Use Only Exemption 7-Law Enforcement (OUO-7)
RPP-PLAN-57352 7/20/2015 - 12:51 PM 1 of 92
Jul 20, 2015DATE:
JRR 7/20/15
DOCUMENT RELEASE AND CHANGE FORM Doc No: RPP-PLAN-57352 Rev. 01
2 SPF-001 (Rev.0)
10. Distribution:
Name Organization
BAIDE, DAN TFP ENGINEERING
BARNES, TRAVIS J TANK AND PIPELINE INTEGRITY
BOOMER, KAYLE D TANK AND PIPELINE INTEGRITY
CASTLEBERRY, JIM L TFP PROJECT MANAGEMENT
FEERO, AMIE J TANK AND PIPELINE INTEGRITY
GARFIELD, JOHN TANK AND PIPELINE INTEGRITY
GUNTER, JASON R TANK AND PIPELINE INTEGRITY
JOHNSON, JEREMY
LITTLE, DAVID B ENGINEERING
TURKNETT, MARILYN J TANK AND PIPELINE INTEGRITY
VAZQUEZ, BRANDON J TANK AND PIPELINE INTEGRITY
WASHENFELDER, DENNIS TANK AND PIPELINE INTEGRITY
11. TBDs or Holds ☒ N/A
12. Impacted Documents – Engineering ☒ N/A
Document Number Rev. Title
13. Other Related Documents ☒ N/A
Document Number Rev. Title
14. Related Systems, Structures, and Components:
14a. Related Building/Facilities ☐ N/A
241-AN
241-AP
241-AW
241-AY
241-AZ
241-SY
14b. Related Systems ☒ N/A
14c. Related Equipment ID Nos. (EIN) ☒ N/A
RPP-PLAN-57352 7/20/2015 - 12:51 PM 2 of 92
3 SPF-001 (Rev.0)
DOCUMENT RELEASE AND CHANGE FORM CONTINUATION SHEET
Document No: RPP-PLAN-57352 Rev. 01
NA
RPP-PLAN-57352 7/20/2015 - 12:51 PM 3 of 92
RPP-PLAN-57352 7/20/2015 - 12:51 PM 4 of 92
H. K. Lawrence, Email att.
7/20/15 JRR
By Julia Raymer at 1:04 pm, Jul 20, 2015
RPP-PLAN-57352 7/20/2015 - 12:51 PM 5 of 92
Jerry Holloway- See attached e-mail
Brad Page - See attached e-mailSteve Beehler - See attached e-mail
By Julia Raymer at 1:06 pm, Jul 20, 2015
Approved for Public Release; Further Dissemination Unlimited
7/20/15
Jeremy Johnson - See attached e-mailDOE-ORP SME
RPP-PLAN-57352 6/30/2015 - 7:04 AM 7 of 88RPP-PLAN-57352 7/20/2015 - 12:51 PM 6 of 92
1
Vorpagel, Lindsay R
From: Holloway, Jerry N
Sent: Tuesday, July 14, 2015 11:52 AM
To: Vorpagel, Lindsay R
Subject: RE: 2nd request - Digital ICR request - RPP-PLAN-57352-01-Record.pdf
Follow Up Flag: Follow up
Flag Status: Completed
Categories: 3 red light
Lindsay,
I approve on behalf of External Affairs.
Jerry
Jerry Holloway
External Affairs Manager
Washington River Protection Solutions,
contractor to the United States Department of Energy
509.372.9953
From: Vorpagel, Lindsay R
Sent: Tuesday, July 14, 2015 10:52 AM
To: Cherry, Stephen B; Page, Brad; Roxburgh, Robert T; Holloway, Jerry N; Vorpagel, Lindsay R
Subject: 2nd request - Digital ICR request - RPP-PLAN-57352-01-Record.pdf
The below ICR request still needs a response from External Affairs and Legal please.
Sincerely,
Lindsay Vorpagel, WRPS External Affairs and Procurement SEAPC representative 509-376-5380
From: Vorpagel, Lindsay R
Sent: Monday, July 06, 2015 10:15 AM
To: Beehler, Stephen J; Cherry, Stephen B; Page, Brad; Poynor, Tara N; Roxburgh, Robert T; Vorpagel, Lindsay R
Subject: Digital ICR request - RPP-PLAN-57352-01-Record.pdf
Please coordinate with your department colleagues as to who will do the below review. After reviewing, please send
your email response to me of-
approval,
RPP-PLAN-57352 7/20/2015 - 12:51 PM 7 of 92
1
Vorpagel, Lindsay R
From: Page, Brad
Sent: Thursday, July 16, 2015 11:29 AM
To: Vorpagel, Lindsay R; Cherry, Stephen B
Subject: RE: 3rd request - Digital ICR request - RPP-PLAN-57352-01-Record.pdf
Follow Up Flag: Follow up
Flag Status: Completed
Categories: 2 yellow light
Lindsay,
I have reviewed the ICR and approve its release on behalf of legal.
Brad
From: Vorpagel, Lindsay R
Sent: Thursday, July 16, 2015 7:15 AM
To: Page, Brad; Cherry, Stephen B; Vorpagel, Lindsay R
Subject: 3rd request - Digital ICR request - RPP-PLAN-57352-01-Record.pdf
Please see below -
Sincerely,
Lindsay Vorpagel, WRPS External Affairs and Procurement SEAPC representative 509-376-5380
From: Vorpagel, Lindsay R
Sent: Tuesday, July 14, 2015 10:52 AM
To: Cherry, Stephen B; Page, Brad; Roxburgh, Robert T; Holloway, Jerry N; Vorpagel, Lindsay R
Subject: 2nd request - Digital ICR request - RPP-PLAN-57352-01-Record.pdf
The below ICR request still needs a response from External Affairs and Legal please.
Sincerely,
Lindsay Vorpagel, WRPS External Affairs and Procurement SEAPC representative
RPP-PLAN-57352 7/20/2015 - 12:51 PM 8 of 92
1
Vorpagel, Lindsay R
From: Beehler, Stephen J
Sent: Thursday, July 09, 2015 12:00 PM
To: Vorpagel, Lindsay R
Cc: Poynor, Tara N
Subject: DOCUMENT REVIEW REQUEST - DST Integrity
Follow Up Flag: Follow up
Flag Status: Completed
Categories: 1 green light
Lindsay-
The document contained in the link below has been reviewed and approved by ORP Subject Matter Expert Jeremy
Johnson. His email noting such is below. I concur on behalf of ORP Public Affairs. Please consider this email as approval
to clear the document for public release in lieu of providing signatures on the ICR form.
Regards,
Steve BeehlerSteve BeehlerSteve BeehlerSteve Beehler Media Relations Specialist
North Wind Solutions, LLC
General Support Services Contractor
Office of River Protection
Office - 509.376.4637
Cell - 509.521.4498
[email protected] [email protected]
From: Johnson, Jeremy M
Sent: Wednesday, July 08, 2015 1:32 PM
To: Beehler, Stephen J
Subject: RE: DOCUMENT REVIEE REQUEST - DST Integrity
I reviewed, ok to release.
Jeremy Johnson
Office of River Protection
Tank Farms Projects
509-376-1866
From: Vorpagel, Lindsay R
Sent: Monday, July 06, 2015 10:15 AM
RPP-PLAN-57352 7/20/2015 - 12:51 PM 9 of 92
2
To: Beehler, Stephen J; Cherry, Stephen B; Page, Brad; Poynor, Tara N; Roxburgh, Robert T; Vorpagel, Lindsay R
Subject: Digital ICR request - RPP-PLAN-57352-01-Record.pdf
Please coordinate with your department colleagues as to who will do the below review. After reviewing, please send
your email response to me of-
approval,
OR
approval with edits
OR
non-approval with comments
To Review –
RPP-PLAN-57352-01-Record.pdf
Thanks!
Sincerely,
Lindsay Vorpagel, WRPS External Affairs and Procurement SEAPC representative 509-376-5380
RPP-PLAN-57352 7/20/2015 - 12:51 PM 10 of 92
Tank Operations Contractor (T0C) Record of Revision
RPP-PLAN-57352, Rev. 1
Double-Shell Tank Integrity Improvement Plan
Change Control Record
Rev Description of change Author Manager
1 Deleted action to Sample Tank AY-102 Prioritized Annulus Sampling
J. S. Garfield
D. G. Baide
RPP-PLAN-57352 7/20/2015 - 12:51 PM 11 of 92
A-6002-767 (REV 3)
RPP-PLAN-57352 Rev. 1
Double-Shell Tank Integrity Improvement Plan Author Names:
J. S. Garfield, B. J. Vazquez, J. R. Gunter, A. J. Feero, & K. D. Boomer Washington River Protection Solutions, LLC
Richland, WA 99352 U.S. Department of Energy Contract DE-AC27-08RV14800
EDT/ECN: DRCF UC: N/A
Cost Center: N/A Charge Code: N/A
B&R Code: N/A Total Pages:
Key Words: double-shell tanks, integrity, corrosion
Abstract: The High-level Waste Integrity Assessment Panel are nationally recognized experts
in corrosion chemistry and structural tank integrity issues who were convened three times in
FY-2013 and FY-2014 to review the Tank 241-AY-102 status along with the integrity of all
double-shell tanks. The Panel identified specific recommendations documented in RPP-
ASMT-57582. WRPS engineering staff developed a path forward for each recommendation in
this Implementation Plan.
TRADEMARK DISCLAIMER. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof or its contractors or subcontractors.
Release Approval Date Release Stamp
Approved For Public Release
RPP-PLAN-57352 7/20/2015 - 12:51 PM 12 of 92
By Julia Raymer at 1:10 pm, Jul 20, 2015
Jul 20, 2015DATE:
92 JRR 7/20/15
RPP-PLAN-57352 Rev. 1
Double-Shell Tank Integrity Improvement Plan
J. S. Garfield A E M Consulting, LLC K. D. Boomer B. J. Vazquez J. R. Gunter A. J. Feero Washington River Protection Solutions, LLC
Date Published
June, 2015
Prepared for the U.S. Department of Energy Office of River Protection
Contractor for the U.S. Department of Energy Office of River Protection under Contract DE-AC27-08RV14800
P.O. Box 850 Richland, Washington
RPP-PLAN-57352 7/20/2015 - 12:51 PM 13 of 92
RPP-PLAN-57352 Rev. 1
ES-1
EXECUTIVE SUMMARY
The Hanford Site Tank Operations Contractor (TOC), Washington River Protection Solutions
LLC (WRPS), has contracted an expert panel to provide advice and recommendations for the
Double-Shell Tank (DST) Integrity Program. The purpose of this DST Integrity Improvement
Plan is to translate the High-level Waste Integrity Assessment Panel (HIAP) recommendations to
specific project activities that are technically and practically responsive. These project actions in
Figure ES-1 are developed conceptually to address the technical justification and provide a
definition of scope and schedule for budgeting consideration. The numbering provides an index
to the narrative sections in this document. Revision 1 deletes the Tank-AY-102 bottom plate
sampling activities and updates schedules and priorities on the remaining tasks.
Figure ES-1. Proposed Actions to the Recommendations Given by the High-Level Waste
Integrity Assessment Panel
RPP-PLAN-57352 7/20/2015 - 12:51 PM 14 of 92
RPP-PLAN-57352 Rev. 1
ES-2
The HIAP reviewed the DST integrity issues in two meetings and addressed forensic
examination of Tank 241-AY-102 (AY-102) in a third meeting. The two integrity issue
meetings placed an emphasis on corrosion and degradation mechanisms. The third meeting was
in August 2014, addressed commercial and nuclear industry methods to examine the leak site
pre- and post-retrieval. The HIAP meetings were documented as follows:
RPP-ASMT-56329 9/13 Workshop
RPP-ASMT-57582 4/14 Workshop
RPP-ASMT-59980 9/25 Workshop
The initial integrity meeting was in September 2013, and discussed the Tank AY-102 leak
assessment. The second meeting was in April 2014, and discussed the extent of condition
reviews from the leak assessment along with an overall program review. The focus of this
implementation plan is to address the recommendations from the first two meetings, which the
HIAP concentrated on two concerns:
• No Early warning – Determine why the existing DST Integrity Program did not
predict a primary tank failure or provide early warning of the pending failure.
• Program improvements – Recommend activities to either predict a primary tank
failure or increase the probability of early warning.
The project activities, which implement the HIAP recommendations listed in Table ES-1, have
been developed at a pre-conceptual level for funding beginning in fiscal year (FY) 2016. The
tasks identified to implement the panel recommendations were reviewed with the HIAP in the
August 2014 meeting. WRPS provided a prioritization and path forward for each of the tasks as
discussed in Section 6.0 and summarized in Figure ES-2.
In the August 2014, meeting the HIAP provided additional recommendations regarding post-
retrieval forensic assessment of Tank AY-102 to facilitate a conclusion on why the leak
occurred. Implementation of these recommendations will be addressed separately.
Since the Rev. 0 was issued, it was determined that the AY-102 Core sample and analysis
activities would interfere with tank retrieval. These activities were deleted and 5.3.3 (Sample
AY-102 Annulus with Robotic Crawler) was elevated in priority to address the HIAP concern
with AY-102 leak status.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 15 of 92
RPP-PLAN-57352 Rev. 1
ES-3
Figure ES-2. Double-Shell Tank Integrity Task Priorities
RPP-PLAN-57352 7/20/2015 - 12:51 PM 16 of 92
RPP-PLAN-57352 Rev. 1
i
CONTENTS
1.0 INTRODUCTION ............................................................................................................ 1-1
1.1 Objectives – Predict a Failure or Identify Early Warnings .................................... 1-3
1.2 High-Level Waste Integrity Assessment Panel Findings ....................................... 1-3
1.2.1 Why Tank AY-102 Leak Was Not Predicted ........................................... 1-3
1.2.2 Possible Degradation Mechanisms in Tank AY-102 ................................ 1-4
1.2.3 Specific High-Level Waste Integrity Assessment Panel
Recommendations ..................................................................................... 1-4
1.2.4 Supplemental Panel Recommendations From August Meeting ............... 1-7
2.0 SUMMARY OF PROGRAM IMPROVEMENTS ........................................................... 2-1
3.0 DATA ANALYSIS AND INTERPRETATION ACTIVITIES ....................................... 3-1
3.1 Review Tank Chemistry History ............................................................................ 3-1
3.1.1 Document Tank Chemistry History .......................................................... 3-1
3.2 Rank Tank Leak Risks ........................................................................................... 3-2
3.2.1 Qualitative Risk Ranking for All Double-Shell Tanks ............................. 3-2
Figure 3-2. Schedule to Update Qualitative Risk Ranking for All
Double-Shell Tanks ................................................................................... 3-3
3.2.2 Risk Analysis Based on Sidewall Ultrasonic Testing Data ...................... 3-3
3.2.3 Double-Shell Tank Risk Analysis Based on Bottom Plate Data............... 3-5
3.3 Validate Double-Shell Tank Integrity Program ..................................................... 3-5
3.3.1 Primary Tank Chemistry Controls ............................................................ 3-5
4.0 IMPROVED DATA GATHERING ACTIVITIES .......................................................... 4-1
4.1 Perform Augmented Wall Scanning Inspections ................................................... 4-1
4.1.1 Develop Electromagnetic Acoustic Transducer and Phased Array .......... 4-1
4.1.2 Evaluate Additional Nondestructive Examination (Flash
Thermography) .......................................................................................... 4-3
4.2 Increase Visual Observations In the Annulus ........................................................ 4-4
4.2.1 Automated Annulus Camera System ........................................................ 4-4
4.3 Visual Observation and NDE of the Primary Tank Bottom ................................... 4-7
4.3.1 Visual – Robotic Crawler in Air Slots ...................................................... 4-7
4.3.2 Visual–Robotic Annulus Air Supply Pipe Inspections ............................. 4-9
4.3.3 Nondestructive Examination–Synthetic Aperture Focusing
Technique and Tandem Synthetic Aperture Focusing Technique .......... 4-12
4.3.4 Nondestructive Examination - Robotic Crawler (Guided Wave in
Air Slots) ................................................................................................. 4-13
4.3.5 Nondestructive Examination–Guided Wave System (Across Tank
Diameter) ................................................................................................ 4-14
4.4 Perform Ultrasonic Testing on Secondary Tank Bottom in the Annulus ............ 4-16
4.4.1 Perform Ultrasonic Testing with Existing Procedure ............................. 4-16
4.5 Optimize Use of Thermocouples for Early Leak Notification ............................. 4-16
4.5.1 Use of Thermocouples to Detect Leaks .................................................. 4-16
4.6 Improved Continous Air Monitoring ................................................................... 4-17
4.6.1 Improved Annulus Air Monitoring Design ............................................. 4-17
RPP-PLAN-57352 7/20/2015 - 12:51 PM 17 of 92
RPP-PLAN-57352 Rev. 1
ii
5.0 ENHANCED EXISTING INTEGRITY PROGRAM TO MINIMIZE
DOUBLE-SHELL TANK DEGRADATION................................................................... 5-1
5.1 Corrosion Test Secondary Liner and Leak Detection Pit Steel for Tank AY-
102 .......................................................................................................................... 5-1
5.1.1 2014 Corrosion Work on Tank AY-102 Steel .......................................... 5-1
5.2 Ensure Low Humidity between Primary and Secondary Liners ............................ 5-1
5.2.1 Dehumidifiers on Annulus Air Inlet ......................................................... 5-1
5.3 Sampling and Analysis of Sludge at the Bottom Plate ........................................... 5-4
5.3.1 Core Sample Tank AY-102 at Bottom Plate ............................................. 5-4
5.3.2 Analyze Sample (Corrosion Testing) ........................................................ 5-4
5.3.3 Sample AY-102 Annulus with Robotic Crawler ...................................... 5-4
6.0 CONCLUSIONS AND PATH FORWARD ..................................................................... 6-1
7.0 REFERENCES .................................................................................................................. 7-1
APPENDICES
Appendix A Qualitative Risk Ranking Performance Measures ............................................... A-i
FIGURES
Figure ES-1. Proposed Actions to the Recommendations Given by the High-Level Waste
Integrity Assessment Panel ......................................................................................1
Figure ES-2. Double-Shell Tank Integrity Task Priorities .............................................................3
Figure 1-1. High Level Waste Integrity Assessment Panel Charter ....................................... 1-1
Figure 1-2. Summary of the Proposed Actions and Recommendations ................................. 1-2
Figure 2-1. Double-Shell Tank Integrity Task Priorities ........................................................ 2-1
Figure 3-1. Schedule to Review Tank Chemistry History ...................................................... 3-1
Figure 3-2. Schedule to Update Qualitative Risk Ranking for All Double-Shell Tanks ........ 3-3
Figure 3-3. Schedule for Frequency of Ultrasonic Wall Inspection ....................................... 3-4
Figure 3-4. EPOC Oversight of Tank Chemistry Controls ..................................................... 3-6
Figure 4-1. Force Institute P-Scan Stack System ................................................................... 4-2
Figure 4-2. AGS-2 Magnetic Crawler .................................................................................... 4-2
Figure 4-3. Schedule for Electromagnetic Acoustic Transducer Scans and Phased
Array Ultrasonic Transducers .............................................................................. 4-3
Figure 4-4. Schedule for Flash Thermography ....................................................................... 4-4
Figure 4-5. Conceptual Design for the Annulus Video Monitoring System .......................... 4-5
Figure 4-6. Schedule for a Premium Annulus Video Monitoring System ............................. 4-6
RPP-PLAN-57352 7/20/2015 - 12:51 PM 18 of 92
RPP-PLAN-57352 Rev. 1
iii
Figure 4-7. Robotic Air Slot Visual Inspection Crawler ............................................................ 4-7
Figure 4-8. Deployment Method of Crawler Concept ............................................................ 4-8
Figure 4-9. Crawler Oriented on Annulus Floor and Aligned with Air Slot .............................. 4-8
Figure 4-10. Camera Inserted into Refractory Air Slot for Visual Inspection (note:
Primary Tank Hidden from View) ....................................................................... 4-8
Figure 4-11. Schedule for the Robotic Air Slot Visual Inspection Crawler ............................. 4-9
Figure 4-12. Robotic Pipe Crawler ........................................................................................ 4-10
Figure 4-13. Ventilation Air Supply System Overview ......................................................... 4-10
Figure 4-14. Air Supply Piping .............................................................................................. 4-10
Figure 4-15. Schedule for Robotic Annulus Air Supply Crawler .......................................... 4-11
Figure 4-16. FORCE–Extended Arm and Tandem Synthetic Aperture Focusing
Technique for Lower Knuckle Region .............................................................. 4-12
Figure 4-17. Schedule for Ultrasonic Testing using Synthetic Aperture Focusing
Technique and Tandem Synthetic Aperture Focusing Technique ..................... 4-13
Figure 4-18. Schedule for the Robotic Multi-Air Slot Nondestructive Evaluation ................ 4-14
Figure 4-19. Long Range Guided Wave Ultrasonic Testing .................................................. 4-15
Figure 4-20. Schedule for Inspection using Guided Wave Transducers ................................ 4-15
Figure 4-21. Schedule for Improved Annulus Air Monitoring Design .................................. 4-19
Figure 5-1. Proposed Dehumidifier Layout ............................................................................ 5-2
Figure 5-2. Portable Industrial Dehumidifier with Condenser Reheat ................................... 5-2
Figure 5-3. Schedule for Annulus Air Humidity Control ....................................................... 5-4
Figure 5-4. Washington River Protection Solutions Off Riser Sampling System .................. 5-5
Figure 5-5. AREVA Remote Underground Sampler .............................................................. 5-5
Figure 5-6. Schedule for Robotic Annulus Sampling ............................................................. 5-6
TABLES
Table 3-1. Double-Shell Tank Inspection Frequencies ......................................................... 3-4
Table 4-1. Tank AY-101 and Tank AY-102 Thermocouples Operable (8/2012) ............... 4-17
Table 6-1. Double-Shell Tank Integrity Task Priorities and Path Forward (3 Pages) .......... 6-1
RPP-PLAN-57352 7/20/2015 - 12:51 PM 19 of 92
RPP-PLAN-57352 Rev. 1
iv
TERMS
Acronyms
CAM continuous air monitoring
CLR Caustic Limits Report
CPP cyclic potentiodynamic polarization
CSS core sampling system
DST double-shell tank
EMAT Electromagnetic Acoustic Transducer
ENRAF Honeywell ENRAF-Nonius 854
EPOC Expert Panel Oversight Committee
FAT factory acceptance test
FY fiscal year
HIAP High-level Waste Integrity Assessment Panel
IHI IHI Southwest Technologies, Inc.
