214
BWR TRANSIENT ANALYSIS MODEL WPPSS-FTS-129, Rev. 01 September 1990 Principal Engineers Y. Y. YUNG S. H. BIAN D. E. BUSH Contributing Engineer B. M. Moore Approved: Date: R. O. Vosbur h Manager, Saf y '& Reliability Analysis Date: D. L. Larkin Manager, Engineering Analysis & Nuclear Fuel

DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

BWR TRANSIENT ANALYSIS MODEL

WPPSS-FTS-129, Rev. 01

September 1990

Principal Engineers

Y. Y. YUNGS. H. BIAND. E. BUSH

Contributing Engineer

B. M. Moore

Approved: Date:R. O. Vosbur hManager, Saf y '& Reliability Analysis

Date:D. L. LarkinManager, Engineering Analysis & Nuclear Fuel

Page 2: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

I

I~

~

~

Page 3: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

DISCLAIMER

This report was prepared by the Washington Public Power Supply

System ("Supply System" ) for submittal to the Nuclear Regulatory

Commission, NRC. The information contained herein is accurate tothe best of the Supply System's knowledge. The use of information

contained in this document by anyone other than the Supply

System, or the NRC is not authorized and with respect to any

unauthorized use, neither the Supply System nor its officers,directors, agents,

responsibility, or

or employees assume any obligation,0

liability or makes any warranty or

representation concerning the contents of this document or itsaccuracy or completeness.

Page 4: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

t

5~ 4

I

4

; 'tv

Page 5: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

ACKNOWLEDGEMENTS

The Supply System acknowledges the consulting reviews and

recommendations provided by Energy Incorporated and Yankee Atomic

Electric Company during the course of development of this model.

The Supply System also acknowledges the efforts of Mr. J. C.

Chandler, Consultant, and Mr. Z. . T. Cronin, Yankee Atomic

Electric Company for their reviews and comments on this report.The technical discussions with Philadelphia Electric Company and

Pennsylvania 'Power & Light Company regarding the Peach Bottom0

benchmarks is greatly appreciated.

Page 6: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

~ ~ 1

0

'

'*

I

l

II

Page 7: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

ABSTRACT

System-wide models, based on the WNP-2 plant-specific design and

utilizing the RETRAN-02 computer code, are described. Both best-

estimate and conservative models are included. The models are

applicable to a wide range of transients and will.initially be

used for, but not limited to, analysis of the limitingpressurization transients considered for reload core licensing.The best-estimate model is qualified by comparisons to a range ofpower ascension test transients and to the Peach Bottom Unit 2

Turbine Trip Tests. A representative application of the model forlicensing basis calculations of the limiting pressurizationtransients (based on WNP-2 end of cycle 4 conditions) is also

presented.

The benchmark comparisons show good agreement between calculated

and measured data, thereby demonstrating the Supply System's

capability to perform transient analyses for licensingapplications.

Page 8: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

l

~

l

I

Page 9: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE OF CONTENTS

Pacae

1.0 INTRODUCTION . . . . . . . . . . . . . . . . . . . . 1-1

2.0 MODEL DESCRIPTION 2-1

2.1 Model Geometry

2.1.1 Control Volumes, JunctionsConductors

and Heat

2-6

2-6

2.1.2 Vessel Internals2.1.3 Core Region

2.1.4 Recirculation Loops

2.1.5 Steam and Feedwater Lines

2.2 Component Models

2.2.1 Jet Pumps

2.2.2 Recirculation Pumps

2.2.3 Steam Separators

2,.2.4 Safety/Relief Valves

2.2.5 Core Hydraulics

2.3 Trip Logic

2.4 Control System Models

2.4.1 Feedwater Control System

2.4.2 Pressure Control System

2.4.3 Recirculation Flow Control System

2.4.4 Direct Bypass Heating

2.5 Steady-state Initialization

2-7

2'-8

2-9

2-10

2-16

2-16

2-17

2-17

2-18

2-19

2-21

2-23

2-23

2-24

2-25

2-25

2-35

Page 10: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE OF CONTENTS (Continued)

2.6 RETRAN KineticsPacae

2-35

2.6.1

2.6.2

2.6.3

2.6 '

General Description of the Generationof One-dimensional Data

Calculation of the Initial KineticInput Data

Adjustment of Kinetics Data

Verification of the Supply System'sMethodology

2-36

2-38

2-40

2-41

3.0 QUALIFICATION 3-1

3.1 WNP-2 Power Ascension Tests . .'.* . . . . . . . 3-1

3 ~ 1 ~ 1 Water Level Setpoint Change(Test PAT 23A) 3-4

3.1.1.1 RETRAN Model for Test PAT 23A . 3-4

3.1.1.2 Results and Discussions . . . . 3-4

3 ' ' Pressure Regulator Setpoint Change(Test PAT 22) 3-9

3.1.2.1 RETRAN Model for Test PAT 22 . 3-9

3.1.2.2 Results And Discussions . . . . 3-9

3 ' 3 One Recirculation Pump Trip(Test PAT 30A) 3-15

3.1.3.1 RETRAN Model for Test PAT 30A . 3-15

3.1.3.2 Results And Discussions . . . . 3-16

3.1.4 Generator Load Rejection with Bypass(Test PAT 27) 3-30

3.1.4.1 RETRAN Model for Test PAT 27 . 3-30

3.1.4.2 Results and Discussions . . . . 3-31

Page 11: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE OF CONTENTS (Continued)

3.2 Peach Bottom Turbine Trip Tests

Pacae

3-40

3.2.1 Test Description . . . . . . . . . . . . 3-40

3.2.2 Peach Bottom Unit 2 Model Description . 3-42

3.2.3 Initial Conditions and Model Inputs . . 3-44

3.2.4 Comparison with Measurements . . . . . . 3-47

3.2.4.1 Pressure Comparisons 3-47

3.2.4.2 Power and Reactivity Comparisons 3-62

4.0 LICENSING BASIS ANALYSIS

4.1 Licensing Basis Model

4.2 Load Rejection Without Bypass (LRNB)

4.2.1 Sequence of Events

4.2.2 Results of LRNB RETRAN Analysis

4.3 Feedwater Controller Failure to Maximum( FWCF ) ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

4.3.1 Sequence of Events

4.3.2 Results of FWCF RETRAN Analysis

4.4 Summary of Transient Analysis

Demand

4-1

4-2

4-8

4-8

4-10

4-27

4-27

4-28

4-53

5.0 SUMMARY AND CONCLUSIONS . . . . . ~ . ~ . . . . . . 5-1

6.0 REFERENCES . . . . . . . . . . . . ~ ~ ~ . . . . . . 6-1

Page 12: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

LIST OF FIGURES

Ficiure

2.1

2.2

2.3

2.4

2 2 1

2.4.1

2;4.2

2.4.3

2.6.1

2. 6.2

2.6.3

Supply System Reload Transient Analysis MethodsComputer Flow Chart

WNP-2 RETRAN Model (Vessel)

WNP-2 RETRAN Model (Active Core Region)

WNP-2 RETRAN Model (Recirculation Loops)

WNP-2 RETRAN Model (Steam Line)

Jet Pump Performance Curve

Feedwater Control System

Pressure Control System

Direct Bypass Heating .

Initial Axial Power DistributionPeach Bottom Unit 2 TT1

Initial Axial Power DistributionPeach Bottom Unit 2 TT2

Initial Axial Power DistributionPeach Bottom Unit 2 TZ3

Pacae

1-5

2-2

2-3

2-4

2-5

2-20

2-27

2-31

2-34

2-43

2-44

2-45

3.F 1

3.1;2

3.1.3

3.1.4

3.1.5

3.1.6

3 1 7

3. 1.8

3. 1.9

3. 1. 10

Feedwater Flow — PAT Test 023

Water Level — PAT Test 023

Dome Pressure - PAT Test 022

Normalized Power — PAT Test 022

Steam Flow — PAT Test 022

Feedwater Flow — PAT Test 022

Recirc Flow Pump A — PAT Test 030A

Recirc Flow Pump B — PAT Test. 030A

Recirc Flow Pump A — PAT Test 030A

Recirc Flow Pump B — PAT Test 030A

1D

1D

3-7

3-8

3-11

3-12

3-13

3-14

3-18

3-19

3-20

3-21

iv

Page 13: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Ficiure

3.1.11

3 ' '23. 1. 13

3. 1. 14

3. 1. 15

3.1.16

3.1.17

3.-1.18

3.1.19

3.1.20

3.1.21

3 '.223.1.23

3.1.24

3 ~ 2

3 2 ~ 1

3.2.2

3.2.3

3.2.4

3.2 '

3.2.6

3.2.7

3.2.8

LIST OF FIGURES (Continued)

Jet Pump A Flow — PAT Test 030A

Zet Pump B Flow — PAT Test 030A

Zet Pump A Flow — PAT Test 030A — 1D

Zet Pump B Flow — PAT Test 030A — 1D

Power — PAT Test 030A

Power — PAT Test 030A — 1D RETRAN

Core Heat Flux — PAT Test 030A'oreHeat Flux — PAT Test 030A

Power — PAT Test 027

RRC Flow A - PAT Test 027

RRC Flow B — .PAT Test 027,.

Total Core Flow — PAT Test 027

Dome Pressure — PAT Test 027

Steam Flow — PAT Test 027

PB2 RETRAN Model

PB TT1 Turbine Inlet Pressure

PB TT2 Turbine Inlet Pressure

PB TT3 Turbine Inlet Pressure

PB TT1 Steam Dome Pressure

PB TT2 Steam Dome Pressure

PB TT3 Steam Dome Pressure

PB TT1 Upper Plenum Pressure

PB TT2 Upper Plenum Pressure

1D

~ ~

Pacae

3-22

3-23

3-24

3-25

3-26

3-27

3-28

3-29

3-34

3-35

3-36

3-37

3-38

3-39

3.-43

3-50

3-51

3-52

3-53

3-54

3-55

3-56

3-57

Page 14: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

LIST OF FIGURES (Continued)

Ficiure

3.2.9

3.2.10

PB TT3 Upper Plenum Pressure

PB TTl Upper Plenum Pressure

3 ~ 2. 12

3 ~ 2. 13

3.2. 14

3.2.15

3.2.16

3.2.17

3.2.18

3.2.19

3.2.20

3 ' '13 ' '23 ' '33.2.24

3.2.25

3 '.263.2 27

3.2.28

3.2.29

3 '.304.2.1

PB TT3 Upper Plenum Pressure

PB TT1 Core Average Power

PB TT2 Core Average Power

PB TT3 Core Average Power

PB TTl Level A Average LPRM

PB TTl Level B Average 'LPRM ;

PB TTl Level C Average LPRM

PB TT1 Level D Average LPRM

PB TT2 Level A Average LPRM

PB TT2 Level B Average LPRM

PB TT2 Level C Average LPRM

PB TT2 Level D Average LPRM .

PB TT3 Lhvel A Average LPRM .

PB TT3 Level B Average LPRM .

PB TT3 Level C Average LPRM .

PB TT3 Level D Average LPRM

PB TT1 ReactivityPB TT2 Reactivity .

PB TT3 ReactivityWNP-2 LRNB LBM — Steamline Pressure

3.2.11 PB TT2 Upper Plenum Pressure

Pacae

3-58

3-59

3-60

3-61

3-67

3-68

3-69

3-70

3-71

3-72

3-73

3-74

3-75

3-76

3-77

3-78

3-79

3-80

3-81

3-82

3-83

3-84

4-13

Vi

Page 15: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

LIST OF FIGURES (Continued)

Ficiure

4.2.2

4.2.3

4.2.4

4.2.5

4.2.6

4.2.7

4.2 '

4 ' '

4.2.10

4.2.11

4.2.12

4.2.13

4.2.14

4 ~ 3 ~ 1

4.3.2

4.3.3

4.3.4

4 '.54.3.6

4 ' '

4.3 '

4 '.94.3.10

WNP-2 LRNB LBM — Vessel Steam Flow

WNP-2 LRNB LBM — Dome PressureA

WNP-2 LRNB LBM — Pressure (Mid-Core)

WNP-2 LRNB LBM — Pressure (Core Exit)WNP-2 LRNB LBM — Total Reactivity .

WNP-2 LRNB LBM — Core Power

WNP-2 LRNB LBM — Core Average Heat Flux

WNP-2 LRNB LBM — Liquid Level

WNP-2 LRNB LBM — Feedwater Flow

WNP-2 LRNB LBM — Void Fraction (Mid-Core)

WNP-2 LRNB LBM — Void Fraction (Core Exit)WNP-2 LRNB LBM — Recirculation Flow

WNP-2 LRNB LBM — Core Inlet Flow

WNP-2 FWCF LBM — Feedwater Flow .

WNP-2 FWCF LBM — Core Inlet Subcooling

WNP-2 FWCF LBM — Liquid Level

WNP-2 FWCF LBM — Turbine Steam Flow .

WNP-2 FWCF LBM — Turbine Bypass Flow

WNP-2 FWCF LBM — Dome Pressure

WNP-2 FWCF LBM — Total ReactivityWNP-2 FWCF LBM — Core Power

WNP-2 FWCF LBM — Core Average Heat Flux

WNP-2 FWCF LBM - Group 1 SRV Flow

Pacae

4-14

4-15

4-16

4-17

4-18

4-19

4-20

4-21

4-22

4-23

4-24

4-25

4-26

4-31

4-32

4-33

4-34

4-35

4-36

4-37

4-38

4-39

4-40

vii

Page 16: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

LIST OF FIGURES (Continued)I

Ficiure

4.3.11

4.3.12

4.3.13

4.3.14

4.3.15

4.3.16

4.3.17

4.3.18

4.3.19

4.3.20

4.3.21

4.3.22

WNP-2 FWCF LBM

WNP-2 FWCF LBM

WNP-2 FWCF LBM

WNP-2 FWCF LBM

Group 2 SRV Flow

Group 3 SRV Flow .

Group 4 SRV Flow

Group 5 SRV Flow

WNP-2 FWCF LBM

WNP-2 FWCF LBM

WNP-2 FWCF LBM

WNP-2 FWCF LBM

WNP-2 FWCF LBM

WNP-2 FWCF LBM

WNP-2 FWCF LBM

Core Inlet Flow

Core Exit Flow

Recirculation Flow

Pressure (Mid-Core)

Pressure (Core Exit)Void Fraction (Mid-Core)

Void Fraction (Core Exit)

WNP-2 FWCF LBM — Vessel Steam Flow

~ ~

Pacae

4-41

4-42

4-43

4-44

4-45

4-46

4-47

4-48

4-49

4-50

4-51

4-52

Page 17: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

LIST 'OF TABLES

Table

2.1.1

2 ~ 1 ~ 2

2 ~ 1 ~ 3

2.3.1

2.4.1

3 ~ 2 ~ 1

Description of Trip Logic

Control Input DefinitionPeach Bottom Turbine Trip TestsTest Conditions

2-22

2-26

3-41

Pacae

Volume Geometric Data . . . . . . . . . . . . . 2-12

Junction Geometric Data . . . . . . . . . . . . 2-13

Heat Conductor Geometric Data . . . . . . . . . 2-15

3 ' ' Peach Bottom Turbine Trip TestsInitial Conditions 3-46

3.2 ' Peach Bottom Turbine Trip TestsPressure change (Psi) at Peak of FirstOscillation 3-49

3.2.4

3.2.5

Peach Bottom Turbine Trip TestsSummary of Core Average Peak Neutron Power ..Peach Bottom Turbine Trip TestsTime (Sec) of Peak Neutron Power

3-64

3-64

3.2.6 Peach Bottom Turbine Trip TestsSummary of LPRM Level Neutron Power Peaks 3-65

3 '.74.1

4.2

Peach Bottom Turbine Trip TestsReactivity Summary

Input Parameters and Initial TransientConditions, Comparison of Licensing Basisand Nominal plant Conditions

Technical Specification LimitsMaximum Control Rod Insertion Time to

Position'fter

Deenergization of Pilot Valve Solenoids

3-66

4-3

4-6

4.3 Sequence of Events for LRNB Transient 4-9

4 '

4.5

Sequence of Events for Feedwater ControllerFailure t ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

Summary of Pre'ssurization Transient Results

4-30

4-53

ix

Page 18: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

l'

g ~

l

I

Page 19: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

1.0 INTRODUCTION

This report describes and presents qualification results of a

transient analysis model for WNP-2. WNP-2 is a boiling water

reactor using a BWR/5 Nuclear Steam Supply System (NSSS) provided

by General Electric (GE) and operated by the Washington Public

Power Supply System (The Supply System). The transient, analysis

model, developed by the Supply System, uses the RETRAN-02 MOD04

("RETRAN-02" or "RETRAN") computer code . As demonstrated inthis topical report, the transient analysis model shows good

agreement to operational transients using plant data and with

proper input assumptions gives limiting or conservative resultsapplicable to core reload or licensing analyses.

RETRAN-02 is a versatile time dependent computer code developed

by the Electric Power Research Institute (EPRI) to model complex

thermal-hydraulic systems. It is capable of providing realisticresponses to system upset conditions. A user inputs a system

model consisting of control volumes, heat slabs, and a flow path

network; for nuclear reactor systems a kinetics model utilizingeither point or one-dimensional kinetics is available.

