Developing Training Programs for Decommissioning

  • Upload
    kentla

  • View
    220

  • Download
    0

Embed Size (px)

Citation preview

  • 8/13/2019 Developing Training Programs for Decommissioning

    1/19

    Revision 0

    December 2013

    Establishing Training Programs to Support

    Decommissioning Activities at Commercial Nuclear

    Power Plants

    A Guide for Training Specialists and Managers

    By Lauren Kent, Senior Training Specialist

    San Onofre Nuclear Generating Station (SONGS)

  • 8/13/2019 Developing Training Programs for Decommissioning

    2/19

    Revision 0

    December 2013

    Table of Contents

    Introduction 1

    Chapter 1: Navigating a Reduction in Force (RIF)

    Pre-RIF Activities 2

    Post-RIF Activities 3

    Chapter 2: Reviewing Sources of Information and

    Identifying Training Requirements

    Generic Sources of Information 5

    Station-Specific Sources of Information 8

    Chapter 3: Establishing a Process for Conducting

    Training Activities at the Station

    Describe the Major Training Activities 9

    Identify Roles and Responsibilities 11

    Publish the Procedure and Communicate Changes

    11

    Chapter 4: Establishing Specific Training Programs

    Develop Task Lists and Training Materials

    13

    Develop Procedures to Govern Training Programs

    14

    Conclusion 16

    Appendix A: List of Tables and Figures 17

  • 8/13/2019 Developing Training Programs for Decommissioning

    3/19

    Revision 0

    December 2013

    1

    Introduction

    Written for training specialists and training managers, this guide describes a

    process for developing training programs that support the initial stages of

    decommissioning. This document was written by a training specialist at San OnofreNuclear Generation Station (SONGS) in San Clemente, CA. In June 2013, the

    company that owns SONGS announced that it would decommission both Units 2 and

    3. The staff was reduced from 1500 to approximately 500 people just two months

    later. The training staff was reduced from 71 to four.

    With significantly fewer resources, the training staff worked to develop

    programs and procedures for a permanently shutdown station. The training staff

    quickly discovered that there is no instruction manual for developing trainingprograms during the initial stages of decommissioning. Guidance from the NRC and

    INPO is scattered and sparse. After benchmarking two other stations, conducting a

    significant amount of research, and eight months, the SONGS training staffsuccessfully developed a single procedure for the conduct of training at the station

    as well as task lists, qualification guides, and training program descriptions for each

    department.

    As Americas nuclear power plants age and struggle to compete with cheapersources of energy, it is likely that more stations will be decommissioned over the

    next few decades. Training staff at these stations will need clear guidance for how

    to develop training programs and procedures during the initial stages of

    decommissioning. To that end, this document discusses the following items.

    Activities that should occur once decommissioning is announced, prior toand following a reduction in force (Chapter 1)

    References that should be reviewed to identify training and qualificationrequirements (Chapters 2)

    A process to design, develop, and implement a procedure to govern theconduct of training activities at the station (Chapter 3)

    A process to use to design and develop task lists, qualification guides, andtraining program descriptions for each program at the station, such ascertified fuel handler and general employee training (Chapter 4)

  • 8/13/2019 Developing Training Programs for Decommissioning

    4/19

    Revision 0

    December 2013

    2

    Chapter 1: Navigating a Reduction in Force (RIF)

    It is not uncommon for companies to downsize the staff at a station that is going

    to be decommissioned. One major issue for the staff members who remain at the

    station is the loss of knowledge that accompanies the RIF. At SONGS, the staffmembers who were selected to stay post-RIF were notified anywhere from one

    week to one day prior to the RIF. This left only a very small amount of time for

    turnover and transfer of knowledge to occur. The list of pre-RIF activities in this

    chapter can be used to ensure that essential knowledge is transferred from the staff

    that is leaving to the staff that will remain.

    After such a major reduction in staff size, it may take several months for people

    to settle into their roles in the new organization structure. It is not uncommon forpeople to have to learn and perform new job functions on a daily basis. At SONGS,

    the remaining training staff members had to earn Nantel proctoring qualifications

    and take over the administration of general employee training and radiation workerpractical factors training. This period of time can be unsettling, confusing, and

    frustrating. The list of post-RIF activities identifies actions that training staff can

    take immediately following the RIF to move forward efficiently during this

    transition time.