ISL interstitial liquid
LDP leak detection pit
LED light emitting diode
LRGWUT long range guided wave ultrasonic testing
NDE nondestructive examination
OAT operation acceptance test
ORSS off riser sampling system
OSD Operation Specification Document
PAUT phased array ultrasonic testing
PDT performance demonstration test
PNNL Pacific Northwest National Laboratory
PWHT post weld heat treatment
ROM rough order of magnitude
RUS remote underground sampler
SAFT Synthetic Aperture Focusing Technique
SCC stress corrosion cracking
SCE saturated calomel electrode
SSR slow strain rate
SST single-shell tank
T-SAFT Tandem Synthetic Aperture Focusing Testing
UT ultrasonic testing
WRPS Washington River Protection Solutions, LLC
WTP Waste Treatment and Immobilization Plant
RPP-PLAN-57352 7/20/2015 - 12:51 PM 20 of 92
RPP-PLAN-57352 Rev. 1
v
Units
% percent
cm2 centimeter squared
ft feet
Gy gray (unit of absorbed radiation)
in. inch
mA milliamp
mV millivolt
sec second
V Volt
RPP-PLAN-57352 7/20/2015 - 12:51 PM 21 of 92
RPP-PLAN-57352 Rev. 1
1-1
1.0 INTRODUCTION
The High-Level Waste Integrity Assessment Panel (HIAP), or Panel, reviewed the double-shell
tank (DST) integrity issues with an emphasis on corrosion and degradation mechanisms. HIAP
has met twice to discuss integrity issues. The initial meeting in September 2013, discussed RPP-
ASMT-53793, Tank 241-AY-102 Leak Assessment Report. The second meeting in April 2014,
discussed the extent of condition reviews from the leak assessment along with an overall
program review. The HIAP charter is shown in Figure 1-1.
Figure 1-1. High Level Waste Integrity Assessment Panel Charter
RPP-PLAN-57352 7/20/2015 - 12:51 PM 22 of 92
RPP-PLAN-57352 Rev. 1
1-2
HIAP suggestions are indexed by sections in this document and summarized in Figure 1-2. The
HIAP focused on two concerns:
• No early warning – Determine why the existing DST Integrity Program did not predict a
primary tank failure or provide early warning of the pending failure.
• Program improvements – Recommend activities to either predict a primary tank failure or
increase the probability of early warning.
Figure 1-2. Summary of the Proposed Actions and Recommendations
The recommendations were formally documented by HIAP and are summarized in Section 1.2.
HIAP suggestions, shown in Figure 1-2, include addressing the risk of future DST failures,
improvements to monitoring functions, and program or operational improvements that are
preventive in nature.
The tasks identified to implement the panel recommendations were reviewed with the HIAP in
the August 2014 meeting. Washington River Protection Solutions, LLC (WRPS) provided a
prioritization and path forward for each of the tasks as discussed in Section 6.0.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 23 of 92
RPP-PLAN-57352 Rev. 1
1-3
The main focus of the HIAP meeting in August 2014 was to address forensic examination of
Tank AY-102 after the waste is retrieved. The goal of this meeting was to develop methods and
procedures for the examination and to determine whether the tank can be repaired and return to
service. The HIAP will provide additional recommendations regarding pre- and post-retrieval
forensic assessment of Tank AY-102 to facilitate a conclusion on why the leak occurred.
1.1 OBJECTIVES – PREDICT A FAILURE OR IDENTIFY EARLY WARNINGS
The purpose of this DST improvement plan is to translate the HIAP recommendations to specific
project activities that are technically and practically responsive. These project actions are
developed conceptually to address the technical justification and provide a definition of scope.
1.2 HIGH-LEVEL WASTE INTEGRITY ASSESSMENT PANEL FINDINGS
The HIAP considered three primary areas to address.
1. Why there was no early warning in the failure of Tank AY-102.
2. Suggestions to increase the probability of early warning.
3. Suggested program improvements. Some of these activities serve the dual purpose of
interrogating sound tanks as well as forensic discovery of the leak mechanism in Tank
AY-102.
1.2.1 Why Tank AY-102 Leak Was Not Predicted
The HIAP focused on four areas that may have prevented the leak from being predicted. These
four areas are summarized below. The full text is contained in Section 4.0 of RPP-ASMT-
57582, Second Workshop of the High Level Waste Integrity Assessment Panel: Extent of
Condition and Balance of Program.
Difficulty of Inspection
• No nondestructive evaluation (NDE) inspection data for tank bottom.
• No visual evidence of the tank bottom.
Limited Corrosion and Chemistry Data
• Limited corrosion data for historical environments.
• Limited corrosion data on welds and heat affected zones.
• Waste chemistry uncertainties. The heterogeneous nature of tank waste creates
uncertainties and difficulties in understanding and controlling internal corrosion.
• Limited chemistry data from bottom layer of sludge.
• Uncertainty related to chemistry controls.
Aging and Degradation Conditions Not Fully Considered
• Significant ventilation downtime leading to wet thermal insulation under the tank.
• Water intrusion in the annulus leading to humid environment.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 24 of 92
RPP-PLAN-57352 Rev. 1
1-4
• Stress and thermal cycling.
• Impact of stresses on pre-existing weld defects on tank bottom.
Fabrication Conditions Not Fully Considered
• Condition of the refractory.
• Weld rejection rate.
• Post-weld heat treatment (PWHT) issues.
• Lack of nondestructive evaluation after PWHT.
1.2.2 Possible Degradation Mechanisms in Tank AY-102
The Panel ranked the following degradation mechanisms in order of likelihood (1 being the most
likely and 8 being the least likely) for being at the metallurgical cause of the Tank AY-102 leak:
1. Primary tank external corrosion (general or pitting)
2. Pitting corrosion from tank inside, waste chemistry induced
3. Nitrate-induced stress corrosion cracking (SCC) from tank inside
4. Corrosion under insulation (CUI) that is halogen-specific–induced heavy pitting on tank
external side (outside) of the primary tank bottom
5. Opening of pre-existing through-wall weld defect
6. Carbonate-induced SCC from tank inside
7. Corrosion-Fatigue; Fatigue crack growth
8. Caustic-induced SCC from tank inside
1.2.3 Specific High-Level Waste Integrity Assessment Panel Recommendations
The HIAP recommendations are provided in RPP-ASMT-57582 and are repeated below.
Data Analysis and Interpretation Activities
• Review tank chemistry history. The investigation into Tank AY-102 leak revealed a
much more complex history of waste transfers, chemistry, and in-tank waste mixing than
was previously appreciated. Based on the aforementioned risk ranking, the program
should investigate the detailed history of tanks with a higher potential for leaks. In
addition to potentially identifying previously overlooked troublesome chemistries in the
tanks, such analysis will also allow for a better understanding of the uncertainty
associated with a tank’s chemistry history.
• Rank tank leak risks. The Tank AY-102 leak caused a reevaluation of the DST
Integrity Program that includes the scope of this Panel. In this reevaluation, the factors
outlined in Section 4.0 of this report provide insight into potential clues to future tank
leaks. Using existing data, WRPS should perform a risk analysis to assess which tanks
are most likely to leak. This, in conjunction with the analysis presented in Appendix A,
RPP-PLAN-57352 7/20/2015 - 12:51 PM 25 of 92
RPP-PLAN-57352 Rev. 1
1-5
can be used to inform program priorities in allocating resources for integrity activities to
at-risk tanks and those that are most important to the mission.
Initially, the HIAP sees the following information as particularly important in judging a
tank’s likelihood of leaking:
1. Temperature during PWHT: This factor affects SCC and therefore is an
important consideration as it could lead to a large leak.
2. Weld rejection rate: This factor is also important as it affects SCC.
3. Liner bulging: Liner bulges during construction can affect SCC by
producing large residual stresses.
4. Maximum waste temperature and temperature cycling: This factor affects
both pitting and SCC.
5. Out of specification chemistry: This factor affects both pitting and SCC.
6. Years of service: This factor affects both pitting and SCC.
7. Operational period without active ventilation: Operation without the
annulus air ventilation may lead to thinning of the outside surface of the
primary tank.
Review and validate DST integrity program drivers. During the Panel’s review, it
emerged that the DST integrity program is governed by a number of drivers (e.g.
chemistry models, waste compatibility assessment process and caustic limits) that have
developed and evolved over the course of the program’s history (since 1994). The Panel
recommends the program review these drivers to validate that they are based on current,
valid programmatic needs.
Improved Data Gathering Activities
• Perform augmented inspections. A key to improving the leak prediction ability of the
program is increased collection of data indicative of conditions that could lead to a leak.
In these recommendations, HIAP emphasizes the importance of improving the ability to
collect data on the condition of both the primary tank and secondary liner.
Considerations should be given to:
Increase visual observations in the annulus. A goal of developing a 100% baseline of
visual observations in the annulus of all DST’s should be adopted. Specific to Tank AY-
102, WRPS should increase its frequency of visual observations, particularly at Riser 83,
to as frequent as is practicable. If multiple images can be obtained per hour or per day,
this should be considered.
• Perform visual and NDE observations of the primary tank bottom. Techniques to
provide observational data for the external surface of the primary tank liner steel,
RPP-PLAN-57352 7/20/2015 - 12:51 PM 26 of 92
RPP-PLAN-57352 Rev. 1
1-6
refractory and foam of Tank AY-102 should be investigated. These techniques can then
be transferred to investigate the state of other priority DSTs.
The air slots in the refractory provide an opportunity to access the bottom of the primary
tank. Robotic technologies should be pursued that, at a minimum, can enter air slots to
the initial 90o
turn, and provide visual evidence of the condition of the external surface of
the primary tank. Ideally, these technologies could turn multiple corners to access the
center of the tank. This may require widening of air slots, which, as long as it does not
impact structural integrity, would be acceptable.
The Panel was briefed on RolaTubeTM technology that can deploy visual and
Electromagnetic Acoustic Transducer (EMAT) technology through the air
ventilation slots. This appears to be a promising technology and should be pursued
to improve inspection of the primary tank.
Perform ultrasonic testing (UT) of secondary liner bottom in the annulus. The
annulus provides access to the secondary liner bottom and, as such, is an area where UT
data could provide some insight into the state of the condition of the secondary liner.
Optimize use of thermocouples. Tank AY-102 fortunately still has a number of reliable
thermocouples that could potentially provide early notification of a leak. WRPS should
consider deploying technologies that can utilize the existing thermocouples to provide
real-time readings and tracking of anomalies. A sudden, minor change in temperature
could be indicative of a leak.
Improve Continuous Air Monitors (CAMs). The current sample collection point for
the CAMs is in the main duct of the annulus exhaust. In this location, the CAM airborne
detection threshold has proven too high to detect small primary tank leaks. WRPS should
explore altering the sample collection point (e.g. near the annulus floor and other
locations around the annulus perimeter) to again utilize the CAM network as a viable tool
for DST leak detection.
Enhancing Existing Tank Integrity Program Elements to Prevent or Minimize
Degradation of the Double-Shell Tanks
• Perform corrosion tests on the secondary Tank AY-102 and leak detection pit (LDP)
steels at waste-specific and materials-specific conditions in aqueous and vapor
conditions. The Expert Panel Oversight Committee (EPOC) has provided
recommendations on testing of Tank AY-102 (RPP-ASMT-54634, Propensity for
Corrosion in 241-AY-02 Annulus, and RPP-ASMT-55871, Propensity for Corrosion in
241-AY-02 Annulus) and this testing should be performed.
• Ensure low humidity between primary tank and secondary liner. The ventilation
system should be continually operated to prevent moisture collection that could lead to
corrosion. Additionally, WRPS should consider purging the annulus with nitrogen as a
means of drying the potentially wet foam insulation. The presence of nitrogen also has
the potential to reduce the corrosion rate of the steel.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 27 of 92
RPP-PLAN-57352 Rev. 1
1-7
• Perform additional sampling and analysis of sludge at the primary tank bottom.
WRPS should obtain improved data on the nature of the bottom sludge layer that is in
contact with the Tank AY-102 primary tank steel.
1.2.4 Supplemental Panel Recommendations From August Meeting
The supplemental HIAP recommendations from the August meeting documented in RPP-ASMT-
59980 are repeated below.
Rank tank leak risks - WRPS should consider adding a ‘consequences’ evaluation to the
risk ranking. The programmatic, environmental and/or worker health and safety
consequences of a DSTs leak could vary significantly depending on the waste contents
and programmatic importance (e.g. evaporator feed tank).
Perform augmented inspections - The visual and NDE inspection are a high priority for
the Panel. The augmented visual inspections (weekly visual monitoring of 241-AY-102
leak sites, monthly visual monitoring of 95% of the annulus space, increasing the
monitoring frequency for all DST’s from five to three years with visual coverage of 95%)
– are all examples of integrity activities that are responsive to this recommendation.
Ensure Low humidity between primary and secondary tanks – WRPS has been
responsive to this recommendation by continuing operation of the ventilation system.
WRPS should consider utilizing nitrogen tanker trucks to provide the purge gas. This
approach is used efficiently and effectively at many chemical plants and refineries.
Calculate flaw size - Leak rate estimates were presented to the Panel for the three areas
in the annulus where leaked Tank 241-AY-102 waste is located. The Panel recommends
WRPS estimate the flaw size based on these leak estimates. The Panel does not view this
a lengthy or expensive endeavor.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 28 of 92
RPP-PLAN-57352 Rev. 1
2-1
2.0 SUMMARY OF PROGRAM IMPROVEMENTS
The proposed actions which addressed the HIAP recommendations (see Figure 1-2) have been
developed conceptually in Section 3.0, Section 4.0, and Section 5.0 with approximate schedules.
