Upload
doanthu
View
216
Download
0
Embed Size (px)
Citation preview
2.0 dEscRiPTiot4 OF THE PROPOSED DEVELOPMENT
2.1 Site History, Context and Location
Site Historv
The lands in question were used for the production of cereal until 1978 when
planning permission (78/l 182) was granted to the Polaroid Corporation for film
making and camera manufacture, and in 1987 (87/65) to manufacture reflective
film for road signs. Permission was granted in 1989 for the change of use of
existing buildings (89/262).
Wyeth was granted planning permission in 1992 (910443) to produce and
package tablets.
On purchasing the site in 1991 Wyeth recognised that some existing structures
were generally suitable for the company’s immediate purposes but they were not
ideal in the long term. In this regard, WMI applied for permission in 1996
(Planning ref. no. 961374) to expand the facility to provide for a new warehouse
and to allow increased production of tablets and capsules. WMI applied for
permission in 1999 to extend the canteen (99/2193).
From 2000 to 2001 further developments occurred on site in the form of a new
main entrance sign (00/557), extension of Building 3 and bunded tank area
(01/1819), change of use for partial area of warehouse to production (01/791),
and retention of warehouse and car park extension (01/2263).
WMI is now considering a number of developments within the subject lands.
These developments are within varying stages of planning consent (from fully
granted to permissions, through to those still to be sought) and none has yet, as
of the date of submission of this document, been constructed on the site. These
are listed and fully described in Section 2.6 of this chapter.
Staffinu - EmrAovment 1 Workina Hours I Traffic Current operations within the WMI site involve the complete manufacturing and
packaging of a range of pharmaceutical products. The site operates 24 hours per
day, 7 days per week, with up to 1,100 employees and up to 150 contractors on
site between 8 am and 5 pm, with a much smaller number of employees being on
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:20
i. . , ._
‘y ‘, , ,
: I :/~’ . . :
.._ FLUOR.
employed at the facility. The site currently generates approximately 40 HGV
movements per day, 7 days per week. The majority of employees travel to work
by private car, with an average car occupancy of 1.6 employees per car.
Site Context
The WMI site at Newbridge is located within the townland of Little Connell
northeast of Newbridge town centre, adjacent to the R445 as shown on Figure
2.1. The current WMI landholding consists of 48.6 hectares, of which
approximately 22 hectares are attributed to the existing pharmaceutical
operations. The facility is currently accessed from the R 445 dual carriageway via
a roundabout and single access road.
The existing development within WMI is located principally within the north
western area of the WMI property with undeveloped space located in the
southern and eastern margins of the lands. These undeveloped lands are largely
Greenfield, comprised of agricultural and landscaped grasslands. The proposed
buildings relevant to this planning application and EIS are to be located adjacent
to the existing Building 3 as shown on Drawing No. 800235.02-DG-AR-PNF-AE-
003.
The WMI property is bounded to the north by the R 445, and to the west by a
county road (Greatconnell Road). Agricultural lands border the property to the
east and a Lidl distribution facility borders the property to the south. The
adjoining land uses include agriculture, the Oldconnell horse stud farm,
commercial and residential development. An area of residential development is
located across the road from the site, fronting onto Greatconnell Road.
2.2 The Applicant
As per the guidance of the formal scoping opinion from Kildare County Council
(Appendix 1.3), a full and detailed description concerning the applicant is
provided within the planning application documentation which accompanies this
EIS. However in order to place the proposed PNFX development in context, a
brief description of the principal activities are included within this section.
The WMI facility produces a variety of medical/pharmaceutical products, with the
principal products detailed in Table 2.1.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:20
FLUOR.
Medical Category Product Name
Hormone Replacement Premarin, Premarin MPA, Prempack C, Premelle and Premique
Oral Contraceptives Harmonet, Trinordiol, Nordette, Ovranette, Minesse, Minulet, Loette
I--~ Gastrointestinal I Zoton I
1 Central Nervous System 1 Efexor, Efexor XR, Sonata, Tavor
Table 2.1 Principal Products Manufactured at WMI
Operations within WMI are based on formulation activities, consisting of blending
of raw materials, granulation, drying and coating processes, with subsequent
filling and packaging operations and product distribution from the site. There are
associated on-site warehouse facilities to provide storage facilities for raw
materials and final product.
Current production facilities comprise six main buildings;
l Administration
l Packaging
9 Tablet Manufacture
l Warehouse
. Utility Building
l Shipping & Receipt (ASRS)
Additionally there are areas dedicated to solvent recovery, combined heat &
power (CHP) and cooling towers.
2.3 Proposed Development
The proposed PNFX development consists of a planning application for a three
storey extension to the existing 38 manufacturing facility within WMI lands,
including office accommodation, ancillary site building, structures and site
services. The buildings within this development comprise a total footprint area of
8,110 m2 within the 49.7 hectare site application area.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:20
,. FLUOR.
2.3.1 Constrkkion Phase Overview
The final details on how construction will be undertaken will be a decision for the
appointed contractor. It is therefore envisaged that there will be some flexibility in
the methods of construction to be used, subject at all times to compliance with the
planning permissions sought and all relevant statutory approvals. As part of the
contract requirements all construction contractors employed will be obliged to
implement high standards of housekeeping in order to minimise possible
environmental impacts. Environmental performance criteria or limits will form part
of contract documents. The likely construction methods are discussed below,
and the impacts of these construction methods are assessed in the relevant
sections of the EIS.
Site evaluation
An extensive programme of geotechnical site investigation works was undertaken
as part of the proposed PNFX site evaluation to obtain the information required to
produce appropriate foundations and sub-structures at individual building
development locations. The site investigation consisted of 10 trial pits and 13
boreholes, which were placed in the areas selected for the locations of the
proposed PNFX development and associated support buildings.