The RETRAN-02 computer code was developed by utility sponsorship

through EPRI. The computer code qualification studies were based

on code predictions of various separate effects tests, system

effects experiments, and power reactor startup tests which can be

1-1

Page 20: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

found in the RETRAN-02 documentation. The NRC Staff's 'Safety

Evaluation Report (SER) for RETRAN-02 has been issued. The NRC

found "... RETRAN-02 is an acceptable computer program for use inlicensing applications for calculating the transients described

in Chapter 15 ... and other transients and events as appropriate

and necessary for nuclear power plant operation.". The RETRAN-02

limitations discussed in the SER and applicable to reload

licensing analysis will be addressed in the Supply System

Applications Topical Report (to be submitted later).

The Supply System has developed the input for the model presented

in this report, representing the WNP-2 plant, from as-builtdrawings and vendor specifications. The nodalization network was

developed over many years by trial and error, comparison tosimilar plant models, and finally through comparison of model

predictions to actual WNP-2 data. This report provides

qualification of the WNP-2 RETRAN model and of the Supply

System's ability to analyze WNP-2 transient behavior through the

application of RETRAN-02 to the analysis of

1. WNP-2 Power Ascension Tests;

2. Peach Bottom 2 Cycle 2 Turbine Trip Tests; and

3. WNP-2 Licensing Basis Analysis.

The Supply System's reload transient analysis methods are based

on the EPRX code package as depicted in Figure 1.1. The steady

1-2

Page 21: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

state core physics. codes and models used to provide input to the

transient analysis models are described and qualifiedelsewhere . The SIMTRAN-E MOD3A ("SIMTRAN-E") code collapses

the three-dimensional neutronics data generated by the steady

state core physics codes to the one-dimensional neutronics inputrequired by RETRAN-02 and calculates the moderator density and

fuel temperature dependencies. The one-dimensional kineticsparameter dependencies generated by SIMTRAN-E are modified as

described in Section 2.6 to account for differences between the

RETRAN-02 one-dimensional and SIMULATE-E three-dimensional

moderator 'density calculations. RETRAN-02 is used to model the

NSSS and the VIPRE-01 MOD02 ("VIPRE-01") code is used to model

a single fuel assembly for thermal margin evaluations. Thermal

margin evaluation for WNP-2 is described and qualified in a

separate Applications Topical Report (to be submitted later).

The base WNP-2 RETRAN-02 model is described in Chapter 2. It isdesigned to serve as a best-estimate, time dependent (transient),systems analysis tool. Intended uses of the best-estimate model

include simulator qualification, evaluating operationaltransients, and evaluating proposed system design changes. InChapter 3, the WNP-2 RETRAN-02 model is qualified by comparison

of best-estimate data predictions with plant data collectedduring startup testing. To analyze limiting transients for core

reload design in support of technical specification action, a

Licensing Basis Model is developed by modifying the best estimate

1-3

Page 22: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

model with conservative assumptions. The Licensing Basis Model

is described in Chapter 4, which also contains example

calculations with the conservative model. The Applications

Topical Report that will be published later will provide

additional detail on a) the process and interface between the

EPRZ codes for licensing analyses, b) the Licensing Basis Model

input sensitivity and uncertainity analyses, and c) the hotchannel thermal margin methodology. Chapter 5 contains the

Summary and Conclusions and Chapter 6 the References.(

1-4

Page 23: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FlGURE 1.1

Supply System Reload Transient Analysis MethodsComputer Code Flow Chart

CORE PHYSICSANALYSIS

SIMTRAN-E

3-0 to IN Link

MODIFICATIONOFCROSS SECTIONDEPENDENCIES

RETRAN-02

NSSS Model

VIPRE-01

Mot Bundle Model

1-5

Page 24: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

I

I

L

i

Il

I

Page 25: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

2.0 MODEL DESCRIPTION

This chapter describes the WNP-2 RETRAN-02 Best Estimate Model

developed to analyze a wide range of transients. The Supply

System has been involved with the RETRAN development effort since

1979 and the WNP-2 model has evolved over time with our code

development involvement. In addition, the Supply System has had

two separate and independent reviews performed on the WNP-2

model, by Energy Incorporated (now a Division of NUS Corp) and by

Yankee Atomic. These reviews have provided valuable insightsinto the model and options used and are documented as part of the

model development file.

The best estimate model description is given in the followingsections. Figures 2.1 through 2.4 depict the nodalization scheme

utilized for the WNP-2 model, whereas Section 2.1 provides

additional detail on the Model Geometry, Section 2.2 discusses

models of special components such as the jet pumps and the safetyrelief valves, and the trip logic and control systems models are

described in Sections 2.3 and 2.4, respectively. The steady-

state initialization is discussed in Section 2.5. The WNP-2

model uses twelve active core nodes as is shown in Figure 2.2 and

the interface/input between the RETRAN WNP-2 model and the

reactor physics input to the kinetics model is given in Section

2.6.

2-1

Page 26: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 2.1

WNP-2 RETRAN HODEL (Vessel)

Q5

318

28 ga

Qs

pi~

Qs

287

Q9

21

12

(y

18

22 2H

Qi0"

281 288

03

2-2

Page 27: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 2 '

WNP-2 RETRAN MODEL (Active Core Region)

CORE OUTLET

62 Qii

61 0Qsi

Is

9

59

58

Qss

Qss

Qs

Qs

Junction No. 8

7

58

Q92

Qs

Heutronlc Region Na 8 55 Qss

5

53

Qss

Qs~

liia,

02 51 0

CORE INLETQi

2-3

Page 28: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

s s IS a ~ 00 ~

~i ~

~i !

O

fi ~

~ ~W

Page 29: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

To Turbine WNP-2 RETRAN MODEL (Steam Line)

398

Stop388 Valve

Q378

Metwell

SafetyReliefValves

381

382

383

38'1

385

Q3ie

328

O326

ReactorVessel

0363

338

368358

361

358

Inboar dMSIV

BypassLine

Page 30: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

2. 1 Model 'Geometry

The physical geometry and volume of the WNP-2 nuclear steam

supply system is modeled as series of control volumes and

junctions. The following sections discuss this physicalarrangement and how it is modeled in the WNP-2 RETRAN model.

2.1.1 Control volumes, Junctions, and Heat Conductors

The control volume nodes are defined as distinct regions withinthe primary system, such as the steam dome or downcomer,'s

shown in Figures 2.1 through 2.4. The physical dimensions of the

volumes, junction areas, lengths, etc. were obtained from WNP-2

plant specific as-built drawings. The nodalization scheme used

has been developed over several years and is based on code

limitations, solution stability, economical run-times, and, most

importantly, agreement to experimental or test data.

In Figures 2.1 through 2.4, the nodal volumes are denoted by

numbers in small circles. The pertinent data associated witheach of these volumes is given in Table 2.1.1. The mass/energy

transfer between volumes is through junctions, depicted inFigures 2.1 through 2.4 as numbered arrows. The junction inputdata is given in Table 2.1.2. In Figure 2.2, the heat conduction

in the active core region is shown as small squares numbered 1

2-6

Page 31: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

through 12 for each active core volume. The pertinent data foreach heat conductor is given in Table 2.1.3.

Additional discussion of the salient nodalization by region isgiven in, Subsections 2.1.2 through 2.1.5 below. Features of WNP-2

that are represented by special control volumes, e.g.,safety/relief valves, are discussed in Section 2.2.

2.1.2 Vessel Internals (Refer to Figure 2.1)

Volumes 18, 19, and 20 constitute the middle, lower, and upper

downcomer regions, respectively, of the reactor vessel. The

middle downcomer region, Vol. 18, is the volume in which the

feedwater and the saturated liquid and steam carryunder from the

steam separators are mixed. The upper downcomer region, Vol. 20,

models the liquid/steam interface region and utilizes the RETRAN

"non-equilibrium" option. This option is used in this volume toaccurately account 'or the superheating of steam during

pressurization transients (the pressurization/de-pressurizationeffects are governed by this interface region).

As shown in Figure 2.1, the steam dome, Vol. 16, and the fluidregion below the core support plate (lower plenum), Vol. 3, are

single large volumes. The jet pump volumes, Vol. 1 and 2, are

discussed further in Section 2.2.4.

2-7

Page 32: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

The upper plenum region above the upper guide plate, Vol. 13, and

the standpipes, Vol. 14, are both modeled as single volumes. A

single volume, Vol. 15, is used to model the internal region ofthe 225 steam separators. From the steam separator internalregion, the major steam flow is to the steam dome, Vol. 16,

whereas the steam carryunder flows to and mixes in the middle

downcomer, Vol. 18, as mentioned above.

2.1.3 Core Region (Refer to Figure 2.2).

The WNP-2 core region is considered to be the twelve controlvolumes used to model the active region of the core (Vols. 51

through 62), the single volumes for the unheated core inlet and

outlet regions (Vols. 4 and 11), and the core bypass singlevolume region. (The core bypass volume is shown on Figure 2.1 as

Vol. 12) .

There are two means of energy deposition modeled in the core

region. In the active core volumes, twelve heat conductors are

used to represent the reactor fuel. The geometric data for the

heat conductors is presented in Table 2.1.3. In addition, 'a

direct moderator heating model is included to account for directenergy deposition into the active core volumes due to'amma and

neutron heating. For the core bypass volume, a constant fractionof the core thermal power is directly deposited via a RETRAN non-

conducting heat exchanger model.

2-8

Page 33: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

As shown in Figure 2.2, the one-dimensional kinetics calculations

are supported by twenty-seven neutronic regions, i.e., twenty-

five in the active core volumes and one per reflector volume.

Thermal-hydraulic feedback of each active core and reflectorvolume is provided to the associated neutronic regions. This

feedback of the calculated water density of each active core and

reflector volume and the attendant corrections are discussed

further in Section 2.6 of this report.

The fuel temperature feedback for each'egion is provided by the

heat conductor models in each active core volume. The average

fuel rod is xepresented by three cylindrical regions — fuel, gap,

and cladding. The cladding is modeled with four nodes, the gap

one node, and the fuel region is modeled with six nodes. The

material conductivity and heat capacity for the U02 fuel and the

Zircaloy cladding are taken from MATPRO and WREM data. For

purposes of the model benchmarking, the gap conductance of the

average core region is assumed to be a constant value

2.1.4 Recirculation Loops (Refer to Figure 2.3)

The two recirculation loops are modeled separately. In each

recirculation loop, five control volumes are used to represent

the recirculation pump and loop piping. In each loop, a singlevolume is used to model ten jet pumps driven by the recirculation

2-9

Page 34: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

loop. A special two-stream momentum mixing option is used by

RETRAN to describe the interaction of the recirculation loop

drive flow with the suction flow from the downcomer. Additionaldetail of the jet pump and the recirculation pump modeling isprovided in Section 2.2.

2.1.5 Steam and Feedwater Lines (Refer to Figure 2.4)

The four main steam lines are lumped into one composite line,which is divided into seven control volumes (see Figure 2.4).From the reactor vessel there are three volumes modeling the

steam lines to the Main Steam Isolation Valves (MSIVs), Vols.

310, 320, and 330. The middle of these volumes (Vol. 320) isconnected to the junctions representing the safety/relief valves.

Due to their redundancy, the MSIVs are modeled as a single valve.

The steam lines from the MSIVs to the turbine stop valves are

also modeled in three volumes, Vols. 340, 350, and 360. The

middle of these volumes, Vol. 350, provides a line model for the

turbine bypass, whereas the third volume, Vol. 360 provides the

pressure feedback signal to the Pressure Control System. The

steam line volume between the turbine stop valve and the turbinecontrol valves is modeled as Vol. 390.

The flows from steam line to the turbine (through Zct. 390) and,

subsequently, to the condenser (through Zct. 361) are modeled as

2-10

Page 35: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

negative fill junctions with flow rates controlled by the

Pressure Control System (see Section 2.4.2).

The feedwater lines are modeled as a positive fill junction with

flow rate controlled by the Feedwater Control System. For

simulation of very fast transients, the feedwater is constant and

explicit modeling of the lines and pumps is not necessary.

2-11

Page 36: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 2.1.1

VOLUME GEOMETRIC DATA

FIOW HYDRAULIC

AREA DIAMEKRFT2 (FF

ELEV.

(FF)

123

41112131415

161819

2051"

5253

545556575859606162

201202204205206

207208210211212310320330340350360370390

136.942136.942

2240.00066.640

111.280950.708

. 943,000400.000442.834

6285.3002196.7002498.7001901.700

83.95583.95583.95583.95583.95583.95583.95583.95583.95583.95583.955

125.933148.00030.500

115.00043.50091.710

148.00030.500

115.00043.50091.710

446.430275.370555.400504.280

2747.1601654.540

2.56E+586.750

16.51716.51717.2810.7451.198

14.4433,816

- 8.9186.167

18.54410.22124.1777.8121.0001.0001.0001.0001.0001.0001.0001.0001.0001.0001.0001.500

34.6823.375

21.9791.193

20.11634.6823.375

21.9791.193

20.11633.5092.200

39.0907.1466.861

25.88242.610

2.350

16.51716.51721.4500.7451.198

14.4433.8168.9187.092

21.1008.5319.9607.8121.0001.0001.0001.0001.0001.0001.0001.0001.0001.0001.0001.500

58.36012.02745.3479.727

25.98058.36012.02745.3479.727

25.98037.49023.12546.64142.348

170.589102,74142.61010.001

19.89719.897

114.28089.47483.95565.825

247,12044.85371.807

270.000257.496103.350149.62183.95583.95583.95583.95583.95583.95583.95583.95583.95583.95583.95583.9552.5362.5362.5362.2363.5302.5362.5362.5362.2363.530

11.90811.90811.90811.90816.10416.104

4520.0008.674

1.5921.5920.7810.0450.0450.182

17.7380.5050.641

20.7682.2562.1620.7320.0450.0450.0450.0450.0450.0450.0450.0450.0450.0450.0450.0451.7971.7971.7971.1930.9481.7971.7971.7971.1930.9481.9471.9471.9471.9472.2642.264

75.8622.350

9.9179.9170.000

17.28130.52617.28131.72435.54044.45850.61534.30210.12542.82318.02619.02620.02621.02622.02623.02624.02625.02626.02627.02628.02629.026

-19.409-16.510-15.492

6.4877.680

-19.409-16.510-15.492

6.4877.680

21.46421.206

-15.930-21.792-28.650-40.903

21.460-16.196

JEF PUMP

JEP PUMP

IlNER PIZKi'1(DRE INLET(DRE EKITONE BYPASS

UPPER PLBRMSTANDPIPE

SEPARATOR

MID DOWNCOMER

IQWER DOWNCOtKR

UPPER DOWNKMER

(DRE 51KORE 52KjRE 53

(DRE 54CORE 55(DRE 56GSE 57CORE 58CORE 59GNE 510(DRE 511GNE 512RRC 51 SUCFION

RRC 51 PUMP

RRC 51 HEADER INLETRRC 51 HEADER

RRC 51 RISER

RRC 52 SUCFION

RRC 02 PUMP

RRC 52 HEADER INIETRRC 52 HEADER

RRC 52 RISER

SKAM QlflZFSTEAM LINESKAM LINE

STEAM LINESKAM LINE(QVI3INMEÃFSTEAM LINE

2-12

Page 37: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 2.1.2

JUNCTION GEOMETRIC DATA

KtmECIS FUNJCl'. VOUJME AREA

NO. FROM 'Io FF2

I

ELEV.

FT

HYDRAULIC

L0SS DIAtEFERKEF. FF

I23

410111213

141516171819

2021

2223

515253

5455

56

575859

6061

201

202204205206207208209

211212213214310320

I 3

2 33 44 51

62 1111 1312 1313 1414 1515 16

19.897019.897022.668054.139063.046483.955055.992045.140033.796030.6800

15 1851 5252 5353 5454 5555 5656 57

57 5858 5959 6060 6161 6219 201

201 202202 204204 205205 206206 I

19 207207 208208 210210 211211 212212 216 310

310 320

51.825083.955083.955083.955083.955083.955083.955083.955083.955083.955083.955083.95502.53602.53601.79242.53603.53000.46092.53602.53601.79242.53603.53000.4609

11.908011.9080

20 16 239.320020 18 149.621018 19 85.1340

4 12 1.50003 12 0.8420

19 I 1.773019 2 1.7730

9.91709.9170

17.281318.026130.526131.724031.724035.540044.458050.625050.625042.833034.302017.281317.281326.434026.434044.503019.026120.026121.026122.026123.026124.026125.026126.026127.026128.026129.026114.3750

-16.5100-15.4920

6.48707.6800

26.434014.3750

-16.5100-15 '920

6.48707.6800

26.434054.000022.4300

0.50890.50890.09800.01010.0161 .

