Upload
dotu
View
217
Download
4
Embed Size (px)
Citation preview
1
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: RES13970
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING
OF
NATIONAL ROADS IMPROVEMENT AND MANAGEMENT PROGRAM (APL) PHASE 2
LOAN IBRD-7552-PH
BOARD APPROVAL DATE: MAY 13, 2008
TO THE
REPUBLIC OF THE PHILIPPINES
December 12, 2014
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
GTIDR
EAST ASIA AND PACIFIC
This document has a restricted distribution and may be used by recipients only in the performance of
their official duties. Its contents may not otherwise be disclosed without World Bank authorization.
3
ABBREVIATIONS AND ACRONYMS
BQS
CPS
Bureau of Quality and Safety
Country Partnership Strategy
DPWH
FM
GOP
IAS
Department of Public Works and Highways
Financial Management
Government of Philippines
Internal Audit Services
ICD
IPE
Irap
ISAP
Institutional Capacity Development
Independent Procurement Evaluator
International Road Assessment Program
Integrity Strengthening Action Plan
LGU Local Government Unit
LTPBM Long-Term Performance-Based Maintenance
NRIMP2 National Roads Improvement and Management Program Phase 2
NRS
OCCP
National Road System
Organizational Culture Change Program
PDO Project Development Objective
PMO Project Management Office
PMS Pavement Management System
RI
SEMS
Road Improvement
Social and Environment Management System
4
UTF AusAID-World Bank Umbrella Trust Fund
Regional Vice President: Axel van Trotsenburg
Country Director:
Sector Director:
Motoo Konishi
John Roome, EASSD (through June 30, 2014)
Senior Global Senior Practice Director:
Global Practice Director:
Sector Manager
Practice Manager:
Pierre Guislain (from July 1, 2014)
Jose Luis Irigoyen (from July 1, 2014)
Ousmane Dione, EASPS (through June 30, 2014)
Michel Kerf (from July 1, 2014)
Task Team Leader: Ashok Kumar
5
PHILIPPINES
NATIONAL ROADS IMPROVEMENT AND MANAGEMENT PROGRAM (APL) PHASE 2
CONTENTS
Page
A. SUMMARY 6
B. PROJECT STATUS 8
C. PROPOSED CHANGES 9
ANNEX 1: RESULTS FRAMEWORK AND MONITORING 20
ANNEX 2: OPERATIONAL RISK ASSESSMENT FRAMEWORK 27
6
PROJECT RESTRUCTURING DATA SHEET
Philippines
National Roads Improvement and Management Program (APL) Phase 2 (P079935)
EAST ASIA AND PACIFIC
Report No: RES13970
Basic Information
Project ID: P079935 Lending Instrument: Adaptable Program Loan
Regional Vice President: Axel van Trotsenburg Original EA Category: Partial Assessment (B)
Country Director: Motoo Konishi Current EA Category: Partial Assessment (B)
Senior Global Practice
Director: Pierre Guislain Original Approval Date: 13-May-2008
Practice
Manager/Manager: Michel Kerf Current Closing Date: 31-Dec-2014
Team Leader: Ashok Kumar
Borrower: Republic of the Philippines
Responsible
Agency: Department of Public Works and Highways
Restructuring Type
Form Type: Full Restructuring Paper Decision Authority: Board Approval
Restructuring Level: Level 1
7
Financing ( as of 07-Nov-2014 )
Key Dates
Project Ln/Cr/TF Status Approval
Date Signing Date
Effectiveness
Date
Original
Closing Date
Revised
Closing Date
P079935 IBRD-75520 Effective 13-May-2008 24-Oct-2008 16-Apr-2009 31-Dec-2012 31-Dec-2014
Disbursements (in Millions)
Project Ln/Cr/TF Status Currency Original Revised Cancelled Disbursed Undis-
bursed
% Dis-
bursed
P079935 IBRD-75520 Effective USD 232.00 232.00 0.00 112.02 119.98 48
8
Policy Waivers
Does the project depart from the CAS in content or in other significant respects? Yes [ ] No [ X ]
Does the project require any policy waiver(s)? Yes [ ] No [ X ]
A. Summary of Proposed Changes
This proposed restructuring of the Second National Road Improvement Management Project (NRIMP2) is being
undertaken in response to the request of the Borrower (the Republic of the Philippines) to allow DPWH to
provide urgent technical assistance to Local Government Units (LGUs) for reconstruction and rehabilitation of
local infrastructure in Typhoon Yolanda/Haiyan affected areas and mapping of local roads network in
Mindanao. The Government of Philippines (GOP), as per its policy to “build back better”, has deputed DPWH to
provide high quality technical assistance, overall policy guidance and oversight, and project management
support to LGUs which lack the required capacity and technical expertise to support this policy. To
accommodate the expanded scope of the original PDO that focused on the national road system, the PDO will
be revised to the following: “to improve the condition of the national roads network and management
effectiveness of the Department of Public Works and Highways (DPWH) at national and local level”. This is a
level 1 restructuring because of the change in the PDO. Other proposed changes are:
a. Modifications in the Results Framework mainly to include outcome indicators that will measure the
management effectiveness of DPWH at the local level, and align and link indicators to each of the PDO
outcomes;
b. Extension of the Loan Closing Date from December 31, 2014 to December 31, 2016 to enable DPWH to
provide the proposed technical assistance, implement the ongoing asset preservation works, and carry
forward the on-going institutional capacity development initiatives which are critical to accomplish the PDO;
c. Addition of a new component “C: Technical Assistance to LGUs amounting to US$8.1 million”;
d. Increase in Bank Financing percentage from 50 percent to 75 percent for Expenditure Category 2A Civil
works for “National Road Improvement Works” component under Part A.1 and from 36 percent to 75 percent
for Expenditure Category 2B Civil works for “Long Term Performance Based Maintenance (LTPBM) Contracts”
component under Part A.2 (a) of the Project;
9
e. Reallocation of US$30.22 million from Expenditure Category 2A Civil Works under Part A.1 (Road
Improvement Works) to Expenditure Category 1 (Goods, Consultant Services, Training and Workshops) for
US$12.167 million and to Expenditure Category 2B Civil Works under Part A.2a (LTPBM) for US$18.053 million.
f. Change in Australian co-financing, as all funds from the Government of Australia was used for separate
Australian technical assistant project or shifted to other parallel technical assistance activities to support
NRIMP2 (and not Borrower-executed activities); and
g. Changes in Social and Environment Management System Policy Framework (SEMS) to incorporate
management of social and environment aspects during the design and supervision of
rehabilitation/reconstruction of local infrastructure works;
h. Change in the Legal Covenant, as DPWH will now use its Bureau of Quality and Safety (BQS) and
Internal Audit Services (IAS) to provide integrity support services instead of the consulting firm that was
originally envisaged under Australian financing. The legal covenant in paragraph 4, Section I of Schedule 2 to
the Loan Agreement will be amended accordingly.
