31
DISTRIBUTION SYSTEM PLANNING TUTORIAL MN Power Systems Conference November 6, 2014

DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

DISTRIBUTION SYSTEM PLANNING TUTORIAL

MN Power Systems Conference

November 6, 2014

Page 2: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

2

CONNEXUS ENERGY

• 128,000 customers

• 1,000 sq. miles territory

• 44 substations

• 8,800 miles distribution

• 12.47 kV

• Wholesale supplier –

Great River Energy

Hwy 10

Hwy 65

Page 3: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

3

OUTLINE

Planning – reacting “Reactive Planning”

• Externalities – stuff comes up not planned for

• Reactive Planning

Backfeeding – Contingency Planning

• Emergency vs Alternate Normal

• Capacity Planning

Case Example – Johnsville Transformer Failure

• Capacity Planning

• Reactive Planning

• Contingency Event

Page 4: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

4

“REACTIVE PLANNING”

Events or Plans by Others – direct effect to Distribution Plant • Road construction (road moves) • Infrastructure failure (cable)

New “Opportunities” • New developments (why didn’t we hear about his last year?) • Large Load Development – ex: Data center

Other “Externalities” • Economic changes (crash of 2008) • Conservation (by plan, or trying reducing due to higher energy costs) Need to plan; scan your environment ; be prepared to react; adjust (re-create) the “plan” Quote by a Senior Planning Engineer: “the forecast will never be correct”

Review

Forecast

Identify Solutions

Select

Construct

“Adjust” plan

Page 5: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

5

PLANS BY OTHERS… ROAD CONSTRUCTION

Distribution Lines Located in Public Road Right-of-way • Permitting required for construction • No “easement” cost • Risk – utility bears cost if needed due to road construction

Can We Plan for Road Work? • Plan “road moves” capital budget • Challenge: Entities have plan, not always executed to plan • Often details not defined until after utility budgeting season • Road projects often crop up during the year

Page 6: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

6

ROAD MOVE “PLANNING”

Planning Year Construction Year

System Analysis & Engineering Planning

Complete

Contact Rd Agencies for Plans24

Budget Plan Complete

Receive Final Schedule / Details from Rd Agencies

Rd Construction Start

Rd Construction Complete

Design (or redesign) time Permitting Construction time Variance to “planned” budget

Page 7: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

7

ROAD MOVE PLANNING – ANNUAL CAPITAL SPENDING

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

2006 2007 2008 2009 2010 2011 2012 2013

Mean Median Std Deviation

1.00 1.01 0.22

Page 8: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

8

CABLE PLANT – FAILURE TRENDING

0

1000

2000

3000

4000

5000

6000

1969

1972

1975

1978

1981

1984

1987

1990

1993

1996

1999

2002

2005

Mil

es o

f W

ire

OH

Cable

•988 miles of cable installed before 1981.

• higher than normal failure rates.

Cable installed in 1981-1988 begins to reach its 30-year life in 2010.

