171
Jodhpur XVII DETAILED PROJECT REPORT DETAILED PROJECT REPORT DETAILED PROJECT REPORT DETAILED PROJECT REPORT NAME OF WATERSHED : CHANDRAKH (JODHPUR XVII) MACRO/MICRO WATERSHED No. : CLUSTER GRAM PANCHAYAT : CHANDRAKH PROJECT AREA : 3000 Ha. PROJECT COST : 450 Lakh -: SUBMITTED BY :- ASSISTANT ENGINEER PROJECT IMPLEMENTING AGENCY PANCHAYAT SAMITI - BAORI (JODHPUR)

DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

DETAILED PROJECT REPORTDETAILED PROJECT REPORTDETAILED PROJECT REPORTDETAILED PROJECT REPORT NAME OF WATERSHED : CHANDRAKH (JODHPUR XVII) MACRO/MICRO WATERSHED No. : CLUSTER GRAM PANCHAYAT : CHANDRAKH PROJECT AREA : 3000 Ha. PROJECT COST : 450 Lakh

-: SUBMITTED BY :-

ASSISTANT ENGINEER PROJECT IMPLEMENTING AGENCY

PANCHAYAT SAMITI - BAORI (JODHPUR)

Page 2: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

PAGE No.

CHAPTER - 1 Introduction

1.1 Introduction

1.2 Philosophy of Integrated watershed management Pragramme

1.3 Objectives of IWMP

1.4 Need of Watershed Development Programme

1.5 Criteria and weightage for selection of Watershed

Table No. 1 Criteria and weightage for selection of watershed

Table No. 1.1 Weightage of the watershed

1.6 Project Background

Table No. 2 Basic Project Information

Table No. 3 Watershed information

CHAPTER - 2 Project Implementing Agency

2.1 Project Implementing Agency

Table No. 4 Detail of PIA

Table No. 5 Staff at PIA level

2.1.1 Role and responsibility of WDT

2.1.2 SWOT analysis of PIA

CHAPTER - 3 Basic Information of Watershed

3.1 Geography and Geo-hydrology

3.1.1 Land use pattern

Table No. 6 Land use pattern

3.1.2 Soil and topography

Table No. 7 Soil type and topography

Table No. 8 Flood and drought condition

Table No. 9 Climatic conditions

Table No. 10 Physiography and relief

Table No. 11 Slope detail of watershed

INDEX

PARTICULARS

Page 3: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Table No. 12 Erosion status in project area

3.1.3 Land and Agriculture

Table No. 13 Land ownership details

Table No. 14 Land use & land classification

Table No. 15 Agriculture

Table No. 16 Crop details

Table No. 17 Crop production

3.1.4 Livestock

Table No. 18 Livestock

Table No. 19 Milk Production

Table No. 20 Drinking water

3.2 Socio-Economic Profile

3.2.1 Demographic Status

Table No. 21 Demographic information

Table No. 22 Literacy rate

Table No. 23 Poverty

3.2.2 Migration Pattern

Table No. 24 Migration details

Table No. 25 Village infrastructure

Table No. 26 Facilities / HH assets

CHAPTER - 4 Watershed Activities

4.1 Scientific Planning

Table No. 27 Details of Scientific planning and Inputs in the project

4.2 Watershed Development Approach and Strategy

4.2.1 Social Strategy

4.2.2 Technical Strategy

4.2.3 Water Budgeting

Table No. 28 Strange's Table

Table No. 29 Total Available Runoff

Table No. 30 Runoff Tapped in Existing Structures

Page 4: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Table No. 31 Balance Available Runoff

4.3 Institution building

4.3.1 Watershed Committee (WC)

Table No. 32 Watershed Committee Chandrakh

4.3.2 Self Help Group

4.3.3 User Group

Table No. 33 Status of SHG

4.4 Physical activities to be undertake

4.4.1 Entry Point Activity (EPA)

Table No. 34 Entry Point Activity (EPA)

4.4.2 PRODUCTION MEASURES

4.4.2.1 AGRO FORESTRY

4.4.2.2 MIXED HORTICULTURE

4.4.2.3 CROP DEMONSTRATION

4.4.2.4 ORGANIC FARMING SYSTEM/ COMPOST PITS

4.4.2.5 HOMESTEAD KITCHEN GARDENS

4.4.2.6 PASTURE DEVELOPMENT

4.4.2.7 FENCING

4.4.2.8 DITCH CUM BUND (DCB)

4.4.3 CONSERVATION MEASURES

4.4.3.1 CONTOUR CULTIVATION

4.4.3.2 CONTOUR BUND/ CONTOUR VEGETATIVE HEDGE

4.4.3.3 V DITCH

4.4.3.4 STAGGERED TRENCHES

4.4.3.5 WATER HARVESTING STRUCTURE (TANKA)

4.4.3.6 LOOSE STONE CHECK DAM

4.4.3.7 EARTHEN DAM

4.4.3.8 DUG OUT POND (NADI)

4.4.3.9 MASONRY CHECK DAM

CHAPTER - 5 Activity wise Abstract of Cost

Page 5: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

CHAPTER - 6 Annual Action Plan

CHAPTER - 7 Project Outcomes

CHAPTER - 8 Technical Design & Estimates

CHAPTER - 9 Annexure

Page 6: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

CHAPTER - 1

IIIIIIIINNNNNNNNTTTTTTTTRRRRRRRROOOOOOOODDDDDDDDUUUUUUUUCCCCCCCCTTTTTTTTIIIIIIIIOOOOOOOONNNNNNNN

Page 7: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

1.1 Introduction

In India, where a lot of water goes waste, it is important to apply the technology of Watershed

management to solve its annual problems of droughts and floods. The demand for water exceeds its supply.

Conflicts sharing water resources are on the rise. Planning and development of Watersheds calls for a rigorous

understanding of the occurrence and movement of water in the surface and sub-surface systems along with soil

and nutrient losses in a Watershed as the need arises for a proper Watershed management of that area. In a

country like India, where a lot of running water goes waste, it becomes very important to apply the technology of

Watershed management to solve its annual problems of droughts and floods.

Watershed management basically involves harmonizing the use of soil and water resources between

upstream and downstream areas within a Watershed toward the objectives of natural resource conservation,

increased agricultural productivity and a better standard of living for its inhabitants. Identifying and addressing

the significant externalities associated with Watershed is critical for these objectives to be achieved in a

sustainable manner.

In the 1980s and 1990s, agricultural scientists and planners aimed to promote rain-fed agriculture through

Watershed development. A Watershed is an area from which all water drains to a common point, making it an

interesting unit for managing water and soil resources to enhance agricultural production through water

conservation

1.2 Philosophy of Integrated Watershed management Programme

Page 8: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

IWM planning is a comprehensive multi-resource management planning process, involving all stakeholders

within the Watershed, who together as a group, cooperatively work towards identifying the resource issues and

concerns of the Watershed, as well as develop and implement a Watershed plan with solutions that are

environmentally, socially and economically sustainable.

In India, the IWM efforts go back to 1970. There have been many changes in the implementation strategies

during the following years. Until 1995, Watershed development projects were officially coordinated by multi-

sectoral programmes (with differing objectives) launched by the Government of India. After review in 1999 by

the Ministry of Rural Development and the Ministry of Agriculture, a common set of operational guidelines,

objectives, strategies and expenditure norms were established for Watershed development programmes in 2001.

These are implemented through programmes such as DPAP (Drought-Prone Area Programme), DDP (Desert

Development Programme) and IWDP (Integrated Watershed Development Programme).

The guidelines encourage the active involvement of non-governmental organizations, semi-governmental

institutions and private enterprises, universities and training institutions. However, concerns are being raised that

emphasis in Watershed development programmes is still firmly based on the belief that water is an infinite

resource, through development of groundwater abstraction and water harvesting techniques. IWM does not

merely imply the amalgamation of different activities to be undertaken within a hydrological unit. It also requires

the collation of relevant information so as to evaluate the cause and effect of all the proposed actions. The

Watershed is the smallest unit where the evaluation of human-induced impacts upon natural resources becomes

possible. Therefore, although the ‘Panchayat’ remains the preferred implementation unit, the Watershed should

be the evaluation unit used in assessing impacts

Page 9: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

1.3 Objectives of the IWMP

The main objectives of the IWMP are to restore the ecological balance by harnessing, conserving and

developing degraded natural resources such as soil, vegetative cover and water. The outcomes are prevention of

soil run-off, regeneration of natural vegetation, rain water harvesting and recharging of the ground water table.

This enables multi-cropping and the introduction of diverse agro-based activities, which help to provide

sustainable livelihoods to the people residing in the Watershed area.

1.4 Need of Watershed Development Programme

Watershed Development Programme is prioritized on the basis of thirteen parameters namely Poverty

Index, Percentage of SC/ST, Actual wages, Percentage of small and marginal farmers, Ground water status,

Moisture Index, Area under rain-fed agriculture, Drinking water situation in the area, Percentage of the degraded

land, Productivity potential of the land, Contiguity of another Watershed that has already developed/treated,

Watershed approach for plain or for hilly terrain

1.5 Criteria and weightage for selection of Watershed

State Remote Sensing Application Center, Jodhpur (SRSAC) has prepared "Watershed Atlas of Rajasthan ".

Watersheds have been delineated into macro / micro in each block. These have been prioritized on the basis of

two important parameters i) extent of availability of cultivable arable lands and ii) Drainage Density. Besides this

priority Watershed with preponderance of resource poor, SC/ST population is given importance. Willingness of

community to participate, contribute in the programme and to take up responsibility of post project maintenance

of the created assets. Weightage given to these criteria for selection is as follows:

Page 10: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

Table No. 1 Criteria and weightage for selection of Watershed

S. No

.

Criteria Maximum

score Ranges & scores

i Poverty index (% of

poor to population)

10 Above 80 % (10) 80 to 50 % (7.5) 50 to 20 % (5) Below 20 %

(2.5)

ii % of SC/ ST population 10 More than 40 % (10)

20 to 40 % (5) Less than 20 % (3)

iii Actual wages 5 Actual wages are significantly lower

than minimum wages (5)

Actual wages are equal to or

higher than minimum wages

(0)

iv % of small and marginal farmers

10 More than 80 % (10)

50 to 80 % (5) Less than 50 % (3)

v Ground water status 5 Over exploited (5) Critical (3) Sub critical (2) Safe (0)

vi Moisture index/ DPAP/ DDP Block

15 -66.7 & below (15) DDP Block

-33.3 to -66.6 (10) DPAP Block

0 to -33.2 (0) Non DPAP/ DDP Block

vii Area under rain-fed

agriculture

15 More than 90 %

(15)

80 to 90 % (10) 70 to 80% (5) Above 70 %

(Reject)

viii Drinking water 10 No source (10) Problematic village (7.5)

Partially covered (5)

Fully covered (0)

ix Degraded land 15 High – above 20 % (15)

Medium – 10 to 20 % (10)

Low- less than 10 % of TGA (5)

x Productivity potential

of the land

15 Lands with low

production & where productivity

can be

Lands with

moderate production &

where

Lands with high

production & where

productivity can

Page 11: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

significantly

enhanced with reasonable efforts

(15)

productivity can

be enhanced with reasonable

efforts (10)

be marginally

enhanced with reasonable efforts

(5)

xi Contiguity to another

Watershed that has

already been developed/ treated

10 Contiguous to

previously treated

Watershed & contiguity within the micro-Watersheds in the

project (10)

Contiguity within

the micro-

Watersheds in the project but non contiguous to previously

treated Watershed (5)

Neither

contiguous to

previously treated Watershed nor contiguity within the micro-

Watersheds in the project (0)

xii Watershed approach in the plains (more than

one contiguous micro-Watersheds in the

project)

15 Above 6 micro-Watersheds in

Watershed (15)

4 to 6 micro-Watersheds in

Watershed (10)

2 to 4 micro-Watersheds in

Watershed (5)

xiii Watershed approach in the hills (more than

one contiguous micro-Watersheds in the

project)

15 Above 5 micro-Watersheds in

Watershed (15)

3 to 5 micro-Watersheds in

Watershed (10)

2 to 3 micro-Watersheds in

Watershed (5)

Total 150 150 90 41 2.5

Based on these thirteen parameters a composite ranking was given to Jodhpur XVII Watershed project as

given in table No. 1.1

Total number of families under BPL is 182 which are less than 50 per cent of the total households. The

percentage of SC/ST is about 20 per cent to the total population. Rain fed agriculture forms the primary

Page 12: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

occupation of the Watershed due to the fact that ground water is very deep and there is no source of irrigation.

More than 50 per cent of the farmers are small and marginal by nature and the actual wages earned by the

labour is more than the minimum wages.

Since the rainfall received is erratic and irregular, the moisture index is low and the area is classified under

DDP block. The Jodhpur XVII Watershed falls in the continuity with other Watershed namely Chandrakh

(HARIYALI-IV). Watershed approach was followed taking into consideration five Watersheds covering a total area

of 3000 ha.

Table No. 1.1 Weightage of the Watershed

S.

No.

Distt Block Project

Name

No. of micro

W/s covered

Proposed

project

area

Type of

project

(Hilly /

Desert /

others)

Propo

sed

cost

Weightage under the criteria

I II III IV V VI VII VIII IX X XI XII Total

1 Jodhpur Baori Jodhpur

XVII

Cluster 3000 Desert 450 7.5 5 0 5 5 10 15 7.5 10 10 10 10 95

1.6 Project Background

Page 13: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

Jodhpur XVII project is located in Baori Panchayat Samiti, Jodhpur District of Rajasthan State. The project

is a Cluster of three villages namely Chandrakh, Raikoria and Nahri Nadi.

The total project area of the Watershed is about 3600 ha of which 3000 ha. has been undertaken to be

treated under Integrated Watershed Management Programme (IWMP) starting year 2009-10.

The nearest town is Baori which is about 16 Km from Jodhpur XVII and is well connected by pucca road.

The Watershed includes area of three villages namely Chandrakh, Raikoria and Nahri Nadi. Jat, Rajput, Bishnoi,

and SC communities are the primary inhabitants of the Watershed. The livelihood of these people is primarily

based on rain-fed agriculture, animal husbandry, wage labour, cow, goat and sheep rearing. The project area falls

under the Desert Prone area according to DoLR Classification and situated at 28o N Latitude & 71o E Longitude.

Table no. 2: Basic Project Information

S.

No.

Name of

Project

Villages Area

(ha.)

Gram

Panchayats

District PIA Area

falling in

Project

(ha.)

Project

Cost Name Census

Code

1 Jodhpur

XVII

Chandrakh

Nahri Nadi

01938600 4097 Chandrakh Jodhpur A. En.

3000

450

lakh

2 Raikoria 01942300 997 Chandrakh Jodhpur A. En.

Page 14: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

Table no. 3: Watershed information

Name of the

project

Watershed to be

treated

Watershed type

Jodhpur XVII 3000 ha Cluster

Page 15: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

CHAPTER – 2

PPPPPPPPRRRRRRRROOOOOOOOJJJJJJJJEEEEEEEECCCCCCCCTTTTTTTT

IIIIIIIIMMMMMMMMPPPPPPPPLLLLLLLLEEEEEEEEMMMMMMMMEEEEEEEENNNNNNNNTTTTTTTTIIIIIIIINNNNNNNNGGGGGGGG

AAAAAAAAGGGGGGGGEEEEEEEENNNNNNNNCCCCCCCCYYYYYYYY

Page 16: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

2.1 Project Implementing Agency

The Project Implementing Agency (PIA) is selected by State Level Nodal Agency (SLNA) for Integrated

Watershed Management Programme (IWMP) in Rajasthan. The PIA for Jodhpur XVII Watershed is Assistant

Engineer Panchayat Samiti Baori. The PIA is a block level nodal agency responsible for smooth implementation of

Watershed project. The objectives of PIA are supervising, planning, implementing and promoting Watershed

development project and related development activities as per guide lines. The PIA has dedicated and experienced

staff:

Table no. 4 : Detail of PIA

Sr.

No. Names of project Details of PIA

1 IWMP Jodhpur XVII

Designation

& Address

AEn Watershed development & soil conservation

Baori (Jodhpur)

Telephone 02921277024

Fax

E-mail [email protected]

Page 17: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

Table no. : 5 Staff at PIA level

S.

No.

Name Age Sex Designation Qualification

1 Suresh Kumar Duggal 52 M Assistant Engineer B.E. (Ag)

2 Giriraj Kishor Nagla 40 M Junior Engineer B.E. (Ag) M.E. (SWC)

3 Jitendra Mathur 38 M WDT (Technical) Diploma in Civil Engg.

4 Shivdan Singh Rathore 40 M WDT (Agriculture) B.Sc. (Ag)

5 Nathuram Punia 30 M WDT (Veterinary) Diploma in Vet. Astt.

2.1.1 Roles and Responsibilities of WDT

1 Assist Gram Panchayat / Gram Sabha in constitution of the Watershed Committee and their

functioning.

2 Organizing and nurturing User Groups and Self - Help Group.

3 Mobilizing women to ensure that the perspectives and interests of women are adequately reflected in

the Watershed action plan.

4 Conducting the participatory base - line surveys, training and capacity building.

Page 18: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

5 Preparing detailed resource development plans including water and soil conservation or reclamation

etc. to promote sustainable livelihoods at household level.

6 Common property resource management and equitable sharing.

7 Preparing detailed Project Report (DPR) for the consideration of Gram sabha.

8 Undertake engineering surveys, prepare engineering drawings and cost estimates for any structures

to be built

9 Monitoring, checking, assessing, and undertaking physical verification and measurements of the work

done.

10 Facilitating the development of livelihood opportunities for the landless.

11 Maintaining project accounts.

12 Arranging physical, financial and social audit of the work undertaken.

13 Setting up suitable arrangement for post-project operation, maintenance and future development of

the assets created during the project period

2.1.2 SWOT Analysis of the PIA

Strength:

1 Dedicated and experience staffs and multidisciplinary team

2 Strong linkages with national and state level institutions, agricultural universities, for

capacity building and technical guidance.

3 Scientific planning in Watershed project with the help of SRSAC, Jodhpur

Page 19: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

4 District level monitoring, coordination & cooperation committee.

5 Well establishment of PRIs for social audits.

6 Watershed Dept. have long experience in Watershed works and has won five national

productivity awards

Weakness:

1 Lack of proper supporting staff.

2 No permanent staff

3 No permanent office building.

4 Unwanted political interference.

Opportunities:

1 Sustainable livelihood generation landless and asset less.

2 Improvement of socio-economic status of poor’s.

3 Awareness generation among the illiterates through IEC activities by usage of new ICT

activities.

4 Reduction of migration rate.

5 Usage of new technologies of Watershed modeling and GPS for monitoring the Watershed

activities.

6 Over all integrated development of rural peoples

7 Independent DWDU, PIA & Watershed committee to over all monitoring and execution of

Page 20: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

activities.

Threats:

(1)Lack of sustainable agriculture development.

(2)Delay of releasing project fund from the higher authority.

(3)Lack of contribution and cooperation from local peoples.

(4)Low and erratic rainfall in the project area.

(5)Low literacy rate in the project area.

Page 21: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

CHAPTER - 3

BBBBBBBBAAAAAAAASSSSSSSSIIIIIIIICCCCCCCC IIIIIIIINNNNNNNNFFFFFFFFOOOOOOOORRRRRRRRMMMMMMMMAAAAAAAATTTTTTTTIIIIIIIIOOOOOOOONNNNNNNN

OOOOOOOOFFFFFFFF WWWWWWWWAAAAAAAATTTTTTTTEEEEEEEERRRRRRRRSSSSSSSSHHHHHHHHEEEEEEEEDDDDDDDD

Page 22: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

3.1 Geography and Geo-hydrology

3.1.1 Land use pattern

The net geographical area of Watershed is about 3000 ha out of which 0.0 % is forest area.

About 39 % of the total land is classified under wasteland of which 7 % is cultivable and rest is

uncultivable. About 59.7 % of land is under agriculture from which 72.77 % is under rain-fed and a

kharif crop is taken, 27 % of land is irrigated by tube wells.

Table no. : 6 Land use pattern

S.

No.

Name of

Village

Geographical

area

Forest

area

(ha

)

Land under

agri. Use

(ha)

Rain-fed

area

(ha)

Permanent

pasture

Wasteland

Cultivable

(ha)

Non

cultivable

(ha)

1 Chandrakh

Nahri Nadi

4097 0.00 3660 2500 34 1091 1249

2 Raikoria 997 0.00 990 975 18 0 26

3.1.2 Soil and topography

Jodhpur XVII Watershed project falls under North West Rajasthan Agro Climatic Zone. The

soil is mainly sandy loam and. The soil is brown to very dark grayish brown in surface colour. The

depth of soil is moderate to deep about 25 to 75 cm. The predominant texture of soil is loamy sand

Page 23: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

and silt and clay. The soil fertility is very poor with low nitrogen, phosphorus and potash. The soil

falls in Aridsol and Inseptisols order. The topography of the area is moderate ranging from 0-10%

slope

Table no. : 7 Soil type and topography

S.

No.

Name of Agro-

climatic zone

covers w/s area

Area in

ha

Name of villages Major soil types Topography

Type Area

1 I A 4097 Chandrakh,

Nahri Nadi

Sandy to

Loamy sand

4097 Moderate

slope

2 I A 997 Raikoria Sandy to

Loamy sand

997 Moderate

slope

Table no. : 8 Flood and drought condition

S. No. Village Flood (Incidence) Drought (Incidence)

1 Chandrakh Nahri Nadi Nil Once in three year

2 Raikoria Nil Once in three year

Page 24: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

Page 25: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

Table no. : 9 Climatic conditions

S.

No.

Year Rainfall (mm) Temperature (degree centigrade) Highest intensity of

rainfall (mm in a

day)

Annual

Rainy days

Maximum Minimum

1 2010 420 48.5 6.3 121 33

2 2009 145 48.0 7.4 45 10

3 2008 270.2 47.5 6.1 44 16

4 2007 201 46.0 6.2 43 17

5 2006 205.5 46.5 5.8 33 18

The rainfall is scanty which has resulted in recurrent phenomenon of drought in every two to three

years. The average rainfall of this area is about 250 mm (from past five year data) with a highest intensity

of 121 mm within span of a day. This uneven distribution is leading to runoff of soil every year to the

streams resulting in silting of the village tank.

