Development of ABC System

Embed Size (px)

Citation preview

  • 7/30/2019 Development of ABC System

    1/19

    Presented by-Sneha Bajpai

    MBA-2nd sem

    Roll no.-39FMS-BHU

  • 7/30/2019 Development of ABC System

    2/19

    Two-Dimensional ABC and Activity-Based Management

    Cost Assignment ViewResource cost

    activities

    Cost objects

    Process ViewActivity AnalysisRootcause

    Activitytriggers

    ActivityEvaluationPerformance

    measures

  • 7/30/2019 Development of ABC System

    3/19

    Traditional product costing systems weredesigned when the company manufacturednarrow range of products. Also it can onlymeasure volume related cost. Non-volumerelated activities like material handling , set-

    up etc are important and their costs cannotbe apportioned on volume basis.

    However today companies produce a widerange of products. Simple methods of

    apportioning overheads based on directlabour are not justified.

    Hence the need for activity based costingarises.

  • 7/30/2019 Development of ABC System

    4/19

    All of a companys activities are considered as product

    costs. Philosophy of ABC is that costs can be controlledmore effectively by focusing directly on managing theforces that cause the activities-the cost drivers ratherthan costs. Thus ABC provides better and more accurateinformation and decision making on prices and product

    mix and for the control of manufacturing operations. Costs are grouped into pools according to the

    activities which drive them. E.g.-a cost pool may be ofprocurement of goods. In this, all the costs associatedwith the procurement(ordering,inspection,sorting)would

    be included in this cost pool and cost driver identified.The procurement cost per requisition is then calculatedand this provides a means of tracing the cost ofprocurement to product.

  • 7/30/2019 Development of ABC System

    5/19

    The following are the three key areas of ABC: Product cost differentiation

    activities and their cost drivers

    identification of non-value added costABC is the planned and systematic study and

    determination of cost of each of the branchesof business activities that add to the value of

    product and services. This matrix shows longand short term cost strategy presented asfollows: Short term Long term

    Product value

    pricing

    Value addition

    Corporate growth

  • 7/30/2019 Development of ABC System

    6/19

    The steps required to develop an ABC system are as

    follows- Identify the main activities performed in the

    organization, such as manufacturing, assemblyetc., as well as support activities ,includingpurchasing ,packing and dispatching.

    Identify the factors which influence the cost of eachactivity-the cost drivers.

    Collecting accurate data on direct labour , materialand overhead costs.

    Establishing the demands made by particularproducts on activities, using the cost drivers as ameasure of demand.

    Trace the cost of activities to products according toa products demand for each activity.

  • 7/30/2019 Development of ABC System

    7/19

    Focus on expensive resources, thus directingattention to resource categories where the new

    costing process has the potential to make bigdifferences on product cost.

    Emphasis on resources whose consumption variessignificantly by product and product type-look fordiversity.

    Focus on resources whose demand patterns are un-correlated with traditional allocation measures.

    ABC is the process of tracing costs first from resourcesto activities and then from activities to specificproducts. The technique of ABC lays the importance

    of different costs for different purposes and theidentification of just those costs, which are relevantto a particular decision. It refines the ideas andconcepts of conventional methods.

  • 7/30/2019 Development of ABC System

    8/19

    Functional areas Activities involved Cost driversMaterial management 1.Issuing tenders

    2.Receiving indents3.Inspection ofmaterial

    No. of tenders issuedNo. of indentsNo. of purchaseorders

    Quality management 1.Receive sample2.Test sample3.Issue of testcertificates

    No. of batchesproduced

    Personal management 1.Recruitment2.Training3.Labour turnover

    No. of employeerecruited

    marketing 1.Demand criterion2.Advertising effort3.Preparation of salesforecast

    Percentage increasein salesTime spent withdistributors

  • 7/30/2019 Development of ABC System

    9/19

    A COMP. PRODUCES 4 PRODUCTS A ,B ,C, D USING THE SAME PLANT ANDPROCESS. FOLLOWING ARE THE INFO RELATED TO PRODUCTION PERIOD:

    ILLUSTRATION:

    product volume MATERIALCOST/UNIT DIRECTLABOUR/UNIT HOURMACHINETIME/UNIT LABOURCOST/UNITRS.