Figure 2-1 provides a summary of the task priorities discussed in Section 6.0. The post-retrieval
forensic recommendations identified in the August 2014 meeting are documented in RPP-
ASMT-59980, High Level Integrity Assessment Plan Workshop Summary.
Figure 2-1. Double-Shell Tank Integrity Task Priorities
RPP-PLAN-57352 7/20/2015 - 12:51 PM 29 of 92
RPP-PLAN-57352 Rev. 1
3-1
3.0 DATA ANALYSIS AND INTERPRETATION ACTIVITIES
3.1 REVIEW TANK CHEMISTRY HISTORY
3.1.1 Document Tank Chemistry History
The panel recommendation on tank chemistry history is provided in the sections below with the
WRPS response and schedule.
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
The investigation into the Tank 241-AY-102 leak revealed a much more complex history
of waste transfers, chemistry and in-tank waste mixing than was previously appreciated.
Based on the aforementioned risk ranking, the program should investigate the detailed
history of tanks with a higher potential for leaks. In addition to potentially identifying
previously overlooked troublesome chemistries in the tanks, such analysis will also allow
for a better understanding of the uncertainty associated with a tank’s chemistry history.
Response/Scope
A review of the chemical history of Tanks AY-102 and AY-101 has been initiated in FY-2014 to
identify periods in time when the waste in these tanks was not in compliance with the current
chemistry specifications, in OSD-T-151-00007, Rev 12, Operating Specifications for the
Double-Shell Storage Tank (OSD), Table 1.5.1 potentially putting the integrity of the tanks at
risk. A template has been designed to present this information that can be used for the analysis
of the other high-risk tanks. The high risk tanks for future reviews include Tanks AY-101,
AY-102, SY-101, SY-103, AW-101, AW-104, and AP-102.
Schedule
High-risk tank chemistry histories will be reviewed and documented in a written report. Starting
in FY 2016 and continuing through for the next three years as shown in Figure 3-1.
Figure 3-1. Schedule to Review Tank Chemistry History
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Develope Template
at $150,000 per tank $300,000 $450,000 $300,000
3.1.1 Develop Template Based
on AY-102
FY 16 FY17 FY18 FY19
RPP-PLAN-57352 7/20/2015 - 12:51 PM 30 of 92
RPP-PLAN-57352 Rev. 1
3-2
3.2 RANK TANK LEAK RISKS
The HIAP recommendation regarding tanks risk was:
Rank tank leak risks. The Tank 241-AY-102 leak caused a reevaluation of the DST
Integrity Program that includes the scope of this Panel. In this reevaluation, the factors
outlined in Section 4.0 of this report provide insight into potential clues to future tank
leaks. Using existing data, WRPS should perform a risk analysis to assess which tanks
are most likely to leak. This, in conjunction with the analysis presented in Attachment 1,
can be used to inform program priorities in allocating resources for integrity activities to
at-risk tanks and those that are most important to the mission.
Initially, the Panel sees the following information as particularly important in judging a
tank’s likelihood of leaking:
1. Temperature during PWHT: This factor affects SCC and therefore is an important
consideration as it could lead to a large leak.
2. Weld rejection rate: This factor is also important as it affects SCC.
3. Liner bulging: Liner bulges during construction can affect SCC by producing large
residual stresses.
4. Maximum waste temperature and temperature cycling: This factor affects both
pitting and SCC.
5. Out of specification chemistry: This factor affects both pitting and SCC.
6. Years of service: This factor affects both pitting and SCC.
7. Operational period without active ventilation: Operation without the annulus air
ventilation may lead to thinning of the outside surface of the primary tank.
This comment resulted in three responses; the first was to develop a qualitative risk ranking that
can be used to weight all of the factors which could influence tank integrity to arrive at a
subjective risk ranking (discussed in Section 3.2.1).
The second step will be to rank the tanks with a more formal assessment, such as a Monte Carlo
analysis, based on the existing UT data from the tank walls (discussed in Section 3.2.2).
The third would be would expand results from the UT wall data to include results from the
bottom plate along with any other relevant factors in a formal risk assessment (discussed in
Section 3.2.3).
3.2.1 Qualitative Risk Ranking for All Double-Shell Tanks
Panel Recommendation
The HIAP recommendation regarding tanks risk was:
Using existing data, WRPS should perform a risk analysis to assess which tanks are most
likely to leak. This, in conjunction with the analysis presented in Attachment 1, can be
RPP-PLAN-57352 7/20/2015 - 12:51 PM 31 of 92
RPP-PLAN-57352 Rev. 1
3-3
used to inform program priorities in allocating resources for integrity activities to at-risk
tanks and those that are most important to the mission.
WRPS should consider adding a ‘consequences’ evaluation to the risk ranking. The
programmatic, environmental and/or worker health and safety consequences of a DSTs
leak could vary significantly depending on the waste contents and programmatic
importance (e.g. evaporator feed tank). (from RPP-ASMT-59980)
Response/Scope
The qualitative risk ranking is attached in Appendix A. It cannot be used to “predict” failures. It
is merely a ranking based on potential factors that may influence operating life. This ranking
will be updated when the forensic activities for Tank AY-102 yield information on the cause of
the bottom plate failure. The weights have been provided by WRPS personal in Tank and
Pipeline Integrity.
Risk ranking criteria are the logical categories of influence provided by HIAP. The measures
were developed from available data on the 28 DSTs. These data points were quantified and
referenced back to source documents to the extent possible.
For each of the evaluation criteria, multiple measures have been developed to help evaluate their
respective criterion and to act as discriminators for making comparisons between alternatives.
Data for each tank is provided and referenced. The scoring is structured so that the tanks can be
discriminated according to performance differences in risk; higher scores represent higher risk.
The performance measures are described in Appendix A. Consequences will be considered in a
future revision
Schedule
This simplified version of the risk ranking would be maintained current with newly developed
data in FY 2016 and FY 2017 until it is replaced with a more formal assessment.
Figure 3-2. Schedule to Update Qualitative Risk Ranking for All Double-Shell Tanks
3.2.2 Risk Analysis Based on Sidewall Ultrasonic Testing Data
Panel Observation
The HIAP observed visual and UT inspection results of the 28 DSTs which, generally, showed
little primary tank wall corrosion. The inspection frequencies should be adjusted according to
the corrosion rates observed.
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Updating Risk Ranking $30,000 $20,000
3.2.1 Document Tank
Chemistry History
FY 16 FY17 FY17
RPP-PLAN-57352 7/20/2015 - 12:51 PM 32 of 92
RPP-PLAN-57352 Rev. 1
3-4
Response/Scope
This risk analysis provides a technical basis for adjusting the inspection frequencies based on the
results acquired to date.
The DST wall inspections cost about two million dollars per year at the frequencies shown in
Table 3-1.
Table 3-1. Double-Shell Tank Inspection Frequencies
Type Frequency Requirement from
Visual (video) Primary 5-7 years RPP-7574, Double-Shell Tank Integrity Program
Plan
Visual (video) Annulus 5-7 years RPP-7574, Double-Shell Tank Integrity Program
Plan
UT Primary Tank Wall from Annulus 8-10 years RPP-7574, Double-Shell Tank Integrity Program
Plan
A formal risk analysis would provide a technical basis for adjusting tank inspection frequencies
based on corrosion rates in individual tanks, and the other factors identified in the risk ranking.
The technical basis for reduced UT inspection frequencies of the primary walls of the DSTs
would be obtained by performing tank-specific analyses. Analyses would address all relevant
tank degradation mechanisms, tank operating history, field measurements, previous inspection
records, chemical constituents, and how these constituents may vary over time. Supporting
analyses would demonstrate that reducing inspection frequencies in the upper sidewall will not
compromise the continued safe operation and confirm that the likelihood of through-wall leak in
the tank sidewall is below acceptable thresholds over the tank anticipated service life.
Schedule
The evaluation would take 12 months to complete, as shown in Figure 3-3. Support from WRPS
would be required to provide the prior chemical analysis and UT wall inspection data.
Figure 3-3. Schedule for Frequency of Ultrasonic Wall Inspection
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Contract Bid/Award $10,000
Evaluation
WRPS Support/Review $10,000
External Review by
DNFSB and Regulators$50,000 $50,000
3.2.2 Risk Analysis Based
on Sidewall UT Data
FY 16 FY17
$200,000
$40,000
RPP-PLAN-57352 7/20/2015 - 12:51 PM 33 of 92
RPP-PLAN-57352 Rev. 1
3-5
3.2.3 Double-Shell Tank Risk Analysis Based on Bottom Plate Data
This activity would be undertaken with successful results from the risk analysis on the UT data
for the sidewalls. The former study would provide conclusions for the frequency of UT scans.
This formal risk analysis needs visual and UT data from inspection of the bottom plate to be
meaningful.
3.3 VALIDATE DOUBLE-SHELL TANK INTEGRITY PROGRAM
3.3.1 Primary Tank Chemistry Controls
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
Review and validate DST integrity program drivers. During the Panel’s review, it
emerged that the DST integrity program is governed by a number of drivers (e.g.
chemistry models, waste compatibility assessment process and caustic limits) that have
developed and evolved over the course of the program’s history (since 1994). The Panel
recommends the program review these drivers to validate that they are based on current,
valid programmatic needs.
The HIAP recommended chemistry models be reassessed in light of the unknowns of the bottom
sludge layer next to the surface of the primary tank bottom plate. The waste compatibility
assessment process and the caustic/nitrate/nitrite limits guiding the program should be revisited
once the chemistry at the bottom plate is known. This action applies to Tank AY-102 from a
forensic standpoint and to the rest of the tanks from the standpoint of maintaining chemistry
control.
Response/Scope
The current practice is to take data from stored core samples taken prior to 2006, document it in
RPP-7795, Technical Basis for the Chemistry Control Program, and determine if concentrations
fit within the current corrosion specifications. Process temperatures from the highest
temperatures in the tank waste are used to determine compliance with the OSD specifications.
No attempts to model old interstitial liquid (ISL) data in current, future compositions, or
temperatures are routinely performed. Some long term modeling is performed by subcontractors
with a finite element analysis.
The following key programmatic drivers that govern chemistry shall be reviewed by the HIAP:
• OSD-T-151-00007, Operating Specifications for the Double-Shell Storage Tanks,
• RPP-7795, Technical Basis for the Chemistry Control Program,
• RPP-13639, Caustic Limits Report,
• RPP-8974, Chemistry Control Program Calculation Methodology for Prediction of
Hydroxide Depletion in Double-Shell Tanks.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 34 of 92
RPP-PLAN-57352 Rev. 1
3-6
Schedule
Updates to the chemistry modeling are part of the current program which occur on an ongoing
basis and are currently funded in the baseline. In addition, the EPOC will be funded for the
oversight and review functions of the programmatic drivers and address any shortcomings found
in FY-2016 through 2016 as shown in Figure 3-4.
Figure 3-4. EPOC Oversight of Tank Chemistry Controls
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
SRNL Lab Support
DNV Lab Support
222-S Lab Support
$600,000 $600,000
$1,000,000
$700,000
$600,000
$1,000,000
$700,000
$1,000,000
$700,000
3.3.1 EPOC Oversight of
Tank Chemistry Controls
FY 16 FY17 FY18 FY19
RPP-PLAN-57352 7/20/2015 - 12:51 PM 35 of 92
RPP-PLAN-57352 Rev. 1
4-1
4.0 IMPROVED DATA GATHERING ACTIVITIES
4.1 PERFORM AUGMENTED WALL SCANNING INSPECTIONS
4.1.1 Develop Electromagnetic Acoustic Transducer and Phased Array
WRPS currently utilizes a P-Scan UT system to perform NDE of the primary tank walls for the
Hanford Site DSTs. The P-Scan system returns high resolution measurements of material
defects (thinning, pitting, cracking), but with a very slow rate of material interrogation. Due to
this slow material interrogation rate, only a small percentage of the tank wall is inspected.
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
Increase visual observations in the annulus. A goal of developing a 100% baseline of
visual observations in all DST annuli should be adopted. Specific to Tank 241-AY-102,
WRPS should increase it’s frequency of visual observations, particularly at Riser 83, to
as frequent as is practicable. If multiple images can be obtained per hour or per day, this
should be considered.
Response/Scope
To address the slow material interrogation rates and limited volume of material inspected, WRPS
has placed a contract in April of 2014 with the Pacific Northwest National Laboratory (PNNL) to
develop and test an integrated EMAT and Phased Array Ultrasonic Transducer (PAUT) system.
Benefits of the EMAT-PAUT system include an increased material interrogation rate and the
subsequent ability to inspect a greater volume of material per deployment. The integrated
EMAT-PAUT system will be deployed using the Force Institute AGS-2 magnetic crawler
chassis. The AGS-2 is currently used to deploy Hanford’s existing P-Scan UT system.
EMAT was successfully deployed into DST AP-102 during the first quarter of FY 2015 with
great results. Deployment operations lasted two days with ~1.5 shifts worth of data collection.
Total wall area interrogated in the first EMAT deployment covered ~1.3% of the entire primary
tank wall which is roughly the equivalent area covered using the P-Scan system during an entire
DST UT campaign (~2-3 months). Additional EMAT deployments into DSTs are currently
planned which will be supplemented with lab testing so that a fully matured implementation
strategy can be developed for the EMAT system within the scope of the DST NDE program.
WRPS has also procured a Force Institute P-Scan Stack system (Figure 4-1) and will be working
with PNNL to test and validate the technology as a means to accelerate primary tank wall weld
joint inspections. The goal is to merge EMAT and PAUT into one cohesive data collection
system mounted to a single Force Institute AGS-2 magnetic crawler (Figure 4-2). This crawler is
identical to current UT crawlers and will be deployed and operate in the same manner.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 36 of 92
RPP-PLAN-57352 Rev. 1
4-2
Figure 4-1. Force Institute P-Scan Stack System
Figure 4-2. AGS-2 Magnetic Crawler
RPP-PLAN-57352 7/20/2015 - 12:51 PM 37 of 92
RPP-PLAN-57352 Rev. 1
4-3
Schedule
The following schedule (Figure 4-3) shows the work flow and time associated with each top
level task. Field testing of the integrated EMAT system is planned to be performed on each
subsequent DST following completion of traditional UT. Mockup testing in the lab will serve to
validate the detection capabilities of the system. The primary objective for supplementing in-
tank evaluations with mockup testing is to reduce the time required to fully implement EMAT
and PAUT into the DST integrity program.
Figure 4-3. Schedule for Electromagnetic Acoustic Transducer Scans and Phased Array
Ultrasonic Transducers
4.1.2 Evaluate Additional Nondestructive Examination (Flash Thermography)
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
Increase visual observations in the annulus. A goal of developing a 100% baseline of
visual observations in all DST annuli should be adopted. Specific to Tank 241-AY-102,
WRPS should increase it’s frequency of visual observations, particularly at Riser 83, to
as frequent as is practicable. If multiple images can be obtained per hour or per day, this
should be considered.
Response/Scope
WRPS will further evaluate additional NDE to enhance the efficiency of the existing wall
scanning method to free-up limited resources for increase support on inspections of tank bottom
plates. Flash Thermography is the planned NDE technology under investigation.
The basic concept of Flash Thermography is that the illumination source induces a temperature
rise at the inspection surface, generally in the form of an impulse, or delta function (short
duration, high intensity pulse). Locations interrupting the flow of heat, such as porosity, will
tend to “insulate” the heat pulse at the surface, creating a thermal indication which can be read
with an infrared (IR) camera. Such indication helps to identify problem areas for further
inspection by UT and visual testing. Flash Thermography is able to detect degradation such as
corrosion, leaks, cracks, porosity, etc.
1Q 2Q 3Q 4Q
EMAT-PAUT DST Field Deployments $10,000 $10,000 $10,000 $10,000
Mockup Testing at PNNL $50,000 $50,000
EMAT-PAUT Engineering Evaluation $10,000
4.1.1 Develop Electromagnetic Acoustic
Transducer Scans and Phased Array
FY 16
RPP-PLAN-57352 7/20/2015 - 12:51 PM 38 of 92
RPP-PLAN-57352 Rev. 1
4-4
Schedule
The projected schedule (Figure 4-4) was provided by AREVA NP Inc. in 2012 and is based on
one (Flash Thermography) of the three proposed NDE methods. The work is tentative planned
for FY 2016.
Figure 4-4. Schedule for Flash Thermography
4.2 INCREASE VISUAL OBSERVATIONS IN THE ANNULUS
The current DST annulus visual inspection program performs enhanced visual inspections of all
28 DSTs on a three year cycle. This visual evidence shows that a three year inspection interval
as described by the enhanced annulus visual inspection plan may fail to give early warning of
additional newly developing leak sites. Currently, Tank AY-102 undergoes a much more
rigorous visual inspection practice which consists of enhanced visual inspection performance on
a monthly basis along with weekly entry into three additional risers (77, 83, and 87) to monitor
known leak accumulation sites. Performing an enhanced visual inspection consists of entering
eight to 12 risers, depending on the tank, to visually observe greater than 95% of the annulus
floor.
4.2.1 Automated Annulus Camera System
In April 2014, HIAP recommended increasing visual inspection frequency to performing
enhanced visual inspections annually on all 28 DSTs. If the recommendation is adopted by
WRPS, then it is evident the current visual inspection practice will need to be optimized in order
to perform the required number of inspections. An automated annulus camera system would
enable field work crews to complete all of the required visual inspections on schedule.
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
Increase visual observations in the annulus. A goal of developing a 100% baseline of
visual observations in all DST annuli should be adopted. Specific to Tank 241-AY-102,
WRPS should increase its frequency of visual observations, particularly at Riser 83, to as
frequent as is practical. If multiple images can be obtained per hour or per day, this
should be considered.