The site investigation works concluded that the site of the proposed PNFX
building and associated support buildings and structures is underlain by bands of
sand, gravel and clay, with some made ground, in the form of gravel, extending
along the north western boundary of the PNFX building. The ground was found
to be soft in places and it was recommended that excavation to approximately
3.2 m below ground level would be required, in order to expose a ground layer
suitable for construction of the foundation. It was also found that groundwater at
the site is subject to artesian pressure and may ingress to the excavation at
approximately the 3.2 m below ground level depth. A detailed discussion of the
site investigation is provided in Section 7.3 of Chapter 7 of this EIS.
It is proposed that a raft foundation structure be used to support the PNFX
building. This foundation will be suitable to safely support the loads imposed on
it.
Time of vear, duration and Dhasinq
The proposed construction programme will take approximately 18 ,months. The
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:20
.’ ‘i
. ; >’ . :
: . / , ,
FLUOR,
partial assembly off site, pre-cast slabs and specification of skid mounted
equipment, where possible, to maximise efficiency. The key construction
programme phases will be site preparation works, excavation, construction of
foundations, erection of structures, cladding of buildings, electrical and
mechanical fit out and commissioning, validation and start up.
1 Stage Timing I
Site Preparation I Months 1 -3 I
Main Civil Engineering Works Phase Months 2 - 8 I
Erection and Fabrication of Structures / Installation of
Equipment Months 4 - 12
Plant Commissioning & Testing Months 13 - 18 I
Table 2.2 Duration of Construction Works
Site Preaaration Works
Site preparation works will include topsoil stripping and storage, erection of
temporary hoarding and fencing where appropriate, creation of temporary
construction compounds and temporary site roads, welfare facilities, contractors
car park and laydown areas, and localised underground services diversion. This
element of work is expected to take approximately 3 months.
Emelovment
Employment levels will vary throughout the construction period depending upon
the operations being undertaken. It is estimated that some 850 construction
workers will be employed during the peak construction phase of the proposed
PNFX development.
Accommodation
Equipment and office housing facilities required during the construction phase will
be provided by the various contractors.
Requirements for local accommodation will depend on the level to which local
labour is employed. It is hoped that many of the construction workers will be
based in the local area. Workers will also most likely travel from Dublin and other
major centres of population, to the construction site.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:20
Typical construction hours are expected to be 7am to 6pm, Monday to Friday and
7am to 4pm on Saturday. However, it is likely that the contractor will wish to carry
out certain operations outside of these hours, from time to time i.e. during certain
stages of the construction programme some aspects of the work may extend to
late night and Sunday working. Such occurrences will be kept to a minimum and
take place over a short time-frame to avoid excessive disturbance as far as
possible.
Construction Techniaues
Construction techniques will include mechanical excavation, reinforced concrete
pad footings, structural steel braced frame, in situ concrete floor slabs, composite
cladding and block/brickwork and single ply roofing membrane, with insulation on
metal deck.
A comprehensive geotechnical site investigation has been carried out at the site
of the proposed PNFX development in order to obtain the information required to
produce appropriate foundations and sub-structures at individual building
development locations. The final foundation scheme to be adopted will be based
on the soil investigations and will be suitable to safely support the loads imposed
on it. The topsoil within the areas proposed for construction will be removed and
replaced with a layer of crushed stone to provide a working platform for
construction works. All pipework installation (for mains water supply, sewage
piping network) and associated excavations will be carried out using ‘best
engineering practices’.
The final details on how construction will be undertaken will be a decision for the
appointed contractor. As part of the contract requirements all construction
contractors employed will be obliged to implement high standards of
housekeeping in order to minimise possible environmental impacts.
The design and construction of the civil works will be to the standards applied in
the Irish construction industry. The work will be fit for the purpose intended and
comply with all requirements of a competent authority, Irish standards or Irish
standard codes of practices. Health and Safety procedures/protocols adopted in
the development will be carried out in accordance with all applicable National and
EU Regulations e.g. Safety Health and Welfare at Work (Construction)
Regulations 1995 (SI No. 138 of 1995).
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.6
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
_1 ,.‘- . ‘ . ; , .A .
FLUOR.
During construction it is planned that HGVs (material and equipment deliveries)
and cars (contractor personnel, developer personnel and visitors) will move to
and from the site via the proposed new signalised junction on the R445 and new
site access. The junction will be controlled by traffic lights, which will be phased
to ensure that the incidence of a queue developing on the R445 is minimised and
that the traffic related impacts of construction, are kept to a minimum. A full
description of this junction is provided in the Traffic Chapter of this EIS (chapter
12) which also addresses access for HGV traffic relating to the construction
phase which will only be permitted during certain hours.
Temporary car parking facilities will be provided within the site during the
construction phase. The temporary hard standing areas (car park and minor
access roads) will have an unbound hardcore surface.
Noise, Vibration and Dust
A range of noise control measures will be put in place to ensure the construction
related noise impacts are minimised. With regard to construction activities,
guidance is taken from BS5228: noise control on construction and open sites,
which offers detailed guidance on the control of noise and vibration from
demolition and construction activities. Various mitigation measures will be
considered and can be applied during the construction of the proposed PNFX
development, such as:
l Limiting the hours during which site activities likely to create high levels of
noise or vibration are permitted;
l Establishing channels of communication between the contractor/developer,
Local Authority and residents;
l Appointing a site representative responsible for matters relating to noise and
vibration;
l Monitoring levels of noise during critical periods and at sensitive locations;
and
l Keeping site roads reasonably even so as to mitigate the potential for
vibration from lorries.
Furthermore, it is envisaged that a variety of practicable noise control measures
will be employed. These may include:
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.7
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
l Selection of plant with low inherent potential for generation of noise and/ or
vibration;
l Erection of barriers as necessary around items such as generators or high
duty compressors;
l Location of any noisy plant as far away from sensitive properties as permitted
by site constraints; and
l The use of vibration isolated support structures where necessary.
No significant vibrational impacts are expected as a result of construction
activities on site (see Noise and Vibration Chapter of this EIS, Chapter 10, for a
detailed discussion of noise and vibration impacts and mitigation measures).
