Design Documentation Report

Embed Size (px)

Citation preview

  • 7/29/2019 Design Documentation Report

    1/317

    Design Documentation Report

    Tolna Coulee

    Advance MeasuresNelson County, North Dakota

    Prepared By

    US Army CorpsOf EngineersSt. Paul District / St. Louis District

    July 2011 100% Submittal

  • 7/29/2019 Design Documentation Report

    2/317

    Table of Contents

    1 Introduction ........................................................................................................................................... 1

    1.1 Existing Project Description ......................................................................................................... 1

    1.2 Current Conditions of Tolna Coulee ............................................................................................. 1

    1.3 Purpose .......................................................................................................................................... 2

    1.4 Authorization ................................................................................................................................ 2

    2 Project Features ..................................................................................................................................... 2

    2.1 Overview ....................................................................................................................................... 2

    2.2 Sheet Pile I-Wall ........................................................................................................................... 2

    2.3 Embankments ................................................................................................................................ 2

    2.3.1 Embankments next to I-wall. ................................................................................................ 2

    2.3.2 Embankment north of the Control Structure ......................................................................... 3

    2.4 Control Structure ........................................................................................................................... 3

    2.5 Riprap Erosion Protection ............................................................................................................. 3

    2.6 Access Road .................................................................................................................................. 3

    2.7 Cofferdams .................................................................................................................................... 3

    2.8 Previously Obtained Data ............................................................................................................. 4

    2.8.1 Topographic Data .................................................................................................................. 4

    2.8.2 Property Line Data ................................................................................................................ 4

    2.8.3 Related Construction Projects ............................................................................................... 4

    2.9 Property Acquisitions and Adjacent Properties ............................................................................ 4

    3 PERTINENT DATA ............................................................................................................................. 4

    3.1 Controlling Elevations .................................................................................................................. 44 PREVIOUS REPORTS ........................................................................................................................ 5

    5 Hydrology and Hydraulics .................................................................................................................... 5

    5.1 Introduction ................................................................................................................................... 5

    5.2 Straight Drop Structure ................................................................................................................. 5

    5.3 Stilling Basin ................................................................................................................................. 6

    5.4 Composite I-Wall/Embankment ................................................................................................... 6

    6 Geotechnical Engineering ..................................................................................................................... 7

    6.1 General .......................................................................................................................................... 7

    7 Civil Engineering .................................................................................................................................. 77.1 Introduction ................................................................................................................................... 7

    7.2 Technical Guidelines and References ........................................................................................... 7

    7.3 Source of Data for Existing Topographic Information ................................................................. 8

    7.4 Programs and Standards for Design and Drawings ....................................................................... 8

    7.5 Design Process and Standards for Civil Features ......................................................................... 8

    7.5.1 Geometric Design Criteria Access Road ............................................................................ 8

  • 7/29/2019 Design Documentation Report

    3/317

    7.6 Engineering Drawings for Embankments and Site Work ............................................................. 8

    7.7 Phase 1 Environmental Site Assessment....................................................................................... 9

    8 Structural Engineering .......................................................................................................................... 9

    8.1 General .......................................................................................................................................... 9

    8.2 Structure Design ............................................................................................................................ 9

    8.2.1 Stoplog Control Structure ..................................................................................................... 9

    8.2.2 Retaining Walls and Wing Walls .......................................................................................... 9

    8.2.3 Sheet Pile I-wall .................................................................................................................... 9

    8.2.4 Walkway ............................................................................................................................. 10

    8.2.5 Gantry Crane ....................................................................................................................... 10

    8.2.6 Lifting Beam ....................................................................................................................... 10

    8.2.7 Stoplogs ............................................................................................................................... 10

    8.3 Miscellaneous ............................................................................................................................. 10

    8.3.1 Frost Protection ................................................................................................................... 10

    9 Mechanical and Electrical Engineering .............................................................................................. 10

    9.1 Mechanical Design ...................................................................................................................... 10

    9.1.1 Gantry Crane and Hoist Selection ....................................................................................... 10

    9.2 Electrical Design ......................................................................................................................... 11

    10 Constructability ................................................................................................................................... 11

    10.1 Introduction ................................................................................................................................. 11

    10.2 Sequence of Construction ........................................................................................................... 11

    10.3 Embankments .............................................................................................................................. 11

    10.4 Structure ...................................................................................................................................... 11

    10.5 Coordination with Other Agencies ............................................................................................. 11

    11 Instrumentation ................................................................................................................................... 11

    11.1 Monitoring Points ....................................................................................................................... 11

    11.2 Construction Monitoring ............................................................................................................. 11

    11.3 Long-Term Performance Monitoring .......................................................................................... 11

    12 Cost Estimate and Construction Schedule .......................................................................................... 11

    12.1 Cost Estimate .............................................................................................................................. 11

    12.2 Construction Schedule ................................................................................................................ 12

    13 REVIEW DOCUMENTATION ......................................................................................................... 12

    13.1 District Quality Control (DQC) Review ..................................................................................... 1213.2 Agency Technical Review (ATR) ............................................................................................... 12

    13.3 Independent External Peer Review (IEPR) ................................................................................. 12

  • 7/29/2019 Design Documentation Report

    4/317

    Appendices

    Appendix A Plan Set

    Appendix B Specifications

    Appendix C Hydrology/Hydraulic Appendix

    Appendix D Geotechnical Appendix

    Appendix E Structural Appendix

    Appendix F Mechanical Appendix

    Appendix G Quantities

    Appendix H Cost Estimate and Construction Schedule

    Appendix I Engineering Considerations and Instructions for Field Personnel

    Appendix J Phase I Environmental Site Assessment

    Appendix K Quality Control Documentation

  • 7/29/2019 Design Documentation Report

    5/317

    1

    1 INTRODUCTION

    1.1 Existing Project Description

    Devils Lake is a natural lake located south of the City of Devils Lake, located in Ramsey County in the

    northeast portion of North Dakota. Since 1940 the lake has risen fifty-two feet, with almost twenty-nine feet of rise since 1993. In March 1993 Devils Lake had a surface area of 44,230 acres. At its

    April 30, 2010 elevation (1452.63feet NAVD88) Devils Lake covered about 177,100 acres. During that

    same period the volume of water in Devils Lake had grown by more than six times. The current lake

    elevation (May 11, 2011) is 1454.0 feet. All elevations in this report are in feet and referenced to

    North American Vertical Datum of 1988 (NAVD88) unless specifically stated otherwise. The

    conversion from NAVD88 to National Geodetic Vertical Datum of 1929 (NGVD29) in the area of this

    project is: NGVD29 = NAVD88 -1.17 feet.

    Devils Lake naturally spills into Stump Lake (located east of Devils Lake) at an elevation of

    approximately 1447.7. Since water began flowing into Stump Lake in 1999, Stump Lake has now

    been filled and has become part of Devils Lake. At its current water levels, Devils Lake has no natural

    outlet. At an elevation of 1459.2 the lake overtops the high point in Tolna Coulee and begins to spillthrough the coulee into the Sheyenne River, a tributary of the Red River of the North. Tolna Coulee

    is located at the southwest end of what was Stump Lake. Devils Lake has reached its spill elevation

    and overflowed into the Sheyenne and Red Rivers at least twice during the past 4,000 years. The

    lake last spilled into the Sheyenne River less than 2,000 years ago. At its spill elevation, Devils Lake

    covers more than 261,000 acres.

    The State of North Dakota completed construction of an outlet to allow water from the West Bay of

    Devils Lake to flow into the Sheyenne River in the summer of 2005. The outlet is made up of two

    pump stations, a series of buried pipelines and open channels, a sand filter, three siphons, a gated

    control structure and a stilling basin. The original pump capacity of the system was 100 cubic feet

    per second (cfs). Modifications to increase the pump capacity to 250 cfs were approved by the North

    Dakota State Engineer in June 2010. Discharge from the outlet is limited by the 600 cfs channelcapacity of the upper Sheyenne River and the North Dakota Department of Healths maximum

    allowed concentration level of 750 milligrams per liter of sulfate at the discharge point in the

    Sheyenne River. The West Bay of Devils Lake is located on the other side of Devils Lake from the

    Tolna Coulee project and is several miles from Tolna Coulee. This information is provided only for

    situational awareness, since it adds flow to the Sheyenne River upstream of the confluence of Tolna

    Coulee and the Sheyenne River.

    At the time of this project, the State of North Dakota is planning to expand its west end pumped

    outlet with an additional capacity of 100 cfs and construct an east end pumped outlet from East

    Devils Lakewith a capacity of 350 cfs, which is currently planned to transport water to Tolna Coulee,just downstream of the high point in the coulee. The east end pumped outlet would be located in

    the vicinity of the Tolna Coulee project, but would not impact the design of the Tolna Coulee project

    since it would discharge into Tolna Coulee downstream of the project.

    1.2 Current Conditions of Tolna Coulee

    Tolna Coulee is a natural outlet from the Devils Lake basin. There is a significant layer of silts and

    organic material with grassy vegetation at the bottom of Tolna Coulee that will have to be removed

    before an embankment and/or or structure can be constructed. This layer of silt and organic material

    varies in thickness to as much as 14 feet near the middle of the coulee. Under this soft material is a

  • 7/29/2019 Design Documentation Report

    6/317

    2

    layer of sand and boulders, with stiff clay underneath. Due to the high ground water (at or near the

    ground surface) and the seepage of groundwater from the sides of the coulee near the toe of the

    coulee slopes, dewatering during construction will be required. Due to the rising lake level, a

    cofferdam will be constructed on the east side of the project.

    1.3 Purpose

    The purpose of the Tolna Coulee project is to prevent catastrophic release of flows through Tolna

    Coulee into the Sheyenne River. The State of North Dakota has also requested that the Corps of

    Engineers include a control structure with the project to allow controlled discharge down to

    elevation 1446 feet NGVD29 (1447.2 NAVD88). HQUSACE directed that Measures to control water

    elevation or releases above or below 1458 will be borne by the non-Federal sponsor, including

    engineering and design. (Note the elevation referenced in the HQ memo is referenced to NGVD29

    Datum)

    1.4 Authorization

    The Tolna Coulee Advance Measures project is authorized under PL84-99, Flood Control and Coastal

    Emergencies.

