34
Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information Regarding DTSC’s Compliance to Health & Safety Code Section 25200.8 in Permit Decisions for Facilities with Three or More Notices of Deficiency In its April 21, 2016 quarterly report to the Governor and Legislature, the Independent Review Panel (IRP) requested information about the Department of Toxic Substances Control’s (DTSC’s) compliance with requirements to deny a permit application if an applicant unsatisfactorily responds to multiple Notices of Deficiency (NOD). Specifically, in the IRP’s Second Report to the Governor and the Legislature, the Panel made the following request: By January 1, 2017, report to the IRP on whether DTSC is complying with the Health & Safety Code Section 25200.8 requirement to initiate proceedings to deny a permit application if an applicant does not respond to three or more Notices of Deficiency, or responds with substantially incomplete or unsatisfactory information on three or more occasions. If the DTSC is not currently complying, it should explain the reasons for not doing so and indicate whether the code section should be amended. This document is prepared in response to this inquiry from the IRP. In implementing section 25200.8, DTSC recognized that before it could deny permits based on failure to adequately respond to three or more NODs, it had to standardize how it wrote NODs, among other improvements to the permitting process. DTSC has adopted changes to make the permitting process more efficient and thorough, and is now implementing those improvements. Overview When DTSC receives a permit application, it conducts two main types of reviews prior to making a decision on the application. The first is the Administrative Review to identify whether all required elements of the application have been submitted. The second is the Technical Review, during which DTSC evaluates the content of the required elements and whether they demonstrate that the facility, as described, will comply with all applicable laws and regulations. If DTSC determines that the information provided in the application does not demonstrate compliance, DTSC issues a Notice of Deficiency, or NOD, to the applicant. The NOD details the additional information needed to allow DTSC to conclude that the facility would comply with the law and to support approval of the permit application. Health and Safety Code Section 25200.8 states that “…If an applicant responds to three or more of these notices of deficiency regarding the same or different deficiencies or responds with substantially incomplete or substantially unsatisfactory information on three or more occasions, the department shall, pursuant to regulations adopted by the department, initiate proceedings to deny the permit application.” Historically, DTSC has not had a policy regarding the interpretation or implementation of this language. In addition, DTSC did not have clear guidance on required application content or on preparing NODs.

Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information

  • Upload
    leminh

  • View
    216

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information

Department of Toxic Substances Control January 2017  

1  

DTSC’s Response to the IRP’s Request for Information Regarding DTSC’s 

Compliance to Health & Safety Code Section 25200.8 in Permit Decisions for 

Facilities with Three or More Notices of Deficiency 

In its April 21, 2016 quarterly report to the Governor and Legislature, the Independent Review Panel 

(IRP) requested information about the Department of Toxic Substances Control’s (DTSC’s) compliance 

with requirements to deny a permit application if an applicant unsatisfactorily responds to multiple 

Notices of Deficiency (NOD).  Specifically, in the IRP’s Second Report to the Governor and the 

Legislature, the Panel made the following request:  

By January 1, 2017, report to the IRP on whether DTSC is complying with the Health & Safety 

Code Section 25200.8 requirement to initiate proceedings to deny a permit application if an 

applicant does not respond to three or more Notices of Deficiency, or responds with 

substantially incomplete or unsatisfactory information on three or more occasions.  If the DTSC 

is not currently complying, it should explain the reasons for not doing so and indicate whether 

the code section should be amended.   

This document is prepared in response to this inquiry from the IRP.  In implementing section 25200.8, 

DTSC recognized that before it could deny permits based on failure to adequately respond to three or 

more NODs, it had to standardize how it wrote NODs, among other improvements to the permitting 

process.  DTSC has adopted changes to make the permitting process more efficient and thorough, and is 

now implementing those improvements. 

Overview 

When DTSC receives a permit application, it conducts two main types of reviews prior to making a 

decision on the application. The first is the Administrative Review to identify whether all required 

elements of the application have been submitted.  The second is the Technical Review, during which 

DTSC evaluates the content of the required elements and whether they demonstrate that the facility, as 

described, will comply with all applicable laws and regulations.  If DTSC determines that the information 

provided in the application does not demonstrate compliance, DTSC issues a Notice of Deficiency, or 

NOD, to the applicant.  The NOD details the additional information needed to allow DTSC to conclude 

that the facility would comply with the law and to support approval of the permit application.  

Health and Safety Code Section 25200.8 states that “…If an applicant responds to three or more of these 

notices of deficiency regarding the same or different deficiencies or responds with substantially 

incomplete or substantially unsatisfactory information on three or more occasions, the department 

shall, pursuant to regulations adopted by the department, initiate proceedings to deny the permit 

application.”  Historically, DTSC has not had a policy regarding the interpretation or implementation of 

this language.  In addition, DTSC did not have clear guidance on required application content or on 

preparing NODs.  

Page 2: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information

Department of Toxic Substances Control January 2017  

2  

This led to considerable variation in the comprehensiveness of the NODs that were issued by DTSC.  

