26
1 Development and Bench-Scale Testing of a Novel Biphasic Solvent-Enabled Absorption Process for Post-Combustion Carbon Capture (DE-FE0031600) Presenter: Paul Nielsen Illinois State Geological Survey Pittsburgh, PA August 16, 2018

Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

1

Development and Bench-Scale Testing of a Novel Biphasic Solvent-Enabled

Absorption Process for Post-Combustion Carbon Capture (DE-FE0031600)

Presenter: Paul NielsenIllinois State Geological Survey

Pittsburgh, PA ⋅ August 16, 2018

Page 2: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

2

Project Overview

Technology Background

Scope of Work/Technical Approaches

Current Status

Plan for Future Scale-Up /Development

Page 3: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Objectives

Advance the development of a transformational biphasic CO2 absorption technology from lab- to bench-scale

Design, fabricate and test an integrated 40 kWe bench-scale capture unit with simulated and actual coal flue gas

Demonstrate the technology progressing toward achieving the DOE’s Transformational Capture goals

3

Page 4: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Project Participants

University of Illinois (Technology Developer) Illinois State Geological Survey David Ruhter (MS, Lab Manager) Hafiz Salih (PhD, Environmental Engineer) Hong Lu (PhD, Chemical Engineer) Qing Ye (Post-Doctoral Research Fellow) Varenya Mehta (MS, Environmental Engineer) Paul Nielsen (PhD, Chemical Engineer) Yongqi Lu (PhD, Chemical/Environmental Engineer)

Illinois Sustainable Technology Center BK Sharma (PhD, Senior Chemical Engineer) Kevin O’Brien (PhD, Director) Wei Zheng (PhD, Senior Chemist)

Trimeric Corporation (Design and Fabrication, TEA) Darshan Sachde (PhD, Senior Chemical Engineer) Katherine Dombrowski (Principal Technical Staff) Kevin Fisher (VP, P.E., Principal Engineer) Ray McKaskle (P.E., Principal Engineer)

4

Page 5: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Budget Profile and Duration

Project duration: 36 mon, 3 Budget Periods (4/6/18–4/5/21) BP1: 9 mon (4/6/18-1/5/19) BP2: 12 mon (1/6/19-1/5/20) BP3: 15 mon (1/6/20-4/5/21)

Funding Profile: DOE funding of

$2,981,779 Cost share (in-kind) of

$750,051 (20.1%)

5

0200400600800

1,0001,2001,4001,600

BP1 BP2 BP3

Budg

et (k

$)

DOE fundsCost share

(12-m) (15-m)(9-m)

Page 6: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

6

Project Overview

Technology Background

Scope of Work/Technical Approaches

Current Status

Plan for Future Scale-Up /Development

Page 7: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Biphasic Process (BiCAP)

7

Water lean Aqueous/Organic amine blend CO2-rich solvent separates into 2 liquid phases

Reduced solvent flow to regenerator Enhanced CO2 absorption via removal of rich solvent

Page 8: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

8

Progression of Technology Development

10 kWe Test,Laboratory

Solvent study,Laboratory

Overview of experimental

setup

40 kWe Test, Laboratory & Power

Plant Slipstream

Proof-of-ConceptFunding: UI (Part of

Dissertation Research, 2013-2015)

Separate Absorber / Stripper

Funding: DOE / UI (2015-2018)

Bench Scale Closed-Loop Unit Funding: DOE / UI (2018-2021)

Currently

Page 9: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Current Status of Solvent and Process R&D

Solvent Development Results Status~80 solvents screened 2 solvents selected Completed VLE Absorption capacity: similar to 5 m MEA Completed

Absorption kinetics Comparable to faster than MEA Completed Oxidation and thermal stabilities

Thermal stability at 150°C ~ MEA at 120°C; Oxidation stability ~8 times < MEA

Completed

Viscosity CO2-saturated rich phase solutions < 50 cP CompletedPhase Separation ≥98% of CO2 uptake in <50% of solution CompletedHeat of desorption Estimated with VLE data CompletedCorrosion effect Less corrosion than MEA on CS or SS Completed

CO2 absorption Lab 10 kWe absorption column; Faster rates than MEA demonstrated in testing Completed

CO2 stripping Lab 10 kWe desorption system; Heat duty 2400 kJ/kg CO2 for BiCAP-1, 2000 for -2