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
NDE SOW/Contract Development
NDE Evaluation/Requirements $30,000NDE Development and Tests
NDE Design and Procedure $100,000NDE Operation and Implementation
4.1.2 Evaluate Additional NDE (Flash
Thermography)
FY 17 FY18
70,000
$50,000
$70,000 $110,000
$200,000
RPP-PLAN-57352 7/20/2015 - 12:51 PM 39 of 92
RPP-PLAN-57352 Rev. 1
4-5
Response/Scope
An annulus video monitoring system would consist of permanently mounted cameras on selected
annulus risers and would function remotely, without an operator field presence, as an annulus
surveillance system. Each riser camera would perform a visual inspection automatically
according to a preprogrammed schedule. All of the recorded video would be wirelessly
transferred to a network drive allowing access to the video files for post processing and review.
At any time, a designated operator could take over manual control of a specific riser camera and
manipulate the view at will.
Each of the permanently mounted riser cameras would be a stand-alone unit with all feedback
and control equipment contained internally. Remote manual manipulation of the camera system
would be accomplished through the use of a graphical user interface developed specifically for
the DST annulus video camera system. The entire 28 DST annulus video camera system would
be unified on a wireless network enabling data transfer and control with remote access.
Conceptually, the physical form function of the installed system might look like in Figure 4-5.
Figure 4-5. Conceptual Design for the Annulus Video Monitoring System
RPP-PLAN-57352 7/20/2015 - 12:51 PM 40 of 92
RPP-PLAN-57352 Rev. 1
4-6
The DST annulus video camera system would significantly reduce the amount of time needed to
perform a visual inspection and the cost of operators. Additionally, the quality and uniformity of
each inspection video would be greatly enhanced, making the post processing and review
activities much more efficient, thus, directly reducing cost and schedule impacts. The possibility
exists to eliminate field work activities associated with inspection performance along with the
associated work package preparation and mobile camera system deployment.
Currently, WRPS is acquiring a custom built visual inspection platform referred to as the Mobile
Still Camera System. The purpose of the new system is to obtain high quality still shots from
within the primary tank space (Waste Group C tanks only). The mechanical function of the
permanently installed riser video cameras closely parallels the function of the Mobile Still
Camera System. The largest difference between the two systems is the control system used to
enable remote operability of the permanently installed riser cameras.
Schedule
The design and fabrication of such a system would be a significant undertaking and, therefore, a
market survey should be performed to gather further information. The survey and concept
review should include discussions within WRPS as well as with capable vendors who could
design and manufacture the automated annulus camera system.
Discussion with capable subcontractors should be able to obtain ROM schedule and costs for
design, prototype development, testing, and manufacturing of a field ready system. Once these
items are addressed, a mature render of the overall cost and schedule can be realized.
After design of a viable concept, the number of applications for each tank would be determined.
Greater than 95% coverage of the annulus floor would require 8-12 risers per tank. High risk
tanks may deserve full coverage but it may not be cost effect to install a full complement of
automated cameras on all 28 tanks. The work is tentatively planned for FY 2016. The schedule
is presented in Figure 4-6.
Figure 4-6. Schedule for a Premium Annulus Video Monitoring System
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Internal WRPS Survey & Concept Review $10,000Procurement
SOW Development
Contract Placement
$10,000
Equipment Development
Prototype Design/Test/Deliver
Work Planning
Operational Readiness Review$40,000
Field Work Prep
Prototype System Field Installation$200,000
WRPS internal engineering system
evaluation period$10,000
Incorporate design modification to field
prototype as needed$10,000
Build 20 additional units @ 25k each
Field Work Prep
Final System Field Installation
4.2.1 Automated Camera SystemFY 17 FY18
$700,000
$500,000
$1,100,000
RPP-PLAN-57352 7/20/2015 - 12:51 PM 41 of 92
RPP-PLAN-57352 Rev. 1
4-7
4.3 VISUAL OBSERVATION AND NDE OF THE PRIMARY TANK BOTTOM
4.3.1 Visual – Robotic Crawler in Air Slots
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
The air slots in the refractory provide an opportunity to access the bottom of the primary
liner. Robotic technologies should pursue that, at minimum, can enter air slots to the
initial 90° turn, and provide visual evidence of the condition of the primary tank.
Response/Scope
Robotic visual inspection of the refractory air slots would be accomplished through the use of a
crawler deployed to the annulus floor. Document RPP-ASMT-55798, Alternatives Evaluation
for Tank 241-AY-102 Robotic Inspection, gives the basis for selection of Vista Engineering, now
Kurion, and a robotic solution to perform refractory air slot inspections (see Figure 4-7).
The key technical feature used in the Kurion concept is RolaTube technology. The RolaTube
and reel drive system used to deploy the camera into the refractory air slots. Deployment of the
Kurion concept would be accomplished via a 12 in. riser at grade to lower the platform down to
the annulus floor (see Figure 4-8).
Once on the annulus floor, the crawler would be
remotely oriented to be tangent to the refractory
pad. The RolaTube reel mechanism would be
rotated 90° to align with the refractory air slots
while magnets on the reel system would lock the
crawler in alignment with the refractory retaining
ring (see Figure 4-9).
Following orientation of the crawler on the
annulus floor the RolaTube is deployed into the
air slot. As the reel is extended through the first
12-foot straight section, the camera attached to
the end of the RolaTube will return live footage
of the refractory air slot (see Figure 4-10).
The camera head will incorporate a mirror to capture multiple views of the air slot without the
need to manipulate the orientation of the camera head itself.
Multiple air slots can be inspected with one deployment of the crawler. Using this inspection
system, visual data can be collected regarding:
• Condition of the refractory material towards the center bottom of the tank.
• Condition of the bottom of the primary tank.
Figure 4-7. Robotic Air Slot Visual
Inspection Crawler
RPP-PLAN-57352 7/20/2015 - 12:51 PM 42 of 92
RPP-PLAN-57352 Rev. 1
4-8
• Number of air slots blocked with leaked tank waste.
• Possible location of the primary tank leak.
Figure 4-8. Deployment Method of Crawler Concept
Figure 4-9. Crawler Oriented on
Annulus Floor and Aligned with Air
Slot
Figure 4-10. Camera Inserted into Refractory Air
Slot for Visual Inspection (note: Primary Tank
Hidden from View)
RPP-PLAN-57352 7/20/2015 - 12:51 PM 43 of 92
RPP-PLAN-57352 Rev. 1
4-9
Schedule
The schedule for this proposed action is summarized in Figure 4-11.
Figure 4-11. Schedule for the Robotic Air Slot Visual Inspection Crawler
4.3.2 Visual–Robotic Annulus Air Supply Pipe Inspections
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
The air slots in the refractory provide an opportunity to access the bottom of the primary
liner. Robotic technologies should be pursued that, at a minimum, can enter air slots to
the initial 90o
turn, and provide visual evidence of the condition of the external surface of
the primary tank. Ideally, these technologies could turn multiple corners to access the
center of the tank.
The annulus air supply pipe provided access to the air plenum at the center of the tank.
Since the leak of Tank AY-102 was discovered, the exact location of the leak in the primary tank
still remains unknown. Leakage on the bottom plate of the primary tank is taking a path through
the refractory pad air slots. The air slots may allow the leak a path to travel with little restriction
to other areas of the tank. Currently, the theory of how the waste may be leaking and traveling
within the refractory pad air slots is only speculation. The objective of visual inspection
performance within the air supply piping is to substantiate the existing theory. Combining the
results of air supply piping robotic visual inspection and the refractory air slots (see Section
4.3.1) will give hard data to answer the following questions:
• How many slots are blocked by leaking waste?
• Where is the exact location of the primary tank leak site?
• What is the condition of the air supply piping?
• Is the central air distribution chamber full (blocked) with waste?
• What is the condition of the center bottom of the primary tank shell?
1Q 2Q 3Q 4Q
Procurement
SOW Development
Contract Placement
$10,000
Tooling Development
Kurion Design/Test/Deliver
Work Planning
Operational Readiness Review$50,000
Field Work Prep
Robotic Inspection$250,000
4.3.1 Visual - Kurion Robotic
Crawler in Air Slots
FY 16
$850,000
RPP-PLAN-57352 7/20/2015 - 12:51 PM 44 of 92
RPP-PLAN-57352 Rev. 1
4-10
• What are the temperature/humidity/flow conditions within the air supply piping?
Response/Scope
Robotic inspection of the ventilation header
would be performed with a scaled variant of the
IHI Southwest Technologies, Inc. (IHI) pipe
crawler that was previously used to perform the
visual inspection of the Tank AY-102 leak
detection pit. Details and results of that
inspection can be found in RPP-RPT-56464,
241-AY-102 Leak Detection Pit Drain Line
Inspection Report. The IHI pipe crawler utilizes
a chassis configuration that allows the robot to
travel through piping bends in addition to
straight sections of pipe (Figure 4-12). On the
front of the crawler chassis is a pan/tilt/zoom
camera head with a dimmable circular array of
light emitting diodes (LEDs).
An overview of Tank AY-102 ventilation air supply piping with relation to tank geometry is
shown in Figure 4-13. The headers travel around the tank circumferentially bellow grade. Color
has been applied to the piping to differentiate the supply and exhaust headers.
Figure 4-14 shows a stripped model of a DST, leaving only the air supply piping. Branching
from the header ring is four supply lines (Drop leg 1-4) which jointly supply air to the center
distribution chamber located centrally within the refractory layer.
Each 4 in. drop leg is cast within the refractory layer up to the central distribution chamber
interface.
Figure 4-12. Robotic Pipe Crawler
Figure 4-13. Ventilation Air Supply System
Overview
Figure 4-14. Air Supply Piping
RPP-PLAN-57352 7/20/2015 - 12:51 PM 45 of 92
RPP-PLAN-57352 Rev. 1
4-11
Upon entering the central air distribution chamber, the direction of flow reverses and travels
radially outward through the refractory air slots and into the annular space between the primary
tank and secondary liner. Upon reaching the annulus, the air is drawn up to each of the six
exhaust risers and evacuated from the system by the exhauster fan. Before the IHI pipe crawler is
deployed in the farm, excavation activities must be performed to expose the joints where the 4 in.
drop legs attach to the supply header ring.
Schedule
Two major portions of work are required to successfully accomplish this inspection. These work
scopes can proceed in parallel.
Ventilation air supply header modification includes:
• Fabrication of new risers for attachment to the existing vent header
• Excavation activities in the farm to expose vent header
• Weld in the farm to attach new risers
• Backfill new risers to grade
IHI custom robotic pipe crawler chassis for 4 in. Schedule 40 pipe includes:
• Prototype CAD design, fabrication, testing and rework
• Field ready crawler fabrication
• Field ready crawler factory acceptance testing
This Activity is prioritized to begin in FY-2017 as shown in the schedule presented in Figure
4-15.
Figure 4-15. Schedule for Robotic Annulus Air Supply Crawler
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Procurement
SOW Development
Contract Placement
$10,000
Tooling Development
IHI Southwest Design/Test/Deliver
ECN Development
Excavation Work Package Planning
Riser Cutting Work Package Development
Mock up Work Package
New Riser Stub Assembly fab Work Package
Robotic Inspection Work Package
On Site Mock up Demonstration $30,000Work Planning
Operational Readiness Review$10,000
Field Work Prep
Robotic Inspection$880,000
4.3.2 Visual - Robotic Annulus Air Supply Pipe
Inspections
$170,000
FY 18 FY19
$200,000
RPP-PLAN-57352 7/20/2015 - 12:51 PM 46 of 92
RPP-PLAN-57352 Rev. 1
4-12
4.3.3 Nondestructive Examination–Synthetic Aperture Focusing Technique and Tandem
Synthetic Aperture Focusing Technique
Panel Recommendation
The HIAP recommended WRPS perform enhanced NDE to inspect the tank bottoms. The
implementation of advanced UT techniques at the tank bottom is to obtain quantitative data to
validate the structural integrity in the lower region of DST. The recommendation is in
RPP-ASMT-57582:
Visual and NDE observations of the primary tank bottom. Techniques to provide
observational data for the bottom steel, refractory and foam of Tank 241-AY-102 should
be investigated. These techniques can then be transferred to investigate the state of other
priority tanks.
Response/Scope
The existing Synthetic Aperture Focusing
Technique (SAFT) and Tandem Synthetic
Aperture Focusing Technique (T-SAFT) (Figure
4-16) will be deployed to perform the following:
1. Perform preliminary evaluation which
involves assembling existing inspection
hardware that is already owned by
WRPS to evaluate its current condition
and applicability for inspection of the
primary tank bottom.
2. Develop mockup to demonstrate the
revised capabilities of this T-SAFT
technique.
3. Provide limited detection but not dimensioning capability.
4. Assemble, test, and document the pros and cons of these techniques in conjunction with
normal ultrasonic inspection. The report will provide path forward recommendation as to
whether any or all of the existing systems could be utilized as an enhanced inspection
device for the primary tank bottoms.
Schedule
For PNNL to make further progress for redeployment and revalidation of the existing
SAFT/T-SAFT methods, the following schedule is given in Figure 4-17.
Figure 4-16. FORCE–Extended Arm and
Tandem Synthetic Aperture Focusing
Technique for Lower Knuckle Region
RPP-PLAN-57352 7/20/2015 - 12:51 PM 47 of 92
RPP-PLAN-57352 Rev. 1
4-13
Figure 4-17. Schedule for Ultrasonic Testing using Synthetic Aperture Focusing Technique
and Tandem Synthetic Aperture Focusing Technique
4.3.4 Nondestructive Examination - Robotic Crawler (Guided Wave in Air Slots)
The HIAP has recommended that WRPS to gather data specific to the bottom of the primary
tank. The majority of the proposed robotic inspections will return visual data of the primary tank
bottom. UT and/or guided wave UT scans of the lower primary tank plates would supplement
the visual inspection.
Panel Recommendation
The HIAP recommended in Section 6.1 of RPP-ASMT-57582:
The Panel was briefed on RolaTube technology that can deploy visual and EMAT
technology through the air ventilation slots. This appears to be a promising technology
and should be pursued to improve inspection of the primary tank.
Response/Scope
To supplement the visual data there should be an effort made to gather data about the lower
primary tank liner, specifically; thinning, pitting, and cracking. A potential solution to gather
this kind of data resides in the annulus crawler used to perform the refractory air slot visual
inspection. The crawler chassis shown in Figure 4-7 might be modified to deploy UT or guided
wave UT sensor elements into the refractory air slots.
Conceptually the UT/guided wave UT sensory device would be mounted to the end of the
RolaTube and inserted into the refractor air slot to the desired depth and then temporarily affixed
to the bottom of the primary liner. If a guided wave UT material interrogation method is pursued
it will most likely require two crawlers to be deployed to the annulus floor and work in a parallel
effort.
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Procurement
SOW Development
Contract Placement
$40,000
Enhancement Development
PNNL Design/Test/Deliver
Work Planning
Operational Readiness Review$80,000
Field Work Prep
TSAFT In-Service Implementation$60,000
$120,000
4.3.3 UT - SAFT and T-SAFTFY 16 FY17
RPP-PLAN-57352 7/20/2015 - 12:51 PM 48 of 92
RPP-PLAN-57352 Rev. 1
4-14
Schedule
The following schedule is presented in Figure 4-18.
Figure 4-18. Schedule for the Robotic Multi-Air Slot Nondestructive Evaluation
4.3.5 Nondestructive Examination–Guided Wave System (Across Tank Diameter)
Panel Recommendation
The HIAP recommended WRPS perform enhanced NDE to inspect the tank bottom. The
implementation of advanced UT techniques at the tank bottom is to obtain quantitative data to
validate the structural integrity in the lower region of DSTs.
Response/Scope
The Long Range Guided Wave Ultrasonic Testing (LRGWUT) (see Figure 4-19) is being
proposed as a method for evaluation of the primary tank bottom in two stages.
1. Research will be conducted to ascertain what has been performed in industry to identify
similar applications. The literature survey will provide a basis for further investigation
using similar techniques.
2. A small scale proof of principal test using guided wave equipment will be performed to
evaluate various guided wave-mode propagations. The test will be performed on plate
material representative of the type and thickness of the tank bottom used in the AY Tank
Farm to confirm useable acceptability of the application.
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Procurement
SOW Development
Contract Placement
$10,000
Tooling Development
Kurian Design/Test/Deliver
Work Planning
Operational Readiness Review 50,000Field Work Prep
Robotic Inspection $250,000
$850,000
FY 16 FY174.3.4 UT - Kurion Robotic
Crawler (Guided Wave in Air
Slots)
RPP-PLAN-57352 7/20/2015 - 12:51 PM 49 of 92
RPP-PLAN-57352 Rev. 1
4-15
Figure 4-19. Long Range Guided Wave Ultrasonic Testing
LRGWUT enables a large area of structure to be tested from a single transducer position thereby
avoiding the time-consuming scanning required by the conventional ultrasonic methods. This
technique becomes even more attractive if part of the structure to be tested is inaccessible. The
test is usually done in pulse-echo mode. The transducer is transmitting the guided wave along
the structure and returning echoes indicating the presence of defects or other structural features.
To demonstrate this technique, a 75 ft diameter DST carbon steel mockup with consistence tank
constructability and field conditions will be needed.
The LRGWUT method will be evaluated and the limitations are to be documented with a path
forward recommendation as to whether LRGWUT technology could be utilized as an inspection
device for the primary tank bottoms.
Schedule
The projected schedule references the basis for LRGWUT development and implementation as
shown in Figure 4-20.
Figure 4-20. Schedule for Inspection using Guided Wave Transducers
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Procurement
SOW Development
Contract Placement
$60,000
Enhancement Development
Design/Test/Deliver
Onsite Mock-Up Demonstration
(Guided-Waves)$250,000 $250,000
Field Work Prep
Guided Waves In-Service
Implementation$120,000
4.3.5 UT - Guided Wave System (Across
Tank Diameter)
FY18 FY19
$340,000
Transmitter Receiver
Volume Inspected
RPP-PLAN-57352 7/20/2015 - 12:51 PM 50 of 92
RPP-PLAN-57352 Rev. 1
4-16
4.4 PERFORM ULTRASONIC TESTING ON SECONDARY TANK BOTTOM IN
THE ANNULUS
4.4.1 Perform Ultrasonic Testing with Existing Procedure
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
The annulus provides access to the secondary tank bottom and, as such, is an area where
UT data could provide some insight into the state of the condition of the secondary tank
bottom.
