Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
DEPARTMENT OF DEFENSE Defense Contract Management Agency
INSTRUCTION
Manufacturing and Production
Engineering and Analysis Directorate DCMA-INST 204 OPR: DCMA-EAM August 16, 2012
Change 1, November 5, 2018
SUMMARY OF CHANGES: This Change permanently removes the requirements of paragraph: 3.2.8. Contractor Performance History Input; Figure 4: Contractor Performance History Input Flowchart; Deletes references to performing Contractor Performance History in Table 8 and Figure 3. Production Surveillance Flowchart, block 1. 1. PURPOSE. This Instruction: a. Reissues Revises DCMA Instruction (DCMA-INST) 204, “Manufacturing and Production” (Reference (a)). b. Establishes policies and assigns responsibility for all individuals assigned responsibility for Production Surveillance (Defense Acquisition Regulations System (DFARS) 242.1104) (Reference (b)) by their assigned Contract Management Office (CMO). c. Is established in compliance with DoD Directive 5105.64, “Defense Contract Management Agency (DCMA)” (Reference (c)). 2. APPLICABILITY. This Instruction applies to all DCMA activities that have contract administration responsibilities. 3. MANAGERS’ INTERNAL CONTROL PROGRAM. In accordance with DCMA-INST 710, “Managers’ Internal Control Program” (Reference (d)), this Instruction is subject to evaluation and testing. The process flow is integrated into this Instruction. 4. RELEASABILITY – UNLIMITED. This Instruction is approved for public release. 5. PLAS LABOR CODES. 087A-C, 088, 089A-F, 090A-F Located on the Resource Page 6. POLICY RESOURCE PAGE. https://360.dcma.mil/sites/policy/EA/SitePages/204R.aspx 7. EFFECTIVE DATE. By order of the Director, DCMA, this Instruction Change is effective immediately. Karron E. Small Executive Director, Engineering and Analysis Change 1 Approved by: David H. Lewis, VADM, USN, Director
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
2
TABLE OF CONTENTS
REFERENCES ...............................................................................................................................4 CHAPTER 1 – POLICY 1.1. Policy ................................................................................................................................5 CHAPTER 2 – ROLES AND RESPONSIBILITIES 2.1. Director, DCMA ...............................................................................................................6 2.2. Executive Director ............................................................................................................6 2.3. CMO Commander/Director ..............................................................................................6 2.4. Technical Specialist ..........................................................................................................6 CHAPTER 3 – Procedures 3.1. Surveillance Planning .......................................................................................................7 3.2. Surveillance Execution and Documentation ...................................................................21 TABLES Table 1. Mandatory systems and processes requiring surveillance in Resident Office environment ..................................................................................... 9 Table 2. Mandatory systems and processes requiring surveillance in Geographic Office environment .............................................................................. 10 Table 3. Mandatory PPC key processes for Resident Office risk assessment and process adequacy requiring evaluation during the risk assessment process .............11 Table 4. Mandatory PPC key processes for Geographic Office risk assessment and process adequacy requiring evaluation during the risk assessment process ......12 Table 5. Mandatory Work Measurement risk assessment and process adequacy requiring evaluation during the risk assessment process .........................................13 Table 6. Mandatory DPAS risk assessment and process adequacy requiring evaluation during the risk assessment process ..........................................................14 Table 7. Mandatory Producibility risk assessment and process adequacy requiring evaluation during the risk assessment process ..........................................15 Table 8. Production surveillance category table .....................................................................16 FIGURES Figure 1. Surveillance Planning Flowchart .............................................................................17 Figure 2. Document Production Surveillance Plan Flowchart ...............................................22 Figure 2a. Surveillance Plan Documentation Flowchart ........................................................23 Figure 3. Production Surveillance Flowchart .........................................................................25 Figure 4. Contractor Performance History Input Flowchart ...................................................26 Figure 5. Development Surveillance Flowchart .....................................................................28 Figure 6. Over and Above Surveillance Flowchart ................................................................30 Figure 7. Time and Material Surveillance Flowchart .............................................................31
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
3
Figure 8. Delay Reporting Flowchart ....................................................................................33 Figure 9. Customer Requests Flowchart .................................................................................35 Figure 10. Physical Progress Reviews Flowchart ...................................................................37 Figure 11. Performance Based Payment Support Flowchart ..................................................38 Figure 12. Delegation Flowchart ............................................................................................40 Figure 13. Corrective Action Requests Flowchart ..................................................................41 Figure 14. Continuous Improvement Opportunities Flowchart ..............................................42 Figure 15. Industrial Labor Relations Flowchart ....................................................................43 GLOSSARY Acronyms .................................................................................................................................44
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
4
REFERENCES (a) DCMA-INST 204, “Manufacturing and Production,” July 2010 (hereby canceled) (b) DFARS 242.1104, “Production Surveillance,” April 23, 2008 (c) DoD Directive 5105.64, “Defense Contract Management Agency (DCMA),” January 10, 2013 (d) DCMA-INST 710, “Managers’ Internal Control Program,” September 12, 2011 (e) DCMA-INST 118, “Contract Receipt and Review,” June 25, 2013 (f) DFARS 252.242-7004, “Material Management and Accounting System,” May 2011 (g) Part 700 of Title 15, Code of Federal Regulations, “Defense Priority Allocation System” (h) FAR 42.11, “Production Surveillance and Reporting” (i) DCMA-INST 809, “Records Management,” May 2011 (j) FAR 42-302(a)(67) (k) FAR 42-302(a)(31) (l) FAR 22.101-1 through 4 (m) DFARS 222.1
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
5
CHAPTER 1
POLICY 1.1. POLICY. This Instruction ensures that all the applicable Federal Acquisition Regulations (FAR), DFARS, statutory and regulatory requirements that apply to DCMA for contract surveillance of manufacturing and production activities are met.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
6
CHAPTER 2
ROLES AND RESPONSIBILITIES 2.1. DIRECTOR, DCMA. The Director, DCMA is responsible for all regulatory and statutory requirements referenced in this Instruction. 2.2. EXECUTIVE DIRECTOR. The DCMA Executive Director of each directorate responsible for FAR 42 contract administration is responsible in ensuring their directorate meets the requirements of this Instruction. 2.3. CMO COMMANDER/DIRECTOR. The CMO ensures the CMO meets the requirements of this Instruction. 2.4 TECHNICAL SPECIALIST. The Technical Specialist performs the duties and actions required in this Instruction
[NOTE: The term “Technical Specialist” referenced throughout this Instruction pertains to Industrial Specialists, Industrial Engineers, and other technical personnel assigned responsibility for Production Surveillance (DFARS 242.1104, (Reference (b)) by their assigned CMO.]
