DOCUMENT RELEASE AND CHANGE FORM Prepared For the U.S. Department of Energy, Assistant Secretary for Environmental Management By Washington River Protection Solutions, LLC., PO Box 850, Richland, WA 99352 Contractor For U.S. Department of Energy, Office of River Protection, under Contract DE-AC27-08RV14800
1a. Doc No: RPP-RPT-58298 Rev. 00
1b. Project Number: T2R02☐ N/A
1 SPF-001 (Rev.0)
TRADEMARK DISCLAIMER: Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof or its contractors or subcontractors. Printed in the United States of America.
Release Stamp
2. Document Title
LEAN Improvement Project Business Case to Benchmark Retrieval Technologies
3. Design Verification Required
☐ Yes ☐ No
4. USQ Number ☒ N/A 5. PrHA Number ☒ N/A
Rev.
6. USQ Screening:
a. Does the change introduce any new failure modes to the equipment? ☐ Yes ☒ No
Basis is required for Yes:
b. Does the change increase the probability of existing failure modes? ☐ Yes ☒ No
Basis is required for Yes:
c. For Safety Significant equipment, does the change require a modification to Chapter 4 of the DSA and/or FRED? ☐ Yes ☐ No ☒ N/A
Basis is required for Yes:
7. Description of Change and Justification (Use Continuation pages as needed)
Initial Release
8. Approvals
Title Name Signature Date
Checker WHITE, MICHAEL A WHITE, MICHAEL A 01/29/2015
Document Control Approval RAYMER, JULIA R RAYMER, JULIA R 03/09/2015
Originator WHITE, KATIE A WHITE, KATIE A 01/29/2015
Responsible Engineer BELLOMY, JIM BELLOMY, JIM 01/29/2015
Responsible Manager BAUER, ROGER E BAUER, ROGER E 01/29/2015
9. Clearance Review:
Restriction Type:
☒ Public
☐ Undefined
☐ Unclassified Controlled Nuclear Information (UCNI)
☐ Export Control Information (ECI)
☐ Official Use Only Exemption 2-Circumvention of Statute (OUO-2)
☐ Official Use Only Exemption 3-Statutory Exemption (OUO-3)
☐ Official Use Only Exemption 4-Commercial/Proprietary (OUO-4)
☐ Official Use Only Exemption 5-Privileged Information (OUO-5)
☐ Official Use Only Exemption 6-Personal Privacy (OUO-6)
☐ Official Use Only Exemption 7-Law Enforcement (OUO-7)
RPP-RPT-58298 3/9/2015 - 7:47 AM 1 of 106
DOCUMENT RELEASE AND CHANGE FORM Doc No: RPP-RPT-58298 Rev. 00
2 SPF-001 (Rev.0)
10. Distribution:
Name Organization
BAUER, ROGER E A/AX RETRIEVAL ENGRNG
BELLOMY, JIM A/AX RETRIEVAL ENGRNG
BROWN, NICOLE L BASE OPERATIONS PROCESS ENGRNG
CARPENTER, KEITH E SST R&C PROJECT ENGINEERING
WITHERSPOON, JP P A/AX RETRIEVAL ENGRNG
11. TBDs or Holds ☒ N/A
12. Impacted Documents – Engineering ☒ N/A
Document Number Rev. Title
13. Other Related Documents ☒ N/A
Document Number Rev. Title
14. Related Systems, Structures, and Components:
14a. Related Building/Facilities ☐ N/A
241-C
241-C-101
241-C-107
241-C-111
241-C-112
14b. Related Systems ☐ N/A
241-WT
14c. Related Equipment ID Nos. (EIN) ☒ N/A
RPP-RPT-58298 3/9/2015 - 7:47 AM 2 of 106
3 SPF-001 (Rev.0)
DOCUMENT RELEASE AND CHANGE FORM CONTINUATION SHEET
Document No: RPP-RPT-58298 Rev. 00
[Start Continuation Here]
RPP-RPT-58298 3/9/2015 - 7:47 AM 3 of 106
A-6002-767 (REV 3)
RPP-RPT-58298, Rev. 0
LEAN Improvement Project Business Case to Benchmark Retrieval Technologies
Author Name: KA White ARES Corporation for Washington River Protection Solutions, LLC Richland, WA 99352 U.S. Department of Energy Contract DE-AC27-08RV14800 EDT/ECN: EDT 825781 UC: N/A Cost Center: N/A Charge Code: N/A B&R Code: N/A Total Pages: 104
Key Words: WRS, MARS, HHR, ERSS, LEAN, benchmark, retrieval, 241-C, C Farm, 241-C-101, 241-C-107, 241-C-111, 241-C-112, pump, failure, hydraulic, leak, ventilation, camera, temperature, sluicer, sluicing, bulk retrieval, hard heel retrieval, arm, extended reach sluicing system
Abstract: This document reviews the information from the 241-C-101 bulk retrieval campaign using the Waste Retrieval System (WRS), the 241-C-107 retrieval campaign using the Mobile Arm Retrieval System (MARS), the 241-C-111 bulk retrieval campaign using WRS, the 241-C-112 bulk retrieval campaign using WRS, and 241-C-112 hard heel retrieval (HHR) campaign to identify areas for equipment and operation process improvement. The evaluation addresses both equipment reliability and availability.
TRADEMARK DISCLAIMER. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof or its contractors or subcontractors.
Release Approval Date Release Stamp
Approved For Public Release
RPP-RPT-58298 3/9/2015 - 7:47 AM 4 of 106
A-6002-767 (REV 3)
LEAN IMPROVEMENT PROJECT BUSINESS CASE TO BENCHMARK RETRIEVAL TECHNOLOGIES
November 2014
prepared by
ARES Corporation Energy Services Division 1100 Jadwin Avenue, Suite 400 Richland, Washington 99352
(509) 946-3300
prepared for
Washington River Protection Solutions, LLC
RPP-RPT-58298 3/9/2015 - 7:47 AM 5 of 106
RPP-RPT-58298, Rev. 0
i
EXECUTIVE SUMMARY
Information for five retrieval campaigns was reviewed and events which caused either retrieval
shut-down or delay were noted by equipment type. Once documented, the findings were
evaluated to identify areas with repeated events. The information was obtained from the
Retrieval and Closure Operational Engineer Log Books, the Base Operations Log Books, the
retrieval completion reports, and the notes recorded by the Process Engineers in the material
balance calculation spreadsheets. Several hundred Problem Evaluation Requests, also known as
PERS, were reviewed and determined to not provide new pertinent information. The Document
Management Control System database was searched for lessons learned reports. No lessons
learned reports were found for the campaigns being evaluated.
There have been three distinct types of retrieval systems used in 241-C Tank Farm retrieval
efforts: the Modified Sluicing Waste Retrieval System, the Mobile Arm Retrieval System –
Sluicing, and Mobile Arm Retrieval System – Vacuum. The campaigns evaluated in this report
used either the Waste Retrieval System or the Mobile Arm Retrieval System – Sluicing. The
five campaigns evaluated are the 241-C-101 bulk retrieval campaign the 241-C-107 retrieval
campaign, 241-C-111 bulk retrieval campaign, the 241-C-112 bulk retrieval campaign, and
241-C-112 hard heel retrieval campaign.
A total of 487 events occurring over 390 operating days were documented. These events were
sorted into a number of categories as detailed in Section 3.0, “Methodology.” Analysis of these
events resulted in nine specific recommendations for areas needing improvement or further
review, as detailed in Section 5.0, “Recommendations.”
RPP-RPT-58298 3/9/2015 - 7:47 AM 6 of 106
RPP-RPT-58298, Rev. 0
ii
TABLE OF CONTENTS
1.0 INTRODUCTION ..................................................................................................................1
2.0 SCOPE ....................................................................................................................................1
2.1 Evaluated Retrieval Systems ..........................................................................................1
2.1.1 Modified Sluicing Waste Retrieval System .......................................................1
2.1.2 Mobile Arm Retrieval System – Sluicing ..........................................................2
2.2 Evaluated Campaigns .....................................................................................................2
2.2.1 241-C-101 Bulk Retrieval ..................................................................................2
2.2.2 241-C-107 Retrieval...........................................................................................3
2.2.3 241-C-111 Bulk Retrieval ..................................................................................4
2.2.4 241-C-112 Bulk Retrieval ..................................................................................5
2.2.5 241-C-112 Hard Heel Retrieval .........................................................................5
2.3 Evaluated Equipment .....................................................................................................6
3.0 METHODOLOGY .................................................................................................................7
4.0 FINDINGS ..............................................................................................................................8
4.1 Significant Delay Equipment Failures ...........................................................................8
4.2 Minor Delay Equipment Failures...................................................................................8
4.2.1 241-C-101 Bulk Retrieval ..................................................................................9
4.2.2 241-C-107 Retrieval.........................................................................................14
4.2.3 241-C-111 Bulk Retrieval ................................................................................19
4.2.4 241-C-112 Bulk Retrieval ................................................................................23
4.2.5 241-C-112 Hard Heel Retrieval .......................................................................27
4.3 Equipment Failure Trends............................................................................................31
4.3.1 Hydraulic Leak Events .....................................................................................31
4.3.2 Ventilation Events ............................................................................................32
4.3.3 Camera and Lighting Events ............................................................................32
4.3.4 Supernatant Pump Start-Up and Shut-Down Events .......................................33
4.3.5 Supernatant Pump Flow Events .......................................................................33
4.3.6 Slurry Pump Low Flow and Plugging Events..................................................33
4.3.7 Slurry Pump Movement Events .......................................................................34
4.3.8 Sluicer / Extended Reach Sluicer System / Arm Movement Events ...............34
4.3.9 Hydraulic Temperature Events ........................................................................35
4.3.10 Miscellaneous Events .......................................................................................36
4.3.11 Total Number of Events ...................................................................................37
5.0 RECOMMENDATIONS ......................................................................................................38
6.0 REFERENCES .....................................................................................................................40
RPP-RPT-58298 3/9/2015 - 7:47 AM 7 of 106
RPP-RPT-58298, Rev. 0
iii
LIST OF FIGURES
Figure 4-1. 241-C-101 Bulk Retrieval Recorded Events. ...............................................................9
Figure 4-2. 241-C-101 Bulk Retrieval Miscellaneous Events. .....................................................12
Figure 4-3. 241-C-101 Bulk Retrieval Total Number of Events. .................................................13
Figure 4-4. 241-C-107 Retrieval Recorded Events. ......................................................................14
Figure 4-5. 241-C-107 Retrieval Miscellaneous Events. ..............................................................17
Figure 4-6. 241-C-107 Retrieval Total Number of Events. ..........................................................18
Figure 4-7. 241-C-111 Bulk Retrieval Recorded Events. .............................................................19
Figure 4-8. 241-C-111 Bulk Retrieval Miscellaneous Events. .....................................................21
Figure 4-9. 241-C-111 Bulk Retrieval Total Number of Events. .................................................22
Figure 4-10. 241-C-112 Bulk Retrieval Recorded Events. ...........................................................23
Figure 4-11. 241-C-112 Bulk Retrieval Miscellaneous Events. ...................................................25
Figure 4-12. 241-C-112 Bulk Retrieval Total Number of Events. ...............................................26
Figure 4-13. 241-C-112 Hard Heel Retrieval Recorded Events. ..................................................27
Figure 4-14. 241-C-112 Hard Heel Retrieval Miscellaneous Events. ..........................................29
Figure 4-15. 241-C-112 Hard Heel Retrieval Total Number of Events. ......................................30
Figure 4-16. Retrieval Campaign Recorded Events. ....................................................................31
Figure 4-17. Hydraulic Fluid Temperature Events by Season. .....................................................35
Figure 4-18. Retrieval Activities Total Miscellaneous Events. ....................................................36
Figure 4-19. Retrieval Activities Total Number of Events. ..........................................................37
Figure 4-20. Retrieval Activity Events by Season. .......................................................................38
RPP-RPT-58298 3/9/2015 - 7:47 AM 8 of 106
RPP-RPT-58298, Rev. 0
iv
LIST OF APPENDICES
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H
Appendix I
Appendix J
Appendix K
–
–
–
–
–
–
–
–
–
–
–
–
241-C-101 Bulk Retrieval Activities Events
241-C-107 Retrieval Activities Events
241-C-111 Bulk Retrieval Activities Events
241-C-112 Bulk Retrieval Activities Events
241-C-112 Hard Heel Retrieval Activities Events
241-C-101 Bulk Retrieval Event Analysis
241-C-107 Retrieval Activities Event Analysis
241-C-111 Bulk Retrieval Activities Event Analysis
241-C-112 Bulk Retrieval Activities Event Analysis
241-C-112 Hard Heel Retrieval Activities Event Analysis
Evaluated Retrieval Activities Event Analysis
LIST OF ATTACHMENTS
Attachment 1
–
Reference Materials
RPP-RPT-58298 3/9/2015 - 7:47 AM 9 of 106
RPP-RPT-58298, Rev. 0
v
LIST OF TERMS
Abbreviations, Initialisms, and Acronyms
CAM Continuous Air Monitor
DST Double-Shell Tank
ERSS Extended Reach Sluicer System
HHR Hard Heel Retrieval
HIHTL Hose-in-Hose Transfer Line
HMI Human-Machine Interface
HPU Hydraulic Power Unit
IDMS Integrated Document Management System
MARS Mobile Arm Retrieval System
OE Operational Engineer
SST Single-Shell Tank
VTP Ventilation Tank Primary
WRPS Washington River Protection Solutions, LLC
WRS Waste Retrieval System
Units
M moles
rpm revolutions per minute
RPP-RPT-58298 3/9/2015 - 7:47 AM 10 of 106
RPP-RPT-58298, Rev. 0
1
1.0 INTRODUCTION
This document reviews information for five bulk and hard heel retrieval (HHR) campaigns to
identify areas for equipment and operational process improvement. The evaluation addresses
both equipment reliability and availability.
2.0 SCOPE
Information for five retrieval campaigns was reviewed and events which caused either retrieval
shut-down or delay were noted by equipment type. Once documented, the findings were
evaluated to identify areas with repeated events. The information was obtained from the
Retrieval and Closure Operational Engineer (OE) Log Books, the Base Operations Log Books,
the retrieval completion reports, and the notes recorded by the Process Engineers in the material
balance calculation spreadsheets. Several hundred Problem Evaluation Requests, also known as
PERS, were reviewed and determined to not provide new pertinent information. The Document
Management Control System database was searched for lessons learned reports. No lessons
learned reports were found for the campaigns being evaluated.
2.1 EVALUATED RETRIEVAL SYSTEMS
There have been three distinct types of retrieval systems used in 241-C Tank Farm retrieval
efforts: the Modified Sluicing Waste Retrieval System (WRS), the Mobile Arm Retrieval System
(MARS) – Sluicing, and MARS – Vacuum. The five campaigns evaluated in this report used
either the WRS or the MARS – Sluicing.
There are three styles of sluicers used in the sluicer-based retrieval systems: the standard sluicer,
the Extended Reach Sluicer System (ERSS) sluicer, and the arm-mounted sluicer used with the
MARS. All of the sluicers are hydraulically driven. The standard sluicer is capable of pan and
tilt movement. The ERSS consists of an extendable boom-mounted sluicer capable of pan and
tilt movement. The boom allows the ERSS sluicer nozzle to be placed closer to the waste
therefore increasing the sluicing effectiveness in breaking up solid waste in the single-shell tank
(SST). The ERSS are also equipped with two high-pressure water nozzles located on either side
of the sluicing nozzle.
2.1.1 Modified Sluicing Waste Retrieval System
A WRS includes three main components in the SST being retrieved and two in the receiving
double-shell tank (DST). The three SST components are two sluicers and a slurry pump. The
DST components are a slurry distributor, and a supernatant pump. The sluicers are generally
placed in risers toward the outside of the SST and the slurry pump located in the center. In the
DST, the slurry distributor and supernatant pump are co-located in the central pump pit. The
slurry distributor is a passive device which is manually raised or lowered. The supernatant pump
may be either electrically or hydraulically driven while the slurry pump is hydraulically driven.
During retrieval, the slurry pump is lowered as the SST waste level lowers. The supernatant
RPP-RPT-58298 3/9/2015 - 7:47 AM 11 of 106
RPP-RPT-58298, Rev. 0
2
pump is raised as the solids level in the DST increases. The slurry distributor is raised and
lowered as necessary to minimize the amount of solids in suspension and therefore returned to
the SST in the supernate.
Hose-in-hose-transfer lines (HIHTLs) connect the two tanks via a portable valve pit and a
portable diversion box. Other ancillary equipment required for a WRS-based retrieval include
active ventilation systems on both the SST and DST tanks, leak detection, and in-tank cameras
and associated lighting systems.
2.1.2 Mobile Arm Retrieval System – Sluicing
A MARS includes two main components in the SST being retrieved and two in the receiving
DST. The two SST components are an arm-mounted sluicer and a slurry pump. The DST
components are a slurry distributor and a supernatant pump. The sluicer arm and slurry pump
are generally placed in risers located in the center of the SST. In the DST, the slurry distributor
and supernatant pump are co-located in the central pump pit. The slurry distributor is a passive
device which is manually raised or lowered. The supernatant pump may be either electrically or
hydraulically driven while the slurry pump is hydraulically driven. During retrieval, the slurry
pump is lowered as the SST waste level lowers. The supernatant pump is raised as the solids
level in the DST increases. The slurry distributor is raised and lowered as necessary to minimize
the amount of solids in suspension and therefore returned to the SST in the supernate.
HIHTLs connect the two tanks via a portable valve pit and a portable diversion box. Other
ancillary equipment required for a WRS-based retrieval include active ventilation systems on
both the SST and DST tanks, leak detection, and in-tank cameras and associated lighting
systems.
2.2 EVALUATED CAMPAIGNS
The retrieval campaigns evaluated are discussed in the following sections. The campaigns were
selected based on their use of MARS, standard, and ERSS sluicer technology, and their use of
diverse media to mobilize the waste.
2.2.1 241-C-101 Bulk Retrieval
Tank 241-C-101 was retrieved using a WRS with ERSS sluicers. Retrieval occurred from
December 2012 until September 2013 with the following non-equipment failure-related
interruptions:
Resources were diverted from the 241-C-101 retrieval to support the 241-C-107 retrieval
on March 19, 2013, and were not available until May 14, 2013;
Resources were diverted to support the 241-C-107 retrieval efforts again from May 18,
2013, until June 2, 2013;
RPP-RPT-58298 3/9/2015 - 7:47 AM 12 of 106
RPP-RPT-58298, Rev. 0
3
Delays for installation and testing of high-pressure water support equipment occurred
from June 20, 2013, to July 8, 2013, and from September 3, 2013, to September 5, 2013;
and
An event investigation interrupted retrieval from August 22, 2013, until September 3,
2013.
The sluicing media used for the more readily retrieval solids was supernate from 241-AN-101.
High pressure water was the media used for larger pieces of hard waste that could not be broken
up by typical sluicing methods.
The following documents were used to evaluate the performance of the WRS and associated SST
and DST equipment:
A photocopy of the 241-C-101 Retrieval and Closure OE Log Book provided by
Washington River Protection Solutions, LLC (WRPS) Process Engineering (Attachment
1);
A photocopy of Base Operations Shift Office Log Book, BOSO-009, 11-21-11 to
08-19-12, obtained from Integrated Document Management System (IDMS) (Attachment
1);
A photocopy of Base Operations Shift Office Log Book: BOSO-010, 08/20/2012 to
03/03/2013, obtained from IDMS (Attachment 1);
A copy of the 241-C-101 volume balance Excel®1 file provided by WRPS Process
Engineering (Attachment 1); and
RPP-RPT-55573, “Retrieval Completion Report for Modified Sluicing of Tank
241-C-101 Using Extended Reach Sluicing and High Pressure Water.”
A compilation of the pertinent information obtained from these sources is contained in
Appendix A.
2.2.2 241-C-107 Retrieval
Tank 241-C-107 was retrieved using the MARS. Retrieval occurred from September 2011 until
April 2014 with intermittent interruptions to support 241-C-104 and 241-C-109 retrieval efforts.
The sluicing media used for the more readily retrievable solids was supernate from 241-AN-106.
High pressure water was the media used for larger pieces of hard waste that could not be broken
up by typical sluicing methods.
1 Excel is a registered trademark of Microsoft Corporation in the United States and/or other countries.
RPP-RPT-58298 3/9/2015 - 7:47 AM 13 of 106
RPP-RPT-58298, Rev. 0
4
The following documents were used to evaluate the performance of the MARS and associated
SST and DST equipment:
A photocopy of the 241-C-107 Retrieval and Closure OE Log Book provided by WRPS
Process Engineering (Attachment 1);
A photocopy of Base Operations Shift Office Log Book: BOSO-007, 10-20-10 to
05-02-11, obtained from IDMS (Attachment 1);
A photocopy of Base Operations Shift Office Log Book: BOSO-008, 05-02-11 to
11-20-11, obtained from IDMS (Attachment 1);
A photocopy of Base Operations Shift Office Log Book: BOSO-009, 11-21-11 to
08-19-12, obtained from IDMS (Attachment 1);
A photocopy of Base Operations Shift Office Log Book: BOSO-010, 08/20/2012 to
03/03/2013, obtained from IDMS (Attachment 1);
A photocopy of Base Operations Shift Office Log Book: BOSO-011, 3/4/13 to 9/8/13,
obtained from IDMS (Attachment 1);
A copy of the 241-C-107 volume balance Excel file provided by WRPS Process
Engineering (Attachment 1); and
RPP-RPT-54959, “Single-Shell Tank 241-C-107 Hard Heel Retrieval Completion
Report.”
A compilation of the pertinent information obtained from these sources is contained in
Appendix B.
2.2.3 241-C-111 Bulk Retrieval
Tank 241-C-111 was retrieved using a WRS with standard sluicers. Retrieval occurred from
September 2010 until November 2010.
The sluicing media used was supernate from 241-AN-101.
The following documents were used to evaluate the performance of the WRS and associated SST
and DST equipment:
A photocopy of the 241-C-111 Retrieval and Closure OE Log Book provided by WRPS
Process Engineering (Attachment 1);
A photocopy of Base Operations Shift Office Log Book, BOSO-006, 4-30-10 to
10-19-10, obtained from IDMS (Attachment 1);
RPP-RPT-58298 3/9/2015 - 7:47 AM 14 of 106
RPP-RPT-58298, Rev. 0
5
A photocopy of Base Operations Shift Office Log Book, BOSO-007, 10-20-10 to
05-02-11, obtained from IDMS (Attachment 1); and
A copy of the 241-C-111 volume balance Excel file provided by WRPS Process
Engineering (Attachment 1).
A completion report was not found.
A compilation of the pertinent information obtained from these sources is contained in
Appendix C.
2.2.4 241-C-112 Bulk Retrieval
Tank 241-C-112 bulk retrieval used a WRS with one standard sluicer and one ERSS sluicer.
Retrieval occurred from December 2011 until April 2012.
The sluicing media used was supernate from 241-AN-101.
The following documents were used to evaluate the performance of the WRS and associated SST
and DST equipment:
A photocopy of the 241-C-112 Bulk Retrieval and Closure OE Log Book provided by
WRPS Process Engineering (Attachment 1);
A photocopy of Base Operations Shift Office Log Book, BOSO-009, 11-21-11 to
08-19-12, obtained from IDMS (Attachment 1);
A copy of the 241-C-112 volume balance Excel file provided by WRPS Process
Engineering (Attachment 1); and
RPP-RPT-52480, “Retrieval Completion Report for Modified Sluicing of Tank
241-C-112.”
A compilation of the pertinent information obtained from these sources is contained in
Appendix D.
2.2.5 241-C-112 Hard Heel Retrieval
Tank 241-C-112 HHR used a WRS with one standard sluicer and one ERSS sluicer. Retrieval
occurred from November 2013 until January 2014.
Concentrated 19.4 M sodium hydroxide was used during the two soaking and recirculation
periods. The sluicing media used for the majority of the retrieval was supernate from
241-AN-101. Hot water was used at the end to allow for dissolution of any water soluble salts
remaining in the tank.
