Upload
fastidious5
View
252
Download
0
Embed Size (px)
Citation preview
7/29/2019 Design Documentation Report
1/317
Design Documentation Report
Tolna Coulee
Advance MeasuresNelson County, North Dakota
Prepared By
US Army CorpsOf EngineersSt. Paul District / St. Louis District
July 2011 100% Submittal
7/29/2019 Design Documentation Report
2/317
Table of Contents
1 Introduction ........................................................................................................................................... 1
1.1 Existing Project Description ......................................................................................................... 1
1.2 Current Conditions of Tolna Coulee ............................................................................................. 1
1.3 Purpose .......................................................................................................................................... 2
1.4 Authorization ................................................................................................................................ 2
2 Project Features ..................................................................................................................................... 2
2.1 Overview ....................................................................................................................................... 2
2.2 Sheet Pile I-Wall ........................................................................................................................... 2
2.3 Embankments ................................................................................................................................ 2
2.3.1 Embankments next to I-wall. ................................................................................................ 2
2.3.2 Embankment north of the Control Structure ......................................................................... 3
2.4 Control Structure ........................................................................................................................... 3
2.5 Riprap Erosion Protection ............................................................................................................. 3
2.6 Access Road .................................................................................................................................. 3
2.7 Cofferdams .................................................................................................................................... 3
2.8 Previously Obtained Data ............................................................................................................. 4
2.8.1 Topographic Data .................................................................................................................. 4
2.8.2 Property Line Data ................................................................................................................ 4
2.8.3 Related Construction Projects ............................................................................................... 4
2.9 Property Acquisitions and Adjacent Properties ............................................................................ 4
3 PERTINENT DATA ............................................................................................................................. 4
3.1 Controlling Elevations .................................................................................................................. 44 PREVIOUS REPORTS ........................................................................................................................ 5
5 Hydrology and Hydraulics .................................................................................................................... 5
5.1 Introduction ................................................................................................................................... 5
5.2 Straight Drop Structure ................................................................................................................. 5
5.3 Stilling Basin ................................................................................................................................. 6
5.4 Composite I-Wall/Embankment ................................................................................................... 6
6 Geotechnical Engineering ..................................................................................................................... 7
6.1 General .......................................................................................................................................... 7
7 Civil Engineering .................................................................................................................................. 77.1 Introduction ................................................................................................................................... 7
7.2 Technical Guidelines and References ........................................................................................... 7
7.3 Source of Data for Existing Topographic Information ................................................................. 8
7.4 Programs and Standards for Design and Drawings ....................................................................... 8
7.5 Design Process and Standards for Civil Features ......................................................................... 8
7.5.1 Geometric Design Criteria Access Road ............................................................................ 8
7/29/2019 Design Documentation Report
3/317
7.6 Engineering Drawings for Embankments and Site Work ............................................................. 8
7.7 Phase 1 Environmental Site Assessment....................................................................................... 9
8 Structural Engineering .......................................................................................................................... 9
8.1 General .......................................................................................................................................... 9
8.2 Structure Design ............................................................................................................................ 9
8.2.1 Stoplog Control Structure ..................................................................................................... 9
8.2.2 Retaining Walls and Wing Walls .......................................................................................... 9
8.2.3 Sheet Pile I-wall .................................................................................................................... 9
8.2.4 Walkway ............................................................................................................................. 10
8.2.5 Gantry Crane ....................................................................................................................... 10
8.2.6 Lifting Beam ....................................................................................................................... 10
8.2.7 Stoplogs ............................................................................................................................... 10
8.3 Miscellaneous ............................................................................................................................. 10
8.3.1 Frost Protection ................................................................................................................... 10
9 Mechanical and Electrical Engineering .............................................................................................. 10
9.1 Mechanical Design ...................................................................................................................... 10
9.1.1 Gantry Crane and Hoist Selection ....................................................................................... 10
9.2 Electrical Design ......................................................................................................................... 11
10 Constructability ................................................................................................................................... 11
10.1 Introduction ................................................................................................................................. 11
10.2 Sequence of Construction ........................................................................................................... 11
10.3 Embankments .............................................................................................................................. 11
10.4 Structure ...................................................................................................................................... 11
10.5 Coordination with Other Agencies ............................................................................................. 11
11 Instrumentation ................................................................................................................................... 11
11.1 Monitoring Points ....................................................................................................................... 11
11.2 Construction Monitoring ............................................................................................................. 11
11.3 Long-Term Performance Monitoring .......................................................................................... 11
12 Cost Estimate and Construction Schedule .......................................................................................... 11
12.1 Cost Estimate .............................................................................................................................. 11
12.2 Construction Schedule ................................................................................................................ 12
13 REVIEW DOCUMENTATION ......................................................................................................... 12
13.1 District Quality Control (DQC) Review ..................................................................................... 1213.2 Agency Technical Review (ATR) ............................................................................................... 12
13.3 Independent External Peer Review (IEPR) ................................................................................. 12
7/29/2019 Design Documentation Report
4/317
Appendices
Appendix A Plan Set
Appendix B Specifications
Appendix C Hydrology/Hydraulic Appendix
Appendix D Geotechnical Appendix
Appendix E Structural Appendix
Appendix F Mechanical Appendix
Appendix G Quantities
Appendix H Cost Estimate and Construction Schedule
Appendix I Engineering Considerations and Instructions for Field Personnel
Appendix J Phase I Environmental Site Assessment
Appendix K Quality Control Documentation
7/29/2019 Design Documentation Report
5/317
1
1 INTRODUCTION
1.1 Existing Project Description
Devils Lake is a natural lake located south of the City of Devils Lake, located in Ramsey County in the
northeast portion of North Dakota. Since 1940 the lake has risen fifty-two feet, with almost twenty-nine feet of rise since 1993. In March 1993 Devils Lake had a surface area of 44,230 acres. At its
April 30, 2010 elevation (1452.63feet NAVD88) Devils Lake covered about 177,100 acres. During that
same period the volume of water in Devils Lake had grown by more than six times. The current lake
elevation (May 11, 2011) is 1454.0 feet. All elevations in this report are in feet and referenced to
North American Vertical Datum of 1988 (NAVD88) unless specifically stated otherwise. The
conversion from NAVD88 to National Geodetic Vertical Datum of 1929 (NGVD29) in the area of this
project is: NGVD29 = NAVD88 -1.17 feet.
Devils Lake naturally spills into Stump Lake (located east of Devils Lake) at an elevation of
approximately 1447.7. Since water began flowing into Stump Lake in 1999, Stump Lake has now
been filled and has become part of Devils Lake. At its current water levels, Devils Lake has no natural
outlet. At an elevation of 1459.2 the lake overtops the high point in Tolna Coulee and begins to spillthrough the coulee into the Sheyenne River, a tributary of the Red River of the North. Tolna Coulee
is located at the southwest end of what was Stump Lake. Devils Lake has reached its spill elevation
and overflowed into the Sheyenne and Red Rivers at least twice during the past 4,000 years. The
lake last spilled into the Sheyenne River less than 2,000 years ago. At its spill elevation, Devils Lake
covers more than 261,000 acres.
The State of North Dakota completed construction of an outlet to allow water from the West Bay of
Devils Lake to flow into the Sheyenne River in the summer of 2005. The outlet is made up of two
pump stations, a series of buried pipelines and open channels, a sand filter, three siphons, a gated
control structure and a stilling basin. The original pump capacity of the system was 100 cubic feet
per second (cfs). Modifications to increase the pump capacity to 250 cfs were approved by the North
Dakota State Engineer in June 2010. Discharge from the outlet is limited by the 600 cfs channelcapacity of the upper Sheyenne River and the North Dakota Department of Healths maximum
allowed concentration level of 750 milligrams per liter of sulfate at the discharge point in the
Sheyenne River. The West Bay of Devils Lake is located on the other side of Devils Lake from the
Tolna Coulee project and is several miles from Tolna Coulee. This information is provided only for
situational awareness, since it adds flow to the Sheyenne River upstream of the confluence of Tolna
Coulee and the Sheyenne River.
At the time of this project, the State of North Dakota is planning to expand its west end pumped
outlet with an additional capacity of 100 cfs and construct an east end pumped outlet from East
Devils Lakewith a capacity of 350 cfs, which is currently planned to transport water to Tolna Coulee,just downstream of the high point in the coulee. The east end pumped outlet would be located in
the vicinity of the Tolna Coulee project, but would not impact the design of the Tolna Coulee project
since it would discharge into Tolna Coulee downstream of the project.
1.2 Current Conditions of Tolna Coulee
Tolna Coulee is a natural outlet from the Devils Lake basin. There is a significant layer of silts and
organic material with grassy vegetation at the bottom of Tolna Coulee that will have to be removed
before an embankment and/or or structure can be constructed. This layer of silt and organic material
varies in thickness to as much as 14 feet near the middle of the coulee. Under this soft material is a
7/29/2019 Design Documentation Report
6/317
2
layer of sand and boulders, with stiff clay underneath. Due to the high ground water (at or near the
ground surface) and the seepage of groundwater from the sides of the coulee near the toe of the
coulee slopes, dewatering during construction will be required. Due to the rising lake level, a
cofferdam will be constructed on the east side of the project.
1.3 Purpose
The purpose of the Tolna Coulee project is to prevent catastrophic release of flows through Tolna
Coulee into the Sheyenne River. The State of North Dakota has also requested that the Corps of
Engineers include a control structure with the project to allow controlled discharge down to
elevation 1446 feet NGVD29 (1447.2 NAVD88). HQUSACE directed that Measures to control water
elevation or releases above or below 1458 will be borne by the non-Federal sponsor, including
engineering and design. (Note the elevation referenced in the HQ memo is referenced to NGVD29
Datum)
1.4 Authorization
The Tolna Coulee Advance Measures project is authorized under PL84-99, Flood Control and Coastal
Emergencies.
