Date www.stunning-project.eu Revision: 1 Due date: 31/03/2018 (M06) Submission date: 16/05/2018 (M08) Lead contractor: Steinbeis 2i GmbH (S2i) Dissemination level STUNNING PU Public X PP Restricted to other program participants (including the Commission Services) RE Restricted to a group specified by the consortium (including the Commission Services) CO Confidential, only for members of the consortium (including the Commission Services) Deliverable 2.1 1st stakeholder community database Franziska Bergmann Steinbeis 2i GmbH Ref. Ares(2018)2545854 - 16/05/2018

Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

Date www.stunning-project.eu

Revision: 1

Due date: 31/03/2018 (M06)

Submission date: 16/05/2018 (M08)

Lead contractor: Steinbeis 2i GmbH (S2i)

Dissemination level STUNNING

PU Public X

PP Restricted to other program participants (including the Commission Services)

RE Restricted to a group specified by the consortium (including the Commission

Services)

CO Confidential, only for members of the consortium (including the Commission

Services)

Deliverable 2.1

1st stakeholder community

database

Franziska Bergmann Steinbeis 2i GmbH

Ref. Ares(2018)2545854 - 16/05/2018

Page 2: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 2

Deliverable Administration & Summary STUNNING

Status Final Due M 06 Date 31/03/2018

Author(s) Franziska Bergmann (S2i)

Editor Karine Laffont-Eloire (Technofi)

Page 3: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 3

DoA Description of the deliverable as reflected in the DoA

T2.1 Construction of the stakeholder community (Lead: S2i, M01-24)

The concept underpinning the CSA is to build a community of stakeholders around

a web-based platform that provides key facts and recommendations on renovation

packages (solutions, business models and business cases), building upon the

knowledge and results of past and ongoing EU projects. Stakeholder engagement

activities are then articulated around this platform to maximise the impact.

A stakeholder community of eight groups of stakeholders will be set up. They will

give priority to associations, which will act as intermediates and represent the

interests of their members:

- Industrials (incl. associations such as ACE, FIEC, EUREFAS, EuroACE, REHVA)

- SMEs

- Banks and financial institutions

- Cities and local authorities (e.g. Energy Cities, EuroCities, ICLEI, Replication

Cluster from the SINFONIA & EUGUGLE

projects);

- Building owners, including social housing (including associations such as Housing

Europe)

- Citizens (users / consumers) (with consumer associations such as BEUC or

ANEC)

- Research institutes and academics

Task leader S2i will create at the beginning of the project an electronic information

factsheet and invitation to join the STUNNING community for the targeted

stakeholder groups. The factsheet will contain information about the project, the

added value of becoming a stakeholder as well as a link to sign up for the

community. All partners will distribute this factsheet among the stakeholder groups

they are active in themselves very actively within the first months of STUNNING in

order to have an initial community created until M06. Nevertheless the factsheet will

be used throughout the project to gain more and more stakeholders.

The consortium has furthermore identified potential synergies with the BUILD

UPON project, which has already developed a very large EU stakeholder database.

It will be checked that BUILD UPON stakeholders are also invited to become part of

the STUNNING community.

S2i will create a stakeholder database, which will also be used for the dissemination

activities of WP6. The first version of the database will constitute D2.1 at M06 and

contain at least 100 members. It is expected to at least double the number of

STUNNING community members throughout the project duration.

S2i will ensure an appropriate data based management by categorisation of

- target user specification

- level of involvement (input of and feed back to information)

- history

- level of commitment, meaning the willingness to become a user

Comments

Page 4: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 4

Document change history STUNNING

V Date Author Description

1. 15/05/2018 Franziska Bergmann (S2i)

First version

2. 16/05/2018 Franziska Bergmann (S2i)

Final version

3.

4.

5.

Disclaimer

The information in this document is as provided and no guarantee or warranty is given that the

information is fit for any particular purpose.

This document reflects the author’s views and the Community is not liable for the use that may be made

of the information it contains.

Page 5: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 5

Contents

1. Introduction ............................................................................................................6

2. Deviation from work plan ......................................................................................6

3. STUNNING Stakeholder Database .......................................................................7

4. Next steps ..............................................................................................................9

5. Conclusions ......................................................................................................... 11

Page 6: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 6

1. Introduction

WP2 “Stakeholder engagement and knowledge sharing platform” aims at federating a large community

of stakeholders, including all the players of the construction sector by building and maintaining a strong

commitment and interest of the stakeholder community. To fulfil this objective, a community of

committed stakeholders in Europe is being established, centred around an initial group with at least 100

stakeholders who will profit from STUNNING through the provision of information, the submission of

own articles and the moderation of other submitted articles. The number of stakeholders is supposed to

be doubled by the end of the project. These stakeholders are identified by all project partners and

through a dedicated stakeholder campaign run by project partner S2i. A database with STUNNING

stakeholders has been set up and is available for project-related interaction for the STUNNING project

partners.

Task 2.1 “Construction of the stakeholder community” has started at M01 and is terminated with the

completion of the project. This deliverable aims at providing an overview of the stakeholder database at

M06, in which Milestone 1 “Stakeholder Community set up” (with at least 100 members) is supposed to

be achieved.