    Pre-RIF Activities

    Gather and store passwords. Exam banks, exam records, attendancerecords, and lesson plans that are saved electronically may require a

    password. Gather a list of any passwords that may be required to access

    documents. Even if its likely that the training staff wont use thesedocuments ever again, it is possible that staff may need to locate them during

    internal and external audits.

    Obtain network/database access. At some stations, important files arestored in various areas of the internal computer network or in databases.

    Ask the current network or database owner to grant access for the post-RIF

    training staff, as necessary. At SONGS, the licensed operator exam banks

    were stored on an internal network, which allowed access only to a handful

    of people. Since none of those individuals were staying after the RIF, it was

    essential for at least one person on the post-RIF staff to gain access to that

    network location in order to conduct licensed operator training activities1.

    Obtain keys. There may be locations in the training building that are lockedand contain items that the post-RIF staff may need. It is also possible that

    1SONGS staff decided to maintain operator licenses for a period of time after decommissioning. This was

    because the NRC originally told Kewaunee that 10CFR 50.54M applied to permanently shutdown plants.

  • 8/13/2019 Developing Training Programs for Decommissioning

    5/19

    Revision 0

    December 2013

    3

    these areas may contain items like halon bottles and fire extinguishers thatmust be inspected on a regular basis.

    Submit records. After the RIF is announced, most people will be thinkingabout finding a new job, moving, and starting a new life elsewhere. Post-RIF

    staff members should work with management to ensure that all employeessubmit training records in their possession, such as lesson plans, completed

    remediation plans, attendance records, and exam scores prior to their

    departure.

    Make a list of contacts. It may be necessary to contact former coworkersafter their departure. Consider connecting on LinkedIn or Facebook with

    coworkers, or exchange personal email and/or cell phone numbers.

    Additionally, creating a list of contact information for contractors (for

    simulator support or other training support) will be helpful.

    Identify and learn essential skills. If there are any staff members withessential skills, it may be necessary for the post-RIF staff to learn thesebefore the RIF. At SONGS, there was one person who processed invoices for

    the training department, and he was leaving. Prior to his departure, he

    created a simple user guide so that the post-RIF staff could process several

    outstanding invoices. Other essential skills may be entering attendanceinformation into a database, submitting records for storage, or

    reactivating/renewing operator licenses.

    Post-RIF Activities

    Inventory the skillset of the post-RIF training staff.The remainingmembers of the training staff should meet shortly after the RIF to discuss

    their areas of expertise. At SONGS, the post-RIF training staff consisted of a

    supervisor with experience in project management and general employee

    training, an engineering training instructor, a non-licensed operator training

    instructor, and a licensed operator training instructor. Knowing which skills

    each individual has will allow the staff to solve problems faster and

    distribute work appropriately.

    Review the new organization chart. A review of the new organizationchart can identify potential training needs. For example, if radiationprotection (RP) and chemistry departments are merged, then it is possible

    that RP technicians may be required to perform sampling. If this is a new

    task for RP technicians, then training may be required.

    Review training procedures. Procedures owned by the TrainingDepartment should be reviewed to determine which ones can be voided,

    superseded, or revised to eliminate requirements that no longer apply. The

  • 8/13/2019 Developing Training Programs for Decommissioning

    6/19

    Revision 0

    December 2013

    4

    Procedures Department can provide a list of procedures owned by theTraining Department. It may be necessary to transfer ownership of certain

    procedures to other departments. At SONGs, the Engineering Training

    Department was responsible for the cyber security training procedure before

    the RIF. Post-RIF, it was determined that the Engineering Department

    should take ownership of this procedure, since the Engineering TrainingDepartment was eliminated post-RIF.

    One concept to remember is to take things one RIF at a time. It is only possibleto develop and implement programs and procedures for the current state of the

    station. Procedures should reflect current business practices, not what might

    happen after the next RIF or in five years.