RPP-RPT-58298 3/9/2015 - 7:47 AM 15 of 106
RPP-RPT-58298, Rev. 0
6
The following documents were used to evaluate the performance of the WRS and associated SST
and DST equipment:
A photocopy of the 241-C-112 HHR Retrieval and Closure OE Log Book provided by
WRPS Process Engineering (Attachment 1);
A photocopy of Base Operations Shift Office Log Book, BOSO-011, 3/4/13 to 9/8/13,
obtained from IDMS (Attachment 1);
A copy of the 241-C-112 volume balance Excel file provided by WRPS Process
Engineering (Attachment 1); and
RPP-RPT-56900, “Single-Shell Tank 241-C-112 Hard Heel Retrieval Completion
Report.”
A compilation of the pertinent information obtained from these sources is contained in
Appendix E.
2.3 EVALUATED EQUIPMENT
Equipment included in the evaluation can be separated into two categories: SST-specific
equipment and shared equipment. The shared equipment includes the SST ventilation systems,
all of the DST equipment, the majority of the HIHTLs, the valve pits, the diversion boxes, and
control trailers.
The 241-C Tank Farm SSTs were retrieved to either 241-AN-101 or to 241-AN-106. The shared
equipment associated with the 241-AN-101 receiver tank is:
The POR137-WT-TRLR-001 control trailer,
The POR138-WT-VP-001 valve pit,
The POR134-WT-DB-001 diversion pit,
The 241-AN-101 transfer pump, and
The HIHTL which connects them.
Four of the campaigns evaluated were retrieved to 241-AN-101. These are the 241-C-101,
241-C-111, and both of the 241-C-112 retrievals. In addition to these tanks, 241-C-102 and
241-C-104 used 241-AN-101 as their receiver tank.
The shared equipment associated with the 241-AN-106 receiver tank is:
The POR104-WT-VP-001 valve pit,
The POR209-WT-DB-001 diversion pit,
The 241-AN-106 transfer pump, and
The HIHTL which connects them.
RPP-RPT-58298 3/9/2015 - 7:47 AM 16 of 106
RPP-RPT-58298, Rev. 0
7
The 241-C-107 retrieval utilized 241-AN-106 as its receiver tank. MARS activities have a
dedicated control trailer, POR246-WT-TRLR-001. Other tanks which used 241-AN-106 as their
receiver tank include 241-C-103, 241-C-106, 241-C-108, 241-C-109, and 241-C-110. These
tanks used WRS for retrieval and used a WRS-dedicated control trailer.
All seven of the 241-AN Tank Farm tanks use the same primary tank ventilation system, the AN
ventilation tank primary (VTP). DSTs are required to maintain active ventilation and are
connected to the ventilation systems continuously. The 16 SSTs in the 241-C Tank Farm only
require active ventilation during retrieval activities and are usually passively ventilated. There
are two main ventilation systems in 241-C Tank Farm, POR008 and POR107. POR107 has been
connected to POR03 in order to increase the exhaust flow rate provided by the system. Many of
the SSTs in 241-C may be connected to either the POR008 ventilation system or to the
POR107/POR03 ventilation system.
Each of the SSTs includes sluicers, either standard, ERSS, or arm-mounted, and adjustable
height slurry pumps. In the WRS configuration, each of the sluicers is equipped with a hydraulic
power unit (HPU). Sluicer functions are controlled via a hydraulic valve manifold. The MARS
arm-mounted sluicer is also hydraulically driven and controlled with hydraulic valves. The
slurry pumps also are equipped with an HPU.
The DSTs each have an adjustable height slurry distributor as well as an adjustable height
supernatant pump. The pumps used in 241-AN-101 are hydraulically driven and as such are
equipped with an HPU. Tank 241-AN-106 used both electrically driven and hydraulically driven
pumps during the retrieval campaigns evaluated.
Sluicing activities are conducted using in-tank cameras, two per SST, which allows the operator
to determine the retrieval progress and direct the sluicer nozzle. These are portable camera units
with a built in light. In addition to the camera light, additional in-tank lighting is provided for
each camera.
Water at 241-C Tank Farm is provided from a common source, POR135.
These components and the instrumentation monitoring them were included in this evaluation.
3.0 METHODOLOGY
The information contained in Appendices A through E document a total of 487 events occurring
over 390 operating days. These events were sorted into a number of categories which were
suggested by the development of Appendices A through E. These categories are:
Hydraulic leak events,
Ventilation events,
Camera and lighting events,
Supernatant pump start-up and shut-down events,
Supernatant pump flow rate events,
Slurry pump flow rate events,
RPP-RPT-58298 3/9/2015 - 7:47 AM 17 of 106
RPP-RPT-58298, Rev. 0
8
Slurry pump movement events,
Sluicer / ERSS / arm movement events,
Hydraulic temperature events, and
Other miscellaneous events.
Tables documenting the events by day and category for each retrieval campaign are contained in
Appendices F through J. Events were tallied in each category for each day. If a particular event
happened multiple times on a given day, it was counted as a single instance since it was likely
reoccurring due to not having completely resolved the initiating event. If a new initiating event
occurred on the same day, it counted as a new event in the tally. For example, if the ventilation
system was shut-down due to a continuous air monitor (CAM), it counted as a single event, even
if the ventilation system was shut down multiple times for CAM problems on that day. If there
were also seal pot issues on the same day, it would count as a separate event on that day.
Event categorizations by category over time for the entirety of the campaigns reviewed are
included in Appendix K.
4.0 FINDINGS
4.1 SIGNIFICANT DELAY EQUIPMENT FAILURES
There were four equipment failures which required component replacements resulting in
significant interruptions in the retrieval process. These failures were:
The AN106-WT-P-22 electric pump which failed during retrieval activities;
The AN106-WT-P-23 electric pump which failed during pre-installation testing;
The AN106-WT-P-24 hydraulic pump which failed during retrieval activities; and
The 241-C-107 slurry pump which failed during retrieval activities.
Retrieval activities did not resume for 208 days after the failure of the AN106-WT-P-22 pump
and subsequent failure of the AN106-WT-P-23 pump during testing. After the AN106-WT-P-24
pump failure, retrievals did not resume for an additional 241 days. Retrievals resumed 198 days
after the failure of the 241-C-107 pump. All of the pump failures were associated with the
241-C-107 MARS retrieval efforts. Given that the other retrieval efforts associated with the
241-AN-106 receiving tank are not within the scope of this review, it is not possible to evaluate
the total number of hours of pump use prior to failure.
No other failures were noted which resulted in a sustained suspension of retrieval activities.
4.2 MINOR DELAY EQUIPMENT FAILURES
The vast majority of failures resulted in short duration shutdowns or reduced capacity during
continued operations. The typical short duration shutdown impact was less than one shift with a
few extending into one or two days while the equipment was undergoing troubleshooting. The
other failures included here typically resulted in reduced capacity such as lost mobility in a
RPP-RPT-58298 3/9/2015 - 7:47 AM 18 of 106
RPP-RPT-58298, Rev. 0
9
sluicer nozzle or reduced flow from a sluicer nozzle. The events are summarized by tank in the
following subsections. Trends and analysis of the findings are discussed in Section 4.3.
4.2.1 241-C-101 Bulk Retrieval
The information documented in Appendix A was sorted into the categories listed in Section 3.0,
“Methodology.” The resulting table is in Appendix F. A total of 110 entries were made
documenting issues over 101 days of operation. Figure 4-1 shows the distribution of the events
between categories. No trends were noted within the 241-C-101 information. Analyses of each
of the categories are summarized in the following subsections.
Figure 4-1. 241-C-101 Bulk Retrieval Recorded Events.
4.2.1.1. Hydraulic Leak Events. Eight hydraulic leak events were recorded during the
241-C-101 bulk retrieval campaign. Two of these events were associated with the slurry pump
HPU. One event was associated with the supernatant pump HPU. The other five were
associated with the two sluicers.
The slurry pump HPU leaks were at a flange on the HPU. The supernatant pump hydraulic leak
was at the pressure hose connection point of the HPU. All three of these leaks appear to have
been repaired with minimal impact to the retrieval efforts.
One of the sluicer leak entries was associated with the number 1 sluicer. The leak was apparent
during operation of the horizontal movement function. The hose providing the function was
0
5
10
15
20
25
Nu
mb
er
of
Eve
nts
Event Type
RPP-RPT-58298 3/9/2015 - 7:47 AM 19 of 106
RPP-RPT-58298, Rev. 0
10
disconnected. Operation of the number 1 sluicer continued utilizing vertical movement of the
nozzle.
The remaining four hydraulic leak events noted were associated with the number 2 sluicer.
Those four entries documented the discovery and effects of the same two failures. The leaks
associated with the number 2 sluicer were at the rotary union. The initial entry identified both
leaks. The horizontal motion function had a drip-wise leak at the rotary union. A steady stream
of hydraulic fluid was observed at the rotary union during vertical motion. Sluicing continued
with the number 2 sluicer using the horizontal motion functions while the hoses to the vertical
motion functions were disconnected. Later investigation attributed these leaks to electro-spark
damage to the Teflon hydraulic hoses as identified in RPP-RPT-55036, “Summary Evaluation of
ERSS Hydraulic Hose Failures”. Corrective actions are in place to address this issue.
4.2.1.2. Ventilation Events. Seventeen entries were logged associated with ventilation issues.
Ten of the events were associated with the POR107 ventilation system, one was related to the
241-C-101 demister, and the remaining six were associated with the 241-AN VTP.
Eight of the 17 entries were associated with the CAMs, 5 on the POR107 ventilation system and
3 on the 241-AN system. Three entries documented the efforts associated with a single event of
the POR107 glycol heater smoking. The five entries note issues with the POR107 seal pot
temperature, the POR107 low flow alarm, the POR107 sample pump, high differential pressure
across the 241-C-101 demister, and entering an extended outage for 241-AN VTP upgrades for
compliance with RPP-13033, “Tank Farms Documented Safety Analysis.” One entry simply
noted that the 241-AN ventilation system was shut down.
4.2.1.3. Camera and Lighting Events. Fourteen entries were logged associated with the in-
tank cameras and lighting systems. Only one of the camera and lighting entries was for the
241-AN-101 camera. The remaining 13 entries were for the 241-C-101 in-tank cameras and
lights.
There were five entries associated with the in-tank lighting, including a stop work on the use of
all Alhberg lighting and three for the cameras and lighting. The camera and lighting installed in
Riser 3 had the majority of entries with replacement being noted ten times. The cameras and
lighting installed Riser 8 required replacement seven times.
4.2.1.4. Supernatant Pump Start-Up and Shut-Down Events. The 241-C-101 retrieval data
did not contain any information indicating the 241-AN-101 supernatant pump was having start-
up or shut-down issues.
4.2.1.5. Supernatant Pump Flow Events. Four entries noted problems with the 241-AN-101
supernatant pump flow rate. Three of these events were likely related to inlet screen plugging.
The fourth documents a loss of pump HPU speed increase/decrease controls. The HPU speed
control issue self-corrected as the system worked as designed during troubleshooting.
RPP-RPT-58298 3/9/2015 - 7:47 AM 20 of 106
RPP-RPT-58298, Rev. 0
11
4.2.1.6. Slurry Pump Low Flow and Plugging Events. Twenty low flow and plugging events
were noted during the 241-C-101 campaign. Two of these events were associated with final
pump down as part of the volume displacement activities. The other 18 appear to have been
expected events as there was no indication that engineering or maintenance was notified.
4.2.1.7. Slurry Pump Movement Events. Three entries documented difficulties in moving the
slurry pump. All three events appear to have been due to material below the pump creating a rest
for the pump. The logs do not indicate that engineering or maintenance was notified, suggesting
this was expected behavior from the pump.
4.2.1.8. Sluicer / Extended Reach Sluicer System / Arm Movement Events. A single event
was noted during the 241-C-101 campaign. The sluicer number 1 controls were operating
backward, e.g., the command to move the nozzle in the upward direction resulted in downward
motion, etc. Engineering confirmed that the sluicer was oriented 180 degrees out causing the
backward nozzle controls. This was neither the first nor the last use of sluicer number 1.
4.2.1.9. Hydraulic Temperature Events. Twenty-one entries noted hydraulic system
temperature anomalies. Five instances were for low temperature, the other 16 were for high
temperature.
4.2.1.10. Miscellaneous Events. Twenty-two events were noted which did not appear to either
fit within one of the other categories or to reoccur. Figure 4-2 shows the distribution of the
events over time. The trend does not show that there was a noticeable difference in the rate of
occurrence associated with campaign start-up.
RPP-RPT-58298 3/9/2015 - 7:47 AM 21 of 106
RPP-RPT-58298, Rev. 0
12
Figure 4-2. 241-C-101 Bulk Retrieval Miscellaneous Events.
4.2.1.11. Total Number of Events. Figure 4-3 is a graph showing the distribution of the 110
events over time. As with the rate of miscellaneous events, the trend does not show that there
was a noticeable difference in the rate of occurrence associated with campaign start-up. The
events occur at a steady rate over the duration of the campaign. This suggests that the
construction and start-up testing processes are of sufficient quality as to not adversely impact
operations.
0
5
10
15
20
25
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 101
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 22 of 106
RPP-RPT-58298, Rev. 0
13
Figure 4-3. 241-C-101 Bulk Retrieval Total Number of Events.
0
20
40
60
80
100
120
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 101
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 23 of 106
RPP-RPT-58298, Rev. 0
14
4.2.2 241-C-107 Retrieval
The information documented in Appendix B was sorted into the categories listed in Section 3.0,
“Methodology.” The resulting table is in Appendix G. A total of 231 entries were made
documenting issues over 136 days of operation. Figure 4-4 shows the distribution of the events
between categories. No trends were noted within the 241-C-107 information. Analyses of each
the categories are provided in the following subsections.
Figure 4-4. 241-C-107 Retrieval Recorded Events.
4.2.2.1. Hydraulic Leak Events. Nine hydraulic leak events were noted during the 241-C-107
campaign. Two events documented a drop in the supernatant pump hydraulic fluid level with no
apparent leakage immediately prior to failure of the pump. Two events were associated with a
spray leak by a filter in the POR237-WT-ENCL-400 hydraulic cabinet. A fitting leak at
POR241-WT-HPU-001 was noted as was a leak at the constant tension hoist reel in the MARS
containment box. Two events documented a seal leakage from the wrist sweep stack valve. The
final hydraulic leak event noted a steady stream of fluid from POR237-WT-ENCL-400.
4.2.2.2. Ventilation Events. Ventilation issues were noted 37 times during the campaign.
Thirty-two of the entries were associated with POR107, three were associated with POR03, and
one each with POR008 and the AN VTP.
Twenty of the events noted were associated with either the CAM or the record sampler. One of
these events was the result of a confirmed high radiation condition on the sample paper.
0
10
20
30
40
50
60
70
80
Nu
mb
er
of
Eve
nts
Event Type
RPP-RPT-58298 3/9/2015 - 7:47 AM 24 of 106
RPP-RPT-58298, Rev. 0
15
Thirteen events were associated with the instrument flow rates. The other six events were noted
as CAM failures.
The other 17 events documented a variety of issues including 2 for Human-Machine Interface
(HMI) issues and 3 for control valve problems. Four events noted involved the 241-C-107
pressure transmitter. Five events were associated with problems with the stack temperature
differential. There was a single instance noted of low stack flow and two instances of the
systems shutting down without a cause being identified.
4.2.2.3. Camera and Lighting Events. Two camera and lighting events were noted. The first
event noted that the Riser 2 and Riser 7 cameras in 241-C-107 had both degraded to near failure
and that retrieval was not able to continue with the resulting visibility. The second event noted
that the 241-AN-106 camera had failed.
4.2.2.4. Supernatant Pump Start-Up and Shut-Down Events. Supernatant pump start-up or
shut-down events were noted on five occasions. Two of the events were associated with signal
problems for the flow control valves. The other three instances were simply described as “timed
out.”
4.2.2.5. Supernatant Pump Flow Events. There were 13 events noted associated with low
flow from the supernatant pump. Two were associated with the failure of the AN106-WT-P-22
electric pump. Two occurred when the pump speed was being ramped up or down. One event
was associated with flow control valve issues while another was documented as being due to the
MARS’ arm being moved to 90 degrees. Seven other events were associated with blockage of
the intake screen.
4.2.2.6. Slurry Pump Low Flow and Plugging Events. Plugging of the slurry pump intake
screen and associated shut down was noted on 71 days. Many of these days had in excess of five
events of shut down per shift worked. The logs do not indicate that engineering or maintenance
was notified, suggesting this was expected behavior from the pump. RPP-RPT-54959 notes that
the supernate used as sluicing medium starting in early 2014 reacted with the solids, creating
phosphate crystallized waste solids agglomerations within 241-C-107. Subtracting the events
after the introduction of the phosphate bearing supernate leaves 45 days where there were low-
flow related shut downs not related to the phosphate crystallized waste solids agglomerate. A
quick count indicates that in excess of 250 shut downs were experienced during these 45 days.
As this is the only example of the MARS retrieval technology included within the scope of this
analysis, it is not possible to determine if the reason the waste was not being broken down into
pieces small enough to be transferred was due to the waste type or due to the retrieval
technology.
There were four additional events documenting issues with the slurry pump speed sensors. The
first entry simply states that there were issues with the speed sensors. The second and third
entries documented the troubleshooting evolution associated with the failure of both speed
sensors. The final entry states that the speed sensor shows 0 rpm on start-up. No additional
information was provided.
RPP-RPT-58298 3/9/2015 - 7:47 AM 25 of 106
RPP-RPT-58298, Rev. 0
16
4.2.2.7. Slurry Pump Movement Events. The slurry pump and back stop could not be moved
as desired 11 times during the campaign. Nine of the events were associated with the pump; the
other two were for issues with the back stop.
Pump movement was limited due to the lower cable limit six times. There was a single instance
of the pump not lowering because the contactor had tripped and one from having blockage
beneath it. The final entry discusses the slurry pump dragging when the turntable was rotated
which affected the reeving of the cable onto the winch. There were no apparent long-term ill-
effects to the winch.
There was one instance of the backstop being limited by the lower cable limit and one instance
of the backstop not moving without a cause being given.
4.2.2.8. Sluicer / Extended Reach Sluicer System / Arm Movement Events. There were 15
entries associated with the movement of the MARS’ arm. Seven of the events were related to
HMI operation. Problems with the constant tension hoist resulted in five entries. Two entries
were associated with failure of the proximity switches and the associated compensating efforts.
There was one documented instance of problems with the HPU and one where the curb feeler
stopped actuating.
4.2.2.9. Hydraulic Temperature Events. The hydraulic fluid temperature was either too high
or too low eight times.
RPP-RPT-58298 3/9/2015 - 7:47 AM 26 of 106
RPP-RPT-58298, Rev. 0
17
4.2.2.10. Miscellaneous Events. Fifty-five events were noted which did not appear to either fit
within one of the other categories or to reoccur. Figure 4-5 is a graph showing the distribution of
the events over time. The trend does not show that there was a noticeable difference in the rate
of occurrence associated with campaign start-up.
Figure 4-5. 241-C-107 Retrieval Miscellaneous Events.
Five leak events were associated with the rotary union. During an interview with 241-C-107
project personnel, it was discovered that the leaks observed were not hydraulic leaks as
originally believed from the entries, but were waste leaks (WRPS-PER-2012-1321, “Evidence of
Previous leakage from the Rotary Union on the C-107 MARS Unit” and WRPS-PER-2012-1346,
“C-107 MARS Containment Box Rotary Union Drip Leak”). The project determined that the
leaks were the result of the manufacturing methods used when fabricating the rotary union. A
new rotary union was fabricated using a modified manufacturing method and installed in the
241-C-107 MARS. No leaks were observed at the rotary union after the new union was
installed.
0
10
20
30
40
50
60
1 6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
10
1
10
6
11
1
11
6
12
1
12
6
13
1
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 27 of 106
RPP-RPT-58298, Rev. 0
18
4.2.2.11. Total Number of Events. Figure 4-6 is a graph showing the distribution of the 231
events over time. As with the rate of miscellaneous events, the trend does not show that there
was a noticeable difference in the rate of occurrence associated with campaign start-up. The
events occur at a steady rate over the duration of the campaign. This suggests that the
construction and start-up testing processes are of sufficient quality as to not adversely impact
operations.
Figure 4-6. 241-C-107 Retrieval Total Number of Events.
0
50
100
150
200
250
1 6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
10
1
10
6
11
1
11
6
12
1
12
6
13
1
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 28 of 106
RPP-RPT-58298, Rev. 0
19
4.2.3 241-C-111 Bulk Retrieval
The information documented in Appendix C was sorted into the categories listed in Section 3.0,
“Methodology.” The resulting table is in Appendix H. A total of 37 entries were made
documenting issues over 40 days of operation. Figure 4-7 shows the distribution of the events
between categories. No trends were noted within the 241-C-111 information. Analyses of each
the categories are provided in the following subsections.
Figure 4-7. 241-C-111 Bulk Retrieval Recorded Events.
4.2.3.1. Hydraulic Leak Events. The 241-C-111 campaign log books did not document any
hydraulic leak events.
4.2.3.2. Ventilation Events. There were nine events noted associated with the ventilation
system in the log books. All nine events were associated with the 241-C Farm ventilation
systems, split between POR008 and POR03.
POR008 had two events. The first event noted was the system making significant noise and
cycling the variable frequency drive. Toward the end of the campaign, the system was shut
down on rate of increase in differential pressure.
POR03 was involved with seven events. Five of the events were associated with the CAM, one
documented software modifications, and one addressed a low plenum flow condition.
0
2
4
6
8
10
12
Nu
mb
er
of
Eve
nts
Event Type
RPP-RPT-58298 3/9/2015 - 7:47 AM 29 of 106
RPP-RPT-58298, Rev. 0
20
4.2.3.3. Camera and Lighting Events. Camera and lighting events were noted seven times
during the campaign. The first entry may reflect the initial camera and lighting installation. A
second entry later in the campaign documents replacing the Riser 7 camera and lighting. The
Coffman lights were noted to have high amps on three occasions, once in Riser 1, once in Riser 7
and one entry did not indicate which riser was affected. The Riser 7 high amp entry was
followed shortly by the light in Riser 7 failing.
Three entries discussed concerns with the camera. The camera was noted to have lost the ability
to rotate. Shortly afterward an entry stated that the camera was adjusted. The entries did not
indicate which camera was involved. The Riser 1 camera was noted to have electrical issues
early in the campaign with burned wiring and a failed ground-fault circuit interrupter breaker.
4.2.3.4. Supernatant Pump Start-Up and Shut-Down Events. A single event was noted
indicating the supernatant pump had difficulties with start up or shut down. The pump would not
come up to speed in a timely fashion and would time out. Four attempts to start the pump all had
the same result – they timed out before the pump could reach operating speeds. Engineering
provided direction to wait 5-10 minutes after starting the HPU before attempting to increase the
supernatant pump speed. The log book indicates that this approach was successful.
4.2.3.5. Supernatant Pump Flow Events. The supernatant pump was observed to have 11
flow events. All of these events appear to be related to the speed indication and how it affected
the flow rate. Ten of these events took place over 14 operating days. During these 14 days,
operations continued with intermittent pauses for trouble shooting.
4.2.3.6. Slurry Pump Low Flow and Plugging Events. The slurry pump was noted to have
two low flow events. The first was associated with material build up and appears to have been
an expected event as there was no indication that engineering or maintenance was notified. The
second coincided with a supernatant pump shut down, also on low flow. The shift log noted that
the reason for the second shut down was unknown.
4.2.3.7. Slurry Pump Movement Events. One entry noted that the slurry pump went slack
when attempting to lower the pump. The logs do not indicate that engineering or maintenance
was notified, suggesting this was expected behavior from the pump.
4.2.3.8. Sluicer / Extended Reach Sluicer System / Arm Movement Events. The 241-C-111
campaign log books did not document any sluicer movement events.
4.2.3.9. Hydraulic Temperature Events. The 241-C-111 campaign log books did not
document any hydraulic temperature excursions.
RPP-RPT-58298 3/9/2015 - 7:47 AM 30 of 106
RPP-RPT-58298, Rev. 0
21
4.2.3.10. Miscellaneous Events. Six events occurred which did not appear to either fit within
one of the other categories or to reoccur. Figure 4-8 is a graph showing the distribution of the
events over time. The trend does not show that there was a noticeable difference in the rate of
occurrence associated with campaign start-up.