0.01490.11740.10710.43900.08850.06520.04270.06480.11390.20364.73304.73300.06590.01190.01190.01190.01190.01190.01190.01190.01190.01190.01190.0149

11.554413.877511.311911.11575.85503.8530

11.554413.877511.311911.11575.85503.85301.61322.5451

1.83001.8300

-1.00003.26900.41170.73000.68000.4100

-1.0000-1.0000

0.18000.2700

-1.00006.98510.05420.05424.01000.00001.24001.24000.00001,24000.00001.24001.24000.00001.24001.24000.24500.6300

-1.00000.54601.28600.21220.24500.6300

-1.00000.54601.28600.21220.27210.3391

1.59201.59200.19600.02700.03190.04460.30220.50540.15690.41670.05180.73202.75000.00280.00190.21000.21000.08950,04460.04460.04460.04460.04460.04460.04460.04460.04460.04460.04461.79691.79691.79691.79690.94800.10831.79691.79691.79691.79690.94800.10831.94701.9470

JEF PUMP ¹I DIKHJEF PUMP ¹2 DISCH

GNE MZFGNE ¹I MZFKRE ¹12 EXITGNE OmfZFBYPASS OUI1ZFSFANDPIPE MZFSEPARATOR INLEFSEPARA'IOR QJFLZFIlNER DOME MZFMID DOWNGNER 'INLET

IVER DOWNKMER INLEFKRE BYPASS MZF ¹2KRE BYPASS INLEF ¹1JEF PUMP ¹I SUCFION

JEF PUMP ¹2 SUCFION

SEP. m MID IXMKMERKRE ¹I EXITGNE ¹2 EXITGNE ¹3 EXITKRE ¹4 EXITKRE ¹5 EXITKRE ¹6 EXITGNE ¹7 EXITGNE ¹8 EXITGNE ¹9 EGTKRE ¹10 EXITGNE ¹11 EXITRRC LOOP ¹IRRC LOOP ¹1RRC LOOP ¹IRRC UDP ¹IRRC IQOP ¹IRRC 10OP ¹IRRC lOOP ¹2RRC LOOP ¹2RRC KOP ¹2RRC lOOP ¹2RRC LOOP ¹2RRC rmP ¹2SKAM UNESFEAM LINE

2-13

Page 38: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 2.1.2 (CONT.)

JUNCTION GEOMETRIC DATA

65NECFS FIOW

JCF. VOIHME AREA

NO. FRCN m FF2

HYDRAULIC

EIZV. INDIA IOSS DIAMEKRFF 1 FF COEF. FF DESCRIPFICN

330 320 330 3.6370340 330 340 4.1250350 340 350 . 16.1040360 350 360 16.1040380 360 390 14.1860381 320 370 0.2238382 320 370 0.44773&3 320 370 0.4477384 320 370 0,4477385 320 370 0.4477602 0 13 1.0000601 0 16 1.0000490 0 18 5.0000390 0 390 1.0000

. 361 0 350 1.0000

22.1800-15.1300-21.7920-27.5200-15.0210

21.460021.460021.460021.460021.460031.724069.158041.1000

-16.1960-28.6500

2.92943.73657.07468.48643.76640.97570.97570.97570.97570.97570.00770.03910.01660.57655.2965

0.18520.15410.42031.17802.57620.26300.26300.26300.26300.26300.00000.00000.0000

-1.0000-1.0000

1.07601.14601.94702.26402.12500.37750.37750.37750.37750.37751.12841.12840.13331.12801.3440

SKAM UNESKAM LXNE

SKAM LINESKAM IZKSKAM ICESRV INIEFSRV INIZPSRV INLEFSRV INLEFSRV INLEFHPCS

RCIC LINEFEEDWATER LINE'IURBINE NHG FILLSKAM BYP KEG FILL

2-14

Page 39: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 2.1.3

HEAT CONDUCTOR GEOMETRIC DATA .

HEAT M)IHME CN: 65DUCIOR SURFACE AREA

(DtD. LEFT RIGHI'EMEIRY VOIlME LEFTRIGIII'O.

INSIDE QJFSIDE) TYPE NO. (FT3 FT2 FT2) DESCRIPTION

12

3

456

78

9

101112

515253

545556

575859

606162

CYL. 1

CYL 1CYL. 1

CYL. 1CYL. 1CYL 1

CYL. 1CYL. 1CYL. 1

CYL 1CYL. 1

CYL. 1

60.2760.2760.2760.2760.2760.2760.2760.2760.2760.2760.2760.27

0.0.0.0.0.0.0.0.0.0.0.0.

5990.5990.5990.5990.5990.5990.5990.5990.5990.5990.5990.5990.

CORE 1

GNE 2GNE 3

GNE 4GNE 5(ORE 6

GNE 7GNE 8G)RE 9 .

GNE 10(DRE 11

GNE 12.

2-15

Page 40: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

2.2 Component Models

The transient behavior of a BWR is affected by system components

such as jet pumps, recirculation pumps and steam separators. The

following sections describe the major component models of theWNP-2 RETRAN model.

2.2.1 Jet Pumps

There are ten jet pumps in each of the two recirculation loops.

The ten jet pumps per loop are modeled as a single jet pump. This

jet pump is modeled as a single control volume in the WNP-2

RETRAN model. Jet pump performance is represented by a M-N

characteristic curve (N as a function of M, M = The ratio of the

suction flow to the driving flow, N = The ratio of the specificenergy increase of the suction flow to the specific energy

decrease of the driving flow). To determine RETRAN inputparameters that produce the expected M-N characteristic curve forthe WNP-2 jet pump, a RETRAN sub-model of the recirculation loop

and jet pumps was set up. Pressure distribution data from the

vendor was used to determine the suction and drive nozzle losscoefficients. The momentum mixing formulation was applied to the

suction and nozzle junctions. All other junction and volume

geometry data were calculated using design drawings. The M-N

curve generated with this model is compared to vendor's data in

2-16

Page 41: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 2.2.1. The comparison shows that this modeling technique

provides an acceptable representation for the WNP-2 jet pumps.

2.2.2 Recirculation Pumps

The centrifugal pump model in RETRAN is used to represent theWNP-2 recirculation pumps. The pump unique characteristics (i.e.,moment of inertia, rated values for pump flow, head and torque)

and the pump homologous curves supplied to the RETRAN pump model

are based on pump manufacturer's'ata . Since the recirculationflow control is achieved by varying the position of the flow

control valve, not by varying the pump speed, the recirculationpump motor is modeled with a constant speed.

2.2.3 Steam Separators

The steam separators couple the reactor core and the steam dome.I'he

emphasis in modeling the separators is on achieving the

appropriate coupling between these regions.

The 225 steam separators are modeled as a single control volume.

The Bubble Rise model in RETRAN is used to simulate the separator

performance. Referring to Figure 2.1, the interior of the

separators is represented by Volume 15. The entering two-phase

fluid flow is represented by Junction 14. Separation takes place

2-17

Page 42: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

within Volume 15. The exiting steam and liquid flows are

represented by Junction 15 and Junction 23 respectively.

The most important separator input parameters relative to the

coupling between the reactor core and steam dome are the

separator inlet inertia and the pressure drop across the

separators. The separator inertia is determined from vendor's

data . It is calculated as a function of the separator inletquality at the transient initial condition. The separator inletand exit loss coeffic'ients are determined by RETRAN using the

steady state initialization option. The pressure drop

distribution at the rated operating condition is in agreement

with vendor's calculation

2.2.4 Safety/Relief Valves

WNP-2 has 18 relief valves arranged in groups of 2 to 4 valves ata common setpoint. Each of the groups of valves at a common

setpoint is represented by a junction connecting the steam lineto a sink volume in the RETRAN model. The area of the junctionsis taken as the flow area of the valve times the number of valves

being modeled. When the valve is opened with the steam linepressurized, the junction flow becomes choked and the Moody

critical flow option is chosen in RETRAN to calculate the choked

flow rate. Contraction coefficients of the relief valve junctions

2-18

Page 43: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

are adjusted to match the specified flow at the reference

pressure.

The opening and closing of the relief valves is modeled using

RETRAN trips. When the pressure in the steam line volume

containing the relief valves reaches the specified setpoint , the

valve is opened linearly after a time delay. The valve stays

fully open until the pressure drops to the reclosing setpoint. Itis then completely closed in a stepwise manner.

2.2.5 Core Hydraulic

The core region is modeled using the compressible, single-stream

flow with momentum flux form of flow equation. The two-phase

friction multiplier is computed with the Baroczy correlation. The

form loss coefficients are set to match values calculated with a

steady-state thermal-hydraulic model. This model was developed

with the FIBWR code and has been benchmarked against plantdata. Initial values of core bypass flow and core support platepressure drop are also determined by steady-state thermal-

hydraulic calculation and input to RETRAN. The algebraic slipmodel allowing the liquid and vapor phases to flow with unequal

velocities is used to simulate the two-phase flow phenomena. The

profile fit subcooled void model is included for neutronic

feedback calculation.

2-19

Page 44: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

PXGURE 2.2.1

a

0

JET PUMP PERFORMANCE CURYE

OZ

0Hl-

K

0QGI

Qo

00 0.0 1.0 2.0

FLOH RATIO (H)

Page 45: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

.2.3 Trip Logic

The trip capability in RETRAN allows parameters (e.g., elapsed

time, normalized reactor power, pressure, control block output,

etc.) to be tested against a high or low threshold (tripsetpoint). The test can then be used to activate or deactivate a

system. This trip logic is used in the WNP-2 RETRAN model tosimulate the actuation of the Reactor Protection System (RPS) and

to initiate various valves and pump actions. Table 2.3.1

provides a description of the trip logic used in the WNP-2 RETRAN

model. This trip logic can be expanded to incorporate additionaltrips if they are needed.

2-21

Page 46: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 2.3.1

DESCRIPTION OF TRIP LOGIC

01 End calculation

02 'Aubine Trip(initiate stop valve closure)

03 Initiate MSIV closure

05 Initiate Scram

06 Open S/R valve group 1

-06 reclose S/R valve group 1

CAUSES OF TRIP ACFIVATIOÃ

Simulate transient time > setpoint

Control block -8 (water level) > setpoint (L8)

Contml block -8 (water level) < setpoint (L2)Volte 360 (turbine inlet) pressure < setpoint

Normalized power > setpointVolume 16 (steam dc') pressure > setpointControl block -8 (water level) < setpoint (L3)Trip 502 activatedTrip 503 activate'd

Volume 320 (steam line) pressure > setpoint

Volte 320 (steam line) Pressure < setpoint

Trips K7 thmugh +10 are used for other four S/R valve gmups

11 Trip recirculation pmps

12 Trip FW turbine

13 RCIC initiation

-13 Trip RCIC

14 Initiate HPCS

-14 Trip HPCS

Simulated transient time > setpointTrip 502 activatedVolwe 16 (steam deme) pressure > setpointControl block -8 (water level) < setpoint (L2)

Ccntml block -8 (water level) > setpoint (L8)

Contml block -8 (water level) < setpoint (L2)

Control block -8 (water level) > setpoint (L8)

Contml block -8 (water level) < setpoint (L2)

Contml block -8 (water level) > setpoint (L8)

2-22

Page 47: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

2.4 Control System Models

RETRAN control blocks (e.g., integrator, multiplier, function

generator, etc.) provide for the simulation of a variety ofreactor control systems. These control blocks can also be used to

prepare combinations of parameters for editing and to perform

other special functions as may be necessary. All of the RETRAN

minor edit variables aret

inputs. Table 2.4.1 listsavailable for use as control block

the control inputs used in the WNP-2

RETRAN model; The WNP-2 specific control system models are

described below.

2.4.1 Feedwater Control System

The Feedwater Control System comprises a level control system and

a feedwater flow delivery system. The level control system allows

for either one-element or three-element control. In one-element

control, the controller output is only a function of the

difference in setpoint and sensed level. In the three-element

control which is normally used, an additional steam-feed mismatch

is added to the level error. All controller settings and gains

are based on actual plant settings and the vendor's Control

System Design Report . The feedwater delivery system isrepresented by the simulation of the pump flow actuator based on

vendor provided plant specific information.

2-23

Page 48: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 2.4.1 illustrates the WNP-2 Feedwater Control System

model. Upon reactor scram, the Feedwater Control System switches

to one-element control and the water level setpoint is lowered 18

inches.

2.4.2 Pressure Control System

The Pressure Control System is composed of a reactor pressure

regulation system, a turbine control valve system, and a steam

bypass valve system. The signals from the pressure regulationsystem to turbine control valve and steam bypass system can be

regulated either by the difference in turbine inlet pressure and

its setpoint or by the load-speed error signal. The primary

settings which affect the pressure regulation system output are

the regulation gain and lag-lead time constants. They are based

on vendor provided data < . The turbine-generator is not

modeled and the turbine speed is specified as a function oftime.

Figure 2.4.2 illustrates the WNP-2 Pressure Control System model.

Upon a turbine trip, the turbine control valve demand signal isgrounded, thus the turbine bypass valve demand is set ecpxal tothe pressure regulator demand. This will cause the bypass valves

to open immediately, rather than waiting through the pressure

regulator lag time constant.

2-24

Page 49: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

2.4.3 Recirculation Flow Control System

WNP-2 is operated with the recirculation flow control system set

in manual control mode. No control element is required and the

flow control valve position is modeled with a function generator.

2.4.4 Direct Bypass Heating

The nonconducting heat exchanger model is used to account fordirect bypass heating. The heat removal rate for this heat

exchanger is determined by a control system. It is assumed to be

a constant fraction of the transient core power as shown inFigure 2.4.3.

2-25

Page 50: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 2.4.1

CONTROL INPUT DEFINITION

ID VARIABLE

NO. SYMBOL DESCRIPFION

01 WP'*

02 WP*03 LIQV04 LIQV05 LIQV06 KNS07 CONS

08 POWR

09 PRES

10 TRIP11 KNS12 WP"*

13 PRES

18 TIMX19 PRES

21 WQCR

Steam (Jct. 330) flow (8 NBR)

FW (Jct. 490) flow (4 NBR)

Middle downccmer (Vol. 18) liquid volwe (ft**3)lower downcarer (Vol. 19) liquid volme (ft**3)Upper downccmer (Vol. 20) liquid volume (ft*"3)Fraction of total core power deposited directly in core bypass regionConstant of 1.0active core (less core bypass) power (MW)

Turbine inlet (Vol: 390) pressure (psia)Scram (trip ID=5) activation indicatorConstant of 0.0Steam (Jct. 16) flow (8 NBR)

Turbine stop valve inlet (Vol. 360) pressure (psia)Simlation tiae (sec)Turbine bypass inlet (Vol. 350) pressure (psia)Heat transferred frcm clad to coolant for core section 1 (Btu/ibm)

ID No. 22 through 32 are used for heat to coolant for other core sections

50 CCNS

51 TRIP52 63NS

53 KNS

Constant of 1.0Turbine trip (ID=2) activation indicatorTurbine speed reference (100t)load bias (10t)

2-26

Page 51: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FXGURE 2.4.1

Feedwater Control System

jIADC

Va. SUM -014

~ LDC

Vol.

LlqddVol. (fl "3)

SUM -015 FNG -118

Toblo 25

Leva! vs,Volvma

SUM -086 LAG -008

Vol. 12

12

Dryor Flow

lFracllon ol Ralod) MUL -087

G "8.8

Sloam DryarPrassuro Drop

Corroclion

hAUL 0)9L l F

{One ElemonlConlr oil

10Scram

Acllvallon lndlcalor

Page 52: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FXGURE 2.4.1 (CONT.)

Feedwater Control System

SloamI Flow(Fraclion of Rolodl

LAG -OI I

G"100.

g—1.0SUM -007 SUM "009

Filler

LLG -OI0

g-l.O

FW

Flow(Frocllon of Rated)

LAG -006

G"100.

g" 1.0LAG -008 MUL "0l8 Level Feedback

(Three Elemenl Conlral)

50

Cons."1.0

g-l.O SUM "016 g-l.OScrom

Acllvollonhdhcalor

IO

Page 53: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 2. 4. 1 (CONT. )

Feedwoter Control System

50 Cans.- 1.0

Lovol Sol Palnlvs. Time

FNG -080Toblo I I

G "563.55

Lovol Sol DownIB'florScram

SUM -082 MUL -08 I

G"- I B.IO

ScramAcllvollonlndicolor

g-1.0

Pl Conlroiler

SUM -004 g"-1.0 SUM -OOI

G "0.0161

INT -002

G"0.024

g-1.0 SUM "003 To FW Pump Flow

Acluolor

MUL -0l9

g» I.B

Page 54: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FXGURE 2.4.1 (CONT.)

Feedwater Control System

FW Pump Flow Actuator

SUM -003 SUM -120 INT -121g-l.O SUM -122 g-l.O g- I.I5

g"-l.O g"-l.2

G" I.25

FNG "126

Toblo l4

FW Flux vs.Acluolor Oulpul

G-I.25

Page 55: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 2. 4. 2

Pressure Control System

18Time

Load vs.Time

FNG -012 SUM -454

Load BiosCons.-O. I

g"1.0

52

Turbine SpeedReference

g" l.O SUM -453 g"20. SUM "I IO Speed / Load

Domond ILD)

g"-l.O

18Time FNG "452

Turbine Speedvs. Time

Page 56: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 2.4.2 (CONT-)

Time

Turbhe htelPressure '-l.O

Pressure Control System

Pressure Regulator

FNG -013

Pressure Selpointvs Time

g--(Pr es.Re (.-30.) SUM "04)

G-O.03333

LLG -046

g-l.O

LAG -040 DER -049

G-0.274

g" I.O

Presswe

Repvter Demand(PRO)

SUM "053p -I.O LAG -052

G-2.924

INT -05 I SUM -050

g--l.O

Steom Line Compensator

Page 57: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FXGURE .2 (CONT.)