Table no. : 10 Physiography and relief

Page 26: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

S. No. Village Area Highest

contour level

Lowest

contour level

Level

difference

Length of

travel

% slope

1 Chandrakh

Nahri Nadi

4097 370 360 5 4002 0.1

2 Raikoria 997 354 342 6 2940 0.2

Table no. : 11 Slope Detail of Watershed

S. No. Slope % Area

1 0-1 % 1790

2 1-3 % 730

3 3-5 % 480

Total 3000

Table no.: 12 Erosion status in project Area

Cause Type of erosion Area affected (ha) Run

off(mm/

year)

Average soil loss

(Tonnes/ ha/

year)

Water erosion

a Sheet 1114 300 4112

Page 27: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

b Rill 32 300 230

c Gully 17 300 860

Sub-Total 5202

Wind erosion 1780 NA 2240

Total for project 2943 7442

Project Area is affected by water erosion & wind erosion both, such that loss of soil fertility takes

place every year. Production depleting year by year. It is major problem of Watershed

3.1.3 Land and Agriculture

Lack of surface water source and very deep ground water has limited the sufficient base for irrigation

as well as drinking purpose. The average land holding is about 6.75 ha ranging from 1 to 20 ha. Lack of

irrigation source forces the majority of the farmers to migrate to ensure their livelihood. This affects

directly the demographic profile of the Watershed. The major crops cultivated by the farmers are Bajra

(Pearl millet). Some of the farmers have Tube well as source of irrigation and take up Rabi crop also. The

soil and moisture conservation measures such as earthen bunds and farm bunds in the area will help them

to take up rabi crop of Arandi and cumin in the residual moisture.

Table no. : 13 Land ownership details

Page 28: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

S. No. Village Total owned land (ha)

Gen OBC SC ST

No. Area No. Area No. Area No. Area

1 Chandrakh

Nahri Nadi

178 697.6 245 640.16 60 247 12 124

2 Raikoria 42 382.56 56 516.73 1 8 0 0

S. No. Village Total owned land (ha)

Type of farmer

Large Small Marginal BPL

No. Area No. Area No. Area No. Area

1 Chandrakh

Nahri Nadi

172 1087.2 130 304 31 17.28 146 20

2 Raikoria 72 825.77 22 69.53 5 2.94 36 12

Table No: 14 Land use & land classification

Page 29: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

S.N.

Name of village Micro

no

Arable Land

Non arable land

(community Land)

Road/

Other

total

land

Irrigate

d

Un

Irrigated

fellow

Govt. Panchayat land

Ha. Ha.

DLT & magra

Pasture

Nadi Aagor

Habitation

Ha. Ha. Ha. Ha. Ha. Ha. Ha.

1 Chandrakh

Nahri Nadi Cluster 0 3000 541 12 34 6 2 2 3597

2 Raikoria Cluster 0 920 35 2 37 2 1 2.5 997

Table No: 15 Agriculture

S. No. Village Net sown area (ha)

One time Two times Three times

1 Chandrakh Nahri Nadi 500 200 50

2 Raikoria 350 100 40

Table No: 16 Crop details

S.

No.

Village Net sown area (ha.) in Kharif

Bajra Gowar Moong Moth Til

1 Chandrakh

Nahri Nadi

501 50 100 250 158

2 Raikoria 450 40 50 150 80

Page 30: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

S. No. Village Net sown area (ha.) in Rabi

Wheat Arandi Sarson Onion Garlic

1 Chandrakh Nahri

Nadi

190 180 69 22 2

2 Raikoria 105 110 85 10 2

Table No: 17 Crop production

S. No. Crop production Kg per ha.

Wheat Bajra Moong Moth Onion Arandi

1 2500 1700 385 380 21000 210

3.1.4 Livestock

Majority of community in the Watershed depends on cows and buffaloes for milk. Lack of rain

reduced the fodder availability for animals in Watershed area. This leads to migration to other parts of the

country with their herds of goats and sheep. Milk production is very low and there is no dairy co operative

in the Watershed.

Page 31: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

Table No : 18 Livestock

S.

No.

Village Cow (No.) Buffalo

(No.)

Goat (No.) Sheep

(No.)

Camel

(No.)

Other

(No.)

1 Chandrakh Nahri Nadi 150 14 1350 1330 55 40

2 Raikoria 110 2 200 300 12 10

Table No: 19 Milk Production

S. No. Village Cow (ltr/annum) Buffalo (ltr/annum) Goat (ltr/annum) Total (ltr/annum)

No. Milk No. Milk No. Milk No. Milk

1 Chandrakh

Nahri Nadi

100 2010 4 160 1200 2010 1304 4108

2 Raikoria 70 1400 2 80 150 755 222 2235

Table No: 20 Drinking water

Page 32: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

S. No. Village Ground water

table (Ft.)

Source of

drinking water

Availability in

months

Quality

1 Chandrakh Nahri Nadi 445 Tube well 12 Slightly Saline

2 Raikoria 442 Tube well 12 Slightly Saline

3.2 Socio-Economic Profile

3.2.1 Demographic Status

Jodhpur XVII Watershed project has a total of 610 households with a population of 4435 (as per

base-line survey) out of which 2328 are male and 2107 female .The sex ratio is 905 female to 1000 male.

There are 182 BPL families. The average family size is 6. The literacy rate is very low i.e. 32.7 per cent;

male literacy rate is 48.7 per cent (of total male population) and female literacy rate is as low as 13.75 per

cent (of total female population). It is noticeable that only five persons have reached up to Secondary

standard. The major castes in the Watershed are Jat, Rajput, Bishnoi, and SC communities. Majority of

population is involved in agriculture and animal husbandry.

Table No: 21 Demographic information

Page 33: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

S. No. Village Population SC / ST population

Male Female Total Male Female Total

1 Chandrakh

Nahri Nadi

1853 1657 3510 403 344 747

2 Raikoria 475 450 925 67 58 125

Table No: 22 Literacy rate

S. No. Village Literacy

Total % Male % Female %

1 Chandrakh

Nahri Nadi

1157 32.96 915 49.38 242 14.6

2 Raikoria 275 29.73 224 47.16 51 11.33

Table No: 23 Poverty

S.

No.

Village Total

household

Total BPL

HH

% of BPL

HH

Landless HH % of Land

less HH

1 Chandrakh, Nahri

Nadi

495 146 29.5 6 0.04

Page 34: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

2 Raikoria 115 36 31.3 5 0.04

3.2.2 Migration Pattern

People migrate during summer season to different parts of state and country like Jodhpur,

Bangalore, Mumbai and Pune as daily wagers and construction workers. Lack of irrigation facility,

employment and fodder availability force these people to migrate to other places.

Table No: 24 Migration details

S.

No.

Village Total

Population

Migration Migration by months Income

during

migration

Total Male Female Up to 3

months

3-6

months

>6

months

1 Chandrakh

Nahri Nadi

3510 27 15 12 5 12 10 40000

2 Raikoria 925 16 10 6 12 2 2 34000

Table No: 25 Village infrastructures

Page 35: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

S.

No.

Village Pucca

road to

village

Schools Aangan

wadi

Post office Milk

collection

centre

PHED

tube well

PHC

1 Chandrakh

Nahri Nadi

Yes 4 3 0 0 4 1

2 Raikoria No 3 2 0 0 2 0

Table No: 26 Facilities / HH assets

S.

No.

Village HHs with

electricity

HHs with

safety

latrines

HHs with

phones

HHs with

vehicle

HHs

with

TV set

HHs

with

LPG

gas

HHs

with

fridge

HHs

with

Tube

Well

1 Chandrakh

Nahri Nadi

285 23 180 175 33 20 0 10

2 Raikoria 72 16 33 50 9 10 0 5

The Jodhpur XVII Watershed comes under arid zone. So farmers grow crop according to the rainfall. If

they get good rainfall they generally grow high value crops like mustard, cumin, Cotton, Moong etc. In case

of low rainfall they go for Bajra. So we can say that monsoon decides cropping patterns of Jodhpur XVII

Page 36: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

Watershed.

The Jodhpur XVII Watershed area has low productivity because of the following

reasons:-

i) Full dependence on monsoon

Jodhpur XVII Watershed is dependent on monsoon. Water is essential input in agriculture. Due to the

absence of proper irrigation facility, most of the cultivated area depends on the uncertain monsoon.

Therefore, the success or failure of the monsoon determines the success or failure of agriculture

production. The rainfall is unreliable due to two factors: untimely and inadequate

ii) Low use of fertilizer per unit cropped area

Farmers do not use sufficient fertilizer due to lack of water, scarcity of fertilizer in market and

insufficient money for fertilizer. Many a times they don’t get fertilizer at the right time.

iii) Traditional farming methods

This also leads to low productivity. There is a lot of ignorance about the use of new farming

methods and technologies such as multiple cropping. They don’t use FYM and other input in a proper

way that is why they don’t get 100% output. So these factors contribute to low productivity.

iv) Lack of adequate farm machinery

Even today a large number of farmers in Jodhpur XVII Watershed use traditional methods of

ploughing and irrigation. They don’t have adequate machinery like seed drill, Combine harvester etc. So, old

machineries take more time in tillage practices

Page 37: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

iv) Lack of good quality seeds and fertilizers:

Good quality seed, fertilizer and pesticide are important factor in agriculture productivity. The

use of good quality leads to higher land productivity. In Lavera Kalan, however, there are two

limitations in the use of fertilizer. First these fertilizers are most useful in irrigated condition. But in Jodhpur

XVII most of the land depends on rainfall, mostly farmers use nitrogenous fertilizers especially urea.

This has resulted in disproportionate use of fertilizer depleting the quality of land

v) Lack of other facilities such as storage and marketing

5-10% of agriculture product damage after harvesting due to scarcity of proper storage and proper

market for sale. So he sells to local traders at the low prices. Farmers mainly face proper means of

transportation and roads. and second problem is farmers don’t have proper storage facilities.

Page 38: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

CHAPTER - 4

WWWWWWWWAAAAAAAATTTTTTTTEEEEEEEERRRRRRRRSSSSSSSSHHHHHHHHEEEEEEEEDDDDDDDD

AAAAAAAACCCCCCCCTTTTTTTTIIIIIIIIVVVVVVVVIIIIIIIITTTTTTTTIIIIIIIIEEEEEEEESSSSSSSS

Page 39: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Watershed Activities

Watershed management as a strategy has been adopted by Government of India especially in the rain-fed

regions of semi-arid tropics. These regions are characterized by low and undependable rain, low soil fertility, poor

infrastructure development, low literacy and high incidence of migration. Several studies have identified that there

is a dire need of a systematic and scientific approach to deal with Watershed development. The common

guidelines generate a fresh and flexible framework for the next generation Watershed development.

4.1 Scientific Planning

(i) Watershed Approach

This envisages a broader vision of Geo-hydrological unit which involves treating a Watershed of micro-

Watershed. The Jodhpur XVII Watershed project consists of five village. Further Jodhpur XVII Watershed project is

in continuation with other Watershed namely Chandrakh (Hariyali IV), this gives an element of continuation of the

programme.

(ii) Base line survey

To access the impact of any Watershed development programme a detailed base line survey has to be

conducted. This acts a benchmark for any intervention during and post implementation of any development

programme. A detailed base line survey was undertaken by WDT which involved household census survey, Bio-

physical survey and village level data collection. Household census survey includes a detailed questionnaire which

Page 40: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

was filled by visiting each and every household in the villages. This gave in the details of the demographic profile

of the village, the literacy percentage, SC/ST population, number of BPL household, cattle population, and net

consumption rate in the village, average milk production of the cattle and various schemes running and their

benefits.

Bio-physical survey was undertaken to identify various natural resources available in the villages. It included

the soil typology, well in the area, crop taken in the field, cropping pattern, fertilizer used and various sources of

irrigation in the field.

(iii) Participatory Rural Approach (PRA)

The past experience of Watershed has given tremendous input to focus on creating accountability of the

stakeholders towards the programme. This has created an emphasis to include all the stakeholder communities

and their local indigenous technological knowledge while planning for any activity. Participatory Rural Approach

provides a new path for planning, implementing, monitoring and post-withdrawal activities with a complete

accountability of the stakeholders. Various PRA techniques like resource mapping, social mapping and season

calendars were used to understand the physical and social orientation of the village in general and the Watershed

in specific. Various tools like matrix ranking, Venn Diagram were used to identify various local vegetations, fodder

crops, various institution and their significance in the life of farmers.

(iv) Use of GIS and Remote sensing for planning

Use of various high science tools has been promoted at various stages of Watershed development.

(A) Prioritization

Geographical Information System (GIS) has been used for prioritization process. Various parameters were taken

into account like Geo-morphological, Soil, BPL population, Ground water status, Drinking water situation and Slope

Page 41: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

percent. These were all given proper weightage according to the DoLR specification. This helped in prioritization of

various Watershed area.

(B) Planning

State Remote Sensing Application Centre has provided various maps like slope map, contour map, Land use land

cover map, Satellite image maps were used to identify each and every water conservation structures available in

the project area. Contour map of vertical interval of 1 meter at a scale of 1:10000 was used for identifying various

locations for soil and water conservation structures.

(C) Topographical survey of DLT

There is a good drainage line in the Watershed, so for treatment of drainage line a topographical survey was

essential. This help in selection of site for LSCD, Nallah bunding and Masonry check dams.

Table No. 27 Details of Scientific planning and Inputs in the project

S. No. Scientific criteria / inputs used Whether Scientific

criteria used

1 A. Planning

a. Watershed approach Yes

b. Whether technical back-stopping for the project has been arranged?

If yes, mention the name of the institute

c. Baseline survey Yes

d. Hydro-geological survey Yes

e. Contour mapping Yes

Page 42: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

f. Participatory Rural Approach (PRA) Yes

g. Remote sensing data Yes

h. Ridge to valley treatment planning Yes

i. Online IT connectivity between -

(1) Project and DRDA cell / ZP Yes

(2) DRDA and SLNA Yes

(3) SLNA and DoLR Yes

j. Availability of GIS layers -

(1) Cadastral map

(2) Village boundaries Yes

(3) Drainage Yes

(4) Slope map Yes

(5) Land use Yes

(6) Ground water status No

(7) Watershed boundaries Yes

2 Inputs

(1) Bio- pesticides No

(2) Organic manure Yes

(3) Vermi-compost Yes

(4) Bio-fertilizer No

Page 43: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

(5) Water saving devices Yes

(6) Mechanized tools / Implements Yes

(7) Bio-fencing Yes

(8) Automatic water level recorders & sediment samplers No

4.2 Watershed Development Approach and Strategy

The developmental strategy is two pronged- technical and social, both integrated for sustainable development

of natural resources. Social strategy is for creating awareness and capacity building of community for self-

motivation and long term commitment to the project for its sustainability. Technical strategy is for planning

designing & implementation of activities for development of natural resources

4.2.1 Social Strategy

• Participatory Approach for empowerment of Community: People’s participation is the key to sustainable

Watershed development programmes.

• Demand Driven Project Proposals of the community and Flexibility in choice of Technology.

• Equity for Resource Poor and Women: In all Watershed development projects thrust is on improving equity

by addressing needs of all sections of community

• Social Audit

Page 44: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

• Linkages of Watershed community with Panchayat Raj Institutions: An important element of long term

sustainability is to forge linkages with permanent institutions in the area. So, linkages are forged between

the Panchayats and the Watershed communities.

4.2.2 Technical Strategy

• Ridge to Valley approach

• In-situ moisture conservation

• Reduce Runoff velocity

• Rain Water harvesting with the approach of ‘Water Budgeting

• Alternate land use i. e. Horticulture, Agro forestry, Pasture development & forestry plantation based on

land capability classification.

• Flexibility in choice of Technology: Taking account of the high degree of heterogeneity in the socio

economic and agro ecological conditions in rain fed areas, a high degree of flexibility is provided in the

choice of appropriate, at the Watershed level

• Low cost, replicable & indigenous technologies

Page 45: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

4.2.3 Water Budgeting

Table No. 28 Strange's Table Yield from 1 hectare of Natural (Untreated) catchment

Total Monsoon

rainfall in mm

Good Catchment Average Catchment Bad Catchment

% of utilisable

rain water

Utilisable

rain water

(Cum)

% of

utilisable

rain water

Utilisable

rain water

(Cum)

% of utilisable

rain water

Utilisable

rain water

(Cum)

20 0.08 0.16 0.06 0.12 0.04 0.08

40 0.13 0.52 0.0975 0.39 0.065 0.26

60 0.245 1.47 0.1735 1.041 0.1225 0.735

80 0.41 3.28 0.3075 2.46 0.205 1.64

100 0.7 7 0.525 5.25 0.35 3.5

120 0.9 10.8 0.675 8.1 0.45 5.4

140 1.1225 15.715 0.91875 12.8625 0.6125 8.575

160 1.625 26 1.21875 19.5 0.8125 13

180 2.12 38.16 1.59 28.62 1.06 19.08

200 2.7 54 2.025 40.5 1.35 27

220 3.26 71.72 2.445 53.79 1.63 35.86

240 3.81 91.44 2.8575 68.58 1.905 45.72

260 4.45 115.7 3.3375 86.775 2.225 57.85

280 5.19 145.32 3.3925 94.99 2.595 72.66

Page 46: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

300 5.9 177 4.425 132.75 2.95 88.5

320 6.72 215.04 5.04 161.28 3.36 107.52

340 7.75 263.5 5.6775 193.035 3.785 128.69

360 8.55 307.8 6.4125 230.85 4.275 153.9

380 9.45 359.1 7.0876 269.329 4.725 179.55

400 10.25 410 7.6875 307.5 5.125 205

420 11.05 464.1 8.2875 348.075 5.525 232.05

440 12 528 9 396 6 264

460 12.95 595.7 7.7125 354.775 6.475 297.85

480 13.9 667.2 10.425 500.4 6.95 333.6

500 14.7 735 11.025 551.25 7.35 367.5

520 15.5 806 11.625 604.5 7.75 403

540 16.36 883.44 12.2625 662.175 8.175 441.45

560 17.2 963.2 12.9 722.4 8.6 481.6

580 18 1044 13.5 783 9 522

600 19 1140 14.25 855 9.5 570

Good catchment - Hills or plains with little cultivation and moderately absorbant soil

Average catchment - Flat partly cultivated stiff gravely sandy absorbant soil

Bad catchment - Flat and cultivated sandy soil

Page 47: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Table No. 29 Total available runoff

Cluster Area

ha.

Type of

catchment

Utilisable rain water/ ha

(Cu.m.)

Utilisable rain water from w/s

(Cu.m.)

Chandrakh 3000 Average 132.75 398250

Total 398250

Table No. 30 Run off tapped in existing structure

S.No. Name No. Storage Capacity (Cu.m.)

i) Major Irrigation

Project 0

ii) Medium Irrigation

Project 0 0

iii) Form Ponds/Tanks 103 112000

iv) Anicuts 1 5600

Total 117600

Balance 280650

Page 48: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Table No. 31 Balance available runoff

Available for Harvesting 75% (Cu.m.) 210487.5

Activity No. Storage capacity per

No. (Cu.m.)

Total water to be harvested

(Cu.m.)

Tanka 188 25 4700

Khadin 4 3350 13400

LSCD 9 200 1800

Bunding 550 300 165000

Dug out pond 10 500 5000

Nalla bund 4 20 80

PD 10 1100 11000

Total 200980

The water budgeting indicates potential for water harvesting in the area. Loose stone check dam, Masonry check

dam, Contour bunding, Dug out pond, Nallah bunding and water harvesting structure in arable land (Tanka) etc.

activities could be done.

Page 49: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

4.3 Institution building

4.3.1 Watershed Committee (WC)

Watershed committee is constituted by Gram Sabha to implement the Watershed project with

technical support of WDT. The Gram Sabha of the Gram Panchayat select the chairman of the w/s

committee with the secretary who will be a paid functionary. In Jodhpur XVII Watershed one w/s

committee was formed namely Chandrakh w/s committee of Chandrakh gram panchayat.

Table No. 32 W/s Committee Chandrakh

S. No. Name Designation Sex Category Educational

Qualification

1 Omaram / Hukmaram Jat President M OBC Literate

2 Rajesh / Kaluram Godara Secretary M OBC Secondry

3 Pannalal / Nawlaram Member M OBC Illiterate

4 Ms. Mani devi / Moolaram Godara Member F OBC Literate

5 Ms. Mohni Devi / Pannaram

Meghwal

Member F SC Illiterate

6 Ms. PaduKanwar / Budhhsingh

Rajput

Member F Gen Literate

7 Sumer singh / Jor singh Member M Gen Illiterate

8 Bhanwar singh / Achal singh Member M Gen Illiterate

Page 50: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

9 Ms. Devi / Pannaram Member F OBC Illiterate

10 Swaroop ram / Rana ram Bhil Member M ST Literate

11 Ms. Amri devi / Hariram Harijan Member F SC Literate

12 Sawai singh / Member M Gen Illiterate

13 Salam singh / Jugat singh Member M Gen Illiterate

14 Bhomaram / Kisturam Meghwal Member M SC Illiterate

15 Pusaram / Bhura ram Jat Member M OBC Illiterate

Details of Bank Account :

For each water shed committee, the separate saving bank account has been opened with the name of

Sarpanch, Secretary WC and WDT member (Junior Engineer). One separate Watershed Development Fund (WDF)

account will be opened for each committee. In the WDF Account no transaction will be done only the contribution

received from beneficiaries will be deposited. The details of bank account are :

Table No. 33

S.No.

Watershed

Committee

Account No. Bank Name

Saving A/C No. WDF A/C No.

1. Chandrakh 05380110030622 05380110030639 UCO Bank Baori

Page 51: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S.no Name of the Gram Panchayat Date on which Grama Sabha

approved EPA

1. Chandrakh

4.3.2 Self Help Group

Self Help Groups are motivated, small homogenous groups organized together through credit and

thrift activities. Self Help Group initiative especially for women help uplift their livelihood, generally Self

Help Groups include landless and poor men and women.

Before formation of the SHGs during PRA activities focused group discussion (FGDs) were held with the

women, which came up with the following observations

a) Lack of proper credit facilities due to low intervention of formal financial credit institution.

b) Excessive exploitation of weaker section by money lenders

c) Lack of attitude for saving among poor people.

d) Lack of knowledge on credit and thrift activity and banking.

Status of new SHG is shown in table no.33

4.3.3 User Group

User Groups are normally formed to manage an activity or asset created under the programme on

a long term basis. The User Group collect user charges from their members, oversee the works and

Page 52: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

manage the benefits.

It was decided that each group would formulate certain internal rules and have a feeling of ownership

with community spirit.