Some NODs were very detailed and comprehensive, while others followed a more iterative approach to 

identifying information needed to complete the permit review.  This iterative process frequently 

resulted in more NODs and  contributed to delays in DTSC decisions on permit applications.   

In 2014, DTSC began a systematic review of its permitting process to improve the consistency and rigor 

of the review, and eliminate inefficiencies that led to delays.  This review has been described in other 

reports (see, for example, the Permitting Program Update for the Independent Review Panel, presented 

to the IRP on March 9, 2016).  As part of this review, DTSC applied a Lean Six Sigma (LSS) analysis to 

three different aspects of the permitting process: the Technical Review, the Administrative Review, and 

the Notice of Deficiency.  While only one LSS project specifically focused on the NOD process, all three 

projects are expected to improve the quality of the permit applications and reduce the number of NODs 

issued.  A brief summary of these projects and an explanation of how the projects are expected to affect 

the NOD process are provided in this report (see Process Improvement Projects, below).  

DTSC currently has forty‐four permit applications pending.1  Forty‐one of these applications have two or 

fewer NODs.  Three of the applications (all predating the new guidance) have received three or more 

NODs; however none of the applicants responded with “substantially incomplete” or “substantially 

unsatisfactory” information.  Table 1, Current Application Status, provides a list of the pending 

applications, showing the project type and number of NODs issued.  With the guidance established 

through these LSS projects DTSC is establishing a consistent interpretation and implementation of 

Health and Safety Code Section 25200.8.   

Table 1 – Current Application Status 

No.   Project Name  Activity Type  # of NODs 

1  American Oil  Renewal  0 

2  Asbury Environmental Services   Mod Class 2  0 

3  Atlas Precious Metals  Renewal  2 

4  Chemical Waste Management – Kettleman  Renewal  1 

5  Chevron El Segundo  Renewal  0 

6  Chevron Richmond  Renewal  0 

7  Chevron Richmond Post Closure  Renewal  2 

8  Clean Harbors Button Willow  Renewal  2 

9  Clean Harbors Westmorland  Renewal  2 

10  Clean Harbors San Jose  Renewal  0 

11  Dynegy Moss Landing  Renewal  0 

12  Edwards Air Force Base  Renewal  2 

13  EPC Westside  Renewal  0 

                                                            1This includes applications for new hazardous waste facility permits, and modifications to, or renewals of, existing hazardous waste facility permits.  For a discussion of permit decisions, see Appendix A, Background on Permit Decisions.  

Page 3: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information

Department of Toxic Substances Control January 2017  

3  

No.   Project Name  Activity Type  # of NODs 

14  Evoqua Water Tech/ US Ecology  Renewal  5 

15  Filter Recycling Services  Renewal  1 

16  GEM of Rancho Cordova  Renewal  0 

17  HGST  Renewal  1 

18  HGST  Mod Class 1  0 

19  Industrial Service Oil Co Inc  Mod Class 1*  0 

20  John Smith Road Landfill  Renewal  2 

21  Kearney – KPF  Renewal  0 

22  KW Plastics of CA  Renewal  0 

23  Lawrence Berkeley National Laboratory  Renewal  0 

24  Lawrence Livermore Laboratories  Renewal  0 

25  Lawrence Livermore Laboratories PC  Renewal  0 

26  Lighting Resources  Renewal  0 

27  Naval Air Weapons Station China Lake  Renewal  1 

28  Naval Station San Diego  Renewal  1 

29  PG&E/Diablo Canyon  Renewal  0 

30  Pacific Scientific  Renewal  0 

31  Phibro‐Tech  Renewal  0 

32  Quemetco Inc.  Renewal  0 

33  Riverbank Oil Transfer, LLC  Renewal  3 

34  Safety‐Kleen Systems Inc, Sacramento  Renewal  1 

35  Safety‐Kleen Systems Inc, Newark  Renewal  1 

36  Sandia National Laboratories  Renewal  0 

37  San Diego Gas  Renewal  0 

38  Southern Cal Pico Riviera  Renewal  0 

39  Southern Cal Gas Los Angeles  Renewal  0 

40  TFX Aviation  Mod Class 1  0 

41  The Dow Chemical Co MS‐HAF  Renewal  3 

42  The Dow Chemical Drums  Renewal  0 

43   World Oil – San Joaquin  Mod Class 3  0 

44  Safety‐Kleen Systems Inc,  Renewal  0 

       

Page 4: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information

Department of Toxic Substances Control January 2017  

4  

ProcessImprovementProjects

1. TechnicalCompleteness

The steps DTSC takes to make a permit decision are numerous and in the past have taken a long time.  In 

light of this, DTSC completed a Lean Six Sigma (LSS) project in 2014 to identify process improvements.  

Data analysis suggested that the extended period spent reviewing the technical completeness of the 

permit applications was the leading cause of the time required to make a permit decision.  After further 

analysis, the project team concluded that requiring the permit project manager (PPM) to use the Permit 

Completeness Checklist during the technical review would be the most impactful way to shorten the 

permit decision‐making process.   

