39
Document of The World Bank Report No: ICR00001313 IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-90077) ON A GRANT IN THE AMOUNT OF SDR 6.6 MILLION (US$ 10 MILLION EQUIVALENT) TO THE ISLAMIC REPUBLIC OF AFGHANISTAN FOR A MANAGEMENT CAPACITY PROGRAM June 12, 2012 Governance and Public Sector Afghanistan South Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Document of The World Bankdocuments.worldbank.org › curated › en › ... · AEP Afghan Expatriate Program MIP Management Internship Program ARTF Afghanistan Reconstruction Trust

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Document of

The World Bank

Report No: ICR00001313

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(TF-90077)

ON A

GRANT

IN THE AMOUNT OF SDR 6.6 MILLION

(US$ 10 MILLION EQUIVALENT)

TO THE

ISLAMIC REPUBLIC OF AFGHANISTAN

FOR A

MANAGEMENT CAPACITY PROGRAM

June 12, 2012

Governance and Public Sector

Afghanistan

South Asia Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

CURRENCY EQUIVALENTS

(Exchange Rate Effective June 04, 2012)

Currency Unit = Afghani (AFN)

US$ 1.00 = AFN 50

FISCAL YEAR: March 20-March 21

ABBREVIATIONS AND ACRONYMS

AEP Afghan Expatriate Program MIP Management Internship Program

ARTF Afghanistan Reconstruction Trust

Fund

MoCI Ministry of Commerce and

Industries

CDS Capacity Development Secretariat MoE Ministry of Education

GDPD

M

General Directorate of Program

Design and Management

MoJ Ministry of Justice

GoA Government of Afghanistan MoM Ministry of Mines

HRM Human Resource Management MoWA Ministry of Women Affairs

IARCS

C

Independent Administration Reform

and Civil Service Commission

PAR Public Administration Reform

ITA International Technical Assistance PMU Program Management Unit

LEP Lateral Entry Program PRR Priority Reform & Restructuring

Program

M&E Monitoring and Evaluation TAFSU Technical Assistance and

Feasibility Support Unit

MAIL Ministry of Agriculture and

Livestock

TER Technical Evaluation Report

MCP Management Capacity Program

Vice President: Isabel M. Guerrero, SARVP

Country Director: Robert Saum, SACAF

Sector Manager: Antonius Verheijen, SASGP

Project Team Leader: Satyendra Prasad, SASGP

ICR Team Leader: Richard Spencer Hogg, SASGP

Afghanistan

Management Capacity Program

CONTENTS

Data Sheet

A. Basic Information

B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

A. Basic Information ........................................................................................................ i B. Key Dates .................................................................................................................... i

C. Ratings Summary ........................................................................................................ i

D. Sector and Theme Codes ........................................................................................... ii

E. Bank Staff ................................................................................................................... ii F. Results Framework Analysis ...................................................................................... ii

G. Ratings of Project Performance in ISRs .................................................................... v H. Restructuring (if any) ................................................................................................. v I. Disbursement Profile .................................................................................................. v

1. Project Context, Development Objectives and Design ............................................... 1 2. Key Factors Affecting Implementation and Outcomes .............................................. 3

3. Assessment of Outcomes ............................................................................................ 8 4. Assessment of Risk to Development Outcome ......................................................... 13 5. Assessment of Bank and Borrower Performance ..................................................... 14 6. Lessons Learned ....................................................................................................... 17 7. Comments on Issues Raised by Grantee/Implementing Agencies/Donors .............. 19

Annex 1. Project Costs and Financing .......................................................................... 20 Annex 2. Outputs by Component ................................................................................. 21

Annex 3. Grant Preparation and Implementation Support/Supervision Processes ....... 23 Annex 4. Summary of Grantee's ICR and/or Comments on Draft ICR ........................ 24 Annex 5. List of Supporting Documents and MCPs Interviewed ................................ 28

MAP

i

A. Basic Information

Country: Afghanistan Project Name: AF: Management

Capacity Program

Project ID: P106170 L/C/TF Number(s): TF-90077

ICR Date: 10/05/2009 ICR Type: Core ICR

Lending Instrument: TAL Grantee: GOVERNMENT OF

AFGHANISTAN

Original Total

Commitment: USD 10.00M Disbursed Amount: USD 11.05M

Revised Amount: USD 10.00M

Environmental Category: C

Implementing Agencies:

Independent Administrative Reform & Civil Service Commission

Cofinanciers and Other External Partners:

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 10/27/2006 Effectiveness: 10/31/2007 10/17/2007

Appraisal: 12/27/2006 Restructuring(s):

Approval: 02/13/2007 Mid-term Review: 09/29/2010

Closing: 03/31/2010 12/31/2011

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately unsatisfactory

Risk to Development Outcome: High

Bank Performance: Moderately satisfactory

Grantee Performance: Moderately satisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Moderately

unsatisfactory Government:

Moderately

unsatisfactory

Quality of Supervision: Moderately satisfactory Implementing

Agency/Agencies: Moderately satisfactory

Overall Bank

Performance: Moderately satisfactory

Overall Borrower

Performance: Moderately satisfactory

ii

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem Project

at any time (Yes/No): No

Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): No

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status:

Moderately

Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

Central government administration 50

General public administration sector 50

Theme Code (as % of total Bank financing)

Poverty strategy, analysis and monitoring 100

E. Bank Staff

Positions At ICR At Approval

Vice President: Isabel.M.Guerrero Praful.C.Patel

Country Director: Robert Saum Alastair.J.Mckechnie

Sector Manager: Antonius Verheijen Ijaz Nabi

Project Team Leader: Satyendra Prasad Anne Tully

ICR Team Leader: Richard Spencer Hogg

ICR Primary Author: Richard Spencer Hogg

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document) To achieve sustained improved performance in the management capacity of key

departments dealing with any or all of the common functions including financial

management, human resource management, policy and regulatory design, and

administration. This should ultimately result in improved utilization and cost

effectiveness of budgetary resources and faster and better development results on the

ground.

iii

Revised Project Development Objectives (as approved by original approving authority)

Not Applicable

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Numbers of MCP's in key centre and sub-national positions

Value

quantitative or

Qualitative)

0 175 161

Date achieved 10/17/2007 12/31/2011 12/31/2011

Comments

(incl. %

achievement)

161 appointments are made till date which includes resignations, terminations and end of

contract appointments. Current active number of MCPs is 95.

Indicator 2 : Departments with MCPs achieving rating of satisfactory (or equivalent) following annual

performance assessment

Value

quantitative or

Qualitative)

0 70% 0

Date achieved 10/17/2007 12/31/2011 12/31/2011

Comments

(incl. %

achievement)

Monitoring mechanism for measuring departmental outcomes is weak and was not

established properly.

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Appointment of MCPs

Value

(quantitative

or Qualitative)

0 175 161

Date achieved 10/17/2007 12/31/2011 12/31/2011

Comments

(incl. %

achievement)

161 appointments are made till date which includes resignations, terminations and end of

contract appointments. Current active number of MCPs is 95.

Indicator 2 : Percentage of appointments at sub-national level

Value

(quantitative

or Qualitative)

0 20 5

Date achieved 10/17/2007 12/31/2011 12/31/2011

iv

Comments

(incl. %

achievement)

9 MCP appointments made at sub-national level. 4 resigned due to various reasons.

Indicator 3 : Focus MCPs on 10 priority ministries

Value

(quantitative

or Qualitative)

0 70% 54.2%

Date achieved 10/17/2007 12/31/2011 12/31/2011

Comments

(incl. %

achievement)

54.2 % of MCPs are targeted at the priority ministries.

Indicator 4 : HR practices are merit based

Value

(quantitative

or Qualitative)

n/a Annual Audit of HR

Practices

All appointments

conducted in

accordance to the

Civil Service Law,

Civil Servants Law

and other regulations

of the IARCSC. The

Audit department of

IARCSC conducts

review of HR

activities of GDPDM

annually.

Date achieved 10/17/2007 12/31/2011 12/31/2011

Comments

(incl. %

achievement)

Indicator 5 : Percentage terminations following performance appraisal process

Value

(quantitative

or Qualitative)

0 5 3.5

Date achieved 10/17/2007 12/31/2011 12/31/2011

Comments

(incl. %

achievement)

5 terminations carried out till date.

Indicator 6 : Departments with MCPs achieving rating of satisfactory (or equivalent) following annual

performance assessment

Value

(quantitative

or Qualitative)

0 70% 0

Date achieved 10/17/2007 12/31/2011 12/31/2011

Comments

(incl. %

achievement)

Monitoring mechanism for measuring departmental outcomes is weak and was not

established properly.

v

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 06/26/2008 Moderately Satisfactory Moderately Satisfactory 0.00

2 03/17/2009 Moderately Satisfactory Moderately Satisfactory 0.55

3 03/09/2010 Moderately

Unsatisfactory

Moderately

Unsatisfactory 3.31

4 12/28/2010 Moderately

Unsatisfactory Moderately Satisfactory 6.47

5 01/07/2012 Moderately Satisfactory Moderately Satisfactory 10.59

H. Restructuring (if any)

Not Applicable

I. Disbursement Profile

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

By 2002, years of conflict had eroded Afghanistan‘s public sector. An administrative

structure still existed in many parts of the country after the war, but few senior staff were

left in Kabul to manage relations with the provinces, and even fewer resources remained

to deliver any services. Given the low skills base and the need for an immediate impact

on the ground, donors launched various initiatives to raise government capacity, but

progress in building capacity in government institutions has been slow. Many efforts

relied more on substituting for civil service capacity than strengthening it, and often

included the following range of modalities: regular civil servants on standard government

terms; civil servants receiving higher salaries or top-ups via government or donor-funded

initiatives; contract positions in the civil service filled by national or international

consultants; national staff in NGOs, the United Nations, and international agencies on

secondment to the government; and contractors employed either directly or through

donors to carry out development projects.