    Most training specialists and managers know how to maintain INPO-accreditedtraining programs. However, when a station permanently shuts down, stations are

    not required to maintain accreditation or follow guidance contained in INPO

    academy documents (ACADs). The following chapter will help training staff toidentify the requirements for training and qualifications that apply to a station in

    the initial stages of decommissioning.

  • 8/13/2019 Developing Training Programs for Decommissioning

    7/19

    Revision 0

    December 2013

    5

    Chapter 2: Reviewing Sources of Information and Identifying

    Training Requirements

    This chapter describes the generic and station-specific sources of

    information that can help training staff to understand the regulatory basis fortraining, identify training commitments that must be upheld, and identify

    commitments that no longer apply.

    Generic Sources of Information

    Table 1 lists sources of information that are applicable to all stations duringthe initial stages of decommissioning.

    Table 1: Generic Sources of Information for Training and Qualification

    Source Applicability

    INPO ACAD 02-002 Discusses administrative withdraw of accreditation2for plants that are

    permanently shutdown.

    NRC rules and

    associated NUREGs3

    10CFR 50.120,Training andQualification of

    Nuclear PowerPlant Personnel,

    and NUREG 1220,

    Training Review

    Criteria Procedure

    10CFR 50.54M,Staffing and

    Licensed Operator

    Requirements

    NUREGs provide guidance on how to implement NRC rules as stated in the

    Code of Federal Regulations (10CFR).

    Discusses the requirement for training programs to follow a systems

    approach to training (SAT) as described in NUREG 1220. These

    documents describe the bare bones requirements of the SAT process.

    Pay close attention to the REQUIRED ELEMENT statements andApplicable Program Characteristics (refer to Figure 1for an example

    using the second SAT element, learning objectives). This rule is

    discussed in further detail in Chapter 3.

    Discusses requirements for licensed operators on shift. The NRC initiallystated that 50.54M applied to defueled stations. As a result, the NRC

    required SONGS to submit a license amendment request (LAR) and arevision to its administrative technical specifications before it allowed

    removal of operator licenses. However, the NRC has recently changed its

    position on 50.54M. Refer to Chapter 4 for additional information.

    2Withdraw of accreditation from INPO can be accomplished by submitting a copy of the letter the station

    sends to the NRC declaring that the plant is permanently shutdown. Note that the station can retain access

    to Nantel for general employee training.

  • 8/13/2019 Developing Training Programs for Decommissioning

    8/19

    Revision 0

    December 2013

    6

    10CFR 50.82,Termination of

    License

    Requires a station to submit written notification to the NRC once the

    decision has been made to permanently cease operations and once the

    reactor(s) have been permanently defueled. Once both of these steps are

    taken, the NRCs oversight activities at the station change: utilities will beinspected per Inspection Manual Chapter (IMC) 2561, Decommissioning

    Power Reactor Inspection Program.

    NRC inspection

    procedures

    IMC 2561,Decommissioning

    Power Reactor

    Inspection

    Program

    IP 36801Organization,

    Management, andCost Controls

    (core procedure)

    IP 37801 SafetyReviews, Design

    Changes, and

    Mods (core

    procedure)

    Inspection manual chapters (IMCs) and inspection procedures (IPs) are

    available atwww.NRC.gov.

    Lists the core and discretionary IPs that the NRC will use to evaluate

    activities at a permanently shutdown plant. Core procedures will beincorporated into the annual inspection schedule. Discretionary

    procedures may or may not be incorporated into the inspection schedule.

    Contains information regarding general employee training (GET) and

    certified fuel handler (CFH) training requirements. This is discussed in

    greater detail in Chapter 4.

    Contains information about training related to 50.59 screening and

    design changes at permanently shutdown facilities. This is discussed in

    greater detail in Chapter 4.

    Operating

    experience/

    benchmarking

    Provides insight to how to structure programs and procedures. Its

    important to ensure that all of the stations unique regulatorycommitments are maintained and a systems approach to training is

    applied when designing and developing training programs. Refer to

    Chapter 4 for additional information on benchmarking and operating

    experience.