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
7
CHAPTER 3
PROCEDURES 3.1. SURVEILLANCE PLANNING.
3.1.1. Perform Contract Technical Review. Initial contract review and review of subsequent contract modifications shall be accomplished in accordance with the DCMA-INST 118, “Contract Receipt and Review” (Reference (e)). Contract deficiencies shall be addressed via the Contract Deficiency Report (DD1716) application in Electronic Document Access (EDA). The Technical Specialist should identify/review:
• Applicable FAR/DFARS clauses • Weapon System Code • Defense Priorities and Allocations System (DPAS) requirements • Surveillance Criticality Designation (SCD). If the Technical Specialist considers the
SCD inaccurate, the Contracting Officer should be notified • Progress Payments Requirements • Performance Based Payments Requirements • First Article Requirements • Line Item/Schedule Data • Shipment Data (Ship To) • Quantity on Order or Variance • Work Statement • Contract Data Requirements List (CDRL)
3.1.2. Review Agreements. The Technical Specialist should review:
• Memorandums of Agreement (MOA) • Performance Based Agreements (PBA)
3.1.3. Ensure Mechanization of Contract Administration Services (MOCAS) Data Integrity. The Technical Specialist shall ensure MOCAS data integrity by reviewing and correcting data in shipments, delinquencies, acceptance, cancellations, terminations, completion of line items, and performance history. At a minimum, the Technical Specialist should verify the following data elements:
• DPAS requirements • Line Item/Schedule Data • First Article • Shipment Data (Ship To) • Quantity on Order or Variance
3.1.4. Perform Manufacturing Supplier Risk Assessment (MSRA). The Technical Specialist shall conduct a MSRA on all suppliers that have SCD A or B contracts (DFARS 242.1104,
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
8
(Reference (b)), utilizing the DCMA Manufacturing Supplier Risk Assessment Tool (Geographic Office Tool or Resident Office Tool) (see the Resource Page). Suppliers considered high delivery risk should be assessed biannually, with all others assessed annually or as conditions warrant. New suppliers should be considered as moderate risk and subject to continued assessment and rating adjustment as warranted. 3.1.4.1. Manufacturing Systems Risk Assessments. Manufacturing Systems risk assessment results are an input to the MSRA. These risk assessments are also used to determine the risks associated with key processes and to determine the frequency and detail of periodic key process surveillance activities. Table 1 defines the mandatory systems and their requisite processes requiring surveillance by Resident Offices (Producibility System risk assessment and surveillance is required on suppliers with Acquisition Category (ACAT) 1 and ACAT 2 contracts that have completed Milestone B and have not initiated Full rate Production). Table 2 defines the mandatory systems and their requisite processes requiring surveillance by Geographic Offices. Manufacturing System risk assessments should be updated when either a major change is made to the system’s existing processes or when recurring surveillance activities indicate a change in process performance.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
9
Table 1. Mandatory systems and processes requiring surveillance in Resident Office environment
RESIDENT MANDATORY SYSTEMS AND PROCESSES
SYSTEM KEY PROCESS
Production Planning and Control (PPC)
Demand Management Resource Requirements Planning Aggregate Planning Master Production Scheduling Rough Cut Capacity Planning Material Requirements Planning Capacity Requirements Planning Shop Floor Control
Work Measurement
Standards Development Standards Maintenance Standards Usage
Producibility
Producibility Infrastructure Establishment Manufacturing Design Integration Process Capability Determination Producibility Measurement
Defense Priorities and
Allocation System (DPAS)
Contract Review and Order Acceptance Requirements Flow-Down Delay Notification Preferential Scheduling
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
10
Table 2. Mandatory systems and processes requiring surveillance in Geographic Office environment
GEOGRAPHIC MANDATORY SYSTEMS AND
PROCESSES SYSTEM KEY PROCESS
Production Planning and Control (PPC)
Master Production Scheduling Rough Cut Capacity Planning Material Requirements Planning Capacity Requirements Planning Shop Floor Control
Defense Priorities and
Allocation System (DPAS)
Contract Review and Order Acceptance Requirements Flow-Down Delay Notification Preferential Scheduling
3.1.4.2. Production Planning and Control (PPC) System Risk Assessment. The Technical Specialist shall conduct a risk assessment by evaluating the adequacy of the supplier’s PPC key processes. PPC system risk assessments and recurring system surveillance are performed in order to assess processes that impact supplier delivery performance and when applicable DFARS 252.242-7004 (Reference(f)) compliance. 3.1.4.2.1. Resident Office PPC System Surveillance. The mandatory PPC key processes for Resident Office risk assessment are defined in Table 3. Table 3 also defines process adequacy criteria requiring evaluation during the risk assessment process. Technical Specialists may utilize recommended guidance for assessing PPC process adequacy or utilize CMO derived guidance. Metrics for consideration in recurring surveillance efforts are also included in the recommended guidance.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
11
Table 3. Mandatory PPC key processes for Resident Office risk assessment and process adequacy criteria
requiring evaluation during the risk assessment process
RESIDENT PPC SYSTEM - ADEQUACY CRITERIA
PROCESS ADEQUACY CRITERIA Demand
Management Reasonable demand forecasts are made and customer orders are managed.
Resource Requirements
Planning
Long term needs for personnel, facilities, and physical equipment are determined.
Aggregate Planning
Long term levels of production (mix and volume) are determined.