This restructuring follows the previous restructuring of the project undertaken in December 2012 to extend
the Loan Closing Date from December 31, 2012 to December 31, 2014 and modified the project scope and
activities.
Change in Implementing Agency Yes [ ] No [ X ]
Change in Project's Development Objectives Yes [ X ] No [ ]
Change in Results Framework Yes [ X ] No [ ]
Change in Safeguard Policies Triggered Yes [ ] No [ X ]
Change of EA category Yes [ ] No [ X ]
Other Changes to Safeguards Yes [ X ] No [ ]
Change in Legal Covenants Yes [ X ] No [ ]
10
Change in Loan Closing Date(s) Yes [ X ] No [ ]
Cancellations Proposed Yes [ ] No [ X ]
Change to Financing Plan Yes [ X ] No [ ]
Change in Disbursement Arrangements Yes [ ] No [ X ]
Reallocation between Disbursement Categories Yes [ X ] No [ ]
Change in Disbursement Estimates Yes [ X ] No [ ]
Change to Components and Cost Yes [ X ] No [ ]
Change in Institutional Arrangements Yes [ ] No [ X ]
Change in Financial Management Yes [ ] No [ X ]
Change in Procurement Yes [ ] No [ X ]
Change in Implementation Schedule Yes [X] No [ ]
Other Change(s) Yes [ ] No [ X ]
Appraisal Summary Change in Economic and Financial Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Technical Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Social Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Environmental Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Risk Assessment Yes [ ] No [ X ]
B. Project Status
Both overall project implementation and progress towards achievement of PDO have been rated as
“moderately satisfactory” or above since May 2013. Most of the civil works under the project are approaching
satisfactory completion. There are no significant safeguards and fiduciary related issues. The progress on
institutional capacity development initiatives is impressive, and the senior management of DPWH is showing
11
high level of commitment to institutional development initiatives supported under the project.
National Road Improvement and Asset Preservation Works: All of the road improvement works have been
substantially completed. Despite the delayed start, all four LTPBM contracts are progressing well
(implementation period 2013 to 2018). DPWH is synthesizing the experiences gained from these contracts for
their wider application on the national road network to promote efficient delivery of maintenance works.
DPWH has decided to implement road safety improvement schemes on these contracts during the proposed
extension period. The “Year 1” and “Year 2” preventive maintenance works have been substantially
completed. “Year 3” and “Year 4” preventive maintenance works are either under an advanced stage of
procurement or at the beginning of implementation.
Institutional Capacity Development (ICD): This component is supporting overall transformation of DPWH.
DPWH is now using a Pavement Management System for allocating the Road Fund Budget. Road Board
Secretariat policy and procedures are being improved to institute internal controls for approvals and release of
funds. DPWH has established a Road and Bridge Management Information System for the entire national road
network in Geographical Information System Platform. The e-NGAS (New Government Accounting System) and
e-Budget have been implemented in 203 offices of DPWH as part of financial management reforms. DPWH has
made substantial reduction in the unreconciled general ledger balances with the associated subsidiary ledgers,
improving the accuracy and reliability of financial information and reporting. It is introducing “Organizational
Culture Changes” in its various offices including regions and districts through IT-enabled process improvements
such as Multi-Year Programming and Scheduling, Electronic Project Life cycle, enhanced Project and Contract
and Management Application, and Executive Information System to assist management in the monitoring of
civil works projects including procurement.
DPWH is also (i) upgrading its IT infrastructure and communication network in its various offices to support the
above initiatives; (ii) preparing right-of-way legislation to improve right-of-way acquisition; (iii) expanding its
current Data Administration Program into a full Data Governance Program; (iv) implementing an “Integrity
Strengthening Action Plan” and a comprehensive Rationalization Plan in various offices; (v) preparing road
safety improvement schemes on major traffic corridors (supported through the World Bank Global Road Safety
Facility); (vi) reforming DPWH public procurement using a state-of-the-art e-procurement system; and (vii)
preparing comprehensive design guidelines to improve design practices for national roads.
Procurement and Financial Management (FM): All major procurements under the project have been
completed, except for a few preventive maintenance works. Overall FM is rated moderately satisfactory and
Procurement satisfactory. There are no pending audit reports.
12
Social and environment safeguards are currently rated satisfactory. All land acquisition and compensation
packages have been fulfilled. Ten Environmental Assessments/Environment Management Plans, two
Indigenous People Development Plans, and nine Resettlement Action Plans have been prepared and
implemented under the project after approval from the Bank. The Environmental and Social Safeguards
Division of DPWH is ensuring effective management and monitoring of safeguards issues for the project roads.