The potential for dust to be emitted depends on the type of construction activity
being carried out in conjunction with environmental factors such as levels of
rainfall, wind speeds and wind direction. The potential for impact from dust
depends on the distance to potentially sensitive locations and whether the wind
can carry the dust to these locations. The majority of dust produced will be
deposited close to the generated source. A dust minimisation plan will be
formulated for the construction phase of the project, as construction activities are
likely to generate dust emissions.
In order to ensure that no dust nuisance occurs, a series of measures listed
below will be implemented:
l Wheel washing facilities will be provided for vehicles exiting the site in order
to ensure that mud and other wastes are not tracked onto public roads.
l Public roads outside the site will be regularly inspected for cleanliness, and
cleaned as necessary.
9 On-site hard surfaced roads will be swept to remove mud and aggregate
materials from their surface, while un-surfaced roads will be restricted to
essential site traffic only, apart from the contractor’s carpark which will be
hardcore only.
l Any internal road that has the potential to give rise to fugitive dust will be
regularly watered, as appropriate, during dry and I or windy conditions.
l Vehicles using site roads will have their speed restricted. On any un-surfaced
site roads, this is expected to be 20 kph, as well as on hard surfaced roads,
as site management dictates.
Wyeth Medica Ireland Proposed PFNX Development Environmental impact Statement
Description of the Proposed Development 2.8
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
l Vehicles delivering material with dust potential (soil, aggregates etc.) will be
dampened down, enclosed or covered with tarpaulin to restrict the escape of
dust.
l Material handling systems and on-site stockpiling of materials will be
designed and laid out to minimise exposure to wind. Water misting or sprays
will be used as required if particularly dusty activities are necessary during
dry or windy periods.
l During movement of materials both on and off-site, trucks will be stringently
covered with tarpaulin where necessary and practicable. Before entrance
onto public roads, trucks will be adequately inspected to ensure no potential
for dust emissions.
. At all relevant times, these procedures will be strictly monitored and
assessed. In the event of dust emissions occurring outside the site boundary,
movements of materials likely to raise dust will be assessed and satisfactory
procedures implemented to rectify the problem.
The dust minimisation plan will be reviewed by WMI and the Main Contractor at
regular intervals during the construction phase to ensure the effectiveness of the
procedures in place and to maintain the goal of minimisation of dust through the
use of best practice and procedures. A detailed description of the dust
minimisation plan is provided in the Air Chapter of the EIS, Chapter 9).
Water Discharaes
Welfare facilities will be provided for the contractors on site during the
construction works. These facilities will be connected to the existing foul drainage
system on site.
The sub-soil at the site is relatively permeable and the likelihood of surface water
collecting in excavations is low, except in localised areas where significant soil
compaction may have taken place due to regular trafficking of heavy machinery.
There is also a risk that groundwater ingress may occur, due to the relative
depths of the water table and the excavation.
Any surface water run-off collecting in excavations, or groundwater ingress to
excavations will be pumped from the excavation and treated by use of suitably
sized grit chambers and a 3 chamber Class I hydrocarbon interceptor prior to
discharge to a holding tank. Once the water is deemed to be uncontaminated
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.9
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
: ._,
:
;’
FLUOR.
with respect to suspended solids and hydrocarbons, it will be discharged in
compliance with the requirements of IPC Licence Register No. 673 (see Water
Chapter of this EIS, Chapter 8, for a full description of mitigation measures
proposed).
Extensions of infrastructure
A proposed new signalised junction on the R445 and new site access and car
parking will be constructed (for which permission has been applied for under
planning ref. 04/1428). No other infrastructure extensions are envisaged.
Materials (includina Sourcina. Tranwortation & Storaae)
Key materials will include steel, concrete, composite cladding, piping, electrical
cabling, process equipment and architectural finishes. A “Just In Time” delivery
system will operate to minimise storage of materials on site.
Sourcinq
General construction materials such as concrete, bricks, sand, gravel,
tarmacadam, asphalt and steel will be sourced from different areas throughout
the country. Where practicable it is proposed to source materials from the Kildare
area.
Storaae
Aggregate materials such as sands and gravels will be stored in clearly marked
bins within a secure compound area to prevent contamination. Liquid materials
will be stored within temporary bunded areas (all bunds will conform to standard
bunding specifications - BS8007-1987) to prevent spillage.
Tranwortation
Construction materials will be brought to the site by road. Construction materials
will be transported in clean vehicles. Lorries / trucks will be suitably enclosed or
covered during transportation of friable construction materials and spoil to prevent
the escape material along the public roadway.
PiDe Laving
Pipe laying will be carried out within the WMI site, and a connection will also be
required external to the site, to the proposed new 300 mm diameter water main
which Kildare County Council are proposing to construct and which will provide
potable water to the site.
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.10
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
Fencing
The construction compound and temporary contractors facilities will be fenced off
from the remainder of the WMI site for health and safety reasons. During the
construction phase appropriate temporaly fencing will be erected to indicate the
routes to be taken by vehicles in order to minimise compaction of soils outside of
the areas proposed for development.
SDoil DeDosition
Excavated topsoil and subsoil will be stored on site and largely if not entirely
reused for landscaping purposes. Contractors will be required to submit and
adhere to a method statement indicating the extent of areas likely to be affected
and demonstrating that this is the minimum disturbance necessary to achieve the
required works.
Where soil stripping occurs the resulting excavated soil fractions will be separated
into topsoil and subsoil stockpiles. Temporary storage of spoil will be managed to
prevent accidental release of dust and uncontrolled surface water run-off which
may contain sediment and solid matter. Heavy vehicle movement and
construction works on exposed soils will be minimised during prolonged periods
of wet weather. Appropriate temporary fencing will be erected on site indicating
the routes to be taken by vehicles in order to minimise compaction of soils outside
of areas proposed for development. Machinery / equipment compounds and
heavy vehicle / machinery movements will be concentrated wherever possible on
areas proposed for future hard standing I impervious features i.e. roads buildings
etc. A full description of excavated materials is given in the Soil Chapter of this
EIS, Chapter 7.