PRD 9Pressure Control System

Byposs Valvel9

Inle I Pr essur e

50

Cons." l.O

9-1.0

SUM -054

9—I.O

3% 8los

FNG -047Table l9G-4.0

LAG -055

Valve Areavs. Poslllon

FNG -033

Tablo 26

MUL -032

G"-992.7 4

ProssuroCorroclion

SUM "450 MUL -451 MIN -027 PRD8ypass Valve Fill Flux

LDTurbine Conlrol Volve Fil Flui

5lg"-I.O

Turbine TripAclivelion hdlco lor

LAG -029 LAG -030 VLM -025

Volvo Aroavs. Poslllon

FNG -035

Toble 27

MUL -034

G--3970.97

PressureCarr ac lion

Conlrol Valve9 Irdul Prossure

Page 58: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 2.4.3

Direct Bypass Heating

Acllve Core8 Powor

Cons." I.O

g-l.O

g--1.0

SUM "4IO I DIV -402 LAG -403Sensed Coro

Power

Cons."0.02

Cons;0.02

MUL "404

G"-1.0

ldeol Aemovol Aolo

for Heol Exchongor

Page 59: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

2.5 Steady-state Initialization

The RETRAN steady-state initialization option is used toinitialize the model. The parameters specified for the

initialization of WNP-2 model are dome pressure, core inletenthalpy, core flows (flow through core active region and flow

from lower plenum to core inlet region), recirculation flow, jetpump suction flow, feedwater and steam flows.

In addition to the inputs for the thermal-hydraulic

initialization, the values of the various controller setpointsand the initial output of control elements are specified. A nulltransient run is performed to confirm the consistency of the

thermal-hydraulic and control system initialization and to verifythat the steady-state is well established.

2.6 RETRAN Kinetics

The RETRAN-,02 MOD04 code has both point kinetics and one-I

dimensional kinetics capabilities. Selection of point or one-

dimensional kinetics for a given transient depends on the

accuracy requirements of the simulation. Point kinetics is used

in a simulation when the axial power shape is relatively constant

during the period of interest. Pressurization transients are

typically analyzed with one-dimensional kinetics because the

reactivity effects of void collapse and control rod movement play

2-35

Page 60: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

an important role in determining the overall results of the

calculation. The one-dimensional kinetics model provides a more

accurate calculation of these effects (particularly control rod

reactivity) than the point kinetics model.

The RETRAN model described herein uses nuclear cross-section

information prepared by the core analysis methodology described

in Reference 2. Files containing kinetics data for the variousfuel types present in the reactor core are produced by CASMO-2

and three-dimensional nodal characteristics of the core are

determined by SIMULATE-E . SIMTRAN-E collapses corewide cross-

sections from three-dimensional form to one-dimensional or pointkinetics form as required by RETRAN. Since SIMULATE-E and RETRAN

calculate moderator density differently, the SIMTRAN-E cross-

sections are adjusted manually to account for thy difference.This process is described more fully in Section 2.6.1 below.

2.6.1 General Description of the Generation of One-dimensional

Data

The first step in the process uses the EPRI codes SIMULATE-E and

SIMTRAN-E. SIMULATE-E predicts core power and burnup

distributions during detailed depletion analyses of the reactorcore. Qualification of the Supply System's SIMULATE-E

methodology is provided elsewhere

2-36

Page 61: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

SIMTRAN-E was developed under EPRI sponsorship for linkingSIMULATE-E and RETRAN. SIMTRAN-E reads restart files written by

SIMULATE-E, extracts the appropriate information for determiningcvf'sthe kinetics parameters, and generates the direct, RETRAN input

for transient analysis.

In this first step, SIMTRAN-E produces a one-dimensional kineticsdata file in the form of polynomials which describe the effectsof relative changes in water density and fuel temperature on

calculated two-group cross sections, diffusion coefficients,inverse neutron velocities, radial bucklings, and delayed neutron

fractions. This data file could be used directly by RETRAN.

However, without the adjustments described below, this approach

would lead to very conservative RETRAN predictions for severe

pressurization events. For benchmark analysis of pressurization

events, this conservatism would create artificially large

uncertainty factors.

The kinetics conservatism is due to differences between the

SIMULATE-E model of core average thermal hydraulics and the

RETRAN model of average channel thermal hydraulics. As a resultof these difference, SIMULATE-E and RETRAN predict differentchanges in average moderator density for the same change in core

pressure. Since SIMTRAN-E receives data only from SIMULATE-E, itcannot adjust for the differences. Therefore, a manual

adjustment is made to the SIMTRAN-E output in the second step in

2-37

Page 62: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

the kinetics process. This step produces a revised data fileconsisting of a set of adjusted polynomials that can be used

directly by RETRAN in the best estimate mode.

Except as noted in the text, all of the transient benchmark and

example analyses described in this report used the adjusted

kinetics parameters as produced by the second step of the

kinetics process. For transients which do, not involve a

substantial change in moderator density, the adjustment isunnecessary because the induced conservatism is small.

Verification of the Supply System's methodology utilizing a pre-

released version of SIMTRAN-E is discussed in Section 2.6.4,below.

2.6.2. Calculation of the Initial Kinetics Input Data

To begin the first step in the generation of the one-dimensional

data, a nominal SIMULATE-E case is run at a core configurationconsistent with the initial conditions for the given transient.This nominal SIMULATE-E case uses power and void feedback todetermine the three-dimensional core power and flux distributionsand the critical eigenvalue. The nominal SIMULATE-E case uses

cross-sections which have not been adjusted to match k-infinitiesof the lattice physics code (i.e. unadjusted Zal), but it is run

from a SIMULATE-E restart file generated with cross-sections

2-38

Page 63: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

which were adjusted to match k-infinities of the lattice physics

code (i.e. adjusted Zal) .

For transients in which it is necessary to model the effects ofcontrol rod insertion resulting from a scram, an additionalSIMULATE-E case is required. This case is based on the nominal

case and is run with power feedback disabled. The only

difference between this case and the nominal case is the controlrod position array, which has all rods fully inserted.

As noted above, SIMTRAN-E reads the restart files generated by

the SIMULATE-E cases. It then collapses the three-dimensional

SIMULATE-E data to one-dimensional data for RETRAN and determines

the dependence of the kinetics parameters on relative water

density, square root of fuel temperature, and control state.

SIMTRAN-E generates all kinetics parameters except kZf> and kZf2

by radial collapse with adjoint flux weighting. kEf] and k~f2

are radially collapsed with volume weighting. The dependence ofthe kinetics parameters on water density and fuel temperature isdetermined by making perturbations in these quantities. Allrelative water density and square root of average fueltemperature perturbations are done in three dimensions and are

then radially collapsed. The one-dimensional nominal and

perturbed kinetics variables are then analyzed to produce

polynomials that are functions of the relative change in water

2-39

Page 64: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

I

density and the change in the square root of the average fueltemperature at each axial node. This procedure is performed forboth the nominal case and for the controlled case.

2.6.3. Adjustment of Kinetics Data

To begin the second step in the generation of the, one-dimensional

data, the SIMTRAN-E output from the first step is used and

parallel SIMULATE-E and RETRAN cases are run to quantify the

difference in axial moderator density distributions between the

two models for identical variations in core pressure.

The coefficients in the kinetics parameter polynomials that are

associated with the changes in relative moderator density are

then modified so the change in each kinetics variable in RETRAN

for a given pressure change js the same as that pressure change

would give in the one-dimensional SIMTRAN-E model. Thus

reactivity changes at each axial node generated by a pressure

change are preserved between SIMTRAN-E and RETRAN. The constant

term in each kinetics parameter polynomial determines the initialsteady state eigenvalue in the RETRAN unperturbed state. The

constant terms are not modified when new polynomial fits are

developed; consequently, the SIMULATE-E eigenvalue is preserved

in the RETRAN unperturbed state.

2-40

Page 65: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

The cross section libraries used in the core physics analysis are

based on ENDF/B-III. ENDF/B-III includes delayed neutron frac-tions which are artificially low. Preliminary ENDF/B-V data

shows an increase in delayed neutron fraction ranging upwards

from 5.44 in all fissile isotopes. To bring the delayed neutron

fraction closer to those specified in ENDF/B-V, a +54 manual

adjustment is applied to all delayed neutron fractions before

final data is put into the RETRAN input file.

2.6.4. Verification of the Supply System's Methodology

The Supply System's version of SIMTRAN-E is not a formallyreleased EPRI code. Results obtained by this version were

reviewed by EI International and were found to be acceptable

Further verification'as obtained by the Supply System for the

steady state results by comparing the axial power distributionsproduced by SIMTRAN-E for the initial states of the three Peach

Bottom turbine trip tests. Figures 2.6.1, 2.6.2 and 2.6.3 show

the axial power shapes predicted by RETRAN compared to those

predicted by SIMULATE-E and by the process computer for the

initial state of each of these turbine trips. In each case, the

RETRAN model is based on the one-dimensional kinetics inputproduced by SIMTRAN-E and modified as described above.

The ultimate validation of the SIMTRAN-E calculation is the

accuracy with which RETRAN predicts system behavior in benchmark

2-41

Page 66: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

transient analyses. The transient mode is validated by the

predictions of the Peach Bottom turbine trip tests, which also

match the data closely. These results are shown in Section 3.2.

2-42

Page 67: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

aauaZZe.1initialAxialPower Distribatlon

Peach Bottom Unit2 TT11.500

1.400

1.300

1.200

1.100

w I.OOO

> 0.900Q, P&OO

~ 0.700~g 0.600

0.500

0.400

0.3000.2000.100

~ ~ ~ ~ %1 'I

' ' ~ ~ r ~ ~ ~ '

. ~ '. ~ iC.r ~ ~

O' [}I(I * ~ ~

~ 'I 'I 1

I ~ %1 I"-'Cr:'~ ~

I~ ~ ~ ~

~ ~ ',t ~ . ~ ~

I

~1 ~ 'I ~ ~ ~ ~

~ I'

~

r rlM Y

~ ~ ~ ~' ~ ~ ~ ~ ~

I ~ ~ ~ 'I

I ~ %1 'I1

~ - ~ ~ ~

~ ~ ~ ~ ~ ~ I'' '~ .

~ ~ ~ i I ~ ~ ~

~ ~ %%

r

h I.':t.r: h.hr

I '

1 ~ ~ ~- ~ ~ ' ~ ~ ~

~ 1 ~ ~~ Ir

~ ~ \ ~

~ 'I 'I'r

11 ~" ".'II ~

~ ~ ~ ~ ~ ~ ~

' ' ~

~ ~

~ 'ItIr IJ ~

~ %'%

~ I

1 ~

-'% ~

'1 I 'I ~

t

1 ~ ~

'I I

~'I

~ ~ V

I

~ ~

\ ' 'I '

. ~:." ~ }.". ~

~ ~ % ~ 1 ~

~ ~ ~ ~ ~ ~ ~ ~ ~

II r Ir ~

I

~A ~ I I I~ ~,I

~ ~

~ ~ ~ ~

\~ ~ .

~ I ~ r ~ I I

i~ j"cg .' , I ~ ~ 1 ~

~ ~

) ~ - ~ h ~ ~ ~

% 'r J~ ~ ~ ~

. ~ ~ - '}t~

I ~ '~ witt ~ ~ ~

t ~

~ ~ ~ } ~ ~ ~

"~

'II

~ r ~

~ ~,I ~ ~ , \ ~

't %1 ~:..1 r}

~ ~ ~ ~ h ~

~ It ~

, ~ ~

~ ~ ~ } r ~ ~

'I

~ ~ ~ '~

~ ~ ~ ~ r} ~ ~ ~ ~

I % ~ ~ .~ ~ ~ ~ ~ '.}~ ~ ~ ~ . ~

~ ~ ~ ~ hh ~

~ ~ ~ ~ ~ ~

l.~ ~'"." I.

" .'I'

~ ~

~ ~ ~ ~ ~ ~ ~ ~

> ~ I~ I t ~

'~ ~ r

'. r' ~

rr

Process RETRAN 8NULATE-EComputer—Ej- ';. I

. i ~'.

1'I 1 % " ~

1 Ah

'I~ ~ "}'

~ 'r'*~ ~ '

~ 'I ~

~ ~

I I ~ I Irtr ~ ~ I~ ~ h ~ ~

rh

h\

~ ~ ~ ~ ~

~ ~ ~ '~

' ~ ~ ~ I%%% Ih

,'

~~1 t'I '%

~ h ~

'

I~ ~ h ~ ~ ~

~ r r

~ . ~ ~ ~ ih h ~

:::t. r~,, ~ ~

'.OOQ

r ~

0 12 24 36 4& 60 72 84 96 I 0& 120 132 144Distance Above Boffom ofActive Fael (Inches)

Page 68: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

HGURE2.5'.2InitialAxialPower Disfrihutlon

Peach Bottom Unit2 TT21.500

1.400

1.3001.200

1.100

1.000~ 0.9004- 0.800~ 0.700

~g) 0.6000.5000.4000.3000.2000.1000.000

l h I

~ ~ ~ ~ ~ ~ r ~ ~ ~ ~ ~ ~ ~

~ ' ' ~ ~ ~ ~ ~ ~

~ ~ ~ k ~ ~ '

~ ~ ~ ~ ~ 'Lr~ ~ ~ ~ ~ ~

h'I- r 'I I ~ 'I

It tk

I

!

~ ~ ~ ~ ~

.' ~ l~ "~ ~ ",

~ ~ ~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~

< ~ ~ ~ :

jk.

r.'

~ ~ ~ ~

~ ~ ~ ~ ( ~ ~ ~ J ~ ~

h

~'' I ~ ~ ~ ~

'

I~ ~ I-9 ~ I ~

I

~ «"" I""

~ I ~

('. ~

I ~ I'I

~ ~ ~ ~ I ~ ~'

~ 1 'j ~ I'I..' rg;r~' j '

~

~ ~

. ""l-'. -.h ll

'L ~''

~ ~ ~ ~

~ .I ~ 'r ) ~ ~ .,

I

~ ~ ~

'I ~

I~ I ~ ~ ~

h ~ ~

t 't

11

~h

.r.rl,;"-Q

~ ~ ~ ~

r.rhr t

~ ~ ~ ~ ~ ~

I~ ~

j I ~~

~ tt ~

~ ~

>jjk~ *t..

~ r'/ ~

I~ ~ ~

'

"" "I~ L ~ ~ '

~ ~ ~ ~

'I~ jl~

I ~"

1~ ~

~ L ~

~ ~- ~rI

'/ ~ ~ ~

~ I ~ ~ '

~ ~ r ~ ~ ~

~ 'I'1 ~ 1 I ~

~ ~ + ~ ~ ~

, ~ ~ l. ~ k ~

~ ~ ~ t

ProcessComputer

I," ~

~ ~ ~ \ th

t

tlat

tent

1 'I ~ ~ I

I

~ 'Ij ~ ~ ~

~ ~ ~ ~ ~

I 'I

~ + hh

, ~

I 't Ih 'I I'I"

'1 1

1 ~

~,Ir ~r ~

~ I~;" l.' ~

~ 'I ~~ ~ I

~ ' ~ L ~ ~I ~-'

'I t

I ~ jl Ikt ~ I lj~

~ I "I ~~ "L) .L ~ . ~

~ ''I '1'I

\ I~ t~ I Al lkkk

, 'I

A

~ ~ ~ ~ ~ ~ L ~

t " rt h

, ~ ~

~ ~

~ ~

','L

~ j'', "~

I ~ I ~

~ lh I n ~

'~ ~ ~ ~ ~ ~

'I1

~ ~ ~ L ~ ~ ~ ~ ~

*

AD ~ ~ ~ ~ ~ ~ ~ ~

RETRAN 'IMULATE-E

1 ~ ~ ~ ~ 1 kr ~ ~ ~ I

''I 'I 1 ~ ~ 'I I

L

~ '1

j

~ ' ~ ~ ~ \ ~ ~

~ I 'I 1'I 1

~ ~ rr ~ ~ ~ ~ ~ ~

'r;~ ~ 'LE ~ ~

~ r I ~ '

~ ~ ~ ~

~ L ~ ~ ~

'I

~ ~ ~, ~ r ~

~ ~ L ~ ~

1 ~

*

I t~ ~ ~

'~ L

LL' ~

~ ~ kl I ty ~ tk ~

~ ~ ~ ~ I - Ml

I'

~

~ ~ ~ ~

~ k 1 litt W I

t~ 1\. ''I

~ 'L '

0 12 24 36 48 60 72 84 96 108 120 132 144

Distance Above Boffom ofActive Fuel (fnches)

Page 69: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

I=IGURE2.6.8InitialAxialPower Distribution

Peach Bottom Unit2 TT81.500

1AOO

1.300

1.200

1.100

< 1.000~ 0.900< 0.800

~~ 0.700~g 0.600

0.500OAOO

0.3000.2000.100

0.000

~,J . I

4 J L ' ~

~, ~ I ~

~ II'k

~ LJ ~ . ~ ~

I.l I I I ELI ~

J

EJ ~ ~

~ I 'f( I ~ira

~ ~ ~ k EIJ

~ I J I '

k. ~ ~ J ~ I

,"1I J L

'

~ I~ II.'IJ

iftI ~ rl ~ ~ ~

~ I

~ ~ ~ ~ I ~ I ~ ~ ~

~ ~ ~

I I'

, ~ ',

~ vhr ~ ~

~ ~, ~

~ ~ I. ~ ~ ~

Ill~ J ~ I ~ I

, ~

~ ~ ~ L' . I ~ ~ ~ ~ ILE ~ 'll LL

I . ~ ~ J

~ J 1 ~

LL ~ I L

, ~ '

I ~ ~ \. ~ ~

Ll~ Jll ~ I~ r

~ f I lt fft

~ I rt I I I'

rt I ~ krt ~ tEhl LIk I~ LI.L~ I ~

f I 'l' ~

~ ~

r ~,k ~

'

~ J ~ ~ ~

ProcessComputer

Jhhl 11

, ~

~ggt ..1~ ~ = J I

~ ~ I ~ I 4 ~ ~ I,'I ~

~ l.lIII4 ~ ~ ~

~ ~ I I ~ t ttt ~,I El.lkll J I

~ ~ J

~ ~ ~ ~ I, ~ I

~ ~ ~ tr

~ ~ ~

I LLI~ I~ L El 4

I ~ I ~ ~ tkklIl

ik-~ rrrt ~

I~ IE4LL

~ 1 ~ LLI

t ~ t Itltt,

LL LJE ~ ~ ~

1~ ttt'I I tl It

I\ ~ L4

~ ~ I t

t rt ~ k I'

J ~ ~ EE ~ I I

I r tt tt~ I ~ IILIII

~ ~

I ~ ~ r I ~

, ~ '

~ ~ ~ I

~ I

RETRAN SIMULATE-E

. ~'I

tl I ~

ILI ~ 4 I~ ~ LI I

'I~ E.

