104
Toronto Tower Foundation Stabilizing a Landslide Contaminated Soils High Capacity Rock Anchors for Bluestone Dam Safety Program DEEP FOUNDATIONS THE MAGAZINE OF THE DEEP FOUNDATIONS INSTITUTE MAR/APR 2014 DFI I O T N A S D I N N S U T O I F T U P E T E E D

DFI Magazine March/April 2014

Embed Size (px)

DESCRIPTION

DFI Magazine released in march 2014.

Citation preview

Page 1: DFI Magazine March/April 2014

Toronto Tower Foundation

Stabilizing a Landslide

Contaminated Soils

High Capacity Rock Anchors for Bluestone Dam Safety Program

DEEP FOUNDATIONSTHE MAGAZINE OF THE DEEP FOUNDATIONS INSTITUTE MAR/APR 2014

DFIIOT NA SD INN

SU TO IF T

UPE T

E E

D

Page 3: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 3

49 Member Profile: Marine Lasne, Soletanche Freyssinet — Sustainability Crusader

55 Soil Mixing in Contaminated SoilsKen Andromalos, P.E., and Daniel Ruffing, EIT

A thorough overview of the history

of working with contaminated sites

in the U.S. Soil mixing originated in

the late 1990s, with the first non-

structural containment wall to

isolate PCBs. Government

sponsored sites followed, and

equipment was developed over the

years to deal with varying

contaminants. Cost-efficiency

improved as well. In-situ

stabilization and in-situ treatment

are defined as well as other kinds of

treatment commonly used today.

12 Jeff Hopple, P.E.

The U.S. Army Corps began its safety assurance program in 2001 at the Bluestone Dam

in West Virginia. The multiple-phase construction project is intended to upgrade the

capacity and the stability of the dam to meet the probable maximum flood. The Corps

chose Brayman Construction to perform Phase 2B, which involved installing 216 high

capacity rock anchors, 57 of which were meant to resist overturning. The other 159

rock anchors were installed on the dam face at an angle to resist sliding. Phase 2B also

included a steel platform to gain access to the spillway anchors.

Bluestone Dam Safety Assurance Program: An OPA Runner Up

DFIIOT NA SD INN

SU TO IF T

UPE T

E E

D

DEEP FOUNDATIONSThe Magazine of the Deep Foundations Institute (DFI) is published bimonthly by DFI.

326 Lafayette Avenue, Hawthorne, NJ, 07506, USAT: 973.423.4030 | F: 973.423.4031Email: [email protected]

Executive DirectorTheresa [email protected]

Executive EditorsVirginia [email protected] [email protected]

Managing Editor EmeritusManuel A. Fine, [email protected]

Advertising ManagerKarol Paltsios, [email protected]

DFI Executive CommitteePresident, Robert B. Bittner

Vice President, John R. Wolosick

Secretary, Matthew Janes

Treasurer, Dan Brown

Past President, James A. Morrison

Other TrusteesPatrick Bermingham

David Borger

Gianfranco Di Cicco

Khaldoun Fahoum

Rudolph P. Frizzi

Frank Haehnig

Bernard H. Hertlein

Gerry Houlahan

James O. Johnson

Douglas Keller

Samuel J. Kosa

K.S. Rama Krishna

Marine Lasne

J. Erik Loehr

Raymond J. Poletto

Michael H. Wysockey

CONTENTS FEATURES

Page 4: DFI Magazine March/April 2014

AMERIC

AN P

ILEDRIVING EQUIPMENT

J&M

FO

UNDATION EQUIPM

ENT

AMERIC

AN P

ILEDRIVING EQUIPMENT

J&M

FO

UNDATION EQUIPM

ENT

C

M

Y

CM

MY

CY

CMY

K

AD40V4.0DFI.pdf 1 9/30/2013 10:22:06 AM

Page 5: DFI Magazine March/April 2014

CONTENTS FEATURES

DEEP FOUNDATIONS • MAR/APR 2014 • 5

Departments

Are Your Young Engineers Fired Up and Enthusiastic? . . . . . . . . . . . . . . . . . . . . . 7

It’s All About Communication . . . . . . . . 9

A report on the recent Winter Planning Meeting; news on upcoming DFI activities including the DFI-EFFC International Conference on Deep Foundations in Sweden, SuperPile ’14 in Cambridge, Mass., International Workshop on Micropiles in Krakow and the 39th Annual Conference in Atlanta; an update on the DFI Journal and more.. . . . . . . . 21

DFI Middle East. . . . . . . . . . . . . . . . . . 41

. . . . 45

Updates on the activities of several DFI Technical Committees . . . . . . . . . . . . . 71

News about people, companies and products . . . . . . . . . . . . . . . . . . . . . . . 92

. . . . . . . . . . . . . . . . . . . 102

. . . . . . . . . . . . . . . . . . . . 102

PRESIDENT’S MESSAGE

EXECUTIVE DIRECTOR UPDATE

DFI ACTIVITIES

REGIONAL REPORT

EDUCATIONAL TRUST REPORT

TECHNICAL ACTIVITIES UPDATE

DFI PEOPLE AND COMPANIES

CALENDAR

AD INDEX

FINDING COMMON GROUND

DFI is an international association of

contractors, engineers, suppliers,

academics and owners in the deep

foundations industry. We find common

ground through networking, education,

communication and collaboration. Our

multi-disciplinary membership creates a

consensus voice and a common vision for

continual improvement in the planning,

design and construction of deep

foundations and excavations.

Become a Member of DFI at www.dfi.org

77 Deep Excavation Support at Toronto’s Shangri-LaBrain Isherwood, MICE, FCSCE, P.Eng.; Tara Brown, P.Geo.; and Jenny Earle, EIT

The Shangri-La hotel and tower was built

at a challenging Toronto site, surrounded

by other city buildings, and over an

active subway, highly sensitive to move-

ment during construction. The risks to

the subway were major, and Isherwood

Associates had to find the best shoring

solution. After evaluating the situation,

they recommended that the owner give

up part of the eight-level basement so

the engineers could provide a more uni-

form movement pattern along one wall.

85 Seepage Control, Cutoff Walls Manual: A Progress Report David B. Paul

The U.S. Army Corps of

Engineers is working on a

manual about seepage control

and cutoff walls, with input

from DFI. This preview of the

contents includes a summary of

the Corps’ history with cutoff

walls and the engineering

thinking involved in their

design.

63 Landslide with Steel H-PilesKessi E. Zicko, P.E., Paul J. Lewis, P.E., and

Robert E. Johnson

A landslide along a Pennsylvania state

highway caused concern, and PennDOT

retained Gannett Fleming to evaluate

methods to stabilize the slope. They chose

driven steel H-piles based on construction

costs and site impacts. The final design

minimized land disturbance by using an

existing, inactive roadbed along the toe of

the embankment for the pile footprint. This

design avoided wetlands, habitat for the

timber rattle snake, and an area of

archaeological interest.

Stabilizing the Mill Creek

®

Page 6: DFI Magazine March/April 2014

Watson Philosophy:While it is true that “making hole” basically translates to “making money”,it is the overall time on the job that translates into profitability.From the moment a rig leaves the yard, the clock is ticking on your profits. Watson rigsnot only excel at the drilling itself, but are specifically designed to reduce the time spentoutside the hole.

The 4400 targets big diameter rock drilling, but minimal setup and cycle times are two keys to its success:• Remote controls and hydraulic pins keep setup/teardown to under an hour.• Continuous Torque rotary and variable speed hoist reduce cycle time.• New interchangeable low headroom option and superior mobility make short work of rugged powerline jobs.

Minimizing the time you spend NOT turning to the right.

Productivity.

Short Mast configuration now available.

Best in the World • Made in America

800-927-8486 • Fort Worth, Texas

Watson_4400_DFI_ad_2013.indd 1 1/25/13 7:48 AM

Page 7: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 7

This experience conveyed the

message that my creative ideas

were valued and respected

on the same level as my

senior associates, and added

confidence in my work and a

sense of satisfaction. From

that point, there was no look-

ing back. I knew I was in the

right field and was truly mak-

ing a significant difference.

I cite this example to

illustrate the importance of

tapping into the creative

spirit in all your staff and

especially your young

engineers. Seek out oppor-

tunities for them to use their

creative talents and when

they do, treat that talent with

respect. They can provide a

fresh perspective, one that

can be very rewarding to your company and

very important to them personally.

n a previous message, I wrote that if we

want to bring bright, young engineers

into the deep foundations industry and

keep them, we must convey to them our

enthusiasm and excitement about

construction in general and our industry in

particular. I cannot tell you how many

times in the last 40 years doctors, dentists

and attorneys have told me that they

started out in engineering and then

changed careers. Even in my own

engineering career, after I was out of college

a few years, I thought about getting a

graduate degree in another field and

leaving construction. It was not because I

didn’t find the work engaging. I was

working on very interesting marine

construction projects both overseas and in

the Pacific Northwest, and had a broad

range of assignments that were challenging

and provided valuable training. It was

more a feeling that I was not using my

creative talents. And when I did, they were

not being valued and respected.

It was only after the upper management

of the company I was working for at the

time, Riedel International, began involving

me in their problem-solving sessions, or

what they referred to as “brainstorming

sessions,” that I felt my creative talents were

Are Your Young Engineers Fired Up and Enthusiastic?

I Robert B. Bittner, [email protected]

DEEP FOUNDATIONS • MAR/APR 2014 • 7

PRESIDENT’S MESSAGE

of value and encouraged by my

associates. These sessions gener-

ally focused on two types of

challenges. The first was to

develop concepts for giving our

company a competitive edge on a

given project that we were

pursuing. The advantage could

be in the form of an

innovative way to perform

the work or developing a

piece of equipment that was

more efficient than our

competitors’. The second

type of challenge addressed

in these sessions involved a

specific problem or oppor-

tunity on a project already

under construction. Typi-

cally, I participated in these

sessions with the upper

management; project man-

ager, project field superin-

tendents, chief estimator,

and usually, one outside

construction engineering

consultant. Following the

session, the outside consul-

tant and I would then develop the selected

concepts jointly.

I cannot tell you how

many times in the

last 40 years

doctors, dentists and

attorneys have told

me that they started

out in engineering

and then changed

careers.

DFI 2014 Awards: Call for Entries

DFI annually showcases and celebrates the achievements and

contributions of individuals, teams and companies in the deep

foundations industry.

We encourage you to submit your work and nominate your

colleagues for recognition.

The Outstanding Project Award recognizes the superior

work of DFI members. Each year, a project is chosen from several

geotechnical projects submitted for consideration by DFI members.

The Distinguished Service Award recognizes individuals

who have made exceptionally valuable contributions to the

advancement of the deep foundations industry.

C. William Bermingham Innovation Award encourages

and recognizes innovative contributions to deep foundation

technology. The award pays tribute to the innovative spirit of Bill

Bermingham, DFI past president, and his contributions to DFI

and the deep foundations industry.

Ben C. Gerwick Award for Innovation in Design and

Construction of Marine Foundations recognizes excellence in

marine engineering. The award is a tribute to Ben Gerwick, and

recognizes his exceptional achievements and contributions to

the design and construction of marine foundations.

For more information visit www.dfi.org/awardslectures.asp

Submissions for the 2014 Awards due by April 15, 2014

Page 8: DFI Magazine March/April 2014

When you buy a LōDril® from Bay Shore Systems, you’ve made an investment that will keep paying you over and over again. That's because, regardless of whether you choose LōDril®, TR Series or LAD Series, Bay Shore rigs keep working over and over again.

Bay Shore equipment is built with solid engineering that utilizes easy-to-�nd parts and rugged construction. Plus, Bay Shore customer service is committed to keep you drilling with 98% on-time parts delivery and experienced service technicians who will come to your jobsite. It’s no wonder that Bay Shore customers say things like this:

“Bay Shore has by far the best service in the industry and has been a real breath of fresh air compared to other like companies.”

– Ray Sander, Xcel Energy

So, if you’re getting more downtime than drill time from your current equipment, it’s time to make a move. Call Bay Shore Systems today.

Visit: www.bayshoresystems.comCall: 888.569.3745

LōDril® DH60

Page 9: DFI Magazine March/April 2014

EXECUTIVE DIRECTOR UPDATE

Invitation to Speakers

DFI’s Deep Foundations for Landslides/Slope Stabilization and

Tiebacks and Soil Nailing Committees are organizing a two-day

event featuring presentations on current technologies, as well as

key design concepts and case histories that illustrate effective

application of deep foundations for stabilization of slopes and

excavation support.

Presentation proposals on the following topics are being

requested: Case Studies, History/Theoretical Background, Quality

Control and Inspection, Long-term Maintenance, Innovative

Applications and Techniques and Practice-Oriented Research.

Interested parties should submit a brief summary (no more

than one page) describing the subject matter of their proposed

presentation to [email protected]. The due date for submissions

is May 1, 2014.

Notification of acceptance and guidelines for presentation

development will be returned to all submitters by June 2, 2014.

Authors of accepted proposals will be required to commit to

presenting their topic at the seminar and to submit a PowerPoint

presentation handout to be included in the seminar publication

by July 1, 2014.

DEEP FOUNDATIONS • MAR/APR 2014 • 9

Communication may be the single most

important element in every thread of our

life. Think about it! Personal relationships

do not work without communicating your

thoughts, feelings, likes and dislikes with

the other person, be it a spouse, relative or

friend. Working as a team in the workplace

is not possible without clear communi-

cation with your co-workers, so that each

piece of the puzzle falls into place for a

successful project. Fruitful business deals

cannot be realized unless each party

communicates their needs, expectations

and what part they are willing to play in the

partnership, verbally or in a contract.

Communication makes the world go

round, while “a failure to communicate”

can be detrimental to all these important

facets of our lives.

Last week, DFI’s leadership — board

members, senior staff and committee chairs

— met for the annual winter planning meeting

to do just that — communicate. Each attendee

informed the others of what projects have

been completed, what is in process and

their ideas for the future. DFI’s new 5-year

strategic plan, Revitalizing our Mission, was

the main topic of discussion with four

breakout sessions covering each main goal

of the plan (see page 21 for details).

Theresa RappaportExecutive [email protected]

It’s All About Communication

With Past President Jim

Morrison, I led the globalization

workshop, where we determined

that communication across the

various DFI regions is key. In

order for DFI headquarters to

support the regional chapters,

there needs to be consistent

communication to ensure

that resources are allocated

as needed and activities to

benefit the local industry

are advanced. DFI and DFI

of India have accomplished

this with a weekly confer-

ence call to keep on track

with their plans for training

courses, workshops and

conferences. These events

communicate advances

and new methodology

being used elsewhere that

the Indian deep foundation

community can use in their projects.

Bringing the regional leaders together at the

planning meeting also gave them the

opportunity to explore ways they can work

together and communicate with each other

in order to serve all DFI members, wherever

they are.

We are lucky that communi-

cation far and wide is more easily

done with virtual meet-

ings, audio and video

conference calls, email,

web platforms for docu-

ment sharing and social

media. Having a global

organization provides a

forum where all members,

no matter where they are,

can communicate with

each other. This ability is a

benefit to each member

and to the industry. Be part

of the process and partici-

pate as much as your

schedule allows. The true value of being a

DFI member lies in the ability to commun-

icate and network with others who have

similar interests, challenges and needs.

Having a global

organization provides

a forum where all

members, no matter

where they are, can

communicate with

each other.

Deep Foundations for Slope Stabilization and Excavation Support: TBD August/September 2014, Pittsburgh, PA

Page 10: DFI Magazine March/April 2014

10 • DEEP FOUNDATIONS • MAR/APR 2014

[email protected]

Family Owned Since 1949

®

TransitionMatsCrane, Timber

& ExcavatorMats

Pre-Cut Lagging& Lagging Panels

OutriggerMatsAccess

Mats

CONSTRUCTION

Buy Direct from the Sawmill and SAVE!

LaggingandMats

• Largest Inventory in theMidwest• Convenient, Quick Delivery to Your Job Site• Truck-Rail-Barge

ACCESS MATS EARTH RETENTION

ConstLumMatDFIAd092313:Layout 1 9/24/13 4:09 PM Page 1

Page 11: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 11

Brasfond USA Corp.1785 N. Geyers Chapel Rd.Wooster, Ohio 44691

Office phone: 1-330-262-0015e-mail: [email protected]

Page 12: DFI Magazine March/April 2014

12 • DEEP FOUNDATIONS • MAR/APR 2014 DEEP FOUNDATIONS • MAR/APR 2014 • 13

Once the directionally drilled pilot holes are completed and

found to be within tolerance, workers ream each anchor hole to its

final specified diameter. The reaming was completed using down-

the-hammer (DTH) rotary drilling techniques. The project

included anchor holes of 10, 13 and 15 in (25.4, 33.0 and 38.1 cm)

diameters. Hammer bits for these diameters were designed with 5-

3/4 in (14.6 cm) diameter “snouts.” This specific hammer bit design

allowed the ream drilling to follow the original directionally drilled

pilot holes to provide assurance that the reamed holes met the

required drill tolerances.

A downhole survey instrument, manufactured by Reflex

Instruments, verified the borehole location. The instrument is

commonly used in the oil and gas industry. The engineers conducted

two downhole surveys for each hole; the first survey was run after

directional drilling was complete. The second survey ran on

completion of the final reaming of the hole. The surveys were

performed with the instrument centralized inside the drill rods. For

each survey, data obtained at 10 ft (3 m)

intervals and the average from the survey,

going into and out of the hole, was used.

The project team compiled all the survey

data to make a final survey report.

The following two plots are typical of

what would be found in the final align-

ment survey report. The first plot depicts

the upstream deviation (Figure 1). Three

sets of survey data are shown for eval-

uation. The three-dimensional tolerance

cone is shown in two-dimensions for a

perspective reference. The data confirms

that the reaming passes followed the pilot

hole and the accuracy of the downhole

instrument compared well to the optical

directional survey shots. The second plot

depicts the dam axis deviations (Figure 2).

The project also called for a 780 ft (237 m) long steel platform to

gain access to the spillway anchors. The Stratus Group designed the

platform to support two 85 ton (80 tonne) crawler cranes and as

many as five drill rigs that were the equivalent to a design load of

3.5 ton per sq ft (335 kN per sq m). Once the final platform design

was approved, fabrication of roughly 3 million lbs (1,360 tonnes)

of structural steel began. Brayman’s in-house fabrication shop, in

conjunction with Dura-Bond Industries and Advantage Steel,

collaborated to fabricate and install the platform in less than five

months. Flexibility in the platform design allowed for sections of

the platform to be lowered as much as 16 ft (4.9 m) to provide

access to anchors at lower elevations along the spillway face. In

addition to the main spillway platform, Stratus Group, Brayman,

Dura-Bond and Advantage designed, fabricated and installed six

other unique platforms to facilitate anchor construction on various

areas of the dam.

The tops of dam anchors and face of dam anchors crossed planes at

depths up to 200 ft (61 m) with only 3 ft (0.9 m) of clearance

between boreholes. Due to the risk of intercepting adjacent

boreholes or tensioned anchors, the project specification called

for drill tolerances of 1:150 or 1 ft (0.3 m) of deviation for every

150 ft (45.7 m) of drill depth. In addition to the risk of

intercepting adjacent anchors, there are multiple obstructions

Obstacles at the Site

Bluestone Dam in Hinton, W.Va., along the New River, is owned

and operated by the U.S. Army Corps of Engineers (USACE).

Completed in 1949, the dam is 165 ft (50 m) tall, 2,048 ft

(624 m) wide, and encompasses a water shed that is 4,600 sq mi

(11,914 sq km). The Bluestone Dam Safety Assurance (DSA)

Program began in 2001, and is a multiple-phase construction

project to upgrade the capacity and stability of the structure to meet

the probable maximum flood event. Installing 216 high capacity

rock anchors was a major feature of the work.

The USACE selected Brayman Construction Corporation to

perform Phase 2B of the construction modifications to the

Bluestone Dam. Brayman was responsible for installing the high

capacity rock anchors, which range in size from 3 to 61 strands and

have a design load up to 2,145 kips (9,541 kN). Drill holes range in

size from 6.5 to 15 in (16.5 to 38 cm), and required full length

corrosion protection. Of the 216 anchors, 57 were installed on top

of the dam to resist overturning and the remaining 159 were

installed on the face of the dam at a 45-degree angle to resist sliding.

To gain access to the face of the dam anchor locations, the

project required dirt benches, excavations with temporary shoring,

and steel platforms. To access anchors on the east and west

abutment faces, the team excavated over 10,000 cu yds (7,645 cu

m) of material. Support of these excavations included the design

and installation of three soil nail walls with over 145 nails and

3,500 sq ft (325 sq m) of shotcrete.

Bluestone Dam Safety Assurance Program: An OPA Runner Up

Jeff Hopple, P.E., Brayman Construction CorporationAUTHOR

within the dam including two service galleries, hundreds of

foundation drains, mechanical controls for gate operation and

18 ft (5.5 m) diameter penstocks.

The USACE conducted a study in 2002 to verify whether

conventional drilling methods could produce the desired

tolerances. The results of this study proved that conventional

drilling methods could not produce the accuracy required. Thus,

Brayman developed a real-time directional drilling system

specifically for the project. The system needed to provide real-time

feedback in order to efficiently drill the quantity of holes required.

The system needed to be nonmagnetic due to embedded steel

within the dam and also be isolated from the drilling equipment

due to vibration. The system’s main component is an optical survey

instrument fitted with a camera. The camera monitors an LED

target located at the top of the down-the-hole hammer. The camera

is connected to a video monitor and gives real-time video footage of

the target. Dual-wall drill rods allow air to flow through the outer

rod to operate the hammer, leaving the inner rod free of water and

debris. This makes viewing the target at depths up to 275 ft (84 m)

possible. The slant-face bit is used in lieu of a standard button bit

and steers the drill string. The independent drill stand holds the

survey instrument and camera above the drill where it is isolated

from vibrations by the mass of the dam. The system constantly

monitors the location of the drill string throughout the entire

length of the hole.

Workers used a small hydraulic crawler drill to directionally drill a

5.75 in (14.6 cm) pilot hole. The first step in setting up the

directional drill was to place the independent drill stand to support

the optical instrument. With the stand in place, the optical

instrument was located in-line with the theoretical drill line. The

drill was then set at the appropriate angle and azimuth along the

drill line between the optical instrument and a survey nail located at

the entry point on the concrete. As the hole advanced, the operator

was able to watch in real time the theoretical drill line versus the

actual drill line. The theoretical drill line was shown as a crosshair

on the operator’s computer screen.

Deviation from the crosshair can be

corrected by stopping the rotation of the

drill string and chiseling, or steering the

slant face bit back into the theoretical drill

line. The target has an extra LED light that

aligns with the slant face of the bit allowing

the operator to know its orientation at all

times. For quality control purposes,

optical three-dimensional observations

are made at intervals as the hole

progresses. The optical shots are more

accurate than the instrument surveys;

however, since they are taken before the

final drill operation has been completed,

they do not meet the contract speci-

fications, but are used as reference in the

final verification survey.

Directional Drilling

COVER STORY

Figure 1. Upstream deviation

The USACE conducted a study in

2002 to verify whether

conventional drilling methods

could produce the desired

tolerances. The results of this

study proved that conventional

drilling methods could not produce

the accuracy required.

Page 13: DFI Magazine March/April 2014

12 • DEEP FOUNDATIONS • MAR/APR 2014 DEEP FOUNDATIONS • MAR/APR 2014 • 13

Once the directionally drilled pilot holes are completed and

found to be within tolerance, workers ream each anchor hole to its

final specified diameter. The reaming was completed using down-

the-hammer (DTH) rotary drilling techniques. The project

included anchor holes of 10, 13 and 15 in (25.4, 33.0 and 38.1 cm)

diameters. Hammer bits for these diameters were designed with 5-

3/4 in (14.6 cm) diameter “snouts.” This specific hammer bit design

allowed the ream drilling to follow the original directionally drilled

pilot holes to provide assurance that the reamed holes met the

required drill tolerances.

A downhole survey instrument, manufactured by Reflex

Instruments, verified the borehole location. The instrument is

commonly used in the oil and gas industry. The engineers conducted

two downhole surveys for each hole; the first survey was run after

directional drilling was complete. The second survey ran on

completion of the final reaming of the hole. The surveys were

performed with the instrument centralized inside the drill rods. For

each survey, data obtained at 10 ft (3 m)

intervals and the average from the survey,

going into and out of the hole, was used.

The project team compiled all the survey

data to make a final survey report.

The following two plots are typical of

what would be found in the final align-

ment survey report. The first plot depicts

the upstream deviation (Figure 1). Three

sets of survey data are shown for eval-

uation. The three-dimensional tolerance

cone is shown in two-dimensions for a

perspective reference. The data confirms

that the reaming passes followed the pilot

hole and the accuracy of the downhole

instrument compared well to the optical

directional survey shots. The second plot

depicts the dam axis deviations (Figure 2).

The project also called for a 780 ft (237 m) long steel platform to

gain access to the spillway anchors. The Stratus Group designed the

platform to support two 85 ton (80 tonne) crawler cranes and as

many as five drill rigs that were the equivalent to a design load of

3.5 ton per sq ft (335 kN per sq m). Once the final platform design

was approved, fabrication of roughly 3 million lbs (1,360 tonnes)

of structural steel began. Brayman’s in-house fabrication shop, in

conjunction with Dura-Bond Industries and Advantage Steel,

collaborated to fabricate and install the platform in less than five

months. Flexibility in the platform design allowed for sections of

the platform to be lowered as much as 16 ft (4.9 m) to provide

access to anchors at lower elevations along the spillway face. In

addition to the main spillway platform, Stratus Group, Brayman,

Dura-Bond and Advantage designed, fabricated and installed six

other unique platforms to facilitate anchor construction on various

areas of the dam.

The tops of dam anchors and face of dam anchors crossed planes at

depths up to 200 ft (61 m) with only 3 ft (0.9 m) of clearance

between boreholes. Due to the risk of intercepting adjacent

boreholes or tensioned anchors, the project specification called

for drill tolerances of 1:150 or 1 ft (0.3 m) of deviation for every

150 ft (45.7 m) of drill depth. In addition to the risk of

intercepting adjacent anchors, there are multiple obstructions

Obstacles at the Site

Bluestone Dam in Hinton, W.Va., along the New River, is owned

and operated by the U.S. Army Corps of Engineers (USACE).

Completed in 1949, the dam is 165 ft (50 m) tall, 2,048 ft

(624 m) wide, and encompasses a water shed that is 4,600 sq mi

(11,914 sq km). The Bluestone Dam Safety Assurance (DSA)

Program began in 2001, and is a multiple-phase construction

project to upgrade the capacity and stability of the structure to meet

the probable maximum flood event. Installing 216 high capacity

rock anchors was a major feature of the work.

The USACE selected Brayman Construction Corporation to

perform Phase 2B of the construction modifications to the

Bluestone Dam. Brayman was responsible for installing the high

capacity rock anchors, which range in size from 3 to 61 strands and

have a design load up to 2,145 kips (9,541 kN). Drill holes range in

size from 6.5 to 15 in (16.5 to 38 cm), and required full length

corrosion protection. Of the 216 anchors, 57 were installed on top

of the dam to resist overturning and the remaining 159 were

installed on the face of the dam at a 45-degree angle to resist sliding.