Waste Manaaement
The handling and storage of construction wastes arising on site will be conducted
in full compliance with the requirements of WMI’s IPC Licence. It is anticipated
that construction activities will generate a range of waste materials, including
wood, concrete, steel, plastic, cement bags, cabling, damaged building materials,
waste paint and sealant containers.
The Main Contractor for the project will be required to operate a segregation
system on site, such that each waste is segregated in separate covered skips,
within a dedicated waste management area of the construction site. Materials will
V@eth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.11
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
,._
FLUOR.
be sent off-site for recycling where possible and if not suitable for recycling,
materials will be disposed of to an appropriate waste disposal facility. All waste
movement, transport, recycling, recovery and disposal, will be carried out in
compliance with the requirements of the WMI IPC Licence.
2.3.2 Operational Phase Overview
The key objective of the proposed PNFX development is to add a high
containment solid dose manufacturing unit to the existing WMI facility which will
allow a transfer from the existing production of Premarin products to the
production of Premarin New formulation Products. The key difference between
Premarin and Premarin New Formulation is that Premarin is produced using
solvent-based technology (which consumes approximately two tonnes of
Industrial Methylated Spirits solvent per year), while Premarin New Formulafion is
produced using water-based technology.
The proposed PNFX development will comprise:
l A three-storey extension (approx. 1 8,000m2) to Building 3 containing:
--j Two high containment tablet manufacturing modules (Ml+M2);
+ Single process utilities and HVAC block (U) feeding both
manufacturing modules;
+ Single personnel access and gowning area (Gl) feeding both
manufacturing modules; and
+ Administration offices.
l A central utilities building (CUB) (1 ,760m2) containing:
+ Chillers;
+ Boilers;
---, Compressors;
--+ Electrical switchgear;
+ Water treatment equipment;
+ External equipment;
+- Cold store;
--z Diesel fuel tank;
--j External cooling towers and pumps;
+ Generators; and
--j Main water storage tank and equipment.
l An automated guided vehicle (AGV) route to the existing AGV feeding the
existing central automated warehouse (located within existing buildings).
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.12
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
: : . .
‘_ : ‘, : . .
FLUOR.
l A temporary construction compound over existing car parking space which
will revert to car parking within 18 months (3,875m2).
l A temporary construction compound over Greenfield which will revert to
Greenfield after 18 months (1 8,980m2).
The proposed new PNFX building will be a three storey steel construction in
keeping with the shape and look of the existing buildings. Approximate floor areas
for the interior of the manufacturing building are as listed in Table 2.3 below.
PNFX Level
1
General Purpose Gross Infernal Floor Area
Changing I Gowning Area and 6,294 m2 General Manufacturing
Materials Handling and Off ices 6,573 m2
1 Technical Support 1 5,112 m2
17,979 m2
Table 2.3 Gross Internal Floor Areas for PNFX
TvDe of Raw Materials
The principal raw materials that will be used at the PNFX facility are listed in
Table 2.4 below.
Nature of CAS Use Number
Quantity used
(kg/annum)
Quantity stored on site
(kg) 8,500
Storage Location
Premarin Production Premarin
Production Premarin
Production
Premarin Production Premarin
Production
Premarin Production Premarin
Production
Material
12126-59-g 50,000 Premarin CE and Lactose Lactose
Hydroxy Propyl Methyl Cellulose Hydroxy Propyl Cellulose Microcrystalline Cellulose Sucrose
Cold Store ASRS
ASRS
63-42-3
9004-67-5
200,000
92,000
34,000
15,500
2,250 ASRS 13,500
79,000 13,200 ASRS
227,000 38.000 ASRS
( ASRS MPA 71-58-9 500 100
Table 2.4 The principal raw materials that will be used at the PNFX facility. Note The ASRS is an on site warehousing facility
VVyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.13
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
‘2
. I ( , ; , , , . I ,
: FLUOR.
The products listed below in Table 2.5 will be exported from the site.
Table 2.5 Product to be exported from the PNFX facility
Formulation, Handlina and Transportation of Raw Materials and Products
Tablet making in simple terms involves the mixing of a certain dose of medicine,
referred to as an Active Pharmaceutical Ingredient (API), with an inert and
pharmaceutically in-active bulking agent (referred to as the excipient) such as
lactose, to produce tablets. The overall operation of the proposed development
will involve the mixing, blending, coating and drying of pharmaceutical active and
inactive ingredients using a water-based process.
The proposed new PNFX manufacturing facility will house an automated
equipment process, which will provide full containment of materials to Wyeth
REBC (Risk Based Exposure Control) guideline. The APls that will be used are
conjugated oestrogens and Mecfroxy Progesterone Acetate, which are both
hormones used in Hormone Replacement Therapy which are currently used on-
site and are contained in low concentrations in the solid dosage form tablet which
is produced. In their concentrated form these APls have a low OEL
(Occupational Exposure Limit) (OEL) and therefore are classified as highly
potent. The high potency and hence low OEL for these chemicals determines
that controls are required on the allowable overall exposure levels of the
compound in the working area, based on an eight hour time-weighted average.
To guarantee the highest levels of safety, the proposed PNFX development will
be built as a high containment facility to Wyeth RBEC level 4 giving the maximum
safeguard to the occupational health of WMI staff working on-site, and of the
external environment.
Two possible media for the potential escape of the APls to the natural
environment outside of the production building are via air through the air vent
system, or via water in small traces possibly contained in the wet washing of the
equipment. The design of the production building has taken account of these
factors by installing best practice air-quality abatement controls such as HEPA
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.14
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
FLUOR.
(High Efficiency Particulate Air) filtration and high efficiency dust minimisation and
collection systems.
The wash down waters will be first treated by an on-site waste water treatment
system designed to bring discharge levels well within IPC licensed emissions
limits. These discharges are then routed to the municipal foul sewer which is part
of the Kildare County Council sewerage network. This flows to the Osberstown
Waste Water Treatment plant.