Response/Scope
The existing wall scanning UT equipment can be used to scan the floor of the annulus. This
action is fairly straightforward and will be included in the scope of all future wall scans.
4.5 OPTIMIZE USE OF THERMOCOUPLES FOR EARLY LEAK NOTIFICATION
4.5.1 Use of Thermocouples to Detect Leaks
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
Tank 241-AY-102 fortunately still has a number of reliable thermocouples that could
potentially provide early notification of a leak. WRPS should consider deploying
technologies that can utilize the existing thermocouples to provide real-time readings and
tracking of anomalies. A sudden, minor change in temperature could be indicative of a
leak.
Response/Scope
This recommendation is not accepted. About half the thermocouples have failed and would not
be particularly useful in detecting a leak (Table 4-1). Normal temperatures from the
thermocouples that do exist would simply be a false positive indication that no leak had
occurred.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 51 of 92
RPP-PLAN-57352 Rev. 1
4-17
Table 4-1. Tank AY-101 and Tank AY-102 Thermocouples Operable (8/2012)
Refractory AY-101 AY-102
7-ft ring 3 of 4 2 of 4
21-ft ring 8 of 8 4 of 8
36-ft ring 9 of 13 8 of 13
Base slab 0 of 9 4 of 9
Additionally, the variation in thermocouple temperatures is from the operation of the annulus
ventilation system. Outages and outside air temperature are primary drivers that would mask
leaks, presuming a leak did occur in the vicinity of an operable thermocouple.
4.6 IMPROVED CONTINOUS AIR MONITORING
4.6.1 Improved Annulus Air Monitoring Design
Each DST is equipped with a CAM. Each CAM unit draws and returns samples from its
respective tank annulus exhaust. The sampling and return ports on the duct are located upstream
of the filtration equipment. A vacuum pump at the CAM station pulls air from the annulus duct
into the CAM analyzer. If contamination is detected, a signal activates a local alarm light and
the alarm horn at the radiation-monitor station. Simultaneously, a signal is transmitted to the
respective control room, activating an annunciator on the monitor and control system and
energizing the alarm light on the human-machine interface monitors.
By design, each DST annulus ventilation exhaust CAM serves as a primary means of leak
detection. Through experience gained from Tank AY-102 leak observation, the only time the
annulus CAM alarms is when the waste accumulation on the annulus floor is disturbed. Annulus
Honeywell ENRAF-Nonius 854 (ENRAF) leak detectors in Tank AY-102 are proving
ineffective in that they are not in alarm despite waste clearly leaking into the annulus. Overall,
the extent of our DST design provides no effective detection capability for small and slow leaks
such as the one observed in Tank AY-102.
A possible cause for the CAM problem could be that the reduction of velocity when the annulus
air exits the air slots under the primary tank is too great to maintain radioactive particulate
suspension in the annulus chamber, and carry the contamination to the top of the annulus into the
exhaust ductwork where it would be sampled, triggering an alarm.
Some initial work has been done to understand the flow phenomenon through the annulus
ventilation system, utilizing mass flow rate balancing to determine the reduction of velocity
experienced transitioning from the air slot to the complete annulus cross section. Estimates of
the air velocity transition from the refractory air slots to the annulus are 18.6 ft/sec to
0.034 ft/sec. This significant reduction in flow velocity is of interest in that it helps to
understand the ventilation systems ability to uplift airborne radionuclide particles into the
exhaust system flow with enough reliability to consistently detect a small and slow leak.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 52 of 92
RPP-PLAN-57352 Rev. 1
4-18
More complicated modeling of particle-laden air flow would be required to determine the extent
to which particles can be entrained in the ventilation system flow and travel to the CAM unit,
located just before the on-grade exhaust system.
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
CAMs in the DST system have historically been used as a leak detection mechanism.
However, in recent years, the CAMs have not been sufficiently reliable to be useful in this
application. WRPS should explore improving the design of the CAMs to again utilize the
network as a tool for detecting leaks
Response/Scope
Improvements to the system have been identified to address current detection limitations. Since
these limitations generally stem from the CAM system sampling location and the ability to
reliably deliver annulus radionuclide particles to it through the exhaust system, any modification
to the system to achieve more reliable particle detection will reduce the resistance between
potential leak sites and the CAM sampling system. With this criteria in mind, the following
subset of improvement possibilities have been identified:
Option 1: Improve Continuous Air Monitoring System
To improve the current CAM system, modifications to the exhaust risers and CAM sample
locations would be required. Problems with the current system likely relate to inadequate
particle entrainment in flow and friction losses in the exhaust header through the flow path. That
is to say that radioactive particles cannot be confidently uplifted by the reduced annulus
ventilation velocity to the riser penetration and upon entry into the system, inherent friction
within the extensive exhaust header presents resistance to flow that may hinder collection of
particles on the upstream CAM system.
Current exhaust risers penetrate the top of the annulus space where a cross-sectional area
increase in the annulus space causes a significant velocity reduction. Mitigation of this reduction
in velocity could be accomplished by extending the source of vacuum further down toward the
bottom of the annulus space with an extended exhaust riser. An extension of these risers would
serve to reduce the distance which entrained particles travel.
In addition to modifications to the riser penetration, CAM units could be collocated in-line with a
number of existing exhaust riser penetrations to limit the length of pipe travel from a leak site to
a detection method. This modification would function just as the existing system does, but with
more sampling points located closer to the sources to improve detection capability.
While the scope of improved air monitoring throughout the DST system and number of CAM
units required for each tank are items requiring further engineering evaluation, the advantages of
an effective continuous monitoring system as a primary means of leak detection cannot be
overstated. With the current absence of slow and small leak detection capability via existing
CAMs or automated level indicators, the existing manual, visual inspection program has
RPP-PLAN-57352 7/20/2015 - 12:51 PM 53 of 92
RPP-PLAN-57352 Rev. 1
4-19
expanded to function in leak detection and monitoring capacity. Any improvements to the
automated and continuous monitoring solutions for leak detection to achieve reliable
functionality would serve to alleviate the significant operational burden related to the growing
scope of the manual, visual inspection program.
Option 2: Develop a Riser Deployable Air Monitoring System
While a reliable and automated CAM system as described in Option 1 is the most desirable
improvement methodology, provisions could be made to deploy a more modular air monitoring
system. This system would be a self-contained, annulus riser mounted assembly. Generally
speaking, it would provide its own source of vacuum and recirculate flow back through the same
riser. Within the closed loop system, a filter would be raised and lowered into the annulus space
to variable depth allowing manual control of sample location and duration.
Upon filter return to the riser mounted assembly, radiological monitoring of the paper would
occur to trend contamination presence in the annulus space on an engineering defined
periodicity. This system could operate in a manual and/or automated fashion. It is conceivable
that these two options could be integrated into one cohesive system for annulus inspection.
Schedule
This work is deferred to FY 2018. The schedule is summarized in Figure 4-21.
Figure 4-21. Schedule for Improved Annulus Air Monitoring Design
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Engineering Evaluation of Improvement
Scope$10,000
Evaluation Options for Improvement and
Conclude
Mockup/Prototype Development $50,000
Test Chosen Concept $50,000
Update Concept Based on Test Results $20,000
4.6.1 Improved Annulus Air Monitoring
Design
FY 18 FY19
$100,000
$100,000
RPP-PLAN-57352 7/20/2015 - 12:51 PM 54 of 92
RPP-PLAN-57352 Rev. 1
5-1
5.0 ENHANCED EXISTING INTEGRITY PROGRAM TO MINIMIZE
DOUBLE-SHELL TANK DEGRADATION
5.1 CORROSION TEST SECONDARY LINER AND LEAK DETECTION PIT STEEL
FOR TANK AY-102
5.1.1 2014 Corrosion Work on Tank AY-102 Steel
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
Corrosion test the secondary Tank 241-AY-102 and Leak Detection Pit steels at waste-
specific and materials-specific conditions in aqueous and vapor conditions. The EPOC
has provided recommendations on testing of Tank-AY-102 (RPP-ASMT-54634 and RPP-
ASMT-55871) and this testing should continue to be performed.
Response/Scope
This recommendation is being resolved with work currently ongoing and is being reviewed by
the EPOC.
5.2 ENSURE LOW HUMIDITY BETWEEN PRIMARY AND SECONDARY LINERS
5.2.1 Dehumidifiers on Annulus Air Inlet
Panel Recommendation
The HIAP recommended in RPP-ASMT-57582:
Ensure low humidity between primary and secondary tanks. The ventilation system
should be continually operated to prevent moisture collection that could lead to
corrosion. Additionally, WRPS should consider purging the annulus with nitrogen as a
means of drying the potentially wet foam insulation. The presence of nitrogen also has
the potential to reduce the corrosion rate of the steel.
WRPS should consider utilizing nitrogen tanker trucks to provide the purge gas. This
approach is used efficiently and effectively at many chemical plants and refineries. (from
RPP-ASMT-59980)
Water vapor in the humid ambient air is drawn into the ventilation piping and may be creating a
moist environment in the annular space of the DSTs, which may result in corrosion of the
primary tank bottom or secondary liner. It was recommended by the HIAP to achieve low
humidity between the primary tank and secondary liner. Reducing the water vapor in the air
used to ventilate the annular space of the DSTs reduces the propensity for corrosion on the
bottom of the primary tank and secondary liner.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 55 of 92
RPP-PLAN-57352 Rev. 1
5-2
Response/Scope
DSTs contain radioactive sludge that is
thermally hot because of heat generated by the
decay of radioactive elements. The heat makes
it necessary to cool primary tanks utilizing air
slots beneath the primary tank bottom which
exhaust into the annulus.
An exhauster is used to pull air through four
ventilation pipes (241-AW, AN, and AP Farm
tanks all have eight ventilations pipes, all other
tanks use four) which enter the annulus through
risers. The ventilation piping runs down the
secondary liner wall and across the secondary
liner bottom to the center of the tank and is
embedded in the refractory. The ventilation
piping ends at an air distribution ring at the
center of the tank. From the air distribution
ring, the air flows through the air slots in the
refractory and out to the annulus where it is
routed out of the annulus to the exhauster (see
Figure 5-1).
A dehumidifier can be used to reduce the
water vapor found in humid ambient air by
condensing the water vapor. Atmospheric air
enters a chiller condenser, which cools the air
down to the dew point to allow water vapor to
condense and dry air leaves the system.
Heaters are used prior to the discharge during
cooler temperatures. Desiccants are
sometimes used as a pre-treatment to reduce
the amount of cooling that needs to take place.
Dehumidifiers are commonly used in industry
and portable industrial humidifiers are readily
available in pre-built packages.
A silica gel desiccant can also be used to
dehumidify the air. The desiccant works by
attracting the moisture in the air to stick to it.
Some of these systems reactivate the desiccant
by heating it to drive off the moisture. These
desiccants can last up to 20 years. Desiccant
systems can be used in tandem with the chiller
condenser unit to further reduce the relative
humidity.
Figure 5-1. Proposed Dehumidifier
Layout
Figure 5-2. Portable Industrial
Dehumidifier with Condenser Reheat
RPP-PLAN-57352 7/20/2015 - 12:51 PM 56 of 92
RPP-PLAN-57352 Rev. 1
5-3
A single dehumidifier can be purchased for each DST farm. A manifold can be used to connect
the dehumidifier to the air inlet for each tank in the farm. See Figure 5-2 for an example of a
commercial dehumidifier.
Schedule
Design:
Design of the dehumidification system involves determining the best placement of
dehumidification equipment including a dehumidifier and ductwork. Drawing modifications,
new drawings, calculations, specifications, electrical flash, and arc flash are also part of the
design process. Calculations for dome loading, structural analysis, ducting supports, ventilation
duct loss, and seismic analysis are necessary.
Dehumidifier Procurement:
There are two main ways to dehumidify air. The first method is to use a chiller condenser
(refrigeration unit) to remove water vapor from the air and reduce the relative humidity. The
other method is to use silica desiccants, which draw moisture out of the air. These two systems
can be used in tandem to reduce the relative humidity even more. It is not currently known how
low the relative humidity should be to reduce any possible corrosion. Therefore, at this time
only the refrigeration dehumidification unit is considered.
Develop Test Plan and Test Dehumidifier:
There are several sets of tests that may need to be conducted on the system prior to operation.
There are two categories which govern the testing of equipment. They are as follows:
• Factory acceptance test (FAT)
• Operation acceptance test (OAT)
The FAT is conducted directly after receipt of the equipment from the factory. Each part of the
system is tested to determine that it meets factory specifications and tolerances. The OATs are
usually the same as the FATs. However, OATs are completed after the equipment is moved into
the field and prior to operation of the equipment. These tests are to ensure that nothing was
damaged during transportation and placement in the field. FATs and OATs require the
development of a test plan, sub-test plan, and a test requirement matrix.
Field Installation and Connecting Dehumidifier:
The placement of the dehumidifier will require the use of a crane and rigging crew along with
other support personnel required for entry into a tank farm. It will require the determination of
exclusion zones and access points within the tank farm. The dehumidifier shall be placed on a
concrete base pad. Excavation and digging permits may be required to place the base.
Connecting the dehumidifier includes running ducting to the tanks. All ducting is to be run from
the dehumidifier to the annulus air inlets for each tank. Ducting can be run below grade or above
RPP-PLAN-57352 7/20/2015 - 12:51 PM 57 of 92
RPP-PLAN-57352 Rev. 1
5-4
grade. Ducting routed above grade runs the risk of cutting off access points and crane routes
within the tank farm. Running ducting below grade requires digging permits, and extensive
radiological surveillance.
Assuming 150 ft of ducting, this activity includes digging, placing the ductwork, and back filling
requirements.
This work is deferred to FY 2018. Schedule durations are shown in Figure 5-3.
Figure 5-3. Schedule for Annulus Air Humidity Control
5.3 SAMPLING AND ANALYSIS OF SLUDGE AT THE BOTTOM PLATE
5.3.1 Core Sample Tank AY-102 at Bottom Plate
This activity was deleted to avoid delays in Tank AY-102 retrieval.
5.3.2 Analyze Sample (Corrosion Testing)
This activity, analysis of the AY-102 sample, was deleted to avoid delays in Tank AY-102
retrieval.
5.3.3 Sample AY-102 Annulus with Robotic Crawler
Although remote sampling of leaked tank waste in the annulus of Tank AY-102 has been
successfully performed in past events, WRPS currently has no remote capability to obtain
new/additional samples from the annular space of a DST. Forgoing the opportunity to get a
primary tank bottom sample in Tank AY-102, shifts the annulus sampling activity to a higher
priority. Maintaining remote annulus sampling capability assures that in an emergent situation
the equipment is on the shelf and capable of performing the work. Currently there is need of
additional samples which will be used to perform corrosion testing. Acquisition of the much
needed sample material is contingent on WRPS obtaining a remote sampling technology
designed specifically for the annular space of the DSTs.
Panel Recommendation
The HIAP recommended obtaining a better sample from the accumulating material in the
annulus of Tank AY-102. This was once attempted with little success. With a better
understanding of the material in the annulus, a potential cause of the leak may be determined.
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
Design
Procure Dehumidifier
Develop Test Plan
Test Dehumidifier $20,000
Place Dehumidifier $50,000
Connect Dehumidifier to Tank $30,000
5.2.1 Dehumidifiers on Annulus
Air Inlet
FY 18 FY19
$300,000
$90,000
$10,000
RPP-PLAN-57352 7/20/2015 - 12:51 PM 58 of 92
RPP-PLAN-57352 Rev. 1
5-5
This activity becomes a priority in the absence of taking a sample near the bottom of the primary
tank.
Response/Scope
WRPS should perform a market survey of
capable vendors who can provide the necessary
equipment to perform remote sampling
activities in the annular space of the DSTs. The
study should begin by reviewing previously
used annulus sampling equipment and then
utilize lessons learned to develop an optimized
remote sampling platform designed specifically
for the DST annulus environment. Previously
used annulus sampling equipment can be seen in
Figure 5-4 and Figure 5-5. The market survey
should conclude by designating a vendor
capable of procuring a remote annulus sampling
platform optimized for the DST annulus
environment.
The off riser sampling system (ORSS) was
originally used to scoop solid samples from the
floor of SSTs following retrieval activities. The
ORSS was deployed through Riser 91 of Tank
AY-102 on September 26, 2012 to sample the
leaked waste accumulation site near Riser 83.
Sampling efforts were successful but not
without challenges which could be overcome
had the ORSS been designed specifically for
annulus sampling missions.
The remote underground sampler (RUS) was
developed by AREVA as a remote underground
sampler designed to collect potentially hard
material. Sampling of material near Riser 90 of
Tank AY-102 occurred on October 15 and 17,
2012. Mounted to the front of the crawler was
an auger bit in a sleeve with a scoop underneath that could dump sampled material into a
container.
Following the final report’s recommendation, the selected technology vendor would be
contracted to develop, procure, and test the remote sampling technology. After the technology is
proven lab capable of deployment into the field, the system will be deployed into the annular
space of Tank AY-102 to collect additional samples of the leaked tank waste so that corrosion
testing can be performed with actual materials as opposed to simulants.
Figure 5-4. Washington River Protection
Solutions Off Riser Sampling System
Figure 5-5. AREVA Remote Underground
Sampler
RPP-PLAN-57352 7/20/2015 - 12:51 PM 59 of 92
RPP-PLAN-57352 Rev. 1
5-6
Schedule
The following schedule shows the work flow and time associated with each top level task
(Figure 5-6). The subject scope of the document would include: a recommendation for the
optimal remote annulus sampling system, a system design description, implementation strategy,
and recommended path forward.