To gain access to the face of the dam anchor locations, the

project required dirt benches, excavations with temporary shoring,

and steel platforms. To access anchors on the east and west

abutment faces, the team excavated over 10,000 cu yds (7,645 cu

m) of material. Support of these excavations included the design

and installation of three soil nail walls with over 145 nails and

3,500 sq ft (325 sq m) of shotcrete.

Bluestone Dam Safety Assurance Program: An OPA Runner Up

Jeff Hopple, P.E., Brayman Construction CorporationAUTHOR

within the dam including two service galleries, hundreds of

foundation drains, mechanical controls for gate operation and

18 ft (5.5 m) diameter penstocks.

The USACE conducted a study in 2002 to verify whether

conventional drilling methods could produce the desired

tolerances. The results of this study proved that conventional

drilling methods could not produce the accuracy required. Thus,

Brayman developed a real-time directional drilling system

specifically for the project. The system needed to provide real-time

feedback in order to efficiently drill the quantity of holes required.

The system needed to be nonmagnetic due to embedded steel

within the dam and also be isolated from the drilling equipment

due to vibration. The system’s main component is an optical survey

instrument fitted with a camera. The camera monitors an LED

target located at the top of the down-the-hole hammer. The camera

is connected to a video monitor and gives real-time video footage of

the target. Dual-wall drill rods allow air to flow through the outer

rod to operate the hammer, leaving the inner rod free of water and

debris. This makes viewing the target at depths up to 275 ft (84 m)

possible. The slant-face bit is used in lieu of a standard button bit

and steers the drill string. The independent drill stand holds the

survey instrument and camera above the drill where it is isolated

from vibrations by the mass of the dam. The system constantly

monitors the location of the drill string throughout the entire

length of the hole.

Workers used a small hydraulic crawler drill to directionally drill a

5.75 in (14.6 cm) pilot hole. The first step in setting up the

directional drill was to place the independent drill stand to support

the optical instrument. With the stand in place, the optical

instrument was located in-line with the theoretical drill line. The

drill was then set at the appropriate angle and azimuth along the

drill line between the optical instrument and a survey nail located at

the entry point on the concrete. As the hole advanced, the operator

was able to watch in real time the theoretical drill line versus the

actual drill line. The theoretical drill line was shown as a crosshair

on the operator’s computer screen.

Deviation from the crosshair can be

corrected by stopping the rotation of the

drill string and chiseling, or steering the

slant face bit back into the theoretical drill

line. The target has an extra LED light that

aligns with the slant face of the bit allowing

the operator to know its orientation at all

times. For quality control purposes,

optical three-dimensional observations

are made at intervals as the hole

progresses. The optical shots are more

accurate than the instrument surveys;

however, since they are taken before the

final drill operation has been completed,

they do not meet the contract speci-

fications, but are used as reference in the

final verification survey.

Directional Drilling

COVER STORY

Figure 1. Upstream deviation

The USACE conducted a study in

2002 to verify whether

conventional drilling methods

could produce the desired

tolerances. The results of this

study proved that conventional

drilling methods could not produce

the accuracy required.

Page 14: DFI Magazine March/April 2014

14 • DEEP FOUNDATIONS • MAR/APR 2014 DEEP FOUNDATIONS • MAR/APR 2014 • 15

The sensitivity of the survey instrument and the effects of the sun

had to be monitored closely since the instrument was mounted on a

steel frame. Throughout the day, the lattice of the stand would

expand and contract moving the optical instrument with the camera.

This had the effect of moving the directional drill target that

appeared on the driller’s screen. Since this was a slow change, it

would appear to the driller that the hole was moving off target. To

prevent this problem, the surveyor would block sunlight from the

stand when possible, along with back sighting and adjusting the instru-

ment more frequently when the weather conditions warranted it.

Most of the holes on the project have three sets of survey data:

the optical data, the directional downhole instrument survey and

the final downhole instrument survey. The ability to capture the

optical data was not understood at the time the specifications were

written or when the initial construction plans were established. As

the data became available, it became evident that the optical data

was the most reliable and accurate survey information. Thus, after

completing the directional drill hole, the USACE decided the

downhole survey with the Reflex Instrument was not required.

With proper design of the reaming bits and observing drill

penetration rates, the reaming process was guaranteed to follow the

pilot hole. Consequently, the downhole instrument survey could be

eliminated or reduced to a small percentage of verification tests.

The directional drilling system developed by Brayman at the

Bluestone Dam is ideal for drilling straight holes where accuracy is

vital to the object being anchored. It has been adapted for very

extreme rock drilling. Drilling through obstructions is difficult, but

can be accomplished with this system. The bit locating system is

not affected by embedded steel in the concrete and the location of

the bit is known to a high degree of accuracy in real time.

Working alongside the USACE, Brayman successfully installed the

largest rock anchors in the United States by way of directional

drilling. These anchors will effectively stabilize the dam under the

new flood protection design and prevent failure. The completion of

the first 216 anchors plays an integral part in the on-going

rehabilitation efforts at Bluestone Dam. Phase 2B was completed in

December 2011, and Brayman is now working on Phase 3.

Summary

Early installation of ACIP piles

The same sets of data are shown as in the upstream deviation graph.

Similarly, the deviations measured by the different sets of survey

data overlay closely.

The scale of the graph is notable. The vertical axis of each graph

is elevation with a 200 ft (61 m) range. The horizontal axis

represents the deviation in inches with a range of 4 in (10 cm). If the

graphs were shown on a 1:1 scale the deviation would not be visible

for evaluation.

For evaluation, the final survey for the hole shown in these

examples has a deviation of less than 1 in (2.4 cm) until a depth of

206 ft (62.7 m) and a maximum deviation of roughly 2 in (5 cm) to

the west at the bottom of the survey along the dam axis.

Perpendicular to the dam, the maximum deviation is 4 in (10 cm)

near the top of the hole and 4.5 in (11.4 cm) at the bottom of the

hole. The deviation for the total hole shown based on the last survey

reading is 4.5 in (11.4 cm). The tolerance at the bottom of the

survey is 1:608 compared to the required 1:150.

Of the 216 anchors, only 2% were out of tolerance at the bottom

of the hole. However, these anchors were within tolerance at 100 ft

(30.5 m). The anchors went out of tolerance beyond the depth of

any obstructions and were accepted in this manner. At 100 ft (30.5 m),

all of the anchors were within tolerance with the majority more

than triple the required tolerance. Distinguishing a varying

tolerance acceptance criteria based on known obstructions could

allow stricter tolerances in critical zones while allowing larger

tolerances in less critical zones. This offset can lead to a time savings

in the drilling process and thus reduce the expectation of having to

repeat work due to out-of-tolerance drilling.

Brayman modified the directional drill system throughout the

Bluestone Dam Safety Assurance project. The diameter of the

directional drill tooling was reduced to balance stiffness to keep the

hole aligned, with flexibility to steer and correct the hole when it

deviates from the target alignment. The directional drill pilot hole

size increased early in the project to allow design changes to the

reaming bits. Multiple reaming bits fractured while others drilled a

unique hole outside of the pilot hole prior to the pilot hole size

changes being made. Material changes were made to the directional

drill tooling to withstand the wear of hammer drilling in hard rock.

This ranged from metallurgy changes in the tooling manufacturing

to O-ring upgrades to keep rod seals lasting longer. Each part of the

drilling system became a potential source of error or problems in

the drilling process. Through experience, the drillers developed

sensitivity to detect problems early and fix them quickly.

Anchors installed and ready for stressing

Section of platform lowered for second row of anchorsDirectional drilling setup

Figure 2. Dam access deviation

Page 15: DFI Magazine March/April 2014

14 • DEEP FOUNDATIONS • MAR/APR 2014 DEEP FOUNDATIONS • MAR/APR 2014 • 15

The sensitivity of the survey instrument and the effects of the sun

had to be monitored closely since the instrument was mounted on a

steel frame. Throughout the day, the lattice of the stand would

expand and contract moving the optical instrument with the camera.

This had the effect of moving the directional drill target that

appeared on the driller’s screen. Since this was a slow change, it

would appear to the driller that the hole was moving off target. To

prevent this problem, the surveyor would block sunlight from the

stand when possible, along with back sighting and adjusting the instru-

ment more frequently when the weather conditions warranted it.

Most of the holes on the project have three sets of survey data:

the optical data, the directional downhole instrument survey and

the final downhole instrument survey. The ability to capture the

optical data was not understood at the time the specifications were

written or when the initial construction plans were established. As

the data became available, it became evident that the optical data

was the most reliable and accurate survey information. Thus, after

completing the directional drill hole, the USACE decided the

downhole survey with the Reflex Instrument was not required.

With proper design of the reaming bits and observing drill

penetration rates, the reaming process was guaranteed to follow the

pilot hole. Consequently, the downhole instrument survey could be

eliminated or reduced to a small percentage of verification tests.

The directional drilling system developed by Brayman at the

Bluestone Dam is ideal for drilling straight holes where accuracy is

vital to the object being anchored. It has been adapted for very

extreme rock drilling. Drilling through obstructions is difficult, but

can be accomplished with this system. The bit locating system is

not affected by embedded steel in the concrete and the location of

the bit is known to a high degree of accuracy in real time.

Working alongside the USACE, Brayman successfully installed the

largest rock anchors in the United States by way of directional

drilling. These anchors will effectively stabilize the dam under the

new flood protection design and prevent failure. The completion of

the first 216 anchors plays an integral part in the on-going

rehabilitation efforts at Bluestone Dam. Phase 2B was completed in

December 2011, and Brayman is now working on Phase 3.

Summary

Early installation of ACIP piles

The same sets of data are shown as in the upstream deviation graph.

Similarly, the deviations measured by the different sets of survey

data overlay closely.

The scale of the graph is notable. The vertical axis of each graph

is elevation with a 200 ft (61 m) range. The horizontal axis

represents the deviation in inches with a range of 4 in (10 cm). If the

graphs were shown on a 1:1 scale the deviation would not be visible

for evaluation.

For evaluation, the final survey for the hole shown in these

examples has a deviation of less than 1 in (2.4 cm) until a depth of

206 ft (62.7 m) and a maximum deviation of roughly 2 in (5 cm) to

the west at the bottom of the survey along the dam axis.

Perpendicular to the dam, the maximum deviation is 4 in (10 cm)

near the top of the hole and 4.5 in (11.4 cm) at the bottom of the

hole. The deviation for the total hole shown based on the last survey

reading is 4.5 in (11.4 cm). The tolerance at the bottom of the

survey is 1:608 compared to the required 1:150.

Of the 216 anchors, only 2% were out of tolerance at the bottom

of the hole. However, these anchors were within tolerance at 100 ft

(30.5 m). The anchors went out of tolerance beyond the depth of

any obstructions and were accepted in this manner. At 100 ft (30.5 m),

all of the anchors were within tolerance with the majority more

than triple the required tolerance. Distinguishing a varying

tolerance acceptance criteria based on known obstructions could

allow stricter tolerances in critical zones while allowing larger

tolerances in less critical zones. This offset can lead to a time savings

in the drilling process and thus reduce the expectation of having to

repeat work due to out-of-tolerance drilling.

Brayman modified the directional drill system throughout the

Bluestone Dam Safety Assurance project. The diameter of the

directional drill tooling was reduced to balance stiffness to keep the

hole aligned, with flexibility to steer and correct the hole when it

deviates from the target alignment. The directional drill pilot hole

size increased early in the project to allow design changes to the

reaming bits. Multiple reaming bits fractured while others drilled a

unique hole outside of the pilot hole prior to the pilot hole size

changes being made. Material changes were made to the directional

drill tooling to withstand the wear of hammer drilling in hard rock.

This ranged from metallurgy changes in the tooling manufacturing

to O-ring upgrades to keep rod seals lasting longer. Each part of the

drilling system became a potential source of error or problems in

the drilling process. Through experience, the drillers developed

sensitivity to detect problems early and fix them quickly.

Anchors installed and ready for stressing

Section of platform lowered for second row of anchorsDirectional drilling setup

Figure 2. Dam access deviation

Page 18: DFI Magazine March/April 2014

18 • DEEP FOUNDATIONS • MAR/APR 2014

Taking the Leadin over 40 countries around the world

Lead SystemsImpact Hammers

Reverse Circulation DrillsHard Rock Drill Bits

Custom Foundation EquipmentSite Support

Project Planning

600 Ferguson Avenue NorthHamilton, Ontario, Canada L8L 4Z9

Tel: 1.905.528.7924 Fax: 1.905.528.6187Toll Free: 1.800.668.9432 (in Canada and USA)

www.berminghammer.comEmail: [email protected]

Page 19: DFI Magazine March/April 2014

ADV2014_USATODAY8.5x11+ref_tr 3-02-2014 15:50 Pagina 1

Colori compositi

C M Y CM MY CY CMY K

Page 20: DFI Magazine March/April 2014

20 • DEEP FOUNDATIONS • MAR/APR 2014

Ground Improvement

Above Left: Cutter Soil Mixing, Seattle, WABelow Left: Jet Grouting, Seattle, WARight: Deep Soil Mixing, Miami, FL

We excel at tough challenges. Malcolm's experience and specialized resources drive the construction state-of-practice, evolving new solutions to meet the demands of our clients. Malcolm offers a full array of ground improvement techniques to modify and enhance the existing ground In-situ through densification, solidification, reinforcement and drainage. When you have conditions that require a higher level of expertise, contact us at MalcolmDrilling.com

Cutter Soil Mixing

Multi-Axis Soil Mixing

Jet Grouting

Vibro Systems

Deep Soil Mixing

Specialized Geotechnical

Grouting

Page 21: DFI Magazine March/April 2014

DFI ACTIVITIES

DEEP FOUNDATIONS • MAR/APR 2014 • 21

telephone/virtual meetings and using various media to enhance

communication and disseminate information was explored. DFI is

working with current regional chapters to enhance the benefits to

members. Goals were set for increasing membership in each region,

and new regions will be explored over the next five years. Those

mentioned were Australasia, South America, Mexico and Sub-

Saharan Africa. A task force was set up to determine the criteria

required to embark on the formation of a regional chapter and to

formalize a guidance document for the creation of chapters.

A principal subject of the board meeting was the project funding

program. This is the third year DFI designated funds to the program

where DFI technical committees submit proposals to conduct

research projects that “support approved undertakings, those

deemed useful toward advancing deep foundation technology.”

This year 11 proposals were submitted. A panel reviewed and

ranked them, recommending five projects for funding. The five were

submitted by DFI committees on Soil Mixing, Driven Piles, Marine

Foundations, Drilled Shafts/Seismic and Lateral Loads, and Deep

Foundations for Landslides and Slope Stabilization. The trustees

agreed to fund $100,000 towards four of these projects. Two of the

five were contingent on separate funding from other groups, so the

final projects will be announced in the next issue of this magazine.

The WPM ended with a trustee meeting where the 2013

financials were reviewed, the 2014 budget was adopted, a new

technical committee on subsurface characterization for deep

foundations was approved, and future meetings were discussed.

DFI Board Meeting

Early every year, DFI’s Winter Planning Meeting provides a venue

for trustees to think about the future and discuss other business,

including the budget. In January, DFI’s trustees and the chairs of the

15 technical committees met at Marco Island, Fla. (The DFI

Educational Trust Board met the day before, see p. 45.)

At the meeting, participants took a fresh look at areas of

continuing interest to DFI. All were assigned to breakout groups

that addressed the four goals in DFI’s five-year strategic plan:

globalization of the institute, revitalization of technical activities,

engaging manufacturer/supplier members, and fostering

involvement of younger members. The recommendations for

accomplishing each goal were wide and varied, and many tasks

were identified for implementation through 2019.

The newest initiative to be strategized was the participation of

the manufacturer/supplier members; following up on a roundtable

discussion by this group during the Annual Conference in Phoenix

last September. The breakout group discussed how these members

are important to DFI, providing information about innovations in

quality, safety, sustainability and durability. One suggestion was to

introduce sessions or panel discussions on the future of the

industry and requirements in particular sectors during seminars

and conferences. The idea of an advisory committee comprised of

these technology providers was also proposed.

Another group looked at DFI’s technical committees, and

focused on identifying potential new committee activities. They

discussed publications, including the possibility of committee-

generated white papers as well as papers for DFI’s Journal. Among

other ideas was creating liaisons with organizations with similar

committees, and seeking exposure at their conferences. Webinars,

planned by technical committees, were also discussed.

Younger members are always important to DFI, and this

breakout group discussed many ideas, including a course aimed at

young college professors, and providing volunteer speakers for

universities. The group also talked about ways to incentivize

employers to encourage younger employees to participate in DFI

events. They proposed a definition of “younger” members as 35

years old or younger, or as having five years or less of experience.

The breakout group also proposed a survey of younger engineers

and their employers, if feasible, with the help of an expert.

The breakout group on globalization focused on the exchange

of information through regional chapters. The practice of regular

WPM: Brainstorming Breakouts

Paul Axtell (Drilled Shaft Committee chair), Ed Laczynski (Tiebacks and Soil Nailing Committee), Kwabena Ofori-Awuah (Seismic and Lateral Loads Committee chair) and Emad Sharif from Dubai

Attendees at the WPM (photo by Herb Engler)

Page 23: DFI Magazine March/April 2014

Experience the progress.

The Group

Liebherr Nenzing Crane Co.7075 Bennington StreetHouston, TX 77028-5812Phone: +1 713 636 [email protected]/LiebherrConstructionwww.liebherr.com

Page 24: DFI Magazine March/April 2014

Follow Our Lead To A Solid FoundationBAUER-Pileco is a leading global provider of foundation equipment and service to the construction

industry. Recognized for its technological advances and innovation, BAUER-Pileco and its network of dealers represent the BAUER Group across North and Central America.

BAUER PILECORTG KLEMMFAMBO MAT BETEK PRAKLA

www.bauerpileco.com BAUER-Pileco Inc., 111 Berry Road, Houston, TX [email protected] (713) 691-3000 / (800) 474-5326 www.facebook.com/bauerpileco www.youtube.com/PilecoTX

Scan this QR Code to your smart phone

and contact us directly.

Page 25: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 25

FoundationsPiling & Deep International Conference on 2 0 1 4 S T O C K H O L M S W E D E N

Plan to Attend the DFI-EFFC International Conference in Sweden

The complete program for the DFI-EFFC international conference

“Global Perspective on Sustainable Execution of Deep Foundation

Works,” being held in Stockholm, Sweden from May 21-23, 2014 is

available at www.dfi-effc2014.org.

During the three-day event, 23 technical presentations will be

made in five sessions: Harmonization of Execution Standards,

Bored and Driven Piles, Deep Mixing —Wet and Dry Methods,

Walls — In-situ and Pre-formed, and New Trends in Foundation

Practice. The fifth session also includes the tenth John Mitchell

Lecture by Bengt Fellenius and the Special Heritage Lecture on

Swedish Contributions to Geotechnical Engineering by Stefan

Aronsson and K. Rainer Massarsch. The technical presentations

were selected from more than 150 submitted papers from around

the globe. Each session also has a keynote lecture and concludes

with a panel discussion on the session topic. Additionally, many of

the other submitted papers will be viewable as Electronic Poster

Presentations. These presentations will be viewable from the

conference website before, during and after the conference as well

as on kiosks at the conference for attendee convenience.

The exhibition will be open all three days of the conference,

featuring products and services of 40 companies. Exhibitor videos

will be shown throughout the conference, and will be available for

download from the conference website.

There are still booths available; view the

floor plan at www.dfi-effc2014.org.

At press time, the conference partner

sponsor is Ruukki, and Robit Rocktools

Ltd is a mentorship sponsor. Sponsorship

packages are still available for Banquet

Sponsors, General Sponsors and addi-

tional Partner and Mentorship Sponsors.

This conference is a unique opportunity for knowledge

dissemination and technical exchange between contractors, project

owners, authorities, equipment manufacturers, material suppliers

and researchers working with different aspects of deep foundations.

To register as an attendee, exhibitor or sponsor visit www.dfi-

effc2014.org.

Exhibitor and Sponsor Opportunities

Page 26: DFI Magazine March/April 2014

RELY ON DSI

DYWIDAG-SYSTEMS INTERNATIONAL USA Inc.

DYWI® Drill Hollow Bar System for Soil Nails - Micro Piles - Ground Anchors - Rock Bolts

Installation Advantages:K Ability to work with small drill rigs without casing in narrow spacesK Similar installation methods for all ground conditionsK Simultaneous Drill and Grout InstallationK No Casing RequiredK Rotary Percussive Drilling Enables quick rates of installation

www.dsiamerica.com

Material Characteristics: K Fully Threaded Rod Sections

K Thread Profile

Standard ISO rope thread and T-Thread

produces an excellent bond between the

bar and grout

K The hollow core serves for flushing

with air or water during drilling

K Choice of drill bits for different

Ground conditions

K Enhanced corrosion protection is

available upon request

NORTH CENTRALBolingbrook, ILPhone (630) 739-1100

SOUTH CENTRALMansfield, TXPhone (817) 473-6161

NORTH WESTKent, WAPhone (253) 859-9995

WESTLong Beach, CAPhone (562) 531-6161

CENTRAL AMERICAPompano Beach, FLPhone (954) 532-1326

SOUTH EASTTucker, GAPhone (770) 491-3790

N. EAST / MID ATLANTICToughkenamon, PAPhone (610) 268-2221

ALASKA: Call North West

HAWAII: Call West

CANADA WESTSurrey, BCPhone (604) 888-8818

CANADA EASTGormley, ONPhone (905) 888-8988

DYWIDAG-SYSTEMS INTERNATIONAL CANADA, LTD

Quick – Safe - Reliable

DYWI Drill® Hollow bar now optionally

available in 100% Domestic Steel

manufactured in our Bolingbrook,

Illinois facility!

Contact your local representatives for available sizes.

www.dsicanada.ca

120906_ 9/6/2012 2:04:31 PM�

Page 27: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 27

June 18-20, 2014

Register for SuperPile ’14

DFI’s SuperPile organizing committee expects more than 200

attendees and 40 exhibitors at the Hyatt Regency in Cambridge,

Mass., for SuperPile ’14. From June 18 through June 20 seven of

DFI’s Technical Committees will host meetings and technical

presentations of local and national importance. Teams

of reviewers from the Driven Piles, Augered Cast-in-

Place Pile/Drilled Displacement Pile, Micropile,

Marine Foundations, Testing and Evaluation,

Seismic and Lateral Loads, and Drilled

Shaft Committees are reviewing

abstracts and finalizing the

technical program for the

conference. SuperPile

2014 Chair Les R. Chernauskas, P.E. (Geosciences Testing and

Research, Inc.), has assembled an enthusiastic team of local

committee members to help bring attendees the most innovative,

state-of-the-practice piling technologies available to the deep

foundations industry. Also make plans to attend DFI’s

Technical Committee Meetings the evening of June 18, prior

to the conference.

To register or for more information

on the program, accommodations,

exhibit space and sponsor-

ship opportunities visit

www.dfi.org.

Hyatt Regency in Cambridge

Page 28: DFI Magazine March/April 2014

PROJECT: ______________________________________________________________________ PAGE: _________

LOCATION: __________________________________________________________ DATE: _____________

JD Fields & Company Inc. I 55 Waugh Drive I Suite 1250 I Houston, TX 77007 I 855- GRADE 60 I www.jdfields.com

PROBLEM; DETERMINE BEST AND MOST ECONOMICAL HOT ROLLED SHEET PILE WALL SOLUTION FOR CLIENT’S PROJECT.

STEP 1) FIND MIN. SECTION MODULUS (Sx) REQUIRED FROM THE Mmax. USACE Design of Sheet Pile Walls EM 1994; 50% safety factor for allowable bending stress (Fa) (Fa = .50 x ksi for steel grade)

Sx = Mmax / Fa Sx = 84 kip-ft/ft (12in/ft) / 25ksi NOTE: JD FIELDS EXCLUSIVELY SUPPLIES HOESCH 700mm SERIES IN MIN 60ksi YTM GR 60! Determine (Sx) for Fa = 60 ksi

Sx = 84 kip-ft/ft (12in/ft) / 30ksi

STEP 2) COMPARE AVAILABLE HOT ROLLED Z-SHEET PILE SECTIONS. (MATERIAL MUST BE STOCK SECTION FOR QUICK DELIVERY.)

SECTION WEIGHT GRADE Sx AZ 26-700 28.37 lb/ft² 50 ksi 48.4 in³/ft

PZC 26 31.8 lb/ft² 50 ksi 48.4 in³/ft

PZ 35 35.0 lb/ft² 50 ksi 48.5 in³/ft

(H 1907) 23.3 lb/ft² 60 ksi 34.7 in³/ft *

SPECIFY HOESCH!

SHEET PILE WALL DESIGN 1/1

NORTH AMERICAN PILING MARKET Q1 - 2014

DREDGE LINE

TIEBACK

SHEET PILE

F

L

DESIGN PARAMETERS

ANCHORED WALL: \/ UNI. SURCHARGE (q) = 300 psf DEFLECTION: < 1 in RESULTS FROM SOFTWARE ANALYSIS

SHEET PILE LENGTH (L) = 40ft ANCHOR FORCE (F) = 6 kips/ft MAX MOMENT (Mmax) = 84 kip-ft/ft

SAND ɤ = 120lb/ft³ c´ = 0 Ø = 40°

SAND ɤsat = 129.4lb/ft³ c´ = 0 Ø = 40°

40.3 in³/ft (A572 GR 50)

33.6 in³/ft (A572 YTM GR 60)

CHECK FOR DEFLECTION; OK, TIEBACKS OFFER SUFFICIENT ANCHOR FORCE TO LIMIT WALL MOVEMENT. \/ H 1907 MEETS STRUCTURAL REQUIREMENT. \/

TECHNICAL BENEFITS: H 1907 YTM GR 60

*OFFERS A SIGNIFICANT WEIGHT SAVINGS OF ~20% OR MORE COMPARED TO OTHER GR 50 STOCK OPTIONS. *HIGHER YIELD STEEL CAN IMPROVE DESIGN DURABILITY, EXTEND WALL SERVICE LIFE, AND POTENTIALLY ELIMINATE COATING. *60 KSI YIELD WILL HOLD UP BETTER UNDER HIGHER DRIVING STRESSES IN DIFFICULT SOIL CONDITIONS. CALL JDF; THEY’RE SETTING THE STANDARD FOR SHEET PILING & GEOSTRUCTURAL SYSTEMS.

q

Page 29: DFI Magazine March/April 2014

WHAT DO THE LINCOLN MEMORIAL

AND THE MID-ATLANTIC REGIONAL SPACEPORT

AT WALLOPS ISLAND, VA

HAVE IN COMMON?

NATIONAL RIG RENTAL

WHY ? JUNTTAN AVAILABILITY

Exclusively JUNTTAN www.nationalrigrental.com 302-539-1963

Page 30: DFI Magazine March/April 2014

30 • DEEP FOUNDATIONS • MAR/APR 2014

The annual Hal Hunt Lecturer for DFI’s

39th Annual Conference on Deep

Foundations will be Paul W. Mayne, Ph.D.,

P.E., professor of Geosystems Engineering,

School of Civil and Environmental

Engineering at the Georgia Institute of

Technology. The lecture is a highlight of the

Annual Conference, and is named after Hal

Hunt, a trustee on the first DFI Board and

the first executive director. The lecture, set

up in 1989, was created to recognize

notable communicators in the deep

foundations community.