4.4 Physical activities to be undertaken

4.4.1 Entry Point Activity (EPA)

EPA activities are taken up under Watershed project to build a rapport with the village community at

the beginning of the project, generally, certain important works which are in urgent demand of the local

community are taken up. A group discussion was conducted with Watershed development committee

regarding the EPA activity. It was conveyed to the WC that an amount of Rs. 18.648 Lakh was allotted for

EPA activity, which was 4% of total allocated budget. The villagers discussed various activities which they

felt is important but after a brief discussion it was conveyed to them that only those activities can be taken

which revive the common natural resources. It was also taken into priority that there should be an

instrument of convergence which will result in sustainability of activities.

Table No. 34 Entry Point Activity (EPA)

Page 53: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S.

No.

Name of WC Amount

earmarked for

EPA

Entry Point Activity planned Estimated Cost

(Lakh)

1 Chandrakh 18.00 Installation of Solar light 4

Rain water harvesting structure

(Tanka), GLR, Pipe Line

12

Repairing of Rain water harvesting

structure (Tanka)

2

4.4.2 PRODUCTION MEASURES

4.4.2.1 AGRO FORESTRY

Suitable forestry plants like Khejri, Ardoo, Desi Babool, Neem, Kumtha etc. are planted on the field

boundaries to meet the fuel & fodder requirements of the farmer.

4.4.2.2 MIXED HORTICULTURE

Page 54: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Suitable horticulture plants like Mango, Lemon, Guava, Ber, Pomegranate, Anwala etc. are grown with

the crops, to improve the income & nutrition level of the cultivators. A water harvesting structure (Tanka)

is constructed to fulfill the water requirement of horticulture plants

4.4.2.3 CROP DEMONSTRATION

To show the quantitative and qualitative difference between traditional and improved practices/ inputs and

in order to motivate the farmers to adopt improved agricultural practices/ inputs recommended by the

Research Institutions/ Department of Agriculture, demonstrations are conducted in a small area of 0.5 ha.

4.4.2.4 ORGANIC FARMING SYSTEM/ COMPOST PITS

Organic manure is decomposed agricultural waste and cow dung, which is applied in the field in place of

chemical fertilizers. It is cheaper, locally available and without any kind of side effect.

4.4.2.5 HOMESTEAD KITCHEN GARDENS

Emphasis is given on developing backyard gardens to meet the day to day needs of the vegetables of the

villagers.

4.4.2.6 PASTURE DEVELOPMENT

Page 55: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

To meet the fuel, fodder, timber requirements

of the community and to increase the carrying

capacity of the degraded pastures, proper

fencing, planting and over seeding of grasses

like Dhaman, Sevan, Stylohameta is done on

Govt./Panchayat and Pasture lands.

Conservation measures are also adopted to

conserve soil and water. Contour furrows/

trenches are excavated on the contours and

pits are dug in the trenches for plantation.

4.4.2.7 FENCING

Fencing is necessary to protect the production measures and pastures developed on non arable lands.

The fencing is designed in such a way that it intercepts runoff and conserves rain water. Different types of

fencing are as under:

1. DITCH CUM BUND (DCB)

This is most popular method of fencing. A ditch of particular cross section considering the type of the soil is

Page 56: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

dug around the pasture area. The aim is to prevent cattle from entering the protected area. The soil so

excavated is used for construction of a bund. It can be fortified with local species of vegetation.

2. STONE WALL FENCING

Stone wall fencing is done in area where stone is locally available especially in hilly areas. The stone

wall is constructed to prevent the cattle from entering the protected area.

4.4.3 CONSERVATION MEASURES

4.4.3.1 CONTOUR CULTIVATION

Cultivation is done along the contours. This forms the mini barriers across the flow path of the runoff,

which conserves rain water in situ & check soil erosion. Effectiveness of contour cultivation varies with

slope, crop cover and soil. It is most effective on moderate slope ranging from 1 to 5%

4.4.3.2 CONTOUR BUND/ CONTOUR VEGETATIVE HEDGE

Contour bunds are small earthen bunds constructed along the contour on the agriculture lands to

check soil erosion and conserve sufficient moisture to grow crops. These bunds are purified with locally

available vegetation like Khus, Munja, Dhaman and Stylo Hamata are raised on the bund.

Page 57: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

4.4.3.3 V DITCH

These are constructed parallel to contour in areas of gentle slope to conserve in sito moisture and to

check velocity of run off.

4.4.3.4 STAGGERED TRENCHES

Number of rows of trenches are dug in hilly areas having steep slopes. Distance between two

trenches is kept equal to the length of a trench. Adjacent rows are staggered to reduce the maximum

length of runoff for better retention. These trenches check the velocity of runoff as well as conserve in-situ

moisture and check soil erosion.

4.4.3.5 WATER HARVESTING STRUCTURE (TANKA)

Tanka is a covered masonry runoff storage tank

which collects runoff water from artificial

catchment constructed around it. It is also an age

old practice in the desert areas and is used for

harvesting surface runoff water for life saving

irrigation and drinking purposes.

Page 58: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

4.4.3.6 LOOSE STONE CHECK DAM

These structures are constructed in small and

medium size gullies using locally available

stones/ boulders as dry masonry. A waste weir is

also provided to discharge the peak runoff safely

from the catchment.

4.4.3.7 EARTHEN DAM

These are constructed in medium to large size gullies

by making earthen embankment in the nallah bed

across the drainage line duly supported by locally

available vegetation/ grass. They are provided where

separate surplus arrangement for water is available at

site.

Page 59: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

4.4.3.8 DUG OUT POND (NADI)

It is a water harvesting structure constructed in middle to large drainage lines across the flow to store

surplus runoff . The pond is constructed near the point of use where maximum water can be stored

requiring minimum amount of earth work. The earthen bund is fortified with vegetation and waste

weir.

4.4.3.9 MASONRY CHECK DAM

It is a weir like masonry structure constructed across the natural drain/ nallah which intercepts the

runoff from local catchment and stores it for optimum utilization. This helps in recharging of

surrounding wells. The stored water can also be used for lift or flow irrigation as well as for drinking

purposes of human and livestock population. Due to these direct and indirect benefits, masonry check

dam is in great demand in the rural areas.

Page 60: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

CHAPTER - 5

AAAAAAAACCCCCCCCTTTTTTTTIIIIIIIIVVVVVVVVIIIIIIIITTTTTTTTYYYYYYYY WWWWWWWWIIIIIIIISSSSSSSSEEEEEEEE

AAAAAAAABBBBBBBBSSSSSSSSTTTTTTTTRRRRRRRRAAAAAAAACCCCCCCCTTTTTTTT OOOOOOOOFFFFFFFF CCCCCCCCOOOOOOOOSSSSSSSSTTTTTTTT

Page 61: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Unit RATE QTY. Amt from project

fund

Convergence fund Total Cost Beneficiary

contribution

I. ADMINISTRATIVE COST 10% 45.000 0.000 45.000 0.000

1 WDT MANDEYA

2 W C SEC MANDEYA

3OFFICE EXPENSES (JEEP/STATIONARY &

OTHER)

SUB TOTAL 0.000 0.000 0.000

II MONITORING 1% 4.500 0.000 4.500 0.000

III EVALUATION 1% 4.500 0.000 4.500 0.000

54.000 0.000 54.000 0.000

W/S PREPARATORY PHASE 0.000 0.000 0.000

IV ENTRY POINT ACTIVITY 4% 18.000 0.000 18.000 0.000

1 SOLAR LIGHT 0.000 0.000 0.000

2 WATER TANKA 0.000 0.000 0.000

3 REPAIRING OF TANKA 0.000 0.000 0.000

6 OTHER 0.000 0.000 0.000

0.000 0.000 0.000

V TRAININGS & CAPACITY BUILDING 5% 22.500 0.000 22.500 0.000

1 USERS GROUP 0.000 0.000 0.000

(i) KHARIF 0.000 0.000 0.000

(ii) RABI 0.000 0.000 0.000

(iii) HORTICULTURE 0.000 0.000 0.000

(iv) PASTURE DEVELOPMENT 0.000 0.000

2 OTHERS TRAINING & CO 0.000 0.000

0.000 0.000

VI DETAILED PROJECT REPORT 1% 4.500 0.000 4.500

0.000 0.000

ACTIVITY WISE TOTAL ABSTRACT OF COST

JODHPUR XVII

S. N. NAME OF ACTIVITY

TOTAL

TOTAL

TOTAL

TOTAL

TOTAL

Page 62: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

W/S WORK PHASE 0.000 0.000

VII NRM 60% 270.000 0.000 270.000

1 ARABLE CONSERVATION WORK 0.000

(i) Earthen Bund Ha. 13300 550 73.150 13.300 86.450 6.916

(ii) WHS (Tanka) No. 80000 178 142.400 24.000 166.400 13.312

(iii) Waste weir No. 13000 28 3.640 2.600 6.240 0.499

(iv) Gulley Control Structure Nallah BundingNo. 10000 6 0.600 0.000 0.600 0.048

(v) Khadin No. 500000 4 20.000 0.000 20.000 1.600

2 NON ARABLE CONSERVATION WORK 0 0.000 0.000 0.000

(i) V Ditch for PD Ha. 17900 10 1.790 0.000 1.790 0.000

(ii) Staggered Contour Trenches for PD Ha. 12700 0 0.000 0.000 0.000 0.000

(iii) Dug out Pond No. 50000 10 10.000 0.000 10.000 0.000

(iv) WHS (Tanka) No. 80000 20 16.000 1.600 17.600 0.000

(v) Nallah Bunding with ww No. 43000 4 0.920 0.000 0.920 0.000

3 DRAINAGE LINE TREATMENT 0 0.000 0.000 0.000

(i) LSCD 'A' No. 20000 1 0.200 0.000 0.200 0.000

(ii) LSCD 'B' No. 18500 2 0.370 0.000 0.370 0.000

(iii) LSCD 'C' No. 17000 2 0.340 0.000 0.340 0.000

(iv) LSCD 'D' No. 15500 2 0.310 0.000 0.310 0.000

(v) LSCD 'E' No. 14000 2 0.280 0.000 0.280 0.000

(vi) Masonry Check Dam No. 0 0.000 0.000 0.000 0.000

0 270.000 41.500 311.500 0.000

VIIIPRODUCTION SYSTEM & MICRO

ENTERPRISES 67.500 15% 0.000 0.000 0.000

For Arable Land 0 0.000 0.000 0.000

1 Arable bund Ha. 0 0 0.000 0.000 0.000 0.000

2 Agro Forestry No. 73 4520 3.300 0.000 3.300 1.510

3Horticulture Plantation with fencing &

Tanka No. 24700 178 43.966 7.410 51.376 6.118

4Horticulture Plantation without fencing

(Orchard) No. 10000 25 2.500 0.500 3.000 1.600

TOTAL

Page 63: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

5 Vermi Compost No. 36000 7 2.520 0.000 2.520 1.843

6 Crop Demonstration No. 2000 400 4.000 0.000 4.000 1.133

7 Homested Kitchen Gerden No. 1000 20 0.200 0.000 0.200 0.141

8 Medicinal Plants No. 3000 15 0.150 0.000 0.150 0.394

For Non-arable Land 0 0 0.000 0.000 0.000

1 V Ditch for PD Ha. 2200 10 0.220 0.000 0.220 0.000

2 Staggered Contour Trenches for PD Ha. 900 0 0.000 0.000 0.000 0.000

3 Fencing of PD (by SW) Ha. 0 0 0.000 0.000 0.000 0.000

4 Fencing of PD (by DCB) Ha. 0 10 2.681 0.000 2.681 0.000

1TOOLKIT, TRAINING & REVOLVING

FUND OF SHG 0 0 0.000 0.000 0.000 0.000

(i) KARIGER No. 26250 1 0.263 0.000 0.263

(ii) WHITEWASH & PENT No. 40500 1 0.405 0.000 0.405 0.000

(iii) TAILORING No. 67000 1 0.670 0.000 0.670 0.000

(iv) MASALA UDYOG No. 42200 1 0.422 0.000 0.422 0.000

(v) BICYCLE/MOBILE No. 34000 1 0.340 0.000 0.340 0.000

(vi) KUMAHRI UDYOG No. 22000 1 0.220 0.000 0.220 0.000

(vii) ARI TARI UDYOG No. 50000 1 0.500 0.000 0.500 0.000

2 LIVESTOCK MANAGEMENT 0 0 0.000 0.000 0.000 0.000

(i.) Animal Health Camp No. 25000 17 4.250 0.000 4.250 0.000

(ii) Vaccination 0 0 0.200 0.000 0.200 0.000

(iii) Purchase of Bull / Pada No. 25000 2 0.500 0.000 0.500 0.000

(iv) A I 0 0 0.194 0.000 0.194 0.000

0 0 67.500 7.910 75.410 0.000

IX CONSOLIDATION PHASE 13.50 3% 13.500 0.000 13.500 0.000

GRAND TOTAL 450.000 49.410 499.410 0.000

TOTAL

Page 64: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XV

CHAPTER – 6

AAAAAAAANNNNNNNNNNNNNNNNUUUUUUUUAAAAAAAALLLLLLLL AAAAAAAACCCCCCCCTTTTTTTTIIIIIIIIOOOOOOOONNNNNNNN

PPPPPPPPLLLLLLLLAAAAAAAANNNNNNNN

Page 65: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of the Project IWMP XVII Cluster Geographical Area 4094 Ha

G.P. Chandrakh Chandrakh Effective Area 3000 Ha

Block Baori IWMP Total Arable land Ha

District. Jodhpur Date of Sanction 30.09.2009 1. Irrigated 732 Ha

Village Covered 3 NO. 2. Unirrigated 1830 Ha

Project outlay 450 LAC Total Nonarable land Ha

Total Area 3000 Hectare No. of SHG's formed 8 1. Pasture 15 Ha

No. of WC's formed 1 No. of UG's formed 12 2. Govt. / waste /OTHER LAND 423 Ha

QTY. RATE AMOUNT PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN

I. ADMINISTRATIVE COST 10% 45

1 WDT MANDEYA

2 W C SEC MANDEYA

3OFFICE EXPENSES (JEEP/STATIONARY & OTHER)

SUB TOTAL 45.000 45.000

II MONITORING 1% 4.500 4.500 4.500

III EVALUATION 1% 4.500 4.500 4.500

54.000 54.000

W/S PREPARATORY PHASE

IV ENTRY POINT ACTIVITY 4% 18.000 18.000

1 SOLAR LIGHT

2 WATER HARVESTING TANKA

3 REPAIRING OF TANKA

6 OTHER

18.000 18.000

VTRAININGS & CAPACITY

BUILDING 5% 22.500

1 USERS GROUP

(i) KHARIF

(ii) RABI

(iii) HORTICULTURE

(iv) PASTURE DEVELOPMENT

2 OTHERS TRAINING & CO

22.500 22.500

VI DETAILED PROJECT REPORT 1% 4.500 4.500 1 4.500 4.500

4.500 4.500 1 4.500 4.500

TOTAL 45.000 4.500 45.000

SECOND YEAR

TOTAL

FIFTH YEAR SIXTH YEAR

Date of

Approval of

the work plan

TOTAL

TOTAL

TOTAL

YEAR WISE WORK PLAN OF WATERSHED JODHPUR XVII

FOURTH YEARFIRST YEARNAME OF ACTIVITYTARGET

S. N.

(YEAR WISE BREAK UP)

Macro/Micro

W C

TOTALTHIRD YEAR

Scheme/Batch

Page 66: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

QTY. RATE AMOUNT PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN

SECOND YEAR FIFTH YEAR SIXTH YEARFOURTH YEARFIRST YEARNAME OF ACTIVITYTARGET

S. N.TOTAL

THIRD YEAR

W/S WORK PHASE

VII NRM 60% 270.000 0.000 45.000 67.500 67.500 54.000 36.000 270.000

1ARABLE CONSERVATION

WORK

(i) Earthen Bund 550 13300 73.150 0 0.000 100 13.300 180 23.940 170 22.610 70 9.310 30 3.990 550 73.150

(ii) WHS (Tanka) 178 80000 142.400 0 0.000 24 19.200 30 24.000 50 40.000 46 36.800 28 22.400 178 142.400

(iii) Waste weir 28 13000 3.640 0 0.000 4 0.520 22 2.860 1 0.130 1 0.130 0 0.000 28 3.640

(iv)Gulley Control Structure Nallah

Bunding 6 10000 0.600 0 0.000 4 0.400 0 0.000 0 0.000 0 0.000 2 0.200 6 0.600

(v) Khadin 4 500000 20.000 0 0.000 1 6.240 2 7.970 1 3.760 0 1.360 0 0.670 4 20.000

2NON ARABLE CONSERVATION

WORK

(i) V Ditch for PD 10 17900 1.790 0 0.000 0.000 10 1.790 0.000 0.000 0 0.000 10 1.790

(ii)Staggered Contour Trenches for

PD 0 12700 0.000 0 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000

(iii) Dug out Pond 10 100000 10.000 0 0.000 3 3.000 2 2.000 1 1.000 0 0.000 4 4.000 10 10.000

(iv) WHS (Tanka) 20 80000 16.000 0 0.000 2 1.600 5 4.000 0 0.000 8 6.400 5 4.000 20 16.000

(v) Nallah Bunding with ww 4 23000 0.920 0 0.000 2 0.460 1 0.230 0 0.000 0 0.000 1 0.230 4 0.920

3 DRAINAGE LINE TREATMENT

(i) LSCD 'A' 1 20000 0.200 0 0.000 0 0.000 1 0.200 0 0.000 0 0.000 0 0.000 1 0.200

(ii) LSCD 'B' 2 18500 0.370 0 0.000 0 0.000 1 0.185 0 0.000 0 0.000 1 0.185 2 0.370

(iii) LSCD 'C' 2 17000 0.340 0 0.000 0 0.000 1 0.170 0 0.000 0 0.000 1 0.170 2 0.340

(iv) LSCD 'D' 2 15500 0.310 0 0.000 0 0.000 1 0.155 0 0.000 0 0.000 1 0.155 2 0.310

(v) LSCD 'E' 2 14000 0.280 0 0.000 2 0.280 0 0.000 0 0.000 0 0.000 0 0.000 2 0.280

(vi) Masonry Check Dam 0 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

270.000 45.000 67.500 67.500 54.000 36.000 270.000

VIIIPRODUCTION SYSTEM &

MICRO ENTERPRISES 15% 67.500

For Arable Land

1 Arable bund 0 0 0.000 0 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

2 Agro Forestry 4520 73 3.300 0 0.000 300 0.219 600 0.438 500 0.365 500 0.365 2620 1.913 4520 3.300

3Horticulture Plantation with

fencing & Tanka 178 24700 43.966 0 0.000 10 2.470 40 9.880 50 12.350 50 12.350 28 6.916 178 43.966

4Horticulture Plantation without

fencing (Orchard) 25 10000 2.500 0 0.000 0.000 3 0.300 5 0.500 5 0.500 12 1.200 25 2.500

5 Vermi Compost 7 36000 2.520 0 0.000 0 0.000 1 0.360 1 0.360 1 0.360 4 1.440 7 2.520

6 Crop Demonstration 400 1000 4.000 0 0.000 5 0.050 40 0.400 40 0.400 40 0.400 275 2.750 400 4.000

7 Homested Kitchen Gerden 20 1000 0.200 0 0.000 5 0.050 5 0.050 0 0.000 10 0.100 0 0.000 20 0.200

8 Medicinal Plants 15 1000 0.150 0 0.000 0 0.000 0 0.000 5 0.050 10 0.100 0 0.000 15 0.150

TOTAL

Page 67: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

QTY. RATE AMOUNT PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN

SECOND YEAR FIFTH YEAR SIXTH YEARFOURTH YEARFIRST YEARNAME OF ACTIVITYTARGET

S. N.TOTAL

THIRD YEAR

For Non-arable Land 0.000 0.000 0.000 0.000 0 0.000 0 0.000

1 V Ditch for PD 10 2200.000 0.220 0 0.000 0.000 10 0.220 0.000 0.000 0 0.000 10 0.220

2 Staggered Contour Trenches for PD 0 900.000 0.000 0 0.000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000

3 Fencing of PD (by SW) 0 0.000 0 0.000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000

4 Fencing of PD (by DCB) 10 2.681 0 0.000 0.000 10 2.681 0.000 0.000 0 0.000 10 2.681

1TOOLKIT, TRAINING &

REVOLVING FUND OF SHG

(i) KARIGER 1 26250 0.263 0 0.000 1 0.263 0.000 0.000 0.000 0 0.000 1 0.263

(ii) WHITEWASH & PENT 1 40500 0.405 0 0.000 0.000 1 0.405 0.000 0.000 0 0.000 1 0.405

(iii) TAILORING 1 67000 0.670 0 0.000 0.000 0.000 1 0.670 0.000 0 0.000 1 0.670

(iv) MASALA UDYOG 1 42200 0.422 0 0.000 0.000 0.000 0.000 1 0.422 0 0.000 1 0.422

(v) BICYCLE/MOBILE 1 34000 0.340 0 0.000 0.000 0.000 0.000 1 0.340 0 0.000 1 0.340

(vi) KUMAHRI UDYOG 1 22000 0.220 0 0.000 0.000 0.000 1 0.220 0.000 0 0.000 1 0.220

(vii) ARI TARI UDYOG 1 50000 0.500 0 0.000 0.000 0 0.000 0.000 0.000 1 0.500 1 0.500

2 LIVESTOCK MANAGEMENT 0

(i.) Animal Health Camp 17 25000 4.250 0 0.000 2 0.500 4 1.000 5 1.250 5 1.250 1 0.250 17 4.250

(ii) Vaccination 0.200 0 0.000 0.000 0.100 0.050 0.050 0.000 0 0.200

(iii) Purchase of Bull / Pada 2 25000 0.500 0 0.000 0.000 0 0.000 1 0.250 0.000 0.250 2 0.500

(iv) A I 0.194 0 0.000 0.000 0.100 0.040 0.040 0.014 0 0.194

67.500 0.000 3.552 15.934 16.505 16.277 15.233 67.500

IX CONSOLIDATION PHASE 3% 13.500 13.500 0.000 0.000 0.000 0.000 8.100 5.400 13.500

GRAND TOTAL 450.000 4.500 53.052 83.434 84.005 78.377 56.633 450.000

TOTAL

Page 68: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

QTY. RATE AMOUNT PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN PHY FIN

W/S WORK PHASE

VII NRM

1ARABLE CONSERVATION

WORK

(i) Earthen Bund 100 13300 13.300 0 0.000 0.000 0.000 40 5.320 50 6.650 0 0.000 10 1.330 100 13.300

(ii) WHS (Tanka) 30 80000 24.000 0 0.000 0.000 0.000 5 4.000 5 4.000 15 12.000 5 4.000 30 24.000

(iii) Waste weir 20 13000 2.600 0 0.000 0.000 0.000 11 1.430 4 0.520 3 0.390 2 0.260 20 2.600

(iv)Gulley Control Structure Nallah

Bunding 0 10000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

(v) Khadin 0 455000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

2NON ARABLE CONSERVATION

WORK

(i) V Ditch for PD 0 17900 0.000 0.000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000

(ii)Staggered Contour Trenches for

PD 0 12700 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000

(iii) Dug out Pond 0 50000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0.000 0 0.000 0 0.000

(iv) WHS (Tanka) 2 80000 1.600 0 0.000 0.000 0.000 1 0.800 1 0.800 0.000 0 0.000 2 1.600

(v) Nallah Bunding with ww 0 23000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

3 DRAINAGE LINE TREATMENT

(i) LSCD 'A' 0 20000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

(ii) LSCD 'B' 0 18500 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

(iii) LSCD 'C' 0 17000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

(iv) LSCD 'D' 0 15500 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

(v) LSCD 'E' 0 14000 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

(vi) Masonry Check Dam 0 0 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

41.500 0.000 0.000 11.550 11.970 12.390 5.590 41.500

VIIIPRODUCTION SYSTEM &

MICRO ENTERPRISES

For Arable Land

1 Arable bund 0 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

2 Agro Forestry 0 73 0.000 0 0.000 0.000 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000

3Horticulture Plantation with

fencing & Tanka 30 24700 7.410 0 0.000 0.000 0.000 5 1.235 5 1.235 10 2.470 10 2.470 30 7.410

4Horticulture Plantation without

fencing (Orchard) 5 10000 0.500 0.000 0.000 1 0.100 2 0.200 1 0.100 1 0.100 5 0.500

7.910 0.000 0.000 1.335 1.435 2.570 2.570 7.910

GRAND TOTAL 49.410 0.000 0.000 12.885 13.405 14.960 8.160 49.410

TOTAL

TOTAL

SECOND YEAR SIXTH YEARTOTAL

FIRST YEAR THIRD YEAR FOURTH YEAR FIFTH YEAR

YEAR WISE WORK PLAN OF WATERSHED JODHPUR XVII (Through Convergence)

S. N. NAME OF ACTIVITYTARGET

Page 69: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XV

CHAPTER - 7

TTTTTTTTEEEEEEEECCCCCCCCHHHHHHHHNNNNNNNNIIIIIIIICCCCCCCCAAAAAAAALLLLLLLL DDDDDDDDEEEEEEEESSSSSSSSIIIIIIIIGGGGGGGGNNNNNNNN

&&&&&&&& EEEEEEEESSSSSSSSTTTTTTTTIIIIIIIIMMMMMMMMAAAAAAAATTTTTTTTEEEEEEEESSSSSSSS

Page 70: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Total Area 550 haNo. of Waste Weir 28

Name of work Conservation

Measure

Production

Measure

Total Cost

Earthen Bund 7315000 0 7315000Waste Weir 364000 0 364000.00

7679000 0 7679000.00

Say 76.79 Lakh

Conservation Measure 7679000.00Production Measure 0.00

Abstract of Cost

VEGETATIVE EARTHEN BUND IN ARABLE LAND

Page 71: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

CROSS-SECTION OF VEGETATIVE BUND IN ARABLE LAND

Top width =Based on seepage line checkSlope of seepage line 3:1

0.61.5 :1

1 :1 USDS 1

0.6

1 1.50.1 1.8 1.2 0.45 m

3.14.11 m

CS = (Tw+Bw) *HtCS = (Tw+Bw) *Ht2

CS = 1.85 Sq.m.