2 PROJECT FEATURES
2.1 Overview
The project includes: Construction of a sheet pile I-wall with a top elevation of 1467.2 (NAVD88), a
stoplog control structure with a stoplog crest elevation of 1459.2 and a top of concrete footing
elevation of 1447.2. The stoplog control structure includes concrete piers with 10 foot clear spacing
between them and a catwalk with overhead rail to allow removal of the stoplogs. Construction of
the sheet pile I-wall will require embankment to be constructed upstream and downstream of the I-
wall. The embankment on the west side of the sheet pile I-wall between and the north bank of the
coulee and the north end of the structure will be ramped up to elevation 1467.2 to allow access tothe structure.
2.2 Sheet Pile I-Wall
A sheet pile I-wall will extend from the south side of the structure to the south bank of Tolna Coulee
and from the north side of the structure to the north bank of Tolna Coulee. This I-wall will have a top
elevation of 1467.2 (NAVD88), which includes 4 feet of freeboard to limit wave overtopping to
acceptable levels. The I-wall on the north side of the structure will include an embankment which
ramps up to the same elevation as the sheet pile on the downstream side of the sheetpile to allow
access to the control structure.
2.3 Embankments
Embankment construction and design is consistent with District guidance. Due to winter time
construction, 24 hour operation will be required to reduce the issues with frozen material.
2.3.1
Embankments will be constructed on the upstream and downstream sides of the sheet pile I-wall.
These embankments are intended to reduce the stick-up of the I-wall to acceptable levels and
eliminate the need for a king pile system to support the sheet pile wall. The tops of these
Embankments next to I-wall.
7/29/2019 Design Documentation Report
7/317
3
embankments will be at elevation 1461.2 south of the control structure and elevation 1463.2
north of the control structure.
2.3.2
An embankment will be constructed to elevation 1463.2 on both sides of the sheet pile I-wall. The
fill on the downstream side of the sheet pile will be ramped up to the full height of the sheet pile I-
wall to provide access to the control structure. The embankment on the upstream side of the
sheet pile will have a consistent top elevation of 1463.2.
Embankment north of the Control Structure
2.4 Control Structure
A control structure will be constructed near the middle of the coulee and will use stoplogs to control
water levels in the Devils Lake basin down to elevation 1447.2 (NAVD88). The control structure
includes a concrete footing/sill, concrete abutments and wing walls, 11 concrete piers with 10 foot
clear openings/bays, and a full length catwalk with overhead monorail system to allow removal of
the stoplogs. The catwalk will be designed to allow access with an ATV and a trailer or cart, which is
expected to be used to haul stoplogs off the structure.
2.5 Riprap Erosion ProtectionRiprap erosion protection will be placed both upstream and downstream of the structure. The riprap
on the lake side slopes of the embankment is sized for wave impact from Stump Lake.
2.6 Access Road
A permanent access road will be constructed from 33rd Street NE, down the hill to the structure. The
access road will be for maintenance purposes and to access the structure to remove stop logs. The
access road will have a maximum grade of 6% and it will be 20 wide with ditching along both sides.
Wide construction limits will be provided in the event the contractor wants to widen the road for
hauling materials to the project site.
2.7
Cofferdams
Due to the rising lake level, a cofferdam will be required on the east side (lake side) of the structure.
Since the work is expected to be completed in March, the lake is expected to be frozen for the
majority of the construction period, so riprap for erosion protection of the cofferdam will not be
required. A cofferdam design has been prepared to include in the plans as a suggestion and to assist
with preparation of estimates; however, the specifications will require the Contractor to design their
own cofferdam.
The cofferdam will not be the only line of protection from flows to the Sheyenne River and
downstream, as the existing Tolna Coulee high points will remain in place. Because the cofferdam
will be a non-critical structure, the actual height of the cofferdam will be up to the contractor and
will most likely depend on the contractors equipment protection needs. The contractor will submit a
cofferdam plan for USACE approval before the cofferdam is constructed.
The cofferdam and dewatering provides the dry working area needed to construct the embankments
under proper conditions or as near to proper conditions as can be expected in North Dakota in the
winter.
7/29/2019 Design Documentation Report
8/317
4
2.8 Previously Obtained Data
2.8.1
Existing topographic data utilized for the design and drawings was from LIDAR and field survey
information performed by City of Devils lake when the maintenance excavation in the coulee was
performed. The project area was then surveyed manually by a State of North Dakota survey crewin May 2011. The coordinate system and projection of the topographic mapping data is NAD83
(2007), North Dakota State Plane Coordinate System, North Zone (U.S. Survey Feet). The elevation
datum of the topographic mapping data is NAVD88 (U.S. Survey Feet).
Topographic Data
2.8.2
The deed for the existing city owned property around the project site was supplied by the City of
Devils Lake.
Property Line Data
2.8.3
2.8.3.1 Devils Lake City Embankments, Phase 2B and Phase 3
Related Construction Projects
Levees near and around Devils Lake are being raised to an elevation of 1467.2. These projectsinclude levee raises, pump stations, and road raises and other work associated with protecting
the City of Devils Lake from the rising Lake Level. A design criterion for these projects was that
if a PMF occurred with an initial lake elevation of 1458.0, outflow through Tolna Coulee
(assuming no erosion) would limit the maximum lake elevation at Tolna Coulee to 1461.9. The
Tolna Coulee project must not increase the lake elevation for the PMF.
2.8.3.2 East Devils Lake Outlet
The North Dakota State Water Commission is planning to construct an outlet and channel from
East Devils Lake to Tolna Coulee. The route begins on East Devils Lake, runs east southeast 5-
1/2 miles and outlets into Tolna Coulee. The outlet will discharge into Tolna Coulee
downstream from the control structure. The outlet plan consists of a pumping plant with
several pumps with the total capacity of 350 cubic feet per second (cfs).
2.9 Property Acquisitions and Adjacent Properties
The City of Devils Lake owns the property that this project will be constructed on. All work is being
done within the property owned by the City of Devils Lake.
3 PERTINENT DATA
3.1 Controlling Elevations
The following table lists the finish elevations of key features of the project. All elevations shown
refer to NAVD88.
Table 3 1 Controlling Elevations
DESCRIPTION ELEVATION (NAVD88)
Top of Sheet Pile I-Wall 1467.2
Top of Berm North of Control Structure 1463.2*
7/29/2019 Design Documentation Report
9/317
5
Top of Berm South of Control Structure 1461.2
Top of Sill at Stop Logs 1447.2
Top of Stoplogs 4 Center Bays 1458.2
Top of Stoplogs 8 Remaining Bays 1459.2
*A ramp will be constructed on the north side of the structure on the west side of the sheet pile I-
wall to allow access to the catwalk. The earth ramp will be from elevation 1463.2 to elevation
1467.2.
4 PREVIOUS REPORTS
Tolna Coulee Outlet Erosion Report, Barr Engineering, Inc., For: U.S. Army Corps of Engineers,St. Paul District, 2001.
Project Information Report, Advance Measures, Tolna Coulee, Nelson County North Dakota,U.S. Army Corps of Engineers, St. Paul District, Revised 22 March 2011.
5 HYDROLOGY AND HYDRAULICS
5.1 Introduction
Levees near and around Devils Lake are being raised to an elevation of 1467.2 ft. These projects
include levee raises, pump stations, and road raises and other work associated with protecting the
City of Devils Lake from the rising Lake Level. The top of embankment for these levee designs is
predicated on Tolna Coulee flowing into the Sheyenne River when the lake level at Tolna Coulee
exceeds elevation 1459.2 ft.
The following paragraphs provide a summary of the Hydraulic Design considerations for the Tolna
Coulee Project. Detailed information related to the Hydrology and Hydraulic design of the Tolna
Coulee Project can be found in the Hydrology/Hydraulics Appendix (Appendix C).
5.2 Straight Drop StructureIn consistency with flood protection efforts in the Devils Lake sub-basin, including the City of Devils
Lake Embankments and Roads Acting as Water Barriers, the Tolna Coulee control structure is
designed for a Inflow Design Flood (IDF) of Probable Maximum Flood ( PMF) with the lake starting
at full pool (Elevation 1459.2 ft).
The PMF peak lake elevation at Tolna Coulee for Without Project condition assuming No-
erosion is 1463.2 ft with a peak discharge of approximately 3000 cfs. Design of the City of Devils
Lake Embankments is based on a peak lake level of 1463.2 ft at Tolna Coulee for a PMF inflow with
the lake starting at full pool (Elevation 1459.2 ft).
To cause no impacts to the design of the City of Devils Lake Embankments, the design discharge for
the structure at Tolna Coulee must not result in an increase to the peak still water level elevation
above 1463.2 ft at Tolna Coulee for a PMF inflow to Devils Lake on a starting pool elevation of
7/29/2019 Design Documentation Report
10/317
6
1459.2 ft. This corresponds to a minimum peak discharge of approximately 3000 cfs at a PMF peak
lake elevation of 1463.2 ft. Selection of a design discharge exceeding 3000 cfs would not cause
impacts to the design of the City of Devils Lake Embankments. A target design discharge greater than
approximately 3000 cfs was not pursued, as action is required at downstream communities for flows
less than 3,000 cfs.
Based on the assessment that substantial erosion could precede peak lake elevation for the design
event, the weir structure is sized to pass approximately 3000 cfs under free flow conditions at a peak
lake elevation of 1463.2 ft. Steady state hydraulic modeling and analysis using HEC-RAS version 4.1.0
was conducted to develop rating curves for with and without project conditions assuming No-
Erosion. The PMF inflow of 1.44 million acre-feet was routed on a daily time step using a with
project rating curve to ensure the structure does not result in an increase to the peak water surface
elevation of 1463.2 ft.