Master Production Scheduling
Schedule(s) for production by item, date, and quantity for the duration of the planning system is provided.
Rough Cut Capacity Planning
Capacity check(s) of critical resources, to ensure feasibility of the master production schedule, is provided.
Material Requirements
Planning
Time phased plan(s) for all component parts, raw material, sub-assembly and assembly activities required to produce all products on the master production schedule is determined.
Capacity Requirements
Planning
Capacity check(s) of productions plans, generated from material requirements planning, is provided.
Shop Floor Control
Documentation, material, and tooling needed for order processing are present. Orders are released as authorized by the material requirement plan. Priority control is exercised with respect to queues. Order performance is monitored and plans adjusted as necessary.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
12
3.1.4.2.2. Geographic Office PPC System Surveillance. The mandatory PPC key processes for Geographic Office risk assessment are defined in Table 4. Table 4 also defines process adequacy criteria requiring evaluation during the risk assessment process. Technical Specialists may utilize recommended guidance for assessing PPC process adequacy or utilize CMO derived guidance. Metrics for consideration in recurring surveillance efforts are also included in the recommended guidance.
Table 4. Mandatory PPC key processes for Geographic Office risk assessment and process adequacy criteria
requiring evaluation during the risk assessment process
GEOGRAPHIC PPC SYSTEM - ADEQUACY CRITERIA
PROCESS ADEQUACY CRITERIA Master
Production Scheduling
Schedule(s) for production by item, date, and quantity for the duration of the planning system is provided.
Rough Cut Capacity Planning
Capacity check(s) of critical resources, to ensure feasibility of the master production schedule, is provided.
Material Requirements
Planning
Time phased plan(s) for all component parts, raw material, sub-assembly and assembly activities required to produce all products on the master production schedule is determined.
Capacity Requirements
Planning
Capacity check(s) of productions plans, generated from material requirements planning, is provided.
Shop Floor Control
Documentation, material, and tooling needed for order processing are present. Orders are released as authorized by the material requirement plan. Priority control is exercised with respect to queues Order performance is monitored and plans adjusted as necessary.
3.1.4.3. Work Measurement System Risk Assessment. Work measurement system risk assessment shall be conducted on suppliers utilizing work measurement techniques for planning, estimating, or performance measurement. Risk assessments evaluate the adequacy of the supplier’s work measurement key processes. The work measurement key processes requiring risk assessment and recurring surveillance are defined in Table 5. Table 5 also defines process adequacy criteria requiring evaluation during the risk assessment process. Technical Specialists may utilize recommended guidance for assessing work measurement process adequacy or utilize CMO derived guidance. Metrics for consideration in recurring surveillance efforts are also included in the recommended guidance. When system weaknesses are identified, the Technical Specialist should determine whether these identified weaknesses pose risk to supplier planning,
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
13
estimating, or performance measurement processes. If system weaknesses have an adverse impact on the supplier’s Material Management and Accounting System or Estimating System, then a Corrective Action Request (CAR) should be issued. All other system weaknesses should be presented to the supplier as a Continuous Improvement Opportunity (CIO).
Table 5. Mandatory Work Measurement risk assessment and process
adequacy criteria requiring evaluation during the risk assessment process
WORK MEASUREMENT SYSTEM ADEQUACY CRITERIA
PROCESS ADEQUACY CRITERIA Standards
Development Accurate and consistent standards are developed.
Standards Maintenance
Standards are updated in a timely manner and are available.
Standards Usage Standards application is consistent and valid.
3.1.4.4. Defense Priority Allocation System (DPAS) Risk Assessment. DPAS risk assessment shall be conducted on suppliers with contracts containing DPAS requirements. The Technical Specialist should meet with the supplier to ensure the supplier understands the requisite preferential scheduling of rated orders in accordance with part 700 of Title 15 Code of Federal Regulations (Reference (g)) and ensure that DPAS training is provided to the supplier when DPAS requirements are not understood. Risk assessments evaluate the adequacy of the supplier’s DPAS key processes. The DPAS key processes requiring risk assessment and recurring surveillance are defined in Table 6. Table 6 also defines process adequacy criteria requiring evaluation during the risk assessment process. Technical Specialists may utilize recommended guidance for assessing DPAS process adequacy or utilize CMO derived guidance. Metrics for consideration in recurring surveillance efforts are also included in the recommended guidance.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
14
Table 6. Mandatory DPAS risk assessment and process
adequacy criteria requiring evaluation during the risk assessment process
DPAS ADEQUACY CRITERIA
PROCESS ADEQUACY CRITERIA Contract Review
and Order Acceptance
DPAS contracts are reviewed and orders properly accepted.
Requirements Flow-Down
DPAS requirements are flowed down, both internally and externally, throughout the supplier's supply chain.
Delay Notification
Notification of delays on rated orders, along with reason for delay, is provided in advance.
Preferential Scheduling
Preferential scheduling is used to ensure rated order scheduling over non-rated orders.
3.1.4.5. Producibility System Risk Assessment. Producibility system surveillance is performed in order to monitor the integrated processes and resources needed to successfully achieve producibility. Producibility risk assessment shall be conducted on suppliers with ACAT 1 and ACAT 2 contracts that have completed Milestone B and have not initiated Full rate Production. Risk assessments evaluate the adequacy of supplier producibility key processes. The Producibility System key processes requiring risk assessment and recurring surveillance are defined in Table 7. Table 7 also defines process adequacy criteria requiring evaluation during the risk assessment process. Technical Specialists may utilize recommended guidance for assessing Producibility process adequacy or utilize CMO derived guidance. Metrics for consideration in recurring surveillance efforts are also included in the recommended guidance.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
15
Table 7. Mandatory Producibility System risk assessment and process adequacy criteria requiring evaluation during the risk assessment process
PRODUCIBILITY SYSTEM ADEQUACY CRITERIA
PROCESS ADEQUACY CRITERIA
Producibility Infrastructure Establishment
All functions of the organization are involved throughout the design process and collectively have the responsibility for new products.
