36
1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System for the DSD Sheung Wan Stormwater Pumping Station By Eric Li - GCG (Asia) Presented to the HKIE Geotechnical Division 18 th June 2008 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Sheung Wan Stormwater Pumping Station (SWSPS)

Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

Embed Size (px)

Citation preview

Page 1: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

1

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Design of Temporary Excavation

and Lateral Support System

for the DSD Sheung Wan

Stormwater Pumping Station

By Eric Li - GCG (Asia)

Presented to the HKIE Geotechnical Division

18th June 2008

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Sheung Wan Stormwater Pumping Station (SWSPS)

Page 2: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

2

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Project Set Up

� DSD Contract DC/2006/10

� Contract Sum : HK$ 78 million (approx)

� Designer : Drainage Services Department

(with GEO as in-house geotechnical consultant)

� Site Supervision : DSD Drainage Project Division

(with the engagement of an IGE)

� Contractor : China National Chemical Engineering Group

� ELS Designer : Geotechnical Consultant Group (Asia) Ltd.

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

43m

57m

Pile Cap Layout Plan

~ -5.9mPD

~ -7.1mPD

Page 3: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

3

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

43m

Retaining Wall

Pile Cap / Base Slab

Typical North-South Section

~ +4.0mPD

~ -5.9mPD~ -7.1mPD

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Selection of Retaining Wall Type

Wall Types Considered:

• Diaphragm Wall

• Bored Pile Wall

• Pipe Pile Wall

• Sheet Pile Wall

• No wall (open cut)

Design Objectives:

• Approximate max. 10m deep excavation

• Effective control of settlement due to excavation and groundwater drawdown

Page 4: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

4

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Reclamation and Seawall Dredging Plan

Approx. Location of Site

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Typical Cross Section

Vertical Seawall (Indicative) Approx. Extent of SWSPS

Victoria Harbour

Page 5: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

5

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Pre-Contract Borehole Location Plan

Pre-Contract Ground investigation

• 2 series in 2002 & 2006 (32 holes)• Common sampling, field and laboratory tests• In situ vane & pressuremeter tests

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

North-South Geological Section

Sand Fill

Rock Fill

CDG

Marine Deposits

Alluvium

Fill

Page 6: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

6

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

East-West Geological Section (away from Seawall)

Marine Deposits

Fill

CDG

Alluvium

Existing Salt Water PS

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Isopach of Soft Marine Clays

Seawall Cope Line

Page 7: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

7

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Seawall Cope Line

Small sink hole at sea wall

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

5m3 sink hole

Page 8: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

8

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

15m3 sink hole

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

-0.300

-0.200

-0.100

0.000

21

/8/0

6

31

/8/0

6

10

/9/0

6

20

/9/0

6

30

/9/0

6

10

/10

/06

Se

ttle

me

nt

(m)

SS1

SS2

SS3

SS4

Settlement near Seawall-0.300

-0.200

-0.100

0.000

21

/8/0

6

31

/8/0

6

10

/9/0

6

20

/9/0

6

30

/9/0

6

10

/10

/06

Se

ttle

me

nt

(m)

GS20

GS21

GS24

GS25

‘SS’ Markers on Seawall

‘GS’ Markers on Ground Adjacent to Seawall

Page 9: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

9

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Design Considerations

� Reclamation Site

� Sensitive Structures nearby, i.e. WSD Pumping Station

� High water table, i.e. 1.2m below existing ground level

(+3.0mPD)

� Presence of thick layer of variable FILL

& soft MARINE DEPOSITS

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Design Methodology

� Drained and Undrained Conditions

� Lateral Stability

� Global Slope Stability

� Base Stability

� Hydraulic Stability

� Dewatering

� Ground Deformation / Settlement

� Structural Capacities

Page 10: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

10

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Plot of SPT-N against Elevation

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Plot of Undrained Shear Strength (Cu) against Elevation

Page 11: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

11

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Adopted Shoring Layout Plan

FSP IV Sheet Pile Walings & Struts(3 levels)

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Longitudinal Cross Section further from Seawall

Page 12: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

12

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Longitudinal Cross Section nearest Seawall

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Transverse Cross Section

Page 13: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

13

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Elevation of Wall D(Showing Grouting Ground Improvement)

Penetration (T.A.M.) Grout Jet Grout

Sheetpile (not shown for clarity)

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Fill

Marine DepositAlluvium

CDG

EastWestCulvert

Grout A

Grout B

Finite Element Analysis

(East-West Section)

Page 14: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

14

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Wall Deflection (East-West Section)

East WallWest Wall

δmax = 60mm

δmax = 115mm

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Ground Settlement (East-West Section)

West WallEast Wall

δmax = 18mm

δmax = 82mm

Page 15: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

15

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Wall Deflection (North-South Section)

