Design of Firefighting system for oil installation of
PSOPresented ByDanish Obaid
Project CharterTitle: Design Firefighting system for oil installation of Pakistan State OilCompany: Pakistan State OilFacilitator: Health, Safety & Environment Department
Project Need:Pakistan State Oil is the largest oil marketing company of Pakistan having huge infrastructure for storing petroleum products. The storage facilities are protected by firefighting system. Consultants are usually approached to design these systems for PSO who charge handsome amount for the activity. HSE department took initiative to do the same job through internal resources so as to save the money for the company.
In-Scope Out-Scope· Petroleum products (HSD, PMG)
· Heat Flux Modeling· Calculation of foam requirements· Calculation of water requirements· Calculation of GPM of fire pump· Hydraulic Analysis based on NFPA requirementsEstimated Time: Two month Estimated Cost: PKR 630,000/-
Approvals
DGM HSE GM Operations GM Construction
Project ManagementProcess Groups
Knowledge Areas Initiating Process Group Planning Process Group Executing Process Group Monitoring & Controlling Process Group Closing Process Group
Project Integration Management Project Charter Close Project
Project Scope Management Firefighting system design
(Foam, Water, GPM, Hydraulic Analysis)
Project Time Management Activity List & WBS
Project Cost Management Cost Management'!A1
Project Quality Management On time project
completion+- 10 allowable difference
in calculation
Verify results from the consultant report
Re-calculation & Revalidation
Project HR Management Project Organogram'!A1 Select Team
Kick-off meetingInitial training & understanding
Resource Management'!A1
Project Communication Management Stakeholder Register Communication Plan'!A1 Information / Report
distribution
Project Risk Management Risk Assessment'!A1 Manage & Control Risk
Project Procurement Management
Project Management Plan
Project Manageme
nt Plan
WBS
Activity List
Cost Manageme
nt
Quality Manageme
nt
Risk Manageme
nt
Communication
Management
Stakeholder RegisterSr. No.
Stakeholders PriorityStakeholder
interest in the project
RiskStrategy to
reduce impactDocument to
Report
1 Oil Installation 4Handling productsResponsible for the
facility
Lack of awareness
Lack of interestDemand chages
as per experience
Conduct preliminary meeting and explain scope
Periodic updation on the status of
the project
Draft ReportFinal Report
2 Operations Dept. 3
Overall responsible of the facilities
Responsible for safe receipt, storage and
dispatch of the product
Lack of interestVery technical
exercise
Periodic updation on the status of
the projectFinal Report
3 Construction Dept. 2
Responsible for execution of projects
keeping all safety measures in
consideration as recommended by
consultant
Lack of trust on design
Lack of support
Conduct preliminary meeting and explain scope
Periodic updation on the status of
the project
Draft ReportFinal Report
4Management Committee
1 Owner of the facility Ambiguity
Lack of interest
Presentation in ManCom and seek
approvalFinal Report
5 Explosive Dept. 2
Issue / renew explosive lisence on
the basis of recommendations mentioned in the
explosive rule
Lack of trust on design
Communicate results compared with consultant's
report
Final Report
Activity ListSr. No. Activity List
1 Presentation to ManCom for concept approval
2 Approval of the project charter
3 Finalization of Project Team
4 Kick-off meeting with stakeholders (internal)
5 Liturature Review - NFPA codes, Explosive Lisence)
6 Survey of the facility and data gathering
7 Interview with Facility Inchage
8 Measuring physical parameters of tank farm
9 Developing fire lines layout
10 Signing off the measurement and layout from Facility Incharge
11 Developemnt of Calculation template for foam and water requirements and GPM of fire pump
12 Conduct hydraulic analysis on Pipe flow expert
13 Validate results from consultant report
14 Prepare draft report and submit for review
15 Incorporate suggestions / recommendations and issue final report
Work Breakdown StructureSr.
NoTask Name Duration Start Finish
Predecessors
Resource Names
1 Presentation to ManCom for concept approval 1 day Fri 11/11/11
Fri 11/11/11 Project team leader
2 Approval of the project charter 1 day Mon 11/14/11
Mon 11/14/11 1
DGM HSE,GM Construction,GM Operations
3 Finalization of Project Team 3 days Tue 11/15/11
Thu 11/17/11 2 Project team leader
4 Kick-off meeting with stakeholders (internal) 1 day Fri 11/18/11
Fri 11/18/11 3 Project team leader
5 Liturature Review - NFPA codes, Explosive Lisence)
15 days Mon 11/21/11
Fri 12/9/11 1,2,3,4Engineer HSE,Engineer Operations,Engineer Construction
6 Survey of the facility and data gathering 7 days Mon 12/12/11
Tue 12/20/11
7 Interview with Facility Inchage 1 day Mon 12/12/11
Mon 12/12/11 5 Project team leader
8 Measuring physical parameters of tank farm 2 days Tue 12/13/11
Wed 12/14/11 7 Project team
9 Developing fire lines layout 3 days Thu 12/15/11
Mon 12/19/11 8 Project team
10 Signing off the measurement and layout from Facility Incharge 1 day Tue
12/20/11Tue
12/20/11 9Facility Incharge,Project team leader
11Development of Calculation template for foam and water requirements and GPM of fire pump 8 days Wed
12/21/11Fri
12/30/11 10
Engineer Construction,Engineer HSE,Engineer Operations
12 Conduct hydraulic analysis on Pipe flow expert 2 days Mon 1/2/12 Tue 1/3/12 11
Engineer Construction,Engineer HSE,Engineer Operations
13 Validate results from consultant report 2 days Wed 1/4/12 Thu 1/5/12 11,12 Project team leader
14 Prepare draft report and submit for review 7 days Fri 1/6/12Mon
1/16/12 13
GM Construction,GM Operations,Engineer Construction,Project team leader,Engineer HSE,Engineer Operations
15Incorporate suggestions / recommendations and issue final report 5 days Tue
1/17/12Mon
1/23/12 14
Engineer Construction, Project team leader, Engineer HSE,Engineer Operations
Gantt Chart
Cost Management Plan
Task NameDuration
(Days)Cost (Rs.)
