Desing and Selectivity LV_GE

Embed Size (px)

Citation preview

  • 8/17/2019 Desing and Selectivity LV_GE

    1/105

     

    Guide to Low VoltageSystem

    Design and Selectivity

  • 8/17/2019 Desing and Selectivity LV_GE

    2/105

     

  • 8/17/2019 Desing and Selectivity LV_GE

    3/105

     

  • 8/17/2019 Desing and Selectivity LV_GE

    4/105

     

    UnaffectedOpens

    imagination at work

  • 8/17/2019 Desing and Selectivity LV_GE

    5/105

    Contents

    Foreword. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . .1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2 National Electric Code

    Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    .3 Selective System Design ConsiderationsGround Fault Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . .4MCCB Layer Limitations - Riser / Feed Through Lug Panels . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . . . .5Automatic Transfer Switch (ATS) Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .7Switchboard Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . .7

    Transformer / Current Limiting Reactor Applications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . .7

    Design Tips Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . . . . . . . . . . .7 Selectivity for Existing Systems . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8 Arc Flash Considerations . . . . . . . .

    . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8Selective Low Voltage Circuit Breaker Pairings Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . . . . . . .9 Popular GE Selective Circuit Breaker Pairings - Summary TableGE Circuit Breaker / Equipment Combinations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . . . . . .10 AppendixSelective Time Current Curve Templates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . .1315 kVA with FB Primary & TEY Secondary Mains . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . . . . . . . . . . . . . .1430 kVA with FB Primary & TEY Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . . .16

    30 kVA with FG Primary & FG Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . .18

    45 kVA with FG Primary & FG Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . .20

    75 kVA with FG Primary & FG Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . .22

    112.5 kVA with FG Primary & FG Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . . .24112.5 kVA with FG Primary & S7 Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . .26150 kVA with FG Primary & FG Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . .28

    150 kVA with S7 Primary & S7 Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . .30

    225 kVA with FG Primary & S7 Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . .32

    300 kVA with S7 Primary & S7 Secondary Mains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . .34

    Typical GE Dry Type, 480 –  120/208V Transformer Impedances . . . . . . . . . . . . . . . . . . . . . . . . .

    . . . . . . .36Glossary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  • 8/17/2019 Desing and Selectivity LV_GE

    6/105

    . . . . . . . . . . . . . . .37

    Information provided herein may be subject to change without notice. Products in this publication are designed and manufactured in accordance

    with applicable industry standards. Proper application and use o f these products is the responsibility of GE's customers or t heir agents inaccordance with the standards to which they were built . GE makes no warranty or guarantee, expressed or implied, beyond those offered in our

    standard Terms and Conditions, in effect at the time of sale. Any questions about the information provided in this document s hould be referred to

    GE.

  • 8/17/2019 Desing and Selectivity LV_GE

    7/105

    Foreword

    GE's first application publication on instantaneous selectivity, GE Overcurrent InstantaneousSelectivity Tables (DET-537, available in the Publications Library at www.geelectrical.com) lists GE low voltage circuit breakers and the short circuit current to which they are selective.

    Since that was published, product innovation, rigorous selectivity testing and real-world

    experience with selectivity requirements have improved GE's selectivity solutions.

    The 2008 National Electric Code® (NEC) included some refinement and additions to theoriginally published “Coordination” requirements for selectivity. While there is still nouniform interpretation of these requirements, many Authorities Having Jurisdiction (AHJs) inthe United States are enforcing instantaneous selectivity requirements for “Emergency” and“Required and Standby” systems. It can be expected that, once an AHJ has accepted these

    requirements, they will accept later versions of the NEC articles, including NEC Article 708  –  Critical Operations Power Systems.

    Following the introduction of coordination requirements in Articles 700 and 701 in the 2005

    edition of the NEC, “caution” was the operative word as users, designers and suppliers

    adjusted their traditional design and procurement patterns to meet the new NEC selectivityrequirements. Because the regulations are interpreted differently by different AHJs, allinvolved responded to a variety of interpreted requirements. Today, GE will confidently

     provide design assistance and selective solution quotations for the majority of customerapplications, regardless of the local AHJ interpretations.

    This publication does not replace our original selectivity publication, but provides supplemental

    information for those involved in the layout, design and quotation processes. The data inDET-537 continues to be the most comprehensive representation of selective circuit breaker

     pairings that GE offers. In this publication, we convey the essentials of selective systemapplications in a more easily used context. When using DET-537, make sure you are using thelatest version available. The most current version can be found on GE's website.

    http://www.geelectrical.com/http://www.geelectrical.com/http://www.geelectrical.com/http://www.geelectrical.com/

  • 8/17/2019 Desing and Selectivity LV_GE

    8/105

    IntroductionWhat is selectivity?

    The electrical design industry has historically required electrical system circuit breakerselections and settings be validated with a short circuit and coordination study performed by alicensed engineer. These studies assure that circuit breakers are capable of interrupting the

    available current and would operate “selectively.” Traditionally, “selectivity” in  a low voltageelectrical system meant that the long time and short time portions of time-current curves (TCCs)

    would be selective, i.e. the circuit breaker closest to the fault would trip first, maximizing theamount of the electrical distribution system left in service. In most cases, the circuit breaker

    instantaneous overcurrent (IOC) TCCs would not be selective “on paper,” as they typicallyoverlap.

    In Figure 1A, there is no “instantaneous selectivity” apparent on the TCC, as the instantaneous portion (below 0.1 seconds) of the curves show all three breaker characteristics overlapping.The long time and short time characteristics (above 0.1 seconds) do not overlap and are

    therefore selective. In Figure 1B, the 1600 amp AKR and Spectra F200 circuit breakers areselective, as the instantaneous function of the AKR is not used, so there is no overlap of these

    two characteristics.

    Traditionally, selectivity between molded case circuit breakers (MCCBs) and insulated casecircuit breakers (ICCBs) was considered effective, even if there was an overlap of TCCs in theinstantaneous region. The most prevalent type of fault, the line to ground arcing fault, oftenlimits the fault current magnitude enough that the upstream circuit breaker IOC function does

    not operate. If the fault is removed promptly, the likelihood of it escalating into a multi-phase, bolted type fault is very low. As a result, for a large majority of faults, the traditional long time,short time selectivity has been sufficient to produce selective operation of circuit breakers.

    The 2005 and 2008 NEC extend the selectivity requirement to all possible fault types andmagnitudes for certain critical electrical circuits, i.e., those typically fed from automatictransfer switches (ATS). These circuits and requirements are those discussed in the following

     NEC articles:Article 700: Emergency Systems (Legally Required), 700.28 Coordination

    Article 701: Legally Required Standby Systems, 701.17 CoordinationArticle 708: Critical Operations Power Systems, 708.54 Coordination

    CURRENT IN AMPERES CURRENT IN AMPERES

  • 8/17/2019 Desing and Selectivity LV_GE

    9/105

     

    10000.100.011001011Spectra F 200AA P TEY

    TCCs are “selective” TCCs are not “selective” 1K 10K 100KSK 1000ATIME IN SECONDS1 10 100 1K 10K 100K10000.100.01100101Spectra F 200A20A 1P TEY

    TCCs are “selective” 000/1600A AKRTIME IN SECONDS

  • 8/17/2019 Desing and Selectivity LV_GE

    10/105

    Curve 5.tcc Ref. Voltage: 480 Current Scale x10^0 Curve 5.tcc Ref. Voltage: 480 Current Scale x10^0

    Figure 1A Figure 1B

  • 8/17/2019 Desing and Selectivity LV_GE

    11/105

    These requirements state that overcurrent protective devices (OCPD) must be “fully selective.”In other words, given the range of available interrupting currents, any given pair of overcurrent

    devices covered by the NEC Articles referenced above must behave in a coordinated fashion asdefined in NEC Article 100:

    “Coordination (Selective). Localization of an overcurrent condition to restrictoutages to the circuit or equipment affected, accomplished by the choice ofovercurrent protective devices and their r atings or settings.” 

    The NEC requirements are desirable design goals, given the adverse consequences of largerthan necessary power outages within critical circuits. However, there are other design

    considerations that these requirements seem to preclude, i.e., arc flash and the specifics of phase and ground fault overcurrent coordination. The ability of fully selective designs to provide sufficient protection to such important, sensitive equipment as generators or automatic

    transfer switches may be affected.

    This publication uses the information on instantaneously selective breaker pairings contained

    in DET-537 as a base, and goes on to discuss specific tactics for developing fully selectiveelectrical distribution designs. Though instantaneous selectivity is possible in many cases, it is

    not always easily accomplished with the considerations mentioned above. It has long been theresponsibility of the licensed engineer of record to assess all performance requirements and

     produce a balanced, practical design.

    National Electric Code (NEC) Requirements

    The 2008 NEC Articles 700.27, 701.18 and 708.54 requirements for Coordination say:

    “... overcurrent devices shall be selectively coordinated with all supply side overcurrent protective devices.” 

    This wording does not exempt ground fault protection from selectivity, nor does it exempt

    selectivity with the normal side supply sources. Even though this requirement is found in theSpecial Conditions chapter of the NEC dealing with Emergency Systems, Legally Required

    Systems and Critical Operations Power Systems (COPS), it states the emergency overcurrent

     protective devices must be selectively coordinated with all supply side overcurrent

     protective devices. This terminology implies that selectivity with both normal and emergencysupply sources is required for both phase and ground fault OCPDs. (Note: The local AHJ has

    the final word on interpretation of the NEC and other applicable code language. It isimportant to use their interpretation when designing and quoting selective systems.) Fullselective coordination in systems with ground fault protection can be difficult and is beyondthe intended scope of this publication.

    To date, a large variety of interpretations of the NEC requirements have been made. Numerous

    state and local AHJs have excluded these “Coordination” requirements from their enforcementcodes, or have modified them. At the time this publication was written, the most mentionedalternative to the NEC “full selectivity” requirements is the “0.1 second rule.” This definition

    of selectivity has been adopted by some AHJs, including, most notably, Florida's Agency forHealth Care Administration (AHCA). This selectivity requirement preceded the 2005 NEC

    requirements by decades.