Several civil service reform programs were implemented in the 2000s in order to

strengthen public administration. The Independent Administration Reform and Civil

Service Commission (IARCSC) was established in 2003 with a mandate to lead civil

service reforms. The priority reform and restructuring program (PRR) was introduced to

improve how critical departments in key ministries functioned and to enable these

departments to recruit staff on merit, and at modestly better pay. Other activities included

promulgating laws and regulations for the civil service. At the same time several

programs were launched to build or inject capacity. The government initiated the

Technical Assistance and Feasibility Studies Unit in 2003, with support from the World

Bank and Afghanistan Reconstruction Trust Fund (ARTF), to provide the civil service

with skilled national and international expertise to carry out technical feasibility studies.

But the unit provided mainly short-term inputs and did little to build longer term

capacity. In 2002–04 the government, through the ARTF, approved the Afghan

Expatriate Program and Lateral Entry Program. (These two programs were merged in

2005.) The former program sought to hire a small number of expatriate Afghans as senior

advisers, while the latter aimed to address the widespread shortage of competent and

experienced civil servants in upper- and middle- management positions in key ministries

and agencies, offering ―lateral‖ entry to suitably qualified Afghans, many of them from

the Diaspora. Both programs were succeeded by the Management Capacity Program

(MCP) in 2007, which aimed primarily to develop a cadre of senior tashkeel civil

servants in line ministries, who would undertake reform in departments such as finance,

procurement, human resources, and policy and planning.

The MCP provided line ministries with the resources and implementation structure to

recruit highly qualified staff transparently through merit to fill key ―Tashkeel‖ positions,

to create a management team accountable to the minister that provides a critical mass to

implement ministry reforms through strengthening systems and enhancing standards. The

2

MCP focused primarily on supporting the execution of common functions at senior or

managerial levels, including policy and strategy development, project management,

financial management, procurement and human resource management. In addition, it also

facilitated critical positions in the change management process in various ministries as

well as senior key line management positions of core sector functionality in those

ministries that contribute to economic development, such as education, health care, and

infrastructure sectors.

Rationale for Bank Assistance

Building government capacity to deliver services was one of the primary areas of focus of

the donor community after the conflict. Public administration reform was essential to

rebuilding the state, institutionalizing improved governance and combating corruption.

The Bank had extensive experience in promoting public administration reform in

Afghanistan through a series of development policy credit/grants intended to bolster

reforms. The MCP followed two previous capacity injection projects; Afghan Expatriate

Program (AEP) and Lateral Entry Program (LEP) designed to attract expatriate and

qualified Afghans from different backgrounds and areas of work to key ministries. Both

programs were funded through the Afghanistan Reconstruction Trust Fund (ARTF).

Considering the comparative advantage of ARTF with respect to the institutional

knowledge and lessons learnt from these previous operations, there was strong rationale

for the Bank‘s involvement in MCP.

1.2 Original Project Development Objectives (PDO) and Key Indicators (as

approved)

The original project objective was ―To achieve sustained improved performance in the

management capacity of key departments dealing with any or all of the common

functions including financial management, human resource management, policy and

regulatory design, and administration. This should ultimately result in improved

utilization and cost effectiveness of budgetary resources and faster and better

development results on the ground‖.

1.3 Revised PDO (as approved by original approving authority) and Key Indicators,

and reasons/justification

Not Applicable.

1.4 Main Beneficiaries,

All line ministries and agencies of the Government of Afghanistan (GoA) were the

intended beneficiaries of the project. However positions in the judiciary, military, law

and enforcement agencies or politically appointed positions were not eligible to receive

funding. Through the MCP, line ministries and agencies are expected to receive support

to strengthen one or several of the basic functions of public administration. The program

was expected to primarily support common function senior management positions. Areas

covered under common functions were financial management (budgeting and accounting),

human resource management (recruiting, performance monitoring, benefits management,

3

career management and severance), policy and regulatory design, and general

administration and procurement.

1.5 Original Components (as approved)

Component One: Provision of Management Services on Demand.

This component was designed to provide experienced managerial staff to line

ministries/agencies to assume line management responsibility for executing common

functions as well as key managerial responsibility in some sectoral ministries that

contribute to key areas of economic development. Positions under civil service grades 1,

2 and 3 under the current eight-grade system received support through MCP funding.

Positions filled through MCP were authorized under the ministry ―Tashkeel‖ or

establishment structure. Under this component it was intended that MCP recruits would

be provided with two year contracts at the beginning which could be renewed for a

further one year. Assignment of newly recruited MCP experts into the line ministry

positions was facilitated through a Memorandum of Understanding (MoU) signed

between the Capacity Development Secretariat (CDS) also known as the General

Directorate of Program Design and Management (GDPDM) of IARCSC and the line

ministry. The ARTF Management Committee (MC) approved in principle an allocation

of USD 30 million for three years with an initial allocation of USD 10 million to cover

technical assistance requirements and the first year of program costs.

Component Two: Program Management

This component was aimed to strengthen the CDS of GDPDM within the IARCSC which

was the implementing agency of the project. The CDS was responsible for the

management of the program including outreach and communications with line ministries;

screening and evaluating proposals; managing and overseeing recruitment of executives;

managing the monitoring and evaluation of candidates‘ performance in the employing

ministries; contract management and program financial management; and reporting on

and accounting for program results.

1.6 Revised Components

Not Applicable.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

Since 2002, the government has used a variety of approaches and projects to acquire

operational and advisory expertise under contractual arrangements including the Afghan

Expatriate Program (AEP), the Lateral Entry Program (LEP), Technical Assistance and

Feasibility Support Unit (TAFSU), the Priority Reform and Restructuring (PRR) ―Super

Scale‖, and the hiring of numerous experts mobilized by donors in specific sector

4

contexts. These programs were introduced as part of an attempt to make the

Government/Civil Service more competitive as an employer in the face of a limited pool

of skilled Afghans and a labor market where NGOs and international organizations

competed with government for the best qualified Afghans. The AEP was originally

designed to finance the services of experienced Afghan professionals who were willing to

return to the country to participate in the reconstruction effort as senior advisors. It was

complemented in 2004 by the LEP which was designed to bring Afghan nationals

working in-country or regionally, into line positions at senior and middle management

levels on a contractual basis. Both programs were originally financed through the ‗third‘

window of the ARTF, which had been financed to bring qualified Afghans into

government. In 2005 both schemes were merged and financed by the ARTF through its

investment window as the Civil Service Capacity Building Project, TF053940.

MCP was designed with a view to improve upon the shortcomings of AEP and LEP.

From its inception, the AEP‘s operational objectives were intuitively defined, but there

was ambiguity on what specific results to expect, making it difficult to measure

effectiveness. LEP on the other hand, while it was successful in attracting some highly

qualified Afghans from national and regional markets into line ministry positions (not

advisory) had the unintended negative effect of encouraging line ministries to avoid the

implementation of other on-going civil service reforms such as PRR. LEP was also

undermined by capacity constraints on part of the Independent Appointments Board

(IAB) of IARCSC which was tasked with the implementation of the new pay and grading

reform. Both programs recruited relatively few staff: the Afghan Expatriate Program

recruited only 95 Afghans into the government and the Lateral Entry Program some 138.

In 2007 the Civil Service Capacity Building Project was re-designed as the MCP.

Substantial risks were identified during the design phase which were expected to impede

the achievement of MCP objectives. These included the risk of failing to attract sufficient

skilled staff even with the improved MCP salary scales, considering the small size of the

talent pool and competition from NGOs and donors. A second major risk identified was

the expected resistance from within the civil service among other civil servants who

remained on the normal civil service pay scale. This risk was expected to be partly

mitigated by the establishment of a transparent process of recruitment, clarity about the

roles and responsibilities of the MCP recruits and the temporary nature of their

employment. A third risk was that the program would continue to support the

appointment and retention of candidates who made little substantial contribution to the

program‘s objectives. It was envisaged that an annual performance audit of the program

would help mitigate this risk along with a continued emphasis on merit based

appointments and transparency in appointments. The risks and the anticipated mitigation

measures during the time of appraisal are set out in Table 1 below.

The PDO of the project was ambitious. The ―demand driven‖ approach to provide

managerial capacities to line ministries was largely ad-hoc and rarely part of a wider

government or ministry wide capacity building strategy. Communication and outreach

activities were inadequate to inform the line ministries of the purpose of the project. As a

result, during the first two years of project implementation, a large number of positions

5

requested by the line ministries were not aligned to their strategic plans. Instead of

following an ―across the board‖ approach to all ministries, it would have been useful to

prioritize certain key service delivery ministries. This would have allowed the MCP to be

used much more strategically to build the performance of critical ministries. During the

later stages of implementation (2010-2011), this approach was eventually followed and

ministries such as Ministry of Mines (MoM), Ministry of Commerce & Industries

(MoCI), Ministry of Agriculture and Livestock (MAIL) and Ministry of Education (MoE)

were supported with cohorts of experts to create a critical mass of MCPs to implement

the ministry reform initiatives. However, this change of approach came too late in the

project life time (December 2011) to adequately impact its objectives.

