Department of Public Works
FY 2016 - 2020 Capital Improvement Program (CIP)
BudgetAdoption
April 27, 2015
Department of Public Works
2
Recommendation
1. Adopt by resolution FY 2016 – 2020 CIP Budget
2. Approve journal voucher amending 13 projects in the FY 2015 budget resulting in a $12,576,791 net decrease
Department of Public Works
3
Highlights
• 238 active projects with estimated cost of $1.11B
• $567.5M (51%) funded to date• $85.5M (8% of total) recommended for
appropriation• 92 projects recommended for funding• $364M of total unfunded needs
Department of Public Works
Appropriations by Category
Tech-nology, $3.5MMunic-
ipal Build-ings & Facili-ties,
$0.95M
Street Lighting, $0.54MUndergrounding, $1.1M
Pasadena Center,
$0.6M
Parking, $1.12M
Sewers & Storm Drains, $1.2M
Rose Bowl, $4.4M
Parks & Land-
scaping, $2.6M
Water Systems,
$7.7M
Arroyo Projects, $0.2M
Electric System $51.2M
Recommended FY 2016 - $85.5 Million
Transportation, $6.1M
4
Streets & Streetscape
s, $4.3M
Department of Public Works
5
Chronology
• October 2014 – November 2014 - Ideas for new projects solicited>City Council; Five commissions; City
departments
• December 2014 - Project ideas evaluated & prioritized for possible inclusion
• February 2015 - City Manager met with departments & affiliated agencies to develop Recommended CIP
• March 2015 – April 2015 – Four Advisory Commissions’ review
Department of Public Works
6
Chronology
• March 30 – Copies of CIP placed in all public libraries>Link available on City website
• April 13 – Opened public hearing & joint Finance Committee/City Council meetings
• April 27 – Close public hearing & adopt FY 2016 – 2020 CIP
Department of Public Works
Advisory Commission Reviews
Advisory Body CIP Section/Projects Date
Recreation & Parks Commission
Parks & LandscapingArroyo Projects March 17, 2015
Northwest CommissionProjects located fully or partially in Northwest
Pasadena
March 12, 2015
Planning Commission All new projects March 25, 2015, April 22, 2015
Transportation Advisory Commission
Streets & Streetscapes
Transportation
March 26, 2015
7
>March 17, 2015 – Recreation & Parks Commission voted that recommended funding be used to construct park restroom & parking lot at Desiderio Park
Department of Public Works
8
1. Citywide Sidewalk Improvement Project Add new project to FY 2016 CIP budget Presented to Planning Commission on April 22,
2015 Appropriate $1M in General Fund & $250K in
CDBG grant funds
Adjustments to FY 2016 CIP
2. Building Preventive Maintenance FY 2016 - 2020
Appropriate $46,435 in Library Services Fund & increase total estimated project cost for work at Lamanda Park, Linda Vista & Central libraries
Department of Public Works
9
3. Fiber Optic Communication System (3143)
Move project from FY 2015 CIP future project list to Electric System section of FY 2016 CIP budget
Remaining funds exist to complete necessary work
Project will be managed by DoIT
Adjustments to FY 2016 CIP
4. Restoration and Renovation of Historic Civic Auditorium Exhibit Hall
Reduce project cost & appropriation Correct budget is $5,879,000 Correct Appr thru FY15 is $1,060,000
Department of Public Works
10
Adjustments to FY 2016 CIP
5. Civic Auditorium Gold Room Floor Refinish/Replacement
Remove this project from FY 2016 CIP Budget Work will be done under PCOC’s operating
budget6. Rose Bowl – Preventative Maintenance FY 2016
Reduce FY 2016 appropriations from $720K to $692K & lower total project cost by same amount
Scope of work remains the same
Department of Public Works
11
7. Rose Bowl – Preventative Maintenance FY 2017 – 2021
Add five year phase of the preventative maintenance project to FY 2016 CIP
Total estimated cost is $3,937,251
Adjustments to FY 2016 CIP
8. Rose Bowl Major Improvements Projects FY 2017 – 2021
Add five year phase of the major improvements project to FY 2016 CIP
Total estimated cost is $17,895,000
Department of Public Works
12
1. Traffic Mitigation Improvements – Phase I (75711)
Replace $183K in General Fund with Playhouse Parking Meter Operations Fund
Adjustments to FY 2015 CIP
2. Replacement of Medium Duty Transit Vehicles (75040) and Purchase Fixed-Route Vehicles (75051)
Transfer $86,824 in Prop. C funds from “Replacement of Medium Duty Transit Vehicles” to “Purchase Fixed-Route Vehicles”
Department of Public Works
13
3. Traffic Signal Improvements at Intersection of Pasadena Ave and Walnut Street (75049)
Appropriate $50K in Traffic Reduction Fees Caltrans required design changes &
construction bids came in higher than anticipated
Adjustments to FY 2015 CIP
4. Lower Arroyo – Habit Restoration (77422) Appropriate $21,208 in Prop. A (Parks) 1992
funds to this project Funding available from a completed project
Department of Public Works
14
5. Recycle Water Project (1013) Unappropriate $10M in Water Fund to align
with workplan Project scope has not changed & sufficient
funds remain to complete scheduled work
Adjustments to FY 2015 CIP
6. New Wells Project (1021) Unappropriate $1M in Water Fund to align with
workplan Sufficient funds remain to complete scheduled
work
Department of Public Works
15
7. Customer Information System (1011 & 3022)
Unappropriate $1,321,918 in Water Fund from project #1011 & unappropriate $576,081 in Power Fund from project #3022 to align with workplan
Sufficient funds remain to complete scheduled work
Adjustments to FY 2015 CIP
8. Water and Power Warehouse Modernization (1056 & 3175)
Unppropriate $1,650,893 in Water Fund & appropriate $1,650,893 in Power Fund
Department of Public Works
16
9. Water & Power Enterprise Resource Plan (ERP) (1072 & 3207)
Appropriate $75K in Water Fund to project #1072 & $175K in Power Fund to project #3207
For costs unique to PWP associated with implementation of the ERP
Adjustments to FY 2015 CIP
Department of Public Works
17
Fiscal Impact
• Approval of City Manager’s Recommended CIP budget & proposed revisions outlined in report will establish FY 2016 – 2020 CIP>Total appropriation $85,544,705
Department of Public Works
Totals by Fund
Power Funds, $51.2M
Water Funds, $7.7MRose
Bowl Funds, $3.7M
Residential Impact Fees, $2.8M
Gas Tax Fund, $2.7M
Com-puting
& Com-muni-cation Fund, $1.4M
Other Funds,
$7.5M
Recommended FY 2016 - $85.5 million
Grants – State/Fed-eral$3.1M
General Fund, $1.8M
Sewer Fund, $1.8M
18Sewer Funds, $2.3M
Traffic Reduction Fee, $1.9M