    2 PROJECT FEATURES

    2.1 Overview

    The project includes: Construction of a sheet pile I-wall with a top elevation of 1467.2 (NAVD88), a

    stoplog control structure with a stoplog crest elevation of 1459.2 and a top of concrete footing

    elevation of 1447.2. The stoplog control structure includes concrete piers with 10 foot clear spacing

    between them and a catwalk with overhead rail to allow removal of the stoplogs. Construction of

    the sheet pile I-wall will require embankment to be constructed upstream and downstream of the I-

    wall. The embankment on the west side of the sheet pile I-wall between and the north bank of the

    coulee and the north end of the structure will be ramped up to elevation 1467.2 to allow access tothe structure.

    2.2 Sheet Pile I-Wall

    A sheet pile I-wall will extend from the south side of the structure to the south bank of Tolna Coulee

    and from the north side of the structure to the north bank of Tolna Coulee. This I-wall will have a top

    elevation of 1467.2 (NAVD88), which includes 4 feet of freeboard to limit wave overtopping to

    acceptable levels. The I-wall on the north side of the structure will include an embankment which

    ramps up to the same elevation as the sheet pile on the downstream side of the sheetpile to allow

    access to the control structure.

    2.3 Embankments

    Embankment construction and design is consistent with District guidance. Due to winter time

    construction, 24 hour operation will be required to reduce the issues with frozen material.

    2.3.1

    Embankments will be constructed on the upstream and downstream sides of the sheet pile I-wall.

    These embankments are intended to reduce the stick-up of the I-wall to acceptable levels and

    eliminate the need for a king pile system to support the sheet pile wall. The tops of these

    Embankments next to I-wall.

  • 7/29/2019 Design Documentation Report

    7/317

    3

    embankments will be at elevation 1461.2 south of the control structure and elevation 1463.2

    north of the control structure.

    2.3.2

    An embankment will be constructed to elevation 1463.2 on both sides of the sheet pile I-wall. The

    fill on the downstream side of the sheet pile will be ramped up to the full height of the sheet pile I-

    wall to provide access to the control structure. The embankment on the upstream side of the

    sheet pile will have a consistent top elevation of 1463.2.

    Embankment north of the Control Structure

    2.4 Control Structure

    A control structure will be constructed near the middle of the coulee and will use stoplogs to control

    water levels in the Devils Lake basin down to elevation 1447.2 (NAVD88). The control structure

    includes a concrete footing/sill, concrete abutments and wing walls, 11 concrete piers with 10 foot

    clear openings/bays, and a full length catwalk with overhead monorail system to allow removal of

    the stoplogs. The catwalk will be designed to allow access with an ATV and a trailer or cart, which is

    expected to be used to haul stoplogs off the structure.

    2.5 Riprap Erosion ProtectionRiprap erosion protection will be placed both upstream and downstream of the structure. The riprap

    on the lake side slopes of the embankment is sized for wave impact from Stump Lake.

    2.6 Access Road

    A permanent access road will be constructed from 33rd Street NE, down the hill to the structure. The

    access road will be for maintenance purposes and to access the structure to remove stop logs. The

    access road will have a maximum grade of 6% and it will be 20 wide with ditching along both sides.

    Wide construction limits will be provided in the event the contractor wants to widen the road for

    hauling materials to the project site.

    2.7

    Cofferdams

    Due to the rising lake level, a cofferdam will be required on the east side (lake side) of the structure.

    Since the work is expected to be completed in March, the lake is expected to be frozen for the

    majority of the construction period, so riprap for erosion protection of the cofferdam will not be

    required. A cofferdam design has been prepared to include in the plans as a suggestion and to assist

    with preparation of estimates; however, the specifications will require the Contractor to design their

    own cofferdam.

    The cofferdam will not be the only line of protection from flows to the Sheyenne River and

    downstream, as the existing Tolna Coulee high points will remain in place. Because the cofferdam

    will be a non-critical structure, the actual height of the cofferdam will be up to the contractor and

    will most likely depend on the contractors equipment protection needs. The contractor will submit a

    cofferdam plan for USACE approval before the cofferdam is constructed.

    The cofferdam and dewatering provides the dry working area needed to construct the embankments

    under proper conditions or as near to proper conditions as can be expected in North Dakota in the

    winter.

  • 7/29/2019 Design Documentation Report

    8/317

    4

    2.8 Previously Obtained Data

    2.8.1

    Existing topographic data utilized for the design and drawings was from LIDAR and field survey

    information performed by City of Devils lake when the maintenance excavation in the coulee was

    performed. The project area was then surveyed manually by a State of North Dakota survey crewin May 2011. The coordinate system and projection of the topographic mapping data is NAD83

    (2007), North Dakota State Plane Coordinate System, North Zone (U.S. Survey Feet). The elevation

    datum of the topographic mapping data is NAVD88 (U.S. Survey Feet).

    Topographic Data

    2.8.2

    The deed for the existing city owned property around the project site was supplied by the City of

    Devils Lake.

    Property Line Data

    2.8.3

    2.8.3.1 Devils Lake City Embankments, Phase 2B and Phase 3

    Related Construction Projects

    Levees near and around Devils Lake are being raised to an elevation of 1467.2. These projectsinclude levee raises, pump stations, and road raises and other work associated with protecting

    the City of Devils Lake from the rising Lake Level. A design criterion for these projects was that

    if a PMF occurred with an initial lake elevation of 1458.0, outflow through Tolna Coulee

    (assuming no erosion) would limit the maximum lake elevation at Tolna Coulee to 1461.9. The

    Tolna Coulee project must not increase the lake elevation for the PMF.

    2.8.3.2 East Devils Lake Outlet

    The North Dakota State Water Commission is planning to construct an outlet and channel from

    East Devils Lake to Tolna Coulee. The route begins on East Devils Lake, runs east southeast 5-

    1/2 miles and outlets into Tolna Coulee. The outlet will discharge into Tolna Coulee

    downstream from the control structure. The outlet plan consists of a pumping plant with

    several pumps with the total capacity of 350 cubic feet per second (cfs).

    2.9 Property Acquisitions and Adjacent Properties

    The City of Devils Lake owns the property that this project will be constructed on. All work is being

    done within the property owned by the City of Devils Lake.

    3 PERTINENT DATA

    3.1 Controlling Elevations

    The following table lists the finish elevations of key features of the project. All elevations shown

    refer to NAVD88.

    Table 3 1 Controlling Elevations

    DESCRIPTION ELEVATION (NAVD88)

    Top of Sheet Pile I-Wall 1467.2

    Top of Berm North of Control Structure 1463.2*

  • 7/29/2019 Design Documentation Report

    9/317

    5

    Top of Berm South of Control Structure 1461.2

    Top of Sill at Stop Logs 1447.2

    Top of Stoplogs 4 Center Bays 1458.2

    Top of Stoplogs 8 Remaining Bays 1459.2

    *A ramp will be constructed on the north side of the structure on the west side of the sheet pile I-

    wall to allow access to the catwalk. The earth ramp will be from elevation 1463.2 to elevation

    1467.2.

    4 PREVIOUS REPORTS

    Tolna Coulee Outlet Erosion Report, Barr Engineering, Inc., For: U.S. Army Corps of Engineers,St. Paul District, 2001.

    Project Information Report, Advance Measures, Tolna Coulee, Nelson County North Dakota,U.S. Army Corps of Engineers, St. Paul District, Revised 22 March 2011.

    5 HYDROLOGY AND HYDRAULICS

    5.1 Introduction

    Levees near and around Devils Lake are being raised to an elevation of 1467.2 ft. These projects

    include levee raises, pump stations, and road raises and other work associated with protecting the

    City of Devils Lake from the rising Lake Level. The top of embankment for these levee designs is

    predicated on Tolna Coulee flowing into the Sheyenne River when the lake level at Tolna Coulee

    exceeds elevation 1459.2 ft.

    The following paragraphs provide a summary of the Hydraulic Design considerations for the Tolna

    Coulee Project. Detailed information related to the Hydrology and Hydraulic design of the Tolna

    Coulee Project can be found in the Hydrology/Hydraulics Appendix (Appendix C).

    5.2 Straight Drop StructureIn consistency with flood protection efforts in the Devils Lake sub-basin, including the City of Devils

    Lake Embankments and Roads Acting as Water Barriers, the Tolna Coulee control structure is

    designed for a Inflow Design Flood (IDF) of Probable Maximum Flood ( PMF) with the lake starting

    at full pool (Elevation 1459.2 ft).

    The PMF peak lake elevation at Tolna Coulee for Without Project condition assuming No-

    erosion is 1463.2 ft with a peak discharge of approximately 3000 cfs. Design of the City of Devils

    Lake Embankments is based on a peak lake level of 1463.2 ft at Tolna Coulee for a PMF inflow with

    the lake starting at full pool (Elevation 1459.2 ft).

    To cause no impacts to the design of the City of Devils Lake Embankments, the design discharge for

    the structure at Tolna Coulee must not result in an increase to the peak still water level elevation

    above 1463.2 ft at Tolna Coulee for a PMF inflow to Devils Lake on a starting pool elevation of

  • 7/29/2019 Design Documentation Report

    10/317

    6

    1459.2 ft. This corresponds to a minimum peak discharge of approximately 3000 cfs at a PMF peak

    lake elevation of 1463.2 ft. Selection of a design discharge exceeding 3000 cfs would not cause

    impacts to the design of the City of Devils Lake Embankments. A target design discharge greater than

    approximately 3000 cfs was not pursued, as action is required at downstream communities for flows

    less than 3,000 cfs.

    Based on the assessment that substantial erosion could precede peak lake elevation for the design

    event, the weir structure is sized to pass approximately 3000 cfs under free flow conditions at a peak

    lake elevation of 1463.2 ft. Steady state hydraulic modeling and analysis using HEC-RAS version 4.1.0

    was conducted to develop rating curves for with and without project conditions assuming No-

    Erosion. The PMF inflow of 1.44 million acre-feet was routed on a daily time step using a with

    project rating curve to ensure the structure does not result in an increase to the peak water surface

    elevation of 1463.2 ft.

    Tailwater Depth (d2) for the Tolna Coulee structure is assumed to be variable from 5 feet to 17.2 feet

    for the design event as Tolna Coulee erodes. Tailwater elevations for structural and geotechnical

    analysis of different headwater and tailwater combinations are provided in Appendix C.

