Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Design and Fabrication of the 1.9 K Magnet Test Facility at BNL, and Test of the First 4m Long MQXF Coil J. Muratore, M. Anerella, P. Joshi, P. Kovach, A. Marone, P. Wanderer
The future high luminosity upgrade of the Large Hadron Collider (LHC) at CERN will include twenty 4.2 m long Nb3Sn high gradient quadrupole magnets which will be components of the triplets for two LHC insertion regions. In order to test these and four pre-production models, the vertical superconducting magnet test facility of the Superconducting Magnet Division (SMD) at Brookhaven National Laboratory (BNL) has been upgraded to perform testing in superfluid He at 1.9 K and 1 bar, which is the operational condition at the LHC. This has involved extensive modifications of the 40-year old, 4.5 K cryogenics plant at SMD. These upgrades include new piping, compressors, and other critical components, a new vertical test cryostat with top plate and hanging fixture which can accept larger diameter and longer magnets, up to actual length 5 m long, a 1.9 K heat exchanger, newly designed warm bore tube, and a lambda plate designed with a novel seal configuration for both strength and minimum heat loss. In addition, the former short sample cable test facility 30 kA power supply has been upgraded with an energy extraction system using IGBT switches and fast shutoff capability, and a new high energy dump resistor, and reconfigured to supply 24 kA to test high field Nb3Sn magnets.
We have also assembled completely new data acquisition, signal analysis, and control software and hardware, allowing for high precision and large volume data collection. This paper describes the design, assembly, and commissioning of the upgraded test facility and the first magnet test performed, on a mirror model, which consists of a single coil quadrant and an iron yoke filling the other three quadrants and is designed to have peak fields close to that of the production quadrupoles. The mirror coil was the first long coil of the MQXF design to be tested.
Mon-Af-Po1
MQXFA TEST PARAMETERS
Vertical Test
Dewars 2-6
HORIZONTAL TEST STAND A
HORIZONTAL TEST STAND B
HORIZONTAL TEST STAND C
HORIZONTAL TEST STAND D
HORIZONTAL TEST STAND E
CONTROL ROOM
MQXF
30 kA Power
Supply
2.7 m Deep Test Dewars 6.1 m Magnet Deep Test Dewars
CTI 4000 He
Refrigerator
CVI Air Liquide
He Refrigerator
Nash “high
capacity” vacuum
Pump (1.9K)
SMD TEST FACILITY FLOOR PLAN Mycom 800 hp
Compressor
(2 Stages)
160 g/s
Sullair 500 hp
Compressor
(Single Stage)
80 g/s
Sullair 350 hp
Compressor
(Single Stage)
51 g/s
Buffer
Tank
Reciprocating
Helium Expander
CTI Model 4000
1500 W
Refrigerator/
Liquifier
CVI – Magcool
Precooler/Subcooler
(Cold Box)
Turbo-Expander
Helium
Liquifier
CVI/Air Liquide
1000 W
Helium Wet Expander
Koch Model 1600
Cryenco
Inline Purifier
Cryenco
10000 Liter
Storage Dewar
High Pressure
Helium Gas
High Pressure
Helium Gas
@ 8K
Liquid
Helium
Liquid
Helium
Warm Return
1.8 K Test Dewar 2
Cryenco
3785 Liter
Storage
Dewar
Gardner
3785 Liter
Storage
Dewar
Dual
Turbines
High Pressure
Helium Gas
Lambda
plate
Warm Return
Buffer Tank
to Suction CS4
Sullair 100 hp
CS4
1.8 K Test Cryostat
2-Stage CVI/Magcool Purifier A & B
Liquid Helium
Storage Dewar
10000 L
High Pressure Helium
Gas Storage
8.5 x 106 L @ 15.5 bar
Nash 1.8 K Vacuum
Station
As proposed: Using existing infrastructure for the new 1.8 K Testing Facility
Buffer Tank
to Helium Gas
Storage
Warm Helium Return
4.5 K Helium Input
1.8 K
4.5 K
16 mbar1 bar
SMD MAIN CRYOGENICS FACILITY 1.9 K PROCESS FLOW DIAGRAM
Magnet &
Cryostat
24 KA Cable (60 ft)
CLIQ Circuit
CERN Built
REE1,
Energy
Extraction
Resistor
REE2,
Energy
Extraction
Resistor
S2, 6 IGBT
Switches In
Parallel
S1, 6 IGBT
Switches In
Parallel
DCCT
DCCT
30 VDC
15KA
Power
Supply
30 VDC
15KA
Power
Supply
BNL Built Control For
CLIQ Circuit
High Voltage Power
Supply Control
BNL Built Quench
Detector
IGBT Control Power Supply Control
Filter
Filter
Main PS
Tc
Main PS
Vo
CLIQ Switch
Control
C
P. Joshi. BNL July 18 2017
Current
Sensor
D2
24 KA Cable (60 ft)
D2
D3
D3
1000 Amp Shunt
15 KA Cable (85 ft)
L1
L2
L3
L4
20 DIODES
15 kA / 14 V
Power Supply
6 Pulse SCR
Bridge3 Phase
480 V
X 6
15 kA DCCT100 µH
15.5 mF
85 mΩ
62.0 mF
15 kA water-cooled cable
24 kA water cooled cable
15 kA water-cooled cable
15 kA / 14 V
Power Supply
6 Pulse SCR
Bridge3 Phase
480 V
X 6
15 kA DCCT100 µH
16.0 mF
85 mΩ
81.9 mF
33 mΩ
15 kA water-cooled cable
33 mΩ
15 kA water-cooled cable
IGBT (6 parallel units) Switch
with snubber circuits
IGBT (6 parallel units) Switch
with snubber circuits
24 kA water cooled cable
24 kA Vapor-Cooled Leads
1.9 K
4.5 K
800 mF
800 mF
1 Ω
33 mΩ 33 mΩ
1 Ω
30 kA POWER SUPPLY SYSTEM WITH ENERGY EXTRACTION 30 kA POWER SUPPLY SYSTEM WITH CLIQ
QUENCH DETECTION The MQXFA quench detection system is based on a redundant scheme which relies on a number of voltage signals. When any one of the following signals reaches its specified threshold voltage after a specified validation time, a fast discharge is instigated (current decays through dump resistor). Typical threshold voltages and validation times are listed here.
