23
Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

Embed Size (px)

Citation preview

Page 1: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

Design Basis Scoping Paper

Adli S. Khalaf

Facilities Planning Department

Saudi Aramco

Page 2: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 2

Outline

Introduction

Definition

Purpose

Involved Organizations

DBSP Content

Examples

Development Process

Conclusions

Questions

Page 3: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 3

Six Phases of a Project

1. Enthusiasm

2. Disillusionment

3. Panic

4. Search for the Guilty

5. Punishment of the Innocent

6. Praise and Honor the Non-

Participants

Page 4: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 4

Elements of Project Success

Understand Business Objectives

Strategy for Project Goals

Risk and Uncertainty

OBJECTIVES

The

Project

TEAM PROCESS

Customer Focus

Project Team

Contractor

Pre-Project Planning

Project Execution Plan

Controlling Cost/Schedule

Page 5: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 5

Definition

DBSP is a contract between the

signatories to further develop the

proposed project in a manner that

will ensure that the project’s stated

Business Objective is achieved in a

cost effective manner.

Page 6: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 6

PurposeThe purpose of the DBSP is to:

Define the main elements of the project scope

of work (What will be built)

Define the limits of the project scope of work

Provide the design contractor definitive

information to independently develop the

project scope

Provide the Construction Agency the

information to effectively plan and execute the

project

Provide a cost estimate (+/-40%) for budgeting

purposes

Page 7: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 7

Involved Organizations

Planning Organization

Proponent or End User

Construction Agency

Environmental Protection

Organization

Estimating

Page 8: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 8

Planning OrganizationLeads the DBSP preparation effort

Clarifies the definition of the project’s Business

Case

Insures adequate justification for scope

elements

Describes in broad terms the facilities to be

provided

Controls scope

Describes specific studies to be preformed

during Preliminary Design

Issues DBSP for review and approval

Page 9: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 9

Proponent

Provides supporting information

Reviews scope elements

Provides support to establish

interface points

Signs DBSP for endorsing project

scope

Page 10: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 10

Construction Agency

Reviews schedule

Reviews scope elements

Reviews constructability

Reviews study requirements

Signs DBSP for schedule considerations

Page 11: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 11

Environmental Protection

Organization

Reviews project’s environmental

implications

Signs DBSP for environmental

considerations

Page 12: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 12

Estimating

Prepares budgetary cost estimate

Estimate Accuracy is +/- 40%

Page 13: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 13

DBSP Content

Purpose of Facilities

Present Situation

Location Analysis

Interfaces

Design Objectives

General Project Design Basis

Page 14: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 14

DBSP Content (cont’d)

Description of Proposed Facilities

–Type of facility

–Corresponding technical design basis

–Specific facility attributes

Page 15: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 15

DBSP Content (cont’d)

Scope Evaluation to Date

Additional Study Requirements during

Preliminary Design

Constructability and Logistical Assessment

As-Built Drawing Assessment

Value Engineering Study

Project Schedule

Appendices

Page 16: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 16

What to Include in DBSP

What’s IN?Preliminary description of facility to be provided

Evaluation of existing conditions

Results of previous studies

Scope of Work of Project organized by discipline

Limits of scope of work for the Design Engineer

Design bases

Utility sources and interface points

Conceptual layout of equipment

Schematics and Process Flow Diagrams

List of major equipment

Page 17: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 17

What NOT to include in the DBSP

What’s OUT? Exact size of equipment

Type of valves, flow meters, levels, etc.

Name of manufacturer

Final layout, Sections, P&ID, etc.

Detailed design calculations

Detailed specifications

Project cost

Page 18: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 18

Example 1

Building- Location

- Site conditions

- Type of construction

- Built-up Area

- Number of persons

- Sizing criteria

- Preliminary layout

- Utility requirements

Page 19: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 19

Example 2

Sewage Treatment Plant

- Location

- Capacity

- Level of Treatment

- Treatment Process

- Treatment Facilities

- Design Criteria

- Electrical and Instrumentation

- Process Flow Diagram

- Conceptual Layout

Page 20: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 20

Example 3

Water Supply Network- Location

- Number of persons

- Water requirement

- Piping material

- Preliminary pipe sizing

- Preliminary layout

- Pumping and storage facilities

Page 21: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 21

Development Process

Issue Initial

Draft DBSP

Conduct Value

Engineering Study

(if required)

Issue Draft DBSP for

Review

Incorporate

DBSP

Comments

Complete

DBSP

Seek Approval

Of DBSP

Obtain Capital Budget

Cost Estimate

Design Basis Agreement

on Optimized Scope

Prepare DBSP Execution

Plan

Develop

Project

Scope

Assess Synergies of

Combining Projects

YES

NO

Initiate DBSP/

Assign Team Members

YES

Modify Project Scope or

Recommend Cancellation

NO

Business

Case Still

Valid

Modify Project Scope or

Recommend Cancellation

Approve

Business

Case/Stud

y

Page 22: Design Basis Scoping Paper - SAWEA 3/Adli Khalaf - Design Basis Scoping... · Design Basis Scoping Paper Adli S. Khalaf Facilities Planning Department Saudi Aramco

December 3, 2007 SAWEA WORKSHOP - 2007 22

ConclusionsDBSP is a critical document in every project

cycle

DBSP requires proper and timely input from

involved organizations

A GOOD DBSP will put the project on track

(scope, cost and schedule), and prevent future

issues and conflicts

A POOR DBSP will hinder the project design

and execution phases, and negatively impact

the project cost and schedule