    5.3 Stilling BasinFor the design water surface elevation of 1463.2 ft, stop-logs at 1458.2 ft and 1459.2 ft are designed

    to pass 5 ft and 4 ft of total head respectively. Drop heights from stop logs at elevation 1458.2 ft and

    elevation 1459.2 ft are 13.6 ft and 14.6 ft respectively. Stilling basin requirements were determined

    by analyzing peak design head at each invert elevation for both high and low tailwater scenarios.

    Basin dimensions were calculated using experimental results and design guidelines proposed by

    Donnelly and Blaisdell in the technical paper, Straight Drop Spillway Stilling Basin. The floor of the

    designed stilling basin is at elevation 1444.6 ft. The required stilling basin is 49.5 feet long with 43.5

    feet between the straight drop and the baffle blocks. The 16-inch square baffle blocks occupybetween 50% and 60% of the total stilling basin cross sectional area.

    5.4 Composite I-Wall/EmbankmentTo be consistent with the approved Devils Lake Flood Risk Management Project Design Criteria and

    Project Considerations Report, a freeboard requirement of the maximum of 3 feet or wind/wave

    requirements was adopted for the Tolna Coulee structure.

    Wind and wave impacts were analyzed using Coastal Engineering Manual and Shore Protection

    Manual methodologies. For the City of Devils Lake Embankments project, wave analysis and design

    following Shore Protection Manual methodology required that wave run-up be contained by the

    embankments. Because run-up does not apply to vertical structures, guidance for allowable

    overtopping from the Coastal Engineering Manual was used.

    For a lake level of 1463.2 ft, Wind Setup of 0.4 feet, and significant wave height of 3.3 feet - 4 feet of

    freeboard (top of structure elevation of 1467.2 ft) is provided to ensure the structure does not

    exceed a No Damage overtopping discharge of 0.1 cfs/ft for the design event.

  • 7/29/2019 Design Documentation Report

    11/317

    7

    Riprap erosion protection is designed for locations on the Composite I-Wall/Embankment and

    upstream and downstream of the spillway / stilling basin structure using applicable criteria.

    6 GEOTECHNICAL ENGINEERING

    6.1 General

    This section provides the geotechnical engineering in support of the final design, specifications and

    cost estimate for the Tolna Coulee Advance Measures project. The project includes: Construction of a

    composite I-wall/embankment with a top elevation of 1467.2 (NAVD88), a stop log control structure

    with a stop log crest elevation of 1458.2 for the 4 center bays and 1459.2 for the remainder of the

    bays, and a top of concrete footing elevation of 1447.2. Construction of the sheet pile I-wall will

    require embankment to be constructed upstream and downstream of the I-wall to limit stickup to

    acceptable levels. An embankment with a top elevation of 1463.2 and will be constructed between

    the north end of the structure and the north bank of the coulee, with a ramp to 1467.2 to allow

    access to the structure. An embankment with a top elevation of 1461.2 and will be constructed

    between the south end of the structure and the south bank of the coulee. Detailed information

    related to the geotechnical design criteria, design cases, and other information related to

    geotechnical design can be found in the Geotechnical Appendix (Appendix D).

    7 CIVIL ENGINEERING

    7.1 Introduction

    This section summarizes the proposed layout, method of analyses, and support for preparation of

    the plans, specifications, and cost estimate. The layout attempted to optimize the use of the existing

    ground, avoid private property, and meet conditions needed to suit subsurface properties in an

    effort to reduce overall cost. In specific, the civil portion of the project involved the design and

    layout of embankments, site work, access roads, and site drainage. The embankment was utilized

    around the structure and sheetpile to provide access, meet passive and uplift pressures, and

    eliminate sliding of the structure. An embankment elevation of 1463.2 was followed on the north

    side of the structure and an embankment elevation of 1461.2 was utilized on the south side of the

    structure. A half mile long gravel road, turnaround, and parking spaces were designed to provide

    access to the structure. In addition a storage yard was included for the storage of stop logs needed to

    operate the closure structure. Lastly roadside ditching was utilized to convey drainage along its

    natural path.

    7.2 Technical Guidelines and References

    1. A/E/C CADD Standard, Release 3.0; U.S. Army Engineer Research and Development Center,Vicksburg, MS; September 2006.

    2. A/E/C CADD Standard Supplement, Release 6.2.0; U.S. Army Corps of Engineers, St. PaulDistrict; July 2004.

    3. A Policy on Geometric Design of Highways and Streets, Fifth Edition; pp. 131-229, 231-234,and 380-389; American Association of State Highway and Transportation Officials

    (AASHTO); 2004.

  • 7/29/2019 Design Documentation Report

    12/317

    8

    4. United States National CAD Standard, Version 4.0; National Institute of Building Sciences;July 2009.

    5. Guidelines for Geometric Design of Very Low-Volume Local Roads; American Association ofState Highway and Transportation Officials (AASHTO); 2001

    7.3

    Source of Data for Existing Topographic Information

    Existing topographic data utilized for the design and drawings was from topographic LIDAR surveys

    and field survey information performed by City of Devils lake. The project area has been surveyed

    by a State of North Dakota survey crew in May 2011 and the data is in the process of being converted

    for its use in the design. The coordinate system and projection of the topographic mapping data is

    NAD83 (2007), North Dakota State Plane Coordinate System, North Zone (U.S. Survey Feet). The

    elevation datum of the topographic mapping data is NAVD88 (U.S. Survey Feet).

    7.4 Programs and Standards for Design and Drawings

    The computer-aided drafting and design (CADD) program used for the drawings utilized MicroStation

    V8i (Version 8.11, October 2008) and topographic data with INROADS generated TIN file, profiles,

    and cross sections. All drawings adhered to national, Mississippi Valley Division, and St. Paul DistrictCADD standards.

    7.5 Design Process and Standards for Civil Features

    Roadway design was based on the standards included in AASHTOs 2004 bookA Policy on Geometric

    Design of Highways and Streets (Reference 3) ) andAASHTOs 2001 book Guidelines for Geometric

    Design of Very Low-Volume Local Roads (Reference 5).

    7.5.1

    The access road begins 800 feet West from the East edge of section 19 on 33rd Street NE at sta

    0+00 and continues to the south through the natural swale to the project site. The alignment is

    specifically designed to minimize earthwork and reduce vertical grades to acceptable levels. The

    road is classified as a rural minor access road. The road surface consists of gravel at a width of 20

    which includes the shoulders. The specific design information to design the horizontal curves are

    as follows:

    Geometric Design Criteria Access Road

    Design speed 20 mph Design Stopping Sight Distance 115 ft Superelevation e=0 Side friction factor f=0.13

    The vertical alignment of Tolna Coulee access road navigates a difference of 40 in elevation over

    2500 feet in length approximately. The vertical profile of the road is as follows:

    Design speed 20 mph Roadway max Slope -6.0% Design Stopping Sight Distance 115 ft Rate of Vertical Curvature, K = 7 for crest curves and K=17 for sag curves

    7.6 Engineering Drawings for Embankments and Site Work

    Drawings produced for the submittal utilized the following information:

    LIDAR Topographic Survey Data

  • 7/29/2019 Design Documentation Report

    13/317

    9

    City of Devils Lake Field Survey Data MicroStation V8i model and sheet seed files Design files including cross-sections, alignment, and TIN files USACE Standards

    Civil engineering drawings and plans prepared concurrent with this report are included in AppendixA.

    7.7 Phase 1 Environmental Site Assessment

    The St. Paul District has performed a Phase I Environmental Site Assessment (ESA) in conformance

    with the scope and limitations of American Society for Testing and Materials (ASTM) Practice E 1527-

    05. The environmental site assessment has revealed no evidence of recognized environmental

    conditions in connection with the subject properties.

    8 STRUCTURAL ENGINEERING

    8.1 General

    The structural design of the Tolna coulee outlet project is comprised of five major components

    stoplog control structure, including a walkway, overhead frame and monorail, pickup beam, and

    stoplogs; upstream approach walls; downstream wing walls; and left and right bank I-walls. Detailed

    information related to the structural design criteria, design loads, load cases, and other information

    related to structural design can be found in the Structural Appendix (Appendix E).

    8.2 Structure Design

    Structural design of hydraulic structures is in accordance with EM 1110-2-2104 and EM 1110-2-2105

    for reinforced concrete and structural steel, respectively. A single load factor of 1.7 plus hydraulic

    factor of 1.3 are used for reinforced concrete. Structural design for non-hydraulic structures is in

    accordance with ACI 318-05. The design of the walkway and other steel structural components are in

    accordance with AISC Steel Construction Manual. Design information for the following structures can

    be found in the Structural Appendix.

    8.2.1

    The stoplog control structure is an approximately 66-feet wide, 162-feet long and 26-feet high

    reinforced concrete structure. The structure consists of reinforced concrete side walls with a

    reinforced concrete slab in between. There are 11 reinforced concrete piers to support the

    walkway and stop logs. A sheetpile cutoff is included along the entire perimeter of the slab and is

    tied to the adjacent sheetpile I-walls.

    Stoplog Control Structure

    8.2.2

    There are 2 retaining walls on each side of the control structure on the upstream side and two

    wing walls on the downstream side of the structure.

    Retaining Walls and Wing Walls

    8.2.3

    The sheet pile I-wall is designed as a cantilevered wall. The top of the sheet pile wall will be cut off

    at the design elevation. A cap will not be installed on the sheet pile I-wall. The exposed height of

    Sheet Pile I-wall

  • 7/29/2019 Design Documentation Report

    14/317

    10

    the sheet pile on the south embankment is 6 feet. The exposed height of the sheet pile on the

    north embankment is 4 feet.

    8.2.4

    A 5 foot wide (clear distance) walkway will be constructed across the entire width of the control

    structure, and will be supported by the concrete piers. The walkway is intended to provide access

    for inspection and for removal of the stoplogs. It must be wide enough to accommodate an ATV to

    facilitate removal of the stoplogs.

    Walkway

    8.2.5

    A gantry crane with V-shaped steel wheels will run on angle iron tracks for the length of the

    walkway. The gantry crane will support the hoist and pickup beam.