Average Cross section 1.85 Sq.m.Length 1.00 m.Quantity 1.85 Cu.m.

Page 72: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

DESIGN OF VEGETATIVE BUND IN ARABLE LAND

V.I = 0.305 (XS+Y)

0.305(0.8 x 2+1.0)

V.I = 0.549

V.I Vertical interval

X= Rain Fall Factor 0.80.8

Y= Factor due to soil infiltration & Crop cover 11

S= Percent slope 21

He= (Re x VI)1/2

(50) 1/2

He= 0.6199 Say 0.60 m

He Depth of impounding

Re 24Hour rainfall excess in Cms. for 10 year recurrence interval 35

V.I Vertical interval 0.549

Total Height of Bund = 0.6 + 0.4 1.00 m

Top width of Bund = 0.6 m

Bottom width of Bund = 3.1 m

Cross section of bund = (Top width of Bund +Bottom width of Bund) x Height

2X Section= ( 0.60+3.1) x 1.00

2

X Section= 1.85 Sq.m.

Page 73: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Construction of Waste Weir

DETAILS OF WORK AND ABSTRACT OF COST

L B D/H Feet Metre Lab Total Lab Total

1 2 9.5 2 2 76

4 2 2 2 32

1 8.75 2.5 2 43.75

0

0

151.75 4.29453 cum. 92.00 92.00 395.096 395.096

2 2 9.5 2 0.5 19

4 2 2 0.5 8

1 8.75 2.5 0.5 10.938

0

Excavation in hard soil dry or moist &

disposal of excavated material within

initial lead of 30 m and lift of 1.5 m

including dressing etc. complete. (2

B)

Cement concrete well mixed in

cement mortar ( 1 : 5 : 10 ) laid in

position complete including

curing.Aggregate size upto 50 mm,

HB (11 B)

Quantity Unit Rate AmountS.

No.Item No. Detail

0

0

37.938 1.07363 cum. 327.60 1576.00 351.722 1692.04

3 2 9.5 1.5 1.5 42.75

4 2 1.5 1.5 18

1 9.25 2.5 1.5 34.688

0

95.438 2.70088 cum. 473.00 1704.00 1277.52 4602.3

4 2 6 1.25 3.25 48.75

4 2 1.25 2 20

1 9.5 2 1 19

9 3

87.75 2.48333 cum. 628.30 1862.00 1560.27 4623.95

5 1 9.5 3 1 28.5

0

28.5 2.64765 Sq.m 120.50 291.00 319.042 770.466

Dry Stone kharanja (15 to 23 cm)

Item 100(A)

Random rubble stone masonary in

cement sand mortar ( 1 : 6 )For

foundation

Random rubble stone masonary in

cement sand mortar ( 1 : 6 ) For

superstructure

HB (11 B)

Page 74: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

6 2 13 1.25 1 32.5

4 2 1.25 1 10

1 9.5 1.5 1 14.25

1 9.5 1 1 9.5

66.25 6.15463 sqm. 45.60 89.00 280.651 547.762

7 2 6 3.25 1 39

4 2 2 1 16 1.4864 sqm.

1 9.5 1.25 1 11.875

66.875 6.21269 sqm. 45.80 56.00 284.541 347.911

4468.84 12979.5

Rate

Skilled labour 400

Unskilled labour 135

Water A 4468.84

B 8510.69Material

15.29 2064 Amount

-116 Labour

4469

Quantity Amount

6.30 2521

Cement plaster including smooth

finishing in cement mortar (1:6) 20

mm thick.

Ruled pointing in cement mortar

(1:3)

B 8510.69

Cement 2 C 12979.5

Cement 2 20

Total (C+D) 12999.5

Say 13000

S.

No Rate Amount

1 Sand Cu.m. 380 858.852

2 Stone Agg of 40 mm nominal size Cu.m. 350 338.194

3 Stone Cu.m. 575 3279.01

4 Cement Kg 220 2601.86 11.827 Bag

7224.07

Other (Water) 1286.62

Total 8510.69

Material

2.260137

1.0

5.7

591.33

Add contingency

Unit Quantity

Total

4469

Page 75: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

3Construction of Waste Weir

CROSS SECTION AT A A'

1.5

3.25 '

1 '

2.5

9.0 '

2

1' 6"

A A'A A'

2.5

9.5

PLAN

Page 76: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Estimate of One ha.

Length per ha. = 80 mtr

S. no. Name of work Item no. No Length

Width

(TW+BW)/

2 Hight Qty Unit Rate Amount

1 Earth work Excavation for making of

bund, laying in layers of 15 cm,

breaking of clods, sorting of grass

pebbles, disposal of excavated

material up to 1.5 mt Hight and lead

ESTIMATE OF VEGETATIVE BUND IN ARABLE LAND

material up to 1.5 mt Hight and lead

up to 50 m including dressing and

compaction 119 B 1 80 1.85 1 148.00 Cum 85 12580.0

2 Sowing of seeds on the constructed

bund in three rows

114 3 80 240 meter 0.6 144

3 Supply of Stylo/Dhaman seed @ 4 gm

/ m in three rows

CAZRI

Rate

3 80 0.96 Kg 150 144

12868.0Add 3% contingency 386.0

Total 13254.0Say 13300.0

Conservation Measure 13300.0Production Measure 0

Page 77: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

For General & OBC Category

Project Contribution

90% 10%

1 Cost of tanka 80000 72000 8000 80000Conservation measure

for water harvesting

60% 40%

2 Cost of Horticulture plantation 10000 6000 4000 10000 Production

3 Barbed Wire Fencing 14700 8820 5880 14700 Production

Total 2+3 24700 14820 9880 24700

Total Cost of tanka unit 104700 86820 17880 104700

No. of Farmers

80 8376000 6945600 1430400 8376000

For SC/ST/ BPL

Project Contribution

95% 5%

1Cost of tanka 80000.00 76000 4000 80000

Conservation measure

for water harvesting

80% 20%

2Cost of Horticulture plantation 10000 8000 2000 10000 Production

3 Barbed Wire Fencing 14700 11760 2940 14700 Production

Total 2+3 24700 19760 4940 24700

Total Cost of tanka unit 104700.00 95760.00 8940.00 104700.00

No. of Farmers

98 10260600 9384480 876120 10260600

Total Cost 18636600

1 Conservation Measure 14240000

2 Production Measure 4396600

a From project 3122080

b From Contribution 1274520

3 Total Contribution 1439340.00

Abstract of cost of Tanka with Plantation work

Name of workSr. no

Sr. no Name of work

Estimated

cost MeasuresTotal

Estimated

cost Total Measures

Page 78: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Area 0.17 Ha Length 164.9 mtr. Spacing 4 m

Say 165 mtr.

No of post As per length= Length/spacing 41.00

Additional post require after every 10 Posts 4

45.00

Length of Post 7.5 Feet 2.286 m

Width of post 1 Feet 0.3 m

Quantity of one post 0.6858 Sq.m

S.No Description Item no. NoLength of

single wire

Total

lengthKg/mtr Quantity Unit Rate Amount

1 Supply of barbed wire fencing 14

gauge 5 165 825 0.08 66 Kg 46 3036

2 Supply of Jodhpur stone slab for

post 45 30.86 Sq.m 300 9258.30

3 Rehandling of posts to pit LS 45 45.00 No 15 675.00

4 fixing of post in 45 cm. deep pit2B 45 0.45 0.3 0.45 2.73 Cum 92 251.51

5 Cost of binding wire 6 Kg 45 270.00

6 Stretching of barbed wire and fixing

it with the post with thin wire

5.5/forest 825 mtr 0.92 759

7 interlacing the barbed wire with

locally available bushy material at a

spacing of 15 cms 5.6/forest 45 45 mtr 5.48 246.6

14249.81

Add 3% contingency 427.49

14677.30

Say 14700.0

Model estimate Barbed wire fencing

Page 79: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Model Estimate of Water Harvesting Structure (tanka)

Amount : 80000.00

Capacity 25740.72 Ltr.

Dia B H

1 Complete O/O 1 13.00 12.50 Aagor Dia > 42 Feet

2 Hall I/I 1 10.50 11.75 3.00 3.2

5 E/W 1 132.707 1 10.50 3.50 3.2004

6 Concrete 1 132.707 1 0.50 2.00 25.74072

7 Masonary 1 36.9068 1.25 12.00 2.00

8 G.L to P.L 1 2.00

9 Aslat Around 2.00 9.00 1 0.5

12 Door 1 1.50 1.50 1

13 Ventilater -2 1 1 1

S.N

o Details of work No.

Measurements

lk/kkj.k@eqyk;e feêh esa

l[r] fpduh] dadj feêh esa

fo?kfVr pêku

lk/kkj.k pêku

13 Ventilater -2 1 1 1

16 Flooring in side Cement 1 86.546 1 1

17 Flooring on top Cement 1 132.71 1 1

Deduction 1 1.5 1.5 1

DETAILS OF WORK AND ABSTRACT OF COST

0 Model Estimate of Water Harvesting Structure (tanka)

0 0

y- pkS- Åa@x- QhV dqy eh- Je dqy Je dqy

1 0

0

0

0

dz-la- dk;Z dk fooj.k la- fo'ks"k fooj.k ek=k bZdkbZ nj jkf'k

uhao] [kkbZ rFkk ukyk vkfn ds fy, 1-5 eh-xgjkbZ rd feêh dh [kqnkbZ djuk] ry dksdqVuk] ikuh Mkyuk cxy dks laokjuk] [kqnhfeêh dks ckgj fudkyuk uhoa Hkjus ds ckn[kkyh LFkkuksa dks iqu% feêh ls Hkjuk rFkk cphgqbZ feêh dks 50 ehVj dh nwjh rd fuLrkj.k

Page 80: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

0

0

0

¼v½ lk/kkj.k@eqyk;e feêh esa 1 132.707 1 3 398.122 11.27 cum. 75.00 75.00 845.25 845.25

¼c½ l[r] fpduh] dadj feêh esa 1 132.707 1 3.5 464.475 13.15 cum. 92.00 92.00 1209.8 1209.80

¼l½ fo?kfVr pêku 1 132.707 1 2 265.415 7.51 cum. 134.00 134.00 1006.34 1006.34

¼n½ lk/kkj.k pêku 1 132.707 1 2 265.415 7.51 cum. 178.00 178.00 1336.78 1336.78

lk/kkj.k@eqyk;e feêh esa 1 131.922 1.5 1 197.883 5.6 cum. 75.00 75.00 420 420

1-5 ehVj vfrfjDr mBku (Lift)

First lift 1 132.707 0.0929 1.5 18.4928 cum. 10.80 10.80 199.72176 199.7218

Second lift 0 132.707 0.0929 0.2 0 cum. 21.60 21.60 0 0

2 1 132.707 1 0.5 66.3536

0

gqbZ feêh dks 50 ehVj dh nwjh rd fuLrkj.kdjuk

lhesUV dkaØhV uhao ;k Q'kZ esa 40 fe- eh- ukeh; eki dh iRFkj fxÍh@bZV fxÍh] lhesUV & jsr elkyk esa 1 lhesUV % 5 jsr % 10 fxÍh vuqikr eas feykdj Mkyuk rFkk dqVkbZ djuk] 0

0

0

66.3536 1.87 cum. 372.60 1576.00 696.762 2947.12

3

0 1170.83 1 0.5 0

1 131.922 1.5 0.5 98.9415

98.9415 2.8 ?ku eh- 242.40 711.00 678.72 1990.80

4 1 36.9068 1.25 12 553.601

0

553.601 15.67 cum. 473.00 1704.00 7411.91 26701.68

5 1 131.92 1.5 0.5 98.9415

1 131.92 1.25 2 329.805

vuqikr eas feykdj Mkyuk rFkk dqVkbZ djuk] rjkbZ lesrA

uhao es 40 fe-eh- ukeh; eki ds lkFk 40 izfr'kr xkjs feêh dks feykdj Mkyuk vkSj dwVukA

iRFkj dh fxêh ds lkFk

uhao rFkk dqlhZ es iRFkj dh os j)k&<+ksdk lhesaV&ctjh 1 % 6 elkys es] e; cxy dh f>jh cUn djuk rFkk rjkbZ vkfnA

uhao rFkk dqlhZ esa iRFkj dh os j)k&<ksdk fpukbZ] xkjk elkys esasaA

Page 81: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

428.747 12.13 cum. 473.00 1235.00 5737.49 14980.55

6

ikV 2 9 1 0.5 9

;ksx 9 0.250 cum. 1188.90 4066.00 297.225 1016.50

7 1 132.707 1 1 132.707

0

dVksfr;ka -1 1.5 1.5 1 -2.25

130.457 12.11 sqm. 263.50 659.00 3190.985 7980.49

8 1 132.707 1 1 132.707

-1 1.5 1.5 1 -2.25

130.457 12.11 sqm. 116.50 303.00 1410.815 3669.33

9 1 86.5463 1 1 86.5463

1 131.922 1.25 1 164.903

iRFkj ds fljny ¼fyVay½ dh vkiwfrZ dj]fpukbZ es mi;ksx dh xbZ elkys es mls yxkukA

viqzOM [kku dh iVVh dh Nr Nr ds nksuks dsrjQ fles.V 1:4 ls Hkjuk

lhes.V dadjhV 1:2:4 dh Nr dk dk;Z 20 feehfxVVh

lhes.V dadjhV 1:2:4 dh Q'kZ dk dk;Z 20feeh fxVVh

1 131.922 1.25 1 164.903

251.449 23.35 sqm. 91.10 212.00 2127.185 4950.20

10 1 32.9805 1 11.75 387.521

387.521 36 sqm. 77.70 134.00 2797.2 4824.00

11 1 40.833 1 2.5 102.083

1 135.805 1 2 271.61

1 127.955 1 2 255.91

629.603 58.49 sqm. 45.80 56.00 2678.842 3275.44

12 1 1.5 1.5 1 2.25

feeh fxVVh

lhesaV IykLVj nhokj ij 1:6 vuqikr eslhesaV&ctjh feykdj dj tksMksa dks dqjsnusrFkk rjkbZ lfgr 25 fe-eh- esaA

iRFkj dh pqukbZ ij lhes.V elkyk 1:3 ls Vhiksdk dk;Z

22 xst dh lknk ,e- ,l- pn~nj ds 1 eh- x2 eh- nks iYys okys njokts] ftlesa yksgs dh40x40x3 fe-eh- ds dksfu;k yksgs dh pkSjoV rFkkiYyks esa 25x25x3 fe-eh- ds dksfu;k yksgs( (Angle Iron) ds fdukjs fn, x, uD'ks dsvuqlkj e; vxZy fpVduh rFkk idM+ ifê;ksad

Page 82: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

2.25 0.2 sqm. 0.00 LS 100 500.00

13 vU; vko';drk vuqlkj dk;Z 0

0

0 200 2000

32345.03 79854.00

79854.00

Rate

Skilled labour 400

Unskilled labour 135 JeA 32345.03

Water lkexzh B 47508.98

dqyC 79854

146

dqy ;ksx (C+D) 80000

d

Silt Trap, Jali, Hand Pump etc

Quantity Amount

42.20 16881 jkf'k

89.63 12100

3364

32345

Add for contingency

dz-la- dqy lkexzh vko';drk nj jkf'k

1 jsr@ctjh ?k-eh- 400 3684.78

2 fxêh iRFkj dh 40 fe-eh- ukeh; eki dh ?k-eh- 425 1905.28

3 fxêh iRFkj dh 20 fe-eh- ukeh; eki dh ?k-eh- 580 960.625

4 iRFkj ?k-eh- 650 19877

5 lhesUV fd-xzk- 260 12496.4 48.063

6 iRFkj ds fljny 15 ls-eh- eksVkbZ rd ?k-eh- 2700 675

7 iRFkj dh ifê;ka o-eh- 340 4529.14

8 QsDVªh esa cus njokts o-eh- 2000.00 400

9 xkjk&feêh ?k-eh- 83.00 445.337

44973.5

vU; 2535.45

47509

bZdkbZ ek=k

9.21

4.48

1.66

30.58

2403.1

0.25

13.32

0.200

5.366

Silt Trap, Jali, Hand Pump etc

dqy ;ksx

Page 83: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

iapk;r lfefr ckoMh

VkaWds dh MªkbZx

gSa.M iai

<Ddu 1.5' x 1.5'

2'

42

csjÌk iRFkj dh <ksdk pqukb xkjs

es

flesaUV dadjhV

¼1%2%4½Vkads dk vkxkSj

2.00 2'

2' 10.5tehu ry

65'

flesaUV dadjhV

¼1%2%4½

csjÌk iRFkj dh <ksdk

pqukbZ(1:6) 1'3" eksVkbZ

2' 10.51'

tehu ry1'

3' 10.5011.75

flesaUV dadjhV ¼1%4%8½

6"

13.00

Page 84: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Design of Water Harvesting Structure (tanka)

Collection of Water = Area * rainfall* 80% Capacity as per Structural design

Catchment Area = ^4*D2

D= 11.70 Cum= ^4*Dt2 * Hight

= 107.46 Sqm Dt= Inner diameter of tanka

Rainfall = 0.3 Mtr Dt= 3.2 3.2004

Hight = 3.20

Collection of water = 25.79 Cum

25.7261 Cum

Capacity Cum*1000 Capacity Cum*1000Capacity Cum*1000 Capacity Cum*1000

= 25790 = 25726.1

Hence rainfall on catchment area can fillup the tanka by water

Production

Total capacity of tanka 25726.1 Ltr

Use of water for drinking purpose 40% 10290.4 Ltr

Available water for plantation 60% 15435.7 Ltr

One watering require 15 Ltr

No. of watering per Year 20 No

Total Ltr require per plant per year 300 Ltr

No of plant can survive = Available water for Plantation/ water require per plant per year

= 51.45

say 50 plant

Page 85: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Area- 0.17 Ha

No. of Plants - 50

Year No./Year

1 Earth work Excavation in hard soil dry

or moist and disposal of excavated

meterial within initial lift of 1.5 mt

height and lead of 50 metre.Digging of

pit

2(B)

1 0.6 0.6 0.6 0.22 cum. 92 19.87 993.60

2 Apply of manure

(A) Compost Khad5.00 kg. 0.4 2.00 100.00

(B) S.S.P. (16%)1.00 kg. 4 4.00 200.00

(C) Endosulphan (4%) 100 gm 0.10 kg. 30 3.00 150.00

3 Plant cost LS1 1.00 No 20 20.00 1000.00

4 Planting of plant 113(B)1.00 No. 3 3.00 150.00

5 Watering of plants (15 litre) 115 3 20 60.00 No. 1.8 108.00 5400.00

6 Making of Thawla atleast 50 cm radius 117(B) 2 1 2.00 No. 1.8 3.60 180.00

7 Weeding & hoeing of plants 45 cm

radius and 15 cm deep

1163

1 3.00 No. 1.2 3.60 180.00

Amount for

50 Plants

Model estimate of Horticulture Plantation in Arable land

Length Width Height Qty UnitS.

No

Description Item

No.

Total Rate Amount

Page 86: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Year No./Year

Amount for

50 Plants

Length Width Height Qty UnitS.

No

Description Item

No.