Page 9: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

9

MAINLINE CABLE FAILURE – ANNUAL CAPITAL SPENDING

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

1.80

2006 2007 2008 2009 2010 2011 2012 2013

Mean Median Std Deviation

1.00 1.13 0.49

Page 10: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

10

SYSTEM EXPANSION & IMPROVEMENTS – ANNUAL CAPITAL SPENDING

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

2006 2007 2008 2009 2010 2011 2012 2013

Mean Median Std Deviation

1.00 0.98 0.30

Capacity, Voltage, Protection

Page 11: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

11

ANNUAL SYSTEM DEMAND – PICTURE FROM 2007

Growth

1.000

1.500

2.000

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

Customers kWhs Sum of Subs Pk kW

Period Ave Growth

1996-2001 7.1%

2001-2006 4.2%

1996-2006 5.5%

Actual through 2007

Projected 2008

Page 12: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

12

TREND FOR HISTORY VS ACTUAL DEMAND

Average Annual Growth 0.43%

0

100

200

300

400

500

600

700

800

900

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

Annual Growth

5.00%

Total System Demand - MW

Page 13: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

13

COMPARISON – LINE CONSTRUCTION ACTIVITIES

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

1.80

2006 2007 2008 2009 2010 2011 2012 2013

System Expansion

Road Moves

Cable Replacement

Page 14: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

14

TOTALIZED – LINE CONSTRUCTION ACTIVITIES

34

34 2006 2007 2008 2009 2010 2011 2012 2013

Cable Replacement

Road Moves

System Expansion

1.29

34% 39% 40%

49% 37% 35%

13%

42%

43% 43%

46%

44%

60% 53%

70%

41%

23%

18%

14%

7%

3% 12% 17%

17%

Std Deviation

0.18 1.17

1.05

0.66

0.95 0.95 0.94 0.98

Per unit of average

Page 15: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

15

KEYS TO REACTIVE PLANNING

How to react to global shift?

• Continue towards long range plan

• Shift time frame of execution

How to minimize capital costs but be ready to serve?

• Defer major investment until absolutely needed;

• Reduce lead time to complete

Review

Forecast

Identify Solutions

Select

Construct

Page 16: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

16

ALMOST NEED A SUBSTATION????

Example Problem: Load is close to needing substation expansion, but not quite…

Or… 1. Risk high dollar expenditure and the load doesn’t come?

2. Risk deferring the substation, load comes and cannot build fast enough to meet demand?

Economic Risk Reliability / customer service risk

Substation Elements:

• Engineering • Land Acquisition • Site Preparation

• Structures • Bus work / switchgear • Transformer

Plan: Do Up Front (Preparation)

Defer – React: Do when absolutely needed

“Plan - Defer - React”

Page 17: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

17

CONTINGENCY PLANNING (AND REACTING…)

Page 18: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

18

CONTINGENCY PLANNING

Build plant to handle loss / failure / needed alternate source of power

Issues to address:

• Investment made Reliability; Revenue

Duration of backfeed • Emergency only? • Extended? (“alternate normal”)

Use emergency equipment ratings, or normal load ratings?

Design contingency operation; • ANSI A (110 volts at meter) • ANSI B (114 volts at meter)

Use N-1? What do you do if event becomes N-2?

To what level of capacity to you build additional plant for contingency operations? • 100% of peak load • Less than 100%

Need plan for a 100% peak event Need operational plan to execute

Page 19: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

19

LOAD DURATION CURVE – PEAK LOAD

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Peak without AC 106 %

Controllable AC potential - 100% penetration

93% peak ->20 hrs/yr (0.22%)93 %

82 % Total residential central AC demand

Peaking Load - 330 hrs

Page 20: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

20

RELIABILITY RISK BASED ON % OF BACKFEED CAPABILITY

Backfeed Capacity

Exposure Cost Impact 10 yr NPV

(% of peak load)

Days / Year Hours / Day Per unit

No backfeed design 81 - 140 14 - 16 1.0

70 25 - 30 12 - 14 1.15

80 10 - 14 10 - 12 1.34

90 3 - 7 6 - 10 1.57

100 0 0 1.66

Page 21: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

21

EQUIPMENT LOADING – “NORMAL” VS “EMERGENCY”

Plant Equipment “Normal” “Emergency” Incremental capacity (%)

Cable (750 MCM Al) 475 532 12%

OH Wire (4/0 ACSR) 330 440 33%

Substation Transformer 28 MVA 35 MVA 25%

Page 22: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

22

STRATEGY ELEMENTS

Planning & Design Strategy: • Design feeders into multiple sections – backfeed per section • Shift load to 2nd tier substation – leverage existing transformer capacity • High probability of extended backfeed? Consider “normal load ratings” for contingency

plan • Quantify and understand the risk (voltage, capacity, degree of shortfall) • Have spare equipment (i.e., transformer) ready to roll

Operational Strategy: • Plan for placing emergency transformer in service in 24 hours. • Have a plan for contingency system operation • Have a plan to execute the plan !