In addition certain segregated streams will be collected on-site separately for off-
site treatment and disposal. All discharges will be fully compliant with WMI IPC
Licence No. 673 and any revision thereof.
The proposed three storey PNFX manufacturing building will be designed as a
vertically integrated tablet making facility, whereby material will ‘flow’ by
automated gravity fed processes downwards from the floors above. This process
which is summarised in Figure 2.2, will include the following steps:
l Raw Materials Dispensing
l High Shear Granulation Mixing and Milling
l Fluid Bed Drying and Milling
l Material Blending
l Tablet Compression
l Tablet Coating
Raw Materials Dispensing. Raw materials will arrive from the dispensing
section within the existing plant by means of an Automatic Guided Vehicle (AGV).
Raw materials (both API and excipient) will be charged into an Intermediate Bulk
Container (IBC) on Floor Level 2.
High Shear Granulation Mixing and Milling. From the IBC, materials (API and
excipient) are fed into a granulator where purified water is added and the material
is mixed and milled.
Fluid Bed Drying and Milling. After the materials have been mixed and milled,
the mixture is passed through a fluid bed dryer to dry off the water. The resultant
material leaves the fluid bed dryer as a granulate and flows by gravity via a mill
into another IBC.
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.15
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
Mziterial’Blehditig. The IBC full of granulate is then placed in a blender, where it
is spun, ensuring a homogeneous mix.
Tablet Compression. The IBC from the Blender is then connected to a Tablet
Press from the floor above. The material is discharged into the tablet press
where the powder is compressed to form tablets. Compressed tablets are
ejected from the tablet press and stored in an IBC.
Tablet Coating. This is the final stage of the process whereby the compressed
uncoated tablets are fed from the IBC into a coater. The tablets are coated with
three successive solutions. Once with a sugar solution, then with a colour
solution and finally with a gloss solution. Once coated, tablets are unloaded from
the coater and transferred to a printing area within the existing WMI facility, where
they are marked with appropriate text.
The Central Utility Building (CUB) will contain the major utilities required by the
project. This building has been designed to provide hot water, steam,
compressed air, chilled water and mains water treatment for the requirements of
the process equipment associated with the proposed PNFX development.
2.3.3 Site Layout
The proposed development will be located adjacent and to the east of the
existing Building 38 as is shown on Drawing No. 800235.02-DG-AR-PNF-AE-
003. The PNFX production building will also necessitate the construction of a
Central Utilities Building, and an internal extension to the existing AGV route.
In addition to this, two temporary construction compounds will be required,
bringing the total development footprint to 32,115 m* (of which 24,000 m* will
be for temporary construction works) within the 49.7 hectare site application area.
2.3.4 Site Design
Buildinu Structure
The building shell for the proposed building will be a braced steel frame structure
and fire protected where necessary. The floors will be constructed of steel trowel
finished poured concrete on a profiled sheet type providing concrete decks at
6.3 m floor levels with an over flying roof steel and concrete structure.
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.16
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:21
. , :
I
: . . , ‘, _,
FLU0 R.
The floor deck heights have been deliberately aligned with those of the rest of
Building 3 to provide material access, personnel access and escape via the
existing flanking corridors and staircases.
The PNFX Floor Level 1 footprint, including the change rooms, new staff
entrance, link corridor, manufacturing modules and the Utilities/HVAC block, will
be approximately 73.0 m x 91.4m. It will step back at Floor Level 2 from the main
facade (plant north) by approximately 13.4 m. The grid is set at 9 m column
centres running plant east to west and between 8 m to 10 m running plant north
to south.
Wall cladding
Wall cladding will be part insulated brick and blockwork. To reflect the continuity
with Building 3 the brickwork will match the existing brown buff brick of Building
3B. The brickwork will be constructed up to a level of 8.4 m on the proposed
gable elevation (plant east) to tie in with the existing brick banding of Building 38.
Brickwork will be carried up on the stair and lift towers (plant north) to match the
soldier course level of the existing Building 3B. This will create a continuous sight
line of building materials between the existing Building 38 and the new proposed
facility. Pre-insulated cladding panels to match the existing panels of Building 3B
will be provided to all other areas. A double glazed polyester powder coated thin
frame window system will be provided to the personnel corridors on level two to
the plant north and south elevations. Fine line louvre systems will be provided for
HVAC2 intakes at Floor Level 2 and 3 and for the Utilities/HVAC block.
Curtain Walling
A glazed curtain walling system will be provided to the two-storey structure to the
northern elevation of the facility. This curtain walling system will enclose the
personnel link corridor on Floor Level I, linking the proposed PNFX facility with
the existing Buildings 38, 3A, 3 and Building 1. The curtain walling system is
carried up to Floor Level 1 via a spandrel panel (this will conceal the first floor
slab and steel beam support) to a brick parapet. The curtain walling will be
’ HVAC. Heat Ventilation Air Conditioning
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.17
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
_: ..‘.‘ FLUOR.
interrupted at regular intervals with brick piers providing internal display areas to
the link corridor and acting as fire breaks between the existing and proposed
structure. A brise soleil or solar fin will be installed below parapet level to provide
solar shading to the building occupants.
Roofing
Roofing systems are designed to ensure that all building mechanical systems are
internally provided for without the need for roof mounting, and that rain is directed
off and away from the building enclosure. This allows the provision of a
lightweight roofing system with areas of concrete slab for fire protection of
structure and construction laydown. The roof will be provided with a safety
access system.
2.3.5 Site Access
WMI has conducted a Strategic Review of Traffic Management at the Newbridge
Site over the past 12 months. The WMI site is currently accessed via an entrance
located on the western boundary of the site. As a result of the aforementioned
review, a planning application has been lodged with Kildare County Council
(04/l 248) to provide an additional site entrance and new signalised junction at the
north eastern corner of the site, initially to facilitate construction traffic currently
serving the site as part of the Building 3B development and PNFX construction
traffic, and in the longer term to facilitate employees accessing the site.