    Gantry Crane

    8.2.6

    A lifting beam will be required to facilitate removal of the stoplogs. The latching mechanism will

    be designed to work with the welded studs on the sides of the stoplogs. The lifting beam and

    stoplogs will be specified as a system to minimize chances of the stoplogs and lifting beam not

    working properly.

    Lifting Beam

    8.2.7

    The stoplogs will be constructed of steel and will be galvanized. Pickup will be by welded studs on

    the sides of the stoplogs or by slots cut in the tops of the stoplogs.

    Stoplogs

    8.3 Miscellaneous

    8.3.1

    In general, a minimum of five feet of cover is maintained over the base of foundations for frost

    protection.

    Frost Protection

    9 MECHANICAL AND ELECTRICAL ENGINEERING

    9.1 Mechanical Design

    Mechanical design for the control structure is limited to the gantry crane and hoist system to be used

    for removal of stop logs.

    9.1.1

    The control structure will be equipped with a gantry crane and hoist system to remove the

    stoplogs from the stoplog slots.

    Gantry Crane and Hoist Selection

    The selected components include a gantry crane, and a manually operated chain hoist. Thegantry crane will ride on steel V-shaped wheels to allow easy travel without electric power. The

    gantry crane will include a transverse I-beam to allow the hoist to travel sideways within the

    frame since the stoplog slots are off-set from the centerline of the walkway. The manually

    operated chain hoist was selected due to the lack of electric power at the site.

    Gantry crane and hoist information, including loads used in the structural design and structural

    calculations are presented in Appendix E.

  • 7/29/2019 Design Documentation Report

    15/317

    11

    9.2 Electrical Design

    There is no electrical power at the site and there is no need for electric equipment or lights. The

    hoists to be used to remove the stop logs are hand powered and all maintenance work and stop log

    removal can be done during daylight hours so there is no need for lighting. If observation is needed

    at night, portable light plants can be brought in to provide the necessary light.

    10CONSTRUCTABILITYInformation will be added to this section prior to the BCOE submittal.

    10.1 Introduction

    The compressed schedule for design and construction of the project resulting from the rising lake

    levels will require that the majority of this project be constructed in the winter.

    10.2 Sequence of Construction

    10.3 Embankments

    Due to the plan to construct the majority of this project during the winter months, an effort has been

    made to minimize earthwork and limit the compaction requirements for embankment. For the

    earthwork that is required, 24 hour operation during construction will be required to minimize issues

    with freezing of the fill between lifts.

    10.4 Structure

    10.5 Coordination with Other Agencies

    11INSTRUMENTATION

    Information will be added to this section prior to the BCOE submittal.

    11.1 Monitoring Points

    11.2 Construction Monitoring

    11.3 Long-Term Performance Monitoring

    12COST ESTIMATE AND CONSTRUCTION SCHEDULE

    12.1 Cost Estimate

    The cost estimate was prepared using MCACES Second Generation (MII) software, version 3.1, Build2. The cost estimate is based on the acquisition plan, which includes the use of an IFB restricted to

    small businesses. As such, it includes a subcontracting plan and prime contractor overhead rate that

    would be likely for a small business. Productivity was adjusted within the estimate for certain items

    to account for the impacts of cold weather and snow due to the requirement to complete the

    majority of this project during the winter months. Contingencies were developed using the

    abbreviated risk analysis spreadsheets developed by the Corps of Engineers Cost DX.

  • 7/29/2019 Design Documentation Report

    16/317

    12

    12.2 Construction ScheduleA construction schedule was developed for the project that shows that the project can be

    constructed by March 12, 2012, assuming a NTP of 7 October 2011. This schedule, however, does

    not include time for weather days, meaning that the Contractor will be expected to work through the

    winter weather and make accommodations to their operations and planning to account for the

    expected severe weather. The schedule also shows that multiple crews will be required to completethe project on time.

    13REVIEW DOCUMENTATION

    13.1 District Quality Control (DQC) Review

    Documentation will be added after the DQC review has been completed.

    13.2 Agency Technical Review (ATR)

    Documentation will be added after the ATR has been completed.

    13.3 Independent External Peer Review (IEPR)

    Documentation will be added after the IEPR has been completed.

  • 7/29/2019 Design Documentation Report

    17/317

    Appendix A

    Plan Set

    ---

    Provided Under

    Separate Cover

  • 7/29/2019 Design Documentation Report

    18/317

    Appendix B

    Specifications

    ---

    Provided Under

    Separate Cover

  • 7/29/2019 Design Documentation Report

    19/317

    Appendix C

    Hydrology/Hydraulic Appendix

  • 7/29/2019 Design Documentation Report

    20/317

  • 7/29/2019 Design Documentation Report

    21/317

    Tolna Coulee: H&H Appendix Page 2

    TolnaCouleeControlStructure

    FunctionoftheTolnaCouleeStructure:

    Apreliminaryanalysis,TolnaCouleeOutletErosion(BARREngineering,2001)(Reference1),examined

    both

    the

    hydraulic

    and

    the

    geotechnical

    parameters

    of

    Tolna

    Coulee.

    The

    preliminary

    analysis

    indicates

    thatgiventhenatureofthesoils,thereisahighpotentialforsevereerosiontooccur. Erosioncould

    significantlyincreasetheoutflowthroughthecouleeintheeventofanaturaloverflowduetothelarge

    volumeofwaterstoredinthelake. Ananalysiswasdoneonthepotentialoutflowassociatedwiththe

    ProbableMaximumFlood(PMF). Theanalysisassumesaninitialfullpoollakeelevationof1459.2

    ft. Table1comparesthepeakandsustainedoutflowsforthePMFassumingnoerosionofthecoulee,

    andwitherosion.

    Table1a:TolnaCouleeNaturalCondition(NoProject)OutflowComparison

    SummaryStatistic NoErosion Erosion

    PeakElevation 1463.2 1462.7

    Peak

    Outflow

    (cfs)

    3,000

    14,000

    Daysabove2,500cfs 51 136

    Daysabove12,000cfs 0 19

    Volumeinfirst180days(acreft.) 592,000 1,833,000

    Volumeinfirst365days(acreft.) 982,000 2,379,000

    Assumptions:

    a)StartingWSEL=1459.2ft

    b)Inflowvolume=1/2ProbableMaximumFlood(PMF)(1,440,000acreft.)

    Table1ashowsuncontrolledflowsassociatedwitherosioncouldexceed12,000cfsforapproximately19

    dayswithapeakoutflownear~14,000cfsinTolnaCoulee.

    ThestructuredescribedinthisdocumentistobelocatedupstreamofthenaturalhighpointofTolna

    CouleenearStumpLake(Figure1b). Shouldthedownstreamhighpointerode,causingacapacityofthe

    highpointtoexceedapproximately3000cfsattheProbableMaximumFlood(PMF)lakeelevation

    of1463.2ft,thecontrolstructurerestrictspeakflowstolessthanwouldhaveoccurrednaturally. Stop

    logsareincludedinthestructuretoallowforacontrolledloweringofthelake. Stoplogswouldbe

    removedtomatchnaturaldownstreamerosiontoamaximumflowrateofapproximately3000cfs. The

    samevolumeofwaterthatwouldevacuatethelakewithouttheprojectshouldbeallowedtoevacuate

    thelakeoveralongerduration.

    ASAFTypestraightdropstillingbasin,inaccordancewithdesignguidelinesproposedbyDonnellyand

    Blaisdell(1954),hasbeendesignedforenergydissipationimmediatelydownstreamofthestructure.

    Forthe

    SAF

    straight

    drop

    spillway

    stilling

    basin,

    Water

    falling

    over

    the

    spillway

    crest

    falls

    onto

    aflat

    apron. Thenappeisbrokenupbyfloorblocks,whichalsopreventdamagingscourofthedownstream

    channelbanks. Scourofthedownstreamchannelbedispreventedbyanendsill. Flaringwingwalls,

    triangularinelevation,preventerosionofthedamfill(Reference2).

  • 7/29/2019 Design Documentation Report

    22/317

    0 10000 20000 30000 40000 50000 60000 1340

    1360

    1380

    1400

    1420

    1440

    1460

    1480

    Channel Distance (ft)

    Elevation

    (NAVD

    1988)(ft)

    Highway

    15

    TolnaDam

    RailroadEmbankment

    CountyR

    oad24

    98thAvenueNE

    CountyR

    oad4

    3 2 n d S t r e

    e t N E

    Sheyenne River

    Natural High

    Figure 1b: Tolna Coulee Profile - Devils Lake to the Sheyenne River

  • 7/29/2019 Design Documentation Report

    23/317

    Tolna Coulee: H&H Appendix Page 4

    StructureType:

    DesignoftheDevilsLakeTolnaCouleecontrolstructurefollowstheguidelinesforaSaintAnthony

    Falls(SAF)StraightDropStructureoutlinedinthearticleStraightDropSpillwayStillingBasinby

    DonnellyandBlaisdell(Reference2). TheSAFstructurewasselectedinlieuofaCaliforniaInstituteof

    Technology(CIT)structure(Reference3),asthemaximumdesigndropheight/criticaldepthvalueof

    5.5fortheTolnaCouleestructureliesoutsideofexperimentallytestedvaluesforaCITstructure

    (Reference4). TheSAFstillingbasincanbeusedforawiderangeofdischarge,headonthecrest,crest

    length,heightofdrop,anddownstreamtailwaterlevel[s](Reference1). Historyofhighlyvariablelake

    levels,potentialforerosionofthenaturalhighpointdownstreamofthestructure,andintended

    operationmakeitcriticalthatthestructurebeabletoperformoverawiderangeofscenarios.

    SelectionofInflowDesignFlood(IDF):

    InconsistencywithfloodprotectioneffortsintheDevilsLakesubbasin,includingtheCityofDevilsLake

    EmbankmentsandRoadsActingasWaterBarriers,theTolnaCouleecontrolstructureisdesignedfora

    InflowDesignFlood(IDF)ofProbableMaximumFlood(PMF)withthelakestartingatfullpool

    (Elevation1459.2

    ft).

    Information

    related

    to

    the

    accepted

    PMF

    event

    at

    Devils

    Lake

    is

    contained

    in

    the

    DevilsLakeFloodRiskManagementProjectDesignCriteriaandProjectConsiderationsReport

    (Reference5).