LIEIJ II4v' Lt'

k ~ r I'

~

~ ~ Ik~ I I I I ~

I ~

~ J ~ I ~

I ~ I, ~ I. I

~ ~ k ~ Ilk~ I

~ ft tq f f. ~

~ r'

' ~ ~ E ~ ~

h

~ kkkkt I ~ I ~

~ I ' ~ I~ LEE I ~

. ~

I ~ I I

~ J

E~ ~ . ~ ~ f r

) ~ IJEI ELLE

~1 L IL EIII

fr ~

klh EJI ~ I ~

~ I ~ ~ I ~ I.~ I

0 12 24 36 48 60 72 84 96 108 120 132 144Distance Above Bottom ofActive Fuel (Inches)

Page 70: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

-l

l

I

Page 71: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.0 QUALIFICATION

The objective of this chapter is to compare the Supply System's

RETRAN simulation with WNP-2 power ascension tests (PAT) and Peach

Bottom turbine trip tests. The Supply System performed these

benchmark analyses to qualify the WNP-2 RETRAN model and todemonstrate user qualifications. The benchmarks comprise fourWNP-2 PAT tests and three Peach Bottom turbine trip tests.

These benchmark analyses, which were performed in the best-estimate

mode, qualify the WNP-2 RETRAN model for the licensing basis

analysis presented in the next chapter.

3.1 WNP-2 Power Ascension Tests

During the period of October -December 1984, a series of power

ascension tests (PAT) at near full power were performed at WNP-2~~.

The data from these tests is available for verifying the WNP-2

RETRAN model. All of the transients analyzed in this chapter were

recorded during the initial WNP-2 PAT testing.

The best-estimate model described in Chapter 2 was used in the PAT

analyses and the best-estimate analyses, discussed below, verifythe modeling. For future reload analysis, the licensing basis model

will be used to assure conservatism in the output. The licensingbasis model is discussed in Chapter 4.

3-1

Page 72: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

The power ascension tests chosen for benchmark are as follows:

1. Water level setpoint change —This transient is used mainly tobenchmark the feedwater control system, water level predictionand general stability of the RETRAN model.

2. Pressure regulator setpoint changes — This transient is used

to benchmark the pressure regulator control system, RETRAN

stability and system model accuracy.

3 ~

(

One recirculation pump trip — This transient is to benchmark

the pump coastdown characteristics and system response to an

asymmetric recirculation flow variation.

4. Generator load rejection with bypass — This transient is used

to benchmark the steam line modeling and system pressurizationbehavior.

Since the PAT transients are milder than the limiting transients inlicensing basis analysis, the first three transients were analyzed

using the point-kinetics core modeling. The one-dimensional

kinetics model was also run for the recirculation pump trip case todemonstrate the validity of the point kinetics model for these

relatively mild events.

The load rejection with bypass transient was analyzed using the

3-2

Page 73: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

one-dimensional kinetics model. This treatment is consistent withII

the example licensing basis transient analysis (load rejectionwithout bypass) in the next chapter.

3-3

Page 74: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.1.1 Water level Setpoint'hange (Test PAT 23A)

The purpose of Test PAT 23A was to demonstrate the stability of the

level control system. Test PAT 23A was initiated at 95.14 power

and 96.84 flow. The test procedure consisted of a six-inch step

increase in vessel water level setpoint, a delay to allow the

system to reach a new equilibrium condition, and a six-inch step

decrease in vessel water level setpoint.

3.1.1.1 RETRAN Model for Test PAT 23A

Since the test condition is near the rated condition, the standard

RETRAN base model at rated condition as presented in Chapter 2 isused to start the transient simulation. To model the step change

of the level setpoint, a general function table used in the levelsetpoint control block (Control Block 80) is modified.

3.1.1.2 Results and Discussions

The water level setpoint step change test was analyzed mainly toqualify the feedwater control system and vessel water level models.

It also confirms the adequacy of the RETRAN thermal-hydraulic and

neutronic coupling.

The vessel water level in this test is maintained at a specifiedsetpoint through the variation of the feedwater flow which is

3-4

Page 75: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

\

controlled by the feedwater control system. The feedwater

controller uses vessel water level and the mismatch between steam

flow and feedwater flow to determine the feedwater pump speed,

which controls feedwater flow. The controller responds to an

increase in vessel water level setpoint by increasing feedwater

'low. This increased feedwater flow causes water level in downcomer

to increase and the water temperature in core inlet to decrease.

The reduced core inlet temperature leads to a reduced core void,resulting in a core power increase. The feedwater controller,after detecting water level increase, will reduce feedwater flow,which leads to a reduction in power. This combination of feedwater

control logic and core response will lead to a new steady state forboth core power and feedwater flow close to their initial values

and the water level will be stabilized at the new setpoint.

Figure 3.1.1 shows the measured and calculated feedwater flowresponse. Similarly, Figure 3.1.2 shows the measured and calculat-ed water level. These plots show that the RETRAN model predictsevents and timing consistent with the data.

Figure 3.1.2 indicates that RETRAN calculates a water level thatapproaches a value that is six inches higher than the initial water

level at about 20 seconds after the setpoint change. The measured

data indicates a higher asymptotic value of 7.8 inches in water

level change, which may indicate an inconsistency between the levelstep change used in the analysis and actual test.

3-5

Page 76: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Other parameters (steam flow, dome pressure and core power) are not,

plotted because they did not show any significant changes (less

than 34 variation from steady state values) throughout the test.

3-6

Page 77: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.1

FEEDNATER FLON — PAT TEST 023

RETRAN

PLANT DA A

16

SECONDS24 32

Page 78: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.2

HATER LEVEL — PAT TEST 023

RETRAN

PLANT DA

NWZoUfZH

08 p i6

SECONOS24 4p

Page 79: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.1.2 Pressure Regulator Setpoint Change (Test PAT 22)

Test, PAT 22 was performed to demonstrate the stability of the

pressure control system. Test PAT 22 was initiated at 97.54 power

and 95.94 flow. The test procedure consisted of a 10-psi step

decrease in pressure regulator setpoint, a delay to allow the

system to reach a new equilibrium condition, and a 10-psi step

increase in pressure regulator setpoint to the original value.

3.1.2.1 RETRAN Model for Test PAT 22

Test PAT 22 was analyzed with the standard RETRAN base model (cf.Chapter 2). The initial dome pressure in the RETRAN base model is1020 psia, which differs slightly from the 990-psia test pressure.

The transient is very mild and the response to the step change inpressure setpoint was not expected to be sensitive to the small

difference in initial pressure.

To model the test, a general function table used for the pressure

setpoint control block (Control Block 13) is changed to reflect the

step change of the pressure setpoint.

3.1.2.2 Results and Discussions

Zn this test, the pressure regulator and the Digital Electro-Hydraulic Control System (DEH) will respond to a decrease in

3-9

Page 80: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

pressure regulator setpoint by opening the turbine control valves

to allow more steam flow which reduces system pressure. The

resulting decreased system pressure increases core voiding and thus

reduces core power. As pressure decreases, the pressure regulatorand DEH control system starts to close the turbine control valve.

The pressure will eventually be stablized at the new setpoint.

Figure 3.1.3 shows the measured and calculated transient pressure

response. The pressure settles out at about 10 psi below the

initial pressure, indicating good alignment of the pressure system

control model.

Figure 3.1.4 presents the measured and calculated power behavior.

The system stabilizes back to the initial power rapidly, and the

RETRAN model predicts this behavior consistently with the data.

Figure 3.1.5 shows the measured and calculated steam flow. Figure

3.1.6 presents the measured and calculated feedwater flow. The

calculation matches the plant data closely in both of these areas.

The simulation/data comparisons indicate that the pressure

regulation control system in the WNP-2 RETRAN model performs as

intended.

3-10

Page 81: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.3

OOME PRESSURE — PAT TEST 022

+ DOHE PRESSURE

X PLAN'ATA

H0jlL

OJ

8Z

r0 x

x

xx x x x xxxxxxxxx

0I p i2

TAHE (SEC)

Page 82: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.4

NORMALIZED POWER — PAT TEST 022

+ BETRAN

X PLANT DATA

0lUNHJQoK0Z

XX XX„XX

x x x x xX

80

p i2TrvE (sEc)

Page 83: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.5

STEAM FLOW — PAT TEST 022

+ FLPM JUN 39P

X PLANT DATA

0Jh.

Q

N ~

H»JXK0Z

X XX

X

Ol

0 p 12

TINE (SEC)24

Page 84: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.6

FEEDWATER FLOW — PAT TEST 022

+ RETRAN

X PLANT OATA

0JU.

0N ~

HJXK02 X X

80 p f2

TIME (SEC)

Page 85: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.1.3 One Recirculation Pump Trip (Test PAT 30A)

Test PAT 30A was performed to verify the performance of the

recirculation system. The test also demonstrated that the water

level could be controlled without resulting in turbine trip and/or

scram. Test PAT 30A was initiated at 96.2% power and 1004 flow.

The test was initiated by tripping one recirculation pump.

3.1.3.1 RETRAN Model for Test PAT 30A

Test PAT 30A was analyzed with the standard RETRAN base model atrated power and flow. The transient was initiated by introducing a

recirculation pump trip in Recirculation Loop A at time zero.

A Test PAT 30A case with one-dimensional kinetics was run toevaluate the effect of void feedback on the core power calculationat lower core flow conditions such as in this test and the resultscompared to the point-kinetics model. Unadjusted cross sections

for Beginning of Cycle 1 conditions were used in the one-dimension-

al core analysis. (See Section 2.6 for a description of cross

section adjustments.) Use of the unadj'usted cross sections isacceptable because the one-pump trip transient is very mild. The

data comparison in the next section supports this assumption.

3-15

Page 86: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.1.3.2 Results and Discussions

The benchmark verifies the coastdown characteristics of the trippedrecirculation pump and the system model response to asymmetric

recirculation flow disturbances. Neutronics, core hydraulics,pressure regulator control system, and feedwater models were

validated in the analysis. Figure 3.1.7 shows measured and

calculated recirculation drive flow for the tripped loop (Loop A)

for the point kinetics case. Figure 3.1.8 shows measured and

calculated recirculation drive flow for the unaffected loop (Loop

B). The calculated flow tracks measured data in both comparisons.

The Loop B flow increases slightly as the transient is initiatedand stabilizes at a higher value. The unaffected loop sees a lower

flow resistance after one pump is tripped.- Figures 3.1.9 and

3.1.10 show the same comparisons for the case using one-dimensional

kinetics. These comparisons are very similar to the cases withpoint-kinetics model, supporting the use of the point kineticsmodel in the other PAT test benchmarks.

Figure 3.1.11 shows the normalized jet pump flow for Loop A.

Figure 3.1.12 shows the jet pump flow for Loop B. Again the RETRAN

results track the data. Figures 3.1.13 and 3.1.14 are the same

comparisons for the case using one-dimensional kinetics. A

comparison of the one-dimensional case with the point-kineticsmodel showed no difference in the calculated jet pump flows.

3-16

Page 87: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.15 shows that the RETRAN core hydraulic and neutronic

models calculate transient core power consistently with the data.

Initial core power decrease is caused by the increased core void

after the single pump trip. As the core power decreases, the core

void will eventually decrease (after a fuel heat transfer time

constant). The core power begins to increase and level off at a new

equilibrium. Figure 3.1.16 is the corresponding plot for the one-

dimensional RETRAN model. The one-dimensional model gives a

slightly better match with the plant data than the point kineticsmodel later in the transient because the one-dimensional model

tracks the void feedback in the core more accurately than the pointkinetics model. The fluctuations observed at about 4 seconds and.

16 seconds in the one-dimensional case are also the results ofdetailed axial void feedback.

Figures 3.1.17 and 3.1.18 show the core heat flux behavior

calculated by the point-kinetics model and the one-dimensional

model respectively. Both track the plant data with the one-

dimensional model yielding slightly better results.

3-17

Page 88: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.7

RECIRC FLON PUNP A — PAT TEST 030A

PHP A FLPLANT DA

0Jb.

0hJNHJ<e>oK0z

00 p 12

TIME, SEC24 3p

Page 89: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.8

RECIRC FLOW PUMP B — PAT TEST 030A

PHP B FL X

PLANT DA A

nUlNHJ<IZ~K0Z

X X X X X X X X X X X X X X

00 0 12

TIME, SECi8 24

Page 90: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.9

RECIRC FLON PUMP 4 — P4T TEST 0304 — iD

PNP A R.PLANT OA

0tUNHJ<e

K0Z

00

0 i2TINE, SEC

18 24 30

Page 91: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.10

RECIRC FLON PUMP B — PAT TEST 030A — |D

PHP8FL N

PLANT OA A

0hlNHJ<fm

>oK0Z

X X X X X X X X X X X

O0 12

TINE, SECis 24 30

Page 92: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.l.ll

JET PUMP A FLOW — PAT TEST. 030A

FLN JUN 1

PLANT DATA

0IdNHJ<o>oK0Z

XX X X

X X

0I p 12

TINE, SEC

Page 93: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.12

JET PUMP 8 FLOW — PAT TEST 030A

+ FLON~Qx PLAtP 0ATA

30h.

0llfgN ~

H

XK0z

x x xxxx x x x x x

AOO

TIHE. SEC

Page 94: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.13

JET PUMP A FLOW — PAT TEST 030A — iD

FLOM 8JN i~ DATA

0blNHJ<p>oK0Z

x x xX X

0I p

TIME, SEC

Page 95: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.14

JET PUMP B FLOW — PAT TEST 030A — iD

+ FLQI AH Ix PLAUDIT olTA

0>aN ~

JXKOz

x x xxxx xxxxx xxxxx x x

a~o

TIHE, SEC

Page 96: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.15

POWER — PAT TEST 030A

RHRAN

PLANT DA A

aUJ

NHJQoK0Z

x xx

X X

N

0 0 f2vrvE, sEc

18 24 30

Page 97: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.16

POWER — PAT TEST 030A — iD RETRAN

RETRAN iPLANT DA A

0rl

II]

0Q.

0IIINHJyOQoK02

xX X

X X

Ol

0 p

TIME, SECi8 24 30

Page 98: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3. l. 17

CORE HEAT FLUX — PAT TEST 030A

RETRAN

PLANT DATA

X3J0.

>oK0Z

a0 p

TINE, SEC24

Page 99: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.18

CORE HEAT FLUX — PAT TEST 030A — io

BETRAN 1

PLANT DA A

0rl

X3JtL

~p>oK0z

p0 p 6 12

TINE, SEC3p

Page 100: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.1.4 Generator Load Rejection With Bypass (Test PAT 27)

Test PAT 27 was initiated at 97.54 power and 95.44 flow. The

transient was started by the activation of the main generator trippushbutton.

The rapid closure of the turbine control valves pressurizes the

steam lines and the core. As the void collapses, positive void

reactivity is induced. Scram is initiated by the turbine controlvalve fast closure pressure switch. The early scram results innegative overall reactivity throughout the test. The net effect isa power decrease shortly after the initiation of the transient. The

turbine control valve closure also initiates the recirculation pump

trip (RPT).

The turbine control valve closure and subsequent steamline

pressurization activate the opening of the turbine bypass valves torelieve vessel pressure. Since the capacity of the bypass is lessthan the test power level, dome pressure continues to increase.

Eventually the SRVs open to limit the pressure rise. For this event

Group 1 SRVs opened.

3.1.4.1 RETRAN Model for Test PAT 27

The main generator trip is set at 0.0 seconds. The turbine controlvalve performance was taken from the test data. In the WNP-2

3-30

Page 101: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

RETRAN model a single valve (Junction 380) at the end of steam linesimulates both turbine control and stop valves. When the controlvalve fast closure is activated, its corresponding delay time and

closure time are input so that Junction 380 simulates a controlvalve. .Observed control rod performance data was used as the

RETRAN scram time.

The maximum bypass flow for the base deck is set at the design

value of 254 of rated steam flow. Plant data supports a value ofI

37% maximum bypass flow, which was used for this simulation.

I

The one-dimensional kinetics model was used in this simulation. As

mentioned in Section 3.1.3, for a mild transient as in this case,

uncorrected one-dimensional cross sections are sufficient.

3.1.4.2 Results and Discussions

Figure 3.1.19 shows the calculated and measured variation in the

Average Power Range Monitor (APRM) signal during Test PAT 27. The

APRM signal is proportional to the neutron flux. The output from

RETRAN is adjusted so that the decay power is subtracted from thetotal power before it is compared to the measured data.

Test PAT 27 is the only benchmarked power ascension test which

resulted in a reactor scram. Figure 3.1.19 shows that the RETRAN

prediction tracks the initiation and progress of the scram closely,

3-31

Page 102: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

~„~

indicating acceptable scram modeling.