    10CFR 50 Appendix

    B, Quality Assurance

    Criteria

    Describes how to perform quality-affecting activities, which are those

    activities that affect safety-related functions of structures, systems, and

    components (SSCs). Quality-affecting activities must be described in

    controlled procedures or instructions. For example, training programsfor staff that conduct quality-affecting activities should be described incontrolled procedures.

    Regulatory Guide1.184,

    Decommissioning

    Power Reactors

    Provides a broad overview of the entire decommissioning process. Referto Figure 2for a timeline of major decommissioning milestones. The

    activities described in this guide may occur before or after the permanent

    shut down of the unit(s).

    http://www.nrc.gov/http://www.nrc.gov/http://www.nrc.gov/http://www.nrc.gov/
  • 8/13/2019 Developing Training Programs for Decommissioning

    9/19

    Revision 0

    December 2013

    7

    Figure 1: Elements of the Systematic Approach to Training from NUREG 1220,Training Review Criteria and Procedures

    Figure 2: Simple Decommissioning Timeline from Regulatory Guide 1.184,

    Decommissioning Power Reactors

    Station-Specific Sources of Information

    The table below lists sources that should be reviewed to identify

    requirements and commitments that are unique to each station.

  • 8/13/2019 Developing Training Programs for Decommissioning

    10/19

    Revision 0

    December 2013

    8

    Table 2: Station-Specific Sources of Information for Training and Qualification

    Source Applicability

    Administrative

    Technical

    Specifications andLicensee Controlled

    Specifications

    Contain the legal requirements related to qualifications and training.

    Technical specifications may commit4the station to a particular

    regulatory guide or American National Standards Institute (ANSI)document, which should also be reviewed to ensure requirements are

    met.

    Updated Final Safety

    Analysis Report

    (UFASR) chapters on

    training and

    qualifications

    Contain requirements related to qualifications and training. There may

    be commitments also stated in the UFSAR. Identify any changes that will

    need to be made to the UFSAR. At SONGS, the UFSAR chapter on training

    stated that the programs were accredited by INPO. Since accreditation

    was withdrawn, this is no longer true. The UFSAR will need to be

    updated to reflect this change.

    Regulatory guides

    and ANSI documents

    Contain requirements related to qualifications and training. These

    documents should be reviewed to determine the minimum requirementsfor each training program. Pay particular attention to the revision of

    the regulatory guide or ANSI document that is discussed in thetechnical specifications and/or UFSAR. Keep in mind when

    benchmarking that each station may be committed to different revisions

    of the same ANSI document or regulatory guide. As such, requirements

    can differ from station to station. The Quality Assurance or Nuclear

    Oversight Department will be able to provide the training staff with

    copies of these documents.

    The CorrectiveAction Program

    (CAP)

    Contains requirements that must be followed as a result of operatingexperience. There may be CAP products such as corrective actions (CAs)

    and corrective actions to prevent reoccurrence (CAPRs) embedded in

    procedures. Follow station procedures for removing CAs and CAPRs if

    necessary.

    A review of these documents will enable training staff to identify program

    requirements that must be maintained and those that can be removed. The staff

    can now begin developing programs that support decommissioning activities and

    meet regulatory requirements. This is the topic of the next chapter.

    4To be committed to a regulatory guide or ANSI document means that the station has told the NRC that

    it will comply with the guidance contained in that document.

  • 8/13/2019 Developing Training Programs for Decommissioning

    11/19

    Revision 0

    December 2013

    9

    Chapter 3: Establishing a Process for Conducting Training

    Activities at the Station

    One or more events withdraw of accreditation from INPO, cancellation of

    training sessions, and the large reduction in the training staff will likely causemany people at the station to think that training will no longer occur. Although the

    volume and frequency of training will be considerably less than when the plant wasoperating, the requirements of 10CFR 50.120 will still apply for non-licensed

    operator5, chemistry, radiation protection, engineering, and maintenance personnel

    (unless the station requests and is granted an exemption6from the rule).