Process Capability
Determination
Process capability is understood, measured, controlled and documented.
Producibility Measurement
Producibility is addressed during every aspect of design and development in order to achieve affordable products that meet customer needs.
Manufacturing Design Input
Manufacturing is involved in all design phases and as products transition to final design. The design process ensures that every aspect of producibility has been addressed.
3.1.5. Determine Production Surveillance Category (PSC). PSC identifies the degree of production surveillance to be performed on a contract. PSC determination shall be accomplished utilizing the PSC Table and accurately reflected in MOCAS.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
16
Table 8. Production surveillance category table
PRODUCTION SURVEILLANCE CATEGORY (PSC) TABLE
Supplier has
SCD A/B
SCD Production Risk Analysis
PSC Notes Consequence of Delay
Likelihood of Delay
Yes A High High 1
Moderate 1 or 2 Low 2
Yes B Moderate High 1 or 2
Moderate 2 Low 2 or 4
Yes C* Low High 4 Delivery Surveillance should be
performed when 31 days past scheduled due date
Moderate 4 Low 4
No C* Low
High 4 No delivery surveillance required. Upon confirmation of final delivery. complete Contractor Performance History in MOCAS
Moderate 4
Low 4
* When Contracting Officer requests surveillance on SCD C contracts, the Technical Specialist should contact the customer regarding the requested level of surveillance and assign a PSC that is commensurate with the request.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
17
Figure 1
Surveillance Planning Flowchart Surveillance Planning
Contract Technical Review
Contract Deficiencies identified?
Contract Deficiency Report (DD1716)
application in EDA
Y
Review Agreements
MOA
PBA
N
MOCAS Data Integrity
Does MOCAS data match
contract data?
Make corrections to MOCAS data
N
Y
Cont. to Page 2
References:DCMA Contract Receipt and Review PolicyContract Deficiency Report (DD1716) ApplicationDFARS 242.1104DCMA Manufacturing Supplier Risk Assessment Tool (Geographic and Resident)DFARS 252.242-7004DCMA Corrective Action RequestDCMA Continuous Improvement OpportunityDPAS 15 CFR 700
Acronyms:EDA – Electronic Document AccessFAR – Federal Acquisition RegulationDFARS – Defense Federal Acquisition Regulation SupplementDPAS – Defense Priorities & Allocations SystemSCD – Defense Priorities and Allocations SystemCDRL – Contract Data Requirements ListMOA – Memorandums Of AgreementPBA – Performance Based AgreementsMOCAS – Mechanization Of Contract Administration ServicesMSRA – Manufacturing Supplier Risk AssessmentACAT – Acquisition CategoryPPC – Production Planning and ControlCMO – Contract Management OfficeMMAS – Materials Management and Accounting SystemCAR – Corrective Action RequestCIO – Continuous Improvement OpportunityY – YesN – No
Figure 1, page 1 of 4
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
18
Surveillance Planning Flowchart (cont.)
Does supplier have SCD A or B
contracts?
Geographic Office?
Use Geographic Office Tool
Use ResidentOffice Tool N Y
Is supplier considered “high
delivery risk”?
Biannual assessment or as conditions warrant
Annual assessment or as conditions warrant
N
Y
New supplier?Moderate risk.
Continued assessment and rating adjustment as warranted
Y
N
Use Table 1 to determine mandatory systems and
processes requiring surveillance
Use Table 2 to determine mandatory systems and
processes requiring surveillance
ACAT1 & ACAT2Contracts that have
completed Milestone B and have not initiated Full
rate Production?
Producibility System risk assessment and
surveillance is required
Y
Does anMSRA exist for the supplier?
N
Is there a major changeto the system’s existent process?,
or Does recurring surveillance activities indicate a change in process
performance?
Y
Update MSRA tool Y
No updates to MSRA tool are requiredN
Y
N
Evaluate the adequacy of the supplier's PPC key processes
N
Evaluate the adequacy of the supplier's PPC key processes
Use Table 3 (Mandatory PPC key processes and process adequacy criteria requiring evaluation during the risk
assessment process)
Use Table 4 (Mandatory PPC key processes and process adequacy criteria requiring evaluation during the risk
assessment process)
Use table 7 or CMO derived guidance
Cont. to Page 3
Arro
w A
Pa
ge 3
Cont
. fr
om P
age
1
Figure 1, page 2 of 4
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
19
Surveillance Planning Flowchart (cont.)
N
Does supplierutilizes work measurement
techniques for planning, estimating, or performance
measurement?
Conduct Work Measurement System Risk Assessment
Y
Use table 5 or CMO derived guidance
System weakness identified?
Risk to supplier planning,estimating or performance measurement
processes?, and/or does the weakness have an adverse impact on the supplier’s MMAS or
Estimating System?
Y A CAR should be issuedY
Present to the supplier as a CIO
NN
Does supplier’s contract contain DPAS
requirements?
Does thesupplier understands DPAS requirements?
Y
Meet with the supplier to ensure the supplier understands the requisite
preferential scheduling of rated orders
Y
Ensure that DPAS training is provided to the supplier
N
Use table 6 or CMO derived guidance
N
N
Cont. from Page 2
Cont. to Page 4
Arro
w A
Pa
ge 2
Figure 1, page 3 of 4
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
20
Surveillance Planning Flowchart (cont.)
Identify Contract SCD
Determine likelihood of delay (high, moderate, or low)
Use table 8 to derive contract PSC
Does contract PSC match MOCAS PSC?