    The AHCA requirements are broader than those in the NEC as they apply to the entire facility,not just critical circuits. Therefore, faults on non-critical portions of the system will not result in

  • 8/17/2019 Desing and Selectivity LV_GE

    12/105

    an unwanted shutdown of critical circuits because of non-selective breaker operations. Thisstandard is often criticized because it only requires selectivity down to 0.1 seconds. However, it

    represents the long-standing design practices employed be electrical systems designers. TheAHCA requirements, which allow the overlap of OCPD IOC functions, result in reducedclearing times and associated arc flash hazards and require selective coordination for the entirefacility.

    The AHCA 0.1 second allowance does have sound engineering basis. It is probable that most

    system faults are line to ground arcing faults on branch circuits. These faults will probably fall beneath the IOC threshold of the larger circuit breakers above the branch circuit breaker

    nearest the fault. Ground faults in parts of a system with high short circuit currents may bequite high in magnitude. Sensitive ground fault protection is often sufficient to sense and cleararcing ground faults well below IOC levels of upstream devices. Two levels of selective

    ground fault protection have been required in certain hospital systems by NEC Article 517 formany years.

    It is important to note that “full selectivity” is often facilitated by increasing trip time delaysand increasing pickup thresholds in upper tier OCPDs. Allowing instantaneous protection to be

    applied throughout the system improves protection and decreases arc flash hazard. The impactof designing for full selectivity in systems that require “live work” should be studied andunderstood so optimized design decisions can be made and hazards identified.

  • 8/17/2019 Desing and Selectivity LV_GE

    13/105

    The first words of NEC, Article 90.1, Purpose, are: “(A) Practical Safeguarding. The purpose

    of this Code is the practical safeguarding of persons and property from hazards arising from

    the use of electricity.” Historically, the NEC started by establishing protection requirements forlow voltage loads, cables, transformers, etc. This has always been and continues to be the

    Code's first priority. While Articles requiring “fully selective” systems are consistent with the“Practical Safeguarding” requirements, these Articles do not take precedence over competing

     protection and design needs.

    In the absence of specific language in NEC Articles 700, 701 and 708 for coordination,interpretations of the NEC code vary significantly. Some interpretations require full selectivity

    through the critical circuits, to both the normal and emergency supplies. Others require criticalcircuit breakers to be selective to the automatic transfer switch (ATS) using the normal supply

    short circuit current, then continue the selectivity only to the emergency supply above the ATSusing the emergency source short circuit current. A third popular interpretation requires

    selectivity through critical circuits to the emergency supply only. (Please note that the shortcircuit current from the emergency source is often much less in magnitude than the normalsupply.) Where this is the case, designers have more selective breaker pair choices and the

     potential ability to reduce the size and cost of a selective system solution.

    Some AHJ's and the State of Massachusetts require selectivity of critical circuits to beaddressed, but leaves the extent of the requirement to the discretion of the licensed professionalengineer of record. This allows the engineer to balance other design requirements, such as arcflash, with selectivity needs.

    When designing a system for selectivity per NEC requirements, it is important to knowexactly how the AHJ has defined selectivity requirements and how they are verified and

    enforced.

    Selective System Design Considerations

    Ground Fault Protection

    Some selectivity requirement interpretations of the Code exclude ground fault

     protection because it is not specifically addressed in Article 700, 701 or 708. Article 100

    defines “Coordination” as: 

    “Localization of an overcurrent condition to restrict outages to the circuit orequipment affected, accomplished by the choice of overcurrent protective devicesand their ratings or settings.” 

    “Overcurrent” is defined as: 

    “Any current in excess of the rated current of equipment or the ampacity of aconductor. It may result from overload, short circuit, or ground fault.” 

    Even though ground fault selectivity is not expressly mentioned in Articles 700, 701, and 708,it is implied through the overriding NEC definitions of “selectivity” and “overcurrent.” 

    Traditionally, the shape of a ground fault protection characteristic applied on low voltagecircuit breakers would be called a “definite time” or “L-shaped” characteristic. (Note: Often,ground fault relays or ground fault protection integrated with circuit breaker trips will offer a

    way to cut off the bottom left corner of the “L.” This cut -off corner is usually in the shape ofan I2t=K diagonal line on the TCC.)

  • 8/17/2019 Desing and Selectivity LV_GE

    14/105

    Typical GF protection characteristics are illustrated in the low voltage circuit breaker phase andground protection characteristics below. Their dissimilar shapes make selective coordination

    difficult at best. The NEC (Article 230.95) requires thatground fault protection be applied on solidly grounded 480 volt service entrances, 1000amperes and larger.

    Hospitals and other healthcare facilities with critical care or life support equipment arerequired to have a second level of ground fault protection beneath the service entrance (NEC

    Article 517.17(B)). The NEC-stipulated maximum ground fault pick-up setting is 1200amperes and clearing time is limited by a requirement that a 3000A fault must be cleared in

    one second or less (Article 230.95(A)). Emergency system supply sources are exempted fromthese requirements.

  • 8/17/2019 Desing and Selectivity LV_GE

    15/105

    Figure 2A is a one line diagram with two levels of ground fault protection as required by NECArticle 517. Figure 2B diagrams the selective device settings for this one-line diagram. Ground

    fault relay settings for the 4000A main and 1200A branch feeder are selective and at themaximum allowed by the NEC. The next device below the 1200A branch is a 250A OCPD.

     Note that there is significant overlap between the ground fault relays and the 250A deviceTCCs.

    Traditional system designs would size the 250A OCPD to 600A or possibly 800A, making this

    non-selective situation worse. In this and many similar situations involving phase and groundfault protection, this system would not be fully selective for ground faults, as an upstreamOCPD could trip sooner than the downstream OCPD.

     MCCB Layer Limitations - Riser / Feed Through Lug PanelsSome traditional electrical system designs have utilized a “waterfall” of electrical distribution

     panels of declining ampacities, i.e., a series of progressively smaller electrical distribution panels connected to larger upstream panels. This concept is popular because it allows the size

    and cost of the distribution panels and feeder cables to be reduced further from the serviceentrance point. While this has been a satisfactory practice when long time and short timeselectivity is considered, the practice increases the difficulty of achieving “fully selective”solutions.

    For “fully selective” designs, it is desirable to limit the number of selective circuit breakerlayers as there are a limited number of selective molded case circuit breaker (MCCB) pairingsavailable. If you consult GE's (or other manufacturers') circuit breaker instantaneous selectivitytables, you will usually find three or, in some circumstances, four layers of molded case circuit

     breakers that can be made fully selective.

    With a limited number of fully selective MCCB layers in mind, the best electrical distribution

    design strategy is to limit the number of selective layers by utilizing feed-through lugs or riser panels of the same ampacity when sub-panels are required. When feeder cables and panels areall the same ampacity, only one layer of protection is required to protect them.

    In doing so, the tradeoff is the elimination of a local main circuit breaker. Some designs willutilize a main disconnect at each panel to allow local isolation of a panel. Care must be

    exercised if a molded case switch (MCS) is used as a main disconnect. The MCS will have anIOC override in the switch to protect it from damage resulting from high magnitude fault

    currents. This instantaneous override must be considered as part of the selectively coordinatedsystem.

    CURRENT IN AMPERES

  • 8/17/2019 Desing and Selectivity LV_GE

    16/105

     

    10000.100.0110010

    Swbd feed14000A250 RK5

    120020A TEY20A JMain GF Aer GFTIME IN SECONDS

    4000AGF GF

    1200AGF GF

    20A250A

  • 8/17/2019 Desing and Selectivity LV_GE

    17/105

     

    10 100 1K 10K 100K

  • 8/17/2019 Desing and Selectivity LV_GE

    18/105

     

  • 8/17/2019 Desing and Selectivity LV_GE

    19/105

    1600A.tcc Ref. Voltage: 480 Current Scalex10^0

    Figure 2A Figure 2B

  • 8/17/2019 Desing and Selectivity LV_GE

    20/105

    In Figure 3, the 400 ampere feeder is feeding three downstream panels. With the use of riser panels of the same ampacity, only two layers of selective breakers would be needed. If a

    traditional design strategy of progressively smaller sub-panels had been used, four layers offully selective circuit breakers would be required for the waterfall of declining ampacities.

    Fully Selective

    Circuit Breaker

    Options For

    Systems with 65

    kAI C or less

    SOURCE

    480V

    LVPCB w/o instantaneous

    LEG REQD ATS-1**

    30-300 KVA

    208V

    FG

    LIGHTING PANEL

    FB*

    65 kAIC maximum

    MAIN SWBD

    S7 - ICCB or MCCB req'd to protect 3cy ATS rating

    MLO PANEL

    FG or FB set to protect xfmr

    FG600 600 AT Max

    FG600

    400 AT

    PNL

    PNL

    PNL-2PNL-3

    PNL

    PNL-1

    MLO w/ FTL or Riser panels, all equally rated w/ FB* branch breakers

    * TEY or THQ MCCBs may be used, but only if the maximum AIC

    specified in DET-537 is not exceeded. ** See selectivty templates

    for details of transformer

    Figure 3

  • 8/17/2019 Desing and Selectivity LV_GE

    21/105

     Automatic Transfer Switch (ATS) Protection

    Most ATSs built for use in North America are manufactured in accordance with the UL 1008standard, which references UL 489 for molded case circuit breakers. Furthermore, many ATS

    manufacturers provide application data specifying which MCCBs are appropriate for protecting the ATS ampacity and short circuit withstand ratings. In general, most ATSs aredesigned to be protected with circuit breakers that have integral IOC protection functions.

    In some fully selective protection schemes, it may be necessary to protect an ATS with a lowvoltage power circuit breaker (LVPCB) applied without an IOC function. This may be anon-conforming application, which might require special consideration by the ATSmanufacturer. Some ATS manufacturers have published withstand data on such applications,

    while others are considering future products with higher withstand time ratings in view of thenew selectivity requirements.