South Wall North Wall

δmax = 102mm

δmax = 88mm

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Ground Settlement (North-South Section)

North WallSouth Wall

δmax = 53mm

δmax = 75mm

Page 16: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

16

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Exaggeration scale: 30

Tilt = 1/650 Seawall

Fill (Sand)

Fill (Rock)

Seawater

Deformation of Seawall

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Slope Stability Analysis

(South Wall)

Page 17: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

17

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Instrumentation Layout Plan

Principal Instrumentation :

- Ground settlement markers (SS, GS, SA)

- Inclinometers (IN, INX)

- Standpipe Piezometer (SP, PZ, PP)

- Building Tilt Marker

East Wall

West Wall

North Wall

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Outline Construction Programme for Key Activities

Page 18: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

18

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Settlement against Time

-0.350

-0.300

-0.250

-0.200

-0.150

-0.100

-0.050

0.000

0.050

01-A

ug-06

01-S

ep-06

01-O

ct-06

01-N

ov-06

01-D

ec-06

01-Jan-07

01-F

eb-07

01-M

ar-07

01-A

pr-07

01-M

ay-07

01-Jun-07

01-Jul-07

01-A

ug-07

01-S

ep-07

01-O

ct-07

01-N

ov-07

01-D

ec-07

01-Jan-08

Date

Settlement (m

)

SS3 SS2 SS1 SS4

Settlement against Time

-0.600

-0.500

-0.400

-0.300

-0.200

-0.100

0.000

01-A

ug-06

01-S

ep-06

01-O

ct-06

01-N

ov-06

01-D

ec-06

01-Jan-07

01-Feb-07

01-M

ar-07

01-A

pr-07

01-M

ay-07

01-Jun-07

01-Jul-07

01-A

ug-07

01-S

ep-07

01-O

ct-07

01-N

ov-07

01-D

ec-07

01-Jan-08

Date

Settlement (m

)

GS23 GS24 GS20

Ground Settlement Time Plot behind North Wall (Seawall)

‘SS’ Markers on Seawall

‘GS’ Markers on Ground Adjacent to Seawall

ExcavationH-Piling, Sheetpiling, Ground Improvement Grouting

Pile Cap

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Settlement against Time

-0.500

-0.450

-0.400

-0.350

-0.300

-0.250

-0.200

-0.150

-0.100

-0.050

0.000

01

-Au

g-0

6

01

-Se

p-0

6

01

-Oc

t-0

6

01

-No

v-0

6

01

-De

c-0

6

01

-Ja

n-0

7

01

-Fe

b-0

7

01

-Ma

r-0

7

01

-Ap

r-0

7

01

-Ma

y-0

7

01

-Ju

n-0

7

01

-Ju

l-0

7

01

-Au

g-0

7

01

-Se

p-0

7

01

-Oc

t-0

7

01

-No

v-0

7

01

-De

c-0

7

01

-Ja

n-0

8

Date

Se

ttle

me

nt

(m)

GS31 GS34 GS28

Ground Settlement Time Plot behind East Wall

Excavation

H-Piling, Sheetpiling, Ground Improvement Grouting

Pile Cap

Page 19: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

19

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Ground Deformation behind East Wall(due to excavation only)

GS28 (6.2m) GS31 (9.6m) GS34 (15.6m)

Inclinometer IN2 (1m)

Predicted δδδδmax = 115mm

Predicted δδδδmax = 82mm

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Settlement against Time

-0.070

-0.060

-0.050

-0.040

-0.030

-0.020

-0.010

0.000

0.010

01

-Au

g-0

6

15

-Au

g-0

6

29

-Au

g-0

6

12

-Se

p-0

6

26

-Se

p-0

6

10

-Oc

t-0

6

24

-Oc

t-0

6

07

-No

v-0

6

21

-No

v-0

6

05

-De

c-0

6

19

-De

c-0

6

02

-Ja

n-0

7

16

-Ja

n-0

7

30

-Ja

n-0

7

13

-Fe

b-0

7

27

-Fe

b-0

7

13

-Ma

r-0

7

27

-Ma

r-0

7

10

-Ap

r-0

7

24

-Ap

r-0

7

08

-Ma

y-0

7

22

-Ma

y-0

7

05

-Ju

n-0

7

19

-Ju

n-0

7

03

-Ju

l-0

7

17

-Ju

l-0

7

31

-Ju

l-0

7

14

-Au

g-0

7

28

-Au

g-0

7

11

-Se

p-0

7

25

-Se

p-0

7

09

-Oc

t-0

7

23

-Oc

t-0

7

06

-No

v-0

7

20

-No

v-0

7

04

-De

c-0

7

18

-De

c-0

7

01

-Ja

n-0

8

Date

Se

ttle

me

nt

(m)