Correct MOCAS record
Surveillance Planning completed
N
Y
Cont. from
Page 3
Figure 1, page 4 of 4
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
21
3.2. SURVEILLANCE EXECUTION AND DOCUMENTATION.
3.2.1. Document Production Surveillance Plan. Technical Specialists shall develop and maintain production surveillance plans for all suppliers awarded SCD A and/or B contracts and when Contracting Officers request surveillance of suppliers with only SCD C contracts (DFARS 242.1104, (Reference (b)). The production surveillance plan shall be applicable to all government contracts administered by DCMA and address:
• Surveillance strategies for monitoring PSC 1, PSC 2, and PSC 4 coded contracts. • Surveillance strategies for special surveillance requirements (including those
requested by the Contracting Officer, Program Integrator and delegations). • Recurring key process surveillance activities resulting from manufacturing systems
risk assessments. 3.2.1.1. The manufacturing surveillance plan is a risk and resourced based plan and should be developed per paragraph 2.1 utilizing the MSRA and those CMO resources assigned to fulfill FAR 42.11 requirements (Reference (h)). 3.2.2. Surveillance plan documentation includes:
• DCMA and Supplier points of contact • Surveillance activity • Monitoring intervals • Reference to where surveillance results are maintained • Manufacturing Supplier risk assessment
3.2.3. The manufacturing surveillance plan and results are considered record materials and treated as such in accordance with the DCMA-INST 809, “Records Management” (Reference (i)). Additionally, all information created for DCMA use and delivered to or falling under the legal control of the CMO are Federal records and managed accordingly.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
22
Figure 2 Document Production Surveillance Plan Flowchart
Document Production Surveillance Plan
Incorporate Supplier Risk Assessment
Define Strategies for Monitoring PSC 1, 2, or 4
Contracts
Identify Strategies for Special Surveillance
Requirements
Identify Recurring Key Process Surveillance
activities
Planning is Risk and Resource
Based?
Suppliers with SCD A &/or SCD B
Contracts
Y
Documented Surveillance Plan not Required
Document Surveillance Plan
Y
N
N
Acronyms:SCD – Surveillance Criticality DesignationPSC – Production Surveillance Category
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
23
Figure 2a Surveillance Plan Documentation Flowchart
Document Surveillance Plan
Identify and Note Supplier and DCMA POCNote Surveillance
Strategies for Monitoring PSC 1, 2 and 4 Contracts
Note Surveillance Activities
Note Surveillance Intervals
Note where Surveillance Results are Maintained
Include Supplier Risk Assessment Tool
Detail
Perform Production Surveillance
Y
Tangible, Documented
Surveillance Plan (Record) has been
created?
N
Acronyms:POC – Point Of ContactPSC – Production Surveillance Category
References:DFARS 242.1104
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
24
3.2.4. Production surveillance is performed in accordance with the documented production surveillance plan, utilizing risk management principles. Production surveillance efforts include manufacturing surveillance, delivery surveillance (proactive and reactive), and special surveillance requirements for individual contracts (including any requirements identified by the Contracting Officer, Program Integrator, and delegations). Production surveillance activities are to ensure that suppliers:
• Have adequate manufacturing processes in place for contract execution • Have established a manufacturing plan for contract execution • Have adequate resources for plan execution • Monitor their performance to plan, take corrective action, or make adjustments as
necessary
3.2.5. In major program support environments, manufacturing surveillance is typically conducted in support of an overarching Program Surveillance Plan (PSP). The manufacturing surveillance requirements specified in this Instruction are applicable to all major program environments, including those where PSPs are utilized (FAR 42-302(a)(67) (Reference (j)). All manufacturing surveillance results which may have a material impact on programs should be provided to the Program Integrator (this includes those results from the PSP and results obtained through the execution of this Instruction).
3.2.6. Manufacturing Surveillance. Contracts bearing a PSC 1 or 2 shall include the following manufacturing surveillance actions:
• Review, evaluate, and monitor the supplier’s plan for production. This includes
schedule analysis to identify and monitor milestones, critical path, pacing events of production, and resourcing
• Evaluate and monitor supplier re-planning and corrective action efforts 3.2.6.1. These actions may be accomplished utilizing individual contract surveillance activities or utilizing PPC process surveillance with individual contract sampling. Although the required surveillance activities of PSC 1 and PSC 2 coded contracts are the same, the frequency and detail of surveillance activities of PSC 1 contracts is greater than that of PSC 2 contracts.
3.2.7. Delivery Surveillance. All contracts bearing a PSC 1 or 2 shall include proactive delivery surveillance activities that monitor contract progress and identify potential delinquencies. For SCD B contracts coded as PSC 4, the Technical Specialist shall perform proactive delivery surveillance, by monitoring contract progress and identifying potential delinquencies. Reactive delivery surveillance should be performed on SCD C contracts in supplier facilities with SCD A/B contracts. Customer notification of potential or actual delays is accomplished as described in paragraph 3.2.12., Delay Reporting.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
25
Figure 3 Execute Plan – Production Surveillance Flowchart
Perform Production
Surveil lance
Supplier has an Established Plan for Contract/Program
Execution
Supplierhas Adequate
Manufacturing Processes to Execute
Contract(s)
Y
Supplier has Adequate Resources to
Execute his plan
Y
Monitor Supplier’s Performance to Plan
Y
Major Program,SCD A/B, PSC 1 or 2
contracts
Review, Evaluate and Monitor Supplier’s Plan
for Production
Y
Perform Schedule Analysis
Perform Proactive Delivery Surveillance
CO requested surveillance on SCD C contracts
No Surveillance Required. Complete Contractor Performance History
N
End
Evaluate and Monitor Supplier’s Re-planning and
Corrective Action
N
N
Identify Actual and Potential Delinquencies
Create Delay Noticesin DSM
Create CARsin CAR Database
Manufacturing related Contractual
ViolationsY
N
N
Y
Acronyms:SCD – Surveil lance Criticality DesignationPSC – Production Surveillance CategoryCO – Contracting OfficerDSM – Delivery Schedule ManagerCAR – Corrective Action Request
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
26
3.2.8. Contractor Performance History Input. The Technical Specialist shall ensure the input of Contractor Performance History information in MOCAS for all contracts. Contractor Performance History information in MOCAS is input upon confirmation of final shipment, where total order quantity balances with the total shipped on all line items in MOCAS, and all line items not requiring DD Form 250, Material Inspection and Receiving Report, have been shipped complete. In cases where evidence of shipment is not readily obtainable, confirmation from the PCO may be used as evidence of physical completion. These activities should be performed by a Procurement Technician.