    Switchboard Protection

    Switchboards, distribution panels and lighting panels utilize MCCBs, ICCBs or LVPCBs withIOC functions. Therefore, the withstand ratings of these boards and panels are usually based on3 cycles. Similar to the ATS ratings discussed above, LVPCBs without an IOC function should

    not be used to protect a switchboard unless special application consideration has been given toits withstand rating. Some manufacturers have 30 cycle withstand ratings for specificswitchboard designs. If selectivity requirements result in the use of LVPCBs without an IOCfunction or very high IOC settings, it is important to know the withstand ratings of thedownstream equipment.

    GE has introduced UL Listed Spectra Series Switchboards rated for 30 cycles of short circuit

    withstand. Since UL 891 does not have standard requirements for 30 cycle ratings, ANSI 37.20was used to validate the switchboard performance. These switchboard designs enable them towithstand longer duration faults.

    Transformer / Current Limiting Reactor Applications

    Considerations for NEC “fully selective” applications focus on the selective performance ofcircuit breaker pairs in the IOC regions of their TCCs. Usually, higher short circuit currentslimit the options for pairs of selective breakers. Consequently, some electrical designs useone-to-one ratio transformers or current limiting reactors to restrict fault current magnitudes.

    This works well where one of these devices can provide a small amount of series reactance tocontrol the short circuit current to a magnitude where more options for selective breaker

     pairings are available. It may not be effective if two-to-one or three-to-one reductions in shortcircuit current magnitude would be required to make selectivity possible.

    Design Tips Summary

     Note the actual calculated short circuit currents for the critical circuit buses on the bid drawings.Define the circuits and sources that must be made selective, according to the local AHJ

    (preferable), the end customer or the engineer of record.

    Limit service entrance short circuit current to less than 65 kA whenever possible.Limit the “critical” feeder sizes in the service entrance gear to 1200A maximum. Limit the number of MCCB selective layers below an ATS to two if using a 1200A frame

    MCCB to protect the ATS.If ATS or switchboards are protected by an LVPCB without IOC, this equipment will

    require a 30 cycle short circuit withstand rating.

    Utilize main lug only (MLO) with FTL or riser panels to minimize required layers of fullyselective circuit breakers.

  • 8/17/2019 Desing and Selectivity LV_GE

    22/105

    Increasing the frame size of an ICCB or MCCB may increase maximum short circuit currentselectivity with a downstream breaker.

    Small lighting transformer impedance can be used to limit the secondary short circuit current,with resulting full selectivity (secondary main IOC set above the secondary short circuitcurrent).

    For systems with 35kA short circuit current or less:

     –  Utilize an LVPCB without IOC as the service entrance main as the fifth andtop layer of selective protection. –  Utilize PB II as the fourth layer of selective

     protection. –  Utilize S7 MCCB as the third layer of selective protection. –  Utilize FG MCCB as the second layer of selective protection. –  Utilize FB, TEY, THQB MCCBs (depending on short circuit current requirement and

    voltage at this level) as the bottom branch device layer of selective protection system.For systems with 65kA short circuit current or less,

     –  Utilize an LVPCB without IOC as the service entrance main as the fifth andtop layer of selective protection. –  Utilize an LVPCB without IOC as the fourth

    layer of selective protection. –  Utilize S7 MCCB as the third layer of selective protection.

     –  Utilize FG MCCB as the second layer of selective protection. –  Utilize FB, TEY, THQB MCCBs (depending on short circuit current requirement and

    voltage at this level) as the bottom branch device layer of selective protection system.

    Utilize lighting transformer TCC templates to define breaker applications for transformer protection and fully selective protection.Contact GE Specification Engineers in Florida for assistance with 0.1 second selectivity

    requirements.

  • 8/17/2019 Desing and Selectivity LV_GE

    23/105

    Selectivity for Existing Systems

    Several projects have been reviewed where NEC requirements for selectivity on criticalcircuits have been stipulated for add-on systems within pre-existing power distributionsystems. Interpretations of requirements for these situations have varied significantly.

    Assuming that the critical circuits in the original system were designed to the “traditional”selective coordination requirements, adding new critical circuits under the existing system

    would probably result in a non-selective system. Under fault conditions in the new portion ofthe circuit, the upstream, pre-existing breakers would probably be non-selective, resulting in a

     potential shutdown of the entire new system for some faults. Where devices with instantaneous

    trips from different manufacturers are mixed, it is unlikely that there is enough data todetermine the selectivity capability between them. The one application

    exception to this would be the addition of a new sub-system under an ANSI circuit breakerthat was applied without an IOC function or a circuit breaker with an IOC threshold largerthan the AIC.

    In some cases, a variance from the Code requirement has been requested and granted based onconsiderations of the difficulty in analyzing or achieving selectivity for systems involving a

    mix of manufacturers. If absolute adherence to the new NEC requirements for add-on systemsis required, this will probably result in costly replacement of existing circuit breakers and

     possibly equipment. Often, fully selective circuit breaker pairings and associated equipmentmay be larger and more expensive than breakers and equipment designed around traditionalselectivity definitions. Therefore, an expansion of the space allocated to original equipment

    may be required.

    Arc Flash Considerations

    At the core of fully selective designs based on NEC Coordination (fully selective) requirements

    is the concept of coordination of circuit breaker OCPD time-current characteristics. Practically,this means that the circuit breaker immediately upstream of the breaker closest to the fault will

     be set (delayed or desensitized) to prevent it from operating until the downstream breaker clearsthe fault.

    Considering that a typical 1500 kVA service entrance and associated power distributionsystem designed for full selectivity may have five layers of coordinated circuit breakers, the

    time delayed response of the service entrance main breaker may be considerable. This timedelay could correspond to high arc flash incident energy and a correspondingly high HazardRisk category classification.

    The Standard for Electrical Safety in the Workplace, NFPA70E, requires that all electricalhazards be identified by qualified personnel before work on electrical equipment is

    undertaken. Usually, this requires assessment of arc flash hazard. Ideally, an Arc Flash Studyof the electrical system should be considered during design so that the consequences of design

    decisions, including those made for selectivity purposes, are understood.

    Increasing OCPD pickup settings, increasing IOC settings and adding time delays to obtainsfully selective design can have a significant impact on available incident energy. For systemslikely to be serviced while energized, these time delays may cause serious risk to personnel.

    High incident energy levels may force the system to be shut down before any work can be

  • 8/17/2019 Desing and Selectivity LV_GE

    24/105

     performed. Additionally, excessive energy levels and time delayed (slow) protective deviceresponse may allow extensive fault related damage, requiring extensive down time and repair.

  • 8/17/2019 Desing and Selectivity LV_GE

    25/105

    THQ 35-60A

    Selective Low Voltage Circuit Breakers Pairing Diagram-P2,3

    4kATHQ 15-30-P2,36kATHQ 15-30A-P114kATEYF 15-30A-P1,2,314kAFE 250A-PTEY 15-30A2,3-PFE 250AFE 250A-P-P14.21,2,32,3

    2,3 100kA10kA65kA

    Maximum Short Drag Rating for CBs Listed Below

    100kA 65kA 200kA 150kA 65kA 200kA 200kA 100kA 65kA 10kA 22kA208VFB 15-100

    FB 15-100A1,2,3-P

    -PFE 25-150A1,2,3

    35.0kA

    100kA 65kA150kA 100kA 65kA200kA 100kA 100kA 14kASF 250A

    2,3-P-P2,3-P 2,3-P430V

    2,310kA 10kA 22kA 22kA 2.5kA 2.5kA 2.5kA 14kA 14kA 65kA65kA 100kA65kA 65kAFrame Range500-3200A2000-800A4000-3000A 2000-800A1200-1000A 600-250A600-150A

    100A 100A 125A 125AFE 250AFE 250A-P-P

     All Other MCCB's 800A and Less2,3 71.3kA2,3 100kA

    -PTEY 15-30A

    1-PSE 150

    2,3 12.8kA1-P 1,2,3-P 1,2,3-P 1-P

    1,2,3-P 1,2,3-P 1-P 1,2,3-PFB 100A 1,2,3-PSE 150A1,2,3-P 1,2,3-P 1,2,3-P800A

    Wave Pro Wave Pro PE111PE11157FG 599SE, SF, SGFBTEY THQ THHQPB2,WP, ENTELLIGUARD

    (w/ INST.)TypeS7 1000/1200A-PTEYF 15-100A

    SK w/MVT orMET 1200A

    2,3-P1,2,3TEYF 15-100A10.8kA-PTHQ 15-100A3-P1,2,3

    FB 100A 1,2,3-PTHQ 100A1,2,3-P 1,2,3-P 1,2,3-P-P27kA14kA21.6kA

    1,2,322kA6kA 10kA 10kA 14kA 22kA65kA100kA15-100A1,2,3-P

    SG w/MVT orMET 600A

    2,3-PSF 250ATEY 70-100A-PFB 15-100A

     All Other MCCB's 400A and Less

  • 8/17/2019 Desing and Selectivity LV_GE

    26/105

    TEY/THQ2,3 40.0kA

    TEY 15-30A28.3kATHQ 100A10.8kA1-P 1,2,3-P-P

    1,2,365kA22kAFG 250-400A-P-P-PTEY 35-60ASE 150TEY 15-100ASE 150-P

    2,3 40kATEY 15-30ATEY 35-60A

    2,3 71.2kA2,3 10.8kA

    1600A2,3-P 1-P1,2,32,3-P 1-P 1,2,3-P1,2,3-P 1-P-P5.4kA

    1,2,3PB2,WP, ENTELLIGUARD 3200-5000A14kA14kAPB2,WP, ENTELLIGUARD(w/ INST.)FG 250-600(WITHOUT INST.)-P-PTEY 35-60ATEYF 15-100ASF 250TEY 35-60ATEY 35-60A2,3

    2,3 25kA67.4kA-P

    1,2,3100kA14kA10kA 10kA57 1000/1200AFG 250-600A2,3-P 3-P

    3-PTHQ 15-30ATEY 70-100ATEY 35-60A-P-P-P27kA2,3

    1,2,32,365kAFG 600ATHQ 15-30ATEY 70-100ATEYF 15-100A

    1-P 1-P

    1-P44.0kA2000A-P-P

    1,2,31,2,314kA4kAPB2,WP, ENTELLIGUARD

    (w/ INST.)FG 400A-PTHQ 35-60ATEYF 15-100A2,32,3-P 1-P44.0kA-P

    1,2,314kA100kAFG 250A-PTHQ 35-60A

    2,3 44.0kA

    THQ 70-100A

    -P1,2,32.5kA

    Figure 4

  • 8/17/2019 Desing and Selectivity LV_GE

    27/105

    Maximum AIC Ratings for Popular, Fully Selective Circuit Breaker Pairs

    Instantaneous selectivity AIC values in these tables are for 277/480V and 120/208V ratings.THQB breakers listed are rated for  120/208V. SF, SE, FB, TEY and THQB breakers will

     probably not be selective with any breakers applied downstream from them.