Figure 4-8. 241-C-111 Bulk Retrieval Miscellaneous Events.
0
1
2
3
4
5
6
7
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 31 of 106
RPP-RPT-58298, Rev. 0
22
4.2.3.11. Total Number of Events. Figure 4-9 is a graph showing the distribution of the 37
events over time. As with the rate of miscellaneous events, the trend does not show that there
was a noticeable difference in the rate of occurrence associated with campaign start-up. The
events occur at a steady rate over the duration of the campaign. This suggests that the
construction and start-up testing processes are of sufficient quality as to not adversely impact
operations.
Figure 4-9. 241-C-111 Bulk Retrieval Total Number of Events.
0
5
10
15
20
25
30
35
40
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 32 of 106
RPP-RPT-58298, Rev. 0
23
4.2.4 241-C-112 Bulk Retrieval
The information documented in Appendix D was sorted into the categories listed in Section 3.0,
“Methodology.” The resulting table is in Appendix I. A total of 69 entries were made
documenting issues over 72 days of operation. Figure 4-10 shows the distribution of the events
between categories. No trends were noted within the 241-C-112 bulk retrieval information.
Analyses of each the categories are provided in the following subsections.
Figure 4-10. 241-C-112 Bulk Retrieval Recorded Events.
4.2.4.1. Hydraulic Leak Events. There were six notations of hydraulic leak events. Five of
these notations address the actions surrounding a leak associated with sluicer number 1. The
other notation documents a slurry pump HPU drip.
4.2.4.2. Ventilation Events. Nine ventilation events were documented during the 241-C-112
bulk retrieval campaign. One of these events documented that both POR008 and the 241-AN
VTP systems were off-line due to a power outage. There were four instances where the POR008
seal pot transmitter was indicating either a high or low level. It was noted that the low level
events appeared to be related to low ambient temperatures affecting the sensing legs. There were
two instances where the documentation simply stated that the 241-AN VTP was off-line. There
were also two notations documenting POR008 high differential pressure events.
4.2.4.3. Camera and Lighting Events. There were 15 entries associated with the cameras and
lighting. Four of the notations documented camera issues without indicating there were
problems with the lights. Four indicated instances where both the cameras and the lighting were
0
2
4
6
8
10
12
14
16
Nu
mb
er
of
Eve
nts
Event Type
RPP-RPT-58298 3/9/2015 - 7:47 AM 33 of 106
RPP-RPT-58298, Rev. 0
24
inoperable or significantly degraded. Of these four, three of them were associated with a single
event where both of the cameras and all of the lights were impacted. The delay associated with
this event was longer than typical for camera or lighting issues due to poor weather curtailing
field activities.
There were seven entries which only addressed lighting issues. By the end of the campaign, as
soon as a light was replaced, the one in the other riser would fail, to the point that operations was
noting that only one light at a time would be used in an attempt to conserve the lights.
4.2.4.4. Supernatant Pump Start-Up and Shut-Down Events. The supernatant pump had
start-up or shut-down events noted seven times. Six of these events address start-up concerns,
while the remaining one is for a delay in the pump shutting down. All seven of the events appear
to be based on controlling the pump from the control trailer instead of at the HPU. All six
instances related to pump start-up include discussion on the pump amps not increasing. The log
books indicate that the pump would either start later that day or the next day without
maintenance or repair.
4.2.4.5. Supernatant Pump Flow Events. Events related to supernatant pump flow were noted
six times. All six events appear to be related to intake screen blockage. Operations documented
several attempts to clear the blockage with drain back with varying success. Flushing of the line
was used in two instances which cleared the blockage and the flow rates returned to the expected
ranges.
4.2.4.6. Slurry Pump Low Flow and Plugging Events. The slurry pump was noted to have
low flow and plugging events on seven days. This appears to have been anticipated behavior as
there was no indication that engineering or maintenance was notified.
4.2.4.7. Slurry Pump Movement Events. The slurry pump was noted to have hampered
movement on four occasions. In all four instances, it is likely that the pump was resting on
solids which prevented the pump from going lower into the tank. This appears to have been
anticipated behavior as there was no indication that engineering or maintenance was notified.
4.2.4.8. Sluicer / Extended Reach Sluicer System / Arm Movement Events. A single entry
for sluicer number 2 indicates that the sluicer’s range of motion was limited to around 180
degrees.
4.2.4.9. Hydraulic Temperature Events. Two events were noted where the hydraulic fluid
temperature disrupted operations. Both entries document low temperature conditions.
RPP-RPT-58298 3/9/2015 - 7:47 AM 34 of 106
RPP-RPT-58298, Rev. 0
25
4.2.4.10. Miscellaneous Events. Ten events occurred which did not appear to either fit within
one of the other categories or to reoccur. Figure 4-11 shows the distribution of the events over
time. The trend does not show that there was a noticeable difference in the rate of occurrence
associated with campaign start-up.
Figure 4-11. 241-C-112 Bulk Retrieval Miscellaneous Events.
0
2
4
6
8
10
12
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 35 of 106
RPP-RPT-58298, Rev. 0
26
4.2.4.11. Total Number of Events. Figure 4-12 is a graph showing the distribution of the 67
events over time. As with the rate of miscellaneous events, the trend does not show that there
was a noticeable difference in the rate of occurrence associated with campaign start-up. The
events occur at a steady rate over the duration of the campaign. This suggests that the
construction and start-up testing processes are of sufficient quality as to not adversely impact
operations.
Figure 4-12. 241-C-112 Bulk Retrieval Total Number of Events.
0
10
20
30
40
50
60
70
80
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 36 of 106
RPP-RPT-58298, Rev. 0
27
4.2.5 241-C-112 Hard Heel Retrieval
The information documented in Appendix F was sorted into the categories listed in Section 3.0,
“Methodology.” The resulting table is in Appendix J. A total of 42 entries were made
documenting issues over 42 days of operation. Figure 4-13 shows the distribution of the events
between categories. No trends were noted within the 241-C-112 HHR information. Analyses of
each the categories are provided in the following subsections.
Figure 4-13. 241-C-112 Hard Heel Retrieval Recorded Events.
4.2.5.1. Hydraulic Leak Events. The 241-C-112 HHR campaign log books did not document
any hydraulic leak events.
4.2.5.2. Ventilation Events. Fourteen ventilation events were noted during the 241-C-112
HHR campaign. Three events were related to the POR008 seal pot level transmitter sending
erroneous high or low level signals. Two events documented the 241-AN VTP being shut down.
The remaining nine events document POR008 high differential pressure across various
components. All nine of these events appear to have been correctly indicated. Although
engineering was contacted for direction to proceed under the high differential pressure
conditions, maintenance was not called for equipment repair.
4.2.5.3. Camera and Lighting Events. The cameras and lighting were noted to have impacted
the retrieval four times during the 241-C-112 HHR campaign. The four entries document that
the Riser 6 camera was replaced twice, the riser 3 camera was replaced once, the riser 6 lights
were replaced once, and the riser 3 lights were replaced twice.
0
2
4
6
8
10
12
14
16
18
Nu
mb
er
of
Eve
nts
Event Type
RPP-RPT-58298 3/9/2015 - 7:47 AM 37 of 106
RPP-RPT-58298, Rev. 0
28
4.2.5.4. Supernatant Pump Start-Up and Shut-Down Events. The 241-C-112 HHR
campaign log books did not document any supernatant pump start-up or shut-down events.
4.2.5.5. Supernatant Pump Flow Events. The 241-C-112 HHR campaign log books did not
document any supernatant pump flow events.
4.2.5.6. Slurry Pump Flow Events. There were two instances noted of slurry pump flow
excursions. The first instance resulted from a speed sensor failure. The second entry noted a
low flow event resulting from blocking of the intake screen.
4.2.5.7. Slurry Pump Movement Events. A single event was identified where the slurry pump
was raised and then lowered. The end position of the pump appeared the same as the original
position despite being raised and lowered different amounts. The log noted that there were
several turns of slack on the pump. As neither engineering nor maintenance were notified, it is
likely that the pump was resting on solids.
4.2.5.8. Sluicer / Extended Reach Sluicer System / Arm Movement Events. One entry
documented that sluicer number 2 was unable to rotate toward the sample sleeve opening. Thirty
minutes later, sluicer number 2 was fully rotating again.
4.2.5.9. Hydraulic Temperature Events. Four hydraulic fluid temperature excursions were
noted. Three of the events were associated with the slurry pump HPU while the other was
associated with the supernatant pump HPU. These events were in addition to those instances
where the ambient temperature drove the overall pit temperatures below the range where
transfers could occur.
RPP-RPT-58298 3/9/2015 - 7:47 AM 38 of 106
RPP-RPT-58298, Rev. 0
29
4.2.5.10. Miscellaneous Events. Sixteen events occurred which did not appear to either fit
within one of the other categories or to reoccur. Figure 4-14 shows the distribution of the events
over time. The trend does not show that there was a noticeable difference in the rate of
occurrence associated with campaign start-up.
Figure 4-14. 241-C-112 Hard Heel Retrieval Miscellaneous Events.
0
2
4
6
8
10
12
14
16
18
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 39 of 106
RPP-RPT-58298, Rev. 0
30
4.2.5.11. Total Number of Events. Figure 4-15 is a graph showing the distribution of the 42
events over time. As with the rate of miscellaneous events, the trend does not show that there
was a noticeable difference in the rate of occurrence associated with campaign start-up. The
events occur at a steady rate over the duration of the campaign. This suggests that the
construction and start-up testing processes are of sufficient quality as to not adversely impact
operations.
Figure 4-15. 241-C-112 Hard Heel Retrieval Total Number of Events.
0
5
10
15
20
25
30
35
40
45
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 40 of 106
RPP-RPT-58298, Rev. 0
31
4.3 EQUIPMENT FAILURE TRENDS
There were 487 events noted in the retrieval information reviewed in this analysis. The table
tallying the events is contained in Appendix K. Figure 4-16 shows the distribution of the events
between categories. Trends were not observed on an individual retrieval basis as documented
above. Of interest in this finding is that there was not an increase in events at the start or the end
of the retrieval activities indicating that the failures are not entirely related to installation
concerns or equipment wear. Comparison of the total number of events per retrieval campaign
did not reveal any significant trends. An evaluation of the events based on the categories
described in Section 3.0, “Methodology,” is detailed in the following subsections.
Figure 4-16. Retrieval Campaign Recorded Events.
4.3.1 Hydraulic Leak Events
Hydraulic leaks were noted a total of 23 times. Nine of these events were noted during the
241-C-107 retrieval activities. No leaks were noted during the 241-C-111 bulk retrieval
activities or the 241-C-112 HHR activities.
Four of the events were related to the slurry pumps, with an additional three associated with
supernatant pumps. Twenty-one were specified as having come from the sluicer associated
equipment. Eleven of the sluicer related failures were on the MARS arm. The majority of the
hydraulic leaks resulted in the equipment continuing in service with reduced retrieval efficiency.
Notable exceptions to this trend were the two hydraulic leak entries immediately prior to the
0
20
40
60
80
100
120
Nu
mb
er
of
Eve
nts
Event Type
RPP-RPT-58298 3/9/2015 - 7:47 AM 41 of 106
RPP-RPT-58298, Rev. 0
32
failure of supernatant pump AN106-WT-P-24. Seven of the leaks were in components external
to the tank while the other 21 occurred inside the tank or tank headspace.
One particular category of equipment was noted as leaking on multiple occasions. Two of the
hydraulic leaks from the 241-C-101 bulk retrieval were from a rotary union. Further
investigation into the 241-C-101 hydraulic leaks attributed these to electro-spark damage to the
Teflon hydraulic hoses. Waste leaks from the rotary union are discussed in Section 4.3.10.
4.3.2 Ventilation Events
Eighty-six entries in the various logs were connected to the four ventilation systems – POR107,
POR03, and POR008 in 241-C Farm and the 241-AN VTP. The 241-AN VTP being shut down
affected the retrieval campaigns 12 times. POR03 was shut down in a manner that delayed
retrieval 10 times while POR008 was noted as being shut down unexpectedly 22 times. POR107
impacted retrieval 42 times.
The ventilation failure mode which occurred most frequently involved the CAM or record
samplers. The stack particulate emissions monitoring systems disrupted retrieval 32 times
during the various campaigns. Many of these alarms were due to low record sample or CAM
sample flow. It is recommended that the record sample and CAM systems and the rate of
associated alarms be further investigated to explore design improvements (e.g., a different
vacuum pump) and alternate operational strategies (e.g., increasing the rate of filter paper change
out).
The next most common alarm condition was high differential pressure across various ventilation
components including the pre-filter, heater, and filters. The majority of the high differential
pressure events were associated with the hot water use during the 241-C-112 HHR activities.
Although they did not result in alarms, visibility issues (i.e., foggy conditions within the tank)
were noted many times during the high-pressure wall washing at the end of the various retrieval
activities. Reducing the rate at which the hot water is sprayed may help reduce the number of
differential pressure alarms. Increasing the tank’s ventilation flow rate would help with the
foggy conditions; however, it may increase the rate that the filter is loaded with water, which is
causing the high differential pressure alarms.
4.3.3 Camera and Lighting Events
Camera and lighting events are fairly common and occurred during all of the evaluated retrieval
campaigns. A total 42 entries were noted where at least one of these components required
replacement. Frequently, the cameras and lights were replaced at the same time. In total, the
cameras were replaced 32 times, as were the lights. Although these camera and lighting systems
serve their function well, there may be a more cost-effective solution than continuing to replace
the failed components with the same ones currently implemented in the field.
RPP-RPT-58298 3/9/2015 - 7:47 AM 42 of 106
RPP-RPT-58298, Rev. 0
33
4.3.4 Supernatant Pump Start-Up and Shut-Down Events
Unexpected conditions during the start up or shut down of the supernatant pump were noted 13
times during the 5 retrieval campaigns. Ten times the pumps did not start or stop and were
described as having timed out. Generally the timing out was indicative of either a problem with
the signal from the control trailer to the HPU or the hydraulic fluid being too cold.
The other common failure was related to the operation of the supernatant line flow control
valves. The 241-C-107 retrieval activities had several events where the flow control valves did
not respond as anticipated which resulted in the pump shutting down for low flow conditions.
The logs indicate that the flow control valve problems were signal related and not associated
with valve or actuator failure.
4.3.5 Supernatant Pump Flow Events
There were 34 entries associated with supernatant pump flow events. Sixteen of the events were
associated with the intake screen being blocked, apparently an anticipated behavior as there was
no indication that engineering or maintenance was notified. Two of the events were documented
just prior to the failure of the AN106-WT-P-22 electric pump. Two other events were related to
operation of the flow control valves or the sluicer.
Fourteen events were related to issues with the speed sensors and the pumps’ response to
increases and decreases in speed. Evaluation of the pump speed and flow rate control devices
and the correct device to use for monitoring for each parameter during retrieval campaigns may
reduce the number of operational upsets.
4.3.6 Slurry Pump Low Flow and Plugging Events
Slurry pump low flow events were noted on 102 days. One event was attributed to the pump
timing out. There were two events clearly related to the final pump down process and four
events caused by issues with the speed sensors.
The slurry pump was shut down due to low flow on 99 days. The majority of these are during
the 241-C-107 retrieval campaign. On the 28 days where low flow shut down the pumps during
the other campaigns, one or two events were typically noted per day. During the 241-C-107
campaign, most of the days documented more than five low flow slurry pump events per shift
worked. As noted above, over one three-day period, the 241-C-107 slurry pump was shut down
due to low flow 34 times. The total number of 241-C-107 events was not tallied for this
analysis; however, it is likely that the pump was shut down on low flow more than 200 times.
The logs do not indicate that engineering or maintenance was notified, leading one to believe that
this was anticipated behavior. As the 241-C-107 campaign is the only example of the MARS
retrieval technology included within the scope of this analysis, it is not possible to determine if
the reason the waste was not being broken down into pieces small enough to be transferred was
due to the waste type or due to the retrieval technology. An evaluation of retrieval campaigns
which would include multiple retrieval efforts using the MARS technology is recommended to
RPP-RPT-58298 3/9/2015 - 7:47 AM 43 of 106
RPP-RPT-58298, Rev. 0
34
determine if the MARS equipment should include additional equipment to reduce waste chunk
sizes.
4.3.7 Slurry Pump Movement Events
The slurry pump did not adjust its position as desired on 20 occasions. Ten of these events were
associated with a build-up material under the pump, restricting its downward progress. Seven
events were recorded when the 241-C-107 slurry pump reached the lower cable limit and was
unable to be further lowered. There was one instance where the pump did not move which was
attributed to the contactor having been tripped. The final event documented an occasion where
the 241-C-107 pump dragged on the bottom of the tank when the turntable was rotated.
4.3.8 Sluicer / Extended Reach Sluicer System / Arm Movement Events
Eighteen events were noted where the sluicer apparatus did not respond as anticipated. Fifteen
of these were during the 241-C-107 campaign. As the 241-C-107 campaign is the only example
of the MARS retrieval technology included within the scope of this analysis, is it not possible to
determine if the relatively high percentage of events associated with the 241-C-107 retrieval is
due to the MARS approach or is specific to the equipment installed in the 241-C-107 retrieval
equipment.
Eight of the events were attributed to problems with the control system, with seven of them from
the 241-C-107 campaign. The 241-C-107 campaign also noted five events where the constant
tension hoist, used to maintain the cables and lines leading to the end effector and its associated
nozzles and sluicer cannon, did not respond correctly and impacted the retrieval efforts.
RPP-RPT-58298 3/9/2015 - 7:47 AM 44 of 106
RPP-RPT-58298, Rev. 0
35
4.3.9 Hydraulic Temperature Events
Thirty-five entries noted that the HPU temperature was either too high or too low. This does not
include entries when the in-pit air temperature readings were below the acceptable limit for
transfers under the waste transfer structure temperature monitoring program. Although the HPU
fluid temperatures were not at shut-down criteria levels, they were close enough that either the
system was not responding as desired or increased monitoring was required to ensure the system
was operating within the acceptable range. Figure 4-17 documents the number of hydraulic
temperature event per operating day by season. The findings suggest that the HPU cooling and
heating systems are not adequate for the temperature extremes of the depths of winter or the
height of summer.
Figure 4-17. Hydraulic Fluid Temperature Events by Season.
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
Spring/Fall Summer Winter
Eve
nts
Pe
r O
pe
rati
ng
Day
Season
RPP-RPT-58298 3/9/2015 - 7:47 AM 45 of 106
RPP-RPT-58298, Rev. 0
36
4.3.10 Miscellaneous Events
Many events did not fall into the categories listed in Section 3.0, “Methodology,” and did not
reoccur frequently enough to result in generation of a new category. There were 109 of these
entries noted during the 390 operating days. These were graphed over the number of operating
days in Figure 4-18. The graph shows a steady trend that does not change noticeably over time.
This indicates that the events are not related to campaign start-up or campaign completion.
Figure 4-18. Retrieval Activities Total Miscellaneous Events.
Five 241-C-107 system leaks were from the MARS rotary union. The 241-C-107 project
determined that these waste leaks were the result of the manufacturing methods used when
fabricating the rotary union. Corrective actions are in place for both the hydraulic hose electro-
spark issue discussed in Section 4.3.1 and the fabrication issues with the MARS rotary union.
Further monitoring of these components is recommended to ensure that the corrective actions
have addressed the issues.
0
20
40
60
80
100
120
1
13
25
37
49
61
73
85
97
10
9
12
1
13
3
14
5
15
7
16
9
18
1
19
3
20
5
21
7
22
9
24
1
25
3
26
5
27
7
28
9
30
1
31
3
32
5
33
7
34
9
36
1
37
3
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 46 of 106
RPP-RPT-58298, Rev. 0
37
4.3.11 Total Number of Events
There were 487 events noted over 390 operating days. These were graphed over the number of
operating days in Figure 4-19. The graph shows a steady trend that does not change noticeably
over time. This indicates that on average the events are not related to campaign start-up, or
campaign completion.
Figure 4-19. Retrieval Activities Total Number of Events.
The events were checked to determine if there were seasonal changes. Figure 4-20 shows the
breakdown by category of the events normalized by operating day by season. With the exception
of the hydraulic thermal events discussed in Section 4.3.9 and the ventilation seal pot transmitter
issues discussed in Section 4.2.4.2, no other significant trends were observed. The slight trend
shown by the miscellaneous events and total number of events indicating that they are more
likely to occur during the summer months may be attributed to the number of weather-related
events noted during the summer months. The miscellaneous category is where events such as
rain induced leak detection events and weather-related work/rest regimes are documented. This
skews the data indicating a seasonal trend.
0
100
200
300
400
500
600
1
13
25
37
49
61
73
85
97
10
9
12
1
13
3
14
5
15
7
16
9
18
1
19
3
20
5
21
7
22
9
24
1
25
3
26
5
27
7
28
9
30
1
31
3
32
5
33
7
34
9
36
1
37
3
Cu
mm
ula
tive
Nu
mb
er
of
Eve
nts
Operating Days
RPP-RPT-58298 3/9/2015 - 7:47 AM 47 of 106
RPP-RPT-58298, Rev. 0
38
Figure 4-20. Retrieval Activity Events by Season.
5.0 RECOMMENDATIONS
This document reviewed the various log books and reports associated with five retrieval
campaigns: 241-C-101 bulk retrieval, 241-C-107 retrieval, 241-C-111 bulk retrieval, 241-C-112
bulk retrieval, and 241-C-112 HHR. A total of 487 events over 390 operating days were noted
that impacted retrieval duration and/or equipment effectiveness. These were graphed over the
number of operating days as shown in Figure 4-19. The graph shows a steady trend that does not
change noticeably over time. This indicates that on average the events are not related to
campaign start-up, campaign completion, or seasonal changes (with the exception of the
hydraulic thermal events discussed in Section 4.3.9 and the ventilation seal pot transmitter issues
discussed in Section 4.2.4.2).
Analysis of the events results in the following recommendations.
Monitor the rotary unions in future MARS installations where the manufacturing method
corrective actions have been implemented to determine if the waste leaks have been
resolved.
The record sample and CAM systems and the rate of associated alarms should be
reviewed to determine if a different design (e.g., a different vacuum pump) and/or
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
Spring/Fall Summer Winter
Eve
nts
Pe
r O
pe
rati
ng
Day
Season
Hydraulic Leak
Vent Issues
Camera
AN Pump Startup/ Shutdown
AN Pump Flow
C Pump Flow
C Pump Movement
ERSS/ARM Movement
Hydraulic Fluid Temperature
Miscellaneous
RPP-RPT-58298 3/9/2015 - 7:47 AM 48 of 106
RPP-RPT-58298, Rev. 0
39
alternate operational strategies (e.g., increasing the rate of filter paper change out) would
reduce the number of ventilation system related outages.
The camera and lighting systems should be evaluated to determine if there may be a more
cost-effective solution than continuing to replace the failed components with the same
ones currently implemented in the field.
Signal transmission for both supernatant and slurry pump control should be reviewed.
Pump start-up, shut-down, and flow control issues were attributed to the system either
timing out or responding erratically in multiple instances.
An evaluation of the parameters and equipment used to control the supernatant and slurry
pumps (e.g., pump speed, flow control valves, flow rate indication, etc.) may lead to
changes in the operating strategy which could improve equipment responsiveness and
reduce inadvertent shut downs. The log entries frequently refer to pump speed with flow
indication and flow rate with speed indication.
An evaluation of retrieval campaigns which would include multiple retrieval efforts using
the MARS technology is recommended to determine if the MARS equipment should
include additional equipment to reduce waste chunk sizes. As the 241-C-107 campaign is
the only example of the MARS retrieval technology included within the scope of this
analysis, it is not possible to determine if the reason the waste was not being broken
down into pieces small enough to be transferred was due to the waste type or due to the
retrieval technology.
An evaluation of the HPU cooling and heating systems is recommended. The 35 entries
associated with either high or low HPU temperatures suggest that the HPU cooling and
heating systems are not adequate for the temperature extremes of the depths of winter or
the height of summer.
An evaluation of the total cost per gallon retrieved should be done for each technology.