Total Rate Amount

8 Spray

(A) Endosulphan (35 ec) 3 0.01 Ltr 0.03 Ltr. 280 8.40 420.00

(B) Sulpher 3 0.02 Kg 0.06 200 12.00 600.00

9 Transportation of Plant from Jodhpur 70

km including loading and unloading

LS

1.00 no 2 3.00 150.00

10 Protection of plants from frost / loo

using grass or other locally available

material by making jhonpa of 0.6 m dia.

Of plant height and covering the plant.

Forest

bsr

1 1 1.00 no 3.56 3.56 178.00

TOTAL 187.47 9701.60

Add 3% contingency 291.048

Total 9992.65

say 10000.0

Page 87: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Work :- Khadin - I

INTRODUCTION :

OBJECT :

The adventage of constructing such structure is:-

1. When rainfall is inadequate kharif can be taken

2. When rainfall is sufficient both kharif and rabi crop can be raised.

3. If the rainfall is in the latter end of the monsoon the water can be used for rabi

TECHNICAL REPORT

To conserve the moisture in the soil profile KHADIN’s are constructed as a bund across the slop on flater lands so that

runoff is spread over a larger cultivable area, this will improve soil fertility, check soil erosion. While selecting the site

preference is given to the fields owned by the weaker sections of the society.

The problem can be solved upto certain extent by constructing different structures for harvesting the runoff water

which will increase the production. Construction of different structure will reduce the siol erosion and conserve the moisture in

the soil. The rabi crop can be taken by conserving the moisture in the soil. KHADIN is one of the water harvesting structure

which will reduce the soil erosion , provide labour employment in the area and increases the production by conserving the

moisture in the soil profile.

In arid and semi arid region rainfall is erratic, scanty and insuffcient for crops. In this region frequent famine conditions

prevalls which causses mass migration of humen and cattle population in search of food, fodder and water for servival.

Page 88: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

GENERAL FEATURES :

SOIL DESCREPTION :

JUSTIFICATION :

CROPING PATTERN :

The crop can be taken in the submerged area kharif / rabi season depending on monsoon which is going to benefit the

cultivators.The major crops growing in the area are Bajra, Moong, Moth and Til etc. in kharif season. The present cropping pattern is

followed by cultivators as they have to depend upon rains. But the cropping pattern will be changed after harvesting the runoff water in

the KHADIN.

The KHADIN area is having gentle slop of 0.2% average with slop direction towards South–East to North – West. The cimate

of the area is hot and dry. The maximum temperature recorded in summer is 43°C to 47°C and in winter 20°C to 40°C. In summer

hot dusty winds blows in the area with high velocity. The annual rainfall is about 300mm which is low and erratic. The ground water in

the area is very deep having depth 100m to 150m.

The soils of this area are deep to very deep coarse to medium textured and are moderately to well drained. This KHADIN

area soil type is loamy - sand. After water impounding in the KHADIN area soils are likely to be converted to sandy -loam type.

The catchment area is 125 ha.which can be clasified 125 ha. average – catchment. The area do not have any problem of

salinity / alknity.

The KHADIN work has been sanctioned in Jodhpur-XVII. An amount of Rs 4.5lacs as per enclosed abstract estimate is

required for this work. The estimates of KHADIN work are prepared on the basis of Gramin Kariya Nirdeshika 2010. The proposed

submergence area of the KHADIN is 9 Hact. The maximum height of the KHADIN bund as per design plan is 1.48 m.with storage

capacity of 2.1 X 10^4 Cum. The mandays to be generated are 6429 no.

Page 89: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

2 Submergence area Hect.

3 Average Rainfall 12”

4 Rainfall intensity 5 cm / hr

5 Side slope U/s 2.5 : 1 D/s 1.5 : 1

6 Seepage line slope 5 :1

7 Expected runoff from the catchment area Q from strang table at 12” rainfall

where catchment is = mcft / Sqm

Q = (1.296 X 10000 X0.0393 X 125 ) / 2.589

= Cum

Lowest level of the filed boundry =

8 Capacity of the khadin upto F.T.L. it is calculated by following formula

A) V0 = H/3 (A0+A1+ v A0 X A1) Where V1 = Capicity of the area covered by the lowest

= 0.30 / 3 ( 0.00 + 2.40 + 0.00 X 2.40 ) level of the boundry & First contour

= 0.24 X10 4 H= Vertical hight (Difference between two contour) = 0.30

A0= .Area of lower leevel of the boundry = 0.00 Hact

A1= Area of 1st contour = 2.40 Hact

B) V1 = H/3 (A1+A2+ v A1 X A2) Where V1 = Capicity of the area covered by the First contour

= 0.25 / 3 ( 2.40 + 5.30 + 2.40 X 5.30 ) level & Second contour level

= 0.94 X10 4 H= Vertical hight (Difference between two contour) = 0.25

A1= .Area of the First contour = 2.40 Hact

A2= Area of the Second contour = 5.30 Hact

D E S I G N O F K H A D I N

8.22

1.296

24519

9.00

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 90: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

C) V2 = H/3 (A2+A3+ v A2 X A3) Where V2 = Capicity of the area covered by the Second contour

= 0.13 / 3 ( 5.30 + 9.00 + X 9.00 ) level & Third contour level

= 0.92 X10 4 H = Vertical hight (Difference between two contour) = 0.13

A3= = Area of the Third contour = 9.0 Hact

Therefore V = V0+V1+V2

V = 0.24 + 0.94 + 0.92 )X 10 4

V = 2.10 X10 4

Crossection of the Khadin bund at maximum depth of submergence

Depth of the submergence = m Depth of flow over the crest = m

Free board = 1.5 X Hw in meter Where Hw = 0.014 (df)½

FB = 1.5 X Hw = 1.5X Depth of submergence

FB = % of slop of basin in meter

But proposed is 0.50 m df = ( / )X 100

= m

Total height of Khadin bund = m Hw = 0.014 ( ) ½

Hw =

Top width of bund = h /5 +1.5 or / 5 +1.5 = But proposed is m

Side slop U/S 2.5 :1 :1 Base width = ( X5 ) + 2.00 = m

Seepage line check –

Seepage line Width = Maximum impounding depth (up to F.T.L.)X (Seepage line slope + up stream side slop)

= X( 5.00 + 3.0 ) = 5.44

Base width > Seepage line width i.e. >

Hence design is safe

Length of pipe

The pipe (RCC) is placed at lowest level of the bund , length of pipe is required = 10.00 m

7.92 5.44

0.333

2.00

566.67

0.333

566.67

df =

1.48

1.48

7.92

0.68

1.80

1.48D/S 1.5

5.30

0.300.68

0.68 0.12

0.500

Page 91: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

For the design of the crest lenth of the weste weir following formula is used

Q = Peak rate of discharge

C = Runoff cofficient of the catchment area = 0.30

I = More intensity of rain fall during 10 years recuring interval

= 5 cm / hour

A= Catchment area = Hact.

Therefor Q = 0.0276 X C.I.A.

= 0.0276 X 0.30 X 5 X

=

Hence L = Q / (1.71 X h 3 /2 )

Q = Peak rate of discharge in Cum /mt. /sec

h = Depth of flow over the crest in mt.

L = Lenth of crest in meter

= / ( 1.71 X (0.30)3/2 )

= / 0.28

=

But Proposed is 30.00mt

W A S T E W E I R

5.16

18.43

5.16

125

125

5.16

Page 92: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Name of Village

2 Panchayat Samiti

4 Name of work

5 No of beneficiries

6 Submerged area (Hect.) 9.00 Hect.

7 Total capicity of W.H.S. 20978 Cum

8 Soil texture

9 Imperevious layer at depth

10 Average rainfall (mm)

11 Maximum rainfall (mm)

12 Flood lift

13 Cost of W.H.S.

14 Labour component

15 Material component

16 Per hect. Cost of W.H.S.

17 Employment Man days 6375

50000.00

Raikoriya

Baori

Khadin

67500.00

S U M M A R Y 0 F KHADIN

382500.00

12”

5 cm/hr

0.30 m

450000.00

6

Sandy – Loam

10 m

Page 93: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Layout of Bund 1820.00 0.25 M. 455.00

2 Clearance of Jungle 5609.60 1.40 Sq.M. 7853.44

3 Earth work Excavation for making of bund, laying in layers of 15

cm, breaking of clods, sorting of grass pebbles, disposal of

excavated material up to 1.5 mt Hight and lead up to 50 m

including dressing and compaction

4238.05 85.00 Cu.M. 360234.08

4 P/F ISI mark RCC pipe in C:M 1:3 (300 mm dia) 10.00 600.00 M. 6000.00

5 Excavation in hard soil ordinary muram or earth mixed with bajri

and kankar or boulder dry or moist & disposal of excavated

material within initial lead of 30 m and lift of 1.5 m including

dressing etc. complete.

32.83 92.00 Cu.M. 3020.54

6 Cement concrete well mixed in cement mortar ( 1 : 4 : 8 ) laid in

position complete including curing.Aggregate size upto 50 mm,

HB

8.21 1756.00 Cu.M. 14413.25

7 Random rubble stone masonary in cement sand mortar ( 1 : 6

)For foundation

18.12 1618.00 Cu.M. 29313.31

8 Random rubble stone masonary in cement sand mortar ( 1 : 6 )

For superstructure

3.00 1776.00 Cu.M. 5320.27

9 Cement concrete coping in 1:2:4 19.40 212.00 Sq.M. 4111.74

10 Ruled pointing in cement mortar (1:3) 10.65 56.00 Sq.M. 596.26

11 Dry stone pitching (20-23 cm) 27.26 670.00 Cu.M. 18260.85

TOTAL 449578.74

450000.00

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

ABSTRACT OF COST (KHADIN)

Say Rs.

KHADIN

Page 94: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Layout of Bund X 2 = 1820.0 1820.0 M.

2 Clearance of Jungle X 6.37 = 5609.6 5609.6 Sq.M.

3 Earth work Excavation for making of bund, laying in layers of 15 cm,

breaking of clods, sorting of grass pebbles, disposal of excavated 4238.05 Cu.M.

4 P/F ISI mark RCC pipe in C:M 1:3 (300 mm dia) 10 M.

5 1 X 1.00 X 0.90 X 0.80 = 0.72

4 X 0.90 X 0.90 X 0.80 = 2.592

1 X 7.00 X 0.90 X 0.80 = 5.04

2 X 2.00 X 0.90 X 0.80 = 2.88

1 X 30.0 X 0.90 X 0.80 = 21.6

32.832 32.832 Cu.M.

6 1 X 1.00 X 0.90 X 0.20 = 0.18

4 X 0.90 X 0.90 X 0.20 = 0.648

1 X 7.00 X 0.90 X 0.20 = 1.26

2 X 2.00 X 0.90 X 0.20 = 0.72

1 X 30.0 X 0.90 X 0.20 = 5.4

8.208 8.208 Cu.M.

7 1 X 1.00 X 0.75 X 0.30 = 0.225

4 X 0.75 X 0.75 X 0.30 = 0.675

1 X 1.00 X 0.60 X 0.30 = 0.180

4 X 0.60 X 0.60 X 0.30 = 0.432

1 X 7.00 X 0.75 X 0.30 = 1.575

2 X 2.00 X 0.75 X 0.30 = 0.900

1 X 30.0 X 0.75 X 0.30 = 6.750

1 X 7.00 X 0.60 X 0.30 = 1.260

Excavation in hard soil ordinary muram or earth mixed with bajri and

kankar or boulder dry or moist & disposal of excavated material within

initial lead of 30 m and lift of 1.5 m including dressing etc. complete.

10M.

4238.05

910

880

DETAILS OF WORK (KHADIN)

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

KHADIN

Cement concrete well mixed in cement mortar ( 1 : 4 : 8 ) laid in

position complete including curing.Aggregate size upto 50 mm, HB

Random rubble stone masonary in cement sand mortar ( 1 : 6 )For

foundation

Page 95: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

2 X 2.00 X 0.60 X 0.30 = 0.720

1 X 30.0 X 0.60 X 0.30 = 5.400

18.117 18.117 Cu.M.

8 1 X 1.00 X 0.45 X 1.00 = 0.450

3 X 0.45 X 0.45 X 0.30 = 0.182

1 X 0.45 X 0.60 X 0.30 = 0.081

2 X 2.00 X 0.45 X 0.30 = 0.540

= 2.025

3.278

4 X 3.14 / 4.00 X 0.3^2 = 0.283

2.996 2.996 Cu.M.

9 1 X 1.00 X 0.45 = 0.450

1 X 0.60 X 0.45 = 0.270

1 X 30.0 X 0.45 = 13.500

1 X 7.50 X 0.45 = 3.375

2 X 2.00 X 0.45 = 1.800

19.395 19.395 Sq.M.

10 2 X( 1.00 $ 0.45 )X 1.00 = 2.900

3 X( 4.00 $ 0.45 )X 0.45 = 2.430

2 X( 0.60 $ 0.45 )X 0.60 = 1.260

2 X( 2.00 $ 0.45 )X 0.30 = 0.540

1 X 7.00 X 0.30 = 2.100

(7 + 2) / 2 X 0.45 X 0.7 = 1.418

10.648 10.648 Sq.M.

11 1 X 30.0 X 2.00 X 0.23 = 13.80

1 X 10.0 X 1.80 X 0.23 = 4.14

1 X 15.0 X 2.70 X 0.23 = 9.32

27.26 27.26 Cu.M.

Random rubble stone masonary in cement sand mortar ( 1 : 6 ) For

superstructure

Cement concrete coping in 1:2:4

Ruled pointing in cement mortar (1:3)

Dry stone pitching (20-23 cm)

Page 96: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

level T.B.L. of bund U/s D/s section C. Sec. in M in Cum

0 9.80 9.80 0.00 2.00 2.5:1 1.5:1 0.00 0.00 0 0 0

40 9.70 0.10 2.40 0.22 0.11 40 4.40

80 9.62 0.18 2.72 0.42 0.32 40 12.90

120 9.40 0.40 3.60 1.12 0.77 40 30.90

160 8.96 0.84 5.36 3.09 2.11 40 84.22

200 8.70 1.10 6.40 4.62 3.86 40 154.22

240 8.64 1.16 6.64 5.01 4.82 40 192.62

280 8.60 1.20 6.80 5.28 5.15 40 205.82

320 8.62 1.18 6.72 5.14 5.21 40 208.50

360 8.64 1.16 6.64 5.01 5.08 40 203.12

400 8.65 1.15 6.60 4.95 4.98 40 199.12

440 8.55 1.25 7.00 5.63 5.29 40 211.40

480 8.45 1.35 7.40 6.35 5.99 40 239.40

520 8.30 1.50 8.00 7.50 6.92 40 276.90

560 8.22 1.58 8.32 8.15 7.83 40 313.06

600 8.25 1.55 8.20 7.91 8.03 40 321.16

640 8.30 1.50 8.00 7.50 7.70 40 308.10

680 8.42 1.38 7.52 6.57 7.03 40 281.38

720 8.49 1.31 7.24 6.05 6.31 40 252.42

760 8.61 1.19 6.76 5.21 5.63 40 225.29

800 8.68 1.12 6.48 4.75 4.98 40 199.22

840 8.84 0.96 5.84 3.76 4.26 40 170.24

880 8.90 0.90 5.60 3.42 3.59 40 143.66

140.24 4238.05

Average base width = 6.37

KHADIN

Earth work chart

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 97: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Series1 0 40 80 120 160 200 240 280 320 360 400 440 480 520 560 600 640 680 720 760 800 840 880

Series2 9.80 9.70 9.62 9.40 8.96 8.70 8.64 8.60 8.62 8.64 8.65 8.55 8.45 8.30 8.22 8.25 8.30 8.42 8.49 8.61 8.68 8.84 8.90

Series3 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80

Series4 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30

Series5 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

7

7.5

8

8.5

9

9.5

10

10.5

L-Section of Khadin

Page 98: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Cement Concrete (1:4:8) 8.208 26.27 3.69 7.39 -

2 Copping in C.C. (1:2:4) 19.395 6.05 0.43 0.87 -

3 Massonary in Cement 21.113 22.59 6.33 - 23.22

Mortar ( 1:8 )

4 Pointing in Cement 10.648 0.30 0.03 - -

Mortar ( 1:3 )

5 Dry Stone Pitching 27.255 - - - 29.98

6 R.C.C. Cement Pipe 2 Nos.

TOTAL 55.21 10.49 8.26 53.20

Say Bags 55

Stone

CumITEMS.No.

MATERIAL CONSUMPTION STATEMENTQuantity

Cum / Sqm

Cement

Begs

Sand

Cum

Aggrigate

Cum

Page 99: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

0.15

G.L.

0.45

0.45

0.6

0.15

1.0

0.45

EARTHEN STRUCTURE

G.L.

2.0M

0.075

0.9

0.15

0.451.00 0.60

2.50

0.15

ELEVATION

PLAN

0.30

0.075

Page 100: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

2

U/S

DRAWING OF SIDE WASTE-WEIR FOR LOW COSTING KHADINS

2.0

M

1

5.2

30 M

SID

E V

IEW

30.00

2

D/S

2.0

M

0.8

30 M

SID

E V

IEW

PLAN

30.00

Page 101: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Work :- Khadin - II

INTRODUCTION :

OBJECT :

The adventage of constructing such structure is:-

1. When rainfall is inadequate kharif can be taken

2. When rainfall is sufficient both kharif and rabi crop can be raised.

3. If the rainfall is in the latter end of the monsoon the water can be used for rabi

TECHNICAL REPORT

To conserve the moisture in the soil profile KHADIN’s are constructed as a bund across the slop on flater lands

so that runoff is spread over a larger cultivable area, this will improve soil fertility, check soil erosion. While selecting the

site preference is given to the fields owned by the weaker sections of the society.

The problem can be solved upto certain extent by constructing different structures for harvesting the runoff water

which will increase the production. Construction of different structure will reduce the siol erosion and conserve the

moisture in the soil. The rabi crop can be taken by conserving the moisture in the soil. KHADIN is one of the water

harvesting structure which will reduce the soil erosion , provide labour employment in the area and increases the

production by conserving the moisture in the soil profile.

In arid and semi arid region rainfall is erratic, scanty and insuffcient for crops. In this region frequent famine

conditions prevalls which causses mass migration of humen and cattle population in search of food, fodder and water

for servival.

Page 102: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

GENERAL FEATURES :

SOIL DESCREPTION :

JUSTIFICATION :

CROPING PATTERN :

The crop can be taken in the submerged area kharif / rabi season depending on monsoon which is going to benefit the

cultivators.The major crops growing in the area are Bajra, Moong, Moth and Til etc. in kharif season. The present cropping pattern is

followed by cultivators as they have to depend upon rains. But the cropping pattern will be changed after harvesting the runoff water in

the KHADIN.

The KHADIN area is having gentle slop of 0.2% average with slop direction towards South–East to North – West. The cimate

of the area is hot and dry. The maximum temperature recorded in summer is 43°C to 47°C and in winter 20°C to 40°C. In summer

hot dusty winds blows in the area with high velocity. The annual rainfall is about 300mm which is low and erratic. The ground water in

the area is very deep having depth 100m to 150m.

The soils of this area are deep to very deep coarse to medium textured and are moderately to well drained. This KHADIN

area soil type is loamy - sand. After water impounding in the KHADIN area soils are likely to be converted to sandy -loam type.

The catchment area is 156 ha.which can be clasified 156 ha. average – catchment. The area do not have any problem of

salinity / alknity.

The KHADIN work has been sanctioned in Jodhpur-XVII. An amount of Rs 5.14lacs as per enclosed abstract estimate is

required for this work. The estimates of KHADIN work are prepared on the basis of Gramin Kariya Nirdeshika 2010. The proposed

submergence area of the KHADIN is 8.1 Hact. The maximum height of the KHADIN bund as per design plan is 1.58 m.with storage

capacity of 2.71 X 10^4 Cum. The mandays to be generated are 7343 no.

Page 103: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Total catchment area 156 Hect.

2 Submergence area Hect.

3 Average Rainfall 12”

4 Rainfall intensity 5 cm / hr

5 Side slope U/s 2.5 : 1 D/s 1.5 : 1

6 Seepage line slope 5 :1

7 Expected runoff from the catchment area Q from strang table at 12” rainfall

where catchment is = mcft / Sqm

Q = (1.296 X 10000 X0.0393 X 156 ) / 2.589

= Cum

Lowest level of the filed boundry =

8 Capacity of the khadin upto F.T.L. it is calculated by following formula

A) V0 = H/3 (A0+A1+ v A0 X A1) Where V1 = Capicity of the area covered by the lowest

= 0.29 / 3 ( 0.00 + 2.40 + 0.00 X 2.40 ) level of the boundry & First contour

= 0.23 X10 4 H= Vertical hight (Difference between two contour) = 0.29

A0= .Area of lower leevel of the boundry = 0.00 Hact

A1= Area of 1st contour = 2.40 Hact

B) V1 = H/3 (A1+A2+ v A1 X A2) Where V1 = Capicity of the area covered by the First contour

= 0.25 / 3 ( 2.40 + 5.10 + 2.40 X 5.10 ) level & Second contour level

= 0.92 X10 4 H= Vertical hight (Difference between two contour) = 0.25

A1= .Area of the First contour = 2.40 Hact

A2= Area of the Second contour = 5.10 Hact

D E S I G N O F K H A D I N

8.22

1.296

30617

8.00

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 104: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

C) V2 = H/3 (A2+A3+ v A2 X A3) Where V2 = Capicity of the area covered by the Second contour

= 0.24 / 3 ( 5.10 + 8.00 + X 8.00 ) level & Third contour level

= 1.56 X10 4 H = Vertical hight (Difference between two contour)= 0.24

A2= = .Area of the Second contour = 5.10 Hact

A3= = Area of the Third contour = 8.0 Hact

Therefore V = V0+V1+V2

V = 0.23 + 0.92 + 1.56 )X 10 4

V = 2.71 X10 4

Crossection of the Khadin bund at maximum depth of submergence

Depth of the submergence = m Depth of flow over the crest = m

Free board = 1.5 X Hw in meter Where Hw = 0.014 (df)½

FB = 1.5 X Hw = 1.5X Depth of submergence

FB = % of slop of basin in meter

But proposed is 0.50 m df = ( / )X 100

= m

Total height of Khadin bund = m Hw = 0.014 ( ) ½

Hw =

Top width of bund = h /5 +1.5 or / 5 +1.5 = But proposed is m

Side slop U/S 2.5 :1 :1 Base width = ( X5 ) + 2.00 = m

Seepage line check –

Seepage line Width = Maximum impounding depth (up to F.T.L.)X (Seepage line slope + up stream side slop)

= X( 5.00 + 3.0 ) = 6.24

Base width > Seepage line width i.e. >

Hence design is safe

Length of pipe

The pipe (RCC) is placed at lowest level of the bund , length of pipe is required = 10.00 m

8.32 6.24

0.357

2.00

650.00

0.357

650.00

df =

1.58

1.58

8.32

0.78

1.82

1.58D/S 1.5

5.10

0.300.78

0.78 0.12

0.535

Page 105: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

For the design of the crest lenth of the weste weir following formula is used

Q = 0.0276 C.I.A

Q = Peak rate of discharge

C = Runoff cofficient of the catchment area = 0.30

I = More intensity of rain fall during 10 years recuring interval

= 5 cm / hour

A= Catchment area = Hact.