Professor Mayne is an international

researcher, focusing on in-situ testing, geo-

technical site characterization and the eval-

uation of rock and soil properties. He gave

the 2006 James K. Mitchell Lecture and the

2009 Michael W. O’Neill Lecture, both high

honors within the geotechnical profession.

He also delivered the state-of-the-art lecture

at the 17th International Conference on Soil

Mechanics & Geotechnical Engineering in

Alexandria, Egypt in 2009. Mayne has

consulted on projects all over the world,

and written or co-authored countless

books, manuals and technical papers.

Mayne attended Cornell University for

doctoral studies and since 1990 has been a

faculty member at Georgia Tech.

The Annual Conference is being held at

the Atlanta Marriott Marquis. It begins

Tuesday, October 21 with day-long

meetings of DFI’s 15 technical committees.

The conference officially opens Wednesday,

October 22, when the exhibit hall, featuring

over 100 manufacturer and supplier

displays, opens its doors, and presentations

on projects and case studies begin. The

conference closes on Friday, October 24.

The conference chair is John Wolosick,

Hayward Baker, and vice president of DFI.

Program co-chairs are Scott Ballenger,

Schnabel Foundation Company, and

Antonio Marinucci of American Equipment

and Fabrication. The organizing committee

is currently reviewing abstracts and

selecting keynote speakers.

Among the many DFI Awards to be presented are the Outstanding

Project Award (OPA), Distinguished Service Award (DSA), C.

William Bermingham Innovation Award, Young Professors Paper

Competition and the Student Paper Competition. The deadline to

submit nominations for these awards is April 15, 2014. More

information is available at http://www.dfi.org/awardslectures.asp.

City-by-City, the companions program, is an opportunity for

spouses, family and friends of conference attendees to experience

the great sights of Atlanta. Diane Bittner, wife of DFI President

Robert Bittner, has volunteered to work with DFI event

coordinator, Lauren Nance, 2014 Companions’ Program Chair

Megan Fitzgerald (HIIG Construction) and Pete Rose (ECA) to

ensure the group has a great time onsite and as they tour the city.

Exhibit space and underwriting opportunities are still available

for this exciting conference. Go to www.deepfoundations2014.org

to register online.

Award Nominations Due April 15

City-by-City

Hal Hunt Lecturer Chosen for 39th Annual Conference in Atlanta

Mayne has consulted on

projects all over the world,

and written or co-authored

countless books, manuals and

technical papers.

Page 31: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 31

C

M

Y

CM

MY

CY

CMY

K

2012 - MAIT ad.pdf 1 13/07/2012 9.48.16

Page 32: DFI Magazine March/April 2014

THE NEW

CASAGRANDE USA, Inc. 93 Stickles Pond Road - Newton, NJ 07860 Tel. 973-579-1906www.casagrande-usa.com

Eastern Distributor • INTERNATIONAL DRILLING EQUIPMENT, Inc.645 Angus Street - Rural Hall, NC 27045 Tel. 877-207-6062

[email protected]

Texas Distributor • RODRILL, Inc.11670 Interstate 10 Frontage Rd, - Converse, TX 78109 Tel. [email protected]

Page 33: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 33

DFIIOT NA SD INN

SU TO IF T

UPE T

E E

D

The 2014 International Workshop on Micropiles (IWM) is just a few

months away, from June 11-14, 2014 in Kraków, Poland. “Whether

you have been to every IWM since 1997 or this would be your first,

we look forward to seeing each of you to share past experiences and

create new memories,” says Allen Cadden, P.E., D.GE, chairman,

International Society for Micropiles (ISM). “You will not find a

better place to learn about what has been accomplished with

micropiles and what is being developed for future challenges. New

for the workshop is the added full day short course on micropiles on

Wednesday, June 11 and the World Cup of Micropiles Challenge.”

Kraków is one of the most culturally and politically significant cities

in Poland. The companions’ and social programs will showcase

some of Kraków’s most interesting sites. On Thursday, June 12,

companions will visit the nearby Auschwitz concentration camp.

On Friday, June 13, the delegates and companions will take a

walking tour of the Kraków historic city center brimming with

cafés, shops and pubs. The traditional ISM awards dinner will

follow the walking tour. All delegates and companions are also

invited to tour the Wieliczka Salt Mine, one of the oldest salt mines

in the world. The mine’s attractions include dozens of statues, three

chapels and an entire cathedral carved from rock salt.

According to the holiday review site Zoover, Kraków is the best

European city trip in 2014. The complete review is at http://weblog.

zoover.com/press_release/krakow-best-european-city-trip-2014.

Titan Polska is the host sponsor for the event. Several other cate-

gories of sponsorship are available. For sponsorship details contact

Jan Hall at ADSC ([email protected]).

Registration will be open in March on the ADSC website at

www.adsc-iafd.com. For details, contact Dan MacLean, of Con-Tech

Systems, technical program chair, at [email protected] or

Mary Ellen Bruce, ISM technical lead at DFI, at [email protected].

Social Program

Sponsorship Opportunities

12th International Workshop On Micropiles: Kraków, Poland

COOPERATING ALLIANCE

Wawel Castle, Krakow

Page 34: DFI Magazine March/April 2014

34 • DEEP FOUNDATIONS • MAR/APR 2014

At a time when many technical journals

are focused on the former, the DFI

Journal plays a vital role by offering a

balance between theory and experience.

DFI Journal Information Available

As reported in the Jan/Feb issue of Deep Foundations, Anne

Lemnitzer, Ph.D., and Timothy C. Siegel, P.E., G.E., D.GE, were

appointed co-editors of DFI Journal: The Journal of the Deep

Foundations Institute, and are eager to assume their roles this year.

They succeed Zia Zafir, Ali Porbaha and Dan Brown, who are

stepping down after serving as lead editors since the Journal’s

inception; though Zia will continue on the editorial board. Maney

Publishing, an independent publishing company specializing in

technical journals, contracted with DFI late last year to publish the

DFI Journal as Manny Fine, previous publisher, retired.

Siegel is a principal engineer

with Dan Brown and Associates, PC

and member of the adjunct faculty at

the University of Tennessee. He

holds a B.S. and M.S. in Civil

Engineering from Georgia Institute

of Technology, and has spent over 20

years working in industry. He is a

m e m b e r o f D F I ’s G r o u n d

Improvement and Seismic and

Lateral Loads Committees, has

authored or co-authored over 45 technical papers and has

presented at conferences throughout the U.S. His areas of expertise

are cast-in-place piles, foundations in Karst and foundation design

for seismic conditions. Lemnitzer is assistant professor at the

University of California in Irvine. She holds a Ph.D. in structural

engineering from UCLA as well as a M.S. from California State

University, Long Beach and B.S. from the University of Applied

Science in Leipzig, Germany, where she was awarded a Fulbright

Scholarship to continue her education. Her research interests lie at

the interface of geotechnical and structural earthquake

engineering, including soil structure interaction, lateral design of

deep foundations, large scale and shake table testing, and seismic

behavior of bridge foundation systems.

Siegel comments on the state of foundation engineering, saying

“At no time in history has the practice been as challenging as it is

now.” Ambitious projects, stringent design codes, the likelihood of

Timothy C. Siegel, P.E., G.E., D.GE, co-editor

Page 35: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 35

litigation and high expectations require engineers to effectively

intertwine theory and experience, he adds. At a time when many

technical journals are focused on the former, the DFI Journal plays a

vital role by offering a balance between theory and experience. This

is one reason the DFI Journal is a “leading platform for technology

transfer on design and construction of deep foundations and

ground improvement.”

Lemnitzer says she looks forward to working with colleague Tim

Siegel as co-editor of the DFI Journal and hopes to further enhance

the reputation of the Journal and its circulation in the geotechnical

community. “We are determined to seek the best deep foundation

research from across the world and combine it with the most

innovative design projects currently built, hereby creating a unique

stage for intellectual exchange, transfer of knowledge and

professional development.” The DFI Journal provides this

alternative approach compared to traditional scientific journals, she

“We are determined to seek the best deep

foundation research from across the world

and combine it with the most innovative

design projects currently built, ...”

says, and she looks forward to widening the audience through

“hands-on, understandable publications” that can make lasting

impacts on our foundation industry.

Theresa Rappaport, DFI’s executive director, says that DFI is

striving to increase the Journal readership and thinks the co-editors

Siegel and Lemnitzer will help towards that goal. The Journal is the

“perfect vehicle,” she says, for achieving DFI’s mission to

disseminate practical and useful content to the deep foundations

construction industry and be the information resource for design

and construction of foundations and excavations.

DFI Journal publishes practice-oriented, high quality papers related

to the broad area of deep foundation engineering and construction.

Papers are welcome on topics of interest to the geo-professional

community. This includes all systems designed and constructed for

the support of heavy structures and

excavations. Submissions are welcomed

via the online submission site at

http://www.edmgr.com/dfi.

The co-editors can be contacted by

email at [email protected]

and for more information please visit

www.maneyonline.com/dfi.

Current and past issues of DFI Journal

are available online to DFI members at no

cost as a member benefit by signing-in to

My DFI and selecting the Journal from the

left-hand menu. Members and non-members can order printed

copies of the 2007-2013 volumes of the Journal from the

publications page of www.dfi.org; members at preferential rates.

Members can also subscribe to the 2014 print issues at a discounted

rate. DFI Journal is available to institutions as a print and online or

online-only subscription. Details of 2014 rates and ordering

information are available at www.maneyonline.com/pricing/dfi.

Author and Subscriber Information

Anne Lemnitzer, Ph.D., co-editor

Save the Date

September 18-20, 2014

Conference on Deep Foundation Technologies for Infrastructure Development in India

DFI of India, in collaboration with the Indian

Geotechnical Society – Delhi Chapter and Indian

Institute of Technology Delhi, will present the 2014

Conference on Deep Foundation Technologies for

Infrastructure Development in India on September

18-20, 2014 at IIT Delhi. Mark your calendars today!

Page 36: DFI Magazine March/April 2014

36 • DEEP FOUNDATIONS • MAR/APR 2014

800.348.1890 HMC-US.COM

Be the most versatile player on the worksite with the new Self-Contained Track Rig (STR). While other machines in

its class can perform only one function without the ability to switch tools, the STR tops them all by easily converting

from the Impact driver to the Vibro driver to the drill tool when installing small piles for solar or other applications.

One machine with the fl exibility of three tools right at your fi ngertips makes you the MVP of any worksite.

Discover how the STR can transform your business. Call us today to fi nd out how you can pre-order an STR.

STR

Page 37: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 37

Did you know that you can get help with searches by typing the

word “tips” in the search box.

The search box allows you to search for keywords within the

Publications, Members and Terms databases.

You may enter one or more keywords, separated by one space,

in the search text box above. You can then press the Enter key or

click on the button to initiate a search.

Normally the search engine will only return database entries

that contain a match for ALL of the keywords entered. The keyword

may appear anywhere within the database entry, and case is not

significant. So entering the keyword ab will match on words like

absolute and taxicab and fabricate.

For the Publications database, the search engine will look in

the SUBJECT, ARTICLE TITLE, SUMMARY and AUTHOR fields

for matches.

For the Members database, the search engine will look in

the ORGANIZATION, MEMBER NAME and SERVICES fields

for matches.

For the Terms database, the search engine will look in the

ENGLISH field for matches.

When searching through the Members and Terms database it is

sometimes useful to be able to search for names or terms that begin

with a sequence of letters. For example, companies that begin with

American. Any keyword that ends with an asterisk will match this

way in the Members and Terms databases. So to find companies

like the example above, use the keyword American*. The keyword

A* finds all companies that begin with A, etc. When you use this

kind of “begins with” keyword in the Members database it will only

be matched against the ORGANIZATION and LAST NAME.

WWW.DFI.ORG

DFI Website: Did You Know?

Page 38: DFI Magazine March/April 2014

A leading global insurance company enterprise that delivers sustainable protection for your deep foundation operations.

HOUSTON INTERNATIONAL INSURANCE GROUP

Have your agent contact: [email protected] 770.933.3418

EASY ACCESSfor your agent to (4) wholly-owned

insurance carriers with ‘A’ ratings by A.M. Best Company

ALL LINESof coverage with market-competitive rates

KNOWLEDGEABLEunderwriters in foundation / pile driving construction trades

Page 39: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 39

My Seven Year Stint at DFI

It’s hard to believe I’ve

been the executive

editor of DFI’s Deep

Foundations magazine

for seven years. When

I began, the magazine

appeared four times a year. Since 2012,

there have been six issues each year, or 50%

more articles and ads, with no additional

staff. (Disclosure department – we did use

two freelance writers for a total of six

articles over two years, so it wasn’t a single-

handed effort, but I’m still proud.)

DFI is different than it was when I

became editor. I’ve been a witness to many

changes the DFI Trustees have made, the

introduction and subsequent growth of the

DFI Regional Chapters is one. Another

positive change was that of hiring Technical

Activities Manager Mary Ellen Bruce to

oversee the 15 technical committees.

Perhaps the most remarkable change has

been the growth of the DFI Educational

Trust and the money disbursed to students.

The generosity of the DFI members is

impressive. I see a profession proud of its

accomplishments and one whose members

give to help others.

What have I been doing on a day-to-day

basis over those years? As executive editor,

I’ve been wading through technical papers,

PowerPoint presentations, press releases,

conference programs, seminar and short

course programs, and juggling subject

matter among DFI’s areas of deep

foundation concentration. I remain

impressed by the fact that every DFI

member who writes for the magazine and

serves on a committee also has a “real” job!

I also picked members’ brains about

what subjects are important and what’s new.

I spent more time imploring DFI members

to write articles. Then there is the ancillary

aspect, that of putting a magazine together.

I’ve been doing that for decades, if I count

my prior editorship at Civil Engineering

(ASCE), and I still like that part of the job.

It’s something akin to a 500-piece puzzle. I

thank Karol Paltsios, magazine and advertis-

ing manager, and Faye Klein, graphic designer,

for making all those pieces come together.

My admiration for Theresa Rappaport is

endless. She is always on top of a multitude

of details, juggling numberless priorities and

being patient. The talented, friendly and

helpful DFI staff reflect her example. I wish

the best to all of them and to my successor,

Helen Robinson.

Finally, the DFI members are terrific

people. Everyone I’ve met or dealt with

electronically over the years has been highly

professional, knowledgeable and devoted

to the deep foundation industry and to DFI.

It’s all been engrossing, interesting and

fun. I’ve loved doing it. I will miss the job

and all the people, and contributing to DFI.

So why am I leaving? I wonder.

Thanks! ... Virginia Fairweather,

Executive Editor, Deep Foundations

Page 40: DFI Magazine March/April 2014

International Construction Equipment, Inc

ICE, Inc

301 Warehouse Drive,

Matthews, North Carolina 28104 USA

[email protected]

www.iceusa.com

Ph: 704 821 8200

ICE, Inc

259 Jernee Mill Road

Sayreville, New Jersey 08872 USA

[email protected]

www.iceusa.com

Ph: 704 821 8200

Hammer & Steel, Inc.

11916 Missouri Bottom Rd.

Hazelwood, Missouri 63042 USA

Toll Free: 1.800.325.PILE (7453)

[email protected]

Ph: 314.895.4600

Hammer & Steel, Inc.

401 West Channel Rd.

Benicia, California 94510 USA

Toll Free: 1.877.224.3356

[email protected]

Ph: 707.746.7820

[email protected]

STEP UPTO THE

FUTUREInnovative Drilling Solutions

Page 41: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 41

REGIONAL REPORT

DFI Middle East

Recent announcements regard-

ing mega-projects in the Middle

East have reinvigorated the con-

struction market in the region. In

Qatar, the country is bracing for a

new wave of construction pro-

jects to support the 2022 FIFA

World Cup, and in Saudi Arabia,

the completion of the foundation

works for the 3,300 ft (1,006 m)

high Kingdom Tower was

announced in December 2013.

In Dubai, the construction indus-

try is expecting a significant boost

with the city winning the bid to

host the World Expo in 2020. We expect the DFI Middle East

Chapter’s technical activities to surge over the next couple of years,

in tandem with these developments.

The Second DFI Middle East Conference (DFIMEC) takes place in

Dubai on April 2-3, 2014. The first one was held in November

2012, attended by more than 150 participants from the region. This

year’s conference builds on the success of DFIMEC 2012 and

promises to provide a top-quality forum for discussing cutting-edge

technologies and developments in the field through case histories.

The aim is to provide an opportunity for the region’s geotechnical

engineering practitioners and academicians to interface, exchange

information and experience, and present the latest developments in

the deep foundation field. The conference will be held at the

American University in Dubai in collaboration with the Dubai

Technology and Media Free Zone Authority.

Conferences and Events

A DFI-sponsored dewatering workshop held in 2013 also

attracted more than 100 local attendees. We expect the 2014

conference to draw more participants, given the recent launch of

new mega-projects in the region. Professor Dr.-Ing. Rolf

Katzenbach of Technical University of Darmstadt is the keynote

speaker at the conference, and he will discuss the latest

developments in pile-raft foundations.

The First Arabian Tunneling Conference took place in Dubai

on December 12-13, with the support of several DFI Middle East

Chapter corporate members. Among the keynote speakers at the

conference were Soren Eskesen, president of the International

Tunneling Association and chief project manager at COWI in

Denmark, and Joe Roby, vice president at The Robbins Company

in Seattle, Wash.

Nakheel, the real estate development firm behind Dubai’s Palm

Jumeirah Island project, recently closed the bidding process for

major foundation works in the proposed $680 million Nakheel

Mall, which will be constructed on the so-called trunk section of

the island. The project includes 4.5 million sq ft (418,000 sq m),

supported by drilled shafts. One of the main challenges is the

construction, waterproofing and protection of three basement

floors, which will be fully submerged in a highly corrosive marine

environment. The project is scheduled to go on a fast track, with a

projected completion date of December 2016.

The Saudi Railways Organization confirmed that the Saudi

Railway Master Plan (SRMP) is on schedule. The project entails

more than $17 billion in infrastructure investments through the

year 2025, with the goal to connect the kingdom’s main cities

through a high-speed rail network. Among the early phases of the

project are the Dammam-Jubail Rail Link and the Mecca-Medina

Projects

Khaldoun Fahoum, Ph.D., P.E.Chair DFI Middle [email protected]

The foundation works for the Dubai Pearl project with more than 500 drilled shafts are complete, and superstructure construction is currently underway.

Page 42: DFI Magazine March/April 2014

42 • DEEP FOUNDATIONS • MAR/APR 2014

This report from the DFI Middle East Chapter was written by Professor Alaa Ashmawy, P.E., dean of engineering, American University of Dubai

High Speed Rail. In addition, the project entails construction of

underground metro systems in three large cities. Among the key

challenges of the project are excavation and tunneling works in the

densely populated urban centers of Riyadh, Mecca and Jeddah, and

more than 800 bridges and tunnels in urban and rural settings to

ensure seamless connectivity of the transportation network.

In early December 2013, the International Bureau of Expositions

formally announced that Dubai will host the World Expo in 2020,

paving the way for a number of large-scale construction projects

that will break records in terms of size and budget. A new urban

center will be developed over 1,100 acres (4.5 sq km) at the

southwestern suburb of Jebel-Ali to accommodate the exposition,

and will connect to key locations in the city through an intricate

transportation network. In parallel, the government of Dubai

unveiled a master plan for six other large-scale developments to be

completed over the next 10 years.

1. The Mohammad Bin Rashid City is a mixed-use development

with over 100 hotels, a large shopping mall, an art gallery and a

theme park. The geotechnical site investigation works for a

number of projects within the city have already taken place, and

the initial foundation designs for several residential and hotel

structures are completed. We expect several foundation tenders

to start circulating for new projects soon.

2. The Dubai Water Canal is a $7 billion mega-project that will

expand the artificial waterway network across the city, and

includes a number of transportation infrastructure works to be

completed by 2017. A key challenge will be the construction of

a 300 ft (91 m) span bridge over the canal, along the city’s

existing 12-lane expressway.

Expo 2020 – Dubai

3. Bluewaters Island is the latest land reclamation project, which

will extend the city’s waterfront by another 4 mi (6.4 km), and

provide space for an entertainment theme park. The project will

feature the world’s largest Ferris wheel, Dubai Eye, which will

require the design and construction of a unique offshore

foundation system. Land reclamation works for the project

have not commenced yet, so it appears that this project is a

longer- term proposition.

4. A similar announcement was made regarding the Dubai

Adventure Studios, which will be completed in time for Expo

2020. This theme park will be built near the Expo Village and

will pose numerous foundation design and construction

challenges, given the unique nature of the structures.

5. The Deira project will be constructed on top of an existing land

reclamation site, offshore of the old city. It will feature a

traditional market, commercial and retail units, and a

recreational pier and marina.

6. The Lagoons is a mixed-use development encompassing two

skyscrapers, the Dubai Twin Towers, as well as a number of

smaller waterfront structures. The site was originally surveyed

and prepared prior to the real estate market recession of 2009,

but work had not commenced. The site was recently transferred

to a new developer, who announced plans to resume construc-

tion. DFI members have confirmed that subsurface exploration

works are underway, and tenders should circulate soon.

The chapter provided scholar-

ships for three students from the

American University in Dubai

(AUD) to spend a semester at

Georgia Tech, as part of the

exchange program between the

two universities. Nourhan Farrag,

G h a l i a G a m a l - E l d i n a n d

Mohammed Khimjee, who have

been on the Dean’s List at their

home university, are members of

the DFI Student Chapter at AUD.

The scholarship fund was

endowed through industry

sponsorships from the DFI 2012

conference in Dubai, and will

provide them with partial coverage of their tuition at Georgia Tech,

where the students registered for their classes in early January.

According to the students, the scholarship allows them to engage in

a unique opportunity to immerse in a new cultural and educational

experience. “We are particularly excited about the opportunity to

take classes in geotechnical engineering and concrete design at

Georgia Tech, and apply them toward our engineering program at

AUD,” said Gamal-Eldin, who is a third year honor student at her

home university.

Education Activities

Secant piles are commonly used to support deep excavations in urban settings in Dubai. For this project in Dubai Media City, the consultant recommended the use of a diaphragm wall.

AUD students Nourhan Farrag, Ghalia Gamal-Eldin and Mohammed Khimjee are attending a semester at Georgia Tech in Atlanta, Ga., through a DFI Middle East Chapter Scholarship.

Page 43: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 43

June 16-20, 2014

This course covers injection grouting as a method to improve soil settlement and strength characteristics, and to decrease permeability of soil and rock masses. Major topics covered include properties of cementitious and chemical grouts, procedures for cement and chemical grouting, field monitor-ing and verification, grouting rock under dams, grouting of rock anchors and micropiles, deep mixing, jet grouting, dia-phragm walls, compaction grouting, slab jacking, structural grouting, and grouting for underground structures. Included in the curriculum is a field demonstration of compaction and permeation grouting, flow of ultrafine cement, grout mixing, use of cellular concrete in annular grouting, overburden drill-ing, grouting of rock anchors, and use of packers.

Grouting Fundamentals & Current Practice

www.csmspace.com

Geotechnical GroupGrazGraz Univ. of Technology

3 5 T H A N N U A L S H O R T C O U R S E :

CSM Grouting DFI.indd 1 12/17/13 4:57 PM

RED: PMS 185

p i l e p r o t e c t i o n t o p s P.O. Box 3153•800 Southwest Boulevard•Kansas City, Kansas•66103

We have you covered,from top to bottom.

p i l e p r o t c t i o n t o p sWWW.PPTKC.COM • 913•207•2460

www.pieresearch.com 800.342.2409

CENTRALIZERSAUGER CORKS

PILE TOPS PIER BOOT TM

QUICK-LOCK HD TM AVAILABLE IN 2”/ 3”/ 4”/ 6” COVER

QUICK-LOCK TM 2”/ 3”/ 4” COVER

Page 44: DFI Magazine March/April 2014

44 • DEEP FOUNDATIONS • MAR/APR 2014

RENTALS • SALES • RPO • TOOLING • PARTS • SERVICE • TECHNICAL SUPPORT

Today’s Best Drilling Solutions

hennessyinternational.com 800-656-6766

FINANCING AVAILABLE

hennessyinternational.com 800-656-6766

MAIN1623 Mission Drive, Ste. #14 • Solvang, CA [email protected] • (800) 656-6766

SERVICE CENTER1046 Carrier Parkway • Bakersfi eld, CA 93308(800) 656-6766

Call or email today!

• Earth Retention Crawler Drills

• Piling Equipment

• Jet Grout & Soilmix Equipment, Pumps, Tooling

• CFA Equipment

• Diaphragm Wall Equipment

• Tunneling Equipment

• Geothermal Drilling Equipment

• Limited Access & Specialty Equipment

• Crawler Cranes

• Reverse Circulation Drilling Equipment

• Casing Oscillators, Hydromills

• Drill Tooling & Accessories

Your Foundation Distributor Since 1988

Diaphragm Wall EquipmentDiaphragm Wall Equipment

Reverse Circulation Drilling Reverse Circulation Drilling

2/3/14

DFI magazine

Hennessy Int’l.Full page ad

- 8.5 x 11 in.- CMYK- Full bleed

For art questions:

Corinne [email protected]

For All Your Drilling Needs!

HII_DFI_FullPageGenericAd0114_fnl.indd 1 2/3/14 9:26 AM

Page 45: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 45

authorities on the construction

and design of deep foundations

for transportation structures.

After 22 years on the faculty at Auburn

University, Brown remains active in

deep foundation practice through his

consulting firm, Dan Brown and

Associates. He is the recipient of the DFI

Distinguished Service Award, ASCE

Martin Kapp Foundation Engineering

Award and the ADSC Outstanding

Service Award.

The elected officers for the 2014 DFI

Educational Trust Board are:

Chairman: David Coleman

Vice Chairman: M. Byrl Williams

Treasurer: Dan Brown

Secretary: Dan Dragone

DFI Educational Trust and ACE

Mentor Program of NJ Annual Golf

Outing at Forsgate Country Club,

Monroe Township, NJ

Awards Reception/Dinner at DFI’s

39th Annual Conference on Deep

Foundations, Atlanta, GA

The Annual Golf Outing

Fundraiser at the Castlewood

Country Club, Pleasanton, CA

Annual Gala Fundraising Dinner

to benefit DFI Educational Trust

Stanley Merjan CCNY Civil

Engineering Scholarship, NY/NJ

October 23

October 27

November

Check for details at www.dfitrust.org

April 29

July 21

August

Osterberg Memorial Lecture and

Dinner in conjunction with the

DFI/ADSC Drilled Shaft Seminar,

Greensboro, NC

The Annual Golf Outing Fundraiser

at Chartiers Country Club in

Pittsburgh, PA

The Ben C. Gerwick Award for

Innovation in the Design and

Construction of Marine

Foundations in conjunction with the

Marine Foundations Seminar

Tarrytown, NY

Upcoming DFI Trust Fundraising Events

David Coleman, [email protected]

DFI Educational Trust Update

Trust Board Meeting at Winter Planning Meeting The DFI Educational Trust Board met on

January 29 in Marco Island, Fla., during the

Institute’s Winter Planning Meeting. A

substantial portion of the day’s agenda was

devoted to the discussion and development

of a five-year strategic plan to cover the

period from 2014-2019. Although the plan

is a work in progress that will be finalized

over the next few months, board members

reached consensus on various initiatives.