Should the application for the new site entrance not be successful, then WMI will
continue to use the construction site entrance adjoining the existing employee
entrance from the Greatconnell road.
Once construction works are complete, the new site entrance and related
signalised junction is planned to become a new employee and visitor entrance to
the WMI site. The new entrance will incorporate new site security barriers and a
security office, which will be sufficiently set back from the road to ensure that
HGVs stopping at the barrier do not impact on traffic on the R445.
On-site a new.staff entrance to the WMI facility will be created at the north east
corner of the proposed PNFX building. The proposed entrance is orientated
towards the proposed new site entrance (04/l 248) and road network.
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.18
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
FLUOR.
0 2.3.6 Traffic
The site currently generates approximately 40 HGV (Heavy Goods Vehicle)
movements per day, 7 days per week. The proposed PNFX development is
expected to give rise to an additional 2 - 4 HGV movements per day once
operational.
It is not proposed to provide car parking with this proposed development as the
car parking that is currently under the consideration of Kildare County Council
(04/1248) will adequately cater for its needs. Wyeth is also preparing a Mobility
Management Plan for the site, which will improve the sustainability of the
transport options available to employees accessing the site.
2.3.7 Waste Generation and Waste Management
As part of the general requirements of EU regulations, WMI will continue to
operate a distinct hierarchical approach to waste management for the proposed
PNFX and planned developments as follows:
l Prevention (Source reduction / elimination)
l Minimisation (Substitution)
l Reuse
l Recycling
l Energy Recovery (Treatment)
l Disposal
A waste management strategy will be developed for the proposed PNFX and
planned developments as per the requirements of Condition 7 of IPC Licence
Register No. 673 or any revised licence. To this end by strictly adhering to plant
operating instructions waste arisings at the plant should be minimal. Procedures
are specified for the management of contaminated raw materials i.e. if reusable,
material will be returned to material storage areas and I or the process system,
otherwise the material must be treated by appropriate means. All waste
generated at the site will be collected and stored in designated controlled storage
areas prior to removal by an appropriately licensed and EPA approved waste
management contractor for off-site treatment. No waste will be disposed of at the
site. Where possible metal, paper, cardboard, oil, wood or glass components will
be recycled (off-site).
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.19
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
Both solid wastes and aqueous liquid wastes will be produced as part of the
normal operation of PNFX.
The solid waste stream will comprise the following:
CIP Wastewaters
Table 2.6 Predicted waste types generated from operation of PNFX (an asterisk
beside the EWC codes refers to waste being described as hazardous)
Waste actives and excipients will be generated by rejection of product and raw
materials, and from dust collection systems and equipment cleaning.
It is estimated that the PNFX waste streams (excluding waste actives and
excipients) will generate some 27 tonnes of waste per annum, all of which will be
classed as hazardous.
In addition, it is estimated that approximately 13 tonnes per annum of non-
hazardous waste, comprising cardboard, paper, plastic, metal, organic waste
from canteen and mixed residual non-hazardous wastes will be generated by the
additional 70 employees who will work on-site in PNFX.
Wyeth Meciica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.20
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
All waste disposal from PNFX will be as per the requirements of WMl’s IPC
Licence No. 673. (Condition 7) or any revised licence. Hazardous and non-
hazardous wastes are segregated on site and managed to ensure the potential
for contamination of the non-hazardous waste stream by hazardous waste is
removed.
Wastes will be directed from the point of generation to a dedicated waste storage
area within PNFX and will be transferred from this area to an appropriate area of
the existing on-site internal and external hazardous and non-hazardous waste
management compounds.
Only waste management contractors approved by the EPA will be used for
removal and disposal of wastes generated by PNFX, in compliance with the
requirements of WMl’s IPC Licence.
2.3.8 Water Discharges The following sources of wastewater generation will be present in the proposed
PNFX development:
l Effluents generated by the CIP (Clean In Place) systems which are used to
clean process equipment between batches;
l Rinse waters;
l Cooling tower make up water;
l Boiler blowdown;
l Water treatment reject waters; and
l Effluent from employees use of welfare and canteen facilities.
The wastewater stream will total some 197 m3 / day, of which some 103 m3 / day
will be generated by the CIP process. Of this it is expected that some 3 m3 / day
will be classed as hazardous waste and disposed off site at appropriately licensed
waste treatment facilities, in compliance with WMl’s IPC Licence.
The remainder will be disposed of via the new proposed on-site process
wastewater treatment plant, along with other effluents generated at the PNFX
facility.
It is expected that this system will be fully operational by January lSt 2006,
approximately 6 months before the PNFX development is planned to be fully
operational, in accordance with the requirements of the current IPC Licence for
the WMI site (IPC Licence No. 673). Domestic strength wastewater will be
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.21
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
/ - ‘,/
1’,,. ; . ; . T __
FLUOR.
generated by employees working at the PNFX development. It is expected that
some 90 employees in total will work in the development, generating
approximately 4 m3 / day of wastewater, which will also be directed to the
proposed on-site wastewater treatment plant.
Surface water run off will be generated from rainwater falling on impermeable
surfaces at the proposed PNFX development. The run-off will be attenuated
using an attenuation tank to ensure there will be no nett increase in the surface
water run off rate at the WMI site.
213.9 Atmospheric Emissions
Process emissions will occur from the following emission points on the PNFX
facility:
l 3 no. boilers
l 2 no. granulators
9 2 no. fluid bed driers
l 16 no. tablet coaters
l 2 no. dust extract points
l 2 no. vacuum extract points
The following substances will be emitted and monitored from the boilers:
l Nitrogen dioxide (NO*)
l Sulphur Dioxide (S02)
l Carbon Monoxide (CO)
The following substances will be emitted and monitored from the other stacks:
l Total Dust (as PM,,-,)
All air emission points which have the potential to contain APls will be treated
through HEPA filters, which are designed to remove some 99.97% of all dusts
entering the filter.