Figure 4 Contractor Performance History Input Flowchart
Contractor Performance History Input (Ideally performed by a
Procurement Technician)
MOCAS or DSM Evaluation of Contract Line Item
Schedule(s)
Evidenceof Physically Complete
Contract (Total Quantity ordered balances with
Total QuantityShipped on all
Line Items)
Ensure input of Contractor Performance History in
MOCAS
Line Itemsnot requiring DD250/
MIRRs are shipped complete
Y
Y
Seek confirmation from PCO as evidence of physical completion
N
N
End
Acronyms:MOCAS – Mechanization Of Contract Administration ServicesDSM – Delivery Schedule ManagerPCO – Procuring Contracting OfficersMIRR – Material Inspection and Receiving ReportACO – Administrative Contracting Officer
3.2.9. Development Program Surveillance. The surveillance requirements described in paragraphs 3.1 through 3.2.6 may be tailored to address the manufacturing development
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
27
environment. The objectives of development surveillance activities are to evaluate and predict supplier performance with respect to the development of executable and affordable manufacturing processes. Development program surveillance shall monitor incremental program maturity throughout the development process, beginning with Milestone B and continuing through low rate initial production. Frequency and detail of surveillance activities should be commensurate with the assessed risks. When permitted by the supplier, the Technical Specialist should participate on supplier integrated program teams.
3.2.9.1. Development program surveillance activities are to ensure that suppliers:
• Have established a detailed manufacturing development plan for program execution
• Have adequate manufacturing producibility processes that facilitate an efficient and effective transition between acquisition phases
• Have adequate resources for plan execution • Monitor their performance to plan, take corrective action or make adjustments as
necessary 3.2.9.2. When Program Offices utilize the Manufacturing Readiness Level (MRL) criteria and conduct Manufacturing Readiness Assessments (MRA) the Technical Specialist should formally request participation in the planning and execution of the assessments. When the Program Office does not utilize the MRL process and instead conduct other review such as Production Readiness Review, the Technical Specialist should formally request to participate in the planning and execution of such readiness reviews.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
28
Figure 5 Development Surveillance Flowchart
Development Program Surveillance
Contract Review
Development Contract
SCD A/Band PSC 1 or 2
Contract
CO Requested Surveillance
Acq. Phase,Post Milestone B and Pre-Low Rate Initial
Production
Development Surveillance not Required
N
Perform Requested SurveillanceY
Y
Y
End
SupplierUtilizes IPTs
Request Team Membership
Y
Y
ProgramOffice Performs
MRAs orPRR
Request Participation in Planning and Execution
Process
Y
Monitor Incremental Program Maturity
Manufacturing Related Contractual
Violation
N
Issue Corrective Action and Enter in CAR
DatabaseY
N
N
N
N
Acronyms:SCD – Surveillance Criticality DesignationCO – Contract OfficerIPT – Integrated Product TeamMRA – Manufacturing Readiness AssessmentPRR – Production Readiness ReviewCAR – Corrective Action Request
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
29
3.2.10. Over and Above (O&A) Surveillance. The Technical Specialist in coordination with the Contracting Officer, typically the Administrative Contracting Officer (ACO) should establish risk based surveillance activities addressing supplier submitted O&A work requests. Surveillance activities should address review of work requests received from the supplier and monitoring of labor hours and material costs associated with the O&A effort. The Technical Specialist should assure that the supplier is executing maintenance, repair and overhaul contracts in accordance with their documented procedure as agreed to between the ACO and the supplier.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
30
Figure 6 Over & Above Surveillance Flowchart
O&A Contract Review
Coordinate with CO/ACO to review Supplier submitted O&A Work Requests and Procedures
Establish Risk-Based Surveillance Activities
addressing supplier submitted O&A requests
O&A Surveillance
Review and monitor labor costs associated the O&A request(s)
Document Planned Surveillance Activities in Manufacturing
Surveillance Plan
Report results to ACO
Issue CAR
Supplieris executing
Maintenance,Repair & Overhaul
contract IAWagreed toprocedure
N
Y
Y
Acronyms:O&A – Over & AboveCO – Contract OfficerACO – Administrative Contracting OfficerCAR – Corrective Action Request
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
31
3.2.11. Time and Materials Surveillance. Following contract review and prior to the approval of the first payment voucher, the Technical Specialist (in coordination with the ACO) should establish risk activities for Time and Material contracts. Surveillance activities should include scheduled observations by the Technical Specialist based on the frequency of invoices, to ensure efficient utilization of resources including labor and material. The Technical Specialist should assure that the supplier is executing time and material contracts in accordance with their documented process.
Figure 7
Time & Material Surveillance Flowchart
T&M Contract Review
Contact and coordinate with ACO prior to approval of 1st
payment voucher
Establish Risk-Based Surveillance Activities based
on frequency of invoices
T&M Surveillance
Review and monitor supplier resource (labor & material)
utilization
Supplieris executing T&M
contract IAW agreed to procedure
Document Planned Surveillance Activities in Manufacturing
Surveillance Plan
Report results to ACO
Issue CAR
N
Y
Y
Acronyms:T&M – Time & MaterialsACO – Administrative Contracting OfficerCAR – Corrective Action Request
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
32
3.2.12. Delay Reporting. Using the knowledge and information gained during surveillance efforts, the Technical Specialist shall provide customer organizations with written notification of delivery delays (FAR 42-302(a)(31)) (Reference (k)), in advance of schedule due date, using the Delivery Schedule Manger (DSM) eTOOLS application. If the delay is unexpected and may result in an immediate high risk to the customer, the CMO should use the fastest notification method available and ensure receipt by the customer. The CMO should follow-up by inputting the notification into DSM. While notification of actual delays is beneficial, surveillance should also focus on identifying potential delays to provide delay notification well in advance of contractually required delivery dates. Delay Notices shall include:
• Clear descriptions of the reasons for delay based on independent DCMA surveillance and analysis
• Delay codes applicable to the conditions causing the delay • Forecasted recovery dates • DCMA analysis of the supplier corrective action. Also, any government actions
that are needed • Action proposed by supplier to correct the immediate problem and eliminate the
root cause • Independent, value added responses that provide useful information • Government actions being taken or needed to reduce or avoid further delays • Recommendations that enable customers to make informed business decisions
3.2.12.1. When revised delivery forecasts have not been met and the contract
delivery schedule has not been modified, subsequent delay notices shall be issued to maintain the currency of delivery status with the customer. 3.2.12.2. In the absence of the Technical Specialist the Contract Management Team (CMT) has the responsibility to issue Delay Notices. 3.2.12.3. The CMO should establish a process to maintain the integrity of the DSM tool suite. Changes regarding team make up shall be provided to the local CMT Administrator so that changes to the CMT Locator can be made. 3.2.12.4. Waiver in the use of the DSM as the vehicle for delay notification, and capturing customer requests and responses is prohibited.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
33
Figure 8 Delay Reporting Flowchart
Delay Reporting
Surveillance Efforts (identify potential delays)
Delivery Delay identified?