Figure 5-6. Schedule for Robotic Annulus Sampling
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q
WRPS Engineering Concept Development $7,000
RFP Placed $40,000
Review of Proposal(s) $3,000
Develop RPP
Develop SOW/Place Contract $40,000
Procure Remote Annulus Sampling System
Work Planning/Operational Readiness Review $50,000
Field Work Preparation/Remote Sampling Performed
5.3.3 Sample Annulus with Robotic CrawlerFY 16 FY17
$10,000
$100,000
$250,000
RPP-PLAN-57352 7/20/2015 - 12:51 PM 60 of 92
RPP-PLAN-57352 Rev. 1
6-1
6.0 CONCLUSIONS AND PATH FORWARD
In the August 2014 meeting with the HIAP, an out brief was provided with their
recommendations. The most important areas for future work are 1) the condition of the top and
bottom surfaces of the primary tank, and 2) the viability of the secondary liner. The actions that
logically flow from these priorities are:
1. Visual inspection of the annulus air slots and air supply lines.
2. Measuring the primary bottom plate thickness.
3. Waste samples from a core in the primary tank at the surface of the bottom plate and the
leaked material on the floor of the annulus.
4. Corrosion testing.
With these priorities and recommendations, the path forward has been established for each of the
project actions as summarized in Table 6-1. The task priorities are defined as follows:
1a. Ongoing work from existing budgets in FY 2015 and/or FY 2016.
1b. Deploy in FY 2016 via Budget Change Request (BCR).
1c. Develop the technology in FY 2016 via BCR.
2. Second priority candidates for further develop and funding in FY 2017.
3. Third priority activities deferred to FY 2018 or later.
Table 6-1. Double-Shell Tank Integrity Task Priorities and Path Forward (3 Pages)
Task Priority Description of Path Forward
3.1.1 Document Tank
Chemistry History
1b A template has been established and work has been initiated for
Tanks AY-101, AY-102, AN-102 and AN-107. The remaining
tanks will be completed within the scope of the Base Operations
Process Engineering and the results will be integrated into the
Qualitative Risk Analysis.
3.2.1 Qualitative Risk
Ranking for All DSTs
1b An initial risk ranking has been completed and included in
Appendix A. This evaluation will be maintained current with
results from Task 3.1.1 and related performance measure
additions or changes.
3.2.2 Risk Analysis Based
on Sidewall UT Data
1b The sidewall UT data will be evaluated formally as a bases to
adjust the frequency of the inspections.
3.2.3 DST Risk Analysis
Based on Bottom Plate
Data
3 This work depends on future bottom plate measurements which
will not be available for several years.
3.3.1 Primary Tank
Chemistry Controls
1b The EPOC will be engaged in an overview of chemistry control
program as funding is available.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 61 of 92
RPP-PLAN-57352 Rev. 1
6-2
Table 6-1. Double-Shell Tank Integrity Task Priorities and Path Forward (3 Pages)
Task Priority Description of Path Forward
4.1.1 Develop EMAT and
Phased Array
1a Limited testing of these technologies will be accomplished with
existing funding as a basis to assess future use. These
approaches do not add water to the annulus. The current UT
approach adds 3-5000 gallons of water per inspection.
4.1.2 E valuate Additional
NDE (Flash
Thermography)
2 Some vendor investigations will be conducted but development
and testing will be deferred.
4.2.1 Automated Annulus
Camera System
2 The annulus camera system concept will be developed but
deployment will be deferred pending system performance.
4.3.1 Visual– Robotic
Crawler in Air Slots
1b The crawler will be fabricated and deployed in Tank AY-101 to
inspect the air slots.
4.3.2 Visual–Robotic
Annulus Air Supply Pipe
Inspections
3 The annulus air supply pipe inspection will be deferred until
after retrieval to avoid schedule impacts.
4.3.3 NDE–SAFT and T-
SAFT
1c Limited demonstration work will be conducted with SAFT and
T-SAFT. Deployment will be deferred.
4.3.4 NDE–Robotic
Crawler (Guided Wave in
Air Slots)
1c The Crawler developed for visual inspection (Task 4.3.1) will be
designed such that the platform can be used for NDE after a
successful visual deployment.
4.3.5 NDE–Guided Wave
System (Across Tank
Diameter)
3 Limited development will be conducted to assess feasibility.
Deployment will be deferred pending an assessment of the
viability.
4.4.1 Perform UT with
Existing Procedure
1a The annulus bottom will be inspected as part of the normal UT
scanning procedure. Consideration will be given to assessing
tanks with moisture in the tertiary collection system beneath the
annulus liner.
4.5.1 Use of
Thermocouples to Detect
Leaks
2 An engineering evaluation will be conducted to assess historic
thermocouple data with a heat transfer model of the air slots to
see if a correlation between temperatures and leak location can
be made. Follow-on actions will be determined based on the
results.
4.6.1 Improved Annulus
Air Monitoring Design
(CAM)
3 No viable concepts have been identified to improve the CAM
design approach as a means of detecting tank leaks into the
annulus.
5.1.1 2014 Corrosion
Work on Tank AY-102
Steel
1a The corrosion work is ongoing with FY 2014 funding. Results
will be reviewed by the EPOC.
5.2.1 Dehumidifiers on
Annulus Air Inlet
3 Dehumidifiers will not be installed on the annulus inlet air. The
annulus ventilation system will be operated with ambient air
with outages limited by the current operating specifications.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 62 of 92
RPP-PLAN-57352 Rev. 1
6-3
Table 6-1. Double-Shell Tank Integrity Task Priorities and Path Forward (3 Pages)
Task Priority Description of Path Forward
5.3.1 Core Sample AY-
102 at Bottom Plate
1a This activity was deleted to avoid delays in Tank AY-102
retrieval.
5.3.2 Analyze AY-102
Sample (Corrosion
Testing)
1a This activity was deleted to avoid delays in Tank AY-102
retrieval.
5.3.3 Sample Annulus
with Robotic Crawler
2 The annulus sampling in Tank AY-102 is a priority in the
absence of taking the bottom sample in Tank AY-102.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 63 of 92
RPP-PLAN-57352 Rev. 1
7-1
7.0 REFERENCES
ASTM G129-00, 2013, Slow Strain Rate Testing to Evaluate the Susceptibility of Metallic
Materials to Environmentally Assisted Cracking, ASTM International, West
Conshohocken, PA.
ASTM G61-86e1, 2003, Standard Test Method for Conducting Cyclic Potentiodynamic
Polarization Measurements for Localized Corrosion Susceptibility of Iron-, Nickel-, or
Cobalt-Based Alloys, ASTM International, West Conshohocken, PA.
OSD-T-151-00007, 2013, Operating Specifications for the Double-Shell Storage Tanks, Rev. 12,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-13639, 2014, Caustic Limits Report – For Period Ending January 1, 2014, Rev. 10,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-29600, [DRAFT], Evaluation of Tank 241-AW-104 Supernatant and Interstitial Liquid
Hydroxide Concentration, Rev. 2, Washington River Protection Solutions, LLC,
Richland, Washington.
RPP-52349, 2013, Tank 241-AN-106 Thermal Analyses Uncertainty Evaluation, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-53070, 2013, Tank 241-AN-101 Thermal Analysis, Rev. 0, Washington River Protection
Solutions, LLC, Richland, Washington.
RPP-53793, 2012, Tank 241-AY-102 Leak Assessment Report, Rev. 0, Washington River
Protection Solutions, LLC, Richland, Washington.
RPP-56864, 2014, Tank 241-AY-102 Thermal Evaluation of Supernatant Reduction, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-7574, 2010, Double-Shell Tank Integrity Program Plan, Rev. 3, Washington River
Protection Solutions, LLC, Richland, Washington.
RPP-7795, 2013, Technical Basis for the Chemistry Control Program, Rev. 11, Washington
River Protection Solutions, LLC, Richland, Washington.
RPP-8974, 2011, Chemistry Control Program Calculation Methodology for Prediction of
Hydroxide Depletion in Double-Shell Tanks, Rev. 4, Washington River Protection
Solutions, LLC, Richland, Washington.
RPP-ASMT-54634, 2013, Propensity for Corrosion in 241-AY-102 Annulus, Rev. 0, Washington
River Protection Solutions, LLC, Richland, Washington.
RPP-ASMT-55798, 2013, Alternatives Evaluation for Tank 241-AY-102 Robotic Inspection,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 64 of 92
RPP-PLAN-57352 Rev. 1
7-2
RPP-ASMT-55871, 2013, Propensity for Corrosion in 241-AY-102 Annulus, Rev. 0, Washington
River Protection Solutions, LLC, Richland, Washington.
RPP-ASMT-57582, Second Workshop of the High Level Waste Integrity Assessment Panel:
Extent of Condition and Balance of Program, Rev. 0, Washington River Protection
Solutions, LLC, Richland, Washington.
RPP-RPT-56464, 2014, 241-AY-102 Leak Detection Pit Drain Line Inspection Report, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 65 of 92
RPP-PLAN-57352 Rev. 1
A-i
Appendix A
QUALITATIVE RISK RANKING PERFORMANCE MEASURES
A-
RPP-PLAN-57352 7/20/2015 - 12:51 PM 66 of 92
RPP-PLAN-57352 Rev. 1
A-ii
CONTENTS
A1.0 QUALITATIVE RISK RANKING OF DOUBLE-SHELL TANK FAILURE .............. A-1
A1.1 Performance Measures .......................................................................................... A-2
A1.2 Risk Ranking Results ............................................................................................ A-2
A1.3 Consequences ........................................................................................................ A-2
A2.0 CONSTRUCTION QUALITY ........................................................................................ A-3
A2.1 Primary Tank Bottom Weld Rejection Rates ........................................................ A-3
A2.2 Primary Tank Bottom Bulging .............................................................................. A-4
A2.3 Secondary Liner Bottom Budging ......................................................................... A-4
A2.4 Refractory and Foam ............................................................................................. A-5
A2.5 Post Weld Heat Treatment .................................................................................... A-5
A2.6 Raw Water Idle Time ............................................................................................ A-6
A3.0 PLATE MATERIAL AND THICKNESS ....................................................................... A-7
A3.1 Plate Material ........................................................................................................ A-8
A3.2 Primary Tank Bottom Thickness ........................................................................... A-8
A3.3 Secondary Liner Bottom Thickness ...................................................................... A-8
A3.4 Ultrasonic Testing on Primary Tank Wall ............................................................ A-8
A4.0 WATER INTRUSION ................................................................................................... A-10
A4.1 Annulus Water Intrusion ..................................................................................... A-11
A4.2 Leak Detection Pit Intrusion ............................................................................... A-11
A5.0 TEMPERATURE HISTORY AND EXCURSIONS .................................................... A-12
A5.1 Tank Temperatures .............................................................................................. A-12
A5.2 Heat Load ............................................................................................................ A-13
A5.3 Fill Cycles ........................................................................................................... A-13
RPP-PLAN-57352 7/20/2015 - 12:51 PM 67 of 92
RPP-PLAN-57352 Rev. 1
A-iii
A6.0 CONTINUITY OF ANNULUS VENTILATION OPERATION ................................. A-14
A6.1 Annulus Ventilation Outage ................................................................................ A-15
A7.0 CORROSION CHEMISTRY HISTORY ...................................................................... A-16
A7.1 Age of Tanks ....................................................................................................... A-16
A7.2 Year Out-of-Specification ................................................................................... A-17
A7.3 Predictive Corrosion History ............................................................................... A-17
A8.0 HOMOGENEITY OF WASTE ..................................................................................... A-18
A8.1 ASolids Volume .................................................................................................. A-19
A9.0 COMPLEXITY OF CONTENTS .................................................................................. A-20
A9.1 Interstitial Liquid Nitrite/Nitrate Ratio ............................................................... A-21
A9.2 Hydroxide Ion Concentration .............................................................................. A-21
A9.3 Total Organic Carbon .......................................................................................... A-21
A10.0 REFERENCES ............................................................................................................... A-22
TABLES
Table A-1. Qualitative Risk Ranking of Double-Shell Tank Weighting System ................. A-1
Table A-2. Risk Ranking Data for Construction Quality ...................................................... A-3
Table A-3. Risk Ranking Data for Plate Material and Thickness ......................................... A-7
Table A-4. Risk Ranking Data for Water Intrusion ............................................................ A-10
Table A-5. Risk Ranking Data for Temperature History and Excursions .......................... A-12
Table A-6. Risk Ranking Data for Continuity of Annulus Ventilation Operation ............. A-14
Table A-7. Risk Ranking Data for Corrosion Chemistry History ....................................... A-16
Table A-8. Risk Ranking Data for Homogeneity of Waste ................................................ A-18
Table A-9. Risk Ranking Data for Complexity of Contents ............................................... A-20
FIGURES
Figure A-1. Risk Ranking Comparison Graph ....................................................................... A-2
RPP-PLAN-57352 7/20/2015 - 12:51 PM 68 of 92
RPP-PLAN-57352 Rev. 1
A-iv
TERMS
Acronyms
BBI Best Basis Inventory
CFC chloroflouocarbon
DMCS Document Management and Control System
DST double-shell tank
ISL interstitial liquid
NCR nonconformance report
NO2- nitrite ion
NO3- nitrate ion
OH- hydroxide ion
PCSACS Personal Computer Surveillance Analysis Computer System
POC point of contact
QA quality assurance
SDDS Surveillance Data Display System
TOC total organic carbon
UT ultrasonic testing
HIAP High-Level Waste Integrity Assessment Panel
WRPS Washington River Protection Solutions, LLC
HTWOS Hanford Tank Waste Operations Simulator
SST single-shell tank
WTP Waste Treatment and Immobilization Plant
DF LAW direct feed low-activity waste
Units
°C Celcius
°F Fahrenheit
BTU British thermal unit
hr hour
in. inch
M molar
mil one thousandth of an inch
% percent
ft foot
Kgal thousand gallons
RPP-PLAN-57352 7/20/2015 - 12:51 PM 69 of 92
RPP-PLAN-57352 Rev. 1
A-1
A1.0 QUALITATIVE RISK RANKING OF DOUBLE-SHELL TANK FAILURE
The High-Level Waste Integrity Assessment Panel (HIAP) recommended a qualitative risk-
ranking of the double-shell tanks (DSTs) as a basis to prioritize more rigorous inspection
activities. The risk ranking cannot be used to “predict” failures. It is merely a ranking based on
potential factors that may influence operating life. This ranking will be updated when the
forensic activities for Tank 241-AY-102 (AY-102) yield information on the cause of the bottom
plate failure. The weights have been provided by Washington River Protection Solutions, LLC
(WRPS) personal in Tank and Pipeline Integrity (Table A-1).
Table A-1. Qualitative Risk Ranking of Double-Shell Tank Weighting System
Criteria Measures Weights
A1.0 Construction Quality 25
A1.1 Primary Tank Bottom Weld Rejection Rates 3
A1.2 Primary Tank Bottom Bulging 6
A1.3 Secondary Liner Bottom Budging 3
A1.4 Refractory and Foam 3
A1.5 Post Weld Heat Treatment 7
A1.6 Raw Water Idle Time 3
A2.0 Plate Material and Thickness 15
A2.1 Plate Material 6
A2.2 Primary Tank Bottom Thickness 3
A2.3 Secondary Liner Bottom Thickness 1
A2.4 Ultrasonic Testing on Primary Tank Wall 5
A3.0 Water Intrusion 5
A3.1 Annulus Water Intrusion 3
A3.2 Leak Detection Pit Intrusion 2
A4.0 Temperature History and Excursions 5
A4.1 Tank Temperatures 2
A4.2 Heat Load 2
A4.3 Fill Cycles 1
A5.0 Continuity of Annulus Ventilation Operation 10
A5.1 Annulus Ventilation Outage 10
A6.0 Corrosion Chemistry History 20
A6.1 Age of Tanks 10
A6.2 Year Out-of-Specification 6
A6.3 Predictive Corrosion History 4
A7.0 Homogeneity 10
A7.1 Solids Volume 10
A8.0 Complexity of Contents 10
A8.1 Interstitial Liquid Nitrite/Nitrate Ratio 5
A8.2 Hydroxide Ion Concentration 3
A8.3 Total Organic Carbon 2
Total 100 100
Risk ranking criteria are the logical categories of influence provided by the HIAP. The measures
were developed from available data on the 28 DSTs. These data points were quantified and
referenced back to source documents to the extent possible.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 70 of 92
RPP-PLAN-57352 Rev. 1
A-2
A1.1 PERFORMANCE MEASURES
For each of the evaluation criteria, multiple measures have been developed to help evaluate their
respective criterion and to act as discriminators for making comparisons between alternatives.
Data for each tank is provided and referenced in the following sections. The scoring is
structured so that the tanks can be discriminated according to performance differences in risk;
higher scores represent higher risk.
A1.2 RISK RANKING RESULTS
As shown in Figure A-1, the AY, AZ and SY Farm tanks score highest in the risk ranking. The
individaul contributions of the criteria categories show that the construction quality issues and
corrosion history are primary drivers.
Figure A-1. Risk Ranking Comparison Graph
A1.3 CONSEQUENCES
The future loss of additional DSTs is being evaluated with system planning to document findings
from Hanford Tank Waste Operations Simulator (HTWOS) model runs which assume a tank
failure every four years (RPP-56408, Selected Scenarios for the River Protection Project System
Plan, Revision 7). Losing one or more DSTs due to leaks has significant consequences, which
must be managed. If the leaking DST is immediately retrieved the general impacts which must
be managed are delays in single-shell tank (SST) retrieval and potential delays in in processing
[e.g. feed delivery to the Waste Treatment and Immobilization Plan (WTP) or waste returns from
direct feed low-activity waste (DF LAW)]. There are planning cases to provide varying numbers
of new DSTs to mitigate these impacts.