Table 1: Risks and Mitigation Measures

Risks Identified Mitigation Measures (At Appraisal)

Unavailability of Skilled Candidates Competitive Salary scales, Senior Managerial

Tashkeel Positions in Ministry and Better

Communication and Outreach Measures

Resistance from Existing Civil Servants Clear Definition of MCP Roles, Transparent

Process of Recruitment and Temporary Nature

of Appointments

Appointment and Retention of Non-Performing

Candidates

Annual performance Audits

Capacity Building of National Staff (Civil

Servants) and Knowledge Transfer

GoA to Train and Mentor the Next Generation

of Managers. Beyond the Scope of MCP

2.2 Implementation

Implementation of MCP has never been easy. A mid-term review (MTR) conducted in

September 2010 and subsequent supervision missions repeatedly raised the following

issues which were further explored during the ICR mission.

Inadequate Funding: The initial funds committed to the project through the Afghanistan

Reconstruction Trust Fund (ARTF) were inadequate to accommodate all the requests

made by ministries/agencies for MCP appointees. This led to frustration on part of many

Ministers. However, while additional finance was available from the approved

‗earmarked‘ ARTF funds, there was concern in the Bank to scale up too rapidly given

capacity constraints in the implementing agency, the time it took to recruit and

uncertainty about impact. 1

Salary Negotiations: MCP salaries were determined in an ad-hoc manner based on

salary history, rather than salary scales. As a result some Director-Generals (grade 1)

received near to the MCP ceiling of USD $7,000 while others received much less. The

inequities in pay between comparable posts across the civil service that have been created

due to MCP will need to be resolved under the follow-on CBR program. During

1 USD $35 million was originally approved by the ARTF Management Committee, but only USD $15 million was committed.

6

interviews with the MCP experts, the ICR mission noted that the salary negotiations

between the MCP appointees and the Civil Service Commission have been unsatisfactory.

A considerable number of MCPs had grievances about the salary packages offered to

them, citing inequities with other MCPs.

Low Quality of Applications: For many skilled posts, there were too few qualified

applicants. This reflects the highly competitive labor market conditions, lack of skilled

Afghan professionals, and perception that even high paying public sector jobs are not

desirable when compared to donor financed jobs. Poor quality of the applicants has

resulted in re-advertisements for many of these positions and the associated delays

created a source of frustration for the MCP-receiving ministers.

Capacity Development for MCP Recruits: In some ministries and agencies the MCP

recruits have faced logistical problems for several months such as not having access to a

dedicated computer or phone because of procurement delays and/or other reasons.

Further, the Management Capacity Program itself had no dedicated resources to support

MCPs once appointed to ministries, such as professional or job related development

training. The CBR project will need to resolve both these issues for the different cadres of

civil servants that it wishes to create for a well performing and structured Afghanistan

Civil Service.

Focus on Sub-National Positions: It was envisaged during the design of the program

that 20 per cent of total MCP recruitments would be at the sub-national level. This

objective has not been fulfilled. Only a total of 7 MCP appointments have been made at

the sub-national level by December 2011. This was not entirely the fault of the

implementing agency, which advertised for sub-national staff, but largely the result of

combination of Ministry preferences to keep senior staff in Kabul, insecurity in some of

the provinces and lack of a developed incentive structure to get staff to apply to hardship

areas.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

The results framework for the project was inadequate to assess the actual outcomes of the

project activities. While there is anecdotal evidence that individual MCPs made a

difference to department performance, too much reliance was placed on ‗inputs‘, such as

the total number of recruitments and terminations rather than focusing on indicators

pertaining to service delivery improvements and budget execution performance.

Monitoring of line ministry departmental performance by IARCSC was weak and was

not addressed properly under the project design. The PDO level indicator ―Departments

with MCPs achieving rating of satisfactory (or equivalent) following annual performance

assessment‖ is too broad and the project does not detail any underlying mechanism to

measure performance of the line ministry departments under this indicator. Due to

shortfall in original budget allocated adequate Technical Assistance (TA) support to

strengthen the monitoring and evaluation unit of GDPDM could not be provided under

the project. Further, there was no formal high level oversight of the MCP by either the

IARCSC leadership or a more broadly based cross-ministerial committee. As a result

7

there was weak government oversight to determine if the program was achieving its

objectives and no mechanism to achieve consensus on corrective actions to be taken in a

timely manner to address implementation issues.

The performance appraisal process for MCP recruits established at GDPDM was strong.

All MCPs were appraised at the end of six months of their appointment, at the end of

their first year and annually thereafter. The performance appraisal process is a 360°

review involving the appointee, his/her supervisor and four subordinates selected by

MCP program staff. The monitoring and evaluation of project activities also suffered

from frequent changes of Bank Task Team Leaders (4 TTLs over the life of the project)

and inadequate transfer of institutional memory during these changes. It is a

recommendation of this ICR that to achieve effective results on the ground for all present

and future projects of this nature in fragile institutional contexts such as Afghanistan,

task-teams implementing such projects should be based in country with longer term

tenures to work alongside the implementing partners.

2.4 Safeguard and Fiduciary Compliance

Regular implementation support missions (ISM) by the Bank ensured fiduciary

compliance during the life of the project. However the mid-term review (MTR) of the

project highlighted weaknesses in the internal control system of the implementing agency

(GDPDM) which included lack of monthly reconciliation of bank books and inadequate

internal audit arrangements. The scope of the internal audit unit of IARCSC mandated to

carry out internal audit of the project was only limited to checking compliance of the

project with government rules and regulations to be followed for submission of payment

request (form M16) to Ministry of Finance, and did not cover the activities of the project

as prescribed in the agreed financial management arrangements.

The MTR and the last implementation support mission Aide Memoire (AM) also noted a

number of deficiencies in the procurement arrangements of the project. These include

submission of incomplete procurement documents for prior review which caused

significant delays, deficiencies in the selection process of individuals and re-opening of

some vacancies without obtaining prior Bank approval.

2.5 Post-completion Operation/Next Phase

A much larger project named Capacity Building for Results (CBR) Facility has been

designed by the Bank as a successor to the MCP. Many of the lessons of the MCP have

contributed to the design of the CBR:

As mentioned earlier, the approach towards implementation of the project

changed from 2010 onwards. Instead of the ‗scattergun‘ approach of providing

―ad-hoc‖ MCP experts to large number of line ministries and agencies, it was

considered that clustering of MCPs in critical line ministries in important

common function positions such as HR, Procurement and Financial Management

(FM) would lead to better results and improved service delivery. But this change

8

of strategy was effected too late during the project life time to impact project

results and outcomes as set out in the PDO.

A major concern of the MCP has been the lack of skills and expertise of lower

rank civil servants who were subordinate to the MCP experts. The MCP could

only recruit staff to grades 1, 2 and 3 of the civil service and this became a serious

bottleneck in many ministries which needed a second tier of managers under the

MCP experts to execute the ministry mandates in Kabul as well as in the

provinces. The new CBR initiative addresses this issue head on and focuses on the

creation of different cadres of civil servants under Senior Management Group

(SMG), Common Function (FM, Procurement, HR and Admin) and Professional

Cadres (Health Specialists, Economists, Mining Engineers etc.) with definitive

career development plans. This could pave the way for the third generation of

civil service reforms and the genesis of an Afghanistan Civil Service (ACS)

structure in line with more developed civil services such as in UK and New

Zealand.

At the end of the project in December 2011, contracts for more than 100 MCP experts

were active. Based on discussions with the GDPDM/IARCSC these contracts were

extended till July 31, 2012 with an understanding that all active positions will be re-

advertised and recruited as part of the new CBR project. At the time of writing, the

migration of MCP's into the CBR program was awaiting a formal decision by the

Steering Committee (SC) of the CBR comprised of the Minister of Finance and the

Chairman of the IARCSC. The technical recommendation being considered by the SC

was that MCP contracts would be brought into the CBR framework for the period until

the end of the MCP contract period. MCP's would retain their pay scales if this was

higher than the CBR pay scales (for around 15 persons) until the end of their contracts.

At the end of their contracts, individuals would need to reapply for their posts if they

wished and if appointed their salaries would be consistent with the CBR pay scales. This

formulation if accepted would ensure that there was a smooth transition between the two

projects.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation (to current country and global priorities, and Bank assistance strategy)

Capacity building of the civil service has been a major concern of the donor community

from 2002 to-date. But much of this capacity building effort has been to pay for

externally funded staff outside the ‗tashkeel’ to carryout civil service functions. The MCP

was different. It was designed to build capacity from within the civil service by recruiting

qualified Afghans as contract civil servants to fill ‗tashkeel‘ positions. The objective was

to transform government‘s capacity to deliver services from within. The project to some

extent has been able to improve the utilization and cost effectiveness of donor resources

flowing through the national budget and importantly contribute to the overall legitimacy

of the state in the eyes of citizens. The Bank‘s new ISN (approved by the Board in April)

9

will maintain this objective for the Bank engagement in Afghanistan over the Transition

Period through to 2014.

Afghanistan‘s experience of capacity development over the last 10 years is far from

unique. The immediate post-conflict experience of most low- and middle-income

countries—such as Georgia, Liberia, Serbia, Sierra Leone, and Timor-Leste—has been

similar to Afghanistan‘s, especially in their initial widespread dependency on mostly ad

hoc, donor-driven technical assistance and salary supplementation schemes to fill the

vacuum left by the lack of government capacity immediately after the conflict. During the

immediate transition local consultants‘ salaries often increase sharply, as the best and

brightest leave the civil service (if they had not already) to join donor-funded programs or

NGOs on much higher wages. Rebuilding the civil service after such interventions is

therefore extremely difficult without donor-supported salary-supplement schemes, as

most skilled civil servants show little interest in working directly for the government.