    Rule 10CFR 50.120 also directs that training must be derived from a

    systems approach to training as defined in 10 CFR 55.4. Rule 10CFR 55.4 describes

    the five elements of the systems approach to training (SAT). These five elements,

    which are discussed in detail in NUREG 1220, are essentially the same as INPOs

    ADDIE model (analysis, design, development, implementation, and evaluation):

    A systematic analysis is conducted of the jobs to be performed Learning objectives are derived from the analysis and describe the

    desired performance of trainees

    Training design and implementation are based on the learningobjectives

    Traineesmastery of the learning objectives is evaluated The training program is evaluated and revised based on the

    performance of personnel in the job setting

    Training staff at SONGS developed a procedure to describe the conduct oftraining activities at the site (titled Conduct of Training). This procedure replaced

    the five ADDIE procedures. The next three sections in this chapter describe how to

    develop and implement a procedure to govern the conduct of training at a

    permanently shutdown facility with reduced staffing.

    Describe the Major Training Activities

    The procedure written to govern the conduct of training will need to

    incorporate all five elements of the SAT process in order to comply with 10CFR

    50.120. Staff may choose to review and simplify existing training procedures,modify procedures from other decommissioned stations, or start from scratch.

    5This includes the certified fuel handler program, which is described in detail in Chapter 4.6The compliance or regulatory affairs personnel at the station can assist with submission of exemptions

    from 10CFR rules.

  • 8/13/2019 Developing Training Programs for Decommissioning

    12/19

    Revision 0

    December 2013

    10

    SONGS staff used several references to write its procedure: Kewaunees

    procedure, NUREG 1220, and SONGs ADDIE procedures. The procedure contains

    guidance for conducting the following activities:

    Conducting analysis.The procedure directs that each program maintain atask list. The list must identify the tasks that are selected for initial and/or

    continuing training. Because curriculum review committees (CRCs) are no

    longer required, the procedure requires that a representative sample of job

    incumbents review the task list biennially to ensure its accuracy. The

    procedure also requires that line managers conduct an annual training needs

    survey. This survey solicits feedback from incumbents about the quality of

    their training programs and can be used to identify gaps in the program. In

    addition, the procedure directs how to address training requests.

    Developing learning objectives.The procedure includes direction on howto write learning objectives that contain an action, condition, and standardbased on the job analysis. Examples are included.

    Design and implementation. A lesson plan template included as anattachment to the procedure provides guidance on how to create self-study

    and/or classroom training materials. A checklist in a separate attachment

    provides guidance for how to conduct training in all settings (e.g., on the job

    training and classroom training).

    Trainee evaluation. The procedure discusses how to create evaluationitems, including written and oral exams. Instructions for maintaining exam

    security, proctoring exams, and conducting remedial exams are provided inattachments.

    Program evaluation and revision. Observations of incumbents performingwork and observations of training (including OJT) are used to determine

    training program effectiveness. These observations are performed by

    supervisors, managers, and training staff.

    The Conduct of Training procedure also contains guidance for training

    activities that support the five elements of the SAT process:

    Verifying worker qualifications. All staff must verify qualifications prior toconducting work, and supervisors must verify qualifications prior to

    assigning work. The procedure prescribes how to verify qualifications.

    Writing training requests. Incumbents need to know how to initiatetraining requests. At SONGS, training requests are initiated via a nuclear

  • 8/13/2019 Developing Training Programs for Decommissioning

    13/19

    Revision 0

    December 2013

    11

    notification (NN), which is entered into the Corrective Action Program andreviewed by management.

    Stations are encouraged to look at similar procedures from other stations

    and to simplify their existing procedures to fit the needs of a permanently shutdown

    station. When drafting this procedure, the writer(s) should remember thatthe users may not necessarily be INPO-qualified training instructors or even

    members of the training staff. They may be job incumbents who are subject

    matter experts (SMEs) but not experienced with training. Thus, the procedures

    should be written to be as flexible and straightforward as possible if the procedure

    users include staff outside of the training organization.

    Identify Roles and Responsibilities

    At SONGS, personnel involved in training activities include training staff,

    training program owners (TPOs), and subject matter experts (SMEs).