0
10
20
30
40
50
60
70
80
90
AY-
10
2
AY-
10
1
AZ-
10
2
AZ-
10
1
SY-1
01
SY-1
02
SY-1
03
AN
-10
7
AN
-10
6
AN
-10
2
AW
-10
6
AW
-10
4
AN
-10
1
AW
-10
1
AN
-10
5
AW
-10
5
AN
-10
4
AN
-10
3
AW
-10
3
AW
-10
2
AP
-10
8
AP
-10
3
AP
-10
4
AP
-10
5
AP
-10
2
AP
-10
7
AP
-10
1
AP
-10
6
Risk Ranking SummaryComplexity ofContentsHomogeneity of Waste
Corrosion ChemistryHistoryContinuity of AnnulusVentilation OperationTemperature Historyand ExcursionsWater Intrusion
Plate Material andThicknessConstruction Quality
RPP-PLAN-57352 7/20/2015 - 12:51 PM 71 of 92
RPP-PLAN-57352 Rev. 1
A-3
A2.0 CONSTRUCTION QUALITY
Table A-2 contains values for weld rejection rate, primary tank bottom bulging, secondary liner
bottom bulging, refractory and foam, post weld heat treatment, and raw water idle time.
Table A-2. Risk Ranking Data for Construction Quality
Tank Weld Rejection
Rate
Primary Tank Bottom Bulging
Secondary Liner Bottom
Bulging
Refractory and Foam
Post Weld Heat
Treatment
Raw Water Idle Time
AY-101 10.2% None Identified Bulging Sig. Damage 1000°F for 3 h > 10 months
AY-102 33.8% None Identified Bulging Sig. Damage 915°F for 3 h > 10 months
AZ-101 14.5% None Identified Few Issues No Damage 1000°F for 3 h > 10 months
AZ-102 6.3% None Identified Few Issues No Damage 1000°F for 3 h > 10 months
SY-101 30.1% Bulging Bulging No Damage 1000°F for 3 h —
SY-102 21.9% None Identified Bulging Minor Damage 1100°F for 1 h —
SY-103 25.7% Bulging Bulging No Damage 1100°F for 1 h —
AW-101 30% None Identified None Identified Minor Damage 1100°F for 1 h 9 months
AW-102 31% None Identified Bulging No Damage 1000°F for 3 h 8 months
AW-103 27% None Identified None Identified No Damage 1000°F for 3 h 7 months
AW-104 34% None Identified None Identified No Damage 1000°F for 3 h 8 months
AW-105 31% None Identified None Identified No Damage 1000°F for 3 h 6 months
AW-106 24% None Identified Bulging No Damage 1000°F for 3 h 7 months
AN-101 13% None Identified None Identified No Damage 1000°F for 3 h 8 months
AN-102 13% None Identified None Identified No Damage 1000°F for 3 h 7 months
AN-103 9% None Identified None Identified No Damage 1000°F for 3 h 7 months
AN-104 9% None Identified None Identified Minor Damage 1000°F for 3 h 10 months
AN-105 15% None Identified None Identified No Damage 1000°F for 3 h 6 months
AN-106 10% None Identified None Identified No Damage 1000°F for 3 h 5 months
AN-107 20% None Identified None Identified No Damage 1000°F for 3 h 5 months
AP-101 6% None Identified None Identified No Damage 1000°F for 3 h —
AP-102 9% None Identified None Identified No Damage 1000°F for 3 h —
AP-103 10% None Identified None Identified No Damage 1000°F for 3 h —
AP-104 9% None Identified None Identified No Damage 1000°F for 3 h —
AP-105 12% None Identified None Identified No Damage 1000°F for 3 h —
AP-106 6% None Identified None Identified No Damage 1000°F for 3 h —
AP-107 7% None Identified None Identified No Damage 1000°F for 3 h —
AP-108 5% None Identified None Identified Minor Damage 950°F for 5 h —
A2.1 PRIMARY TANK BOTTOM WELD REJECTION RATES
Primary tank bottom weld rejection rates are documented in RPP-ASMT-53793, Tank
241-AY-102 Leak Assessment Report; RPP-RPT-54817, 241-AY-101 Tank Construction Extent of
Condition Review for Tank Integrity; RPP-RPT-54818, 241-AZ Tank Farm Construction Extent
RPP-PLAN-57352 7/20/2015 - 12:51 PM 72 of 92
RPP-PLAN-57352 Rev. 1
A-4
of Condition Review for Tank Integrity; RPP-RPT-54819, 241-SY Tank Farm Construction
Extent of Condition Review for Tank Integrity; RPP-RPT-55981, 241-AW Tank Farm
Construction Extent of Condition Review for Tank Integrity; RPP-RPT-55982, 241-AN Tank
Farm Construction Extent of Condition Review for Tank Integrity; RPP-RPT-55983, 241-AP
Tank Farm Construction Extent of Condition Review for Tank Integrity; TOC-PRES-14-1370,
Double-Shell Tank Construction: Extent of Condition. These weld rejection values were
calculated based on radiographic film which evaluated 1 ft sections of weld. The radiographic
reports were used to determine the weld rejection percentage (Table A-2).
(1) Less than 10% weld rejection
(3) 10 to 20% weld rejection
(5) More than 20% weld rejection
A2.2 PRIMARY TANK BOTTOM BULGING
Primary tank bottom bulging refers to the 3/8 in./ft or a peak-to-valley difference greater than the
2 in. specifications for the primary tank bottom. The primary tanks were stress relieved to
reduce stresses in the metal and reduce the possibility of stress corrosion cracking. However,
many of the primary tank bottoms were found to be out specification concerning flatness. Some
repairs were attempted but generally failed. The bulges were then accepted as is and left in
place. The bulges create extra stress in the steel when loads are applied (Table A-2).
This information is documented in the following reports: RPP-ASMT-53793, RPP-RPT-54817,
RPP-RPT-54818, RPP-RPT-54819, RPP-RPT-55981, RPP-RPT-55982, RPP-RPT-55983, and
TOC-PRES-14-1370.
(1) No flatness issues. No questionable repairs and/or acceptance. – There were no
bulges specifically identified or the flatness was described as “generally good” in the
Quality Assurance (QA) Log Books. Out-of-tolerance locations were identified.
However, they were found to be within tolerance after lowering the tank bottom.
(5) Many flatness issues. Questionable repairs and/or acceptance. – Several
out-of-tolerance areas existed after the bottom was lowered and nonconformance
reports (NCR) were generated (typically six or more out-of-tolerance locations or
severe bulging near the knuckle region).
A2.3 SECONDARY LINER BOTTOM BUDGING
Secondary liner bottom budging refers to the 3/8 in./ft and/or a peak-to-valley difference greater
than 2 in. specifications for the secondary liner bottom. The secondary liner was not stress
relieved and residual stresses exist near the welds. Bulging in the secondary liner can add
significant stresses to the steel when loads are applied. These bulges can also lead to the
cracking and breaking of the refractory (Table A-2).
(1) No flatness issues. No questionable repairs and/or acceptance. – There were no
bulges specifically identified or the flatness was described as “generally good” in the
QA Log Books.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 73 of 92
RPP-PLAN-57352 Rev. 1
A-5
(3) Few flatness issues. Questionable repairs and/or acceptance. – Out-of-tolerance
locations were identified. However, they were found to be within tolerance after
lowering the tank bottom.
(5) Many flatness issues. Questionable repairs and/or acceptance. – Several out-of-
tolerance areas existed after the bottom was lowered and nonconformance reports
were generated (typically six or more out-of-tolerance locations or severe bulging
near the knuckle region).
A2.4 REFRACTORY AND FOAM
The primary purpose of the refractory was to keep the concrete foundation temperature below
500°F during stress relieving of the primary tank. However, the refractory supports the primary
tank. If the compressive strength of the refractory is not such that it can withstand the loads
applied to the tank, the refractory will be crushed, and the primary tank bottom can settle. This
condition would create an uneven surface along the tank bottom and introduce stresses to the
steel (Table A-2).
Tanks AY-101 and AY-102 had bulging issues which resulted in replacing the outer few feet of
the Kaolite refractory material and replacing it with concrete. This action could have resulted in
different compression properties resulting in unexpected stresses on the bottom plate at the
interface between the concrete and Kaolite. Additionally, insulating foam (styrene foam) was
used to fill voids between the bottom plate and the refractory. It is likely that
chlorofluorocarbons (CFC) were in the styrene foam used at the time of AY Farm construction.
The CFCs were blowing agents and would be trapped in the expanded foam. Decomposition
products of the CFC could be corrosive to the tank steels. These include chlorine free radicals
and chlorodifluoracetic acid. For a full discussion of the use of foam, refer to Section 3.2.5 in
RPP-ASMT-53793.
(1) No damage/Minor damage – No damage to the refractory were noted in any of the
reviewed documentation. This includes simple repairs to minor cracking that was
usually the result of shrinkage cracking which occurred because of high temperatures
and curing too fast. Also, possible cracking caused from cribbing. Minor damage
consists of small areas of refractory damaged by cribbing which required chipping
removing material prior to placing new material.
(5) Significant damage – Damage which required large areas of refractory to be removed
due to post weld heat treatment; repairs including the use of structural concrete to
support the tank bottom.
A2.5 POST WELD HEAT TREATMENT
Post weld heat treatment information is documented in TOC-PRES-14-1370. These values are
obtained from Stress Relief and QA Log Books (Table A-2).
Tanks AY-101 and AY-102 are scored differently due to differing PWHT conditions. Tank
AY-102 temperature could not surpass 200°F for several days due to escaping steam on account
of free water boiling off the insulating concrete. Four days after stress relieving began; Tank
RPP-PLAN-57352 7/20/2015 - 12:51 PM 74 of 92
RPP-PLAN-57352 Rev. 1
A-6
AY-102 reached 915°F and was accepted as meeting the 1,000°F criteria according to
RPP-ASMT-53793.
(1) Reached 1100°F for one hour
(3) Reached 1000°F for three hours
(5) Did not reach 1000°F for three hours (or other issues)
A2.6 RAW WATER IDLE TIME
The primary tank was exposed to raw water which caused some pitting for hydrostatic testing,
dome construction, and preparation for hot feed receipt. Tank AN-107 and AW-104 were
checked for corrosion prior to radioactive service. Corrosion 20-30 mils deep was observed and
it was assumed the rest of the AN Farm tanks had similar amounts of corrosion. Water used in
AP Farm construction was inhibited and cathodic protection was used to protect the tanks (Table
A-2).
(1) Treated water and cathodic protection
(3) Less than ten months with raw water
(5) Greater than ten months with heated raw water
RPP-PLAN-57352 7/20/2015 - 12:51 PM 75 of 92
RPP-PLAN-57352 Rev. 1
A-7
A3.0 PLATE MATERIAL AND THICKNESS
Table A-3 contains values for plate material, primary tank bottom thickness, secondary liner
bottom thickness, and ultrasonic testing on primary tank walls.
Table A-3. Risk Ranking Data for Plate Material and Thickness
Tank Plate Material Primary Tank Bottom Thickness
Secondary Liner Bottom Thickness
Ultrasonic Testing on Primary Tank
Walls
AY-101 A515 3/8 in. 1/4 in. Reportable
AY-102 A515 3/8 in. 1/4 in. Reportable
AZ-101 A515 1/2 in. 3/8 in. Not Reportable
AZ-102 A515 1/2 in. 3/8 in. Reportable
SY-101 A516 1/2 in. 3/8 in. Reportable
SY-102 A516 1/2 in. 3/8 in. Reportable
SY-103 A516 1/2 in. 3/8 in. Reportable
AW-101 A537 1/2 in. 3/8 in. Reportable
AW-102 A537 1/2 in. 3/8 in. Not Reportable
AW-103 A537 1/2 in. 3/8 in. Not Reportable
AW-104 A537 1/2 in. 3/8 in. Not Reportable
AW-105 A537 1/2 in. 3/8 in. Not Reportable
AW-106 A537 1/2 in. 3/8 in. Not Reportable
AN-101 A537 1/2 in. 3/8 in. Reportable
AN-102 A537 1/2 in. 3/8 in. Reportable
AN-103 A537 1/2 in. 3/8 in. Not Reportable
AN-104 A537 1/2 in. 3/8 in. Not Reportable
AN-105 A537 1/2 in. 3/8 in. Not Reportable
AN-106 A537 1/2 in. 3/8 in. Not Reportable
AN-107 A537 1/2 in. 3/8 in. Not Reportable
AP-101 A537 1/2 in. 3/8 in. Not Reportable
AP-102 A537 1/2 in. 3/8 in. Reportable
AP-103 A537 1/2 in. 3/8 in. Not Reportable
AP-104 A537 1/2 in. 3/8 in. Not Reportable
AP-105 A537 1/2 in. 3/8 in. Not Reportable
AP-106 A537 1/2 in. 3/8 in. Not Reportable
AP-107 A537 1/2 in. 3/8 in. Not Reportable
AP-108 A537 1/2 in. 3/8 in. Reportable
RPP-PLAN-57352 7/20/2015 - 12:51 PM 76 of 92
RPP-PLAN-57352 Rev. 1
A-8
A3.1 PLATE MATERIAL
Plate material is documented in TOC-PRES-14-1370. This information was gathered from Mill
Test Reports (Table A-3).
(1) ASTM A537
(3) ASTM A516
(5) ASTM A515
A3.2 PRIMARY TANK BOTTOM THICKNESS
Primary tank bottom thickness is documented in TOC-PRES-14-1370. Following the AY Farm
construction, primary tank bottom plate thickness was increased in an attempt to reduce the
bottom bulging (Table A-3).
(1) 1/2 in.
(5) 3/8 in.
A3.3 SECONDARY LINER BOTTOM THICKNESS
Secondary liner bottom thickness is documented in TOC-PRES-14-1370. Following the AY
Tank Farm construction, secondary liner plate thickness was increased in an attempt to reduce
the bottom bulging (Table A-3).
(1) 3/8 in.
(5) 1/4 in.
A3.4 ULTRASONIC TESTING ON PRIMARY TANK WALL
Ultrasonic testing (UT) on the primary tank wall is to inspect for general wall thinning, pitting
and linear indications (cracking) of the tank wall per RPP-7574, Double-Shell Tank Integrity
Program Plan. WRPS has generated numerous UT Inspection Results documents. At 100%
completion, all 28 DSTs have at least one UT Inspection Report and each report is in Document
Management and Control System (DMCS). Presently, 23 of 28 DSTs have two or more
completed UT Reports. Three DSTs (AP-102, AP-104 and AP-106) are slated to have the
second UT inspections completed in 2014 with the final two DSTs (AN-103 and AN-104) UT
inspections planned in 2015.
To determine general wall thinning, pitting, and/or linear indications (cracking) for all 28 DSTs;
the UT data results from each tank (including the bottom knuckle and Course one, two, three,
and four) were compared to the minimum UT measured data point minus the nominal wall
RPP-PLAN-57352 7/20/2015 - 12:51 PM 77 of 92
RPP-PLAN-57352 Rev. 1
A-9
thickness (Table A-3). After comparing the minimum wall thickness results from each section of
the 28 tanks, the overall rating of each tank is delineated as follow:
(1) Not Reportable
(3) Reportable Level (10% plate wall thickness; pitting 25% of plate thickness and
cracking <6 in. of 10% plate thickness)
(5) Action Level (20% plate wall thickness; pitting 50% plate thickness and cracking
>12 in. of 20% plate thickness or <12 in. of 50% plate thickness)
RPP-PLAN-57352 7/20/2015 - 12:51 PM 78 of 92
RPP-PLAN-57352 Rev. 1
A-10
A4.0 WATER INTRUSION
Table A-4 shows whether there is annulus water intrusion and leak detection pit intrusion.
Table A-4. Risk Ranking Data for Water Intrusion
Tank Annulus Water Intrusion Leak Detection Pit Intrusion
AY-101 Yes Exceeds maximum authorized limit
AY-102 Yes Exceeds maximum authorized limit
AZ-101 No Exceeds maximum authorized limit
AZ-102 No Exceeds maximum authorized limit
SY-101 No Exceeds maximum authorized limit
SY-102 No Exceeds maximum authorized limit
SY-103 No Exceeds structural limit
AW-101 No No
AW-102 No No
AW-103 No Exceeds maximum authorized limit
AW-104 No No
AW-105 No Exceeds structural limit
AW-106 No No
AN-101 No No
AN-102 No No
AN-103 No No
AN-104 No No
AN-105 No No
AN-106 No No
AN-107 No Exceeds structural limit
AP-101 No No
AP-102 No No
AP-103 No No
AP-104 No No
AP-105 No Exceeds maximum authorized limit
AP-106 Yes Exceeds maximum authorized limit
AP-107 No Exceeds maximum authorized limit
AP-108 No Exceeds maximum authorized limit
RPP-PLAN-57352 7/20/2015 - 12:51 PM 79 of 92
RPP-PLAN-57352 Rev. 1
A-11
A4.1 ANNULUS WATER INTRUSION
Annulus water intrusion is documented in RPP-7695, Double-Shell Tank Annulus Ventilation
Engineering Study, for AY and AZ Farms (Table A-4). Tank AP-106 has an annulus water
intrusion documented in RPP-RPT-38738, Double-Shell Tank Integrity Inspection Report for
241-AP Tank Farm. Moisture in the annulus may lead to corrosion of the primary tank. Active
intrusion of water to the annulus via cracks in the concrete dome is a corrosion issue for the
primary tank. Only the AY Tanks have had significant water intrusion (RPP-RPT-33273, 241-
AY-101/102 Annulus Moisture Intrusion Analysis).
(1) None or very minor
(5) Yes
A4.2 LEAK DETECTION PIT INTRUSION
Leak detection pit intrusion is documented in RPP-RPT-55666, Double-Shell Tank Tertiary Leak
Detection System Evaluation. Moisture in the soil around the tank and in the air used for annulus
ventilation may create corrosion conditions beneath the secondary liner (Table A-4).
(1) No
(3) Exceeds maximum authorized limit
(5) Exceeds structural limit
RPP-PLAN-57352 7/20/2015 - 12:51 PM 80 of 92
RPP-PLAN-57352 Rev. 1
A-12
A5.0 TEMPERATURE HISTORY AND EXCURSIONS
Table A-5 contains values for tank temperature, heat loads, and fill cycles.