With regard to design and implementation, the main lessons from MCP (mentioned later)

and other previous projects reflect the weak capacity of the IARCSC in implementing

large and complex civil service capacity building projects, as well as the need to align the

placement of appointees within a broader strategic framework. One MCP recruit will not

change a Ministry, but a cluster of MCPs supported by a clear Ministry reform plan and

with committed ministerial leadership might.

3.2 Achievement of Project Development Objectives (including brief discussion of causal linkages between outputs and outcomes, with details on

outputs in Annex 2)

The project development objective ―To achieve sustained improved performance in the

management capacity of key departments dealing with any or all of the common functions

including financial management, human resource management, policy and regulatory

design, and administration. This should ultimately result in improved utilization and cost

effectiveness of budgetary resources and faster and better development results on the

ground‖ is considered ambitious by this ICR. The project was initially designed for 3

years and was extended for another year in 2010 after the MTR. Initial recruitments of

MCP experts started much later than project effectiveness in October 2007. Part of this

delay was caused by the protracted mobilization of International Technical Assistance

(ITA) to assist GDPDM with Human Resource Management (HRM) issues, Monitoring

and Evaluation (M&E) and Communication and Outreach. Procurement issues caused

major delays throughout the project. During the first year of project implementation line

ministries had little knowledge of MCP objectives which resulted in incomplete

proposals and inadequate terms of References (ToR) for the requested positions causing

delays in procurement and recruitment.

This ICR also feels that the outputs and outcomes under the project were disconnected.

The results framework of the project was flawed and did not reflect the actual intended

outcomes of the project. The outputs as measured by the results indicators mentioned in

the project documents are based on the performance of the project in terms of quantitative

targets achieved such as total number recruited at center and sub-national positions,

10

percentage of terminations etc. On the other hand, the outcomes of the project as defined

by the PDO should have been captured by improvement in business processes, budget

execution and service delivery results accruing to the end user.

Brief discussion of the project components is mentioned below:

Provision of Management Services “On Demand”

During the life of the project a total of 153 appointments were made by IARCSC across

28 ministries/agencies. During the first two years of project implementation, a number of

positions requested by the line ministries were rejected by IARCSC due to their nature

and incomplete terms of references (ToR). The first procurement plan under the project

was approved by the Bank in August 2008. The following table represents the total

number of positions requested by the ministries/agencies as well as the number of

approved positions by end December 2011.

Table 2: Positions by Ministries / Agencies

Ministry

proposal

received

Position

requested

Positions

approved

Applications

received

August 2008 –

July 2009

7 174 83 924

August 2009 –

July 2010

37 373 74 1714

August 2010 –

December 2011

43 107 0 /a 1776

Source: General Directorate of Program Design and Management (IARCSC)

/a: recruitment continued under the previous procurement plan

During four years of implementation, more than 650 positions were requested by the line

ministries/agencies and approximately 4650 applications in total were received for the

positions that were approved and advertised. A total of 34 MCP experts resigned during

the life of the project and contracts ended for another 16 MCP recruits. The MTR and the

last Supervision Mission Aide Memoire (December 2011) have discussed the advantages

of recruiting cohorts or ―clusters‖ of MCP experts in line ministries/agencies which

started from late 2009 under the project. The ministries which received clusters of MCP

experts and improved their functions considerably relative to other ministries which

received fewer experts include Ministry of Finance (MoF), Ministry of Commerce and

Industry (MoCI), Ministry of Mines (MoM) and Ministry of Agriculture and Livestock

(MAIL). The distribution of MCP experts in different line ministries/agencies is

represented in the following graph.

11

The project was unsuccessful in recruiting sufficient number of people in sub-national

positions. Over the project implementation period of four years only 7 MCP

appointments were made at sub-national level as against a target of 20 per cent of total

appointments under the project. Recruitments of sub-national positions have suffered

because of security reasons, lack of suitable incentives for such positions and insufficient

infrastructure and logistical facilities in the provinces. These constraints are also likely to

affect the Capacity Building for Results (CBR) program as well since a large number of

positions to be funded by the CBR Facility will be targeted at the provinces. This ICR

recommends the implementing partners for the CBR program and the Bank to work

together towards devising suitable incentives for attracting qualified Afghan nationals for

sub-national positions.

Program Management

This component was aimed at strengthening the capacity of the Capacity Development

Secretariat which was later renamed as GDPDM. At the time of project effectiveness, this

component was provided with a total of USD 5 million for overall program management

including outreach and communication, technical evaluation of ministry proposals,

recruitment and contract management. The program management unit at GDPDM also

received International Technical Assistance (ITA) during the initial implementation

period in terms of executive search/recruitment/HR management and M&E of the project

under this component. However TA support was not successful in building capacity in

GDPDM due to lack of proper co-ordination and engagement. A request for further

technical assistance from GDPDM under this component could not be accommodated

due to budget constraints and protracted administrative processes. The program

management unit (PMU) at GDPDM had significant weaknesses in terms of staff strength

and capacities. Attrition of staff from the MCP PMU made project implementation

difficult considering the small size of talent pool and the competitive labor market in the

country. The Human Resources (HR) and Monitoring and Evaluation (M&E) department

of the GDPDM in particular were faced with severe staff shortages and lack of technical

support.

0

2

4

6

8

10

12

AN

SA

HO

O

IAR

CSC

MA

IL

Mo

CI

Mo

CIT

Mo

CN

Mo

Ec

Mo

E

Mo

EW

Mo

F

Mo

HE

Mo

IC

Mo

J

Mo

LSA

MD

Mo

M

Mo

PH

Mo

PW

MR

RD

Mo

TCA

Mo

UA

Mo

WA

Oo

P

12

There was no significant involvement of other departments of the IARCSC in

management and oversight of the MCP. As a result GDPDM leadership exercised full

control over program management. In the views of this ICR, this concentration of power

and responsibilities in terms of managing the senior most civil servants of the

Government in a standalone directorate of IARCSC was not beneficial to the project.

Communication and information sharing with other departments would have provided

more flexibility and strategic direction to the project.

In spite of these difficulties, GDPDM managed to recruit some excellent MCPs, place

them in ministries, monitor their individual performance and within the constraints of any

operation in a fragile conflict affected environment such as Afghanistan, achieve a degree

of success in terms of capacity development in some limited areas. This was not as much

as the PDO required, and depended on the individual qualities of the MCPs recruited, but

the PDO was always over-ambitious.

3.3 Efficiency

This section is not applicable for this project.

3.4 Justification of Overall Outcome Rating

(combining relevance, achievement of PDOs, and efficiency)

Rating: Moderately unsatisfactory (MU)

There is no doubt that the project has recruited many well qualified Afghans who,

anecdotally, appear to have raised the standard of management in their Ministries. But

this is extremely difficult to measure systematically as no baseline data was collected to

allow for such measurement. The project M&E system could not capture very clearly

ministry outcomes and the cause and effect linkages between MCP appointments and

improvements in service delivery. To this extent the project falls short of its stated

development objectives. The intention of the project was to significantly enhance

budgetary performance and service delivery standards of the line ministries with which it

worked. Strictly, this was not achieved, although towards the end of the project life a shift

of approach towards the clustering of MCP experts in critical line ministries does appear

to have made a significant difference.

The project was unable to recruit sufficient number of MCP experts during its years of

operation. Lack of qualified candidates was the major reason for this shortfall. But delays

in No Objection (NOL) issuances by the World Bank for qualified candidates throughout

the implementation period made the recruitment process lengthy and complicated which

acted as a deterrent to the achievement of PDOs. Discussions with the Bank‘s Financial

Management and Procurement units revealed that incomplete documentation and

safeguards on the part of the implementing agency were the primary reason for these

delays. Regular Bank supervision and guidance on financial management and

procurement standards improved the quality of document submission and reporting which

subsequently reduced the administrative delays during the later stages of the project.

The project could not deliver on sub-national recruitments. In spite of the difficulties,

only 7 MCP recruitments in provincial positions over a period of four years of project

13

implementation is poor, but this was not entirely in the hands of the GDPDM leadership

to deliver, but depended on combination of factors, including lack of Ministry demand,

lack of individual incentives, poor security, etc.

3.5 Overarching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects, and Social Development

None of the project development objective indicators directly dealt with poverty

reduction and social development aspects. It is therefore impossible to say to what extent

these benefitted from the project. The number of women inducted as MCPs under the

project was too small to create a critical mass which would facilitate any cultural change

in the civil service. Furthermore, no incentive mechanisms were designed under the

project to make the civil service a more attractive environment for women.

(b) Other Unintended Outcomes and Impacts (positive or negative)

The strongest unintended outcome of MCP was that it helped expand the technocrat pool

from which future leaders of Afghanistan would be drawn. For instance, the current

Director General Budget in Ministry of Finance, the Deputy Ministers for Policy and

Planning in Ministry of Commerce and Industry (MoCI) and Ministry of Mines (MoM)

were all previously recruited through the MCP.

4. Assessment of Risk to Development Outcome

Rating: High

The outcomes of any project in a fragile and conflict affected context are associated with

substantial risks. In Afghanistan civil service reform is one of the most delicate and

politically sensitive areas because of political, economic and ethnic considerations.