    A 500 5 3

    B 5000 15 3

    C 600 16 2 1 12

    D 7000 7 1 1/2 1 1/2 9TOTAL PRODUCTION OVERHEADS:Factory overhead applicable to machine oriented activity : Rs. 37,425Set up cost : Rs. 4,355Cost of ordering material : Rs. 1,920Handling material : Rs. 7,580Administration for spare parts : Rs. 8,600

    Rs. 59,880

  • 7/30/2019 Development of ABC System

    10/19

    PERIOD No. of setups No. ofmaterialordered

    No. of timematerialhandled

    No. of sparepartsA 1 1 2 2

    B 6 4 10 5

    C 2 1 3 1

    D 8----174----10

    12-----274----12

    COMPUTEAN OVERHEAD COST PER PRODUCT USING ABC, TRACING

    OVERHEADS TO PRODUCTION UNITS BY MEANS OF COST DRIVERS.

  • 7/30/2019 Development of ABC System

    11/19

    SOLUTION:

    Overhead cost based on machine hr rate:

    product volume machinetime/unit Total machinetimeA 500 125

    B 5000 1250

    C 600 1 600

    D 7000 1 1/2 10500

    --------12475

    TOTAL OVERHEAD COST ABSORBED BY THE PRODUCTS= TOTAL PRODUCTIONOVERHEAD/ total machine time

    Rs. 59880/12475= Rs. 4.80 per hour

    Thus overhead cost per product A= 1/4 of Rs 4.80 = Rs 1.20B= 1/4 of Rs 4.80 =Rs 1.20C= 1 of Rs. 4.80 =Rs. 4.80D=1.5 of Rs. 4.80 = Rs. 7.20

  • 7/30/2019 Development of ABC System

    12/19

    Factory overhead applicable to machine oriented activity= Rs 37,424

    Total machine hours=12,475

    Machine hour rate for machine overhead charges= 37,424/12,475= Rs. 3 per hour

    Set up cost to be applied on the basis of no of set ups=Rs 4355/17=Rs 256.18 per set-ups

    (Cost driver is no. of set-ups)

    Materials ordering cost to be absorbed on the basis of number of materialorders= ordering cost/ total no of orders

    = Rs 1920/10= Rs 192 per order

    (Cost driver is number of times material is ordered.)

    Activity based costing..

  • 7/30/2019 Development of ABC System

    13/19

    Contd.

    Material handling cost = handling cost / No. of times material handled.= Rs 7580/27

    = Rs 280.74 per time material handled(Cost driver is number of times material handled)

    Administration for spare parts = Rs 8,600/ 12=Rs 716.67

  • 7/30/2019 Development of ABC System

    14/19

    Computation of overhead cost per product using ABC

    0verhead items A BMachine overhead hour @ Rs 3/mc hr= Rs.

    0.75

    hour @ Rs 3/mc hr= Rs.

    0.75

    Set up cost (1 X Rs 256.18)/500volume=1.12

    6X Rs 256.18)/5000volume=0.56

    Material handling cost (1 X Rs 280.74)/500=0.38

    (10X Rs 280.74)/5000=0.15

    Material ordering cost (1 X Rs 192)/500=0.38

    (4xRs.192)/5000=0.72

    Administration forspare parts

    (1 X Rs 716.67)/500=0.38

    (5X Rs 716.67)/5000=0.717

    Total overhead

    cost/unita/c to ABC

    5.63 2.49

  • 7/30/2019 Development of ABC System

    15/19

    products Overhead costper unit basedon ABC

    Overhead costbased on presentsys of machinehr rate ofRs.4.80 /hr

    difference

    A 5.63 1.20 +4.43

    B 2.49 1.20 +1.29

    C 6.67 4.80 +1.96

    D 5.79 7.20 -1.41

    Over head cost based on two system and their difference

  • 7/30/2019 Development of ABC System

    16/19

    Benefits of implementing ABC:

    Cost management and downsizing.

    Determination of product and servicescost.

    Improvement in performance.

    Product/service pricing.

    Make or buy decisions.

    Transfer pricing.

  • 7/30/2019 Development of ABC System

    17/19

    Substantial resourcesrequired to implement

    and maintain.

    Resistance tounfamiliar numbers

    and reports.

    Does not conform toGAAP. Two costing

    systems may beneeded

    Desire to fullyallocate all costs

    to products

    Potentialmisinterpretation ofunfamiliar numbers

  • 7/30/2019 Development of ABC System

    18/19

    Conclusion:-

    ABC may not be appropriate for all companies,particularly those where overheads are small andwhich do not produce a wide range of products.But many of the benefits of ABC can still be

    obtained by implementing a partial system, whichfocuses on most important activities. Nor themethod should be used for preparing monthlyprofit statements. Traditional methods should beused for that, leaving ABC to support strategic

    decision-making, profitability analysis and controlof manufacturing cost.

  • 7/30/2019 Development of ABC System

    19/19

    THANK YOU..