Tailwater Depth (d2) for the Tolna Coulee structure is assumed to be variable from 5 feet to 17.2 feet
for the design event as Tolna Coulee erodes. Tailwater elevations for structural and geotechnical
analysis of different headwater and tailwater combinations are provided in Appendix C.
5.3 Stilling BasinFor the design water surface elevation of 1463.2 ft, stop-logs at 1458.2 ft and 1459.2 ft are designed
to pass 5 ft and 4 ft of total head respectively. Drop heights from stop logs at elevation 1458.2 ft and
elevation 1459.2 ft are 13.6 ft and 14.6 ft respectively. Stilling basin requirements were determined
by analyzing peak design head at each invert elevation for both high and low tailwater scenarios.
Basin dimensions were calculated using experimental results and design guidelines proposed by
Donnelly and Blaisdell in the technical paper, Straight Drop Spillway Stilling Basin. The floor of the
designed stilling basin is at elevation 1444.6 ft. The required stilling basin is 49.5 feet long with 43.5
feet between the straight drop and the baffle blocks. The 16-inch square baffle blocks occupybetween 50% and 60% of the total stilling basin cross sectional area.
5.4 Composite I-Wall/EmbankmentTo be consistent with the approved Devils Lake Flood Risk Management Project Design Criteria and
Project Considerations Report, a freeboard requirement of the maximum of 3 feet or wind/wave
requirements was adopted for the Tolna Coulee structure.
Wind and wave impacts were analyzed using Coastal Engineering Manual and Shore Protection
Manual methodologies. For the City of Devils Lake Embankments project, wave analysis and design
following Shore Protection Manual methodology required that wave run-up be contained by the
embankments. Because run-up does not apply to vertical structures, guidance for allowable
overtopping from the Coastal Engineering Manual was used.
For a lake level of 1463.2 ft, Wind Setup of 0.4 feet, and significant wave height of 3.3 feet - 4 feet of
freeboard (top of structure elevation of 1467.2 ft) is provided to ensure the structure does not
exceed a No Damage overtopping discharge of 0.1 cfs/ft for the design event.
7/29/2019 Design Documentation Report
11/317
7
Riprap erosion protection is designed for locations on the Composite I-Wall/Embankment and
upstream and downstream of the spillway / stilling basin structure using applicable criteria.
6 GEOTECHNICAL ENGINEERING
6.1 General
This section provides the geotechnical engineering in support of the final design, specifications and
cost estimate for the Tolna Coulee Advance Measures project. The project includes: Construction of a
composite I-wall/embankment with a top elevation of 1467.2 (NAVD88), a stop log control structure
with a stop log crest elevation of 1458.2 for the 4 center bays and 1459.2 for the remainder of the
bays, and a top of concrete footing elevation of 1447.2. Construction of the sheet pile I-wall will
require embankment to be constructed upstream and downstream of the I-wall to limit stickup to
acceptable levels. An embankment with a top elevation of 1463.2 and will be constructed between
the north end of the structure and the north bank of the coulee, with a ramp to 1467.2 to allow
access to the structure. An embankment with a top elevation of 1461.2 and will be constructed
between the south end of the structure and the south bank of the coulee. Detailed information
related to the geotechnical design criteria, design cases, and other information related to
geotechnical design can be found in the Geotechnical Appendix (Appendix D).
7 CIVIL ENGINEERING
7.1 Introduction
This section summarizes the proposed layout, method of analyses, and support for preparation of
the plans, specifications, and cost estimate. The layout attempted to optimize the use of the existing
ground, avoid private property, and meet conditions needed to suit subsurface properties in an
effort to reduce overall cost. In specific, the civil portion of the project involved the design and
layout of embankments, site work, access roads, and site drainage. The embankment was utilized
around the structure and sheetpile to provide access, meet passive and uplift pressures, and
eliminate sliding of the structure. An embankment elevation of 1463.2 was followed on the north
side of the structure and an embankment elevation of 1461.2 was utilized on the south side of the
structure. A half mile long gravel road, turnaround, and parking spaces were designed to provide
access to the structure. In addition a storage yard was included for the storage of stop logs needed to
operate the closure structure. Lastly roadside ditching was utilized to convey drainage along its
natural path.
7.2 Technical Guidelines and References
1. A/E/C CADD Standard, Release 3.0; U.S. Army Engineer Research and Development Center,Vicksburg, MS; September 2006.
2. A/E/C CADD Standard Supplement, Release 6.2.0; U.S. Army Corps of Engineers, St. PaulDistrict; July 2004.
3. A Policy on Geometric Design of Highways and Streets, Fifth Edition; pp. 131-229, 231-234,and 380-389; American Association of State Highway and Transportation Officials
(AASHTO); 2004.
7/29/2019 Design Documentation Report
12/317
8
4. United States National CAD Standard, Version 4.0; National Institute of Building Sciences;July 2009.
5. Guidelines for Geometric Design of Very Low-Volume Local Roads; American Association ofState Highway and Transportation Officials (AASHTO); 2001
7.3
Source of Data for Existing Topographic Information
Existing topographic data utilized for the design and drawings was from topographic LIDAR surveys
and field survey information performed by City of Devils lake. The project area has been surveyed
by a State of North Dakota survey crew in May 2011 and the data is in the process of being converted
for its use in the design. The coordinate system and projection of the topographic mapping data is
NAD83 (2007), North Dakota State Plane Coordinate System, North Zone (U.S. Survey Feet). The
elevation datum of the topographic mapping data is NAVD88 (U.S. Survey Feet).
7.4 Programs and Standards for Design and Drawings
The computer-aided drafting and design (CADD) program used for the drawings utilized MicroStation
V8i (Version 8.11, October 2008) and topographic data with INROADS generated TIN file, profiles,
and cross sections. All drawings adhered to national, Mississippi Valley Division, and St. Paul DistrictCADD standards.
7.5 Design Process and Standards for Civil Features
Roadway design was based on the standards included in AASHTOs 2004 bookA Policy on Geometric
Design of Highways and Streets (Reference 3) ) andAASHTOs 2001 book Guidelines for Geometric
Design of Very Low-Volume Local Roads (Reference 5).
7.5.1
The access road begins 800 feet West from the East edge of section 19 on 33rd Street NE at sta
0+00 and continues to the south through the natural swale to the project site. The alignment is
specifically designed to minimize earthwork and reduce vertical grades to acceptable levels. The
road is classified as a rural minor access road. The road surface consists of gravel at a width of 20
which includes the shoulders. The specific design information to design the horizontal curves are
as follows:
Geometric Design Criteria Access Road
Design speed 20 mph Design Stopping Sight Distance 115 ft Superelevation e=0 Side friction factor f=0.13
The vertical alignment of Tolna Coulee access road navigates a difference of 40 in elevation over
2500 feet in length approximately. The vertical profile of the road is as follows:
Design speed 20 mph Roadway max Slope -6.0% Design Stopping Sight Distance 115 ft Rate of Vertical Curvature, K = 7 for crest curves and K=17 for sag curves
7.6 Engineering Drawings for Embankments and Site Work
Drawings produced for the submittal utilized the following information:
LIDAR Topographic Survey Data
7/29/2019 Design Documentation Report
13/317
9
City of Devils Lake Field Survey Data MicroStation V8i model and sheet seed files Design files including cross-sections, alignment, and TIN files USACE Standards
Civil engineering drawings and plans prepared concurrent with this report are included in AppendixA.
7.7 Phase 1 Environmental Site Assessment
The St. Paul District has performed a Phase I Environmental Site Assessment (ESA) in conformance
with the scope and limitations of American Society for Testing and Materials (ASTM) Practice E 1527-
05. The environmental site assessment has revealed no evidence of recognized environmental
conditions in connection with the subject properties.
8 STRUCTURAL ENGINEERING
8.1 General
The structural design of the Tolna coulee outlet project is comprised of five major components
stoplog control structure, including a walkway, overhead frame and monorail, pickup beam, and
stoplogs; upstream approach walls; downstream wing walls; and left and right bank I-walls. Detailed
information related to the structural design criteria, design loads, load cases, and other information
related to structural design can be found in the Structural Appendix (Appendix E).
8.2 Structure Design
Structural design of hydraulic structures is in accordance with EM 1110-2-2104 and EM 1110-2-2105
for reinforced concrete and structural steel, respectively. A single load factor of 1.7 plus hydraulic
factor of 1.3 are used for reinforced concrete. Structural design for non-hydraulic structures is in
accordance with ACI 318-05. The design of the walkway and other steel structural components are in
accordance with AISC Steel Construction Manual. Design information for the following structures can
be found in the Structural Appendix.
8.2.1
The stoplog control structure is an approximately 66-feet wide, 162-feet long and 26-feet high
reinforced concrete structure. The structure consists of reinforced concrete side walls with a
reinforced concrete slab in between. There are 11 reinforced concrete piers to support the
walkway and stop logs. A sheetpile cutoff is included along the entire perimeter of the slab and is
tied to the adjacent sheetpile I-walls.
Stoplog Control Structure
8.2.2
There are 2 retaining walls on each side of the control structure on the upstream side and two
wing walls on the downstream side of the structure.
Retaining Walls and Wing Walls
8.2.3
The sheet pile I-wall is designed as a cantilevered wall. The top of the sheet pile wall will be cut off
at the design elevation. A cap will not be installed on the sheet pile I-wall. The exposed height of
Sheet Pile I-wall
7/29/2019 Design Documentation Report
14/317
10
the sheet pile on the south embankment is 6 feet. The exposed height of the sheet pile on the
north embankment is 4 feet.
8.2.4
A 5 foot wide (clear distance) walkway will be constructed across the entire width of the control
structure, and will be supported by the concrete piers. The walkway is intended to provide access
for inspection and for removal of the stoplogs. It must be wide enough to accommodate an ATV to
facilitate removal of the stoplogs.
