Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Distributed Energy Resources
and Microgrids for Resiliency-------------------------------------------------------------------------------------
Considerations for State Energy Officers on
Technology and Program Design
Chris Lotspeich
NASEO Conference
September 19th, 2017 1
• The Rhode Island Office of Energy Resources (OER) hired Celtic Energy Inc. (CEI) team to make program recommendations
• CEI team included Arup and Rocky Mountain Institute
• Report delivered March 2017, available at:
http://www.energy.ri.gov/reports-publications/past-projects/resilient-microgrids-for-critical-services.php
Rhode Island Microgrid Program Design
• USDOE Microgrid Exchange Group: “A microgrid is a group of interconnected loads and distributed energy resources within clearly defined electrical boundaries that acts as a single controllable entity with respect to the grid. A microgrid can connect and disconnect from the grid to enable it to operate in both grid-connected or island-mode.”
• NJ BPU report taxonomy (slightly modified):
Microgrid type DERs Facilities Meters Facility owners
Level 1 single facility 1–2+ 1 1 1
Level 2 campus 1–2+ 2+ 1–2+ 1
Level 3 multi-user
community
1–2+ 2+ 2+ 2+
Microgrid Definitions
Energy assurance planning factors
• What are your mission critical loads?
• How long do you want to operate off grid?
• What Distributed Energy Resources (DERs)?
– Efficiency, back up generators, PV, storage, CHP
• Assess feasibility, costs and benefits
• What procurement “business model”?
– Cash, bond, PPA, ESPC, ESA, C-PACE, …
Energy efficiency and passive design
Advantages:
• Universal, economical, uninterruptible
• Passive features enhance no-power functionality
• Load reduction reduces DER capacity requirements
Limitations:
• Easier in new design, but most facilities needs retrofits
• Business case less compelling with low energy costs
Aggressive passive
Donald Watson FAIA 2011. Used by permission.
Hancock County, MS Emergency Operations Center & community safe room
Passive ventilation strategies
SOURCE: Dean Sakamoto HURRIPLAN
Image Courtesy of Unabridged Architects
Donald Watson FAIA 2011.
Used by permission.
Image by Jeff Goldberg/Esto. From EDC magazine, 12/16/13.
320,000 SF, $80 million facility completed in 2013
• Designed to withstand 7.5 Richter scale seismic event
• Critical facility sustained operations during power outages
• 350 kW rooftop solar power array, solar thermal hot water
• 35 kW PV canopy is public device charging station
Image by Jeff Goldberg/Esto. From EDC magazine, 12/16/13.
Title
Photo: Russell Carr
Title
• TK
• TK
• TK
• TK
• TKPhoto: Russell Carr
Title
• TK
• TK
• TK
• TK
• TKPhoto: Russell Carr
Back Up Generators (BUGs)
Advantages:
• Vernacular tech, wide size range, mobile units
• Good load following, partial load efficiency
• Diesel, gasoline, propane, natural gas, dual fuel
Limitations:
• Standby depreciating asset
• Poor maintenance & testing = poor availability
• Onsite fuel storage, supply disruption risks
• High emissions
Solar photovoltaic (PV) power
Advantages:
• Clean, quiet power anywhere with no fuel cost
• Innovative financing, competitive business models
Limitations:
• Low energy density for facility-scale loads
• Requires energy storage for 24/7 applications
• Public sector can’t use tax credits
• PPA-funded arrays disconnect during grid outages
Energy storage
Advantages:
• Rapidly maturing technologies, mobile & stationary
• Can firm up intermittent renewables, support grid ops
• Rapid response, power- or energy-intensive discharge
• Wide capacity range, can be modular and scalable
Limitations:
• High costs falling rapidly, typically not yet economical
• Challenges of monetizing benefits and services
• Low energy density and capacity for facility-scale loads
• Limited useful life, degradation rates vary by application
• Variety of types and chemistries, siting challenges
FL SunSmart Schools E-Shelters program
Photo: Florida Solar Energy Center
FL SunSmart Schools E-Shelters program
• FL Energy Office, FL Solar Energy Center, DOE
– 2009 ARRA funds to expand shelter program
– Goals: save energy costs, shelter, educational tool
• 115 schools totaling ~1 MW PV
– Goals: save energy costs, shelter, educational tool
– Total shelter capacity of 10,000–50,000 people
• Teachers, school facilities staff training
FL SunSmart Schools E-Shelter program
• 10 kW PV, 48 kW / 25 kWh lead acid batteries
– 150 mph wind loading requirement
– $74,000–$90,000 installed, savings $1,500+/yr
• 1 kW critical loads defined by local committee
– American Red Cross, Emergency Management, school facility personnel and FSEC
• Lighting, plug loads for device charging
– Enhanced Hurricane Protected Area in each school
– Typically gyms, cafeterias, classrooms
Stafford Hill, Rutland, VT
Photo: Green Mountain Power