Therefor Q = 0.0276 X C.I.A.

= 0.0276 X 0.30 X 5 X

=

Hence L = Q / (1.71 X h 3 /2 )

Q = Peak rate of discharge in Cum /mt. /sec

h = Depth of flow over the crest in mt.

L = Lenth of crest in meter

= / ( 1.71 X (0.30)3/2 )

= / 0.28

=

But Proposed is 30.00mt

W A S T E W E I R

6.44

23.01

6.44

156

156

6.44

Page 106: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Name of Village

2 Panchayat Samiti

3 District

4 Name of work

5 No of beneficiries

6 Submerged area (Hect.) 8.00 Hect.

7 Total capicity of W.H.S. 27075 Cum

8 Soil texture

9 Imperevious layer at depth

10 Average rainfall (mm)

11 Maximum rainfall (mm)

12 Flood lift

13 Cost of W.H.S.

14 Labour component

15 Material component

16 Per hect. Cost of W.H.S.

17 Employment Man days 7282

64250.00

Raikoriya

Baori

Jodhpur

Khadin

77100.00

S U M M A R Y 0 F KHADIN

436900.00

12”

5 cm/hr

0.30 m

514000.00

5

Sandy – Loam

10 m

Page 107: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM Qty Rate Unit Amount

1 Layout of Bund ###### 0.25 M. 515.00

2 Clearance of Jungle ###### 1.40 Sq.M. 9120.16

3 Earth work Excavation for making of bund, laying in layers of

15 cm, breaking of clods, sorting of grass pebbles, disposal

of excavated material up to 1.5 mt Hight and lead up to 50 m

including dressing and compaction

###### 85.00 Cu.M. #######

4 P/F ISI mark RCC pipe in C:M 1:3 (300 mm dia) 10.00 600.00 M. 6000.00

5 Excavation in hard soil ordinary muram or earth mixed with

bajri and kankar or boulder dry or moist & disposal of

excavated material within initial lead of 30 m and lift of 1.5 m

including dressing etc. complete.

32.83 92.00 Cu.M. 3020.54

6 Cement concrete well mixed in cement mortar ( 1 : 4 : 8 ) laid

in position complete including curing.Aggregate size upto 50

mm, HB

8.21 ###### Cu.M. 14413.25

7 Random rubble stone masonary in cement sand mortar ( 1 : 6

)For foundation

18.12 ###### Cu.M. 29313.31

8 Random rubble stone masonary in cement sand mortar ( 1 : 6

) For superstructure

3.00 ###### Cu.M. 5320.27

9 Cement concrete coping in 1:2:4 19.40 212.00 Sq.M. 4111.74

10 Ruled pointing in cement mortar (1:3) 10.65 56.00 Sq.M. 596.26

11 Dry stone pitching (20-23 cm) 27.26 670.00 Cu.M. 18260.85

TOTA

L

#######

514000.00

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

ABSTRACT OF COST (KHADIN)

Say Rs.

KHADIN - II

Page 108: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM

1 Layout of Bund X 2 = 2060.0 2060.0 M.

2 Clearance of Jungle X 6.51 = 6514.4 6514.4 Sq.M.

3 Earth work Excavation for making of bund, laying in layers of 15 cm,

breaking of clods, sorting of grass pebbles, disposal of excavated 4978.40 Cu.M.

4 P/F ISI mark RCC pipe in C:M 1:3 (300 mm dia) 10 M.

5 1 X 1.00 X 0.90 X 0.80 = 0.72

4 X 0.90 X 0.90 X 0.80 = 2.592

1 X 7.00 X 0.90 X 0.80 = 5.04

2 X 2.00 X 0.90 X 0.80 = 2.88

1 X 30.0 X 0.90 X 0.80 = 21.6

32.832 32.832 Cu.M.

6 1 X 1.00 X 0.90 X 0.20 = 0.18

4 X 0.90 X 0.90 X 0.20 = 0.648

1 X 7.00 X 0.90 X 0.20 = 1.26

2 X 2.00 X 0.90 X 0.20 = 0.72

1 X 30.0 X 0.90 X 0.20 = 5.4

8.208 8.208 Cu.M.

7 1 X 1.00 X 0.75 X 0.30 = 0.225

4 X 0.75 X 0.75 X 0.30 = 0.675

1 X 1.00 X 0.60 X 0.30 = 0.180

4 X 0.60 X 0.60 X 0.30 = 0.432

1 X 7.00 X 0.75 X 0.30 = 1.575

2 X 2.00 X 0.75 X 0.30 = 0.900

1 X 30.0 X 0.75 X 0.30 = 6.750

1 X 7.00 X 0.60 X 0.30 = 1.260

2 X 2.00 X 0.60 X 0.30 = 0.720

1 X 30.0 X 0.60 X 0.30 = 5.400

18.117 18.117 Cu.M.

Excavation in hard soil ordinary muram or earth mixed with bajri and

kankar or boulder dry or moist & disposal of excavated material within

initial lead of 30 m and lift of 1.5 m including dressing etc. complete.

10M.

4978.40

1030

1000

DETAILS OF WORK (KHADIN)

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Measurement Qty.

KHADIN - II

Cement concrete well mixed in cement mortar ( 1 : 4 : 8 ) laid in position

complete including curing.Aggregate size upto 50 mm, HB

Random rubble stone masonary in cement sand mortar ( 1 : 6 )For

foundation

Page 109: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM Measurement Qty.

8 1 X 1.00 X 0.45 X 1.00 = 0.450

3 X 0.45 X 0.45 X 0.30 = 0.182

2 X 2.00 X 0.45 X 0.30 = 0.540

(7 + 2) / 2 X 0.45 X 1 = 2.025

3.278

4 X 3.14 / 4.00 X 0.3^2 = 0.283

2.996 2.996 Cu.M.

9 1 X 1.00 X 0.45 = 0.450

1 X 0.60 X 0.45 = 0.270

1 X 30.0 X 0.45 = 13.500

1 X 7.50 X 0.45 = 3.375

2 X 2.00 X 0.45 = 1.800

19.395 19.395 Sq.M.

10 2 X( 1.00 $ 0.45 )X 1.00 = 2.900

3 X( 4.00 $ 0.45 )X 0.45 = 2.430

2 X( 0.60 $ 0.45 )X 0.60 = 1.260

2 X( 2.00 $ 0.45 )X 0.30 = 0.540

1 X 7.00 X 0.30 = 2.100

(7 + 2) / 2 X 0.45 X 0.7 = 1.418

10.648 10.648 Sq.M.

11 1 X 30.0 X 2.00 X 0.23 = 13.80

1 X 10.0 X 1.80 X 0.23 = 4.14

1 X 15.0 X 2.70 X 0.23 = 9.32

27.26 27.26 Cu.M.

Random rubble stone masonary in cement sand mortar ( 1 : 6 ) For

superstructure

Cement concrete coping in 1:2:4

Ruled pointing in cement mortar (1:3)

Dry stone pitching (20-23 cm)

Page 110: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Chainage Ground Proposed Height Top width Side slop Base width Cross- Average Lenth Earth work

level T.B.L. of bund U/s D/s section C. Sec. in M in Cum

0 9.70 9.80 0.10 2.10 2.5:1 1.5:1 0.40 0.02 0 0 0

40 9.70 0.10 2.50 0.23 0.13 40 5.00

80 9.62 0.18 2.82 0.44 0.34 40 13.46

120 9.40 0.40 3.70 1.16 0.80 40 32.06

160 8.96 0.84 5.46 3.18 2.17 40 86.70

200 8.70 1.10 6.50 4.73 3.95 40 158.10

240 8.64 1.16 6.74 5.13 4.93 40 197.14

280 8.60 1.20 6.90 5.40 5.26 40 210.54

320 8.62 1.18 6.82 5.26 5.33 40 213.26

360 8.60 1.20 6.90 5.40 5.33 40 213.26

400 8.55 1.25 7.10 5.75 5.58 40 223.00

440 8.62 1.18 6.82 5.26 5.51 40 220.26

480 8.64 1.16 6.74 5.13 5.20 40 207.80

520 8.65 1.15 6.70 5.06 5.09 40 203.74

560 8.55 1.25 7.10 5.75 5.41 40 216.20

600 8.45 1.35 7.50 6.48 6.12 40 244.60

640 8.30 1.50 8.10 7.65 7.07 40 282.60

680 8.22 1.58 8.42 8.31 7.98 40 319.22

720 8.25 1.55 8.30 8.06 8.19 40 327.42

760 8.30 1.50 8.10 7.65 7.86 40 314.20

800 8.42 1.38 7.62 6.71 7.18 40 287.14

840 8.49 1.31 7.34 6.18 6.45 40 257.80

880 8.61 1.19 6.86 5.33 5.76 40 230.29

920 8.68 1.12 6.58 4.86 5.10 40 203.84

960 8.84 0.96 5.94 3.86 4.36 40 174.40

1000 9.00 0.80 5.30 2.96 3.41 40 136.38

163.26 4978.40

Average base width = 6.51

KHADIN - II

Earth work chart

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 111: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Series1 0 40 80 120 160 200 240 280 320 360 400 440 480 520 560 600 640 680 720 760 800 840 880 920 960 1000

Series2 9.70 9.70 9.62 9.40 8.96 8.70 8.64 8.60 8.62 8.60 8.55 8.62 8.64 8.65 8.55 8.45 8.30 8.22 8.25 8.30 8.42 8.49 8.61 8.68 8.84 9.00

Series3 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80

Series4 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30

Series5 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

7

7.5

8

8.5

9

9.5

10

10.5

L-Section of Khadin

Page 112: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Cement Concrete (1:4:8) 8.208 26.27 3.69 7.39 -

2 Copping in C.C. (1:2:4) 19.395 6.05 0.43 0.87 -

3 Massonary in Cement 21.113 22.59 6.33 - 23.22

Mortar ( 1:8 )

4 Pointing in Cement 10.648 0.30 0.03 - -

Mortar ( 1:3 )

5 Dry Stone Pitching 27.255 - - - 29.98

6 R.C.C. Cement Pipe 2 Nos.

TOTAL 55.21 10.49 8.26 53.20

Say Bags 55

Stone

CumITEMS.No.

MATERIAL CONSUMPTION STATEMENT

Quantity

Cum / Sqm

Cement

Begs

Sand

Cum

Aggrigate

Cum

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 113: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

G.L.

DRAWING OF PIPE OUTLET AT THE LOWEST POINT OF KHADIN

0.45

0.45

0.6

1.0

0.45

EARTHEN STRUCTURE

G.L.

2.0M

0.15

G.L.

0.9

0.15

0.451.00 0.60

2.50

0.15

ELEVATION

PLAN

G.L.

0.30

0.075

Page 114: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

2

U/S

DRAWING OF SIDE WASTE-WEIR FOR LOW COSTING KHADINS

2.0

M

0.6

5.2

SID

E V

IEW

2

D/S

2.0

M

0.8

30 M

SID

E V

IEW

PLAN

30.00

Page 115: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Work :- Khadin - III

OBJECT :

The adventage of constructing such structure is:-

1. When rainfall is inadequate kharif can be taken

2. When rainfall is sufficient both kharif and rabi crop can be raised.

3. If the rainfall is in the latter end of the monsoon the water can be used for rabi

TECHNICAL REPORT

To conserve the moisture in the soil profile KHADIN’s are constructed as a bund across the slop on flater lands

so that runoff is spread over a larger cultivable area, this will improve soil fertility, check soil erosion. While selecting the

site preference is given to the fields owned by the weaker sections of the society.

The problem can be solved upto certain extent by constructing different structures for harvesting the runoff water

which will increase the production. Construction of different structure will reduce the siol erosion and conserve the

moisture in the soil. The rabi crop can be taken by conserving the moisture in the soil. KHADIN is one of the water

harvesting structure which will reduce the soil erosion , provide labour employment in the area and increases the

production by conserving the moisture in the soil profile.

In arid and semi arid region rainfall is erratic, scanty and insuffcient for crops. In this region frequent famine

conditions prevalls which causses mass migration of humen and cattle population in search of food, fodder and water

for servival.

Page 116: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

GENERAL FEATURES :

SOIL DESCREPTION :

JUSTIFICATION :

CROPING PATTERN :

The crop can be taken in the submerged area kharif / rabi season depending on monsoon which is going to benefit the

cultivators.The major crops growing in the area are Bajra, Moong, Moth and Til etc. in kharif season. The present cropping pattern is

followed by cultivators as they have to depend upon rains. But the cropping pattern will be changed after harvesting the runoff water in

the KHADIN.

The KHADIN area is having gentle slop of 0.2% average with slop direction towards South–East to North – West. The cimate

of the area is hot and dry. The maximum temperature recorded in summer is 43°C to 47°C and in winter 20°C to 40°C. In summer

hot dusty winds blows in the area with high velocity. The annual rainfall is about 300mm which is low and erratic. The ground water in

the area is very deep having depth 100m to 150m.

The soils of this area are deep to very deep coarse to medium textured and are moderately to well drained. This KHADIN

area soil type is loamy - sand. After water impounding in the KHADIN area soils are likely to be converted to sandy -loam type.

The catchment area is 179 ha.which can be clasified 179 ha. average – catchment. The area do not have any problem of

salinity / alknity.

The KHADIN work has been sanctioned in Jodhpur-XVII. An amount of Rs 5.12lacs as per enclosed abstract estimate is

required for this work. The estimates of KHADIN work are prepared on the basis of Gramin Kariya Nirdeshika 2010. The proposed

submergence area of the KHADIN is 7.9 Hact. The maximum height of the KHADIN bund as per design plan is 1.68 m.with storage

capacity of 3.17 X 10^4 Cum. The mandays to be generated are 7315 no.

Page 117: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Total catchment area 179 Hect.

2 Submergence area Hect.

3 Average Rainfall 12”

4 Rainfall intensity 5 cm / hr

5 Side slope U/s 2.5 : 1 D/s 1.5 : 1

6 Seepage line slope 5 :1

7 Expected runoff from the catchment area Q from strang table at 12” rainfall

where catchment is = mcft / Sqm

Q = (1.296 X 10000 X0.0393 X 179 ) / 2.589

= Cum

Lowest level of the filed boundry =

8 Capacity of the khadin upto F.T.L. it is calculated by following formula

A) V0 = H/3 (A0+A1+ v A0 X A1) Where V1 = Capicity of the area covered by the lowest

= 0.30 / 3 ( 0.00 + 2.10 + 0.00 X 2.10 ) level of the boundry & First contour

= 0.21 X10 4 H= Vertical hight (Difference between two contour) = 0.30

A0= .Area of lower leevel of the boundry = 0.00 Hact

A1= Area of 1st contour = 2.10 Hact

B) V1 = H/3 (A1+A2+ v A1 X A2) Where V1 = Capicity of the area covered by the First contour

= 0.26 / 3 ( 2.10 + 4.90 + 2.10 X 4.90 ) level & Second contour level

= 0.88 X10 4 H= Vertical hight (Difference between two contour) = 0.26

A1= .Area of the First contour = 2.10 Hact

A2= Area of the Second contour = 4.90 Hact

D E S I G N O F K H A D I N

8.22

1.296

35223

8.20

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 118: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

C) V2 = H/3 (A2+A3+ v A2 X A3) Where V2 = Capicity of the area covered by the Second contour

= 0.32 / 3 ( 4.90 + 8.20 + X 8.20 ) level & Third contour level

= 2.07 X10 4 H = Vertical hight (Difference between two contour)= 0.32

A2= = .Area of the Second contour = 4.90 Hact

A3= = Area of the Third contour = 8.2 Hact

Therefore V = V0+V1+V2

V = 0.21 + 0.88 + 2.07 )X 10 4

V = 3.17 X10 4

Crossection of the Khadin bund at maximum depth of submergence

Depth of the submergence = m Depth of flow over the crest = m

Free board = 1.5 X Hw in meter Where Hw = 0.014 (df)½

FB = 1.5 X Hw = 1.5X Depth of submergence

FB = % of slop of basin in meter

But proposed is 0.50 m df = ( / )X 100

= m

Total height of Khadin bund = m Hw = 0.014 ( ) ½

Hw =

Top width of bund = h /5 +1.5 or / 5 +1.5 = But proposed is m

Side slop U/S 2.5 :1 :1 Base width = ( X5 ) + 2.00 = m

Seepage line check –

Seepage line Width = Maximum impounding depth (up to F.T.L.)X (Seepage line slope + up stream side slop)

= X( 5.00 + 3.0 ) = 7.04

Base width > Seepage line width i.e. >

Hence design is safe

Length of pipe

The pipe (RCC) is placed at lowest level of the bund , length of pipe is required = 10.00 m

4.90

0.300.88

0.88 0.12

0.569

8.72

0.88

1.84

1.68D/S 1.5

8.72 7.04

0.379

2.00

733.33

0.379

733.33

df =

1.68

1.68

Page 119: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Q = 0.0276 C.I.A

Q = Peak rate of discharge

C = Runoff cofficient of the catchment area = 0.30

I = More intensity of rain fall during 10 years recuring interval

= 5 cm / hour

A= Catchment area = Hact.

Therefor Q = 0.0276 X C.I.A.

= 0.0276 X 0.30 X 5 X

=

Hence L = Q / (1.71 X h 3 /2 )Q = Peak rate of discharge in Cum /mt. /sec

h = Depth of flow over the crest in mt.

L = Lenth of crest in meter

= / ( 1.71 X (0.30)3/2 )

= / 0.28

=

But Proposed is 30.00mt

W A S T E W E I R

7.41

26.47

7.41

179

179

7.41

Page 120: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Name of Village

3 District

4 Name of work

5 No of beneficiries

6 Submerged area (Hect.) 8.20 Hect.

7 Total capicity of W.H.S. 31681 Cum

8 Soil texture

9 Imperevious layer at depth

10 Average rainfall (mm)

11 Maximum rainfall (mm)

12 Flood lift

13 Cost of W.H.S.

14 Labour component

15 Material component

16 Per hect. Cost of W.H.S.

17 Employment Man days

S U M M A R Y 0 F KHADIN

435200.00

12”

5 cm/hr

0.30 m

512000.00

5

Sandy – Loam

10 m

7253

62439.02

Chandrakh

Jodhpur

Khadin

76800.00

Page 121: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM Qty Rate Unit Amount

1 Layout of Bund ###### 0.25 M. 515.00

2 Clearance of Jungle ###### 1.40 Sq.M. 9093.28

3 Earth work Excavation for making of bund, laying in layers of

15 cm, breaking of clods, sorting of grass pebbles, disposal

of excavated material up to 1.5 mt Hight and lead up to 50 m

including dressing and compaction

###### 85.00 Cu.M. #######

4 P/F ISI mark RCC pipe in C:M 1:3 (300 mm dia) 10.00 600.00 M. 6000.00

5 Excavation in hard soil ordinary muram or earth mixed with

bajri and kankar or boulder dry or moist & disposal of

excavated material within initial lead of 30 m and lift of 1.5 m

including dressing etc. complete.

32.83 92.00 Cu.M. 3020.54

6 Cement concrete well mixed in cement mortar ( 1 : 4 : 8 ) laid

in position complete including curing.Aggregate size upto 50

mm, HB

8.21 ###### Cu.M. 14413.25

7 Random rubble stone masonary in cement sand mortar ( 1 : 6

)For foundation

18.12 ###### Cu.M. 29313.31

8 Random rubble stone masonary in cement sand mortar ( 1 : 6

) For superstructure

3.00 ###### Cu.M. 5320.27

9 Cement concrete coping in 1:2:4 19.40 212.00 Sq.M. 4111.74

10 Ruled pointing in cement mortar (1:3) 10.65 56.00 Sq.M. 596.26

11 Dry stone pitching (20-23 cm) 27.26 670.00 Cu.M. 18260.85

TOTA #######512000.00

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

ABSTRACT OF COST (KHADIN)

Say Rs.

Page 122: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM

1 Layout of Bund X 2 = 2060.0 2060.0 M.

2 Clearance of Jungle X 6.50 = 6495.2 6495.2 Sq.M.

3 Earth work Excavation for making of bund, laying in layers of 15

cm, breaking of clods, sorting of grass pebbles, disposal of 4951.16 Cu.M.

4 P/F ISI mark RCC pipe in C:M 1:3 (300 mm dia) 10 M.

5 1 X 1.00 X 0.90 X 0.80 = 0.72

4 X 0.90 X 0.90 X 0.80 = 2.592

1 X 7.00 X 0.90 X 0.80 = 5.04

2 X 2.00 X 0.90 X 0.80 = 2.88

1 X 30.0 X 0.90 X 0.80 = 21.6

32.832 32.832 Cu.M.

6 1 X 1.00 X 0.90 X 0.20 = 0.184 X 0.90 X 0.90 X 0.20 = 0.648

1 X 7.00 X 0.90 X 0.20 = 1.26

2 X 2.00 X 0.90 X 0.20 = 0.72

1 X 30.0 X 0.90 X 0.20 = 5.4

8.208 8.208 Cu.M.

7 1 X 1.00 X 0.75 X 0.30 = 0.2254 X 0.75 X 0.75 X 0.30 = 0.675

1 X 1.00 X 0.60 X 0.30 = 0.180

4 X 0.60 X 0.60 X 0.30 = 0.432

1 X 7.00 X 0.75 X 0.30 = 1.575

2 X 2.00 X 0.75 X 0.30 = 0.900

1 X 30.0 X 0.75 X 0.30 = 6.750

1 X 7.00 X 0.60 X 0.30 = 1.260

2 X 2.00 X 0.60 X 0.30 = 0.720

1 X 30.0 X 0.60 X 0.30 = 5.400

18.117 18.117 Cu.M.

8 1 X 1.00 X 0.45 X 1.00 = 0.450

Cement concrete well mixed in cement mortar ( 1 : 4 : 8 ) laid in

position complete including curing.Aggregate size upto 50 mm, HB

Random rubble stone masonary in cement sand mortar ( 1 : 6 )For

foundation

Random rubble stone masonary in cement sand mortar ( 1 : 6 ) For

superstructure

Excavation in hard soil ordinary muram or earth mixed with bajri and

kankar or boulder dry or moist & disposal of excavated material

within initial lead of 30 m and lift of 1.5 m including dressing etc.

complete.