Page 23: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

23

JOHNSVILLE SUBSTATION – FEEDER TIES TO 1ST TIER SUBS

BLN

HAM

APT

SLP

VTN

BUL

JON

Page 24: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

24

SCADA TRACE – TRANSFORMER TEMPERATURE

Page 25: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

25

TRANSFORMER DAMAGE

Page 26: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

26

CONTINGENCY PLANNING

Feeder BF Source Details (Range B requirement is 114 v.) ResultJON01 HAM04 106.9 v. 6.1 MW un-served

JON06 > 114 v. not applicable

SLP02 109.6 v. 6.1 MW un-served

JON01 Sec 1 SLP02

"Section Switch" is TP disconnects 2170-S: 111.7 v.; 4/0

ACSR 102% 4.7 MW un-served

JON01 Sec 2 HAM04

> 114 v.; ALSO > 114 v. if HAM04 BF JON02 with JON01

Sec 2; BUT 110.5 v. & 4/0 ACSR 114% if HAM04 BF JON02

& 03 with JON01 Sec 2 1.8 MW OK

JON02 HAM04 > 114 v. 2.8 MW OK

JON03 > 114 v. not applicable

JON03 JON02 > 114 v. not applicable

JON02 -HAM04 112.2 v. 2.2 MW un-served

JON04 BLN05 110.1 v. 4.4 MW un-served

HAM02 112.2 v.; 4/0 ACSR 109% 4.4 MW un-served

JON04 Sec 1 BLN05 "Section Switch" is disconnects 475-S: 113.6 v. 1.3 MW un-served

JON04 Sec 2 HAM02 > 114 v. 3.1 MW OK

JON05 APT05 > 114 v. 4.6 MW OK

JON06 > 114 v. not applicable

JON06 JON01 > 114 v. not applicable

JON05 > 114 v. not applicable

SLP06 113.8 v. 5.0 MW un-served

Page 27: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

27

LOADING SUMMARY

Projected peak: 24.8 MVA

Backfeed ability through distribution: 12.3 MW (~50%)

• System as is

• Plant normal load ratings

Feeder sectionalizing enhancement 5 MW

___________________________________________________

Remaining shortfall: ~7.5 MW (~30%)

Page 28: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

28

“ALTERNATE NORMAL” - PLAN

• 14 MVA “Spare” transformer

• Feeder section switches

• Tap phase changes

• LDC settings changes

Page 29: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

29

N-2 RISK….

Feeder BF Source Details (Range B requirement is 114 v.) Result

HAM04 JON01 111.2 v. 4.4 MW un-served

SLP02 JON01 > 114 v. 4.8 MW OK

HAM04 JON02 > 114 v. 4.4 MW OK

BLN05 JON04 112.7 v., 4/0 ACSR 107% 6.7 MW un-served

HAM02 JON04 111.0 v., 4/0 ACSR 105% 6.1 MW un-served

APT05 JON05 > 114 v. 4.3 MW OK

SLP06 JON06 > 114 v. 3.6 MW OK

With 14 MVA spare transformer, backfeed to OTHER subs still short by 8 MW

Page 30: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

30

CONTINUING CHANGE / EVOLUTION

Business Drivers:

Grid efficiency

Conservation

Reliability

Tools & Strategies:

IVVC – Integrated Volt/VAR Control

CVR – Conservation Voltage Reduction

FLISR – Fault Detection, Isolation, System Restoration

Line Sensors

AMI

DMS – Demand Management System

Communications System

Page 31: DISTRIBUTION SYSTEM PLANNING TUTORIALcce.umn.edu/documents/CPE-Conferences/MIPSYCON...Quote by a Senior Planning Engineer: “the forecast will never be correct” Review Forecast

31