A consistent level of detail of the log entries in the various log books is recommended
and would make reviews of this type more fruitful. The logs reviewed for this report do
not consistently identify if a system was restarted after shut down or why the shut down
occurred. Very little can be determined, for example, when the entry simply states that
the 241-AN VTP was shut-down. It is not always clear from the entries on that day if the
retrieval activities were impacted, how long the ventilation system was down, or why the
system went down in the first place.
RPP-RPT-58298 3/9/2015 - 7:47 AM 49 of 106
RPP-RPT-58298, Rev. 0
40
6.0 REFERENCES
RPP-13033, 2014, “Tank Farms Documented Safety Analysis,” Washington River Protection
Solutions, LLC, Richland, Washington.
RPP-RPT-52480, 2012, “Retrieval Completion Report for Modified Sluicing of Tank
241-C-112,” Washington River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-54959, 2014, “Single-Shell Tank 241-C-107 Hard Heel Retrieval Completion Report,”
Washington River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-55036, 2013, “Summary Evaluation of ERSS Hydraulic Hose Failures,” Washington
River Protection Solutions, LLC, Richland, Washington.
RPP-RPT-55573, 2013, “Retrieval Completion Report for Modified Sluicing of Tank 241-C-101
Using Extended Reach Sluicing and High Pressure Water,” Washington River Protection
Solutions, LLC, Richland, Washington.
RPP-RPT-56900, 2014, “Single-Shell Tank 241-C-112 Hard Heel Retrieval Completion Report,”
Washington River Protection Solutions, LLC, Richland, Washington.
WRPS-PER-2012-1321, “Evidence of Previous leakage from the Rotary Union on the C-107
MARS Unit”
WRPS-PER-2012-1346, “C-107 MARS Containment Box Rotary Union Drip Leak”
RPP-RPT-58298 3/9/2015 - 7:47 AM 50 of 106
RPP-RPT-58298, Rev. 0
A-1
APPENDIX A
241-C-101 BULK RETRIEVAL ACTIVITIES EVENTS
RPP-RPT-58298 3/9/2015 - 7:47 AM 51 of 106
RPP-RPT-58298, Rev. 0
A-2
241-C-101 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
12/10/2012 AN01A-WT-TE-302 / -303 low temperature – p 1
Lines flushed – p 1 -
Low temperatures (below the 50 °F shutdown limit) – AN01A
No issues reported. Cold weather causing low temperatures
12/11/2012 IH equipment issues – management directed shut down – p 3 IH equipment issues – p 120 IH equipment issues No issues reported. Site wide equipment issues
12/12/2012
No activities this date
-
No retrieval operations performed
New Red Arrow: Entry into SST & DST Tank Farms is prohibited except for HPT and NCO rounds and routines
No issues reported.
-
12/13/2012 No activities this date - Cleared the Red Arrow regarding tank farm entry No issues reported. -
12/14/2012 No activities this date - Completed pre-requisites No issues reported. -
12/15/2012 No activities this date - - No issues reported. -
12/16/2012 No activities this date - - No issues reported. -
12/17/2012 No activities this date - POR107 power supply and CAM issues No issues reported. POR107 CAM issues
12/18/2012 POR107 CAM issues – p 4 Pumps active – p 130 POR107 power supply and CAM issues No issues reported. POR107 CAM issues
12/19/2012 Low temp AN – p 4
AN VTP CAM issues – p 4
Pumps active – p 131 AN VTP CAM issues No issues reported. AN VTP issues
12/20/2012 Slurry pump up and down – p 5
POR350 hydraulic leak – p 5
Pumps active – p 132 POR350 hydraulic leak No issues reported. Hydraulic leak
12/21/2012 No issues reported. Pumps active – p 135 No issues reported. No issues reported. -
12/22/2012 No activities this date - - No issues reported. -
12/23/2012 No activities this date - - No issues reported. -
12/24/2012 No activities this date - - No issues reported. -
12/25/2012 No activities this date - - No issues reported. -
12/26/2012 POR350 high temperature – p 7 Pumps active – p 139 No issues reported. No issues reported. Hydraulic unit temperature issues
12/27/2012 POR350 high temperature – p 7
Slurry pump up and down – p 7
Pumps active – p 139 No issues reported. No issues reported. Hydraulic unit temperature issues
12/28/2012 POR309 high temperature – p 8/9
Riser 3 light failed – p 9
C-101 light failed – p 140 POR309 high temperature
Riser 3 light failed
No issues reported. Hydraulic unit temperature issues
Camera issues
12/29/2012 No activities this date - - No issues reported. -
12/30/2012 No activities this date - - No issues reported. -
12/31/2012 No activities this date
- Riser 3 and Riser 8 camera and lights changed
out
No issues reported. -
01/01/2013 No activities this date - - No issues reported. -
01/02/2013 POR309 and POR307 low temperature – p 9
AN VTP shut down – FI/FSL-175 out of service – p 9
AN VTP issues – p 143 AN Farm pressurization alarm is out of service
AN01A-WT-FI/FSL-175 malfunction
No issues reported. Hydraulic unit temperature issues
01/03/2013 FI/FSL-175 issues – p 10
AN VTP down – CAM issues – p 10 - AN Farm CAM high sample flow alarm
No issues reported. AN VTP issues
01/04/2013 Flush of transfer lines – p 11 - Transfer line flush No issues reported. -
01/05/2013 No activities this date - - No issues reported. -
01/06/2013 No activities this date - - No issues reported. -
01/07/2013 No issues reported - No issues reported. No issues reported. -
01/08/2013 Slurry pump up and down – p 12 Pumps active – p 151 Slurry pump screen plugging No issues reported. Slurry pump low flow
01/09/2013 Slurry pump up and down – p 12
Unable to move slurry pump – p 13
Pumps active – p 152 Slurry pump did not lower
Slurry pump screen plugging
No issues reported. Slurry pump low flow
Slurry pump movement issues
01/10/2013 Slurry pump up and down – p 13 Pumps active – p 153 Slurry pump screen plugging No issues reported. Slurry pump low flow
01/11/2013
Supernatant pump up and down – p 14
POR350 pressure dropping – p 14
Slurry pump up and down – p 14
Pumps active – p 154 Slurry pump screen plugging No issues reported. Slurry pump low flow
Supernatant pump low flow
01/12/2013 No activities this date - - No issues reported. -
01/13/2013 No activities this date - - No issues reported. -
01/14/2013 POR107 seal pot cold temperatures issues – p 17
Sluicer #1 dose rate issues – p 17
Pumps active – p 157
POR107 shut down – seal pot level high – p 157
No issues reported. No issues reported. POR107 seal pot issues
Dose rate problems
RPP-RPT-58298 3/9/2015 - 7:47 AM 52 of 106
RPP-RPT-58298, Rev. 0
A-3
241-C-101 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
01/15/2013
Slurry pump up and down – p 18
Sluicer #1 dose rate issues – p 18
POR309 high temperature – p 18
Pumps active – p 158
Slurry pump screen plugging
No issues reported. Slurry pump low flow
Dose rate problems
Hydraulic unit temperature issues
01/16/2013
Slurry pump up and down – p 19
AN101 camera replaced – p 19
POR350 high pressure – p 19
Pumps active – p 159 No issues reported. No issues reported. Slurry pump low flow
Camera issues
Hydraulic unit pressure issues
01/17/2013 Slurry pump screen plugging issues – p 20 - Slurry pump screen plugging No issues reported. Slurry pump low flow
01/18/2013 POR314 dose issues – p 21 Pumps active – p 161 No issues reported. No issues reported. Dose rate problems
01/19/2013 No activities this date - - No issues reported. -
01/20/2013 No activities this date - - No issues reported. -
01/21/2013
No issues reported.
-
No issues reported. ~41,000 gal of tank 241-AN-101 (AN-101) supernate was added to tank 241-C-101 to soak the waste in an attempt to soften the solids
-
01/22/2013 Sluicer #1 temperatures low / heater not plugged in – p 24 POR107 shut down – p 165 No issues reported. - Hydraulic unit temperature issues
01/23/2013
POR107 exhauster secured – p 25 AN VTP issues – p 166 Outage begins for AN Farm ventilation upgrades in preparation for the implementation of Safety Basis amendment tor safety significant designation for DST primary tank ventilation systems.
Restart of C-101 retrieval expected ~2/11/13.
-
AN VTP down for planned activities
No activities until …
02/11/2013 No activities this date - Riser-003 & Riser-008 cameras replaced - Camera issues
02/12/2013 No activities this date POR107 shut down heater temperature issues –
p 188 POR107 shut down due to smoke coming from
glycol heater. -
POR107 heater issues
02/13/2013 No activities this date - POR107 glycol heater troubleshooting - POR107 heater issues
02/14/2013 No activities this date POR107 shut down heater temperature issues –
p 189 POR107 glycol heater troubleshooting, switching
to POR03 -
POR107 heater issues
02/15/2013 No activities this date - Prerequisites and startup checklists - -
02/16/2013 No activities this date - - - -
02/17/2013 No activities this date - - - -
02/18/2013 No activities this date - - - -
02/19/2013 C-101 Enraf issues – p 25 - Prerequisites and startup checklists - -
02/20/2013
POR03 exhauster used for C-101 – p 25
C-101 pressure set point issues – 25
Supernatant pump low flow up and down – p 26
-
Supernatant pump screen plugging No issues reported. Supernatant pump low flow
Programming issues
02/21/2013
POR03 exhauster used for C-101 – p 27
Low inlet temperature (TI-176)
Slurry pump low flow up and down – p 27
Pumps active – p 198 Slurry pump screen plugging No issues reported. POR03 heater issues
Slurry pump low flow
02/22/2013 POR03 exhauster used for C-101 – p 28
Slurry pump low flow up and down – p 28
Pumps active – p 198 Slurry pump screen plugging No issues reported. Slurry pump low flow
02/23/2013 No activities this date - - No issues reported. -
02/24/2013 No activities this date - - No issues reported. -
02/25/2013
POR03 exhauster used for C-101 – p 29
POR307 sluicer HPU hydraulic fluid level decreasing – p 29
Sluicer #1 hydraulic fluid leak on the nozzle transverse function – p 29
Pumps active – p 202 Sluicer #1 is out of service due to a hydraulic fluid leak on the nozzle transverse function.
Hydraulic fluid was observed to be leaking from the nozzle transverse function of ERSS #1 in riser 7
Hydraulic fluid leaks
02/26/2013
POR03 exhauster used for C-101 – p 30
Hydraulic fluid added to POR307 – p 30
Slurry pump low flow up and down – p 30
Supernatant pump increase/decrease control issues – p 30
Pumps active – p 203 Slurry pump screen plugging No issues reported. Slurry pump low flow
Supernatant pump controls issue
Hydraulic fluid leaks
02/27/2013 No activities this date
- AN-106 leak check being performed using AN-
101 pit
No issues reported. -
RPP-RPT-58298 3/9/2015 - 7:47 AM 53 of 106
RPP-RPT-58298, Rev. 0
A-4
241-C-101 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
02/28/2013
POR107 exhauster used for C-101 – p 31
POR107 CAM hi flow set point issues – p 31
Slurry pump low flow up and down – p 31
Pumps active – p 206 Exhausting with POR107 No issues reported. Slurry pump low flow
POR107 CAM set point issues
03/01/2013
POR107 exhauster used for C-101 – p 32
POR107 CAM hi flow set point issues – p 32
Riser 3 light issues – p 33
POR309 slight hydraulic fluid level leak – p 33
Pumps active – p 206
Slurry pump did not lower
Slurry pump hydraulic leak a POR309 flange
No issues reported. Light issues
POR107 CAM set point issues
Hydraulic fluid leak
03/02/2013
POR107 exhauster used for C-101 – p 33
Riser 3 light issues – p 33
Ahlberg light use restricted – p 33
- -
No issues reported. Camera and light issues
03/03/2013 No activities this date - - No issues reported. -
03/04/2013 No activities this date
- Stop work was issued to restrict all use of
Ahlberg lights
No issues reported. -
03/05/2013 POR107 exhauster used for C-101 – p 34 - - No issues reported. -
03/06/2013 POR107 exhauster used for C-101 – p 34
Riser 3 and riser 8 light issues – p 34 - -
No issues reported. Light issues
03/07/2013 POR107 exhauster used for C-101 – p 35
Riser 3 and riser 8 lights replaced, riser 8 camera replaced – p 35
Pumps active – p 11 No issues reported. No issues reported. Light issues
Camera issues
03/08/2013
POR107 exhauster used for C-101 – p 35
Slurry pump low flow up and down – p 36
POR309 temperature and fan issues – p 36
POR107 secured – p 13 Sluicer #1 hydraulic lines to the sluicer’s transverse nozzle function were disconnected to prevent further loss of hydraulic fluid
Hydraulic lines transverse movement of the ERSS #1 nozzle were disconnected, ERSS #1 nozzle operation restored in locked position..
Slurry pump low flow
Hydraulic unit temperature issues
03/09/2013 No activities this date - - No issues reported. -
03/10/2013 No activities this date - - No issues reported. -
03/11/2013
POR107 exhauster used for C-101 – p 36
Slurry pump low flow up and down – p 37
Odor issues around AN-101 – p 16/17
Pumps active – p 18
POR107 shut down – p 18
No issues reported. No issues reported. Slurry pump low flow
03/12/2013
POR107 exhauster used for C-101 – p 37
POR309 HPU disconnect reset – p 37
Camera in Riser 8 failure – p 37 -
Sluicer #2 mast transverse is operating sporadically/slowly in the counter clockwise direction
Riser 8 camera stopped
No issues reported. Camera issues
Hydraulic unit temperature issues
03/13/2013 POR107 exhauster used for C-101 – p 38
Slurry pump low flow up and down – p 38
Pumps active – p 20 Slurry pump screen plugging No issues reported. Slurry pump low flow
03/14/2013 POR107 exhauster used for C-101 – p 39
POR107 low flow alarm issues – p 39
Pumps active – p 21 POR107 low flow alarm issues No issues reported. POR107 low flow issues
03/15/2013 POR107 exhauster used for C-101 – p 40 - No issues reported. No issues reported. -
03/16/2013 No activities this date - - No issues reported. -
03/17/2013 No activities this date - - No issues reported. -
03/18/2013 POR107 exhauster used for C-101 – p 40
-
No issues reported. Tank 241-C-101 retrieval operations were suspended while resources were shifted to tank 241-C-107 retrieval operations.
-
03/19/2013 POR107 exhauster used for C-101 – p 41
Supernatant and slurry lines and pumps flushed – p 41 -
Flush of the transfer lines, sluicers, and pumps performed
- -
No activities until …
05/05/2013 No activities this date Pumps active – p 98 - - -
05/06/2013 No activities this date - - - -
05/07/2013 No activities this date - - - -
05/08/2013 No activities this date - - - -
05/09/2013 POR107 exhauster used for C-101 – p 42
Riser 8 and riser 3 cameras and lights installed – p 42 -
New cameras and Ahlberg lights were installed in risers 3 and 8.
- Light issues
Camera issues
05/10/2013 No activities this date - - - -
05/11/2013 No activities this date - - - -
RPP-RPT-58298 3/9/2015 - 7:47 AM 54 of 106
RPP-RPT-58298, Rev. 0
A-5
241-C-101 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
05/12/2013 No activities this date - - - -
05/13/2013 POR107 exhauster sample pump issues– p 43
POR107 exhauster used for C-101 – p 43 -
Slurry distributor and supernatant pump adjustments
- POR107 sample pump issues
05/14/2013
POR107 exhauster used for C-101 – p 43
Sluicer #1 controls appear reversed (up is down, etc.) – p 44
Slurry pump low flow up and down – p 44
-
No issues reported. No issues reported. Slurry pump low flow
Sluicer #1 control issues
05/15/2013
POR107 exhauster used for C-101 – p 45
POR309 temp high – p 45
POR307 temp high, low oil level – p 45
-
Slurry pump HPU temperature high
Sluicer HPU POR307 temperature high, low oil levels
Hydraulic fluid began leaking from the nozzle elevation function of ERSS #2 in riser 2
Hydraulic unit temperature issues
05/16/2013
POR307 oil added – p 46
POR107 exhauster used for C-101 – p 46
Sluicer #2 leakage at rotary union during transverse functions of the wrist (drip wise) and up and down motions of nozzle (steady stream) – p 46
No retrieval activities per management direction – p 46
POR107 shut down – p 100 Sluicer HPU POR307 oil added Nozzle elevation function of ERSS #2 in riser 2 hydraulic lines disconnected.
Hydraulic system leaks – rotary union
05/17/2013 POR107 exhauster used for C-101 – p 46
Sluicer #2 nozzle functions to be disconnected due to leaks – p 47
- Leak observed from fitting on line that controls
ERSS #2 wrist up/down motion coming from the rotary union area
Tank C-101 retrieval operations were suspended while resources were shifted to tank 241-C-107 retrieval operations.
Hydraulic system leaks – rotary union
05/18/2013 No activities this date - - - -
05/19/2013 No activities this date - - - -
05/20/2013 No activities this date
- Resources will be shifted from tank C-101 to tank
C-107. - -
No activities until …
05/31/2013 POR132 water skid leaking water to ground from tank overfill
– p 47
POR107 exhauster used for C-101 – p 47
- Prerequisites and startup checklists
- Water system overflow
06/01/2013 No activities this date - - - -
06/02/2013 No activities this date - - - -
06/03/2013 Supernatant pump low flow up and down – p 48
POR307 temperature high – p 48 -
No issues reported. No issues reported. Supernatant pump low flow
Hydraulic unit temperature issues
06/04/2013 POR107 CAM high flow rate issues – p 49 Pumps active – p 121 POR107 CAM flow rate issues No issues reported. POR107 CAM flow issues
06/05/2013
POR107 exhauster used for C-101 – p 50
Slurry pump low flow up and down – p 51
Supernatant pump low flow up and down – p 51
POR307 high temperature issues – p 51
POR309 low pressure issues – p 51
Pumps active – p 123 Slurry pump screen plugging
Supernatant pump screen plugging
Slurry pump HPU POR309 showing low pressure
ERSS HPU POR307 temperature running high
ERSS HPU POR307 low hydraulic fluid – no visible leaks
Hydraulic fluid levels in the sluicer hydraulic power units began to drop
Supernatant pump low flow
Slurry pump low flow
Hydraulic unit temperature issues
06/06/2013
No issues reported.
- ERSS #1 elevation function for the nozzle is
leaking – hydraulic lines to this function disconnected
The lines to the nozzle elevation function of ERSS #1 were disconnected
Hydraulic system leaks
06/07/2013
POR107 exhauster used for C-101 – p 52
Supernatant and slurry pumps and lines flushed – p 53
POR309 flange hydraulic fluid leak – p 54
Pumps active – p 125 Slurry pump HPU POR309 motor flange hydraulic fluid leak
No issues reported. Hydraulic system leaks
06/08/2013 No activities this date - - No issues reported. -
06/09/2013 No activities this date - - No issues reported. -
06/10/2013 POR307 high temperature issues – p 54 Pumps active – p 128 No issues reported. No issues reported. Hydraulic unit temperature issues
06/11/2013 POR307 insulation removed – p 55 - No issues reported. No issues reported. Hydraulic unit temperature issues
06/12/2013 Slurry pump won’t lower – p 55
Sluicer #2 wrist function leak – p 56 -
Sluicer #2 nozzle transverse function hydraulic fluid leak
The nozzle transverse function of ERSS #2 appeared to begin leaking
Slurry pump movement issues
Hydraulic fluid leaks
06/13/2013 No issues reported. Pumps active – p 133 Sluicer #2 nozzle transverse function hydraulic
lines disconnected The nozzle transverse function hydraulic lines of
ERSS #2 were disconnected -
06/14/2013 POR307 high temperature issues – p 57 Pumps active – p 136 ERSS HPU POR307 low hydraulic fluid – no
visible leaks
No issues reported. Hydraulic unit temperature issues
06/15/2013 No activities this date - - No issues reported. -
RPP-RPT-58298 3/9/2015 - 7:47 AM 55 of 106
RPP-RPT-58298, Rev. 0
A-6
241-C-101 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
06/16/2013 No activities this date Pumps active – p 140 - No issues reported. -
06/17/2013 POR307 hydraulic fluid added – p 57
Power loss with lightening in the area – p 58
Transfer line flushing – p 144 ERSS HPU POR307 low hydraulic fluid – no visible leaks
No issues reported. Weather related issues
06/18/2013 C-102 ERSS hydraulic lines disconnected – p 59
Supernatant and slurry lines flushed – p 59
Transfer line flushing – p 145 ERSS HPU POR307 low hydraulic fluid – no visible leaks
Transfer line flushes performed
No issues reported.
-
06/19/2013 POR307 hydraulic fluid level constant – p 59 Pumps active – p 146
Transfer line flushing – p 146
C-102 hydraulic lines isolated – POR307 hydraulic level stabilized
Riser 3 camera deteriorating
No issues reported. Camera issues
06/20/2013
No activities this date
-
Riser 3 camera replaced
C-101 high pressure water manifold installation activities
Tank C-101 retrieval operations were suspended while manifolds for the connection of high-pressure water to the tank C-101 ERSSs was completed and tested.
Camera issues
06/21/2013 No activities this date - - - -
06/22/2013 No activities this date - - - -
06/23/2013 No activities this date - - - -
06/24/2013 No activities this date
- C-101 high pressure water manifold installation
activities - -
06/25/2013 No activities this date - - - -
06/26/2013 No activities this date - - - -
06/27/2013 No activities this date - - - -
06/28/2013 No activities this date - - - -
06/29/2013 No activities this date - - - -
06/30/2013 No activities this date - - - -
07/01/2013 No activities this date - - - -
07/02/2013 No activities this date
- C-101 high pressure water manifold testing
issues - -
07/03/2013 No activities this date - - - -
07/04/2013 No activities this date - - - -
07/05/2013 No activities this date - - - -
07/06/2013 No activities this date - - - -
07/07/2013 No activities this date - - - -
07/08/2013 No activities this date - Prerequisites and startup checklists - -
07/09/2013
POR137 flow indication issues – p 60
POR307 high temperature issues – p 60
High heat working condition issues – p 60/61
-
No issues reported. No issues reported. Weather related issues
Hydraulic unit temperature issues
07/10/2013 High heat working condition issues – p 62 - No issues reported. No issues reported. Hydraulic unit temperature issues
07/11/2013 Riser 3 camera issues – p 62
POR307 high temperature issues – p 62 -
No issues reported. No issues reported. Camera issues
Hydraulic unit temperature issues
07/12/2013 No activities this date - - No issues reported. -
07/13/2013 No activities this date - - No issues reported. -
07/14/2013 No activities this date - - No issues reported. -
07/15/2013 No activities this date - No issues reported. No issues reported. -
07/16/2013 No issues reported.
- Prerequisites and startup checklists
AN01A LDE wiring insulation melted/ burnt
No issues reported. Wiring issues
07/17/2013 No activities this date - AN01A LDE wiring issues No issues reported. Wiring issues
07/18/2013 No activities this date - No issues reported. No issues reported. -
07/19/2013 No activities this date - - No issues reported. -
07/20/2013 No activities this date - - No issues reported. -
07/21/2013 No activities this date - - No issues reported. -
07/22/2013 AN VTP issues – p 63 - No issues reported. No issues reported. -
RPP-RPT-58298 3/9/2015 - 7:47 AM 56 of 106
RPP-RPT-58298, Rev. 0
A-7
241-C-101 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
07/23/2013 High heat working condition issues – p 64/65
AN VTP low CAM sample flow – p 65
Pumps active – p 203 AN VTP CAM sample flow low issues No issues reported. AN VTP CAM issues
07/24/2013 High heat working condition issues – p 66
POR307 high temperature issues – p 66
Pumps active – p 205 No issues reported. No issues reported. Weather related issues
Hydraulic unit temperature issues
07/25/2013
Riser 3 and 8 cameras replaced – p 66
C-101 demister differential pressure issues – p 67
High pressure washing causing visibility issues – p 68
Pumps active – p 208 New cameras and lights were installed in risers 3 and 8.