In the area of fundraising, the Trust

board set an ambitious goal of raising a total

of at least $1 million by 2019. The efforts

will be intensified in several ways:

members will approach more industry

leaders; expand fundraising drives and

campaigns to Canadian companies; and

explore new fundraising vehicles such as

planned giving, annual appeals, matching

gifts and on-line donations.

The Trust will seek to grow program-

matically by continuing to develop targeted

efforts such as the Women in Engineering

initiative. In addition, the Trust will explore

expanding its scholarship assistance

beyond schools of engineering, making

funding available to students pursuing

studies in other areas relevant to the deep

foundations industry.

Similarly, the Trust is considering

developing programs other than schol-

arships that will help young people enter

the deep foundations industry, by

exploring cooperative relationships with

technical schools and other organizations,

especially those devoting substantial efforts

to STEM (Science, Technology, Engi-

neering and Mathematics) initiatives.

Finally, the Trust board, with the

consent of the DFI Board of Trustees,

amended the Trust’s governance docu-

ments to allow the addition of several At-

Large Trustees who will serve two-year

terms and complement the efforts of the

five regular members. The board will also

add two classes of non-voting Trustees:

Emeritus Trustees, composed of former

Trust board chairs; and Honorary Trustees,

composed of individuals who have in some

way performed outstanding

service to the Trust. The Trustees

are confident that this expansion

will solidify and enhance

fundraising efforts and develop-

ment of the organization.

In addition, David Coleman

of Underpinning & Foundation

Skanska, was elected to a second five-

year term as Trustee (2014-2019), and

Roger Healey of Goettle, was elected to

second two-year term as At-Large Trustee

(2014-2016).

Dan Brown joined

the DFI Educational

Trust Board as trea-

surer effective January

1, 2014. Professor

Brown is also treasurer of DFI’s Board of

Trustees. He is one of America’s leading

Trust Board Welcomes New Treasurer

Dan Brown, Treasurer

Page 46: DFI Magazine March/April 2014

46 • DEEP FOUNDATIONS • MAR/APR 2014

724.443.1533 | www.brayman.com

Heavy Civil and Geotechnical ContractorsMicropiles • Caissons • Sheet Piling • Anchors/Tiebacks

Bridges & Complex Structures • Demolition

Page 47: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 47

McKees Rocks, PA Winchester, VA Punxsatawny, PA

800-245-4420 866-459-5309 877-938-1250

Colloidal Grout Plants Threaded Micropile Pipe

Portable Cement Silos Duplexes, Micropile Subs

Drill Tooling and Foundation Teeth Subs, Adapters, and more

PennDrill Manufacturing is quickly becoming the industries “one stop shop” for all things foundations, geotechnical, and grouting. Our goal is to provide you with high quality products and second to none cus-tomer support. We have two manufacturing facilities, with equipment capable of making your “napkin ideas” a reality. Weather you’re looking to rent or buy equipment, in need of jobsite materials, or need

custom work, our knowledgeable team will get it done. Call today for sales, quotes, or service.

Page 48: DFI Magazine March/April 2014

48 • DEEP FOUNDATIONS • MAR/APR 2014

The Leaders in Soil Mixing forEnvironmental Remediation

for 25 years.

Geo-SolutionsSoil and Groundwater Problems Solved

724-335-7273www.geo-solutions.com

In-Situ:Chemical OxidationChemical Reduction

Stabilization/SolidificationZero Valent Iron/Clay Soil Mixing

Blending of a Wide Variety of Reagents

C

M

Y

CM

MY

CY

CMY

K

Page 49: DFI Magazine March/April 2014

MEMBER PROFILE

DEEP FOUNDATIONS • MAR/APR 2014 • 49

She is “passionate,

committed and

convincing ... It

wasn’t easy,” but

people in the

company are now

aware of

sustainability.

Marine Lasne: Sustainability Crusader

As a young girl in a small town in Brittany,

France, Marine Lasne had some broad,

unfocused goals. For example, she wanted

to practice a profession that served the

public and also served nature, but didn’t

know how. At some point in her long and

thorough education, she realized that

engineers have the potential to change the

environment. Her idea of changing the

world became increasingly focused on

sustainability. “If more emphasis were

placed on the early phases of project

design,” she says, “we wouldn’t have to

spend so much energy to protect the

environment and to repair damage done in

the construction phase.”

Lasne has made extraordinary strides as

an individual engineer toward a sustainable

world. She developed a singular vision of

how the construction world could change,

and has made her mark globally. Her

current title is sustainability director, VINCI

Construction, Soletanche Freyssinet,

where she reaches over 19,000 employees

with her message. She also has been a major

figure in the development of the

Geotechnical Carbon Calculator, with DFI,

EFFC (European Federation of Foundation

Contractors) and other international

construction groups. This tool (see the

Sept/Oct 2013 issue of this magazine) puts

specifics to carbon effects in construction

and offers guidance to the

engineering profession.

Philippe Liausu, deputy

managing director, Menard,

and past president of the

SOFFONS (Syndicat des

Entrepreneurs de Sondages,

Forages et Fondations

Spéciales), worked with

Lasne for about six years on

sustainability issues and

developing the carbon

calculator. He thinks the

carbon calculator’s existence

is “strongly” due to her,

partly he suggests, because

“she has a great facility to

communicate.” Within the

company, Lasne shows “strong determin-

ation to increase awareness of sustainability

issues to all staff.”

Another executive describes Marine

Lasne’s impact on the mammoth company.

Bruno Dupety, executive vice president-

COO, VINCI Construction, recounts how

Lasne joined the firm as a result of the

merger between Soletanche Bachy and

Freyssinet in 2009. Dupety had launched

the motto “Sustainable Technologies.” In

October of that year, Lasne made an

impressive presentation at the company’s

convention in Paris in which, he says, she

“set forth the strategy and tools to attain

sustainability, down to the details.” She is

“passionate, committed and convincing,”

says Dupety. “It wasn’t easy,” but people in

the company are now aware of

sustainability. For Lasne, she says that

presentation was a milestone of her

education and preparation—and her

realization that changing the way design is

done in the first place is one of the keys to

solving the problem.

Lasne’s career path was unusual. She

received her (five year) civil engineering

graduate degree from the Institut National

de Sciences Appliquées in Lyon, during

which she applied to study one year at

Concordia University in

Canada. There she met

students from all over the

world, from many cultures,

and sought knowledge of

those other ways of life. She

realized she really enjoyed

interacting with people from

different countries and

learning how to work with

others. She also earned a

masters in environmental

management, a postdoctoral

diploma awarded by the

Ecole des Mines de Paris.

After that lengthy and

highly-academic prep-

aration, Lasne worked 13

Unusual Career Path

years in the field. Part of her experience was

in France, but major portions were at gas

and oil pipeline sites in various parts of the

world. Sometimes she and other engineers

lived in construction camps at the sites and

endured some stressful work situations.

“We worked for 10 weeks, then went home

for 2 weeks to recover, then began again,”

she says. However she mentions being able

to practice sports there with her coworkers,

which helped maintain a “normal” life.

Those sports included running, squash and

tennis, depending on where she was

including Yemen and South Africa. Lasne

seems to have flourished at her many

arduous overseas assignments.

A brief summary of her career shows

her growing responsibilities. Lasne was an

environmental engineer for AMEC-Spie-

Batignolles in France, during which time

she wrote her thesis, an environmental

impact assessment of the firm’s activities.

Next she worked for ANTEA Group, doing

geotechnical and natural risk assessments.

She particularly liked the ANTEA work on

former quarries, many of which had been

partially backfilled. The work required a lot

of research and investigation as well as

interaction with local citizenry, which made

a lot of sense to her, as the work contributed

to solving some of their problems. Next, she

returned to AMEC Spie-Batignolles, to

Page 50: DFI Magazine March/April 2014

50 • DEEP FOUNDATIONS • MAR/APR 2014

her sports activities contributed to her ease

and skill at interacting with people from

other cultures. Through DFI and other

construction organizations, Lasne has

spread the word about sustainability. She is

the chair of DFI’s Sustainability Committee

and a trustee on the DFI Board of Trustees.

Speaking about her own work, she says she

likes working as a problem solver, helping

corporations deal with complex situations

and getting systems up to speed. She

explores various ways to incorporate

sustainability into construction projects at

different stages of the work. She also enjoys

relating what she has learned from these

experiences to younger generations and

tries to lecture at universities when she can.

She also says in her field, “one needs to

expend a lot of energy even to accomplish

little.” Lasne accepts that and, fortunately,

has a lot of energy and the perseverance to

continue her sustainability crusade.

Virginia Fairweather

and information with them. She is also

“very comfortable” speaking in public,

conveying her knowledge to others. She

works to make things happen, believes in

what she does and is “very persevering,”

according to Verrouil.

Jérôme Stubler, president-CEO,

Soletanche Freyssinet, adds that Lasne “can

transform a complex subject to clear

guidance for our business. She delivers

pragmatic ways to improve our projects

and resolve the details.” Lasne also works

hard and provides leadership through her

enthusiasm. Summing her up, Stubler says,

“she is totally devoted to sustainability.”

Some of Lasne’s early goals, those involving

sports, were much more easily attained, or

so it seems. She was a competitive squash

and tennis player as a youth, and later

found ways to play tennis in Sana’a in

Yemen and to pursue long-distance

running in South Africa. It’s possible that

Spreading the Word on Sustainability

work on oil and gas pipelines in Georgia,

Azerbaijan and Turkey, as a site

environmental manager, coordinating

environmental operational activities and a

staff of 50. Her next job was also for AMEC,

a gas pipeline, where her title was project

environment and socio-economic manager,

here with a staff of about100 people.

Until 2009, Lasne was project environ-

mental manager on a Spiecapag, a 700 km

(435 mi) multiproduct pipeline. Lasne was

based near Johannesburg, South Africa. In

many of these projects, she oversaw

compliance with national, ISO and World

Bank standards. At various points in her

career, she contributed to ISO operational

strategy, making recommendations.

Another colleague, Didier Verrouil,

executive vice president, Eurofrance, North

America, United Kingdom, Soletanche

Bachy, says Lasne likes interacting with her

colleagues and sharing ideas, points of view

Implementing Sustainability

Page 51: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 51

800.527.9948 I cetco.com

YOUR DRILLING PRODUCT EXPERTS

DRILLING FLUIDS I FIELD SERVICES I GROUTS & SEALANTS I POLYMERS & ADDITIVES I TRAINING

Page 52: DFI Magazine March/April 2014

Check out New Orleans’ newest piece of mind.

Made from Nucor recycled steel, our steel pile is driven deep into the Louisiana earth,

and supports this levee that helps protect millions of the most resilient people in America.

Each and every person committed to rebuild New Orleans stronger, safer, and even more prepared for the future.

So it can be filled back up with a sea of fun-loving people.

www.nucoryamato.com

It’s Our Nature.®

60058 NUC Deep Foundations.indd 1 4/28/10 4:13 PM

Page 53: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 53

Check out New Orleans’ newest piece of mind.

Made from Nucor recycled steel, our steel pile is driven deep into the Louisiana earth,

and supports this levee that helps protect millions of the most resilient people in America.

Each and every person committed to rebuild New Orleans stronger, safer, and even more prepared for the future.

So it can be filled back up with a sea of fun-loving people.

www.nucoryamato.com

It’s Our Nature.®

60058 NUC Deep Foundations.indd 1 4/28/10 4:13 PM

Page 54: DFI Magazine March/April 2014

54 • DEEP FOUNDATIONS • MAR/APR 2014

• Does not modify the excavator

• Uses TEI’s patented components

• Electric Drills for micropiles

• Man-Portable to Mini-Drills

• Patented Drifters• Rotary Heads• Feed Systems• Clamp/Breaker• Shock Subs

DRILLINGATTACHMENTS

LIMITEDACCESS DRILLS

DRILLCOMPONENTS

Drilling Attachments and Limited Access

MONTROSE, COLORADO USA

TEI Rock Drills | Montrose, Colorado USA | +1 (970) 249-1515 | teirockdrills.com

Page 55: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 55

AUTHORS

The ability to economically treat large

volumes of soil made large diameter (2.4 m

to 3.0 m [7.8 ft to 9.8 ft]) single auger soil

mixing equipment the equipment of choice

for ISS applications in the U.S. High profile

government-led efforts to clean-up projects

further developed the technology. These

included the Department of Energy-led

project in Piketon, Ohio (1990s), where a

combination of SSM and thermally

enhanced vapor extraction was used to treat

trichloroethylene (TCE) contaminated

soils, and the Geiger Oil Superfund Site

where ISS and IST were used to remediate

chromium, lead, PCB and VOC

contaminated soils near Charleston, S.C.

in1994. The technology had a great impact

on the former manufactured gas plant

(MGP) industry. From the late 1800s

through the early 1900s manufactured gas

(produced from the gasification of coal) was

FEATURE ARTICLE

Soil mixing at an MGP site in northern N.Y.

Ken Andromalos, P.E., vice president, and Daniel Ruffing, EIT, project manager, Geo-Solutions

part of the U.S. EPA’s Superfund Innovative

Technology Evaluation Program, Geo-Con

also performed an ISS pilot project at a

Florida Superfund site. This was the first

U.S. EPA-led project using this technology.

In 1990, the first large scale ISS project

used single auger soil mixing equipment at

a contaminated site in Texas. By 1991,

stabilization/solidification (S/S) was the

recommended treatment technology for

over a quarter of the U.S. EPA’s national

priority sites, primarily using ex-situ

techniques. After the initial applications

succeeded, development and use of the in-

situ S/S technology (ISS) was fueled by its

advantages over alternative remediation

options including eliminating the need for

excavation support, dewatering (including

the need for treatment of contaminated

dewatering waters) and double handling of

contaminated soils.

Soil Mixing in Contaminated Soils

The term soil mixing commonly refers to

any process by which reagents (wet or dry)

are added to and mixed with unsuitable or

contaminated soils. Other terms such as

deep mixing method, shallow soil mixing,

deep soil mixing , cutter soil mixing and

trench cutting remixing deep wall are

commonly used by engineers and

contractors in the geotechnical industry to

refer to soil mixing or a particular type of

equipment. The purpose is similar: the

efficient creation of a soil-reagent

composite with improved properties

relative to the in-situ soils. Improvements

for contaminated soil mixing generally

include factors such as strength increase,

permeability reduction and contaminant

mobility reduction. Contaminated soil

mixing is commonly performed in-situ

using single axis large diameter auger

mixing with wet reagent addition. Large

diameter auger mixing in this application is

performed by pumping a liquid reagent

mixture down through a hollow drill stem

into a large auger (auger diameters in the

0.9 m to 3.7 m [3 ft to 12 ft] range) where

the fluid is allowed to exit the system via

ports on the back of the auger and is mixed

with the soils. The result is a soil column

evenly mixed or treated with the reagent.

Subsequent columns are installed in an

overlapping pattern to confirm 100%

coverage of the target treatment area. In the

geoenvironmental industry, the terms used

to describe the application of soil mixing to

the stabilization/solidification and

treatment of contaminated soils are in-situ

stabilization/solidification (ISS) and in-situ

(chemical) treatment (IST).

The Nov/Dec 2013 Deep Foundations

magazine included a brief overall history of

deep mixing methods focused on soil

mixing to solve geotechnical problems. Soil

mixing of contaminated soils originated in

the United States in 1988 when Geo-Con

installed the first non-structural DSM

containment wall to isolate PCB-

contaminated soils and groundwater from

a nearby river. The firm installed the wall

using the first U.S. manufactured multi-

auger soil mixing drill. In the same year,

Contaminated Soil Mixing History

Page 56: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 5756 • DEEP FOUNDATIONS • MAR/APR 2014

the source of light and heat for most major

cities. The process of creating manufac-

tured gas created a significant amount of

wastes, the most prevalent of which were

coal tars. Despite efforts to containerize the

coal tar in subsurface holding tanks, pure

product and by-products (benzene,

toluene, ethylbenzene, xylene, among

others) migrated into the soils and

groundwater beneath and surrounding

MGPs. Some sources state that at one point

in the U.S. over 50,000 MGPs were

operating. Tens of thousands of these sites

still have heavily impacted subsurfaces. The

ISS technology using soil mixing has

proven to be one of the most cost-effective

and technically sound means of addressing

these sites. The Electric Power Research

Institute (EPRI), Georgia Power and other

utility owners have helped advance the

technology through paid research and by

specifying ISS for some of their MGP

projects. The major projects that helped

reinforce ISS for use on MGP sites include

the use of soil mixing for the S/S of coal tar

impacted soils on former MGP sites in

Columbus, Ga., in 1992, and Cambridge,

Mass., in 2001. Today, many major electric

utilities have programs to remediate their

MGP sites using the soil mixing technology.

Soil mixed walls to contain contaminated

soil and prevent lateral migration of

contaminated groundwater are installed

using the same equipment and techniques

that are used in geotechnical applications.

However, these walls are installed to be

non-structural by design. Instead of

Containment Walls

Conceptual stabilized monolith’s impact on groundwater flow

strength improvement, the primary design

parameter is horizontal permeability

reduction. These walls are preferred over

other more conventional, and often less

expensive, cutoff wall types (e.g., slurry

trench cutoff walls) where there is an

elevated safety risk from exposure to

harmful constituents. Examples of early

applications of cutoff walls include two

projects involving the containment of

chemical warfare material with the

included risk of encountering unexploded

ordnances at a former U.S. Army facility in

1999. A more recent application involved

installing a DSM wall at a DOE facility to

contain tritium contamination in 2011.

In-situ solidification/stabilization (ISS)

refers to processes that utilize a binding

agent to manipulate the physical properties

of contaminated soils in place. In most

cases, ISS leaves the contaminants

chemically unaltered, but their impact on

the surrounding subsurface is greatly

reduced. ISS is the most common form of

soil mixing used for contaminated soil

remediation and Portland cement is by far

the most common binding reagent used.

Other common reagents include blast

furnace slag, fly ash, activated carbon,

bentonite clay and organophilic clay. Many

of these reagents are used in combination

with Portland cement to achieve property

improvements that would not be possible

if Portland cement were used alone. The

most common improvement objectives for

ISS projects are permeability reduction and

strength increase, but contaminant

mobility reduction objectives are

becoming more common.

In terms of volume mixed, the most

common appl ica t ion o f ISS for

contaminated soil remediation is for the

remediation of DNAPL (dense non-

aqueous phase liquids, those denser than

water) impacted soils resulting from former

manufactured gas plant (MGP) or wood

treating operations. ISS has found wide-

scale use in these applications because

other remediation alternatives are limited

by the properties of the coal tar and

creosote byproducts found on these sites,

both of which are viscous DNAPL materials

at the temperature ranges found in the

subsurface. Excavation and disposal can be

a competitive alternative to ISS for the

remediation of these sites in terms of cost

and treatment efficacy, but excavation and

disposal cause greater impact to the

surrounding community in nuisance

odors, public health concerns and

increased truck traffic than ISS. MGPs are

commonly located in heavily traveled

former industrial or commercial centers

that have since been converted into mixed-

use res ident i a l and commerc ia l

neighborhoods that are sensitive to the

impacts caused by excavation and disposal

operations. ISS has become an accepted

alternative for MGP and wood treating site

remediation, and in many cases, the

preferred alternative.

In 2012, ISS was used to remediate MGP

impacted soils in Sacramento, Calif. On this

project, ISS with Portland cement and

granular regenerated activated carbon was 3used to S/S 31,000 m (41,000 cu yds) of

coal tar impacted soils down to a maximum

depth of 12 m (40 ft) below ground surface.

This was the first documented use of ISS for

an MGP site remediation in California.

Another recent use of ISS was for the S/S of

wood treating impacted soils in

Portsmouth, Va. On this project, ISS with

Portland cement and organophillic clay was 3used to S/S 36,000 m (47,000 cu yds) of

creosote impacted soils to depths ranging

from 2.4 to 8.2 m (8 to 27 ft). This work was

overseen by the Norfolk District of the U.S.

Army Corps of Engineers.

In-situ treatment (IST) refers to processes

that use reagents to purposely alter harmful

contaminants in place. In some cases, IST

converts contaminants into inert

compounds, and in other cases into less

harmful compounds. IST is generally

performed using one of two chemical

processes, chemical oxidation or chemical

reduction, referred to as in-situ chemical

In-situ Treatment

oxidation (ISCO) and in-situ chemical

reduction (ISCR). Treatment objectives

vary widely, ranging from contaminant

mass reduction to complete contaminant

mass destruction. Common reagents

include zero valent iron (ZVI), potassium

permanganate, sodium persulfate, ferrous

sulfate, calcium polysulfide, biological

nutrients and hot air. Commonly, other

reagents are injected with the main reagent

to catalyze the chemical reaction. These

other catalyzing reagents include lime,

soda ash, quick lime and phosphoric acid.

The widest application of IST to con-

taminated soil remediation has been in the

use of ZVI and bentonite clay added to

remediate chlorinated solvent impacted

soil. The concept of using ZVI delivered in a

bentonite slurry via soil mixing was

developed and patented by DuPont in the

early 90s. DuPont has since donated the

patent and royalty rights to Colorado State

University. In the authors’ experience, the

Large diameter soil mixing augers

Soil mixing with potassium permanganate

Page 57: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 5756 • DEEP FOUNDATIONS • MAR/APR 2014

the source of light and heat for most major

cities. The process of creating manufac-

tured gas created a significant amount of

wastes, the most prevalent of which were

coal tars. Despite efforts to containerize the

coal tar in subsurface holding tanks, pure

product and by-products (benzene,

toluene, ethylbenzene, xylene, among

others) migrated into the soils and

groundwater beneath and surrounding

MGPs. Some sources state that at one point

in the U.S. over 50,000 MGPs were

operating. Tens of thousands of these sites

still have heavily impacted subsurfaces. The

ISS technology using soil mixing has

proven to be one of the most cost-effective

and technically sound means of addressing

these sites. The Electric Power Research

Institute (EPRI), Georgia Power and other

utility owners have helped advance the

technology through paid research and by

specifying ISS for some of their MGP

projects. The major projects that helped

reinforce ISS for use on MGP sites include

the use of soil mixing for the S/S of coal tar

impacted soils on former MGP sites in

Columbus, Ga., in 1992, and Cambridge,

Mass., in 2001. Today, many major electric

utilities have programs to remediate their

MGP sites using the soil mixing technology.

Soil mixed walls to contain contaminated

soil and prevent lateral migration of

contaminated groundwater are installed

using the same equipment and techniques

that are used in geotechnical applications.

However, these walls are installed to be

non-structural by design. Instead of

Containment Walls

Conceptual stabilized monolith’s impact on groundwater flow

strength improvement, the primary design

parameter is horizontal permeability

reduction. These walls are preferred over

other more conventional, and often less

expensive, cutoff wall types (e.g., slurry

trench cutoff walls) where there is an

elevated safety risk from exposure to

harmful constituents. Examples of early

applications of cutoff walls include two

projects involving the containment of

chemical warfare material with the

included risk of encountering unexploded

ordnances at a former U.S. Army facility in

1999. A more recent application involved

installing a DSM wall at a DOE facility to

contain tritium contamination in 2011.

In-situ solidification/stabilization (ISS)

refers to processes that utilize a binding

agent to manipulate the physical properties

of contaminated soils in place. In most

cases, ISS leaves the contaminants

chemically unaltered, but their impact on

the surrounding subsurface is greatly

reduced. ISS is the most common form of

soil mixing used for contaminated soil

remediation and Portland cement is by far

the most common binding reagent used.

Other common reagents include blast

furnace slag, fly ash, activated carbon,

bentonite clay and organophilic clay. Many

of these reagents are used in combination

with Portland cement to achieve property

improvements that would not be possible

if Portland cement were used alone. The

most common improvement objectives for

ISS projects are permeability reduction and

strength increase, but contaminant

mobility reduction objectives are

becoming more common.

In terms of volume mixed, the most

common appl ica t ion o f ISS for

contaminated soil remediation is for the

remediation of DNAPL (dense non-

aqueous phase liquids, those denser than

water) impacted soils resulting from former

manufactured gas plant (MGP) or wood

treating operations. ISS has found wide-

scale use in these applications because

other remediation alternatives are limited

by the properties of the coal tar and

creosote byproducts found on these sites,

both of which are viscous DNAPL materials

at the temperature ranges found in the

subsurface. Excavation and disposal can be

a competitive alternative to ISS for the

remediation of these sites in terms of cost

and treatment efficacy, but excavation and

disposal cause greater impact to the

surrounding community in nuisance

odors, public health concerns and

increased truck traffic than ISS. MGPs are

commonly located in heavily traveled

former industrial or commercial centers

that have since been converted into mixed-

use res ident i a l and commerc ia l

neighborhoods that are sensitive to the

impacts caused by excavation and disposal

operations. ISS has become an accepted

alternative for MGP and wood treating site

remediation, and in many cases, the

preferred alternative.

In 2012, ISS was used to remediate MGP

impacted soils in Sacramento, Calif. On this

project, ISS with Portland cement and

granular regenerated activated carbon was 3used to S/S 31,000 m (41,000 cu yds) of

coal tar impacted soils down to a maximum

depth of 12 m (40 ft) below ground surface.

This was the first documented use of ISS for

an MGP site remediation in California.

Another recent use of ISS was for the S/S of

wood treating impacted soils in

Portsmouth, Va. On this project, ISS with

Portland cement and organophillic clay was 3used to S/S 36,000 m (47,000 cu yds) of

creosote impacted soils to depths ranging

from 2.4 to 8.2 m (8 to 27 ft). This work was

overseen by the Norfolk District of the U.S.

Army Corps of Engineers.

In-situ treatment (IST) refers to processes

that use reagents to purposely alter harmful

contaminants in place. In some cases, IST

converts contaminants into inert

compounds, and in other cases into less

harmful compounds. IST is generally

performed using one of two chemical

processes, chemical oxidation or chemical

reduction, referred to as in-situ chemical

In-situ Treatment

oxidation (ISCO) and in-situ chemical

reduction (ISCR). Treatment objectives

vary widely, ranging from contaminant

mass reduction to complete contaminant

mass destruction. Common reagents

include zero valent iron (ZVI), potassium

permanganate, sodium persulfate, ferrous

sulfate, calcium polysulfide, biological

nutrients and hot air. Commonly, other

reagents are injected with the main reagent

to catalyze the chemical reaction. These

other catalyzing reagents include lime,

soda ash, quick lime and phosphoric acid.