Walkway
8.2.5
A gantry crane with V-shaped steel wheels will run on angle iron tracks for the length of the
walkway. The gantry crane will support the hoist and pickup beam.
Gantry Crane
8.2.6
A lifting beam will be required to facilitate removal of the stoplogs. The latching mechanism will
be designed to work with the welded studs on the sides of the stoplogs. The lifting beam and
stoplogs will be specified as a system to minimize chances of the stoplogs and lifting beam not
working properly.
Lifting Beam
8.2.7
The stoplogs will be constructed of steel and will be galvanized. Pickup will be by welded studs on
the sides of the stoplogs or by slots cut in the tops of the stoplogs.
Stoplogs
8.3 Miscellaneous
8.3.1
In general, a minimum of five feet of cover is maintained over the base of foundations for frost
protection.
Frost Protection
9 MECHANICAL AND ELECTRICAL ENGINEERING
9.1 Mechanical Design
Mechanical design for the control structure is limited to the gantry crane and hoist system to be used
for removal of stop logs.
9.1.1
The control structure will be equipped with a gantry crane and hoist system to remove the
stoplogs from the stoplog slots.
Gantry Crane and Hoist Selection
The selected components include a gantry crane, and a manually operated chain hoist. Thegantry crane will ride on steel V-shaped wheels to allow easy travel without electric power. The
gantry crane will include a transverse I-beam to allow the hoist to travel sideways within the
frame since the stoplog slots are off-set from the centerline of the walkway. The manually
operated chain hoist was selected due to the lack of electric power at the site.
Gantry crane and hoist information, including loads used in the structural design and structural
calculations are presented in Appendix E.
7/29/2019 Design Documentation Report
15/317
11
9.2 Electrical Design
There is no electrical power at the site and there is no need for electric equipment or lights. The
hoists to be used to remove the stop logs are hand powered and all maintenance work and stop log
removal can be done during daylight hours so there is no need for lighting. If observation is needed
at night, portable light plants can be brought in to provide the necessary light.
10CONSTRUCTABILITYInformation will be added to this section prior to the BCOE submittal.
10.1 Introduction
The compressed schedule for design and construction of the project resulting from the rising lake
levels will require that the majority of this project be constructed in the winter.
10.2 Sequence of Construction
10.3 Embankments
Due to the plan to construct the majority of this project during the winter months, an effort has been
made to minimize earthwork and limit the compaction requirements for embankment. For the
earthwork that is required, 24 hour operation during construction will be required to minimize issues
with freezing of the fill between lifts.
10.4 Structure
10.5 Coordination with Other Agencies
11INSTRUMENTATION
Information will be added to this section prior to the BCOE submittal.
11.1 Monitoring Points
11.2 Construction Monitoring
11.3 Long-Term Performance Monitoring
12COST ESTIMATE AND CONSTRUCTION SCHEDULE
12.1 Cost Estimate
The cost estimate was prepared using MCACES Second Generation (MII) software, version 3.1, Build2. The cost estimate is based on the acquisition plan, which includes the use of an IFB restricted to
small businesses. As such, it includes a subcontracting plan and prime contractor overhead rate that
would be likely for a small business. Productivity was adjusted within the estimate for certain items
to account for the impacts of cold weather and snow due to the requirement to complete the
majority of this project during the winter months. Contingencies were developed using the
abbreviated risk analysis spreadsheets developed by the Corps of Engineers Cost DX.
7/29/2019 Design Documentation Report
16/317
12
12.2 Construction ScheduleA construction schedule was developed for the project that shows that the project can be
constructed by March 12, 2012, assuming a NTP of 7 October 2011. This schedule, however, does
not include time for weather days, meaning that the Contractor will be expected to work through the
winter weather and make accommodations to their operations and planning to account for the
expected severe weather. The schedule also shows that multiple crews will be required to completethe project on time.
13REVIEW DOCUMENTATION
13.1 District Quality Control (DQC) Review
Documentation will be added after the DQC review has been completed.
13.2 Agency Technical Review (ATR)
Documentation will be added after the ATR has been completed.
13.3 Independent External Peer Review (IEPR)
Documentation will be added after the IEPR has been completed.
7/29/2019 Design Documentation Report
17/317
Appendix A
Plan Set
---
Provided Under
Separate Cover
7/29/2019 Design Documentation Report
18/317
Appendix B
Specifications
---
Provided Under
Separate Cover
7/29/2019 Design Documentation Report
19/317
Appendix C
Hydrology/Hydraulic Appendix
7/29/2019 Design Documentation Report
20/317
7/29/2019 Design Documentation Report
21/317
Tolna Coulee: H&H Appendix Page 2
TolnaCouleeControlStructure
FunctionoftheTolnaCouleeStructure:
Apreliminaryanalysis,TolnaCouleeOutletErosion(BARREngineering,2001)(Reference1),examined
both
the
hydraulic
and
the
geotechnical
parameters
of
Tolna
Coulee.
The
preliminary
analysis
indicates
thatgiventhenatureofthesoils,thereisahighpotentialforsevereerosiontooccur. Erosioncould
significantlyincreasetheoutflowthroughthecouleeintheeventofanaturaloverflowduetothelarge
volumeofwaterstoredinthelake. Ananalysiswasdoneonthepotentialoutflowassociatedwiththe
ProbableMaximumFlood(PMF). Theanalysisassumesaninitialfullpoollakeelevationof1459.2
ft. Table1comparesthepeakandsustainedoutflowsforthePMFassumingnoerosionofthecoulee,
andwitherosion.
Table1a:TolnaCouleeNaturalCondition(NoProject)OutflowComparison
SummaryStatistic NoErosion Erosion
PeakElevation 1463.2 1462.7
Peak
Outflow
(cfs)
3,000
14,000
Daysabove2,500cfs 51 136
Daysabove12,000cfs 0 19
Volumeinfirst180days(acreft.) 592,000 1,833,000
Volumeinfirst365days(acreft.) 982,000 2,379,000
Assumptions:
a)StartingWSEL=1459.2ft
b)Inflowvolume=1/2ProbableMaximumFlood(PMF)(1,440,000acreft.)
Table1ashowsuncontrolledflowsassociatedwitherosioncouldexceed12,000cfsforapproximately19
dayswithapeakoutflownear~14,000cfsinTolnaCoulee.
ThestructuredescribedinthisdocumentistobelocatedupstreamofthenaturalhighpointofTolna
CouleenearStumpLake(Figure1b). Shouldthedownstreamhighpointerode,causingacapacityofthe
highpointtoexceedapproximately3000cfsattheProbableMaximumFlood(PMF)lakeelevation
of1463.2ft,thecontrolstructurerestrictspeakflowstolessthanwouldhaveoccurrednaturally. Stop
logsareincludedinthestructuretoallowforacontrolledloweringofthelake. Stoplogswouldbe
removedtomatchnaturaldownstreamerosiontoamaximumflowrateofapproximately3000cfs. The
samevolumeofwaterthatwouldevacuatethelakewithouttheprojectshouldbeallowedtoevacuate
thelakeoveralongerduration.
ASAFTypestraightdropstillingbasin,inaccordancewithdesignguidelinesproposedbyDonnellyand
Blaisdell(1954),hasbeendesignedforenergydissipationimmediatelydownstreamofthestructure.
Forthe
SAF
straight
drop
spillway
stilling
basin,
Water
falling
over
the
spillway
crest
falls
onto
aflat
apron. Thenappeisbrokenupbyfloorblocks,whichalsopreventdamagingscourofthedownstream
channelbanks. Scourofthedownstreamchannelbedispreventedbyanendsill. Flaringwingwalls,
triangularinelevation,preventerosionofthedamfill(Reference2).
7/29/2019 Design Documentation Report
22/317
0 10000 20000 30000 40000 50000 60000 1340
1360
1380
1400
1420
1440
1460
1480
Channel Distance (ft)
Elevation
(NAVD
1988)(ft)
Highway
15
TolnaDam
RailroadEmbankment
CountyR
oad24
98thAvenueNE
CountyR
oad4
3 2 n d S t r e
e t N E
Sheyenne River
Natural High
Figure 1b: Tolna Coulee Profile - Devils Lake to the Sheyenne River
7/29/2019 Design Documentation Report
23/317
Tolna Coulee: H&H Appendix Page 4
StructureType:
DesignoftheDevilsLakeTolnaCouleecontrolstructurefollowstheguidelinesforaSaintAnthony
Falls(SAF)StraightDropStructureoutlinedinthearticleStraightDropSpillwayStillingBasinby
DonnellyandBlaisdell(Reference2). TheSAFstructurewasselectedinlieuofaCaliforniaInstituteof
Technology(CIT)structure(Reference3),asthemaximumdesigndropheight/criticaldepthvalueof
5.5fortheTolnaCouleestructureliesoutsideofexperimentallytestedvaluesforaCITstructure
(Reference4). TheSAFstillingbasincanbeusedforawiderangeofdischarge,headonthecrest,crest
length,heightofdrop,anddownstreamtailwaterlevel[s](Reference1). Historyofhighlyvariablelake
levels,potentialforerosionofthenaturalhighpointdownstreamofthestructure,andintended
operationmakeitcriticalthatthestructurebeabletoperformoverawiderangeofscenarios.
SelectionofInflowDesignFlood(IDF):
InconsistencywithfloodprotectioneffortsintheDevilsLakesubbasin,includingtheCityofDevilsLake
EmbankmentsandRoadsActingasWaterBarriers,theTolnaCouleecontrolstructureisdesignedfora
InflowDesignFlood(IDF)ofProbableMaximumFlood(PMF)withthelakestartingatfullpool
(Elevation1459.2
ft).
Information
related
to
the
accepted
PMF
event
at
Devils
Lake
is
contained
in
the
DevilsLakeFloodRiskManagementProjectDesignCriteriaandProjectConsiderationsReport
(Reference5).