10M.

4951.16

1030

1000

DETAILS OF WORK (KHADIN)

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-BaoriMeasurement Qty.

Page 123: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM Measurement Qty.

3 X 0.45 X 0.45 X 0.30 = 0.182

1 X 0.45 X 0.60 X 0.30 = 0.081

2 X 2.00 X 0.45 X 0.30 = 0.540

(7 + 2) / 2 X 0.45 X 1 = 2.025

3.278

4 X 3.14 / 4.00 X 0.3^2 = 0.283

2.996 2.996 Cu.M.

9 1 X 1.00 X 0.45 = 0.450

1 X 0.60 X 0.45 = 0.270

1 X 30.0 X 0.45 = 13.500

1 X 7.50 X 0.45 = 3.375

2 X 2.00 X 0.45 = 1.800

19.395 19.395 Sq.M.

10 2 X( 1.00 $ 0.45 )X 1.00 = 2.900

3 X( 4.00 $ 0.45 )X 0.45 = 2.430

2 X( 0.60 $ 0.45 )X 0.60 = 1.260

2 X( 2.00 $ 0.45 )X 0.30 = 0.540

1 X 7.00 X 0.30 = 2.100

(7 + 2) / 2 X 0.45 X 0.7 = 1.418

10.648 10.648 Sq.M.

11 1 X 30.0 X 2.00 X 0.23 = 13.80

1 X 10.0 X 1.80 X 0.23 = 4.14

1 X 15.0 X 2.70 X 0.23 = 9.32

27.26 27.26 Cu.M.

superstructure

Cement concrete coping in 1:2:4

Ruled pointing in cement mortar (1:3)

Dry stone pitching (20-23 cm)

Page 124: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Chainage Ground Proposed Height Top width Side slop Base width Cross- Average Lenth Earth work

level T.B.L. of bund U/s D/s section C. Sec. in M in Cum

0 9.65 9.80 0.15 2.10 2.5:1 1.5:1 0.60 0.05 0 0 0

40 9.62 0.18 2.82 0.44 0.24 40 9.76

80 9.58 0.22 2.98 0.56 0.50 40 20.03

120 9.40 0.40 3.70 1.16 0.86 40 34.38

160 8.96 0.84 5.46 3.18 2.17 40 86.70

200 8.70 1.10 6.50 4.73 3.95 40 158.10

240 8.55 1.25 7.10 5.75 5.24 40 209.60

280 8.60 1.20 6.90 5.40 5.58 40 223.00

320 8.62 1.18 6.82 5.26 5.33 40 213.26

360 8.60 1.20 6.90 5.40 5.33 40 213.26

400 8.55 1.25 7.10 5.75 5.58 40 223.00

440 8.62 1.18 6.82 5.26 5.51 40 220.26

480 8.64 1.16 6.74 5.13 5.20 40 207.80

520 8.65 1.15 6.70 5.06 5.09 40 203.74

560 8.55 1.25 7.10 5.75 5.41 40 216.20

600 8.45 1.35 7.50 6.48 6.12 40 244.60

640 8.30 1.50 8.10 7.65 7.07 40 282.60

680 8.22 1.58 8.42 8.31 7.98 40 319.22

720 8.25 1.55 8.30 8.06 8.19 40 327.42

760 8.30 1.50 8.10 7.65 7.86 40 314.20

800 8.42 1.38 7.62 6.71 7.18 40 287.14

840 8.49 1.31 7.34 6.18 6.45 40 257.80

880 8.61 1.19 6.86 5.33 5.76 40 230.29

920 8.80 1.00 6.10 4.10 4.72 40 188.62

960 8.95 0.85 5.50 3.23 3.67 40 146.60

1000 9.10 0.70 4.90 2.45 2.84 40 113.60

162.98 4951.16

Average base width = 6.50

KHADIN - III

Earth work chart

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 125: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Series1 0 40 80 120 160 200 240 280 320 360 400 440 480 520 560 600 640 680 720 760 800 840 880 920 960 1000

Series2 9.65 9.62 9.58 9.40 8.96 8.70 8.55 8.60 8.62 8.60 8.55 8.62 8.64 8.65 8.55 8.45 8.30 8.22 8.25 8.30 8.42 8.49 8.61 8.80 8.95 9.10

Series3 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80

Series4 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30

Series5 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

7

7.5

8

8.5

9

9.5

10

10.5

L-Section of Khadin

Page 126: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Cement Concrete (1:4:8) 8.208 26.27 3.69 7.39 -

2 Copping in C.C. (1:2:4) 19.395 6.05 0.43 0.87 -

3 Massonary in Cement 21.113 22.59 6.33 - 23.22

Mortar ( 1:8 )

4 Pointing in Cement 10.648 0.30 0.03 - -

Mortar ( 1:3 )

5 Dry Stone Pitching 27.255 - - - 29.98

6 R.C.C. Cement Pipe 2 Nos.

TOTAL 55.21 10.49 8.26 53.20

Say Bags 55

Stone

CumITEMS.No.

MATERIAL CONSUMPTION STATEMENT

Quantity

Cum / Sqm

Cement

Begs

Sand

Cum

Aggrigate

Cum

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 127: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

2.0M

0.45

EARTHEN STRUCTURE

G.L.

DRAWING OF PIPE OUTLET AT THE LOWEST POINT OF KHADIN

0.45

0.45

0.6

1.0

G.L.

0.30

0.075

ELEVATION

PLAN

G.L.

0.451.00 0.60

2.50

0.15

0.15

G.L.

0.9

0.15

Page 128: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

2

U/S

DRAWING OF SIDE WASTE-WEIR FOR LOW COSTING KHADINS

2.0

M

0.6

5.2

SID

E V

IEW

2

D/S

PLAN

30.00

2.0

M

0.8

30 M

SID

E V

IEW

Page 129: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Work :- Khadin - IV

INTRODUCTION :

OBJECT :

The adventage of constructing such structure is:-

1. When rainfall is inadequate kharif can be taken

2. When rainfall is sufficient both kharif and rabi crop can be raised.

3. If the rainfall is in the latter end of the monsoon the water can be used for rabi

TECHNICAL REPORT

To conserve the moisture in the soil profile KHADIN’s are constructed as a bund across the slop on flater lands

so that runoff is spread over a larger cultivable area, this will improve soil fertility, check soil erosion. While selecting the

site preference is given to the fields owned by the weaker sections of the society.

The problem can be solved upto certain extent by constructing different structures for harvesting the runoff water

which will increase the production. Construction of different structure will reduce the siol erosion and conserve the

moisture in the soil. The rabi crop can be taken by conserving the moisture in the soil. KHADIN is one of the water

harvesting structure which will reduce the soil erosion , provide labour employment in the area and increases the

production by conserving the moisture in the soil profile.

In arid and semi arid region rainfall is erratic, scanty and insuffcient for crops. In this region frequent famine

conditions prevalls which causses mass migration of humen and cattle population in search of food, fodder and water

for servival.

Page 130: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

GENERAL FEATURES :

SOIL DESCREPTION :

JUSTIFICATION :

CROPING PATTERN :

The crop can be taken in the submerged area kharif / rabi season depending on monsoon which is going to benefit the

cultivators.The major crops growing in the area are Bajra, Moong, Moth and Til etc. in kharif season. The present cropping

pattern is followed by cultivators as they have to depend upon rains. But the cropping pattern will be changed after harvesting

the runoff water in the KHADIN.

The KHADIN area is having gentle slop of 0.2% average with slop direction towards South–East to North – West. The

cimate of the area is hot and dry. The maximum temperature recorded in summer is 43°C to 47°C and in winter 20°C to 40°C.

In summer hot dusty winds blows in the area with high velocity. The annual rainfall is about 300mm which is low and erratic.

The ground water in the area is very deep having depth 100m to 150m.

The soils of this area are deep to very deep coarse to medium textured and are moderately to well drained. This

KHADIN area soil type is loamy - sand. After water impounding in the KHADIN area soils are likely to be converted to sandy -

loam type.

The catchment area is 215 ha.which can be clasified 215 ha. average – catchment. The area do not have any problem

of salinity / alknity.

The KHADIN work has been sanctioned in Jodhpur-XVII. An amount of Rs 5.24lacs as per enclosed abstract estimate

is required for this work. The estimates of KHADIN work are prepared on the basis of Gramin Kariya Nirdeshika 2010. The

proposed submergence area of the KHADIN is 8.3 Hact. The maximum height of the KHADIN bund as per design plan is

1.78 m.with storage capacity of 3.87 X 10 4̂ Cum. The mandays to be generated are 7486 no.

Page 131: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Total catchment area 215 Hect.

2 Submergence area Hect.

3 Average Rainfall 12”

4 Rainfall intensity 5 cm / hr

5 Side slope U/s 2.5 : 1 D/s 1.5 : 1

6 Seepage line slope 5 :1

7 Expected runoff from the catchment area Q from strang table at 12” rainfall

where catchment is = mcft / Sqm

Q = (1.296 X 10000 X0.0393 X 215 ) / 2.589

= Cum

Lowest level of the filed boundry =

8 Capacity of the khadin upto F.T.L. it is calculated by following formula

A) V0 = H/3 (A0+A1+ v A0 X A1) Where V1 = Capicity of the area covered by the lowest

= 0.30 / 3 ( 0.00 + 2.20 + 0.00 X 2.20 ) level of the boundry & First contour

= 0.22 X10 4 H= Vertical hight (Difference between two contour) = 0.30

A0= .Area of lower leevel of the boundry = 0.00 Hact

A1= Area of 1st contour = 2.20 Hact

B) V1 = H/3 (A1+A2+ v A1 X A2) Where V1 = Capicity of the area covered by the First contour

= 0.29 / 3 ( 2.20 + 5.25 + 2.20 X 5.25 ) level & Second contour level

= 1.05 X10 4 H= Vertical hight (Difference between two contour) = 0.29

A1= .Area of the First contour = 2.20 Hact

A2= Area of the Second contour = 5.25 Hact

D E S I G N O F K H A D I N

8.22

1.296

42243

8.20

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

KHADIN - IV

Page 132: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

C) V2 = H/3 (A2+A3+ v A2 X A3) Where V2 = Capicity of the area covered by the Second contour

= 0.39 / 3 ( 5.25 + 8.20 + X 8.20 ) level & Third contour level

= 2.60 X10 4 H = Vertical hight (Difference between two contour)= 0.39

A2= = .Area of the Second contour = 5.25 Hact

A3= = Area of the Third contour = 8.2 Hact

Therefore V = V0+V1+V2

V = 0.22 + 1.05 + 2.60 )X 10 4

V = 3.87 X10 4

Crossection of the Khadin bund at maximum depth of submergence

Depth of the submergence = m Depth of flow over the crest = m

Free board = 1.5 X Hw in meter Where Hw = 0.014 (df)½

FB = 1.5 X Hw = 1.5X Depth of submergence

FB = % of slop of basin in meter

But proposed is 0.50 m df = ( / )X 100

= m

Total height of Khadin bund = m Hw = 0.014 ( ) ½

Hw =

Top width of bund = h /5 +1.5 or / 5 +1.5 = But proposed is m

Side slop U/S 2.5 :1 :1 Base width = ( X5 ) + 2.00 = m

Seepage line check –

Seepage line Width = Maximum impounding depth (up to F.T.L.)X (Seepage line slope + up stream side slop)

= X( 5.00 + 3.0 ) = 7.84

Base width > Seepage line width i.e. >

Hence design is safe

Length of pipe

The pipe (RCC) is placed at lowest level of the bund , length of pipe is required = 10.00 m

9.12 7.84

0.400

2.00

816.67

0.400

816.67

df =

1.78

1.78

9.12

0.98

1.86

1.78D/S 1.5

5.25

0.300.98

0.98 0.12

0.600

Page 133: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

For the design of the crest lenth of the weste weir following formula is used

Q = 0.0276 C.I.A

Q = Peak rate of discharge

C = Runoff cofficient of the catchment area = 0.30

I = More intensity of rain fall during 10 years recuring interval

= 5 cm / hour

A= Catchment area = Hact.

Therefor Q = 0.0276 X C.I.A.

= 0.0276 X 0.30 X 5 X

=

Hence L = Q / (1.71 X h 3 /2 )

Q = Peak rate of discharge in Cum /mt. /sec

h = Depth of flow over the crest in mt.

L = Lenth of crest in meter

= / ( 1.71 X (0.30)3/2 )

= / 0.28

=

But Proposed is 30.00mt

W A S T E W E I R

8.89

31.75

8.89

215

215

8.89

Page 134: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Name of Village

2 Panchayat Samiti

3 District

4 Name of work

5 No of beneficiries

6 Submerged area (Hect.) 8.20 Hect.

7 Total capicity of W.H.S. 38702 Cum

8 Soil texture

9 Imperevious layer at depth

10 Average rainfall (mm)

11 Maximum rainfall (mm)

12 Flood lift

13 Cost of W.H.S.

14 Labour component

15 Material component

16 Per hect. Cost of W.H.S.

17 Employment Man days 7423

63902.44

Chandrakh

Baori

Jodhpur

Khadin

78600.00

S U M M A R Y 0 F KHADIN

445400.00

12”

5 cm/hr

0.30 m

524000.00

6

Sandy – Loam

10 m

Page 135: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM Qty Rate Unit Amount

1 Layout of Bund ###### 0.25 M. 555.00

2 Clearance of Jungle ###### 1.40 Sq.M. 9528.96

3 Earth work Excavation for making of bund, laying in layers of

15 cm, breaking of clods, sorting of grass pebbles, disposal

of excavated material up to 1.5 mt Hight and lead up to 50 m

including dressing and compaction

###### 85.00 Cu.M. #######

4 P/F ISI mark RCC pipe in C:M 1:3 (300 mm dia) 10.00 600.00 M. 6000.00

5 Excavation in hard soil ordinary muram or earth mixed with

bajri and kankar or boulder dry or moist & disposal of

excavated material within initial lead of 30 m and lift of 1.5 m

including dressing etc. complete.

32.83 92.00 Cu.M. 3020.54

6 Cement concrete well mixed in cement mortar ( 1 : 4 : 8 ) laid

in position complete including curing.Aggregate size upto 50

mm, HB

8.21 ###### Cu.M. 14413.25

7 Random rubble stone masonary in cement sand mortar ( 1 : 6

)For foundation

18.12 ###### Cu.M. 29313.31

8 Random rubble stone masonary in cement sand mortar ( 1 : 6

) For superstructure

3.00 ###### Cu.M. 5320.27

9 Cement concrete coping in 1:2:4 19.40 212.00 Sq.M. 4111.74

10 Ruled pointing in cement mortar (1:3) 10.65 56.00 Sq.M. 596.26

11 Dry stone pitching (20-23 cm) 27.26 670.00 Cu.M. 18260.85

TOTA

L

#######

524000.00

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

ABSTRACT OF COST (KHADIN)

Say Rs.

KHADIN - IV

Page 136: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM

1 Layout of Bund X 2 = 2220.0 2220.0 M.

2 Clearance of Jungle X 6.30 = 6806.4 6806.4 Sq.M.

3 Earth work Excavation for making of bund, laying in layers of 15

cm, breaking of clods, sorting of grass pebbles, disposal of 5084.86 Cu.M.

4 P/F ISI mark RCC pipe in C:M 1:3 (300 mm dia) 10 M.

5 1 X 1.00 X 0.90 X 0.80 = 0.72

4 X 0.90 X 0.90 X 0.80 = 2.592

1 X 7.00 X 0.90 X 0.80 = 5.04

2 X 2.00 X 0.90 X 0.80 = 2.88

1 X 30.0 X 0.90 X 0.80 = 21.6

32.832 32.832 Cu.M.

6 1 X 1.00 X 0.90 X 0.20 = 0.18

4 X 0.90 X 0.90 X 0.20 = 0.648

1 X 7.00 X 0.90 X 0.20 = 1.26

2 X 2.00 X 0.90 X 0.20 = 0.72

1 X 30.0 X 0.90 X 0.20 = 5.4

8.208 8.208 Cu.M.

7 1 X 1.00 X 0.75 X 0.30 = 0.225

4 X 0.75 X 0.75 X 0.30 = 0.675

1 X 1.00 X 0.60 X 0.30 = 0.180

4 X 0.60 X 0.60 X 0.30 = 0.432

1 X 7.00 X 0.75 X 0.30 = 1.575

2 X 2.00 X 0.75 X 0.30 = 0.900

1 X 30.0 X 0.75 X 0.30 = 6.750

1 X 7.00 X 0.60 X 0.30 = 1.260

2 X 2.00 X 0.60 X 0.30 = 0.720

1 X 30.0 X 0.60 X 0.30 = 5.400

Excavation in hard soil ordinary muram or earth mixed with bajri and

kankar or boulder dry or moist & disposal of excavated material

within initial lead of 30 m and lift of 1.5 m including dressing etc.

complete.

10M.

5084.86

1110

1080

DETAILS OF WORK (KHADIN)

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Measurement Qty.

KHADIN - IV

Cement concrete well mixed in cement mortar ( 1 : 4 : 8 ) laid in

position complete including curing.Aggregate size upto 50 mm, HB

Random rubble stone masonary in cement sand mortar ( 1 : 6 )For

foundation

Page 137: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. ITEM Measurement Qty.

18.117 18.117 Cu.M.

8 1 X 1.00 X 0.45 X 1.00 = 0.450

3 X 0.45 X 0.45 X 0.30 = 0.182

1 X 0.45 X 0.60 X 0.30 = 0.081

2 X 2.00 X 0.45 X 0.30 = 0.540

(7 + 2) / 2 X 0.45 X 1 = 2.025

3.278

4 X 3.14 / 4.00 X 0.3^2 = 0.283

2.996 2.996 Cu.M.

9 1 X 1.00 X 0.45 = 0.450

1 X 0.60 X 0.45 = 0.270

1 X 30.0 X 0.45 = 13.500

1 X 7.50 X 0.45 = 3.375

2 X 2.00 X 0.45 = 1.800

19.395 19.395 Sq.M.

10 2 X( 1.00 $ 0.45 )X 1.00 = 2.900

3 X( 4.00 $ 0.45 )X 0.45 = 2.430

2 X( 0.60 $ 0.45 )X 0.60 = 1.260

2 X( 2.00 $ 0.45 )X 0.30 = 0.540

1 X 7.00 X 0.30 = 2.100

(7 + 2) / 2 X 0.45 X 0.7 = 1.418

10.648 10.648 Sq.M.

11 1 X 30.0 X 2.00 X 0.23 = 13.80

1 X 10.0 X 1.80 X 0.23 = 4.14

1 X 15.0 X 2.70 X 0.23 = 9.32

27.26 27.26 Cu.M.

Random rubble stone masonary in cement sand mortar ( 1 : 6 ) For

superstructure

Cement concrete coping in 1:2:4

Ruled pointing in cement mortar (1:3)

Dry stone pitching (20-23 cm)

Page 138: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Chainage Ground Proposed Height Top width Side slop Base width Cross- Average Lenth Earth work

level T.B.L. of bund U/s D/s section C. Sec. in M in Cum

0 9.60 9.80 0.20 2.00 2.5:1 1.5:1 0.80 0.08 0 0 0

40 9.62 0.18 2.72 0.42 0.25 40 10.10

80 9.58 0.22 2.88 0.54 0.48 40 19.23

120 9.40 0.40 3.60 1.12 0.83 40 33.14

160 8.96 0.84 5.36 3.09 2.11 40 84.22

200 8.70 1.10 6.40 4.62 3.86 40 154.22

240 8.55 1.25 7.00 5.63 5.12 40 204.90

280 8.60 1.20 6.80 5.28 5.45 40 218.10

320 8.62 1.18 6.72 5.14 5.21 40 208.50

360 8.60 1.20 6.80 5.28 5.21 40 208.50

400 8.55 1.25 7.00 5.63 5.45 40 218.10

440 8.62 1.18 6.72 5.14 5.38 40 215.40

480 8.64 1.16 6.64 5.01 5.08 40 203.12

520 8.70 1.10 6.40 4.62 4.82 40 192.62

560 8.69 1.11 6.44 4.68 4.65 40 186.08

600 8.70 1.10 6.40 4.62 4.65 40 186.08

640 8.55 1.25 7.00 5.63 5.12 40 204.90

680 8.45 1.35 7.40 6.35 5.99 40 239.40

720 8.30 1.50 8.00 7.50 6.92 40 276.90

760 8.22 1.58 8.32 8.15 7.83 40 313.06

800 8.25 1.55 8.20 7.91 8.03 40 321.16

840 8.30 1.50 8.00 7.50 7.70 40 308.10

880 8.42 1.38 7.52 6.57 7.03 40 281.38

920 8.49 1.31 7.24 6.05 6.31 40 252.42

960 8.70 1.10 6.40 4.62 5.34 40 213.44

1000 9.00 0.80 5.20 2.88 3.75 40 150.00

1040 9.15 0.65 4.60 2.15 2.51 40 100.50

1080 9.20 0.60 4.40 1.92 2.03 40 81.30

170.96 5084.86

Average base width = 6.30

KHADIN - IV

Earth work chart

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 139: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Series1 0 40 80 120 160 200 240 280 320 360 400 440 480 520 560 600 640 680 720 760 800 840 880 920 960 1000 1040 1080

Series2 9.60 9.62 9.58 9.40 8.96 8.70 8.55 8.60 8.62 8.60 8.55 8.62 8.64 8.70 8.69 8.70 8.55 8.45 8.30 8.22 8.25 8.30 8.42 8.49 8.70 9.00 9.15 9.20

Series3 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80 9.80

Series4 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30 9.30

Series5 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

7

7.5

8

8.5

9

9.5

10

10.5

L-Section of Khadin

Page 140: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

1 Cement Concrete (1:4:8) 8.208 26.27 3.69 7.39 -

2 Copping in C.C. (1:2:4) 19.395 6.05 0.43 0.87 -

3 Massonary in Cement 21.113 22.59 6.33 - 23.22

Mortar ( 1:8 )

4 Pointing in Cement 10.648 0.30 0.03 - -

Mortar ( 1:3 )

5 Dry Stone Pitching 27.255 - - - 29.98

6 R.C.C. Cement Pipe 2 Nos.

TOTAL 55.21 10.49 8.26 53.20

Say Bags 55

Stone

CumITEMS.No.

MATERIAL CONSUMPTION STATEMENT

Quantity

Cum / Sqm

Cement

Begs

Sand

Cum

Aggrigate

Cum

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

Page 141: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

G.L.