The widest application of IST to con-

taminated soil remediation has been in the

use of ZVI and bentonite clay added to

remediate chlorinated solvent impacted

soil. The concept of using ZVI delivered in a

bentonite slurry via soil mixing was

developed and patented by DuPont in the

early 90s. DuPont has since donated the

patent and royalty rights to Colorado State

University. In the authors’ experience, the

Large diameter soil mixing augers

Soil mixing with potassium permanganate

Page 58: DFI Magazine March/April 2014

58 • DEEP FOUNDATIONS • MAR/APR 2014

peroxide mixed with the soils, down to a

maximum depth of 8.2 m (27 ft), in

conjunction with fertilizer nutrients and

phosphoric acid. Prior to the treatment

“polishing step,” designed to enhance long

term biodegradation, a significant amount

of the acetone was stripped from the soils

using hot air soil mixing.

Potential Future Trends and Conclusions

• Increased scrutiny of sustainability related metrics in remedial method evaluation.

• A shift from S/S to treatment as regulators target gross concentration reduction rather

than impact reduction.

• Increased application of ISS to the in-place remediation of saturated sediments. (See

recent EPRI research, including information on the recent pilot study completed in

Springfield, Mass., in 2013).

• Increased viability of ISS to more sites as more applicable leaching/diffusion tests are

accepted. See the new EPA LEAF tests (methods 1313 – 1316) and the ITRC guidance

document (2011).

• Increased application of jet grouting to environmental remediation projects.

• An increase in novel reagent combinations that will further expand the use of soil

mixing to remediate historically difficult contaminants.

• Additional equipment modification and development, including improved batch

plants, drill rigs and quality control that will make soil mixing more cost effective.

The current practices in the soil mixing of contaminated soils were developed over 30

plus years. The technology has been used to stabilize, treat and contain contaminated soils.

The geoenvironmental industry has embraced this technology, particularly over the last 5

to 10 years, and should continue to support soil mixing for contaminated soil remediation.

Better overall understanding of this technology by designers, acceptance of this technology

by environmental regulators, the use of more realistic contaminant leaching methods, and

the further refinement of equipment, technique, and quality control procedures will help

further the growth of this technology.

Close-up of soils mixed with potassium permanganate

application of the ZVI/clay technology to

solve environmental remediation problems

has seen significant increase over the last half

decade, after a relatively quiet period since

the initial applications in the early to mid-90s.

The ZVI/clay soil mixing technology

was used in 2011 to treat a TCE impacted

source zone on the OMC Superfund Site in

Waukegan, Ill. On the Waukegan project,

the ZVI was delivered and mixed with the

soils using a large diameter soil mixing rig

in a mixture with bentonite and water. On 3that project, approximately 6,500 m

(8,500 cu yds) of impacted soils were

treated down to a maximum depth of 7.2 m

(24 ft) BGS. Additionally, ISCR with the

ZVI/clay technology was used in 2012 to

treat PCE impacted soils at a former

wastewater lagoon that contained wastes

from a former industrial dry cleaning

facility in Alberta, Canada. The Alberta 3project included soil mixing 7,500 m

(9,800 cu yds) down to a maximum depth

of 8 m (26 ft).

Less common uses of IST include

oxidizing chlorinated solvents and other

volatile contaminants through adding

oxidants with or without catalysts. ISCO

performed with soil mixing has grown

rapidly over the last half decade as

engineers and owners have adapted the

technology to solve problematic sites. Soil

mixing offers numerous benefits over other

methods of performing IST, including the

potential for a reduced construction

schedule, a reduced cost, a reduced carbon

footprint, and improved contact between

the reagent and contaminated media in a

low permeability or fractured subsurface.

IST was used in combination in 2010 3with ISS for the ISCO and S/S of 5,700 m

(7,500 cu yds) of TCE impacted soils down

to a maximum depth of 5.8 m (19 ft) in East

Rutherford, N.J. Potassium permanganate

was used as the oxidant on that project. On

another project, in Robbinsville, N.J., in

2011, a base-catalyzed sodium persulfate

treatment was used on xylene and pesticide

impacted soils. The soil mixing in Robbins-3ville included treating 2,100 m (2,800 cu

yds) down to 4.6 m (15 ft) BGS. ISCO was

also used in Norwich, N.Y. (2012) in

combination with hot air stripping to treat

acetone impacted soils. The treatment

reagent used in Norwich, N.Y. was calcium

Page 59: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 59

Manufacturer of Quality Concrete Accessories

Your solution to rebar cage alignment.

INTEGRATED SYSTEMS FOR EVERY JOB!INTEGRATED SYSTEMS FOR EVERY JOB!Quick-Lock™ pier wheels are made of durable, noncorrosive plastic. One model fits numbers 3 through 5 rebar ties and two models fit 3 through 7 rebar ties. Quick - Lock™ wheels of various sizes handle concrete cover of 2" to 4". They are also perfect for a variety of other applications where concrete cover must be maintained.

Bar Boosters™ and Quick-Lock™ pier wheels are the economical solution for support and alignment of reinforcing steel cages. Bar Boosters™ are made of durable, noncorrosive plastic and attach to rebar of any size. Bar Boosters™ handle concrete cover of 3". They are also great for supporting reinforcing steel over waterproofing, in mat foundations and providing vertical support of slurry wall mats.

Bar Booster TMBar Booster TMQuick - Lock

Quick - Lock

Quick-Lock HD™ installation is a simple process, and is designed to properly position a reinforcing steel cage in a drilled shaft. Quick-Lock HD™ pier wheels are made of durable, noncorrosive plastic and fit numbers 3 through 7 rebar ties and handle 2" to 6" of concrete cover. They are also perfect for a variety of other applications where concrete cover must be maintained.

Pier Boots™ and Quick-Lock HD Heavy Duty Pier Wheels™ are your heavy duty solutions to rebar cage alignment. Pier Boots™ are made of durable, noncorrosive plastic and attach to rebar sizes #6 thru #14. Pier Boots™ handle 3" of concrete cover. They are also great for supporting reinforcing steel over waterproofing, in mat foundations and providing vertical support of slurry walls.

Pier Boot ™Quick - Lock HD™

Pier Boot ™Quick - Lock HD™

Centraligner Pier Sled and Hijacker Pier Bolster™ ™ Centraligner Pier Sled and Hijacker Pier Bolster™ ™

From PIERESEARCH comes the top of the line solution to cage-positioning problems consisting of two 7,500 psi high-strength grout devices, the Centraligner™ Pier Sled and Hijacker™ Pier Bolster.

Centraligner™ Pier Sled contains a notch for the spiral or circle tie and has four sets of integral, embedded 16 gauge galvanized wires for ease of installation. Centraligner™ Pier Sleds handle 2" to 9" of concrete cover. The sled's shape prevents the cage from hanging on the casing and it doesn't protrude into the interior of the cage so interference with the tremie is not a concern.

The Hijacker™ Pier Bolster is disk-like in shape and contains 12 gauge galvanized looped tie wires for installation. The high-strength grout supports the weight of the cage and will not shatter should the cage strike the casing or some other object. The Hijacker™ Pier Bolster can handle 3" or 6" concrete cover. Because the sled and the bolster are tied to the cage, the possibility of them becoming detached is eliminated.

For more information about these and other products or a FREE SPEC KIT, visit us at

www.pieresearch.com or call 800. 342.2409

“Helping To Build A Better Foundation For America!”©

Visit our website for information on our Concrete Wheels and Concrete Slurry Wall Sleds!

C

M

Y

CM

MY

CY

CMY

K

Magazine Ad DFI copy.pdf 1 1/24/14 5:00 PM

Page 60: DFI Magazine March/April 2014

EQUIPMENT CORPORATION OF AMERICA

B U I L D I N G F O U N D A T I O N S S I N C E 1 9 1 8

TORONTO 166 Bentworth Ave Toronto, Ontario M6A 1P7 P 416.787.4259 F 416.787.4362

WASHINGTON, D.C. 6300 Foxley Road Upper Marlboro, MD 20772 P 301.599.1300 F 301.599.1597

PHILADELPHIA PO Box 837 Aldan, PA 19018 P 610.626.2200 F 610.626.2245

PITTSBURGH PO Box 306 Coraopolis, PA 15108 P 412.264.4480 F 412.264.1158

BUILDING A POSITIVE FUTURETOGETHER

BUILDING A POSITIVE FUTURETOGETHER

P R O V E N E X P E R T I S E

ECA is consistently represented on nearly every major and high profile project across the U.S and Canada, and in a variety of capacities. Our success stems from the diversity of our product lines, our best-in-class service and our specialized knowledge to adapt equipment to a variety of projects.

This knowledge and demonstrated success has placed our employees and equipment in crucial roles when and where they are needed the most. Like the widening projects on the Pennsylvania and New Jersey Turnpikes, Ground Zero, levee restoration in the Gulf after Hurricane Katrina, and the post-collapse replacement of the Mississippi River Bridge in Minneapolis. Stadiums? We have had our equipment on basically every major stadium built east of the Mississippi. Environmentally sensitive projects? We have solved customer problems where local emission standards have exceeded Federal EPA standards or where the use of biodegradable and synthetic oils are required.

S E R V I C E S & T E C H N O L O G I E S

➭ New and Used Equipment Sales and Rentals➭ Large Diameter Drill Rigs➭ Soil Mixing@ Slurry Wall Equipment➭ Earth Retention & Micropile Drills➭ Fixed & Telescopic Mast Mobile Piling Rigs➭ Pile Driving Equipment - Diesel

- Air

- Hydraulic Impact

- Free Hanging Vibratory Hammers

- Excavator Mounted Vibratory Hammers

➭ Drilling Tools and Accessories➭ Overburden Drilling Systems➭ Sectional Casing Systems ➭ Equipment Service and Rebuilding ➭ Welding & Fabricating➭ Field Service Fleet➭ Parts, Accessories, Replacement Drill Teeth

Equipment Corporation of America (ECA) was founded in 1918 as a provider of construction, industrial and material handling equipment. Today, ECA focuses primarily on the Foundation Industry and is a premier distributor of Drilling Equipment for Large Diameter Drilled Shafts, Small Diameter Drills for Earth Retention, Dedicated Piling Rigs and Pile Driving Equipment and Accessories. We offer a full array of new equipment manufactured by the Bauer Machine Group and Affiliated companies, supports a large and diverse rental fleet, and provides parts and service from their five locations. Just as in 1918, ECA is the premier provider of reliable and innovative products, services and solutions to the construction industry.

Find out how we can build a foundation together. 1.800.PILE-USA -or- www.ecanet.com

AUTHORIZED DEALER:

Page 61: DFI Magazine March/April 2014

EQUIPMENT CORPORATION OF AMERICA

B U I L D I N G F O U N D A T I O N S S I N C E 1 9 1 8

TORONTO 166 Bentworth Ave Toronto, Ontario M6A 1P7 P 416.787.4259 F 416.787.4362

WASHINGTON, D.C. 6300 Foxley Road Upper Marlboro, MD 20772 P 301.599.1300 F 301.599.1597

PHILADELPHIA PO Box 837 Aldan, PA 19018 P 610.626.2200 F 610.626.2245

PITTSBURGH PO Box 306 Coraopolis, PA 15108 P 412.264.4480 F 412.264.1158

BUILDING A POSITIVE FUTURETOGETHER

BUILDING A POSITIVE FUTURETOGETHER

P R O V E N E X P E R T I S E

ECA is consistently represented on nearly every major and high profile project across the U.S and Canada, and in a variety of capacities. Our success stems from the diversity of our product lines, our best-in-class service and our specialized knowledge to adapt equipment to a variety of projects.

This knowledge and demonstrated success has placed our employees and equipment in crucial roles when and where they are needed the most. Like the widening projects on the Pennsylvania and New Jersey Turnpikes, Ground Zero, levee restoration in the Gulf after Hurricane Katrina, and the post-collapse replacement of the Mississippi River Bridge in Minneapolis. Stadiums? We have had our equipment on basically every major stadium built east of the Mississippi. Environmentally sensitive projects? We have solved customer problems where local emission standards have exceeded Federal EPA standards or where the use of biodegradable and synthetic oils are required.

S E R V I C E S & T E C H N O L O G I E S

➭ New and Used Equipment Sales and Rentals➭ Large Diameter Drill Rigs➭ Soil Mixing@ Slurry Wall Equipment➭ Earth Retention & Micropile Drills➭ Fixed & Telescopic Mast Mobile Piling Rigs➭ Pile Driving Equipment - Diesel

- Air

- Hydraulic Impact

- Free Hanging Vibratory Hammers

- Excavator Mounted Vibratory Hammers

➭ Drilling Tools and Accessories➭ Overburden Drilling Systems➭ Sectional Casing Systems ➭ Equipment Service and Rebuilding ➭ Welding & Fabricating➭ Field Service Fleet➭ Parts, Accessories, Replacement Drill Teeth

Equipment Corporation of America (ECA) was founded in 1918 as a provider of construction, industrial and material handling equipment. Today, ECA focuses primarily on the Foundation Industry and is a premier distributor of Drilling Equipment for Large Diameter Drilled Shafts, Small Diameter Drills for Earth Retention, Dedicated Piling Rigs and Pile Driving Equipment and Accessories. We offer a full array of new equipment manufactured by the Bauer Machine Group and Affiliated companies, supports a large and diverse rental fleet, and provides parts and service from their five locations. Just as in 1918, ECA is the premier provider of reliable and innovative products, services and solutions to the construction industry.

Find out how we can build a foundation together. 1.800.PILE-USA -or- www.ecanet.com

AUTHORIZED DEALER:

Page 62: DFI Magazine March/April 2014

62 • DEEP FOUNDATIONS • MAR/APR 2014

®

Page 63: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 63

AUTHORS

FEATURE ARTICLE

Mill Creek landslide project site (Photo courtesy of Glenn O. Hawbaker, Inc.)

Kessi E. Zicko, P.E., and Paul J. Lewis, P.E., Gannett Fleming, Inc. andRobert E. Johnson, P.E., Pennsylvania Department of Transportation

habitat for the timber rattlesnake and an

area of archaeological interest. Further-

more, it minimized impacts to reservoir

storage capacity and slope restoration due

to fill placement.

The landslide extended approximately

600 ft (183 m) along the length of highway

and spanned an average distance of about

300 ft (91 m) from the scarp toward the

reservoir. Instability occurred in the

portion of the highway embankment that

had been constructed at a slope angle of

1.75H:1V. Field reconnaissance was per-

formed to identify landslide features, and

an exploration/instrumentation program

was conducted in summer 2011 to

investigate subsurface conditions and

identify the location of the failure plane.

Site Conditions

The Mill Creek landslide occurred along the

lower portion of the southbound embank-

ment of State Route 15 adjacent to the Tioga

Reservoir in north central Pennsylvania.

Engineers from the Pennsylvania Depart-

ment of Transportation (PennDOT)

observed a scarp following heavy rains and

snow melt in spring 2011. Although they

saw no damage to the highway, its close

proximity to the road posed a concern for

the long-term stability.

Gannett Fleming evaluated several

alternatives to stabilize the slope and, with

concurrence from PennDOT, selected

driven steel H-piles based on construction

costs and site impacts. The chosen design

minimized land disturbance by using an

existing, inactive roadbed along the toe of

the embankment for the footprint of the

piles. This design avoided wetlands,

Stabilizing the Mill Creek Landslide With Steel H-piles

The program included:

• Seventeen borings aligned along two

cross-sections

• Two open standpipes and four vibrating

wire piezometers

• Ten inclinometers

• Two geophysical lines in the toe region

• Laboratory testing

Soils within the embankment footprint were

typically medium to very dense, granular

materials. In the toe area, the subsurface

profile consisted of a surficial granular layer

overlying glacial lake sediments, which

were underlain by glacial outwash, till and

eventually bedrock. Two natural conditions

in the toe region contributed to slope

instability: 1) artesian pressures up to 5 ft

(1.5 m) above ground surface carried in the

Page 64: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 6564 • DEEP FOUNDATIONS • MAR/APR 2014

Variable Station 1300+00 Station 1303+00

F 50 kips/ft 729 kN/m 75 kips/ft 1,094 kN/mh

s 6 ft 1.8 m 6 ft 1.8 m

r 3 rows 3 rows 4 rows 4 rows

l 25 ft 7.6 m 35 ft 10.7 m

Calculated P 667 lbs/in 1,168 N/cm 536 lbs/in 939 N/cmh

geometry of the failure plane was favorable

to inserting one row of piles spaced 1 ft

(0.3 m) center-to-center along the embank-

ment length near the toe of slope. This

spacing allowed the pile load to be eval-

uated on a per unit length basis and then

distributed onto individual piles based on

spacing and number of rows of piles.

Required lateral pile loads of 50 and

75 kips per ft (kpf) (729 and 1094 kN/m) of

embankment length were calculated at two

representative sections.

An important consideration during design

was the relationship between the required

lateral load from the slope stability based

on limit equilibrium analyses and design of

Limit Equilibrium and LRFD

Slope Stability AnalysesThe project team performed slope stability

analyses initially to evaluate the deformed

slope condition and to calibrate the selec-

tion of soil parameters. The model included

a band of residual strengths along the exist-

ing failure plane to represent the weaker

shear strength of soils that had experienced

deformation. Maintaining the laboratory

test values for the silt layer, back analyses

were then conducted to adjust parameters

of other soil strata until the model was

calibrated to a factor of safety of 1.0.

The engineers subsequently added

vertical structural elements (i.e., piles) to

the calibrated model and applied different

lateral pile resistances at the failure plane to

achieve a target factor of safety of 1.3. The

ResultsFor the selected HP 12x53 pile, the

factored moment and shear resistances and

the results of the computer analyses appear

in Table 2. For the triangularly distributed

lateral load applied to the piles, the

controlling design criterion was moment,

not shear. Although we did not evaluate

deflection under the service limit state, the

maximum pile deflection was 3.4 in (9 cm)

under the strength limit state. The pile

length required to extend below the failure

plane was conservatively selected as 10 ft

(3.0 m) although lesser depths satisfied pile

tip fixity requirements.

The MASW survey provided a

continuous subsurface profile for estima-

tion of the minimum embedment depths

required for lateral pile stability (Figure 2).

The engineers aligned the piles along seven

straight-lined chords over a distance

of 780 ft (238 m) along Old S.R. 15.

We specified test piles to be

driven for verification of the design

lengths before procurement of the

project’s entire 462 piles. The test

piles were 10 ft (3.0 m) longer than

the estimated lengths of the stabiliz-

ation piles to help ensure penetration

into the competent soil stratum. The

test piles were not load tested, but a

pile driving analyzer was used to

monitor driving stresses in the piles.

Variable Station 1300+00 Station 1303+00

M 696 kip·in 79 kN·m 1,744 kip·in 197 kN·mMAX

V -10 kips -44 kN 41 kips 182 kNMAX

glacial outwash and 2) a zone of very soft

glacial lake sediment. Figure 1 shows the

critical cross-section for analysis.

To estimate the extent of the very soft

glacial lake sediment, we conducted a

geophysical survey using the Multichannel

Analysis of Surface Waves (MASW)

technique, which measures the elastic

condition (stiffness) of the ground. The

results of the survey are shown in Figure 2.

Laboratory testing indicated that the

glacial lake deposits classified as silt (ML)

and frequently had natural moisture

contents greater than their liquid limits.

Based on direct shear and consolidated-

undrained triaxial shear strength tests, the

angles of internal friction for the silt layer

were 25º (peak) and 16.4º (residual).

Engineers have monitored the

piezometers and inclinometers since their

installation. The four inclinometers along

the S.R. 15 roadway above the head scarp

have shown no slope movement. The six

inclinometers located on the embankment

below the scarp and within the toe area

have indicated slope deformations up to

1.3 in (3.3 cm). In conjunction with the

field identified scarp and toe bulge, the

measured depths of movement in the

inclinometers provided an estimate of the

location of the failure surface. As shown in

Figure 1, the failure surface was wedge

shaped and followed near the bottom of the

lake deposits.

the pile based on load and resistance factor

design (LRFD). We considered pile loads

that resulted in a factor of safety of 1.3 to be

factored loads for the strength limit state.

Computer analyses, therefore, were used to

evaluate the structural pile integrity

(moment and shear criteria) under the

strength limit state.

We considered a factor of safety of 1.0

for slope stability to correspond to the

service limit state, and design guidelines

indicate that the deflection of piles should

be evaluated under this case. Because the

slope stability model was calibrated to 1.0

without piles, deflection under the service

limit state was not evaluated.

The lateral resistance of soil is dependent

upon soil conditions and pile configura-

tions, and is represented in computer

models using soil response (p-y)

curves. To account for the installation

of the piles within an active landslide,

the engineers reduced the lateral soil

resistance above the failure plane by

applying a p-multiplier of 0.231 in

the analyses. This p-multiplier was a

function of the factor of safety for

slope stability of the soil mass

downslope of the piles, pile spacing

and pile diameter. Soils below the

failure plane were assumed to

provide full lateral resistance.

The engineers conducted lateral pile

analyses using numerous pile config-

urations, center-to-center spacings, and

sizes to determine the most economical

design. Steel HP12X53 piles driven at 6 ft

(1.8 m) centers and in three to four rows,

depending on location along the slide area,

were the most cost-effective option.

Engineers modeled corrosion by reduc-

ing all pile surfaces by 1/16 in (1.6 mm)

and then basing the width, area and

moment of inertia on the reduced pile sec-

tions. The top of the piles behaved in a free

head condition in the lateral pile analyses.

Soil Resistance

Pile Properties

Lateral Load DistributionThe point loads from the slope stability

analyses were triangularly distributed along

the length of the H-piles starting at zero at

the ground surface and increasing to the

intersection of the failure plane (Figure 3).

Engineers determined distribution of the

lateral load on an individual pile by the

following equation and as shown in Table 1:

F (s/r) = ½ l (P )h h

Where:

F = lateral load per unit length of embank-h

ment required by slope stability analysis

s = center-to-center pile spacing

r = number of rows of piles

l = distance from ground surface to failure

plane

P = distributed lateral load at the failure h

plane for use in lateral pile analyses

Figure 1. Subsurface profile along the critical cross-section at Station 1303+00

Figure 3. Distribution of lateral load on a pile

Figure 2. Geophysical MASW subsurface profile along Old S.R. 15 at toe of embankment

Table 1. Distribution of lateral loads for pile design

Table 2. Results of pile analyses for strength limit state

M = Resisting moment of pile = 1,983 kip·in (224 kN·m)R

M = Maximum applied moment in pileMAX

V = Resisting shear force of pile = 98 kips (436 kN)R

V = Maximum applied shear load on pileMAX

Page 65: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 6564 • DEEP FOUNDATIONS • MAR/APR 2014

Variable Station 1300+00 Station 1303+00

F 50 kips/ft 729 kN/m 75 kips/ft 1,094 kN/mh

s 6 ft 1.8 m 6 ft 1.8 m

r 3 rows 3 rows 4 rows 4 rows

l 25 ft 7.6 m 35 ft 10.7 m

Calculated P 667 lbs/in 1,168 N/cm 536 lbs/in 939 N/cmh

geometry of the failure plane was favorable

to inserting one row of piles spaced 1 ft

(0.3 m) center-to-center along the embank-

ment length near the toe of slope. This

spacing allowed the pile load to be eval-

uated on a per unit length basis and then

distributed onto individual piles based on

spacing and number of rows of piles.

Required lateral pile loads of 50 and

75 kips per ft (kpf) (729 and 1094 kN/m) of

embankment length were calculated at two

representative sections.

An important consideration during design

was the relationship between the required

lateral load from the slope stability based

on limit equilibrium analyses and design of

Limit Equilibrium and LRFD

Slope Stability AnalysesThe project team performed slope stability

analyses initially to evaluate the deformed

slope condition and to calibrate the selec-

tion of soil parameters. The model included

a band of residual strengths along the exist-

ing failure plane to represent the weaker

shear strength of soils that had experienced

deformation. Maintaining the laboratory

test values for the silt layer, back analyses

were then conducted to adjust parameters

of other soil strata until the model was

calibrated to a factor of safety of 1.0.

The engineers subsequently added

vertical structural elements (i.e., piles) to

the calibrated model and applied different

lateral pile resistances at the failure plane to

achieve a target factor of safety of 1.3. The

ResultsFor the selected HP 12x53 pile, the

factored moment and shear resistances and

the results of the computer analyses appear

in Table 2. For the triangularly distributed

lateral load applied to the piles, the

controlling design criterion was moment,

not shear. Although we did not evaluate

deflection under the service limit state, the

maximum pile deflection was 3.4 in (9 cm)

under the strength limit state. The pile

length required to extend below the failure

plane was conservatively selected as 10 ft

(3.0 m) although lesser depths satisfied pile

tip fixity requirements.

The MASW survey provided a

continuous subsurface profile for estima-

tion of the minimum embedment depths

required for lateral pile stability (Figure 2).

The engineers aligned the piles along seven

straight-lined chords over a distance

of 780 ft (238 m) along Old S.R. 15.

We specified test piles to be

driven for verification of the design

lengths before procurement of the

project’s entire 462 piles. The test

piles were 10 ft (3.0 m) longer than

the estimated lengths of the stabiliz-

ation piles to help ensure penetration

into the competent soil stratum. The

test piles were not load tested, but a

pile driving analyzer was used to

monitor driving stresses in the piles.

Variable Station 1300+00 Station 1303+00

M 696 kip·in 79 kN·m 1,744 kip·in 197 kN·mMAX

V -10 kips -44 kN 41 kips 182 kNMAX

glacial outwash and 2) a zone of very soft

glacial lake sediment. Figure 1 shows the

critical cross-section for analysis.

To estimate the extent of the very soft

glacial lake sediment, we conducted a

geophysical survey using the Multichannel

Analysis of Surface Waves (MASW)

technique, which measures the elastic

condition (stiffness) of the ground. The

results of the survey are shown in Figure 2.

Laboratory testing indicated that the

glacial lake deposits classified as silt (ML)

and frequently had natural moisture

contents greater than their liquid limits.

Based on direct shear and consolidated-

undrained triaxial shear strength tests, the

angles of internal friction for the silt layer

were 25º (peak) and 16.4º (residual).

Engineers have monitored the

piezometers and inclinometers since their

installation. The four inclinometers along

the S.R. 15 roadway above the head scarp

have shown no slope movement. The six

inclinometers located on the embankment

below the scarp and within the toe area

have indicated slope deformations up to

1.3 in (3.3 cm). In conjunction with the

field identified scarp and toe bulge, the

measured depths of movement in the

inclinometers provided an estimate of the

location of the failure surface. As shown in

Figure 1, the failure surface was wedge

shaped and followed near the bottom of the

lake deposits.

the pile based on load and resistance factor

design (LRFD). We considered pile loads

that resulted in a factor of safety of 1.3 to be

factored loads for the strength limit state.

Computer analyses, therefore, were used to

evaluate the structural pile integrity

(moment and shear criteria) under the

strength limit state.

We considered a factor of safety of 1.0

for slope stability to correspond to the

service limit state, and design guidelines

indicate that the deflection of piles should

be evaluated under this case. Because the

slope stability model was calibrated to 1.0

without piles, deflection under the service

limit state was not evaluated.

The lateral resistance of soil is dependent

upon soil conditions and pile configura-

tions, and is represented in computer

models using soil response (p-y)

curves. To account for the installation

of the piles within an active landslide,

the engineers reduced the lateral soil

resistance above the failure plane by

applying a p-multiplier of 0.231 in

the analyses. This p-multiplier was a

function of the factor of safety for

slope stability of the soil mass

downslope of the piles, pile spacing

and pile diameter. Soils below the

failure plane were assumed to

provide full lateral resistance.