High pressure system used – down for fogging High-pressure water operation began
Camera issues
Demister pressure issues
Visibility issues
07/26/2013
High heat working condition issues – p 69
POR307 high temperature issues – p 69
High pressure washing causing visibility issues – p 69/70
AN VTP issues – p 209 High pressure system used – down for fogging No issues reported. Weather related issues
Hydraulic unit temperature issues
Visibility issues
07/27/2013
No activities this date AN VTP issues – p 210 -
Retrieval operations were suspended while quarterly electrical cord inspections were performed at the 241-C Tank Farm.
-
No activities until …
08/07/2013 High heat working condition issues – p 71
POR137 leak detector jumper needed – p 71 -
Prerequisites and startup checklists
C-112 TVFM issues affecting C-101 operations -
Weather related issues
Prerequisites issues
08/08/2013
High pressure water work – p 71
POR307 high temperature – p 72
High pressure washing causing visibility issues – p 72
-
No issues reported.
High-pressure water operations
Hydraulic unit temperature issues
Visibility issues
08/09/2013 High pressure water work – p 73 Pumps active – p 233 No issues reported. High-pressure water operations -
08/10/2013 No activities this date - - No issues reported. -
08/11/2013 No activities this date - - No issues reported. -
08/12/2013 Riser 8 camera issues – p 74/75
High heat working condition issues – p 75
Pumps active – p 240 No issues reported. No issues reported. Camera issues
Weather related issues
08/13/2013 High heat working condition issues – p 75/76 Pumps active – p 241 No issues reported. No issues reported. Weather related issues
08/14/2013 High heat working condition issues – p 75/76/77
Slurry pump would not lower – p 77
Pumps active – p 244/246 The hydraulic lines to the nozzle functions of ERSS #2 were reconnected to reposition the nozzle
The hydraulic lines to the nozzle functions of ERSS #2 were reconnected to reposition the nozzle.
Slurry pump movement issues
Weather related issues
08/15/2013 POR132 out of service – p 78
- POR132 water skid out of service – directed to
shut down
No issues reported. Water system issues
08/16/2013 POR107 used for C-101 – p 79
Riser 3 and riser 8 camera/light issues – p 79 - Riser 3 and 8 camera issues
No issues reported. Camera issues
08/17/2013 No activities this date - - No issues reported. -
08/18/2013 No activities this date - - No issues reported. -
08/19/2013 Riser 3 and riser 8 camera/light issues – p 79
High heat working condition issues – p 80 -
New camera and lights installed in riser 8
New lights installed in riser 3
No issues reported. Camera issues
Weather related issues
08/20/2013
High pressure water work – p 80
V-600 and PRV-200 leaks – p 80/82
Pumps active – p 258 HPWS #2 water leak at V-600 and PRV-200
The hydraulic lines to the nozzle functions of ERSS #1 were reconnected to reposition the nozzle
Additional water spray leak at a PRV
The hydraulic lines to the nozzle functions of ERSS #1 were reconnected to reposition the nozzle
High-pressure water operations
Water leaks
08/21/2013
PI-404 issues – p 82
High pressure washing causing visibility issues – p 83
Dose issues at HIHTL to Sluicer #1 – p 83
Pumps active – p 259
High dose rates – p 260
High rad in C farm, HPT management directs shutdown
High-pressure water operations
Tank wall sluicing
Dose rate issues
Visibility issues
08/22/2013
No activities this date Red arrow. Do not operate C-101 high pressure water system until event investigation and path forward is developed – p 261/262
No retrieval operations were performed – event investigation to determine the cause of the elevated radiation readings.
No retrieval operations were performed – event investigation to determine the cause of the elevated radiation readings.
Dose rate issues
08/23/2013
No activities this date
- No retrieval operations were performed – event
investigation to determine the cause of the elevated radiation readings.
- Dose rate issues
08/24/2013 No activities this date - - - -
08/25/2013 No activities this date - - - -
08/26/2013
No issues reported.
- No retrieval operations were performed – event
investigation to determine the cause of the elevated radiation readings.
- Dose rate issues
RPP-RPT-58298 3/9/2015 - 7:47 AM 57 of 106
RPP-RPT-58298, Rev. 0
A-8
241-C-101 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
08/27/2013
No activities this date
- No retrieval operations were performed – event
investigation to determine the cause of the elevated radiation readings.
- Dose rate issues
08/28/2013
No activities this date Red arrow cleared to allow access to C farm – p 274
No retrieval operations were performed – event investigation to determine the cause of the elevated radiation readings.
- Dose rate issues
08/29/2013
No activities this date
-
Closed red arrow restricting access into C-Farm without R&C Manager approval based upon ISR results and communications from Senior Management.
- -
08/30/2013 No activities this date - - - -
08/31/2013 No activities this date - - - -
09/01/2013 No activities this date - - - -
09/02/2013 No activities this date - - - -
09/03/2013 No activities this date - Hot water skid POR357 OAT Hot water skid POR357 OAT
09/04/2013 No activities this date Red arrow cleared to allow retrieval – p 290 Hot water skid POR357 OAT delayed due to
weather issues -
Weather related issues
09/05/2013 No activities this date - Hot water skid POR357 OAT - -
09/06/2013 No issues reported. Pumps active – p 294 Flush of the transfer lines performed No issues reported. -
09/07/2013 No activities this date - - No issues reported. -
09/08/2013 No activities this date - - No issues reported. -
09/09/2013
High pressure pump #5 leak – p 85
High pressure washing causing visibility issues – p 85
High heat working condition issues – p 85
Slurry pump low flow up and down – p 85
-
No issues reported. No issues reported. Hydraulic fluid leaks
Visibility issues
Weather related issues
Slurry pump low flow issues
09/10/2013 High pressure washing causing visibility issues – p 86/87 - No issues reported. No issues reported. Visibility issues
09/11/2013 Slurry pump low flow up and down – p 87
Volume displacement activities – p 88 -
Performed a liquid displacement measurement of the waste remaining in the tank.
Performed a liquid displacement measurement of the waste remaining in the tank.
Slurry pump low flow issues
09/12/2013 Flushing activities – p 90
- Performed a liquid displacement measurement of
the waste remaining in the tank. Performed a liquid displacement measurement of
the waste remaining in the tank. -
No activities until …
09/24/2013 No issues reported. - - - -
09/25/2013 No activities this date - - - -
09/26/2013 No activities this date - - - -
09/27/2013 No activities this date - - - -
09/28/2013 No issues reported. - - - -
09/29/2013 No issues reported. - Performed rinse of C-101 wastes. - -
09/30/2013 No issues reported. - Final pump down of C-101. - -
RPP-RPT-58298 3/9/2015 - 7:47 AM 58 of 106
RPP-RPT-58298, Rev. 0
B-1
APPENDIX B
241-C-107 RETRIEVAL ACTIVITIES EVENTS
RPP-RPT-58298 3/9/2015 - 7:47 AM 59 of 106
RPP-RPT-58298, Rev. 0
B-2
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
09/27/2011
Slurry pump lower cable limit issues – p 1
Slurry pump enable mess-ups – p 1
Supernatant pump bell housing leak – p 2
Start of retrieval work – p 238
Possible AN-106 transfer pump bell housing leak – p 239
-
No issues reported. Cable limit issues
Waste leak
09/28/2011 No activities this date - - No issues reported. -
09/29/2011 Speed sensor issues on the slurry pump – p 2
- - No issues reported. Procedure issues
Set point issues
09/30/2011 No activities this date - - No issues reported. -
10/01/2011 No activities this date - - No issues reported. -
10/02/2011 No activities this date - - No issues reported. -
10/03/2011 No activities this date - - No issues reported. -
10/04/2011 No activities this date - - No issues reported. -
10/05/2011 No activities this date Hydraulic fluid spill during install – p 248 - No issues reported. -
10/06/2011 POR240 Sump pump – p 3
ARM problems – p 3 - -
No issues reported. Programming issues
10/07/2011 Slurry pump fault alarm / HPU – p 4 - - No issues reported. Procedure / electrical line-up issues
10/08/2011 No activities this date - - No issues reported. -
10/09/2011 No activities this date - - No issues reported. -
10/10/2011 ARM will not lower – p 5
No local indication for slurry pump therefore no speed protection – p 5
Removed admin locks – p 253
Problems with Slurry pump HPU speed sensor – p 253
-
No issues reported. Failed speed sensors
ARM issues
10/11/2011 Speed sensor issues on the slurry pump – p 6
Shut down / slurry low flow multiple times – p 6, p 7
Pumps active – p 255 -
No issues reported. Failed speed sensors
Slurry pump low flow
10/12/2011 Shut down / slurry low flow multiple times – p 7, p 8 Pumps active – p 256 - No issues reported. Slurry pump low flow
10/13/2011 No activities this date - - No issues reported. -
10/14/2011 No activities this date - - No issues reported. -
10/15/2011 No activities this date - - No issues reported. -
10/16/2011 No activities this date - - No issues reported. -
10/17/2011
POR107 Shutdown, record sampler – p 9
Retrieval Prerequisites underway – p 9
C-108 activities concurrent – p 261
POR107 Vent shutdown – p 261
POR107 shutdown due to record sample low flow – p 262
-
No issues reported. Record sampler low flow
10/18/2011 POR107 restarted, pumps restarted – p 10
Slurry Pump shut down low flow – p 10
POR107 restarted, pumps restarted – p 262 -
No issues reported. Slurry pump low flow
10/19/2011
Supernatant pump low flow – p 11
POR107 CAM Issues – p 11
POR214 leaking hydraulic fluid – p 11/12
- -
No issues reported. Slurry pump low flow
CAM low flow
Fitting leak
10/20/2011
Slurry pump shut down low flow – p 13
POR107 shut down low sample flow, restarted – p 13
Cameras failed – p 14
Red arrow entry – don't restart if down >2 hr due to particulate formation/ expansion of freezing issue to include precipitation – p 265
POR107 shutdown due to sample pump failure, restarted – p 266
Red arrow entry – In tank camera issues shutting down transfers – p 266
-
No issues reported. Slurry pump low flow
Record sampler vacuum pump failure
Camera issues
10/21/2011 No activities this date C-108 activities begin – p 267 - No issues reported. -
10/22/2011 No activities this date - - No issues reported. -
10/23/2011 No activities this date AN-106 to AP-104 transfer – no C-107 – p 268 - No issues reported. -
10/24/2011 No activities this date - - No issues reported. -
10/25/2011
No activities this date POR-107 accidental shutdown, restart – p 271, 272
C-108 concurrent p 272
-
No issues reported.
-
10/26/2011 POR107 problems – p 13 POR-107 shutdown, planned – p 273 - No issues reported. Record sampler low flow
RPP-RPT-58298 3/9/2015 - 7:47 AM 60 of 106
RPP-RPT-58298, Rev. 0
B-3
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
10/27/2011
AN-106 camera failure – p 14
AN-106 pump winch stuck – p 14
Slurry pump shut down low flow – p 15
POR-107 restarted, planned – p 273
C-108 concurrent- p 273
C-107 starting – p 274
-
No issues reported. Slurry pump low flow
Camera issues
Winch issues
10/28/2011
Slurry pump shutdown low flow / restart – p 15
Supernatant pump shutdown low flow / restart – p 15
Supernatant pump out on high amps – p 16
High pressure on ARM HPU – p 16
Installed admin locks – p 274
-
Retrieval was halted by failure of the electric supernatant pump AN06A-WT-P-022 in 241-AN-106.
Replacement electric pump AN06A-WT-P-023 failed on the test stand.
Slurry pump low flow
ARM HPU issues
AN06A pump issues
10/29/2011 No activities this date - - - -
10/30/2011 No activities this date - - - -
10/31/2011 No activities this date - - - -
11/1/2011 No activities this date - - - -
11/2/2011 POR104-WT-FCV-102 indication failure – p 17 - - - Valve position indication issues
11/3/2011 Pump bump – p 17 - - - -
No activities until …
01/25/2012 Supernatant pump level confirmed – p 17 - - - -
No activities until …
04/20/2012 POR240 sump pumped – p 18
POR107 HMI issues – p 18 - - -
Programming issues
No activities until …
05/01/2012 POR104 sump pumped – p 18 - - - -
No activities until …
05/09/2012 Retrieval Prerequisites underway – p 18 - - - -
05/10/2012 AN-106 pump issues – p 19
POR240-WT-FCV-161 and FCV-162 issues – p 20 - - -
Valve position indication issues – causes pump starting issues
No activities until …
05/17/2012 AN-106 pump issues – p 21
POR240-WT-FCV-161 and FCV-162 issues – p 21 - - -
Valve position indication issues – causes pump starting issues
05/18/2012 POR240-WT-FCV-161 and FCV-162 issues – p 22
- - - Valve position indication issues – causes pump
starting issues
05/19/2012 No activities this date - - - -
05/20/2012 No activities this date - - - -
05/21/2012 POR240-WT-FCV-161 and FCV-162 issues – p 22
- - - Valve position indication issues – causes pump
starting issues
05/22/2012 POR107 exhauster issues – p 23 - - - Exhauster issues
05/23/2012 Changed from POR107 to POR03 – p 23 POR03 started, pumps started – p 201 - - -
05/24/2012
AN-106 annulus LDA – p 25
Constant tension hoist issue (ARM) – p 25
ARM motion issues – p 25
AN-106 annulus LDE activates, transfers shut down, restarted – p 202 -
No issues reported. Constant tension hoist issues
05/25/2012 No issues this date AN-106 pump on HPU high return oil pressure –
p 203 -
No issues reported. -
05/26/2012 No activities this date - - No issues reported. -
05/27/2012 No activities this date - - No issues reported. -
05/28/2012 No activities this date - - No issues reported. -
05/29/2012
Slurry pump speed sensor issues – p 27
Supernatant pump rate issues – p 27
Slurry pump low flow issues – p 27
POR107 started – p 205
-
No issues reported. Slurry pump low flow
AN06A pump flow rate control issues
05/30/2012 Supernatant pump rate issues – p 28
POR107 shut down low CAM sample flow – p 29
Vapors in C farm / farm access down for day – p 207
- No issues reported. AN06A pump flow rate control issues
CAM low flow
05/31/2012 No activities this date POR107 unplanned shutdown – p 207
C farm vapors / access down – p 207 -
No issues reported. C Farm vapors – restricted access
06/01/2012 No activities this date - - No issues reported. -
RPP-RPT-58298 3/9/2015 - 7:47 AM 61 of 106
RPP-RPT-58298, Rev. 0
B-4
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
06/02/2012 No activities this date - - No issues reported. -
06/03/2012 POR240 sump pumped – p 30 - - No issues reported. Weather caused leak detection alarms
06/04/2012
Supernatant pump down on low flow – p 31
AN06A LDA – p 31
ARM extend/retract indications no longer reliable – p 32
C-107 admin locks reapplied, leak detector at AN-06A in, likely due to rains – p 213 -
No issues reported. ARM position indication issues
Weather caused leak detection alarms
06/05/2012
POR240 LDA / sump pumped – p 32
POR104 LDA / sump pumped – p 32
AN06A LDA – p 33
Constant tension hoist issues / dragging cable – p 33
C-107 admin locks removed p 213
-
No issues reported. Constant tension hoist issues
06/06/2012 Slurry pump low flow / cable limit interlock issues – p 34/35 POR03 exhauster shut down, planned outage –
p 214 -
No issues reported. Cable limit issues
Slurry pump low flow
06/07/2012 POR03 on C107 only – p 36
Supernatant / slurry pump low flow – p 36/37
"Retrieval completed" – p 215 -
No issues reported. Slurry pump low flow
Supernatant pump low flow
06/08/2012 Supernatant / slurry pump low flow – p 37
ARM HPU discharge pressure issue – p 38
POR03 planned shutdown – p 215 -
No issues reported. Slurry pump low flow
Supernatant pump low flow
06/09/2012 No activities this date - - No issues reported. -
06/10/2012 No activities this date - - No issues reported. -
06/11/2012
AN VTP issues – p 39
POR107 cam flow issues – p 39
Slurry pump low flow – p 39/40
C-107 pump started – p 218
-
No issues reported. CAM low flow
Slurry pump low flow
06/12/2012
POR107 cam flow issues – p 40
Moved to POR03 – p 40
Slurry / supernatant pump low flow – p 40/41
POR107 exhauster down – p 218
-
No issues reported. CAM low flow
Slurry pump low flow
06/13/2012 Slurry pump low flow – p 42
Slurry pump lower cable limit issues – p 42 - -
Declaration of 50% retrieval complete
Declaration of completion of bulk retrieval
Cable limit issues
Slurry pump low flow
06/14/2012 On POR107 vent sys – p 43
Valving misroute – p 43
No flow condition observed, miss-positioned valve in POR209 – p 221
- No issues reported. Procedure issues
06/15/2012 No activities this date - - No issues reported. -
06/16/2012 No activities this date - - No issues reported. -
06/17/2012 No activities this date - - No issues reported. -
06/18/2012 Slurry pump low flow – p 44 - - No issues reported. Slurry pump low flow
06/19/2012 No activities this date - - No issues reported. -
06/20/2012 Preparations – p 45 C-107 containment box heater under admin lock
control – p 228 -
No issues reported. -
06/21/2012
POR107 down for high C-107 vacuum – p 46
Slurry pump low flow – p 46/47
C-107 transfer started – p 228
POR107 down for high C-107 vacuum – p 229
POR107 shutdown in include more tanks – p 230
-
No issues reported. C-107 vacuum issues
Slurry pump low flow
06/22/2012 No activities this date - - No issues reported. -
06/23/2012 No activities this date - - No issues reported. -
06/24/2012 No activities this date - - No issues reported. -
06/25/2012 POR103 breaker issues – p 48 - - No issues reported. POR103 breaker tripped
06/26/2012
Slurry pump low flow – p 49
Hoses in waste due to constant tension hoist issues – p 49
POR246 LDA – p 50
POR104 LDA / Sump pumped – p 50
POR240 LDA / Sump pumped – p 50
C-107 restarted – p 238
-
No issues reported. Slurry pump low flow
Weather caused leak detection alarms
Constant tension hoist issues
06/27/2012 Slurry pump low flow – p 51
POR107 cam failure – p 52
POR107 shut down due to cam failure – p 240 -
No issues reported. CAM failure
Slurry pump low flow
06/28/2012 Slurry pump low flow – p 52
POR240-WT-FCV-161 issues – p 53
POR107 restarted – p 240 -
No issues reported. Slurry pump low flow
Valve closed causing pump shut downs
06/29/2012 No issues this date - - No issues reported. -
06/30/2012 No activities this date - - No issues reported. -
07/01/2012 No activities this date - - No issues reported. -
RPP-RPT-58298 3/9/2015 - 7:47 AM 62 of 106
RPP-RPT-58298, Rev. 0
B-5
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
07/02/2012 POR107 Sample pump issues – p 54
Slurry pump low flow – p 54
POR107 shutdown – p 249 -
No issues reported. Sample pump low flow
Slurry pump low flow
07/03/2012 Slurry pump low flow – p 55/56
Supernatant pump shutdown – p 55 - -
No issues reported. Slurry pump low flow
Supernatant pump low flow
07/04/2012 No activities this date - - No issues reported. -
07/05/2012 Slurry pump low flow – p 56/57 - - No issues reported. Slurry pump low flow
07/06/2012 POR107 cam failure – p 57
POR107 Sample pump issues – p 57
POR107 shut down due to cam failure, restarted, transfers restored, POR107 shutdown again for sample flow low – p 247
-
No issues reported. Sample pump low flow
CAM failure
07/07/2012 No activities this date - - No issues reported. -
07/08/2012 No activities this date - - No issues reported. -
07/09/2012 POR107 CAM Sample failure – p 58 POR107 shut down – p 251 - No issues reported. CAM low flow
07/10/2012
Pumps started, slurry pump up and down – p 59/60
Supernatant pump hoist not operable – p 59
ARM HPU Cabinet high temperature – p 59
- -
No issues reported. Slurry pump low flow
AN06A pump hoist issues
07/11/2012
Slurry / supernatant pumps up and down – p 60/61
POR03 ventilating C107 – p 60
POR03 Instrument Enclosure problems – p 61
Moved C-107 to POR03, restarted – p 253
Vent system shut down, restarted – p 258 -
No issues reported. Slurry pump low flow
Supernatant pump low flow
Power spike suspected in instrument enclosure issues
07/12/2012 Slurry pump up and down – p 62
POR107 Cam/Sampler problems – p 63 - -
No issues reported. Slurry pump low flow
CAM low flow
07/13/2012 Slurry /supernatant pumps up and down – p 63
POR107 Sampler problems – p 64 - -
No issues reported. Slurry pump low flow
Sample pump low flow
07/14/2012 No activities this date - - No issues reported. -
07/15/2012 No activities this date - - No issues reported. -
07/16/2012 ARM HPU Leaking hydraulic fluid – p 66 C-107 retrieval stopped, admin locks installed –
p 262 -
No issues reported. ENCL-400 visible hydraulic leak
07/17/2012
POR03 started – p 66
POR240 sump pumped – p 66
ENCL-002 for ARM HPU AC failing – p 66
Slurry pump up and down – p 66/67
AN VTP down and up – p 264
C-107 retrieval restarted – p 265 -
No issues reported. Slurry pump low flow
Weather caused leak detection alarms
ENCL-002 AC issues
07/18/2012
Back-stop not operable – p 67
Slurry pump up and down – p 67/68
Lower cable limit issues – p 68
POR107 CAM failure problems – POR03 stack high temp shutdown – p 68
C-107 retrieval stopped, POR03 stack air temperature high alarms – p 266
POR03 restarted, C107 lines flushed – p 267 -
No issues reported. Slurry pump low flow
Back-stop issues
Cable limit issues
CAM instrument failures
Stack air temperature issues
07/19/2012 Slurry / supernatant pumps up and down – p 69/70 - - No issues reported. Slurry pump low flow
07/20/2012 Slurry / supernatant pumps up and down – p 70/71 C-107 shut down / planned activity – p 269 - No issues reported. Slurry pump low flow
07/21/2012 No activities this date - - No issues reported. -
07/22/2012 No activities this date - - No issues reported. -
07/23/2012 No activities this date - - No issues reported. -
07/24/2012 No activities this date - - No issues reported. -
07/25/2012 No activities this date - - No issues reported. -
07/26/2012
Slurry / supernatant pumps up and down – p 71/72
ARM angle indication issues – p 72
C-107 retrieval secured – p 274
-
No issues reported. Slurry pump low flow
Supernatant pump low flow
ARM indication issues
07/27/2012 No issues this date - - No issues reported. -
07/28/2012 No activities this date - - No issues reported. -
07/29/2012 No activities this date - - No issues reported. -
07/30/2012
POR107 issues – p 73
Slurry / supernatant pumps up and down – p 74
Slurry pump off vertical, continues typical operation – p 74
POR107 down high radiation / CAM failure – p 277
-
No issues reported. CAM instrument failures
Slurry pump low flow
RPP-RPT-58298 3/9/2015 - 7:47 AM 63 of 106
RPP-RPT-58298, Rev. 0
B-6
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
07/31/2012 Slurry pump up and down – p 75
Leak path evaluations of rotary union, leakage residue observed – p 75
C-107 starting – p 283 -
No issues reported. Slurry pump low flow
08/01/2012 No activities this date POR03 shutdown on low differentia pressure –
p 280 -
No issues reported. -
08/02/2012 No activities this date - - No issues reported. -
08/03/2012 No activities this date Op Eval for POR237 rotary union dealt with leak
from union – p 282/283 -
No issues reported. -
08/04/2012 No activities this date - - No issues reported. -
08/05/2012 No activities this date POR007 started (107?) – p 283 - No issues reported. -
08/06/2012
POR107 temperature issues – p 78
Slurry / supernatant pumps up and down – p 78
Rotary union leak, flush water to ground – p 78/79
POR03 started – p 285
-
No issues reported. Slurry pump low flow
Supernatant pump low flow
Rotary union leak
Flush water spill
Exhauster low differential temperature
08/07/2012 Repaired damaged gasket which caused leak to ground –
p 79 Rotary union visible leak shut down – p 285
- - -
08/08/2012 POR107 issues – p 79 - - - Low HEPA differential pressure
No activities until …
08/20/2012 HPWS-1 work package – p 80 - - - -
08/21/2012 POR107 down on C-107 signal failure – p 80 - - - C-107 pressure transmitter issues
08/22/2012 No activities this date - - - -
08/23/2012 No activities this date - - - -
08/24/2012 No activities this date - - - -
08/25/2012 No activities this date - - - -
08/26/2012 No activities this date - - - -
08/27/2012 POR107 down on C-107 signal failure – p 80
ARM operation issues – p 80
Planned POR107 shut down/restart – p 12 -
No issues reported. C-107 pressure transmitter issues
ARM proximity switch failure
08/28/2012
Proximity switch issues – p 81
Flow indicator issues – p 81
Fogging issues – p 81
POR107 unplanned shutdown sometime on 8/27 – p 15 -
No issues reported. C-107 pressure transmitter issues
ARM proximity switch issues
08/29/2012
Flow indicator issues – p 82
Fogging issues – p 82/83
Issues with ARM contacting the waste – p 83
End effector issues
- -
No issues reported. ARM Proximity switch issues – software fix
Fogging due to operation
FI-214 “stuck”
End effector curb feeler failure
08/30/2012 Pumps up and down, Fogging issues – p 84/85 - - No issues reported. Fogging due to operation
08/31/2012 Pumps up and down, Fogging issues?? – p 85/86
- - Wall cleaning was discontinued with the failure of
one of the four high pressure water nozzles on the end effector.