Project Disbursements/Allocations: Out of US$232 million of the Bank funds, US$112 million have been
disbursed to date, and additional US$25 million would be disbursed by December 31, 2014, leaving an
unutilized amount of about US$95 million if there were no restructuring. The breakdown of this amount by
component is as follows: National Roads Improvement (NRI, US$36 million); LTPBM (US$32 million);
Preventive Maintenance (US$12 million); and Institutional Capacity Development (ICD, US$15 million). The NRI
component could not use its full loan allocation because three (3) road improvement packages were dropped
from the project scope to be funded locally, and at the same time for NRIMP2 packages, there were lower bid
prices compared to original estimates. LTPBM and PM procurement was delayed because priority was given
by the implementing agency to NRI procurement, the biggest component of the project. This however allowed
more extensive discussion to resolve policy questions and administrative issues regarding LTPBM and PM
contracts. From an original program of eight (8) LTPBM contract packages, DPWH decided to pursue four (4) in
Luzon, Mindoro and Panay, but the existing road conditions warranted higher civil works cost across all four (4)
packages. Each annual PM program consists of 8-10 civil works packages that are procured using national
competitive bidding procedures. Selection of road sections required coordination with and approval of the
Road Board. Given the delayed start, the project was able to finance two out of the initially planned four years
of PM contracts before the current closing date. The scope and packaging of several ICD contracts were
reviewed prior to procurement causing some delays. There are currently 16 ICD goods and consultancy
contracts, and additional contracts are expected to be procured in the extension period.
C. Proposed Changes
Development Objectives/Results
Project Development Objectives
Original PDO
The Program goal is the establishment of road management arrangements which ensure the upgrading and
13
preservation of the National Road System (NRS) in an environmentally, socially and financially sustainable
manner.
The development objective for Phase 2 is: Improved operation, organizational effectiveness and fiduciary
control in the management and financing of the national road system, to enhance road user satisfaction in the
project areas and efficiency and integrity in the use of financial resources.
Change in Project's Development Objectives
Explanation
The change in project development objective is proposed to allow DPWH to provide technical assistance to
LGUs for reconstruction and rehabilitation of local infrastructure sub-projects in Typhoon Yolanda/Haiyan
affected areas and mapping of local roads network in Mindanao (as per DPWH’s request dated April 4, 2014).
The PDO has also been reformulated to better align and link it to various project activities, and to clarify the
achievements and transformations expected from this project. This reformulated PDO also clarifies and
simplifies the expected achievements envisioned from this project given its expansion towards providing
assistance to LGUs’ rehabilitation and reconstruction efforts. Apart from including the technical assistance to
LGUs (US$8.1 million; involving about 3 percent of the Bank funding), the project will continue to focus on the
activities supported under the original PDO.
Typhoon Yolanda (international code name: Haiyan) has caused large scale destruction to physical
infrastructure in Philippines in November 2013. GOP has been undertaking recovery programs to avoid
national losses equivalent to one percent of GDP due to typhoon Yolanda. These programs include
rehabilitation and reconstruction of local infrastructure through LGUs, which are also being supported by many
donors, NGOs and the private sector. Two World Bank-assisted projects, the Regional Infrastructure for
Growth Project (RIGP; P108904) and the Support for Strategic Local Development and Investment Project
(SSLDIP; P064925) are being restructured to provide financial assistance to LGUs for post-disaster
rehabilitation/reconstruction of local infrastructure.
GOP is committed to support LGUs both financially and technically to effectively prepare and implement a
large number of post-disaster reconstruction and rehabilitation sub-projects, using cost-effective and climate
resilient designs, ensuring value for money and adequate quality of construction, and avoiding time and cost
overruns. To achieve this and pursue its policy to “build back better”, GOP has deputed the national agency,
“DPWH”, to provide high quality technical assistance, overall policy guidance and oversight, and project
management support to LGUs. The LGUs are responsible for preparing and delivering the local infrastructure
sub-projects but lack the required capacity and technical expertise. The proposed technical assistance under
this project will enable LGUs to quickly prepare and implement a large number of sub-projects with technical
support from consultants having experience and expertise in post-disaster reconstruction works, operating
14
under the overall guidance and oversight of DPWH. Apart from meeting these needs, the proposed technical
assistance will see significant improvements in the way local infrastructure is designed and delivered by LGUs
and set new models for partnership between DPWH and LGUs.
The restructured NRIMP2 will only finance technical assistance in relation to the above sub-projects. Civil
works under those will be financed under the RIGP and SSLDIP or from other sources.
Proposed New PDO
To improve the condition of the national roads network and management effectiveness of the Department of
Public Works and Highways at national and local level.
Change in Results Framework
Explanation:
The changes in the results framework are being sought to: (i) include outcome indicators that will measure
management effectiveness of DPWH at the local level and the improved condition of national roads network;
(ii) clearly align and link results indicators with each of the PDO outcomes; (iii) include Core Sector indicators;
(iv) drop or modify results indicators that are either not measurable or outside the project scope; and (v)
capture important institutional development initiatives which are missing in the current results framework.
Annex I shows the revised results framework after incorporating these changes. Some of the important
changes are as follows:
PDO Level:
The first PDO indicator “Administrative Efficiency – project delivery time reduced” is modified to
“Administrative Efficiency – percentage of projects delivered with less than 15 percent excess to original cost
and time” which is considered a better definition of administrative efficiency. It was difficult to fix a common
delivery time to a variety of contract sizes;
The second PDO indicator “Sustainability of financing for NRS asset management – Increased cost recovery
from road users” is revised to “Improved asset management of National Road Network – Percentage of roads
in good and fair condition as a share of total classified national roads”. This is also a Core Sector Indicator.
There is no project activity linked to increased cost recovery;
15
The third PDO indicator “Value for money – Medium-term average cost of preserving national paved roads
reduced” is dropped as it is hard to measure value for money. The cost of preserving national roads would vary
widely according to traffic, climate, technical specifications, and many other factors. DPWH has no reliable
data (yet) to measure this indicator; and
The fourth PDO indicator “Road user satisfaction with the National Road System (NRS)” is revised to
“Percentage of satisfactory perception of external stakeholders with the National Road System (NRS)” as
DPWH is currently undertaking regular surveys for “external stakeholder perception” after the closure of the
consultancy services to measure road user satisfaction.
New PDO Indicators:
“Percentage of local infrastructure subprojects, receiving technical assistance under the project, that are in
compliance with the prescribed technical standards by DPWH” to capture management effectiveness of DPWH
at the local level.
“Percentage of DPWH’s infrastructure projects subjected to life cycle monitoring using improved IT enabled
tools” to capture management effectiveness of DPWH at the national level.
New Intermediate Outcome Indicators:
“Number of kilometers of National Roads rehabilitated, non-rural” is added as a Core Sector Indicator. Other
new and revised indicators are shown under Annex I.