2. Deviation from work plan

The deliverable is delayed and is submitted in M08 instead of M06. This delay is due to the fact that the

Renovation Hub is still under development and not yet publicly available. Linked to the delays in the

development of the Renovation Hub also the start of the stakeholder campaign was delayed and was

only initiated by M06. Although continuous and broad interest from stakeholders across Europe is there,

by now only 23 people have registered as stakeholders. It is, however, expected that this number will

rise faster once the Renovation Hub has gone live and the number of at least 40 stakeholders will be

reached within the first project year. As a consequence, this deliverable will be submitted with a lower

number of reached stakeholders and Milestone 1 not yet reached. These deviations affecting the

deliverable have been discussed with and accepted by the STUNNING Project Officer Janis Folkmanis

during the M06 partner meeting in Paris (April 16/17, 2018 – see meeting minutes).

Page 7: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 7

3. STUNNING Stakeholder Database

Interested stakeholders can register themselves as a stakeholder on https://stunning-project.eu/join-

the-network/ in order to become a STUNNING stakeholder and join the community.

Figure 1: Entry point for the registration as a STUNNING stakeholder

Stakeholders have three options for their level of engagement:

Follower: Follows social media, gets newsletters and reads all public information

Expert: Gets access to the submit articles section and occasionally provides own articles. Validates

articles of others and gets invited to STUNNING workshops

Ambassador: Takes a leading role in the validation of articles and promotes STUNNING in their own

community

Page 8: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 8

Furthermore, all stakeholders have the option to indicate whether they would like to publish a best

practice in renovation case, their innovative financing model or renovation technology.

All information entered is only accessible for project partners and not shown publicly.

The database is an Excel table enabling to filter quickly the different categories if needed:

Person’s details

First Name

Last Name

Position (in the organisation)

Stakeholder category

Organisation’s details

Organisation name

E-mail

City

Country

Currently, the database entails 23 stakeholder members recruited by all STUNNING partners.

No Level of involvement Target group Country

1 Follower Consulting (SME) Poland

2 Follower Research Italy

3 Follower SME Spain

4 Follower SME Belgium

5 Follower Consulting (SME) UK

6 Follower SME Spain

7 Follower Research Luxemburg

8 Follower Research Sweden

9 Follower Planners UK

10 Follower City & Municipality Germany

11 Follower Research Italy

12 Expert Research Finland

13 Expert Industry Spain

14 Expert SME France

Page 9: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 9

15 Expert Research Germany

16 Expert Research Spain

17 Expert Chamber Croatia

18 Expert Research Brazil

19 Expert SME France

20 Expert Research France

21 Ambassador Planners Romania

22 Ambassador Chamber Croatia

23 Ambassador SME/Investor France

At the current stage, 11 stakeholders are registered as followers, 9 as experts, as well as three

stakeholders as ambassadors. The stakeholders are coming from 12 different European countries, as

well as one from Brazil. Hence, the coverage of EU countries is already very wide. Furthermore, five of

the eight target groups envisaged by STUNNING are also covered by a broad mix by the stakeholders:

Planners/architects: 2

Research organisations: 9

SMEs: 8

Industry: 1

Financial institutions: 1 (one French SME is advising on construction investment opportunities)

4. Next steps

For the success of STUNNING it will be crucial to consequently continue with the strategy defined for

the implementation of the stakeholder campaign at to further refine it.

It has been further decided to follow a “phased” approach, meaning that for the first months the main

focus should be put on attracting stakeholders representing planners, architects, research organisations

and SMEs/construction industry companies. Once the community is built around these stakeholders, a

deeper focus should be put on all other defined STUNNING stakeholder groups:

The following activities are going to be implemented:

Use of social media (ongoing): Regular posts on Twitter and LinkedIn to attract potential stakeholders (at least 2-4 times per week) (S2i). They include:

o Posts directly about the Renovation Hub and its benefits

Page 10: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 10

o Posts about selected articles of the Renovation Hub (once available) o Posts on events, especially those attended by STUNNING partners o Re-post of EeB renovation-related information

Involvement of Advisory Board members’ networks (from May 2018 onwards): Contacting all Advisory Board members and define how they can spread information about STUNNING in their networks. Options are articles in their newsletters or on their websites or involvement in their events (S2i, Technofi).

Involvement of stakeholders having the Ambassador status (from May 2018 onwards): Contacting all STUNNING Ambassador status stakeholders and define how they can spread information about STUNNING in their networks. Options are articles in their newsletters or on their websites or involvement in their events (S2i).

1st STUNNING Press release: Will be published once the Renovation Hub is launched (S2i).

Publication of articles in non-scientific journals and magazines: From June 2018 onwards, once the Renovation Hub is launched (all partners).

Publications on online platforms: This activity has started, but will be continued over the next months (S2i, all partners).

Attendance of events: From September 2018 onwards, the identification of relevant events has already started (all partners).

Page 11: Deliverable 2.1 1st stakeholder community database › ... › WP2 › D2.1_FINAL.pdf · completion of the project. This deliverable aims at providing an overview of the stakeholder

STUNNING D2.1 – 1st stakeholder database Page 11

5. Conclusions

The STUNNING stakeholder database has not yet reached the expected number of registered

stakeholders, instead of 100 only 23 stakeholders are listed so far. The reason for this disparity can be

mainly found in the delays in delivering the Renovation Hub. A positive sign is, however, that the existing

stakeholders already represent a very good mix according to their nationality, stakeholder category and

interested level of involvement. This can be interpreted as a very positive sign for the future interest and

willingness to engage in STUNNING.

In order to keep up the visibility and interest in registering as a STUNNING stakeholder, important

activities have been defined. These are partly already being implemented or at least more precisely

planned in order to be implemented in the upcoming months. By launching the Renovation Hub and

actively promoting STUNNING it is expected that the number of database entries will reach at least 40

by M12 (September 2018).