  • 8/17/2019 Desing and Selectivity LV_GE

    28/105

     

    TCC

    Table 1A

    Selectivity to be determined via TCC overlay method using

    specific OCPD settings Selectivity probably not achievable

    Main

    Breaker

    Bra

    nch 

    Brea

    ker

    (ABB) S7H 

    ** Record Plus

    FG

    Spec

    tra 

    SF

    Spect

    ra 

    SE

    Recor

    Plus

    FE

    Recor

    Plus

    FB

    Fra

    me 

    TE

    YF

    No.

    Poles3 3

    3,2 3,2 3,2 3,23,2

    3,23,2,1 3,2,1

    Max

    Sensor 

    or Trip*

    12

    001000

    600 400 250 250

    150

    250

    100 30

    WavePro

    (LSTrip)

    5000 65.0

    65.0

    100.0

    100.0 100.0 100.0

    100.0

    100.0

    100.0 14.0

    4000 65.0 65.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 14.0

    3200 65.0 65.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 14.0

    2000 65.0 65.0 65.0 65.0 65.0 65.0 65.0 65.0 65.0 14.0

    1600 65.0 65.0 65.0 65.0 65.0 65.0 65.0 65.0 65.0 14.0

    800 NIS 65.0 65.0 65.0 65.0 65.0 65.0 14.0

    WavePro(LSI

    Trip)

    5000 31.5

    31.5

    64.7

    64.7 64.7 97.5

    100.0

    100.0

    100.0 14.0

    4000 32.4 32.4 69.0 69.0 69.0 100.0 100.0 100.0 100.0 14.0

    3200 37.437.4

    100.0100.0 100.0 100.0

    100.0100.0

    100.0 14.02000 27.0 27.0 44.0 44.0 44.0 67.4 71.2 100.0 100.0 14.0

    1600 21.6 21.6 25.0 25.0 25.0 40.0 40.0 71.3 100.0 14.0

    800 NIS 11.0 11.0 11.0 13.0 14.2 35.0 14.0

    PowerBreak II

    4000 32.432.4

    69.069.0 69.0 100.0

    100.0100.0

    100.0 14.0

    3000 35.1 35.1 85.0 85.0 85.0 100.0 100.0 100.0 100.0 14.0

    2500 29.3 29.3 54.0 54.0 54.0 81.6 90.0 100.0 100.0 14.0

    2000 27.0 27.0 44.0 44.0 44.0 67.4 73.0 100.0 100.0 14.0

    1600 21.6 21.6 25.0 25.0 25.0 40.0 40.0 71.3 100.0 14.0

    800 11.0 11.0 11.0 13.0 14.2 35.0 14.0

    S7H (ABB) 1200 65.0 65.0 65.0 65.0 65.0 65.0 14.0

    1000 65.0 65.0 65.0 65.0 65.0 65.0 14.0Record PlusFG

    600 TCCTCC

    TCC100.0

    65.0 14.0

    400 TCC TCC TCC TCC 65.0 14.0

    250TCC TCC TCC 65.0 14.0 

    14.0

    Record PlusFE

    250

  • 8/17/2019 Desing and Selectivity LV_GE

    29/105

    * For Record Plus FG & FE and ABB

    S7, maximum IOC is based on sensorsize

     

    ** S7 LTPU is 0.4-1.0 x sensor size

    and does not use rating plugs

  • 8/17/2019 Desing and Selectivity LV_GE

    30/105

    Table 1B

    Main

    Breaker

    Branc

    Break 

    er

    Frame TEY Q-Line THQB

    No. Poles 3,2 1 3,2 1 3,2 1 2 3, 2 3, 2, 1 3 1

    Max

    Sensor orTrip

    100

    100

    60 60

    30 30

    125 100

    60 30

    30

    WavePro(LS

    Trip)

    5000 14.0

    14.0

    14.0 14.0 14.0

    14.0

    22.0 22.0

    22.0 22.0

    22.0

    4000 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    3200 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    2000 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    1600 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    800 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    Wave

    Pro

    (LSITrip)

    5000 14.0

    14.0

    14.0 14.0 14.0

    14.0

    22.0 22.0

    22.0 22.0

    22.0

    4000 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    3200 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    2000 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    1600 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    800 12.8 12.8 12.8 12.8 12.8 12.8 18.1 18.1 18.1 18.1 18.1

    Power BreakII

    4000 14.014.0

    14.0 14.0 14.014.0

    22.0 22.022.0 22.0

    22.0

    3000 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    2500 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    2000 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    1600 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0800 12.8 12.8 12.8 12.8 12.8 12.8 18.1 18.1 18.1 18.1 18.1

    S7H (ABB) 1200 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    1000 14.0 14.0 14.0 14.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    Record PlusFG

    600 6.06.0

    10.0 10.0 14.014.0

    22.0 22.022.0 22.0

    22.0

    400 4.0 4.0 10.0 10.0 14.0 14.0 22.0 22.0 22.0 22.0 22.0

    250 2.5 2.5 2.5 2.5 14.0 14.0 2.5 2.5 10.0 22.0 22.0

    Record PlusFE

    250 TCCTCC

    TCC TCC 10.010.0

    TCC TCC4.0 6.0

    14.0

    Table 1C

    120/240V breaker ratingsFor 120/240V breaker pairs not listed below, use selective values from the

    208 & 480V table above.

    Main

    Breaker

    Bran

    ch 

    Brea

    ker

    Record Plus FG

    Spect

    ra 

    SF

    Spect

    ra 

    SE

    Recor

    Plus

    FB

    No. Poles 3,2 3,2 3,2 3,2 3,2 3,2,1

    Max 600 400 250 250 150 100

  • 8/17/2019 Desing and Selectivity LV_GE

    31/105

    Sensor 

    or Trip

    WavePro(LSI

    Trip)

    5000 130

    130

    130

    130

    130

    100

    4000 130 130 130 130 130 100

    3200 130 130 130 130 130 100

    2000 130 65 65 130 130 65

    1600 130 65 65 130 130 65

    800 TCC 10 10 130 130 65

    Power Break

    II4000 100

    100100

    100100

    100

    3000 100 100 100 100 100 100

    2500 92 92 92 100 100 100

    2000 75 75 75 85 85 85

    1600 42 42 42 72 72 85

    800 TCC 10 10 14 17 32

  • 8/17/2019 Desing and Selectivity LV_GE

    32/105

    Table 2

    GE Circuit Breaker / Equipment Combinations

    Breakers Equipment

    Enclos

    ure

    Mount

    ed

    A-Series II

    PanelboardsA-Series

    II

    Powerpa

    nel

    Spectra

    Powerpan

    els

    Switchboard

    sSwitchgear

    A

    Q

    A

    E

    A

    D

    AV-1,

    2,5

    AV

    -3

    PB

    II

    AKD

    10

    Entellis

    ys

    AKD

    20

    Mai

    n

    WavePro without

    IOC

    WavePro with

    IOC

    EntelliGuard

    without IOC

    EntelliGuard with

    IOC

    EntelliGuard G

    without IOC

    EntelliGuard Gwith IOC

    Power Break II

    ABB S7

    Record Plus FG8/0

    8

    Record Plus FE200

    9

    200

    9

    Feed

    er

    WavePro without

    IOC

    WavePro with

    IOC

    EntelliGuardwithout IOC

    EntelliGuard with

    IOC

    EntelliGuard G

    without IOC

    EntelliGuard G

    with IOC

    Power Break II

    ABB S7 ABB

    Record Plus FG

    Record Plus FE 2009 8/08

    Record Plus FB 3 8/08

    TEY / TEYF 3

    THQ 3

  • 8/17/2019 Desing and Selectivity LV_GE

    33/105

    Appendix

    Selective Time– Current Curve TemplatesThe followed time-current curves were composed with the following objectives:

    1.  Achieve full selectivity (LT, ST and IOC) between each pair of circuit breakersapplied

    2.  Provide required NEC transformer protection3.  Provide recommended ANSI through fault protection of transformers4.  Provide the secondary power panel protection in accordance with its ampacity

    (Note: To be “fully selective,” there must be no overlap of the long time and short timecharacteristics of an upstream and downstream circuit breaker pair. If the IOC function of this

     pair of breakers overlap, then their instantaneous selectivity must be identified as selective in

    the manufacturer's instantaneous overcurrent selectivity application literature.)

    While it may be desirable to have the primary and secondary main circuit breakers selectivewith one another, it is not usual when applying MCCBs to protect transformers. In the 2008

     NEC, a specific exception was added to exempt selectivity requirements from the primary and

    secondary mains. The branch circuit breakers shown are the largest possible breakers and tripsthat will be fully selective with both the upstream primary and secondary main transformercircuit breakers. If selectivity between the branch breakers and the upstream secondary main isnot apparent because of IOC TCC overlap, the application is fully selective based on the

    tabular pairing cited in DET-537, GE Overcurrent Device Instantaneous Selectivity Tables.

    One other item of note is that the maximum AIC values shown in DET-537 are symmetrical

    values. All analysis and testing done to validate these numbers were done with the appropriatestandard based X/R value and corresponding asymmetrical offset. The equivalent symmetricalvalue was placed in the tables. It has long been standard practice to terminate the IOC functionon a TCC at the maximum asymmetrical value of fault current, as IOC functions are oftenresponsive to the peak value of current.