Compliance
Other Changes to Safeguards
Explanation:
The current Social and Environment Management System Policy Framework (SEMS) for NRIMP2 is mainly
focused on national roads. Therefore, DPWH has revised it to ensure effective management of social and
environment aspects during the detailed engineering designs and construction supervision for local
infrastructure (e.g., schools, clinics, public markets, water systems, municipality buildings) under the
16
restructured project to ensure compliance with the Bank polices and to introduce good practice examples as
per the “build back better” policy. Rehabilitation/reconstruction of local infrastructure is not expected to
generate significant social and environment impacts as the local infrastructure will mostly be
rehabilitated/reconstructed at their existing sites. Most of the impacts would be construction related and
could be managed using good construction practices as defined in the technical specifications.
DPWH will also introduce many good practice examples of design and construction of local infrastructure such
as use of climate resilient and environmentally optimized engineering designs, improved drainage,
construction waste management, community oversight, and construction related impacts. These good
practices will be integrated with the current design guidelines, technical specifications, and construction
procedures that will be used by DPWH. Suitable training will be provided to the local engineers and LGUs on
the use of these good practices.
Already DPWH has an environmental policy which requires integration of environmental and social concerns in
all stages of the project cycle of an infrastructure sub-project. The revised SEMS includes simplified screening
procedures for local infrastructure subprojects which are to be used by the design consultants to identify the
site-specific environmental and social impacts that may be generated by the restoration of the damaged local
infrastructure. The revised SEMS is fully consistent with the Environment and Social Management Frameworks
of the restructured RIGP and SSLIDP (already agreed by the Bank) which will be funding most of the
rehabilitation/reconstruction works. The design consultants will prepare sub-project specific safeguard
documents to mitigate the impacts identified through the screening process. The revised SEMS also defines
the institutional responsibility of managing the safeguards aspects during the design stages of the sub-projects.
The DPWH has carried out requisite consultations on the revised SEMS with LGUs and locally disclosed it on
October 28, 2014. The same has also been re-disclosed in the Bank Infoshop on October 30, 2014.
Change in Legal Covenants
Explanation:
Paragraph 4 of Section I, Schedule 2 of the Loan Agreement requires that a consulting firm be engaged by the
Government of Australia (parallel co-financier of the project) to provide integrity support services to DPWH.
However, the subsidiary arrangements for the Australian co-financing closed before there were a sufficient
number of road works under implementation under NRIMP2 to justify engagement of an audit firm. The legal
covenant in the Loan Agreement was not dated, i.e., there was no specific date by which the consulting firm
had to be engaged. By the time all parties concerned agreed that the consulting firm should be engaged, the
17
subsidiary arrangements for the AusAID co-financing had already closed. In addition, the Bureau of Quality
and Safety (BQS) had been established within DPWH which was non-existent at the time of project approval..
DPWH is already using BQS and IAS to undertake regular audits of its various activities including the civil works
supported under NRIMP2. The Bank reviewed the guidelines on audit procedures, and sample reports and
outputs of BQS and IAS, and found that these will meet the expected standards. IAS reports directly to the
Secretary of DPWH. Using BQS and IAS for the audit of project activities will further strengthen DPWH’s
capacity to undertake regular audits of the entire national roads network. The Bank will closely review the
audit reports including compliance with the observations made during the audit.
Paragraph 4 of Section 1, Schedule 2 of the Loan Agreement will, therefore, be amended to require DPWH to
undertake the necessary integrity support services, which will be provided by its BQS and IAS. The technical
audits will be done on a semi-annual basis, or as often as otherwise agreed with the Bank for specific NRIMP2
activities.
Further, paragraph 5 of Section 1, Schedule 2 of the Loan Agreement requires that a consulting firm be
engaged by the Government of Australia (co-financier of the project) to assist DWPH to implement its
Rationalization Plan. The consulting firm was not engaged by the Government of Australia as DPWH used the
“Project Management and Coordination Consultant” already engaged under NRIMP2 to assist in implementing
the Plan. DPWH, nevertheless, implemented its Rationalization Plan as required. The legal covenant in
paragraph 5 of Section 1, Schedule 2 of the Loan Agreement is therefore amended to remove the reference to
the consulting firm to be engaged by the co-financier, but the obligations on DPWH otherwise remain the
same.
Ln/Cr/TF
Finance
Agreement
Reference
Description of Covenant Date Due Status Recurrent Frequenc
y Action
IBRD-
75520 Section 1. 3
The Borrower shall
undertake semi-annual
internal audits for
DPWH’s operations and
Project accounts.
Complied
with
SemiAnn
ual
No
Change
IBRD-
75520 Section 1.5
The Borrower shall
implement its
Rationalization Plan after
31-Oct-
2011
After delay
complied
with
Revised
18
approval by DBM in the
event that the
Rationalization Plan is
not put in to effect,
develop a plan.
IBRD-
75520 Section 1.6
The Borrower through
DPWH shall post the
Road Watch report cards
on its website by
November 30, 2009, and
biannually on November
30thereafter.
30-Nov-
2011
Complied
with
No
Change
IBRD-
75520 Section 1.7
Within one month, the
Borrower shall publish a
business plan comprising
of its proposed annual
program for next year
and the expenditure
incurred and outputs
delivered in the previous
year.
31-Dec-
2009
Complied
with
No
Change
IBRD-
75520 Section 1.8
The Borrower through
DPWH shall furnish to
the Road Partners a road
assets preservation plan
for the national road
networks.
31-Mar-
2012
Complied
with
No
Change
IBRD-
75520 Section 1.10
The Borrower shall
ensure that amendments
updating the operations
and responsibilities of
the Road Board will be
approved by DPWH and
the Department of
Transport and
Communications.
31-Mar-
2011
After delay
complied
with
No
Change
19
IBRD-
75520 Section 1. 11
The Borrower shall
submit a progress report
on implementing the
Integrity Strengthening
Action Plan.
31-Oct-
2011
Complied
with
No
Change
IBRD-
75520 Section 1.12
The Borrower shall
complete the
implementation of
recommendations arising
from its 2006 external
audit report.