In addition to exhaust air emissions from the HEPA filters, which could contain
traces of APls, the PNFX facility will also emit combustion emissions from the
operation of boilers (normally fuelled by gas and in emergency situations by oil).
The boiler combustion units will be fitted with low NOx burners (burners which
produce low concentrations of nitrogen oxides) to ensure the potential for
formation of NOx in the air emissions is kept to a minimum.
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.22
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
l
:: FLUOR.
All emission concentrations will be in compliance with the limit values defined by
the IPC Licence for the Site.
2.3.10 Services infrastructure
The site which is supplied by a 38kV electricity supply, is currently drawing
7.5 mVA. ESB has confirmed that infrastructure is adequate to meet the future
demands of the proposed PNFX development which will be an additional 4 mVA,
and also the future demands of other planned development which will account for
a further 3.1 mVA.
The steam boilers will be fuelled by natural gas and the emergency generator by
diesel. The predicted maximum gas usage will be in the region of 2250 m3 / hr.
Back-up generators will only be used when the electrical power supply to the site
is interrupted.
In addition to the ESB supply, WMI also operates a CHP plant (Combined Heat
and Power), which operates on natural gas and produces both electrical power
and waste heat, which is reused in the WMI facility.
The site is currently connected to the Newbridge town water supply and
sewerage systems. The facility currently receives some 500 m3 / day of
potable water and is licensed to discharge 450 m3 / day of wastewater.
As a result of the proposed PNFX development process water consumption will
rise from its current value of 500 my/day to 740 m3/day by the second quarter of
2006. Potable water demand from other planned developments is estimated to
increase by 250 m3/day by summer 2004. Kildare County Council has advised
that this proposed total increase of 490 m3/day will be met by its new 300 mm
diameter water main.
It is expected that wastewater production will rise from its current maximum value
of 450 m3 / d to 647m3 / d by the second quarter of 2006, as a result of the
operation of the PNFX development. Planned developments within the site will
give rise to an additional 130 m3/day, giving an overall predicted wastewater
production by second quarter 2006 of 777 m3/day. Kildare County Council advise
that the off site sewage infrastructure and Osberstown Wastewater Treatment
VQfeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.23
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
FLUOR.
Plant will be able to accommodate this proposed increase in wastewater
production.
2.3.1 I Landscaping
Landscaping measures comprising two large planted berms are currently
under consideration by Kildare County Council as part of the planning
application no. 04/1248. Additional planting to areas of new build and new
pedestrian . routes will be provided as part of the proposed PNFX
development.
Mitigation measures have been incorporated at the design development stage to
minimise visual intrusion / obtrusiveness and integrate the proposed PNFX
development seamlessly into its surrounding semi-urban context. The scale and
height of the proposed PNFX development have been carefully considered and
designed to achieve a balance between making best use of the site without
dominating or compromising the surrounding area.
The proposed new PNFX facility will be in keeping with the existing external
finishes and emphasis has been given to minimising the building mass and the
development footprint of the proposed new facility.
Roofing systems have been designed to ensure that all building mechanical
systems are internally provided for without the need for roof mounting, and that
rain is directed off and away from the building enclosure. This allows the
provision of a lightweight roofing system with areas of concrete slab for fire
protection of structure and construction laydown.
The floor deck heights have been deliberately aligned with those of the rest of
Building 3 to provide material access, personnel access and escape via the
existing flanking corridors and staircases.
In keeping with the existing architectural context, wall cladding will be part
insulated brick and blockwork. To reflect the continuity with Building 3 the
brickwork will match the existing brown brick of Building 3B.
A new staff entrance will be created at the northeast corner of the PNFX facility. It
will create an appropriately appointed focal point for the new facility.
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.24
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
I .
FUJOR.
The scale‘and intensity of the landscape works have also been designed to allow
the proposed development to conform to the character of the existing WMI site in
general. The building location was considered to minimise visual intrusion by
locating it adjacent to the existing buildings, and as such it will provide continuity
with the rest of the site when viewed from the eastern side of the facility.
The sensitive use of grading and planting to the north eastern fringes of the site is
also proposed in order to reduce the views into the site and provide an attractive
landscape setting for views into the WMI site.
Lighting will be designed to have a minimal impact on the environment. External
light sources will be designed to shine downwards, and will be designed to cause
minimum glare beyond the boundary of the WMI site.
2.3.12 Employment & Hours of Operation
The proposed development will require approximately 90 employees when
operational. The jobs will be highly skilled, and will involve specified training.
Of the approximate 90 employees, 5 will be office / administration staff and
the balance will be production staff, approximately 20 of whom will transition
from the existing Premarin facility and the remaining 70 of whom will be new
employees.
The coating process is 60-hours long and therefore a 24hr, seven days a
week three-cycle shift3 will be in place. Some of the peripheral processes
within the site will not be tied to the coating process, which may result in some
employees working a Monday to Friday 08:OO - 17:00 week.
2.3.13 Health and Safety
The proposed design of the PNFX development and additional planned
developments, has taken full account of the requirements of regulatory
authorities, the Building Regulations 1997 to 2000 (SI No. 497 of 1997 and * various amendments), construction industry guidelines and British Standards. In
addition the Safety, Healfh and We/fare (Construction) Regulations, 2001 and
Safety, Health and Welfare Work (General Application) Regulations, 1993 have
also been taken into consideration.
3 The three-cycle shift will run from 08:OO - 16:00, 16:00 - 24:00, 24:00 - 08:OO.
weth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.25
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:22
j ’ : ‘.,
FLUOR.
Gene&l Principles of Prevention (First Schedule of the SHW (General
Amlication) Reauiations 1993)
Insofar as is reasonably practicable the facility and process design adheres to the
principles of the General Application Regulations 1993 including:
l The avoidance or risks.
l The evaluation of unavoidable risks.
l The combating of risks at source.
l The adaptation of work to the individual, especially with regard to the design
of places of work and the choice of work equipment.
l The choice of systems of work, with a view, in particular, to alleviating
monotonous work and work at a predetermined work rate.
l The adaptation of the place of work to technical progress.
l The replacement of dangerous articles, substances or systems of work by
non-dangerous or less dangerous articles, substances or systems of work.
l The development of an adequate prevention policy in relation to safety, health
and welfare at work, which takes account of technology, organisation of work,
working conditions, social factors and the influence of factors related to the
working environment.
l Giving collective protective measures priority over individual protective
measures.
l Provision of appropriate training and instructions to employees.