Stafford Hill, Rutland, VT• Green Mountain Power with Dynapower,
GroSolar, DOE, ESTAP, State of VT
• 1st 100% solar microgrid,1st on brownfield
– ES provides ancillary services to the grid
– Island mode energy support for HS shelter
• 2.5 MW PV panels, 4 MW ES
– 2 MW / 1 MWh Lithium ion
– 2 MW / 2.4 MWh lead acid batteries
• ~$10.8 million cost, ~ 10 year payback
Combined Heat and Power (CHP) Advantages:
• Onsite generation of electricity, heating and cooling
• Baseload energy output, relatively clean
• Economical with conducive conditions and loads
• Modular systems available
Limitations:
• Constant fuel supply: gas pipeline, site storage capacity
• Challenge: economical use for heat in critical facilities
• The smaller the CHP system, the longer the payback
• Business case less compelling with low electricity costs
FDA White Oak campus microgrid, MD
Multi-user community microgrids are coming…
Barriers to Microgrid Development• Organizational risk
– Many stakeholders with veto power, lack of specialized knowledge
• Technical risk– Complexity, challenge of safe operation, interoperability of proprietary equipment
• Economic risk– Potentially high first and operating costs, no standard cost/benefit analysis
method, challenge of business models for Level 3 multi-user microgrid
• Technical/economic risk– Highly case-specific feasibility, smaller scale constrains third-party development
• Administrative/economic risk– Public agency procurement constraints, interconnection approval, utility rate risk
• Legal risk– Potential challenge to utility franchise, distributing power across public Right Of
Way (ROW) or utility easement, selling power as a non-utility entity
• Regulatory risk– Rules might change, uncertain status of some microgrid types
Suggested Program Design Principles• Take an “All hazards” approach
• Multi-stakeholder program design
• Align with existing programs and goals
• Prioritize public benefits, protection of vulnerable populations
• Focus on support for state and local agencies
• Prioritize energy efficiency, renewable energy
• Deploy funds cost-effectively
• Leverage market forces & private investment
• Educate the marketplace with outreach, template documentation
• Balance simplicity with enough detail to foster successful projects
• Enable projects to have choice, foster flexibility & creativity
Program Design: Measure Types
• Administrative
– Measures that state agencies can implement without changes to current law or the regulatory environment
• Legislative
– Measures that legislatures can enact to support program development, typically focused and relatively limited
• Regulatory
– Changes to the regulatory regime regarding regulated entities (utilities) and other actors in the energy marketplace
Sample Administrative Measures
• Competitive solicitation with scoring for preferred aspects
• Detailed template RFP and feasibility analysis to guide design
• Define minimum performance requirements
• Provide funds and technical support for feasibility analysis
• Fund microgrid equipment: electric infrastructure, controls, storage
• Allow time for public procurement processes, rolling deadlines
• Design/construction schedule flexibility for marketplace learning
• Streamlined or preferential permitting and administrative processes
• Disburse funds at project milestones, and/or after commissioning
• Require microgrid performance data to be made public
Sample Legislative Measures
• Define microgrid types that are eligible for special measures, exemptions, and funding
• Expand DER support and incentives
• Allow public sector microgrids to distribute power across ROW
• Create Energy Improvement Districts or similar entities to facilitate microgrid development by municipalities and public agencies
• Enable Green Banks / PACE / Resilience Banks to support microgrids
Regulatory Measures and Caveats
• CAUTION: Consider big regulatory changes only as part of a comprehensive process, don’t revise regime for microgrids alone
• Exempt microgrids of defined type /size from (some) regulation
• Require utilities to provide information on cost/benefit impacts of microgrids on local Electric Power System (EPS)
• Enable microgrids to lock in utility rates for long term contracts
• Custom tariffs and/or on-bill financing for microgrid development, EPS benefit monetization and utility cost recovery
• BIG: Require/incent utilities to buy energy/services from microgrids?
• BIG: Require/incent utilities to develop microgrids?
• BIG: Enable third party competition with utilities to create microgrids?
Thank you for your time!For more information, please contact:
Chris Lotspeich, MBA, MES, CEMDirector of Sustainability Services
Celtic Energy Inc. 437 Naubuc Avenue, Suite 106
Glastonbury, CT 06033(860) 882-1515 x311
For a brief overview of CEI, see:
CEI Overview - 2 minute video31