    The TPO is the line manager of a department (e.g., the Operations Manager is

    the TPO for Operations Department). Each TPO is responsible for training activities

    in their department. The procedure allows TPOs to delegate training activities to

    training staff or to SMEs in their department. Depending on the size of the training

    staff, TPOs may have to delegate all training activities to SMEs.

    At SONGS, the training staff includes three trainers and one training

    supervisor for a population of 200+ job incumbents. There simply are not enough

    trainers to perform training activities for each department. As a result, the training

    staff provides more coaching and oversight of the training programs than actual

    training; the role of the SONGS training staff is to facilitate training of job

    incumbents by SMEs.

    Publish the Procedure and Communicate Changes

    Once a new or revised procedure has been drafted, changes should be

    communicated to all affected personnel.

    There are several methods to use to inform staff at the station about the

    changes. For changes that affect all personnel, several methods should be used inorder to reach the largest audience. For example, if there is a change to the way staff

    verify qualifications or enroll in training, then a required reading, site-wide email, or

    an announcement in the weekly bulletin may all be required to reach the largest

    audience.

    If certain staff members are going to have to take on more responsibilities as

    a result of post-shut down reductions in force, then it may be best for training staff

  • 8/13/2019 Developing Training Programs for Decommissioning

    14/19

    Revision 0

    December 2013

    12

    to schedule one-on-one meetings with these individuals to make sure that they are

    aware of their new roles and responsibilities. At SONGS, the three trainers each

    met with the TPOs to review the procedure with them. In this meeting, the trainers

    ensured the TPOs were aware of their responsibilities and the resources available to

    them to conduct training activities.

    The Conduct of Training procedure is applicable to all training programs;

    however, each department will need a procedure to outline the specific

    requirements for its training and qualification program(s). The next chapter

    discusses the development of training program descriptions for each department.

  • 8/13/2019 Developing Training Programs for Decommissioning

    15/19

    Revision 0

    December 2013

    13

    Chapter 4: Establishing Specific Training Programs

    As discussed in Chapter 3, 10CFR50.120 requires that training programs be

    established for non-licensed operator, chemistry, radiation protection, engineering,

    and maintenance personnel using a systems approach to training. During the initialstages of decommissioning, training requirements will be substantially less than

    when the plant was operating. However, the training programs will need to comply

    with all commitments described in the UFSAR, technical specifications, and licensee

    controlled specifications until exemptions are granted, as discussed in Chapter 2.

    This section describes a process to use to develop training programs for non-

    licensed operator, chemistry, radiation protection, engineering, and maintenance

    personnel during the initial stages of decommissioning.

    Develop Task Lists and Training Materials

    The existing task lists for each program should be revised to reflect onlythose tasks that are still relevant to a permanently shutdown station. At SONGS, the

    training staff completed an initial revision of the task lists and then asked the

    incumbents to review it. A final draft was submitted to each training programowner for review and approval. Task lists should also include new or modified

    tasks that may result from reductions in staff, redistribution of workload, and

    changes to procedures resulting from decommissioning. The revised tasks lists are

    the first step in creating training programs for decommissioning.

    After an approved task list has been created, it will be necessary to identify

    the learning objectives and training materials associated with the tasks that are

    selected for training. A document such as a task to training matrix, which can beproduced from a VISION database, should be developed or revised to indicate the

    training materials that contain learning objectives associated with tasks.

    It will also be necessary to develop new training materials for each program.

    Qualification guides will need to be updated to reflect the tasks associated with

    decommissioning. Also, new qualifications will need to be developed. For

    Operations Department, certified fuel handlers and certified operators will replace

    licensed senior reactor operators and licensed reactor operators (once the certified

    fuel handler program is approved by the NRC, as required by 10CFR 50.2).

    Many of the people remaining at the station will be able to be exempted from

    the new qualifications. Training staff should ensure that all exemptions are

    documented properly and that supporting documentation justifies theexemption. Reasons for exemptions should not be vague, such as, So and so has

    five yearsexperience doing such and such job. However, So and so has been

    qualified as a welder for five years, and inclusion of the individuals qualificationhistory, would be adequate.