30-Jun-
2011
Complied
with
No
Change
IBRD-
75520 Section II. B.1
Maintain a financial
management system and
prepare financial
statements in
accordance with
consistently applied
accounting standards
Complied
with
Yearly No
Change
IBRD-
75520 Section II. B.2
Furnish quarterly interim
unaudited financial
report to the Bank, not
later than one month
after each calendar
quarter
Complied
with
Quarterly No
Change
IBRD-
75520 Section II. B.3
Financial statements to
be audited by
independent auditors
acceptable to the Bank
and audit report
submitted to the Bank
not later than six month
after the end of each
fiscal year.
Complied
with
Yearly No
Change
IBRD-
75520 Section 1.4
The Borrower shall
undertake technical
audits on Project
Not yet due
SemiAnn
ual Revised
20
expenditures and
implementation of
Project activities.
Financing
Change in Loan Closing Date(s)
Explanation:
The current Loan Closing Date of December 31, 2014 is proposed to be extended by two years to December
31, 2016 to enable DPWH to implement the following activities by using about US$95 million of undisbursed
balance beyond the current closing date:
a) Provide technical assistance to LGUs for reconstruction and rehabilitation of local infrastructure in
Typhoon Yolanda/Haiyan affected areas and mapping of local road network in Mindanao (US$8
million);
b) Finance an increased share of the civil works under NRI (for payments made after March 31, 2014)
(US$6 million);
c) Implement the remaining activities of the ongoing LTPBM contracts, at an increased financing share
(after March 31, 2014), including road safety infrastructure improvements (US$50 million);
d) Implement ongoing Year 3 and 4 Preventive Maintenance Program, as originally envisaged (US$ 12
million);
e) Build on and carry-forward the ongoing institutional development initiatives (US$19 million).
The proposed two years extension is essential to accomplish the above activities and to achieve the PDO.
Continued Bank support is critical to ensure effective implementation of the comprehensive and rich
institutional agenda supported under the project which, when fully implemented, will see major reforms in the
management of the national road network in the Philippines and organizational effectiveness of DPWH. DPWH
will also be able to synthesize the rich experience being gained through implementation of LTPBM contracts
and road safety improvements for their wider application on the national road network ensuring efficient
delivery of maintenance and improved road safety. It will also allow the Bank to further deepen and enhance
its engagement in the road sector in Philippines.
The proposed extension meets the requirements of paragraph 47 of BP 10.00 as the revised PDO is achievable
within the extended period; the performance of DPWH remains satisfactory; and the Bank and the Borrower
have already identified the activities to be supported during the proposed extension period and agreed on the
21
actions to be taken to complete those during the last implementation support mission in May 2014 and
subsequent discussions with DPWH. All the technical assistance activities are to be procured latest by March
31, 2015.
Ln/Cr/TF Status Original Closing
Date
Current Closing
Date Proposed Closing Date
Previous Closing
Date(s)
IBRD-
75520 Effective 31-Dec-2012 31-Dec-2014 31-Dec-2016 31-Dec-2012
Change to Financing Plan
Explanation:
The Government of Australia (through then AusAID) originally committed to allocate parallel co-financing of
US$10.5 million for various activities under the Institutional Capacity Development (ICD) component of
NRIMP2. This amount was to be allocated from two existing grant facilities provided by the Government of
Australia under Subsidiary Agreements with the Government. Of this amount, US$6.72 million was granted to
support the Independent Procurement Evaluator (IPE), Road Partnership Support (with Bantay Lansangan or
RoadWatch), Financial Management, Internal Control and Internal Audit Capacity Building activities. These
activities were executed by AusAID through its Partnership for Economic Governance Reforms under a
Subsidiary Agreement with the Government. This grant facility has since ceased operation. As part of the first
restructuring of the Project in December 2012, implementation of the two governance activities (Corporate
Modernization and Support to the Integrity Strengthening Action Plan), which were to be funded and managed
under the AusAID grant, were shifted to be executed by DPWH. However, these two activities have been
absorbed by the existing DPWH functions and consultants, and under a Bank-executed technical assistance
package. Therefore, all references to the AusAID co-financing will be removed from the Loan Agreement. This
does not change the amount of the Bank’s loan.
It is proposed to increase the Loan Financing percentage from 50 percent to 75 percent for Expenditure
Category 2A for Civil Works under Part A.1 “National Road Improvement Works component”, and from 36
percent to 75 percent for Expenditure Category 2B for Civil Works under Part A.2 (a) “Long Term Performance
Based Maintenance Contracts component” of the Project. These changes are to be applied to the unpaid
balance as of March 31, 2014 as per the DPWH request of May 21, 2014. The proposed change will allow the
Borrower to fully utilize the loan funds given that a number of projects on road improvement have achieved
substantial completion progress with relatively low disbursements of 48 percent. This will also reduce the
Borrower’s counterpart contribution from US$333.52 million to US$270.26 million.
Considering the above, the percentages of Eligible Expenditures to be financed will be amended in Section
22
IV.A.2, Schedule 2 of the Loan Agreement, and the project financing plan is to be changed as follows (The
figures are in USD):
Source(s) At Approval Current (from AUS) Proposed
AUSL 10,500,000.00 10,500,000.00 0.00
BORR 333,520,000.00 333,520,000.00 270,260,000.00
IBRD 232,000,000.00 232,000,000.00 232,000,000.00
Total 576,020,000.00 576,020,000.00 502,260,000.00
Reallocations
Explanation:
The National Road Improvement Works component (Expenditure Category IBRD75520 CW PT A1) would have
an unutilized allocation of US$30.22 million after accounting for the increase in Bank financing percentage to
this component. On the other hand, there would be a shortfall of US$18.053 million to fund the LTPBM
contracts (Expenditure Category IBRD75520 CW PT A2a) with a revised Bank financing percentage (current
allocations US$53 million; requirements US$72.053 million). Finally, US$55.587 million are required (under the
Expenditure Category IBRD75520 GO CS TR WS) to support the technical assistance to LGUs (US$8.1 million)
and ongoing institutional development initiatives but only US$43.42 million are currently available, which
means additional allocation of US$12.167 million is needed. Thus the estimated unutilized amount of
US$30.22 million is proposed to be reallocated to meet the requirements of LTPBM and ICD as shown in the
Table below. The current allocation of US$32 million for Year 1 to 4 Preventive Maintenance Programs will be
adequate.