Near Completion

9

Page 10: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Lab 10 KWe Absorption and Desorption Tests Demonstrated Performance of BiCAP

10

CO2 absorption rate 12% faster than 5 m MEA for BiCAP-1

Demonstrated effectiveness of liquid-liquid phase separation unit

Tested up to 150 °C, 9 bar Minimum Reboiler Heat Duty:

BiCAP-1: 2400 kJ/kg CO2 BiCAP-2: 2000 kJ/kg CO2

Page 11: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Projected Energy Performance for Net 550 MWe

* Updated BiCAP case (Cold rich feed bypass the heat exchanger)

Total derate 43% less than MEA CAPEX 20% less than MEA

11

BiCAP*DOE Case 12 (MEA)

DOE Case B12B (Cansolv)

Net Generating Capacity, MWe 550 550 550Gross Generating Capacity, MWe 700 802 728Amount of CO2 captured, tonne/hr 478 548 480Total Steam Derate, MWe 71.1 139 86

Reboiler/Flash Heat Duty, MWth 278 542 331Thermal to Electric Energy, % 25.6 25.6 25.8

Direct Electrical Derate, MWe 44.8 75.2 51.7Compression Duty, MWe 31.5 44.9 35.7Other (Pumps, Fans, etc.), MWe 13.3 30.3 16.0

Total Derate for CO2 Capture, MWe 116 214 137Total parasitic use for entire plant, MWe 150 252 178

Page 12: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Biphasic Solvents are Stable

12

0.5

0.6

0.7

0.8

0.9

1

0 10 20 30

Frac

tion

of in

itial

sol

vent

Experiment time (days)

5 M MEA, 150 °C

5 M MEA, 120 °C

BiS4, 135 °CBiS4, 150 °C

0.5

0.6

0.7

0.8

0.9

1

0 3 6 9 12

Frac

tion

of in

itial

sol

vent

Experiment time (days)

5 M MEA

BiS4

50 oC96% O2/4% CO2 gasPresence of metal catalysts

Thermal Stability: BiCAP-1 @ 150 °C ~ MEA @ 120 °C

Oxidative Stability: BiCAP-1 8x < MEA @ 50 °C

(BiCAP-1)

Corrosion rate of 2-3 times < MEA for carbon steel, minimal for stainless Viscosity <50 cP for CO2-rich phase, <10 cP mixed @ 40 °C

Page 13: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

13

Project Overview

Technology Background

Scope of Work/Technical Approach

Current Status

Plan for Future Scale-Up /Development

Page 14: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Schedule and Milestones (36-mon, 4/6/18-4/5/21)

14BP1 BP2 BP3

Page 15: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Project Task Flow

15

New studies of (1) solvent volatility/loss and (2) process

modeling & optimization

Design of Bench-Scale Capture Unit

Fabrication of Bench-Scale Capture Unit

Solvent Management Studies

Testing of Bench Unit with (1) Simulated Flue Gas [6 months] and (2)

Actual Flue Gas [2-3 weeks]

Techno-Economic Analysis

Technology Gap Analysis

EH&S Risk Assessment

Technology Maturation

Plan

Previous results of solvent (VLE, kinetics, viscosity,

stability, corrosion) & process (column tests) R&D

Project starts

9-mon

21-mon

36-mon

BP12018

BP22019

BP32020-21

Page 16: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Design and Fabrication (BP1 and BP2)

16

Task 4 Modeling and Optimization

ASPEN modeling to identify optimal configuration

Provide mass & energy balance

Design of Bench-Scale Capture Unit

Fabrication of Bench-Scale Capture Unit

Project starts

9-mon

21-mon

BP12018

BP22019

Task 5 DesignDesign Skid

Review & Final ApprovalConduct prelim HAZOP

Task 6 FabricationBidding

Vendor Selection

Oversee fabricationSafety review and FAT

Page 17: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Operation (BP3)

17

Testing of Bench Unit with (1) Simulated Flue Gas [6 months] and (2)

Actual Flue Gas [2-3 weeks]

Techno-Economic Analysis

Technology Gap Analysis

EH&S Risk Assessment

Technology Maturation

Plan

21-mon

36-mon

BP32020-21

Task 8 Parametric TestingInstallation and Commission

6 months testing w/ synth gas2 solvents

Task 9 Field TestingMove skid to Abbot

2 weeks testing1 solvent

Monitor degradation, corrosion, emissions

Page 18: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Solvent Management (BP1 and BP2)