The engineers conducted lateral pile

analyses using numerous pile config-

urations, center-to-center spacings, and

sizes to determine the most economical

design. Steel HP12X53 piles driven at 6 ft

(1.8 m) centers and in three to four rows,

depending on location along the slide area,

were the most cost-effective option.

Engineers modeled corrosion by reduc-

ing all pile surfaces by 1/16 in (1.6 mm)

and then basing the width, area and

moment of inertia on the reduced pile sec-

tions. The top of the piles behaved in a free

head condition in the lateral pile analyses.

Soil Resistance

Pile Properties

Lateral Load DistributionThe point loads from the slope stability

analyses were triangularly distributed along

the length of the H-piles starting at zero at

the ground surface and increasing to the

intersection of the failure plane (Figure 3).

Engineers determined distribution of the

lateral load on an individual pile by the

following equation and as shown in Table 1:

F (s/r) = ½ l (P )h h

Where:

F = lateral load per unit length of embank-h

ment required by slope stability analysis

s = center-to-center pile spacing

r = number of rows of piles

l = distance from ground surface to failure

plane

P = distributed lateral load at the failure h

plane for use in lateral pile analyses

Figure 1. Subsurface profile along the critical cross-section at Station 1303+00

Figure 3. Distribution of lateral load on a pile

Figure 2. Geophysical MASW subsurface profile along Old S.R. 15 at toe of embankment

Table 1. Distribution of lateral loads for pile design

Table 2. Results of pile analyses for strength limit state

M = Resisting moment of pile = 1,983 kip·in (224 kN·m)R

M = Maximum applied moment in pileMAX

V = Resisting shear force of pile = 98 kips (436 kN)R

V = Maximum applied shear load on pileMAX

Page 66: DFI Magazine March/April 2014

66 • DEEP FOUNDATIONS • MAR/APR 2014

SummaryEngineers designed steel piles to stabilize a

highway embankment slope in northern

Pennsylvania. They conducted slope stability

modeling to determine the lateral pile load

required to obtain a factor of safety of 1.3,

which was triangularly distributed from the

top of the piles to the failure plane for the

LRFD lateral pile design. To account for

installing piles within a landslide, the lateral

soil resistance for soils above the failure

plane was reduced using a p-multiplier.

Based on lateral pile analyses and cost, the

design called for Grade 50 HP12x53 steel

piles to be driven at 6 ft (1.8 m) centers and

in three and four rows. A geophysical survey

provided a continuous subsurface profile

that was successfully used to estimate pile

lengths over a distance of approximately 780 ft

(238 m) along the toe of the embankment.

The results of the test pile program are

shown in Figure 2. Pile driving blow counts

were generally less than 10 blows per ft (33

blows per meter) as the pile advanced

through surficial soils and glacial lake deposits.

Blow counts increased as underlying soils

improved, and the estimated blow count

indicating competent material was 20 bpf

(66 bpm). The pile driving analyzer (PDA)

results showed similar trends in resistance.

An aerial view of the pile driving program is

shown at right.

The engineers specified that the piles be

driven their full lengths, or to refusal, and

adjusted the final pile layout based on the

test piles and results of production driving.

The pile lengths at the southern chord of

the project site were increased from 35 to

40 ft (10.7 to 12.2 m) as a result of the test

piles. During production driving in two

small areas, the pile driving records

indicated that competent soil was deeper

than anticipated, so we added 10 piles,

each 60 ft (18.3 m) long. Overall, this was

only a 3% increase for a project with

22,325 lineal ft (6,805 m) of piles.

Pile driving along Old S.R. 15 at the embankment toe (Photo courtesy of Glenn O. Hawbaker, Inc.)

Page 67: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 67

800.348.1890 HMC-US.COM

THE DRILLING REVOLUTION IS HERE

You’ll never look at your current foundation drilling equipment the same way again. Hercules has partnered

with the preeminent drill designer in the world and owner of HPM, Giuseppe Cartechini, to bring the most

robust, highest quality foundation drills in the world to North America. Designed using high-strength

materials, HPM foundation drills provide excellent stability without the need for a large base. That means

you get a high-performing, robust machine at a good value.

Hercules is the exclusive HPM drill dealer in North America. Call us today to fi nd out how you can

pre-order an HPM foundation drill.

Giuseppe Cartechini

HPM HYDRAULIC PERFORMANCE MACHINES

SRL

Page 68: DFI Magazine March/April 2014

68 • DEEP FOUNDATIONS • MAR/APR 2014

WORLD LEADERS IN DEEP FOUNDATION TESTING

LOADTESTDubai, UAESingaporeLondon, UKGainesville, Florida

800.368.1138 [email protected]

Rajiv Gandhi Sea LinkMumbai, India

Venetian Causeway BridgeMiami, Florida

Rosario-Victoria BridgeRosario, Argentina

Carquinez BridgeContra Costa County, California

Loadtest is dedicated to advancing state-of-the-art deep foundation load testing. Founded in 1991, Loadtest specializes in bi-directional deep foundation load testing using the award winning Osterberg Cell®. Through research and hard work, Loadtest has redefined the art of load testing.

TM

Page 70: DFI Magazine March/April 2014

KIEWIT FOUNDATIONS GROUP

Keeping safety in the forefront, Kiewit Foundations Group performs complex geotechnical projects across North America. We deliver innovative and cost-effective solutions tailored to the specific needs of each project. Our range of services include:

• Diaphragm Walls• Slurry Cutoff Walls• Ground Improvements• Drilled Shafts

Kiewit Infrastructure Co.302 South 36th Street, Suite 400Omaha, NE 68131(201) 571-2502

KIEWIT.COM/FOUNDATIONS

Page 71: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 71

TECHNICAL ACTIVITIES

Committee LiaisonsThe beginning of the year is always filled

with conferences and planning meetings for

the geotechnical community. For example,

the Transportation Research Board confer-

ence (Washington, D.C.), ADSC’s (The

International Association of Foundation

Drilling) Annual Meeting (Coronado,

Calif.), DFI’s Workshop on Levee and

Coastal Rehabilitation (Miami, Fla.) and the

GeoInstitute’s GeoCongress (Atlanta, Ga.)

in February, were opportunities to be involved

in the active foundation community.

DFI’s members are involved in many

other organizations. Knowledge and

experience of members involved in other

groups can enhance DFI’s understanding of

relevant issues and changes in the industry

that affect the foundation market and

practices. DFI works closely with the

technical committees of ADSC (Anchored

Committee Webpages

New Landslide Chair, Professor Vern Schaefer

Details on committee projects, members

and publications are available through the

enhanced Technical Committee webpages

on the DFI website at www.dfi.org. Please

see the Groups tab to navigate to pages

dedicated to the activities of each of DFI’s

technical committees, regional chapters,

conference organizing committee,

operational committees, younger members

council and student chapters. All technical

committee pages contain the most recent

chairman’s report; a roster of committee

members with names, companies and

contact information; recent news; related

publications; other important news; and

instructions for joining committees. Please

visit these pages frequently as we update

information often.

We are grateful for the

continued commitment

of Technical Commit-

tee chairs and vice

chairs. Professor Vern

Schaefer of Iowa State

University has accepted

the position of chair of

DFI’s Committee on Deep Foundations for

Landslides and Slope Stabilization.

Schaefer is currently on sabbatical with the

FHWA (Federal Highway Administration)

in Washington D.C., and he led the research

team preparing the www.GeoTechTools.org

system as part of the Strategic Highway

Research Program (SHRP 2).

We thank the outgoing and inaugural

chair, Professor Erik Loehr of University of

Missouri-Columbia, who did a great job

fostering this new committee and initiating

its success. We are delighted that Loehr con-

tinues his involvement with DFI by accep-

ting a position on the Board of Trustees.

Technical Activities Update

TECHNICAL ACTIVITIES MANAGER MARY ELLEN BRUCE

Earth Retention, Drilled Shafts and the

joint ADSC-DFI Micropile Committees),

and we have a good understanding of

mutual interests and benefits of

membership. We welcome members of

relevant technical committees in other

organizations, e.g., AASHTO (American

Association of State Highway and

Transportation Officials), ACI (American

Concrete Institute), ASTM (American

Society for Testing and Materials),

GeoInstitute, USSD (U.S. Society on

Dams), and ASDSO (Association of State

Dam Safety Officials), to share their

experiences by joining a technical

committee and serving as a liaison. The

goal of having liaisons is to improve

communication between committees for

our mutual benefit. If you have interest in a

liaison position, please contact Mary Ellen

Bruce at [email protected].

COMMITTEE CHAIR MIKE MORAN

Augered Cast-in-Place Pile CommitteeThe ACIP Pile Committee was active in

2013, and has planned several activities

through 2014. Our committee last met at

SuperPile 2013 in Minneapolis, Minn., in

May and also at the DFI Annual Conference

in Phoenix, Ariz., in September. The

meetings were well attended and pro-

vided a good opportunity for members to

stay current with our many ongoing com-

mittee activities.

The committee organized a seminar in

November 2013 in New York City on the

design, installation methods and quality

control of ACIP piles and drilled

displacement (DD) piles. The seminar

comprised a morning short course and an

afternoon of case histories involving ACIP

and DD piles. The seminar closed with a

panel discussion on the use of compressed

air during augering

and the pros and cons

of hydraulic fixed

mast installation plat-

forms versus crane

attached augering rigs.

The following com-

mittee members made

this seminar a success:

• Matthew Meyer, Langan Engineering

and Environmental Services, and past

committee chair, spoke about the

evolution of the state of practice due to

technological advancements and avail-

ability of design and installation

guidance. He also discussed best

practices for quality control and con-

struction, and automated monitoring

equipment and testing methods.

Page 72: DFI Magazine March/April 2014

74 • DEEP FOUNDATIONS • MAR/APR 2014

Augered Cast-in-Place PileMike Moran, Cajun Deep Foundations, [email protected]

Codes and StandardsThomas Gurtowski, Shannon & Wilson, [email protected]

Deep Foundations for Landslides/Slope StabilizationProf. Vern Shaefer, Iowa State [email protected]

Drilled ShaftsPaul Axtell, Dan Brown and Associates

[email protected]

Driven PileAndrew Verity, Gerdau

[email protected]

Ground ImprovementMarty Taube, [email protected]

Helical Piles and TiebacksGary Seider Chance Hubbell Power Systems, Inc. [email protected]

Marine FoundationsRick Ellman

Mueser Rutledge Consulting Engineers

[email protected]

MicropilesJonathan BennettBrayman Construction [email protected]

Seismic and Lateral LoadsKwabena Ofori-Awuah

KCI Technologies, [email protected]

Slurry WallsNicolas Willig, Case Foundations

[email protected]

Soil Mixing Dennis Boehm, Hayward Baker, [email protected]

SustainabilityMarine Lasne, Soletanche [email protected]

Testing and EvaluationDon Robertson, Applied Foundation [email protected]

Tiebacks and Soil NailingEd Laczynski, G.A. & F.C. Wagman, [email protected]

DFI Technical Committee Chairs

• Andres Baquerizo, HJ Foundation,

covered equipment, materials and tech-

niques used to construct and assure the

quality of ACIP and DD piles. He also

addressed the effects of construction

installation on foundation performance.

• Morgan NeSmith, Berkel & Company

Contractors, presented commonly

referenced design methods and

comments on these methods based on

his experience with load test results vs.

predicted performance.

• Bernie Hertlein, GEI Consultants, Inc.,

introduced current commercially

available non-destructive test (NDT)

methods for deep foundations and

reviewed their operating principles,

and their various capabilities and

limitations for ACIP and DD piles.

• Case histories were provided by NeSmith

and Satyajit Vaidya, Langan Engineer-

ing and Environmental Services.

The committee is updating the Augered

Cast-In-Place Pile Manual (originally

published in 1990, and updated in 2003).

The text updates will include evolutions in

equipment and procedures over the past

decade. Thank you to Chris Shewmaker,

Illini Drilled Foundations, who is leading

this committee-wide effort.

The ACIP Pile Committee Project Fund

project is practically complete. DFI

awarded the project to Professor Armin

Stuedlein of Oregon State University to

conduct an independent review and

analysis of available pile design

information, load testing results and

associated pile construction costs to

quantify the level of over-conservatism that

results from inappropriate acceptance

criteria commonly included in building

codes. Stuedlein submitted the project

report to the committee for approval, and

the summary will be published this year in

the DFI Journal.

Committee members Dan Stevenson

and Morgan Nesmith of Berkel &

Company have been involved in the

industry-wide effort to update Chapter 18

of the International Building Code. The

DFI Codes and Standards Committee is

working closely with representatives from

ASCE (American Society of Civil

Engineers), GeoInstitute, ASFE/GBA (The

Geoprofessional Business Association),

PDCA (Pi le Driving Contractors

Association) and ADSC (the International

Association of Foundation Drilling) to

propose responsible changes to the

foundations provisions for the betterment

of the industry.

The committee is helping to organize

the SuperPile 2014 conference in Cambridge,

Mass., June 18-20, 2014. Several abstracts

for ACIP piles and DD piles papers have

been received, and we expect the

technologies to be well represented at this

DFI event that covers all piling techniques.

Please contact DFI headquarters at

[email protected] if you are interested in joining

the ACIP Pile Committee. We always

welcome new members.

The DFI Ground

Improvement Com-

mittee is comprised of

government agency

representatives, con-

tractors, engineers

and researchers who

are involved in the

practice of technologies that are intended

to densify, reinforce or enhance drainage

characteristics of ground. The ground

improvement technologies covered

include, but are not limited to, vibratory

stone columns, vibrocompaction, vibro

concrete columns, aggregate piers,

dynamic compaction, wick drains and

grouted inclusions.

The committee recently completed two

liquefaction-related projects. One was a

survey funded through DFI’s Committee

Project Fund to define the state of practice

of ground improvement for liquefaction

COMMITTEE CHAIR MARTY TAUBE

Ground Improvement Committee

Page 73: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 73

mitigation. Tim Siegel of Dan Brown and

Associates led this project, which involved

preparing and issuing a detailed survey,

and compiling and synthesizing the results.

Over 150 practitioners from around the

world responded to the survey and

provided information related to the

prevalence of liquefaction as a design

consideration, and answered specific

technical questions regarding fine-grained

soils, site characterization tools, analytical

and computational methods, references

and resources, mitigation techniques, and

verification methods. Dan Brown and

Associates also contributed financially to

this successful study. The survey results

were reported in the August 2013 volume

of the DFI Journal.

The other project was completed by a

task force of committee members, led by

William (Billy) Camp of S&ME, Inc. The

group completed a study and report,

“Commentary on the Selection, Design and

Specification of Ground Improvement for

Mitigation of Earthquake-Induced

Liquefaction” published in the DFI Journal

in August 2013. This document reviews

the fundamental ground improvement

mechanisms for liquefaction mitigation

and the applicability of and limitation of

the various methods used. This

information is needed by designers when

recommending and specifying various

ground improvement methods for

liquefaction mitigation.

The committee has also finalized its

wick drain guide specifications. Thanks to

Matt Barendse of the New York State

Department of Transportation for working

with me on the project and to the

committee members and DFI Technical

Advisory Committee who provided

valuable comments. The specification

includes suggested text and guidance on

the materials, installation and quality

control and assurance for wick drain

projects, and is available through DFI.

The committee is looking forward to

working more closely with the GeoInsti-

tute’s Soil Improvement Committee,

chaired by Professor Kyle Rollins of

Brigham Young University. The committees

hope to present joint seminars on ground

improvement topics in 2014 and 2015,

possibly in conjunction with ASCE

Geotechnical Sections. We are also working

on initiatives that relate to working

platform safety and guidance for preparing

ground improvement specifications.

If you have any questions or comments,

or if you would like to get involved with the

Ground Improvement Committee, please

contact DFI headquarters at [email protected].

Page 74: DFI Magazine March/April 2014

74 • DEEP FOUNDATIONS • MAR/APR 2014

Mike Walker, P.E.781.721.4057

Giovanni Bonita, Ph.D., P.E.202.828.9511

Bill Walton, P.E., S.E.847.984.3494

Managing Uncertainty UndergroundGeostructural Solutions Delivered Nationwide

Wolf Creek Dam Gallery and Plaza Grouting Jamestown, KY

Iron Works, Inc.Serving the Drilling Industry

MAILING ADDRESS: 257 Caroline Street, Punxsutawney, PA 15767SHIPPING ADDRESS: Mitchell Avenue, Big Run, PA 15715

814-427-2555 • USA/Canada 800-927-0560 • FAX: 814-427-5164www.starironworks.com • e-mail: [email protected]

WE MANUFACTURE ACCESSORIES FOR ALL DRILLING APPLICATIONS

• Mini-Micro PileThreaded Casing

• Metric ThreadedCasing

• Drill Rods

• Equalizer/BalanceRods

• Grout EquipmentTremie Pipe, HoppersRacks and Rods

• Rotary Subs

• Fishing Tools

• Overburden Systems

• Percussion Hammersand Bits

• Drop-Off Bits

• Drag Bits

• Swivels/Flushing Heads

Page 75: DFI Magazine March/April 2014

PTC FRANCE56, rue de Neuilly93130 Noisy-le-SecTel : +33 1 4942 [email protected]

PTC U.S.A.2000, Kentville Rd61443 Kewanee ILTel : +1 309 852 [email protected]

PTC FAR EAST3, Tuas Avenue 16638926 SingaporeTel : +65 6861 [email protected]

PTC CHINA2808, West Huancheng Road201401 Fengxian ShanghaiTel : +86 21 3365 [email protected]

For more information www.ptc.fayat.com

Sales & Rental

PR16s PILING RIG

The PTC PR16S Piling Rig building a PU22 sheet pilewall for a riverbank reinforcement project. The PR16S is equipped with a 16RHFVS, a variable moment and high frequency Vibrodriver, which allows for resonance free driving of piles near sensitive areas.

With interchangeableVibrodriver andhydraulic hammer

Pile Driving &Ground Improvement Equipment

Page 76: DFI Magazine March/April 2014

Hayward Baker DFI MarApr2014.pdf 1 1/6/2014 3:07:45 PM

Page 77: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 77

AUTHORS

FEATURE ARTICLE

Aerial view of the site at final depth while ramp is being removed

Brian Isherwood, MICE, FCSCE, P.Eng.; Tara Brown, P.Geo.; and Jenny Earle, EIT, all of Isherwood Associates; and Paul Kreycir, CET, Anchor Shoring & Caissons Ltd.

However, the bedrock under Toronto is known to contain high

locked-in horizontal stresses around 3.8 MPa (40 tons/sf), much

higher than can be resisted by shoring techniques, resulting in inevit-

able wall movement when excavating deep into the rock. Vertical

joints in the rock are sealed tight by these stresses, but appear as the

excavation proceeds, with dominantly east-west orientation.

The TTC box structures are sensitive to movement, particularly

at the construction joints, typically spaced 12.2 m (40.0 ft) apart.

The TTC enforces strict alert levels for such movements because of

potential service disruption. The tender drawings indicated one of

these joints may be located very near the site’s critical southeast

corner, where differential rock movement along existing vertical

fissures was expected to be at a maximum.

In 2007, Anchor Shoring & Caissons retained Isherwood

Associates to provide an alternative design-build solution for its

shoring proposal, with a mandate to better address the perceived

serious risks to the TTC subway. Isherwood recommended asking

the owner to give up space, allowing relocation of the basement wall

further away from the critical corner. The owner agreed to abandon

all eight basement levels in a 9 m x 35 m (29.5 ft x 114.8 ft)

triangular area and thus move the closest approach to the subway

from the southeast corner nearer to the center of the wall, providing

Giving up Underground Space

Deep Excavation Support at Toronto’s Shangri-La

The Shangri-La hotel and luxury condominium tower is a

landmark of downtown Toronto. Located on prestigious University

Avenue, it comprises 81,104 sq m (873,000 sq ft) and has 66

storeys. Eight underground basement levels provide parking; the

lower four extending into the shale bedrock. The excavation for

Shangri-La was one of the deepest in Toronto’s history.

The site, bounded by city streets on three sides (Simcoe on the

west, Adelaide on the south and University on the east), shares the

block with a 14-storey building (200 University) with 5 under-

ground levels, built from 1957-60. Along the east perimeter, seated

on the rock surface under University Avenue, is the Toronto Transit

Commissions (TTC) University Subway Line, with running track in

a triple-box structure built in the 1950s. This was intended to lie only

2.5 m (8.2 ft) from the property boundary at the site’s southeast corner.

The proposed excavation was to be 26.0 m (85.3 ft) deep. The

surface of the bedrock is relatively flat at about 13.0 m (42.7 ft)

below ground level. Earlier buildings on the site resulted in various

depths of fill and existing foundations.

The bedrock of the Georgian Bay Formation consists of shale

containing inter-beds of calcareous shale, limestone and calcareous

sandstone. It has very pronounced horizontal jointing typical of

shale, but provides a reliable foundation with allowable bearing

pressures of 2.4 MPa (25 tons/sf) for footings and 7.2 MPa

(75 tons/sf) for drilled shafts.

Page 78: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 7978 • DEEP FOUNDATIONS • MAR/APR 2014

location. Because of the complex geometry,

Isherwood’s drafting team created a section

for each of the 27 piles. Tiebacks employed

150 mm (6 in) diameter cased holes in soil

and 115 mm (4.5 in) diameter in rock.

With the 13 m (42.7 ft) high rock face

assumed to be self-supporting, the design

did not attempt to resist the release of the

locked-in stresses. During rock excavation,

prominent east-west vertical joints

appeared. These were of concern at the

south wall where the jointing was

subparallel, creating thin vertical slabs with

the potential to break loose. Isherwood

decided to protect this face with a curtain of

wire mesh and rock-bolts. The east and

west walls were stable, as was the north

rock face under 200 University. At the

remainder of the north wall, between the

existing building and University Avenue,

Isherwood used the mesh as well.

Under 200 University, rock anchors,

installed in a grid pattern directly on the

rock face, were designed to counteract the

building’s weight. Layout included active

anchors at the column lines and passive

anchors elsewhere.

Two-dimensional Fast Lagrangian Analysis

of Continua (FLAC) modeling was

completed for the proposed shoring and

construction sequence at one location in

the center of the east wall. For each stage,

the model provided soil and structure

behavior: soil stress and strain, structural

displacements, axial, shear and moment

forces. Soil parameters were derived from

the geotechnical investigation conducted

by Terraprobe Ltd. The geometry was

based on a 7 m (23 ft) clearance between

the excavation and the subway tunnel.

The baseline analysis was conducted

with a lateral rock stress of 3.8 MPa

(40 tons/sf) and a rock bulk modulus of

3.8 MPa (40 tons/sf). Two parametric

studies were also conducted, using rock

bulk moduli of 2.9 MPa (30 tons/sf) and

7.7 MPa (80 tons/sf). The maximum move-

ments predicted for the 2D displacement at

the center of the excavated face ranged

between 9 and 32 mm (0.35 and 1.26 in).

Isherwood standard practice is to

attach inclinometer casings to soldier piles

at representative locations and targets near

FLAC Modeling

technique to drill the 12 m (39.4 ft) deep,

380 mm (15 in) diameter rock sockets.

Lateral bracing comprised two rows of

rock anchors plus a rock pin at the top of

the pile rock socket, except for University

Avenue. Here, the combination of one or

two upper soil anchors was individually

selected, depending on the subway

a more uniform movement pattern along

the whole east wall.

The shoring design proposed by Isher-

wood comprised standard soldier pile and

lagging, braced by two levels of rock anchor

tiebacks to retain the overburden soils at the

streets. This shoring penetrated and sup-

ported the upper weathered rock. The rock

face below was deemed self-supporting.

Along the east boundary, where the

subway obstructed use of normal rock

anchors, Isherwood proposed substituting

soil anchors (generally two levels) in place

of the tender drawing’s internal bracing,

using the space between the excavation and

subway where adequate. Otherwise, the

design called for threading them between

the subway roof and under existing street

utilities to anchor in the subway fill.

After the award, Isherwood approached

all private and public authorities to obtain

as-built drawings of adjacent structures and

utilities. The subway’s precise location in

the portion adjacent to the site was

unknown, so a survey of the tunnel was

required. Isherwood had information from

work at two adjacent stations, and was

retained to locate the structure. At the same

time, crews installed remote-reading

instruments in the tunnels bordering the

site to determine joint movement

accurately. The survey showed that the

structure was almost 1.0 m (3.3 ft) nearer to

the property than assumed, with offsets of

1.8 m (5.9 ft) and 14.1 m (46.3 ft) at

southeast and northeast corners, and that

the nearest joint was some 9 m (29.5 ft)

north of the critical corner. With the revised

excavation footprint, the smallest clearance

to the subway became 7.3 m (24 ft).

At 200 University, inspection showed

the basements were built in a half-step

scissor arrangement along the building’s

south wall, rather than horizontally as the

tender drawings showed. Isherwood

obtained copies of the original structural

drawings. No construction details were

available, but Isherwood assumed

previous buildings on the Shangri-La site

had been underpinned by concrete panels

to the rock. This proved to be the case.

Anchor Shoring chose double piles at 3.2 m

(10.5 ft) centers along Adelaide and Simcoe

Streets, installed in 915 mm (36 in)

diameter holes. Along University Avenue,

the use of single piles at 3.0 m (9.8 ft)

centers allowed tiebacks to be skewed

where needed to avoid obstructions, such

as abandoned subway shoring piles.

Generally, Toronto practice is to take piles

to full depth rather than perch them on the

rock; Anchor Shoring elected to employ

pipe “flamingos” for the extensions through

the rock. The firm installed the piles in

915 mm (36 in) diameter holes using Bauer

rigs, but employed a down-the-hole hammer

Shoring System

the top of each pile for survey monitoring

by total station. At Shangri-La, the TTC

subway and 200 University both required

more comprehensive monitoring.

At the east wall, the monitoring plan

required for the TTC approval process

comprised pile targets at the top and at each

tieback elevation (as exposed during

excavation) on every pile, as well as four

inclinometers attached to shoring piles

plus two in boreholes behind the shoring,

extending 6 m (19.7 ft) below pile toes.

These instruments had an accuracy of 2 mm

(0.08 in) or better. In the subway tunnel,

electrolevels were installed across 10

expansion joints to record relative

displacement and tilt of the subway box

sections in real time, with an accuracy of

0.1 mm (0.004 in). Precision survey targets

at expansion joints, with an accuracy of

1 mm (0.04 in) or better, served as a back-

up for electrolevel readings. Borehole

extensometers installed at three locations

monitored differential rock movement

directly below the subway tunnel,

recording elongation at sensors 5 m (16.4 ft)

apart along the 30 m (98.4 ft) length.

The inclinometer and pile target moni-

toring indicated that overburden excavation

down to the rock surface resulted in shoring

wall movements in the expected 15 mm

(0.59 in) range, and that excavation of the

unsupported rock face below resulted in a

further 10 to 13 mm (0.39 to 0.51 in), bring-

ing the overburden and shoring with it.