The WNP-2 RETRAN model contains two separate recirculation loops.

Figure 3.1.20 and 3.1.21 show that RETRAN follows the rates ofdecrease for both loops. The lower flow predicted for Loop B is due

to uncertainty of delay time for RPT initiation and a RETRAN

deficiency which results in calculating slightly asymmetrical loop

flows in a symmetric system with symmetric transient conditions.

However, the differences in flows are small. They are not expected

to affect the overall accuracy of the simulation. Figure 3.1.22.

compares the calculated and measured core flow. The results verifythe capability to calculate recirculation loop and core flows aftera Recirculation Pump Trip (RPT).

Figure 3.1.23 shows measured and calculated dome pressure during

the test. Turbine control and stop valve closure causes a rapidsystem pressurization. RETRAN predicts the pressure transientaccurately, particularly during the early stages of the transient(0-4 seconds) when the fuel thermal behavior is important for the

thermal limit predictions. The measured pressure spike at 0.3

seconds appeared only in the wide range Division 2 signal; wide

range Division 1 and narrow range signals do not show thisdeviation. The apparent pressure spike may have been an instrument

aberration. The plant data shows that one relief valve opened

while a second one opened and closed repeatedly. The WNP-2 RETRAN

model treats the first two SRVs with lowest pressure setpoint as a

3-32

Page 103: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

single equivalent valve. Both SRVs opened in the RETRAN simulation

and the RETRAN pressure results are lower after about 5 seconds.

Figure 3.1.24 shows the steam flow variation. The oscillation inthe flow rate from 0 to 3 seconds is caused by pressurization waves

after the turbine control and stop valves are closed.

3-33

Page 104: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.19

POHER — PAT TEST 027

+ POXGl IO NINCTIC

X PLANT CATA

KlU

0Q

0llINMJX„K o

Oo2

00 0 4

TIME, SEC

Page 105: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.20

RRC FLON A — PAT TEST 027

+ PLlW All ROT -SD

)( PLANT DATA

XX

X

0

030h.

0UJNM

XK0Z

4

00 D 4

TINE. SEC

Page 106: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.21

RRC FLOH B — PAT TEST 027

+ PLON ~ 404 -lOX PlANT OATA

0h.

0illNHJXK0Z

r4

XX

XX

X

XX

XX

X

00 O 4

TIME, SEC

Page 107: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.22

TOTAL CORE FLOW — PAT TEST 027

0

0U.

0hlNMJEK0z

'

O

xx x

0O y 4

TIHE, SEC

Page 108: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.23

OOME PRESSURE — PAT TEST 027

+ PAICS 10 KINETIC

X PLANl'ATA

IUKUlll)IllogaLo

xxxxxx

x

x x x x x xx x x x

004X 4

TIHE, SEC

Page 109: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Figure 3.1.24

STEAM FLOW — PAT TEST 027

+ aa iso n.ox sn

X PLAHz 0ATA

30h.

0IllNHJXK0z

O

X Xx x

X x xXx

X

x

X X X

O

O y 4TIME, SEC

Page 110: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.2 Peach Bottom Turbine Trip Tests

Benchmarking of the WNP-2 RETRAN model to the power ascension

test measurements verifies the capability and accuracy of most

elements in the model. These benchmarks cover expected operation,but normal startup testing does not cover circumstances which

challenge the core operating limits. To demonstrate the overallcapability of the RETRAN model under design basis conditions, the

Supply System performed an analysis of the three pressurizationtransient tests. (TT1,- TT2, TT3),conducted at Peach Bottom Atomic

Power Station Unit 2 (PB2).

3.2.1 Test Description

Detailed accounts of the Peach Bottom turbine trip tests can be

found in the EPRI report . A brief description is given here.

Turbine trip tests TT1, TT2 and TT3 were performed at PB2 priorto shutdown for refueling at the end of cycle 2 in April 1977.

These tests were conducted jointly by Philadelphia ElectricCompany, GE and EPRI to investigate the effect of the pressure

transient generated in the reactor vessel following a turbinetrip on the neutron flux in the reactor core. Measurements ofmajor process variables such as core pressure, dome pressure and

neutron flux were recorded at a frequency of 166 samples a.

3-40

Page 111: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

second. These measurements provide the best set of data for the

qualification of transient analysis methods.

The tests were initiated by manually tripping the turbine

(turbine stop valve closure) at three reactor power levels and

near rated core flow. The turbine stop valve (TSV) position scram

signal was intentionally delayed to allow a significant neutron

flux transient to take place in the core, providing adequate

qualification data. The power increase was terminated by a tripof the reactor protection system on high neutron flux. To

maintain sufficient operating margin, the APRM high neutron fluxscram setpoint was set down closer to the initial reactor power

level. The initial reactor power, core flow and the APRM scram

setpoint for each test are shown in Table 3.2.1.

TABLE 3.2.1

PEACH BOTTOM TURBINE TRIP TESTS

TEST CONDITIONS

POWER CORE FLOW APRM SETPOINT

TEST ~MW Rated Mlbm hr Rated 0 Rated

TT2

TT3

1562

2030

2275

47.4

61.6

69.1

101. 3

82. 9

101.9

98.8

80.9

99.4

85

95

77

3-41

Page 112: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.2.2 Peach Bottom Unit 2 Model Description

The Peach Bottom model incorporates the modeling techniques ofthe WNP-2 model. A schematic of the model is shown in Figure 3.2.

(The WNP-2 model is shown in Figures 2.1 through 2.4.) The

nodalization within the reactor vessel is identical except thatthe two downcomer volumes are combined into one in the Peach

Bottom model. Also the two recirculation loops are combined intoone in the Peach Bottom model and the recirculation loop isrepresented by two nodes whereas the WNP-2 model has five nodes

for each recirculation loop. The Peach Bottom model includes the

entire main steam bypass system whereas the WNP-2 model uses a

negative fill junction. This model is the best estimate bypass

system model of Hornyik and Naser , and was included to provide

a realistic simulation of this component. Because the steam linegeometry has a significant effect on pressurization transients,the geometric data for the steam line from Philadelphia ElectricCompany's topical report was used. The Peach Bottom steam lineis modeled with six nodes whereas the WNP-2 steam line is modeled

with seven nodes. An additional node was used in the WNP-2 model

to provide more accurate pressure for SRVs lifting. SRVs did not

open during the Peach Bottom turbine trip tests. The physicaldimensions and- characteristics of the dominant fuel type were

used. The dimensions and characteristics for the dominant 7x7

fuel type were obtained from EPRl documentation

3-42

Page 113: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

PXGURE 3.2 PB2 RETRAN MODEL

10

19

Feed-waler

2 Loops

13

p; 26,25 j~

5l

30

34

12

14

SRVs

15

Slop valves

Conlrol valves

27 '8 i 29

18

Recirculalion pumps

I

MSIVs

17

Bypassvalves

31

9 Lines

20

Condenser

32 33

Page 114: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.2.3 Initial Conditions and Model Inputs

Since comparison with actual measurements was a primary

objective, best estimate model inputs developed from originaldata sources such as drawings and measured plant performance data

were used.

The core thermal power, total core flow, core inlet enthalpy and

initial steam flow were obtained from the process computer P-1

edits taken before each transient test. The steam dome pressures

were obtained from the recorded data. The recirculation system

was adjusted to correspond to the initial reactor conditions. The

core bypass flow was calculated for each test with the SIMULATE-E

MOD03 ("SIMULATE-E") computer code . The loss coefficient at the

core bypass region entrance was also adjusted to match the core

plate pressure drop calculated by SIMULATE-E. Reactor water

levels were initialized to match the test data. Table 3.2.2 liststhe initial conditions for each test of the Peach Bottom

analyses.

The feedwater flow rate was specified as a constant value foreach test. The short duration of the tests minimizes the

potential effects of the feedwater control system. The constant

flow assumption was validated through an additional analysisusing feedwater flow characteristics provided by Philadelphia

3-44

Page 115: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Electric Company. Both analyses provided the same results fortransient power and pressure responses.

The control rod scram time and speed can be estimated from the

measured plant Rod Position Information System drift relay output

signals. The average of the measured scram speeds (a sample of31 of the 185 control rods from TT1) is plotted in Re'ference 18

and was used with correction for rod acceleration for all three

tests. All of the control rods were assumed to insert at the

average speed.

The measured time dependent Turbine Stop Valve (TSV) positionand the Turbine Bypass Valve (BPV) position were used as RETRAN

input. A linear TSV opening was assumed with the stroke time

obtained from measured data. The BPV flow area was assumed to be

proportional to the measured position. Since the TSV positionsignal channel malfunctioned during TTl, the average of the

signals from TT2 and TT3 was used.

Since the Peach Bottom Turbine trip tests were pressurizationtransients, they were analyzed using the one-dimensional kineticsmodel. The SIMULATE-E code was used to generate the RETRAN one

dimensional kinetics data at the initial conditions for each

test. A stepwise depletion of cycles 1 and 2 based on the EPRI

documentation was used to determine the fuel exposure, void

history and control history at the time of the tests. The basic

3-45

Page 116: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

procedures described in Section 2.6 were used to develop each ofthe three sets of kinetic data.

TABLE 3.2.2

PEACH BOTTOM TURBINE TRIP TESTS

INITIALCONDITIONS

TT2 TT3

Core Thermal Power (MW) 1562 ' 2030.0 275.0

Total Core Flow (ibm/sec)

Core Bypass Flow (ibm/sec)

Core Plate Pressure Drop (psid)

Steam Dome Pressure (psia)

Core Inlet Enthalpy (Btu/ibm)

Steam Flow (ibm/sec)

Recirculation Flow (ibm/sec)

16 '991.6

528.0

1628.0

ll.61

976. 1

518. 1

17. 71

986 '

521.6

2183 ' 2461 '

9386.0 7686.0 9443.0

28139.0 23028.0 28306.0

1636 '0 1384.87 1762.75

3-46

Page 117: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.2.4 Comparison with Measurements

The goal of these Peach Bottom analyses was to demonstrate the

Supply System's RETRAN model of PB2 can accurately simulate the

power and pressure increase during rapid pressurization

transient. Therefore, comparisons of RETRAN calculations to the

measured pressures (turbine inlet, steam dome and upper plenum)

and LPRM signals are essential. They are presented in the

following two sections.

3.2.4.1 Pressure Comparisons

Pressure comparisons are expressed in terms of pressure change

from the initial value. This eliminates the need to account forthe sensing line elevation head, uncertainties in the pressure

loss coefficient and differences between nodal and localpressures.

Pressure transients calculated at three locations are compared

with the measured values in Figures 3.2.1 through 3.2.3 (at the

turbine inlet), Figures 3.2.4 through 3.2.6 (at steam dome), and

Figures 3.2.7 through 3.2.9 (at core upper plenum). The measured

pressures are obtained directly from the test data file and have

not been. filtered. Time shifts (to account for sensing linedelay) based on information provided in the EPRI documentation

were applied to the calculated pressures. To eliminate the

3-47

Page 118: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

instrument line effects, the RETRAN model calculated upper plenum

pressures are compared to the filtered test data in Figures

3.2.10 through 3.2.12.

The good agreements .in turbine inlet pressures and steam dome

pressures indicate that the dynamic of the steam lines is wellsimulated. The first pressure oscillation in the steam dome isslightly overpredicted for TT1 and slightly .underpredicted forTT2 and TT3. The upper plenum pressure calculated by RETRAN forTT1 is slightly higher than. the measured data. For TT2 and TT3,

the calculated and measured upper plenum pressures agree

'reasonably well. Adequate prediction of the core upper plenum

pressure response is essential to transient power predictions.Table 3.2.3 summarizes the calculated and measured steam dome and

upper plenum pressures at the peak of first oscillation.

Overall, the RETRAN calculated pressures are in good agreement

with the measured data. The discrepancies are within the

tolerances due to uncertainties in RETRAN model inputs such as

initial steam flow, bypass valve opening delay and turbine stopvalve closing time.

3-48

Page 119: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 3.2.3

PEACH BOTTOM TURBINE TRIP TESTS

PRESSURE CHANGE (PSI) AT PEAK OF FIRST OSCILLATION

CALC. DATA

STEAM DOME UPPER PLENUM

CALC. DATA

34.7

40.5

46.2

33.4

41.9

47.4

37.5

42.3

48.3

34.9

44.2

49.9

3-49

Page 120: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.1

PB TTi TURBINE INLET PRESSURE

HEASURED

RETRAN

ld82+OQItI

NWK0.

O

I

0I p

Tlute (sec)

Page 121: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.2

PB TT2 TURBINE INLET PRESSURE

HRog 8

ld8zioOn(

NWKQ.

oOlI

ooI p

TIME (SEC j

Page 122: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.3

PB TT3 TURBINE INLET PRESSURE

HEASURED

RETRAN

IIJ8Z

*aQa

NhlKIL

ONI

O

I p

TINE (SEC)

Page 123: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3-2.4

PB TT1 STEAM DOME PRESSURE

HEASURED

RETRN

OIQ

HNtL

hJ8Z~

z0

NlUKfL

00.

TIME (SEC)

Page 124: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2 5

PB TT2 STEAN DONE PRESSURE

}KASUREO

HNQ.

O

td8Z

xD

O~'f

NOlKQ.

O0

TIME (SEC}

Page 125: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.6

PB TT3 STEAN DOME PRESSURE

HEASURED

HNIL

0

Id8Z

z0

O~'f

U)IdKQ.

Oill

O0

TINE (SEC)

Page 126: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

PXGURE 3.2.7

PB TTi UPPER PLENUM PRESSURE

MEASURED

BETAAN

06

HNQ.

M8ZQ«f'fx0

NhJKQ.

00

Tree (sec)

Page 127: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.8

OO

PB TT2 UPPER PLENUM PRESSURE

H80.

0

ld8zZ0

O~ V

SlUKIl

Og

O0

nuc (sec)

Page 128: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.9

O0

PB TT3 UPPER PLENUM PRESSURE

HNQ

O

hl82x0

O~'i

SWKQ.

00

TINE fSEC)

Page 129: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.10

PB TTI UPPER PLENUM PRESSURE

MEAS. (FILTERED)

RETRAN

NIvPuKQ.

O0.0 0.6

TINE (SEC)1.2

Page 130: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2 11

0l0

PB TT2 UPPER PLENUM PRESSURE

HEAS. tfILTEREO)

RETRAH

HUjo

NUJPu

KIL

D.D 0.6Tzvc (sec)

Page 131: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.12

Oa

PB TT3 UPPER PLENUN PRESSURE

HEAS. (fILTERED)

RETRAH

0.0 0.6Tree (sec)

Page 132: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

3.2.4.2 Power an/ Reactivity Comparisons

The calculated core average neutron powers are compared to thenormalized core average LPRM signals for each of the three testsin Figures 3.2.13 through 3.2.15. In all three cases, the rates

of power change, timing trends and power peak magnitudes are ingood agreement with the measured data. The capability to predictthe power transients was further evaluated by comparing the area

under the power peak during the pressurization transients to thatpredicted by RETRAN. In the thermal margin calculation, thecritical power ratio is a function of. the area under the power

peak, not the magnitude of the peak. Tables 3.2.4 presents a

summary of the calculated and measured power peaks and the area

under the peaks for each test. A comparison of the time of the

calculated and measured power peaks is given in Table 3.2.5.

The LPRM detectors are located at four elevations (from bottom totop, levels A, B, C, D). Comparisons of calculated flux tomeasured flux (average of all LPRMs at a level) at each axiallevel are presented in Figures 3.2.16 through 3.2.27. The

calculated and measured peak values at each level is summarized

in Table 3.2.6. Timing trend and relative peak magnitude are

predicted well in the individual LPRM levels. This demonstrates

that RETRAN is capable of predicting accurately the power shape

change during rapid pressurization transient.

3-62

Page 133: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

The calculated net. reactivity, scram reactivity, and net

reactivity implied by the data are presented in Figures 3.2.28

through 3.2.30. The implied net reactivity was calculated using

an inverse point kinetic algorithm and the average of the

measured LPRM signals. Table 3.2.7 summarizes the calculated and

implied peak reactivities. The agreement between the calculated

and the implied net reactivities is good. The slightoverprediction of the peak reactivity for all three tests iscaused by the overprediction of the upper plenum pressure at the

time of peak reactivity. It is noted that the magnitudes of the

overpredictions in reactivity are small relative to those of the

neutron power. This is due to the extreme sensitivity of the

neutron power to .changes in reactivity close to the prompt

critical condition. The reactivity figures also show that thecalculated TT1 and TT2 net reactivity turns before scram occurs

while TT3 net reactivity is turned by scram. The same trends are

observed for the implied net reactivities.

3-63

Page 134: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 3.2.4

PEACH BOTTOM TURBINE TRIP TESTS

SUMMARY OF CORE AVERAGE PEAK NEUTRON 'POWER

PEAK NEUTRON POWER (NORM)

CALC. DATA O'IFF.AREA UNDER PEAK

CALC. DATA DIFF.

5.41'.68

5.39

4.83

4.54

4.90

12.0

3.1

10. 0

0.960

0.769

0 '170.743 3.5

0.669 7.2

0.888 8.1

TABLE 3.2.5

PEACH BOTTOM TURBINE TRIP TESTS

TIME (SEC) OF PEAK NEUTRON POWER

CALC. DATA

TT1

TT2

TT3

.774

.720

.702

.774

.726

.702

3-64

Page 135: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 3.2 '

PEACH BOTTOM TURBINE TRIP TESTS

SUMMARY OF LPRM LEVEL NEUTRON POWER PEAKS

CORE

D AVG.