    DesignDischarge:

    Thedesignwatersurfaceelevationof1464.2ftfortheCityofDevilsLakeEmbankmentsisbasedona

    PMFinflowvolumeof1.44MillionAcreFeetwithafullpoolstartinglakeelevationof1459.2ft. The

    PMFpeaklakeelevationatTolnaCouleeassumingnoerosionis1463.2ftwithanapproximatepeak

    dischargeof3000cfs. ThedesignwatersurfacefortheCityofDevilsLakeEmbankmentsassumes1

    footoflakeslopefromtheCityofDevilsLakeEmbankmentstotheoutflowatTolnaCoulee.

    TocausenoimpactstothedesignoftheCityofDevilsLakeEmbankments,thedesigndischargeforthe

    structureatTolnaCouleemustnotresultinanincreasetothepeakstillwaterlevelelevationabove

    1463.2ftatTolnaCouleeforaPMFinflowtoDevilsLakeonastartingpoolelevationof1459.2ft. This

    correspondstoaminimumpeakdischargeofapproximately3000cfsatthePMFpeaklakeelevation

    of1463.2ft. Selectionofadesigndischargeexceeding3000cfswouldnotcauseimpactstothedesign

    oftheCityofDevilsLakeEmbankments. Atargetdesigndischargegreaterthanapproximately3000cfs

    wasnotpursued,asactionisrequiredatdownstreamcommunitiesforflowslessthan3,000cfs.

    ThereportTolnaCouleeOutletErosion(Reference1)describeserosionofTolnaCouleeinitiatingat

    thedownstreamslopeofthenaturalhighpointandprogressingupstreamtowardthelake. Forthe

    designevent,hydraulicroutingusingsedimenttransportanalysismethodsproposedbyColby

    (Reference1)showsDevilsLakereachingpeakelevationafterthecouleehassubstantiallyeroded.Hydraulicroutinganderosionanalysiswascomputedonadailytimestepusingthespreadsheet

    Devils_Lake_Run_ESO.xls.

    Basedontheassessmentthatsubstantialerosioncouldprecedepeaklakeelevationforthedesign

    event,theweirstructurewassizedtopassapproximately3000cfsunderfreeflowconditionsatalake

    elevationof1463.2ft.

  • 7/29/2019 Design Documentation Report

    24/317

    Tolna Coulee: H&H Appendix Page 5

    StraightDropStructure:

    Severalcombinationsofstartingstoplogelevationswithweiropeningsizeswereevaluatedthatwould

    achieveadesigndischargeofapproximately3000cfs. Basedonprojectsponsorpreference,starting

    stoplogelevationsbetween1458.2ftand1459.2ftwereselectedtocloselymatchexistinggradeofthe

    highpointthalweg. Astartingelevationof1458.2ftfor4of12totalstoplogbaysensuresthatwateris

    notinhibitedfrommovingtooroverthehighpointbetweenelevation1458.2ftand1459.2ftifallowed

    byexistinggrade.

    Usingtheweirflowequation(Equation1)andacoefficientofC=3.0(Reference3),acombinedweir

    lengthof40feetat1458.2ftand80feetat1459.2ftresultsinaflowrateofapproximately3000cfsata

    lakeelevationof1463.2ft.

    1 Q C L H

    QMF 3.080ft1463.2 ft 1459.2 ft

    3.040ft1463.2 ft 1458.2 ft

    3262 cfs 3000 cfsWeirlength,discharge,andassociatedratingcurvesweredeterminedusingthe

    FreeFlow_RatingCurve_CalculatortaboftheUpstream_Structure_Analysisdesignspreadsheet.

    Aratingcurvefortheweirstructureunderfreeflowconditions,anticipatedgivensufficienterosionof

    thecoulee,isshowninTable2. TheratingcurveforthestructurefortheNoErosionorPreErosion

    scenarioisshowninTable3. TheNoErosionratingcurveshowninTable3wasinterpolatedfrom

    watersurfaceprofilesthatweredevelopedusingTolnaCoulee_Upstream_Structure_12gates.g07

    (Plan:TolnaCoulee_12_Gates)

    from

    the

    HEC

    RAS

    model

    TolnaCoulee.

    Profiles

    were

    developed

    using

    steadyflowanalysisinHECRASversion4.1.0.

    Table2: StructureFreeFlowRatingCurve Table3:StructureNoErosionRatingCurve

  • 7/29/2019 Design Documentation Report

    25/317

    Tolna Coulee: H&H Appendix Page 6

    HECRASModelandNoErosionAnalysis:

    ThegeometryfileTolnaCoulee_Upstream_Structure_12gates.g07(Plan:TolnaCoulee_12_Gates)from

    theHECRASversion4.1.0ModelTolnaCouleewasusedtoanalyzetheweirstructure. Steadystate

    modelresultswereusedtoverifythatthestructuredoesnotresultinanincreasetothepeakStillWater

    Level(SWL)of1463.2ftatTolnaCouleeforthePMFeventusedtodesigntheCityofDevilsLake

    embankments.

    TheTolnaCouleecontrolstructurewasmodeledasanInlineStructurewithtwelve10footoverflow

    gates(InvertElevations:8at1459.2ft,4at1458.2ft)havingaweircoefficientofC=3.0. Overflowgates

    areseparatedby2footpiers. Ineffectiveareasassumeexpansionandcontractionratiosof1:1.

    Contractionandexpansioncoefficientsaresetto0.3and0.5respectivelyforcrosssectionsadjacentto

    thestructuretorepresentcontractionofflowfromthewiderlakecrosssectionstothenarrowercontrol

    structure. AcrosssectionviewofthestructureisshowninFigure4.

    Figure4:CrossSectionViewofTolnaCouleeStructureModeledUsingHECRAS

    WatersurfaceprofilesfortheweirstructureassumingNoErosionweredevelopedusingtheHECRAS

    model. AratingcurvefortheweirstructureassumingNoErosionwasinterpolatedat1footelevation

    intervalsfromwatersurfaceprofilesattheupstream(DevilsLake/StumpLake)endofthemodel. The

    PMF

    inflow

    event

    on

    a

    starting

    lake

    elevation

    of

    1459.2

    ft

    was

    routed

    through

    the

    interpolated

    rating

    curve(Table3)onadailytimestepusingthespreadsheetDevils_Lake_Run_ESO. Figure5onthe

    followingpageshowslakeelevationvs.timeforwithandwithoutprojectconditionsforthedesign

    eventassumingNoErosion.

    RoutingthedesigneventassumingNoErosiondoesnotresultinasignificantincreasetothePMF

    designwatersurfaceelevationof1463.2ftatTolnaCoulee. ForaPMFpeaklakelevelof1463.2ftat

    TolnaCoulee,assuming1footoflakeslopefromTolnaCouleetotheCityofDevilsLakeEmbankments,

    thedesigneventpeakwatersurfaceremains1464.2ftfortheCityofDevilsLakeEmbankments.

  • 7/29/2019 Design Documentation Report

    26/317

    1,462

    1,463

    1,464

    n(NAVD

    1988Ft)

    TolnaCouleeElevations(NAVD1988ft)forthe1/2PMF

    NoErosion W.S.WithProject

    NoErosion W.S.WithoutProject

    Summ

    NoEroPeakWWithPr

    Withou

    1,459

    1,460

    1,461

    0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 480 510 540 570

    Elevati

    DaysMar

    Apr

    May

    Jul

    Jun

    Aug

    Sept

    Oct

    Nov

    Jan

    Dec

    Feb

    May

    Jul

    Jun

    Aug

    Sept

    Oct

    Figure 5: Tolna Coulee Water Surface Elevations for the 1

  • 7/29/2019 Design Documentation Report

    27/317

    Tolna Coulee: H&H Appendix Page 8

    StillingBasinDesign

    Forthedesignwatersurfaceelevationof1463.2ft,stoplogbaysat1458.2ftand1459.2ftareexpected

    tooperateunder5feetand4feetoftotalheadrespectively. SAFstillingbasindimensionsare

    dependentuponcriticaldepthanddropheight. Astillingbasinwassizedforbothstartingstoplog

    elevations,withtherecommendedbasindimensionsselectedforthemostseverecase.

    DesignguidancefortheSAFstructurestatesthatthestillingbasinlengthcomputedforaminimum

    tailwaterlevelrequiredforgoodperformancemaybeinadequateathighertailwaterlevels. Dangerous

    scourofthedownstreamchannelmayoccurifthenappeissupportedsufficientlybyhightailwaterso

    thatitlandsbeyondtheendofthestillingbasin(Reference2).

    Becausetailwaterisanticipatedtobevariableforthedesignevent,fromabovetheweirinverttobelow

    theinvert,stillingbasindesignwasconductedforbothhightailwater(1463.2ft)andlowtailwater

    (1451.2ft)scenarios. Stillingbasindesignwasconductedusingthedesignspreadsheet

    SAF_StraightDrop_Design.xlsx. Designdimensionsthatwillperformforhigh,low,andintermediate

    tailwaterscenarioswereselected. CriticalhydraulicdimensionsforthestillingbasinareshowninTable

    6. Baffleblocksarespacedtoensurethatbetween50% 60%ofthebasincrosssectionalareaisblocked,asrecommendedinthedocumentStraightDropSpillwayStillingBasin(Reference2).

    ThetoeoftherequiredIWall/Embankmentcompositesystemextendsfurtherdownstreamthanthe

    endofthestillingbasinandwingwallsrequiredforhydraulicperformance. Lengtheningthestilling

    basinbymovingtheendsillfurtherdownstream andchangingthewingwallslopetogradewere

    requiredtofacilitatesitelayoutandensurethewingwallsretainallembankmentfill. Lengtheningthe

    stillingbasinwasconductedinaccordancewithStraightDropSpillwayStillingBasin(Reference2).

    Modificationstothewingwallsfollowthethedesignguidelinesoutlinedin,HydraulicDesignoftheBox

    InletDropSpillway(Reference17).

  • 7/29/2019 Design Documentation Report

    28/317

    Tolna Coulee: H&H Appendix Page 9

    Table6:DesignDimensionsforTolnaCouleeSAFTypeStructure

    DesignrecommendationsforSAFstructuresprovidedbyRiceandKadavy(Reference15)suggestadding

    aradiustransitionfromtheheadwalltotheweir. Addingtheradiustransitionreducesflow

    concentrationatthecenteroftheweir,resultinginlesslocalizedscourdownstreamofthebasin.

