13
Design and Implementation of Forced Draft Cooling Towers for Loviisa NPP Antti Teräsvirta / 03.11.2016

Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Design and Implementationof Forced Draft CoolingTowers for Loviisa NPPAntti Teräsvirta / 03.11.2016

Page 2: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Preface

Nuclear power plants must be able to remove the residual heat from the nuclear fuelafter the plant trip when the turbine island no longer consumes the generated steam,and on the long term when the plant is in the shutdown states.The spent fuel stored in the plant area must be cooled at all times.

• Loviisa NPP safety systems rely on seawater cooling• Seawater cooling systems can be vulnerable to freezing, fouling or other external

pollutants (e.g. oil)• Project to implement the cooling towers to power plant as an additional ultimate

heat sink was approved in 2012

2

Page 3: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Design

• Wide range of cooling requirements

3

Heat loads

Ambient conditions

Flow rates

Page 4: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Design

• Other requirements/basis:– Simplicity– Personal safety– Cost effectiveness– Ease of use– Weather protection, protection against extreme weather conditions

4

Page 5: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Design

• Two cooling towers for each plant unit• One tower is used for removing decay heat from the reactor, the other for

removing decay heat from the spent fuel pools as well as for cooling off otherequipment critical for safety.

• The cooling towers are connected to existing systems of Loviisa NPP. One coolingtower is connected in reserve residual heat removal system RR and the othercooling tower is connected to intermediate component cooling system TF in eachunit.

5

Page 6: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Design

6

Page 7: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Design

7

Page 8: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Implementation

8

Page 9: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Implementation

9

Design: GEA EGI Contracting/Engineering Co. Ltd

Page 10: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Implementation

10

Page 11: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Implementation

11

• Challenges:– Heavy lifts in difficult circumstances– Capasity testing– Avoidance of corrosion and contamination

• Good practices– Lisencing documentation– Preassembly and pretesting (FAT)– Flushing and drying of the towers

• Accomplisments:– Classification EYT/STUK– Good feedback from operation personnel– Validation of cooling tower dynamic model

Page 12: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Conclusion

• The project to implement the cooling towers to power plant was approved in 2012.The erection works were finished in February 2015, and tower was taken intooperation during year 2015

• With the cooling tower, the plant ultimate heat sink can be assured in mostextreme conditions.

• By implementing the cooling towers, the total plant core melt risk is reduced by16% for all operating stages in both units.

12

Page 13: Design and Implementation of Forced Draft Cooling Towers ... · • Two cooling towers for each plant unit • One tower is used for removing decay heat from the reactor, the other

Thank You!

13