Use the DSM eTool to provide to the customer a written notification of delivery delay in advance
of schedule due date
Y
Will the unexpected
delay result in an immediate high
risk to the customer?
N
CMO should use the fastest notification method available and
ensure receipt by the customerY
Reason for the delay
Delay codes
Forecasted recovery dates
DCMA analysisof the supplier corrective action
Action proposed by supplier to correct immediate problem and eliminate the root cause
Additional useful information
Government actionsto reduce/avoid further delays
Recommendations that enable customers to make informed business decisions
Delay Reporting is not required
N
Is theTechnical Specialist absent?
The CMT has the responsibility to issue
Delay Notices
Y
N
Technical Specialist to continue monitoring the
delayed items
Reviseddelivery forecast have been met?
Close the delay report
Y
Contractdelivery schedule has
been modified?N Subsequent delay notices
shall be issuedN
Y
Acronyms:CMO – Contract Management OfficeCMT – Contract Management TeamDSM – Delivery Schedule Manager
References:FAR 42-302(a)(31)
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
34
3.2.13. Customer Requests. Customer Requests should be answered with timely, independent and value added responses and information/recommendations that enable customers to make informed business decisions. Customer requests should be investigated and monitored; specifically, when a customer’s request for expedite/acceleration will impact the delivery of other work. The response should indicate this as an impact and an appropriate corresponding Delay Notice issued. Requests shall be answered within the timeframe specified by the customer. Regardless of the suspense date specified, if the request is for readiness, a two business day reply time is required. 3.2.13.1. When the Technical Specialist is not immediately available to provide the requested assistance, another member of the CMT should provide an appropriate response. When the customer does not choose to use the DSM tool suite or DSM is not available to the Customer, the CMO should notify their Region. The Region is responsible for advising the customer on the use and benefits of DSM. The cognizant Customer Liaison Representative can also assist with the customer's introduction to the Customer Request process. 3.2.13.2. If the customer makes a request outside of DSM, the CMO shall use the fastest response method available to answer the request on or before the Customer imposed deadline and input the action into DSM.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
35
Figure 9 Customer Requests Flowchart
Customer RequestsCustomer Requests
Request forexpedite/acceleration
will impactdelivery?
Investigate and respond within the timeframe
specified by the customer
Is thecustomer
request forreadiness?
Investigate and respond within two business days
Response to indicate delivery impact and
corresponding Delay Notice
Y Y
N
Is theTechnical Specialist Available?
Another member of the CMT should provide an appropriate response
CMO should notify their Region
N
Region is responible for advising the customer on the
use and benefits of DSM
Customer Request outside
DSM?
N
CMO shall use the fastest response method available on or before the deadline
Input action into DSMY
N
Y
Investigate and respond within the timeframe
specified by the customer
Technical Specialist to continue monitoring the customer
request and delayed items
Close Customer Request and Delay Notice
Acronyms:DSM – Delivery Schedule ManagerCMO – Contract Management OfficeCMT – Contract Management Team
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
36
3.2.14. Physical Progress Reviews. Within 45 days of contract receipt, the Technical Specialist should develop a baseline, for those suppliers exercising the Progress Payment clause. If the supplier maintains an approved Progress Payment System, physical progress reviews are performed as requested by the ACO. The Technical Specialist shall utilize the established baseline to identify the direct cost value of items or services (direct material and labor) required by the contract and monitor and validate the supplier’s progress towards achieving contract deliveries in accordance with the baseline.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
37
Figure 10 Physical Progress Reviews Flowchart
Physical Progress Review (PPR)
Supplier intends to exercise
ProgressPayments
Identify and review contracts with Progress
Payment clause
Establish communication with ACO to identify plan/
need for PPR early
Establish Baseline as early as possible ideally within 45 days
of contract receipt
Y
Be aware of potential future request for progress payments
Use established baseline to identify direct material and
labor costs required by contract
On-site monitor and validate supplier’s progress towards
contract deliveries IAW baseline
Issue report to ACO. Note significant findings, indicators of
cost overruns and provide percentage of physical completion.
End
N
Acronyms:PPR – Physical Progress ReviewACO – Administrative Contracting Officer
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
38
3.2.15. Performance Based Payments. When requested by the ACO, the Technical Specialist should validate the supplier’s completion of the successful performance criteria or event/milestone which is being requested for payment, by providing a written report of the results of the requested event verification with a conclusion statement attesting to the status of the event (e.g., complete, incomplete, delayed, and cause).
Figure 11 Performance Based Payment Support Flowchart
Performance Based Payment
Support
Supplierperformance of
required criteria/milestone or
event verified
In response to ACO request for support validate supplier’s successful completion of
performance criteria/milestone
End
Prepare written report of the results of the requested event
verification. Include conclusion statement (complete,
incomplete, delayed & cause)
YN
Acronyms:ACO – Administrative Contracting Officer
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
39
3.2.16. Delegations. The Technical Specialist shall initiate delegations at sub-tier levels as appropriate to monitor progress towards delivery of products and services, utilizing the Delegation eTool application.