  • 8/13/2019 Developing Training Programs for Decommissioning

    16/19

    Revision 0

    December 2013

    14

    At SONGS, an audit of training and qualifications was performed by theNuclear Oversight Department about five months after the reduction in force. The

    audit identified weaknesses in the exemption process, such as lack of supporting

    documentation, and vague reasons for qualification exemption. Ensuring that

    exemptions are accurate and detailed will prevent rework later.

    Develop Procedures to Govern Training Programs

    Each training program owner should maintain a training program

    description (TPD) procedure (just like they did when the plant was operating). The

    TPD should list the requirements of the initial qualification program, requirements

    for continuing training to maintain proficiency, and any other requirements related

    to training and qualification.

    Training staff should review select NRC Inspection Manual Chapters (IMCs)

    to identify training program requirements. The following table lists the IMCsapplicable to specific training programs.

    Table 3: Sources of Information for Specific Training Programs

    Source Applicability

    IP 36801

    Organization,

    Management, and

    Cost Controls

    Describes how inspections will be conducted for compliance with 10CFR

    50.120:

    A review of training should include an assessment of the licensee's

    implementation of 10 CFR 50.120, if applicable. Although the NRC staff

    expects that most licensees will apply for full or partial exemption fromthis requirement, requirements still apply to the certification and

    periodic training of certified fuel handlers, operators of refueling

    equipment, and personnel who perform maintenance and

    surveillance of equipment important to safety.

    Includes discussion on the certified fuel handler programs:

    Operator training should include: normal and abnormal fuel handling

    at the spent fuel pool or Interim Spent Fuel Pool Storage

    Facility (references 5 and 6); fuel handling accidents and/or

    events; and, the identification and mitigation of operatingconditions adverse to the safe storage of spent fuel or highlevel radioactive waste to name a few. An effective training

    program could also include, in part, safety evaluations,

    modifications, radiation protection, effluent controls, and

    design changes.

    Includes discussion about general employee training:

  • 8/13/2019 Developing Training Programs for Decommissioning

    17/19

  • 8/13/2019 Developing Training Programs for Decommissioning

    18/19

    Revision 0

    December 2013

    16

    Conclusion

    In summary, the goal of the training staff during the initial stages of

    decommissioning should be to develop revised task lists, training materials, training

    program descriptions, and a procedure to govern the conduct of training activitieswith reduced staff and reduced training requirements (i.e., INPO requirements).

    When developing these documents, training staff should keep in mind the

    following items:

    Simply as much as possible to support a reduced staff. Make processes as flexible as possible. Communicate changes to personnel using the most effective methods. Ensure the procedure that governs the conduct of training activities incudes

    each element of the SAT process as described in NUREG 1220.

    Trainers still need to be the training conscience for the organization,particularly when it comes to processing exemptions and waivers.

    Maintain objective evidence of each phase of the SAT process duringprogram development (e.g., approved task lists, a document that identifies

    tasks and their associated training materials, copies of lesson plans and

    exams, and training records such as attendance sheets).

    Sometimes the decision to decommission a station is announced eighteen

    months prior to its permanent shutdown. Other times the decision todecommission plant seems to come suddenly, after a plant has been shut down

    for equipment concerns. Either way, the decommissioning will bring about huge

    changes in staffing and station activities.

    As more stations begin the process of decommissioning, it will be beneficial

    for the staff at these stations to learn as much as possible from others in theindustry that have lived through the process. Sharing operating experience and

    expertise will enable the staff at these stations to know where to start when astation will be decommissioned.

  • 8/13/2019 Developing Training Programs for Decommissioning

    19/19

    Revision 0

    December 2013

    17

    Appendix A: List of Figures and Tables

    Figures

    Figure 1: Elements of the Systematic Approach to Training fromNUREG 1220, Training Review Criteria and Procedures

    7

    Figure 2: Simple Decommissioning Timeline from Regulatory

    Guide 1.184, Decommissioning Power Reactors7

    Tables

    Table 1: Generic Sources of Information for Training andQualification

    5

    Table 2: Station-Specific Sources of Information for Training

    and Qualification8

    Table 3: Sources of Information for Specific Training Programs 14