The three extensometers gave very similar

results, indicating lateral movement of the

rock just below the subway of 10 to 12 mm

(0.39 to 0.47 in) at the excavation face and

at the 5 m (16.4 ft) node, reducing to 7 to 8 mm

(0.28 to 0.31 in) at the 10 m node (32.8 ft),

3 mm (0.12 in) at the 15.0 m node (49.2 ft),

2 mm (0.08 in) at the 20 m (65.6 ft) node,

and less than 1 mm (0.04 in) at the remain-

ing nodes. A comparison with the FLAC

predictions indicates the displacement at

the near edge of the subway of 7 to 9 mm

(0.28 to 0.35 in) was significantly smaller

than the prediction of 12 mm (0.47 in).

However, the extensometers indicated the

rock movement did not extend back to the

far side of the subway, so differential dis-

placement across the width of the subway

structure of 7 to 9 mm (0.28 to 0.35 in)

appeared to be larger than the FLAC

prediction of 5 mm (0.20 in).

PTM results for east wall Inclinometer 5 results

Monitoring at TTC: A section of FLAC analysis and actual readings

Page 79: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 7978 • DEEP FOUNDATIONS • MAR/APR 2014

location. Because of the complex geometry,

Isherwood’s drafting team created a section

for each of the 27 piles. Tiebacks employed

150 mm (6 in) diameter cased holes in soil

and 115 mm (4.5 in) diameter in rock.

With the 13 m (42.7 ft) high rock face

assumed to be self-supporting, the design

did not attempt to resist the release of the

locked-in stresses. During rock excavation,

prominent east-west vertical joints

appeared. These were of concern at the

south wall where the jointing was

subparallel, creating thin vertical slabs with

the potential to break loose. Isherwood

decided to protect this face with a curtain of

wire mesh and rock-bolts. The east and

west walls were stable, as was the north

rock face under 200 University. At the

remainder of the north wall, between the

existing building and University Avenue,

Isherwood used the mesh as well.

Under 200 University, rock anchors,

installed in a grid pattern directly on the

rock face, were designed to counteract the

building’s weight. Layout included active

anchors at the column lines and passive

anchors elsewhere.

Two-dimensional Fast Lagrangian Analysis

of Continua (FLAC) modeling was

completed for the proposed shoring and

construction sequence at one location in

the center of the east wall. For each stage,

the model provided soil and structure

behavior: soil stress and strain, structural

displacements, axial, shear and moment

forces. Soil parameters were derived from

the geotechnical investigation conducted

by Terraprobe Ltd. The geometry was

based on a 7 m (23 ft) clearance between

the excavation and the subway tunnel.

The baseline analysis was conducted

with a lateral rock stress of 3.8 MPa

(40 tons/sf) and a rock bulk modulus of

3.8 MPa (40 tons/sf). Two parametric

studies were also conducted, using rock

bulk moduli of 2.9 MPa (30 tons/sf) and

7.7 MPa (80 tons/sf). The maximum move-

ments predicted for the 2D displacement at

the center of the excavated face ranged

between 9 and 32 mm (0.35 and 1.26 in).

Isherwood standard practice is to

attach inclinometer casings to soldier piles

at representative locations and targets near

FLAC Modeling

technique to drill the 12 m (39.4 ft) deep,

380 mm (15 in) diameter rock sockets.

Lateral bracing comprised two rows of

rock anchors plus a rock pin at the top of

the pile rock socket, except for University

Avenue. Here, the combination of one or

two upper soil anchors was individually

selected, depending on the subway

a more uniform movement pattern along

the whole east wall.

The shoring design proposed by Isher-

wood comprised standard soldier pile and

lagging, braced by two levels of rock anchor

tiebacks to retain the overburden soils at the

streets. This shoring penetrated and sup-

ported the upper weathered rock. The rock

face below was deemed self-supporting.

Along the east boundary, where the

subway obstructed use of normal rock

anchors, Isherwood proposed substituting

soil anchors (generally two levels) in place

of the tender drawing’s internal bracing,

using the space between the excavation and

subway where adequate. Otherwise, the

design called for threading them between

the subway roof and under existing street

utilities to anchor in the subway fill.

After the award, Isherwood approached

all private and public authorities to obtain

as-built drawings of adjacent structures and

utilities. The subway’s precise location in

the portion adjacent to the site was

unknown, so a survey of the tunnel was

required. Isherwood had information from

work at two adjacent stations, and was

retained to locate the structure. At the same

time, crews installed remote-reading

instruments in the tunnels bordering the

site to determine joint movement

accurately. The survey showed that the

structure was almost 1.0 m (3.3 ft) nearer to

the property than assumed, with offsets of

1.8 m (5.9 ft) and 14.1 m (46.3 ft) at

southeast and northeast corners, and that

the nearest joint was some 9 m (29.5 ft)

north of the critical corner. With the revised

excavation footprint, the smallest clearance

to the subway became 7.3 m (24 ft).

At 200 University, inspection showed

the basements were built in a half-step

scissor arrangement along the building’s

south wall, rather than horizontally as the

tender drawings showed. Isherwood

obtained copies of the original structural

drawings. No construction details were

available, but Isherwood assumed

previous buildings on the Shangri-La site

had been underpinned by concrete panels

to the rock. This proved to be the case.

Anchor Shoring chose double piles at 3.2 m

(10.5 ft) centers along Adelaide and Simcoe

Streets, installed in 915 mm (36 in)

diameter holes. Along University Avenue,

the use of single piles at 3.0 m (9.8 ft)

centers allowed tiebacks to be skewed

where needed to avoid obstructions, such

as abandoned subway shoring piles.

Generally, Toronto practice is to take piles

to full depth rather than perch them on the

rock; Anchor Shoring elected to employ

pipe “flamingos” for the extensions through

the rock. The firm installed the piles in

915 mm (36 in) diameter holes using Bauer

rigs, but employed a down-the-hole hammer

Shoring System

the top of each pile for survey monitoring

by total station. At Shangri-La, the TTC

subway and 200 University both required

more comprehensive monitoring.

At the east wall, the monitoring plan

required for the TTC approval process

comprised pile targets at the top and at each

tieback elevation (as exposed during

excavation) on every pile, as well as four

inclinometers attached to shoring piles

plus two in boreholes behind the shoring,

extending 6 m (19.7 ft) below pile toes.

These instruments had an accuracy of 2 mm

(0.08 in) or better. In the subway tunnel,

electrolevels were installed across 10

expansion joints to record relative

displacement and tilt of the subway box

sections in real time, with an accuracy of

0.1 mm (0.004 in). Precision survey targets

at expansion joints, with an accuracy of

1 mm (0.04 in) or better, served as a back-

up for electrolevel readings. Borehole

extensometers installed at three locations

monitored differential rock movement

directly below the subway tunnel,

recording elongation at sensors 5 m (16.4 ft)

apart along the 30 m (98.4 ft) length.

The inclinometer and pile target moni-

toring indicated that overburden excavation

down to the rock surface resulted in shoring

wall movements in the expected 15 mm

(0.59 in) range, and that excavation of the

unsupported rock face below resulted in a

further 10 to 13 mm (0.39 to 0.51 in), bring-

ing the overburden and shoring with it.

The three extensometers gave very similar

results, indicating lateral movement of the

rock just below the subway of 10 to 12 mm

(0.39 to 0.47 in) at the excavation face and

at the 5 m (16.4 ft) node, reducing to 7 to 8 mm

(0.28 to 0.31 in) at the 10 m node (32.8 ft),

3 mm (0.12 in) at the 15.0 m node (49.2 ft),

2 mm (0.08 in) at the 20 m (65.6 ft) node,

and less than 1 mm (0.04 in) at the remain-

ing nodes. A comparison with the FLAC

predictions indicates the displacement at

the near edge of the subway of 7 to 9 mm

(0.28 to 0.35 in) was significantly smaller

than the prediction of 12 mm (0.47 in).

However, the extensometers indicated the

rock movement did not extend back to the

far side of the subway, so differential dis-

placement across the width of the subway

structure of 7 to 9 mm (0.28 to 0.35 in)

appeared to be larger than the FLAC

prediction of 5 mm (0.20 in).

PTM results for east wall Inclinometer 5 results

Monitoring at TTC: A section of FLAC analysis and actual readings

Page 80: DFI Magazine March/April 2014

80 • DEEP FOUNDATIONS • MAR/APR 2014

modeling and monitoring program for the

north and east shoring walls. FLAC

modeling of predicted rock movement

provided good insight into the extent of

total movement, and the monitoring pro-

gram confirmed actual movements were

within predictions. The level of monitoring

proved adequate for assessment of shoring

performance throughout construction.

The project team achieved the exca-

vation and construction of the eight level

underground basement structure with

insignificant impact on the existing build-

ing at 200 University and the TTC Subway,

and on adjacent streets and utilities.

The authors acknowledge the contributions of the following contributors: Professor K.Y. Lo for review of rock behavior; Renata Li and Keith Stott, Shangri-La, for

objectivity and support; Marcelo Chuaqui, Monir Precision Monitoring for all monitoring and tunnel survey work; Paul Kreycir, Anchor Shoring, for comradeship and

all the great projects he introduced to Isherwood. Kreycir died in February 2011.

The electrolevels indicated that

movement across the joints never exceeded

0.4 mm (0.02 in), well below TTC alert

levels of 2 mm (0.08 in).

At the north wall (200 University), the

foundation, 1 to 1.5 basements below the

rock surface, comprised a grillage of grade

beams along the column grids cast

integrally with the lowest floor slab to

provide a continuous raft. Because of the

potential for rock expansion to cause

differential movement, the monitoring

plan included precision survey monitoring

of the exterior walls and interior columns,

tape extensometers in north-south arrays

within the lower basement, and two

borehole extensometers installed in the

rock just below the foundations.

Internal precision survey monitoring of

parking level 3 (5th lowest level) indicated

a maximum of 3 mm (0.12 in) into-site

movement of the building’s south wall;

exterior monitoring on the south wall

indicated a maximum of 4 mm (0.16 in)

into-site movement. Monitoring of the east

and west walls of the building indicated

negligible movement throughout.

The tape extensometer monitoring

indicated negligible movement between

adjacent columns, with a maximum

cumulative movement of 3 mm (0.12 in)

across the entire building. The borehole

extensometers indicated up to 3 mm

(0.12 in) movement at the excavated rock

face, 3 mm (0.12 in) at the 5 m (16.4 ft)

node, 2 mm (0.08 in) at the 10 m (32.8 ft)

node and less than 1 mm (0.04 in) at the 15

to 30 m (49.2 to 98.4 ft) nodes, consistent

with the other measurements.

A reasonable explanation for the more

modest movements at the north wall is that

the 1950s construction of that building had

removed the upper 5 to 7 m (16.4 to 23 ft)

of rock, relieving the locked-in stresses,

and the new rock excavation below the

foundations was no more than 7 m (23 ft)

in height. The largest rate of rock

movement occurred under the first two

bays of the building during excavation

through the first 5 m (16.4 ft) of rock. Rock

movement continued with decreasing rates

until excavation was complete.

ConclusionsThe design-build excavation shoring

scheme by Isherwood and Anchor Shoring

succeeding in addressing the serious risks

associated with the project. By communi-

cating all potential risks to the owner and

reducing the basement footprint, with no

impact to the future foundations or parking

capacity, the team limited the risk to the

subway significantly. Using external rather

than internal bracing improved construct-

ability of the shoring system, excavation,

and underground forming.

Another pillar of Isherwood’s effective

risk management was the comprehensive

North wall and 200 University basement

Monitoring at 200 University: A section of actual readings

Page 82: DFI Magazine March/April 2014

82 • DEEP FOUNDATIONS • MAR/APR 2014

IBO®/TITAN SystemMicropiles / Anchors / Soil Nails

• One step fast installation

• Simultaneous drilling and grouting

• Smaller equipment at lower cost

• Low overhead and limited access installation

• Ground improvement (densifi cation)

• Higher skin friction

• Total corrosion protection

The registered trademark is owned by Con-Tech Systems Ltd. and the registered trade-mark Ischebeck Titan® is owned by Friedrich Ischebeck GMBH and is used under license.

www.contechsystems.com Toll-free: 1-888-818-4826

The ORIGINAL

TITAN Bar®!

• Only available through

Con-Tech Systems Ltd.

in North America!

• Never duplicated.

• New competitive pricing.

Page 83: DFI Magazine March/April 2014

DRILL AND GO.

1.888.955.3559 www.kellytractor.com/foundation-groupGet a Link-Belt telescopic crawler crane on site at competitive rental rates.

The new A125 Tier 4 hydraulic drilling rig is a high-performing power house that is efficient and super reliable. It folds down to transport mode and in only 10 minutes is moving down the road to its next big job.

Over 100 machines in our hydraulic rig rental fleet.

Kelly Tractor has 15 years of experience in the foundation industry with the dealer network, parts and service to keep your equipment going.

Page 84: DFI Magazine March/April 2014

At L.G. Barcus and Sons, we’re proud of the fact that we helped pioneer today’s Augered Cast-In-Place Pile foundation engineering and construction technology. AugerPiles have proven their effectiveness again and again. With six decades of experience as a General Contractor and a Specialty Subcontractor, you can feel confident in knowing that we understand your construction requirements. We will work with you to develop the most efficient and cost effective high-strength pile foundation. With offices strategically located around the United States, we can mobilize to your job quickly and inexpensively. Why take a chance with anyone less than a Contractor who pioneered the way and continues to lead today.

“When we needed anexperienced, qualified AugerPile® contractor, we called Barcus.”

REGIONAL OFFICES: Albuquerque • Atlanta • Beaumont/Port Arthur • New Orleans

A Pioneer In AugerPile ConstructionStill Leads The Way

CORPORATE OFFICE:1430 State Ave.Kansas City, KS 66102913-621-1100 • 1-800-255-0180 • FAX 913-621-3288www.barcus.com

Multiple Rigs

Pile Load Testing

Low Headroom Piles

Page 85: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 85

AUTHOR

FEATURE ARTICLE

David B. Paul, Risk Management Center, Lead Engineer, U.S. Army Corps of Engineers, Lakewood, Colo.

USACE Dam and Levee Safety ProgramsUSACE and other federal agencies are using risk-informed decision

processes in dam and levee safety programs. The basic elements are:

potential failure modes analysis, event trees, load frequency

analyses, probabilistic analyses and models, subjective probability

and expert elicitation, and consequence evaluation. USACE

classifies its dams into one of five Dam Safety Action Classifications

(DSAC). We determined that 319 dams were either I, II or III, with

failure modes above the Tolerable Risk Guidelines, which will likely

require a structural modification. The most prevalent actionable

failure mode for dams was seepage and piping that could lead to

breach, see Figure 1.

The manual we are developing with DFI will be limited to

foundation treatments by vertical cutoff-type barriers for dams and

levees, and does not discuss horizontal seepage barriers or other

upstream sealing alternatives. It contains eight chapters:

• Chapter 1 – Introduction

• Chapter 2 – Dam Safety Issues

• Chapter 3 – Geologic Considerations

• Chapter 4 – Engineering Considerations

• Chapter 5 – Continuous Trench Cutoff Walls

• Chapter 6 – Soil Mix Cutoff Walls (excluding jet grouting)

• Chapter 7 – Element Walls (panel and secant)

• Chapter 8 – Jet Grouting and Other Methods including

Geomembrane, Sheet Pile and Vibratory Beam

Seepage Control, Cutoffs Walls Manual: A Progress Report

The U.S. Army Corps of Engineers (USACE) has 704 dams in its

inventory and over 100,000 miles of levees with a capital value of

more than $150 billion. Currently, USACE has over $2 billion of

cutoff wall projects under construction and/or design/planning.

Given the magnitude of the dam and levee safety issues, we are

developing a new engineering manual, Seepage Control Cutoffs for

Dams and Levees. USACE has partnered with Deep Foundations

Institute (DFI) in preparing the manual to ensure that it is

comprehensive and draws from the expertise of the specialty

foundation engineering companies that design, manufacture and

construct seepage control cutoffs around the world.

The manual contains case histories as well as a comprehensive

project statistical summary and guide specifications. The goal of

USACE was to make the manual a state-of-the-art document for use

by USACE districts and the civil engineering profession.

Currently, there are 319 dams classified as high hazard, with

actionable failure modes that will require structural modifications.

The USACE dam inventory has been evaluated and assigned a Dam

Safety Action Classification (DSAC) rating from I to V, with I being

the most serious. We are also evaluating the levee inventory, using

Levee Safety Action Classification (LSAC) ratings assigned from I to V.

Slurry wall construction techniques were developed in the late

1940s in Italy by ICOS. The first use of the slurry trench method of

construction in the U.S. was by the USACE Memphis District in

September 1945, to form a partial cutoff along the Mississippi River

levee just below Memphis, Tenn. A soil-bentonite slurry trench

cutoff was first used for control of underseepage at a major earth dam

at Wanapum Dam on the Columbia River in Washington in 1959. A

cutoff wall using cement-bentonite was first utilized in the U.S. at the

Tilden Tailings Project to store tailings from the Tilden Mine in

Michigan in 1976. And finally the first cement-bentonite cutoff

constructed at a dam on a river retaining a reservoir was completed

in 1978 at the Elgo Dam (formerly the San Carlos Dam) in Arizona.

The USACE has designed and constructed some of the deepest

and most complex cutoff walls for dams since the 1970s. The first

major concrete panel cutoff wall constructed in a dam in the U.S.

was at Wolf Creek Dam by ICOS from 1974-77. Arturo Ressi, who

was a trustee of DFI, was president of ICOS at the time. In 1968,

about 17 years after first being impounded, wet areas and muddy

flows in the tailrace and sinkholes in the downstream toe adjacent

to the switchyard occurred. Other major cutoff wall projects

include Mud Mountain Dam — one of the deepest walls ever

constructed, Beaver Dam, Mississinewa Dam and the Walter F.

George Dam. Center Hill Dam is currently under construction.

Cutoff Wall History

Figure 1. Source of life safety risks for USACE dams

Page 86: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 8786 • DEEP FOUNDATIONS • MAR/APR 2014

Data Management

Seepage Barrier Research Needs

In recent cutoff wall projects, collection,

storage and presentation of geo-referenced

data in GIS (Geographic Information

System) databases advanced significantly.

For Wolf Creek Dam, the Wolf Creek

Information Management System was

developed by Treviicos, Geosyntec and

USACE. The system contains topographic,

geologic, instrumentation, grouting and

cutoff wall QA/QC data, and allows for

rapid and accurate verification of depth

and overlap elements as well as creating a

detailed as-built record. The USACE

Nashville District and Dam Safety Program

is using the system for the post-

implementation evaluation for changing

the DSAC rating. A similar system is in use

at Center Hill Dam, where it allows real-

time data uploads from the equipment and

is tied to the dam instrumentation system

that issues alarms to the contractor and

USACE if a threshold value is exceeded

during construction.

Professor John Rice of Utah State

University has been conducting research

on seepage barrier erosion of various

backfill mixes and gradients for USACE.

Testing has been completed on four cutoff

wall backfill mixes: AV Watkins-cement

bentonite, Herbert Hoover Dike-soil

cement bentonite, New Waddell Dam-

“plastic” concrete, and Wolf Creek Dam-

conventional concrete. As we expected, the

cement bentonite mix had the greatest

amount of erosion and the Wolf Creek

samples exhibited little to no erosion.

Testing showed that the mixes with the

highest degree of erosion also showed an

ability to plug with time. There are two

testing devices developed that simulate

open fractures in rock foundation surfaces

and evaluate erosion characteristics of

different soil types under different flow

velocities and gradients. The testing of

Teton Dam core material is complete, and

the testing of East Branch Dam core

material is ongoing. The testing devices,

instrumentation and test procedures have

been refined to a stable reproducible

condition. The goal is to establish a testing

procedure for the Cutoff Wall Crack

several percent. Deformability can be

steered by using a proper mixture for the

backfill. Finally, permanence refers to the

wa l l ’s s t ab i l i t y w i th re spec t to

decomposition by leaching or aggressive

environmental conditions. Specifications

for cutoff walls should be based on these

design criteria, keeping in mind the details

of a particular structure.

The practical applications of each

cutoff wall construction method are

illustrated by case histories in an appendix

to the manual. They demonstrate how

specific difficulties have been dealt with at

a particular site. One of the most widely

used type of cutoff wall for sites of great

depths in rock is the element wall, see

Figure 3. Well documented case histories

have been published in the technical

literature of the Association of State Dam

Safety Officials, U.S. Society on Dams, and

International Commission on Large Dams.

Case histories for jet grouting and deep

mixing are not as common.

Currently, USACE is going through a

similar screening process for the levee

systems in the U.S. A similar percentage of

seepage and piping issues also exist for

levees, see Figure 2.

The manual will also have various

appendices containing relevant informa-

tion and example contract documents and

specifications. A comprehensive summary

table of projects with relevant information

for each type of cutoff wall has been com-

piled as well as a detailed list of terminology.

The primary factors affecting the

selection of a cutoff are:

• Depth of the pervious strata to be sealed

• Shape (morphology) of the valley

• Characteristics of the embankment and

foundation materials to be sealed

• Loading and stress conditions

• Location of cutoff within embankment

or levee

• Modulus of surrounding material

• Hydraulic gradient at operating

conditions

• Available equipment for making the

cutoff

• Operation requirements

• Site access and constraints

The critical design criteria for cutoff barrier

walls are: deformability, permeability and

permanence. The design of a cutoff wall is a

soil-structure interaction problem, and the

most important issue is to select the proper

modulus of deformation of the wall. The

forces on the wall are different depending

on whether the wall has been constructed

prior to embankment fill or constructed

through the core of an existing dam. When

the embankment is constructed and the

foundation loaded, the alluvial material

will undergo deformations, both in vertical

and horizontal directions. When the

reservoir is filled, the wall has to carry an

extra hydrostatic load. The wall should

have a modulus such that it can follow

these deformations without cracking. If the

wall is too rigid to follow the soil when it

Cutoff Walls

settles under the weight of the dam, load

will be transferred to the wall. The

additional stresses caused by this load

transfer may lead to cracking. Cracks in the

cutoff wall reduce its sealing efficiency. If

the cutoff wall is too plastic, its resistance

to shear forces and internal erosion by

seepage flow is reduced.

If the expected settlements and late

settlements and lateral deformations under

the dam are large, some designers choose

to install the cutoff near the upstream toe of

the dam to decrease the load on top of the

cutoff. However, horizontal deformations

in the dam foundation are not eliminated

in this way and are even greater at that

location than below the central part of the

dam. Finite element modeling is most

suitable to treat such questions and to find

an optimal location for the cutoff wall.

Permeability is considered the cutoff

wall’s most important characteristic.

Deformability addresses the capability of

the wall to sustain without cracking

foundation strains, which may amount to

Erosion test that can be used by the civil

engineering profession. We plan to

conduct further research efforts on “plastic”

concrete mixes. Similar work has been

completed by Hydro Quebec and BC

Hydro as well as in The Netherlands, U.K.

and France.

As summarized previously, the levee

inventory has a significant percentage of

seepage issues that wil l require

remediation. USACE envisions that jet

grouting applications will be more

commonly used, particularly in locations

where there are pipe penetrations through

the levee. The use of jet grouting for these

applications requires careful monitoring

given the high pressures involved.

Additional research is required to develop

monitoring instrumentation to measure

pressures in-situ and to validate overlap of

elements that are created.

Cutoff walls are one of the most effective

engineering solutions for mitigating

seepage and piping failure modes for dams

and levees. Equipment and construction

techniques have been developed and field

tested that show that a uniform cutoff wall

can be constructed to depths in excess of

Conclusions

425 ft (129 m) with a high degree of

confidence. Drilling techniques to assure

overlap and alignment have been proven

on Wolf Creek Dam and other recent dam

safety projects.

Data management systems are an

important improvement in the industry

and profession. The ability to collect and

store geo-referenced data is very important

for the future management of USACE’s dam

and levee inventories. There are other

design standards and documents available.

For example, the U.S. Bureau of

Reclamation is updating its Design Standard,

Chapter 10, Cutoff Walls (1986). In Europe,

EN 1538 – Execution of Special Geotechnical

Works – Diaphragm Wall (2010) is used as a

standard. The Embankment Dams

Committee of ICOLD has also recently

published a bulletin on cutoff walls.

The dam safety profession needs to

research the long-term performance of

various cutoff wall backfills, including their

cracking and erosion potential under high

stress and gradient loading conditions.

USACE anticipates completing and

issuing the new engineering manual,

Seepage Control Cutoffs for Dams and Levees

by the end of September 2014.

Figure 2. Estimated percentage of failure modes by type for USACE levee inventory

Figure 3. Walter F. George Dam – secant wall elements being drilled through casing from the water side of the dam

Page 87: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 8786 • DEEP FOUNDATIONS • MAR/APR 2014

Data Management

Seepage Barrier Research Needs

In recent cutoff wall projects, collection,

storage and presentation of geo-referenced

data in GIS (Geographic Information

System) databases advanced significantly.

For Wolf Creek Dam, the Wolf Creek

Information Management System was

developed by Treviicos, Geosyntec and

USACE. The system contains topographic,

geologic, instrumentation, grouting and

cutoff wall QA/QC data, and allows for

rapid and accurate verification of depth

and overlap elements as well as creating a

detailed as-built record. The USACE

Nashville District and Dam Safety Program

is using the system for the post-

implementation evaluation for changing

the DSAC rating. A similar system is in use

at Center Hill Dam, where it allows real-

time data uploads from the equipment and

is tied to the dam instrumentation system

that issues alarms to the contractor and

USACE if a threshold value is exceeded

during construction.

Professor John Rice of Utah State

University has been conducting research

on seepage barrier erosion of various

backfill mixes and gradients for USACE.

Testing has been completed on four cutoff

wall backfill mixes: AV Watkins-cement

bentonite, Herbert Hoover Dike-soil

cement bentonite, New Waddell Dam-

“plastic” concrete, and Wolf Creek Dam-

conventional concrete. As we expected, the

cement bentonite mix had the greatest

amount of erosion and the Wolf Creek

samples exhibited little to no erosion.

Testing showed that the mixes with the

highest degree of erosion also showed an

ability to plug with time. There are two

testing devices developed that simulate

open fractures in rock foundation surfaces

and evaluate erosion characteristics of

different soil types under different flow

velocities and gradients. The testing of

Teton Dam core material is complete, and

the testing of East Branch Dam core

material is ongoing. The testing devices,

instrumentation and test procedures have

been refined to a stable reproducible

condition. The goal is to establish a testing

procedure for the Cutoff Wall Crack

several percent. Deformability can be

steered by using a proper mixture for the

backfill. Finally, permanence refers to the

wa l l ’s s t ab i l i t y w i th re spec t to

decomposition by leaching or aggressive

environmental conditions. Specifications

for cutoff walls should be based on these

design criteria, keeping in mind the details

of a particular structure.

The practical applications of each

cutoff wall construction method are

illustrated by case histories in an appendix

to the manual. They demonstrate how

specific difficulties have been dealt with at

a particular site. One of the most widely

used type of cutoff wall for sites of great

depths in rock is the element wall, see

Figure 3. Well documented case histories

have been published in the technical

literature of the Association of State Dam

Safety Officials, U.S. Society on Dams, and

International Commission on Large Dams.

Case histories for jet grouting and deep

mixing are not as common.