Technocratic approaches to state building in Afghanistan have historically had to contend

with the nature of politics in the country, where formal office and position are used as

resources to balance competing elite interests. The Afghan state—while having a highly

centralized, unitary character as embodied in successive Constitutions—has always had

weak central control and has needed to build coalitions of common interest with a strong

periphery. The use of state position and office as bargaining tools in the wider political

process has a long history, ensuring that attempts to introduce modern, merit-based public

sector reforms face an uphill struggle.

In hindsight the MCP recruitment and selection process should have been subject to more

careful oversight from within government itself. To leave this process almost exclusively

to a single unit within the IARSC was a high risk strategy, and put considerable burden

on that department.

The PDO of MCP was extremely ambitious to be achieved within a short period of 3

years. Better performance of line ministries in terms of service delivery to end users and

efficient use of budgetary resources is a long term goal for the Government and the

14

donors. In a weak capacity environment like Afghanistan very little is likely to be

achieved in just 3 years. But nevertheless MCP experts managed to improve capacities in

key departments such as HR, Finance, Policy and Planning and Administration in a

number of key ministries including Ministry of Finance (MoF), Ministry of Commerce

and Industry (MoCI), Ministry of Education (MoE) and Ministry of Agriculture,

Irrigation and Livestock (MAIL).

The project could not deliver on the number of sub-national recruitments due to the

absence of proper incentive measures for those positions. This poses a significant risk for

the follow-on Capacity Building for Results (CBR) project.

5. Assessment of Bank and Borrower Performance (relating to design, implementation and outcome issues)

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

Rating: Moderately unsatisfactory

(b) Quality of Supervision

Rating: Moderately satisfactory

(c) Overall Bank Performance

Rating: Moderately satisfactory

Quality at Entry

The MCP was initiated at a time when there was considerable demand for capacity

injection into the civil service. Its design drew on the lessons from the implementation of

the Afghan Expatriates Program (AEP) and Lateral Entry Program (LEP). MCP satisfied

the need for a unified program which followed a single set of criteria for identifying need,

recruitment, remuneration and supervision. However it had two principal design

weaknesses: firstly, it adopted a scattergun approach to providing capacity injection to

ministries. It would have been far better to ensure a) that capacity injection was linked to

a clear ministry reform plan, and b) provided a cluster of MCPs that could have operated

at scale. Neither of these was achieved through the life of the project. Preparation and

implementation of a ministry reform plan was never a condition of receiving MCP

appointees, while, at the same time, too much faith was given to the transformative power

of one or two qualified MCPs to change a ministry‘s culture and service delivery

performance.

Secondly, it was over-ambitious in terms of what it could achieve within three years. In a

fragile and conflict affected environment like Afghanistan affecting long term

institutional change requires a much longer time horizon. Given the delays in recruitment

of MCP staff there was very little time for the project to make its mark. Thirdly, its

results framework did not capture the necessary indicators to measure ministry outcomes.

As a result it is difficult to measure its impact. There is some anecdotal evidence that

15

good MCPs made a difference to Ministry outputs and helped improve management

performance, but there was never any systematic evidence collected that this actually led

to improved outcomes. In terms of design, the project had only one major component

dealing with the provision of management services. Interviews with various MCP experts

during the ICR mission indicate that a separate component on training and capacity

building of the MCP recruits would have delivered better results.

Quality of Supervision

Three major issues affected the implementation of the project. First, the Bank team had

four task team leaders during the course of the project. This rapid turnover of TTLs was

detrimental to effective and continuous supervision of the project. Secondly, the quality

of some of the supervision was variable. As a result the project suffered from significant

delays in NOL approvals issued by the Bank team. These delays were not entirely the

fault of the Bank team but in part were caused by incomplete documentation provided to

the Bank which included deficient terms of references (ToR) and technical evaluation

reports (TER) for the recruitments, incomplete withdrawal applications and procurement

plans. Thirdly, many of the MTR recommendations in late 2010 were never taken

forward because the project was overtaken by planning for its successor the CBR, which

took up large amount of Bank staff time. Rather than re-structure the project it was

decided to incorporate many of the recommendations and lessons learnt from MCP into

the new project.

For the preparation of this ICR, a significant number of MCP experts were interviewed

by the project team whose names are provided in annex 5. Interviews were designed to

capture the advantages of recruiting clusters of MCPs to that of individual positioning of

these experts. The ICR team interviewed cohorts of MCPs based in Ministry of Mines

(MoM), Ministry of Education (MoE) and Ministry of Agriculture, Irrigation and

Livestock (MAIL) to assess the performance of these ministries. Interviews were

conducted with individual MCPs present in Ministry of Justice (MoJ) and Ministry of

Women Affairs (MoWA) to ascertain the significance of the cluster approach. Focus

group discussions were held with MCPs in specific common function positions such as

HR, FM and Procurement to understand the shortcomings of the MCP and improve upon

them while implementing CBR. In addition, the ICR team also benefitted from the views

provided by the supervisors (Deputy Ministers) of the MCP experts.

The ICR team also reviewed several policy notes prepared during the design of the CBR

which contained valuable insights on issues such as civil service cadre development,

training of potential CBR recruits and creation of a Management Internship Program

(MIP). These topics were not included under the MCP structure and were developed after

in-depth discussions with various stakeholders including the MCP experts.

5.2 Borrower Performance

(a) Government Performance

Rating: Moderately unsatisfactory

16

(b) Implementing Agency or Agencies Performance

Rating: Moderately satisfactory

(c) Overall Borrower Performance

Rating: Moderately satisfactory

Government Performance

Since 2002, civil service reform has been an important government priority. After

implementing projects such as AEP and LEP, MCP was designed to build capacity within

the civil service. A separate IDA financed project named Civil Service Reform Project

(CSRP, P097030) was developed simultaneously to implement public administration

reforms in five key ministries. While there were significant linkages between the MCP

and CSRP as MCP provided the skilled managers to the ministries to carry out the

planned activities under CSRP, the synergies between the two were never adequately

exploited. The two programs were also implemented by two different departments within

the IARSC which made coordination between them more difficult. At the same time

other government capacity building initiatives such as the Civilian Technical Assistance

Program, which provided non-tashkeel technical assistance to ministries at much higher

wage rates than MCP, were never properly coordinated with the MCP.

Nevertheless, it is important to recognize firstly, that there was considerable demand for

MCPs on the part of government ministries that the project was unable to meet. Ministers

valued the contribution of MCP appointees, and while the project could have been better

embedded within an overall ministry led reform process, it was recognized across

government as an important way to build capacity within the civil service rather than in

project implementation unit enclaves. Secondly, given the nature of the overall reform

environment with large numbers of externally funded staff implementing a series of often

disconnected donor driven interventions, it was extremely difficult for government to

harmonize capacity development approaches around the MCP alone.

Implementing Agency Performance

The implementing agency for MCP was the General Directorate of Programs Design and

Management (GDPDM) unit of the IARCSC. According to the implementation

arrangements stated in the PAD, oversight of the project was assigned to the Public

Administration Reform (PAR) Steering Committee of the Government. However, in

practice communication linkages between the MCP Project Management Unit (PMU) and

the PAR Steering Committee were never established properly. As a result GDPDM

functioned as a standalone department within IARCSC with no reporting obligation to the

higher echelons of the Government.

A majority of MCP experts interviewed during the ICR mission and preceding

supervision missions have raised concerns on substantial delays in payment of salaries.

One of the reasons for the delayed salary payments was the low special account ceiling

approved for MCP expenses. Still, delays in payments in some cases for more than 6

months poses serious questions about the financial management and documentation

17

systems of the GDPDM. In addition, a considerable number of MCPs had grievances

about the salary packages offered to them citing inequities with other MCPs in similar

positions. The MCP salary scales were determined in an ad-hoc manner based on salary

history rather than the salary scales approved for the project.

In spite of this, it should be acknowledged that GDPDM had had to deal with a series of

Bank TTLs who bought little consistency to the relationship. Project funding to finance

international TA to support the department was inadequate and was quickly exhausted,

and while discussions took place to recruit new international TA to support the project

this was overtaken by planning for the new CBR follow-on project to the MCP.

6. Lessons Learned (both project-specific and of wide general application)

There are both more general lessons of approach and specific lessons from

implementation.

Design

On design the main lesson is that capacity injection schemes like MCP need to be aligned

with a wider reform process. Unless they are it is difficult to see how injecting capacity

alone in an unreformed ministry will make any difference to performance. The strength

of MCP will only be fully realized when it is tied to a wider strategic reform pathway. To

this extent capacity injection has to be part and parcel of a whole of ministry reform

program, which includes MCP appointees as part of a package of wider ministry support.

The second lesson is that capacity injection has to be at scale. Dropping one or two MCPs

into a ministry and expecting them to make a difference is fanciful. The real effect and

impact will only be achieved by ensuring a ‗cluster‘ approach to MCP placement. In this

way a ministry gets the full benefit of the program at scale. The consequence of this is the

approach has to be selective and phased. Not all of government can benefit at the same

time.

The third lesson is that the PDO needs to SMART (Specific, Measurable, Achievable,

Realistic and Time bound). There is no point having a wonderful and smooth running

capacity injection program if at the end of the day you do not know its impact on

improving government services. Much more work therefore needs to go into

understanding and measuring the linkages between capacity inputs and ministry outputs

and this needs to be captured adequately in the results framework and identification and

articulation of appropriate indicators.

