Distributed Software Development. Customers : Damir Isovic (MDH) and  Klas Eriksson (OneDial AB). Beta prototype: Live TV. What we’ll speak about ?. 1. Project status 2. Project statistics 3. Experiences 4. Beta Prototype. 1. Project status. 1. Project status - Objective. - PowerPoint PPT Presentation

Citation preview

123-04-20

Distributed Software Development

223-04-20

Beta prototype: Live TV

Customers : Damir Isovic (MDH) and Klas Eriksson (OneDial AB)

323-04-20

What we’ll speak about ?

• 1. Project status

• 2. Project statistics

• 3. Experiences

• 4. Beta Prototype

1. Project status

423-04-20

1. Project status - Objective

523-04-20

• Objective: use mobile phones to record an event, select the better stream and send it live via the mobile network

1. Project status

623-04-20

• The project status is « almost » on track

• Studio Application and Player integrated

• Recorder is on the way (almost there )

2. Project statistics

723-04-20

2. Project statistics - General

823-04-20

2. Project statistics – Working hours

923-04-20

Member W40 W41 W42 W43 W44 W45 W46 Total %

Dalibor 12 11 6 11 7 6 7 60 -16.7%

Clément 8 6 3 12 11 13 8 61 -14.8%

Amer 8 5 13 10 10 16 11 73 4.1%

Nima 1 10 8 9.5 5 7.5 10 51 -37.3%

Neven 8 7 5 4 9 14 11 58 -20.7%

Darko 10.5 12 6 7 21 17 14.5 88 20.4%

Željko 8 7 5 8 14 19 21 82 14.6%

Total 55.5 58 46 61.5 77 92.5 82.5 473 -3.5%

1023-04-20

2. Project statistics - Working hours

1123-04-20

2. Project statistics - Working hours

• 473 (+252) hours on the project

• Almost 9.7 hours per week per person– Objective of 10 almost reached

• Difference of 72% (+12%) of work between members– Due to different tasks, different level of

knowledge

1223-04-20

2. Project statistics - Cost

• Base on 40€ per hour

• A bit lower the planned cost

Current Planned Cost  19600 €

Current Actual Cost 18920€

Planned Project Cost  19760 €

Forecasted Project Cost 21840€

3. Experiences

• Communication reduced

• Still some difficulties on the recording part

• Better interaction between members

• Good communication

• Really good motivation

• Easy to manage : everyone is autonomous

1323-04-20

4. Beta prototype : LiveTV