Upload
rolandnikles
View
594
Download
1
Tags:
Embed Size (px)
Citation preview
ABAMarch 26, 2013
Design-Build Gone WrongLessons Learned
J. Mark DunganDelta Consulting Group
1
Design-Build vs. Design-Bid-Build
The Growth of D/B Method (DBIA 2004)
82.3%
72.0%
65.0%
54.0%
40.5%
5.3%
16.0%26.0%
36.0%
45.3%
50.0%
12.4% 12.0%9.0% 10.0% 9.4% 9.5%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
1985 1990 1995 2000 2005 2010
Traditional Design/Bid/Build Design/Build Construction Management @Risk
Design-Build Projected Trend in 2004
2
Design-Build vs. Design-Bid-Build
3
Design Risk in a Design-Bid-Build Contract
Design-Bid-Build vs. Design-Build
4
Design Risk in a Design-Build Contract
Design-Bid-Build vs. Design-Build
5
Owner
DesignProfessional
CONTRACT
SUBCONTRACT
SubContractors
Comparison of Contractual Structure Design-Bid-Build vs. Design-Build
ConstructionDocuments
CONTRACT
Contractor
Bid Based onDefined Scope
Design-Bid-Build
6
Design-Bid-Build Design-Build
CONTRACT
Owner
Contractor
Comparison of Contractual Structure Design-Bid-Build vs. Design-Build
Owner
DesignProfessional
CONTRACT
SUBCONTRACT
SubContractors
ConstructionDocuments
CONTRACT
Contractor
Bid Based onDefined Scope
Bid Based onPerformance Criteria and
General Specifications
Designer Builder
SUBCONTRACT
SubContractors
ConstructionDocuments
7
ContractorDesigner Builder
Design-Build
• Provides Performance Criteria
• Provides General Specifications
Owner
• Provides Design Team• Detailed Construction
Documents• Management of
Construction
Contractor
CONTRACT
Owner
Bid Based onPerformance Criteria and
General Specifications
SUBCONTRACT
SubContractors
ConstructionDocuments
8
Design Build Concept
Owner Specifies
Project Needs
Owner and Design Builder agree on Price and Contract
Design Builder Prepares Detailed Design
Documents
Owner Approves
Design
Contractor Builds
According to Agreed Designs
Owner Reviews Design for
Compliance
9
10
Design-Build vs. Design-Bid-Build
Both Owners and the Design Builders Occasionally Misapply the Design Build Concept…
We will present examples of each.
Typical Problem Areas
11
ScopeDesign Construction
DB designs minimal to meet performance, Owner expected higher standard
Unlike DBB, Scope is sometimes vague, a change to the DB is a design evolution to the Owner
DB may provide basic industry standards while Owner expected greater standards
Example of Owner Misapplied Concept
Owner Specifies
Project Needs
Owner and Design Builder Agree on Price and Contract
Design Builder Prepares Design
Documents
Owner Approves
Design
Contractor Builds
According to Agreed Designs
Owner Burdens Design Process
12
Typical Problem Areas
Design
DB designs minimal to meet performance, Owner expected higher standard
Example:Large Industrial Complex.
13
14
A1
• Design development to point of Owner review.
AFC orRev 00
• Incorporates Owners Comments to A1, Approved for Construction
Rev 01
• Incorporates any minor comments or from unforeseen issues
DB’s Expected Drawing Development
Evolution of Drawing 101
15
101 – A1
101 – A2
101 - 00
101 Rev. 1
101 Rev. 2
101 Rev. 3
101 Rev. 4
………………….
101 Rev. 12
12/21/07
20092007 2008
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Work Started in July 2007. The evolving design, due to owner
changes, delayed the initial drawing submittals until
December.
16
E1
Evolution of Drawing 101
Owner Rejects Drawing:
• Comment #1: Owner prefers the two plans be combined and produced at a larger scale.
• Comment #2: Owner directs preferred labeling of Walls
17
E2
2/24/08
20092007 2008
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Contractor adds changes complying with Owner changes.
The two drawings were combined into one as
requested.