    The partial system templates diagrammed on the following TCCs were laid out and modeled based on a maximum fault current of 65 kA at 480V, with an X/R ratio of 4.9. Transformerimpedances used are the minimum for which a full selectivity solution could be achieved. Also

    noted on the TCCs are the typical GE transformer impedances for aluminum wound, 150°Crated transformers. In every case, the impedance diagrammed is equal to or less than thetypical GE value. To make the solution as conservative as possible, no or negligible cableimpedances were included in the short circuit calculations.

    While Article 450 of the NEC requires that transformers be properly protected fromovercurrent conditions, it allows several alternative approaches to achieve protection. For480V to 120/208V lighting transformers, 15 kVA and larger, the protection requirements are

    described in Table 450.3B of the NEC. The two options described are to use a circuit breaker

    as the primary main rated at no more than 250% of the primary ampere rating and a secondarymain circuit breaker rated at no more than 125% of the secondary. (Note: See NEC Table450.3 and associated notes for additional application allowances and restrictions.) It is also

     permissible to use only a primary main circuit breaker rated at no more than 125% of the

     primary ampacity.

    In general, since the ANSI “through” fault protection criteria is a recommendation, it is

    desirable to have the ANSI protection characteristic to the right of the primary and secondarycircuit breaker TCCs. However, it is the standard practice that adequate protection is still

  • 8/17/2019 Desing and Selectivity LV_GE

    34/105

     provided if most of the ANSI characteristic is to the right of the secondary main TCC.

    In the TCCs that follow, A is always the transformer primary main and B is the secondary main

    circuit breaker.

  • 8/17/2019 Desing and Selectivity LV_GE

    35/105

     

    A

    B

    C

    480V

    BUS-115 KVA

    3.5%

    65 KAIC (SYM)

    A

    B C*

    208V

    BUS-2

    GE Record Plus MCCB Frame Type: FBN Frame Size: 100A Trip: 25A

    GE TEY MCCB

    Frame Type: TEY Frame Size: 100A Trip: 50A

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 20A

  • 8/17/2019 Desing and Selectivity LV_GE

    36/105

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 6.1%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    37/105

     15.6.81234678

    9102346789100234678910002346789

    10000.55555

    Time-current CurveFully Selective Solution for 15 kVA TransformerCURRENT IN AMPERES X 10 AT 208 VOLTS8007001000 1000900 900600500400300200100908070605040302010 987654321.9.8.7.6.5.4.3

    .2.1

    .09

    .08

    .07

    .06

    .05

    .04

    .03

    .02

    .01 .01TIME IN SECONDS

    V

     

  • 8/17/2019 Desing and Selectivity LV_GE

    38/105

    A

    15

    F

    L

    A

    AGE

    Re

    cor

    d

    P

    l

    u

    s

    F

    B

    N

    T

    ri

    p

    Fr

    a

    m

    e

    =

    =

    10

    0A25

    A

    15

    KVA

    3.5%

    C

    *

    GETHQ

    Q

    Li

    ne

  • 8/17/2019 Desing and Selectivity LV_GE

    39/105

    B

    Fr

    a

    m

    e

    Tr

    ip

    =

    20

    A

    =

    10

    0A

    B GE

    E1

    50

    T

    E

    Y

    T

    ri

    p

    Fr

    a

    m

    e

    =

    5

    0

    A

    =

    1

    0

    0

    A

    1

    5

    K V

    A

    I

    N

    U

    S

    H

    B12

    17

    A

    8007001

    0090

    600

  • 8/17/2019 Desing and Selectivity LV_GE

    40/105

    50040030020080706050403020

    10 98765432

    1.9

    .8

    .7

    .6

    .5

    .4

    .3

    .2.1

    .09.08.07.06

    .05.04

    .03

    .02TIME IN SECONDS

    The following parameters are the basis of the above selective coordination plot:Minimum allowable Z% = 3.5%65 kA (X/R=4.9) @ 480V; 1.2 kA @ 208V

  • 8/17/2019 Desing and Selectivity LV_GE

    41/105

     

    B

    C

    A

    D

    BUS-1

    480V

    65 KAIC (SYM)

    A

    30 KVA 4%

    B 208V

    BUS-2

    C* D*GE Record Plus MCCB Frame Type: FBN Frame Size: 100A Trip Plug: 70A

    GE Record Plus MCCB Frame Type: FGN Frame Size: 600A Sensor: 250A

    Rating Plug: 100AIOC Setting: 11X (2750A)

    * GE Q-Line MCCB

    Frame Type: THQB Model C Frame Size: 100A-1,2P Trip: 50A

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 35A

  • 8/17/2019 Desing and Selectivity LV_GE

    42/105

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 5.6%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    43/105

     CURRENT IN AMPERES X 10 AT 208 VOLTS23456789

    100234.5.6.81234567891056789

    10002345678910000

    Time-current CurveFully Selective Solution for 30 kVA Transformer.5.8123468

    1023467910034678100023467910000.6

    579585958800800700700

    30 KVA FLA600

  • 8/17/2019 Desing and Selectivity LV_GE

    44/105

    600500500

    BG

    400400

    E RecordPlus300300

    200200

    Trip =

    100A

    Inst = 11X (27

    50A)1

    0090

    100908080707060605050

    30 KVA4040

    4%3030202010

    910 98877665544332

    21.9

    1.9.8.8.7.7

    Trip =

    35A.6.6.5.5.4.4.3.3.2.2

    C *30 KVA INRUSH

    .1.09

    .1

    .09

    .08

    .08

    .07

    .07

    Trip = 50A.06.06.05.05.04

  • 8/17/2019 Desing and Selectivity LV_GE

    45/105

    .04

    .03

    .03

    .02

    .02

    B

    2126ATIME IN SECONDS

    1000 10900 900.01 .01

    GE Q LineTHQB Model C - 1,2P Frame = 100A

    D *

    GE Q Line THQB

    Frame = 100A

    FGN

    Frame = 250A

    A

    GE Record Plus FBN

    Frame = 100A Trip = 70ACURRENT IN AMPERES X 10 AT 208 VOLTS

    The following parameters are the basis of the above selective coordination plot:Minimum allowable Z% = 4.0%65 kA (X/R=4.9) @ 480V; 2.1 kA @ 208V

    TIME IN SECONDS

  • 8/17/2019 Desing and Selectivity LV_GE

    46/105

     

    BUS-1

    BUS-2

    B 208V

    65 KA (SYM)

    480V

    A

    30 KVA 4%

    A

    B

    C

  • 8/17/2019 Desing and Selectivity LV_GE

    47/105

     

    D

    GE Record Plus MCCB Frame Type: FGN Frame Size: 600A Sensor: 250ARating Plug: 100AIOC Setting: 11X (2750A)

    GE Record Plus MCCB Frame Type: FGN Frame Size: 600A Sensor: 250ARating Plug: 100AIOC Setting: 11X (2750A)

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 50A

    * GE Q-Line MCCB

    Frame Type: THQB Model C Frame Size: 100A - 1, 2P Trip: 60A

  • 8/17/2019 Desing and Selectivity LV_GE

    48/105

    C* D*

  • 8/17/2019 Desing and Selectivity LV_GE

    49/105

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 5.6%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    50/105

     19.5.6.812345

    6789102345678910023467891000

    2345678910000

    Time-current CurveFully Selective Solution for 30 kVA Transformer

    TIME IN SECONDS1000 1000900 900400800700600500300

    2001.1

    .09

    .08

    .07

    .06

    .05

    .04

    .03

    .02

    .01 .010090

    807060504030201

    1.9

    .8

    .7

    .6

    .5

    .4

    .3

    .209

    8654327

  • 8/17/2019 Desing and Selectivity LV_GE

    51/105

    4%

    30 KVA

    GE Q Line THQB

    Frame = 100A Trip = 50A

    C*

    THQB Modlel C - 1,2P

    Frame = 100A

    Trip = 60AD* GE Q

    Line30 KVA FLA30 KVA INRUSHA

    GE RecordP

    Trip = 100A

    Inst = 11X (2750A)FGN Frame =

    2126A

    B

    250A

    lus

    Trip = 100A

    Inst = 11X (2750A)B GE

    FGN

    Fra

    RecordPlus

    me = 250A8006005004003002001009080605040302010 9

    8765432700701.9.8.7.6.5.4.3.2.1.09.08.07.06

    .05

    .04

    .03

    .02

    CURRENT IN AMPERES X 10 AT 208 VOLTSTIME IN SECONDS

    The following parameters are the basis of the above selective coordination plot:Minimum allowable Z% = 4.0%

    65 kA (X/R=4.9) @ 480V; 2.1 kA @ 208V

  • 8/17/2019 Desing and Selectivity LV_GE

    52/105

    45 kVA Transformer Template(with Record Plus Type FG Primary Main)

  • 8/17/2019 Desing and Selectivity LV_GE

    53/105

     

    480V

    A

    45 KVA

    3.5%

    B208VA

    B

    C

    D

    BUS-1

    BUS-265 KA (SYM)C* D*

    GE Record Plus MCCB Frame Type: FGNFrame Size: 600A

    Sensor: 250ATrip: 100AIOC Setting: 11X (2750A)

    GE Record Plus MCCB Frame Type: FGN

    Frame Size: 600A

    Sensor: 250ATrip: 150A

    IOC Setting: 11X (2750A)

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 50A

    * GE Q-Line MCCB

    Frame Type: THQB Model C Frame Size: 100A - 1, 2P Trip: 60A

  • 8/17/2019 Desing and Selectivity LV_GE

    54/105

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 5.4%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    55/105

     CURRENT IN AMPERES X 10 AT 208 VOLTS34567891002

    34.5.6.812345678910567891000234

    5678910000.6.8123467891024678910023467891000234678910000.55555

    Time-current CurveFully Selective Solution for 45 kVA TransformerCURRENT IN AMPERES X 10 AT 208 VOLTS800700800700