DesignDischarge:
Thedesignwatersurfaceelevationof1464.2ftfortheCityofDevilsLakeEmbankmentsisbasedona
PMFinflowvolumeof1.44MillionAcreFeetwithafullpoolstartinglakeelevationof1459.2ft. The
PMFpeaklakeelevationatTolnaCouleeassumingnoerosionis1463.2ftwithanapproximatepeak
dischargeof3000cfs. ThedesignwatersurfacefortheCityofDevilsLakeEmbankmentsassumes1
footoflakeslopefromtheCityofDevilsLakeEmbankmentstotheoutflowatTolnaCoulee.
TocausenoimpactstothedesignoftheCityofDevilsLakeEmbankments,thedesigndischargeforthe
structureatTolnaCouleemustnotresultinanincreasetothepeakstillwaterlevelelevationabove
1463.2ftatTolnaCouleeforaPMFinflowtoDevilsLakeonastartingpoolelevationof1459.2ft. This
correspondstoaminimumpeakdischargeofapproximately3000cfsatthePMFpeaklakeelevation
of1463.2ft. Selectionofadesigndischargeexceeding3000cfswouldnotcauseimpactstothedesign
oftheCityofDevilsLakeEmbankments. Atargetdesigndischargegreaterthanapproximately3000cfs
wasnotpursued,asactionisrequiredatdownstreamcommunitiesforflowslessthan3,000cfs.
ThereportTolnaCouleeOutletErosion(Reference1)describeserosionofTolnaCouleeinitiatingat
thedownstreamslopeofthenaturalhighpointandprogressingupstreamtowardthelake. Forthe
designevent,hydraulicroutingusingsedimenttransportanalysismethodsproposedbyColby
(Reference1)showsDevilsLakereachingpeakelevationafterthecouleehassubstantiallyeroded.Hydraulicroutinganderosionanalysiswascomputedonadailytimestepusingthespreadsheet
Devils_Lake_Run_ESO.xls.
Basedontheassessmentthatsubstantialerosioncouldprecedepeaklakeelevationforthedesign
event,theweirstructurewassizedtopassapproximately3000cfsunderfreeflowconditionsatalake
elevationof1463.2ft.
7/29/2019 Design Documentation Report
24/317
Tolna Coulee: H&H Appendix Page 5
StraightDropStructure:
Severalcombinationsofstartingstoplogelevationswithweiropeningsizeswereevaluatedthatwould
achieveadesigndischargeofapproximately3000cfs. Basedonprojectsponsorpreference,starting
stoplogelevationsbetween1458.2ftand1459.2ftwereselectedtocloselymatchexistinggradeofthe
highpointthalweg. Astartingelevationof1458.2ftfor4of12totalstoplogbaysensuresthatwateris
notinhibitedfrommovingtooroverthehighpointbetweenelevation1458.2ftand1459.2ftifallowed
byexistinggrade.
Usingtheweirflowequation(Equation1)andacoefficientofC=3.0(Reference3),acombinedweir
lengthof40feetat1458.2ftand80feetat1459.2ftresultsinaflowrateofapproximately3000cfsata
lakeelevationof1463.2ft.
1 Q C L H
QMF 3.080ft1463.2 ft 1459.2 ft
3.040ft1463.2 ft 1458.2 ft
3262 cfs 3000 cfsWeirlength,discharge,andassociatedratingcurvesweredeterminedusingthe
FreeFlow_RatingCurve_CalculatortaboftheUpstream_Structure_Analysisdesignspreadsheet.
Aratingcurvefortheweirstructureunderfreeflowconditions,anticipatedgivensufficienterosionof
thecoulee,isshowninTable2. TheratingcurveforthestructurefortheNoErosionorPreErosion
scenarioisshowninTable3. TheNoErosionratingcurveshowninTable3wasinterpolatedfrom
watersurfaceprofilesthatweredevelopedusingTolnaCoulee_Upstream_Structure_12gates.g07
(Plan:TolnaCoulee_12_Gates)
from
the
HEC
RAS
model
TolnaCoulee.
Profiles
were
developed
using
steadyflowanalysisinHECRASversion4.1.0.
Table2: StructureFreeFlowRatingCurve Table3:StructureNoErosionRatingCurve
7/29/2019 Design Documentation Report
25/317
Tolna Coulee: H&H Appendix Page 6
HECRASModelandNoErosionAnalysis:
ThegeometryfileTolnaCoulee_Upstream_Structure_12gates.g07(Plan:TolnaCoulee_12_Gates)from
theHECRASversion4.1.0ModelTolnaCouleewasusedtoanalyzetheweirstructure. Steadystate
modelresultswereusedtoverifythatthestructuredoesnotresultinanincreasetothepeakStillWater
Level(SWL)of1463.2ftatTolnaCouleeforthePMFeventusedtodesigntheCityofDevilsLake
embankments.
TheTolnaCouleecontrolstructurewasmodeledasanInlineStructurewithtwelve10footoverflow
gates(InvertElevations:8at1459.2ft,4at1458.2ft)havingaweircoefficientofC=3.0. Overflowgates
areseparatedby2footpiers. Ineffectiveareasassumeexpansionandcontractionratiosof1:1.
Contractionandexpansioncoefficientsaresetto0.3and0.5respectivelyforcrosssectionsadjacentto
thestructuretorepresentcontractionofflowfromthewiderlakecrosssectionstothenarrowercontrol
structure. AcrosssectionviewofthestructureisshowninFigure4.
Figure4:CrossSectionViewofTolnaCouleeStructureModeledUsingHECRAS
WatersurfaceprofilesfortheweirstructureassumingNoErosionweredevelopedusingtheHECRAS
model. AratingcurvefortheweirstructureassumingNoErosionwasinterpolatedat1footelevation
intervalsfromwatersurfaceprofilesattheupstream(DevilsLake/StumpLake)endofthemodel. The
PMF
inflow
event
on
a
starting
lake
elevation
of
1459.2
ft
was
routed
through
the
interpolated
rating
curve(Table3)onadailytimestepusingthespreadsheetDevils_Lake_Run_ESO. Figure5onthe
followingpageshowslakeelevationvs.timeforwithandwithoutprojectconditionsforthedesign
eventassumingNoErosion.
RoutingthedesigneventassumingNoErosiondoesnotresultinasignificantincreasetothePMF
designwatersurfaceelevationof1463.2ftatTolnaCoulee. ForaPMFpeaklakelevelof1463.2ftat
TolnaCoulee,assuming1footoflakeslopefromTolnaCouleetotheCityofDevilsLakeEmbankments,
thedesigneventpeakwatersurfaceremains1464.2ftfortheCityofDevilsLakeEmbankments.
7/29/2019 Design Documentation Report
26/317
1,462
1,463
1,464
n(NAVD
1988Ft)
TolnaCouleeElevations(NAVD1988ft)forthe1/2PMF
NoErosion W.S.WithProject
NoErosion W.S.WithoutProject
Summ
NoEroPeakWWithPr
Withou
1,459
1,460
1,461
0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 480 510 540 570
Elevati
DaysMar
Apr
May
Jul
Jun
Aug
Sept
Oct
Nov
Jan
Dec
Feb
May
Jul
Jun
Aug
Sept
Oct
Figure 5: Tolna Coulee Water Surface Elevations for the 1
7/29/2019 Design Documentation Report
27/317
Tolna Coulee: H&H Appendix Page 8
StillingBasinDesign
Forthedesignwatersurfaceelevationof1463.2ft,stoplogbaysat1458.2ftand1459.2ftareexpected
tooperateunder5feetand4feetoftotalheadrespectively. SAFstillingbasindimensionsare
dependentuponcriticaldepthanddropheight. Astillingbasinwassizedforbothstartingstoplog
elevations,withtherecommendedbasindimensionsselectedforthemostseverecase.
DesignguidancefortheSAFstructurestatesthatthestillingbasinlengthcomputedforaminimum
tailwaterlevelrequiredforgoodperformancemaybeinadequateathighertailwaterlevels. Dangerous
scourofthedownstreamchannelmayoccurifthenappeissupportedsufficientlybyhightailwaterso
thatitlandsbeyondtheendofthestillingbasin(Reference2).
Becausetailwaterisanticipatedtobevariableforthedesignevent,fromabovetheweirinverttobelow
theinvert,stillingbasindesignwasconductedforbothhightailwater(1463.2ft)andlowtailwater
(1451.2ft)scenarios. Stillingbasindesignwasconductedusingthedesignspreadsheet
SAF_StraightDrop_Design.xlsx. Designdimensionsthatwillperformforhigh,low,andintermediate
tailwaterscenarioswereselected. CriticalhydraulicdimensionsforthestillingbasinareshowninTable
6. Baffleblocksarespacedtoensurethatbetween50% 60%ofthebasincrosssectionalareaisblocked,asrecommendedinthedocumentStraightDropSpillwayStillingBasin(Reference2).
ThetoeoftherequiredIWall/Embankmentcompositesystemextendsfurtherdownstreamthanthe
endofthestillingbasinandwingwallsrequiredforhydraulicperformance. Lengtheningthestilling
basinbymovingtheendsillfurtherdownstream andchangingthewingwallslopetogradewere
requiredtofacilitatesitelayoutandensurethewingwallsretainallembankmentfill. Lengtheningthe
stillingbasinwasconductedinaccordancewithStraightDropSpillwayStillingBasin(Reference2).
Modificationstothewingwallsfollowthethedesignguidelinesoutlinedin,HydraulicDesignoftheBox
InletDropSpillway(Reference17).
7/29/2019 Design Documentation Report
28/317
Tolna Coulee: H&H Appendix Page 9
Table6:DesignDimensionsforTolnaCouleeSAFTypeStructure
DesignrecommendationsforSAFstructuresprovidedbyRiceandKadavy(Reference15)suggestadding
aradiustransitionfromtheheadwalltotheweir. Addingtheradiustransitionreducesflow
concentrationatthecenteroftheweir,resultinginlesslocalizedscourdownstreamofthebasin.