Ln/Cr/TF Currency Current Category of
Expenditure Allocation
Disbursement % (Type
Total)
Current Proposed Current Proposed
IBRD-75520 USD IBRD75520 GO CS TR WS 43,420,000.00 55,587,000.00 100.00 100.00
IBRD75520 CW PT A1:
Nat. Road Improvement
103,000,000.0
0 72,780,000.00 50.00 75.00
IBRD75520 CW PT A2(a): 53,000,000.00 71,053,000.00 36.00 75.00
23
LTPBM
IBRD75520 CW PT A2(b)
FY08 8,000,000.00 8,000,000.00 100.00 100.00
IBRD75520 CW PT A2(b)
FY09 8,000,000.00 8,000,000.00 100.00 100.00
IBRD75520 CW PT A2(b)
FY10 8,000,000.00 8,000,000.00 100.00 100.00
IBRD75520 CW PT A2(b)
FY11 8,000,000.00 8,000,000.00 100.00 100.00
IBRD75520 PREMIA INT
RATE CAP 0.00 0.00 0.00 0.00
Designated Account 0.00 0.00 0.00 0.00
FRONT END FEE 580,000.00 580,000.00 0.00 0.00
Total: 232,000,000.0
0
232,000,000.0
0
Disbursement Estimates
Change in Disbursement Estimates
Explanation:
The revised disbursement estimates, taking into account the increase in Bank financing percentage to the Road
Improvement Works and LTPBM contracts, reallocation to different categories, technical assistance to LGUs
and implementation of the ongoing institutional development initiatives during the proposed extension period
are as follows:
Fiscal Year Current (USD) Proposed (USD)
2008 0.00 0.00
2009 580,000.00 580,000.00
24
2010 5,016,860.11 5,016,860.11
2011 8,222,118.45 8,222,118.45
2012 15,657,138.01 15,657,138.01
2013 36,940,022.47 36,940,022.47
2014 33,279,066.95 33,279,066.95
2015 12,316,933.61 61,880,794.01
2016 45,000,000.00
2017 26,000,000.00
Total 111,436,139.60 232,000,000.00
Components
Change to Components and Cost
Explanation:
A new component “C Technical Assistance to Local Government Units” has been added to allow DPWH to
provide technical assistance support LGUs on post-disaster reconstruction activities. The new component is
described as follows:
“Component C: Technical Assistance to Local Government Units (US$8.1 million): To support DPWH to provide
technical assistance support to LGUs to prepare and effectively deliver good quality, cost-effective, and climate
resilient sub-projects for reconstruction and rehabilitation of local infrastructure in the Typhoon
Yolanda/Haiyan affected areas. This technical assistance will include: (a) selection of sub-projects, detailed
engineering designs, management of social and environment issues, and preparation of contract document of
various infrastructure such as city/municipal/barangay halls, classrooms, public hospitals/health centers, local
roads, water supply and irrigation facilities; (b) construction supervision for local infrastructure; (c) project
management and capacity building support to DPWH and LGUs including training, workshops, and preparation
of related technical documents; and (d) preparation of maps and road inventory data-base for local roads
network in Mindanao”.
25
The above component will be implemented in a way to complement the restructured RIGP and SSLIDP as well
as the multi-donor support to the affected areas. DPWH would mobilize 50 licensed engineers and 100
engineering graduates to augment its capacity to respond to the technical assistance needs of the LGUs. It
would also engage a coordinating consultant to provide overall technical supervision; undertake field
investigations and site surveys; prepare/review detailed engineering designs, and tender documents; assist in
procurement of local infrastructure works; and conduct output measurements and independent verifications
of engineering designs, safeguard documents, and construction quality to ensure their compliance to the
prescribed standards and Bank’s safeguards policies. DPWH plans to procure all the technical assistance
services before March 31, 2015, leaving sufficient time for their execution. The responsibility to implement this
component remains with DPWH.
Consultancy activities under A.3 Maintenance Engineering Services, B.2 Corporate Effectiveness and Integrity,
and B.3 Strategic Road Sector Reform in the table below were implemented under the ICD component.
Moreover, selected activities under B.2 and B.3 were implemented by DPWH and Road Board with local
funding or with existing consultants,
Costs: The revised costs of various project components are given below. The total cost of the National Road
Improvement component has been reduced from US$238.50 million to US$183.67 million due to its reduced
scope because of the dropping of some roads and bridges, and lower bid prices compared to the original
estimates. Similarly, the total cost of the LTPBM contracts component is also reduced marginally from
US$280.80 million to US$269.52 million, mainly due to lower bid prices compared to the estimated costs.
Current Component
Name
Proposed Component
Name
Current Cost
(US$M)
Proposed Cost
(US$M) Action
C. Technical Assistance to
LGUs 8.10 New
A.1 National Road
Improvement
A.1 Road Network
Improvement 238.50 183.67 Revised
A.2 Road Asset
Preservation
A.2 Road Asset
Preservation 280.80 269.52 Revised
A.3 Maintenance
Engineering Services 2.80 0.00
Merged under B.
ICD
26
B.1 Optimization of
Business Process
improvements
B. Institutional Capacity
Development 47.10 40.39 Revised
B.2 Corporate
Effectiveness and
Integrity
7.50 0.00 Merged under B.
ICD
B.3 Strategic Road Sector
Reform 1.20 0.00
Merged under B.
ICD
Front End Fee 0.58
Total: 577.90 502.26
27
ANNEX 1: RESULTS FRAMEWORK AND MONITORING
Project
Name:
National Roads Improvement and Management Program
(APL) Phase 2 (P079935)
Project
Stage: Restructuring Status: DRAFT
Team
Leader: Ashok Kumar
Requesting
Unit: EACPF Created by: Kristine May San Juan Ante on 04-Mar-2014
Product
Line: IBRD/IDA
Responsible
Unit: GTIDR Modified by: Kristine May San Juan Ante on 11-Dec-2014
Country: Philippines Approval FY: 2008
Region: EAST ASIA AND PACIFIC Lending
Instrument: Adaptable Program Loan
Project Development Objectives
Original Project Development Objective:
The Program goal is the establishment of road management arrangements which ensure the upgrading and preservation of the National Road
System (NRS) in an environmentally, socially and financially sustainable manner.