    TIME IN SECONDS

    1000 10900 9004002006005003001.01 .0140

    00

  • 8/17/2019 Desing and Selectivity LV_GE

    56/105

    9080706050302014

    09

    8

    76532

    45

    KVA

    FLA

    A

    GE

    F

    G

    N

    Reco

    rd

    Pl

    us

    T

    ri

    p

    I

    n

    st

    F

     

    =

     

    1

    1

    X

    10

    0A

    25

    0A

    (

    2

    7

    5

    0

    A

    )

    B

    GE

    e

    c

    o

    r

    d

    P

    lu

    s

    FGNF

    =

    250A

  • 8/17/2019 Desing and Selectivity LV_GE

    57/105

    rame

    T

    ri

    p

    I

    n

    st

    =

    15

    0A

    =

    11

    X

    (2750A

    )

    45

    KV

    A

    3.5

    %

    C

    *

    G

    EQ

    Li

    ne

    T

    H

    Q

    B

    Fr

    a

    m

    e

    =1

    0

    0

    A

    T

    ri

    p

    =

    50

    A

    4

    5

    V

    A

    I

    N

     

  • 8/17/2019 Desing and Selectivity LV_GE

    58/105

    U

    S

    H

    D

    *

    G

    E

    T

    H

    Q

    B

    Q

    Li

    ne

    M

    od

    el

    C

    F

    ra

    m

    e =

    10

    0A

    -

    1,2P

    T

    ri

    p

    =

    60

    A

    B

    3627A

    4002004020426005003001009080706050

    3010 987653

    TIME IN SECONDS1.9

    .8

    .7

    .6

    .5

    .4

    .3

    .2

  • 8/17/2019 Desing and Selectivity LV_GE

    59/105

    .1.09

    .08

    .07

    .06

    .05

    .04

    .03

    .021.9.8

    .7

    .6

    .5

    .4

    .3

    .2

    .1

    .09

    .08

    .07

    .06

    .05

    .04

    .03

    .02

    The following parameters are the basis of the above selective coordination plot:Minimum allowable Z% = 3.5%65 kA (X/R=4.9) @ 480V; 3.6 kA @ 208V

  • 8/17/2019 Desing and Selectivity LV_GE

    60/105

     

    BUS-2

    B 208V

    65 KA (SYM)

    BUS-1

    480V

    A

    75 KVA

    4.5%

    C* D*

    B

    C

    D

    GE Record Plus MCCB Frame Type: FGN

    Frame Size: 600A

    Sensor: 250A

    Trip: 110AIOC Setting: 11X (2750A)

  • 8/17/2019 Desing and Selectivity LV_GE

    61/105

    GE Record Plus MCCB Frame Type: FGN

    Frame Size: 600A

    Sensor: 400ATrip: 225A

    IOC Setting: 11X (4400A)

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 100A

    * GE Q-Line MCCB

    Frame Type: THQB Model C Frame Size: 100A –  1, 2P Trip: 60A

  • 8/17/2019 Desing and Selectivity LV_GE

    62/105

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 6.0%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    63/105

     23

    Time-current CurveFully Selective Solution for 75 kVA Transformer.5.6.812345678910234567891002345678910002345678910000800800700700

    75 KVA600600

    FLA500500400

    4003003002002001

    0090

    10090808070706060

    = 11X (2750A)

    Inst50504040

    75 KVA4.5%3030202010910 9887766

  • 8/17/2019 Desing and Selectivity LV_GE

    64/105

    554433

    Trip

    = 100A22

    1.91.9.8.8.7.7.6.6.5.5.4.4.3.3.2.2

    D*GE

    75 KVAINRUSH

    0A).1

    .09.1.09.08.08.07.07.06.06.05.05.04.04.03.03.02.02

    B

    4704ATIME IN SECONDS

    TIME IN SECONDS1000 10900 900.01 .01

    Q Line

    THQB Model C

    Frame = 100A - 1,2P

    Trip = 60A

    C*

    GE Q Line THQB

    Frame = 100A

    A

    GE RecordPlus FGNFrame = 250A Trip = 110A

    B

    GE RecordPlus FGN Frame = 400A Trip = 225A Inst = 11X (440

    CURRENT IN AMPERES X 10 AT 208 VOLTSThe following parameters are the basis of the above selective coordination plot:

    Minimum allowable Z% = 4.5%

    65 kA (X/R=4.9) @ 480V; 4.7 kA @ 208V

  • 8/17/2019 Desing and Selectivity LV_GE

    65/105

    112.5 kVA Transformer Template(with Record Plus Type FG Secondary Main)

  • 8/17/2019 Desing and Selectivity LV_GE

    66/105

     

    65 KA (SYM)

    BUS-1 480V

    A

    112.5 KVA

    4.2%

    A

    GE Record Plus MCCB Frame Type: FGNFrame Size: 600A

    Sensor: 400ATrip: 225A

    IOC Setting: 11X (4400A)

    B

    GE Record Plus MCCB Frame Type: FGN

    Frame Size: 600A

    Sensor: 400ATrip: 350A

    IOC Setting: 11X (4400A)

    C

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 100A

  • 8/17/2019 Desing and Selectivity LV_GE

    67/105

    208V

    BUS-3

    B

    C* D*

    D * GE TEY MCCB

    Frame Type: TEY, 3P Frame Size: 100A Trip: 60A

  • 8/17/2019 Desing and Selectivity LV_GE

    68/105

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 5.9%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    69/105

     25

    CURRENT IN AMPERES X 10 AT 208 VOLTS2345678

    9100234.5.6.8123456789105678

    910002345678910000

    Time-current CurveFully Selective Solution for 112.5 kVA Transformer.6.8123467810234679100234678100023467

    910000.559585958800800700700

  • 8/17/2019 Desing and Selectivity LV_GE

    70/105

    112.5 KVAFLA

    600600500500400400300300

    A GERecordPlus200200

    B GE

    RecordPlus

    Trip =

    22

    5A

    11X (4400A)

    Inst =1

    0090

    10090808070706060505040403030202010

    910 9887766554

    43322

    D*GE

    E1501.9

    1.9

    TEY Frame =.8.8

    100A.7.7.6.6

    Trip = 60A.5.5.4.4.3.3.2.2

    C* GE Q

    Line

    THQB.1

    .09.1.09

  • 8/17/2019 Desing and Selectivity LV_GE

    71/105

    112.5 KVA.08.08.07.07

    INRUSH.06.06.05.05

    .04

    .04

    .03

    .03

    .02

    .02

    B

    7507ATIME IN SECONDS

    1000 10900 900.01 .01

    Trip = 350A

    Inst = 11X (4400A)

    FGN

    Frame = 400A

    112.5 KVA

    4.2%

    Frame = 100A

    Trip = 100A

    FGN

    Frame = 400ACURRENT IN AMPERES X 10 AT 208 VOLTS

    The following parameters are the basis of the above selective coordination plot:

    Minimum allowable Z% = 4.2%65 kA (X/R=4.9) @ 480V; 7.5 kA @ 208V

    TIME IN SECONDS

  • 8/17/2019 Desing and Selectivity LV_GE

    72/105

    A

    B

    C

    D

    112.5 kVA Transformer Template (with ABBS7 Secondary Main)

  • 8/17/2019 Desing and Selectivity LV_GE

    73/105

     

    BUS-2

    208V

    B

    CA

    112.5 KVA

    4.2%

    65 KVA (SYM)

    BUS-1

    480V

    BUS-3

    D* E*

    GE Record Plus MCCB Frame Type: FGN

    Frame Size: 600A

    Sensor: 400ATrip: 225A

    IOC Setting: 11X (4400A)

    ABB S7 MCCB

    Frame Type: ISOMAX Frame Size: 1200A

    Sensor: 1000ALT Trip: 0.4X (400A)LT Delay: AST Trip: 10X (10000A)

    ST Delay: DI2t: Out

    IOC Setting: 12X (12000A)

    GE Record Plus MCCB Frame Type: FGNFrame Size: 600A

    Sensor: 250ATrip: 225A

    IOC Setting: 11X (2750A)

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 100A

  • 8/17/2019 Desing and Selectivity LV_GE

    74/105

     

    E * GE TEY MCCB

    Frame Type: TEY Frame Size: 100ATrip: 60A

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 5.9%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    75/105

     

    Time-current CurveFully Selective Solution for 112.5 kVA Transformer

    TIME IN SECONDS1000 10900 900400800

    7006005003002001

    .1.09.08.07.06.05.04.03.02.01 .01

    0090

    8070605040

    302010

    1.9

    .8

    .7

    .6

    .5

    .4

    .3

    .286429753

    Trip = 225AC GE

    FGNFrame = 250A

    Inst = 11X

    RecordPlus

    4.2%

    112.5 KVA

    (2750A)

    E*

    GE E150 TEY

    Trip = 60A

    Frame= 100A

    THQB

    Frame = 100A Trip = 100A

    D*GE Q Line112.5 KVA FLA

    112.5 KVA

    INRUSH

    A

    GE RecordPlus

    TripBABB

  • 8/17/2019 Desing and Selectivity LV_GE

    76/105

    Tap =

    Sensor =Cur Set = 0.4X (400A)LT Band =

    STPU = 10X (10000A)

    ST Delay

    STPU I2t = Out

    FGN

    Frame = 400A

    Inst =

    Inst =

    = 2

    PR212

    1000A

    11X

    12X (12000A)

    25A

    C

    7507A

    S7 (1000ACT)

    = D

    A

    (4400A)4004048007006005003002001009080706050302098765

    321.9.8.7.6.5.4.3.2.1.09.08.07.06.05.04.03.0210

    TIME IN SECONDS

    The following parameters are the basis of the above selective coordination plot:Minimum allowable Z% = 4.2%65 kA (X/R=4.9) @ 480V; 7.5 kA @ 208V

  • 8/17/2019 Desing and Selectivity LV_GE

    77/105

    150 kVA Transformer Template(with Record Plus Type FG Primary Main)

  • 8/17/2019 Desing and Selectivity LV_GE

    78/105

     