Implementation

The following experiences from MCP bear special attention:

Inclusion of Middle-management and Junior Professionals under MCP: The MCP

only catered to the senior grades of the Afghan Civil Service (Grades 1 & 2). A common

issue raised by a majority of the MCP experts was the deficient skill levels and lack of

18

support for lower grade staff in their ministries/agencies. Under future such programs,

such as CBR, these issues need to be addressed through the creation of a Senior

Management Group (SMG), Common Function and Professional Staff cadres.

Recruitment under common function and professional staff cadres should be expanded to

include lower grades of the civil service.

Training and Capacity Building of Recruits: Many MCP experts expressed their need

for on-the-job training and capacity building during the interviews. MCP had no training

component to address these issues. A key lesson is that such programs require a dedicated

project component on training and capacity building of recruits through specialized

courses and exposure visits to other countries as part of the overall approach to capacity

development.

Sub-National Outreach: The civil service infrastructure at sub-national levels in

Afghanistan is extremely weak. The MCP envisaged to build line ministry functioning in

the provinces but failed to mobilize expert personnel at the relevant positions. Future

programs (such as CBR) must develop appropriate measures to increase sub-national

recruitments, including tackling the issue of appropriate hardship allowances, to bring

about changes in provincial recruitment and service delivery across Afghanistan.

Country Based Bank Task Team: MCP faced enormous amount of delays in NOL

approvals and continuous change of Bank task team leaders (TTL) throughout the project

period. A country based Bank task team with longer term continuity will significantly

increase project performance in fragile contexts such as Afghanistan.

Transparent Salary Negotiations: A majority of MCP experts expressed their

grievances on the determination of salary scales which were largely based on their salary

history. Salaries should be based on the skills, qualifications and experience required for

the positions rather than personal salary history. This is a general lesson but has also been

incorporated into the CBR which will emphasize the establishment of fixed salary scales

for the different categories of civil servants it intends to support.

Quality of Recruits: While it was sometimes difficult for the program to recruit good

quality experts, when it did they made all the difference to the success of the program.

This is an important lesson for the future and shows the importance of maintaining a high

standard in terms of caliber of experts even at the risk of not recruiting at all.

Discontinue/Merge other parallel capacity building initiatives: Interviews with

several MCP recruits reflected that similar civil service capacity building programs such

as Civilian Technical Assistance program (CTAP) are creating negative incentives for the

MCP staff. CTAP supports advisory level positions which are not part of the Government

Tashkeel (Establishment) and salary scales under CTAP are generally two to three times

of MCP scales. Such proliferation of capacity development programs should be avoided

as it undermines the overall reform effort.

19

7. Comments on Issues Raised by Grantee/Implementing Agencies/Donors

(a) Grantee/Implementing agencies

The government‘s response lays particular stress on the fact that the MCP was never allowed to

expand to its total allocation of $35 million, as it was overtaken by its successor program, the

Capacity Building for Results initiative, so it could never achieve its planned recruitment of staff

at sub-national level, that during individual ministry assessments all MCP teams displayed an

increase in percentage of expenditures in critical ministries, and that far from lacking oversight

from other departments, the GDPDM was fully embedded within the IARCSC. On the basis of

the achievements of the MCP the IARCSC-GDPDM believe the project warrants an overall

―Highly satisfactory‖ rating.

While we recognize the government‘s disappointment, we do not feel that such a rating would be

warranted in the circumstances nor would it be supported by the evidence. The MCP had both

design and implementation failings. As this ICR makes plain these were not necessarily the fault

of the implementing agency, but often reflected the broader difficulties of operating in

Afghanistan, and lack of an overall capacity development plan. Nevertheless, the project never

collected the necessary evidence to indicate level of project achievement against PDO. While it is

clear that some MCPs performed extremely well, there were significant weaknesses in the overall

approach which were only addressed towards the end of the project lifetime. While it is true that

failure to appoint MCPs at sub-national level was result of combination of factors, a more

concentrated effort might have seen better results in this regard. At the same time, it is important

to acknowledge that the GDPDM had to contend with a series of Bank TTLs over the life of the

project. This inevitably caused some inconsistency in messaging and supervision of the project.

(b) Cofinanciers/Donors

Not applicable

(c) Other partners and stakeholders (e.g. NGOs/private sector/civil society)

Not applicable

20

Annex 1. Project Costs and Financing

(a) Project Cost by Component (in USD Million equivalent)

Components Appraisal Estimate

(USD millions)

Actual/Latest

Estimate (USD

millions)

Percentage of

Appraisal

provision of management

services (on demand) 27.00 30.00 111

program management 3.00 5.00 166

Total Baseline Cost 30.00 35.00 116

Physical Contingencies

Price Contingencies

Total Project Costs 30.00 35.00 116

Project Preparation Costs

Total Financing Required 30.00 35.00 116

(b) Financing

Source of Funds Type of

Cofinancing

Appraisal

Estimate

(USD

millions)

Actual/Latest

Estimate

(USD

millions)

Percentage of

Appraisal

Trust Funds 0.00 0.00

Afghanistan Reconstruction Trust

Fund 10.00 15.00 150

21

Annex 2. Outputs by Component

Provision of Management Services “On Demand”

The project recruited a total of 161 MCP experts over a period of four years against a

target of 175 over the same period. Recruitments under MCP started almost 10 months

after the effectiveness of the project. Initially the line ministries were slow to grasp the

objective of MCP and thus requested a variety of positions to be funded through MCP

which were outside its mandate. Many of these positions were not aligned to the ministry

strategic plans and reflected ad-hoc requirements. Performance of the communication and

outreach activities of the GDPDM in informing the line ministries about the MCP

approach and objectives could be termed as unsatisfactory in this regard. This is also

supported by the information provided in table 2 above. The number of positions

approved is considerably lower than the requested number of positions throughout the

project period.

The MCP was able to attract talented and qualified Afghan nationals from the Diaspora

and other private and donor-funded positions into the core Civil Service. The program

was able to create a critical mass of champions in ministries such as Ministry of Finance

(MoF), Ministry of Commerce and Industries (MoCI), Ministry of Agriculture, Irrigation

and Livestock (MAIL) and Ministry of Mines (MoM) who led their ministry-wide reform

processes. The majority of the MCP recruits possessed at least an undergraduate degree.

About 25 per cent of the MCP experts obtained a post graduate qualification or a

Master‘s in Business Administration (MBA). The ICR mission noted that administrative

procedures associated with the verification of educational documents caused major delays

in postings and salary payments of the selected individuals.

Sub-national recruitments needed more attention under the program. GDPDM failed to

achieve significant numbers for sub-national positions during the project life-time. It is

important that under CBR, the IARCSC needs to prepare a well-designed strategy for

provincial recruitments given the enormous responsibility it bears with respect to the

Transition period and beyond. A snapshot of challenges faced by some of the regional

offices of Ministry of Agriculture, Irrigation and Livestock (MAIL), Ministry of Public

Health (MoPH) and IARCSC is provided in Table 3 below.

Table 3: Sub-national Challenges

Ministry/Agency Department/Directorate Challenges

MAIL

Helmand Provincial Office (i)Lack of Infrastructure

(ii)Vacant positions and lack of skilled staff.

(iii)Lack of Tashkeel (Establishment) for certain areas such as

forestry and research.

Nangarhar Valley Development (i)Shortage of budget under operations and development

component

(ii)Inadequate office facilities

(iii)Shortage of managerial and technically skilled staff

(iv)Lack of training facilities for staff

MoPH Farah Provincial Office (i)Security Condition

22

(ii)Lack of female doctors

(iii)Low salaries for P&G staff

IARCSC Kandahar Regional Office (i)Lack of professional cadres at provincial levels

(ii)Educational and training programs for the P&G staff

(iii)Inadequate office Infrastructure

(iv)Lack of a comprehensive capacity development plan

Some Achievements under the “Cluster” Approach

During late 2009/early 2010, the program started recruiting batches or ―clusters‖ of

MCPs for key ministries. A brief account of the achievements of this approach for some

of the ministries is mentioned below.

Ministry of Commerce & Industries (MoCI): The MCP expert for International

Trade department facilitated the World Trade Organization (WTO) accession

process and the South Asian Free Trade Agreement (SAFTA) has been signed.

The MCP expert for the Business Licensing Department conducted a capacity

needs assessment and has prepared a Capacity Development Plan. Six zonal

offices are now connected to the online database. The MCP expert has also

modified the legal framework for licensing.

Ministry of Finance (MoF): The MCP expert for State Owned Enterprises (SoE)

has led the liquidation of a number of government establishments according to the

Privatization Policy of the government. The MCP appointee for the large

taxpayers office have simplified the tax filing procedures as a result of which

taxpayers compliance have increased from 60% to 90%. An Aid Effectiveness

Policy Unit under the Aid Management Directorate has been established and a

capacity development plan has been prepared.

Ministry of Communication and Information Technology (MoCIT): MoCIT has

three MCPs currently, Director General of Information and Communication

Technology, Director General of Planning and International Relations and the

Head of the National Data Center. Specific achievements include designing of

eighty government websites under the E-Government Interoperability Framework

Standards and collection of statistical data for telecommunications, postal and IT

services from 34 provinces. Overseas training for 32 staff members of MoCIT has

been facilitated through the Ministry of Foreign Affairs.