The checklist contains a total of 1,029 line items that serve as a guide to the project manager to help 

with a complete and thorough review.   Using the checklist will provide a consistent review process by 

clarifying what needs to be reviewed in each application.  Because of the increased clarity and 

thoroughness of the review, the number of NOD comments will be reduced.  The permit completeness 

checklist can also be utilized to track the progress of permit reviews by the PPM or supervisors.  Figure 1 

shows a sample portion of the Permit Completeness Checklist.   

Figure 1 – Permit Completeness Checklist (Sample) 

 

 

2. AdministrativeCompleteness

Page 5: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information

Department of Toxic Substances Control January 2017  

5  

The process improvements delivered from the initial LSS project led to a LSS Phase II project in 2014.  

The LSS Phase II project further addressed the length of time to complete a permit decision.  The Phase 

II project considered whether other tasks in the permitting process (beside the technical review process) 

could be improved upon to expedite reaching a decision.  The Phase II analysis identified the need for 

improvements to the administrative review of the permit application to shorten the time to complete 

the review from an average of 7 months to 30 days.   

3. NoticesofDeficiency

In 2015 a third LSS project was completed, which addressed the inefficiencies in the NOD process.  The 

objective of the LSS Phase III project was to cut in half the average number of NOD comments per 

permit.   

 

The LSS team analyzed all of the individual comments within 25 of the most recently issued NODs and 

the causes of the comments.  It was determined that 532 of the 618 NOD comments were due to 

administrative issues (not technical issues) and that 331 of the 532 comments were the result of missing 

information.  Figures 2 and 3 show the two level Pareto analysis breakdown of the causes for NOD 

comments.  

Figure 2 – Pareto Analysis of NOD Comments 

 

 

 

Page 6: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information

Department of Toxic Substances Control January 2017  

6  

Figure 3 – Pareto Analysis of NOD Comments (Administrative) 

 

 

 

The LSS Phase III project resulted in thirteen recommendations, including the need for guidance 

documents and training.  The Pre‐Application Meeting Agenda and Signature sheet (shown in Appendix 

B) was created to give facilities notice of format expectations, guidance and an opportunity to get up 

front clarity and direction from DTSC.  The Pre‐Application meeting is expected to reduce the number of 

NODs issued, as facilities will understand, up front, what information must be included in the permit 

application.   

The Guidance on Notice of Deficiency (shown in Appendix C) was issued in May of 2016 to address the 

need for standardized training for staff.  The Guidance includes training, a new template cover letter, a 

model NOD, some “dos and don’ts” tips, factors to consider and a sample meeting agenda for an NOD 

meeting.   

As part of the new Guidance on Notice of Deficiency, the new template cover letter (which is included in 

the NOD documents issued to the facility) contains the following text regarding multiple NOD’s:   

Please note that pursuant to Health and Safety Code Section 25200.8 and California Code of 

Regulations, Title 22, Section 66271.2(e), DTSC may deny permit applications based on a failure 

Page 7: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information

Department of Toxic Substances Control January 2017  

7  

of the applicant to respond to a NOD or when the applicant responds with substantially 

incomplete or substantially unsatisfactory information. 2 

Along with the Guidance on Notice of Deficiency, a Notice of Deficiency Meeting Guidance was issued 

(Shown in Appendix D) to aid in preparing for and conducting a meeting with the facility when 

communicating the NODs.  This should reduce the number of future NODs, as the meeting with the 

facility will allow it to ask specific questions and submit a response to the NOD that will be sufficient and 

complete.   

SUMMARY

DTSC has established new guidelines, processes, and checklists to improve the quality of permit 

applications and allow the department to deny a permit if an applicant fails to provide substantially 

complete and satisfactory information.  This includes the Guidance on Notice of Deficiency, Notice of 

Deficiency Meeting Guidance, the Permit Completeness Checklist, and the Pre‐Application Meeting 

Agenda.  All permitting staff have been trained in the implementation of the new guidelines and tools.  

DTSC will ensure all new staff are trained prior to beginning permitting review work.   

DTSC is preparing similar guidance documents for standardized facility permits that will be completed by 

June 30, 2017.  Model permit applications for permits under the Resource Conservation and Recovery 

Act (RCRA) will be completed by June 30, 2018.  These tools will further improve the quality of permit 

applications, the rigor of the permit review, and the timeliness of the permit process.   

The management team of the Permitting Division conducts a quarterly audit on EnviroStor to determine 

the number of NODs issued per permit decision and the duration of the permit decision‐making process.  

This control measure allows management to ensure improvements are being made.   

                                                            2 DEPARTMENT OF TOXIC SUBSTANCES CONTROL NOTICE OF DEFICIENCY COVER LETTER TEMPLATE 

Page 8: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 9: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 10: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 11: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 12: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 13: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 14: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 15: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 16: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 17: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 18: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 19: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 20: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 21: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 22: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 23: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 24: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 25: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 26: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 27: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 28: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 29: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 30: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 31: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 32: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 33: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information
Page 34: Department of Toxic Substances Control January 2017 · PDF file11.01.2017 · Department of Toxic Substances Control January 2017 1 DTSC’s Response to the IRP’s Request for Information