    480V

    A

    150 KVA

    4.4%

    AB

    C

    D

    BUS-1

    BUS-3

    208V

    65 KVA (SYM)

    B

    C* D*

    GE Record Plus MCCB Frame Type: FBN

    Frame Size: 600A

    Sensor: 400ATrip: 250AIOC Setting: 11X (4400A)

    GE Record Plus MCCB Frame Type: FGN Frame Size: 600A Sensor: 600ARating Plug: 450A

    IOC Setting: 11X (6600A)

    * GE Q-Line MCCB Frame Type: THQ Frame Size: 100A Trip: 100A

    * GE Q-Line MCCB

    Frame Type: THQB Model C Frame Size: 100A –  1, 2P Trip: 60A

  • 8/17/2019 Desing and Selectivity LV_GE

    79/105

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 4.4%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    80/105

    TIME IN SECONDS

    CURRENT IN AMPERES X 10 AT 208 VOLTS

    .5

    .81234567810234567910023456781000234567910000.69898

    TIME IN SECONDS1000 10900 900400800700600500300200100

    90.1

    .09

    .08

    .07

    .06

    .05

    .04

    .03

    .02

    .01 .01408070605030201

    1.9

    .8

    .7

    .6

    .5

    .4

    .3

    .209

    8765432

    Trip = 450A

    Inst = 11X (6600A)

    B

  • 8/17/2019 Desing and Selectivity LV_GE

    81/105

    GE RecordPlFGNFrame =

    4.4%

    150 KVATHQB Frame

    Trip = 100AC*

    GETHQB Model C Frame = 100A - 1,2P Trip = 60A

    D* GE Q

    600A

    Q LineusLine

    = 100A150 KVA FLA

    150 KVA

    INRUSHA

    GE RecordPlus

    Trip = 250AFGN Fram

    Inst = 11X (4400A)e =400A

    9806A

    B40020040204280070060050030010090807060503010 9876531.9.8.7.6.5.4.3.2.1.09.08.07.06

    .05

    .04

    .03

    .02

    .5 .6 .8 1 2 3 4 5 67 8 9 10 2 3 4 5 67 8 9 100 2 3 4 5 67 8 9 1000 2 3 4 5 67 8 9 10

    Time-current CurveFully Selective Solution for 150

    kVA Transformer

  • 8/17/2019 Desing and Selectivity LV_GE

    82/105

    The following parameters are the basis of the above selective coordination plot:Minimum allowable Z% = 4.4%

    65 kA (X/R=4.9) @ 480V; 9.8 kA @ 208V

    CURRENT IN AMPERES X 10 AT 208 VOLTS

  • 8/17/2019 Desing and Selectivity LV_GE

    83/105

    150 kVA Transformer Template (with ABB S7 Primary Main)

  • 8/17/2019 Desing and Selectivity LV_GE

    84/105

     

  • 8/17/2019 Desing and Selectivity LV_GE

    85/105

     

    A

    B

    C

    D

    A150 KVA

    4.4%

    65 KA (SYM)

    BUS-1

    480V

    BUS-2

    B

    C*

    208V

    BUS-3

    D* E*ABB S7 MCCB

    Frame Type: ISOMAX Frame Size: 1200A

    Sensor: 1000ALT Trip: 0.4X (400A)LT Delay: AST Trip: 8X (80000A)

    ST Delay: DI

    2t: Out

    IOC Setting: 12X (12000A)

    ABB S7 MCCB

    Frame Type: ISOMAX Frame Size: 1200A

    Sensor: 1200ALT Trip: 0.4X (480A)

    LT Delay: BST Trip: 8X (9600A)ST Delay: C

    I2t: Out

    IOC Setting: 12X (14400A)

    GE Record Plus MCCB Frame Type: FGN

    Frame Size: 600A

    Sensor: 400A

    Trip: 350AIOC Setting: 11X (4400A)

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 100A

  • 8/17/2019 Desing and Selectivity LV_GE

    86/105

     

    E * GE TEY MCCB

    Frame Type: TEY FrameSize: 100A Trip: 60A

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem

    to indicate non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were

    used to validate selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 4.4%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

  • 8/17/2019 Desing and Selectivity LV_GE

    87/105

     31.6.812346 78

    9102346 7891002346 78910002346 789

    10000.55555

    Time-current CurveFully Selective Solution for 150 kVA TransformerCURRENT IN AMPERES X 100 AT 208 VOLTS87800700

    TIME IN SECONDS

    18 ;8

    6543

    .09..

    .

    .

    .

    .01 .01

    000000 

    150

    V

    A

    00 FL

    A00ABBPR212

    00 ensorTap=1200A

    =

    S7

    (

    1

    2

    0

    0

    A

    C

     

  • 8/17/2019 Desing and Selectivity LV_GE

    88/105

    T

    )00 15

    0

    4.4

    %

    VA

    Cur

    Set

    LT

    Ban

    d

    STP

    U =

    =

    0.

    4

    X

    =

    B

    8

    X

    (9

    60

    0

    A

    )

    (4

    80

    A)

    00

    ST

    Dela

    y

    = C

    90

    80STP

    U I2t

    =

    Ou

    t

    Inst

    =

    12X

    (

    1

    4

    4

    0

    0

    A

    )60

    30

    4020

    8

    6

    5

    4

    3

    21

    A

    B

    BPR212

    GEE150

    GE

    9Sensor= S7 (1  

  • 8/17/2019 Desing and Selectivity LV_GE

    89/105

    0

    0

    0

    A

    C

    T

    )

    8

    7

    Fram

    e =

    10

    0A

    T

    a

    p

    =

    1000A

    6

    Trip

    = 60A

    C

    u

    r

    Set =

    0.4X

    (4

    0

    0

    A

    )5 L

    T

    Band

    = A4

    ST

    PUST

    =

    3 C

    *

    GE

    Re

    cor

    dPl

    us

    STP t=

    U I

    2 FG

    Fra

    meTri

    p =

    =

    40

    0A 

    35

    0A

    1

    50

    VA

    I

    n

    st

    = 12X

    (12000

    A)

    1 Inst =

    11

    X

    (

    4

    4

    0

    0

    A

    )

    I

    N

    U

    SH

    GE

    Li

    ne

  • 8/17/2019 Desing and Selectivity LV_GE

    90/105

     

    T

    H

    Q

    Fr

    am

    e=

    10

    0

    A

    Trip =

    10

    0A

    B A

    9806A 82

    17

    9A

    60040020010090

    60

    40206425003008070503010987531.9.8.7.6.5

    .4

    .3

    .2TIME IN SECONDS

    21

    .

    .

    .1

    .09

    .08

    .07

    .06

    .05

    .04

    .03

    .02

    The following parameters are the basis of the above selective coordination plot:

    Minimum allowable Z% = 4.4%65 kA (X/R=4.9) @ 480V; 9.8 kA @ 208V

  • 8/17/2019 Desing and Selectivity LV_GE

    91/105

    225 kVA Transformer Template (with ABB S7 Secondary Main)

  • 8/17/2019 Desing and Selectivity LV_GE

    92/105

     

    A

    B

    C

    D

    480VA

    208V

    B

    BUS-1

    BUS-2

    65KA (SYM)225 KVA

    4.1%

    C

    1BUS-3

    D*GE Record Plus MCCB Frame Type: FGN Frame Size: 600A Sensor: 600ARating Plug: 450A

    IOC Setting: 11X (6600A)

    ABB ISOMAX MCCB Frame Type: S7

    Frame Size: 1200A

    Sensor: 1000ALT Setting: 0.7X (700A)

    LT Delay: B

    ST Setting: 10X (10000A)ST Delay: D

    I2t: OutIOC Setting: 12X (12000A)

    1 GE Record Plus MCCB Frame Type: FGN Frame Size: 600A Sensor: 600ARating Plug: 400A

    IOC Setting: 11X (6600A)

    * GE Q-Line MCCB Frame Type: THQB Frame Size: 100A Trip: 100A

  • 8/17/2019 Desing and Selectivity LV_GE

    93/105

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate

    selective operation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole

    configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 7.0%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 

    1 FG400 and FG600 are selective with all THQB MCCBs. Certain THQBs not selective with FG250

    MCCBs.

  • 8/17/2019 Desing and Selectivity LV_GE

    94/105

    TIME IN SECONDS

    CURRENT IN AMPERES X 10 AT 208 VOLTS

    .5

    .81234567810234567910023456781000234567910000.69898

    TIME IN SECONDS

    1000 10900 9004002008007006005003001

    .1.09

    .08

    .07

    .06

    .05

    .04

    .03

    .02

    .01 .0140

    0090

    8070605030201.9.8.7.6.5

    .4.3

    .24

    09

    8765321

    Tap = 1000A Cur Set = 0.7XB ABB

    Sensor = S7

  • 8/17/2019 Desing and Selectivity LV_GE

    95/105

    LT Band = B STPU = 10X

    (10000A)

    ST Delay = D

    STPU I2t = Out

    Inst = 12

    PR212

    X (12000A)

    (1000ACT)4.1%

    225

    (700A)

    Trip = 400A

    Inst = 11X (6600A)C GE

    FG

    Fram

    KVA

    N

    RecordPlus

    D*

    GE Q Line

    THHQB

    Frame = 100ATrip = 100A

    e = 600A225 KVA FLA

    225 K

    INRU

    VA

    SH

    Trip

    A

    GE RecordPlus

    FGN

    Frame = 600A

    Inst = 11X (6600A)

    = 450A

    B16319A800600400200806050402010 9865432700500300100

    90703071.9.8.7.6.5.4.3.2.1.09.08.07

  • 8/17/2019 Desing and Selectivity LV_GE

    96/105

    .06

    .05

    .04

    .03

    .02.5 .6 .8 1 2 3 4 5 67 8 9 10 2 3 4 5 67 8 9 100 2 3 4 5 67 8 9 1000 2 3 4 5 67 8 9 10