ExperimentaltestresultspresentedinRiprapDesignDownstreamofStraightDropSpillways(Reference15)recommendaradiusofatleast3dctorealizemaximumbenefitsoftheradiustransition.
Basedondc(criticaldepth)of3.3feetforstoplogbaysatelevation1458.2ft,a10footradiustransition
fromtheabutmentstotheweirwasincorporatedintothedesignoftheconcretestructure.
TailwaterAssumptionsandLoadCaseDetermination
TailwaterDepth(d2)fortheTolnaCouleestructureisassumedtobevariablefrom5feetto17.2feetfor
thedesigneventasTolnaCouleeprogressivelyerodes. Thefollowingtailwaterelevationswere
providedforanalysisandloadcaseformulation:
TailwaterElevation:
1451.8
ft
Atailwaterelevationof1451.8ftcorrespondstoanerodedTolnaCouleechannelhavingathalwegat
elevation1447.2ft. ThedepthwasdeterminedusingManningsequationforuniformflowwithsomeof
theerosionassumptionsoutlinedinthereportTolnaCouleeOutletErosionbyBARREngineering
(Reference1). ParametersusedforanalysisareshowninTable7.
7/29/2019 Design Documentation Report
29/317
Tolna Coulee: H&H Appendix Page 10
Table7:ManningsEquationParameters
Tailwater Analysis Parameters
Channel Slope (ft/ft) 0.00126
Channel Bottom Width (ft) 150
Manning's Roughness (n) 0.035
Channel Side SlopesHorizontal 1.5
Vertical 1
TailwaterElevation:1448.4ft
Atailwaterelevationof1448.4correspondsto3000cfsflowingatcriticaldepth(dc)overthe142foot
wideendsillofthestillingbasin. Thiswasassumedtobethelowestreasonabletailwaterfor3000cfs
passingoverthestructure. Theelevationwasdeterminedusingtheequationforcriticaldepththrough
arectangularchannel(Equation2):
2 d Q
d
./ =2.4feet
TailwaterDepth=EndSillElevation+dc1446ft+2.4feet= 1448.4ft
TailwaterElevation:1450.8ft
Thecontrolstructurewasanalyzedforaheadwaterelevationequaltothetopofthewallelevationof
1447.2ft. Forthiscase,morethan3000cfswouldbepassingoverthestoplogs. Usingtheweir
equationwithaweircoefficientofC=3.0calculatesthat8,671cfspassesoverthestructure. Aflowrateof8,671cfsatcriticaldepthoverthe142footwideendsillofthestillingbasincorrespondstoa
tailwaterelevationof1450.8ft. Theelevationwasdeterminedusingtheequationforcriticaldepth
througharectangularchannel(Equation2):
2 d Q
d
./ =4.87feet
TailwaterDepth=EndSillElevation+dc1446ft+4.8feet= 1450.8ft
7/29/2019 Design Documentation Report
30/317
Tolna Coulee: H&H Appendix Page 11
WindandWaveAnalysis
DesignWind
DesignwindspeedswereadoptedfromapproveddesigndocumentationfortheDevilsLakePhase3
Embankments. Thedesignwindanalysisusestenyearsofwinddata,fromJune1985to1995.Astudy
byBaker(Reference6)concludedthattenyearsofrecordisamplewhenlookingforwindpatterns.Theaverageofthemaximumannualwindspeedsovertenyearswasadoptedforeachwinddirection(Table
8).ThesearethesamewindspeedsadoptedfortheexistingCityofDevilsLakeembankments,which
havewithstoodthewindandwaveforcessinceconstructionin2004withoutanyissues. Awindrose
illustratingprevalentwinddirectionforthe1985to1995periodisshowninFigure9.
Table8:DevilsLakeAverageofMaximumAnnualWindSpeeds(mph)(19851995)
Figure9:WindRoseDevilsLakeAverageofMaximumAnnualWindSpeeds(mph) (19851995)
7/29/2019 Design Documentation Report
31/317
Tolna Coulee: H&H Appendix Page 12
WindSetup
WindsetupbasedonaJuly2006MemorandumforRecord(Reference7).Windsetupascomputedby
theformulapresentedintheCEMishighlydependentonwaterdepth,makingtheassumedwater
depthcriticaltotheresultingwindsetupvalue. Foreaseofcomputation,themethodologycurrentlyin
usebytheStPaulDistrictatthelocksanddamsistoassumeaonetenthriseinthewatersurfacefor
everytenmilesperhourofwindspeed. Whilethismayseemoverlysimplistic,ithasworkedwellatthelocksanddamsandhasthebenefitofnotbeingwaterdepthdependant. Thismethodwasalsousedin
theapproveddesignoftheDevilsLakePhase3Embankments. Windsetupof0.4ftwasusedforthe
TolnaCouleecontrolstructure.
FetchLength,CriticalWindDirection,andWaveGeneration
Theeffectivefetchlengthwasdeterminedbymethodsdiscussedin339oftheShoreProtectionManual
(SPM)(Reference8). Fetchvectors,perpendicularwiththestructurealignmentandat3degreeoffsets
wereanalyzed. Theperpendiculardistancefromthestructuretotheupstreamshorelineis0.6Miles.
Theaveragefetchlengthof9radialsspacedat3degreesisapproximately1.8miles.Themaximumfetch
vectoris5milesandtheminimumfetchvectoris0.1miles. Afetchlengthof5mileswasselectedfor
design.
A
map
of
Stump
Lake
with
wind
fetch
vectors
is
shown
in
Figure
10.
Criticalfetchlengthsforthestructurecorrespondtowinddirectionsbetween45degreesand135
degrees. Awindof27.2MPHOverlandEastwasusedfordesign. Thecriticaldesignwindresultsin
WaveHeight(H)=3.3ft,WavePeriod(T)=3.5seconds,andWavelength(L)=62Ft. Designformulas
andcalculationsrelatedtoWind/Wavedeterminationsarecontainedinthespreadsheet
TolnaCoulee_WindWave.xlsx.
FreeboardRequirements
Typically,DamSafetyCriteriaER111082(FR)(Reference9)requires5feetoffreeboardfor
embankmentdams. TobeconsistentwiththeapprovedDevilsLakeFloodRiskManagementProject
DesignCriteriaandProjectConsiderationsReport(Reference5),afreeboardrequirementofthe
maximumof3feetorwind/waverequirementswasadoptedfortheTolnaCouleestructure.
FortheCityofDevilsLakeEmbankmentsproject,waveanalysisanddesignfollowingShoreProtection
Manualmethodologyrequiredthatwaverunupbecontainedbytheembankments. Becauserunup
doesnotapplytoverticalstructures,guidanceforallowableovertoppingfromtheCoastalEngineering
Manualwasused.
TheIWall/EmbankmentcompositestructurewasanalyzedusingtheovertoppingformulabyFrancoand
Franco(1999)fromTableVI513oftheCoastalEngineeringManual. Foralakelevelof1463.2ft,Wind
Setupof0.4feet,andsignificantwaveheightof3.3feet:
OvertoppingDischarge(q) 0.1cfs/ft foratopofsheetpileelevationof1467.2ft.
Elevation1467.2ftis4feetabovetheStillWaterLevel(SWL)of1463.2ftforthedesignevent.
TableVI56:CriticalValuesofAverageOvertoppingDischargesfromtheCoastalEngineeringManual
(Reference10)showsthatq 0.1cfs/ftfallswithinthestructuralsafetylimitsfor"NoDamage"for
GrassSeaDikes. Anyadditionalerosionresistancetowaveovertoppingprovidedbyrockonthe
downstreamslopeoftheembankmentwasnotconsideredindeterminationoftheappropriate"No
Damage"threshold.
7/29/2019 Design Documentation Report
32/317
5
4.9
4.6
0.6
0.4
0.1
Map Legend
Perpendecular Fetch Vector
Fetch Vectors
Lake Extent at 1459.2 ft (NAVD 1988)
Lake Extent at 1463.2 ft (NAVD 1988)
Tolna Coulee : Control Structure - Wind / Wave Impacts
/0 1 20.5 1.5 Miles
Perpend icular Fetch Lengt h: 0.6 Miles
Average Fetch Length ( SPM) : 1.8 M iles
Maxim um Fetch Length : 5 Miles
ure 10: Stump Lake Fetch Map
7/29/2019 Design Documentation Report
33/317
Tolna Coulee: H&H Appendix Page 14
IceImpacts
AmajorityofDevilsLakeinflowandassociatedlakeriseoccursinthelatespringandsummer(April
July). Icejammingisnotanticipatedtobeamajorproblemduringthemajorityoftheinfloweventdue
towarmweatherconditions. Forthe4monthPMFdesignevent,iceisnotanticipatedtorestrictor
preventflowfromleavingthelakeforadurationthatwouldresultinasignificantincreasetothedesign
watersurface
elevation
of
1463.2
ft.
The
structure
is
designed
for
ice
loading
where
applicable.
Piers
aredesignedassumingicecouldpotentiallybridgebetweenpiersthusincreasingiceload. Stoplogsare
designedforiceloadswhenbridgingisnotoccurring.RiprapDesign
Gradations
RiprapgradationsthatwereestablishedfortheCityofDevilsLakeEmbankmentswereadoptedforthe
TolnaCouleestructure. Thesegradationswereadopted,astheyhavealreadybeendevelopedandwill
beinuseintheareaaroundthetimeofconstruction. Summarystatisticsforeachofthegradations
selectedfor
the
project
are
shown
in
Table
11.
Further
information
related
to
graded
riprap
and
beddingcanbefoundinthespecificationsandgeotechnicaldesigndocumentation.
