CONCRETE PLACEMENT AND FINISHING ANDREW MERRICK

Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Embed Size (px)

Citation preview

Page 1: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

CONCRETE PLACEMENT AND FINISHING

ANDREW MERRICK

Page 2: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Purpose of Meeting

Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects on neighbours

Review schedule of concrete placements

Page 3: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Attempt for an early morning start time within the by-law requirements

Goal is to get concrete in early so that it sets up early to allow finishing to start and be completed earlier.

If necessary, could be started later in the day to accommodate weather forecasts, inspections, etc.

Early Morning Start

Page 4: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Pour Sequence

Sequence slab placements in a south to north direction to provide a buffer between work and South Street after initial placement.

Page 5: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Placement of Slabs

Place slab in thirds to cut down on the volume of concrete to be placed and finished

Page 6: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Erection of Wind/Sound Screens

Plywood barrier approximately 4 feet high erected to cut down on wind and sound transmission.

Page 7: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Light Direction

Lights when required to be directed away from South and LeMarchant Streets.

Page 8: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Faster Concrete Set Time

Money to be spent on admixture additives placed in the concrete to shorten set time

Page 9: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Concrete Placement Method

Traditional method with tower crane on site is to use concrete bucket for slab placements which is time consuming.

Page 10: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Concrete Placement Method

Slabs to be placed using a concrete pump which will increase the rate that the concrete is placed.

Page 11: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Concrete Placement Method

Supplement concrete pump with deck placer from level 3 to roof.

Articulating arm eliminates need to drag hoses over slab increasing placement rate.

Page 12: Describe measures that will be used to place and finish concrete within the requirements of By-Law Number N-200 – Respecting Noise and minimize effects

Schedule

When concrete placements occur, Aecon site office will be open and personnel can be contacted at 407-7730.

Estimated 26 slab placements to occur First placement scheduled is basement

slab on grade in mid-May 3 placements every 2 weeks once level 3

slab is completed and typical floors start Completion of concrete work scheduled

for early November