    ExperimentaltestresultspresentedinRiprapDesignDownstreamofStraightDropSpillways(Reference15)recommendaradiusofatleast3dctorealizemaximumbenefitsoftheradiustransition.

    Basedondc(criticaldepth)of3.3feetforstoplogbaysatelevation1458.2ft,a10footradiustransition

    fromtheabutmentstotheweirwasincorporatedintothedesignoftheconcretestructure.

    TailwaterAssumptionsandLoadCaseDetermination

    TailwaterDepth(d2)fortheTolnaCouleestructureisassumedtobevariablefrom5feetto17.2feetfor

    thedesigneventasTolnaCouleeprogressivelyerodes. Thefollowingtailwaterelevationswere

    providedforanalysisandloadcaseformulation:

    TailwaterElevation:

    1451.8

    ft

    Atailwaterelevationof1451.8ftcorrespondstoanerodedTolnaCouleechannelhavingathalwegat

    elevation1447.2ft. ThedepthwasdeterminedusingManningsequationforuniformflowwithsomeof

    theerosionassumptionsoutlinedinthereportTolnaCouleeOutletErosionbyBARREngineering

    (Reference1). ParametersusedforanalysisareshowninTable7.

  • 7/29/2019 Design Documentation Report

    29/317

    Tolna Coulee: H&H Appendix Page 10

    Table7:ManningsEquationParameters

    Tailwater Analysis Parameters

    Channel Slope (ft/ft) 0.00126

    Channel Bottom Width (ft) 150

    Manning's Roughness (n) 0.035

    Channel Side SlopesHorizontal 1.5

    Vertical 1

    TailwaterElevation:1448.4ft

    Atailwaterelevationof1448.4correspondsto3000cfsflowingatcriticaldepth(dc)overthe142foot

    wideendsillofthestillingbasin. Thiswasassumedtobethelowestreasonabletailwaterfor3000cfs

    passingoverthestructure. Theelevationwasdeterminedusingtheequationforcriticaldepththrough

    arectangularchannel(Equation2):

    2 d Q

    d

    ./ =2.4feet

    TailwaterDepth=EndSillElevation+dc1446ft+2.4feet= 1448.4ft

    TailwaterElevation:1450.8ft

    Thecontrolstructurewasanalyzedforaheadwaterelevationequaltothetopofthewallelevationof

    1447.2ft. Forthiscase,morethan3000cfswouldbepassingoverthestoplogs. Usingtheweir

    equationwithaweircoefficientofC=3.0calculatesthat8,671cfspassesoverthestructure. Aflowrateof8,671cfsatcriticaldepthoverthe142footwideendsillofthestillingbasincorrespondstoa

    tailwaterelevationof1450.8ft. Theelevationwasdeterminedusingtheequationforcriticaldepth

    througharectangularchannel(Equation2):

    2 d Q

    d

    ./ =4.87feet

    TailwaterDepth=EndSillElevation+dc1446ft+4.8feet= 1450.8ft

  • 7/29/2019 Design Documentation Report

    30/317

    Tolna Coulee: H&H Appendix Page 11

    WindandWaveAnalysis

    DesignWind

    DesignwindspeedswereadoptedfromapproveddesigndocumentationfortheDevilsLakePhase3

    Embankments. Thedesignwindanalysisusestenyearsofwinddata,fromJune1985to1995.Astudy

    byBaker(Reference6)concludedthattenyearsofrecordisamplewhenlookingforwindpatterns.Theaverageofthemaximumannualwindspeedsovertenyearswasadoptedforeachwinddirection(Table

    8).ThesearethesamewindspeedsadoptedfortheexistingCityofDevilsLakeembankments,which

    havewithstoodthewindandwaveforcessinceconstructionin2004withoutanyissues. Awindrose

    illustratingprevalentwinddirectionforthe1985to1995periodisshowninFigure9.

    Table8:DevilsLakeAverageofMaximumAnnualWindSpeeds(mph)(19851995)

    Figure9:WindRoseDevilsLakeAverageofMaximumAnnualWindSpeeds(mph) (19851995)

  • 7/29/2019 Design Documentation Report

    31/317

    Tolna Coulee: H&H Appendix Page 12

    WindSetup

    WindsetupbasedonaJuly2006MemorandumforRecord(Reference7).Windsetupascomputedby

    theformulapresentedintheCEMishighlydependentonwaterdepth,makingtheassumedwater

    depthcriticaltotheresultingwindsetupvalue. Foreaseofcomputation,themethodologycurrentlyin

    usebytheStPaulDistrictatthelocksanddamsistoassumeaonetenthriseinthewatersurfacefor

    everytenmilesperhourofwindspeed. Whilethismayseemoverlysimplistic,ithasworkedwellatthelocksanddamsandhasthebenefitofnotbeingwaterdepthdependant. Thismethodwasalsousedin

    theapproveddesignoftheDevilsLakePhase3Embankments. Windsetupof0.4ftwasusedforthe

    TolnaCouleecontrolstructure.

    FetchLength,CriticalWindDirection,andWaveGeneration

    Theeffectivefetchlengthwasdeterminedbymethodsdiscussedin339oftheShoreProtectionManual

    (SPM)(Reference8). Fetchvectors,perpendicularwiththestructurealignmentandat3degreeoffsets

    wereanalyzed. Theperpendiculardistancefromthestructuretotheupstreamshorelineis0.6Miles.

    Theaveragefetchlengthof9radialsspacedat3degreesisapproximately1.8miles.Themaximumfetch

    vectoris5milesandtheminimumfetchvectoris0.1miles. Afetchlengthof5mileswasselectedfor

    design.

    A

    map

    of

    Stump

    Lake

    with

    wind

    fetch

    vectors

    is

    shown

    in

    Figure

    10.

    Criticalfetchlengthsforthestructurecorrespondtowinddirectionsbetween45degreesand135

    degrees. Awindof27.2MPHOverlandEastwasusedfordesign. Thecriticaldesignwindresultsin

    WaveHeight(H)=3.3ft,WavePeriod(T)=3.5seconds,andWavelength(L)=62Ft. Designformulas

    andcalculationsrelatedtoWind/Wavedeterminationsarecontainedinthespreadsheet

    TolnaCoulee_WindWave.xlsx.

    FreeboardRequirements

    Typically,DamSafetyCriteriaER111082(FR)(Reference9)requires5feetoffreeboardfor

    embankmentdams. TobeconsistentwiththeapprovedDevilsLakeFloodRiskManagementProject

    DesignCriteriaandProjectConsiderationsReport(Reference5),afreeboardrequirementofthe

    maximumof3feetorwind/waverequirementswasadoptedfortheTolnaCouleestructure.

    FortheCityofDevilsLakeEmbankmentsproject,waveanalysisanddesignfollowingShoreProtection

    Manualmethodologyrequiredthatwaverunupbecontainedbytheembankments. Becauserunup

    doesnotapplytoverticalstructures,guidanceforallowableovertoppingfromtheCoastalEngineering

    Manualwasused.

    TheIWall/EmbankmentcompositestructurewasanalyzedusingtheovertoppingformulabyFrancoand

    Franco(1999)fromTableVI513oftheCoastalEngineeringManual. Foralakelevelof1463.2ft,Wind

    Setupof0.4feet,andsignificantwaveheightof3.3feet:

    OvertoppingDischarge(q) 0.1cfs/ft foratopofsheetpileelevationof1467.2ft.

    Elevation1467.2ftis4feetabovetheStillWaterLevel(SWL)of1463.2ftforthedesignevent.

    TableVI56:CriticalValuesofAverageOvertoppingDischargesfromtheCoastalEngineeringManual

    (Reference10)showsthatq 0.1cfs/ftfallswithinthestructuralsafetylimitsfor"NoDamage"for

    GrassSeaDikes. Anyadditionalerosionresistancetowaveovertoppingprovidedbyrockonthe

    downstreamslopeoftheembankmentwasnotconsideredindeterminationoftheappropriate"No

    Damage"threshold.

  • 7/29/2019 Design Documentation Report

    32/317

    5

    4.9

    4.6

    0.6

    0.4

    0.1

    Map Legend

    Perpendecular Fetch Vector

    Fetch Vectors

    Lake Extent at 1459.2 ft (NAVD 1988)

    Lake Extent at 1463.2 ft (NAVD 1988)

    Tolna Coulee : Control Structure - Wind / Wave Impacts

    /0 1 20.5 1.5 Miles

    Perpend icular Fetch Lengt h: 0.6 Miles

    Average Fetch Length ( SPM) : 1.8 M iles

    Maxim um Fetch Length : 5 Miles

    ure 10: Stump Lake Fetch Map

  • 7/29/2019 Design Documentation Report

    33/317

    Tolna Coulee: H&H Appendix Page 14

    IceImpacts

    AmajorityofDevilsLakeinflowandassociatedlakeriseoccursinthelatespringandsummer(April

    July). Icejammingisnotanticipatedtobeamajorproblemduringthemajorityoftheinfloweventdue

    towarmweatherconditions. Forthe4monthPMFdesignevent,iceisnotanticipatedtorestrictor

    preventflowfromleavingthelakeforadurationthatwouldresultinasignificantincreasetothedesign

    watersurface

    elevation

    of

    1463.2

    ft.

    The

    structure

    is

    designed

    for

    ice

    loading

    where

    applicable.

    Piers

    aredesignedassumingicecouldpotentiallybridgebetweenpiersthusincreasingiceload. Stoplogsare

    designedforiceloadswhenbridgingisnotoccurring.RiprapDesign

    Gradations

    RiprapgradationsthatwereestablishedfortheCityofDevilsLakeEmbankmentswereadoptedforthe

    TolnaCouleestructure. Thesegradationswereadopted,astheyhavealreadybeendevelopedandwill

    beinuseintheareaaroundthetimeofconstruction. Summarystatisticsforeachofthegradations

    selectedfor

    the

    project

    are

    shown

    in

    Table

    11.

    Further

    information

    related

    to

    graded

    riprap

    and

    beddingcanbefoundinthespecificationsandgeotechnicaldesigndocumentation.