Table11:RiprapSummaryStatisticsforTolnaCouleeGradations
UpstreamEmbankmentProtection
RockprotectionontheupstreamslopeandcrownoftheembankmentwasdeterminedusingEquation
216:ArmorUnitStabilityfromEM111021614(Reference11). Designcalculationsarecontainedin
thespreadsheetTolnaCoulee_WindWave.xls.
ThestabilitycoefficientusedincalculationofstonesizewasadoptedfromSpiritLake(DevilsLake),
NorthDakota,Phase2EvaluationofExistingRoads(Reference12). Accordingtothatdocument,StabilitycoefficientsforavariousarmorunitsareshownintheSPM. Astabilitycoefficientfora
graded,roundedripraphasneverbeendetermined. Foratriplelayerofsmoothroundedstone,the
stabilitycoefficient
is
3.2.
For
adouble
layer,
its
2.4.
Continuing
with
this
thought,
avalue
of
1.6
was
assumedforasinglelayerofagradedriprap.
Stonesizecalculationfortheupstreamembankmentslopeandcrownassumesasinglelayerofrounded
riprapwithaunitweightof165poundspercubicfoot(pcf)andaspecificgravityof2.65. Calculated
minimumW50fortheupstreamslopeandcrownoftheIWall/Embankmentcompositesystemsisshown
inTable12.
7/29/2019 Design Documentation Report
34/317
Tolna Coulee: H&H Appendix Page 15
Table12:MinimumD50SizeforTolnaCouleeLakesideEmbankmentSlope RoundGradedRiprap
Slope of Embankment ( _H:1V) 3.5
Minimum W50 Rock Weight (lbs): 228
BasedonthecalculatedminimumW50size,Gradation4wasselectedforuseontheupstreamslopeand
crownoftheIWall/Embankmentcompositesystem.
DownstreamEmbankmentProtection
Establishingandmaintaininggrasscoveronthedownstreamslopeandcrownoftheembankment
presentschallenges,astheembankmentwillbeunderwaterforlakeelevationsabove~1453ftpriorto
anyerosionofthenaturalhighpoint. ThedownstreamcrestandslopeofthecompositeIWall/
Embankmentstructurewillbeprotectedwithrockinplaceofgrasstoeasemaintenanceofthe
structure.
Determinationof
appropriate
rock
gradation
is
based
on
the
Minnesota
PCA
Technical
Criteria
Riprap
CriteriaforStabilizationPonds(Reference16). Theguidancewasdevelopedbecause,grasscannot
usuallybeestablishedinoneseasontoadequatelyprotect[stabilizationpond]dikesfromerosion. The
fluctuatingwaterlevelsinapondsoperationarenotconducivetogoodgrassgrowth(Reference16).
TheriprapgradationrecommendedintheMinnesotaPCAdocumentissimilartoandslightlysmaller
thanGradation1.
Gradation1wasselectedforthedownstreamslopeandcrownoftheIWall/Embankmentcomposite
system. Additionalerosionresistancetowaveovertoppingprovidedbytherockwasnotconsideredin
determinationoftheappropriate"NoDamage"threshold.
RockDownstreamofEndSill
RiprapW50sizedeterminedforrockdesignimmediatelydownstreamofthestillingbasinisbasedon
experimentallyderivedguidancepresentedintheASAEpublication,RiprapDesignDownstreamof
StraightDropSpillways(Reference15).
DesignformulascalculateaminimumW50rocksizeasafunctionofcriticaldepth,dropheight,tailwater
depth,andabutmenttype. Becausethetailwaterdepthdownstreamofthestructureisexpectedtobe
variableforthedesigneventasthecouleeerodes,thecriticaldepth,dropheight,andtailwater
combinationyieldingthelargestminimumW50sizewasusedforrockdesign. DesignbasedontheASAE
guidancewasconductedusingthespreadsheetRiprapDesign_StraightDropSpillways.xlsx.
BasedonacalculatedminimumW50of61lb,Gradation3riprapwasselectedforscourprotection
immediatelydownstreamofthestillingbasinendsill.
RiprapDesignDownstreamofStraightDropSpillwaysrecommendsriprapprotectionofappropriate
sizebecontinuedaminimumdistanceof5dc(roundedabutments)to8dc(squareabutments)
downstreamoftheendsill. Thiscorrespondstoadistanceof16.5ftto26.5ftdownstreamoftheend
7/29/2019 Design Documentation Report
35/317
Tolna Coulee: H&H Appendix Page 16
sill. Hightailwaterelevationscancausescour[to]occurinthedownstreamchannelifthebedmaterial
iseasilyerodible,indicatingprovidedriprapprotectionshouldexceedminimumrequirements.
EM111021602(Reference14)recommendsthatriprapextenddownstreamforadistanceof10d2fromtheupstreamendofthestillingbasin. TailwaterDepth(d2)fortheTolnaCouleestructureis
assumedtobevariablefrom~5feetto~17.2feetforthedesigneventasTolnaCouleeerodes. Design
basedon
d2suggestsappropriatelysizedriprapprotectionbeplaced50172feetdownstreamofthe
startofthestillingbasin.
RiprapprotectionfortheTolnaCouleestructureisprovidedforatotalof100feetdownstreamofthe
stillingbasinexit. RiprapGradation3willbeplacedfor50feetdownstreamoftheendsillandaround
thewingwallstoresistlocalscour.
Gradation1riprapwillbeplacedfor50feetdownstreamofthelargerGradation3riprap. Transition
fromlargerocktoasmallerrockpriortotransitioningtothenaturalstreambedreduceslocallyhigh
boundaryturbulencethatwouldresultfromimmediatetransitionfromlargerocktothenaturalchannel
(Reference13). The50feetofsmallerrockalsoprovidesadditionalprotectionfromunderminingshould
downstreamerosion
progress
to
the
riprap
blanket.
Additional
rock
at
the
downstream
riprap
end
protectionsectionallowsforthesloughingofrockintoareasinneedofunderminingprotection.
Topelevationofthedownstreamriprapblanketwillbeat1444.6ft. Thiselevationislowerthanthetop
oftheendsillelevationof1446fttohelppreventbackrollersfrompullingrockintothebasinwhichcan
causeconcreteabrasiondamage. ThisisrecommendedinaccordancewithguidanceprovidedinEM
111021602(Reference14).
OperatingPlan
AfinaloperatingplanistobeprovidedbytheNorthDakotaStateWaterCommission(NDSWC)and
reviewedtoensurecompliancewithapplicableguidelinesandregulations. Generaloperatingplanrules
havebeendevelopedbytheNDSWCtoserveassummaryguidelinesforthefinaloperationplan.
1) Undernocircumstanceswillanystoplogsbeplacedaboveanelevationof1459.2feet.
2) Initiallythestoplogswillbeplacedapproximately1footbelowthewatersurface.
3) Asthewaterlevelincreasesstoplogswillbeaddedtomaintaintheapproximate1footlevelbelow
thewatersurfaceelevationuntilthetopofthestoplogsareatanelevationof1457.2feet.
4) Thetopofthestoplogswillremainat1457.2feetuntilwaterbeginstoflowoverthedivideatwhich
timethestoplogsinbays5through8willbeplacedtoelevation1458.2ftandbays14and912will
beplaceduptoelevation1459.2feet.
5) PriortoerosionofthedividebetweenStumpLakeandTolnaCoulee,thestoplogswillremainin
placeasdescribedin1.4,withtheintentthattheexistingtopography,notthecontrolstructurewill
controlthe
discharge.
6) Ifandwhenerosionoccurs,stoplogswillberemovedtotheerodedhighpointelevationwiththe
maximumlakedischargelimitedto3,000cfs.
7) Stoplogswillberemovedtothenewelevationthatexistsaftererosionhasoccurred. Thiswillbe
conductedinamannernottoexceedadischargeof3,000cfs.
8) Onatleastamonthlybasis,thesitewillbevisitedtoobserveactualconditionsandverifythat
projectisbeingoperatedwithintheparametersofthisOperatingPlan.
7/29/2019 Design Documentation Report
36/317
Tolna Coulee: H&H Appendix Page 17
References
1. BarrEngineering,TolnaCouleeOutletErosion,PreparedfortheU.S.ArmyCorpsofEngineers;2001.
2. Donnelly&Blaisdell.TechnicalPaperNo.15,SeriesB.StraightDropSpillwayStillingBasin. St.
Anthony
Falls
Hydraulic
Laboratory,
University
of
Minnesota;
1954
3. HydraulicDesignCriteria623to624.1. SubcriticalOpenChannelFlowDropStructures,Hydraulic
DesignChart623CITTypeStructure;January1968
4. NRCSStreamRestorationHandbook.TechnicalSupplement14G,GradeStabilizationTechniques,NRCS.
August2007.
5. DevilsLakeFloodRiskManagementProject.DesignCriteriaandProjectConsiderationsReport,U.S.
ArmyCorpsofEngineers;21December2009
6. Baker,D.G.ClimateofMinnesota:Part14,WindClimatologyandWindPower,TechnicalBulletinADTB
1955,AgriculturalExperimentStation,UniversityofMinnesota;1983.
7. MemorandumforRecordWaveRunuponDevilsLake,U.S.ArmyCorpsofEngineers,St.PaulDistrict;
July
2006.
8. ShoreProtectionManual,WaterwaysExperimentStation,U.S.ArmyCorpsofEngineers,Coastal
EngineeringResearchCenter;1984.
9. ER111082(FR),InflowDesignFloodsForDamsandReservoirs,U.S.ArmyCorpsofEngineers,
WashingtonDC;1March1991.
10. EM111021100,CoastalEngineeringManual,U.S.ArmyCorpsofEngineers,WashingtonDC;1August
2008.
11. EM111021614,DesignofCoastalRevetments,Seawalls,andBulkheads,U.S.ArmyCorpsof
Engineers,WashingtonDC;30June1995.