28
The development objective for Phase 2 is: Improved operation, organizational effectiveness and fiduciary control in the management and
financing of the national road system, to enhance road user satisfaction in the project areas and efficiency and integrity in the use of financial
resources.
Proposed Project Development Objective (from Restructuring Paper):
To improve the condition of the national roads network and management effectiveness of the Department of Public Works and Highways at
national and local level.
Results
Core sector indicators are considered: No Results reporting level: Project Level
Project Development Objective Indicators
Status Indicator Name Core Unit of Measure Baseline Actual(Current) End Target
Revised Indicator one: Administrative
Efficiency – Percentage of
projects delivered with less
than 15 percent excess to
original cost and time.
Text Value 6 70
Date 31-Mar-2014 31-Dec-2016
Comment The project
delivered within
original cost and
29
time is a better
indicator than
the delivery
time alone
(used earlier)
which would
vary according
to project size
and thus it is
difficult to set a
bench mark
delivery time
against which
the reduction
could be
measured.
New Roads in good and fair
condition as a share of total
classified roads
Percentage Value 55.00 55.00 60.00
Date 30-Nov-2014 31-Dec-2016
Comment Indicator Two:
“Improved
asset
management
of National
Roads
IRI<7
30
Network –
“Percentage of
roads in good
and fair
condition as a
share of total
classified
national
roads”
New Size of the total classified
network
Kilometers Value 32226.00 32226.00 32226.00
Sub Type
Supplemental
Revised Indicator Three: Percentage of
satisfactory perception of
external stakeholders with the
National Road System (NRS)
Text Value 55% >60%
Date 30-Nov-2014 31-Dec-2016
Comment
New Indicator Four: Percentage of
DPWH’s infrastructure projects
subjected to life cycle
Percentage Value 0.00 70.00
Date 31-Oct-2014 31-Dec-2016
31
monitoring using improved IT
enabled tools
Comment
New Indicator Five: Percentage of
Local infrastructure
subprojects, receiving
technical assistance under the
project, that are in compliance
with the prescribed standards
of DPWH.
Percentage Value 80.00
Date 31-Oct-2014 31-Dec-2016
Comment
Intermediate Results Indicators
Status Indicator Name Core Unit of Measure Baseline Actual(Current) End Target
Revised Component A1: National Roads
Improved
Text Value 0 280 280
Date 31-Dec-2008 31-Oct-2014 31-Dec-2014
Comment
Revised Component A2: Number of
kms of roads maintained
efficiently through Long-Term
Performance Based
Maintenance Contracts
Text Value 0 680 680
Date 31-Dec-2008 31-Dec-2013 31-Dec-2016
Comment
32
New Roads rehabilitated, Non-rural
Kilometers Value 0.00 1200.00 1500.00
Date 31-Dec-2008 31-Mar-2014 31-Dec-2014
Comment Under Project
Components A1
and A2 (a) and
(b)
New Percentage of Annual Road
and Bridge Asset Preservation
Program of DPWH evaluated
by technical and economic
criteria through the use of
DPWH planning applications
Percentage Value 0.00 70.00 80.00
Date 18-Aug-2009 10-Oct-2014 31-Dec-2016
Comment Planning
systems not
operational
Already being
evaluated using
HDM4
New Percentage of Central and
Regional Offices with
operational Multi Year
Programming and Scheduling
(MYPS)
Percentage Value
Date 30-Nov-2014 31-Dec-2015 31-Dec-2016
Comment Operation in
Central offices
Operational in
Central and
Regional Offices
New Number of DPWH offices with
Number Value 0.00 203.00 203.00
33
improved Financial
Management systems of e-
NGAS and e-Budget
Date 18-Aug-2009 31-Oct-2014 31-Dec-2015
Comment These modules
already
introduced in 203
offices
e-NGAS – New
Government
Accounting
System
New National Roads design
guidelines and standards
updated by DPWH and in use
Yes/No Value No Yes
Date 31-Dec-2013 31-Oct-2014 31-Dec-2015
Comment Guidelines are
under
preparation
New Percentage (or number) of
regional and central offices
that are implementing (phase
1) enhanced Project and
Contract Management
Application processes
Number Value
Date 31-Dec-2008 31-Dec-2014 31-Dec-2016
Comment Pilot Launched Implemented in
Central,
Regional, and
Districts
New Percentage (or number) of Number Value 0.00
34
regional and central offices
that are using GIS for forward-
planning through integration
with MYPS (Planning Services
and Regions) Module
Date 31-Dec-2013 31-Oct-2014 31-Dec-2016
Comment Ongoing
initiatives
Both in Central
and Regional
Offices
New Percentage of classified
network of Road Inventory,
condition and traffic data up-
to-date in accordance with
update cycle.