    Table11:RiprapSummaryStatisticsforTolnaCouleeGradations

    UpstreamEmbankmentProtection

    RockprotectionontheupstreamslopeandcrownoftheembankmentwasdeterminedusingEquation

    216:ArmorUnitStabilityfromEM111021614(Reference11). Designcalculationsarecontainedin

    thespreadsheetTolnaCoulee_WindWave.xls.

    ThestabilitycoefficientusedincalculationofstonesizewasadoptedfromSpiritLake(DevilsLake),

    NorthDakota,Phase2EvaluationofExistingRoads(Reference12). Accordingtothatdocument,StabilitycoefficientsforavariousarmorunitsareshownintheSPM. Astabilitycoefficientfora

    graded,roundedripraphasneverbeendetermined. Foratriplelayerofsmoothroundedstone,the

    stabilitycoefficient

    is

    3.2.

    For

    adouble

    layer,

    its

    2.4.

    Continuing

    with

    this

    thought,

    avalue

    of

    1.6

    was

    assumedforasinglelayerofagradedriprap.

    Stonesizecalculationfortheupstreamembankmentslopeandcrownassumesasinglelayerofrounded

    riprapwithaunitweightof165poundspercubicfoot(pcf)andaspecificgravityof2.65. Calculated

    minimumW50fortheupstreamslopeandcrownoftheIWall/Embankmentcompositesystemsisshown

    inTable12.

  • 7/29/2019 Design Documentation Report

    34/317

    Tolna Coulee: H&H Appendix Page 15

    Table12:MinimumD50SizeforTolnaCouleeLakesideEmbankmentSlope RoundGradedRiprap

    Slope of Embankment ( _H:1V) 3.5

    Minimum W50 Rock Weight (lbs): 228

    BasedonthecalculatedminimumW50size,Gradation4wasselectedforuseontheupstreamslopeand

    crownoftheIWall/Embankmentcompositesystem.

    DownstreamEmbankmentProtection

    Establishingandmaintaininggrasscoveronthedownstreamslopeandcrownoftheembankment

    presentschallenges,astheembankmentwillbeunderwaterforlakeelevationsabove~1453ftpriorto

    anyerosionofthenaturalhighpoint. ThedownstreamcrestandslopeofthecompositeIWall/

    Embankmentstructurewillbeprotectedwithrockinplaceofgrasstoeasemaintenanceofthe

    structure.

    Determinationof

    appropriate

    rock

    gradation

    is

    based

    on

    the

    Minnesota

    PCA

    Technical

    Criteria

    Riprap

    CriteriaforStabilizationPonds(Reference16). Theguidancewasdevelopedbecause,grasscannot

    usuallybeestablishedinoneseasontoadequatelyprotect[stabilizationpond]dikesfromerosion. The

    fluctuatingwaterlevelsinapondsoperationarenotconducivetogoodgrassgrowth(Reference16).

    TheriprapgradationrecommendedintheMinnesotaPCAdocumentissimilartoandslightlysmaller

    thanGradation1.

    Gradation1wasselectedforthedownstreamslopeandcrownoftheIWall/Embankmentcomposite

    system. Additionalerosionresistancetowaveovertoppingprovidedbytherockwasnotconsideredin

    determinationoftheappropriate"NoDamage"threshold.

    RockDownstreamofEndSill

    RiprapW50sizedeterminedforrockdesignimmediatelydownstreamofthestillingbasinisbasedon

    experimentallyderivedguidancepresentedintheASAEpublication,RiprapDesignDownstreamof

    StraightDropSpillways(Reference15).

    DesignformulascalculateaminimumW50rocksizeasafunctionofcriticaldepth,dropheight,tailwater

    depth,andabutmenttype. Becausethetailwaterdepthdownstreamofthestructureisexpectedtobe

    variableforthedesigneventasthecouleeerodes,thecriticaldepth,dropheight,andtailwater

    combinationyieldingthelargestminimumW50sizewasusedforrockdesign. DesignbasedontheASAE

    guidancewasconductedusingthespreadsheetRiprapDesign_StraightDropSpillways.xlsx.

    BasedonacalculatedminimumW50of61lb,Gradation3riprapwasselectedforscourprotection

    immediatelydownstreamofthestillingbasinendsill.

    RiprapDesignDownstreamofStraightDropSpillwaysrecommendsriprapprotectionofappropriate

    sizebecontinuedaminimumdistanceof5dc(roundedabutments)to8dc(squareabutments)

    downstreamoftheendsill. Thiscorrespondstoadistanceof16.5ftto26.5ftdownstreamoftheend

  • 7/29/2019 Design Documentation Report

    35/317

    Tolna Coulee: H&H Appendix Page 16

    sill. Hightailwaterelevationscancausescour[to]occurinthedownstreamchannelifthebedmaterial

    iseasilyerodible,indicatingprovidedriprapprotectionshouldexceedminimumrequirements.

    EM111021602(Reference14)recommendsthatriprapextenddownstreamforadistanceof10d2fromtheupstreamendofthestillingbasin. TailwaterDepth(d2)fortheTolnaCouleestructureis

    assumedtobevariablefrom~5feetto~17.2feetforthedesigneventasTolnaCouleeerodes. Design

    basedon

    d2suggestsappropriatelysizedriprapprotectionbeplaced50172feetdownstreamofthe

    startofthestillingbasin.

    RiprapprotectionfortheTolnaCouleestructureisprovidedforatotalof100feetdownstreamofthe

    stillingbasinexit. RiprapGradation3willbeplacedfor50feetdownstreamoftheendsillandaround

    thewingwallstoresistlocalscour.

    Gradation1riprapwillbeplacedfor50feetdownstreamofthelargerGradation3riprap. Transition

    fromlargerocktoasmallerrockpriortotransitioningtothenaturalstreambedreduceslocallyhigh

    boundaryturbulencethatwouldresultfromimmediatetransitionfromlargerocktothenaturalchannel

    (Reference13). The50feetofsmallerrockalsoprovidesadditionalprotectionfromunderminingshould

    downstreamerosion

    progress

    to

    the

    riprap

    blanket.

    Additional

    rock

    at

    the

    downstream

    riprap

    end

    protectionsectionallowsforthesloughingofrockintoareasinneedofunderminingprotection.

    Topelevationofthedownstreamriprapblanketwillbeat1444.6ft. Thiselevationislowerthanthetop

    oftheendsillelevationof1446fttohelppreventbackrollersfrompullingrockintothebasinwhichcan

    causeconcreteabrasiondamage. ThisisrecommendedinaccordancewithguidanceprovidedinEM

    111021602(Reference14).

    OperatingPlan

    AfinaloperatingplanistobeprovidedbytheNorthDakotaStateWaterCommission(NDSWC)and

    reviewedtoensurecompliancewithapplicableguidelinesandregulations. Generaloperatingplanrules

    havebeendevelopedbytheNDSWCtoserveassummaryguidelinesforthefinaloperationplan.

    1) Undernocircumstanceswillanystoplogsbeplacedaboveanelevationof1459.2feet.

    2) Initiallythestoplogswillbeplacedapproximately1footbelowthewatersurface.

    3) Asthewaterlevelincreasesstoplogswillbeaddedtomaintaintheapproximate1footlevelbelow

    thewatersurfaceelevationuntilthetopofthestoplogsareatanelevationof1457.2feet.

    4) Thetopofthestoplogswillremainat1457.2feetuntilwaterbeginstoflowoverthedivideatwhich

    timethestoplogsinbays5through8willbeplacedtoelevation1458.2ftandbays14and912will

    beplaceduptoelevation1459.2feet.

    5) PriortoerosionofthedividebetweenStumpLakeandTolnaCoulee,thestoplogswillremainin

    placeasdescribedin1.4,withtheintentthattheexistingtopography,notthecontrolstructurewill

    controlthe

    discharge.

    6) Ifandwhenerosionoccurs,stoplogswillberemovedtotheerodedhighpointelevationwiththe

    maximumlakedischargelimitedto3,000cfs.

    7) Stoplogswillberemovedtothenewelevationthatexistsaftererosionhasoccurred. Thiswillbe

    conductedinamannernottoexceedadischargeof3,000cfs.

    8) Onatleastamonthlybasis,thesitewillbevisitedtoobserveactualconditionsandverifythat

    projectisbeingoperatedwithintheparametersofthisOperatingPlan.

  • 7/29/2019 Design Documentation Report

    36/317

    Tolna Coulee: H&H Appendix Page 17

    References

    1. BarrEngineering,TolnaCouleeOutletErosion,PreparedfortheU.S.ArmyCorpsofEngineers;2001.

    2. Donnelly&Blaisdell.TechnicalPaperNo.15,SeriesB.StraightDropSpillwayStillingBasin. St.

    Anthony

    Falls

    Hydraulic

    Laboratory,

    University

    of

    Minnesota;

    1954

    3. HydraulicDesignCriteria623to624.1. SubcriticalOpenChannelFlowDropStructures,Hydraulic

    DesignChart623CITTypeStructure;January1968

    4. NRCSStreamRestorationHandbook.TechnicalSupplement14G,GradeStabilizationTechniques,NRCS.

    August2007.

    5. DevilsLakeFloodRiskManagementProject.DesignCriteriaandProjectConsiderationsReport,U.S.

    ArmyCorpsofEngineers;21December2009

    6. Baker,D.G.ClimateofMinnesota:Part14,WindClimatologyandWindPower,TechnicalBulletinADTB

    1955,AgriculturalExperimentStation,UniversityofMinnesota;1983.

    7. MemorandumforRecordWaveRunuponDevilsLake,U.S.ArmyCorpsofEngineers,St.PaulDistrict;

    July

    2006.

    8. ShoreProtectionManual,WaterwaysExperimentStation,U.S.ArmyCorpsofEngineers,Coastal

    EngineeringResearchCenter;1984.

    9. ER111082(FR),InflowDesignFloodsForDamsandReservoirs,U.S.ArmyCorpsofEngineers,

    WashingtonDC;1March1991.

    10. EM111021100,CoastalEngineeringManual,U.S.ArmyCorpsofEngineers,WashingtonDC;1August

    2008.

    11. EM111021614,DesignofCoastalRevetments,Seawalls,andBulkheads,U.S.ArmyCorpsof

    Engineers,WashingtonDC;30June1995.