1) Half coil voltage Vhalf1 - Vhalf2 50-250 mV 2-5 ms
2) Quarter coil voltage V1 – V2 50-250 mV 2-5 ms
3) Quarter coil voltage V3 – V4 50-250 mV 2-5 ms
4) Total coil voltage Vtotal 50-250 mV 2-5 ms
5) SC lead voltages VSCL+ and VSCL- 10-50 mV 2-5 ms
6) Splice voltages V12, V34, V24 8-10 mV 2-5 ms
7) Current Derivative Vtotal – L dI/dt 0.1-1.0 V 5-10 ms
Note: The above thresholds are for currents higher than 6 kA. In Nb3Sn magnets, current-dependent thresholds as high as several volts at low currents are necessary and are set in the software. This is to avoid false QD trips due to flux jump spikes.
There are also designed into the system a number of interlocks which also rely on various signals which, if they do not meet specified conditions such as voltage threshold or on-off state, will instigate a slow discharge, with the dump resistor out of the circuit. These include:
1) Vapor-cooled lead voltages 80-100 mV 500-1000 ms
2) Strip heater capacitor bank not charged
3) IGBT switch temperature or voltage too high
4) Others
• (2) 24 kA main coil vapor-cooled leads
• (2) 1 kA CLIQ vapor-cooled leads
• (3) instrumentation wiring trees
• (2) helium fill lines
• Heat exchanger port, 3rd CLIQ lead port
• Manifolds and solenoid valves under plate
• Warm bore tube port
• Helium vent port
1.9 K MQXFA TOP PLATE DETAILS
New Top Plate
Lambda Plate
Redesigned Inner
He Vessel
Existing Outer
Dewar
MQXF Magnet
4.5 K Heat Shield
Top is 38.1 mm thick G10 (lower heat
load)
Bottom is 19.05 mm thick 304
stainless steel (for added strength
and sealing to He vessel interior
flange)
Bonded together with Stycast
2850FT
Total heat load < 1.4 W
New top plate to accommodate
lambda plate and fixturing for
MQXF 4.2 m quads and 24 kA
vapor-cooled leads and heat
exchanger for 1.9 K, 1 bar
operation.
Rated at 5.86 bar
Components below lambda plate
and internal to heat exchanger are
designed for 5.86 bar,
above lambda plate for 3.45 bar.