Currently, USACE is going through a

similar screening process for the levee

systems in the U.S. A similar percentage of

seepage and piping issues also exist for

levees, see Figure 2.

The manual will also have various

appendices containing relevant informa-

tion and example contract documents and

specifications. A comprehensive summary

table of projects with relevant information

for each type of cutoff wall has been com-

piled as well as a detailed list of terminology.

The primary factors affecting the

selection of a cutoff are:

• Depth of the pervious strata to be sealed

• Shape (morphology) of the valley

• Characteristics of the embankment and

foundation materials to be sealed

• Loading and stress conditions

• Location of cutoff within embankment

or levee

• Modulus of surrounding material

• Hydraulic gradient at operating

conditions

• Available equipment for making the

cutoff

• Operation requirements

• Site access and constraints

The critical design criteria for cutoff barrier

walls are: deformability, permeability and

permanence. The design of a cutoff wall is a

soil-structure interaction problem, and the

most important issue is to select the proper

modulus of deformation of the wall. The

forces on the wall are different depending

on whether the wall has been constructed

prior to embankment fill or constructed

through the core of an existing dam. When

the embankment is constructed and the

foundation loaded, the alluvial material

will undergo deformations, both in vertical

and horizontal directions. When the

reservoir is filled, the wall has to carry an

extra hydrostatic load. The wall should

have a modulus such that it can follow

these deformations without cracking. If the

wall is too rigid to follow the soil when it

Cutoff Walls

settles under the weight of the dam, load

will be transferred to the wall. The

additional stresses caused by this load

transfer may lead to cracking. Cracks in the

cutoff wall reduce its sealing efficiency. If

the cutoff wall is too plastic, its resistance

to shear forces and internal erosion by

seepage flow is reduced.

If the expected settlements and late

settlements and lateral deformations under

the dam are large, some designers choose

to install the cutoff near the upstream toe of

the dam to decrease the load on top of the

cutoff. However, horizontal deformations

in the dam foundation are not eliminated

in this way and are even greater at that

location than below the central part of the

dam. Finite element modeling is most

suitable to treat such questions and to find

an optimal location for the cutoff wall.

Permeability is considered the cutoff

wall’s most important characteristic.

Deformability addresses the capability of

the wall to sustain without cracking

foundation strains, which may amount to

Erosion test that can be used by the civil

engineering profession. We plan to

conduct further research efforts on “plastic”

concrete mixes. Similar work has been

completed by Hydro Quebec and BC

Hydro as well as in The Netherlands, U.K.

and France.

As summarized previously, the levee

inventory has a significant percentage of

seepage issues that wil l require

remediation. USACE envisions that jet

grouting applications will be more

commonly used, particularly in locations

where there are pipe penetrations through

the levee. The use of jet grouting for these

applications requires careful monitoring

given the high pressures involved.

Additional research is required to develop

monitoring instrumentation to measure

pressures in-situ and to validate overlap of

elements that are created.

Cutoff walls are one of the most effective

engineering solutions for mitigating

seepage and piping failure modes for dams

and levees. Equipment and construction

techniques have been developed and field

tested that show that a uniform cutoff wall

can be constructed to depths in excess of

Conclusions

425 ft (129 m) with a high degree of

confidence. Drilling techniques to assure

overlap and alignment have been proven

on Wolf Creek Dam and other recent dam

safety projects.

Data management systems are an

important improvement in the industry

and profession. The ability to collect and

store geo-referenced data is very important

for the future management of USACE’s dam

and levee inventories. There are other

design standards and documents available.

For example, the U.S. Bureau of

Reclamation is updating its Design Standard,

Chapter 10, Cutoff Walls (1986). In Europe,

EN 1538 – Execution of Special Geotechnical

Works – Diaphragm Wall (2010) is used as a

standard. The Embankment Dams

Committee of ICOLD has also recently

published a bulletin on cutoff walls.

The dam safety profession needs to

research the long-term performance of

various cutoff wall backfills, including their

cracking and erosion potential under high

stress and gradient loading conditions.

USACE anticipates completing and

issuing the new engineering manual,

Seepage Control Cutoffs for Dams and Levees

by the end of September 2014.

Figure 2. Estimated percentage of failure modes by type for USACE levee inventory

Figure 3. Walter F. George Dam – secant wall elements being drilled through casing from the water side of the dam

Page 88: DFI Magazine March/April 2014

-- What Lally Pipe customers know --

FAST BREAKING PROJECTS { often benefit from }

INVENTORY BASED SOLUTIONS

Get cut-to-length and spliced-to-length steel pipe piles in sizes up to 24Ó O.D. from inventory. Lally Pipe is AmericaÕs largest single source of New Secondary, Structural and Limited Service steel pipe products and customized solutions.

BE IN THE KNOW. Just call 1-800-533-6835, e-mail [email protected] or visit LallyPipe.com.

Page 89: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 89

Be your own man with the Sonic SideGrip®. Don’t stand by waiting on other contractors.

Work your own schedule. Drive toward higher profits. The Sonic SideGrip® puts it all within

your reach. With two unique side-gripping jaws and one bottom jaw, the Sonic SideGrip®

vibratory pile driver has unmatched dexterity for handling, driving or extracting just about

any style of piling. Choose from a range of models with 40 to 100 tons drive force for

18 to 55 ton excavators. Grab the future and drive your success.

sonic side-grip®

800.348.1890 hmc-us.com

Page 90: DFI Magazine March/April 2014

90 • DEEP FOUNDATIONS • MAR/APR 2014

CONSOLIDATEDPIPE & SUPPLY CO., INC.

“DEDICATED TO SERVICE”

STRUCTURAL DIVISION

-Steel Pipe-All Sizes andSpecifications

-Cut to Length-Tested Material-Mill Certification-Coating and Liningto all Specifications

-Applications for:Piling, Foundation, Marine,Bridge, TunnelBore Casing, Micropile

-Sheet Piling-Prompt Delivery

CONSOLIDATEDPIPE & SUPPLY CO., INC.

CONSOLIDATED PIPE & SUPPLY1205 HILLTOP PARKWAYBIRMINGHAM, AL 35204

WATS 1-800-467-7261BUS. (205) 323-7261FAX (205) 251-7838Cell (205) 739-1211

BRIAN [email protected]

Page 91: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 91

Geokon isISO 9001:2008registered

1 • 603 • 448 •1562 [email protected] www.geokon.com

35 YEARS OF INNOVATION AND QUALITY

MODEL GK- 405 VIBRATING WIRE READOUT new

Model 4900Geokon Vibrating Wire Load Cell

The Model GK- 405 Vibrating Wire Readout is designed for use with all Geokon vibrating wire

sensors. It comprises a battery-powered readout unit that communicates, via Bluetooth®, with a Handheld Field PC running the GK- 405 application. The Model GK- 405 can also read the thermistors included with most Geokon vibrating wire sensors, and display the temperature directly in °C.

All readings can be stored and exported to a number of different fi le formats. Syncing to a host computer is simple and straightforward, allowing project folders and data fi les to be easily saved. The Model GK- 405 Readout is available with or without the Handheld Field PC because the Model GK- 604-6 Field PC, provided with Geokon’s GK- 604 Inclinometer Readout, is compatible with both systems.

For more information visit : www.geokon.com/GK-405

Page 92: DFI Magazine March/April 2014

PEOPLE & COMPANIES

92 • DEEP FOUNDATIONS • MAR/APR 2014

Tracy Brettmann, P.E.,

D.GE, joined A.H. Beck

Foundation Company as

vice president of engineer-

ing working from Houston,

Texas. In this capacity,

Brettmann is responsible for engineering

oversight of all specialty deep foundation,

soil improvement and earth retention

projects. His expertise in the geotechnical

engineering and specialty deep foundation

industry will provide additional leadership

to increase Beck’s design-build oppor-

tunities as the company enters its 82nd year

in business. Brettmann has 25 years of

experience, is a past president of DFI, and a

former chair of the Augered Cast-in-Place

Pile Committee. He currently serves on the

board of the DFI Educational Trust.

Nicholson Construction was awarded a

$72.1 million design-build contract to

replace an existing force main from the

Virginia Key Central District Wastewater

Treatment Plant under Biscayne Bay Norris

Cut to Fisher Island. The project, which

involves changing out the current 54 in

(1.37 m) sewer force main for a 60 in (1.52 m)

replacement, should last approximately 26

months. The main scope includes the

installation of a precast concrete segmental

tunnel, which will stretch more than a mile

from the treatment plant on Virginia Key to

Fisher Island. The design-build contract

includes planning, engineering, design,

permitting, procurement, construction/

installation, testing and the start-up of the

replacement force main. Nicholson will act

as the general contractor for the project,

with subcontractors including Arup and

various local sub-consultants and

subcontractors. The project was slated to

start in early 2014.

Schnabel Engineering, Inc., Glen Allen,

Va., announced an addition to the Schnabel

family of companies with the acquisition of

Geo/Environmental Associates, Inc. (GA),

Knoxville, Tenn. GA specializes in the

design of dams, waste disposal impound-

ments, landslide repairs, retaining structures,

ground improvements, environmental

assessments, environmental remediation and

foundation design. Schnabel specializes in

geotechnical, geostructural, dam and tunnel

engineering, as well as environmental,

geosciences, construction monitoring and

resident engineering services. The merging

of Schnabel and GA provides an

opportunity for both firms to expand and

enhance the services they both provide

throughout the country and globally.

Schnabel, an employee-owned company,

employs nearly 300 in 18 offices nation-

wide. GA, with a staff of 20 in one location

in Knoxville, Tenn., will operate as a

wholly-owned subsidiary of Schnabel.

Schnabel Engineering also

announced that William

K. Petersen, P.E., joined

the firm as senior associate

in the West Chester, Pa.,

office. Petersen has over

24 years of experience in geotechnical and

geological engineering including site

investigations, design recommendations,

and construction monitoring for bridge,

dam, tunnel, highway, railroad, commercial

and residential projects.

ASFE/The Geoprofessional Business

Association (GBA) is now offering DFI

members a free subscription to NewsLog -

the electronic newsletter of the association,

issued every two weeks. GBA is a not-for-

profit organization that specializes in helping

its 300 member firms and their clients con-

front risk and optimize performance in

order to maximize geoprofessionals’

importance and value to the marketplace.

To sign-up for the newsletter go to

www.asfe.com.

Kevin Cargill, P.E., was

promoted to president

and CEO of Schnabel

Foundation Company in

Sterling, Va. Cargill was

previous ly the v ice

president and regional

manager of Schnabel’s

Southeast Regional Office

s ince 2003. Cargi l l

replaces Hubert Deaton

III, P.E., who served as

Schnabel ’s president

since 1988 and will

continue on as a director.

Scott Ballenger, P.E., has

been named to replace

Cargill as Schnabel’s

southeast regional manager. Ballenger

joined Schnabel in 2003 as a construction

manager. Schnabel Foundation Company

is a nationwide contractor specializing in

earth retaining structures, micropiles and

ground improvement since 1959.

Ronald J. Ebelhar, P.E., D.GE, a senior

principal at Terracon in Cincinnati, Ohio,

was elected to serve a one-year term as vice

chairman of the ASTM International board

of directors. Ebelhar, who joined ASTM

International in 1980, is chairman of

Committee D18 on Soil and Rock. An

ASTM fellow and 2003 Award of Merit

recipient, Ebelhar has received several

awards from D18, including R.S. Ladd

Standards Development Awards, the

Woodland G. Shockley Award, the A. Ivan

Johnson Outstanding Achievement Award,

two Special Service Awards and the

Committee D18 Technical Editor’s Award.

He also received a Service Award from the

ASTM Committee on Technical Committee

Operations, on which he served a two-year

term. He has served on the ASTM board of

directors since 2010.

Page 93: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 93

earthquake engineering, have significant

independent contributions and show

promise of excellence in research. The

award is a $1,100 cash prize and a plaque.

See nomination requirements at

www.yoga10.org. For further information,

please contact Shamsher Prakash at

[email protected].

Specialty geotechnical

contractor Moretrench

announced two new

senior management posi-

tions. Scott D. Dodds

joined the company as

g e n e r a l m a n a g e r –

geotechnical group, Mid-

Atlantic & Midwest

Regions. Dodds is a grad-

uate of the University of

Pittsburgh with a B.S. in

Civil Engineering, and has more than 25

years of construction industry experience.

Greg Peitz joined the company as

operations manager–geotechnical group,

Mid-Atlantic & Midwest Regions. Peitz has

a B.A. in business administration from

Robert Morris University, Pittsburgh, Pa.,

and more than 30 years of specialty

geotechnical construction management

experience. His expertise is in large

diameter drilled shafts.

Geocomp’s Dr. Rachid Hankour, 53, of

Harvard, Mass., died in December 2013,

following a brief battle with cancer.

Hankour earned his M.S. and Ph.D. in Civil

Engineering from Tufts University in

Medford, Mass., where he taught for the

next quarter century. In 1994, Hankour

joined Geocomp Corporation in Acton,

Mass., and became vice president and

director of lab systems. He taught

undergraduate and graduate level courses

at Tufts and, in 2011, was appointed

Professor of the Practice in recognition of

his widely-recognized expertise in state-of

the-art geotechnical test ing and

instrumentation and his commitment to

excellence in teaching.

Mary Pohlman joined

Jeffrey Machine, Inc. in

Birmingham, Ala., as

international sales repre-

sentative with over 13

years of experience in the

foundation drilling and construction

industry. Pohlman’s extensive marketplace

knowledge helps to accurately identify

customers’ needs and assists the

manufacturing team with developing the

right drilling tool solution. Her broad

understanding of the foundation tooling

industry will help to extend Jeffrey

Machine’s customer service into the

international marketplace.

The Shamsher Prakash Foundation is

soliciting nominations for the 2014

Shamsher Prakash Research Award for

young engineers, scientists and researchers

(40 years or younger) from all over the

world. Nominations are due March 31,

2014. The candidates should specialize in

geotechnical engineering and/or geotechnical

Page 95: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 95

CANADA & WESTERN U.S.CHAMPION EQUIPMENT SALES, LLC 562.634.8180

www.Soilmec.com

EASTERN & CENTRAL U.S.AMERICAN EQUIPMENT & FABRICATING CORP401.438.2626

Can you be green and more powerful?With Soilmec, you can. New, powerful Tier 4i engines are now available on most Soilmec rigs. Meet emission standards while improving productivity.

Soilmec: Your Solutions Provider.

OUR NEW TIER 4i RIGS

ARE AVAILABLENOW

CALL TODAY

Page 97: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 97

Junttan Oy Rolls Out New X-Series Pile Driving Rigs

Junttan Oy launched three new models in

its X-Series pile driving rig family in

addition to the smaller range PMx20,

PMx22, PMx24 and PMx25 rigs launched

a few years ago. The new models, carrying

the nickname J-reX, are the PMx26,

PMx27 and PMx28, and have maximum

leader capacities of 20, 23 and 25 tonnes

(44, 51 and 55 kips) and maximum pile

lengths of 24, 25 and 28 m (79, 82, and

92 ft) respectively.

The structure and component layout of

the PMx26-28 series was redeveloped

according to Junttan’s 35 years of

experience in the field. The hydraulic

system was overhauled and the X-control

system for the PMx26-28 series was further

developed for convenient and productive

operation and low fuel consumption.

Improving operator efficiency and

safety, as well as minimizing energy losses

within the system, were the key design

goals for the PMx26-28 series. Deep system

integration resulted in reduced emissions,

improved performance and improved fuel

economy without compromising machine

performance. Several developments drama-

tically minimized fuel consumption includ-

ing a thermostatically-controlled engine

and hydraulic oil coolers with an optimized

air circulation system and a streamlined

main hydraulic oil circuit with extended

hose diameters. These changes decreased

fuel consumption by up to 2 L (0.5 gal) per

hour compared to previous models. The

new post-compensated and load sensing

hydraulic system saves another 1 L (.25 gal)

per hour compared to traditional hydraulic

systems. The PileCruise feature eliminates

human factors from the total system

efficiency, decreasing the power consump-

tion of the hammer by up to 20%, depend-

ing on the operator. Tier 4 certified Cummins

engines are also available to further decrease

emissions. The PMx26-28 series premiered

at Conexpo 2014, in Las Vegas, Nev.The new J-reX pile driving rig

Page 98: DFI Magazine March/April 2014

98 • DEEP FOUNDATIONS • MAR/APR 2014

Versatility, Reliability & Durability

EMDE Large and small-bore drill toolingBetek Product DistributorComacchio Drill and Geothermal Rigs- East of the Mississippi Dist.

Customized Drilling Solutions

ICE® Limited Access DrillsICE® Top Drive Rotary Heads and AugersICE® Excavator-mounted Rotary Heads Hydraulic Vibratory Drivers/Extractors Excavator-mounted Vibratory Drivers/ExtractorsDiesel Impact HammersHydraulic Impact HammersICE® Pilemer Hydraulic HammersPiling and Drilling MastLeads, Spotters, and Accessories& Manufacturing and Service of More Deep Foundation Equipment

InternatIonal ConstruCtIon equIpment, InC301 Warehouse Drive

MattheWs, NC 28104 usa704-821-8200 | WWW.iCeusa.CoM

Page 99: DFI Magazine March/April 2014

DEEP FOUNDATIONS • MAR/APR 2014 • 99

BSP Launches New Range ofLightweight Hammers

BSP International Foundations (BSP) announced the launch of a

new range of powerful yet lightweight hammers, which provide

greater stability to piling rigs, especially in applications where a

greater reach is required. Designated the LX range and comprising

three models, the new hammers also provide a solution for the

installation of all pile types.

The three hammers, LX30, LX40 and LX50, can drive steel,

concrete or timber piles in a variety of soil conditions. Major

features include total control of hammer stroke and blow rate,

precise matching of energy to suit the pile driving requirements

while an efficient hydraulic system gives low energy loss, and a low

running cost.

The hammers can be fitted with a single acting hydraulic system

to give an equivalent stroke of 800 mm (31.5 in) or alternatively a

double acting cylinder can be fitted to give an equivalent stroke of

1.2 m (3.9 ft). A range of standard drive caps and pile helmets are

available for the LX range, which can be operated from BSP power

packs or from hydraulic piling rigs or cranes.

The new LX40 lightweight hammer

Page 100: DFI Magazine March/April 2014

DFI_March_April_FP_Ad.indd 1 1/10/2014 4:21:27 PM

Page 101: DFI Magazine March/April 2014

International Foundations Congress and Equipment Expo

w w w . I F C E E 2 0 1 5 . c o m

MARCH 1 7 - 2 1 , 2 0 1 5 ★ S A N A N TO NIO, TEXA

S

March2015

JW MarriottHill CountryResort & SpaSan Antonio

Texas

ExhibiT

booTh SAlES

Now opEN

Visit www.ifcee2015.com

for more information!

➤ Over 2,700 Attendees

➤ Indoor and Outdoor Exhibit Space

➤ Over 27 Hours of Exhibit Time

➤ Exceptional Promotional Program

➤ Face-to-Face with Key Decision Makers

The world’s largest Equipment Exhibition and Technical Conference Dedicated to the

Deep Foundations industry

Page 102: DFI Magazine March/April 2014

102 • DEEP FOUNDATIONS • MAR/APR 2014

AD INDEX CALENDAR

DFI 2014 EventsAmerican Piledriving Equipment Inc . . . . . . 4BAUER Foundation Corp. . . . . . . . . . . . . . . 69BAUER-Pileco . . . . . . . . . . . . . . . . . . . . . . . . 24Bay Shore Systems, Inc. . . . . . . . . . . . . . . . . . 8Bermingham Foundation Solutions . . . . . . 18Brasfond Fundacoes Especiais S/A. . . . . . . . 11Brayman Construction Corporation . . . . . . 46Casagrande USA . . . . . . . . . . . . . . . . . . . . . 32Center Rock Inc. . . . . . . . . . . . . . . . . . . . . . . 16CETCO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51Colorado School of Mines . . . . . . . . . . . . . . 43Comacchio SRL . . . . . . . . . . . . . . . . . . . . . . . 40Consolidated Pipe and Supply. . . . . . . . . . . 90Con-Tech Systems Ltd. . . . . . . . . . . . . . . . . . 82Cranes, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . 91CZM Foundation Equipment . . . . . . . . . . . . 62Dahil Corporation . . . . . . . . . . . . . . . . . . . . 51Drilltools . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22Dywidag Systems International (DSI) . . . . . 26Equipment Corporation of America . . . 60, 61Foundation Technologies, Inc. . . . . . . . . . . 10GEI Consultants, Inc. . . . . . . . . . . . . . . . . . . 74Geokon, Inc. . . . . . . . . . . . . . . . . . . . . . . . . 91Geo-Solutions . . . . . . . . . . . . . . . . . . . . . . . . 48Giken America Corporation . . . . . . . . . . . . 33Givens International Drilling Supplies, Inc. 50GMS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93Goettle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25Hammer and Steel . . . . . . . . . . . . . . . . . . . 103Hardman Construction, Inc. . . . . . . . . . . . . 82Hayward Baker . . . . . . . . . . . . . . . . . . . . . . 76Hennessy International, Inc. . . . . . . . . . . . 44Hercules Machinery Group . . . . . . . 36, 67, 89HIIG Construction. . . . . . . . . . . . . . . . . . . . . 38Hong Xiang Technologies . . . . . . . . . . . . . . 96ICE-International Construction Equipment, Inc. . . . . . . . . . . . . . . . . . . . . . 98Instantel . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18JD Fields & Company, Inc. . . . . . . . . . . . . . . 28Jeffrey Machine, Inc. . . . . . . . . . . . . . . . . . 100Kelly Tractor . . . . . . . . . . . . . . . . . . . . . . . . 83Kiewit Infrastructure Co. . . . . . . . . . . . . . . . 70L. G. Barcus & Sons . . . . . . . . . . . . . . . . . . . . 84Lally Pipe & Tube . . . . . . . . . . . . . . . . . . . . . 88Langan Engineering & Environmental Services . . . . . . . . . . . . . . . 43Liebherr-Werk Nenzing GmbH . . . . . . . . . . 23Loadtest . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68Magnus Pacific Corporation . . . . . . . . . . . . . 2Mait S.p.A . . . . . . . . . . . . . . . . . . . . . . . . . . . 31Malcolm Drilling Company Incorporated . . 20Mueser Rutledge Consulting Engineers . . . 93National Rig Rental . . . . . . . . . . . . . . . . . . . 29Naylor Pipe . . . . . . . . . . . . . . . . . . . . . . . . . . 39Nucor-Yamato . . . . . . . . . . . . . . . . . . . . 52, 53PennDrill Manufacturing. . . . . . . . . . . . . . . 47Pieresearch . . . . . . . . . . . . . . . . . . . . . . . . . 59Pieresearch and Pile Protection Tops . . . . . 43Pile Dynamics . . . . . . . . . . . . . . . . . . . . . . . . 35PJ’s Rebar . . . . . . . . . . . . . . . . . . . . . . . . . . . 97Plaxis bv . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66Pro-Dig, LLC . . . . . . . . . . . . . . . . . . . . . . . . . 27PTC Fayat . . . . . . . . . . . . . . . . . . . . . . . . . . . 75PVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68, 99RST Instruments LTD . . . . . . . . . . . . . . . . . . 34SAS Stressteel, Inc. . . . . . . . . . . . . . . . . . . . . 17Soilmec North America . . . . . . . . . . . . . . . . 95Star Iron Works, Inc.. . . . . . . . . . . . . . . . . . . 74Sterling Lumber . . . . . . . . . . . . . . . . . . . . . . 10Steven M. Hain Co., Inc. . . . . . . . . . . . . . . . 39Subsurface Constructors, Inc. . . . . . . . . . . . 81Tectonic Engineering & Surveying Consultants, P.C. . . . . . . . . . . . . . . . . . . . . . 30TEI Rock Drills . . . . . . . . . . . . . . . . . . . . . . . . 54Treviicos Corporation. . . . . . . . . . . . . . . . . . 19Watson Drill Rigs . . . . . . . . . . . . . . . . . . . . . . 6Williams Form Engineering Corp. . . . . . . . 94

March

April

May

June

July

August

September

October

November

19-20 DFI-ADSC Anchored Earth Retention/Micropile Design and Construction SeminarHilton Seattle Airport and Conference Center, Seattle, WA

2-3 DFIMEC 2014, American University, Dubai, UAE

3 Helical Piles and Tiebacks Specialty SeminarAmeristar Casino Resort Spa, St. Louis, MO

4 DFI-CSCE Spring WorkshopState University of New Haven, West Haven, CT

28-30 DFI-ADSC Drilled Shaft SeminarGrandover Resort & Conference Center, Greensboro, NC

(TBD) Practical Deep Foundation Design and Construction for Seismic and Lateral Loads, Seattle, WA

21-23 DFI-EFFC International Conference on Piling and Deep Foundations, Stockholmsmässan, Stockholm, Sweden

11-14 ISM-DFI-ADSC 12th International Workshop on MicropilesQubus Hotel Kraków, Kraków, Poland

18-20 SuperPile 2014, Hyatt Regency Cambridge, Cambridge, MA

26 Slurry Wall Seminar, Los Angeles, CA

21 DFI Educational Trust Annual Golf Outing FundraiserChartiers Country Club, Pittsburgh, PA

TBD Marine Foundations Seminar – Design and Construction of the New Tappan Zee Bridge, Tarrytown, NY

TBD DFI-CSCE Annual Fall Seminar, CT

TBD Slope Stabilization and Excavation Support SeminarPittsburgh, PA

21-24 39th Annual Conference on Deep FoundationsAtlanta Marriott Marquis, Atlanta, GA

27 DFI Educational Trust Annual Golf Outing FundraiserCastlewood Country Club, Pleasanton, CA

TBD DFI Educational Trust Annual Gala Fundraising DinnerNew York/New Jersey

DFI Events: Go to www.dfi.org/dfievents.asp for up-to-date information

Industry Events: A complete list can be found at www.dfi.org/industryevents.asp

Page 103: DFI Magazine March/April 2014

DRILLING RIGS

www.hammersteel.com800-325-PILE (7453) • (314) 895-4600

Piling, Pile Driving & Drilling Equipment

SALES • RENTAL PARTS • SERVICE

Missouri800.325.PILE (7453) • 877.224.3356 • 904.284.6800 • 913.768.1505 • 952.469.6060 • 973.512.2940 • 936.257.8790

California Florida Kansas Minnesota New Jersey Texas

Hammer & Steel Sells and Rents Comacchio MC Line

The basic line of multiuse rigid and articulated hydraulic crawler drill rigs which are suitable for several types of specialized works, such as ground consolidation, anchor drilling, geotechnical works, water well drilling and geothermal energy.

Hammer & Steel has been in business for 25 years and offer superior after-sales service

on all equipment. We have stocking facilities throughout the U.S.

Page 104: DFI Magazine March/April 2014

DFIIOT NA SD INN

SU TO IF T

UPE T

E E

DPRESORTED STANDARD

U.S. POSTAGE PAIDPHILADELPHIA, PAPERMIT NO. 102

Deep Foundations Institute326 Lafayette AvenueHawthorne, NJ 07506 USA973-423-4030Fax 973-423-4031

Aerial View of Spillway Platform of Bluestone Dam