18
Evolution of Drawing 101
Owner Rejects Drawing:
• Comment #3: Owner states that the combined drawing scale is now too small to describe the details desired.
• Comment #4: Owner comments that the line width used on the drawings was to narrow.
19
00
4/4/08
20092007 2008
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
102 103
104 105
106 107
20
Rev 00The Owner requires what was a
single drawing now be broken out into six new detail drawings
101Key Plan
102 103 104 105 106 107
Effort x 1
Design Effort Increased x 6
Drawing 101 Becomes 7 Separate Drawings
21
01
4/20/08
20092007 2008
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
22
Drawings Issued for Construction on April 4th
Floor slab revised to accommodate preferential
Owner decision to add Storage and Bathrooms.
Change required on 3 separate drawings
Evolution of Drawing 101
Owner Rejects Drawing:
• Comment #5: Owner requires the removal of an a reference to another drawing, wants detail on each drawing.
• Comment #6: Owner requires that a note describing a typical expansion joint be specifically added at each joint location.
23
03
10/18/08
20092007 2008
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
24
Walls moved to increase size.
Evolution of Drawing 101
Owner Rejects Drawing:
• Comment #7: Owner now wants 20 more expansion joints. Although all are the same, the Owner requires that each has to be specifically detailed.
25
04
10/31/08
20092007 2008
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
26
All 7 Drawings reissued specifically detailing 20
Expansion Joints.
Evolution of Drawing 101
Owner Rejects Drawing:
• Comment #8: Owner increases size of equipment in the building, rejects drawing and directs that it be changed to accommodate the new equipment.
27
101
102 103 104 105 106 107 108 Count of Drawings
11/4/07 A1 A1 A1 A1 A1 A1 A1 7
11/18/07 00 00 00 00 00 00 00 7
12/12/07 01 01 01 01 01 01 6
2/7/08 01 02 02 02 02 02 02 7
2/14/08 03 03 2
3/21/08 04 04 2
10/10/08 02 05 02 03 05 03 03 7
5/22/09 04 1
5/29/09 03 04 2
8/19/09 06 06 2
28
29
A1
• Design development to point of Owner review.
AFC orRev 00
• Incorporates Owners Comments to A1, Approved for Construction
Rev 01
• Incorporates any minor comments or from unforeseen issues
Expected Drawing Development
A1
A2
A3
A4
AFC Rev 1
Rev 2 Rev3 Rev4
Rev 5 Rev 6 Rev12
30
Impacts Caused by Owner’s Design Process Involvement
>10,000 Additional Drawings
Impacts of Owner Misapplied Concept
31
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
ReviewSheet
Over 12,000 Drawing Review documents
Issued by the Owner
ReviewSheet
Anticipated
Scope
Preferential
Over 30,000 Individual Owner Comments
Impacts of Owner Misapplied Concept
• The Owner’s design involvement caused the Contractor:
– Unplanned additional resources needed for management, development, and production of drawings
– More time required to progress job
– Contractor’s costs to complete the project increased above what was bid
32
33
Construction
DB may provide basic industry standards while Owner expected greater standards
Example:Power Station
Example of Contractor Misapplied Concept
Example of Contractor Misapplied Concept
Owner Specifies
Project Needs and Price
Owner and Design Builder agree on Price and Contract
Design Builder Prepares Design
Documents
Owner Reviews Design for
Compliance
Contractor Builds
According to Agreed Designs
Contractor Does Not Work With
Owner Specification
34
DBB DB
CONTRACTCONTRACT
SUBCONTRACT
Owner
Contractor
SubContractors
DesignProfessional
CONTRACT
SUBCONTRACT
Owner
Contractor
SubContractors
DesignProfessional
SUBCONTRACT
Comparison of Contractual Structure Design-Bid-Build vs. Design-Build
35
$
DB
CONTRACT
SUBCONTRACT
Owner
Contractor
SubContractors
DesignProfessional
SUBCONTRACT
• Design Errors and Omissions are Under Contractor Liability
• Subcontractor Time and Money Claims are charged against Contractor to correct design issues
• Possible LD’s to Owner
$ $
Design Build – Liabilities
36
• Plant was nearly operational
• Over half of systems turned over
• ~500 well defined punch list items
Completion Work Status
At Termination:
Example of Contractor Misapplied Concept
37
Opposing Views of Project
Contractor’s Story
• Project will Perform as Contracted
• Essentially Operational
• Owner Being Unreasonable
38
Owner’s Story
• Project Not Built as Contracted
• Auxiliary Systems not Built Per Design
• Contractor Failed to Perform
Upon Investigating the Work-in-Place,
–Design did not Conform to Owner’s Criteria,
–Work in Place did not Conform to Detail Construction Design
39
Example of Contractor Misapplied Concept
$
DB
CONTRACT
SUBCONTRACT
Owner
Contractor
SubContractors
DesignProfessional
SUBCONTRACT
Design Professional’s Contract was essentially a Typical Subcontract Agreement.