    12. SpiritLake(DevilsLake)NorthDakotaPhase2EvaluationofExistingRoads,U.S.ArmyCorpsof

    Engineers,

    2005.

    13. EM111021601,EngineeringandDesignHydraulicDesignofFloodControlChannels,U.S.Army

    CorpsofEngineers,WashingtonDC;30June1994.

    14. EM111021602,EngineeringandDesignHydraulicDesignofReservoirOutletWorks,U.S.Army

    CorpsofEngineers,WashingtonDC;15October1980

    15. Rice,C.E.andKadavy,K.C.,RiprapDesignDownstreamofStraightDropSpillways,AmericanSocietyof

    AgriculturalandBiologicalEngineers,JulyAugust1991.

    16.MPCATechnicalCriteria,RiprapCriteriaforStabilizationPonds,MinnesotaPollutionControlAgency,

    May1991

    17.Donnelly&Blaisdell. SCSTechnicalPaper106. HydraulicDesignoftheBoxInletDropSpillway. Soil

    ConservationService

    Research,

    Washington

    25,

    DC;

    July

    1951

  • 7/29/2019 Design Documentation Report

    37/317

    Tolna Coulee: H&H Appendix Page 18

    AccessRoadDitches InteriorFloodControlAnalysis

    TheproposedTolnaCouleeaccessroadalignmentandthetwodelineatedsubwatershedsareshownin

    Figure13onthefollowingpage.Thedrainageareasforthewestandeastsubbasinsweremeasured

    usingtheArcMapGISprogramandweredeterminedtobe6.5and3.9acres,respectively.

    AHEC

    HMS

    model

    was

    set

    up

    to

    calculate

    the

    1percent

    event

    hydrographs

    for

    the

    two

    sub

    basins.

    The

    modelparametersareshowninTable14. Curvenumbersweredeterminedusingavailablelanduseand

    soilsmapping.SoilsinthewestsubbasinaremostlyfromHydrologicSoilGroupB,withverysmallareas

    ofHSGAandC/D. TheeastsubbasinismostlyHSGB,withasmallareaofHSGAatthesouthend. The

    calculatedcurvenumbersare59inthewestsubbasinand58intheeastsubbasin.

    TimeofconcentrationwasdeterminedbasedonmethodspresentedinTR55(Reference18). Lagtime

    wasassumedtobesixtypercentofthecalculatedtimeofconcentration. Noimperviousareawas

    assumedineithersubbasin.

    Table14

    HECHMSModelParameters

    SubArea CurveNumber TimeofConcentration(min) LagTime(min)

    West 59 45 27

    East 58 34 20

    Theprecipitationeventusedintheanalyseswasthe100year,10daystorm. Thisisthesameevent

    usedinpumpstationmodelingfortheCityofDevilsLakeEmbankmentsproject. Theaccessroadditch

    subbasinsarerelativelysmallanddonothavedefineddrainagepatterns,sobaseflowwasnot

    considered. TheHECHMSmodelpeakdischargesforthewestandeastsubareaswere8.3and6.5cfs,

    respectively. Aculvertcrossesundertheaccessroad,carryingflowfromtheeastditchtothewest

    ditch.Downstream

    of

    the

    culvert

    outlet,

    the

    peak

    discharge

    is

    14.2

    cfs.

    This

    is

    slightly

    less

    than

    the

    sum

    ofthepeaksforthewestandeastsubbasinsbecauseofthedifferentlagtimesbeingused.

    AHECRASmodelwasdevelopedforthedrainageditchesoneithersideoftheaccessroadbasedonthe

    crosssectionsincludedintheTolnaCouleeconstructionplans.Theditcheseachhaveabottomwidthof

    fivefeetand3H:1Vsideslopes. Thewestditchhasanaverageslopeofapproximately4.3percent. The

    eastditchhasanaverageslopeofapproximately4.6percent.Theculvertcrossingundertheaccessroad

    thatcarriesflowfromtheeastditchtothewestditchwasmodeledasa55footlong,24inchdiameter

    corrugatedmetalpipe(CMP)projectingfromfill(i.e.noheadwall).

    Forthedesignstorm,themaximumflowvelocityintheeastditchis3.1feetpersecond(fps). The

    maximumvelocityinthewestditchupstreamoftheculvertis3.4fps. Maximumvelocityinthewest

    ditchdownstreamoftheculvertis3.7fps. Forslopeslessthan5%,thegeneralruleisthatthemaximumpermissiblevelocityinagrassedditchisbetween4fps(foreasilyerodedsoils)and5fps(erosion

    resistantsoils). Basedonthemodelvelocities,theditchesdonotrequireriprapifgrasscanbewell

    established.

    Theculvert,asmodeled,isappropriatelysized. Maximumoutletvelocityforthedesignstormis4.5fps.

    Gradation1riprapshouldbeplacedattheupstreamanddownstreamendsoftheculverttoprevent

    erosionandscourfromoccurringduringhighflowevents.

  • 7/29/2019 Design Documentation Report

    38/317Figure 13: Tolna Coulee Access Road Drainage

    Legend

    East ditch drainage area

    West ditch drainage area

    Access Road 0 100 200 300 400 500Fee

  • 7/29/2019 Design Documentation Report

    39/317

    Tolna Coulee: H&H Appendix Page 20

    References18.UrbanHydrologyforSmallWatersheds,U.S.DepartmentofAgriculture,SoilConservationService,

    TechnicalRelease55(TR55),June1986.

    19.Soil

    Survey

    Staff,

    Natural

    Resources

    Conservation

    Service,

    United

    States

    Department

    of

    Agriculture.

    WebSoilSurvey.Availableonlineathttp://websoilsurvey.nrcs.usda.gov/accessedJune30,2011.

  • 7/29/2019 Design Documentation Report

    40/317

    Appendix D

    Geotechnical Appendix

  • 7/29/2019 Design Documentation Report

    41/317

    Design Documentation Report Tolna Coulee Advance Measures D-i

    100% Final Document Geotechnical Design and Geology

    Tolna Coulee Advance Measures

    Nelson County, North Dakota

    Appendix D

    Geotechnical Design and Geology

    Table of ContentsD.1 INTRODUCTION ................................................................................................ D-1D.2 REGIONAL GEOLOGY ...................................................................................... D-1

    D.2.1 Physiography and Topography ........................................................................... D-1

    D.2.2 General Geology ................................................................................................. D-1

    D.2.3 Structure.............................................................................................................. D-2

    D.2.4 Site Hydrogeology .............................................................................................. D-2

    D.2.5 Seismic Risk and Earthquake History ................................................................ D-2D.3 SUBSURFACE INVESTIGATION ..................................................................... D-3

    D.3.1 Site Specific Geology ......................................................................................... D-3D.3.2 Laboratory Testing ............................................................................................. D-4D.3.3 Selection of Design Parameters .......................................................................... D-4

    D.4 GEOTECHNICAL DESIGN ................................................................................ D-6

    D.4.1 Introduction ........................................................................................................ D-6

    D.4.2 Horizontal and Vertical Datums ......................................................................... D-6

    D.4.3 Design Methodology .......................................................................................... D-7

    D.4.4 Cofferdam ........................................................................................................... D-7

    D.4.5 Dewatering and Groundwater Control ............................................................. D-10D.4.6 Temporary Excavation Slopes .......................................................................... D-11

    D.4.7 Stoplog Structure and Retaining Walls ............................................................ D-12

    D.4.8 I-Wall/Embankment Composite System .......................................................... D-14D.5 PHASE I ENVIRONMENTAL SITE ASSESSMENT ...................................... D-22

    D.6 SLOPE PROTECTION ...................................................................................... D-22

    D.7 SOURCES OF CONSTRUCTION MATERIALS ............................................. D-23D.7.1 Impervious Fill ................................................................................................. D-23

    D.7.2 Geotextile Fabric .............................................................................................. D-23

    D.7.3 Stoplog Structure Subdrainage Material........................................................... D-24

    D.7.4 Concrete Aggregate, Riprap, and Bedding ....................................................... D-25

    D.8 INSTRUMENTATION ...................................................................................... D-25

    D.8.1 Construction Monitoring .................................................................................. D-26

    D.8.2 Long-Term Performance Monitoring ............................................................... D-26D.9

    REVIEWS ........................................................................................................... D-27

    D.9.1 District Quality Control .................................................................................... D-27

    D.9.2 Agency Technical Review ................................................................................ D-27D.9.3 Independent External Peer Review ................................................................... D-27

    REFERENCES ................................................................................................................... D-28

  • 7/29/2019 Design Documentation Report

    42/317

    Design Documentation Report Tolna Coulee Advance Measures D-ii

    100% Final Document Geotechnical Design and Geology

    Index of TablesTable D- 1: Summary of Tolna Coulee Soil Parameters ...................................................... D-5

    Table D- 2: Horizontal and Vertical Datums ........................................................................ D-6Table D- 3: Cofferdam Required Factor of Safety ............................................................... D-7

    Table D- 4: National Weather Service Devils Lake peak forecast levels for 2011. ............. D-8

    Table D- 5: Cofferdam Seepage and Stability Results ......................................................... D-9Table D- 6: Temporary Excavation Required Factor of Safety .......................................... D-11

    Table D- 7: Temporary Excavation Stability Results ......................................................... D-12

    Table D- 8: Stoplog Structure Uplift/Seepage Load Cases ................................................ D-13

    Table D- 9: Retaining Wall Monolith 1 Stability Analysis ................................................ D-14Table D- 10: Configuration of I-Wall//Embankment Composite System .......................... D-15

    Table D- 11: Seepage Loading Conditions and Minimum Factors of Safety ..................... D-17

    Table D- 12: Global Stability Loading Conditions and Minimum Factors of Safety ......... D-19Table D- 13: Factor of Safety against Piping ...................................................................... D-20

    Table D- 14: Results of Global Stability Analysis.............................................................. D-21

    Table D- 15: Riprap Gradation ........................................................................................... D-22

    Table D- 16: Bedding Gradations ....................................................................................... D-23Table D- 17: Impervious Fill Requirements ....................................................................... D-23

    Table D- 18: Geotextile Fabric Requirements .................................................................... D-24

    Table D- 19: Sand Gradation Requirements ....................................................................... D-24Table D- 20: Pervious Material Gradation Requirement