23

Annex 3. Grant Preparation and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending

Anne Tully Senior Operations Officer OPCFC Public Sector Management, TTL

Nigel Peter Coulson Senior Public Sector Specialist SASGP TTL

Ranjana Mukherjee Senior Public Sector Specialist SASGP Public Sector Management

Hossai Mahak Aliffi Team Assistant SASPF Program Assistance

Vidya Kamath Program Assistant SASGP Program Assistance

Supervision/ICR

Satyendra Prasad Senior Governance Specialist SASGP TTL

Richard Spencer Hogg Governance Adviser SASGP TTL (ICRR)

Deepal Fernando Senior Procurement Specialist ECSO2 Procurement

Monali Chowdhurie -Aziz Senior Public Sector Specialist WBIOG Public Sector Management

Asif Ali Senior Procurement Specialist SARPS Procurement

Kenneth O. Okpara Sr Financial Management Specialist SARFM Financial Management

Asha Narayan Financial Management Specialist SARFM Financial Management

Zohra Farooq Financial Management Specialist SARFM Financial Management

Rahimullah Wardak Procurement Specialist SARPS Procurement

Vishal Gandhi Consultant SASGP Public Sector Management

Maha Ahmed Consultant SASGP Public Sector ; Monitoring and

Evaluation

Jalpa Patel Consultant SASGP Public Sector Management

Vidya Kamath Program Assistant SASGP Program Assistance

Mohammed Edreess Sahak Team Assistant SASEP Program Assistance

Kaushik Sarkar Consultant SASGP Public Sector Management

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including travel

and consultant costs)

Lending

FY07 0 0

Total: 0 0

Supervision/ICR

FY07 BB – 4.83 20,971.38

FY08 BB – 9.13 55,971.42

FY09 BB – 22.02 113,313.36

FY10 BBTF – 28.70 125,743.69

FY11 BBTF – 15.35 106,206.11

FY12 BBTF – 4.10 31,039.89

Total: 453,245.85

24

Annex 4. Summary of Grantee's ICR and/or Comments on Draft ICR

BORROWER’S EVALUATION

Implementation Completion and Results Report

ARTF funded Management Capacity Program (MCP)

The Independent Administrative Reform and Civil Service Commission (IARCSC) of the

Government of Islamic Republic of Afghanistan (GoIRA) implemented the ARTF

(Afghanistan Reconstruction Trust Fund) funded Management Capacity Program (MCP)

to achieve sustained improved performance in the management capacity of key

departments of GoIRA ministries dealing with any or all of the common functions,

including financial management, policy and regulatory design, and administration. The

implementation was spread over 4 & ½ years from 2007 to 2011. Within IARCSC, the

General Directorate of Programs‘ Design and Management (GDPDM), formerly Capacity

Development Secretariat (CDS) was responsible for the implementation of MCP.

The GDPDM is the lead IARCSC general directorate on institutional capacity

development, project design and management, and donor relation and coordination. The

mandate of GDPDM includes development, review, and coordination of strategic options

for delivering development programs as part of Public Administration Reform (PAR) in

the context of Afghan National Development Strategy (ANDS).

The MCP was a successor to a series of earlier operations of World Bank to support civil

service reform in Afghanistan. The two interventions envisaged in MCP were:

Provision of executive services ―on demand‖ and to provide experienced

managerial level staff to ministries; and,

To put in place an establishment for the efficient management of the program that

evolves into a permanent service of the IARCSC.

These interventions had the objective of improving performance of management capacity

of key departments of GoIRA ministries and thereby contributing to enhanced and cost

effective utilization of budgetary resources and better delivery of public services.

25

During the lifetime of the project, a total of 193 positions were processed under the MCP.

The MCP appointees were placed across 28 ministries / agencies of GoIRA including

provinces. During the initial years, the implementation of the program was supported by

a consulting firm (Adam Smith International) which helped to improve the foundations of

a robust and transparent recruitment process as well as a sound monitoring & evaluation

(M&E) system. GDPDM has used lessons learnt from other projects to improve the

management of MCP, increase the number of MCP applicants and the number of MCP

support requests from Ministries, improve the MCP Appointee selection process for more

transparency, and adopt a clustering approach for a more holistic support through MCP.

The GDPDM has strived hard to ensure transparency in the MCP recruitment process.

The recruitment was fully aligned with the principles of merit based recruitment process

under the civil servants‘ law. The decision making process had involvement of

beneficiary ministries / agencies at all stages of recruitment. Commissioners of

IARCSC‘s Boards chaired the panels and external experts such as university professors

and sector specialists were invited to assist and observe the MCP interviews and provide

their inputs in the recruitment process.

The salary scale which is approved by steering committee where the World Bank was the

observer has always been the base for any salary determinations. The confusion has

mostly been arisen due to different understanding of three different task team lead for the

MCP. The recommended revisions in using the scale have always been adapted by the

IARCSC. Referring to past salary history of candidates was one of recommendations

made by previous WB task team who was clearing the NoLs. The market distortion

caused by donor salary top ups has always been a challenge in determining salary for a

candidate under the MCP.

The M&E section of GDPDM developed a standardized M&E system inclusive of

comprehensive tools to assess departmental performance of MCP experts at regular

intervals (baseline, six months, annual, two years and on ad-hoc basis). The assessment

reports / feedback were regularly shared with respective departments including MCP

experts and other stakeholders to portray the ratio of change in the aforementioned

intervals within the departments under the support of MCP. While the system served very

well for performance assessment of individual MCP experts, at the systems level,

measuring change for broader objectives of improved service delivery proved to be

challenging. Frequent communication regarding the requirement of system modification

took place with the Bank Task Team. However, on account of limited timeframe of the

program and preoccupation of both Bank Task Team and GDPDM with designing a

follow on operations of MCP namely, the Capacity Building for Results (CBR) Facility,

further enhancement to the MCP M&E tools could not be taken up. Service delivery and

budget execution performance are two long term indicators which were difficult to be

achieved over the life cycle of the MCP. However, despite such constraints, the GDPDM

provided the Bank with data indicating the extent to which MCP experts had been

effective in improving the delivery of services and executing their departments‘ budgets.

For example, during the individual Ministry assessments, all MCP teams displayed an

increase in percentage of expenditure in critical Ministries, e.g. Ministry of Finance,

26

Agriculture, Health and etc. As a result of this impact, the procurement process and

contract management systems also improved and most of these Ministries qualified for

Direct Funding by donors and direct procurement authority.

The overall goal of the government is to improve the delivery of public services which

primarily takes place at sub-national level. Capacity for service delivery needs to improve

dramatically at sub-national level to ensure on-going legitimacy of the state and the peace

and stability of Afghanistan. MCP had a target of allocating twenty percent of the

appointments for sub-national level positions. This could not become feasible primarily

on account of the preferences of ministries/ agencies to prioritize for their immediate

needs of strengthening management capacity at central level. Secondly, the program as

envisaged intended to expand to a total allocation of USD 35 million which would have

supported 240 positions. However, within the available resources, only 153 appointments

could be supported under the program, limiting the planned subsequent expansion to sub-

national level. The follow-on program namely the CBR Facility, with its revamped

approach and enhanced allocation is likely to respond to the requirement of expanding

the program to sub-national level.

Further, the MCP could only recruit staff to grades 1, 2 and 3 of the civil service and this

became a serious bottleneck in many ministries which needed a second tier of managers

under the MCP experts to execute the ministry mandates in Kabul as well as in the

provinces. Considering the lessons learnt from the implementation of MCP, GDPDM has

emphasized on the expansion of the scope of the project to support the second and third

tier managers under the follow-on CBR Facility. Also, GDPDM initiated injecting

clusters into the line ministries during the last year of MCP implementation which led not

only to the recognition of MCP at the country level but also increased the productivity of

the respective government ministries. The MCP experts contributions in their respective

areas of work was endorsed and felicitated by the President and their respective

supervisors (mostly deputy ministers) and three of them have been promoted to the

positions of deputy ministers (Ministry of Commerce and Industries, Ministry of Mines

and Ministry of Labor, Social Affairs Martyred and Disabled).

The program assumed that MCP appointees do not need any additional capacity

development and that the ministries / agencies to which they are appointed will provide

them office facilities, etc., for their effective functioning. The IARCSC signed MoUs

with respective ministries / agencies and the responsibility of providing MCP experts

with necessary office supplies, such as computer, phone etc., rested with respective

ministry / agency. There was no provision in the program to step in and provide an

alternative in cases where the ministries / agencies failed to respond to the needs of MCP

appointees in a timely manner. The GDPDM continued with its promotional activities to

sensitize the ministries / agencies in this regard. Further, in coordination with other

capacity development programs, implemented by IARCSC, the MCP appointees were

included in the exposure visits to other countries (Korea, Italy, India) to widen their

knowledge and upgrade their skills.

27

MCP implementation was fully embedded in IARCSC and its relevant departments

played crucial roles in the management of MCP. For example, Appointments Boards‘

Commissioners chaired and led the recruitment process. All cases of grievances /

complaints regarding MCP recruitment process were processed by the IARCSC Appeals

Board. The MCP expert‘s performance evaluation forms were attested by the Chairman.

All financial arrangements of MCP were coordinated with the Finance department of the

Commission. GDPDM also coordinated and communicated MCP‘s provincial related

agendas with the IARCSC Provincial Affairs Directorate (PAD). GDPDM‘s

communication and outreach department frequently shared the MCP progress reports

with IARCSC‘s Communication and Media Relations Directorate. It is therefore not a

correct conclusion that there was no significant involvement of other departments of the

IARCSC in management and oversight of the MCP and GDPDM leadership exercised

full control over program management. In fact, the foremost and significant achievement

of MCP was to mainstream the CDS, an erstwhile PMU of IARCSC responsible for MCP

implementation into GDPDM, a full-fledged general directorate of IARCSC with a

defined mandate such that the processes of GDPDM were fully embedded with the

processes of other directorates of IARCSC.