Fogging due to operation
09/01/2012 No activities this date - - - -
09/02/2012 No activities this date - - - -
09/03/2012 No activities this date - - - -
09/04/2014 Leakage at base of one of the high pressure nozzles – p 86 - - - Leak near one of the high pressure nozzles
No activities until …
09/13/2012
POR107 low heater temperature alarm – p 87
Rotary union still dripping – p 87
Shut down due to low slurry pump flow – p 87
Rotary union issues still – p 28
- A total of 13,393 gallons of accumulated wash
water and residual supernate was pumped from 241-C-107 to 241-AN-106.
Slurry pump low flow
Rotary union leak
Exhauster low heater temperature
09/14/2012 No activities this date - - - -
09/15/2012 No activities this date - - - -
09/16/2012 No activities this date - - - -
09/17/2012 No activities this date - - - -
09/18/2012 No activities this date - - - -
RPP-RPT-58298 3/9/2015 - 7:47 AM 64 of 106
RPP-RPT-58298, Rev. 0
B-7
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
09/19/2012
ARM HPU temp reading issues – p 88
Supernatant pump issues – p 88
Slurry pump up and down, low flow – p 88
C-107 started – p 34
-
No issues reported. Slurry pump low flow
ARM HPU indication issues
Exhauster low heater temperature
09/20/2012
Slurry pump up and down, low flow – p 89
Slurry pump movement issues – p 89
Supernatant pump stopped low HPU fluid level – p 90
C-107 started – p 35
AN-106 pump shutdown low oil interlock – p 35 -
No issues reported. Slurry pump low flow
Slurry pump winch issues
AN06A HPU hydraulic fluid level issues
09/21/2012
Supernatant pump stopped low HPU fluid level – p 91 C-107 started – p 35
AN-106 pump shutdown low oil interlock – p 35
-
Retrieval operations resumed briefly but discontinued to troubleshoot issues with 241-C-107 pump elevation movement and supernatant pump hydraulic power unit fluid losses.
Decant of 241-AN-106 on September 26, 2012, demonstrated significant hydraulic fluid losses resulting in the loss of supernatant pump AN06A-WT-P-024.
AN06A HPU hydraulic fluid level issues
No activities until …
05/06/2013 Retrieval Prerequisites underway – p 90 - - - -
05/07/2013 Apparently lowered slurry distributor instead of pump – p 93 - - - Procedure issues
No activities until …
05/17/2013 Can't lower slurry distributor – p 93
- - - Slurry distributor would only lower 81 turns, not the
161 required
05/18/2013 No activities this date - - - -
05/19/2013 No activities this date - - - -
05/20/2013 FCV-162 issues – p 94
Transfer continued with supernate low flow alarm in – p 94
POR237 changes noted, AN-106 pump secured – p 100
- No issues reported. Valve position indication issues
05/21/2013
Can't lower slurry distributor – p 95
Slurry pump low flow – p 95
Material balance discrepancy – p 95
Transfers secured due to lightning, restarted? – p 101 -
Initial operations were those of a volume displacement on May 20-21st.
Slurry distributor would only lower 22 turns, not the 84 required
Slurry pump low flow
05/22/2013 Pumping stopped until 5/20 material balance discrepancy
issue addressed – p 97 Material balance discrepancy event investigation –
p 103 -
No issues reported. Pumping stopped until 5/20 material balance discrepancy issue addressed
05/23/2013 No activities this date - - No issues reported. -
05/24/2013 No activities this date - - No issues reported. -
05/25/2013 No activities this date - - No issues reported. -
05/26/2013 No activities this date - - No issues reported. -
05/27/2013 No activities this date - - No issues reported. -
05/28/2013
No issues this date Investigation started for C-107 procedure issue – p 109
Pumping resumed, secured for the night – p 109
-
No issues reported.
-
05/29/2013
Slurry pump low flow – p 99
AN06A LDE, floor drain opened, cleared – p 100
"LDE-196" alarm – p 101
Pumping resumed, AN06A LDA shuts down – p 111
Pit drained, pumping resumed, leak condition again shuts down – p 112
-
No issues reported. Slurry pump low flow
AN06A anti-siphon line loose
05/30/2013 Anti-siphon line leak – p 102 Leak observed in AN06A anti-siphon line – p 112 - No issues reported. AN06A anti-siphon line loose
No activities until …
06/26/2013 No issues this date - - No issues reported. -
06/27/2013
Shut down for procedure issues – p 104 AN06A Anti-siphon lines leak checked – p 159
POR03 seal pot leaking – p 159
Procedure issues – p 160
-
No issues reported. Procedure issues
06/28/2013 Supernate starting issues – p 105
Slurry pump low flow/solid build-up – p 105
AN106 pump positioning event investigation started – p 160
Pumps started, shift run – p 162
-
No issues reported. Slurry pump low flow
Supernatant pump low flow
06/29/2013 No activities this date - - No issues reported. -
06/30/2013 No activities this date - - No issues reported. -
07/01/2013 AN vent issues – p 106 POR008 up and down, high stack temperature –
p 171 -
No issues reported. Retrieval not authorized because AN VTP is down
RPP-RPT-58298 3/9/2015 - 7:47 AM 65 of 106
RPP-RPT-58298, Rev. 0
B-8
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
07/02/2013 Work/rest heat issues – p 107 Pump started – p 172
Pump stopped – p 173 -
No issues reported. Weather related work / rest regimen delays
07/03/2013
Pumps up and down, solids blocking – p 108/109
Work/rest heat issues – p 108
Containment box drip wise leak – p 109
Flow indication/alarm agreement issues – p 110
pump stopped – p 174
-
No issues reported. Slurry pump low flow
Supernatant pump low flow
Weather related work / rest regimen delays
Rotary union leak
Flow indication and alarm agreement issues
07/04/2013 No activities this date - - No issues reported. -
07/05/2013 Leaks observed at fitting near constant tension hoist reel
and rotary union- p 111
Slurry pump – liquid pouring out of column – p 111
- -
No issues reported. Rotary union leak
Slurry pump failure starts
07/06/2013 No activities this date - - No issues reported. -
07/07/2013 No activities this date - - No issues reported. -
07/08/2013 Leak test needed on hose runs – p 111 - - No issues reported. -
07/09/2013 No activities this date - - No issues reported. -
07/10/2013 No activities this date Initiated C-107 temporary rounds – p 182 - No issues reported. -
07/11/2013 No activities this date - - No issues reported. -
07/12/2013 High pressure wall washing – p 112
Fogging issues – p 113
Wall washing complete for shift – p 186 -
HP water wall washing with 7,670 gallons of water was conducted on July 12, 2013.
Fogging due to operation
07/13/2013 No activities this date - - No issues reported. -
07/14/2013 No activities this date - - No issues reported. -
07/15/2013 Problems with high pressure pumps – p 114
Apparent slurry pump failure – p 115 - - The slurry pump in 241-C-107 failed. High pressure pump P-003 not working – belt
failure
Slurry pump would not start – pump failure
07/16/2013 Troubleshooting on slurry pump – p 116 - - - Slurry pump would not start – pump failure
07/17/2013 Flushed lines - - - -
07/18/2013 No activities this date - - - -
07/19/2013 No activities this date - - - -
07/20/2013 No activities this date - - - -
07/21/2013 No activities this date - - - -
07/22/2013 Troubleshooting on slurry pump – p 117 - - - Slurry pump would not start – pump failure
07/23/2013 No activities this date - - - -
07/24/2013 Placed system into maintenance mode – p 117 - - - -
No activities until …
09/12/2013 Slurry pump replacement support activities on 9/7/2013 –
p 117 - - - -
No activities until …
10/02/2013 Slurry pump replacement support activities – p 118 - - - -
No activities until …
01/27/2014 Retrieval Prerequisites underway – p 119 - - - -
01/28/2014 MARS arm issues – p 120 - - - ARM motion issues
01/29/2014
Cold temp issues with HPUs – p 121/122
Flow indication issues – p 122
Slurry pump over-speed issues – p 122
- -
No issues reported. HPUs low temperature time-out issues associated with cold weather
FI-168 readings erratic
01/30/2014 Supernatant pump crystal issues – p 123 - - No issues reported. Waste crystals on pump screen washed off
01/31/2014 No activities this date - - No issues reported. -
02/01/2014 No activities this date - - No issues reported. -
02/02/2014 No activities this date - - No issues reported. -
02/03/2014 No activities this date - - No issues reported. -
02/04/2014 Cold temp issues – p 123
- - No issues reported. HPUs low temperature time-out issues associated
with cold weather
RPP-RPT-58298 3/9/2015 - 7:47 AM 66 of 106
RPP-RPT-58298, Rev. 0
B-9
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
02/05/2014 No activities this date - - No issues reported. -
02/06/2014 No activities this date - - No issues reported. -
02/07/2014 No activities this date - - No issues reported. -
02/08/2014 No activities this date - - No issues reported. -
02/09/2014 No activities this date - - No issues reported. -
02/10/2014 AN106 ENRAF issues – p 125 - - No issues reported. ENRAF / TMACS communication issues
02/11/2014 Slurry pump HPU start issues – p 125
FCV-161 indication issues – p 126 - -
No issues reported. Slurry pump speed sensor communications issues
Valve position indication issues
02/12/2014 Slurry pump up/down plugging – p 127 - - No issues reported. Slurry pump low flow
02/13/2014 Slurry pump up/down plugging – p 128/129/130
Constant tension hoist issues – p 128 - -
No issues reported. Slurry pump low flow
Constant tension hoist issues
02/14/2014 Slurry pump up/down plugging – p 130 - - No issues reported. Slurry pump low flow
02/15/2014 No activities this date - - No issues reported. -
02/16/2014 No activities this date - - No issues reported. -
02/17/2014 No activities this date - - No issues reported. -
02/18/2014 Slurry pump up/down plugging – p 131
Cold temp issues – p 131 - -
No issues reported. Slurry pump low flow
HPUs temperature issues
02/19/2014 HPU TE indication issues – p 132 - - No issues reported. HPUs temperature indication issues
02/20/2014 HPU Temp issues – p 132 - - No issues reported. HPUs temperature indication issues
02/21/2014 Slurry pump up/down plugging – p 134/135 - - No issues reported. Slurry pump low flow
02/22/2014 No activities this date - - No issues reported. -
02/23/2014 No activities this date - - No issues reported. -
02/24/2014 Slurry pump up/down plugging – p 135/136
Temp indication issues – p 136 - -
No issues reported. Slurry pump low flow
HPUs temperature issues
02/25/2014 Slurry pump up/down plugging – p 137/138
When on the floor, pump drags when turn table rotated – p 137
- -
No issues reported. Slurry pump low flow
Slurry pump motion issues
02/26/2014 Slurry pump raise/lower issues – p 138
Slurry pump stop/ start low flow – p 139 - -
No issues reported. Slurry pump low flow
Slurry pump motion issues
02/27/2014 Slurry pump stop/ start low flow – p 139/140 - - No issues reported. Slurry pump low flow
02/28/2014 Slurry pump stop/ start low flow – p 141 - - No issues reported. Slurry pump low flow
03/01/2014 No activities this date - - No issues reported. -
03/02/2014 No activities this date - - No issues reported. -
03/03/2014 Slurry pump stop/ start low flow – p 142/143 - - No issues reported. Slurry pump low flow
03/04/2014 Slurry pump stop/ start low flow – p 143
Shutdown for CAM issues – p 144 - -
No issues reported. Slurry pump low flow
CAM alarm – high radiation found on filter
03/05/2014 Slurry pump stop/ start low flow – p 144/145 - - No issues reported. Slurry pump low flow
03/06/2014 Slurry pump stop/ start low flow – p 146/147/ 148/149
MARS arm extension issues – p 146/147/148 - -
No issues reported. Slurry pump low flow
ARM motion issues
03/07/2014 Slurry pump stop/ start low flow – p 149/150/ 151 - - No issues reported. Slurry pump low flow
03/08/2014 No activities this date - - No issues reported. -
03/09/2014 No activities this date - - No issues reported. -
03/10/2014
Slurry pump stop/ start low flow – p 151/152/ 153/154
Water leak at HPWS-2 – p 153
HPWS-2 high-high alarm issues – p 153
- -
No issues reported. Slurry pump low flow
HPWS-2 water leak – possibly associated with high-high level alarm issues
03/11/2014 Slurry pump stop/ start low flow – p 154/155/ 156
Hydraulic leaks at constant tension hoist – p 155/156 - -
No issues reported. Slurry pump low flow
ARM motion issues – leak
03/12/2014 Slurry pump stop/ start low flow – p 156/157/ 158
Wrist sweep motion is leaking seal at constant tension hoist – p 157
- -
No issues reported. Slurry pump low flow
ARM motion issues – leak
03/13/2014 Slurry pump stop/ start low flow – p 158/159/ 160 - - No issues reported. Slurry pump low flow
RPP-RPT-58298 3/9/2015 - 7:47 AM 67 of 106
RPP-RPT-58298, Rev. 0
B-10
241-C-107 Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
03/14/2014 Slurry pump stop/ start low flow – p 161/162 /163 - - No issues reported. Slurry pump low flow
03/15/2014 No activities this date - - No issues reported. -
03/16/2014 No activities this date - - No issues reported. -
03/17/2014 Slurry pump stop/ start low flow – p 163/164
ENCL-400 hydraulic leak – p 164 - -
No issues reported. ENCL-400 visible hydraulic leak
Slurry pump low flow
03/18/2014 No activities this date - - No issues reported. -
03/19/2014 No activities this date - - No issues reported. -
03/20/2014 No activities this date - - No issues reported. -
03/21/2014 No activities this date - - No issues reported. -
03/22/2014 No activities this date - - No issues reported. -
03/23/2014 No activities this date - - No issues reported. -
03/24/2014 No activities this date - - No issues reported. -
03/25/2014 Slurry pump stop/ start low flow – p 165 - - No issues reported. Slurry pump low flow
03/26/2014 Slurry pump stop/ start low flow – p 165/166 /167 - - No issues reported. Slurry pump low flow
03/27/2014 Slurry pump stop/ start low flow – p 167/168 - - No issues reported. Slurry pump low flow
03/28/2014 Slurry pump stop/ start low flow – p 167/169 - - No issues reported. Slurry pump low flow
No activities until …
04/23/2014 No issues this date - - - -
RPP-RPT-58298 3/9/2015 - 7:47 AM 68 of 106
RPP-RPT-58298, Rev. 0
C-1
APPENDIX C
241-C-111 BULK RETRIEVAL ACTIVITIES EVENTS
RPP-RPT-58298 3/9/2015 - 7:47 AM 69 of 106
RPP-RPT-58298, Rev. 0
C-2
241-C-111 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
09/09/10 No activities this date RED ARROW, no C-111 waste retrieval until TSR Readiness Checklist complete
- - -
09/10/10 No activities this date - - - -
09/11/10 No activities this date - - - -
09/12/10 No activities this date - - - -
09/13/10 No activities this date Shift office received AN-101 pump replacement paperwork to support C-111 WRS
- - -
09/14/10 Supernatant pump up and down, flow meter issues
-
The light and camera were replaced Supernatant pump started
Supernatant flow meter instrument reading a factor of 10 low
Supernatant volume based on AN-101 Enraf
-
Lights and camera replaced
Supernatant flow meter instrument reading a factor of 10 low.
09/15/10 Slurry pump active
Supernatant pump active
Post transfer radiation survey issues
-
Retrieval re-started after flow meter repaired
Transfer line radiation readings above procedure limit
-
Flow meter repaired
Transfer line radiation issues
09/16/10 Slurry pump active
Supernatant pump active
Supernatant pump over speed alarm issues
-
Dose rates measured at C-4 on berm reading 5 mrem/hr exceeding criteria.
Several spurious over speed alarms.
-
Supernatant pump over speed alarm issues
Transfer line radiation issues
09/17/10 Slurry pump active
Supernatant pump active
Radiation survey issues
-
Radiological Control reports difference in open and closed window readings where slurry line meets POR134
-
Transfer line radiation issues
09/18/10 No activities this date - - - -
09/19/10 No activities this date - - - -
09/20/10 POR137 Slurry Pump LDE issues
Slurry pump active
Supernatant pump active
-
No issues reported
-
LDE issues
09/21/10 Supernatant pump up and down, low flow
Slurry pump up and down, low flow -
No issues reported -
Slurry pump low flow
Supernatant pump low flow
09/22/10 Slurry pump active
Supernatant pump active
Riser 1 camera issues
Radiation surveys issues
Supernatant pump over speed alarm issues
C-Farm access restriction during retrieval lifted due to IH sampling being within acceptable ranges
Speed sensor troubleshooting for supernatant pump commenced in the afternoon. A 20 second time average appears to have eliminated the spurious alarms.
-
Camera issues
Supernatant pump low flow
09/23/10 Slurry pump active
Supernatant pump active
Direction received to control supernatant pump speed with FCV, not HPU
-
HPU used to control supernatant pump, causing an expected shutdown.
Directed to use FCV-102 to control supernatant flow.
-
Supernatant pump flow control issues
09/24/10 Slurry pump active
Supernatant pump active
- Supernatant soak planned for weekend for center
'bowl' of tank while sluicing is continued to focus on the raised edges.
- -
09/25/10 Supernatant pump up and down, low flow and high flow
Slurry pump active -
No issues reported -
Slurry pump low flow
Supernatant pump flow issues
09/26/10 Slurry pump active
Supernatant pump up and down, low flow
POR008 exhauster making noise
-
No issues reported
-
Supernatant pump flow issues
09/27/10 Supernatant pump up and down, low flow
Slurry pump up and down, low flow -
Supernatant pumped down to obtain an as-of-yet best MBD, but still negative.
- Slurry pump low flow
Supernatant pump low flow
09/28/10 Supernatant pump up and down, low flow and high flow -
The supernatant pump continues to have problems and shut down several times on high speed.
- Supernatant pump flow issues
09/29/10 Supernatant pump up and down, low flow and high flow -
Transfers for volume displacement were performed
- Supernatant pump flow issues
RPP-RPT-58298 3/9/2015 - 7:47 AM 70 of 106
RPP-RPT-58298, Rev. 0
C-3
241-C-111 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
09/30/10 Slurry pump active
Supernatant pump active
POR03 CAM sample issues
POR03 stack air temperature issues
POR03 shutdown low CAM sample flow
Slurry pump shutdown POR03 "stack air temp hi" alarm
Transfers for volume displacement were performed
-
POR03 issues
10/01/10 Leaking gasket on water manifold Added hot water First hot water addition started
The tank headspace fogged up and visibility was lost.
- Water system leak
10/02/10 No activities this date - - - -
10/03/10 No activities this date - - - -
10/04/10 No issues reported - - - -
10/05/10 POR03 shut down Workers in C-Farm sprayed by condensate from POR03, farm evacuated
- - POR03 issues
10/06/10 No issues reported - - - -
10/07/10 POR03 CAM sample flow low
Power outage in 200E Tank Farms - - -
POR03 CAM issues
200E Area wide power outage
10/08/10 POR137 LDA issues
POR03 CAM has water in it - - -
POR137 LDA issues
POR03 CAM issues
10/09/10 No activities this date - - - -
10/10/10 No activities this date - - - -
10/11/10 POR03 CAM issues - - - POR03 CAM issues
10/12/10 No issues reported - - - -
10/13/10 POR03 CAM issues - - - POR03 CAM issues
10/14/10 No issues reported - Riser 7 camera and light replaced. - Riser 7 camera and light issues.
10/15/10 No issues reported Camera and light replaced in Riser 7 - - -
10/16/10 No activities this date - - - -
10/17/10 No activities this date - - - -
10/18/10 POR008 shut down differential pressure issues -
POR-008 exhauster coupling broken, parts ordered.
- POR008 issues
10/19/10 No issues reported - - - -
10/20/10 No issues reported - - - -
10/21/10 Coffman light amp and voltage issues
-
Hot water added to tank C-111
-
Coffman light issues
10/22/10 POR03 low vacuum alarm -
111 °F water added to tank C-111.
Visibility in the tank was poor due to fog, even before the water addition.
- POR03 issues
10/23/10 No activities this date - - - -
10/24/10 No activities this date - - - -
10/25/10 No issues reported
-
Water initially appeared clear, but by afternoon, the sluicing stream appeared reddish brown, indicating some solids have been picked up (may be sludge near the pump inlet below the hard waste layer).
- -
10/26/10 Water truck PTO pump leaking -
Operators report that no changes in the tank waste are evident.
- Water leak issues
10/27/10 Supernatant pump start-up issues - Supernatant pump would not start. - Supernatant pump start-up issues
10/28/10 Riser 7 Coffman light issues
Supernatant pump started -
The pump started up on the first attempt -
Riser 7 Coffman light issues
10/29/10 Camera issues -
Observation of video of the waste in the area below the camera shows that the waste surface appears to have been abraded.
- Camera issues
10/30/10 No activities this date - - - -
RPP-RPT-58298 3/9/2015 - 7:47 AM 71 of 106
RPP-RPT-58298, Rev. 0
C-4
241-C-111 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
10/31/10 No activities this date - - - -
11/01/10 No activities this date - - - -
11/02/10 No issues reported -
Started sluicing with sluicer #1.
Switched to sluicer #2. - -
11/03/10 Attempted to lower the pump but pump did not go down.
-
Sluicer switched from #2 to #1
Camera is having problems panning,
Attempted to lower the pump but pump did not go down.
-
Attempted to lower the pump but pump did not go down.