DRAWING OF PIPE OUTLET AT THE LOWEST POINT OF KHADIN

0.45

0.45

0.6

1.0

0.45

EARTHEN STRUCTURE

G.L.

2.0M

0.15

G.L.

0.9

0.15

0.451.00 0.60

2.50

0.15

ELEVATION

PLAN

G.L.

0.30

0.075

Page 142: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Name of Watershed :- Jodhpur-XVII Panchayat Samiti :-Baori

2

U/S

SID

E V

IEW

DRAWING OF SIDE WASTE-WEIR FOR LOW COSTING KHADINS

2.0

M

0.6

5.2

2

D/S

30 M

SID

E V

IEW

PLAN

30.00

2.0

M

0.8

Page 143: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Bund

50

Outer Length 50 mtr

Inner Length 45.2 mtr

Outer Width 21 mtr

Inner Width 16.2 mtr 21 16.2

Depth 1.2 mtr

Upper Area 1050

Lower Area 732.24

Estimate of Dug out Pond

Lower Area 732.24

45.2

S. no. Name of work Item no. No Upper

Area

Lower

Area

Depth Qty Unit Rate Amount

1 Layout for Pond 2 132.4 1 1 264.80 Cu.m. 0.70 185.36

2 Excavation of earth in dry or moist and

disposal of excavated material within

initial lead of 50 m and lift 1.5 m

2.1 In hard soil 119(b) 1 1050 732.24 1.2 1069.34 Cu.m. 85.00 90894.24

3 Stone Pitching 15-23 cm thick

including supply of stones

124

1 50 1 0.2 10.00 Cu.m. 670.00 6700.00

97779.60

Add 3% contingency 2933.4

Total 100713.0

Say 100000.0

Page 144: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

DESIGN OF LOOSE STONE CHECK DAM (LSCD)

280001500009

140003 2

185001700015500

20000370003400031000

654

1222

Length of

Head wall

No of Lscd Per Unit Cost Total Cost

7 20000

Page 145: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Head Wall Length = 7 m

Plan Elevation

1.5 7 1.5

0.7

0.3 0.3

0.9 0.3 0.3 1.8

GL 0.3 0.3

0.3

Pit

1.6

S. no. Name of work Item no. No Length Width Height Qty rate amount

ESTIMATE OF LOOSE STONE CHECK DAM (LSCD)

0.6

Earth work Excavation in hard

soil up to 1.5 mt Height and

1

2B 1 7 1.6 0.3 3.4 92.0 309.1

2B 2 1.5 1.6 0.3 1.4 92.0 132.5

1 7 1.6 0.3 3.4

1 7 1.3 0.3 2.7

1 7 1.0 0.3 2.1

1 7 0.7 0.3 1.5

1 1.5 1.6 1.8 4.3

1 1.5 1.6 1.8 4.3

18.3 1040.0 19032.0

19473.6

Add 3% Contingency 584.2

Total 20057.8

Say 20000

2 Dry stone masonry

21B

soil up to 1.5 mt Height and

deposited excavated material lead

op to 150

Page 146: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Head Wall Length = 6 m

Plan Elevation

1.5 6 1.5

0.7

0.3 0.3

0.9 0.3 0.3 1.8

GL 0.3 0.3

0.3

Pit

1.6

S. no. Name of work Item no. No Length Width Height Qty rate amount

ESTIMATE OF LOOSE STONE CHECK DAM (LSCD)

0.6

Earth work Excavation in hard

soil up to 1.5 mt Height and

1

2B 1 6.0 1.6 0.3 2.9 92.0 265.0

2B 2 1.5 1.6 0.3 1.4 92.0 132.5

1 6.0 1.6 0.3 2.9

1 6.0 1.3 0.3 2.3

1 6.0 1.0 0.3 1.8

1 6.0 0.7 0.3 1.3

1 1.5 1.6 1.8 4.3

1 1.5 1.6 1.8 4.3

16.9 1040.0 17596.8

17994.2

Add 3% Contingency 539.8

Total 18534.1

Say 18500

2 Dry stone masonry

21B

soil up to 1.5 mt Height and

deposited excavated material lead

op to 150

Page 147: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Head Wall Length = 5 m

Plan Elevation

1.5 5 1.5

0.7

0.3 0.3

0.9 0.3 0.3 1.8

GL 0.3 0.3

0.3

Pit

1.6

S. no. Name of work Item no. No Length Width Height Qty rate amount

ESTIMATE OF LOOSE STONE CHECK DAM (LSCD)

0.6

Earth work Excavation in hard

soil up to 1.5 mt Height and

1

2B 1 5.0 1.6 0.3 2.4 92.0 220.8

2B 2 1.5 1.6 0.3 1.4 92.0 132.5

1 5.0 1.6 0.3 2.4

1 5.0 1.3 0.3 2.0

1 5.0 1.0 0.3 1.5

1 5.0 0.7 0.3 1.1

1 1.5 1.6 1.8 4.3

1 1.5 1.6 1.8 4.3

15.5 1040.0 16161.6

16514.9

Add 3% Contingency 495.4

Total 17010.3

Say 17000

2 Dry stone masonry

21B

soil up to 1.5 mt Height and

deposited excavated material lead

op to 150

Page 148: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Head Wall Length = 4 m

Plan Elevation

1.5 4 1.5

0.7

0.3 0.3

0.9 0.3 0.3 1.8

GL 0.3 0.3

0.3

Pit

1.6

S. no. Name of work Item no. No Length Width Height Qty rate amount

ESTIMATE OF LOOSE STONE CHECK DAM (LSCD)

0.6

Earth work Excavation in hard

soil up to 1.5 mt Height and

1

2B 1 4.0 1.6 0.3 1.9 92.0 176.6

2B 2 1.5 1.6 0.3 1.4 92.0 132.5

1 4.0 1.6 0.3 1.9

1 4.0 1.3 0.3 1.6

1 4.0 1.0 0.3 1.2

1 4.0 0.7 0.3 0.8

1 1.5 1.6 1.8 4.3

1 1.5 1.6 1.8 4.3

14.2 1040.0 14726.4

15035.5

Add 3% Contingency 451.1

Total 15486.6

Say 15500

2 Dry stone masonry

21B

soil up to 1.5 mt Height and

deposited excavated material lead

op to 150

Page 149: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Head Wall Length = 3 m

Plan Elevation

1.5 3 1.5

0.7

0.3 0.3

0.9 0.3 0.3 1.8

GL 0.3 0.3

0.3

Pit

1.6

S. no. Name of work Item no. No Length Width Height Qty rate amount

ESTIMATE OF LOOSE STONE CHECK DAM (LSCD)

0.6

Earth work Excavation in hard

soil up to 1.5 mt Height and

1

2B 1 3.0 1.6 0.3 1.4 92.0 132.5

2B 2 1.5 1.6 0.3 1.4 92.0 132.5

1 3.0 1.6 0.3 1.4

1 3.0 1.3 0.3 1.2

1 3.0 1.0 0.3 0.9

1 3.0 0.7 0.3 0.6

1 1.5 1.6 1.8 4.3

1 1.5 1.6 1.8 4.3

12.8 1040.0 13291.2

13556.2

Add 3% Contingency 406.7

Total 13962.8

Say 14000

2 Dry stone masonry

21B

soil up to 1.5 mt Height and

deposited excavated material lead

op to 150

Page 150: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. no. Name of work Item no. No X Sec Length Depth Qty Unit Rate Amount

1 Excavation of earth in hard soil dry or

moist and disposal of excavated material

within initial lead of 50 m and lift 1.5 m,

laying in layers of 15 cm dressing and

compaction etc. complete

1.1 In Hard soil 119(b)

1 4.84 18 1 87.08 Cu.m. 85.00 7401.38

2 Stone Pitching 15-23 cm thick including

supply of stones

124

1 1 18 0.2 3.60 Cu.m. 670.00 2412.00

9813.38

Add 3% contingency 294.4

Total 10107.8

Say 10000.0

MODEL ESTIMATE OF NALLAH BUNDING

Page 151: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

CROSS-SECTION OF NALLAH BUNDING

Top width =Based on seepage line check

Slope of seepage line 4:1

0.6 Stone Pitching

2 :1

1.5 :1 US

DS 1.5

0.90.9

2.25 3

0.45 3.6 1.8 0.45

5.85

10.75 m

CS = (Tw+Bw) *Ht

2

CS = 4.8375 Sq.m.

Average Cross section 4.84 Sq.m.

Page 152: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

V-Ditches Area = 10 ha.

DCB Fencing

Name of work Conservation

Measure

Production

Measure

Total Cost

V. Ditch 178600 23000 201600.00

Plantation 0 494600 494600.00

Fencing DCB 0 268100 268100.00

Total 178600 785700 964300.00

Say 9.64 Lakh

Silvi Pasture Development

Abstract of Cost

Page 153: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Estimate for V.Ditch in Pasture

Area Length Width Interval No of row Length

Ha mtr mtr mtr mtr

10 1000 100 6 167 16667

Dhaman require on V-ditch =0.002 kg/m 33 Kg

Spacing 5 mtr

Dhaman require between v-ditches =10 kg/ha 100 Kg

0.6

0.3

S. no. Name of work Item no. No Length Width Height Qty Unit Rate Amount

1 Jungal clearance 107 1 500 50 1 25000 Sqm 1.4 35000

2 Excavation in hard soil or earth

mixed with bajri and kankar ormixed with bajri and kankar or

boulder dry or moist & disposal of

excavated material within initial lead

of 30 m and lift of 1.5 m including

dressing etc. complete. 2(B) 0.5 16667 0.60 0.3 1500.00 Cum 92 138000.0

Kg

3 Making of balls of grass

seed(1:1:2:2) 1 grass seed :1 FYM : 2

sand : 2 clay 3/1/9 forest 133 133.00

Per 6 kg

material 17 376.8

4 Sowing of balls of grass seed by

dibbling method at 30 cm spacing 3/2/9 forest 133 133

Per 6 kg

material 109 2416.2

5 Cost of seed CAZARI Jodhpur 133 Kg 150 19950

195743.0Add 3% contingency 5872.3

Conservation Measure 178600.0 Total 201615.3

Production Measure 23000.0 Say 201600.0

Page 154: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Plant to pant Spacing 4 m 24 Sqm No of plant 4166.67

Row to row Spacing 6 m Gap filling 20% 833.3333

Available Area 10 Ha Total no of Plants 5000

Item no

Year No./Year

1 Digging of pit( kankar boulder soil) 112 ('C) 1 0.45 0.45 0.45 1 No 13.4 13.40 67000

2Cost of Plant As per

forest 1 No. 5 5.00 25000

3 Planting of plant 113(A) 1 No. 3.6 3.60 18000

4 Making thavla 117(A) 2 1 1 No. 2.4 4.80 24000

5 Weeding & Hoeing 116 3 1 3 No. 1.2 3.60 18000

6Insecticide treatment Market

rate3

0.03 ml 0.009 Ltr 305 2.75 13725

7 Watering of plants 115 3 5 15 no 1.8 27.00 135000

8 Transportation of water 5 Km 108 3 5 225 /1000Ltr 37.4 8.42 42075

9 Watch & ward Minimum

wages3

12 34 Month 3240 22 110160

10

Transportation of plants from

nursery to planting site

LS

1

1 1 1 1.00 5000

11 Pruning of plants forest bsr 1 1 1.00 / plants 0.89 0.89 4450

12

Protection of plants from frost / loo

using grass or other locally available

material by making jhonpa of 0.6 m

dia. Of plant height and covering the

1 1

1.00 / plants 3.56 3.56 17800

TOTAL 480210

Contingency 3% 14406

Grand total 494616

Say 494600.0

AmountUnit

Model estimate of Plantation Work in Pasture land

QtyDescription

Total

S.No Length Width Height (Amount for

10 ha.)

Rate

Page 155: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

0.9 m

Area 10 Ha

Length 1580 mtr

1.2 m

1.5 m 0.3

1.5 m

1.2 m

Estimate of Ditch Cum Bund Fencing

0.9 m

S. no. Name of work Item no. No Length Width Hight Qty Unit Rate Amount

1 Layout for DCB 2 1580 1 1 3160.00 Cu.m. 0.70 2212.00

2 Excavation of earth in dry or moist

and disposal of excavated material

within initial lead of 50 m and lift 1.5

m

2.1 In hard soil 50% 2(2) 1 790 1.2 1.2 1137.60 Cu.m. 92.00 104659.20

2.2 In Disintegrated rock 50% 2(3) 1 790 1.2 1.2 1137.60 Cu.m. 134.00 152438.40

3 Sowing of seed on ridge 114 1 790 1 1 790.00 Rm 0.60 474.00

Cost of seeds LS 5.00 Kg 50.00 250.00

260033.60

Add 3% contingency 7801.0

Total 268084.6

Say 268100.0

Page 156: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

S. No. Particulars Quantity Unit Rate (Rs) Amount (Rs)

1 Wooden Ballies (3 m long) 20 No. 70 1400

2 Wooden Ballies (4 m long) 25 No. 80 2000

3 Shade mats for covering the roof 125 Sq. m. 40 5000

4 Binding wire for tying wooden ballies and mats 20 Kg 45 900

5 Labour charges for erection of shades 15 No. 135 2025

6 Shovels, spades, crowbars, iron baskets LS 2000

7 Weighing scale (100 Kg capacity) 1 No. 2500 2500

8 Cow dung 10 Ton 1100 11000

9 Worms @ 3 kg per ton 30 Kg 100 3000

10 Formation of vermi-bed with agro-waste, cow-

dung and worms

20 bed 300 6000

11 Miscellaneous 175

Total Cost 36000

No. of Units 7

Cost for 7 Units 252000

Category No. of Units Contributio

n

Cost from

project

Cost from project

(per unit)

Gen, OBC 5 72000 108000

SC ST 2 14400 57600

Total 7 86400 165600 23657.14286

MODEL ESTIMATE FOR A VERMI-COMPOST UNIT

Page 157: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Returns from Vermi-compost units

Benefits

1 Sale of vermi-compost 70 Ton 4000 280000

2 Sale of worms @ 5 kg per ton 350 Kg 50 17500

Total 297500

Net benefit 297500 - 252000 45500

Page 158: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

CHAPTER - 8

PPPPPPPPRRRRRRRROOOOOOOOJJJJJJJJEEEEEEEECCCCCCCCTTTTTTTT

OOOOOOOOUUUUUUUUTTTTTTTTCCCCCCCCOOOOOOOOMMMMMMMMEEEEEEEESSSSSSSS

Page 159: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

1. Project Outcome :

By the end of the project, in the project area, it is expected that the water level in the tube-wells increases

considerably and sufficient water for man and productivity should be increased after the completion of the project.

Few parameters which are expected to be increased after the completion of completion as the project are as follow :

S. No. Parameters Before Execution of

Project

Expected Increase after the

Completion of the Project

1 Availability of water

a. Average Water Table in the

Wells

650 ft 300-350 ft.

b. Available Water in the Wells/Tube Wells Wells/Tube Wells/Ponds

2. Agriculture/ Horticulture

a. Total Sowing Area

b. (Net) Sown Area (ha)

c. Production of Major Crops:

• Gowar

• Bajara

• Moth

9-12 quintal/ ha.

10-12 quintal/ ha.

9-12 quintal/ ha.

11-18 quintal/ ha.

12-18 quintal/ ha.

12-20 quintal/ ha.

Page 160: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

d. Production of Raida 600-700 quintal

800-1000 quintal

e. Average Production of

Horticulture Plants

50-100 quintal

350-500 quintal

(Different types of fruits plants

Mango, Guava, Ber, Papaya, etc)

3. Live Stock

a. Milk Production 3-7 kg/ animal 7-12 kg/ animal

b. Animal Diseases By regular camps, the various diseases will be reduced

4. Livelihood

a. Average income of family by

introduction of other micro

enterprises

Rs.2500-3000

per month

Rs.4000-5000

per month

b. SHG Groups 10 60 The various homogenous groups

will be constituted and the training of

different activities will be given,

especially for land less families.

Page 161: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

During the project period (5-7 years), the various activities will be done. The natural resource management

activities will be done in between the project phase. The proposed NRM works in arable, non arable land and

drainage line treatment will increase the water table, production of agriculture/horticulture crops. Similarly the

livestock will increase the milk production. the year wise various outcomes of the project are as follows :

S.

No.

Activity Unit Before

Project

During the Project Period

I Yr II Yr III Yr IV Yr V Yr VI Yr VII Yr

1. Engineering Structure

a.

Contour Bund, CVH,

Restoration of Old

structures, Gully

Control Structure

Hect. Nil 1000 2000 700

b. Earth Bunds, WHS,

Anicut

No. Nil

2. Increase of Agriculture Production due to construction of above Engineering Structure

a. Rabi Season (Main

Crops)

• Wheat

• Mustard

Qtl/ ha 29

12

29

12

29

12

35

14

37

15

39

16

40

18

40-50

18-20

Page 162: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

b. Kharif Season (Main

Crops)

• Bajra

• Guar

Qtl/ ha 12.5

5.50

12.5

5.5

12.5

5.5

14

6.0

15

8

18

9

20

10

20-25

10-12

3. Increase of Area of Agriculture Production of Engineering Structure

a. Rain fed Area Ha. 1350 3% 5% 7% 8% 10%

b. Irrigated Area Ha. 385 3% 5% 7% 8% 10%

c. Vegetable Area Ha. 20 3% 5% 7% 8% 10%

d. Pasture Development Ha. Nil 10 20

4. Water Table Depth

• May m. 190 160 150 140 130 120

• September m. 170 155 145 135 125 115

• December

m. 180 158 148 138 128 118

5. Availability of

Drinking Water

Dec. Dec. Dec. Dec. Jan. Jan. March May

6. Survival of Plants

• Horticulture

Plants

Nos. 20 30 500 2500 5000 8000 10000 10000

Page 163: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

• Forestry Plants Nos. 100 50 450 1000 2500 4000 6000 8000

7. Milk Production per animal

• Cow Kg. 4.5 4.5 4.5 5.5 5.5 6 7 7

• Buffalo Kg. 7.5 7.5 7.5 8 8 8 9 9

• Goat Kg. 2.00 2.0 2.0 2.0 2.5 3 3 3

8. Control on Migration No. Nil 10% 30% 40% 70% 80%

Critical Assumption

No severe droughts/ unexpected floods/ natural disasters

Adequate funds are allocated for the same and released on time.

There is no significant pest/ disease attack, and if so, then it will have been contained before irreversible damage is

done.

Adverse market conditions do not persist long.

Sound macro-economic and growth conditions continue and the benefits are widely distributed particularly in the

rural areas.

Facilitating agencies and resource providers have the required competent staff so that timely and appropriate

technical advice and services are provided to farmers whenever required.

Page 164: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

The Capacity Building Plan is implemented, monitored and modified to address evolving needs and feedback from

participants.

The execution of the Women’s Empowerment Pedagogy is regularly monitored by the District and State level

Implementing Agencies

Means of Verification of indicators

Baseline surveys like household income ,expenditure, health and nutrition etc at the beginning, mid-term and end of

the project period

Annual participatory assessment by communities during project period.

Regular project monitoring reports prepared by project monitoring teams/ agencies.

Membership and other Records, Minutes of Meetings maintained by the SHGs, WCs/ Individual beneficiaries/project-

related village and local bodies/PRIs.

External review missions

Data maintained by Government department (Revenue, Agriculture, Groundwater, Irrigation, Animal Husbandry

Page 165: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Project outcomes

Watershed - Jodhpur XVII

(a) Natural resource management

1 Erosion

At beginning After treatment At beginningAfter treatment At beginningAfter treatment

Area ha 1114 512 Area ha 32 22 Area ha 17 6

Sheet erosion Rill erosion Gully erosion

0

200

400

600

800

1000

1200

At beginning After treatment

Sheet erosion

Area ha

Area ha

0

5

10

15

20

25

30

35

At beginning After treatment

Rill erosion

Area ha

Area ha

02468

1012141618

At beginning After treatment

Gully erosion

Area ha

Area ha

Page 166: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Project outcomes

(b) Productivity Watershed - Jodhpur XVII

At

beginning

After

treatment

At

beginnin

After

treatment

At

beginnin

After

treatment

At

beginning

After

treatment

At

beginning

After

treatment

kg/ha 1800 2100 350 520 400 560 400 600 180 300

Moth sesamumBajara Goar Mung

2000

2500

kg/ha

Bajara At beginning

Bajara After treatment

0

500

1000

1500

2000

At beg

innin

g

Aft

er

treatm

ent

At beg

innin

g

Aft

er

treatm

ent

At beg

innin

g

Aft

er

treatm

ent

At beg

innin

g

Aft

er

treatm

ent

At beg

innin

g

Aft

er

treatm

ent

Goar At beginning

Goar After treatment

Mung At beginning

Mung After treatment

Moth At beginning

Moth After treatment

sesamum At beginning

sesamum After treatment

Page 167: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Project outcomes

(b) Productivity Watershed - Jodhpur XVII

At

beginning

After

treatment

At

beginning

After

treatment

At

beginning

After

treatment

At

beginning

After

treatment

kg/ha 1900 2800 24000 28000 1200 1500 165 205

Wheat CuminOnion Mustard

25000

30000

kg/ha

Wheat At beginning

Wheat After treatment

0

5000

10000

15000

20000

At beg

innin

g

Aft

er

treatm

ent

At beg

innin

g

Aft

er

treatm

ent

At beg

innin

g

Aft

er

treatm

ent

At beg

innin

g

Aft

er

treatm

ent

Wheat After treatment

Onion At beginning

Onion After treatment

Mustard At beginning

Mustard After treatment

Cumin At beginning

Cumin After treatment

Page 168: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Project outcomes

(C) Milk Production (C) Average Income Per FamilyWatershed - Jodhpur XVII

At beginning After treatment At beginning After treatment

Ltr./ Year 13200 15600 Rs./ Month 2400 5000

IncomeMilk

Ltr./ Year

5000

Rs./ Month

12000

12500

13000

13500

14000

14500

15000

15500

16000

At beginning After treatment

Ltr./ Year

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

At beginning After treatment

Income

Rs./ Month

Page 169: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action

Jodhpur XVII

CHAPTER - 9

AAAAAAAANNNNNNNNNNNNNNNNEEEEEEEEXXXXXXXXUUUUUUUURRRRRRRREEEEEEEE

Page 170: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action
Page 171: DETAILED PROJECT REPORT - Rajasthanwater.rajasthan.gov.in/content/dam/water/watershed...4.4.3.9 MASONRY CHECK DAM CHAPTER - 5 Activity wise Abstract of Cost. CHAPTER - 6 Annual Action