12. SpiritLake(DevilsLake)NorthDakotaPhase2EvaluationofExistingRoads,U.S.ArmyCorpsof
Engineers,
2005.
13. EM111021601,EngineeringandDesignHydraulicDesignofFloodControlChannels,U.S.Army
CorpsofEngineers,WashingtonDC;30June1994.
14. EM111021602,EngineeringandDesignHydraulicDesignofReservoirOutletWorks,U.S.Army
CorpsofEngineers,WashingtonDC;15October1980
15. Rice,C.E.andKadavy,K.C.,RiprapDesignDownstreamofStraightDropSpillways,AmericanSocietyof
AgriculturalandBiologicalEngineers,JulyAugust1991.
16.MPCATechnicalCriteria,RiprapCriteriaforStabilizationPonds,MinnesotaPollutionControlAgency,
May1991
17.Donnelly&Blaisdell. SCSTechnicalPaper106. HydraulicDesignoftheBoxInletDropSpillway. Soil
ConservationService
Research,
Washington
25,
DC;
July
1951
7/29/2019 Design Documentation Report
37/317
Tolna Coulee: H&H Appendix Page 18
AccessRoadDitches InteriorFloodControlAnalysis
TheproposedTolnaCouleeaccessroadalignmentandthetwodelineatedsubwatershedsareshownin
Figure13onthefollowingpage.Thedrainageareasforthewestandeastsubbasinsweremeasured
usingtheArcMapGISprogramandweredeterminedtobe6.5and3.9acres,respectively.
AHEC
HMS
model
was
set
up
to
calculate
the
1percent
event
hydrographs
for
the
two
sub
basins.
The
modelparametersareshowninTable14. Curvenumbersweredeterminedusingavailablelanduseand
soilsmapping.SoilsinthewestsubbasinaremostlyfromHydrologicSoilGroupB,withverysmallareas
ofHSGAandC/D. TheeastsubbasinismostlyHSGB,withasmallareaofHSGAatthesouthend. The
calculatedcurvenumbersare59inthewestsubbasinand58intheeastsubbasin.
TimeofconcentrationwasdeterminedbasedonmethodspresentedinTR55(Reference18). Lagtime
wasassumedtobesixtypercentofthecalculatedtimeofconcentration. Noimperviousareawas
assumedineithersubbasin.
Table14
HECHMSModelParameters
SubArea CurveNumber TimeofConcentration(min) LagTime(min)
West 59 45 27
East 58 34 20
Theprecipitationeventusedintheanalyseswasthe100year,10daystorm. Thisisthesameevent
usedinpumpstationmodelingfortheCityofDevilsLakeEmbankmentsproject. Theaccessroadditch
subbasinsarerelativelysmallanddonothavedefineddrainagepatterns,sobaseflowwasnot
considered. TheHECHMSmodelpeakdischargesforthewestandeastsubareaswere8.3and6.5cfs,
respectively. Aculvertcrossesundertheaccessroad,carryingflowfromtheeastditchtothewest
ditch.Downstream
of
the
culvert
outlet,
the
peak
discharge
is
14.2
cfs.
This
is
slightly
less
than
the
sum
ofthepeaksforthewestandeastsubbasinsbecauseofthedifferentlagtimesbeingused.
AHECRASmodelwasdevelopedforthedrainageditchesoneithersideoftheaccessroadbasedonthe
crosssectionsincludedintheTolnaCouleeconstructionplans.Theditcheseachhaveabottomwidthof
fivefeetand3H:1Vsideslopes. Thewestditchhasanaverageslopeofapproximately4.3percent. The
eastditchhasanaverageslopeofapproximately4.6percent.Theculvertcrossingundertheaccessroad
thatcarriesflowfromtheeastditchtothewestditchwasmodeledasa55footlong,24inchdiameter
corrugatedmetalpipe(CMP)projectingfromfill(i.e.noheadwall).
Forthedesignstorm,themaximumflowvelocityintheeastditchis3.1feetpersecond(fps). The
maximumvelocityinthewestditchupstreamoftheculvertis3.4fps. Maximumvelocityinthewest
ditchdownstreamoftheculvertis3.7fps. Forslopeslessthan5%,thegeneralruleisthatthemaximumpermissiblevelocityinagrassedditchisbetween4fps(foreasilyerodedsoils)and5fps(erosion
resistantsoils). Basedonthemodelvelocities,theditchesdonotrequireriprapifgrasscanbewell
established.
Theculvert,asmodeled,isappropriatelysized. Maximumoutletvelocityforthedesignstormis4.5fps.
Gradation1riprapshouldbeplacedattheupstreamanddownstreamendsoftheculverttoprevent
erosionandscourfromoccurringduringhighflowevents.
7/29/2019 Design Documentation Report
38/317Figure 13: Tolna Coulee Access Road Drainage
Legend
East ditch drainage area
West ditch drainage area
Access Road 0 100 200 300 400 500Fee
7/29/2019 Design Documentation Report
39/317
Tolna Coulee: H&H Appendix Page 20
References18.UrbanHydrologyforSmallWatersheds,U.S.DepartmentofAgriculture,SoilConservationService,
TechnicalRelease55(TR55),June1986.
19.Soil
Survey
Staff,
Natural
Resources
Conservation
Service,
United
States
Department
of
Agriculture.
WebSoilSurvey.Availableonlineathttp://websoilsurvey.nrcs.usda.gov/accessedJune30,2011.
7/29/2019 Design Documentation Report
40/317
Appendix D
Geotechnical Appendix
7/29/2019 Design Documentation Report
41/317
Design Documentation Report Tolna Coulee Advance Measures D-i
100% Final Document Geotechnical Design and Geology
Tolna Coulee Advance Measures
Nelson County, North Dakota
Appendix D
Geotechnical Design and Geology
Table of ContentsD.1 INTRODUCTION ................................................................................................ D-1D.2 REGIONAL GEOLOGY ...................................................................................... D-1
D.2.1 Physiography and Topography ........................................................................... D-1
D.2.2 General Geology ................................................................................................. D-1
D.2.3 Structure.............................................................................................................. D-2
D.2.4 Site Hydrogeology .............................................................................................. D-2
D.2.5 Seismic Risk and Earthquake History ................................................................ D-2D.3 SUBSURFACE INVESTIGATION ..................................................................... D-3
D.3.1 Site Specific Geology ......................................................................................... D-3D.3.2 Laboratory Testing ............................................................................................. D-4D.3.3 Selection of Design Parameters .......................................................................... D-4
D.4 GEOTECHNICAL DESIGN ................................................................................ D-6
D.4.1 Introduction ........................................................................................................ D-6
D.4.2 Horizontal and Vertical Datums ......................................................................... D-6
D.4.3 Design Methodology .......................................................................................... D-7
D.4.4 Cofferdam ........................................................................................................... D-7
D.4.5 Dewatering and Groundwater Control ............................................................. D-10D.4.6 Temporary Excavation Slopes .......................................................................... D-11
D.4.7 Stoplog Structure and Retaining Walls ............................................................ D-12
D.4.8 I-Wall/Embankment Composite System .......................................................... D-14D.5 PHASE I ENVIRONMENTAL SITE ASSESSMENT ...................................... D-22
D.6 SLOPE PROTECTION ...................................................................................... D-22
D.7 SOURCES OF CONSTRUCTION MATERIALS ............................................. D-23D.7.1 Impervious Fill ................................................................................................. D-23
D.7.2 Geotextile Fabric .............................................................................................. D-23
D.7.3 Stoplog Structure Subdrainage Material........................................................... D-24
D.7.4 Concrete Aggregate, Riprap, and Bedding ....................................................... D-25
D.8 INSTRUMENTATION ...................................................................................... D-25
D.8.1 Construction Monitoring .................................................................................. D-26
D.8.2 Long-Term Performance Monitoring ............................................................... D-26D.9
REVIEWS ........................................................................................................... D-27
D.9.1 District Quality Control .................................................................................... D-27
D.9.2 Agency Technical Review ................................................................................ D-27D.9.3 Independent External Peer Review ................................................................... D-27
REFERENCES ................................................................................................................... D-28
7/29/2019 Design Documentation Report
42/317
Design Documentation Report Tolna Coulee Advance Measures D-ii
100% Final Document Geotechnical Design and Geology
Index of TablesTable D- 1: Summary of Tolna Coulee Soil Parameters ...................................................... D-5
Table D- 2: Horizontal and Vertical Datums ........................................................................ D-6Table D- 3: Cofferdam Required Factor of Safety ............................................................... D-7
Table D- 4: National Weather Service Devils Lake peak forecast levels for 2011. ............. D-8
Table D- 5: Cofferdam Seepage and Stability Results ......................................................... D-9Table D- 6: Temporary Excavation Required Factor of Safety .......................................... D-11
Table D- 7: Temporary Excavation Stability Results ......................................................... D-12
Table D- 8: Stoplog Structure Uplift/Seepage Load Cases ................................................ D-13
Table D- 9: Retaining Wall Monolith 1 Stability Analysis ................................................ D-14Table D- 10: Configuration of I-Wall//Embankment Composite System .......................... D-15
Table D- 11: Seepage Loading Conditions and Minimum Factors of Safety ..................... D-17
Table D- 12: Global Stability Loading Conditions and Minimum Factors of Safety ......... D-19Table D- 13: Factor of Safety against Piping ...................................................................... D-20
Table D- 14: Results of Global Stability Analysis.............................................................. D-21
Table D- 15: Riprap Gradation ........................................................................................... D-22
Table D- 16: Bedding Gradations ....................................................................................... D-23Table D- 17: Impervious Fill Requirements ....................................................................... D-23
Table D- 18: Geotextile Fabric Requirements .................................................................... D-24
Table D- 19: Sand Gradation Requirements ....................................................................... D-24Table D- 20: Pervious Material Gradation Requirement