Percentage Value 80.00
Date 31-Dec-2013
Comment Including IRI
New Number of offices that
upgraded/expanded IT
Infrastructure “Voice and Data
communication network”
Number Value 0.00 95.00
Date 31-Dec-2013 31-Dec-2016
Comment
New Enhanced Data Governance
Program implemented Yes/No Value No Yes
Date 31-Dec-2013 31-Dec-2016
Comment New policy to be
issued by end of
2014
35
Revised Improved and Effective
Corporate Structure: Number
of DPWH offices implementing
Rational Plan of DPWH, as
approved by the DBM
Text Value
Date 18-Aug-2009 31-Oct-2014 31-Dec-2016
Comment Rationalization
Plan under
consideration
by
Government
The
Rationalization
Plan, as approved
by DBM
(Department of
Budget and
Management), is
implemented in
203 offices of
DPWH
Revised Improved Road Fund
Performance: Number of New
Road Board Secretariat policy
and procedures introduced to
institute internal controls for
approvals and release of funds
Text Value Yes Yes
Date 31-Oct-2014 31-Dec-2014
Comment Already
achieved
Date 06-Dec-2012 31-Dec-2014
Comment
36
Revised Number of staff trained in
various subjects for
enhancement of Project
Implementation Capacity and
road safety
Text Value 150
Date 31-Dec-2008 31-Oct-2014 16-Dec-2014
Comment The areas of
training include
planning-related
business
procedures,
organizational
Culture Change,
Asset
Preservation,
Change
Management, e-
Procurement, IT
applications,
and road safety
New OCCP (Organizational Culture
Change Program) Road Map
adopted by DPWH
Yes/No Value Yes
Date 31-Dec-2013 31-Oct-2014 31-Dec-2015
Comment To be finalized by
end December
2014
38
ANNEX 2: OPERATIONAL RISK ASSESSMENT FRAMEWORK
Project Stakeholder Risks
Stakeholder Risk Rating Moderate
Risk Description: Risk Management:
Compared to other stakeholders, people who are residing
or doing business in the roads vicinity, who are directly
affected by roads projects are least consulted during
preparation and implementation. On the other hand,
politicians and LGU officials have extraordinary influence
in the project development process for roads.
DPWH has adopted various feedback mechanisms, which need to be supported,
including public consultations, call center, complaints desk, etc. DPWH uses HDM4 in
selection and prioritization of preventive maintenance sections. Procurement decisions
are published.
Resp: Status: Stage: Recurrent: Due Date: Frequency:
Client In Progress Implementation
Implementing Agency (IA) Risks (including Fiduciary Risks)
Capacity Rating Moderate
Risk Description: Risk Management:
DPWH is not able to provide adequate supervision for the
various components of the Project, including civil works,
goods procurement, ICD consultancies, and Technical
Regular supervision meetings with DPWH staff supervising various components to
ensure that proper attention is devoted to each component. Three component
managers from DPWH are in charge of the key components, and Bureaus/Services are
39
Assistance to LGUs, by not being able to assign staff with
the appropriate qualifications and experience.
supervising each activity. A project management consultant will be mobilized for
technical assistance to LGUs.
Resp: Status: Stage: Recurrent: Due Date: Frequency:
Both In Progress Implementation
Governance Rating Substantial
Risk Description:
DPWH’s public roads program is heavily influenced by
non-transparent decisions, resulting from influence of
political personalities, and not based on technical and
economic criteria. Quality control is not stringently
enforced resulting in poor quality of road works.
Risk Management:
Construction supervision contracts are in place for roads improvement component
while Advisors are engaged for the LTPBM contracts reporting to the PMO. BQS and IAS
are, respectively, conducting regular technical audits of civil works and internal audits.
Resp: Status: Stage: Recurrent: Due Date: Frequency:
Both In Progress Implementation
Risk Management:
DPWH has adopted an Integrity Strengthening Action Plan (ISAP) that is regularly
monitored for implementation.
Resp: Status: Stage: Recurrent: Due Date: Frequency:
Both In Progress Implementation
40
Project Risks
Design Rating Moderate
Risk Description: Risk Management:
The project, with its multiplicity of components and
activities, encounter serious issues during
implementation and does not lead to the attainment of
the desired development objective. Results framework is
not directly and completely linked to specific components
and thus becomes beyond the scope of the project. LGUs
do not comply with the prescribed technical standards for
local infrastructure.
Regular supervision missions and constant communication with DPWH PMO and other
units to identify implementation issues and jointly find solutions. The results
framework has already been revised to take away the result indicators which are either
difficult to measure or are outside the project scope. The project is performing well
since its first restructuring in December 2012. Senior management of DPWH is fully
committed to the project specifically to the institutional development initiatives. A
project management consultant will monitor the technical assistance to LGUs.
Resp: Status: Stage: Recurrent: Due Date: Frequency:
Both In Progress Implementation
Social and Environmental Rating Moderate
Risk Description: Risk Management:
Civil works components are implemented without
compliance with social and environmental management
plans developed for the Project, and have adverse impact
on affected persons and the environment. LGUs do not
Regular supervision meetings with DPWH safeguards team and site visits will be
undertaken to ensure relevant issues are spotted early and appropriately addressed.
Management of safeguards in the ongoing civil works has been found satisfactory.
Training of LGUs is included in modified SEMS.
41
fully understand the modified SEMS Resp: Status: Stage: Recurrent: Due Date: Frequency:
Bank In Progress Implementation
Program and Donor Rating Substantial
Risk Description: Risk Management:
The Bank suspends disbursement for the project or any of
its components because of reports on fraud and
corruption. Similar programs of other development
partners have overlapping components which are not
coordinated during implementation.
Regular monitoring of ISAP. Regular donor coordination meetings are held during each
mission, and there is open and constant communication with other development
partners engaged in the roads sector.
Resp: Status: Stage: Recurrent: Due Date: Frequency:
Both In Progress Implementation
Delivery Monitoring and Sustainability Rating Moderate
Risk Description: Risk Management:
DPWH business innovations are not sustained by
concerned units, especially when there is a change in
DPWH leadership.
DPWH ICD Steering Committee monitors all ICD activities to ensure that appropriate
DPWH units are fully engaged for each activity, and that learning by doing is happening
to increase capacity of DPWH staff.
Resp: Status: Stage: Recurrent: Due Date: Frequency:
42
Client In Progress Implementation
Other (Optional) Rating
Risk Description: Risk Management:
Resp: Status: Stage: Recurrent: Due Date: Frequency:
Other (Optional) Rating
Risk Description: Risk Management:
Resp: Status: Stage: Recurrent: Due Date: Frequency:
Overall Risk
Overall Implementation Risk: Rating Moderate
Risk Description:
43
Procurement-related risks for major contracts are significantly reduced considering that only a few preventive maintenance works remain to be
procured. With substantial completion of National Road Improvement Works, critical risks now pertain to quality and payment transactions for
LTPBM and PM contracts. Also important will be monitoring the impact of the ongoing works on affected residents and the environment. The key
risk with ICD activities will be on institutionalization and sustainability of the improvements in business processes and capacity building.