3.2.16.1. Prior to requesting surveillance of subcontracted supplies or services, the Technical Specialist should assure that surveillance is essential to contract performance and may only be adequately accomplished through direct DCMA involvement at the sub-tier supplier level. Considerations for determining the need for issuing subcontract delegations include:
• Customer directed surveillance • Criticality designations • Production Surveillance Category • DPAS • Complex/critical manufacturing and testing • Contract requirements for reporting production progress and performance • Supplier production plans • Items to be manufactured at the supplier that are on the critical path • Supplier delivery performance history • Supplementary instructions from the Contracting Officer • Customer Memorandums of Agreement and desired outcomes
3.2.16.2. The Technical Specialist should make every attempt to establish
communication with the Technical Specialist at the sub-tier supplier facility to discuss the associated risks and plan an appropriate surveillance strategy.
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
40
Figure 12 Delegation Flowchart
Delegations
Essential surveillance needed at
subtier surveillance
level
Y
N
Review conditions to determine need for
delegation
CONSIDERATIONS: Customer directed surveillance,; Criticality designations; Production Surveillance Category; DPAS; Complex/critical manufacturing and testing; Contract requirements for reporting production progress and performance; Supplier production plans,; Items to be manufactured at the supplier that are on the critical path; Supplier delivery performance history; Supplementary instructions from the Contracting Officer; Customer Memorandums of Agreement and desired outcomes
Create Delegation in Delegation E-
Tool
Communicate with Technical Specialist at Sub-tier facility
Discuss Associated
Risks and Plan Surveillance
Strategy
Do not issue Delegation
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
41
3.2.17. Manufacturing Corrective Action Requests. Contractual violations shall be communicated to the supplier using a written CAR through the CAR v1.0 eTool. CAR levels are based on the severity of the non-compliance, supplier responsiveness to previous corrective action requests, and recurring non-compliance. Level II CARs are issued to the supplier management level responsible for initiating corrective action. The Technical Specialist should determine the adequacy of the supplier’s CAR response and establish a follow-up date to verify implementation of supplier corrective action.
Figure 13 Corrective Action Requests Flowchart
Perform Surveillance Activities
Production Surveillance(Manufacturing, Delivery,
and Special)O&A Surveillance Development
SurveillanceT&M Surveillance
Contractual Violation Identified
Create CARusing CAR Data Base
Evaluate Adequacy of Supplier CAR Response
Establish Follow-up date to verify supplier planned
corrective actions
Effective Supplier
Corrective Action
Issue CAR at Level appropriate to severity of
noncompliance
Continue performing surveillance activities
Y
Y
N
N
Acronyms:T&M – Time & MaterialsO&A – Over & AboveCAR – Corrective Action Request
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
42
3.2.18. Continuous Improvement Opportunities (CIO). The Technical Specialist may discover practices or conditions that if changed could improve supplier operations, warranting issuance of a CIO to the supplier. CIOs are not contractual and does not result in constructive change to existing contract requirements. CIOs issued to the supplier in writing and include:
• Entry that the CIO does not change contract requirements • An acknowledgement that implementing the CIO is the sole prerogative of the
supplier • A stipulation that the supplier will assume all costs associated with
implementation • Date issued • Name of Technical Specialist (issuer)
Figure 14 Continuous Improvement Opportunities Flowchart
Perform Surveillance Activities
Production Surveillance(Manufacturing, Delivery,
and Special)O&A Surveillance Development
SurveillanceT&M Surveillance
Opportunity for Improvement
discovered
Indicate CIO does not change contract,
supplier’s preogative to implment, date issued,
Continue performing surveillance activities
Issue written continuous Improvement Opportunity
(CIO) to supplier
Y
N
Acronyms:T&M – Time & MaterialsO&A – Over & AboveCIO – Continuous Improvement Opportunity
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
43
3.2.19. Industrial Labor Relations. General policies regarding industrial labor relations
are contained in FAR 22.101-1 thru 4 and DFARS 222.1 (Reference (l) and (m)).
3.2.19.1. Technical Specialists, involved with in-plant activities, who become aware of discordant labor situations and labor negotiations will engage in active discussion with their CMT. Imminent strike information shall be reported by the Technical Specialist in accordance with the DCMA Bellringer Reporting Instruction.
3.2.19.2. Technical Specialists, associated with the strike affected facilities, should
be prepared to support information gathering, analysis and reporting associated with work stoppages that impact Defense contract fulfillment.
Figure 15 Industrial Labor Relations Flowchart
Perform Surveillance Activities
Awareness of discordant labor conditions
Active discussion with Contract Management Team (ACO, QA, etc)
Report Imminent Strike Information via
Bellringer System
Support information gathering, analysis and reporting that impacts
Defense contracts
Continue Surveillance Activities to the degree
possible given conditions
Acronyms:ACO – Administrative Contracting OfficerQA – Quality Assurance
References:FAR 22.101-1 thru 4DRARS 222.1
DCMA-INST 204 August 16, 2012
Change 1, November 5, 2018
44
GLOSSARY
ACRONYMS ACAT Acquisition Category ACO Administrative Contracting Officer CAR Corrective Action Request CDRL Contract Data Requirements List CIO Continuous Improvement Opportunity CMO Contract Management Office CMT Contract Management Team DCMA-INST DMCA Instruction DFARS Defense Acquisition Regulations System DPAS Defense Priorities and Allocations System DSM Delivery Schedule Manager EDA Electronic Document Access FAR Federal Acquisition Regulations MRL Manufacturing Readiness Level MOA Memorandums of Agreement MOCAS Mechanization of Contract Administration Services MRSA Manufacturing Supplier Risk Assessment O&A Over and Above PBA Performance Based Agreements PLAS Performance Labor Accounting System POC Point of Contact PSC Production Surveillance Category PPC Production Planning and Control PSP Program Surveillance Plan SCD Surveillance Criticality Designation