Calculation

Data

4 Diff.

3 '23.48

6.90

4.98

4.46

11.'7

5.99

5.23

14.5

6.15

5.59

10.0

5.41

4.83

12.0

Calculation

Data

4 Diff.

3.49

3.52

-0.9

~4. 68

4.50

4.0

5. 09

4 '13 ~ 7

4.82

5.02

—.4.0

4.68

4.54

3.1

Calculation

Data

4 Diff.

3.84

3.68

4.3

5.42

4.83

12.2

6.06

5.45

11.2

5.74

5.47

4.9

5.39

4.90

10.0

3-65

Page 136: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 3.2.7

PEACH BOTTOM TURBINE TRIP TESTS

REACTIVITY SUMMARY

PEAK REACTIVITY ($ ) TIME OF PEAK (SEC)

CALC. DATA DIFF. CALC. DATA

0.804

0.780

0.836

0;776

0.767

0. 812

3.6%

1. 74

2.54

0.738

0.690

0. 678

0.744

0.696

0.660

3-66

Page 137: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.13

PB TTI CORE AVERAGE POWER

KW

0ll0bJNH

ZK0z

00.0 0.6

lIME (SEC)

Page 138: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.14

PB TT2 CORE AVERAGE PONER

HEASUREO

RETAAN

0M„NHJXK0z

0.0 0.6TIME (SEC)

1.2

Page 139: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.15

PS TT3 CORE AVERAGE PONER

HEASURED

RETRAN

KIU

0Q.

0hlNHJXK0Z

0.0 0.6

nate

(sec)i.2

Page 140: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.16

PB TTi LEVEL A AVERAGE LPRM

HEASURED

RHHAN

0hlNHJXK0Z

0.0 0.6TDIE (SEC)

Page 141: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.17

PB TTI LEVEL B AVERAGE LPRM

0Id„

HJZK0Z

0.0 0.6TIME (SEC)

Page 142: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.18

PB TTi LEVEL C AVERAGE LPRM

KLU

0Q.

0hlNHJXK0z

0.0 0.6TINE (SEC)

Page 143: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.19

PS TTi LEYEI 0 AYERAGE ARM

0WN

ZK0z

0.0 0.6TIME (SEC)

Page 144: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.20

PB TT2 LEVEL A AVERAGE LPRM

8SUAED

p AHRN

0ld

JZK0z

0.0 0.6nHE (sEc)

i.2

Page 145: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.21

PB TT2 LEVEI B AVERAGE ARM

REASUREDC

RETRAN

KIIJ

0Q.

0tdNHJZK0z

0.0 0.6TINE (SEC)

1.2

Page 146: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.22

PB TT2 LEVEL C AVERAGE LPRM

0tU„N

JXK0Z

0.0 0.6TIME (SEC)

Page 147: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.23

PB TT2 LEVEL D AVERAGE LPRM

0hlN

JXK0z

00.0 D.6

, TIME (SEC)

Page 148: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.24

PB TT3 LEVEL A AVERAGE LPRM

ntd

HJXK0Z

0.0 0.6TINE (SEC)

Page 149: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FXGURE 3.2.25

PB TT3 LEVEL B AVERAGE LPRM

ntdNH

XK0Z

0.0 0.6TIHE (SEC)

Page 150: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.26

PB TT3'LEVEL C AVERAGE LPRM

0lU

JXK0Z

0.0 0.6TINE (SEC)

Page 151: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.27

PB TT3 LEVEL D AVERAGE ARM

HEASURED

RETAN

KIUg0

0lU„N

JXK0z

0.0 0.6TINE (SEC)

1.2

Page 152: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.28

O

PB TTl REACTIVITY

HEASUAED

RET. TOTlL6RA

Cl

0

I-HQ)oH

0IUK

tll

OI

N

0I 0.0 0,6

TIME (SEC)f.2

Page 153: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.29

PB TT2 REACTIVITY

HEASURED

RET. TOTaL

ERAH

l0

0

HN>oHI"0

UJ

KOl

OI

8OI 0.0 0.6

TIME (SEC)

Page 154: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 3.2.30

0PB TT3 REACTIYITY

HEASURED

BET. TOTAL

a0

0-I-Hol>oI"0

IIJK

Ol

0I

0O

0.0 0.6Trwe (sec)

Page 155: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

4. 0 LICENSING BASIS ANALYSIS

A broad spectrum of transient events have been analyzed for WNP-2;

the results are presented in the Final Safety Analysis Report.

These events cover a wide range of scenarios and conditions

contributing to Technical Specification Limits. Most of these

transient events are not sensitive to changes in reload core

configuration, or are within the conservative limits established by

the original FSAR analy'sis. Changes in fuel design and core

configuration are usually bounded by the analysis of selected

limiting events. Based on previous analyses performed by vendors

for WNP-2 + and utilities on similar plants , the two most

limiting events requiring a reanalysis with each reload core are:

1. Load Rejection Without Bypass (LRNB)

2. Feedwater Controller Failure to Maximum Demand (FWCF)

The results of these transients generally determine Technical

Specification limits for minimum critical power ratio (MCPR). This

chapter describes the system analysis for these transients. The

full licensing FSAR analysis, the sensitivity analysis and the hot

channel analysis from which the operating limits are obtained willbe described in a separate applications topical report (to be

submitted later). The purpose of including this section is merely

to indicate the parameters that typically change in modelling

conservative FSAR transients and to show the WNP-2 model, with theparameters modified, indeed calculates conservative results.

4-1

Page 156: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

4.1 Licensing Basis Model

The licensing basis model described in this chapter is a generic

model using the Cycle 4 core configuratiop. For future applica-tions, specific reload configurations and plant parameters will be

used. These calculations are typical of planned WNP-2 reload

analyses.

The licensing basis RETRAN model is 'a modification of the WNP-2

best-estimate model. The modifications assure the cons'ervatism ofthe calculated results by using the values of the key parameters

which bound the expected operating range.

Table 4.1 compares licensing basis model. inputs with the nominal

values. The nominal values and conditions show conservatism in the

licensing basis modeling.

The licensing analysis performed in this report uses the end-of-cy-

cle exposure for the calculation of the nuclear design data. At

EOC, control rods are withdrawn from the core to counteract the

consumption of excess reactivity. The average control rod scram

distanc'e is greater with more rods withdrawn, so scram performance

degrades near the end of cycle. Scram reactivity insertion rate isthe dominant power reversal phenomenon for pressurization tran-sients; the most severe results occur at the maximum cycle

exposure, when scram performance is least effective.

4-2

l1

Page 157: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 4.1

INPUT PARAMETERS AND INITIALTRANSIENT CONDITIONSCOMPARISON OF LICENSING BASIS AND NOMINAL PLANT CONDITIONS

Parameter Nominal Licensin Basis

Core Exposure

Thermal Power (MWt)

Steam Flow (lbs/sec)

BOC — EOC

3323

3970.97

Feedwater Flow Rate (lbs/sec) 3970.97

EOC

3468

4161.11

4161.11

Feedwater Temperature ('F)

Vessel Dome Pressure (psia)

Rod Insertion Speed

Core Inlet Enthalpy (Btu/lb)Fuel Rod Gap Conductance

420'020

Measured

527.6

AxiallyNon-uniform

424

1035

Tech. Spec.

529.3

Uniform

Jet Pump Ratio 2.33

Safety/Relief Valves Relief Function (psig)

Fuel Radial Heat Generation Non-uniform Uniform

2.41

Group 1Group 1Group 2Group 2Group 3.Group 3Group 4Group 4Group 5Group 5OpeningClosingOpening

Opening SetpointClosing SetpointOpening SetpointClosing SetpointOpening SetpointClosing SetpointOpening SetpointClosing SetpointOpening SetpointClosing Setpoint,Stroke Time (sec)Stroke Time (sec)Delay Time (sec)

10761026108610361096104611061056111610660.070.00.3

11061056111610661126107611361086114610960.10.00.4

a. RETRAN will adjust this value at initialization to completethe heat balance.

4-3

Page 158: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 4.1

INPUT PAEVLHETERS AND INITIALTRANSIENT CONDITIONSCOMPARISON OF LICENSING BASIS AND NOMINA) PLANT CONDITIONS

(Continued)

Parameter Nominal Licensin Basis

Safety/Relief Valves Safety Function (psig)Group 1Group 1Group 2Group 2Group 3Group 3Group 4Group 4Group 5Group 5OpeningClosingOpening

Opening SetpointClosing SetpointOpening SetpointClosing SetpointOpening SetpointClosing SetpointOpening SetpointClosing SetpointOpening SetpointClosing SetpointStroke Time (sec)Stroke Time (sec)Delay Time (sec)

1150112611751151

~ . 1185116111951171120511810.070.00.3

11771153118711631197117312071183121711930.10.00.4

Reactor Protection System

High Flux Scram, 4 NBR 118

High Vessel Dome Pressure 1037Scram (psig)

APRM Thermal Trip (4 NBR 113.5at 1004 Core Flow)

Low, Water Level (L3), in 13above instrument zero

Turbine Stop Valve Closure 5Position Scram (4 Closed)

MSIV Closure Position Scram 10(4 Closed)

126 2

1071

122. 03

7.5

10

15

4 4

Page 159: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 4.1

INPUT PAEQMETERS AND INITIALTRANSIENT CONDITIONSCOMPARISON OF LICENSING BASIS AND NOMINAL PLANT CONDITIONS

(Continued)

Parameter

Containment Isolation and Pump TripLow Water Level (L2), inbelow instrument zero

Low Pressure in Steamline(psig)

RPT High Vessel Pressure(psig)

RPT Delay Time (msec)

High Water Level — Turbine andFeedwaters Pump Trip (inchesabove instrument zero)

Recirculation Pump Moment ofInertia (10~ ibm — ft~)

Nominal

50

831

" 1135

97

54.5

2.27

Licensin Basis

70

795

1170

190

59.5

2.47

I 4-5

Page 160: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

The analyses. in this report used the technical specification limitson control rod movement versus time. Table 4.2 shows the assumed

rod motion following scram+. Actual plant performance data shows

more rapid insertion.

TABLE 4.2Technical Specification Limits

Maximum Control Rod Insertion Time to PositionAfter Deenergization of Pilot Valve Solenoids

Position Inserted fromFull Withdra Notch Number

Time~Sec

6.254'8

'754'7.924'9.584'45)(39)(25)(05)

0.4300.8681.9363.497

The initial steam flow in the licensing basis model is conserva-

tively set at 1054 NBR. For pressurization transients, higher

initial steam flow results in a more rapid pressurization and

higher maximum pressures. The initial power is set to 104.44 NBR

which is consistent with the maximum steam flow of 1054 NBR. The

initial reactor dome pressure is conservatively set to a higher

value of 1035 psia, allowing less analytical margin to the safetylimit.

Unless the problem statepoint requires otherwise, the core flow isinitialized at the rated capacity of 108.5 mlb/hr.

4-6

Page 161: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

The RETRAN model uses a fuel rod gap conductance that remains

constant during the transient. The actual gap conductance increases

during power increase transients due to fuel pellet expansion.

Higher gap conductance will lead to faster heat transfer from the

fuel to the coolant, which generates more steam voids. The fasterconversion of fuel stored energy to steam voids in the core helps

to mitigate the transient due to negative void reactivity feedback.

Therefore, the use of a constant gap conductance is conservative

for system analyses involving power increases such as pressuriza-

tion transients.

Conservative equipment design specifications and plant technicalspecification limits are used in the RETRAN model input. These

include relief valve opening response, closure rates for main steam

isolation valves, turbine stop and control valves, reactorprotection system setpoints and delays.

A conservative moment of inertia for the recirculation pump is used

in the licensing basis model. A larger value results in longer

coastdown time after pump trip, delaying the effect of void

formation in the core and increasing the process of void collaps-ing. Positive reactivity effects are magnified by this conserva-

tism.

l 4-7

Page 162: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

4.2 Load Rejection Without Bypass (LRNB)

Whenever external disturbances result in loss of electrical load on

the generator, fast closure of the turbine control valves (TCV) isinitiated. The turbine control valves are required to close as

rapidly as possible to minimize overspeed of the turbine generator

rotor. Closure of the main turbine control valves will cause a

sudden reduction in steam flow which results in an increase insystem pressure and reactor shutdown.

4.2.1 Sequence of Events

A loss of generator electrical load at high power with bypass

failure produces the sequence of events listed in Table 4.3.

The closure characteristics of the turbine control valves are

assumed such that the turbine control valves operate in the fullarc (FA) mode and have a full stroke closure time, from fully open

to fully closed, of 0.15 seconds. Sensitivity study" has shown

that the most severe initial condition for this transient is the

assumption of full arc operation at 1054 NBR steam flow. The plantvalue of 0.07 seconds given in Table 4.3 represents actual expected

closure time, since the turbine control valves are partially open

during normal operation.

4-8

Page 163: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 4.3

Sequence of Events for LRNB Transient

Time-Sec Event

0.0 Turbine generator power load unbalance(PLU) devices trip to initiate turbinecontrol valve fast closure when loss ofelectrical load is detected.

0.0 Turbine bypass valves fail to operate

0.0

0.0

0.07

0 '9

Fast turbine control valve closureinitiates scram tripFast turbine control valve closure ini-tiates a recirculation pump trip (RPT)

Turbine control valves closed

Recirculation pump motor/circuit breakersopen, causing decrease in core flow

0.28

1. 35

1. 40

1.44

1.50

1.63

4.43

5.0

Control rod insertion starts (scram tripsignal at 0 sec, RPS delay : 0.08 sec,solenoid deenergizing delay : 0.2 sec)

Group 1 relief valves actuated

Group 2 relief valves actuated

Group 3 relief valves actuated

Group 4 relief valves actuated

Group 5 relief valves actuated

Group 5 relief valves close

End of simulation

4-9

Page 164: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

4.2.2 Results of LRNB RETRAN Analysis

The WNP-2 LRNB analysis at the end of cycle 4 conditions was

performed with the licensing basis model. Since most. of the fuelin the core at EOC4 was the Advanced Nuclear Fuels (ANF) design,

the average fuel parameters in the best-estimate model were changed

from the GE design to the ANF design. The fast closure of the

turbine control valves (TCV) is simulated by linearly decreasing

the flow at fill Junction 380 (representing steam flow to the

turbine) to zero at 0.07 seconds. Rapid closure of the TCV

initiates a scram.

Several key results of this analysis were compared with analyses ofrecord performed by Advanced Nuclear Fuels (ANF). Zt should be

noted that both sets of analyses were performed conservatively.This comparison is intended to show the similarity of resultsrather than to demonstrate analytical accuracy. The accuracy ofthe WNP-2 RETRAN model is demonstrated by the benchmarks of power

ascension tests reported in Section 3.1.

The pressure in the steam line increases rapidly as shown in Figure

4.2.1. The acronym "LRNB LBM" in the figure stands for Load

Rejection without Bypass Licensing Basis Model. Figure 4.2.2 shows

the vessel steam flow. The flow oscillations are caused by the

pressure wave propagated upstream to the reactor vessel. The

decreased steam flow at about 0.4 seconds causes the rapid

4-10

Page 165: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

pressurization of the steam dome and inside the core as shown inFigures 4.2.3, 4.2.4 and 4.2.5. After 0.42 seconds, the net

reactivity becomes positive because the positive void reactivityexceeds the negative scram reactivity. Zt peaks with a value of

approximately 0.76$ at 0.78 seconds then begins to decrease as the

scram reactivity increases, as shown in Figure 4.2.6.

The ANF prediction~~ of dome pressure during the transient is also

shown in Figure 4.2.3. The WNP-, 2 RETRAN model predicts a pressure

which is. higher than that predicted by ANF throughout the tran-sient.

The reactor power, shown in Figure 4.2.7, increases rapidly and

reaches a peak value of 3984 NBR at 0.89 seconds then rapidlydecreases as Doppler feedback and scram reactivity terminate the

power excursion. ANF's prediction of core power is also shown inFigure 4.2.7. The power history predicted by RETRAN peaks earlierin the transient than the ANF prediction at a lower maximum power

level. The earlier power peak can be attributed in part to the

higher pressure throughout the transient. The lower magnitude ofthe peak is likely to be caused by differences in neutronics

calculations leading to differences in kinetics data and cross

sections.

Figure 4.2.8 shows the core average clad surface heat flux. The

initial reduction in clad-to-coolant heat transfer is caused by the

4-11

Page 166: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

rise in saturation temperature of the liquid phase due to initialpressure rise in the core. As the power rises, the heat fluxquickly reverses and begins to rise, reaching a peak of 133.44 ofthe rated power value at 1.1 seconds. Following the peak, the heat

flux decreases as the core power decreases with a delay determined

by the fuel rod time constant. ANF's calculation of core average

heat flux is also shown in Figure 4.2.8. The two models predictconsistent trends in heat flux and agree closely in the later partof the transient.

t

The water level and feedwater flow during LRNB are shown in Figures

4.2.9 and 4.2.10. When the TCV fast closure calls for scram, the

feedwater controller reduces the water level setpoint by 18 inches.

It then responds to this setpoint change by reducing feedwater

flow. Pressure variations, steam flow oscillations, and void

collapse contribute to the changing water level throughout. the

remainder of the transient.