SS13 SS9 SS10 SS14

Ground Settlement Time Plot behind West Wall

Predicted δδδδmax = 18mm

Page 20: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

20

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

-18.0

-16.0

-14.0

-12.0

-10.0

-8.0

-6.0

-4.0

-2.0

0.0

2.0

4.0

0 5 10 15Displacement (mm)

Ele

va

tion

(m

PD

)"+" toward excavation

Ground Deformation behind West Wall(due to excavation only)

Inclinometer IN5 (1m)

Predicted δδδδmax = 60mm

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Jet grouting

• Jet grout cuts insitu soft clay and mixes that with injected cement

• Disturbed clay is displaced to surface in slurry form

• Jet nozzle is typically 1.4mm to 3mm dia.

• Applicable to more cohesive soils where T.A.M. grouting may not work

Page 21: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

21

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Typical Set up of Jet Grouting

(Double Tube Method)

Temporary casing for drilling through fill.Withdrawn prior to jetting. (optional)

Jet Grout Zone

Soil Overburden

PVC tubing to assist spoil return. (optional)

Ref. : CNCEC

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

1. Set up rig 2. Drill to toe level 3. Test jetting

6. Jet grout completed. Withdraw grout string

5. Simultaneously withdrawal and rotation of grout string to next level4. Commence Jetting

Sequence of Jet Grouting Ref. : CNCEC

Page 22: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

22

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Jet grout parameters

• Jet grout parameters adopted at SWSPS

Target grouted dia. = 1500 – 2000 mm

Grout pressure = 300 – 400 bars

Air pressure = 8 - 12 bars

Withdraw rate = 13 to 15 min/m

Rotation rate = 6 – 7 rev/step

• Target strength & stiffnessUCS = 600 kPa

Elastic modulus = 150 MPa

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Page 23: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

23

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Page 24: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

24

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Jet Grout Core Sample

Page 25: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

25

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Hole S2Hole S5

Jet Grout Core Sample

(UCS: typically 7-10 MPa, sometimes >40 MPa)

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

T.A.M. Grout Core Sample

Page 26: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

26

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

T.A.M. Grout Core Sample

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Sheetpiling (by push-in method)

• Suitable in area where vibration is undesirable

• With limited penetration depth

• Difficult to overcome obstruction

• Tend to be more costly

Page 27: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

27

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Ref : Giken Seisakusho Co. Ltd

Sheetpiling by push-in method

At SWSPS

• Giken rig with special tool to overcome obstruction (up to 1m)

• Maximum 24m long sheet pile

• Limited to Type IV sheetpile

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Sheetpiling by push-in method

Page 28: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

28

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Augering to assist penetration

Page 29: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

29

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Drilling through Obstructions

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Cutter Head for Rock Obstructions

Page 30: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

30

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Alignment out-of-line when encountering obstructions

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Groundwater leaking throughretaining wall

Page 31: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

31

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Excavation in progress

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Disposal by barge

Page 32: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

32

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Installing waling and strut

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Excavation completed

Page 33: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

33

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Concreting in progress

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Concreting in progress (3 concrete pumps & 13 concrete trucks)

Page 34: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

34

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Foundation Completed

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

園林景觀工程設計散石徑散石徑散石徑散石徑////太極區太極區太極區太極區散石徑散石徑散石徑散石徑////太極區太極區太極區太極區

遮雨蓬

長椅

小型廣場小型廣場小型廣場小型廣場小型廣場小型廣場小型廣場小型廣場

方形花園方形花園方形花園方形花園方形花園方形花園方形花園方形花園

觀賞園林觀賞園林觀賞園林觀賞園林觀賞園林觀賞園林觀賞園林觀賞園林

海濱長廊

海濱長廊

海濱長廊

海濱長廊

海濱長廊

海濱長廊

海濱長廊

海濱長廊

海濱長廊海濱長廊海濱長廊海濱長廊海濱長廊海濱長廊海濱長廊海濱長廊

綠化天台綠化天台綠化天台綠化天台綠化天台綠化天台綠化天台綠化天台

散石徑

裝飾性街燈Ref. : DSD

Page 35: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

35

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Before Commencement After Completion

Ref. : DSD

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Summary

Issues to be considered in ELS design

• Site history

• Site characterization

• Design parameters (drained or undrained)

• Design objective and constraints

• Retaining wall installation effects

• Economy and construction programme

Page 36: Design of Temporary Excavation and Lateral Support …1 Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008 Design of Temporary Excavation and Lateral Support System

36

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Acknowledgement

• Drainage Services Department

• China National Chemical Engineering Corp

• Hyder Consulting Limited

Asia HKIE Technical Talk – ELS Design for SWSPS – 18 June 2008

Thank You !