Presentation to ManCom for concept approval 1 12,320.00Approval of the project charter 1 0.00Finalization of Project Team 3 14,784.00Kick-off meeting with stakeholders (internal) 1 4,928.00Liturature Review - NFPA codes, Explosive Lisence) 15 110,880.00Survey of the facility and data gathering 7 22,176.00
Developemnt of Calculation template for foam and water requirements and GPM of fire pump
8 59,136.00
Conduct hydraulic analysis on Pipe flow expert 2 14,784.00Validate results from consultant report 2 9,856.00Prepare draft report and submit for review 7 86,240.00Incorporate suggestions / recommendations and issue final report
5 61,600.00
Logistics 7 days 17,248.00Overhead 52 days 207,168.00
Total 52 621,120.00
Project Organogram
Sr. Executive(HSE)
Sr. Engineer(HSE)
Sr. Engineer(Constructio
n)
Sr. Engineer(Operations)
Resource ManagementWBS Element Responsible HR Services Software Hardware Facilities Communication Material
Presentation to ManCom for concept approval Project Team Leader Deliver Presentation Powerpoint PCProjector Board room
Approval of the project charter Project Team Leader Getting approvals Lotus NotesMS Office PC Email
Telephone
Finalization of Project Team Project Team Leader
Kick-off meeting with stakeholders (internal) Project Team Leader Conduct Meeting MS Office PCProjector
Presentation Hall
EmailTelephone
Liturature Review - NFPA codes, Explosive Lisence) Project Team PC Workstation EmailTelephone
NFPA CodesCopy of Explosive rulesConsultant Report
Survey of the facility and data gathering Project Team LeaderProject Team
MeasurementData gatheringInterviewsLayout design
- Measuring Tape Logistics EmailTelephone
Interview with Facility Inchage Project Team Leader Conduct Interview Meeting Measuring physical parameters of tank farm Project Team Measurements Measuring Tape
Developing fire lines layout Project Team Layout design Pipeflow Expert PC Workstation EmailTelephone
Signing off the measurement and layout from Facility Incharge Project Team Leader
Developemnt of Calculation template for foam and water requirements and GPM of fire pump
Project Team LeaderProject Team Calculations MS Office PC Workstation
NFPA CodesCopy of Explosive rulesConsultant Report
Conduct hydraulic analysis on Pipe flow expert Project Team LeaderProject Team Hydraulics Pipeflow expert PC Workstation
NFPA CodesCopy of Explosive rulesConsultant Report
Validate results from consultant report Project Team Leader Validation Consultant Report
Prepare draft report and submit for review Project Team Leader Report Preparation MS OfficeLotus Notes PC Workstation Email
Telephone
Incorporate suggestions / recommendations and issue final report Project Team Leader Report Preparation MS Office
Lotus Notes PC Workstation EmailTelephone
Communication Plan
Stakeholder Information Required Information provider Form of information Mode of information provide Time of information provision
Management Committee
Justification of the projectBenefits to the companyCost to the companySupport and resources required
Project Team Leader Powerpoint presentation
Management Committee Meeting Before charter approval
Construction Dept.
Consultant ReportTank and dyke wall dataPipeline and pump dataFireline layoutDraft ReportFinal Report
Project TeamManager Construction
Data SheetsReport
EmailPhysical measurement
During site surveyIssue of draft reportIssues of final report
Operations Dept. Draft ReportFinal Report
Project TeamManager Operations Report Email
During site surveyIssue of draft reportIssues of final report
Oil InstallationDraft ReportFinal ReportVisit Plan
Project TeamInstallation Manager Report Email
During site surveyIssue of draft reportIssues of final report
Risk AssessmentWBS Element Risk Probability Severity Risk
RatingRisk
Status Existing Controls Change Control
Presentation to ManCom for concept approval Concept would be rejected 1 3 3 Low Strong jestification with benefits to the company
Approval of the project charter Delay in approval 3 2 6 Medium Timely submission of charter and follow-up
Finalization of Project Team Unavailability of required skills 1 3 3 Low Skills hunting before project initiation
Kick-off meeting with stakeholders (internal) - 0 Low
Liturature Review - NFPA codes, Explosive Lisence) Unavailability of literaute 2 3 6 Medium Make liteature available in advance
Survey of the facility and data gathering Low Interview with Facility Inchage Facility Incharge unavailable 2 2 4 Medium Ask for Back-up in advance
Measuring physical parameters of tank farm Human error 2 3 6 Medium Data validation by Faclity incharge
Developing fire lines layout Design Error 2 3 6 Medium Validation through consultant report
Signing off the measurement and layout from Facility Incharge - 0 Low
Developemnt of Calculation template for foam and water requirements and GPM of fire pump Calculation Error 3 3 9 High Validation through consultant
report
Conduct hydraulic analysis on Pipe flow expert Calculation Error 3 3 9 High Validation through consultant report
Validate results from consultant report Difference in calculation & design 3 3 9 HighReverse engineering approach, development of template and re-calculation
Prepare draft report and submit for review Delay in Review 2 2 4 Medium Timely submission of report and follow-up
Incorporate suggestions / recommendations and issue final report - 0 Low
Change Management
Code Existing Issue Proposed Change Justification of ChangeImpact
Residual Risk ResponsibilityBudget Schedule Resources