Table A-5. Risk Ranking Data for Temperature History and Excursions
Tank Tank Temperature Heat Load Fill Cycles
AY-101 108°F 52,392 BTU/hr Normal Use
AY-102 156°F 106,989 BTU/hr Normal Use
AZ-101 163°F 193,568 BTU/hr Normal Use
AZ-102 148°F 107,796 BTU/hr Normal Use
SY-101 86°F 6,224 BTU/hr Normal Use
SY-102 72°F 9,702 BTU/hr Evaporator 242-S Feed
SY-103 90°F 17,596 BTU/hr Normal Use
AW-101 109°F 24,520 BTU/hr Normal Use
AW-102 86°F 19,537 BTU/hr Evaporator 242-A feed
AW-103 77°F 6,070 BTU/hr Normal Use
AW-104 80°F 14,699 BTU/hr Normal Use
AW-105 70°F 2,082 BTU/hr Normal Use
AW-106 93°F 14,455 BTU/hr Normal Use
AN-101 99°F 26,505 BTU/hr Normal Use
AN-102 94°F 28,052 BTU/hr Normal Use
AN-103 102°F 25,535 BTU/hr Normal Use
AN-104 105°F 29,624 BTU/hr Normal Use
AN-105 101°F 21,700 BTU/hr Normal Use
AN-106 141°F 95,470 BTU/hr Normal Use
AN-107 93°F 30,696 BTU/hr Normal Use
AP-101 117°F 18,470 BTU/hr Normal Use
AP-102 78°F 15,358 BTU/hr Normal Use
AP-103 92°F 16,607 BTU/hr Normal Use
AP-104 80°F 3,021 BTU/hr Normal Use
AP-105 83°F 23,128 BTU/hr Normal Use
AP-106 79°F 11,388 BTU/hr Normal Use
AP-107 81°F 8,981 BTU/hr Normal Use
AP-108 88°F 14,705 BTU/hr Normal Use
A5.1 TANK TEMPERATURES
Tank temperatures are documented in RPP-5926, Steady-State Flammable Gas Release Rate
Calculation and Lower Flammability Level Evaluation for Hanford Tank Waste. These values
are obtained from actual values currently in the tank waste (Table A-5). The highest tank
temperatures in Personal Computer Surveillance Analysis Computer System (PCSACS) are
RPP-PLAN-57352 7/20/2015 - 12:51 PM 81 of 92
RPP-PLAN-57352 Rev. 1
A-13
documented for a four month period ending in 2014 in RPP-13639, Caustic Limits Report – For
Period Ending January 1, 2014.
(1) Less than 30°C
(3) 30 to 50°C
(5) Above 50°C
A5.2 HEAT LOAD
Heat load is derived from the radionuclide content documented in the Best Basis Inventory
(BBI). Total heat in both the sludge and supernatant is provided (Table A-5).
(1) Under 50,000 BTU/hr
(3) 50,000 to 100,000 BTU/hr
(5) Over 100,000 BTU/hr
A5.3 FILL CYCLES
The evaporator feed tanks were saw repeated transfers associated with feeding the
242-S Evaporator (SY-102) and the 242-A Evaporator (AW-102). The additional fatigue related
stress on these two tanks is reflected by the number of fill cycles (Table A-5).
(1) Normal use
(5) Evaporator feed tank
RPP-PLAN-57352 7/20/2015 - 12:51 PM 82 of 92
RPP-PLAN-57352 Rev. 1
A-14
A6.0 CONTINUITY OF ANNULUS VENTILATION OPERATION
Table A-6 contains how long an annulus ventilation outage occurred.
Table A-6. Risk Ranking Data for Continuity of Annulus Ventilation Operation
Tank Annulus Ventilation Outage
AY-101 10 years
AY-102 10 years
AZ-101 5 years
AZ-102 5 years
SY-101 1 month
SY-102 1 month
SY-103 1 month
AW-101 1 month
AW-102 1 month
AW-103 1 month
AW-104 1 month
AW-105 1 month
AW-106 1 month
AN-101 3 months
AN-102 3 months
AN-103 3 months
AN-104 3 months
AN-105 3 months
AN-106 3 months
AN-107 3 months
AP-101 1 month
AP-102 1 month
AP-103 1 month
AP-104 1 month
AP-105 1 month
AP-106 1 month
AP-107 1 month
AP-108 1 month
RPP-PLAN-57352 7/20/2015 - 12:51 PM 83 of 92
RPP-PLAN-57352 Rev. 1
A-15
A6.1 ANNULUS VENTILATION OUTAGE
Annulus ventilation outage timing is derived from temperature rise similar to RPP-56864,
Tank 241-AY-102 Thermal Evaluation of Supernatant Reduction, or exhauster status log sheets
found in IDMS under document number TO-040-035. For AY and AZ Farms, RPP-7695 was
used (the worst annulus outage is believed to be Tank AY-101 which, except for a brief period in
1997, was off from January 1992 to January 2001. This time period was about nine years).
Metrics are for the longest annulus downtime at one time (Table A-6).
(1) Less than two months
(3) Two months to two years
(5) Greater than two years
RPP-PLAN-57352 7/20/2015 - 12:51 PM 84 of 92
RPP-PLAN-57352 Rev. 1
A-16
A7.0 CORROSION CHEMISTRY HISTORY
Table A-7 contains values for the age of tanks, the years out-of-specification, and predictive
corrosion history.
Table A-7. Risk Ranking Data for Corrosion Chemistry History
Tank Age of Tanks Years Out-of-Specification Predictive Corrosion History
AY-101 44 years 6.83 years > 3 years
AY-102 44 years 6.58 years 0 years (est.)
AZ-101 40 years 1.67 years 0 years (est.)
AZ-102 40 years 0.42 years > 3 years
SY-101 38 years 0 years ~2 years
SY-102 38 years 0.5 years > 3 years
SY-103 38 years 0 years 0 years (est.)
AW-101 35 years 0 years 0 years (est.)
AW-102 35 years 0 years > 3 years
AW-103 35 years 0 years 0 years (est.)
AW-104 35 years 0 years 0 years (est.)
AW-105 35 years 0 years 0 years (est.)
AW-106 35 years 0 years 0 years (est.)
AN-101 34 years 0 years > 3 years
AN-102 34 years 12.83 years 0 years (est.)
AN-103 34 years 0 years 0 years (est.)
AN-104 34 years 0 years 0 years (est.)
AN-105 34 years 0 years 0 years (est.)
AN-106 34 years 0.25 years > 3 years
AN-107 34 years 18.42 years 0 years (est.)
AP-101 28 years 0 years 0 years (est.)
AP-102 28 years 0 years 0 years (est.)
AP-103 28 years 1.5 years 0 years (est.)
AP-104 28 years 3.33 years 0 years (est.)
AP-105 28 years 0 years 0 years (est.)
AP-106 28 years 0 years 0 years (est.)
AP-107 28 years 2.67 years 0 years (est.)
AP-108 28 years 0.5 years 0 years (est.)
A7.1 AGE OF TANKS
The DSTs range in age from 28 to 44 years old. The age of the tanks is a risk factor in
determining soundness (Table A-7).
(1) Less than 30 years old
RPP-PLAN-57352 7/20/2015 - 12:51 PM 85 of 92
RPP-PLAN-57352 Rev. 1
A-17
(3) 30 to 35 years old
(5) Greater than 35 years old
A7.2 YEAR OUT-OF-SPECIFICATION
Years out-of-specification sampling is documented in Tables B-1 and B-3 of RPP-7795,
Technical Basis for the Chemistry Control Program (Table A-7).
(1) Less than one year
(3) one year to ten years
(5) More than ten years
A7.3 PREDICTIVE CORROSION HISTORY
Predictive corrosion history is partly documented in RPP-7795 and RPP-13639 (Table A-7).
And best estimate from corrosion mitigation point of contact (POC) (Currently, [May 2014] it is
predicted that Tank AZ-102 has been out-of-specification since April 2013).
(1) Less than 0.5 years
(3) 0.5 years to three years
(5) Greater than three years
RPP-PLAN-57352 7/20/2015 - 12:51 PM 86 of 92
RPP-PLAN-57352 Rev. 1
A-18
A8.0 HOMOGENEITY OF WASTE
Table A-8 contains values for the amount of sludge, saltcake, and supernatant in each DST.
Table A-8. Risk Ranking Data for Homogeneity of Waste
Tank Sludge Saltcake Supernatant
AY-101 105 Kgal 0 Kgal 893 Kgal
AY-102 151 Kgal 0 Kgal 643 Kgal
AZ-101 52 Kgal 0 Kgal 773 Kgal
AZ-102 105 Kgal 0 Kgal 886 Kgal
SY-101 0 Kgal 255 Kgal 864 Kgal
SY-102 199 Kgal 11 Kgal 360 Kgal
SY-103 0 Kgal 356 Kgal 377 Kgal
AW-101 0 Kgal 396 Kgal 736 Kgal
AW-102 52 Kgal 0 Kgal 912 Kgal
AW-103 280 Kgal 40 Kgal 760 Kgal
AW-104 97 Kgal 157 Kgal 800 Kgal
AW-105 248 Kgal 0 Kgal 153 Kgal
AW-106 0 Kgal 264 Kgal 872 Kgal
AN-101 403 Kgal 31 Kgal 340 Kgal
AN-102 0 Kgal 154 Kgal 913 Kgal
AN-103 0 Kgal 486 Kgal 476 Kgal
AN-104 0 Kgal 443 Kgal 608 Kgal
AN-105 0 Kgal 536 Kgal 590 Kgal
AN-106 407 Kgal 25 Kgal 233 Kgal
AN-107 0 Kgal 241 Kgal 835 Kgal
AP-101 0 Kgal 33 Kgal 1200 Kgal
AP-102 28 Kgal 0 Kgal 1110 Kgal
AP-103 0 Kgal 52 Kgal 1182 Kgal
AP-104 0 Kgal 100 Kgal 647 Kgal
AP-105 0 Kgal 105 Kgal 1140 Kgal
AP-106 0 Kgal 0 Kgal 1129 Kgal
AP-107 0 Kgal 0 Kgal 439 Kgal
AP-108 0 Kgal 112 Kgal 1128 Kgal
RPP-PLAN-57352 7/20/2015 - 12:51 PM 87 of 92
RPP-PLAN-57352 Rev. 1
A-19
A8.1 SOLIDS VOLUME
The chemistry is controlled in the supernatant but there is no monitor of the chemistry at the
bottom plate surface. The level of solids represents a layer that solution concentrations must
penetrate from the supernatant layer to the surface of the plate. The total volume of solids is an
indirect reflection of the concentration gradient between the supernatant and the corrosion layer
next to the bottom plate. These sludge and salt cake volumes are taken from HNF-EP-0182,
Waste Tank Summary Report for Month Ending February 28, 2014, and is summarized in Table
A-8.
In addition to the solids level, certain tanks received solids through a layer of supernatant that
was outside the chemistry control limits. The result is that the interstitial liquid (ISL) in the
solids is more likely to have corrosive properties. These tanks are SY-102, AN-106, AW-101,
AW-104 and AY-102.
(1) No solids
(3) Sludge containing solids
(5) Solid receipt through off-spec supernatant
RPP-PLAN-57352 7/20/2015 - 12:51 PM 88 of 92
RPP-PLAN-57352 Rev. 1
A-20
A9.0 COMPLEXITY OF CONTENTS
Table A-9 contains values for nitrite (NO2-)/nitrate (NO3
-) ratio, hydroxide (OH-) concentration,
and total organic carbon (TOC) concentration.
Table A-9. Risk Ranking Data for Complexity of Contents
Tank NO2/NO3 Ratio OH- TOC
AY-101 13.44 0.0013 M 0.09 M
AY-102 0.52 0.002 M 0.15 M
AZ-101 1.57 0.67 M 0.13 M
AZ-102 8.43 0.012 M 0.08 M
SY-101 0.86 2.04 M 0.53 M
SY-102 0.74 1.26 M 0.38 M
SY-103 1.3 2.22 M 0.7 M
AW-101 0.79 5.21 M 0.21 M
AW-102 No Data No Data No Data
AW-103 0.5 1.11 M 0.47 M
AW-104 0.84 1.19 M 1.83 M
AW-105 0.27 0.42 M 0.79 M
AW-106 0.8 1.32 M 0.43 M
AN-101 0.65 0.45 M 0.29 M
AN-102 0.56 0.136 M 2.02 M
AN-103 1.37 4.81 M 0.4 M
AN-104 0.95 3.41 M 0.32 M
AN-105 0.88 2.7 M 0.308 M
AN-106 0.87 0.005 M 0.12 M
AN-107 0.43 0.001 M 3.66 M
AP-101 No Data No Data No Data
AP-102 No Data No Data No Data
AP-103 0.67 1.11 M 0.34 M
AP-104 No Data No Data No Data
AP-105 0.38 3.21 M 0.23 M
AP-106 No Data No Data No Data
AP-107 No Data No Data No Data
AP-108 0.61 2.55 M 0.32 M
RPP-PLAN-57352 7/20/2015 - 12:51 PM 89 of 92
RPP-PLAN-57352 Rev. 1
A-21
A9.1 INTERSTITIAL LIQUID NITRITE/NITRATE RATIO
NO2- is a corrosion inhibitor and NO3
- is a corrosion promoter. The ratio of the concentration of
NO2- divided by the concentration of NO3
- in the ISL of the solids appears to be significant in
estimating the amount of corrosion in the ISL and supernatant. The ISL limit in OSD-T-151-
00007, Operating Specifications for the Double-Shell Storage Tanks, Table 1.5.1-2, is [NO2-
]/[NO3-] >0.32 M. Studies indicate that a ratio of about 0.15 may also be significant. See RPP-
7795, for an estimate of the TOC in both supernatant and ISL (Table A-9).
(1) 0.32 < [NO2-]/[NO3
-]
(3) 0.15 < [NO2-]/[NO3
-] < 0.32
(5) [NO2-]/[NO3
-] < 0.15
A9.2 HYDROXIDE ION CONCENTRATION
OH- concentration is a corrosion inhibitor in certain concentrations. When OH- concentration
can be measured directly it is a good indication if corrosion will occur at significant levels. RPP-
7795 has estimates of OH- concentrations for DST in different layers in the tank. For a worst
case, data from the lowest concentration in supernatant layers and layers in the ISL were used.
OH- concentration changes with time and reactions in the tank waste. OSD-T-151-00007, Tables
1.5.1-1 and 1.5.1-2, have OH- limits depending on the concentration of NO3-. Metrics are greatly
simplified (Table A-9).
(1) [OH-] > 0.3 M
(3) 0.01 M < [OH-] < 0.3 M
(5) [OH-] < 0.01 M
A9.3 TOTAL ORGANIC CARBON
Organics participate in chemical reactions which remove OH- from the supernatant and probably
the ISL of the solids. RPP-7795 documented TOC reactions and correlations that can estimate
the rate of supernatant loss of OH-. The reactions and correlations in the ISL are probably the
same as the supernatant, although this has not been proven. RPP-7795 or RPP-13639 was used
to determine TOC in the layers of supernatant and in ISL (Table A-9). This is about the only
tool available to metric the OH- in the ISL because there have not been any core samples since
February 14, 2008.
(1) TOC < 0.2 M
(3) 0.2 M < TOC < 0.7 M
(5) TOC > 0.7 M
RPP-PLAN-57352 7/20/2015 - 12:51 PM 90 of 92
RPP-PLAN-57352 Rev. 1
A-22
A10.0 REFERENCES
HNF-EP-0182, 2014, Waste Tank Summary Report for Month Ending February 28, 2014,
Rev. 311, Washington River Protection Solutions, LLC, Richland, Washington.
OSD-T-151-00007, 2013, Operating Specifications for the Double-Shell Storage Tanks, Rev 12,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-13639, 2014, Caustic Limits Report – For Period Ending January 1, 2014, Rev. 10,
Washington River Solutions, LLC, Richland, Washington.
RPP-56408, 2013, Selected Scenarios for the River Protection Project System Plan, Revision 7,
Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-56864, 2014, Tank 241-AY-102 Thermal Evaluation of Supernatant Reduction, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-5926, 2014, Steady-State Flammable Gas Release Rate Calculation and Lower
Flammability Level Evaluation for Hanford Tank Waste, Rev. 14, Washington River
Protection Solutions, LLC, Richland, Washington.
RPP-7574, 2010, Double-Shell Tank Integrity Program Plan, Rev. 3, Washington River
Protection Solutions, LLC, Richland, Washington.
RPP-7695, 2001, Double-Shell Tank Annulus Ventilation Engineering Study, Rev. 0A, CH2M
HILL Hanford Group Inc., Richland, Washington.
RPP-7795, 2013, Technical Basis for the Chemistry Control Program, Rev. 11, Washington
River Protection Solutions, LLC, Richland, Washington.
RPP-ASMT-53793, 2012, Tank 241-AY-102 Leak Assessment Report, Rev. 0, Washington River
Protection Solutions, LLC, Richland, Washington.
RPP-RPT-33273, 2007, 241-AY-101/102 Moisture Intrusion Analysis, Rev. 0, CH2M HILL
Group Inc., Richland, Washington.
RPP-RPT-54817, 2013, 241-AY-101 Tank Construction Extent of Condition Review for Tank
Integrity, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-54818, 2013, 241-AZ Tank Farm Construction Extent of Condition Review for Tank
Integrity, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-54819, 2013, 241-SY Tank Farm Construction Extent of Condition Review for Tank
Integrity, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-55666, 2013, Double-Shell Tank Tertiary Leak Detection System Evaluation, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 91 of 92
RPP-PLAN-57352 Rev. 1
A-23
RPP-RPT-55981, 2013, 241-AW Tank Farm Construction Extent of Condition Review for Tank
Integrity, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-55982, 2014, 241-AN Tank Farm Construction Extent of Condition Review for Tank
Integrity, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-55983, 2014, 241-AP Tank Farm Construction Extent of Condition Review for Tank
Integrity, Rev. 0, Washington River Protection Solutions, LLC, Richland, Washington.
TOC-PRES-14-1370, 2014, Double-Shell Tank Construction: Extent of Condition, Rev. 0,
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-38738, [DRAFT], Double-Shell Tank Integrity Inspection Report for 241-AP Tank
Farm, Rev. 4, Washington River Protection Solutions, LLC, Richland, Washington.
RPP-PLAN-57352 7/20/2015 - 12:51 PM 92 of 92