When General Contractor was Terminated, Design Professional took the position they had no further contractual obligation.
Design Build – Liabilities
40
Punchlist Item:
“Drain funnels are spraying fuel oil on the ground”
EXAMPLE of DESIGN ISSUES
Unit Drain System
Example of Contractor Misapplied Concept
41
Owner Equipment
Unit Drain SystemProblem Encountered:
Fuel Oil Is Spilling
• Unexpected Result• Environmental Issue
EXAMPLE of DESIGN ISSUES
42
Owner Equipment
What Was SPECIFIED: Funnel Connection was Specified by Manufacturer
of this Owner Supplied Equipment
Vendor Required Funnel Connection
EXAMPLE of DESIGN ISSUES
2”
1”
43
Conflict in Specifications and Design Drawings.
• Design-Build contractor Changed the Owner’s Requirement for a funnel connection without the Owner’s Review of Approval.
EXAMPLE of DESIGN ISSUES
44
Owner Equipment
What was DESIGNED: Contractor’s Design Drawings showed the 1” pipe being connected to a 1” underground pipe by a Flange Joint
1”
1”
EXAMPLE of DESIGN ISSUES
45
Conflict in Engineering Design Drawings and Actual Construction.
• Owner Refused to Accept Flanged Connection, they were supposed to have a Funnel Connection.
• Design-Build Contractor, Cut Off the Flange and Welded on a Funnel Connection.
EXAMPLE of DESIGN ISSUES
46
Owner Equipment
Field Change: Contractor makes field change for a funnel connection
without the Owner’s Review or Approval
EXAMPLE of DESIGN ISSUES
47
Contractor’s Resolution: A 1” pipe with funnel connection runs
underground to a tank
1”
1”
Owner Equipment
EXAMPLE of DESIGN ISSUES
48
New Design
1”
2”
Owner Equipment
EXAMPLE of DESIGN ISSUES
49
Owner Equipment
Steps to ResolveRemove Work-in-Place and Install New Work
EXAMPLE of DESIGN CORRECTIONS
• Stop System• Hand excavate and
Remove 1” Pipe• Install 2” Pipe and
Appropriate Funnel• Backfill
50
• Unapproved and non-conforming design had to be corrected by the replacement engineer
• Significant portions of work-in-place had to be removed and re-constructed in accordance with corrected design
• As more systems were inspected and design was corrected, the Punch list grew to over 2,000 items
51
Example of Contractor Misapplied Concept
Lessons Learned
52
ScopeDesign Construction
Owner strive to specify its desires pre-contract and then limit review to compliance
Define Scope matrices that specifically identify items and responsible party
Define Standards pre-contract, evaluate experience of Design Builder
Thank You for this Opportunity
The End
53
54
Delta Consulting Group, Inc.4330 Prince William Pkwy., Suite 301Woodbridge, VA 22192703.580.8801 (p) | 703.580.8802 (f)www.DELTA-CGI.com
J. Mark Dungan: Co-Founding PartnerEmail: [email protected]
Delta Consulting Group is an international consulting firm of multi-disciplined professionals in engineering, accounting, construction, project management and litigation support. Our key services include: Dispute Avoidance/Resolution, Expert Witness Testimony, Project Management, Financial Advisory, as well as Troubled Project and Surety Consulting.