Under a visionary leadership accompanied by competent staff, the IARCSC-GDPDM has

been able to transform MCP into a well-known project at country level, signified in

Kabul Conference and acknowledged by the President indicating the impact it made in

the government. The overall implementation progress of the project is strongly believed

to be “Highly satisfactory” and not “Moderately satisfactory”.

The Kabul Conference marked a new phase in the partnership with donor community

namely, the Kabul Process. The Afghan Government‘s program has been defined by

measurable benchmarks contained in National Priority Programs (NPPs) that represent

the prioritized requirements of the ANDS. The hallmark of the Kabul Process is Afghan

leadership and ownership. Earlier, the Consultative Peace Jirga of June 2010 was an

expression of national consensus and gave a mandate to adopt a ―whole of the state‖

approach and ―whole of government‖ path to national renewal. The essence of the ―whole

of the state‖ is constitutionalism and the essence of the ―whole of government‖ approach

is structural reform to create an effective, accountable and transparent government that

can deliver services to the population and safeguard national interests.

The IARCSC is implementing the NPP3 for ―efficient and effective government‖

following the ―whole of government‖ approach and has now taken lead in implementing

Capacity Development programs for Afghan Civil service under the overall Public

Administration Reform agenda that follows a ―whole of ministry‖ approach. The cluster

approach promoted by MCP towards later part of its implementation lays the foundations

of a ―whole of ministry‖ approach which has now been fully embedded in the MCP

follow-on program – ―Capacity Building for Results (CBR) Facility‖.

28

Annex 5. List of Supporting Documents and MCPs Interviewed

World Bank: Management Capacity Program (MCP) Documents (P106170)

MCP Implementation Support Mission Aide Memoire (February, 2009)

Implementation Status and Results (March 2010)

Implementation Status and Results (November 2010)

Mid-Term Review (October-November 2010)

Implementation Status and Results (December 2011)

MCP Technical Annex

Implementation Completion Report for AEP and LEP, IARCSC (August 2010)

Assessment of the TAFSU, AEP and LEP

Review of the Lateral Entry Program (LEP), NORAD (May, 2006)

Interviews

Mr. Rohullah Osmani, Director General, GDPDM

Mr.A.Foshanji, Director (Operations), GDPDM

Mr.Faizan Ahmad, Director (Human Resources), Ministry of Women‘s Affairs

Mr.A.W.Arian, General Director for Policy and Planning, Ministry of Education

Mr.Khair Mohammad ―Niru‖, Director General, Manpower & Labor Affairs Regulations,

Ministry of Labor, Social Affairs, Martyrs and Disabled (MoLSAMD)

Mr.J.H.Samadey, Director (HR), MoLSAMD

Dr.Q.Qaeym, Director General, Directorate of Oil & Gas Survey, Ministry of Mines

(MoM)

Ms.G.Habibyar, Director (Policy), MoM

Mr.M.W.Etabar, Director (Finance & Accounts), Ministry of Agriculture, Irrigation and

Livestock (MAIL)

Mr.M.Y.Hotak, Director (Human Resources & Capacity Development), MAIL

Prof.S.W.Ataye, Director (Policy, Planning and Foreign Affairs), Ministry of Justice

(MoJ)

Mr.A.N.Baizayee, Director General (HR), Ministry of Education (MoE)

Mr.M.Ebrahim, Director (Finance), MoM

Ms.M.Akbari, Director (Investment Promotion), MoM

Mr.S.Z.Hashemi, Director (Legal), MoM

Mr.M.Aqa, Director General (Treasury), Ministry of Finance (MoF)

Mr.H.Jalil, Director of Aid Management Directorate, MoF

Tirich MirTirich Mir(7690 m)(7690 m)

D a s h t - I M a r g oD a s h t - I M a r g o

Khyber PassKhyber Pass

P a r o p a m i s u s R a n g e

H i nd

u

Ku

sh

B A D G H I SB A D G H I S¯¯

H E R ATH E R AT¯ G H O RG H O R

FA R A HFA R A H¯

¯ ¯N I M R O ZN I M R O Z K A N D A H A RK A N D A H A R¯

U R U Z G A NU R U Z G A N¯

PA K T I K APA K T I K A¯ ¯

G H A Z N IG H A Z N I

NANGARHARNANGARHAR¯

KABULKABUL¯LAGHMANLAGHMAN

B A G H L A NB A G H L A N¯

KAPISAKAPISA¯ ¯ ¯

SAMANGANSAMANGAN¯

TAKHARTAKHAR BADAKHSHANBADAKHSHAN¯

KUNDUZKUNDUZ¯¯JAWZJANJAWZJAN

FA R YA BFA R YA B¯ ¯

H I L M A N DH I L M A N D

Z A B U LZ A B U L¯

B A L K HB A L K H

SARIPULSARIPUL NURISTANNURISTAN¯ ¯

Meydan ShahrMeydan Shahr¯

BamyanBamyan¯ ¯¯ ¯ ¯CharıkarCharıkar

GardızGardızGhaznıGhaznı

¯ ¯TaloqanTaloqan¯KondozKondoz

¯BaghlanBaghlan¯SamanganSamangan

¯¯

Mazar-eMazar-eSharıfSharıf

¯SheberghanSheberghan

¯ChaghcharanChaghcharan¯HeratHerat

¯FarahFarah

ZaranjZaranj

¯Lashkar GahLashkar Gah¯KandaharKandahar

¯QalatQalat

¯Tarın KowtTarın Kowt

Pol-e ‘AlamPol-e ‘Alam

¯ ¯ ¯JalalabadJalalabad

¯MehtarlamMehtarlam

¯ ¯NuristanNuristan¯ ¯AsadabadAsadabad

SharanSharan

MeymanehMeymaneh

Qal‘eh-ye NowQal‘eh-ye Now

¯ ¯¯Mahmud-e RaqıMahmud-e Raqı¸

FaisabadFaisabad

KABULKABUL¯

WA R D A KWA R D A K

PARWANPARWAN¯KUNARKUNAR

LOGARLOGAR

KOWSTKOWSTKowstKowst

PAKTIAPAKTIA

PANJSH

IR

PANJSH

IRBazarakBazarak

B A D G H I S¯¯

H E R AT¯ G H O R DAY KUNDIDAY KUNDIDAY KUNDI

FA R A H¯

¯ ¯N I M R O Z K A N D A H A R¯

U R U Z G A N¯

PA K T I K A¯ ¯

PAKTIA

G H A Z N I

NANGARHAR¯

KABUL¯LAGHMAN

B A G H L A N¯

KAPISA

PANJSH

IR

¯ ¯ ¯PARWAN¯

SAMANGAN¯

TAKHAR BADAKHSHAN¯

KUNDUZ¯¯JAWZJAN

FA R YA B¯ ¯

H I L M A N D

KOWST

Z A B U L¯

LOGARWA R D A K

KUNAR

B A L K H

SARIPUL

BAMYAN¯ ¯

NURISTAN¯ ¯

Meydan Shahr¯

Bamyan¯ ¯¯ ¯ ¯Charıkar

Bazarak

GardızGhaznı

¯ ¯Taloqan¯Kunduz

¯Baghlan¯Samangan

¯¯

Mazar-eSharıf

¯Sheberghan

¯Chaghcharan

Nili

¯Herat

¯Farah

Zaranj

¯Lashkar Gah¯Kandahar

¯Qalat

¯Tarın Kowt

Pol-e ‘Alam

¯ ¯ ¯Jalalabad

¯Mehtarlam

¯ ¯Nuristan¯ ¯Asadabad

Sharan

Kowst

Meymaneh

Saripul

Qal‘eh-ye Now

¯ ¯¯Mahmud-e Raqı¸

Faisabad

KABUL¯

TURKMENISTAN

UZBEKISTANTAJIKISTAN

TAJIKISTAN

PAKISTAN

PAKISTAN IND

IA

ISLAMICREPUBLICOF IRAN

Gowd-eZereh

Helmand

Helmand

Hamun-eSaberı˛

¯ ¯¯ ¯

Harırud¯ ¯

Morghab¯¯

¯

Pamir

Pyandzh

Indu

s

MurghobAmu Darya

Khas

Farah¯

Harut

¯ ¯

Darya-y

e Qonduz

Tarnak¯

Arghandab

D a s h t - I M a r g o

Khyber Pass

P a r o p a m i s u s R a n g e

H i nd

u

Ku

sh

Tirich Mir(7690 m)

ToMashad

ToMary

ToChardzhev

ToDushanbe

ToKulob˘

ToDushanbe

To Shazud

ToChitral

ToMardan

To Peshawar

ToKohat

ToZhob

ToQuetta

ToQurghonteppa˘

30°N

30°N

35°N

60°E

35°N

75°E

60°E

65°E 70°E

65°E 70°E

AFGHANISTAN

0 50 100

0 50 100 Miles

150 Kilometers

IBRD 33358R1

OC

TOBER 2011

AFGHANISTANPROVINCE CAPITALS

NATIONAL CAPITAL

RIVERS

MAIN ROADS

RAILROADS

PROVINCE BOUNDARIES

INTERNATIONAL BOUNDARIES

This map was produced by the Map Design Unit of The World Bank. The boundaries, colors, denominations and any other informationshown on this map do not imply, on the part of The World BankGroup, any judgment on the legal status of any territory, or anyendorsement or acceptance of such boundaries.