Figures 4.2.11 and 4.2.12 give the void fractions at mid-core and

core exit. Core voids collapse as the steamline pressure wave .

reaches the core. For the remainder of the transient, variationsin steam flow and pressure drive oscillations in the void fraction.Figure 4.2.13 shows the recirculation flow. The recirculation pumps

start to coast down after RPT initiation at 0.19 seconds, causing

flow reduction in the core as shown in Figure 4.2.14.

4-12

Page 167: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.1

WNP-2 LRNB LBM — STEAMLINE PRESSURE

T IHE (SEC)

Page 168: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.2

WNP-2 LRNB LBM — VESSEL STEAM FLOW

2TIHE (SEC)

Page 169: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.3

HNP-2 LANB LBM — OOME PRESSURE

+ PACQI - VOL $ 4

)( AMP CALO%ATION

Oa0

llJKDNUltaboo[frs

Q

~I yTIME (SEC)

Page 170: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.4

NNP-2 LRNB LBM — PRESSURE (MID-CORE)

0N

MUlQ

UJKU)Ntuoo0.'eo

Q%I

OO0~I

O 2TIME (SEC)

Page 171: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.5

WNP-2 LRNB LBM — PRESSURE (CORE EXIT)

OOa~I

IdKDQQejo(fPe

g rl

OOO~i e

TIME (SEC)

Page 172: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2-6

NNP-2 LRNB LBM — TOTAL REACTIVITY

+ TQZAL REACTIVITY

I-H»+IHlO

WK

TIHE (SEC)

Page 173: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.7

HNP-2 LRNB LBM — CORE POHER

+ CORC PNKA

g ANF CALCAATIOtl

KlU

0Q.o

a

0TIME (SEC)

Page 174: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.8

HNP-2 LRNB LBM — CORE AVERAGE HEAT FLUX

KezR

XoDel

b.

O4O

TIHE (SEC)

Page 175: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.9

OrWNP-2 LRNB LB M — LIQu XO LEVEL

2H

tU

gO~II

0H3UM

O"oTIME [SEC)

Page 176: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.10

WNP-2 LRNB LBM — FEEDWATER FLOW

TIME (SEC)

Page 177: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.11

WNP-2 LRNB LBM — VOID FRAC (MID-COREJ

+ VOIO FRAC VQ..5$

zOHI-

Kh.

0OgQ ~

4OTIME (SEC)

Page 178: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2-12

HNP-2 LRNB LBM — VOID FRAC (CORE EXIT)

O

z0HI-O4oglQ.o

0MO

OQ

OoTINE (SEC)

Page 179: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.13

WNP-2 LRNB LBM — RECIRCULATION FLOW

X0<o

OC7 0

TIME (SEC)

Page 180: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.2.14

WNP-2 LRNB LBN — CORE INLET FLOW

O4

0

ORo

- TIHE (SEC)

Page 181: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

4.3 Feedwater Controller Failure to Maximum Demand (FWCF)

This analysis postulates the feedwater controller failure causing

an increase in feedwater flow. The most severe event of this type

is a failure at maximum flow demand. The feedwater controller isforced to its upper limit at the beginning of the event.

4.3.1 Sequence of Events

When feedwater flow exceeds steam flow, the water. level rises.With the feedwater controller disabled, the water level eventually

rises to the high-level reference point, at which time the

feedwater pumps and the main turbine are tripped and a scram isinitiated. Table 4.4 lists the sequence of events for thistransient.

The transient is simulated by programming an upper limit failure inthe feedwater system such that 146 percent feedwater flow occurs atthe design pressure of 1020 psig.

An increase in feedwater flow will cause a corresponding drop infeedwater temperature. However, the relatively large time constant

of the feedwater heaters (order of minutes) plus the flow transporttime (about 10 seconds from heaters to vessel and about 3 seconds

from sparger to core) delay the cold water effects until the event

has run its course and no further consequences are expected.

4-27

Page 182: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

Feedwater temperature is therefore assumed to remain constant.

4.3.2 -Results of FWCF RETRAN Analysis

The FWCF event was analyzed at EOC4 conditions using the licensingbasis model. As in the LRNB case, the fuel parameters were changed

to reflect the ANF design.

The feedwater flow is shown in Figure 4.3.1.. The increased feedwa-

ter,. after a transport delay through the lower downcomer and

recirculation loops, causes an increase in the core inlet subcool-

ing as shown in Figure 4.3.2. The reactor water level alsoincreases as the feedwater flow increases as shown in Figure 4.3.3.The water level reaches the high level setpoint at approximately17.7 seconds, causing a turbine trip (Figure 4.3.4). The vessel

pressure begins to increase after the closure of the turbine stop

valves. The turbine bypass valves open (Figure 4.3.5). For highinitial power levels the bypass, which has a design capacity of 254

of rated steam flow, will not divert all of the steam flow and thepressure increases as shown in Figure 4.3.6. As the pressure

increases, the core void collapses. The positive void reactivityfrom core pressurization is initially high enough to overcome the

negative scram reactivity (Figure 4.3.7). A rapid increase inpower begins at 18.1 seconds (Figure 4.3.8), reaching a peak of2454 NBR at 18.6 seconds. Trailing the reactor power, the core

average heat flux peaks at 1244 NBR at 18.8 seconds (Figure 4.3.9).

4-28

Page 183: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

The relief valves open after the vessel pressure reaches the

opening setpoints (Figures 4.3.10 through 4.3.14) and additionalsteam is relieved to the suppression pool. The vessel pressure

begins to decrease rapidly. Figure 4.3.15 shows the vessel steam

flow. The fast closure of the turbine stop valves generate pressure

waves which lead to the oscillations in steam flow. The core inletflow and exit flow are shown in Figures 4.3.16 and 4.3.17. Due tothe coastdown of the recirculation pumps, the core flow reduces

near the end of the transient (Figure 4.3.18). Figures 4.3.19 and

4.3.20 show the mid-core and core exit pressures. Figures 4.4,.21

and 4.4.22 show the mid-core and core exit void fractions. The

transient is terminated by the Doppler feedback and the control rod

scram.

The RETRAN results were not compared with ANF analyses of record

for the FNCF transient because different initial conditions were

assumed in the two analyses. The ANF analysis assumed an initialpower level of 474 of rated, while the example calculation reported

here was performed at an initial power level of 104.44 of rated.

4-29

Page 184: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

TABLE 4.4

Secpxence of Events for Feedwater Controller Failure

Time-Sec Event

Initiate simulated failure of 146% upper limiton feedwater flow

17.60

17.66

17. 67

L8 vessel Level setpoint trips feedwater pumps

L8 vessel level setpoint trips main turbine.Turbine bypass operation initiatedReactor scram trip actuated from main turbinestop valve position switches (104 closure)

17. 86

19. 12

19. 33

19. 39

19 '719 70

20.56

20.90

21.74

23.49

24.0

Group 2 relief valves

Group 3 relief valves

actuated

actuated

Group 4 relief valves actuated

Group 5 relief valves actuated

Group 5 relief valves start to close

Group 4 relief valves start to close

Group 3 relief valves start to close

Group 2 relief valves start to close

End of simulation

Recirculation pump trip (RPT) actuated by stopvalve position switches (104 closure)

Group 1 relief valves actuated

4-30

Page 185: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.1

WNP-2 FWCF LBM — FEEOWATER FLOW

TINE (SEC)je

Page 186: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.2

HNP-2 FHCF LBM — CORE INLET SUBCOOLING

S

I-Q

NoH00OQ

N

TIME (SEC)f4

Page 187: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.3

WNP-2 FWCF LBM — LIQUIO LEVEL

mg

0HD

H

TIME (SEC)f4

Page 188: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4 ' '

HNP-2 FHCF LBM — TURBINE STEAM FLQN

TIHE (SEC)

Page 189: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.5

WNP-2 FWCF LBM — TURBINE BYPASS FLOW

KSzR

xO

<or

TIME tSEC)

Page 190: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

PXGURE 4.3.6

WNP-2 FWCF LBM — DOME PRESSURE

lUKMQ+o0:roQ

OOO~I y

TIHf (SEC)ie

Page 191: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3-7

WNP-2 FWCF LBM — TOTAL REACTIVITY

HD>oHI-O

QJK

R

I O

TIME (SEC)

Page 192: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.8

WNP-2 FWCF LBM — CORE POWER

KllJXOQ

0TIHE (SEC)

Ce

Page 193: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.9

WNP-2 FWCF LBM — CORE AVERAGE'HEAT FLUX

. TIME tSEC)i4

Page 194: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3-10

NNP-2 FHCF LBM — GROUP l. SRV FLOW

. TIHE (SEC)

Page 195: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.11

WNP-2 FWCF LBM — GROUP 2 SRV FLOW

30<o

TIME (SEC)

Page 196: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.12

WNP-2 FWCF LBM — GROUP 3 SRV FLOW

04o

TIME (SEC)

Page 197: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.13

WNP-2 FWCF LBM — GROUP 4 SRV FLOW

TIME (SEC)

Page 198: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4 ' '4

WNP-2 FWCF LBM — GROUP 5 SRV FLOW

TIHE (SEC)

Page 199: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.15

WNP-2 FWCF LBM — VESSEL STEAM FLOW

ALON ~ SfO

. TIHE (SEC)

Page 200: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.16

WNP-2 FWCF LBM — CORE INLET FLOW

TIHE (SEC)14

Page 201: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.17

O~I

WNP-2 FWCF LBM — CORE EXIT FLOW

mz1C

'0

0h.

O4O

TIHE (SEC)$4

Page 202: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.18

WNP-2 FWCF LBM — RECIRCULATION FLOW

Kmz

TAHE (SEC)

Page 203: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.19

WNP-2 FWCF LBM — PRESSURE tMED-CORE)

OO0

tlJKlO0)~OQPoQ

OA

O

'IME (SEC)

Page 204: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.20

NNP-2 FHCF LBH — PRESSURE (CORE EXIT)

HMQ

lUKD0)MQJ

0gasg tl

OOe~I 0

TIHE (SEC)

Page 205: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FIGURE 4.3.21

WNP-2 FWCF LBM — VOID FRAC (MID-CORE)

zOHIO

Kh.

0H0

aOO

TINE (SEC)

Page 206: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

FXGURE 4.3.22

WNP-2 FWCF LBM — VOID FRAC (CORE EXIT)

Z0HI-O

Kh.

0H0

O0O

O

TIME (SEC)

Page 207: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

4.4 Summary of Transient Analysis

The key transient simulation„. results for the two MCPR limitingtransients as calculated by RETRAN are summarized in Table 4.5.

TABLE 4.5

Summary of Thermal-Limiting Transient Results

LRNB FWCF

Max Power (%NBR)

Time at'ax power (seconds)

Max core avg heat flux (4NBR)

Time at max heat flux (seconds)

Max dome pressure (psia)

Time at max dome pressure (sec)

398

0.89

133

1207

1 ~ 9

245

18.6

124

18.8

1175

19.5

4-53

Page 208: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

II

I

I

I

Page 209: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

5.0 SUMMARY AND CONCLUSIONS

Benchmark analyses covering specific Power Ascension Tests as

described in Section 3.1 demonstrate the capability of the WNP-2

RETRAN model to predict core and system behavior during normal

operation and mild transients. These analyses validate the

modeling of the feedwater and pressure regulator control systems

and the performance of the recirculation pumps, jet pumps, and

steam lines as modeled for,WNP-2.

Benchmark analyses covering the turbine trip tests performed atPeach Bottom 2 at the end of Cycle 2 as described in Section 3.2

demonstrate RETRAN's ability to model conditions more challengingthan the WNP-2 startup tests and the Supply System technicalstaff's competence to perform these analyses. These analyses

validate the capabilities of the modeling beyond the normal

operating envelope of the reactor.

Example calculations covering typical limiting transients as

reported in Chapter 4 demonstrate the WNP-2 RETRAN model's

ability to predict system performance under conditions which

challenge operating limits. These analyses show consistency withexisting analyses of record and validate the Supply. System

technical staff's ability to formulate and analyze limitingtransient events.

5-1

Page 210: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

The analyses performed in this report demonstrate the ability ofthe WNP-2 RETRAN model and the qualifications of the Supply

System technical staff to predict the course of a wide variety oftransient events. The model is applicable to the evaluation ofnormal- and anticipated operation for plant operational support

and core reload analysis.

5-2

Page 211: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

6.0 REFERENCES

1 ~

2 ~

J.H." McFadden et al., "RETRAN-02 — A Program for TransientThermal-Hydraulic Analysis of Complex Fluid Flow Systems,"EPRI NP-1850-CCM-A, Revision 4, Volumes I-III, Electric PowerResearch Institute, November 1988.

B.M. Moore, A.G. Gibbs, J.D. Imel, J.D. Teachman, D.H.Thomsen, and W.C. Wolkenhauer, "Qualification of Core PhysicsMethods for BWR Design and Analysis," WPPSS-FTS-127,Washington Public Power Supply System, March 1990.

3. J.A. McClure et al., "SIMTRAN-E — A SIMULATE-E to RETRAN-02Data Link," EPRI NP-5509-CCM, Electric Power Research Insti-tute, December 1987.

4. C.W. Stewart et al.,"VIPRE-01 — A Thermal-Hydraulic Code forReactor Cores," EPRI NP-254-CCM-A, Revision 3, Volumes I-III,Electric Power Research Institute, August 1989.

D.L. Hagerman, G.A. Reymann, and R.E. Manson, "MATPROVersion 11 (Revision 2): A Handbook of Materials Propertiesfor Use in, the Analysis of Light Water Reactor Fuel RodBehavior," NUREG/CR-0479, TREE-1280, Revision 2, IdahoNational Engineering Laboratory, August 1981.

6. "WREM, Water Reactor Evaluation Model, Revision 1," NUREG-75/065, U.S. Nuclear Regulatory Commission, May 1975.

7. WPPSS Nuclear Plant 2 Updated Final Safety Analysis Report,Washington Public Power Supply System, 1989.

8.

9.

"Qualification of the One-Dimensional Core Transient Modelfor Boiling Water Reactors," NEDO-24154, Volume 1, GeneralElectric Company, October 1978.

Letter, '. Armenta (GE) to W.C. 'olkenhauer (WPPSS),"Instruction for Use of 4-Quadrant Curve," dated March 26,1985.

10. "Recirculation System Performance," Publication 457HA802,General Electric Company, September 1976.

11. B.J. Gitnick et al., "FIBWR — A Steady-State Core FlowDistribution Code for Boiling Water Reactors," EPRI NP-1924-CCM, Electric Power Research Institute, July 1981.

12. R.E. Polomik and S.T. Chow, "Hanford-2 Nuclear Power StationControl System Design Report," GEZ-6894, General ElectricCompany, February 1980.

6-1

Page 212: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

13 ~

14.

15.

16.

17.

18.

19.

20.

"Turbine Dynamic Response Parameters," Publication CT-24659,Westinghouse Electric Corporation, August 1979.

M. Edenius, A. Ahlin, and H. Haggblom, "CASMO-2, A FuelAssembly Burnup Program, User's Manual," STUDSVIK/NR-81/3,Studsvik Energiteknik AB, March 1981.

D.M. Ver Planck, W.R. Cobb, R.S. Borland, B.L. Darnell, andP.L. Versteegen, "SIMULATE-E (Mod. 3) Computer Code Manual,"EPRI NP-4574-CCM, Part II, Electric Power Research Institute,September 1987.

J.D. Atchison, "Final Report . on Anticipated TransientsWithout Scram Analyses for the WNP-2 Nuclear Power Plant," EIInternational Inc., December 1989.

"Power Ascension Test Program," WNP-2 Plant Procedure Manual,Section 8.2, Washington Public Power Supply System, 1984.

L.A. Carmichael and R.O. Niemi, "Transient and StabilityTests at. Peach Bottom Atomic Power Station Unit 2 at End ofFuel Cycle 2," EPRI NP-564, Electric Power ResearchInstitute, June 1978.

K. Hornyik and J.A. NaSer, "RETRAN Analysis of the TurbineTrip Tests at Peach Bottom Atomic Power Station Unit 2 at Endof Cycle 2," EPRI NP-1076-SR, Electric Power Research Insti-tute, April 1979.

A.M. Olson, "Methods for Performing BWR System TransientAnalysis," PECO-FMS-0004-A, Philadelphia Electric Company,November 1988.

21.

22

'.H. Larsen, "Core Design and Operating Data for Cycles 1 and2 of Peach Bottom Unit 2," EPRI NP-563, Electric PowerResearch Institute, June 1978.

J. E. Krajicek, "WNP-2 Cycle 2 Plant Transient Analysis",XN-NF-85-143, Exxon Nuclear Co., Inc., Richland, WA, December1985.

23 ~

24.

25.

J. E. Krajicek, "WNP-2 Cycle 5 Plant Transient Analysis",ANF-89-01, Rev. 1, Advanced Nuclear Fuels Corp., Richland,WA, March 1989.

S. L. Forkner, et al., "BWR Transient Analysis ModelUtilizing the RETRAN Program", TVA-TR81-01, Tennessee ValleyAuthority, December 1981.

WPPSS Nuclear Plant 2 Technical Specifications, Docket No.50-397.

6-2

Page 213: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

26. J. E. Kraj icek and M. J. Hibbard, "WNP-2 Cycle 4 PlantTransient Analysis", ANF-88-01, Advanced Nuclear Fuels Corp.,Richland, WA, January 1988.

6-3

Page 214: DISCLAIMER This report was prepared by the Washington Public Power Supply System ("Supply System" ) for submittal to the Nuclear Regulatory Commission, NRC. The information contai

I

I