Process Safetv Review
A Process Safety Review was conducted by Fluor Ireland Ltd. which reviewed the
properties of the materials, containment strategy, and accident prevention. The
items reviewed’include:
l Hazards of the Activity or Procedure
l Previous Incidents
l Engineering and Administrative Controls
l Consequences of failures of Engineering and Administrative Controls
l Siting I layout issues
l Qualitative Evaluation of Safety & Health effects
. Other Regulatory Issues (OEL’s etc...)
l Material Problems
l External Effects or Influences
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.26
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:23
<, , . :
..’
FLUOR.
l Operating Errors and Other Human Factors
l Analytical or Sampling Errors
l Equipment/Instrumentation Malfunction
l Process Upsets of Unspecified Origin
l Utility Failures
l Integrity Failure or Loss of Containment
l Emergency Operations
l Environmental Release
Fire Safetv
Fire detection and alarm systems were designed in accordance with Irish
Standards and Practice including:
l Technical Guidance Document B (TGD-B) of the Irish Building Regulations
l BS 5588-l 1 1997 Code of Practice for shops, offices, industrial, storage and
other similar buildings.
l 2000 International Building Code.
Smoke Manaaement
Smoke exhaust in the event of fire has been provided in the unclassified areas in
accordance with building regulations and insurers’ requirements. Similarly smoke
ventilation (to remove smoke from a building in the event of a fire) is provided in
all areas of the buildings which are larger than 300 m2 and which fall outside of
the controlled environments.
Fire Sutwression
Fire protection will be provided in accordance with the LPC (Loss Prevention
Council) Regulations, the 2000 International Building Code and insurers’
requirements. The existing fire mains will be extended as the existing fire pump
and storage tanks are adequately sized to meet the requirements of the
development. The new PNFX production building will be protected by an
automatically activated wet sprinkler system apart from the computer / server
rooms which will be protected by an automatically activated inert gas systems.
The Central Utilities Building (CUB) will be protected by an automatically
activated dry powder system. These automatic fire suppression systems will also
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.27
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:23
FLUOR.
be’supplemented by hand held fire extinguishers strategically placed around the
new development proposals.
Fire-Water Retention
Firewater generated by the hydrant system, sprinkler system or fire brigade fire
fighting equipment will be collected within the PNFX building by the process
drainage system and will be directed to the on-site fire water collection and
storage system. The maximum predicted volume of firewater which, it is
considered, could be generated by the PNFX development is I,21 9 m3, for a 90
minute fire event. The site currently has a firewater retention capacity of
1,000 m3 and this will be increased, as part of the proposed PNFX development,
by extending the existing underground 1000 m3 tank capacity to 1219 m3.
Firewater will be tested for pharmaceutical actives and other contaminants, prior
to release to the municipal sewerage system, via the WMI on site wastewater
treatment plant. A detailed discussion of firewater generation rates and volumes
is provided in the Water Chapter, Chapter 8, of this EIS.
2.4 Decommissioning
In the unlikely event of decommissioning and closure of the WMI facility the
provisions of the Residuals Management Plan (RMP) prepared for the site (which
has been approved by the EPA) will be adopted. The RMP is reviewed and
updated annually as part of the Annual Environmental Report (AER) prepared for
the site. The RMP incorporates a short term programme for decontaminating and
making safe all above ground structures and removing all wastes and hazardous
materials from the site and a long term programme which concentrates on
dealing with any soil or groundwater contamination issues associated with the
site.
It is expected that the RMP will be required to be reviewed and updated to
incorporate the proposed PNFX development.
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.28
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:23
2.5
2.6 Other Planned Developments
Future ‘Grtitih And Expansion
Any further plant expansion found to be necessary will normally require additional
planning applications to be made. In turn, WMl’s IPC licence may require to be
reviewed and updated or revised. Such applications will be the subject of further
study based on the operation of the then current WMI site.
In order to adequately assess the cumulative impact of the proposed PNFX
development, additional developments which are planned for the site have been
assessed within the various chapters of this EIS. These additional developments
are detailed as follows and depicted on Drawing No. 800235.02-DG-AR-PNF-AE-
002.
DeveloDment Where Plannina Permissions Granted But Not Yet
Constructed:
l (0312097) Construction of a new enclosed plant room at roof level of the
existing Building 3 (222m2). The plant room will be constructed in two phases
each equating to 111 m2.
l (0312105) Installation of four new ventilation wall louvers to the south-east
elevation of Building 3.
l (03/2604) Modifications, additions and extensions to the existing Utilities
Facility on the site. These works are: new single storey extension (231m2) to
existing plant room Building 5A (530m2) housing electrical gear and
compressors etc.
l (03/1425) New single storey electrical switch room (206m2) and associated
transformers to be located in new extension to existing electrical compound.
Develooment Where Plannina AoDlication Lodaed But Not Yet Determined
bv Local Authoritv:
l (04/1248) Planning application for the provision of a new access, internal
road, additional 668 car parking spaces, new security building, temporary
construction area and landscaping provisions.
Wyeth Medica Ireland Proposed PFNX Development Environmental Impact Statement
Description of the Proposed Development 2.29
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:23
FLUOR.
Development ProDosed Where Plannina Awlication To Be Lodaed in the
Future:
l Proposal to construct a Waste Water Treatment Plant (WWTP). WMI plans
to submit this application in Quarter 3, 2004.
l Proposal to construct waste management compound. WMI plans to submit
this application in Quarter 3, 2004.
of the Proposed Development 2.30 Erkironmental Impact Statement
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 25-07-2013:15:17:23