11/04/10 Material balance Discrepancy math issues
Supernatant pump low speed shut down issues - Attempted to restart the supernatant pump;
speed would not increase and the pump timed out and shut down
- Supernatant pump low speed shut down issues
11/05/10 No issues reported - Final transfer line flushes were performed. - -
RPP-RPT-58298 3/9/2015 - 7:47 AM 72 of 106
RPP-RPT-58298, Rev. 0
D-1
APPENDIX D
241-C-112 BULK RETRIEVAL ACTIVITIES EVENTS
RPP-RPT-58298 3/9/2015 - 7:47 AM 73 of 106
RPP-RPT-58298, Rev. 0
D-2
241-C-112 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
12/27/2011 Procedure / line-up issues
Supernatant pump start issues
Supernatant pump start issues Supernatant pump start issues No issues reported. Procedure / line-up issues
Supernatant pump start issues
12/28/2011
Supernatant pump start issues
POR008 low flow issues (power outage)
AN VTP issues (power outage)
POR008 shut down issues
AN VTP issues
Supernatant pump start issues No issues reported. Supernatant pump start issues
Power outage issues
12/29/2011 Sluicer #2 motion issues
Slurry pump shut down low flow
No issues reported. No issues reported. No issues reported. Sluicer #2 motion issues
Slurry pump shut down low flow
12/30/2011 Hydraulic fluid leak from the ERSS - Hydraulic fluid leak from the ERSS Hydraulic fluid leak from the ERSS ERSS hydraulic leak issues
12/31/2011 No activities this date - - - -
01/01/2012 No activities this date - - - -
01/02/2012 No activities this date - - - -
01/03/2012 Cold weather issues POR134 - No issues reported. No issues reported. Cold weather issues POR134
01/04/2012 Hydraulic fluid leak from the ERSS - Hydraulic fluid leak from the ERSS No issues reported. ERSS hydraulic leak issues
01/05/2012 Riser 3 camera issues
- Hydraulic fluid leak from the ERSS No issues reported. Riser 3 camera issues
ERSS hydraulic leak issues
01/06/2012 Riser 3 camera issues - No issues reported. No issues reported. Riser 3 camera issues
01/07/2012 No activities this date - - No issues reported. -
01/08/2012 No activities this date - - No issues reported. -
01/09/2012 No issues reported. - No issues reported. No issues reported. -
01/10/2012 No activities this date - Riser 6 camera issues No issues reported. Riser 6 camera issues
01/11/2012 Cold weather issues
Hydraulic fluid leak from the ERSS is from the nozzle positioning controls
- Hydraulic fluid leak from the ERSS Hydraulic fluid leak from the ERSS is from the
nozzle positioning controls ERSS hydraulic leak issues
01/12/2012
POR008 seal pot issues
Riser 3 camera and riser 6 light issues -
Riser 3 camera issues No issues reported. POR008 seal pot issues
Riser 3 camera issues
Riser 6 light issues
01/13/2012 POR008 seal pot issues
Cold weather issues -
No issues reported. No issues reported. POR008 seal pot issues
Cold weather issues
01/14/2012 No activities this date POR008 seal pot issues - No issues reported. POR008 seal pot issues
01/15/2012 No activities this date - - No issues reported. -
01/16/2012 POR008 seal pot issues POR008 seal pot issues Hydraulic fluid leak from the ERSS No issues reported. ERSS hydraulic leak issues
POR008 seal pot issues
01/17/2012 AN VTP issues - AN VTP issues No issues reported. AN VTP issues
01/18/2012 No issues reported.
- Cold weather issues Cold weather related issues
Ventilation system issues
Cold weather issues
01/19/2012 No activities this date Cold weather issues Cold weather issues Cold weather related issues
Ventilation system issues
Cold weather issues
01/20/2012 No activities this date
- Cold weather issues Cold weather related issues
Ventilation system issues
Cold weather issues
01/21/2012 No activities this date - - No issues reported. -
01/22/2012 No activities this date - - No issues reported. -
01/23/2012 POR008 seal pot issues - POR008 seal pot low issues No issues reported. POR008 seal pot issues
01/24/2012 Cold weather issues - No issues reported. No issues reported. Cold weather issues
01/25/2012 AN VTP issues - AN VTP issues No issues reported. AN VTP issues
01/26/2012 No activities this date AN VTP issues AN VTP issues No issues reported. AN VTP issues
01/27/2012 No activities this date AN VTP issues AN VTP issues No issues reported. AN VTP issues
01/28/2012 No activities this date - - No issues reported. -
01/29/2012 No activities this date Cold weather issues - No issues reported. Cold weather issues
01/30/2012
Supernatant pump start issues
-
AN VTP issues
Cold weather issues
Supernatant pump start issues
No issues reported. AN VTP issues
Cold weather issues
Supernatant pump start issues
RPP-RPT-58298 3/9/2015 - 7:47 AM 74 of 106
RPP-RPT-58298, Rev. 0
D-3
241-C-112 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
01/31/2012 Slurry pump flow rate issues
Procedure issues -
Slurry pump flow rate issues
Procedure issues
No issues reported. Slurry pump flow rate issues
Procedure issues
02/01/2012 Hydraulic lines to the ERSS disconnected - Hydraulic lines to the ERSS disconnected Hydraulic lines to the ERSS disconnected ERSS hydraulic leak issues
02/02/2012 No issues reported. - No issues reported. No issues reported. -
02/03/2012 No issues reported. - No issues reported. No issues reported. -
02/04/2012 No activities this date - - No issues reported. -
02/05/2012 No activities this date - - No issues reported. -
02/06/2012 No issues reported. Cold weather issues No issues reported. No issues reported. Cold weather issues
02/07/2012
Cold weather issues
Supernatant pump start issues
POR137 PI-101 out of service
-
Cold weather issues
Supernatant pump start issues
No issues reported. Cold weather issues
Supernatant pump start issues
POR137 issues
02/08/2012
Network outage issues – unable to get temperatures
-
Network outage issues – unable to get temperatures
No issues reported. Network outage issues – unable to get temperatures
02/09/2012 POR132 PM issues - No issues reported. No issues reported. POR132 PM issues
02/10/2012 Slurry pump flow rate issues - No issues reported. No issues reported. Slurry pump flow rate issues
02/11/2012 No activities this date - - No issues reported. -
02/12/2012 No activities this date - - No issues reported. -
02/13/2012 Supernatant pump start issues - Supernatant pump start issues No issues reported. Supernatant pump start issues
02/14/2012 Supernatant pump start issues - Supernatant pump start issues No issues reported. Supernatant pump start issues
02/15/2012 Riser 3 and Riser 6 light issues, Riser 3 camera issues
- Supernatant pump start issues
Riser 3 and Riser 6 light issues, Riser 3 camera issues
No issues reported. Supernatant pump start issues
Riser 3 and Riser 6 light issues, Riser 3 camera issues
02/16/2012 No issues reported. Riser 3 and Riser 6 light issues, Riser 3 camera
issues
No issues reported. No issues reported. Riser 3 and Riser 6 light issues, Riser 3 camera issues
02/17/2012 No issues reported. - No issues reported. No issues reported. -
02/18/2012 No activities this date - - No issues reported. -
02/19/2012 No activities this date - - No issues reported. -
02/20/2012 No issues reported. - No issues reported. No issues reported. -
02/21/2012 Slurry pump flow rate issues - No issues reported. No issues reported. Slurry pump flow rate issues
02/22/2012 Power spike issues Power spike issues Power spike issues No issues reported. Power spike issues
02/23/2012 Slurry pump flow rate issues - No issues reported. No issues reported. Slurry pump flow rate issues
02/24/2012 Slurry pump movement issues
Slurry pump flow rate issues -
Slurry pump movement issues No issues reported. Slurry pump movement issues
Slurry pump flow rate issues
02/25/2012 No activities this date - - No issues reported. -
02/26/2012 No activities this date - No issues reported. No issues reported. -
02/27/2012 Slurry pump movement issues AN VTP issues Slurry pump movement issues No issues reported. Slurry pump movement issues
02/28/2012 No activities this date - Supernatant pump HPU issues No issues reported. Supernatant pump HPU issues
02/29/2012 Slurry pump HPU issues - No issues reported. No issues reported. Slurry pump HPU issues
03/01/2012 No issues reported. Slurry pump HPU issues Slurry pump HPU issues No issues reported. Slurry pump HPU issues
03/02/2012 No activities this date - - No issues reported. -
03/03/2012 No activities this date - - No issues reported. -
03/04/2012 No activities this date - - No issues reported. -
03/05/2012 No issues reported. AN Enraf issues AN Enraf issues No issues reported. AN Enraf issues
03/06/2012 No issues reported. AN Enraf issues AN Enraf issues No issues reported. AN Enraf issues
03/07/2012 No issues reported. - No issues reported. No issues reported. -
03/08/2012 No issues reported. - Ahlberg light issues No issues reported. Ahlberg light issues
03/09/2012 Power outage issues
Ahlberg lights installed
Power outage issues Riser 6 light issues
Power outage issues
No issues reported. Riser 6 light issues
Power outage issues
RPP-RPT-58298 3/9/2015 - 7:47 AM 75 of 106
RPP-RPT-58298, Rev. 0
D-4
241-C-112 Bulk Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Findings
03/10/2012 No activities this date - - No issues reported. -
03/11/2012 No activities this date - No issues reported. No issues reported. -
03/12/2012 No issues reported. - POR008 differential pressure issues No issues reported. POR008 differential pressure issues
03/13/2012 No issues reported. - No issues reported. No issues reported. -
03/14/2012 Slurry pump movement issues - No issues reported. No issues reported. Slurry pump movement issues
03/15/2012 No issues reported. - No issues reported. No issues reported. -
03/16/2012 No issues reported. - No issues reported. No issues reported. -
03/17/2012 No activities this date - - No issues reported. -
03/18/2012 No activities this date - - No issues reported. -
03/19/2012 Riser 3 and Riser 6 camera and light issues - Visibility issues No issues reported. Riser 3 and Riser 6 camera and light issues
03/20/2012 No activities this date - Visibility issues No issues reported. Visibility issues
03/21/2012 Riser 3 and Riser 6 camera and light issues - No issues reported. No issues reported. Riser 3 and Riser 6 camera and light issues
03/22/2012 No activities this date - - No issues reported. -
03/23/2012 POR008 planned outage - POR008 planned outage No issues reported. -
03/24/2012 No activities this date - - No issues reported. -
03/25/2012 No activities this date - - No issues reported. -
03/26/2012 Slurry pump movement issues - Slurry pump movement issues No issues reported. Slurry pump movement issues
03/27/2012 Supernatant pump flow rate issues Supernatant pump flow rate issues Supernatant pump flow rate issues No issues reported. Supernatant pump flow rate issues
03/28/2012 No issues reported. - No issues reported. No issues reported. -
03/29/2012 Slurry pump low flow issues
Supernatant pump speed issues
Light plant drip pan full of water and oil Slurry pump low flow issues
Supernatant pump speed issues
No issues reported. Slurry pump low flow issues
Supernatant pump speed issues
03/30/2012 No issues reported. - No issues reported. No issues reported. -
03/31/2012 No activities this date - - No issues reported. -
04/01/2012 No activities this date - - No issues reported. -
04/02/2012
Supernatant pump flow rate issues -
Supernatant pump flow rate issues
Riser 3 light issues
POR008 differential pressure issues
No issues reported. Supernatant pump flow rate issues
Riser 3 light issues
POR008 differential pressure issues
04/03/2012 Riser 3 and riser 6 light issues
Supernatant pump flow rate issues -
Supernatant pump speed issues
Riser 3 and riser 6 light issues
No issues reported. Supernatant pump flow rate issues
Riser 3 and riser 6 light issues
04/04/2012 No issues reported. - No issues reported. No issues reported. -
04/05/2012 No activities this date - POR008 differential pressure issues No issues reported. POR008 differential pressure issues
04/06/2012 Slurry pump HPU POR272 hydraulic leak issues - Slurry pump HPU POR272 hydraulic leak issues No issues reported. Slurry pump hydraulic leak issues
04/07/2012 No activities this date - - No issues reported. -
04/08/2012 No activities this date - - No issues reported. -
04/09/2012 No activities this date - No issues reported. No issues reported. -
04/10/2012 Supernatant pump flow rate issues
- Supernatant pump flow rate issues
Riser 3 light issues
No issues reported. Supernatant pump flow rate issues
Riser 3 light issues
04/11/2012 Supernatant pump flow rate issues
Supernatant pump stop issues -
Supernatant pump stop issues No issues reported. Supernatant pump flow rate issues
Supernatant pump stop issues
04/12/2012 Riser 3 and 6 light issues - Riser 3 and 6 light issues No issues reported. Riser 3 and 6 light issues
04/13/2012 Riser 3 and 6 light issues
Noise level issues at supernatant pump -
No issues reported. No issues reported. Riser 3 and 6 light issues
Noise level issues at supernatant pump
04/14/2012 No activities this date - - No issues reported. -
04/15/2012 No activities this date - - No issues reported. -
04/16/2012 POR303 TI issues - No issues reported. No issues reported. POR303 TI issues
04/17/2012 No issues reported. - No issues reported. No issues reported. -
04/18/2012 No issues reported. - No issues reported. No issues reported. -
RPP-RPT-58298 3/9/2015 - 7:47 AM 76 of 106
RPP-RPT-58298, Rev. 0
E-1
APPENDIX E
241-C-112 HARD HEEL RETRIEVAL ACTIVITIES EVENTS
RPP-RPT-58298 3/9/2015 - 7:47 AM 77 of 106
RPP-RPT-58298, Rev. 0
E-2
241-C-112 HHR Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Activity Findings
11/18/2013 Caustic Addition – p 1
- Caustic Addition ~12,000 gal 50 wt% caustic followed
by water line flushes are added to initiate caustic pre-soak process
Normal Operating Conditions
-
11/19/2013 Slurry pump speed and flow irregularity issues – p 2/3
- Caustic Addition Recirculation of caustic Off Normal Conditions Slurry pump speed and flow
irregularity issues
11/20/2013
POR008 pre-filter differential pressure issues – p 3/4
Riser 6 camera issues – p 3
Enraf reading issues – p 5 -
Recirculation Recirculation of caustic Off Normal Conditions POR008 pre-filter differential pressure issues
Camera and light issues
Enraf reading issues
11/21/2013 Cold weather related issues in boxes and slurry pump HPU –
p 5 -
Recirculation Recirculation of caustic Off Normal Conditions Cold weather related issues slurry pump HPU
11/22/2013 Cold weather related issues in boxes and slurry pump HPU –
p 6/7 -
Recirculation Recirculation of caustic Off Normal Conditions Cold weather related issues slurry pump HPU
11/23/2013 No activities this date - - - - -
11/24/2013 No activities this date - - - - -
11/25/2013 Cameras replaced in Risers 3 and 6 and light in Riser 3 – p 7
Slurry pump active – p 8 -
Recirculation Recirculation of caustic Normal Operating Conditions -
11/26/2013 Slurry pump active – p 8
Cold weather related issues slurry pump HPU – p 8/9 -
Recirculation Recirculation of caustic Off Normal Conditions Cold weather related issues slurry pump HPU
11/27/2013 POR008 pre-filter differential pressure issues – p 10
- Recirculation Recirculation of caustic Off Normal Conditions POR008 pre-filter differential
pressure issues
11/28/2013 No activities this date - - - - -
11/29/2013 No activities this date - - - - -
11/30/2013 No activities this date - - - - -
12/01/2013 No activities this date - - - - -
12/02/2013 POR008 pre-filter differential pressure issues – p 11/12/13
- Recirculation Recirculation of caustic Off Normal Conditions POR008 pre-filter differential
pressure issues
12/03/2013 Riser 3 camera issues – p 14 - - - Off Normal Conditions Camera and light issues
12/04/2013 Cold weather related issues in boxes and slurry pump HPU –
p 15 -
Recirculation Recirculation of caustic Off Normal Conditions Cold weather related issues slurry pump HPU
12/05/2013 No activities this date - - - - -
12/06/2013 No activities this date - - - - -
12/07/2013 No activities this date - - - - -
12/08/2013 No activities this date - - - - -
12/09/2013
Cold weather related issues in boxes and slurry pump HPU – p 16
Enraf reading issues – p 16
POR117 indication issues – p 16
POR318 circuit 5 tripped – p 16
- - -
Off Normal Conditions Cold weather related issues slurry pump HPU
Enraf reading issues
POR117 indication issues
POR318 circuit issues
12/10/2013 POR008 seal pot issues – p 17 - - - Off Normal Conditions POR008 seal pot issues
12/11/2013 POR008 seal pot issues – p 17 - Transfer of caustic out Transfer of caustic out Off Normal Conditions POR008 seal pot issues
12/12/2013 POR008 seal pot issues – p 18 - - - Off Normal Conditions POR008 seal pot issues
12/13/2013 No activities this date - - - - -
12/14/2013 No activities this date - - - - -
12/15/2013 No activities this date - - - - -
12/16/2013 No activities this date - - - - -
12/17/2013 No activities this date - - - - -
12/18/2013 No issues reported - Sluicing Sluicing Normal Operating Conditions -
12/19/2013 Material balance discrepancy issues – p 21/22
AN VTP issues – p 22 - Sluicing Sluicing 6.1 Off Normal Conditions Material balance discrepancy
issues
AN VTP issues
RPP-RPT-58298 3/9/2015 - 7:47 AM 78 of 106
RPP-RPT-58298, Rev. 0
E-3
241-C-112 HHR Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Activity Findings
12/20/2013 Material balance discrepancy issues – p 22
AN VTP issues – p 23 - Sluicing Sluicing 6.2 Off Normal Conditions Material balance discrepancy
issues
AN VTP issues
12/21/2013 No activities this date - - - - -
12/22/2013 No activities this date - - - - -
12/23/2013 POR334 temperature issues – p 23
- Sluicing Sluicing 6.3 Off Normal Conditions Temperature monitoring
issues
12/24/2013 No activities this date - - - - -
12/25/2013 No activities this date - - - - -
12/26/2013 Material balance discrepancy issues – p 24
- Sluicing Sluicing 6.4 Off Normal Conditions Material balance discrepancy
issues
12/27/2013 No issues reported - Sluicing Sluicing Normal Operating Conditions -
12/28/2013 No activities this date - - - - -
12/29/2013 No activities this date - - - - -
12/30/2013
Cold weather related issues slurry pump HPU – p 26
POR137 FQI-101A reset issues – p 26 -
Sluicing Sluicing 6.5 Off Normal Conditions Cold weather related issues slurry pump HPU
12/31/2013 No issues reported
- Sluicing
Hot water dissolution
Sluicing
Hot water dissolution
Normal Operating Conditions -
01/01/2014 No activities this date - - - - -
01/02/2014 No issues reported - Sluicing Sluicing Normal Operating Conditions -
01/03/2014 No issues reported - Hot water dissolution Hot water dissolution Normal Operating Conditions -
01/04/2014 No activities this date - - - - -
01/05/2014 No activities this date - - - - -
01/06/2014 No activities this date - Caustic Addition Caustic Addition - -
01/07/2014 POR008 high differential pressure issues – p 30
- Caustic Addition Caustic Addition 6.6 Off Normal Conditions POR008 differential pressure
issues
01/08/2014 POR008 high differential pressure issues – p 30
- Recirculation of caustic Recirculation of caustic 6.7 Off Normal Conditions POR008 differential pressure
issues
01/09/2014 No issues reported - Recirculation of caustic Recirculation of caustic Normal Operating Conditions -