NEW RE-DESIGNED TEST CRYOSTAT FOR 1.9 K AND 24 kA
Heat
exchanger
CLIQ LeadsConnector Trees
Quench Heater Connector Tree
24 kA vapor-cooled leads
Top plate 76.2 mm
thick 304 SS
He fill lines
3rd CLIQ Lead
(if needed)
NEW 1.9 K LAMBDA PLATE DESIGN
FAST DATA LOGGER DAQ National Instruments PXIe-4300 (16 Units)
Number of channels = 8 differential, simultaneous sampling
Analog input = ±10 V, ±5 V, ±2 V, ±1 V
ADC resolution = 16 bit
Sampling rate = 250 kHz max per channel
Time scale resolution = 10 ns
TOTAL CHANNELS = 128 differential, simultaneous sampling
Usage = fixed (main) voltage taps and configurable (auxiliary)
voltage taps
Status: Assembled and Tested
SLOW DATA LOGGER DAQ National Instruments PXI-6289 (4 Units)
Number of channels = 16 differential
Analog input = ±10 V, ±5 V, ±2 V, ±1 V, ±0.5 V, ±0.2 V, ±0.1 V
ADC resolution = 18 bit
Sampling rate = 500 kHz max multichannel (31.25 kHz max)
Time scale resolution = 50 ns
TOTAL CHANNELS = 64 differential
Usage = monitoring of vapor-cooled lead voltages, splice
voltages, SC lead voltages, temperatures, LHe levels, and
other instrumentation
Status: Assembled and Tested
64 Channel
Slow Logger
128 Channel Fast Logger
FASTER HIGHER PRECISION DATA ACQUISITION SYSTEMS
TEST FACILITY COMMISSIONING MQXFPM1 MIRROR MAGNET
FIRST LONG MQXF COIL
10000
11000
12000
13000
14000
15000
16000
17000
18000
19000
20000
21000
22000
23000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
QU
ENC
H C
UR
REN
T (A
)
QUENCH NUMBER
MQXFPM1 TRAINING QUENCHES
A3-A4 Pole Multiturn (at 3.25-4.3K)
A5-A6 Pole Turn Long Straight Section
A6-A7 Pole Turn NonLead End Section
A7-A8 Pole Turn Short Straight Section
A8-B8 Ramp
B3-B2 MIDPLANE MULTITURN
THERMAL CYCLES
NO QUENCH - 50A/s to 10kA then 20A/s
NO QUENCH - 50A/s
NO QUENCH- 20 A/s
Quenches 1-12 and 14-17 were at 20A/s.Quench 3 was in A6-A7 but close to or at tap A7.Quench 13 was at 20A/s with 2hr hold at 17890A.
NO QUENCH
4.424K
NO QUENCH
SS 22095A
ULT 17890A
NOM 16480A
300 A/s 3.265 - 4.424K
144K (TOP) - 110K (BOT)
117K (TOP) - 77K (BOT)
Lambda plate sealing detail
Lo
wer
He
ves
sel
Oute
r 4
K h
eat
shie
ld
He
ves
sel
flan
ge
G-10/SST Lambda plate
Lambda Plate Spring-Energized Face Seal to He Vessel
Eight 600 V 12.4 mF Units
Four 900 V 13.05 mF Units
QUENCH PROTECTION HEATER FIRING UNITS FOR 12 INDEPENDENT CIRCUITS
CLIQ (Coupling Loss-Induced Quench) is a system which provides quench protection, along with quench heaters and energy extraction.
CONCLUSION As can be seen by the quench training results for the MQXFPM1 magnet, the upgraded facility as described here successfully fulfilled the acceptance test requirements for the MQXFA quadrupole magnets which are being built and supplied to the LHC for the insertion region Q1/Q3 of the high luminosity upgrade. These requirements include operation at 1.9 K at 1 bar, powering up to 19 kA, and proper protection of the magnet during quench testing. For the test of the MQXFPM1, quench protection included a newly designed and faster quench detection system, energy extraction with faster and state-of the-art electronic switching using specially designed IGBT circuitry and infrastructure. Future magnets will be using the already upgraded energy extraction system with a higher power and more versatile dump resistors, and twelve new quench protection heater firing units, which meet the requirements for quench protection heater systems in the LHC.
Coil inner aperture D = 150 mm
Coil magnetic length l = 4.2 m
Coil actual length l = 4.523 m
Yoke length l = 4.5629 m
Total length with end plates l = 5 m (nom)
Operational temperature T = 1.9 K
LHC nominal operating current (1.9 K) Inom = 16.470 kA
LHC ultimate operating current (1.9 K) Iult = 17.890 kA
Maximum current (300 K) I300 = 10 A
Conductor limit at 1.9 K Iss = 21.600 kA
Conductor limit at 4.5 K Iss = 19.550 kA
Peak field in the coil at Inom (1.9 K) Bnom = 11.4 T
Peak field in the coil at Iult (1.9 K) Bult = 12.3 T
Peak field in the coil at Iss (1.9 K) Bss = 14.5 T
Field Gradient at Inom (1.9 K) Gnom = 132.6 T/m
Field Gradient at Iult (1.9 K) Gult = 143.2 T/m
Field Gradient at Iss (1.9 K) Gss = 168.1 T/m
Magnet resistance at room temperature R = 2.37 Ω
Magnet inductance (20Hz at room temperature) LRT = 38.1 mH
Magnet inductance (at 1.9 and 1 kA) L1 = 40.9 mH
Magnet inductance (at 1.9 and Inom=16.5 kA) L16.5 = 32.8 mH
Operating stored energy (at Bnom, Inom) Emax = 4.5 MJ assuming L=32.8 mH
Maximum allowed temperature at quench Tmax = 350 K
Maximum allowed voltage across magnet Vmax = 1000 V (500 V to ground) with 50 mΩ EE
Dump resistor (energy extraction) options RD = 30, 37.5, 50, 75, 150 mΩ
Overall test fixture and hanging assembly (insert), shown with mirror magnet MQXFPM1.
Diagram courtesy of W. McKeon, Cryogenics Facility Diagram courtesy of W. McKeon, Cryogenics Facility