18

New studies of (1) solvent volatility/loss and (2) process

modeling & optimization

Task 3 Volatility and EmissionsComponent volatility by FTIR

Lab testing water wash optionsAerosol generation and control

Task 7 Solvent ManagementDegradation and reclaimation

Ion exchange/adsorption

Develop in-situ loading measurment

Solvent Management Studies

Project starts

9-mon

21-mon

BP12018

BP22019

Page 19: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

19

Project Overview

Technology Background

Scope of Work/Technical Approaches

Current Status

Plan for Future Scale-Up /Development

Page 20: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Solvent Volatility & Losses

DX-4000 FTIR purchased from GASMET Volatility measurements in existing VLE

cell in August/September Volatile losses and aerosol control to

be tested in existing 10 kW lab absorber column Water wash section to be added 2-3 trays/packings to be tested Total emissions to be measured by FTIR,

aerosols collected by membrane filters and analyzed by TOC

Purchasing SO3 aerosol generator

20

Page 21: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

ASPEN Process Modeling

21

Process model regressed for BiCAP-1, in progress for -2

BiCAP-2 expected to have better performance

Mixed Solvent (Absorber) CO2-Rich Phase (Stripper)

1.E+0

1.E+1

1.E+2

1.E+3

1.E+4

1.E+5

1.E+6

0.0 0.5 1.0 1.5 2.0

CO

2pa

rtial

pre

ssur

e in

mix

ture

(Pa)

CO2 loading in solution (mol/kg CO2 free solvent)

20 °C

40 °C

80 °C

60 °C

100 °C

120 °C140 °C160 °C

Points: Experimental data Lines: Model predictions

1.E+0

1.E+1

1.E+2

1.E+3

1.E+4

1.E+5

1.E+6

1.E+7

1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5

CO

2pa

rtial

pre

ssur

e in

rich

pha

se (P

a)

CO2 loading in solution (mol/kg CO2 free solvent)

20 °C

40 °C

80 °C

60 °C

100 °C

120 °C140 °C160 °C

Points: Experimental dataLines: Model predictions

Page 22: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Proposed Skid Flow Diagram

To stack

Gas return to stack

Direct contact cooler/

SO2polisher

NaOHsolution makeup

Flue gas71 ACFM

High-pressure stripper2-7 bar

120-150 °C

Water knockout

Cooler

CoolerCooler

LP steam

Condensate

Addition of pure CO2 as needed

Flue gas source and polishing treatment

Absorber40 °C

Phase separator

Water wash

ReboilerBlowdown

Solvent makeup Cold feed

35% of total

Heated feed

Heat exchanger

10 °C LMTD

Two absorption columns:Each with 8’’-ID × 12-15’ packing

85-90% CO2 capture

One stripping column:4’’-ID × 12-18’ packing

Reboiler duty <2400 kJ/kg CO2

Finish modeling ASAP (optimization and range for parametric testing) Finalize design by end of year

Page 23: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

23

Project Overview

Technology Background

Scope of Work/Technical Approaches

Current Status

Plan for Future Scale-Up /Development

Page 24: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

24

Progression of Technology Development

10 kWe Test,Laboratory

Solvent study,Laboratory

0.2-1 MWe,Power Plant /Test Center

10 MWe, Power Plant

Overview of experimental

setup

40 kWe Test, Laboratory & Power

Plant Slipstream

Proof-of-ConceptFunding: UI (Part of

Dissertation Research, 2013-2015)

Separate Absorber / Stripper

Funding: DOE / UI (2015-2018)

Bench Scale Close-Loop Unit Funding: DOE / UI (2018-2021)

Small PilotFunding: DOE / UI / Corporate partners/ State

Large PilotFunding: DOE /

Corporate Partners /State / UI

Currently

Page 25: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

Acknowledgments

25

Funding Support by USDOE/NETL through Cooperative Agreement No. DE-FE0031600

DOE/NETL Project Manager: Andrew Jones

DOE/NETL Contract Specialist: Bethan Young

Page 26: Development and Bench -Scale Testing of a Novel Biphasic ......Proof-of-Concept. Funding: UI (Part of Dissertation Research, 2013-2015) Separate Absorber / Stripper. Funding: DOE

26

Contact Information:

Yongqi Lu (Project PI)Illinois State Geological Survey

Tel: 217-244-4985Email: [email protected]

Thank you!