01/10/2014 Slurry pump positioning issues – p 32 - Recirculation of caustic Recirculation of caustic 6.8 Off Normal Conditions Slurry pump positioning issues
01/11/2014 No activities this date - - - - -
01/12/2014 No activities this date - - - - -
01/13/2014
No issues reported
-
Recirculation of caustic
Procedural issues with the prerequisites
ERSS #1 nozzle caught on stiffener ring and bent
In tank light burned out
Recirculation of caustic Normal Operating Conditions
-
01/14/2014
Sluicer #2 positioning issues – p 33
Light issues – p 34
ERSS #1 nozzle caught on stiffener ring and bent – p 34
ERSS #2 nozzle plugging – p 34
-
Grab sampling
ERSS #2 nozzle plugging
Recirculation of caustic
Sluicer response issues
Sluicer nozzle discovered to be bent
6.9 Off Normal Conditions Sluicer positioning issues
In tank lighting issues
ERSS #1 nozzle caught on stiffener ring and bent
ERSS #2 nozzle plugging
01/15/2014 No issues reported - ERSS #2 nozzle plugging Recirculation of caustic Normal Operating Conditions -
01/16/2014
POR008 high demister/heater differential pressure issues – p 36
Visibility issues – p 36 -
ERSS #2 shut down
ERSS #1 used
POR008 high demister/heater differential pressure issues
Visibility issues
Recirculation of caustic 6.10 Off Normal Conditions POR008 differential pressure issues
Visibility issues
01/17/2014 POR008 high demister/heater differential pressure issues –
p 37
Visibility issues – p 37
- POR008 high demister/heater differential
pressure issues
Visibility issues
Recirculation of caustic 6.11 Off Normal Conditions POR008 differential pressure issues
Visibility issues
01/18/2014 No activities this date - - - - -
RPP-RPT-58298 3/9/2015 - 7:47 AM 79 of 106
RPP-RPT-58298, Rev. 0
E-4
241-C-112 HHR Retrieval Activities Events
Date Retrieval/Closure Operations Engineer Log Base Operations Shift Manager Log Process Engineer Log Completion Report Activity Findings
01/19/2014 No activities this date - - - - -
01/20/2014 Jersey barricade missing – p 38 - No issues reported. Recirculation of caustic Normal Operating Conditions Jersey barricade missing
01/21/2014 Cold weather related issues slurry pump HPU – p 39
Sluicer #2 plugging issues – p 39 -
No issues reported. Recirculation of caustic 6.12 Off Normal Conditions Cold weather related issues slurry pump HPU
Sluicer #2 plugging
01/22/2014 No activities this date - - - - -
01/23/2014 Slurry pump flow issues – p 40
- No issues reported. Transfer of caustic out
Sluicing 6.13 Off Normal Conditions Slurry pump flow issues
01/24/2014 Sluicer #2 plugging issues – p 41 - No issues reported. Sluicing 6.14 Off Normal Conditions Sluicer #2 plugging
01/25/2014 No activities this date - - - - -
01/26/2014 No activities this date - - - - -
01/27/2014 POR008 high demister/heater differential pressure issues –
p 42
Radiological control stop work issues – p 43
-
No issues reported. Sluicing 6.15 Off Normal Conditions POR008 differential pressure issues
Radiological conditions issues
01/28/2014 No issues reported
- Volume displacement activities Sluicing
Volume displacement activities
Normal Operating Conditions -
01/29/2014 No issues reported - Flushing Flushing Normal Operating Conditions -
01/30/2014 POR008 differential pressure issues – p 46
- Flushing Flushing 6.16 Off Normal Conditions POR008 differential pressure
issues
01/31/2014 No issues reported - Flushing Flushing Normal Operating Conditions -
RPP-RPT-58298 3/9/2015 - 7:47 AM 80 of 106
RPP-RPT-58298, Rev. 0
F-1
APPENDIX F
241-C-101 BULK RETRIEVAL EVENT ANALYSIS
RPP-RPT-58298 3/9/2015 - 7:47 AM 81 of 106
RPP-RPT-58298, Rev. 0
F-2
241-C-101 Bulk Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
12/10/2012 1 1
12/11/2012 1 1
12/18/2012 1 1
12/19/2012 1 1 2
12/20/2012 1 1 2
12/21/2012 0
12/26/2012 1 1
12/27/2012 1 1 2
12/28/2012 1 1 2
01/02/2013 1 2 3
01/03/2013 1 1
01/04/2013 0
01/07/2013 0
01/08/2013 1 1
01/09/2013 1 1 2
01/10/2013 1 1
01/11/2013 1 1 1 3
01/14/2013 1 1 2
01/15/2013 1 1 2
01/16/2013 1 1 2
01/17/2013 1 1
01/18/2013 1 1
01/21/2013 0
01/22/2013 1 1
01/23/2013 1 1
02/11/2013 1 1
02/12/2013 1 1
02/13/2013 1 1
02/14/2013 1 1
02/19/2013 1 1
02/20/2013 1 1 2
02/21/2013 1 1
02/22/2013 1 1
02/25/2013 1 1
02/26/2013 1 1 2
02/28/2013 1 1 2
03/01/2013 1 1 1 3
03/02/2013 1 1
03/05/2013 0
03/06/2013 0
03/07/2013 0
03/08/2013 1 1 2
03/11/2013 1 1
03/12/2013 1 1 2
03/13/2013 1 1
03/14/2013 1 1
03/15/2013 0
RPP-RPT-58298 3/9/2015 - 7:47 AM 82 of 106
RPP-RPT-58298, Rev. 0
F-3
241-C-101 Bulk Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
03/18/2013 0
03/19/2013 0
05/05/2013 0
05/09/2013 1 1
05/13/2013 1 1
05/14/2013 1 1 2
05/15/2013 2 2
05/16/2013 1 1 2
05/17/2013 1 1
05/31/2013 1 1
06/03/2013 1 1
06/04/2013 1 1
06/05/2013 1 1 1 1 4
06/06/2013 0
06/07/2013 1 1
06/10/2013 1 1
06/11/2013 1 1
06/12/2013 1 1 2
06/13/2013 0
06/14/2013 1 1
06/17/2013 1 1
06/18/2013 1 1
06/19/2013 1 1
06/20/2013 1 1
07/09/2013 1 2 3
07/10/2013 0
07/11/2013 1 1 2
07/16/2013 0
07/22/2013 1 1
07/23/2013 1 1
07/24/2013 1 1
07/25/2013 1 1 1 3
07/26/2013 0
08/07/2013 2 2
08/08/2013 1 1
08/09/2013 0
08/12/2013 1 1
08/13/2013 0
08/14/2013 1 1
08/15/2013 1 1
08/16/2013 1 1
08/19/2013 1 1
08/20/2013 1 1
08/21/2013 2 2
08/26/2013 0
09/06/2013 0
09/09/2013 1 1 2
RPP-RPT-58298 3/9/2015 - 7:47 AM 83 of 106
RPP-RPT-58298, Rev. 0
F-4
241-C-101 Bulk Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
09/10/2013 0
09/11/2013 1 1
09/12/2013 1 1
09/24/2013 0
09/28/2013 0
09/29/2013 0
09/30/2013 0
Number of Events 8 17 14 0 4 20 3 1 21 22 110
RPP-RPT-58298 3/9/2015 - 7:47 AM 84 of 106
RPP-RPT-58298, Rev. 0
G-1
APPENDIX G
241-C-107 RETRIEVAL ACTIVITIES EVENT ANALYSIS
RPP-RPT-58298 3/9/2015 - 7:47 AM 85 of 106
RPP-RPT-58298, Rev. 0
G-2
241-C-107 Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
09/27/2011 1 2 3
09/29/2011 1 1
10/06/2011 1 1 2
10/07/2011 1 1
10/10/2011 1 1 2
10/11/2011 1 1
10/12/2011 1 1
10/17/2011 1 1
10/18/2011 1 1 2
10/19/2011 1 1 1 3
10/20/2011 1 1 1 3
10/26/2011 1 1
10/27/2011 1 1 1 3
10/28/2011 1 1 2 4
11/02/2011 1 1
11/03/2011 0
01/25/2012 0
04/20/2012 1 1
05/01/2012 1 1
05/09/2012 0
05/10/2012 1 1 2
05/17/2012 1 1 2
05/18/2012 1 1
05/21/2012 1 1
05/22/2012 1 1
05/23/2012 1 1
05/24/2012 1 1
05/29/2012 1 1 1 3
05/30/2012 1 1 2
06/03/2012 1 1
06/04/2012 1 1 1 3
06/05/2012 1 3 4
06/06/2012 1 1 2
06/07/2012 1 1 1 3
06/08/2012 1 1 1 3
06/11/2012 2 1 3
06/12/2012 2 1 1 4
06/13/2012 1 1 2
06/14/2012 1 1 2
06/18/2012 1 1
06/20/2012 0
06/21/2012 1 1 2
06/25/2012 1 1
06/26/2012 1 1 3 5
06/27/2012 1 1 2
06/28/2012 1 1 2
06/29/2012 0
RPP-RPT-58298 3/9/2015 - 7:47 AM 86 of 106
RPP-RPT-58298, Rev. 0
G-3
241-C-107 Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
07/02/2012 1 1 2
07/03/2012 1 1 2
07/05/2012 1 1
07/06/2012 2 2
07/09/2012 1 1
07/10/2012 1 1 1 3
07/11/2012 1 1 1 3
07/12/2012 1 1 2
07/13/2012 1 1 2
07/16/2012 1 1
07/17/2012 1 1 1 3
07/18/2012 1 1 2 4
07/19/2012 1 1
07/20/2012 1 1
07/26/2012 1 1 1 3
07/27/2012 0
07/30/2012 1 1 1 1 4
07/31/2012 1 1 2
08/06/2012 1 1 1 1 1 5
08/07/2012 1 1
08/08/2012 1 1
08/20/2012 1 1
08/21/2012 1 1
08/27/2012 1 1 2
08/28/2012 1 1 2
08/29/2012 2 2
08/30/2012 1 1 2
08/31/2012 1 1 2
09/04/2012 1 1
09/13/2012 1 1 1 3
09/19/2012 1 1 1 3
09/20/2012 1 1 1 3
09/21/2012 1 1
05/17/2013 1 1
05/20/2013 1 1 2
05/21/2013 1 2 3
05/22/2013 1 1
05/28/2013 0
05/29/2013 1 1 2
05/30/2013 1 1
06/26/2013 0
06/27/2013 1 1
06/28/2013 1 1 2
07/01/2013 1 1
07/02/2013 1 1
07/03/2013 1 1 1 2 5
07/05/2013 1 1 2
RPP-RPT-58298 3/9/2015 - 7:47 AM 87 of 106
RPP-RPT-58298, Rev. 0
G-4
241-C-107 Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
07/08/2013 0
07/12/2013 0
07/15/2013 2 2
07/16/2013 1 1
07/17/2013 0
07/22/2013 1 1
07/24/2013 0
01/27/2014 0
01/28/2014 1 1
01/29/2014 1 1 1 3
01/30/2014 1 1
02/04/2014 1 1
02/10/2014 1 1
02/11/2014 1 1 2
02/12/2014 1 1
02/13/2014 1 1 2
02/14/2014 1 1
02/18/2014 1 1 2
02/19/2014 1 1
02/20/2014 1 1
02/21/2014 1 1
02/24/2014 1 1 2
02/25/2014 1 1 2
02/26/2014 1 1 2
02/27/2014 1 1
02/28/2014 1 1
03/03/2014 1 1
03/04/2014 1 1 2
03/05/2014 1 1
03/06/2014 1 1 2
03/07/2014 1 1
03/10/2014 1 2 3
03/11/2014 1 1 2
03/12/2014 1 1 2
03/13/2014 1 1
03/14/2014 1 1
03/17/2014 1 1 2
03/25/2014 1 1
03/26/2014 1 1
03/27/2014 1 1
03/28/2014 1 1
04/23/2014 0
Number of Events 16 29 2 5 17 70 9 13 10 55 226
RPP-RPT-58298 3/9/2015 - 7:47 AM 88 of 106
RPP-RPT-58298, Rev. 0
H-1
APPENDIX H
241-C-111 BULK RETRIEVAL ACTIVITIES EVENT ANALYSIS
RPP-RPT-58298 3/9/2015 - 7:47 AM 89 of 106
RPP-RPT-58298, Rev. 0
H-2
241-C-111 Bulk Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
09/14/2010 1 1 2
09/15/2010 1 1
09/16/2010 1 1
09/17/2010 1 1
09/20/2010 1 1
09/21/2010 1 1 2
09/22/2010 1 1 2
09/23/2010 1 1
09/24/2010 0
09/25/2010 1 1
09/26/2010 1 1 2
09/27/2010 1 1 2
09/28/2010 1 1
09/29/2010 1 1
09/30/2010 1 1
10/01/2010 1 1
10/04/2010 0
10/05/2010 1 1
10/06/2010 0
10/07/2010 1 1
10/08/2010 1 1
10/11/2010 1 1
10/12/2010 0
10/13/2010 1 1
10/14/2010 1 1
10/15/2010 0
10/18/2010 1 1
10/19/2010 0
10/20/2010 0
10/21/2010 1 1
10/22/2010 1 1
10/25/2010 0
10/26/2010 1 1
10/27/2010 1 1
10/28/2010 1 1
10/29/2010 1 1
11/02/2010 0
11/03/2010 1 1 2
11/04/2010 1 1 2
11/05/2010 0
Number of Events 0 9 7 1 11 2 1 0 0 6 37
RPP-RPT-58298 3/9/2015 - 7:47 AM 90 of 106
RPP-RPT-58298, Rev. 0
I-1
APPENDIX I
241-C-112 BULK RETRIEVAL ACTIVITIES EVENT ANALYSIS
RPP-RPT-58298 3/9/2015 - 7:47 AM 91 of 106
RPP-RPT-58298, Rev. 0
I-2
241-C-112 Bulk Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
12/27/2011 1 1 2
12/28/2011 1 1 2
12/29/2011 1 1 2
12/30/2011 1 1
01/03/2012 1 1
01/04/2012 1 1
01/05/2012 1 1
01/06/2012 1 1
01/09/2012 0
01/10/2012 1 1
01/11/2012 1 1
01/12/2012 1 1 2
01/13/2012 1 1 2
01/16/2012 1 1 2
01/17/2012 1 1
01/18/2012 0
01/23/2012 1 1
01/24/2012 1 1
01/25/2012 1 1
01/30/2012 1 1
01/31/2012 1 1 2
02/01/2012 1 1
02/02/2012 0
02/03/2012 0
02/06/2012 0
02/07/2012 1 1 2
02/08/2012 1 1
02/09/2012 1 1
02/10/2012 1 1
02/13/2012 1 1
02/14/2012 1 1
02/15/2012 1 1
02/16/2012 0
02/17/2012 0
02/20/2012 0
02/21/2012 1 1
02/22/2012 1 1
02/23/2012 1 1
02/24/2012 1 1 2
02/27/2012 1 1
02/29/2012 1 1
03/01/2012 0
03/05/2012 1 1
03/06/2012 1 1
03/07/2012 0
03/08/2012 1 1
03/09/2012 1 1
RPP-RPT-58298 3/9/2015 - 7:47 AM 92 of 106
RPP-RPT-58298, Rev. 0
I-3
241-C-112 Bulk Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
03/12/2012 1 1
03/13/2012 0
03/14/2012 1 1
03/15/2012 0
03/16/2012 0
03/19/2012 1 1
03/20/2012 1 1
03/21/2012 1 1
03/23/2012 0
03/26/2012 1 1
03/27/2012 1 1
03/28/2012 0
03/29/2012 1 1 2
03/30/2012 0
04/02/2012 1 1 1 3
04/03/2012 1 1 2
04/04/2012 0
04/06/2012 1 1
04/10/2012 1 1 2
04/11/2012 1 1 2
04/12/2012 1 1
04/13/2012 1 1 2
04/16/2012 1 1
04/17/2012 0
04/18/2012 0
Number of Events 6 9 15 7 7 6 4 1 4 10 69
RPP-RPT-58298 3/9/2015 - 7:47 AM 93 of 106
RPP-RPT-58298, Rev. 0
J-1
APPENDIX J
241-C-112 HARD HEEL RETRIEVAL ACTIVITIES EVENT ANALYSIS
RPP-RPT-58298 3/9/2015 - 7:47 AM 94 of 106
RPP-RPT-58298, Rev. 0
J-2
241-C-112 HHR Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
11/18/2013 0
11/19/2013 1 1
11/20/2013 1 1 1 3
11/21/2013 1 1
11/22/2013 1 1
11/25/2013 1 1
11/26/2013 1 1
11/27/2013 1 1
12/02/2013 1 1
12/03/2013 1 1
12/04/2013 1 1
12/09/2013 1 3 4
12/10/2013 1 1
12/11/2013 1 1
12/12/2013 1 1
12/19/2013 1 1 2
12/20/2013 1 1 2
12/23/2013 1 1
12/26/2013 1 1
12/27/2013 0
12/30/2013 1 1 2
12/31/2013 0
01/02/2014 0
01/03/2014 0
01/07/2014 1 1
01/08/2014 1 1
01/09/2014 0
01/10/2014 1 1
01/13/2014 0
01/14/2014 1 1 2 4
01/15/2014 0
01/16/2014 1 1 2
01/17/2014 1 1 2
01/20/2014 1 1
01/21/2014 1 1 2
01/23/2014 1 1
01/24/2014 1 1
01/27/2014 1 1 2
01/28/2014 0
01/29/2014 0
01/30/2014 1 1
01/31/2014 0
Number of Events 0 14 4 0 0 2 1 1 8 16 46
RPP-RPT-58298 3/9/2015 - 7:47 AM 95 of 106
RPP-RPT-58298, Rev. 0
K-1
APPENDIX K
EVALUATED RETRIEVAL ACTIVITIES EVENT ANALYSIS
RPP-RPT-58298 3/9/2015 - 7:47 AM 96 of 106
RPP-RPT-58298, Rev. 0
K-2
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
09/14/2010 1 1 2
09/15/2010 1 1
09/16/2010 1 1
09/17/2010 1 1
09/20/2010 1 1
09/21/2010 1 1 2
09/22/2010 1 1 2
09/23/2010 1 1
09/24/2010 0
09/25/2010 1 1
09/26/2010 1 1 2
09/27/2010 1 1 2
09/28/2010 1 1
09/29/2010 1 1
09/30/2010 1 1
10/01/2010 1 1
10/04/2010 0
10/05/2010 1 1
10/06/2010 0
10/07/2010 1 1
10/08/2010 1 1
10/11/2010 1 1
10/12/2010 0
10/13/2010 1 1
10/14/2010 1 1
10/15/2010 0
10/18/2010 1 1
10/19/2010 0
10/20/2010 0
10/21/2010 1 1
10/22/2010 1 1
10/25/2010 0
10/26/2010 1 1
10/27/2010 1 1
10/28/2010 1 1
10/29/2010 1 1
11/02/2010 0
11/03/2010 1 1 2
11/04/2010 1 1 2
11/05/2010 0
09/27/2011 1 2 3
09/29/2011 1 1
10/06/2011 1 1 2
10/07/2011 1 1
10/10/2011 1 1 2
10/11/2011 1 1
10/12/2011 1 1
RPP-RPT-58298 3/9/2015 - 7:47 AM 97 of 106
RPP-RPT-58298, Rev. 0
K-3
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
10/17/2011 1 1
10/18/2011 1 1 2
10/19/2011 1 1 1 3
10/20/2011 1 1 1 3
10/26/2011 1 1
10/27/2011 1 1 1 3
10/28/2011 1 1 2 4
11/02/2011 1 1
11/03/2011 0
12/27/2011 1 1 2
12/28/2011 1 1 2
12/29/2011 1 1 2
12/30/2011 1 1
01/03/2012 0
01/04/2012 1 1
01/05/2012 1 1
01/06/2012 1 1
01/09/2012 0
01/10/2012 1 1
01/11/2012 1 1
01/12/2012 1 1 2
01/13/2012 1 1 2
01/16/2012 1 1 2
01/17/2012 1 1
01/18/2012 0
01/23/2012 1 1
01/24/2012 1 1
01/25/2012 1 1
01/30/2012 1 1
01/31/2012 1 1 2
02/01/2012 1 1
02/02/2012 0
02/03/2012 0
02/06/2012 0
02/07/2012 1 1
02/08/2012 1 1
02/09/2012 1 1
02/10/2012 1 1
02/13/2012 1 1
02/14/2012 1 1
02/15/2012 1 1
02/16/2012 0
02/17/2012 0
02/20/2012 0
02/21/2012 1 1
02/22/2012 1 1
02/23/2012 1 1
RPP-RPT-58298 3/9/2015 - 7:47 AM 98 of 106
RPP-RPT-58298, Rev. 0
K-4
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
02/24/2012 1 1 2
02/27/2012 1 1
02/29/2012 1 1
03/01/2012 0
03/05/2012 1 1
03/06/2012 1 1
03/07/2012 0
03/08/2012 1 1
03/09/2012 1 1
03/12/2012 1 1
03/13/2012 0
03/14/2012 1 1
03/15/2012 0
03/16/2012 0
03/19/2012 1 1
03/20/2012 1 1
03/21/2012 1 1
03/23/2012 0
03/26/2012 1 1
03/27/2012 1 1
03/28/2012 0
03/29/2012 1 1 2
03/30/2012 0
04/02/2012 1 1 1 3
04/03/2012 1 1 2
04/04/2012 0
04/06/2012 1 1
04/10/2012 1 1 2
04/11/2012 1 1 2
04/12/2012 1 1
04/13/2012 1 1 2
04/16/2012 1 1
04/17/2012 0
04/18/2012 0
04/20/2012 1 1
05/01/2012 1 1
05/09/2012 0
05/10/2012 1 1 2
05/17/2012 1 1 2
05/18/2012 1 1
05/21/2012 1 1
05/22/2012 1 1
05/23/2012 2 2
05/24/2012 2 2
05/29/2012 1 1 1 3
05/30/2012 1 1 2
06/03/2012 1 1
RPP-RPT-58298 3/9/2015 - 7:47 AM 99 of 106
RPP-RPT-58298, Rev. 0
K-5
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
06/04/2012 1 2 1 4
06/05/2012 1 3 4
06/06/2012 1 1 2
06/07/2012 1 1 2
06/08/2012 1 1 1 3
06/11/2012 2 1 3
06/12/2012 2 1 1 4
06/13/2012 1 1 2
06/14/2012 1 1
06/18/2012 1 1
06/20/2012 0
06/21/2012 4 1 5
06/25/2012 1 1
06/26/2012 1 1 3 5
06/27/2012 1 1 2
06/28/2012 1 1 2
06/29/2012 0
07/02/2012 1 1 2
07/03/2012 1 1 2
07/05/2012 1 1
07/06/2012 2 2
07/09/2012 1 1
07/10/2012 1 1 1 3
07/11/2012 1 1 1 3
07/12/2012 1 1 2
07/13/2012 1 1 2
07/16/2012 1 1
07/17/2012 1 1 1 1 4
07/18/2012 3 1 2 6
07/19/2012 1 1
07/20/2012 1 1
07/26/2012 1 1 1 3
07/27/2012 0
07/30/2012 1 1 1 1 1 5
07/31/2012 1 1 2
08/06/2012 1 2 1 1 5
08/07/2012 1 1
08/08/2012 1 1
08/20/2012 1 1
08/21/2012 1 1
08/27/2012 1 1 2
08/28/2012 1 1 2
08/29/2012 1 1
08/30/2012 1 1
08/31/2012 1 1
09/04/2012 1 1
09/13/2012 1 1 1 3
RPP-RPT-58298 3/9/2015 - 7:47 AM 100 of 106
RPP-RPT-58298, Rev. 0
K-6
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
09/19/2012 1 1 1 3
09/20/2012 1 1 3 5
09/21/2012 1 1
12/10/2012 1 1
12/11/2012 1 1
12/18/2012 1 1
12/19/2012 1 1 2
12/20/2012 1 1 2
12/21/2012 0
12/26/2012 1 1
12/27/2012 1 1 2
12/28/2012 1 1 2
01/02/2013 1 2 3
01/03/2013 1 1
01/04/2013 0
01/07/2013 0
01/08/2013 1 1
01/09/2013 1 1 2
01/10/2013 1 1
01/11/2013 1 1 1 3
01/14/2013 1 1 2
01/15/2013 1 1 2
01/16/2013 1 1 2
01/17/2013 1 1
01/18/2013 1 1
01/21/2013 0
01/22/2013 1 1
01/23/2013 1 1
02/11/2013 1 1
02/12/2013 1 1
02/13/2013 1 1
02/14/2013 1 1
02/19/2013 1 1
02/20/2013 1 1 2
02/21/2013 1 1
02/22/2013 1 1
02/25/2013 1 1
02/26/2013 1 1 2
02/28/2013 1 1 2
03/01/2013 1 1 1 3
03/02/2013 1 1
03/05/2013 0
03/06/2013 0
03/07/2013 0
03/08/2013 1 1 2
03/11/2013 1 1
03/12/2013 1 1 2
RPP-RPT-58298 3/9/2015 - 7:47 AM 101 of 106
RPP-RPT-58298, Rev. 0
K-7
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
03/13/2013 1 1
03/14/2013 1 1
03/15/2013 0
03/18/2013 0
03/19/2013 0
05/05/2013 0
05/09/2013 1 1
05/13/2013 1 1
05/14/2013 1 1 2
05/15/2013 2 2
05/16/2013 1 1 2
05/17/2013 1 1 2
05/20/2013 1 1 2
05/21/2013 1 2 3
05/22/2013 1 1
05/28/2013 0
05/29/2013 1 1 2
05/30/2013 1 1
05/31/2013 1 1
06/03/2013 1 1
06/04/2013 1 1
06/05/2013 1 1 1 1 4
06/06/2013 0
06/07/2013 1 1
06/10/2013 1 1
06/11/2013 1 1
06/12/2013 1 1 2
06/13/2013 0
06/14/2013 1 1
06/17/2013 1 1
06/18/2013 1 1
06/19/2013 1 1
06/20/2013 1 1
06/26/2013 0
06/27/2013 1 1
06/28/2013 1 1 2
07/02/2013 1 1
07/03/2013 1 1 1 2 5
07/05/2013 1 1 2
07/08/2013 0
07/09/2013 1 2 3
07/10/2013 0
07/11/2013 1 1 2
07/12/2013 0
07/15/2013 2 2
07/16/2013 1 1
07/17/2013 0
RPP-RPT-58298 3/9/2015 - 7:47 AM 102 of 106
RPP-RPT-58298, Rev. 0
K-8
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
07/22/2013 1 1 2
07/23/2013 1 1
07/24/2013 0
07/24/2013 1 1
07/25/2013 1 1 1 3
07/26/2013 0
08/07/2013 2 2
08/08/2013 1 1
08/09/2013 0
08/12/2013 1 1
08/13/2013 0
08/14/2013 1 1
08/15/2013 1 1
08/16/2013 1 1
08/19/2013 1 1
08/20/2013 1 1
08/21/2013 2 2
08/26/2013 0
09/06/2013 0
09/09/2013 1 1 2
09/10/2013 0
09/11/2013 1 1
09/12/2013 1 1
09/24/2013 0
09/28/2013 0
09/29/2013 0
09/30/2013 0
11/18/2013 0
11/19/2013 1 1
11/20/2013 1 1 1 3
11/21/2013 1 1
11/22/2013 1 1
11/25/2013 1 1
11/26/2013 1 1
11/27/2013 1 1
12/02/2013 1 1
12/03/2013 1 1
12/04/2013 0
12/09/2013 3 3
12/10/2013 1 1
12/11/2013 1 1
12/12/2013 1 1
12/19/2013 1 1 2
12/20/2013 1 1 2
12/23/2013 0
12/26/2013 1 1
12/27/2013 0
RPP-RPT-58298 3/9/2015 - 7:47 AM 103 of 106
RPP-RPT-58298, Rev. 0
K-9
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
12/30/2013 1 1 2
12/31/2013 0
01/02/2014 0
01/03/2014 0
01/07/2014 1 1
01/08/2014 1 1
01/09/2014 0
01/10/2014 1 1
01/13/2014 0
01/14/2014 1 1 2 4
01/15/2014 0
01/16/2014 1 1 2
01/17/2014 1 1 2
01/20/2014 1 1
01/21/2014 1 1
01/23/2014 1 1
01/24/2014 1 1
01/27/2014 1 1 2
01/28/2014 1 1
01/29/2014 1 1 1 3
01/30/2014 1 1 2
01/31/2014 0
02/04/2014 1 1
02/10/2014 1 1
02/11/2014 1 1
02/12/2014 1 1
02/13/2014 1 1 1 3
02/14/2014 1 1
02/18/2014 1 1 2
02/19/2014 1 1
02/20/2014 1 1
02/21/2014 1 1
02/24/2014 1 1
02/25/2014 1 1 2
02/26/2014 1 1 2
02/27/2014 1 1
02/28/2014 1 1
03/03/2014 1 1
03/04/2014 1 1 2
03/05/2014 1 1
03/06/2014 1 1 2
03/07/2014 1 1
03/10/2014 1 2 3
03/11/2014 1 1 2
03/12/2014 1 1 2
03/13/2014 1 1
03/14/2014 1 1
RPP-RPT-58298 3/9/2015 - 7:47 AM 104 of 106
RPP-RPT-58298, Rev. 0
K-10
Retrieval Activities Event Analysis
Date Hydraulic Leak Ventilation
Issues Camera
Supernatant Pump Start-Up /
Shut-Down
Supernatant Pump Flow
Slurry Pump Flow
Slurry Pump Movement
Sluicer / ERSS / ARM Movement
Hydraulic Fluid Temperature
Miscellaneous Total
03/17/2014 1 1 2
03/25/2014 1 1
03/26/2014 1 1
03/27/2014 1 1
03/28/2014 1 1
04/23/2014 0
Number of Events 28 86 42 13 34 102 20 18 35 109 487
RPP-RPT-58298 3/9/2015 - 7:47 AM 105 of 106
RPP-RPT-58298, Rev. 0
1-1
ATTACHMENT 1
REFERENCE MATERIALS
Due to the size of the documents, the reference materials included in this attachment are
provided electronically in the Smart Plant Foundation database with this report.
RPP-RPT-58298 3/9/2015 - 7:47 AM 106 of 106