    Time-current CurveFully Selective Solution for 225

    kVA Transformer

    The following parameters are the basis of the above selective coordination plot:Minimum allowable Z% = 4.1%65 kA (X/R=4.9) @ 480V; 16.3 kA @ 208V

    CURRENT IN AMPERES X 10 AT 208 VOLTS

  • 8/17/2019 Desing and Selectivity LV_GE

    97/105

    A

    B

    300 kVA Transformer Template (with ABB S7 Secondary Main)

  • 8/17/2019 Desing and Selectivity LV_GE

    98/105

     

    65KAIC (SYM)

    BUS-1

    480V

    A

    300 KVA

    4.0%

    BUS-2

    B

    C

    208V1

    BUS-3

    D*, 2  E*C

    D

    E

    ABB ISOMAX MCCB Frame Type: S7

    Frame Size: 1200A

    Sensor: 1000ALT Setting: 0.5X (500A)

    LT Delay: BST Setting: 10X (10000A)

    ST Delay: DI2t: Out

    IOC Setting: 12X (12000A)

    ABB ISOMAX MCCB Frame Type: S7

    Frame Size: 1200A

    Sensor: 1000ALT Setting: 1.0X (1000A)

    LT Delay: AST Setting: 10X (1000A)

    ST Delay: DI2t: Out

    IOC Setting: 12X (12000A)

    1 GE Record Plus MCCB Frame Type: FGN Frame Size: 600A Sensor: 600ARating Plug: 500AIOC Setting: 11X (6600A)

  • 8/17/2019 Desing and Selectivity LV_GE

    99/105

    *2 GE Q-Line MCCB Frame Type: THHQB Frame Size: 100ATrip:  100A

    * GE Record Plus MCCBFrame Type: FBNFrame Size: 100A

    Trip:  100

    A

    Notes:

    Where an overlap of the time-current curve, instantaneous overcurrent characteristics seem to indicate

    non-selectivity, GE Overcurrent Instantaneous Selectivity Tables, DET-537, were used to validate selectiveoperation.

    Unless otherwise noted, overcurrent protective devices shown are for all available pole configurations.

    GE typical transformer impedance: 150°C rise, aluminum winding, Z = 7.4%

    This Z% is equal to or greater than the minimum allowed on this coordination plot

    * Base layer circuit breaker settings are “not to exceed” values 1 FG400 and FG600 are selective with all THQB MCCBs. Certain THHQBs not selective with FG250 MCCBs.2 THHQB can only be used if AIC is less than 22 kA at the THHQB MCCB

  • 8/17/2019 Desing and Selectivity LV_GE

    100/105

     3510

    CURRENT IN AMPERES X 10 AT 208 VOLTS234567

    89100234.5.6.81234567895678

    910002345678910000.5.6.812345678

    9102345678910023456789100023

    45678910000

    Time-current CurveFully Selective Solution for 300 kVA TransformerCURRENT IN AMPERES X 10 AT 208 VOLTS

    TIME IN SECONDS1000 1900 9

  • 8/17/2019 Desing and Selectivity LV_GE

    101/105

    4002008007006005003001

    .1.09.08.07.06.05.04.03.02.01 .014020

    0090

    80706050301

    1.9

    .8

    .7

    .6

    .5

    .4

    .3

    .242

    09

    87653

    GE Q Line 

    THHQB 

    Frame = 1

    Trip = 100A

    D*

    FGN 

    Frame = 600A 

    Trip = 500A 

    Inst = 11X (6600A)

    FBNFrame = 100A 

    Trip = 100A

    CGE RecordPlusE*

    GE Record Plus

    00A

    4%

    300 KVA

    300 KVA 

    FLAA

     

    AB

    Sensor = S7 (1000ACT) 

    Tap = 1000A

    Cur Set = 0.5X (500A) 

    LT Band = B

    STPU = 10X (10000A)

    ST Delay = D 

    STPU I

    2

    t = Out 

    Inst = 12 X (12000A)

    300 KVA

    INRUSH

    B PR212

    ABB PR212 

    Sensor = S7 (1000ACT) 

    Tap = 1000A 

    Cur Set = 1X (1000A) 

    LT Band =

    STPU = 10 X (10000A) 

    ST Delay = D

    STPU I2t =

    Inst = 12X (12000A)

  • 8/17/2019 Desing and Selectivity LV_GE

    102/105

    C

    22434A 

    Asymmetrical

    A

    Out40020040204

    280070060050030010090

    807060503010 9876531.9.8.7

    .6

    .5

    .4

    .3

    .2

    .1

    .09

    .08

    .07

    .06

    .05

    .04

    .03

    .02TIME IN SECONDS

    The following parameters are the basis of the above selective coordination plot:Minimum allowable Z% = 4.0%65 kA (X/R=4.9) @ 480V; 22.4 kA @ 208V

  • 8/17/2019 Desing and Selectivity LV_GE

    103/105

    Typical GE Dry Type Transformer Data

    Table 3

    480V Delta to 208/120V Wye, TP-1 Transformers

    kVA °C Rise Aluminum Copper

    Cat. No.%

    R

    %

    X

    %

    Z

    X/

    RCat. No. %R

    %X %Z X/

    R

    15 150 9T83B3871 5.1 3.3 6.1 0.6 9T83C9871 4.3 2.2 4.8 0.5

    115 9T83B3871G15 5.13.3

    6.10.6 9T83C9871G1

    54.3

    2.24.8 0.5

    80 9T83B3871G80 5.13.3

    6.10.6 9T83C9871G8

    01.3

    2.12.5 1.6

    30 150 9T83B3872 3.7 4.2 5.6 1.1 9T83C9872 2.8 4.3 5.1 1.8

    115 9T83B3872G15 3.74.2

    5.61.1 9T83C9872G1

    52.8

    4.35.1 1.8

    80 9T83B3872G80 2.12.7

    3.41.3 9T83C9872G8

    01.9

    2.33 1.2

    45 150 9T83B3873 3.5 4.1 5.4 1.2 9T83C9873 3 3.5 4.6 1.2

    115 9T83B3873G15 3.54.1

    5.41.2 9T83C9873G1

    53 3.5 4.6 1.2

    80 9T83B3873G80 1.33.1

    3.42.4 9T83C9873G8

    0 1 2.5 2.7 2.5

    75 150 9T83B3874 3.9 4.5 6.0 1.2 9T83C9874 3.4 4 5.2 1.2

    115 9T83B3874G15 2.84.7

    5.51.7 9T83C9874G1

    52.7

    3.54.4 1.3

    80 9T83B3874G80 1.13.5

    3.73.2 9T83C9874G8

    01 2.6 2.8 2.6

    112.5 150 9T83B3875 3.1 5.0 5.9 1.6 9T83C9875 2.7 3.8 4.6 1.4

    115 9T83B3875G15 2.34.1

    4.71.0 9T83C9875G1

    52.5

    4.85.4 1.9

    80 9T40G0005G81 1.82.2

    2.81.2 9T45G0005G8

    11.5

    1.92.4 1.3

    150 150 9T40G0006 2.4 3.7 4.4 1.5 9T45G0006 2 3.1 3.7 1.6

    115 9T40G0006G51 2.43.7

    4.41.5 9T45G0006G5

    12 3.1 3.7 1.6

    80 9T40G0006G81 2.43.7

    4.41.5 9T45G0006G8

    12 3.1 3.7 1.6

    225 150 9T40G0007 4.3 5.6 7.0 1.3 9T45G0007 3.7 4.6 5.9 1.2

    115 9T40G0007G51 2.45.0

    5.51.9 9T45G0007G5

    12 3.8 4.3 1.9

    80 9T40G0007G81 2.64.9

    5.61.9 9T45G0007G8

    12 3.8 4.3 1.9

    300 150 9T40G0008 4.0 6.2 7.4 1.6 9T45G0008 3.3 4.6 5.7 1.4

    115 9T40G0008G51 1.85.2

    5.52.9 9T45G0008G5

    11.6

    3.23.5 2.0

  • 8/17/2019 Desing and Selectivity LV_GE

    104/105

    Glossary

     AbbreviationsAHJ Authority having jurisdictionAIC Amperes interrupting currentATS Automatic transfer switch

    FTL Feed through lugsICCB Insulated case circuit breaker (UL Standard 489 rated)

    IOC Instantaneous overcurrentkA Kilo-amperes

    LVPCBLow Voltage Power Circuit Breaker (ANSI Standard C37. rated)MCCBMolded Case Circuit Breaker (UL Standard 489 rated)

    MCS Molded Case Switch

    NEC  National Electric Code

    OCPD Overcurrent Protective Device

    V Volts

    xfmr Transformer

    Terms As Used in This Publication0.1 second selectivity

    Two adjacent OCPDs are selective with one another over the full range of AIC, but only downto 0.1 seconds on the TCC. This suggests that their long time and short time characteristics areselective with one another, but that their instantaneous characteristics (that portion of the TCC

     below 0.1 seconds) may not be selective

    Code

     National Electrical Code

    Downstream / Upstream

    A circuit breaker's or OCPDs location relative to the power source. For example, a main circuit

     breaker in a panel is closer to the power source than a (smaller sized) branch breaker in thesame panel is upstream of the branch breaker. Correspondingly, the branch breaker isdownstream of the main breaker in this example.

    Full Selectivity

    In the context of NEC Articles 700, 701 and 708, this means two adjacent OCPDs are selective

    with one another over the full range of available fault current magnitudes and for all types offault current.

    Layer

    On a one-line diagram, circuit breaker or OCPD layers are counted from a load back to a power

    source. Each circuit breaker placed above another on the circuit back to the source is anotherlayer.

  • 8/17/2019 Desing and Selectivity LV_GE

    105/105

    GE

    41

    Wood

    ford

    Aven

    ue,

    Plain

    ville,

    CT

    06062

    www.

    geele

    ctrica

    l.com

    © 2010 General Electric Company

    imagination at

    workDET-

    http://www.geelectrical.com/http://www.geelectrical.com/http://www.geelectrical.com/http://www.geelectrical.com/http://www.geelectrical.com/http://www.geelectrical.com/http://www.geelectrical.com/http://www.geelectrical.com/